All content in this website is sourced legitimately

Rs 20000 crore standalone pumped storage project: DPR consultant RFQ in Q-3, 2020.  Rs 2553 crore multipurpose hydel project" RFQs ahead.  Rs 870 greenfield hydel project: RFQ for civil work package-1 in Q3, 3030.  FDG addition coming up ahead.  Our Take.  Download Tenders and Newsclips.  Our Take.  .  Download Tenders and Newsclips.  Our Take.  .  Download Tenders and Newsclips.  .  .  Greenfield hydel project: RFQs in Q2, 2020 subject to grant of funding.  .  Rs 5000 crore greenfield pumped storage project: RFQ for the civil work package in Q3 2020..  .  Rs 17000 crore supercritical thermal power plant: RFQ for the EPC contractor package for main plant works is likely to float on Q3 2020.  .  

Rs 20000 crore standalone pumped storage project: DPR consultant RFQ in Q-3, 2020

Jan 27: Project Name: Standalone Pumped Storage Project
8Project Cost: Rs: Rs:20030 crore
8Project Description: The owner plans to install a 5040 MW standalone pumped storage project. The pre-feasibility report was prepared by in house resources. TOR was accepted by MoEF. The preparation of DPR will start after getting approval. RFQ for the DPR consultant is likely to be floated in Q3 2020.
8Project Event: RFQ for the DPR consultant is likely to be floated in Q3 2020..
Click here for more details Details

Rs 2553 crore multipurpose hydel project" RFQs ahead

Jan 27: Project Name: Multipurpose Greenfield Hydroelectric Project
8Project Cost: Rs 2553.63 crores
8Project Description: The owner plans to install 130 MW Multipurpose Hydroelectric plant
8Project Event: RFQ for drilling and drifting works is likely to be floated in Q3 2020.
Click here for more details Details

Rs 870 greenfield hydel project: RFQ for civil work package-1 in Q3, 3030

Jan 27: Project Name: Greenfield Hydroelectric Power Project
8Project Cost: Rs 870.39 crore
8Project Description: The owner is undertaking additional S&I activities along with relief and rehabilitation activities in a 88.5 MW (3*29.5 MW) greenfield hydel project
8Project Event: RFQ for the civil works package -1 is likely to be floated in Q3 2020.
8Expenditure Approval: Q4: 2019
8RFQ Date: Q3:2020
8Release Date: Q3:2020
8Start Date: 2021
8Completion Date: 2024
Click here for more details Details

FDG addition coming up ahead

Jan 27: Project Name: Thermal Power Station - FGD Addition
8Project Cost: Rs.: 400Crores
8Project Event :RFQs for geotechnical and topographical survey work at the FGD site is likely to be floated in November 2019.RFQ for supply, installation, erection, and commissioning of FGDs are expected to be out by Q1 2020.
Click here for more details  Details

Our Take

Jan 27: 8Siemens: Is the acquisition of C&S electric ltd, a reaction to the Schneider-L&T deal? Details
8Can a party exit from a Long Terms Power Purchase Agreement on being uneconomical or unviable? Details
8Advance Valves Private Limited: Margins exposed to raw material price fluctuations Details
8An conference on  Power & Energy technology is coming soon Details
8United Electricals & Engineering Pvt Ltd: Non Cooperating with rating agency Details
8Maheswari Mining and Energy Pvt Ltd: The projected cash flows sufficient to meet debt servicing requirements Details
You can also click on Reports
for more Details

Download Tenders and Newsclips

Jan 27: For reference purposes the website carries here the following tenders: 
8Tender for Supply, Erection and commissioning of 11kV outgoing feeders Details
8Tender for construction of 11kV line with ACSR conductor Details
8Tender for Supply of Station Transformer & it’s accessories Details
8Tender for construction of balance work of 220kV D/C transmission line Details
8Tender for Supply and Erection of Metallic Expansion Joints of hot air duct of Coal Mills Details
8Tender for Supply & fixing of various tower related material Details
8Tender for Procurement of Test set for measurement of resistivity & dissipation factor Details
8Tender for supply of high voltage DC test kit Details
8Supply, Construction, testing and Commissioning 1.75 Km of HT line with ABC Details
8Tender for procurement of generator management relays Details
8Tender for work of shifting/modification of 132kV LILO D/C line Details
8Design, Supply, installation, testing and commissioning of Battery Charger Details
8Tender for Work of providing 33 kV Isolators for by-pass arrangement Details
8Tender for Repairing of mill motor rotors Details
8Tender for construction of 11kV line with covered conductor Details
8Supply, Erection, Testing and commissioning of 33kV Outdoor Vacuum reclosure Details
8Tender for Procurement of spares of TGCCW pump Details
You can also click on Tenders
for more
For reference purposes the website carries here the following Newsclips:
8NLC eyes 21,011 Mw power generation by 2025, renewables to make up 4,200 Mw Details
8Link funding of state discoms to performance, PMO to Ministry Details
8Telecom gear maker ITI to invest Rs 150cr to boost solar panel capacity Details
8NTPC unlikely conclude THDCIL, NEEPCO acquisition deals this fiscal: Report Details
8CIL adheres to environmental, sustainable standards: CMD Details
8Power Grid moves SC against DoT demand of Rs 22K Crore Details
8Stakeholder meetings on commercial coal mining on Jan 28-29 Details
8Chhattisgarh CM demands Rs 4,000 crore from Centre for coal mining project Details
8Renewable-thermal power plan may find few takers Details
8Bengaluru rooftops can generate 2500MW solar power: Survey Details
8Andhra Pradesh: Govt plans 10,000 MW solar project Details
8Renewable-thermal power scheme unlikely to attract bidders Details
8Chandigarh electricity dept proposes continuing 1% rebate on bill payment Details
8Andhra Pradesh: Power body issues guidelines to distribution firms Details
8Hry to expand single-point connection, HERC okays 10,000 smart meters Details
8Better distribution may ease power sector woes: ETILC Details
8PFC gets $750 million foreign currency bonds listed at NSE IFSC Details
8Eyeing leadership position in electric vehicle segment: Tata Motors Details
8C&S acquisition aimed at making India exports hub: Sunil Mathur, MD& CEO-Siemens India Ltd Details
8UDAY is not a failure, discussed new discom revival scheme with FinMin: Power minister RK Singh Details
You can also click on Newsclips for more Details

Our Take

Jan 24: 8Vena Energy JMD Power Private Limited: Company’s operations may remain exposed to the risk of grid curtailment in future Details
8Udupi Power Corporation Ltd. Moderate credit profile of the off-takers Details
8NTPC: Expect fixed charge recoveries in 2HFY20 Details
8Techser Power Solutions Pvt. Ltd: Healthy capital structure with comfortable debt coverage metrics Details
8Pipartoda Renewable Energy Private Limited: Low counterparty credit risk with GUVNL as sole offtaker Details
8Andhra Pradesh Power Finance Corporation Limited: Modest financial risk profile Details
You can also click on Reports
for more Details

Download Tenders and Newsclips

Jan 24: For reference purposes the website carries here the following tenders: 
8Tender for the work of shifting/diversion 11KV & LT line Details
8Tender for Procurement of Lighting Arrestors Details
8Tender for Installation of Flue Gas Desulphurisation System Details
8Design, supply, erection and commissioning” of Solar Photo Voltaic based grid connected power plant Details
8Tender for Procurement of 200NB Pipes Details
8Tender for the supply of various types of heating element for Air Preheater Details
8Tender for the supply of Inner cone assembly with access door and inside ceramic lining suitable for XRP 803 mills Details
8Tender for biennial contract for operation & maintenance of dozers in CHP Details
8Tender for procurement of ACSR conductor Details
8Tender for procurement of 66/33 KV & 66/11KV Power Transformer Details
8Tender for Supply, erection, testing & commissioning of zirconia oxygen analyzer Details
8Tender for Operation & Maintenance contract of HVAC system of TPP Details
8Tender for AOH of instrumentation and control system Details
8Tender for Supply, Installation & commissioning of Smart 2X50KW networking and 10KW hybrid solar system Details
8Tender for Procurement of Chain Links and Chain Coupler Details
You can also click on Tenders
for more
For reference purposes the website carries here the following Newsclips: 
8For govt’s electricity auction to succeed, producers must relent on prices Details
8Marubeni, Total and Siraj Energy to Develop 800 MW of Solar Projects in Qatar Details
8State-owned EESL to place order for at least five MG Motor SUVs Details
8EESL Issues RfP for Partners in UAE to Execute Energy Efficiency and Renewable Solutions Details
8Solar PPAs Without Restitution Principle Can’t Claim Carrying Cost Compensation: CERC Details
8Power ministry appoints Ashish Upadhyaya as govt nominee director on NTPC board Details
8France’s ENGIE to sell 74% stake in India business to Edelweiss’ fund Details
8Vestas bags 60-MW order for wind project in Poland Details
8SECI to hold pre-bid meeting for 4-MW floating solar plant in Andaman Details
8Punjab: Solar shift for city railway station on cards Details
8Envision Energy commissions 2 wind projects in Gujarat Details
8IndiGrid to raise Rs 7,500 crore debt in 18 months to finance acquisitions Details
8NCLAT defers hearing on JSW Steel's Bhushan Power buyout till Jan 31 Details
8Niti Aayog seeks Cabinet nod for battery push Details
8Karnataka: BMTC rejects higher bid for e-buses; new tender floated Details
8NLC India to raise Rs 525 crore via bonds Details
You can also click on Newsclips for more
Details

Our Take

Jan 23: 8Larsen & Toubro (L&T): Power segment revenue declined sharply due to aggressive competition Details
8Coal monopoly is a deterrent to private investment in the sector: An analysis Details
8Assessment of ramping capability of thermal interstate generating stations (ISGS): What is new in the guidelines? Details
8The global energy storage market will grow to a cumulative 942GW by 2040 and will attract $620 billion in investment: A report
8Havells India: Power cable volume declined 20% Details
8Business opportunity in Coal mining project Details
You can also click on Reports
for more Details

Download Tenders and Newsclips

Jan 23: For reference purposes the website carries here the following tenders: 
8Tender for overhauling and maintenance contract of ash handling equipments Details
8Tender for maintenance of milling system Details
8Tender for Supply of Tubular Protectors & 'U' Clamps for the Boiler Details
8Tender for Supply of Collecting electrodes for ESPs at TPS Details
8Tender for BMC of DCS, PLC, Control System, Motorised Actuator and C&I Shift Maintenance Details
8Tender for Complete overhauling up to zero vibration of rotary breaker Details
8Tender for Procurement of Spares for fly ash system of AHP Details
8Tender for Annual contract of day to day maintenance of electrical control circuit Details
8Tender for procurement of spares of DG set Details
8Tender for Supply of Liners for TPS Details
8Tender for Construction of 132KV S/C Two Phase line on double circuit towers Details
8Tender for construction work of 132kV S/C line Details
8Tender for work of Shifting of tower of 132 KV Transmission line Details
8Tender for Replacement of damage LT alluminium armoured cable on turnkey basis Details
8Design, supply, installation, testing & commissioning of 33kV, 2 X 5MVAR Capacitor Banks Details
8Tender for engineering, procurement, erection, testing and commissioning of 33/11 kV back up power supply system Details
You can also click on Tenders
for more
For reference purposes the website carries here the following Newsclips:
8Power Minister seeks Brazilian investment in energy sector Details
8L&T Q3 consolidated net profit up 15% at Rs 2,560 crore Details
8State govts slash price of electricity generated by sugar mills by 50% Details
8Power producers' coal imports up 17.6% at 52.48 MT in Apr-Dec 2019 Details
8Adani Group aims to become world's largest solar power player by 2025: Gautam Adani Details
8Temasek, EQT set up $500m renewable energy JV Details
8China to stop subsidy for offshore renewables, eyes 2021 start for green quota trading Details
8Sterlite Power inks pact with US-based Smart Wires to bring SmartValve to Indian utilities Details
8Luminous Power appoints Niharika Mohan as Vice-President, HR Details
8Adani Power drives 21 per cent jump in Indian utilities' coal imports in 2019 Details
8Crompton appoints Vishal Kaul as vice-president Details
830 e-buses to ply in Patna by December Details
8ICRA expects Budget to focus on power discoms, RE and gas plants revival Details
8PMI Electro and BYD-Olectra bag most e-bus orders Details
8Chandigarh: Tariff revised, power bills to go up from next month Details
You can also click on Newsclips for more Details

Greenfield hydel project: RFQs in Q2, 2020 subject to grant of funding

Jan 22: Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 350.74 crores
8Project Description: The project promoter has approached a financial institution to fund the 48 MW (3x16 MW) greenfield hydel power
8Project Event:RFQ for the civil work package-1 is likely to be floated are likely to be floated in Q2 2020, subject to finding funding.
Click here for more details Details

Rs 5000 crore greenfield pumped storage project: RFQ for the civil work package in Q3 2020.

Jan 22: Project Name: Greenfield Pumped Storage Project
8Project Cost: 5146.98 crores
8Project Description: The owner and along with the DPR consultant WAPCOS LTD. is carried out site survey activities for a 1500 MW (6x250 MW) pumped storage hydropower project. The forest clearance proposal is stuck at Stage-I level. The PFR has been approved by the Ministry of Water Resources. The DPR works are likely to finish by the mid-2020.EIA and EMP studies under progress by the consultant R.S Envorolink Technology Pvt. Ltd. Tenders for the drilling and drifting activities are likely to be floated in Q3 2020.Further bids are expected soon.
8
Project Event: RFQ for the civil work package-1 is likely to be floated in Q3 2020.
8Expenditure Approval: Q4:2018
8RFQ Date:Nov:Q3: 2020
8Release Date:Q3: 2020
8Start Date:  2021
8Completion Date: Q4: 2024
Click here for more details
Details

Rs 17000 crore supercritical thermal power plant: RFQ for the EPC contractor package for main plant works is likely to float on Q3 2020

Jan 22: Project Name: Supercritical Thermal Power Plant
8Project Cost: Rs 17000.00 crores
8
Project EventRFQ for the EPC contractor package for main plant works is likely to float on Q3 2020
8Expenditure Approval: Q2:2019
8RFQ Date:Nov:Q3: 2020
8Release Date:Q3: 2020
8Start Date:  2021
8Completion Date: Q4: 2025
Click here for more details
Details

Rs 20000 crore standalone pumped storage project: DPR consultant RFQ in Q-3, 2020

Jan 27: Project Name: Standalone Pumped Storage Project
8Project Cost: Rs: Rs:20030 crore
8Project Description: The owner plans to install a 5040 MW standalone pumped storage project. The pre-feasibility report was prepared by in house resources. TOR was accepted by MoEF. The preparation of DPR will start after getting approval. RFQ for the DPR consultant is likely to be floated in Q3 2020.
8Project Event: RFQ for the DPR consultant is likely to be floated in Q3 2020..
Click here for more details Details

Rs 2553 crore multipurpose hydel project" RFQs ahead

Jan 27: Project Name: Multipurpose Greenfield Hydroelectric Project
8Project Cost: Rs 2553.63 crores
8Project Description: The owner plans to install 130 MW Multipurpose Hydroelectric plant
8Project Event: RFQ for drilling and drifting works is likely to be floated in Q3 2020.
Click here for more details Details

Rs 870 greenfield hydel project: RFQ for civil work package-1 in Q3, 3030

Jan 27: Project Name: Greenfield Hydroelectric Power Project
8Project Cost: Rs 870.39 crore
8Project Description: The owner is undertaking additional S&I activities along with relief and rehabilitation activities in a 88.5 MW (3*29.5 MW) greenfield hydel project
8Project Event: RFQ for the civil works package -1 is likely to be floated in Q3 2020.
8Expenditure Approval: Q4: 2019
8RFQ Date: Q3:2020
8Release Date: Q3:2020
8Start Date: 2021
8Completion Date: 2024
Click here for more details Details

FDG addition coming up ahead

Jan 27: Project Name: Thermal Power Station - FGD Addition
8Project Cost: Rs.: 400Crores
8Project Event :RFQs for geotechnical and topographical survey work at the FGD site is likely to be floated in November 2019.RFQ for supply, installation, erection, and commissioning of FGDs are expected to be out by Q1 2020.
Click here for more details  Details

Our Take

Jan 27: 8Siemens: Is the acquisition of C&S electric ltd, a reaction to the Schneider-L&T deal? Details
8Can a party exit from a Long Terms Power Purchase Agreement on being uneconomical or unviable? Details
8Advance Valves Private Limited: Margins exposed to raw material price fluctuations Details
8An conference on  Power & Energy technology is coming soon Details
8United Electricals & Engineering Pvt Ltd: Non Cooperating with rating agency Details
8Maheswari Mining and Energy Pvt Ltd: The projected cash flows sufficient to meet debt servicing requirements Details
You can also click on Reports
for more Details

Download Tenders and Newsclips

Jan 27: For reference purposes the website carries here the following tenders: 
8Tender for Supply, Erection and commissioning of 11kV outgoing feeders Details
8Tender for construction of 11kV line with ACSR conductor Details
8Tender for Supply of Station Transformer & it’s accessories Details
8Tender for construction of balance work of 220kV D/C transmission line Details
8Tender for Supply and Erection of Metallic Expansion Joints of hot air duct of Coal Mills Details
8Tender for Supply & fixing of various tower related material Details
8Tender for Procurement of Test set for measurement of resistivity & dissipation factor Details
8Tender for supply of high voltage DC test kit Details
8Supply, Construction, testing and Commissioning 1.75 Km of HT line with ABC Details
8Tender for procurement of generator management relays Details
8Tender for work of shifting/modification of 132kV LILO D/C line Details
8Design, Supply, installation, testing and commissioning of Battery Charger Details
8Tender for Work of providing 33 kV Isolators for by-pass arrangement Details
8Tender for Repairing of mill motor rotors Details
8Tender for construction of 11kV line with covered conductor Details
8Supply, Erection, Testing and commissioning of 33kV Outdoor Vacuum reclosure Details
8Tender for Procurement of spares of TGCCW pump Details
You can also click on Tenders
for more
For reference purposes the website carries here the following Newsclips:
8NLC eyes 21,011 Mw power generation by 2025, renewables to make up 4,200 Mw Details
8Link funding of state discoms to performance, PMO to Ministry Details
8Telecom gear maker ITI to invest Rs 150cr to boost solar panel capacity Details
8NTPC unlikely conclude THDCIL, NEEPCO acquisition deals this fiscal: Report Details
8CIL adheres to environmental, sustainable standards: CMD Details
8Power Grid moves SC against DoT demand of Rs 22K Crore Details
8Stakeholder meetings on commercial coal mining on Jan 28-29 Details
8Chhattisgarh CM demands Rs 4,000 crore from Centre for coal mining project Details
8Renewable-thermal power plan may find few takers Details
8Bengaluru rooftops can generate 2500MW solar power: Survey Details
8Andhra Pradesh: Govt plans 10,000 MW solar project Details
8Renewable-thermal power scheme unlikely to attract bidders Details
8Chandigarh electricity dept proposes continuing 1% rebate on bill payment Details
8Andhra Pradesh: Power body issues guidelines to distribution firms Details
8Hry to expand single-point connection, HERC okays 10,000 smart meters Details
8Better distribution may ease power sector woes: ETILC Details
8PFC gets $750 million foreign currency bonds listed at NSE IFSC Details
8Eyeing leadership position in electric vehicle segment: Tata Motors Details
8C&S acquisition aimed at making India exports hub: Sunil Mathur, MD& CEO-Siemens India Ltd Details
8UDAY is not a failure, discussed new discom revival scheme with FinMin: Power minister RK Singh Details
You can also click on Newsclips for more Details

Our Take

Jan 24: 8Vena Energy JMD Power Private Limited: Company’s operations may remain exposed to the risk of grid curtailment in future Details
8Udupi Power Corporation Ltd. Moderate credit profile of the off-takers Details
8NTPC: Expect fixed charge recoveries in 2HFY20 Details
8Techser Power Solutions Pvt. Ltd: Healthy capital structure with comfortable debt coverage metrics Details
8Pipartoda Renewable Energy Private Limited: Low counterparty credit risk with GUVNL as sole offtaker Details
8Andhra Pradesh Power Finance Corporation Limited: Modest financial risk profile Details
You can also click on Reports
for more Details

Jan 01: Details

Download Tenders and Newsclips

Jan 24: For reference purposes the website carries here the following tenders: 
8Tender for the work of shifting/diversion 11KV & LT line Details
8Tender for Procurement of Lighting Arrestors Details
8Tender for Installation of Flue Gas Desulphurisation System Details
8Design, supply, erection and commissioning” of Solar Photo Voltaic based grid connected power plant Details
8Tender for Procurement of 200NB Pipes Details
8Tender for the supply of various types of heating element for Air Preheater Details
8Tender for the supply of Inner cone assembly with access door and inside ceramic lining suitable for XRP 803 mills Details
8Tender for biennial contract for operation & maintenance of dozers in CHP Details
8Tender for procurement of ACSR conductor Details
8Tender for procurement of 66/33 KV & 66/11KV Power Transformer Details
8Tender for Supply, erection, testing & commissioning of zirconia oxygen analyzer Details
8Tender for Operation & Maintenance contract of HVAC system of TPP Details
8Tender for AOH of instrumentation and control system Details
8Tender for Supply, Installation & commissioning of Smart 2X50KW networking and 10KW hybrid solar system Details
8Tender for Procurement of Chain Links and Chain Coupler Details
You can also click on Tenders
for more
For reference purposes the website carries here the following Newsclips: 
8For govt’s electricity auction to succeed, producers must relent on prices Details
8Marubeni, Total and Siraj Energy to Develop 800 MW of Solar Projects in Qatar Details
8State-owned EESL to place order for at least five MG Motor SUVs Details
8EESL Issues RfP for Partners in UAE to Execute Energy Efficiency and Renewable Solutions Details
8Solar PPAs Without Restitution Principle Can’t Claim Carrying Cost Compensation: CERC Details
8Power ministry appoints Ashish Upadhyaya as govt nominee director on NTPC board Details
8France’s ENGIE to sell 74% stake in India business to Edelweiss’ fund Details
8Vestas bags 60-MW order for wind project in Poland Details
8SECI to hold pre-bid meeting for 4-MW floating solar plant in Andaman Details
8Punjab: Solar shift for city railway station on cards Details
8Envision Energy commissions 2 wind projects in Gujarat Details
8IndiGrid to raise Rs 7,500 crore debt in 18 months to finance acquisitions Details
8NCLAT defers hearing on JSW Steel's Bhushan Power buyout till Jan 31 Details
8Niti Aayog seeks Cabinet nod for battery push Details
8Karnataka: BMTC rejects higher bid for e-buses; new tender floated Details
8NLC India to raise Rs 525 crore via bonds Details
You can also click on Newsclips for more
Details

Our Take

Jan 23: 8Larsen & Toubro (L&T): Power segment revenue declined sharply due to aggressive competition Details
8Coal monopoly is a deterrent to private investment in the sector: An analysis Details
8Assessment of ramping capability of thermal interstate generating stations (ISGS): What is new in the guidelines? Details
8The global energy storage market will grow to a cumulative 942GW by 2040 and will attract $620 billion in investment: A report
8Havells India: Power cable volume declined 20% Details
8Business opportunity in Coal mining project Details
You can also click on Reports
for more Details

Jan 01: Details

Download Tenders and Newsclips

Jan 23: For reference purposes the website carries here the following tenders: 
8Tender for overhauling and maintenance contract of ash handling equipments Details
8Tender for maintenance of milling system Details
8Tender for Supply of Tubular Protectors & 'U' Clamps for the Boiler Details
8Tender for Supply of Collecting electrodes for ESPs at TPS Details
8Tender for BMC of DCS, PLC, Control System, Motorised Actuator and C&I Shift Maintenance Details
8Tender for Complete overhauling up to zero vibration of rotary breaker Details
8Tender for Procurement of Spares for fly ash system of AHP Details
8Tender for Annual contract of day to day maintenance of electrical control circuit Details
8Tender for procurement of spares of DG set Details
8Tender for Supply of Liners for TPS Details
8Tender for Construction of 132KV S/C Two Phase line on double circuit towers Details
8Tender for construction work of 132kV S/C line Details
8Tender for work of Shifting of tower of 132 KV Transmission line Details
8Tender for Replacement of damage LT alluminium armoured cable on turnkey basis Details
8Design, supply, installation, testing & commissioning of 33kV, 2 X 5MVAR Capacitor Banks Details
8Tender for engineering, procurement, erection, testing and commissioning of 33/11 kV back up power supply system Details
You can also click on Tenders
for more
For reference purposes the website carries here the following Newsclips:
8Power Minister seeks Brazilian investment in energy sector Details
8L&T Q3 consolidated net profit up 15% at Rs 2,560 crore Details
8State govts slash price of electricity generated by sugar mills by 50% Details
8Power producers' coal imports up 17.6% at 52.48 MT in Apr-Dec 2019 Details
8Adani Group aims to become world's largest solar power player by 2025: Gautam Adani Details
8Temasek, EQT set up $500m renewable energy JV Details
8China to stop subsidy for offshore renewables, eyes 2021 start for green quota trading Details
8Sterlite Power inks pact with US-based Smart Wires to bring SmartValve to Indian utilities Details
8Luminous Power appoints Niharika Mohan as Vice-President, HR Details
8Adani Power drives 21 per cent jump in Indian utilities' coal imports in 2019 Details
8Crompton appoints Vishal Kaul as vice-president Details
830 e-buses to ply in Patna by December Details
8ICRA expects Budget to focus on power discoms, RE and gas plants revival Details
8PMI Electro and BYD-Olectra bag most e-bus orders Details
8Chandigarh: Tariff revised, power bills to go up from next month Details
You can also click on Newsclips for more Details

Jan 01: Details

Jan 01: Details

Greenfield hydel project: RFQs in Q2, 2020 subject to grant of funding

Jan 22: Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 350.74 crores
8Project Description: The project promoter has approached a financial institution to fund the 48 MW (3x16 MW) greenfield hydel power
8Project Event:RFQ for the civil work package-1 is likely to be floated are likely to be floated in Q2 2020, subject to finding funding.
Click here for more details Details

Jan 01: Details

Rs 5000 crore greenfield pumped storage project: RFQ for the civil work package in Q3 2020.

Jan 22: Project Name: Greenfield Pumped Storage Project
8Project Cost: 5146.98 crores
8Project Description: The owner and along with the DPR consultant WAPCOS LTD. is carried out site survey activities for a 1500 MW (6x250 MW) pumped storage hydropower project. The forest clearance proposal is stuck at Stage-I level. The PFR has been approved by the Ministry of Water Resources. The DPR works are likely to finish by the mid-2020.EIA and EMP studies under progress by the consultant R.S Envorolink Technology Pvt. Ltd. Tenders for the drilling and drifting activities are likely to be floated in Q3 2020.Further bids are expected soon.
8
Project Event: RFQ for the civil work package-1 is likely to be floated in Q3 2020.
8Expenditure Approval: Q4:2018
8RFQ Date:Nov:Q3: 2020
8Release Date:Q3: 2020
8Start Date:  2021
8Completion Date: Q4: 2024
Click here for more details
Details

Jan 01: Details

Rs 17000 crore supercritical thermal power plant: RFQ for the EPC contractor package for main plant works is likely to float on Q3 2020

Jan 22: Project Name: Supercritical Thermal Power Plant
8Project Cost: Rs 17000.00 crores
8
Project EventRFQ for the EPC contractor package for main plant works is likely to float on Q3 2020
8Expenditure Approval: Q2:2019
8RFQ Date:Nov:Q3: 2020
8Release Date:Q3: 2020
8Start Date:  2021
8Completion Date: Q4: 2025
Click here for more details
Details

Jan 01: Details
  • Jan 21: Download Tenders and Newsclips:Details
  • Jan 20: Our Take:Details
  • Jan 20: Download Tenders and Newsclips:Details
  • Jan 17: Rs 287.59 crore hydroelectric project: Civil work package-1 in Q2, 2020:Details
  • Jan 17: Rs 885.25 crore greenfield hydroelectric project: Civil works package in Q3, 2020:Details
  • Jan 17: Our Take:Details