All content in this website is sourced legitimately

UK power companies: Local entrepreneurs should bring them to India.  Power projects: Business opportunities ahead.  Our exclusives .  Download Tenders and Newsclips.  Download Tenders and Newsclips.  .  Our exclusives .  .  Software updates: Power projects.  .  Download Tenders and Newsclips.  .  .  .  Software updates: Power projects.  Our exclusives .  .  Download Tenders and Newsclips.  .  Software updates: Power projects.  

UK power companies: Local entrepreneurs should bring them to India

May 24: The UK is one of the most advanced countries when it comes to power reforms and use of new technology.
8Here is a complete template of how UK power companies can work in India
8May be this is a good time for Indian entrepreneurs to tie up with these companies to look for unfolding opportunities here
Click on Reports for more Details

Power projects: Business opportunities ahead

May 24: Project Name:Thermal Power Project: Installation of FGD
8Project Cost: 200 crores
8Project Description: The owner has awarded GE Power India a contract for the installation of the FGD system in the 1050 MW (5x210 MW) thermal power project. Earlier, the proponent had informed that the 5x210 MW units were SOx compliant with respect to the new emission norms. However, after the feasibility study, a wet FGD system was planned.
8Project Event: RFQ for the limestone handling and gypsum handling unit is expected by September 2019.
8Expenditure Approval: 2020
8RFQ Date: Sep/2019
8Release Date: Sep/2019
8Start Date: Jun/2022
8Completion Date: 2024
Click here for more details

Project Name: Thermal Power Station - FGD Addition
8Project Cost: 100 crores
8Project Description: The owner along with the consultant TCE has carried out the feasibility studies to install an FGD system in the operating 500 MW unit and DSI system in the remaining 4x210 MW units of a thermal power complex. The project is, however, getting delayed due to pending state clearances. Moreover, TCE is exploring the where to locate the DSI system at site. 
8Project Event: RFQ for the supply of an FGD system is expected to be out by Q4 2019.
8Expenditure Approval: Q1:2017
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2021
8Completion Date: 2022
Click here for more details

Project Name: TPS - FGD Addition
8Project Cost: 200 crores
8Project Description: The owner along with a consultant is carrying out feasibility studies for the installation of a flue gas desulphurisation system in the operating 600 MW power complex out of 1650 MW (5x210+1x600 MW) thermal power plant located in Cuddapah district of Andhra Pradesh. The developer has confirmed that the 5x210 MW units comply with the new norms of the MoEF. Thus, there is no need of installation of FGD in the 5x210 MW units. But, the 600 MW unit commissioned in 2018, need the installation of an FGD system.
8Project Event: RFQ for supply, installation, erection and commissioning of the FGD system is expected by the Q4 2019.
8Expenditure Approval: 2016
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 3000 crores
8Project Description: The owner is planning to sign MoU with the Government of Himachal Pradesh in June 2019 for development of a 355 MW HEP Stage III greenfield hydropower project Preparation of DPR in progress. Geological Investigations (Drilling and Drifting) are under progress. Voyants Solutions Private Limited is carrying out the draft EIA report. Diversion of forest land is under process with concerned DFOs. The SIA study has been awarded to Plan Foundation, for which the field work is in progress. Further bids are expected soon.
8Project Event: RFQ for civil works is expected to be out by Q4 2019.
8Expenditure Approval: 2020
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Super Thermal Power Station Absorber System Package
8Project Cost: 300 crores
8Project Description: The owner is finalizing the price bid for absorber system package in its stage-III (1x500 MW) units out of the 2600 MW (3x200 + 3x500 + 1x500 MW) thermal power complex in the Karimnagar district of Telangana. GE Power India, ISGEC, L&T and Thermax are among those in the race.
8Project Event: The award of the absorber system package is expected by September 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Sep/2019
8Release Date: Sep/2019
8Start Date: Q1:2020
8Completion Date: Q1:2021
Click here for more details

Project Name:Hydroelectric Power Station - Head regulator and Link Canal Project
8Project Cost: 80 crores
8Project Description: The forest clearance at State level is at the final stage. 
8Project Event: Award for rock testing, ground testing, and soil testing contractor is likely to be expected by November 2019
8Expenditure Approval: Q4:2017
8RFQ Date: Nov:2019
8Release Date: Dec:2019
8Start Date: Q3:2019
8Completion Date: 2020
Click here for more details
Details

Our exclusives

May 24: 8The causal link between energy consumption, carbon emissions and economic growth in India A full analysis
8Renewable energy: Continuing to grow  Details
8Ruling: The rate of the late payment surcharge shall be applicable as per the PPA or regulations only Details
8Global energy progress report 2019. A report
8India can capitalize on the declining costs of wind and solar: An analysis
8Electricity supply and demand lies at the heart of India’s energy future: An analysis Details
8Transmission tariffs for FY 2019-20. An analysis
8IndiGrid: Corporate presentation May 2019 Details
8Forecasting CO2 emission by power production mix in India A Report
8Global energy transition to 2050: What needs to be done Details
8Likely Global solar market developments from 2020 to 2023: A Report
8Converting a grid-connected power generation unit into captive status: What kind of regulatory approvals are needed? Details
8Green agenda 2019: Sustainability imperatives for India’s next government Details
8Business opportunities for power companies in the Indian power sector Details 
8The average efficiency of electricity generation from fossil fuels is nearly 40%. How is that so?: An analysis
8How does the power transmission model on long term BOOM (Build Own Operate Maintain) work in India Details
8Fossil fuel-based cogeneration plants are allowed to fulfill their cumulative RPO targets by March 2020 ?  Details
8The Bagasse based power offtake allowed at Rs 3.56/Unit. Details
8Life cycle assessment of a combined-cycle gas turbine with a focus on the chemicals used in water conditioning: A Report
8Scaling up renewable energy (SURE) projects helps India implement clean energy solutions efficiently and effectively Details
You can also click on Reports for more on the above Details

Download Tenders and Newsclips

May 24: For reference purposes the website carries here the following tenders: 
8Tender for procurement of GT Rotor Mid Hollow Shaft at Gas Power Station Details
8Tender for Work of Aresting Oil Leakages from various Power Transformers by Cold welding method Details
8Tender for Procurement of spares for Generator Hydrogen dryer Details
8Tender for Procurement of 24V BOP and SGTG battery banks Details
8Tender for the work of Constructing 15.5km HT ABC Details
8Tender for Providing & fixing of Numerical Distance, Back Up and Differential relays for 220kV EHV lines Details
8Tender for Procurement of Numerical Distance, Back Up and Differential relays for 220kV EHV lines Details
8Tender for the work of construction of 01 No. of Incomer bay for 132/33kV T/F & 01 No. of 33kV Outgoing feeder at 132kV sub-station Details
8Design, Fabrication, Supply ,testing ,Erection & commissioning of LT panel Details
8Supply, testing, installation and commissioning of ABT meters Details
8Supply Of Spare Vacuum Circuit Breakers And Voltage Transformer Trollies Details
8Tender for the Work of Operation & Maintenance of MRHS and transportation of Coal Mill Reject to Reject Yard Details
8Tender for the work of strengthening with material supply of damaged Raw Coal Bunkers Details
8Tender for Purchase of Sliding type Dual Disk Valve Details
8Supply, Installation, Testing and Commissioning of Auxiliary power supply scheme Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Kakrapar Atomic Power plant connected to grid Details
8Greek grid operator launches tenders for $1-bn power link Details
8Coal loans battle Green tide Details
8Australia state says final approvals for Adani's coal mine to be decided within three weeks Details
8CERC Orders Tariff Settlement for a 1.5 GW Hydro Project in Himachal Pradesh Details
8India’s Solar Industry Reacts to Modi Government’s Win in Lok Sabha Elections 2019 Details
8Uttar Pradesh Approves PPA for 14.5 MW of Municipal Solid Waste Projects Details
8Centre looking to ‘insulate’ discoms from payment delays Details
8BHP has no appetite to grow its thermal coal assets: BHP Group CFO Details
8French bank SocGen further reduces business with coal industry Details
8In Vietnam's booming energy sector coal reigns, but renewables play catch-up Details
8Election Results: Renewable energy industry expects govt to sharpen focus on policy stability Details
8Senegal imports turbines for West Africa's first big wind farm project Details
8Montenegro moves to halt small hydro power plants Details
8China to end subsidies for onshore wind power by 2021 Details
8France still to clear EPH's acquisition of Uniper's French assets Details
You can also click on Newsclips for more
Details

Download Tenders and Newsclips

May 23: For reference purposes the website carries here the following tenders: 
8Tender for Running maintenance and overhauling of Main Turbine Auxiliaries Details
8Tender for procurement of GT Stage-3 Stator Vanes & fixing material for Gas Turbine Details
8Tender for Supply of Nylon/Nylon Fiber conveyer belt Details
8Tender for Procurement of Spares of Hydrogen Seal for Generator Details
8Tender for Procurement of set of Worm Shaft and Worm Gear for Coal Mill XRP-763 of TPS Details
8Tender for the Work of servicing & overhauling of 33/22kV VCB Details
8Tender for the Work of Extension of 1.05 kM, 33kV Over Head Line with Laying & Erection of 33kV Underground XLPE cable Details
8Supply, Erection, Site testing & commissioning of 11kV overhead line Details
8Tender for work of testing of EHV grade transformer oil samples Details
8Tender for Supply of three nos of 245kV,800A OIP condenser type bushings for Generator Transformers Details
8Tender for Supply of 100A LT re-wirable type porcelain fuse units Details
8Tender for the work of Rebabbitting of Unit-3 Thrust Pads Details
8Tender for Round the Clock Operation of Main Plant & BOP Equipment Details
8Tender for P-way and S&T Maintenance Services Details
8Annual Rate Contract for Plant & CSR Civil Works Details
8Tender for Procurement of LED street light Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8ReNew Power says India requires double the amount of power supply in next 10-12 years. Details
8Jharkhand Commission Approves PPA for 10 MW of Solar Projects, Details
8Task of procuring wind, solar energy handed over to SECI. Details
8France's Voltalia in exclusive talks to buy Helexia Details
8ElectionResults: Power sector reforms - a new agenda for the new government Details
8Adani's coal hopes look increasingly isolated as BHP joins naysayers Details
8US says Trump coal moves hasten but don't increase emissions Details
8ADB to provide $750 mn loan to India for railway track electrification project Details
8What Modi needs to do to get growth back, push market-reform Details
85th Smart Cities India 2019 expo inaugurated by Durga Shanker Mishra, Secretary, MoHUA Details
8Mining giant BHP says coal outlook 'challenged' Details
8Seeking energy independence, Palestinians open solar power plant Details
8Goa: Solar prosumers await payments Details
8Three-wheelers may have to go electric from FY24 Details
8India proposes electrifying motorbikes, scooters in 6-8 years Details
8Coal India on Rs 10,000 crore equipment buying spree Details
You can also click on Newsclips for more
Details

Our exclusives

May 22: For reference purposes the website carries here the following reports: 
8ABB has introduced a new fusegear with 800V AC ratings to support higher voltage architectures in solar power plants Details
8Wind power generator seeks tariff of Rs.6.33/- per kWhL Regular however pitches for consensus rate, in discussion with offtaker. Details
8Reduction of power production costs in wind power plant: A new way out Details
8Maintenance strategy optimization of a coal-fired power plant cooling tower through generalized stochastic petri nets: An analysis
8High cost of power generation makes a project unviable when third-party sale is involved: An analysis
8Find out how sensitivity of solar power generation to adverse variations in weather conditions as well as panel degradation can negatively impact cash flows Details
8Omegga Power Industry Private Ltd: Ratings withdrawn Details
8An India based power company shares are up as it hedges coal price for up to 60% of coal requirement Details
8Supreme Solar Systems: Rating continues to remain under ‘Issuer Not Cooperating’ category Details
8Establishment of new 400/220 kV substations in northern region: Business development opportunities Details
You can click on Reports for more on the issues above
Details

Software updates: Power projects

May 22: Project Name: Greenfield Hydroelectric Power Project, Stage-1
8Project Cost: 2000 crores
8Project Description: The owner has extended the bidding date for an EPC contract for design and engineering services of main civil and hydro-mechanical works in a greenfield 210 MW (2x80 MW main unit + 2x25 MW auxiliary unit) hydroelectric power project 
8Project Event: RFQ for E&M works worth Rs. 372.78 crores are expected by the Q3 2019.
8Expenditure Approval: Q4:2018
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: 2020
8Completion Date: 2025
Click here for more details

Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 2500 crores
8Project Description: The CEA has vetted the project cost at Rs. 2238 crores. The stage-I forest clearance accorded on 26.02.2018 and stage-II forest clearance is under progress. Construction of boundary pillars for demarcation of forest land is in progress. 
8Project Event: RFQ for design and construction of single-lane steel truss Bridges-IV are expected by June 2019.
RFQ for main plant civil works is expected by the Q4 2019.
8Expenditure Approval: Dec/2018
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: 2020
8Completion Date: 2025
Click here for more details

Project Name: Thermal Power Station - FGD Addition
8Project Cost: 200 crores
8Project Description: BHEL, Tata Power, and L&T have been qualified in the techno-commercial part of the bid for the installation of a flue gas desulphurization system
8Project Event: The award for the FGD package is expected by the Q4 2019.
8Expenditure Approval: Q2:2019
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2021
8Completion Date: 2023
Click here for more details

Project Name: Combustion Modification Package
8Project Cost: 100 crores
8Project Description: The owner has awarded to GE Power -- in the race were ISGEC Heavy Engineering Ltd and Doosan Power System,--  for installation of a combustion modification package for a 1500 MW (3x500 MW)super thermal power plant
8Project Event: RFQ for air compressor, valves and fittings, and ID fans is expected by July 2019.
8Expenditure Approval: Q2:2017
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: Q4:2019
8Completion Date: 2021
Click here for more details

Project Name: Thermal Power Station: Installation of WFGD
8Project Cost: 300 crores
8Project Description: The owner in consultation with NTPC is preparing cost estimate and technical specifications for installation of four wet limestone based flue gas desulphurisation systems 
8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by July 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: 2021
8Completion Date: 2023
Click here for more details

Project Name: Installation of FGD
8Project Cost: 300 crores
8Project Description: The owner is going on with evaluation of bid for installation of FGD in 2x500 MW thermal power station
8Project Event: The award for the flue gas desulphurization system (FGD system) is expected by July 2019.
8Expenditure Approval: Q312017
8RFQ Date: July:2019
8Release Date: July:2019
8Start Date: 2021
8Completion Date: 2023
Click here for more details

Project Name: Thermal Power Station - Installation of new cooling towers
8Project Cost: 200 crores
8Project Description: The owner is preparing feasibility report for installation of new cooling towers in the 3x210 MW  in place of the old cooling towers at the existing facility of 2630 MW (3x210 + 4x500 MW) thermal power station located . The floating of RFQs for supply of new cooling towers is getting delayed due to delay in preparation of DPR. 
8Project Event: RFQ for supply, installation, erection, and commissioning of cooling towers are expected by the Q3 2019.
8Expenditure Approval: Q2:2018
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details
Details

Download Tenders and Newsclips

May 22: For reference purposes the website carries here the following tenders: 
8Tender for Purchase of Different size of Globe Valves for Ash Handling Plant Details
8Tender for the work of Supply ,Laying, testing and commissioning of LT UG cable Details
8Tender for Testing, dismantling & safe carriage of 125 MVA Generator Transformer Details
8Tender for Procurement of Turbine Sealing Ring Details
8Tender for Procurement of Sulphuric Acid Details
8Tender for Procurement of impact and v-return idlers for Conveyor system in CHP Details
8Tender for Procurement of 400kV CT and CVT Details
8Tender for Onsite coating of GT compressor components Details
8Tender for Upgradation of 66kV Substation to 110kV Substation Details
8Annual Rate Contract for repair, rewinding and re-insulation of 6.6 KV motors ranging from 200 KW to 4600 KW Details
8Tender for Rewinding of damaged stators of 0.4 KV LT Motors Details
8Tender for Work of Shifting/Modification of 132 kV D/C line Details
8Tender for Work of Shifting/Modification of 132 kV line Details
8Tender for Work contract for the work of overhauling of 220kV circuit breaker Details
8Tender for Work of Transportation, Winching, Loading & Unloading of Power Transformers Details
8Tender for Purchase contract of Chemical with servicing for cooling water treatment Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8India’s solar dream: Policy reforms, improved execution key to achieving energy transformation Details
8The future of Indian electricity supply: Scenarios of coal use by 2030 Details
8Stress meter: Discoms’ dues to gencos at Rs 3,800 crore Details
8Recharge time for renewable power Details
8BHEL commissions 2 more units of Kaleshwaram irrigation project in Telangana Details
8Two former Ostro executives to set up clean energy firm Details
8India's thermal coal output seen growing 4.3% annually till 2028: Report Details
8Joint Electricity Regulatory Commission issues tariff orders for Union Territories Details
8Vestas takes aim at cheaper U.S. wind power with new turbine Details
8Tata Power Renewable Energy wins Gujarat solar auction Details
8Engie and EDP aim to be second-biggest offshore wind developer with JV Details
8Toshiba, Siemens Gamesa, Blackstone interested in Senvion Details
8Tangedco’s finances head south, reports loss of Rs 7,000 crore Details
8Chandigarh: AAP threatens to launch protest if power tariff hiked Details
858% increase in power transmission capacity of UP in past three years Details
8Polls over, PSERC to announce new power tariff soon Details
8Patchy progress on electricity access casts shadow on global goal Details
You can also click on Newsclips for more
Details

Software updates: Power projects

May 21: Project Name: Yeramarus Super Thermal Power Station: Installation of WFGD
8Project Cost: 500 crores
8Project Description: Raichur Power Corporation Limited, a JV of KPCL, BHEL, and IFCIL is carrying out the bidding process for the development of the wet limestone-based FGD system in the 2x800 MW thermal power project located in the Raichur district of Karnataka. Fichtner Consulting Engineers and STEAG has carried out the design of the FGD equipment. Further bids are expected soon. The pre-bid meeting is expected by the end of May 2019. 
8Project Event: The technical bid date is expected by July 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details

Project Name: Lower Kopili Greenfield Hydroelectric Project
8Project Cost: 1000 crores
8Project Description: The RFQs for an electro-mechanical package in the APGCL's 120 MW (2x55 MW surface power-house + 2x2.5 MW+1x5 MW auxiliary power-house) greenfield hydroelectric project at Longku village, situated in the Karbi Anglong district of Assam is getting further delayed due to clearance pending at the state high-level committee. The civil and hydro-mechanical bids have been floated, and are still under evaluation. Patel Engineering Limited, HCC Limited, Gammon India are among the major contenders in the bid. 
8Project Event: RFQ for engineering, procurement, construction and commissioning of electro-mechanical works is expected by August 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Aug:2019
8Release Date: Aug:2019
8Start Date: Q1:2020
8Completion Date: Q3:2024
Click here for more details

Project Name: Solapur Super Thermal Power: FGD Addition Project
8Project Cost: 500 crores
8Project Description: GE Power India along with sub-contractor Priya Construction is carrying out the RCC works at the chimney for implementation of a Flue Gas Desulphurisation Unit (FGD) in the NTPC's 1320 MW (2x660 MW) thermal power complex in Solapur, Maharashtra. Currently, civil works are under progress. Further bids are expected soon.
8Project Event: RFQ for supply and installation of limestone handing plant is expected by June 2019 by GE Power India.
8Expenditure Approval: Q2:2017
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: Q4:2018
8Completion Date: Q1:2021
Click here for more details

Project Name: Marwa Tendubhata Thermal Power Station - Installation of FGD
8Project Cost: 300 crores
8Project Description: Chhattisgarh State Power Generation Company Limited is preparing technical specifications for installation of a wet limestone based flue gas desulphurization system at its 1000 MW (2x500 MW) thermal power station located at Marwa village, in the Janjgir-Champa district of Chhattisgarh. Development Consultant Private Limited has prepared the DPR for the FGD. Wet Stack will be used instead of GGH. 
8Project Event: RFQ for design, supply, installation, erection, and commissioning of WFGDs is expected by July 2019.
8Expenditure Approval: Q3:2018
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details

Project Name: Rajghat Thermal Power Station - Dismantling
8Project Cost: 200 crores
8Project Description: Indraprastha Power Generation Co. Ltd. is planning to dismantle two plants of 135 MW (2 x 67.5 MW) coal-based thermal power plant in Rajghat, Delhi. The two plants have been shut down since December 2015. Currently, the promoter is approaching the Delhi Government for approval of the dismantling process. 
8Project Event: RFQ for dismantling services of various equipment is expected to kick off by the Q4 2019.
8Expenditure Approval: Q2:2017
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2020
8Completion Date: 2021
Click here for more details

Project Name: Talwandi Sabo Super-Critical Thermal Power Project - Installation of SNCR
8Project Cost: 800 crores
8Project Description: Talwandi Sabo Power Limited is going on with the bidding process of a Primary NOx Emission Control system in the 1980 MW (3x660 MW) super-critical thermal power complex at Mansa, Punjab. The price bid evaluation for the installation of wet flue gas desulphurisation system is under progress in which BHEL, Mitsubishi Hitachi Power Systems India Pvt. Ltd, ISGEC Heavy Engineering Limited, GE Power India Limited, and L&T are the major contenders. 
8Project Event: The award of the FGD package is expected by August 2019.
The award of the Primary NOx control system is expected by September 2019.
8Expenditure Approval: Q3:2019
8RFQ Date: May:2019
8Release Date: May:2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details
Details

Our exclusives

May 21: 8In India, total renewable power investment has topped fossil fuel-based power investment: A report
8IEA's estimates on coal based power investment in India far more pessimistic than reality Details
8India’s transmission outlay in next three years pegged at Rs 30,000 crore  Details
8Energy investment in India has grown the most over the past three years: A report
8Siemens Gamesa: A trusted technological partner for wind power projects Details
8Scheduling and dispatching details of adani solar power project in Tamilnadu Details
8Business opportunities in outages: Get details of what is coming up 
8Ceiling on compensation for the delay in releasing connections to all consumers in the license area shall be twice of the service connection charges deposited by that consumer, clarifies regulatory body Details
8If tariff is frozen under a PPA, revision of tariff possible only under a new PPA Details
8India is projected to invest $44.9bn in smart metering, distribution automation, battery storage and other smart grid market segments over the next decade: A report
You can also click on Reports for more
Details

Download Tenders and Newsclips

May 21: For reference purposes the website carries here the following tenders: 
8Tender for Maintenance Contract for preventive and breakdown maintenance of C&I systems of Boiler Details
8Tender for Rate Contract of Emergency, Breakdown & Maintenance in CHP Details
8Tender for Supply of Tubular Protectors & 'U' Clamps for the Boiler Details
8Tender for Testing, dismantling & safe carriage of 125MVA Generator Transformer Details
8Tender for manufacture, testing, supply and delivery of 3ph 4 wire LT CT operated DLMS compliant Bulk Consumer energy meters Details
8Tender for Purchase of Spares for 220KV SF6 Circuit Breakers Details
8Tender for Procurement of Cyclone Separators for Cooling water System and Shaft seal system Details
8Tender for Purchase of Miscellaneous Turbine Items Details
8Tender for Interlinking 11kV line by drawing ABC and 11kV OH line Details
8Tender for Drawing covered conductor through existing Pullu and Panthode double circuit feeder Details
8Tender for Interlinking Feeder using 1.2Km Covered Conductor Details
8Tender for the work of Supply ,Laying, testing and commissioning of LT UG cable Details
8Annual maintenance & attending emergency breakdown work of 400 KV Transmission Lines Details
8Tender for De-watering pump along with motor Details
8Tender for Procurement of Micro-Controller based Battery Chargers Details
8Tender for Technical Audit of earthing & lightening system of entire plant Details
8Tender for Procurement of Submersible Dewatering Pump Details
8Tender for Procurement of Conveyor Belt for CHP Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8CERC tariff relief for IPPs positive for power gencos: ICRA Details
8Kakrapar nuclear power reactor to be synchronised with grid next week Details
8Uday scheme: Discoms drift back to old ways, key targets missed Details
8Adani Green Energy's 8.75 crore shares to be offered for sale on Tuesday Details
8Court questions Punjab, Haryana on free power to rich farmers Details
8Power sector's outstanding regulatory assets at Rs 76,963 crore Details
8Australian election results bode well for Adani’s coal mine project Details
8Vestas receives 249 MW order from EDF Renewables Details
8Petronas’ subsidiary Amplus Solar to invest Rs 750 crore in Haryana Details
8Oriano completes 9 projects for Cleantech Solar across multiple states Details
8Adani Green Energy, ReNew Power only bidders in hybrid auction Details
8ISA delegation to explore Cochin airport's solar power project as success model Details
8Ashok Leyland ready to ride on Elon Musk's India dream for EVs Details
8New layouts to reserve 0.5% land for power infrastructure Details
8Mahagenco sets a new record for power generation, crosses 10,000 Mw mark Details
You can also click on Newsclips for more
Details

Software updates: Power projects

May 20: Project Name: Guru Hargobind Thermal Power Plant - Installation of FGD
8Project Cost: 400 crores
8Project Description: Punjab State Power Corporation Limited along with consultant NTPC has prepared the technical specifications for installation of wet limestone based flue gas desulphurisation system in the operating 920 MW (2x210+2x250 MW) thermal power plant located in the Lehra Mohabbat district of Punjab. 
8Project Event: RFQ for design, engineering, supply, transportation, installation, erection, and completion of an FGD package is expected by July 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Suratgarh Thermal Power Station - FGD Addition
8Project Cost: 300 crores
8Project Description: Rajasthan Rajya Vidyut Utpadan Nigam Limited along with consultant Fichtner Consulting Engineers Limited is carrying out investigations in order to clarify whether to install an FGD system or a DSI system in its operating 1500 MW (6x250 MW) Thermal Power Station at Suratgarh, in Sri Ganga Nagar district of Rajasthan. Meanwhile, tenders are ongoing for the 2x660 MW under- construction Suratgarh supercritical thermal power project. 
8Project Event: RFQ for design, supply, installation, and commissioning of an FGD is expected to be out by the Q4 2019.
8Expenditure Approval: Q3:2017
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Gas Based Combined Cycle Expansion Power Project
8Project Cost: 3500 crores
8Project Event: RFQ for an EPC contractor for the main plant works is expected by August 2019.
8Expenditure Approval: Q3:2019
8RFQ Date: Aug/2019
8Release Date: Aug/2019
8Start Date: Q3:2020
8Completion Date: Q4:2023
Click here for more details

Project Name: Tanda Thermal Power Expansion Project
8Project Cost: 10000 crores
8Project Description: National Thermal Power Corporation Limited along with ESP contractor BHEL is carrying out erection works for the 1320 MW (2x660 MW) super-critical thermal power expansion project at its existing facility, where a 440MW plant was installed, at Tanda Thermal Power Station. 
8Project Event: RFQ for limestone handling plant and gypsum handling unit for the FGD system is expected by the Q3 2019.
8Expenditure Approval: Sep/2014
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: Oct/2015
8Completion Date: Q4:2019
Click here for more details

Project Name: Shree Singaji Super-Critical Thermal Power Brownfield Project (Stage-II)
8Project Cost: 7500 crores
8Project Description: Madhya Pradesh Power Generating Company Limited is carrying out the price bid evaluation of an EPC contractor for the FGD system package for the 1320 (2x660 MW) super-critical brownfield thermal power complex at the existing 1200 MW (2x600 MW) facility located at the Dongalia village, in the Khandwa district of Madhya Pradesh. L&T, GE Power India, Mitsubishi Hitachi Power Systems India Pvt Ltd, Doosan Power Systems India Pvt Ltd, and ISGEC Heavy Engg. Ltd is the major contenders in the race. 
8Project Event: The award of the FGD system package is expected by June 2019.
8Expenditure Approval: 2014
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: 31/Dec/2014
8Completion Date: Q4:2019
Click here for more details
Details

UK power companies: Local entrepreneurs should bring them to India

May 24: The UK is one of the most advanced countries when it comes to power reforms and use of new technology.
8Here is a complete template of how UK power companies can work in India
8May be this is a good time for Indian entrepreneurs to tie up with these companies to look for unfolding opportunities here
Click on Reports for more Details

Power projects: Business opportunities ahead

May 24: Project Name:Thermal Power Project: Installation of FGD
8Project Cost: 200 crores
8Project Description: The owner has awarded GE Power India a contract for the installation of the FGD system in the 1050 MW (5x210 MW) thermal power project. Earlier, the proponent had informed that the 5x210 MW units were SOx compliant with respect to the new emission norms. However, after the feasibility study, a wet FGD system was planned.
8Project Event: RFQ for the limestone handling and gypsum handling unit is expected by September 2019.
8Expenditure Approval: 2020
8RFQ Date: Sep/2019
8Release Date: Sep/2019
8Start Date: Jun/2022
8Completion Date: 2024
Click here for more details

Project Name: Thermal Power Station - FGD Addition
8Project Cost: 100 crores
8Project Description: The owner along with the consultant TCE has carried out the feasibility studies to install an FGD system in the operating 500 MW unit and DSI system in the remaining 4x210 MW units of a thermal power complex. The project is, however, getting delayed due to pending state clearances. Moreover, TCE is exploring the where to locate the DSI system at site. 
8Project Event: RFQ for the supply of an FGD system is expected to be out by Q4 2019.
8Expenditure Approval: Q1:2017
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2021
8Completion Date: 2022
Click here for more details

Project Name: TPS - FGD Addition
8Project Cost: 200 crores
8Project Description: The owner along with a consultant is carrying out feasibility studies for the installation of a flue gas desulphurisation system in the operating 600 MW power complex out of 1650 MW (5x210+1x600 MW) thermal power plant located in Cuddapah district of Andhra Pradesh. The developer has confirmed that the 5x210 MW units comply with the new norms of the MoEF. Thus, there is no need of installation of FGD in the 5x210 MW units. But, the 600 MW unit commissioned in 2018, need the installation of an FGD system.
8Project Event: RFQ for supply, installation, erection and commissioning of the FGD system is expected by the Q4 2019.
8Expenditure Approval: 2016
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 3000 crores
8Project Description: The owner is planning to sign MoU with the Government of Himachal Pradesh in June 2019 for development of a 355 MW HEP Stage III greenfield hydropower project Preparation of DPR in progress. Geological Investigations (Drilling and Drifting) are under progress. Voyants Solutions Private Limited is carrying out the draft EIA report. Diversion of forest land is under process with concerned DFOs. The SIA study has been awarded to Plan Foundation, for which the field work is in progress. Further bids are expected soon.
8Project Event: RFQ for civil works is expected to be out by Q4 2019.
8Expenditure Approval: 2020
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Super Thermal Power Station Absorber System Package
8Project Cost: 300 crores
8Project Description: The owner is finalizing the price bid for absorber system package in its stage-III (1x500 MW) units out of the 2600 MW (3x200 + 3x500 + 1x500 MW) thermal power complex in the Karimnagar district of Telangana. GE Power India, ISGEC, L&T and Thermax are among those in the race.
8Project Event: The award of the absorber system package is expected by September 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Sep/2019
8Release Date: Sep/2019
8Start Date: Q1:2020
8Completion Date: Q1:2021
Click here for more details

Project Name:Hydroelectric Power Station - Head regulator and Link Canal Project
8Project Cost: 80 crores
8Project Description: The forest clearance at State level is at the final stage. 
8Project Event: Award for rock testing, ground testing, and soil testing contractor is likely to be expected by November 2019
8Expenditure Approval: Q4:2017
8RFQ Date: Nov:2019
8Release Date: Dec:2019
8Start Date: Q3:2019
8Completion Date: 2020
Click here for more details
Details

Our exclusives

May 24: 8The causal link between energy consumption, carbon emissions and economic growth in India A full analysis
8Renewable energy: Continuing to grow  Details
8Ruling: The rate of the late payment surcharge shall be applicable as per the PPA or regulations only Details
8Global energy progress report 2019. A report
8India can capitalize on the declining costs of wind and solar: An analysis
8Electricity supply and demand lies at the heart of India’s energy future: An analysis Details
8Transmission tariffs for FY 2019-20. An analysis
8IndiGrid: Corporate presentation May 2019 Details
8Forecasting CO2 emission by power production mix in India A Report
8Global energy transition to 2050: What needs to be done Details
8Likely Global solar market developments from 2020 to 2023: A Report
8Converting a grid-connected power generation unit into captive status: What kind of regulatory approvals are needed? Details
8Green agenda 2019: Sustainability imperatives for India’s next government Details
8Business opportunities for power companies in the Indian power sector Details 
8The average efficiency of electricity generation from fossil fuels is nearly 40%. How is that so?: An analysis
8How does the power transmission model on long term BOOM (Build Own Operate Maintain) work in India Details
8Fossil fuel-based cogeneration plants are allowed to fulfill their cumulative RPO targets by March 2020 ?  Details
8The Bagasse based power offtake allowed at Rs 3.56/Unit. Details
8Life cycle assessment of a combined-cycle gas turbine with a focus on the chemicals used in water conditioning: A Report
8Scaling up renewable energy (SURE) projects helps India implement clean energy solutions efficiently and effectively Details
You can also click on Reports for more on the above Details

Download Tenders and Newsclips

May 24: For reference purposes the website carries here the following tenders: 
8Tender for procurement of GT Rotor Mid Hollow Shaft at Gas Power Station Details
8Tender for Work of Aresting Oil Leakages from various Power Transformers by Cold welding method Details
8Tender for Procurement of spares for Generator Hydrogen dryer Details
8Tender for Procurement of 24V BOP and SGTG battery banks Details
8Tender for the work of Constructing 15.5km HT ABC Details
8Tender for Providing & fixing of Numerical Distance, Back Up and Differential relays for 220kV EHV lines Details
8Tender for Procurement of Numerical Distance, Back Up and Differential relays for 220kV EHV lines Details
8Tender for the work of construction of 01 No. of Incomer bay for 132/33kV T/F & 01 No. of 33kV Outgoing feeder at 132kV sub-station Details
8Design, Fabrication, Supply ,testing ,Erection & commissioning of LT panel Details
8Supply, testing, installation and commissioning of ABT meters Details
8Supply Of Spare Vacuum Circuit Breakers And Voltage Transformer Trollies Details
8Tender for the Work of Operation & Maintenance of MRHS and transportation of Coal Mill Reject to Reject Yard Details
8Tender for the work of strengthening with material supply of damaged Raw Coal Bunkers Details
8Tender for Purchase of Sliding type Dual Disk Valve Details
8Supply, Installation, Testing and Commissioning of Auxiliary power supply scheme Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Kakrapar Atomic Power plant connected to grid Details
8Greek grid operator launches tenders for $1-bn power link Details
8Coal loans battle Green tide Details
8Australia state says final approvals for Adani's coal mine to be decided within three weeks Details
8CERC Orders Tariff Settlement for a 1.5 GW Hydro Project in Himachal Pradesh Details
8India’s Solar Industry Reacts to Modi Government’s Win in Lok Sabha Elections 2019 Details
8Uttar Pradesh Approves PPA for 14.5 MW of Municipal Solid Waste Projects Details
8Centre looking to ‘insulate’ discoms from payment delays Details
8BHP has no appetite to grow its thermal coal assets: BHP Group CFO Details
8French bank SocGen further reduces business with coal industry Details
8In Vietnam's booming energy sector coal reigns, but renewables play catch-up Details
8Election Results: Renewable energy industry expects govt to sharpen focus on policy stability Details
8Senegal imports turbines for West Africa's first big wind farm project Details
8Montenegro moves to halt small hydro power plants Details
8China to end subsidies for onshore wind power by 2021 Details
8France still to clear EPH's acquisition of Uniper's French assets Details
You can also click on Newsclips for more
Details

Download Tenders and Newsclips

May 23: For reference purposes the website carries here the following tenders: 
8Tender for Running maintenance and overhauling of Main Turbine Auxiliaries Details
8Tender for procurement of GT Stage-3 Stator Vanes & fixing material for Gas Turbine Details
8Tender for Supply of Nylon/Nylon Fiber conveyer belt Details
8Tender for Procurement of Spares of Hydrogen Seal for Generator Details
8Tender for Procurement of set of Worm Shaft and Worm Gear for Coal Mill XRP-763 of TPS Details
8Tender for the Work of servicing & overhauling of 33/22kV VCB Details
8Tender for the Work of Extension of 1.05 kM, 33kV Over Head Line with Laying & Erection of 33kV Underground XLPE cable Details
8Supply, Erection, Site testing & commissioning of 11kV overhead line Details
8Tender for work of testing of EHV grade transformer oil samples Details
8Tender for Supply of three nos of 245kV,800A OIP condenser type bushings for Generator Transformers Details
8Tender for Supply of 100A LT re-wirable type porcelain fuse units Details
8Tender for the work of Rebabbitting of Unit-3 Thrust Pads Details
8Tender for Round the Clock Operation of Main Plant & BOP Equipment Details
8Tender for P-way and S&T Maintenance Services Details
8Annual Rate Contract for Plant & CSR Civil Works Details
8Tender for Procurement of LED street light Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8ReNew Power says India requires double the amount of power supply in next 10-12 years. Details
8Jharkhand Commission Approves PPA for 10 MW of Solar Projects, Details
8Task of procuring wind, solar energy handed over to SECI. Details
8France's Voltalia in exclusive talks to buy Helexia Details
8ElectionResults: Power sector reforms - a new agenda for the new government Details
8Adani's coal hopes look increasingly isolated as BHP joins naysayers Details
8US says Trump coal moves hasten but don't increase emissions Details
8ADB to provide $750 mn loan to India for railway track electrification project Details
8What Modi needs to do to get growth back, push market-reform Details
85th Smart Cities India 2019 expo inaugurated by Durga Shanker Mishra, Secretary, MoHUA Details
8Mining giant BHP says coal outlook 'challenged' Details
8Seeking energy independence, Palestinians open solar power plant Details
8Goa: Solar prosumers await payments Details
8Three-wheelers may have to go electric from FY24 Details
8India proposes electrifying motorbikes, scooters in 6-8 years Details
8Coal India on Rs 10,000 crore equipment buying spree Details
You can also click on Newsclips for more
Details

Jan 01: Details

Our exclusives

May 22: For reference purposes the website carries here the following reports: 
8ABB has introduced a new fusegear with 800V AC ratings to support higher voltage architectures in solar power plants Details
8Wind power generator seeks tariff of Rs.6.33/- per kWhL Regular however pitches for consensus rate, in discussion with offtaker. Details
8Reduction of power production costs in wind power plant: A new way out Details
8Maintenance strategy optimization of a coal-fired power plant cooling tower through generalized stochastic petri nets: An analysis
8High cost of power generation makes a project unviable when third-party sale is involved: An analysis
8Find out how sensitivity of solar power generation to adverse variations in weather conditions as well as panel degradation can negatively impact cash flows Details
8Omegga Power Industry Private Ltd: Ratings withdrawn Details
8An India based power company shares are up as it hedges coal price for up to 60% of coal requirement Details
8Supreme Solar Systems: Rating continues to remain under ‘Issuer Not Cooperating’ category Details
8Establishment of new 400/220 kV substations in northern region: Business development opportunities Details
You can click on Reports for more on the issues above
Details

Jan 01: Details

Software updates: Power projects

May 22: Project Name: Greenfield Hydroelectric Power Project, Stage-1
8Project Cost: 2000 crores
8Project Description: The owner has extended the bidding date for an EPC contract for design and engineering services of main civil and hydro-mechanical works in a greenfield 210 MW (2x80 MW main unit + 2x25 MW auxiliary unit) hydroelectric power project 
8Project Event: RFQ for E&M works worth Rs. 372.78 crores are expected by the Q3 2019.
8Expenditure Approval: Q4:2018
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: 2020
8Completion Date: 2025
Click here for more details

Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 2500 crores
8Project Description: The CEA has vetted the project cost at Rs. 2238 crores. The stage-I forest clearance accorded on 26.02.2018 and stage-II forest clearance is under progress. Construction of boundary pillars for demarcation of forest land is in progress. 
8Project Event: RFQ for design and construction of single-lane steel truss Bridges-IV are expected by June 2019.
RFQ for main plant civil works is expected by the Q4 2019.
8Expenditure Approval: Dec/2018
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: 2020
8Completion Date: 2025
Click here for more details

Project Name: Thermal Power Station - FGD Addition
8Project Cost: 200 crores
8Project Description: BHEL, Tata Power, and L&T have been qualified in the techno-commercial part of the bid for the installation of a flue gas desulphurization system
8Project Event: The award for the FGD package is expected by the Q4 2019.
8Expenditure Approval: Q2:2019
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2021
8Completion Date: 2023
Click here for more details

Project Name: Combustion Modification Package
8Project Cost: 100 crores
8Project Description: The owner has awarded to GE Power -- in the race were ISGEC Heavy Engineering Ltd and Doosan Power System,--  for installation of a combustion modification package for a 1500 MW (3x500 MW)super thermal power plant
8Project Event: RFQ for air compressor, valves and fittings, and ID fans is expected by July 2019.
8Expenditure Approval: Q2:2017
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: Q4:2019
8Completion Date: 2021
Click here for more details

Project Name: Thermal Power Station: Installation of WFGD
8Project Cost: 300 crores
8Project Description: The owner in consultation with NTPC is preparing cost estimate and technical specifications for installation of four wet limestone based flue gas desulphurisation systems 
8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by July 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: 2021
8Completion Date: 2023
Click here for more details

Project Name: Installation of FGD
8Project Cost: 300 crores
8Project Description: The owner is going on with evaluation of bid for installation of FGD in 2x500 MW thermal power station
8Project Event: The award for the flue gas desulphurization system (FGD system) is expected by July 2019.
8Expenditure Approval: Q312017
8RFQ Date: July:2019
8Release Date: July:2019
8Start Date: 2021
8Completion Date: 2023
Click here for more details

Project Name: Thermal Power Station - Installation of new cooling towers
8Project Cost: 200 crores
8Project Description: The owner is preparing feasibility report for installation of new cooling towers in the 3x210 MW  in place of the old cooling towers at the existing facility of 2630 MW (3x210 + 4x500 MW) thermal power station located . The floating of RFQs for supply of new cooling towers is getting delayed due to delay in preparation of DPR. 
8Project Event: RFQ for supply, installation, erection, and commissioning of cooling towers are expected by the Q3 2019.
8Expenditure Approval: Q2:2018
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details
Details

Jan 01: Details

Download Tenders and Newsclips

May 22: For reference purposes the website carries here the following tenders: 
8Tender for Purchase of Different size of Globe Valves for Ash Handling Plant Details
8Tender for the work of Supply ,Laying, testing and commissioning of LT UG cable Details
8Tender for Testing, dismantling & safe carriage of 125 MVA Generator Transformer Details
8Tender for Procurement of Turbine Sealing Ring Details
8Tender for Procurement of Sulphuric Acid Details
8Tender for Procurement of impact and v-return idlers for Conveyor system in CHP Details
8Tender for Procurement of 400kV CT and CVT Details
8Tender for Onsite coating of GT compressor components Details
8Tender for Upgradation of 66kV Substation to 110kV Substation Details
8Annual Rate Contract for repair, rewinding and re-insulation of 6.6 KV motors ranging from 200 KW to 4600 KW Details
8Tender for Rewinding of damaged stators of 0.4 KV LT Motors Details
8Tender for Work of Shifting/Modification of 132 kV D/C line Details
8Tender for Work of Shifting/Modification of 132 kV line Details
8Tender for Work contract for the work of overhauling of 220kV circuit breaker Details
8Tender for Work of Transportation, Winching, Loading & Unloading of Power Transformers Details
8Tender for Purchase contract of Chemical with servicing for cooling water treatment Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8India’s solar dream: Policy reforms, improved execution key to achieving energy transformation Details
8The future of Indian electricity supply: Scenarios of coal use by 2030 Details
8Stress meter: Discoms’ dues to gencos at Rs 3,800 crore Details
8Recharge time for renewable power Details
8BHEL commissions 2 more units of Kaleshwaram irrigation project in Telangana Details
8Two former Ostro executives to set up clean energy firm Details
8India's thermal coal output seen growing 4.3% annually till 2028: Report Details
8Joint Electricity Regulatory Commission issues tariff orders for Union Territories Details
8Vestas takes aim at cheaper U.S. wind power with new turbine Details
8Tata Power Renewable Energy wins Gujarat solar auction Details
8Engie and EDP aim to be second-biggest offshore wind developer with JV Details
8Toshiba, Siemens Gamesa, Blackstone interested in Senvion Details
8Tangedco’s finances head south, reports loss of Rs 7,000 crore Details
8Chandigarh: AAP threatens to launch protest if power tariff hiked Details
858% increase in power transmission capacity of UP in past three years Details
8Polls over, PSERC to announce new power tariff soon Details
8Patchy progress on electricity access casts shadow on global goal Details
You can also click on Newsclips for more
Details

Jan 01: Details

Jan 01: Details

Jan 01: Details

Software updates: Power projects

May 21: Project Name: Yeramarus Super Thermal Power Station: Installation of WFGD
8Project Cost: 500 crores
8Project Description: Raichur Power Corporation Limited, a JV of KPCL, BHEL, and IFCIL is carrying out the bidding process for the development of the wet limestone-based FGD system in the 2x800 MW thermal power project located in the Raichur district of Karnataka. Fichtner Consulting Engineers and STEAG has carried out the design of the FGD equipment. Further bids are expected soon. The pre-bid meeting is expected by the end of May 2019. 
8Project Event: The technical bid date is expected by July 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details

Project Name: Lower Kopili Greenfield Hydroelectric Project
8Project Cost: 1000 crores
8Project Description: The RFQs for an electro-mechanical package in the APGCL's 120 MW (2x55 MW surface power-house + 2x2.5 MW+1x5 MW auxiliary power-house) greenfield hydroelectric project at Longku village, situated in the Karbi Anglong district of Assam is getting further delayed due to clearance pending at the state high-level committee. The civil and hydro-mechanical bids have been floated, and are still under evaluation. Patel Engineering Limited, HCC Limited, Gammon India are among the major contenders in the bid. 
8Project Event: RFQ for engineering, procurement, construction and commissioning of electro-mechanical works is expected by August 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Aug:2019
8Release Date: Aug:2019
8Start Date: Q1:2020
8Completion Date: Q3:2024
Click here for more details

Project Name: Solapur Super Thermal Power: FGD Addition Project
8Project Cost: 500 crores
8Project Description: GE Power India along with sub-contractor Priya Construction is carrying out the RCC works at the chimney for implementation of a Flue Gas Desulphurisation Unit (FGD) in the NTPC's 1320 MW (2x660 MW) thermal power complex in Solapur, Maharashtra. Currently, civil works are under progress. Further bids are expected soon.
8Project Event: RFQ for supply and installation of limestone handing plant is expected by June 2019 by GE Power India.
8Expenditure Approval: Q2:2017
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: Q4:2018
8Completion Date: Q1:2021
Click here for more details

Project Name: Marwa Tendubhata Thermal Power Station - Installation of FGD
8Project Cost: 300 crores
8Project Description: Chhattisgarh State Power Generation Company Limited is preparing technical specifications for installation of a wet limestone based flue gas desulphurization system at its 1000 MW (2x500 MW) thermal power station located at Marwa village, in the Janjgir-Champa district of Chhattisgarh. Development Consultant Private Limited has prepared the DPR for the FGD. Wet Stack will be used instead of GGH. 
8Project Event: RFQ for design, supply, installation, erection, and commissioning of WFGDs is expected by July 2019.
8Expenditure Approval: Q3:2018
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details

Project Name: Rajghat Thermal Power Station - Dismantling
8Project Cost: 200 crores
8Project Description: Indraprastha Power Generation Co. Ltd. is planning to dismantle two plants of 135 MW (2 x 67.5 MW) coal-based thermal power plant in Rajghat, Delhi. The two plants have been shut down since December 2015. Currently, the promoter is approaching the Delhi Government for approval of the dismantling process. 
8Project Event: RFQ for dismantling services of various equipment is expected to kick off by the Q4 2019.
8Expenditure Approval: Q2:2017
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2020
8Completion Date: 2021
Click here for more details

Project Name: Talwandi Sabo Super-Critical Thermal Power Project - Installation of SNCR
8Project Cost: 800 crores
8Project Description: Talwandi Sabo Power Limited is going on with the bidding process of a Primary NOx Emission Control system in the 1980 MW (3x660 MW) super-critical thermal power complex at Mansa, Punjab. The price bid evaluation for the installation of wet flue gas desulphurisation system is under progress in which BHEL, Mitsubishi Hitachi Power Systems India Pvt. Ltd, ISGEC Heavy Engineering Limited, GE Power India Limited, and L&T are the major contenders. 
8Project Event: The award of the FGD package is expected by August 2019.
The award of the Primary NOx control system is expected by September 2019.
8Expenditure Approval: Q3:2019
8RFQ Date: May:2019
8Release Date: May:2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details
Details

Our exclusives

May 21: 8In India, total renewable power investment has topped fossil fuel-based power investment: A report
8IEA's estimates on coal based power investment in India far more pessimistic than reality Details
8India’s transmission outlay in next three years pegged at Rs 30,000 crore  Details
8Energy investment in India has grown the most over the past three years: A report
8Siemens Gamesa: A trusted technological partner for wind power projects Details
8Scheduling and dispatching details of adani solar power project in Tamilnadu Details
8Business opportunities in outages: Get details of what is coming up 
8Ceiling on compensation for the delay in releasing connections to all consumers in the license area shall be twice of the service connection charges deposited by that consumer, clarifies regulatory body Details
8If tariff is frozen under a PPA, revision of tariff possible only under a new PPA Details
8India is projected to invest $44.9bn in smart metering, distribution automation, battery storage and other smart grid market segments over the next decade: A report
You can also click on Reports for more
Details

Jan 01: Details

Download Tenders and Newsclips

May 21: For reference purposes the website carries here the following tenders: 
8Tender for Maintenance Contract for preventive and breakdown maintenance of C&I systems of Boiler Details
8Tender for Rate Contract of Emergency, Breakdown & Maintenance in CHP Details
8Tender for Supply of Tubular Protectors & 'U' Clamps for the Boiler Details
8Tender for Testing, dismantling & safe carriage of 125MVA Generator Transformer Details
8Tender for manufacture, testing, supply and delivery of 3ph 4 wire LT CT operated DLMS compliant Bulk Consumer energy meters Details
8Tender for Purchase of Spares for 220KV SF6 Circuit Breakers Details
8Tender for Procurement of Cyclone Separators for Cooling water System and Shaft seal system Details
8Tender for Purchase of Miscellaneous Turbine Items Details
8Tender for Interlinking 11kV line by drawing ABC and 11kV OH line Details
8Tender for Drawing covered conductor through existing Pullu and Panthode double circuit feeder Details
8Tender for Interlinking Feeder using 1.2Km Covered Conductor Details
8Tender for the work of Supply ,Laying, testing and commissioning of LT UG cable Details
8Annual maintenance & attending emergency breakdown work of 400 KV Transmission Lines Details
8Tender for De-watering pump along with motor Details
8Tender for Procurement of Micro-Controller based Battery Chargers Details
8Tender for Technical Audit of earthing & lightening system of entire plant Details
8Tender for Procurement of Submersible Dewatering Pump Details
8Tender for Procurement of Conveyor Belt for CHP Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8CERC tariff relief for IPPs positive for power gencos: ICRA Details
8Kakrapar nuclear power reactor to be synchronised with grid next week Details
8Uday scheme: Discoms drift back to old ways, key targets missed Details
8Adani Green Energy's 8.75 crore shares to be offered for sale on Tuesday Details
8Court questions Punjab, Haryana on free power to rich farmers Details
8Power sector's outstanding regulatory assets at Rs 76,963 crore Details
8Australian election results bode well for Adani’s coal mine project Details
8Vestas receives 249 MW order from EDF Renewables Details
8Petronas’ subsidiary Amplus Solar to invest Rs 750 crore in Haryana Details
8Oriano completes 9 projects for Cleantech Solar across multiple states Details
8Adani Green Energy, ReNew Power only bidders in hybrid auction Details
8ISA delegation to explore Cochin airport's solar power project as success model Details
8Ashok Leyland ready to ride on Elon Musk's India dream for EVs Details
8New layouts to reserve 0.5% land for power infrastructure Details
8Mahagenco sets a new record for power generation, crosses 10,000 Mw mark Details
You can also click on Newsclips for more
Details

Jan 01: Details

Software updates: Power projects

May 20: Project Name: Guru Hargobind Thermal Power Plant - Installation of FGD
8Project Cost: 400 crores
8Project Description: Punjab State Power Corporation Limited along with consultant NTPC has prepared the technical specifications for installation of wet limestone based flue gas desulphurisation system in the operating 920 MW (2x210+2x250 MW) thermal power plant located in the Lehra Mohabbat district of Punjab. 
8Project Event: RFQ for design, engineering, supply, transportation, installation, erection, and completion of an FGD package is expected by July 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Suratgarh Thermal Power Station - FGD Addition
8Project Cost: 300 crores
8Project Description: Rajasthan Rajya Vidyut Utpadan Nigam Limited along with consultant Fichtner Consulting Engineers Limited is carrying out investigations in order to clarify whether to install an FGD system or a DSI system in its operating 1500 MW (6x250 MW) Thermal Power Station at Suratgarh, in Sri Ganga Nagar district of Rajasthan. Meanwhile, tenders are ongoing for the 2x660 MW under- construction Suratgarh supercritical thermal power project. 
8Project Event: RFQ for design, supply, installation, and commissioning of an FGD is expected to be out by the Q4 2019.
8Expenditure Approval: Q3:2017
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Gas Based Combined Cycle Expansion Power Project
8Project Cost: 3500 crores
8Project Event: RFQ for an EPC contractor for the main plant works is expected by August 2019.
8Expenditure Approval: Q3:2019
8RFQ Date: Aug/2019
8Release Date: Aug/2019
8Start Date: Q3:2020
8Completion Date: Q4:2023
Click here for more details

Project Name: Tanda Thermal Power Expansion Project
8Project Cost: 10000 crores
8Project Description: National Thermal Power Corporation Limited along with ESP contractor BHEL is carrying out erection works for the 1320 MW (2x660 MW) super-critical thermal power expansion project at its existing facility, where a 440MW plant was installed, at Tanda Thermal Power Station. 
8Project Event: RFQ for limestone handling plant and gypsum handling unit for the FGD system is expected by the Q3 2019.
8Expenditure Approval: Sep/2014
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: Oct/2015
8Completion Date: Q4:2019
Click here for more details

Project Name: Shree Singaji Super-Critical Thermal Power Brownfield Project (Stage-II)
8Project Cost: 7500 crores
8Project Description: Madhya Pradesh Power Generating Company Limited is carrying out the price bid evaluation of an EPC contractor for the FGD system package for the 1320 (2x660 MW) super-critical brownfield thermal power complex at the existing 1200 MW (2x600 MW) facility located at the Dongalia village, in the Khandwa district of Madhya Pradesh. L&T, GE Power India, Mitsubishi Hitachi Power Systems India Pvt Ltd, Doosan Power Systems India Pvt Ltd, and ISGEC Heavy Engg. Ltd is the major contenders in the race. 
8Project Event: The award of the FGD system package is expected by June 2019.
8Expenditure Approval: 2014
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: 31/Dec/2014
8Completion Date: Q4:2019
Click here for more details
Details
  • May 15: Software updates: Power projects:Details
  • May 15: Download Tenders and Newsclips:Details
  • May 14: Power Project: Greenfield Hydro Power Project planned:Details
  • May 14: Download Tenders and Newsclips:Details
  • May 13: Power projects: Know where your business opportunities are, going ahead:Details
  • May 13: Download Tenders and Newsclips:Details