All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Sep 2026

8A servo-motor repair at Kerala’s 340 MW Sabarigiri hydro station finished about 19 hours ahead of its approved outage and preserved an estimated 17.59 MU of generation worth Rs 8.79 crore, KSEB says.
8The intervention also addressed a valve defect that could have caused severe hydraulic damage and a prolonged unit outage. Details
8Serentica Renewables has 6.8 GW of contracted renewable capacity but still must deploy about Rs 22,700 crore as 3.6 GW remains under construction.
8Its storage headline is also much larger than its operating base: roughly 2 GW is planned or contracted, while only 50 MW was operational in the rating record. Details
8Uttar Pradesh Power Corporation says it has credited Rs 32.75 crore to 92,231 smart-meter consumers after irregular charges were identified.
8The regulator accepted the verified refund position but ordered a two-month replacement roadmap for 907 older prepaid meters that were excluded because those accounts had not been charged. Details
8SAEL Solar P6 has lost its bid for unrestricted energy banking and complete exemption from banking, transmission and wheeling charges for a captive solar project in Uttar Pradesh.
8The regulator held that project-specific relief would shift costs to other consumers and preserved only the 50% network-charge concession available under state policy. Details
8Karnataka’s electricity regulator has rejected a request to postpone industrial outage compensation for three years.
8Eligible high-tension factories must receive demand-charge relief when monthly interruptions breach the approved limit, with the cost assigned to the distribution company or recovered from the transmission utility according to who caused the outage. Details
8Indowind Energy is asking shareholders to approve a related-party purchase worth up to Rs 57.80 crore—143.31% of its FY2025-26 consolidated turnover.
8The proposed seller is promoter Bala Kutti, and the asset is a 20% stake in EPC contractor Everon Power, putting both valuation and conflict controls at the centre of the vote. Details
8A construction consortium has secured a Rs 392.31 crore arbitral award against NHPC for the 2,000 MW Subansiri Lower hydropower project, less than half its Rs 796.87 crore claim.
8NHPC says the award can enter project cost and be recovered through tariff, a position that still depends on regulatory treatment rather than the tribunal alone. Details
8Fujiyama Power Systems says a May fire affected assets carrying approximately Rs 143.6 crore and temporarily stopped operations at its 1.3 GW lead-acid battery plant in Bawal.
8Insurance and outsourced production may contain the disruption, but neither the final physical loss nor the insurance recovery has yet been established. Details
8Sagardighi’s new 660 MW unit reported unaudited pre-commissioning fuel cost of Rs 9.767 a unit while its infirm power was billed at Rs 1.78.
8The West Bengal regulator has allowed the resulting net cost to be capitalised, placing a Rs 186.01 crore short recovery inside the project-cost account rather than the electricity sale. Details
8A Rs 1,088.91 crore expansion of Data Center Holdings India’s Airoli park has been deferred after the company said it had not obtained fire approvals for two proposed buildings.
8The same proposal carries 209 MW of demand and 189 diesel generator sets, making the missing approvals material to a very large new electricity load. Details
8India’s monitored state-sector hydro stations generated 7,156.98 GWh in August 2026, 30.7% below the 10,322 GWh programme and 34.6% below August 2025.
8The shortfall is broad enough to matter for system balancing: the monitored fleet covers 27,524.94 MW, so this is not a single-station outage dressed up as a national trend. Details
8A new 6 GW export route from Rajasthan’s Barmer solar zone carries annual transmission charges of Rs 3,244.33 crore and a roughly 1,000-km high-voltage direct-current line across three states.
8The scale makes the award more than another evacuation project: it commits users to one of the country’s largest recurring transmission bills while concentrating delivery risk in a single interstate corridor. Details
8India’s monitored coal plants hold 49% of normative stock with 45 stations critical Details
8IEX day-ahead demand reaches 805,933 MWh as offered supply falls to 258,699 MWh
8IEX real-time price jumps 23% as scheduled volume falls 63% in one day
8India’s grid spends 9.67 hours outside its frequency band as low-frequency time dominates
8More than 60.6 GW of monitored generation is unavailable as forced outages lead
8Raigarh Pugalur’s missing reverse mode could remove about 3,000 MW of southern export capability
8A Pothencode insulator failure blacks out the 220 kV station and cuts about 300 MW
8All four Kadamparai pumped-storage units are out on stator and rotor earth faults
8Fifteen southern substations breach the transformer N minus one loading test
8Northern ancillary and SCUC settlements total Rs 111.90 crore for one week
8Bongaigaon’s August SCED adjustment returns Rs 3.74 crore to the regional pool
8North Eastern SCUC settlement reaches Rs 1.69 crore for the latest weekly account Details
8QPower defers Winwin-linked securities issue while funding mode and due diligence remain open
8Shera commits up to Rs 3.52 crore to captive solar vehicle and approves related-party PPA
8Kirloskar Electric directs entire Rs 40 crore preferential issue to working capital and debt
8Hitachi Energy India’s independently assigned ESG score rises eight points to 69
8Servotech seeks five-year MD term with pay capped at Rs 3 crore annually
8KPI Green’s finance chief leaves weeks after resigning, with no successor named
8KPI Green subsidiary changes auditor to BDO firm but reports no management concern
8PTC’s cross-border trade jumps 37% as Bhutan dry-season supply rises 77%
8GK Energy shareholders approve a higher borrowing limit without disclosing the new ceiling
8Mahanadi Coalfields files an offer for sale covering up to 661.8 million shares
8ReNew’s 100 MW Tamil Nadu solar project carries 128 debtor days and Rs 228 crore debt
8Hexa’s Solapur captive solar plant beats its P90 output case but leverage remains above 6.5 times Details
8Rajasthan opens four separate 500 MW October auctions with no ceiling price
8West Bengal seeks 200 MW of high-price evening power without a ceiling
8SECI awards 1,500 MW peak renewable supply after bids total 5,605 MW
8Indowind pushes Rs 21.5 crore solar deadline after domestic-module rule causes two-month delay
8Andhra Pradesh seeks four-hour batteries equal to half each participating renewable plant Details
8NIDP seeks short-term round-the-clock renewable power as its RPO remains in deficit
8Madhya Pradesh offers 30% theft-case reduction and waives all accrued interest
8Uttar Pradesh cuts Rosa Power’s five-year fixed-cost claim by Rs 50.89 crore
8West Bengal secures up to 351.155 MW from Bhutan with tariffs rising to Rs 7.67
8DVC secures up to 137.5 MW from Bhutan under the same escalating hydro tariff
8BRPL’s computed fuel surcharge reaches 57.13% while the July levy remains unstated
8Noida Power seeks approval for 300 MW round-the-clock renewable supply with storage
8Noida Power asks to procure 100 MW thermal supply under the SHAKTI framework
8B and G Renewable’s power agreement dispute moves toward arbitration review in Uttar Pradesh Details
8CERC allows Nathpa Jhakri fixed charges up to Rs 1,693.49 crore by 2028-29
8CERC grants 90% interim tariff to Nalagarh transformer after a 57-day delay
8CERC grants 90% interim tariff to Hassan transformer after a 100-day delay
8CERC grants interim tariffs after eastern reactors arrive 178 and 351 days late
8CERC rejects AMNS transmission fee waiver despite Rs 353.68 crore claimed financial stress
8CERC reopens Greenko bay interest costs that an earlier order had rejected outright
8CERC adds filing, licence and dispatch-fee recovery rights to DVC’s tariff order Details
BHEL seeks GIS OEM for DTL Tikrikhurd on a seven-day window and a conditional order
8BHEL is inviting a tender-specific pre-bid tie-up for 82 bays of 400/220/66 kV GIS at DTL's Tikrikhurd substation, with bids closing 9 September, seven days after issue.
8The selected OEM must hold prices for 180 days, sign an MOU, lodge a 1% bid bond and accept a 60-month defect period, yet receives a purchase order only if BHEL wins the DTL package.
8The sharper exposure is a stray Gopalpur/400/220/33 kV reference inside the operative NIT, leaving project identity unresolved in a document that rejects deviations.

 

AEGCL bundles two 400 kV lines and Agia GIS into one JV-barred package for 3,200 MW evacuation
8AEGCL has invited bids for an indivisible turnkey package covering the Chapar–Rangia and Chapar–Agia Quad Moose lines, a new 400/220 kV Agia substation and Rangia bay extensions, with Rs 24 crore bid security.
8Bidders must show Rs 2,500 crore average turnover, 400 kV GIS credentials and 100 circuit km of 400 kV line experience in a single Assam project, with no joint-venture route and fixed prices over 36 months.
8The unresolved issue is an EMD instruction the portal marks exemptible while the BDS bars digital deposit and disapplies the exemption clauses.

 

WAPCOS Moran River DPR tender carries three completion clocks and an arbitration clause that cancels itself
8WAPCOS has re-issued a Rs 17.70 lakh GeM bid for architectural design and a technical-sanction-ready DPR covering 20 riverfront components at Khadgada, Dungarpur, closing 16 September.
8The consultant must field a 15-year lead architect and deliver coordinated architectural, structural and MEPF designs while WAPCOS pays back-to-back, retains 2.5% from running bills and holds a 5% ePBG for eight months.
8Completion is stated as two months, 60 days from award and 21 days from agreement, and arbitration is both promised and excluded, leaving schedule and forum unsettled.

 

AEGCL's Chapar evacuation tender adds ±15% quantity swing and a next-lowest-bidder step-out to firm pricing
8The 36-month turnkey package treats quantities as provisional within ±15% of contract price while keeping the price firm and deeming unlisted completion items included. GIS carries a second security of 20% of ex-works cost for five years beyond the defect period, alongside an unreduced 10% performance security, 60-day payment terms and no interest on delay.
8AEGCL's right to transfer unfinished work to the next-lowest tenderer raises the harder question of how an integrated system can be split mid-execution without responsibility gaps.

 

BHEL's Tikrikhurd GIS tie-up layers 10%, 2% and 10% guarantees on a zero-EMD tender
8The OEM must supply 82 bays and 5,200 m of 400 kV GIB within 21 months, then supervise commissioning within nine, under a 60-month defect period extendable to 84 plus a five-year latent-defect tail.
8Beyond a 10% BHEL security and 2% DTL guarantee, Route-2 and Route-3 manufacturers post another 10% from collaborators, while items marked "NA" but later needed must be supplied free.
8The type-test and PQR reference date of 18 August predates BHEL's own 2 September invitation, compounding the Gopalpur language and an undisclosed downstream price-sharing formula.

 

NTPC's Rs 300-crore Gadarwara ash contract empanels six agencies but guarantees none a purchase order
8NTPC is seeking slab-wise rates for excavating, loading and hauling pond ash up to 300 km to NHAI and PMGSY sites during FY 2026-27, with a Rs 50 lakh EMD and AST-01 enlistment as the entry gate.
8Up to six L1-matching contractors are each capped at Rs 50 crore, must fit AIS 140 GPS with API access and submit geo-tagged trip evidence, while aggregate value may fall by 100%.
8With one uniform premium across six distance slabs plus excavation and loading, the real exposure is financing a mobilised fleet against volumes NTPC is free to withhold.

 

NSPCL closes 123-day extension chain on Durgapur pulveriser R&M with spares restored from three to 24
8After 12 deadline revisions, NSPCL has declared 8 September final for bids to replace eight coal pulverisers across two 60 MW units at Durgapur PP-II, with a Rs 1 crore EMD.
8Amendment 4 reversed Amendment 2 by restoring 24 pump assemblies in mandatory spares, while Amendment 3 added dual instruments for CLCS and protection duties.
8Bidders who priced on the interim three-pump requirement face an eightfold quantity correction inside a brownfield package whose completion period, LD and PBG remain unstated.

 

SECI fixes turbine coordinates yet leaves the wind contractor liable for a SCADA platform another package owns
8SECI is procuring a 45.6 MW ISTS-connected wind project at Ramagiri plus ten years of O&M, evaluated on EPC price plus O&M NPV at 8.30% before an e-reverse auction.
8The contractor must commission within 14 months, hold 96–98% availability, keep 5% security through the tenth O&M year and integrate its LCS with a CMCS, PPC and grid-compliance study delivered by the solar-plus-BESS contractor.
8LD switches from the uncommissioned portion to 5% of total contract price after ten weeks, while the O&M price workbook still describes the asset as a solar-plus-BESS project.

 

UJVN's Sirkari Bhyol E&M tender reaches 20th extension after estimate climbs 53.3% to Rs 243.05 crore
8The 3×40 MW Francis-turbine package at Munsyari now closes 10 September, 255 days after its original December 2025 deadline, with EMD raised twice to Rs 5.7385 crore.
8Seven addenda widened experience to 15 years, cut the generator threshold to 35 MVA, admitted surety bonds and switched guide bearings from water to oil lubrication.
8Additional security on borrowed credentials rose from 3% to 5% and validity stays at 270 days, so bidders must price against an unconsolidated trail of 23 corrigenda.

 

NREDCAP's 15 MW Vijayawada WtE concession bids on lowest grant with a Rs 19.99-crore security stack behind it
8The 22-year DBFOT project, costed at Rs 324.70 crore, seeks developers with 800 TPD single-facility or two 500 TPD waste-to-electricity references and Rs 81.17 crore net worth.
8The selected bidder posts Rs 16.24 crore to the municipal authority and Rs 25 lakh/MW to APDISCOM, with the O&M-qualified consortium member locked in for the full term.
8Portal text dispenses with originals at evaluation while Clause 27.2(c) makes their receipt by bid date a responsiveness condition, leaving rejection risk unresolved.

 

SECI's bulk-consumer EOI shifts pre-bid meeting three times without touching the 15 September deadline
8SECI is inviting AAA-to-BBB+ rated consumers with 50 MW-plus demand to disclose load, credit and land data for solar, wind, hybrid, FDRE, RTC, BESS and PSP procurement under captive, group-captive, JV and PMC structures.
8SECI proposes to handle land, connectivity, EPC selection, financing and O&M for up to 25 years, while respondents bear all participation cost under a non-binding framework.
8The final meeting notice dropped the public time and link, and tariff, curtailment, change-in-law and payment-security terms remain wholly undefined.

 

TPTL inserts 27-page CFC-HTLS spec four days after publishing Rs 18.38-crore 132 kV LILO tender
8The corrigendum fixes an 800 A carbon-fibre-core conductor, 7.0 m sag at 320 m span and loss-capitalised evaluation at Rs 3,30,220 per kW for 43.8 km of reconductoring beside a live circuit.
8The contractor absorbs tower-load checks, type-test costs, damage restoration and railway crossings without assured shutdowns, with bids now closing 14 September after a 12-day extension.
8Section II's "ten percent (3%)" performance-guarantee wording and the 800 A/437 A sag mismatch remain uncorrected.

 

DVC's 1x800 MW Durgapur BOP package moves 38 days across four corrigenda with two-unit completion text intact
8DVC's international EPC tender for FGD, chimney, coal and ash handling, a 7 km raw-water system, 400/220 kV GIS, DCS and ZLD now closes 24 September, with bid security of Rs 25.69 crore or USD 2.72 million.
8Bidders need Rs 1,250 crore average turnover and face 10% performance security plus a 2% consortium integration guarantee, with LD at USD 106,610 per day capped at 5%.
8BDS Item 9.0 still reads "44 & 48 months for Unit 1 & Unit 2" against a single-unit SCC, leaving the LD baseline dependent on interpretation.

 

Four bidders clear technical stage in DHBVN's Rs 118.78-crore Hisar SCADA DMS infrastructure package
8Agarwal Traders, Century Infrapower, Gawar Construction and RP Infrapower were admitted after two extensions moved closing to 3 August for 11 kV augmentation, feeder bifurcation, RMUs and VCBs.
8Corrigendum-I shifted location approvals and final inspection from the Smart Grid Project wing to the nodal officer and operation wing, and assigned FRTU and DCP supply to the separate SCADA agency.
8Additional security climbs to 24% for bids 24% below estimate, and delay attribution where RMUs wait on another agency's automation kit is unallocated.

 

Five bidders admitted to DHBVNL's Rs 157.83-crore 33 kV augmentation tender carrying two EMD figures
8Agarwal Traders, Century Infrapower, Gawar Construction, Laser Power & Infra and RP Infrapower cleared technical evaluation on 7 August for turnkey augmentation of 72 operating substations within 12 months.
8DHBVNL may interchange substations without time relief, requires approval of all non-labour subcontracts and has raised TPQMA inspection of augmented substations from 5% to 100%.
8The NIT and portal set EMD at Rs 3.16 crore while the SBD summary says Rs 1.55 crore, and no hierarchy resolves the difference.

 

PwC wins MPPTCL S/4HANA migration 35.8% below Deloitte as comparative sheet multiplies contract value
8PricewaterhouseCoopers is L1 at Rs 297.4608 crore against Deloitte's Rs 404.0366 crore for ECC-to-S/4HANA conversion under RISE with SAP, five years of licences, legacy support and hypercare.
8The RFP directs evaluation on GST-inclusive Item H—Rs 104.47 crore versus Rs 141.89 crore—but the published total sums components, subtotal, GST and total together.
8L1 priced migration at Rs 14.39 crore against Rs 36.65 crore and ECC support at Rs 6 lakh against Rs 6.54 crore, while Corrigendum-5 deleted VAPT from scope.

 

WBSETCL adds 120 days to 43-transformer delivery programme and hardens split into 26:17
8The 80 MVA, 132/33 kV package with NIFPS and spare RIP bushings now closes 10 September, with the first eight units due at 300 days instead of 210 and completion at 600 days.
8Bidders face H1 elimination before reverse auction, 10% additional security if L1 falls at or below 80% of estimate, a 60-month defect period and 5% security retained after supply.
8The second supplier receives 17 units only at the L1 price, leaving open whether price-matching reproduces the delivery risk the extension sought to cure.

Details
  For reference purposes the website carries here the following tenders:
 
 
8Tender for replacement of pipe line of mulsifire system at 220kV S/S Details
  
8Design, detailed engineering manufacture supply of 220kV single core 1200 SQMM copper conductor Details
  
8Design, detailed engineering manufacture supply of 220kV single core 2000 SQMM copper conductor Details
  
8Tender for civil works related to construction of 33 kV bay Details
  
8Tender for construction of 132 kV open GIS bay at 220 kV substation Gola, Gorakhpur Details
  
8Tender for construction of 132 kV open GIS bay at 220 kV substation Details
  
8Tender for construction and commissioning of 02 no. 132kV GIS feeder bay (outdoor) (for 132kV Sahjanwa TSS) at 220kV substation Details
  
8Tender for construction of 132 kV SC line on Zebra conductor Details
  
8Tender for construction of 02 Nos. 132kV AIS feeder bay at 220kV substation Details
  
8Tender for storm water drain restoration Details
  
8Tender for replacement of damaged sewer line Details
  
8Tender for construction of new trench covers pre-cast for covering cable trench Details
  
8Tender for supply of spare for bosch make loudophone at switchyard Details
  
8Tender for civil works for extension of 12 store yard including supply and installation of rails, DSLs etc Details
  
8Tender for supply of AAAC rabbit and Dog conductor Details
  
8Tender for annual work contract for providing assistance in day to day work of fire fighting cell unit Details
  
8Tender for procurement of spares for air compressor installed Details
  
8Tender for procurement of spares for pumps installed Details
  
8Tender for supply of steel and fabrication work of platform for inspection and maintenance of various hoists installed Details
  
8Tender for supply, installation commissioning, & testing of soft starter with major/minor modification in existing panels Details
  
8Tender for supply of coal pipes Details
  
8Tender for procurement of T and P (welding sets) Details
  
8Tender for provision of 50Mbps and 100Mbps optical fiber based internet lease line Details
  
8Tender for foundation and erection of yard structures with 2 Nos of 5MVA 33/11kV transformers Details
  
8Tender for construction of compound wall and site leveling at proposed 33kV substation Details
  
8Tender for fabrication of lattice structures Details
  
8Tender for supply of various sizes of M S ERW pipes and bends Details
  
8Tender for work of design, supply, erection, testing and commissioning of new generator relay panels Details
  
8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes of various Details
  
8Tender for work of removal, supply and application of spray thermal insulation on drive turbines Details
  
8Tender for supply of refrigerant gas mafron R-22 and R-134a in cylinders for air conditioning plants Details
  
8Tender for urgent job for inspection and maintenance of control valves and governing system and inspection of bearings of turbogenerator -2 Details
  
8Tender for AMC of instrumentation system in RCPH and cooling towers Details
  
8Tender for biennial maintenance contract for ash dyke Details
  
8Tender for RC for construction of drill sites Details
  
8Tender for procurement of HSD for bulk supply Details
  
8Tender for annual maintenance contract for three years for top drive systems installed Details
  
8Tender for supply of complete assembly of intake screen including SS wire mesh, SS fasteners with washer for CW pump Details
  
8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing open conductor 11 KV lines Details
  
8Tender for supply of 33kV CT with junction box Details
  
8Tender for implementation of transmission infrastructure to evacuate 3200 MW thermal power from upcoming generation station Details
  
8Tender for in situ erosion resistant coating of boiler tubes Details
  
8Tender for providing MDF panelling Details
  
8Tender for construction of 33 kV sub station Details
  
8Tender for supply of surge arresters types of 11kV sub station Details
  
8Tender for R /B/ C maintenance as well as operation of central AC plant, passenger elevators lifts, package/chiller units Details
  
8Tender for supply of positive material identification (PMI) analyzer Details
  
8Tender for providing of retaining wall in tower 33 of 220 kV D/C transmission line Details
  
8Tender for work of aluminium and zinc chromat/phosphate based painting of rusted tower structure of 133 kV S/C transmission line Details
  
8Tender for RFP for procurement of consultancy services for preparation of detail Survey DPR estimate for intra state transmission Details
  
8Design, engineering, supply of materials equipments erection testing and commissioning of 02 Nos. of 132 kV line bay at 132/33 kV grid substation Details
  
8Tender for work of turfing and other miscellaneous work of 132kV and 33kV switchyard Details
  
8Tender for supply of tapping channel cross arm Details
  
8Tender for supply of 3.5 V cross arm Details
  
8Tender for procurement of guarding cross arm Details
  
8Tender for annual maintenance work testing of various water samples collection and testing in RO cum DM plant SWAS panel Details
  
8Tender for supply of LT single phase angle cross arm Details
  
8Tender for engagement of TPSA ,third party sampling agency for collection, preparation and chemical analysis of coal Details
  
8Tender for annual maintenance contract of cisco routers installed Details
  
8Tender for attending leakages/seepages in various underground structures Details
  
8Tender for work of providing expert NDT level II services for inspection and various quality checks during the overhauling of units Details
  
8Tender for Bi-annual maintenance & attending emergency breakdown work of 400kV transmission lines Details
  
8Tender for enhancement of transformation capacity of substation by addition of 1x50MVA, 220/33kV PTR along Details
  
8Tender for enhancement of transformation capacity of substation by replacement of existing 2x25MVA, 220/33kV PTR Details
  
8Tender for work of providing and fixing of high voltage busbar insulation tape, and heat shrinkable busbar insulating tubing Details
  
8Tender for work of providing & fixing of additional jumpers on tension towers of the various lines Details
  
8Tender for annual contract for procurement/ commissioning of air conditioners Details
  
8Tender for AMC for the work of servicing/ overhauling/repairing of ER make OLTC of various capacities’ ICT & power T/F Details
  
8Tender for work of providing & fixing of counter poise & pipe type earthing for 400kV transmission lines Details
  
8Tender for work of providing & fixing of 22/33kV bay equipment’s for readiness of bays at various S/Stns Details
  
8Tender for ARC for supply erection and commissioning of of GI cable tray Details
  
8Tender for Bi- annual rate contract for work of erection of 66kV transmission towers Details
  
8Tender for ARC work of work of erection of 66kV equipment, structures, control wiring Details
  
8Tender for hot line stringing of 66 kV line Details
  
8Tender for supply, installation and commissioning of 60TR screw compressor chiller AC package Details
  
8Tender for supply of various CDS tubes and bend for drain & vent line for boiler Details
  
8Tender for work of misc pressure part related activity of boiler stage Details
  
8Tender for repairing/retrofitting/renovation of raw water pump house Details
  
8Tender for supply of LTSH and economizer coils for boiler stage Details
  
8Tender for BRC for work of rewinding and overhauling of 11kV HT motors Details
 
You can also click on Tenders for more
  For reference purposes the website carries here the following newsclips:
 
8JSW Neo Energy Joins Bidding For Actis' 4 GW BluPine Energy Platform Details
 
8India soon to be 3rd largest wind energy player: Govt official Details
  
8SAEL wins 1 GWp of solar PV module supply orders in six months Details
  
8Share of electricity in India's overall energy mix to reach 45-50 pc by 2047: Official Details
  
8Renewable Energy for Airports: A Quiet but Growing Trend Details
  
8Solar Encapsulant Demand Surges Amid India Module Growth Details
  
8Govt has data for offshore wind sites, but high costs slow progress Details
  
8Power Grid wins Barmer HVDC transmission project, positive read through for GE Vernova T&D, Hitachi Energy and Siemens Details
  
8Inox Wind secures Rs 755 crore order from Indian Oil Corporation Details
  
8Stocks making the big moves midday: Coal India, Vodafone Idea, IndiGo and more Details
  
8India needs unified ministry for energy security Details
  
8Motilal Oswal Initiates Adani Power Coverage With Rs 250 Target Details
  
8India must double electricity's share in energy mix by 2047 to meet net zero goals: CEA Chief Details
  
8Power Sector Investments to Drive 100–200 bps Revenue Growth for Large EPC Companies: CRISIL Ratings Details
  
8India’s power demand is surging, but some solar energy is going to waste Details
  
8Stock Picks Today: Infosys, Tata Power, Adani Ports, Nykaa, RBL Bank, And More On Brokerages' Radar Details
  
8India And Germany Strengthen Energy Cooperation For Sustainable Development Details
  
8Adani finally explains why Godda power supply to Bangladesh has dropped Details
  
8Private players seek ‘green energy’ status for N-power to raise funds Details
  
84 Power Stocks with Strong Future Roadmap Details
  
8CG Power Set For BIS Waiver As Govt Plans Exemption From Mandatory Quality Certification Details
  
8Energy Regulation Is Becoming Central To Deal Strategy: Ashutosh K. Srivastava Details
  
8India Targets 100 GW of Nuclear Capacity by 2047 as Green Finance Excludes It Details
  
8Coal India's Pivot to Gasification: Will it Create Wealth Details
  
8BSE Utilities index up 1%; JSW Energy, Torrent, Tata Power rally up to 4% Details
  
You can also click on Newsclips for more Details
8The number of Indian power plants classified with critical coal stock reached 52 on Aug 31, 2026, covering 68,027 MW.
8The plant-level workbook also shows daily coal consumption exceeding receipts, extending the aggregate drawdown visible in the preceding Energyline edition. Details
8Juniper Green Energy says it has won a firm renewable contract designed to mimic thermal generation, adding a new commercial layer to a portfolio already moving heavily into batteries.
8The award is new, but its power-purchase agreement had not been signed when management spoke. Details
8Tata Power’s Mundra compensation case has become a document-and-method dispute after Gujarat’s buyer challenged the evidence behind coal, transport and profit adjustments.
8The Central Electricity Regulatory Commission has kept the matter part-heard for Sept 10, 2026. Details
8Jharkhand’s regulator has raised Tata Steel’s FY2024-25 aggregate revenue requirement by Rs 92.40 crore after correcting its treatment of surplus-power revenue and accepting a small change in distribution loss.
8The revised ARR is Rs 1,518.81 crore. Details
8Maharashtra’s regulator has granted licences and adopted tariffs for five competitively bid transmission schemes spanning Pune, Solapur, Nagpur and the Mumbai region.
8Their adopted annual transmission charges total about Rs 649.38 crore, creating a material long-duration cost stream for the state grid. Details
8JSW Energy has moved a 2,400 MW expansion at Salboni into environmental studies, but the appraisal panel attached fresh baseline and land-use work to its recommendation.
8The proposal would lift the West Bengal complex from 1,600 MW to 4,000 MW. Details
8A central environmental panel has returned Vedanta’s proposal to add four 800 MW units at Korba after finding that the application did not reconcile its land, ash, water, evacuation and safety case.
8The return keeps a 3,200 MW expansion from entering baseline studies on the record supplied. Details
8India’s solar manufacturing build-out is moving faster than the market that must absorb it.
8An industry study puts module capacity at 233 GW in June 2026, but estimates utilisation at only 35–40% and identifies 45–50 GW of capacity as vulnerable to consolidation or disruption. Details
8Northern evening shortage reaches 2,254 MW while three regions stay near balance
8Grid frequency misses its preferred band for 30% of the day as ER–NR constraints persist
8Telangana reservoir-energy equivalent almost halves from a year earlier
8July SCED pool refunds exceed collections by Rs 37.51 crore
8Western transmission charges rise in five of six states as AMNS bill jumps 25%
8Western reserve and commitment accounts produce Rs 80.52 crore net receivable
8Uttarakhand records an 11.66 MU August energy shortfall despite net purchases
8Day-ahead prices rise 17% as purchase bids surge and cleared volume falls
8India’s conventional generation swings from a daily miss to a 16.76 MU surplus Details
8Adani Power wins AA+ upgrade across Rs 80,500 crore of rated instruments
8Coal India raises supplies while August auction buyers take only 39% on offer
8BCCL’s five-month output remains 18% lower despite firmer August coking coal
8India Power’s creditors approve insolvency entry criteria and invite expressions of interest
8HPL’s Rs 3,200 crore smart-meter book offsets a weak metering revenue year
8Techno Electric’s Rs 9,567 crore order book comes with a receivables surge
8IRCON’s income falls 16% as debtors turn more slowly and borrowing returns
8Gita Renewable seeks Rs 200 crore borrowing room after another zero-revenue year
8Jaiprakash Power stays on negative watch across Rs 5,600 crore of bank debt
8JSW’s O2 renewable subsidiaries secure two upgrades and four reaffirmations
8Refex withdraws its managing-director reappointment proposal before the AGM
8Indosolar related-party resolution passes with 30.6% dissent among votes cast
8Adani Energy says a review lifted its S&P ESG score from 81 to 90
8CLN Energy’s battery revenue grows 58% as working-capital exposure rises Details
8Adani Green adds 139 MW at Khavda and reaches 20,280.8 MW
8KPI Green wins 76.6 MWp wind-solar captive mandate with a 14-month clock
8Indo Tech corrects Waaree transformer award to Rs 55 crore
8GP Eco’s Punjab solar order shrinks 37% after the EPC structure is replaced
8Two 200 MW Kutch solar projects slide a year despite 65% physical progress
8Fatehgarh-II synchronous-condenser project moves to its successful bidder
8Premier Energies puts storage under a battery holding company and plans Singapore arm
8Tamil Nadu and Rajasthan seek thermal power across sharply different delivery blocks Details
8CERC opens twelve plant-tariff records to capital-cost and compliance scrutiny
8Jharkhand raises TSUISL’s five-year ARR after correcting its employee base
8Torrent seeks a new connectivity route for its 408 MW Beed solar project
8UPCL asks Uttarakhand to recognise Rs 5,900 crore from a two-decade transfer dispute
8Andhra Pradesh schedules hearings on central power costs and a bagasse contract
8Bihar reopens two open-access disputes for hearings on 16 September Details
8Tanda retires 440 MW as four 110 MW units leave the national fleet
8Durgapur’s FGD amendment is deferred over stack height and polluted-air evidence
8Ennore’s 1,320 MW extension stalls as its clearance clock runs out
8Five thermal proposals put 4,950 MW of expansion before the environment panel
8PSDF queue holds Rs 2,608 crore of old proposals still under examination
8C40 seeks a Mumbai–Chennai solar model with deadlines that predate the tender Details
1) NTPC opens 2.5 MMT domestic coal bid across five stations with Rs 10 crore security at the top end
8Bidders must declare mine, dispatch point and railway siding separately for each of the 0.5 MMT station lots. Coal breaching absolute moisture, ash or GCV thresholds attracts payment of just Rs 1 per MT, with no right to take it back.
8The GeM screens say no ePBG and no arbitration, but the overriding NTPC document imposes both.

 

2) SECI pushes Chitradurga 88 MW BoS commissioning to 21 months while doubling Route IIIA experience to Rs 234.50 crore
8Amendment-01 carries 47 changes, including deletion of the 0.5%-per-week delay LD and a shift of O&M start to operational acceptance.
8New pricing floors of 15% for services and 7.5% for O&M turn under-allocation into interest-free retention.
8Contractors unable to prove module causation for generation shortfall may have to fund additional capacity themselves.

 

3) RVPN invites Rs 136.60 crore turnkey bid for Lohawat 220 kV and 132 kV lines with Rs 2.74 crore security
8The notice fixes an 18-month programme but discloses no line lengths, tower quantities or ROW status.
8RVPN warns that last-minute portal failure will not justify any submission extension.
8Whether the schedule is production-driven or approval-constrained cannot be judged from the notice alone.

 

4) UPCL seeks 36 MW/90 MWh BESS across eight substations under a 12-year capacity charge and Rs 18 lakh per MWh VGF
8The Rs 180.50 crore build-own-operate package demands 95% availability, two daily cycles and 12-hour breakdown restoration.
8VGF of up to Rs 16.20 crore is released only against a bank guarantee covering the entire grant.
8Conflicting financial-closure periods and a draft BESPA awaiting UERC approval leave the contract base unsettled.

 

5) WBSETCL floats 222.5 CKM HTLS reconductoring with a 10% extra PBG for EPC bidders
8Five live 132 kV corridors must be restrung inside a 6 am–3 pm shutdown window with the parallel circuit charged.
8Tender wording admits annealed-aluminium HTLS broadly, yet the BOQ hard-codes solid carbon-composite core.
8Incorrect tower-loading calculations submitted with the bid trigger outright rejection.

 

6) MPPTCL tenders 23 units of 200 MVA autotransformers with Rs 3.45 crore EMD and cross-fail linked contracts
8Supply runs from the 8th to the 30th month, one unit per month, with 20% of value held until commissioning.
8Commissioning is stated as 75 days in one clause and 90 days in another; performance security appears as both 5% and 10%.
8Manufacturer-only eligibility with no consortium route narrows the field before the e-reverse auction begins.

 

7) UPCL’s Rs 115.50 crore Dehradun BESS cluster arrives with waterworks BOQ remnants and a subcontracting ban
8The 23 MW/57.5 MWh package spans seven tentative sites, each open to relocation after survey.
8A Rs 2.31 crore EMD and Rs 7.25 crore PBG precede any capacity-charge revenue.
8The tender calls itself technology-agnostic while mandating lithium-ion.

 

8) NTPC’s Mouda coal lot ties 50% of payment to laboratory results and reconciliation cycles
8The 0.5 MMT requirement sits inside a five-station package with sequential station-wise price opening.
8GCV below the 3,550 Kcal/kg base cuts price proportionately, then by a further 50% multiplier below 3,100.
8Sampling windows written as “eighteen (3)” and “seven (10)” days leave the testing timetable unclear.

 

9) MPPTCL bundles three 220 kV LILO works into one Rs 119.45 crore turnkey bid with a 3% e-auction trigger
8Bids within 3% above estimate avoid reverse auction; anything higher goes to e-RA.
8The GCC fixes performance security at 5%, but the standard guarantee form still reads 10%.
8MPPTCL may add nearby work up to 115% of contract value at the same rates.

 

10) UPCL’s Rs 206.30 crore Cluster C BESS carries a Rs 52 lakh EMD conflict between RFP and PQR sheet
8The 41 MW/102.5 MWh package requires 95% availability with no banking of monthly overperformance.
8VGF of up to Rs 18.45 crore sits behind a 100% guarantee and a Rs 12.92 crore PBG.
8A blanket subcontracting prohibition sits awkwardly against a multi-discipline scope.

 

11) NTPC Simhadri coal bid schedules the pre-bid conference before its own query deadline closes
8Queries close at 17:00 hrs on the same day the 11:00 hrs conference is held.
8NTPC may extend delivery by three months, vary quantity by ±20% and divert rakes at no cost to itself.
8ITB Clause 19.5 refers to “four stations” in a package that consistently lists five.

 

12) TGGENCO seeks two-year grinding-roll rate contract with no assured volume and a 10,000-hour guarantee
8The published ECV field reads Rs 1, making the 50% turnover test impossible to verify independently.
8Solvency appears as Rs 30 crore in one clause and Rs 7.20 crore in another.
8Failure of either rolls or bull ring segments is treated as failure of both.

 

13) OPTCL extends Baisinga 2×500 MVA substation bid by 17 days while its IFB still carries the old dates
8The portal shows 28 March closing, but the BDS and physical-submission clauses retain 11–12 March.
8Performance security stacks a 10% contract-level guarantee with a further 10% on named equipment.
8The scope stray-references a 220/33 kV Parjang substation and 200 MVA transformers in a 400/220 kV package.

 

14) BHEL grants fifteenth extension on Talabira ash-handling EPC, moving the deadline 115 days in total
8Corrigendum 19 shifts submission and opening to 15 September without altering any other term.
8Bidders need Rs 222 crore turnover, Rs 100 crore liquidity support and ash, civil and structural credentials.
8No reason for any of the 15 movements has been stated.

 

15) DVC stretches DTPS switchyard R&M from 360 days to 21 months after six deadline extensions
8Price-variation ceilings for cables and instrument transformers rise from 10% and 20% to 30% each.
8GIS service continuity relaxes from LSC 2B-PM to LSC 2A-PM, but online PD monitoring stays mandatory.
8Cable-tray quantities are capped at BOQ figures with no extra payment for design overrun.

 

16) NSPCL restores 24 pump assemblies after cutting them to three, amid 13 extensions on Durgapur mill R&M
8Fixed LD of Rs 6.8975 lakh per day gives way to 0.5% per week on uncommissioned mills.
8Mills must deliver 24 Tph with new elements and 90% of that with near-worn ones.
8Shutdown-extension LD still reads “Rs xxxxxx” in the SCC.

 

17) RRECL adds revolving letter of credit to 201 MW VNM solar tender after three deadline pushes
8Generation below 17% CUF draws a penalty while output above 19% goes unpaid. Parent-company credentials are rejected; the bidding entity must qualify on its own balance sheet.
8Beneficiary load data will reach only successful bidders, after tariffs are locked.

 

18) KPCL’s Rs 134.20 crore Naini-to-RTPS coal transport tender appears on the portal as a “computer lab” job
8The portal names a different procuring entity, an earlier deadline and 90-day validity against the NIT’s 180 days.
8Bidders must commit 80 tippers, two payloaders and a Rs 33.55 crore bank line with no guaranteed tonnage.
8KPCL warns its own GST-inclusive ranking may differ from what the portal displays.

 

19) EPI extends Mormugao cruise-terminal balance works by nine days after adding marine scope post-publication
8Corrigendum-01 introduced berths, dolphins, link spans and inventory lists eight days after the NIT went out.
8No mobilisation advance, no secured advance, and RA payments flow only when MPA pays EPI.
8The offline EMD deadline was never expressly moved with the online date.

 

20) KSEBL rejects hybrid-GIS credentials while rewriting cable and switchgear specs across seven corrigenda
8The Rs 106.64 crore TransGrid package gained 31 days but kept its 24-month execution clock.
8A 2% GIS-manufacturer guarantee sits above the contractor’s own 10% security.
8A narrow final-kilometre approach road was raised by a bidder and answered only by clause reference.

 

21) UJVNL dismantles Tiuni Plasu’s value-based qualification after 17 deadline shifts totalling 181 days
8Rs 103.84 crore to Rs 207.68 crore completed-work thresholds are gone, replaced by equipment credentials.
8Two OEMs may now back one bid, but manufacturer-backed bidders face Rs 260 crore turnover and 15% security.
8Corrigendum 04 once set a technical-opening date before its own submission deadline.

 

22) RVUN extends Rs 358 crore LSHS procurement twice, reaching 28 days without touching a single commercial term
8Only refinery-owning manufacturers with rail-loading capacity and Rs 358 crore turnover may bid.
8Plant-wise landed-rate evaluation could split 37,600 MT among several refiners.
8RVUN may divert, defer or cancel quantities with no supplier compensation.

 

23) WBSEDCL closes 2020 PCC-pole rate contract in 2026 with 67 “L1” awards at zero value
8Itemwise spreads between L1 and L3 ranged from 0.1% to 0.6% across four pole-region combinations.
8Bagaria Enterprises led both South Bengal items; PCM Concrete and Baba Loknath took North Bengal.
8The portal’s zero-value entries obscure how much of the Rs 235 crore programme actually reached any supplier.

Details
 For reference purposes the website carries here the following tenders:
 8Tender for construction of 33 kV sub station Details
 8Tender for annual contract for RBC maintenance and operation of various AC systems Details
 8Tender for supply of spares for 24 volumetric feeder of bowl mill XRP 763 Details
 8Tender for procurement and retrofitting of existing L and T Make 4P DC drive panel Details
 8Tender for requirement of refrigerant gases at air conditioning plant Details
 8Tender for construction of 02 Nos. 132kV AIS feeder bay at 220kV substation Details
 8Tender for work of modification/height raising of 132 kV double circuit transmission line Details
 8Tender for procurement of counterweight for installation in I type suspension pilot string in 800kV line Details
 8Tender for biennial maintenance works (masonry & carpentry) to RB's Details
 8Tender for biennial maintenance works (masonry & carpentry) to RB's and NRB's Details
 8Tender for painting of fire water system including pipes tanks Details
 8Tender for supply, installation, commissioning including civil works, stamping and CAMC of One nos (01) pitless electronic road weighbridge of 100MT at ashdyke Details
 8Tender for miscellaneous civil works Details
 8Tender for rate contract for supply of non metallic expansion joints to various Details
 8Tender for repair and rehabilitation strengthening of deteriorated RCC structures Details
 8Tender for biennial JC for civil maint. of V4A And V4B ash dyke Details
 8Tender for additional 5 mva ptr sub station Details
 8Tender for works of new 33 kV line Details
 8Tender for work proposal for fabrication and installation of coal chute using SAIL hard plate size Details
 8Tender for construction of five no. of septic tank in place of existing damaged septic tank Details
 8Tender for procurement of PA Fan blades with accessories installed Details
 8Tender for procurement of spares for temperature and vibration monitoring system of 6.6kV HT motor Details
 8Tender for construction using HT ABC Details
 8Tender for construction of 11kV covered conductor line using PSC poles Details
 8Tender for Re-routing HT line Details
 8Tender for replacement of old plate earthing Details
 8Tender for procurement of capital spares of the condenser vacuum pump installed Details
 8Tender for supply and services of 33 kV VCB between RW transformer Details
 8Tender for treatment of slope stability measures on upstream side Details
 8Tender for work of ACP paneling work on front portion Details
 8Tender for work of providing pipe type earthing and counterpoise earthing Details
 8Tender for annual maintenance contract for the fire and heat detection/alarm system Details
 8Tender for procurement of 132 kV, 50 MVAR capacitor bank with reactor, NCT and structures required Details
 8Tender for procurement of grinding rollers and bull ring segments for coal mill Details
 8Tender for work of erection, testing & commissioning of 132 & 66 kV equipment, structure Details
 8Tender for work contract for carry out cleaning of algae removal from the trash rack of CV, VT & MV pumps Details
 8Tender for Cluster C implementation of standalone battery energy storage system (BESS) of 41MW/102.5MWh capacity Details
 8Tender for Cluster B implementation of standalone battery energy storage system (BESS) of 23MW/57.5MWh capacity Details
 8Tender for Cluster A implementation of standalone battery energy storage system (BESS) of 36MW/90MWh capacity Details
 8Tender for SITC of supervisory control and data acquisition (SCADA) system Details
 8Tender for work for replacement of old/damaged AB cables Details
 8Tender for supply and fixing of 11 kV fault passage indicator feeder Details
 8Tender for supply of various types of clamp for 220 kV switchyard Details
 8Tender for augmentation of 220kV SStn Details
 8Tender for procurement of truck mounted hydraulic cranes Details
 8Tender for procurement of head skirt for bowl mill Details
 8Tender for replacement of existing PANTHER conductor by suitable HTLS conductor Details
 8Tender for construction of new 33 kV indoor switchgear room with 33 kV integrated panel Details
 8Tender for procurement, supervision of installation of One nos. of 220 kV GIS transformer bay along Details
 8Tender for AMC of boiler rotary parts 2x300 MW Details
 8Tender for supply of GI solid wire 6 SWG Details
 8Tender for annual maintenance work collection preparation testing and reporting of bunker fed coal pulverized coal from mills Details
 8Tender for annual maintenance work collection preparation testing and reporting of shipment coal received Details
 8Tender for supply of 11kV fixed and moving contact of double pole 200Amps AB switch Details
 8Tender for attending preventive maintenance and breakdown works etc in air compressors Details
 8Tender for carrying out routine maintenance activities of HVR transformer CERM EERM motors Details
 8Tender for routine maintenance overhauling of important critical modules HT /LT breakers switchgears Details
 8Tender for carrying out routine maintenance works of lighting Details
 8Tender for works contract for loading/unloading, handling and stocking of materials Details
 8Tender for supply of 11kV AB switch complete set (single pole) Details
 8Tender for supply of vacuum pump motor Details
 8Tender for providing services for various types of works including cleaning of silo complex Details
 8Tender for augmentation of 220 kV S/Stn Details
 8Tender for supply of circuit breaker analyser kit with six channel for 220 kV switchyard Details
 8Tender for supply of various insulation materials for boiler Details
 8Tender for supply of various HT power cables Details
 8Tender for work of construction of 400 kV double circuit line Details
 8Tender for establishment of 132/33kV substation Details
 8Tender for work of establishment of link line between 220kV line Details
 8Tender for work of LILO of 220kV line Details
 8Tender for balance work of 400 kV D/C line Details
 8Tender for establishment of 220/132/33 kV GIS sub-station Details
 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50MVA, 132- 110/33 kV T/F with allied civil works Details
 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50MVA, 132- 110/33 kV T/F along Details
 8Tender for work of carrying out earthing audit (health assessment) of existing earth mat and soil resistivity measurement Details
 8Tender for work of providing & applying of high insulation resistance compound coating having Di-electric strength more Details
 8Tender for work of fabrication and supply of 50 kL empty oil tank Details
 8Tender for work of second circuit stringing along with end bays of 132 kV line Details
 8Tender for work of second circuit stringing along with end bays of 220 kV line Details
 8Tender for work of installation of 1X125 MVAR 400kV bus shunt reactor with allied bay equipment Details
 8Tender for construction of 01 x 33kV feeder bay at 132kV substation Details
 8Tender for annual maintenance contract (AMC) for overhauling, repairing & servicing of 33 kV & 11kV CGL make circuit breakers Details
 8Tender for enhancement of transformation capacity of substation by providing 1x50MVA, 132/33kV PTR along with HV & LV bays and allied civil works Details
 8Tender for enhancement of transformation capacity of substation by providing 1x50MVA, 132/33kV PTR along Details
 8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details
 8Tender for misc. civil works Details
 8Tender for roof top rain water harvesting Details
 8Tender for work of (1) replacement of insulator or SRI (2) work of attending the fault or broken conductor Details
 8Tender for EPC contract for establishment of zero liquid discharge system Details
 8Tender for supply of ceramic lined spares of coal mill XRP-1003 of 500 MW Details
 8Tender for work of supply and application of anti-corrosive paint/coating on external surface of various steel structures, pipelines Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
 8
Coal India rallies 4% on huge volume on Mahanadi Coalfields IPO buzz Details
 
8Coal India's supply-first strategy holds as August production declines Details
 
8India’s power demand is surging, but some solar energy is going to waste Details
 
8Juniper Green strengthens portfolio with wind project Details
 
8AltEons Energy secures Sanmar investment for 1.5 GW+ RTC renewable energy portfolio in India Details
 
8KPI Green Energy Receives LOI for 76.6 MW DC Wind-Solar Hybrid Project in Gujarat Details
 
8CEA Proposes Two-Shift Thermal Operations for Renewable Integration Details
 
8China's solar capacity tops coal for first time: Where does India stand Details
 
8India’s Solar Manufacturing Capacity Surges, But Value Chain Integration Remains Key Challenge: IEEFA Details
 
8Saatvik Solar Files for ALMM Enlistment of 2.4 GW Odisha Facility Details
 
8India’s installed power capacity to quadruple by 2047; grid connectivity the biggest challenge Details
 
8India’s Coal Power Growth Slows As Renewables Surge Details
 
8NCRTC To Power Namo Bharat Delhi-Meerut Corridor With 110 MW Captive Solar Plant Details
 
8India's Coal Imports Set To Rise From October As Power Demand Drains Inventories, Says Kpler Details
 
8Power sector at tipping point as SC takes up DERC plea today Details
 
8India’s Renewable Energy Surge Moderates Coal Power Growth Amid Record Heatwave Demand Details
 
8POWERGRID AGM Highlights 99.81% Transmission System Availability Details
 
8Power push to lift revenue growth 100-200 basis points for large EPC cos Details
 
8AFRY Joins HPPCL for Thana Plaun Hydropower Project in India Details
 
8India’s Coal Power Growth Slows As Renewables Surge Details
 
8Coal India records 5.5% growth in coal supplies to 60.60 MT in Aug'26 Details
 
8Coal India: August Output Dips 5.7%, Offtake Rises 5.5% Details
 
8India’s power capacity set to cross 2,000 GW by 2047 Details
 
8India brings nuclear fusion into energy planning as deployment talks begin Details
 
8India’s installed power capacity to quadruple by 2047; grid connectivity the biggest challenge Details
 
You can also click on Newsclips for more Details
8Daily Excel covering new tenders and all published updates including corrigendum,amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details
8Environment panel lines up 4.95 GW of thermal additions for one-day appraisal
8Coal panel’s September agenda spans 2-to-6 MTPA expansion and a 23 MTPA peak mine
8EESL signs 112 of 123 Andhra streetlight agreements for a 750,000-lamp programme
8Environment panel returns or defers four ethanol expansions over land, monitoring and hearing gaps
8ONGC wins one Ankleshwar drilling amendment as a larger 65-well change is returned
8Kodarma’s 100,000-tonne coal-tar plant gets an environmental recommendation Details
8Juniper’s two 200 MW FDRE projects carry a 44-paise tariff gap and common grid risk
8Juniper seeks 300 MW grid access before a PPA as IPO proceeds support its pipeline
8O2 solar ratings rise even as project leverage stays above six times EBITDA
8Repowering lifts a 40 MW solar group’s PLF, but leverage remains at 5.6 times
8Dans Energy’s 96 MW hydro plant improves output but remains inside a debt workout
8Greenergy’s ethanol revenue triples, but half its capacity still depends on fresh allocations
8SJVN completes Buxar Unit 2 trial, leaving commercial operation as the next gate
8Tata Renewables commissions 100 MW captive solar as 5.3 GW remains in the pipeline
8TARIL enters nuclear transformers with Kaiga 5 and 6 order, but discloses no value
8Indo Tech’s transformer award contains a Rs 1 crore disclosure mismatch
8AHAsolar wins consultancy for a 600 MW solar and 1,800 MWh storage project
8Coal India’s first renewable revenue arrives as its 9.5 GW target remains mostly unbuilt
8MSETCL extends IPO banker bids and sets a high experience bar
8AHAsolar’s revenue rises 59% and crosses from loss to profit
8Epic Energy grows revenue 14% while profit nearly halves and arbitration-backed revenue rises
8Tripura finds no eligible candidates for 24 reserved electrical-manager posts
8Meghalaya extends the Umiam spillway-bridge safety-audit tender to 11 September
8TGTRANSCO reserves a Rs 23.61 lakh Donthanpally fencing tender for SC contractors
8Bellary thermal station seeks Rs 36.54 lakh of water-treatment chemicals Details
8Northern renewable scheduling gap reaches 5.87 GW after a 5.1 GW May event
8Rajasthan renewable capacity runs ahead of its Phase III evacuation system
8Eastern electricity use grows 6.4% while peak demand rises only 0.3%
8IEX day-ahead price jumps 69% as bids rise and cleared volume falls
8PXIL clears barely a quarter of real-time demand at the Rs 10,000 ceiling
8Power-plant coal stocks fall 534,000 tonnes in two days while cover stays at 10 days
8India carries 51.9 GW of generation outage as evening shortage reaches 2.4 GW
8Southern generating outages reach 12,133 MW without a coal-shortage entry
8Kaiga-Guttur circuit returns three months after multiple towers collapsed
8Maharashtra shifts feasible farm feeders to an eight-hour daytime window
8GUVNL seeks 400 MW round-the-clock power at a Rs 10,000/MWh ceiling
8SECI opens pre-bid review for a short-term 50 MW/100 MWh storage contract
8Ajmer Discom reports 571,397 complaints and no compensation paid
8Western frequency response ranges from 0.21 to 1.00 across July generators
8IEX high-price day-ahead clears only 68.4 MWh at the Rs 20,000 ceiling
8India loses another 1.11 GW of available capacity in one day as gas use falls 4.8 points
8Northeast grid plan defers 29 September shutdown entries and says 31 need no outage
8Eastern grid weighs 10%-15% tariff penalties for spare transformers kept beyond three years
8NTPC’s solar data clock remains seven hours wrong after weekly notices since April
8Rajasthan’s weekly merit order spans Rs 1.54 to Rs 29.75 a unit
8Uttar Pradesh and Tamil Nadu lead September regional transmission bills
8West African mini-grids would need about 2.25 GWh of batteries by 2030 Details
8MNRE extends old rooftop-solar subsidy claims to 30 November but deletes uninstalled cases
8Rajasthan discoms say a 90-day GST-relief reconciliation is not practicable
8Andhra Pradesh adds 39.6 paise a unit for June power costs
8Jodhpur Discom sets June FPPAS at 4.42%, mostly absorbed by the standing surcharge
8CERC lowers NTPC’s availability norm to 83% for coal-hit years, subject to Supreme Court appeals
8CEA proposes “ramping blocks” after thermal plants face DSM charges while following dispatch
8CERC protects 270 MW at Kurnool after a loan letter missed the financial-close date
8Jalaun’s 1,200 MW solar park regains conditional connectivity after a 20-day finance delay
8Gujarat Ombudsman upholds Rs 24.35 lakh cable charge after a decade-long connection dispute
8Punjab removes the physical net-metering agreement for every rooftop-solar category
8Rajasthan orders the 12%-to-5% renewable GST benefit into tariffs and pending cases
8Bihar buyers challenge NTPC Mining’s Chatti-Bariatu coal-price case as CERC reserves its order
8CERC demands transaction-level proof for SEIL’s disputed Telangana invoice deductions
8Energyedge must obtain an independent audit before CERC considers a larger trading licence
8BESCOM’s July calculation points to a 23-paise-a-unit power-cost refund
8Kerala sets September fuel surcharge at two to three paise after a Rs 6.37 crore July variation
8Himachal regulator approves five small solar PPAs at Rs 3.45 a unit
8Himachal moves Salun hydro’s Rs 3.93 tariff start to the PPA date, rejecting a later claim
8Parliament panel calls the Power Ministry and BBMB for an “atmanirbhar” sector briefing
8Tamil Nadu Ombudsman cuts an electricity demand to Rs 8,656 but refuses compensation Details
SECI's Second Storage Rental Notice Repeats the Same 26-Day Mobilisation Squeeze
8SECI's near-identical 50 MW/100 MWh short-term storage tender pushes techno-commercial opening to 6 October 2026 while still demanding service commencement by 1 November — leaving less than four weeks to complete financial evaluation, e-reverse auction, LoA issuance, PBG verification and ESPA execution.
8Full Rs 6 crore PBG encashment for missing that start date remains the enforcement mechanism, with cross-reference errors scattered across Clauses 3.1, 13.9 and 15.3.

 

GSECL's Ukai ZLD Tender States Both 5% and 10% Performance Security in the Same Document
8GSECL's zero-liquid-discharge and water-reuse EPC package for Ukai TPS shows GeM's ePBG field at 5% for 47 months while the incorporated ATC separately demands a 10% security-cum-performance guarantee — a five-percentage-point gap that directly affects bank-limit planning from LOI onward.
8A 15-year capitalised power-consumption penalty stacked atop an incompletely described "zero liquid discharge" process (RO and UF are listed only as future improvements) leaves both the financial evaluation and the technical scope only partially defined.

GETCO's 1,507-Breaker Tender Extends 19 Days While the Portal Still Shows Old Dates
8GETCO's Rs 113.94 crore switchgear procurement — 95% concentrated in 66kV SF6 breakers — moved its technical opening from 9 to 28 September 2026 through Corrigendum 1, but the public portal continues displaying the original early-September schedule, creating a submission-control risk that bidders shouldn't dismiss as cosmetic.
8A five-times-manufacturing-capacity qualification test could effectively require certified annual output of 7,160 units from any bidder attempting the full 66kV lot alone.

 

BSPHCL's Bagasse Co-Gen Tender Cuts Its Term From 15 Years to 5 After Bidder Pushbac
8BSPHCL's 100 MW bagasse co-generation procurement slashed its contract tenure from 15 years to 5 and dropped the enforceable minimum PLF from 53% to 25% — corrections that acknowledge seasonal crushing realities — but then reversed a separate concession allowing multi-plant owners to submit project-wise bids, restoring the original single-application restriction without explanation.

 

BSPGCL's 150 MW Solar-Plus-Storage Tender Fixes a Doubled ESS Ratio That Nobody Caught
8BSPGCL's firm-and-dispatchable renewable procurement corrected its own PPA, which had originally required twice the battery capacity specified in the RfS — 1 MW/4 MWh instead of the intended 0.5 MW/2 MWh per MW of solar — while extending commissioning from 18 to 24 months and allowing the declared CUF to move downward for the first time, not just upward.

 

RVPN's Budhadeeth GSS Tender Discloses Coordinates But Withholds the Contour Sheet
8RVPN's Rs 50.55 crore turnkey substation package finally pinpointed its exact site location after bidder requests, but the promised contour and ground-level data needed to price foundations, drainage and earthwork remains deferred to "shortly" — leaving civil-cost estimation incomplete just weeks before an 18-month clock is set to start.
8A late-added, highly detailed capacitor-bank breaker specification arrived without any corresponding schedule relief.

 

UJVN's Chilla BESS Tender Raises Its Ceiling Tariff 3.8% But Won't Define When Batteries Get Dispatched
8UJVN's 90 MW/225 MWh storage project corrected its land location from the wrong district and lifted the capacity-charge ceiling to Rs 3,30,400/MW/month, yet still hasn't specified peak/off-peak windows, minimum dispatch notice, or whether scheduling will be day-ahead or real-time — leaving developers to size augmentation and degradation reserves against an undefined two-cycle-per-day operating profile on a site UJVN itself calls "tentative."

 

NTPC's Pudimadaka Green Hydrogen Water Plant Excludes O&M From Its Own Delay Penalty Cap
8NTPC's turnkey water-treatment package for NGEL's hydrogen hub quietly removed the five-year O&M contract value from the denominator used to calculate maximum delay-liquidated-damages exposure — reducing the theoretical LD ceiling — while separately introducing payment relief when NTPC's own delay blocks performance-guarantee testing for a full year.

 

Power Grid's 32-Item Tower Steel Award Shows a Tight L1-L2 Race and a Wide L3-L4 Split
8Power Grid's Rs 171.15 crore transmission-material award to Shilpa Steel separated from the second-place bidder by just 3.3%, but the gap widened to 19.2% by the fourth qualified bidder — a spread suggesting sharply different assumptions on steel, galvanising, prototype assembly and the 730-day execution commitment behind seemingly comparable headline totals.

 

NTPC's Rihand Transformer Tender Says "No Civil Work" While Its Own Spec Says Otherwise
8NTPC's replacement-transformer package for two 400 kV units flatly told a bidder "No Civil work is in scope of vendor," yet the underlying technical specification still assigns transformer and cooler-bank foundations to the supplier — a contradiction NTPC never formally repaired, leaving brownfield interface responsibility genuinely unclear before bid submission.

 

WBSETCL's Rs 339 Crore Transmission Award Shows an Unexplained Rs 4.60 Crore Price Drop
8WBSETCL's composite eight-project EPC award to Kalpataru Projects beat KEC by just 4.9% and Larsen & Toubro by 24.0%, but the winning bidder's evaluated price fell Rs 4.60 crore below its own comparative BOQ total for reasons the disclosed documents never reconcile — while a portal contract date two years after the actual letter of award adds a separate chronology puzzle.

 

WBSETCL's Transformer Auction Ends in a Rs 1 Lakh Photo-Finish, Then Adds 90 Days to Delivery
8WBSETCL's four-transformer procurement saw its reverse auction compress the top two bids to within Rs 1 lakh of each other on a Rs 33+ crore contract, yet the eventual purchase order quietly extended final delivery by 90 days beyond what the original tender demanded — a post-auction concession that shifts the traded value from pure price competition toward negotiated schedule relief.

 

NHPC's Haryana Rooftop Solar Tender Protects Good Bids From Bad Neighbors
8NHPC's 30.93 MWac government-rooftop RESCO tender inserted a new clause preventing a bidder's failure in one district or category from automatically disqualifying its otherwise-compliant bids elsewhere — a fix that kept nine of eleven original bidders in play for the eventual district-wise reverse auctions.

 

NTPC's Darlipali Ash Rate Contract Shows a Documented Award 54.5% Below Its Own Estimate
8NTPC's ash-to-road-construction logistics tender priced six equal Rs 22.75 crore contracts totaling Rs 136.50 crore against an original Rs 300 crore estimate — but with quantity deviation permitted down to zero and no guaranteed purchase orders, that headline gap may reflect discretionary allocation as much as aggressive pricing.

 

REC's YEIDA Transmission Tender Makes the Contractor Indemnify Risks It Never Created
8REC Power Development's Sector-28 YEIDA substation RFP requires the winning bidder to indemnify the seller against all past, present and future third-party claims tied to pre-closing project decisions — while the acquisition price for the project SPV remains blank until just 20 days before bid closure, and a stray reference sends the performance guarantee to CTUIL despite this being a purely intra-state UPPTCL project.

 

REC's Alkud-II Transmission RFP Finally Names Its Own Project Company
8A one-line amendment to REC's 765/400/220 kV Sangli transmission tender replaces every placeholder reference to "[Insert SPV name]" with "Alkud II Power Transmission Limited" — a housekeeping fix touching the RFP, TSA and SPA simultaneously, though the acquisition price, MERC-pending reverse-auction parameters and the project's all-or-nothing 24-month commissioning dependency remain unresolved.

Details
 For reference purposes the website carries here the following tenders:
 8Design, engineering, supply, erection, commissioning and testing of 2 nos 140 ton capacity pit less type in motion electronic rail weigh bridge Details
 8Tender for supply of MS grill and fabrication & epoxy paint of stairs, railing, structure Details
 8Tender for carrying out routine maintenance works of lighting in power house Details
 8Tender for works contract for heightening the pillar boxes Details
 8Tender for supply of tarpaulin sheet for covering of coal Details
 8Tender for work of servicing & repairing of window AC, split AC and water coolers Details
 8Tender for rate contract for removing, lifting, shifting, dismantling, servicing and overhauling of 2.3 kV /6.6 kV / 11 kV HT motors Details
 8Tender for construction of civil work for 02 No 132 kV bay Details
 8Tender for civil works related to construction of 1 No 33 kV bay Details
 8Tender for execution of bypass and restoration arrangements of 33 kV /22 kV /11 kV LT lines Details
 8Tender for procurement of spares for rotary feeder Details
 8Tender for construction of 11kV covered conductor line using PSC poles Details
 8Tender for re-babitting of thurst bearings pads of 40MW turbine Details
 8Tender for supply, erection, testing and commissioning of high light mast Details
 8Tender for reconstruction of the damaged geo green soil stabilization structure Details
 8Tender for supply, installation, testing and commissioning of energy meter Details
 8Tender for work of preventive maintenance of various 220 kV switchyard Details
 8Tender for carrying out maintenance works and all types of cable related works Details
 8Tender for supply, erection and commissioning of insertion type ultrasonic water flow meters Details
 8Tender for work of inspection, repairing / overhauling of existing piping hangers Details
 8Tender for work of attending leaky tubes, joint replacement and tube nest replacement Details
 8Tender for carrying out routine maintenance works for maintenance of uninterrupted power supply Details
 8Tender for construction using HT ABC Details
 8Tender for construction of 110 kV substation Details
 8Tender for routine maintenance and breakdown works of HT and LT motors and their related Details
 8Tender for biennial rate contract for civil maintenance of entrance cabin and loading point Details
 8Tender for supply, erection and commissioning of lighting poles Details
 8Tender for extension of 220kV substation Details
 8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details
 8Tender for regarding work of shifting of 11 kV feeder Details
 8Tender for ARC for erection of HT / LT / TC and maintenance work Details
 8Tender for procurement of LT three phase angle cross arm Details
 8Tender for carrying out routine maintenance works of HT/LT switchgear in RWPH 5 MVA power transformer Details
 8Tender for routine maintenance and breakdown works of HT motors LT motors Details
 8Tender for routine breakdown maintenance works of 230 kV grid bus yard power transformers Details
 8Tender for works contract for the routine maintenance of MRT equipments Details
 8Tender for carrying out maintenance activities of C&I equipments in unit Details
 8Tender for construction of damaged and U fencing to prevent encroachment at 220kV s/s Butari Details
 8Tender for construction of damaged and U fencing to prevent encroachment at 220kV s/s Details
 8Tender for outsourcing work of erection, testing and commissioning of 01 no new 66 kV substation Details
 8Tender for supply of LT XLPE insulated aerial bunched cables Details
 8Tender for supply of hot end and hot intermediate end baskets embedded with heating elements for air pre heater Details
 8Tender for requirement of leak off control valve with pneumatic actuator for turbine gland seal steam system Details
 8Tender for supply of cast basalt pipe fitting and pipes of various sizes Details
 8Tender for supply of different types of GTC sleeves for various pumps, clinker grinders Details
 8Tender for supply of 245kV current transformer (CT) Details
 8Tender for work of providing protection structure by erection of girder pole & tower angle to transmission tower’s Details
 8Tender for construction of electricity test lab Details
 8Tender for special maintenance and repair works of electricity sub-station Details
 8Tender for construction of store and other miscellaneous civil works at 33/11 kV substation Details
 8Tender for construction of 03 Nos store and other miscellaneous civil works at 33/11 kV substation Details
 8Tender for life enhancement works E and F Details
 8Tender for biennial maintenance contract for conservancy work Details
 8Tender for renovation of BAT supporting structures Details
 8Tender for biennial rate contract for repairing and servicing of ESP rapping system gear box Details
 8Tender for Supply, civil, erection, testing & commissioning for implementation of rapid restoration system for 3x105MVA, 400/220/33kV ICT II Details
 8Design, engineering, supply, erection, testing & commissioning of HVWS system for 4 nos. new SFC transformer Details
 8Tender for supply of ceramic blanket for 1X500 MW boiler unit Details
 8Tender for work of dismantling replacement / repairing of PF pipe, orifice & PF bend of coal mills Details
 8Tender for deputation of service engineer for quarterly servicing, maintenance & trouble shooting of PLC system & VFD drives of various auxiliaries Details
 8Tender for work of complete o/h of MS&HRH strainers, HP&IP stop and control valves Details
 8Tender for supply of submersible pump motor set capacity Details
 8Tender for supply and installation of an energy efficient lubricated rotary screw air compressor Details
 8Tender for work of supply and application of anti-corrosive paint on external surfaces of various structures, pipe lines & auxiliaries Details
 8Tender for services for carpentry, masonry, and plumbing works etc. and operation of drinking water supply system Details
 8Tender for supply of various spare of beater wheel Details
 8Tender for miscellaneous fabrication and steel work in various Details
 8Design, supply, installation, commissioning and maintenance of solar PV system for 5 years as a rooftop Keshod Details
 8Design, supply, installation, commissioning and maintenance of solar PV system for 5 years as a rooftop Kodinar Details
 8Design, supply, installation, commissioning and maintenance of solar PV system for 5 years as a rooftop Details
 8Design, supply, installation, commissioning and maintenance of solar PV system Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Coal India accepts resignation of ED Raja Sekhar Kinnera Details
 
8Coal India prepares to list MCL, SECL after board approval: B Sairam Details
 
8Power reforms need an urgent push Details
 
8Bangladesh wants Nepal’s power, but India holds the key Details
 
8Renewables Deliver Record One-Fifth of India’s Power in July Details
 
8What Are DISCOMs, India Power Distribution And Smart Meters Explained Details
 
8Haryana to oppose private parallel power distribution licence in Gurgaon, Nuh: Power Minister Details
 
8Transformer Maker Enters Nuclear Segment With Kaiga Project Order Details
 
8Sealmatic Eyes Growth from India’s Expanding Nuclear Sector Details
 
82 Green Energy Stocks With High Promoter Holding Details
 
8KMCC Infra Secures INR 244 Crore BSPTCL Order for 205 RKM Transmission Infrastructure in Bihar Details
 
8Motilal Oswal bets on Data centres, defence & transmission: Top 6 capital goods picks for FY27 Details
 
8How hydropower decline is reinforcing coal’s role as India’s flexible power source Details
 
8SJVN Completes 72-Hour Trial Run of 660 MW Buxar Unit-2; Commercial Operation Set to Begin Details
 
8India adds 6.6 GW of rooftop solar in H1 Details
 
8From solar to chips: Powering India's manufacturing rise Details
 
8Ceigall India commissions first 5 MW solar project under MSKVY 2.0 Details
 
8Tata Power Commissions 100 MW Group Captive Solar Project Details
 
8Waaree Renewable Technologies Wins 291 MWp Solar-BESS Project Details
 
8Global Solar PV Installations Forecast to Hit 638 GW by 2026 Details
 
8ONGC to invest Rs 1 lakh crore in deepwater exploration over next 5 years, reports 3 new discoveries Details
 
8India Solar Manufacturing: Module Glut and DCR Cell Shortages Details
 
8Solar-Plus-Storage Investments Hit $25 Billion in H1 2026 Details
 
8Westbridge Sells 225 MW Alberta Solar and Storage Project Details
 
8Fujiyama Power Adds 1 GWh Lithium Battery Capacity in Ratlam Details
 
You can also click on Newsclips for more Details
8India could turn 151 coal units aged at least 35 years into the equivalent of a 24.2 GW flexible resource by 2030, a Central Electricity Authority panel has said.
8The proposal is presented as far cheaper than six-hour batteries, but the utilities asked to supply pilot plants have not done so and NTPC disputes the panel’s reading of equipment damage.
Details
8Rajasthan continued to inject surplus power into a high-frequency northern grid even while renewable plants were being backed down, according to the regional system operator.
8The imbalance reached about 4,000 MW on some occasions and persisted through five consecutive operating-committee reviews, turning a state portfolio problem into a wider grid-security concern.
Details
8Two 400/220 kV transformers at IndiGrid’s Sohna Road substation caught fire after a bus-charging fault remained uncleared for about 720 milliseconds, cutting roughly 396 MW of load.
8The incident did not end with the equipment failure: the regional operator also records delays in restoration and in obtaining status from the licensee for a substation supplying Gurugram.
Details
8A broken insulator on a 765 kV line near Jawaharpur caused about 972 MW of generation loss after a local earth fault also tripped four transformers and both generating units.
8The original fault was severe, but the wider outage came from delayed breaker opening and protection settings that the regional committee found sensitive enough to disconnect healthy equipment.
Details
8BGR Energy Systems ended FY2025-26 with consolidated losses of Rs 1,291.72 crore and negative net worth of Rs 2,599 crore, almost twice the deficit a year earlier.
8Its annual report sets live nuclear and thermal contracts against a still-unresolved asset-reconstruction settlement and costs booked before customers have approved corresponding claims.
Details
8Adani New Industries’ manufacturing ecosystem has spent about Rs 4,850 crore of a Rs 9,481 crore expansion designed to take solar module and cell capacity to 10 GW.
8Revenue and the order book are growing, but profitability has already weakened and the export business remains exposed to US tariffs and trade remedies.
Details
8Sarda Energy & Minerals cut consolidated net debt from Rs 1,566 crore to Rs 215 crore as a full year from its 600 MW thermal acquisition lifted earnings.
8The same annual report shows debtor days rising by two-thirds, leaving a working-capital counterpoint to the power-led profit and deleveraging story.
Details
8Two record-demand events produced radically different power-price outcomes in the United States: PJM’s real-time price approached $2,000/MWh during its July peak, while the Electric Reliability Council of Texas cleared its own record hour at $29.11/MWh.
8The comparison puts a measurable consumer consequence against the two markets’ very different renewable and battery build-outs.
Details
 1 2 > 

Showing 1–50 of 56 items