Software Updates : Power Projects
Feb 13:   8Project Name: Procurement of HP rotor in Thermal Power Station
8Project Cost: 10 crores
8Project Description: The owner's procurement for a new HP rotor to replace the existing HP rotor in the turbine is on hold due to delay in administrative approval. The developer will procure a new HP rotor without waiting for the old rotor to be repaired. Further RFQs are expected shortly.
8Project Event: RFQ for purchase of new turbine rotor is expected by April 2018, instead of Q1 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Apr/2018
8Release Date: Jun/2018
8Start Date: Sep/2018
8Completion Date: Oct/2018
Click here for more information
8Project Name: Canal Head Power House Maintenance Project (Unit -5)
8Project Cost: 14 crores
8Project Description: The owner has planned a 17-day scheduled maintenance of Unit-5 (50 MW) in the 250 MW (5x50 MW) canal head power house which includes overhauling of auxiliary parts of the turbine-generator set, tunnel lining, among others.
8Project Event: RFQs for equipment required are expected by third week of February 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: 17/Feb/2018
8Release Date: 3/Mar/2018
8Start Date: 20/Mar/2018
8Completion Date: 5/Apr/2018