Supply of a new screw air compressor is coming up in a thermal power plant: RFQs in Nov, 201
Oct 11: Project Name: Thermal Power Plant: Renovation & Modernisation Project       
8Project Cost: 3 crores
8Project Description: National Thermal Power Corporation Limited is getting delayed in coming out with RFQs for the supply of a new screw air compressor in place of its existing old reciprocating instrument air compressor in the Stage-II plant in its 3000 MW thermal power complex due to decision pending at the Western Region headquarter of the owner. A further bid is expected soon.
8Project Event: RFQ for supply, erection, and commissioning of a new screw air compressor is expected by the November 2018, instead of May 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Q1:2019
8Completion Date: Q2:2019