Addendum-VI reverses Zone VI error and switches Sirkari Bhyol turbine bearings to oil lubrication
8UJVNL has restored the project's IIT Roorkee-derived Zone V seismic basis after an intervening addendum wrongly cited Zone VI, and in the same document replaced water-lubricated guide bearings with babbitted oil-lubricated units with water cooling.
8The bearing change reaches cooling circuits, oil handling, monitoring and maintenance philosophy, so the harder question is how much lifetime auxiliary-system cost bidders must now carry into a 48-month fixed package.
NTPC issues second corrigendum on Simhadri 0.5 MMT coal without resolving 25% versus 10% quantity conflict
8Corrigendum C4 of 11 September supersedes C1 and the original buyer-added terms for the Rs 2 crore EMD Simhadri lot, retaining the right to move ordered quantity by up to 25% at award and again during the contract.
8Technical Specification Clause 3 still carries a plus or minus 10% station band, and with the GeM summary recording no ePBG against ITB Clause 22.0's mandatory 5% PBG, bidders must price a maximum volume and security exposure the documents do not settle.
UPPTCL deletes 'provided by UPPTCL' from transformer rows, forcing Noida GIS bidders to price erection
8Corrigendum-1 has replaced the BOQ for the Rs 112.05 crore Sector-155 substation, removing the entry that let bidders leave installation of the 160 MVA and 63 MVA owner-supplied transformers unpriced, and redefining 33 kV termination kits by interface rather than indoor or outdoor location.
8Submission moved a week to 17 September, but the real exposure is that the contractor now prices commissioning around equipment whose manufacture and delivery stay with UPPTCL, with no project-specific relief formula for late handover.
UPRVUNL converts 640 MW Rihand-Obra pumped storage from BOO to zero-consideration handover after 40 years
8The corrigendum replaces extendable BOO ownership with compulsory transfer to UPRVUNL 40 years from SCOD, in good running condition, free of liens and without transfer price or compensation, while the PBG moves to 5% of the Rs 3,953 crore estimate at Rs 197.65 crore and stays live until 12 months after actual commissioning.
8With nine extensions pushing bids to 12 October and forfeiture possible where the developer's own DPR finds the project infeasible, the test is how banks price terminal transfer beside pre-construction feasibility risk.
OPTCL opens Rs 301 crore HTLS reconductoring with two different estimates in its own records
8The Meramundali–Mendhasal package requires dismantling twin AAAC Moose and stringing twin HTLS on the live 400 kV double-circuit line, plus equipment and bus upgrades at both grid-substation ends, with bids closing 9 October.
8The signed notice states Rs 301,22,38,089 while the portal header reads Rs 3,01,26,70,182, and with outage allocation, tower adequacy and scrap responsibility all unspecified, bidders face a package whose basic commercial reference point is unreconciled.
POWERGRID ties 765kV GIS package SS 185T to a TBCB outcome bidders cannot influence
8The Orai, Patran and Agra extension package requires an exclusive MOU with the lowest evaluated qualified bidder, who receives a contract only if POWERGRID wins the upstream tariff-based bid, while exclusivity bars that bidder and connected entities from supporting rival TSPs.
8Four qualification routes admit manufacturers, collaborator and parent-backed Indian plants and EPC bidders, but with a further 10% ex-works guarantee on Routes 2 and 3 and no quantified compensation if POWERGRID loses, broad access on paper may still leave OEM gatekeeping intact.
NTPC builds six-contractor panel for Rs 300 crore Barh pond ash haulage with no purchase-order guarantee
8The 2026-27 rate contract splits work among up to six AST-01 vendors matching a single L1 price, one part reserved for an SC/ST MSE bidder, with roughly Rs 20 crore placed sequentially and Rs 50 crore as the cumulative ceiling per contractor.
8Payment follows compacted ash certified by the receiving road authority rather than trips or weighbridge tonnage, and with variation from minus 100% to plus 20%, panel entry buys eligibility rather than revenue.
GPCL risk-management RFP carries three submission deadlines and a hard copy that overrides the portal
8The ERM consultancy for GPCL's renewable, BESS, green hydrogen, mining and transmission portfolio records online closing at 18:00 on 21 September on the portal, 3 October in Chapter 1 and physical receipt on 6 October, with clause 5.3.2 giving the posted copy precedence.
8The QCBS 70:30 structure is designed to protect technical quality, but a compliant bidder could still be rejected for following one official instruction over another unless GPCL clarifies which date and channel govern.
MPPTCL bars partial bids on Rs 316 crore Sabalgarh package spanning substation, 34 km line and LILO
8TR-28/2026 bundles a new 400 kV substation, a Quad Moose double-circuit link to Morena Pooling and about 21 km of 220 kV LILO into one indivisible turnkey award, with 30-month and 24-month completion tracks and no rainy-season relief, while three 500 MVA and two 200 MVA transformers and two 125 MVAR reactors stay outside contractor supply.
8Price variation reaches only selected equipment and civil work, so reverse-auction pressure will meet a large block of fixed-price and deemed-inclusion exposure.
NTPC Lara mine-filling tender contradicts itself on diesel escalation and soil-cover thickness
8The Rs 255.06 crore package moving 20 lakh MT of ash into the Bishrampur and Dugga pits says no extra payment for fuel-rate changes at condition 2(h), then indexes 25% of contract price to diesel at Clause 14, while Scope Clause 1 fixes a 500 mm soil cap against Payment Clause 9(i)'s 300-500 mm band.
8With quantity variable from minus 100% to plus 20% across a six-way split and no order-of-precedence statement, both conflicts sit directly on the lump-sum price.
APCPL admits Talabira coal in one clause and excludes OCPL in another for 5 LMT Jhajjar buy
8The invitation for bids for the Rs 5 crore EMD package bars coal from CIL, SCCL, OCPL and NTPC group mines, while Technical Specification Clause 2 expressly permits OCPL and Talabira sources including the NLCIL captive mine.
8A second gap sits between Annexure-B1's 4,300 Kcal/kg ceiling and Clause 11's payment cap at 4,000 Kcal/kg, leaving a bidder unable to know whether its declared source qualifies or its better coal can be monetised.
MSEDCL grants nine days on Rs 97.87 crore cable tender but holds firm price against five bidders
8Shriram Cables, Torrent Electricals, Dynamic, KEI and Tirupati each sought price variation on the 33 kV and 11 kV 300 sq.mm HT XLPE package, and MSEDCL answered every request with "as per tender documents," also refusing KEI's three-month first-lot request and Tirupati's insurance surety bond proposal.
8Bidding moved from 1 September to 10 September, leaving a nine-month firm-price delivery, a 20% two-month mobilisation obligation and 1% weekly LD untouched.
OPTCL forces single award across Palaspanga and Barbil while its notice repeats the EMD as the estimate
8The Rs 315.27 crore package makes Lot-I and Lot-II one indivisible contract covering GIS at both stations, 1.2 Rkm of underground cable and roughly 69.2 Rkm of 220 kV overhead line including Twin Moose on 400 kV towers, all in 24 months.
8The opening notice states the estimate as Rs 3.15 crore, exactly the EMD figure, and Table-A carries 10 August against the portal's 11 August, leaving bidders to rely on portal precedence for basic commercial approvals.
HPPCL seeks green hydrogen offtakers for 1 MW Dabhota plant without naming volume, purity or delivery point
8The EOI sets a Rs 1 EMD, zero form fee and Rs 2,360 processing charge, with closing on 13 August and cost opening one hour later, but does not state saleable output, pressure, metering ownership, custody transfer or contract tenure.
8Classified simultaneously as procurement of services and miscellaneous works with a scheduled cost opening, the notification leaves respondents unsure whether they are quoting a purchase price, a service charge or a bundled logistics proposition.
NTPC leaves three quantity formulations live across its 2.5 MMT five-station coal package
8The Telangana lot under CS-0011-011(10)-9 now carries a plus or minus 20% variation in the revised detailed document, plus or minus 10% in the separate technical specification and a 25% GeM option clause at both order placement and during contract.
8Sequential station opening means a bidder's later price bids stay unopened once it reaches its declared Annexure-TC-10 limit, making award appetite a live competitive variable before any price is compared.
NTPC cuts Tanda coal ceiling to 3,700 Kcal/kg while lifting initial payment to 80%
8Revised Annexure-B1 pulls the GCV envelope down from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal caps of 12% and 14%, and the GCV challenge window contracts from ten working days to seven calendar days with a ±71.7 Kcal/kg admissibility threshold.
8The move from 50% to 80% initial payment is the clearest contractor gain in the package, but it arrives alongside ±20% quantity variation, station diversion rights and a source pool narrowed by the tighter specification.
Nabinagar sits last in NTPC's price-opening order, exposing it to a thinner field
8Corrigendum-1 leaves the 16 September dates unchanged for the 0.5 MMT lot and fixes the opening sequence as Telangana, Simhadri, Mouda, Tanda and Nabinagar, with bid security shown at Rs 10 crore for five stations against a visible overwritten Rs 8 crore in ITB Clause 7.1.
8Because bidders reaching their declared award ceiling drop out before later envelopes are opened, the last station in the queue may face the weakest price competition regardless of its own economics.
NHPC inserts a missing crane chapter and cuts turbine efficiency threshold to 94% at Dulhasti Stage-II
8Corrigendum No. 1 added the absent Chapter 18 covering two 190/30-tonne powerhouse cranes and three others, Corrigendum No. 5 rewrote the cooling-water and HVAC chapters and lowered the non-responsiveness threshold from 94.5% to 94%, and price-adjustment indices moved from 2011-12 to 2022-23.
8Four extensions have taken submission from 24 July to 28 September on the Rs 496.90 crore package, yet unit commissioning stays fixed at months 43 and 44 from the civil zero date.
UJVNL lets two OEMs cover turbine and generator at Tiuni Plasu after 18 extensions
8Addendum-II moved qualification from turbine and generator to turbine "and/or" generator and deleted the contract-value experience thresholds, and Addendum-VI then allowed as many as two manufacturers, with force-majeure substitution limited to BHEL, Voith Hydro, Andritz Hydro and General Electric.
8Addendum-III deleted air-gap, partial-discharge and vibration monitoring and cut excitation redundancy from n+n to n+1, so the widened front door arrives with a thinner reliability margin and a Rs 260 crore turnover test for manufacturer-backed bidders.
JERC bars consultants holding two of three earlier awards from Chandigarh STU-SLDC tariff work
8The Rs 18 lakh QCBS assignment covering business plans, MYT petitions, mid-term review and true-ups to FY 2029-30 excludes firms already awarded two of three specified JERC bids, while demanding ten years of experience, 20 assignments worth Rs 1 crore and two staff stationed at the Commission.
8Corrigendum C3 warns that a participation fee can render the bid null and void, even though the underlying RFP still requires a Rs 10,000 processing fee and advance hard copies.
SECI moves Ramagiri wind auction to cost per certified MU and drops turbine floor to 2.7 MW
8Amendment-01 rewrites ITB Clause 32.4.1 so bids rank on EBV divided by NIWE-certified ten-year P90 generation, with the denominator locked before the reverse auction and only price free to move, while the power-curve pass mark falls from 98% to 95% and the 96-hour test threshold from 98% to 96%.
8Repeated STPT failure no longer triggers WTG rejection and refund with 13% interest but a generation-linked LD at Rs 4.5 per kWh, leaving yield certification quality as commercially decisive as the EPC quote.
NPCL wants 300 MW RTC with 90% availability in six peak hours it picks day-ahead
8The 25-year BOO procurement requires a declared annual CUF of at least 75% held within plus or minus 10%, 50% of contracted capacity in every off-peak 15-minute block and 90% across six peak hours selected by NPCL on a day-ahead basis, with shortfall damages at 1.5 times tariff.
8Configuration and delivery points may change until financial closure but bring no SCSD relief, so the 24-month schedule and daily PBG encashment will likely surface as a firmness premium in the discovered tariff.
NTPC narrows Mouda coal window to 3,700 Kcal/kg as second corrigendum lands five days before bids close
8Corrigendum C4 of 11 September supersedes C1 for the 5 lakh MT package, while the revised document cuts maximum GCV from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal 12% and 14% caps, and moves payment from 50:40:10 to 80:10:10 with sampling charges down to Rs 2.97 per MT.
8GeM records no ePBG and no arbitration against Clause 22.0's 5% security and a Delhi-seated GCC arbitration, leaving document precedence to carry more commercial weight than the headline tonnage.
Odisha Coal and Power Limited caps Tangardihi North's exploration phase at Rs 25 crore and ranks bidders on 397 million tonnes
8A Phase I quotation above the ceiling is reduced to Rs 25 crore rather than improving the evaluated position, while the Base Mining Charge is multiplied across a comparison quantity that detailed drilling has yet to confirm.
8Around 14,000 metres of exploration sits inside the same contract whose 25-year operating commitment depends on what that drilling finds.
WAPCOS gives three masked bidders ten days to respond to a five-year strategy mandate classified as an emergency
8The Rs 1.50 crore QCBS assignment weights technique at 80%, with 60 of 100 technical marks resting on named expert CVs and a presentation.
8Arbitration and consensual ADR are excluded entirely, leaving employer-controlled internal review, mediation and Delhi civil courts as the dispute route.
Gujarat Energy Transmission Corporation Limited's Navsari cable tender lists 193,186 metres of 66 kV cable against a 24,218-metre route survey
8The Rs 98.48 crore item-rate package also carries six foundation categories each showing eight tower foundations while the total tower-erection quantity is also eight, leaving the BOQ open to interpretation before pricing.
8Amendment no. 1 moves delay damages from the delayed portion to 0.5% of the entire contract price per week, capped at 10%, or roughly Rs 9.85 crore plus GST.
Maharashtra State Electricity Transmission Company Limited puts a Rs 73.19 lakh breaker overhaul across 12 substations without a breaker count
8The notice covers spares supply and complete mechanism overhauling of CGL-make 132 kV breakers at sites spanning both 132 kV and 220 kV yards.
8Mechanism types, spare schedules, outage duration, testing protocol, warranty and completion period are not specified in the document, leaving the estimate impossible to test against actual scope.
NTPC Renewable's 600 MW Anantapur wind tender gives bidders a week more to price but no way to ask why
8Corrigendum No. 1 pushed submission to 22 September 2026 while leaving the 1 September query deadline untouched, so late-discovered ambiguity has nowhere formal to go.
8With Rs 50 crore bid security, ten-year comprehensive O&M and roads, pooling and evacuation all outside the WTG package, the unresolved issue is who carries commissioning delay at the boundary.
JdVVNL rewrites the BOQ a third time and swaps Bikaner territories between two RDSS packages
8Corrigendum 3 moved Dungargarh and Nokha into TNTW-796 while DD-I, DD-II and Khajuwala travelled the other way, settling the value at Rs 119.89 crore — a net movement of about 0.1%.
8That small headline change can conceal much larger line-item additions and deletions, which is precisely what bidders repeatedly queried before the revision.
AEGCL's Khumtai 400kV GIS tender carries a Rs 50 lakh EMD contradiction and a 12-month schedule gap
8The invitation and ITB 2.37.1 set two years for completion while SCC 8.2 requires 36 months, and the EMD reads Rs 5.5 crore in numerals against "Rupees Five Crore only" in words.
8Turnover and financial-resource thresholds carry the same numeral-versus-wording conflict, making eligibility itself uncertain before the 12 October closing.
GETCO's Viksit Gujarat @2047 adviser tender records two turnover thresholds twenty times apart
8The GeM page states Rs 48 crore while the RFP and buyer-added conditions demand Rs 1,000 crore, and submission and opening dates differ by a day between portal and document.
8With GST treatment also contradicted between two clauses, the tender risks producing technically incomparable bids priced on different assumptions.
GETCO's Rs 210.62 crore Bharuch cable package lets each approved OEM back only one bid
8Amendment-I restructured qualification into OEM, nominated-OEM and two-member JV routes, then barred any firm from appearing in different roles across competing bids.
8The contest may therefore be settled by early OEM alignment rather than by how many erection contractors can qualify.
KPTCL's Rs 131.92 crore Byadagi package reaches the market tagged as a computer lab
8The portal lists bid validity as 90 days against the signed document's 180, describes the scope as "Setting up of Computer Lab", and keeps the clarification window open 30 minutes after bids close.
8A Clause 3.2(e) heading referring to a 100 MVA transformer against a 160 MVA requirement compounds the risk of divergent qualification readings.
RRVUN cuts the coal experience bar by 6.25% and then quietly extends group credentials to technical qualification
8Amendment-I lowered the single-contract threshold from 1 million MT to 9,37,500 MT and admitted IPP supplies; Corrigendum-I then widened 100%-owned parent or subsidiary reliance from financial to both technical and financial PQR.
8JV and consortium participation stays barred, so the widening favours tightly held corporate groups rather than assembled bidding alliances.
WBSETCL's Sadarghat composite package republishes its evaluation clause with a broken cross-reference
8Amended ITB 28.2 now reads "DP = Differential price calculated according to0", severing the link to the calculation method in ITB 28.4, while the reverse-auction cross-reference disappears entirely.
8Reverse-auction clause 9 separately dispenses with additional security where L1 is "less than 20% of the estimated cost" — a literal reading that relaxes protection at the lowest prices.
NHPC raises generator efficiency loading 20.6% on the Rs 641.11 crore Uri-I Stage-II package
8The turbine equalisation rate moved from Rs 8.32 lakh to Rs 8.74 lakh per 0.1 percentage point, while the generator rate jumped from Rs 21.64 lakh to Rs 26.10 lakh.
8Cheaper machines with weaker guarantees can now lose their price advantage at evaluation, even before PLCC relocation and revised cooling-water scope are priced.
WBSETCL's 68 km Salboni 400 kV line tender resolves a 60 mm creepage conflict but keeps ROW with the contractor
8The pre-bid response directed bidders to the technical specification's 430 mm over the BOQ's 370 mm and issued a revised BOQ, while fixing conductor diameter at 28.62 mm and sag at 15.93 m.
8Tower-footing compensation, trees, crops and access remain contractor-priced with no escalation for court-driven delay, and the 24-month clock survives two extensions.
RRECL's 201 MW solar tender slips 63 days and then adds a letter of credit
8Four corrigenda moved submission from 14 July to 15 September 2026 while the nine-month commissioning obligation and 25-year term stayed fixed.
8The pre-bid addendum inserted a revolving monthly LC and replaced the client's first charge over liquidated assets with priority application of proceeds — a lender accommodation whose value depends on the still-ambiguous "Cover-1 & Cover-2" opening language.
HPSEBL extends its Rs 3.72 crore Kinnaur-Spiti PMC tender for the fifth time without explaining why
8Corrigenda I to V added 64 calendar days to both submission and technical opening while leaving scope, staffing, securities and the 246 man-month deployment untouched.
8The unresolved question is award mechanics: a 70:30 QCBS formula and an English e-reverse auction sit in the same document with no stated hierarchy.
GETCO shifts LD on the Rs 224.80 crore Dholera-II GIS package from the delayed portion to the whole contract
8SCC clause 41 now calculates 0.5% per week on the full contract price capped at 10%, recoverable across GUVNL group contracts, while requests to extend 30 months to 34 and to substitute PEB for RCC were refused.
8A local civil or commissioning slip can now generate package-wide exposure on a site carrying saline conditions, seismic zone 5 and cast-in-situ piling.
MePDCL splits Khasi Hills into six lots and hands four of them to one contractor
8The Rs 120.42 crore award concentrates Rs 82.12 crore, or 68.2% of L1 value, with a single firm across Lots 1, 3, 5 and 6.
8Lot 3 reached financial opening with one responsive bidder out of seven, leaving no L2 comparator to test whether that price was competitive at all.
NHPC rewrites force majeure and idling-cost recovery across both its hydro E&M packages
8The revised GCC Clause 37 adds terrorism, qualifying strikes and pandemic spread while removing the magnitude-7 earthquake threshold and express treatment of bandhs, lightning and unprecedented floods.
8Annex-A now caps compensable idling through a formula using 5% of composite contract price, with a 2% sub-cap on miscellaneous establishment expenditure and extended-warranty recovery at 2.25% per annum.
RVUN's Rs 1,125 crore coal tender is tagged emergency procurement without naming which rule applies
8The portal cites Rule 40(1), 43(6) or 43(7) but does not identify the provision invoked or the factual justification, and the original window ran just seven days from publication to submission.
8Coal grade, sampling agency, delivery duration, LD framework and PBG terms are absent from the published notice, leaving the commercial risk difficult to quantify before bidding.
WBSETCL's H1-elimination auction meets a 10% security stack that runs five years past commissioning
8The Sadarghat package removes the highest offer only where four valid price bids exist, so two or three qualified bidders all proceed to the auction intact.
8The winner must then carry separate 10% guarantees on GIS equipment for three years and transformers for five from the Taking-Over Certificate, with formal joint ventures barred.
APEPDCL grants 24 extra days on its Rs 143.32 crore SCADA package without touching a single execution obligation
8Three corrigenda moved submission from 1 September to 25 September 2026, but the 18-month implementation period, five-year FMS and 10% performance security stayed exactly where they were.
8What the extensions really concede is preparation time for a bidder pool that must satisfy two separate qualification streams and assemble OEM authorisations before it can quote.
RVPN's Rs 83.38 crore Shiv Enclave GIS package makes unlisted work the contractor's problem
8A 132/33 kV, 2x80 MVA GIS substation with a 4 km LILO cable arrangement carries a 545-day execution period and a 10% performance security, extended eight days by Corrigendum No. 01.
8The clause that matters is GCC 3.2, which absorbs reasonably inferable items into the contractor's scope without automatic additional payment.
NTPC puts 2,184 man-months of construction safety at Telangana Stage-II behind a 52-month firm-rate contract
8The consultant must field 47 personnel, run a 24/7 IP-camera control room and approve other agencies' JSA/HIRA documents across a 3 x 800 MW build.
8The commercial risk is not the Rs 5,000-per-day non-deployment penalty but firm rates through a unilateral 12-month extension, 5% retention and no interest on deferred payment.
TNPDCL asks for 5,000 distribution transformers while the protected BOQ shows a quantity of one
8The M-256 tender covers 5,000 units of 100 kVA, EEL-2 aluminium-wound transformers with a Rs 1,00,20,500 EMD, a ±25% quantity variation and a 60-month guarantee.
8The BOQ's "1.0 No." line and its residual civil-work text sit inside a spreadsheet bidders are forbidden to alter, converting a template artefact into a responsiveness risk.
JdVVNL's Rs 119.89 crore Bikaner package carries two completion periods inside the same document
8The NIT records eight months for supply, erection, testing and commissioning while Appendix 4 records nine, both against an unchanged nine-month total, with the portal and NIT also differing on the 22 September opening time.
8Performance security is quoted at both 180 days and 30 days beyond the defect-liability period, and guarantee charges turn on which one controls.
Bidder queries force JdVVNL to reopen the BOQ on its Rs 91.47 crore Bikaner DD package before bids close
8Corrigendum-3 supersedes the 14 August NIT, revising the BOQ, specifications, estimate and EMD to Rs 1.83 crore without publishing the superseded figures for comparison.
8The sharper problem is composition: JdVVNL's own estimate puts supply at 79.6% of value while ITB 37 treats supply above 70% of the quoted price as front-loaded and demands additional security.
Phalodi package climbs 0.7% across two corrigenda, with the entire increase landing in supply
8Between Corrigendum-I and Corrigendum-3, supply rose by Rs 38.89 lakh while erection fell by Rs 1.21 lakh, taking TNTW-792 to Rs 97,59,20,302.39 and EMD to Rs 1,95,18,407.
8No item-level change register accompanies the revision, and the portal and SBD still disagree on whether technical bids open at 11:00 am or 5:00 pm.
Jaisalmer's Rs 121.13 crore RDSS package stacks four separate security layers on one contractor
8Beyond the 10% performance security sit abnormal-bid security, supply-unbalancing security and a further 10% guarantee on major equipment running to 36 months after completion.
8With 77.4% of the estimate in supply and no pre-bid meeting scheduled, bidders must also decide whether the EMD instrument reads Rs 2,42,25,139 or Rs 2,42,25,140.
JVVNL withdraws the vendor-registration security waiver as it tenders 25,000 CSP transformers
8Appendix-A replaces EMD and SBG references with Bid Security and removes the relaxation that JVVNL registration alone previously conferred, on a Rs 16,025 lakh, 16 kVA programme.
8The allocation formula caps L1 at 20% and spreads half the quantity across other firms, making past repair performance an eligibility filter rather than a reference note.
Navkar Global Infra takes NTPC Mouda ash transport at 47.6% of base rates against 23 other accepted bidders
8The accepted percentage produces a Rs 142.80 crore contract value, a 52.4% discount to the Rs 300 crore estimate and far past NTPC's own 10% abnormally-low threshold.
8Section C nonetheless caps each shortlisted bidder at Rs 50 crore cumulative and guarantees no purchase order at all, separating the headline award from bankable work.
Churu package falls Rs 7.45 crore in Corrigendum-3 after rising in Corrigendum-1 TNTW-798 moved from Rs 132.60 crore to Rs 133.13 crore and then down to Rs 125.67 crore, with supply cut 6.5% against erection's 2.0%, and no clause-level reconciliation published.
8Bidders have ten calendar days from republication to reprice, while the portal and corrigendum differ by Rs 60 on an EMD that decides envelope-one compliance.
UJVN Limited raises its BESS tariff ceiling 3.8% but leaves 165 MWh outside VGF support
8The 90 MW/225 MWh Chilla project draws VGF on only 60 MWh, while the ceiling capacity charge moves to Rs 3,30,400/MW/month against the Rs 3,96,747 bidders sought.
8After 12 years the entire asset transfers to UJVN Limited without consideration, so residual value has to be recovered inside a capped tariff stream.
UJVNL puts 3x40 MW Sirkari Bhyol Rupsiabagar electro-mechanical works out at Rs 158.53 crore on a one-page notice
8The turnkey EPC package covers design through commissioning, but the notice carries no equipment configuration, battery limits, completion period, LD regime or security structure, while two corrigenda sit on the portal without disclosed content.
8A 47-day window with only 27 days after the pre-bid meeting leaves bidders pricing "other associated different works" without a responsibility matrix.
NTPC Barauni ash package caps compressor power at 1,050 kW with Rs 1.81 lakh payable for every excess kilowatt
8The dry fly ash augmentation contract carries Rs 6.09 lakh daily delay LD, a 12% performance-LD ceiling and a seven-day continuous trial, while amendments deleted the original scheme and layout drawings and pushed construction power onto the bidder.
8Geotechnical data arrived only through Annexure P after bidders had already priced foundations.
MSEDCL asks for 3,599 SCADA-ready RMUs while its own documents disagree on whether the breaker is 200 A or 400 A
8Section III specifies a 400 A vacuum circuit breaker with 400-200/1 CTs; the embedded 11 kV specification repeatedly says 200 A, a divergence that reaches type-test validity, protection coordination and price comparability across a Rs 387.52 crore package.
8The bid notice and portal also differ by 30 minutes on both submission and opening.
WBSETCL Package C3 lets bidders choose between lead and corrugated aluminium sheath on the same 220 KV cable
8Rather than amending the conflicting specification, the utility resolved KEC International's pre-bid query by transferring sheath selection to bidders while fixing the metallic-sheath fault level at 40 KA for one second.
8A revised BOQ landed on 6 May against an 11 May deadline, with residual formula errors left correctable during price evaluation.
NRPC's Rs 25,000 audit tender cannot decide whether it is a single-packet or two-packet bid
8The GeM configuration prescribes two packets and marks arbitration "No", while ATC Clause 1.1.1 mandates a single-packet process and Clause 4.5.2 installs an arbitrator appointed by NRPC's own Member Secretary.
8Force majeure thresholds inside the same document sit at three months and two months.
SECI ties 700 MW of solar to SEZ/EOU status and tells developers that losing it is neither Change in Law nor Force Majeure
8Clause 20.11 makes de-bonding, cancellation or suspension the developer's sole risk across a 25-year PPA whose ALMM exemption depends on that very status, with the Odisha C&I off-taker unnamed.
8SECI can still annul the process after tariff discovery if no buyer emerges.
RVUN seeks 12.5 lakh MT of coal in seven days, bars JVs and demands a single 1-million-MT contract record
8The Rs 1,125 crore Suratgarh tender requires turnover equal to the full estimate, net worth above Rs 375 crore and rail-loading access, while prohibiting consortiums that would normally combine coal, rail and balance-sheet strength.
8The portal flags it as emergency procurement without naming the rule invoked.
DHBVN admits five bidders on Palwal RDSS package 58 days after the scheduled technical opening
8Agarwal Electrical, Agarwal Traders, Century Infrapower, Laser Power & Infra and RP Infrapower cleared the fee, prequalification and technical stage on 3 September against a 7 July opening date.
8The Rs 133.62 crore turnkey scope still depends on feeder-wise BOQs to be surveyed and approved after award.
UJVNL extends Kulhal RMU bidding five times, moving the deadline 68 days without touching the 52-month schedule
8The Rs 110.57 crore turnkey package makes the contractor reconstruct the engineering baseline of a 1975 plant through reverse engineering, 3D scanning, CFD, FEA and residual-life assessment at its own risk.
8Manufacturer-backed qualification attracts 15% performance security instead of 10%, plus another 5% against the authorised scope.
JUSNL cuts consultancy turnover threshold by 22.9% after tendering against the wrong estimate
8The corrigendum reduces minimum average annual turnover from Rs 17.32 crore to Rs 13.35 crore and relevant-business revenue from Rs 4.33 crore to Rs 3.34 crore, correcting a base that mixed an excluding-GST figure with an including-GST estimate.
8The liquid-resource requirement and the conflicting bid-start and opening timestamps remain untouched.
NTPC prepays CSIR-SERC in full for Farakka structural assessment with no bank guarantee, LD or defect liability
8The single-tender consultancy waives EMD, security deposit, PBG, qualifying requirements and evaluation while NTPC additionally funds travel, boarding, local transport and PPE for the visiting scientists.
8Three extension instruments in the archive state neither the original nor the revised dates.
NHPC trims derived-rate overhead from 20% to 18.63% on Rs 267.94 crore Salal bypass tunnel
8Corrigendum 1 rewrote the insurance clause so NHPC funds the works policy while the contractor handles claims, deductibles and reinstatement, with up to 5% withholdable from running-account bills for incomplete claim information.
8Disclosed geology includes solution cavities, squeezing ground, rock burst, hot water and ingress above 6,000 litres per minute.
GSECL asks one consultant to write the Dharoi PSP contracts and then police them for 68 months
8The Rs 2.10 crore EMD, 75-mark technical threshold, 200 MW hydro reference and JV prohibition narrow the field before methodology scoring begins, while a "Stop Gap" clause lets
GSECL exclude declared periods from the completion count.
8The tender never states the project's installed capacity.
RRVPN rejects every pre-bid attempt to widen the field on Rs 125.98 crore Sawai Madhopur substation
8Requests to count bay-extension work, cut the four-substation threshold to two and drop bidder-level transformer experience were all answered with instructions to follow the existing PQR.
8Bids more than 15% below estimate attract additional security equal to half the unbalanced amount.
Only BHEL and LC Infra clear technical opening on UJVNL's Rs 1,024.45 crore Lakhwar EPC
8Both bids were admitted on 5 September after a single seven-day extension, leaving no redundancy if detailed evaluation eliminates either offer.
8Turnover thresholds rise from Rs 308 crore to Rs 820 crore for manufacturer-backed bidders, who also face 15% performance security and a lock on the named turbine and generator OEM.
WAPCOS excludes arbitration from its own Rs 1.50 crore transformation mandate while listing the Arbitration Act as applicable law
8Claims must pass an internal EIC or GM (HR) decision, a Departmental Review Committee and mediation before reaching the Delhi courts, with early filing treated as material breach.
8A corrigendum chain moved the pre-bid meeting from "not held" to an online session, then pointed to both August and September.
MAHAGENCO's Koradi skirt-board tender carries two qualification frameworks and two different carbides
8Turnover is required at both 30% and 100% of estimated cost, while experience is tested through a seven-year 40/50/80 formula in one schedule and a three-year plus 25%-order test in another.
8The subject line and panel description say tungsten carbide; the service-item text says modular silicon carbide.
UPPTCL taxes aggressive bidding on the Rs 102 crore Prayagraj GIS package with a sliding security ladder
8Every percentage point below benchmark adds performance security, rising to 1.00% per point beyond a 10% discount.
8Routine arbitration is deleted too, so undercutting costs cash and disputes run through internal committees.
8With no combined cap and no transformer delivery schedule, the question is how narrow the field gets by September 24.
TGTRANSCO's Sadashivpet–NIMZ line package carries a 22-RTU obligation the price schedule never mentions
8Clause 5.26.1 calls for 22 RTUs while the priced schedules cover just two SAS units for the NIMZ bays.
8A deemed-completeness clause and a one-way lump-sum correction rule push that gap onto the contractor.
8Whether a corrigendum lands before September 24 decides if it stays drafting noise or becomes scope.
MSEDCL's Rs 179 crore 22 kV cable tender pairs firm prices with a 100% extension option
8Prices for 7,34,000 metres stay firm with no commodity variation, yet MSEDCL can order the same quantity again on unchanged terms.
8Type-test validity is stated as both ten years and five, and IS 7098 appears in both its 1985 and 2011 editions.
8Even after the September 1 opening, the 50% cap on an out-of-state L1 means the lowest price will not settle the order book.
MSEDCL's Rs 98 crore 11 kV and 33 kV cable tender loosens drum lengths but keeps every commercial lever
8Clause 9.02 now allows 500 or 250 metre drums, but MSEDCL can still demand 250 metres wherever it chooses.
8The same type-test and IS 7098 conflicts recur, alongside a payment clock that starts only when a full monthly lot arrives.
8The open question is how many bidders sized their 20% minimum offer to real extrusion capacity.
GETCO rewrites the Tharad STATCOM engineering bargain across four extensions without touching the 24-month clock
8The Rs 244.54 crore package moved 80 days to September 17 while shifting to a 50°C rating and a 1.5% loss ceiling.
8In exchange, bidders take on oscillation proof, HVDC interaction studies and five years of post-guarantee interference liability.
8The reverse auction will show whether easier equipment thresholds get priced harder than open-ended network risk.
NHPC trims derived-rate margins and rewrites insurance on the Rs 268 crore Salal sediment bypass tunnel
8The contractor still funds reinstatement and faces 5% bill withholding if claim paperwork lags.
8Two extensions added 88 days to bidding but nothing to the 29-month execution period.
DVC holds the 12-month clock on Chandrapura's Rs 90 crore line diversion after four extensions and a late arrester spec
8Submission moved 42 days to September 14, with the lightning-arrester specification added only 11 days before that.
8Underground cable is half the estimate, yet the named cable contractor cannot be replaced after award.
8The issue is whether bidders load the uniform percentage or walk away from a schedule they called unworkable.
BHEL's Darlipali ash handling tender adds 50% more slurry pumps and a fixed hydraulic baseline while the 4,600 kW cap stays put
8Corrigendum 05 fixed wash-water and sludge duties and raised bottom-ash disposal pumps from six to nine.
8Four extensions took bids to September 10, but the 34-month schedule and US$5,245-per-kW damages never moved.
8The reverse auction will reveal whether cautious bidders lose to those assuming detailed engineering absorbs the gaps.
BHEL's Darlipali ash handling tender dates its experience cut-off nine months before its own NIT
8Annexure 1 reckons experience "as on 06/11/2025" against an NIT dated July 29, 2026.
8Milestone withholding, 5% delay LD and 12% performance LD stack on one counterparty with no interest on withheld sums.
8Whether the three qualification routes widen the field enough for a meaningful auction is the thing to watch.
NPCIL bolts a 15% import loading onto the Kudankulam 5 and 6 common services package after eight extensions
8Corrigendum-XII inserted high-seas-sale transfer, customs procedures and a 15% CIF loading 177 days after the original deadline.
8Corrigendum-XI separately enlarged chiller envelopes to 32 MT, reaching into foundations on a 1,278-day schedule.
8With BHEL, L&T, NCC and Tata Projects in the query record, the question is whether the loading reorders a small field rather than widening it.
BHEL's Korba West coal handling tender puts 75% of the price on land it does not expect until May 2027
8One lump sum splits 25:75 between internal and external CHP, with no compensation if the external land arrives late.
8Reverse auction was deleted a day after the NIT, but cross-default across every LOA leaves no contractual ring-fence.
8After five extensions to September 10, the open issue is how much contingency lands in Package B.
SECL's Gevra weighbridge consultancy asks five CPSUs to price 2,520 days against a portal that shows five years
8GeM displays five years, but the corrigenda fix 2,520 days of exposure backed by an 86-month ePBG.
8The PMC also runs a 20% imprest and pays contractors, with 45% of its Stage III fee tied to that role.
8With five invitees and no floor price, the question is whether the lowest percentage survives seven years.
NTPC's Rs 200 crore Kahalgaon pond ash contract offers five contractors a panel seat and none of them guaranteed work
8GeM says no bid splitting, but the ATC splits the contract five ways, caps each at Rs 40 crore and allows minus 100% quantity.
8Payment follows the lowest of three measurements before 5% reconciliation and 2% safety retention.
8The real test after the August 31 close is how many ranked bidders accept the discovered L1 across all six distance slabs.
AEGCL bundles two 400 kV lines and Agia GIS into one JV-barred package for 3,200 MW evacuation
8AEGCL has invited bids for an indivisible turnkey package covering the Chapar–Rangia and Chapar–Agia Quad Moose lines, a new 400/220 kV Agia substation and Rangia bay extensions, with Rs 24 crore bid security.
8Bidders must show Rs 2,500 crore average turnover, 400 kV GIS credentials and 100 circuit km of 400 kV line experience in a single Assam project, with no joint-venture route and fixed prices over 36 months.
8The unresolved issue is an EMD instruction the portal marks exemptible while the BDS bars digital deposit and disapplies the exemption clauses.
WAPCOS Moran River DPR tender carries three completion clocks and an arbitration clause that cancels itself
8WAPCOS has re-issued a Rs 17.70 lakh GeM bid for architectural design and a technical-sanction-ready DPR covering 20 riverfront components at Khadgada, Dungarpur, closing 16 September.
8The consultant must field a 15-year lead architect and deliver coordinated architectural, structural and MEPF designs while WAPCOS pays back-to-back, retains 2.5% from running bills and holds a 5% ePBG for eight months.
8Completion is stated as two months, 60 days from award and 21 days from agreement, and arbitration is both promised and excluded, leaving schedule and forum unsettled.
AEGCL's Chapar evacuation tender adds ±15% quantity swing and a next-lowest-bidder step-out to firm pricing
8The 36-month turnkey package treats quantities as provisional within ±15% of contract price while keeping the price firm and deeming unlisted completion items included. GIS carries a second security of 20% of ex-works cost for five years beyond the defect period, alongside an unreduced 10% performance security, 60-day payment terms and no interest on delay.
8AEGCL's right to transfer unfinished work to the next-lowest tenderer raises the harder question of how an integrated system can be split mid-execution without responsibility gaps.
BHEL's Tikrikhurd GIS tie-up layers 10%, 2% and 10% guarantees on a zero-EMD tender
8The OEM must supply 82 bays and 5,200 m of 400 kV GIB within 21 months, then supervise commissioning within nine, under a 60-month defect period extendable to 84 plus a five-year latent-defect tail.
8Beyond a 10% BHEL security and 2% DTL guarantee, Route-2 and Route-3 manufacturers post another 10% from collaborators, while items marked "NA" but later needed must be supplied free.
8The type-test and PQR reference date of 18 August predates BHEL's own 2 September invitation, compounding the Gopalpur language and an undisclosed downstream price-sharing formula.
NTPC's Rs 300-crore Gadarwara ash contract empanels six agencies but guarantees none a purchase order
8NTPC is seeking slab-wise rates for excavating, loading and hauling pond ash up to 300 km to NHAI and PMGSY sites during FY 2026-27, with a Rs 50 lakh EMD and AST-01 enlistment as the entry gate.
8Up to six L1-matching contractors are each capped at Rs 50 crore, must fit AIS 140 GPS with API access and submit geo-tagged trip evidence, while aggregate value may fall by 100%.
8With one uniform premium across six distance slabs plus excavation and loading, the real exposure is financing a mobilised fleet against volumes NTPC is free to withhold.
NSPCL closes 123-day extension chain on Durgapur pulveriser R&M with spares restored from three to 24
8After 12 deadline revisions, NSPCL has declared 8 September final for bids to replace eight coal pulverisers across two 60 MW units at Durgapur PP-II, with a Rs 1 crore EMD.
8Amendment 4 reversed Amendment 2 by restoring 24 pump assemblies in mandatory spares, while Amendment 3 added dual instruments for CLCS and protection duties.
8Bidders who priced on the interim three-pump requirement face an eightfold quantity correction inside a brownfield package whose completion period, LD and PBG remain unstated.
SECI fixes turbine coordinates yet leaves the wind contractor liable for a SCADA platform another package owns
8SECI is procuring a 45.6 MW ISTS-connected wind project at Ramagiri plus ten years of O&M, evaluated on EPC price plus O&M NPV at 8.30% before an e-reverse auction.
8The contractor must commission within 14 months, hold 96–98% availability, keep 5% security through the tenth O&M year and integrate its LCS with a CMCS, PPC and grid-compliance study delivered by the solar-plus-BESS contractor.
8LD switches from the uncommissioned portion to 5% of total contract price after ten weeks, while the O&M price workbook still describes the asset as a solar-plus-BESS project.
UJVN's Sirkari Bhyol E&M tender reaches 20th extension after estimate climbs 53.3% to Rs 243.05 crore
8The 3×40 MW Francis-turbine package at Munsyari now closes 10 September, 255 days after its original December 2025 deadline, with EMD raised twice to Rs 5.7385 crore.
8Seven addenda widened experience to 15 years, cut the generator threshold to 35 MVA, admitted surety bonds and switched guide bearings from water to oil lubrication.
8Additional security on borrowed credentials rose from 3% to 5% and validity stays at 270 days, so bidders must price against an unconsolidated trail of 23 corrigenda.
NREDCAP's 15 MW Vijayawada WtE concession bids on lowest grant with a Rs 19.99-crore security stack behind it
8The 22-year DBFOT project, costed at Rs 324.70 crore, seeks developers with 800 TPD single-facility or two 500 TPD waste-to-electricity references and Rs 81.17 crore net worth.
8The selected bidder posts Rs 16.24 crore to the municipal authority and Rs 25 lakh/MW to APDISCOM, with the O&M-qualified consortium member locked in for the full term.
8Portal text dispenses with originals at evaluation while Clause 27.2(c) makes their receipt by bid date a responsiveness condition, leaving rejection risk unresolved.
SECI's bulk-consumer EOI shifts pre-bid meeting three times without touching the 15 September deadline
8SECI is inviting AAA-to-BBB+ rated consumers with 50 MW-plus demand to disclose load, credit and land data for solar, wind, hybrid, FDRE, RTC, BESS and PSP procurement under captive, group-captive, JV and PMC structures.
8SECI proposes to handle land, connectivity, EPC selection, financing and O&M for up to 25 years, while respondents bear all participation cost under a non-binding framework.
8The final meeting notice dropped the public time and link, and tariff, curtailment, change-in-law and payment-security terms remain wholly undefined.
TPTL inserts 27-page CFC-HTLS spec four days after publishing Rs 18.38-crore 132 kV LILO tender
8The corrigendum fixes an 800 A carbon-fibre-core conductor, 7.0 m sag at 320 m span and loss-capitalised evaluation at Rs 3,30,220 per kW for 43.8 km of reconductoring beside a live circuit.
8The contractor absorbs tower-load checks, type-test costs, damage restoration and railway crossings without assured shutdowns, with bids now closing 14 September after a 12-day extension.
8Section II's "ten percent (3%)" performance-guarantee wording and the 800 A/437 A sag mismatch remain uncorrected.
DVC's 1x800 MW Durgapur BOP package moves 38 days across four corrigenda with two-unit completion text intact
8DVC's international EPC tender for FGD, chimney, coal and ash handling, a 7 km raw-water system, 400/220 kV GIS, DCS and ZLD now closes 24 September, with bid security of Rs 25.69 crore or USD 2.72 million.
8Bidders need Rs 1,250 crore average turnover and face 10% performance security plus a 2% consortium integration guarantee, with LD at USD 106,610 per day capped at 5%.
8BDS Item 9.0 still reads "44 & 48 months for Unit 1 & Unit 2" against a single-unit SCC, leaving the LD baseline dependent on interpretation.
Four bidders clear technical stage in DHBVN's Rs 118.78-crore Hisar SCADA DMS infrastructure package
8Agarwal Traders, Century Infrapower, Gawar Construction and RP Infrapower were admitted after two extensions moved closing to 3 August for 11 kV augmentation, feeder bifurcation, RMUs and VCBs.
8Corrigendum-I shifted location approvals and final inspection from the Smart Grid Project wing to the nodal officer and operation wing, and assigned FRTU and DCP supply to the separate SCADA agency.
8Additional security climbs to 24% for bids 24% below estimate, and delay attribution where RMUs wait on another agency's automation kit is unallocated.
Five bidders admitted to DHBVNL's Rs 157.83-crore 33 kV augmentation tender carrying two EMD figures
8Agarwal Traders, Century Infrapower, Gawar Construction, Laser Power & Infra and RP Infrapower cleared technical evaluation on 7 August for turnkey augmentation of 72 operating substations within 12 months.
8DHBVNL may interchange substations without time relief, requires approval of all non-labour subcontracts and has raised TPQMA inspection of augmented substations from 5% to 100%.
8The NIT and portal set EMD at Rs 3.16 crore while the SBD summary says Rs 1.55 crore, and no hierarchy resolves the difference.
PwC wins MPPTCL S/4HANA migration 35.8% below Deloitte as comparative sheet multiplies contract value
8PricewaterhouseCoopers is L1 at Rs 297.4608 crore against Deloitte's Rs 404.0366 crore for ECC-to-S/4HANA conversion under RISE with SAP, five years of licences, legacy support and hypercare.
8The RFP directs evaluation on GST-inclusive Item H—Rs 104.47 crore versus Rs 141.89 crore—but the published total sums components, subtotal, GST and total together.
8L1 priced migration at Rs 14.39 crore against Rs 36.65 crore and ECC support at Rs 6 lakh against Rs 6.54 crore, while Corrigendum-5 deleted VAPT from scope.
WBSETCL adds 120 days to 43-transformer delivery programme and hardens split into 26:17
8The 80 MVA, 132/33 kV package with NIFPS and spare RIP bushings now closes 10 September, with the first eight units due at 300 days instead of 210 and completion at 600 days.
8Bidders face H1 elimination before reverse auction, 10% additional security if L1 falls at or below 80% of estimate, a 60-month defect period and 5% security retained after supply.
8The second supplier receives 17 units only at the L1 price, leaving open whether price-matching reproduces the delivery risk the extension sought to cure.
Addendum-VI reverses Zone VI error and switches Sirkari Bhyol turbine bearings to oil lubrication
8UJVNL has restored the project's IIT Roorkee-derived Zone V seismic basis after an intervening addendum wrongly cited Zone VI, and in the same document replaced water-lubricated guide bearings with babbitted oil-lubricated units with water cooling.
8The bearing change reaches cooling circuits, oil handling, monitoring and maintenance philosophy, so the harder question is how much lifetime auxiliary-system cost bidders must now carry into a 48-month fixed package.
NTPC issues second corrigendum on Simhadri 0.5 MMT coal without resolving 25% versus 10% quantity conflict
8Corrigendum C4 of 11 September supersedes C1 and the original buyer-added terms for the Rs 2 crore EMD Simhadri lot, retaining the right to move ordered quantity by up to 25% at award and again during the contract.
8Technical Specification Clause 3 still carries a plus or minus 10% station band, and with the GeM summary recording no ePBG against ITB Clause 22.0's mandatory 5% PBG, bidders must price a maximum volume and security exposure the documents do not settle.
UPPTCL deletes 'provided by UPPTCL' from transformer rows, forcing Noida GIS bidders to price erection
8Corrigendum-1 has replaced the BOQ for the Rs 112.05 crore Sector-155 substation, removing the entry that let bidders leave installation of the 160 MVA and 63 MVA owner-supplied transformers unpriced, and redefining 33 kV termination kits by interface rather than indoor or outdoor location.
8Submission moved a week to 17 September, but the real exposure is that the contractor now prices commissioning around equipment whose manufacture and delivery stay with UPPTCL, with no project-specific relief formula for late handover.
UPRVUNL converts 640 MW Rihand-Obra pumped storage from BOO to zero-consideration handover after 40 years
8The corrigendum replaces extendable BOO ownership with compulsory transfer to UPRVUNL 40 years from SCOD, in good running condition, free of liens and without transfer price or compensation, while the PBG moves to 5% of the Rs 3,953 crore estimate at Rs 197.65 crore and stays live until 12 months after actual commissioning.
8With nine extensions pushing bids to 12 October and forfeiture possible where the developer's own DPR finds the project infeasible, the test is how banks price terminal transfer beside pre-construction feasibility risk.
OPTCL opens Rs 301 crore HTLS reconductoring with two different estimates in its own records
8The Meramundali–Mendhasal package requires dismantling twin AAAC Moose and stringing twin HTLS on the live 400 kV double-circuit line, plus equipment and bus upgrades at both grid-substation ends, with bids closing 9 October.
8The signed notice states Rs 301,22,38,089 while the portal header reads Rs 3,01,26,70,182, and with outage allocation, tower adequacy and scrap responsibility all unspecified, bidders face a package whose basic commercial reference point is unreconciled.
POWERGRID ties 765kV GIS package SS 185T to a TBCB outcome bidders cannot influence
8The Orai, Patran and Agra extension package requires an exclusive MOU with the lowest evaluated qualified bidder, who receives a contract only if POWERGRID wins the upstream tariff-based bid, while exclusivity bars that bidder and connected entities from supporting rival TSPs.
8Four qualification routes admit manufacturers, collaborator and parent-backed Indian plants and EPC bidders, but with a further 10% ex-works guarantee on Routes 2 and 3 and no quantified compensation if POWERGRID loses, broad access on paper may still leave OEM gatekeeping intact.
NTPC builds six-contractor panel for Rs 300 crore Barh pond ash haulage with no purchase-order guarantee
8The 2026-27 rate contract splits work among up to six AST-01 vendors matching a single L1 price, one part reserved for an SC/ST MSE bidder, with roughly Rs 20 crore placed sequentially and Rs 50 crore as the cumulative ceiling per contractor.
8Payment follows compacted ash certified by the receiving road authority rather than trips or weighbridge tonnage, and with variation from minus 100% to plus 20%, panel entry buys eligibility rather than revenue.
GPCL risk-management RFP carries three submission deadlines and a hard copy that overrides the portal
8The ERM consultancy for GPCL's renewable, BESS, green hydrogen, mining and transmission portfolio records online closing at 18:00 on 21 September on the portal, 3 October in Chapter 1 and physical receipt on 6 October, with clause 5.3.2 giving the posted copy precedence.
8The QCBS 70:30 structure is designed to protect technical quality, but a compliant bidder could still be rejected for following one official instruction over another unless GPCL clarifies which date and channel govern.
MPPTCL bars partial bids on Rs 316 crore Sabalgarh package spanning substation, 34 km line and LILO
8TR-28/2026 bundles a new 400 kV substation, a Quad Moose double-circuit link to Morena Pooling and about 21 km of 220 kV LILO into one indivisible turnkey award, with 30-month and 24-month completion tracks and no rainy-season relief, while three 500 MVA and two 200 MVA transformers and two 125 MVAR reactors stay outside contractor supply.
8Price variation reaches only selected equipment and civil work, so reverse-auction pressure will meet a large block of fixed-price and deemed-inclusion exposure.
NTPC Lara mine-filling tender contradicts itself on diesel escalation and soil-cover thickness
8The Rs 255.06 crore package moving 20 lakh MT of ash into the Bishrampur and Dugga pits says no extra payment for fuel-rate changes at condition 2(h), then indexes 25% of contract price to diesel at Clause 14, while Scope Clause 1 fixes a 500 mm soil cap against Payment Clause 9(i)'s 300-500 mm band.
8With quantity variable from minus 100% to plus 20% across a six-way split and no order-of-precedence statement, both conflicts sit directly on the lump-sum price.
APCPL admits Talabira coal in one clause and excludes OCPL in another for 5 LMT Jhajjar buy
8The invitation for bids for the Rs 5 crore EMD package bars coal from CIL, SCCL, OCPL and NTPC group mines, while Technical Specification Clause 2 expressly permits OCPL and Talabira sources including the NLCIL captive mine.
8A second gap sits between Annexure-B1's 4,300 Kcal/kg ceiling and Clause 11's payment cap at 4,000 Kcal/kg, leaving a bidder unable to know whether its declared source qualifies or its better coal can be monetised.
MSEDCL grants nine days on Rs 97.87 crore cable tender but holds firm price against five bidders
8Shriram Cables, Torrent Electricals, Dynamic, KEI and Tirupati each sought price variation on the 33 kV and 11 kV 300 sq.mm HT XLPE package, and MSEDCL answered every request with "as per tender documents," also refusing KEI's three-month first-lot request and Tirupati's insurance surety bond proposal.
8Bidding moved from 1 September to 10 September, leaving a nine-month firm-price delivery, a 20% two-month mobilisation obligation and 1% weekly LD untouched.
OPTCL forces single award across Palaspanga and Barbil while its notice repeats the EMD as the estimate
8The Rs 315.27 crore package makes Lot-I and Lot-II one indivisible contract covering GIS at both stations, 1.2 Rkm of underground cable and roughly 69.2 Rkm of 220 kV overhead line including Twin Moose on 400 kV towers, all in 24 months.
8The opening notice states the estimate as Rs 3.15 crore, exactly the EMD figure, and Table-A carries 10 August against the portal's 11 August, leaving bidders to rely on portal precedence for basic commercial approvals.
HPPCL seeks green hydrogen offtakers for 1 MW Dabhota plant without naming volume, purity or delivery point
8The EOI sets a Rs 1 EMD, zero form fee and Rs 2,360 processing charge, with closing on 13 August and cost opening one hour later, but does not state saleable output, pressure, metering ownership, custody transfer or contract tenure.
8Classified simultaneously as procurement of services and miscellaneous works with a scheduled cost opening, the notification leaves respondents unsure whether they are quoting a purchase price, a service charge or a bundled logistics proposition.
NTPC leaves three quantity formulations live across its 2.5 MMT five-station coal package
8The Telangana lot under CS-0011-011(10)-9 now carries a plus or minus 20% variation in the revised detailed document, plus or minus 10% in the separate technical specification and a 25% GeM option clause at both order placement and during contract.
8Sequential station opening means a bidder's later price bids stay unopened once it reaches its declared Annexure-TC-10 limit, making award appetite a live competitive variable before any price is compared.
NTPC cuts Tanda coal ceiling to 3,700 Kcal/kg while lifting initial payment to 80%
8Revised Annexure-B1 pulls the GCV envelope down from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal caps of 12% and 14%, and the GCV challenge window contracts from ten working days to seven calendar days with a ±71.7 Kcal/kg admissibility threshold.
8The move from 50% to 80% initial payment is the clearest contractor gain in the package, but it arrives alongside ±20% quantity variation, station diversion rights and a source pool narrowed by the tighter specification.
Nabinagar sits last in NTPC's price-opening order, exposing it to a thinner field
8Corrigendum-1 leaves the 16 September dates unchanged for the 0.5 MMT lot and fixes the opening sequence as Telangana, Simhadri, Mouda, Tanda and Nabinagar, with bid security shown at Rs 10 crore for five stations against a visible overwritten Rs 8 crore in ITB Clause 7.1.
8Because bidders reaching their declared award ceiling drop out before later envelopes are opened, the last station in the queue may face the weakest price competition regardless of its own economics.
NHPC inserts a missing crane chapter and cuts turbine efficiency threshold to 94% at Dulhasti Stage-II
8Corrigendum No. 1 added the absent Chapter 18 covering two 190/30-tonne powerhouse cranes and three others, Corrigendum No. 5 rewrote the cooling-water and HVAC chapters and lowered the non-responsiveness threshold from 94.5% to 94%, and price-adjustment indices moved from 2011-12 to 2022-23.
8Four extensions have taken submission from 24 July to 28 September on the Rs 496.90 crore package, yet unit commissioning stays fixed at months 43 and 44 from the civil zero date.
UJVNL lets two OEMs cover turbine and generator at Tiuni Plasu after 18 extensions
8Addendum-II moved qualification from turbine and generator to turbine "and/or" generator and deleted the contract-value experience thresholds, and Addendum-VI then allowed as many as two manufacturers, with force-majeure substitution limited to BHEL, Voith Hydro, Andritz Hydro and General Electric.
8Addendum-III deleted air-gap, partial-discharge and vibration monitoring and cut excitation redundancy from n+n to n+1, so the widened front door arrives with a thinner reliability margin and a Rs 260 crore turnover test for manufacturer-backed bidders.
JERC bars consultants holding two of three earlier awards from Chandigarh STU-SLDC tariff work
8The Rs 18 lakh QCBS assignment covering business plans, MYT petitions, mid-term review and true-ups to FY 2029-30 excludes firms already awarded two of three specified JERC bids, while demanding ten years of experience, 20 assignments worth Rs 1 crore and two staff stationed at the Commission.
8Corrigendum C3 warns that a participation fee can render the bid null and void, even though the underlying RFP still requires a Rs 10,000 processing fee and advance hard copies.
SECI moves Ramagiri wind auction to cost per certified MU and drops turbine floor to 2.7 MW
8Amendment-01 rewrites ITB Clause 32.4.1 so bids rank on EBV divided by NIWE-certified ten-year P90 generation, with the denominator locked before the reverse auction and only price free to move, while the power-curve pass mark falls from 98% to 95% and the 96-hour test threshold from 98% to 96%.
8Repeated STPT failure no longer triggers WTG rejection and refund with 13% interest but a generation-linked LD at Rs 4.5 per kWh, leaving yield certification quality as commercially decisive as the EPC quote.
NPCL wants 300 MW RTC with 90% availability in six peak hours it picks day-ahead
8The 25-year BOO procurement requires a declared annual CUF of at least 75% held within plus or minus 10%, 50% of contracted capacity in every off-peak 15-minute block and 90% across six peak hours selected by NPCL on a day-ahead basis, with shortfall damages at 1.5 times tariff.
8Configuration and delivery points may change until financial closure but bring no SCSD relief, so the 24-month schedule and daily PBG encashment will likely surface as a firmness premium in the discovered tariff.
NTPC narrows Mouda coal window to 3,700 Kcal/kg as second corrigendum lands five days before bids close
8Corrigendum C4 of 11 September supersedes C1 for the 5 lakh MT package, while the revised document cuts maximum GCV from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal 12% and 14% caps, and moves payment from 50:40:10 to 80:10:10 with sampling charges down to Rs 2.97 per MT.
8GeM records no ePBG and no arbitration against Clause 22.0's 5% security and a Delhi-seated GCC arbitration, leaving document precedence to carry more commercial weight than the headline tonnage.
Odisha Coal and Power Limited caps Tangardihi North's exploration phase at Rs 25 crore and ranks bidders on 397 million tonnes
8A Phase I quotation above the ceiling is reduced to Rs 25 crore rather than improving the evaluated position, while the Base Mining Charge is multiplied across a comparison quantity that detailed drilling has yet to confirm.
8Around 14,000 metres of exploration sits inside the same contract whose 25-year operating commitment depends on what that drilling finds.
WAPCOS gives three masked bidders ten days to respond to a five-year strategy mandate classified as an emergency
8The Rs 1.50 crore QCBS assignment weights technique at 80%, with 60 of 100 technical marks resting on named expert CVs and a presentation.
8Arbitration and consensual ADR are excluded entirely, leaving employer-controlled internal review, mediation and Delhi civil courts as the dispute route.
Gujarat Energy Transmission Corporation Limited's Navsari cable tender lists 193,186 metres of 66 kV cable against a 24,218-metre route survey
8The Rs 98.48 crore item-rate package also carries six foundation categories each showing eight tower foundations while the total tower-erection quantity is also eight, leaving the BOQ open to interpretation before pricing.
8Amendment no. 1 moves delay damages from the delayed portion to 0.5% of the entire contract price per week, capped at 10%, or roughly Rs 9.85 crore plus GST.
Maharashtra State Electricity Transmission Company Limited puts a Rs 73.19 lakh breaker overhaul across 12 substations without a breaker count
8The notice covers spares supply and complete mechanism overhauling of CGL-make 132 kV breakers at sites spanning both 132 kV and 220 kV yards.
8Mechanism types, spare schedules, outage duration, testing protocol, warranty and completion period are not specified in the document, leaving the estimate impossible to test against actual scope.
NTPC Renewable's 600 MW Anantapur wind tender gives bidders a week more to price but no way to ask why
8Corrigendum No. 1 pushed submission to 22 September 2026 while leaving the 1 September query deadline untouched, so late-discovered ambiguity has nowhere formal to go.
8With Rs 50 crore bid security, ten-year comprehensive O&M and roads, pooling and evacuation all outside the WTG package, the unresolved issue is who carries commissioning delay at the boundary.
JdVVNL rewrites the BOQ a third time and swaps Bikaner territories between two RDSS packages
8Corrigendum 3 moved Dungargarh and Nokha into TNTW-796 while DD-I, DD-II and Khajuwala travelled the other way, settling the value at Rs 119.89 crore — a net movement of about 0.1%.
8That small headline change can conceal much larger line-item additions and deletions, which is precisely what bidders repeatedly queried before the revision.
AEGCL's Khumtai 400kV GIS tender carries a Rs 50 lakh EMD contradiction and a 12-month schedule gap
8The invitation and ITB 2.37.1 set two years for completion while SCC 8.2 requires 36 months, and the EMD reads Rs 5.5 crore in numerals against "Rupees Five Crore only" in words.
8Turnover and financial-resource thresholds carry the same numeral-versus-wording conflict, making eligibility itself uncertain before the 12 October closing.
GETCO's Viksit Gujarat @2047 adviser tender records two turnover thresholds twenty times apart
8The GeM page states Rs 48 crore while the RFP and buyer-added conditions demand Rs 1,000 crore, and submission and opening dates differ by a day between portal and document.
8With GST treatment also contradicted between two clauses, the tender risks producing technically incomparable bids priced on different assumptions.
GETCO's Rs 210.62 crore Bharuch cable package lets each approved OEM back only one bid
8Amendment-I restructured qualification into OEM, nominated-OEM and two-member JV routes, then barred any firm from appearing in different roles across competing bids.
8The contest may therefore be settled by early OEM alignment rather than by how many erection contractors can qualify.
KPTCL's Rs 131.92 crore Byadagi package reaches the market tagged as a computer lab
8The portal lists bid validity as 90 days against the signed document's 180, describes the scope as "Setting up of Computer Lab", and keeps the clarification window open 30 minutes after bids close.
8A Clause 3.2(e) heading referring to a 100 MVA transformer against a 160 MVA requirement compounds the risk of divergent qualification readings.
RRVUN cuts the coal experience bar by 6.25% and then quietly extends group credentials to technical qualification
8Amendment-I lowered the single-contract threshold from 1 million MT to 9,37,500 MT and admitted IPP supplies; Corrigendum-I then widened 100%-owned parent or subsidiary reliance from financial to both technical and financial PQR.
8JV and consortium participation stays barred, so the widening favours tightly held corporate groups rather than assembled bidding alliances.
WBSETCL's Sadarghat composite package republishes its evaluation clause with a broken cross-reference
8Amended ITB 28.2 now reads "DP = Differential price calculated according to0", severing the link to the calculation method in ITB 28.4, while the reverse-auction cross-reference disappears entirely.
8Reverse-auction clause 9 separately dispenses with additional security where L1 is "less than 20% of the estimated cost" — a literal reading that relaxes protection at the lowest prices.
NHPC raises generator efficiency loading 20.6% on the Rs 641.11 crore Uri-I Stage-II package
8The turbine equalisation rate moved from Rs 8.32 lakh to Rs 8.74 lakh per 0.1 percentage point, while the generator rate jumped from Rs 21.64 lakh to Rs 26.10 lakh.
8Cheaper machines with weaker guarantees can now lose their price advantage at evaluation, even before PLCC relocation and revised cooling-water scope are priced.
WBSETCL's 68 km Salboni 400 kV line tender resolves a 60 mm creepage conflict but keeps ROW with the contractor
8The pre-bid response directed bidders to the technical specification's 430 mm over the BOQ's 370 mm and issued a revised BOQ, while fixing conductor diameter at 28.62 mm and sag at 15.93 m.
8Tower-footing compensation, trees, crops and access remain contractor-priced with no escalation for court-driven delay, and the 24-month clock survives two extensions.
RRECL's 201 MW solar tender slips 63 days and then adds a letter of credit
8Four corrigenda moved submission from 14 July to 15 September 2026 while the nine-month commissioning obligation and 25-year term stayed fixed.
8The pre-bid addendum inserted a revolving monthly LC and replaced the client's first charge over liquidated assets with priority application of proceeds — a lender accommodation whose value depends on the still-ambiguous "Cover-1 & Cover-2" opening language.
HPSEBL extends its Rs 3.72 crore Kinnaur-Spiti PMC tender for the fifth time without explaining why
8Corrigenda I to V added 64 calendar days to both submission and technical opening while leaving scope, staffing, securities and the 246 man-month deployment untouched.
8The unresolved question is award mechanics: a 70:30 QCBS formula and an English e-reverse auction sit in the same document with no stated hierarchy.
GETCO shifts LD on the Rs 224.80 crore Dholera-II GIS package from the delayed portion to the whole contract
8SCC clause 41 now calculates 0.5% per week on the full contract price capped at 10%, recoverable across GUVNL group contracts, while requests to extend 30 months to 34 and to substitute PEB for RCC were refused.
8A local civil or commissioning slip can now generate package-wide exposure on a site carrying saline conditions, seismic zone 5 and cast-in-situ piling.
MePDCL splits Khasi Hills into six lots and hands four of them to one contractor
8The Rs 120.42 crore award concentrates Rs 82.12 crore, or 68.2% of L1 value, with a single firm across Lots 1, 3, 5 and 6.
8Lot 3 reached financial opening with one responsive bidder out of seven, leaving no L2 comparator to test whether that price was competitive at all.
NHPC rewrites force majeure and idling-cost recovery across both its hydro E&M packages
8The revised GCC Clause 37 adds terrorism, qualifying strikes and pandemic spread while removing the magnitude-7 earthquake threshold and express treatment of bandhs, lightning and unprecedented floods.
8Annex-A now caps compensable idling through a formula using 5% of composite contract price, with a 2% sub-cap on miscellaneous establishment expenditure and extended-warranty recovery at 2.25% per annum.
RVUN's Rs 1,125 crore coal tender is tagged emergency procurement without naming which rule applies
8The portal cites Rule 40(1), 43(6) or 43(7) but does not identify the provision invoked or the factual justification, and the original window ran just seven days from publication to submission.
8Coal grade, sampling agency, delivery duration, LD framework and PBG terms are absent from the published notice, leaving the commercial risk difficult to quantify before bidding.
WBSETCL's H1-elimination auction meets a 10% security stack that runs five years past commissioning
8The Sadarghat package removes the highest offer only where four valid price bids exist, so two or three qualified bidders all proceed to the auction intact.
8The winner must then carry separate 10% guarantees on GIS equipment for three years and transformers for five from the Taking-Over Certificate, with formal joint ventures barred.
APEPDCL grants 24 extra days on its Rs 143.32 crore SCADA package without touching a single execution obligation
8Three corrigenda moved submission from 1 September to 25 September 2026, but the 18-month implementation period, five-year FMS and 10% performance security stayed exactly where they were.
8What the extensions really concede is preparation time for a bidder pool that must satisfy two separate qualification streams and assemble OEM authorisations before it can quote.
RVPN's Rs 83.38 crore Shiv Enclave GIS package makes unlisted work the contractor's problem
8A 132/33 kV, 2x80 MVA GIS substation with a 4 km LILO cable arrangement carries a 545-day execution period and a 10% performance security, extended eight days by Corrigendum No. 01.
8The clause that matters is GCC 3.2, which absorbs reasonably inferable items into the contractor's scope without automatic additional payment.
NTPC puts 2,184 man-months of construction safety at Telangana Stage-II behind a 52-month firm-rate contract
8The consultant must field 47 personnel, run a 24/7 IP-camera control room and approve other agencies' JSA/HIRA documents across a 3 x 800 MW build.
8The commercial risk is not the Rs 5,000-per-day non-deployment penalty but firm rates through a unilateral 12-month extension, 5% retention and no interest on deferred payment.
TNPDCL asks for 5,000 distribution transformers while the protected BOQ shows a quantity of one
8The M-256 tender covers 5,000 units of 100 kVA, EEL-2 aluminium-wound transformers with a Rs 1,00,20,500 EMD, a ±25% quantity variation and a 60-month guarantee.
8The BOQ's "1.0 No." line and its residual civil-work text sit inside a spreadsheet bidders are forbidden to alter, converting a template artefact into a responsiveness risk.
JdVVNL's Rs 119.89 crore Bikaner package carries two completion periods inside the same document
8The NIT records eight months for supply, erection, testing and commissioning while Appendix 4 records nine, both against an unchanged nine-month total, with the portal and NIT also differing on the 22 September opening time.
8Performance security is quoted at both 180 days and 30 days beyond the defect-liability period, and guarantee charges turn on which one controls.
Bidder queries force JdVVNL to reopen the BOQ on its Rs 91.47 crore Bikaner DD package before bids close
8Corrigendum-3 supersedes the 14 August NIT, revising the BOQ, specifications, estimate and EMD to Rs 1.83 crore without publishing the superseded figures for comparison.
8The sharper problem is composition: JdVVNL's own estimate puts supply at 79.6% of value while ITB 37 treats supply above 70% of the quoted price as front-loaded and demands additional security.
Phalodi package climbs 0.7% across two corrigenda, with the entire increase landing in supply
8Between Corrigendum-I and Corrigendum-3, supply rose by Rs 38.89 lakh while erection fell by Rs 1.21 lakh, taking TNTW-792 to Rs 97,59,20,302.39 and EMD to Rs 1,95,18,407.
8No item-level change register accompanies the revision, and the portal and SBD still disagree on whether technical bids open at 11:00 am or 5:00 pm.
Jaisalmer's Rs 121.13 crore RDSS package stacks four separate security layers on one contractor
8Beyond the 10% performance security sit abnormal-bid security, supply-unbalancing security and a further 10% guarantee on major equipment running to 36 months after completion.
8With 77.4% of the estimate in supply and no pre-bid meeting scheduled, bidders must also decide whether the EMD instrument reads Rs 2,42,25,139 or Rs 2,42,25,140.
JVVNL withdraws the vendor-registration security waiver as it tenders 25,000 CSP transformers
8Appendix-A replaces EMD and SBG references with Bid Security and removes the relaxation that JVVNL registration alone previously conferred, on a Rs 16,025 lakh, 16 kVA programme.
8The allocation formula caps L1 at 20% and spreads half the quantity across other firms, making past repair performance an eligibility filter rather than a reference note.
Navkar Global Infra takes NTPC Mouda ash transport at 47.6% of base rates against 23 other accepted bidders
8The accepted percentage produces a Rs 142.80 crore contract value, a 52.4% discount to the Rs 300 crore estimate and far past NTPC's own 10% abnormally-low threshold.
8Section C nonetheless caps each shortlisted bidder at Rs 50 crore cumulative and guarantees no purchase order at all, separating the headline award from bankable work.
Churu package falls Rs 7.45 crore in Corrigendum-3 after rising in Corrigendum-1 TNTW-798 moved from Rs 132.60 crore to Rs 133.13 crore and then down to Rs 125.67 crore, with supply cut 6.5% against erection's 2.0%, and no clause-level reconciliation published.
8Bidders have ten calendar days from republication to reprice, while the portal and corrigendum differ by Rs 60 on an EMD that decides envelope-one compliance.
UJVN Limited raises its BESS tariff ceiling 3.8% but leaves 165 MWh outside VGF support
8The 90 MW/225 MWh Chilla project draws VGF on only 60 MWh, while the ceiling capacity charge moves to Rs 3,30,400/MW/month against the Rs 3,96,747 bidders sought.
8After 12 years the entire asset transfers to UJVN Limited without consideration, so residual value has to be recovered inside a capped tariff stream.
UJVNL puts 3x40 MW Sirkari Bhyol Rupsiabagar electro-mechanical works out at Rs 158.53 crore on a one-page notice
8The turnkey EPC package covers design through commissioning, but the notice carries no equipment configuration, battery limits, completion period, LD regime or security structure, while two corrigenda sit on the portal without disclosed content.
8A 47-day window with only 27 days after the pre-bid meeting leaves bidders pricing "other associated different works" without a responsibility matrix.
NTPC Barauni ash package caps compressor power at 1,050 kW with Rs 1.81 lakh payable for every excess kilowatt
8The dry fly ash augmentation contract carries Rs 6.09 lakh daily delay LD, a 12% performance-LD ceiling and a seven-day continuous trial, while amendments deleted the original scheme and layout drawings and pushed construction power onto the bidder.
8Geotechnical data arrived only through Annexure P after bidders had already priced foundations.
MSEDCL asks for 3,599 SCADA-ready RMUs while its own documents disagree on whether the breaker is 200 A or 400 A
8Section III specifies a 400 A vacuum circuit breaker with 400-200/1 CTs; the embedded 11 kV specification repeatedly says 200 A, a divergence that reaches type-test validity, protection coordination and price comparability across a Rs 387.52 crore package.
8The bid notice and portal also differ by 30 minutes on both submission and opening.
WBSETCL Package C3 lets bidders choose between lead and corrugated aluminium sheath on the same 220 KV cable
8Rather than amending the conflicting specification, the utility resolved KEC International's pre-bid query by transferring sheath selection to bidders while fixing the metallic-sheath fault level at 40 KA for one second.
8A revised BOQ landed on 6 May against an 11 May deadline, with residual formula errors left correctable during price evaluation.
NRPC's Rs 25,000 audit tender cannot decide whether it is a single-packet or two-packet bid
8The GeM configuration prescribes two packets and marks arbitration "No", while ATC Clause 1.1.1 mandates a single-packet process and Clause 4.5.2 installs an arbitrator appointed by NRPC's own Member Secretary.
8Force majeure thresholds inside the same document sit at three months and two months.
SECI ties 700 MW of solar to SEZ/EOU status and tells developers that losing it is neither Change in Law nor Force Majeure
8Clause 20.11 makes de-bonding, cancellation or suspension the developer's sole risk across a 25-year PPA whose ALMM exemption depends on that very status, with the Odisha C&I off-taker unnamed.
8SECI can still annul the process after tariff discovery if no buyer emerges.
RVUN seeks 12.5 lakh MT of coal in seven days, bars JVs and demands a single 1-million-MT contract record
8The Rs 1,125 crore Suratgarh tender requires turnover equal to the full estimate, net worth above Rs 375 crore and rail-loading access, while prohibiting consortiums that would normally combine coal, rail and balance-sheet strength.
8The portal flags it as emergency procurement without naming the rule invoked.
DHBVN admits five bidders on Palwal RDSS package 58 days after the scheduled technical opening
8Agarwal Electrical, Agarwal Traders, Century Infrapower, Laser Power & Infra and RP Infrapower cleared the fee, prequalification and technical stage on 3 September against a 7 July opening date.
8The Rs 133.62 crore turnkey scope still depends on feeder-wise BOQs to be surveyed and approved after award.
UJVNL extends Kulhal RMU bidding five times, moving the deadline 68 days without touching the 52-month schedule
8The Rs 110.57 crore turnkey package makes the contractor reconstruct the engineering baseline of a 1975 plant through reverse engineering, 3D scanning, CFD, FEA and residual-life assessment at its own risk.
8Manufacturer-backed qualification attracts 15% performance security instead of 10%, plus another 5% against the authorised scope.
JUSNL cuts consultancy turnover threshold by 22.9% after tendering against the wrong estimate
8The corrigendum reduces minimum average annual turnover from Rs 17.32 crore to Rs 13.35 crore and relevant-business revenue from Rs 4.33 crore to Rs 3.34 crore, correcting a base that mixed an excluding-GST figure with an including-GST estimate.
8The liquid-resource requirement and the conflicting bid-start and opening timestamps remain untouched.
NTPC prepays CSIR-SERC in full for Farakka structural assessment with no bank guarantee, LD or defect liability
8The single-tender consultancy waives EMD, security deposit, PBG, qualifying requirements and evaluation while NTPC additionally funds travel, boarding, local transport and PPE for the visiting scientists.
8Three extension instruments in the archive state neither the original nor the revised dates.
NHPC trims derived-rate overhead from 20% to 18.63% on Rs 267.94 crore Salal bypass tunnel
8Corrigendum 1 rewrote the insurance clause so NHPC funds the works policy while the contractor handles claims, deductibles and reinstatement, with up to 5% withholdable from running-account bills for incomplete claim information.
8Disclosed geology includes solution cavities, squeezing ground, rock burst, hot water and ingress above 6,000 litres per minute.
GSECL asks one consultant to write the Dharoi PSP contracts and then police them for 68 months
8The Rs 2.10 crore EMD, 75-mark technical threshold, 200 MW hydro reference and JV prohibition narrow the field before methodology scoring begins, while a "Stop Gap" clause lets
GSECL exclude declared periods from the completion count.
8The tender never states the project's installed capacity.
RRVPN rejects every pre-bid attempt to widen the field on Rs 125.98 crore Sawai Madhopur substation
8Requests to count bay-extension work, cut the four-substation threshold to two and drop bidder-level transformer experience were all answered with instructions to follow the existing PQR.
8Bids more than 15% below estimate attract additional security equal to half the unbalanced amount.
Only BHEL and LC Infra clear technical opening on UJVNL's Rs 1,024.45 crore Lakhwar EPC
8Both bids were admitted on 5 September after a single seven-day extension, leaving no redundancy if detailed evaluation eliminates either offer.
8Turnover thresholds rise from Rs 308 crore to Rs 820 crore for manufacturer-backed bidders, who also face 15% performance security and a lock on the named turbine and generator OEM.
WAPCOS excludes arbitration from its own Rs 1.50 crore transformation mandate while listing the Arbitration Act as applicable law
8Claims must pass an internal EIC or GM (HR) decision, a Departmental Review Committee and mediation before reaching the Delhi courts, with early filing treated as material breach.
8A corrigendum chain moved the pre-bid meeting from "not held" to an online session, then pointed to both August and September.
MAHAGENCO's Koradi skirt-board tender carries two qualification frameworks and two different carbides
8Turnover is required at both 30% and 100% of estimated cost, while experience is tested through a seven-year 40/50/80 formula in one schedule and a three-year plus 25%-order test in another.
8The subject line and panel description say tungsten carbide; the service-item text says modular silicon carbide.
UPPTCL taxes aggressive bidding on the Rs 102 crore Prayagraj GIS package with a sliding security ladder
8Every percentage point below benchmark adds performance security, rising to 1.00% per point beyond a 10% discount.
8Routine arbitration is deleted too, so undercutting costs cash and disputes run through internal committees.
8With no combined cap and no transformer delivery schedule, the question is how narrow the field gets by September 24.
TGTRANSCO's Sadashivpet–NIMZ line package carries a 22-RTU obligation the price schedule never mentions
8Clause 5.26.1 calls for 22 RTUs while the priced schedules cover just two SAS units for the NIMZ bays.
8A deemed-completeness clause and a one-way lump-sum correction rule push that gap onto the contractor.
8Whether a corrigendum lands before September 24 decides if it stays drafting noise or becomes scope.
MSEDCL's Rs 179 crore 22 kV cable tender pairs firm prices with a 100% extension option
8Prices for 7,34,000 metres stay firm with no commodity variation, yet MSEDCL can order the same quantity again on unchanged terms.
8Type-test validity is stated as both ten years and five, and IS 7098 appears in both its 1985 and 2011 editions.
8Even after the September 1 opening, the 50% cap on an out-of-state L1 means the lowest price will not settle the order book.
MSEDCL's Rs 98 crore 11 kV and 33 kV cable tender loosens drum lengths but keeps every commercial lever
8Clause 9.02 now allows 500 or 250 metre drums, but MSEDCL can still demand 250 metres wherever it chooses.
8The same type-test and IS 7098 conflicts recur, alongside a payment clock that starts only when a full monthly lot arrives.
8The open question is how many bidders sized their 20% minimum offer to real extrusion capacity.
GETCO rewrites the Tharad STATCOM engineering bargain across four extensions without touching the 24-month clock
8The Rs 244.54 crore package moved 80 days to September 17 while shifting to a 50°C rating and a 1.5% loss ceiling.
8In exchange, bidders take on oscillation proof, HVDC interaction studies and five years of post-guarantee interference liability.
8The reverse auction will show whether easier equipment thresholds get priced harder than open-ended network risk.
NHPC trims derived-rate margins and rewrites insurance on the Rs 268 crore Salal sediment bypass tunnel
8The contractor still funds reinstatement and faces 5% bill withholding if claim paperwork lags.
8Two extensions added 88 days to bidding but nothing to the 29-month execution period.
DVC holds the 12-month clock on Chandrapura's Rs 90 crore line diversion after four extensions and a late arrester spec
8Submission moved 42 days to September 14, with the lightning-arrester specification added only 11 days before that.
8Underground cable is half the estimate, yet the named cable contractor cannot be replaced after award.
8The issue is whether bidders load the uniform percentage or walk away from a schedule they called unworkable.
BHEL's Darlipali ash handling tender adds 50% more slurry pumps and a fixed hydraulic baseline while the 4,600 kW cap stays put
8Corrigendum 05 fixed wash-water and sludge duties and raised bottom-ash disposal pumps from six to nine.
8Four extensions took bids to September 10, but the 34-month schedule and US$5,245-per-kW damages never moved.
8The reverse auction will reveal whether cautious bidders lose to those assuming detailed engineering absorbs the gaps.
BHEL's Darlipali ash handling tender dates its experience cut-off nine months before its own NIT
8Annexure 1 reckons experience "as on 06/11/2025" against an NIT dated July 29, 2026.
8Milestone withholding, 5% delay LD and 12% performance LD stack on one counterparty with no interest on withheld sums.
8Whether the three qualification routes widen the field enough for a meaningful auction is the thing to watch.
NPCIL bolts a 15% import loading onto the Kudankulam 5 and 6 common services package after eight extensions
8Corrigendum-XII inserted high-seas-sale transfer, customs procedures and a 15% CIF loading 177 days after the original deadline.
8Corrigendum-XI separately enlarged chiller envelopes to 32 MT, reaching into foundations on a 1,278-day schedule.
8With BHEL, L&T, NCC and Tata Projects in the query record, the question is whether the loading reorders a small field rather than widening it.
BHEL's Korba West coal handling tender puts 75% of the price on land it does not expect until May 2027
8One lump sum splits 25:75 between internal and external CHP, with no compensation if the external land arrives late.
8Reverse auction was deleted a day after the NIT, but cross-default across every LOA leaves no contractual ring-fence.
8After five extensions to September 10, the open issue is how much contingency lands in Package B.
SECL's Gevra weighbridge consultancy asks five CPSUs to price 2,520 days against a portal that shows five years
8GeM displays five years, but the corrigenda fix 2,520 days of exposure backed by an 86-month ePBG.
8The PMC also runs a 20% imprest and pays contractors, with 45% of its Stage III fee tied to that role.
8With five invitees and no floor price, the question is whether the lowest percentage survives seven years.
NTPC's Rs 200 crore Kahalgaon pond ash contract offers five contractors a panel seat and none of them guaranteed work
8GeM says no bid splitting, but the ATC splits the contract five ways, caps each at Rs 40 crore and allows minus 100% quantity.
8Payment follows the lowest of three measurements before 5% reconciliation and 2% safety retention.
8The real test after the August 31 close is how many ranked bidders accept the discovered L1 across all six distance slabs.
AEGCL bundles two 400 kV lines and Agia GIS into one JV-barred package for 3,200 MW evacuation
8AEGCL has invited bids for an indivisible turnkey package covering the Chapar–Rangia and Chapar–Agia Quad Moose lines, a new 400/220 kV Agia substation and Rangia bay extensions, with Rs 24 crore bid security.
8Bidders must show Rs 2,500 crore average turnover, 400 kV GIS credentials and 100 circuit km of 400 kV line experience in a single Assam project, with no joint-venture route and fixed prices over 36 months.
8The unresolved issue is an EMD instruction the portal marks exemptible while the BDS bars digital deposit and disapplies the exemption clauses.
WAPCOS Moran River DPR tender carries three completion clocks and an arbitration clause that cancels itself
8WAPCOS has re-issued a Rs 17.70 lakh GeM bid for architectural design and a technical-sanction-ready DPR covering 20 riverfront components at Khadgada, Dungarpur, closing 16 September.
8The consultant must field a 15-year lead architect and deliver coordinated architectural, structural and MEPF designs while WAPCOS pays back-to-back, retains 2.5% from running bills and holds a 5% ePBG for eight months.
8Completion is stated as two months, 60 days from award and 21 days from agreement, and arbitration is both promised and excluded, leaving schedule and forum unsettled.
AEGCL's Chapar evacuation tender adds ±15% quantity swing and a next-lowest-bidder step-out to firm pricing
8The 36-month turnkey package treats quantities as provisional within ±15% of contract price while keeping the price firm and deeming unlisted completion items included. GIS carries a second security of 20% of ex-works cost for five years beyond the defect period, alongside an unreduced 10% performance security, 60-day payment terms and no interest on delay.
8AEGCL's right to transfer unfinished work to the next-lowest tenderer raises the harder question of how an integrated system can be split mid-execution without responsibility gaps.
BHEL's Tikrikhurd GIS tie-up layers 10%, 2% and 10% guarantees on a zero-EMD tender
8The OEM must supply 82 bays and 5,200 m of 400 kV GIB within 21 months, then supervise commissioning within nine, under a 60-month defect period extendable to 84 plus a five-year latent-defect tail.
8Beyond a 10% BHEL security and 2% DTL guarantee, Route-2 and Route-3 manufacturers post another 10% from collaborators, while items marked "NA" but later needed must be supplied free.
8The type-test and PQR reference date of 18 August predates BHEL's own 2 September invitation, compounding the Gopalpur language and an undisclosed downstream price-sharing formula.
NTPC's Rs 300-crore Gadarwara ash contract empanels six agencies but guarantees none a purchase order
8NTPC is seeking slab-wise rates for excavating, loading and hauling pond ash up to 300 km to NHAI and PMGSY sites during FY 2026-27, with a Rs 50 lakh EMD and AST-01 enlistment as the entry gate.
8Up to six L1-matching contractors are each capped at Rs 50 crore, must fit AIS 140 GPS with API access and submit geo-tagged trip evidence, while aggregate value may fall by 100%.
8With one uniform premium across six distance slabs plus excavation and loading, the real exposure is financing a mobilised fleet against volumes NTPC is free to withhold.
NSPCL closes 123-day extension chain on Durgapur pulveriser R&M with spares restored from three to 24
8After 12 deadline revisions, NSPCL has declared 8 September final for bids to replace eight coal pulverisers across two 60 MW units at Durgapur PP-II, with a Rs 1 crore EMD.
8Amendment 4 reversed Amendment 2 by restoring 24 pump assemblies in mandatory spares, while Amendment 3 added dual instruments for CLCS and protection duties.
8Bidders who priced on the interim three-pump requirement face an eightfold quantity correction inside a brownfield package whose completion period, LD and PBG remain unstated.
SECI fixes turbine coordinates yet leaves the wind contractor liable for a SCADA platform another package owns
8SECI is procuring a 45.6 MW ISTS-connected wind project at Ramagiri plus ten years of O&M, evaluated on EPC price plus O&M NPV at 8.30% before an e-reverse auction.
8The contractor must commission within 14 months, hold 96–98% availability, keep 5% security through the tenth O&M year and integrate its LCS with a CMCS, PPC and grid-compliance study delivered by the solar-plus-BESS contractor.
8LD switches from the uncommissioned portion to 5% of total contract price after ten weeks, while the O&M price workbook still describes the asset as a solar-plus-BESS project.
UJVN's Sirkari Bhyol E&M tender reaches 20th extension after estimate climbs 53.3% to Rs 243.05 crore
8The 3×40 MW Francis-turbine package at Munsyari now closes 10 September, 255 days after its original December 2025 deadline, with EMD raised twice to Rs 5.7385 crore.
8Seven addenda widened experience to 15 years, cut the generator threshold to 35 MVA, admitted surety bonds and switched guide bearings from water to oil lubrication.
8Additional security on borrowed credentials rose from 3% to 5% and validity stays at 270 days, so bidders must price against an unconsolidated trail of 23 corrigenda.
NREDCAP's 15 MW Vijayawada WtE concession bids on lowest grant with a Rs 19.99-crore security stack behind it
8The 22-year DBFOT project, costed at Rs 324.70 crore, seeks developers with 800 TPD single-facility or two 500 TPD waste-to-electricity references and Rs 81.17 crore net worth.
8The selected bidder posts Rs 16.24 crore to the municipal authority and Rs 25 lakh/MW to APDISCOM, with the O&M-qualified consortium member locked in for the full term.
8Portal text dispenses with originals at evaluation while Clause 27.2(c) makes their receipt by bid date a responsiveness condition, leaving rejection risk unresolved.
SECI's bulk-consumer EOI shifts pre-bid meeting three times without touching the 15 September deadline
8SECI is inviting AAA-to-BBB+ rated consumers with 50 MW-plus demand to disclose load, credit and land data for solar, wind, hybrid, FDRE, RTC, BESS and PSP procurement under captive, group-captive, JV and PMC structures.
8SECI proposes to handle land, connectivity, EPC selection, financing and O&M for up to 25 years, while respondents bear all participation cost under a non-binding framework.
8The final meeting notice dropped the public time and link, and tariff, curtailment, change-in-law and payment-security terms remain wholly undefined.
TPTL inserts 27-page CFC-HTLS spec four days after publishing Rs 18.38-crore 132 kV LILO tender
8The corrigendum fixes an 800 A carbon-fibre-core conductor, 7.0 m sag at 320 m span and loss-capitalised evaluation at Rs 3,30,220 per kW for 43.8 km of reconductoring beside a live circuit.
8The contractor absorbs tower-load checks, type-test costs, damage restoration and railway crossings without assured shutdowns, with bids now closing 14 September after a 12-day extension.
8Section II's "ten percent (3%)" performance-guarantee wording and the 800 A/437 A sag mismatch remain uncorrected.
DVC's 1x800 MW Durgapur BOP package moves 38 days across four corrigenda with two-unit completion text intact
8DVC's international EPC tender for FGD, chimney, coal and ash handling, a 7 km raw-water system, 400/220 kV GIS, DCS and ZLD now closes 24 September, with bid security of Rs 25.69 crore or USD 2.72 million.
8Bidders need Rs 1,250 crore average turnover and face 10% performance security plus a 2% consortium integration guarantee, with LD at USD 106,610 per day capped at 5%.
8BDS Item 9.0 still reads "44 & 48 months for Unit 1 & Unit 2" against a single-unit SCC, leaving the LD baseline dependent on interpretation.
Four bidders clear technical stage in DHBVN's Rs 118.78-crore Hisar SCADA DMS infrastructure package
8Agarwal Traders, Century Infrapower, Gawar Construction and RP Infrapower were admitted after two extensions moved closing to 3 August for 11 kV augmentation, feeder bifurcation, RMUs and VCBs.
8Corrigendum-I shifted location approvals and final inspection from the Smart Grid Project wing to the nodal officer and operation wing, and assigned FRTU and DCP supply to the separate SCADA agency.
8Additional security climbs to 24% for bids 24% below estimate, and delay attribution where RMUs wait on another agency's automation kit is unallocated.
Five bidders admitted to DHBVNL's Rs 157.83-crore 33 kV augmentation tender carrying two EMD figures
8Agarwal Traders, Century Infrapower, Gawar Construction, Laser Power & Infra and RP Infrapower cleared technical evaluation on 7 August for turnkey augmentation of 72 operating substations within 12 months.
8DHBVNL may interchange substations without time relief, requires approval of all non-labour subcontracts and has raised TPQMA inspection of augmented substations from 5% to 100%.
8The NIT and portal set EMD at Rs 3.16 crore while the SBD summary says Rs 1.55 crore, and no hierarchy resolves the difference.
PwC wins MPPTCL S/4HANA migration 35.8% below Deloitte as comparative sheet multiplies contract value
8PricewaterhouseCoopers is L1 at Rs 297.4608 crore against Deloitte's Rs 404.0366 crore for ECC-to-S/4HANA conversion under RISE with SAP, five years of licences, legacy support and hypercare.
8The RFP directs evaluation on GST-inclusive Item H—Rs 104.47 crore versus Rs 141.89 crore—but the published total sums components, subtotal, GST and total together.
8L1 priced migration at Rs 14.39 crore against Rs 36.65 crore and ECC support at Rs 6 lakh against Rs 6.54 crore, while Corrigendum-5 deleted VAPT from scope.
WBSETCL adds 120 days to 43-transformer delivery programme and hardens split into 26:17
8The 80 MVA, 132/33 kV package with NIFPS and spare RIP bushings now closes 10 September, with the first eight units due at 300 days instead of 210 and completion at 600 days.
8Bidders face H1 elimination before reverse auction, 10% additional security if L1 falls at or below 80% of estimate, a 60-month defect period and 5% security retained after supply.
8The second supplier receives 17 units only at the L1 price, leaving open whether price-matching reproduces the delivery risk the extension sought to cure.
For daily newsletters and other free services, fill in your details: