Dec 13: 8Project Name: Gas Power Station Maintenance Project (GT-4)
8Project Cost: 14 crores
8Project Description: The owner has planned a 35-day scheduled maintenance of GT-4 (130.19 MW) in the 817 MW (4x130.19 MW GT + 2x154.51 MW ST) Gas Based Power Station covering boiler license renewal of 8000 equivalent operating hours, flame tube inspection, inspection of air-fuel ratio and compressor washing.
8Equipment required will be valves, filters, casings, furnace tubes, seals, among others.
8Project Event: RFQ for equipment is expected by third week of December 2017.
8Expenditure Approval: Q2:2017
8RFQ Date: 21/Dec/2017
8Release Date: 5/Jan/2018
8Start Date: 15/Jan/2018
8Completion Date: 18/Feb/2017
Click here for more information
8Project Name: Procurement of a Generator rotor in Thermal Power Station - O&M supply
8Project Cost: 25 crores
8Project Description: The developer is planning to replace the existing generator rotor in the generator at a 600 MW Thermal Power Station in Salem district of Chennai, Tamil Nadu. The generator was supplied by BGR Energy Systems Ltd. The owner will procure a new generator rotor in case of failure of existing generator rotor, as repair of the rotor will take a long time. Administrative approval is awaited, subsequently after which the procurement team of the owner will come out with a bid for the new rotor.
8Project Event: RFQ for purchase of a new generator rotor is expected by Feb 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Feb/2018
8Release Date: Feb/2018
8Start Date: Mar/2018
8Completion Date: May/2018