Major EPC players have been shortlisted for installation of an FGD unit: Find out who
Oct 05: Project Name: Thermal Power Project: Installation of FGD
8Project Cost: 866 crores
8Project Description: Owner is going on with final estimation for an EPC contract for Air Quality Control System including an FGD package in the 1320 MW thermal power station. Big EPC contractors have been shortlisted in the techno-commercial part of the bid. Further bids are expected soon.
8Project Event: RFQ for a letter of intent by the owner is expected by November 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Q3:2019
8Completion Date: Q2:2021