All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Jul 2026

8The station the country is counting on to absorb the solar trough went off bars at the evening peak on 25 July, then twice more on 26 July on bus-bar protection. Unit 1 was still out at the reporting cut with no revival date recorded. Details
8Grid-India's June ancillary services report puts a price on keeping gas capacity available: 210,471.80 MWh delivered for Rs 468.74 crore net. Over the same month renewable generation was curtailed to a peak of 19,281 MW with no compensation paid at all. Details
8The Northern Regional Power Committee's protection sub-committee has the Rihand blackout on its 3 August agenda, and the papers show the special protection scheme performing at a fraction of its design. A month later, on 17 July, only three of nine substations confirmed operation. Details
8India's largest single coal plant reported 0.0 thousand tonnes of stock against a normative requirement of 661.6 thousand tonnes, and did not reduce output. Twenty-seven plants sat in the critical band on the same day. Details
8The utility extended a four-day mass leave to six, 21 to 26 July, then wrote off the entire period for all purposes and admitted in the same order that consumer supply was disrupted. Ropar Unit 3 was recorded out with the cause stated as an empty bunker from a manpower shortage. Details
8The all-India system spent 9 hours 19 minutes outside the 49.90 to 50.05 Hz band that day, its worst of the week, and the frequency violation index tripled. A Chiplima hydro unit then tripped on what the record calls a spurious under-frequency relay operation. Details
8The Western Regional Power Committee withdrew its 21 July statement within two days of Goa's load despatch centre objecting that five named generators had no schedules on 8, 9 and 11 July. WRLDC's stated cause was a synchronisation failure between the renewable energy management centre and the web-based energy scheduling system. Details
8The Western transmission account for July 2026 charges delayed projects under Regulation 13(7) against a regional bill of about Rs 1,203 crore. Waree Forever's 700 MW is being billed at Rs 21 lakh a month for capacity that does not exist yet. Details
8The evidence arrived as an annexure to a small-hydro developers' submission in CERC's generic renewable tariff consultation for FY 2026-27. It is the most consequential thing in a file otherwise full of capital-cost arguments. Details
8The tariff-based competitive bid covers 10,500 MVA of transformation across seven 765/400 kV units, to be built in thirty months through a special purpose vehicle. It is the largest single transmission award in the folder. Details
8The 241st operation co-ordination committee minutes record ERLDC opening inter-connecting lines as a control action, not a contingency. On 26 June, Bihar's over-drawal ran 61.5% above schedule at a frequency the grid code treats as an emergency. Details
8In four days the green day-ahead market went from a Rs 205.14 premium to a Rs 467.02 discount against the conventional day-ahead price. The term-ahead green product cleared at 114 to 124 per cent above day-ahead over the same week. Details
8IEX day-ahead cleared 168,403.82 MWh on 26 July at Rs 4,642.80/MWh, a third straight rise
8IEX real-time cleared 190,397.65 MWh on 26 July at Rs 4,712.82/MWh, dearer than day-ahead
8IEX real-time out-cleared day-ahead on two of three days, by 13.1% on 26 July
8IEX hit the Rs 10,000/MWh ceiling in 124 of 576 blocks over 24 to 26 July
8IEX's weekly weighted day-ahead price sits Rs 1,322.76/MWh below the simple average
8IEX GDAM flipped from premium to a Rs 467.02/MWh discount to day-ahead in four days
8IEX green term-ahead cleared at Rs 9,950.75/MWh, more than double the day-ahead average
8IEX term-ahead traded 64,369.83 MWh in three days with 66.2% of lines at the Rs 10,000 cap
8IEX real-time lost 39.18 MW between clearing and schedule at 18:45 on 24 July, cause unstated
8IEX HPDAM took no bid for eight days against 303,986.15 MWh of unsold standing offer
8The day-ahead ancillary book took zero bids on ten straight days to 27 July
8PXIL's DSM report for 24 to 26 July carries no deviation data and a zero clearing book
8An unattributed exchange's green day-ahead segment cleared nothing for ten days to 27 July
8The same venue's real-time snapshot printed zero on both sides of the book for ten days
8A high-price day-ahead segment at the same venue took no bid on either side for ten days
8A member's real-time book cleared 3,711.00 MWh on two days, every MWh at the Rs 10,000 cap
8A contingency book bid 2,200.00 MWh over four days and met no seller at all
8Rajasthan's RVUITSL seeks 500 MW of thermal evening cover for August on HPX, no ceiling price
8RVUITSL seeks 500 MW in two September blocks on HPX, widening its daily cover to 12 hours
8NLDC fixes the applicable all-India ISTS loss at 3.79% for 27 July to 2 August
8TGTRANSCO notifies a 2.08% intra-state loss binding on Telangana open access from 26 July
8IEX's Supreme Court appeal on market coupling is admitted after APTEL found it not aggrieved
8CERC's draft market coupling regulations name Grid India as the market coupling operator
8Grid India warns that a sole market coupling operator is a single point of failure
8Coal Exchange Rules give e-auction platforms six months once the first exchange goes live
8IGX has filed a DRHP with SEBI and BSE for a proposed initial public offer
8IEX's peak DAM and RTM petition for battery storage is reserved with CERC, not decided Details
8India met 234,614 MW on 26 July with only 289 MW unserved at peak
8All-India frequency fell to 49.423 Hz as evening solar went to zero on 25 July
8The grid ran outside the IEGC band for 9h19m50s on 25 July and 6h23m10s on 26 July
8ER–NR was the only Indian corridor to breach ATC or N-1 in the window
8Renewables supplied 18.83 per cent of Indian generation on 26 July, 35.08 per cent in the South
8NLDC backed off 7,692 MW of wind and solar on 24 July to hold frequency
8Down-regulation ran 6.3 times up-regulation on 26 July, with no Rs value published
8All-India angular spread held near 70 degrees but the stress axis moved to Durgapur
8Northern Region logged 25 grid events in June, losing 8,731 MW of generation
8Northern Region left 70.4 MU unserved in the last four days of June
8NTPC's Tanda TPS generated 0.00 MU in April, May and June 2026
8Tripura breached its available transfer capability for 70.6 per cent of 25 July
8Assam's TTC violation grew five-fold in three days to 23.9 per cent of 25 July
8NEEPCO's Ranganadi HEP, 405 MW, generated nothing on all three days
8Amreli 400 kV sat above the IEGC ceiling for 97.6 per cent of 26 July
8Kerala over-drew and Tamil Nadu under-drew on every day of the Southern window
8SRLDC's day-ahead forecast error for the South peaked at 2.85 per cent on 24 July
8SRLDC's week-ahead forecast under-called 26 July by about 5,700 MW
8Telangana's unrestricted peak demand rose 6,961 MW in seven weeks to 16,650 MW
8Telangana bought its growth: purchased power up 282 per cent as own thermal fell
8Telangana's gas IPPs delivered 0.000 MU on every complete day since 31 May
8Coal supplied 3,628.81 MU - 79 per cent of India's conventional generation on 23 July
8Sikkim's 1,200 MW generated 0.00 MU on 23 July and nothing all financial year
8Stations outside the IEGC voltage band fell from 18 to four in a day
8Silchar 400 kV touched 377 kV on 25 July - India's only under-voltage breach
8Godda 400 kV touched 420.15 kV, the Eastern Region's only band breach
8Malkaram 400 kV held 432.10 kV for ten hours on 25 July
8Haflong 132 kV ran above band for 62.29 per cent of 26 July
8Greenko's pumped storage lost 1,200 MW to under-frequency at 19:20 on 25 July
8A lightning-arrester repair cut the South's import capability by 600 MW
8Tamil Nadu turned net injector, exporting up to 862 MW into the ISTS at midday
8A 1 GW evening schedule cut that drawal did not follow produced the window's largest over-drawals
8Andhra Pradesh's drawal telemetry dropped about 900 MW on each of three days
8ERLDC's day-ahead forecast error doubled to 8.21 per cent on 25 July
8Eastern Region demand met climbed 1,480 MW in two days to 31,256 MW
8J&K and Ladakh carried the whole of India's shortage on 26 July, 0.98 MU
8Northern Region demand reached 86,038 MW at 23:00 on 26 July
8Amritsar 400 kV was the only Northern bus outside band, 29.51 per cent of 25 July Details
8India had 54,865.22 MW out of service on 23 July, 59.5 per cent of it forced
8CEA's coal, lignite and nuclear register held 33,731.51 MW under maintenance across 136 units
817,145.00 MW of 500 MW-and-above units was under maintenance, 11,805.00 MW of it forced
8Uttar Pradesh carried 3,640.00 MW of large-unit outage and not one megawatt was planned
8North Chennai Stage 3 Unit 6, 800 MW, was the largest single unit out of service
834,364.41 MW has been off the grid for more than fifteen days
86,105.41 MW has been out over a year, and 52 of the 116 entries are already zeroed
8India's gas and liquid-fuel fleet was 55.79 per cent out of service on 23 July
8India lost 7,474.97 MW to the grid on 23 July and got 3,694.16 MW back
8Agartala GT's whole 109.50 MW left the grid, four units on stated fuel shortage
8Essar CCPP's 515 MW has been dead on "NO Power Purchase Agreement" since 2015
8Six central gas stations logged roughly 200 fuel-conservation outage spells since March
82,464.00 MW left the grid on 23 July for want of a schedule, not for a fault
8Six units totalling 429.51 MW are shut for want of a Fuel Supply Agreement
8Neyveli TPS-II has seven units, 1,470 MW, on the fifteen-day outage register
8Rayalaseema TPS has five units, 1,050 MW, on the fifteen-day outage register
8Kudankulam Unit 1, 1,000 MW, is the largest single unit on the long-outage register
8Telangana STPP's two 800 MW units have been idle four months for want of a schedule
8Eleven CEA entries carry an expected return date that has already passed
8Haldia GT Unit 2 has been on CEA's register since 21 September 1988
8Boiler-tube failures account for roughly 5,500 MW on the fifteen-day register
8Tuticorin Units 1 and 2 have been out 495 days since the March 2025 control-room fire
8Raichur Unit 1 carries a 13 August 2027 revival against a collapsed coal bunker
8Adani Power's Mundra fleet had 1,650 MW backed down on "RSD/LOW SCHEDULE"
8Rosa Phase-I Unit 4 suffered two separate boiler-tube failures inside eight days
8Suratgarh lost 500 MW to two unrelated faults within fourteen hours
8Tanda TPS Units 1 and 2 have been shut 388 days to conserve fuel
8Three nuclear units sit on CEA's maintenance register, one for over eight years
8NRLDC carried 10,430 MW of generation outage, state-sector forced fifteen times central
8Ropar Unit 3 went out with the cause recorded as an empty coal bunker from a strike
8Ghatampur's two 660 MW supercritical units were forced out together
8Obra C Unit 1 (660 MW) carries a 15 October revival on a generator fault
8Jawaharpur Unit 2 lost 92 hours to a 765 kV line trip, then failed again
8Salal HPS took all six units, 690 MW, off the bar for reservoir flushing
8Parbati III lost all four units within thirteen minutes to high silt
8NHPC's Chamera, Dulhasti and Bairasiul cascades cycled on silt, trash and a landslide
8Around 2,344 MW of Northern gas capacity is on reserve shutdown by despatch instruction
8Dadri's three 130 MW units were revived and put straight back out within three hours
8Giral's two 125 MW units, "likely to be scrapped", are still carried on the register
8RAPS-A Unit 1 carries a 1 January 2030 revival against an outage that began in 2004
8NRLDC's transmission register ran to 653 element-outage entries in three days
8The Northern grid ran 268 voltage-regulation outages in three days
8Energizent_PPL_FTG3's 220/33 kV 160 MVA ICT-2 tripped three times in three days
8The 765 kV Phagi–Bhiwani Ckt-2 was manually opened four times for high voltage
8NRLDC's planned shutdown register holds 103 elements, 31 of them still open
8A 220 kV bay at Dehradun booked for ten hours has now been out 311 days
8The 800 kV Kurukshetra HVDC bipole was taken out on both poles for a Western Region request
8The 765 kV Bikaner–Khetri Ckt-2 was out 29 hours on a B-N fault
8The 765 kV Phagi tie bay stayed open because a GOOSE message did not arrive
8The 220 kV Panchkula double circuit has been down thirteen months from tower collapse
8The 400 kV Orai–Paricha double circuit is down with 28 towers collapsed
8The 400 kV Banda–Rewa Road double circuit is down since Tower 399 collapsed in a rainstorm
8Two 50 MVAR reactors have been out since 2021 with no reason ever furnished
8The 400 kV Kanpur SVC has been decapitalised after the manufacturer withdrew support
8A 220 kV Jammu and Kashmir circuit has been out two years on a failing tower
8Four 220 kV circuits were held open to manage Kishenpur ICT loading through the Salal flushing
8The 765 kV Ajmer–Chittorgarh double circuit ran five days past plan for the Beawar LILO
8Rajasthan's renewable evacuation bays at Fatehgarh have been held out for up to 122 days
8The 330 MVAR Bara–Mainpuri line reactor tripped on internal differential and stayed out
8WRLDC's generation outage ran from 21,864 MW down to 20,527.5 MW across three days
8Wanakbori Unit 8, 800 MW, went out on boiler tube leakage, leaving 1,430 MW down
8CGPL's Mundra Unit 5, 800 MW, tripped on an electrical fault for 38 hours
8A special protection scheme tripped KSK Mahanadi Unit 3, 600 MW, on a 400 kV fault
8Tarapur II Unit 2, 540 MW, entered a biennial shutdown to 6 September
8Kala 400 kV Bus-2 auto-tripped on local breaker back-up, taking six elements down together
8The Vapi 400 kV complex was manually opened for the flood situation
8The Kutch heavy-rain cluster took out seven GSECL elements at 01:14 on 24 July
8The 765 kV Vadodara Bus-2 auto-tripped on LBB protection from Bay 711
8The 765 kV Vadodara–Lakadia Ckt-2 tripped on a Y-phase earth fault and stayed out
8The Chhattisgarh 400 kV network took four fault trips in a single day
8The 400 kV Bhadrawati–Bhilai Ckt-1 was opened for an isolator hot spot near 270 degrees
8The 800 kV Raigarh–Pugalur HVDC blocked all four poles overnight on 26 July
8The 765 kV Wardha–Nizamabad Ckt-1 lost a lightning arrester stud fitting in heavy wind
8Sixty Western elements carried the same outage across two or three daily registers
8Western legacy transmission outages run back to 2016 and are still carried
81,215 MW sits on the Western planned register for commercial reasons alone
8RGPPL Dabhol's entire 1,967 MW is out, two units since 2014 on gas shortage
8ACBIL Unit 1 has been out 48 days on low coal stock
8Five Western revival dates slipped inside a three-day window
8SRLDC's outage held above 12,400 MW while state-sector forced outage climbed 37 per cent
8Greenko Pinnapuram lost Units 7 and 8 at 01:47 with the 400 kV Line-2 trip
8Greenko Pinnapuram lost Units 1 to 5 at 19:13 on MB-2 bus-bar protection
8Bellary TPS Unit 3, 700 MW, tripped on boiler tube leakage
8Rayalaseema TPP lost Units 2 and 3, 420 MW, to boiler tube leakage within fifteen hours
8Neyveli TS II Unit 2 returned at 16:14 and failed again on a boiler tube leak
8LANCO's LKPPL Stage-3, 732 MW, sits on the register with the reason "Under NCLT"
8All four Kadamparai pumped-storage units, 400 MW, are on forced outage together
8Kayamkulam's three units carry a committee-minuted 45-day fuel notice as their restart condition
8The 765 kV Maheshwaram hub had four circuits degraded at once
8The 400 kV Kaiga–Guttur double circuit is down with five towers collapsed
8The 400 kV Gadag–Koppal double circuit is down with thirteen tower locations collapsed
8A 400 kV circuit has been held open twenty months on an expired power purchase agreement
8SRLDC's line register carried 310 element-day entries across three days
8Nine named thermal-defect emergencies in three days, several on IPP evacuation assets
8SRLDC records an approved shutdown rejected on sensitivity overlap, then taken anyway
8The 400 kV Hebbanahalli–UPCL circuit was out 12 hours 33 minutes on a B-N fault
8The 220 kV Ambewadi–Xeldem circuit in Goa tripped twice at two different fault locations
8Three Kudgi evacuation circuits failed on Y-phase contact problems in one day
8Six Southern units have been on forced outage for more than a year
8Yeramaras Unit 1, 800 MW, went under annual overhaul to 25 August
8Srisailam LBPH brought three units back on 25 July and kept three out
8The 400 kV Anaikadavu–Thappukundu Ckt-2 was hand-tripped on voltage regulation every night
8Five 400 kV-class transformers are being dismantled and relocated across Tamil Nadu
8Eastern Region outage moved 5,547.5 to 4,887.5 to 5,147.5 MW with zero coal-shortage outage
8Teesta Stage III's six units, 1,200 MW, still carry no revival date after 33 months
8Barh Unit 1, 660 MW, went out on boiler tube leakage on the edition-fresh day
8Sterlite Unit 3, 600 MW, went out on an air pre-heater problem on 26 July
8Darlipali Unit 1, 800 MW, was out 52 hours on boiler tube leakage
8FSTPP Unit 3, 200 MW, was out 46 hours on boiler tube leakage
8Nabinagar NPGC Unit 2, 660 MW, failed twice inside fifteen hours
8Chiplima Unit 3 tripped on a spurious under-frequency relay operation
8Sagardighi Unit 5, 660 MW, was out five hours across the evening ramp on 25 July
8Balimela Units 5 and 6 have been out eighteen months on renovation and modernisation
8Burla Unit 7's expected revival slipped sixteen days between two consecutive registers
8Five Eastern units, 1,010 MW, have been out for more than three months
8PVVNL Meerut notified 111 planned feeder shutdowns for a single day
8A 33 kV construction job at Amroha took 27 feeders down together
8The CM Grid Yojna is the stated cause of at least twelve PVVNL outages
8The Kanwar Yatra is the stated cause of two Saharanpur outage sets
8Two PVVNL feeders were booked for overlapping outages on the same day
8SRLDC's forced-outage feed prints a revival earlier than the outage on a Greenko row
8Three of NRLDC's 103 planned rows are exact duplicates and one reason field is unreadable Details
8Coal-critical count eases to 27 as the national pile falls a third day to 39.3 million tonnes
8Sasan UMTPP runs its coal stock to zero on 25 July while generating at 86% PLF
8Damodaram Sanjeevaiah holds 3% of normative coal for a third straight day
8JSW's Torangallu SBU-I reports nil coal for three days while running at 90% PLF
8Andhra Pradesh runs three of its four monitored coal stations critical every day
8Three plants moved on and off the coal-critical list in 48 hours
8Coal receipts climb 6.37% to 2,406.0 thousand tonnes and the daily draw narrows to 171.7
8Pithead coal stocks fell 1.94% in two days against the rail-fed fleet's 0.92%
8NTPC's coal pile fell 257.0 thousand tonnes in two days with no station critical
8NTPC's coal cover ranges from 33 days at Bongaigaon to 8 at Kudgi and Mauda
8Coal India's 22 July register flags no plant critical while CEA flags 28 the next day
8Twenty-four plants on Coal India's register hold seven days of coal or less
8Coal Ministry doubles linkage tenure to 30 years for syngas and gasification projects
8North Chennai Stage 3 books zero coal receipt and zero burn for a third day
8Adani's Udupi TPP falls to 7% of normative, the sharpest slide in the critical list
8Suratgarh rebuilds 19.3 thousand tonnes of coal in two days but stays critical
8Dahanu TPS holds 6% of normative coal as six critical plants keep drawing down
8Mahan TPP generated 96% above programme on three days of coal stock
8Sikka Replacement TPS shows one day of coal on the generation ledger but no critical flag
8Kasaipalli TPP runs critical on washery rejects at 22% of normative for three days
8About 9,000 MW of gas capacity was scheduled on 23 July and delivered nothing
8Tanda's four 110 MW units have generated nothing since April on fuel conservation
8Barauni Units 6 and 7 carry 14 days of coal against zero megawatts of capacity Details
8Twenty-four of the CEA's 31 monitored reservoirs sit below last year at the peak of the monsoon
8Srisailam holds 147.9 MU of a possible 1,391.84 MU and has generated 4.23 MU since 1 April
8Telangana's reservoir energy falls to 130.5 MU from 1,847.3 MU a year earlier
8Singur drops below its minimum draw-down level with 0.0 MU of equivalent energy
8Nagarjunasagar sits 3.2 feet above dead storage, down 96.5% in stored energy
8Pochampad falls to 1.5 TMC live storage, one foot above its dead-storage level
8Pulichintala and Nizamsagar are the only two Telangana reservoirs above last year
8Periyar sits 0.74 metres above dead storage with 9.72 MU of a possible 216 MU
8Mettur falls for a third straight day on nil inflow, 13.84 metres below last year
8Idukki sits 11.63 metres below last year as its inflow falls for three straight days
8Four of Odisha's seven OHPC power houses generated nothing on 24 July
8Hirakud spills through 16 gates at 27,358.72 cusecs beside an idle Odisha hydro fleet
8Machkund sits 20.65 feet below its year-ago level, the deepest deficit in Odisha
8Southern reservoir aggregate rises 3.2% while 13 of 14 stores sit below last year
8Linganamakki and Supa inflows collapse to 0.11 and 0.05 in a single day
8Nilagiris prints a zero level while carrying 647.92 of energy content
8Kundah Group and Loktak report incomplete reservoir data to the CEA on 23 July
8Western reservoirs are the country's best filled, Bhira 0.99 metres from full
8The 31 CEA reservoirs have generated 11,498 MU of a 49,833 MU annual design potential
8All four Kadamparai units, 400 MW, are out on rotor and stator faults into 2027
8Salal takes all six 115 MW units off for reservoir flushing, 690 MW out since 18 July
8Sardar Sarovar riverbed power house generated nothing against an 11.23 MU programme
8OHPC's daily sheet prints two totals, 6.517 MU and 13.034 MU, an exact double-count Details
8No CERC order in the day's folder - a live consultation, three notices and one APTEL judgment
8APTEL partly allows Tata Power's Jojobera appeal and remands six of eight issues to JSERC
8CERC's FY 2026-27 generic renewable tariff consultation draws seven responses
8Star Wire asks CERC to lift Haryana biomass fuel cost to Rs 5,337 per tonne
8Himachal small-hydro association seeks Rs 1,266 lakh per MW capital cost
8Yadlapati files the Himachal association's case verbatim for its 9 MW Kut station
8MPPMCL, the only buyer on the record, asks CERC to cut the 10.71% interest on loan
8Devbhoomi Hydro seeks a 7% rise to Rs 1,284 lakh per MW for Uttarakhand small hydro
8Arunachal's state hydro PSU asks Rs 14–15 crore per MW, the consultation's largest ask
8Karnataka developers ask CERC to split MNRE's small-hydro subsidy 50:50
8The hydro bloc files three different capital costs for the same norm
8New India Assurance bars new hydro risks in Himachal and Uttarakhand districts
8CERC proposes a Category-V trading licence for PI Green Consulting, hearing 6 August
8CERC proposes a transmission licence for POWERGRID's Mahan–Rewa 400 kV double circuit
8CERC proposes a 220 kV bay for a 250 MW Rajasthan battery at Bhadla-III Details
8GERC excuses 226 of 535 delay days on Virgo Aluminum's Rs 2.31 crore minimum-charge bill
8GERC gives Surya Roshni 31 of 152 delay days against an eighteen-month claim
8GERC lets GIFT Power bill HT-tariff consumers metered at low tension
8GERC allows GIPCL Rs 41.99 crore safeguard-duty relief, lifting the Raghanesda solar tariff to Rs 2.88
8GERC dismisses Renewgain's extension plea, exposing Stage-II connectivity and a Rs 2 crore bank guarantee
8UPERC admits Adani's licence bid for the DC Development Noida data-centre park, heard 30 July
8WBERC orders a Rs 2.00 per kWh subsidy for WBSEDCL's agricultural irrigation consumers from August 2026
8CESC's 300 MW wind-solar hybrid PPA dies as WBERC disposes of the approval petition as infructuous
8KSEB asks KSERC to price new connections at Rs 1,563 per kW
8UPCL asks UERC for an additional surcharge of Rs 0.88 a unit
8JSERC puts out draft intra-State deviation settlement regulations with 200% penal rates - not yet in force
8Tata Steel's FPPA-definition petition dismissed as withdrawn at JSERC, no liberty reserved
8Tata Steel's 2015 JREDA petition reaches its 35th JSERC hearing with argument still not begun
8Inland Power retires 66 JSERC proceeding entries in one sitting, withdrawing three cases
8JSERC orders JREDA to publish public notice in two tariff petitions against JBVNL
8Usha Martin's JREDA petition part-heard at JSERC, 14 August set as last chance
8JBVNL files counter affidavit against Hindalco at JSERC, rejoinder due before 18 August
8Eastern Coalfields' case against JUSNL adjourned at JSERC for want of senior counsel
8JBVNL wins deferral of all three Inland Power tariff files, oldest nine years and unargued
8ESL Steel's three JREDA petitions each reach a 13th JSERC sitting, adjourned to 14 August
8Amalgam Steel's two JREDA petitions hit 16 sittings each without argument concluding
8Tata Steel's Cases 09 and 10 of 2025 against JREDA adjourned at the ninth sitting
8Tata Steel briefs senior counsel in Case 11 of 2025 as JSERC grants a last indulgence
8JSERC's full 21-case board produced no decision on merits, only four withdrawals Details
8MNRE publishes a model 15-year "Electrolyser as a Service" contract under the Green Hydrogen Mission
8PM Surya Ghar released Rs 11,191.53 crore across 14,20,606 rooftop installations
8Maharashtra took about 60 of PM KUSUM's 111 central releases in 2025
8MNRE released Rs 506.64 crore of solar park assistance across 22 named parks
8Suryamitra has trained 66,351 solar technicians with 33,705 in employment
8MNRE carries 22 pending C&AG paragraphs, nine still without action taken notes
8NLDC backed down 7,692 MW of wind and solar on 24 July to control high-frequency underdrawal
8REMC-monitored renewables ran 140.75 MU below schedule on 24 July
8Tripura's TSECL–TREDA memorandum for 20 solar handloom installations is still unsigned
8REL Wardha Solar 4's 19.8 MWac plant runs below 1.0 times debt cover through FY 2028
8Hexa Energy W5's 19.8 MWac Wardha solar plant faces a 14-month gap in contracted offtake Details
8Adani Energy Solutions wins a Rs 8,500 crore Vizag green-hydrogen evacuation system
8Adani Energy Solutions shareholders clear a Rs 10,000 crore QIP in a twenty-minute EGM
8Jindal Steel's standalone profit tops consolidated at Rs 1,085.97 crore for Q1 FY27
8Jindal Steel replaces its managing director, CFO, COO, HR head and auditor in one meeting
8Jindal Steel carries Rs 4,541.94 crore of loans to a Mauritius arm with negative net worth
8Jindal Steel puts a further Rs 407 crore into its Angul subsidiary through preference shares
8RattanIndia Power's Q1 profit of Rs 44.36 crore came from finance cost, not from revenue
8REC posts a Rs 4,149 crore quarterly profit, up 23 per cent on the March quarter
8CG Power spends Rs 121.85 crore of QIP money on its power transformer plant, and nothing else
8Institutions cast 8.70 per cent against CG Power chairman Vellayan Subbiah's re-appointment
8CG Power's 89th AGM confirms an interim dividend of Rs 1.30 a share for FY26
8TARIL's Q1 order inflow triples to Rs 2,114 crore on a PGCIL ultra-mega transformer award
8NTPC clears Indo Tech Transformers to build 400 kV transformers for battery storage
8S&S Power's subsidiary wins a Siemens Energy isolator order for KCC Wagdari, Maharashtra
8Waaree Renewable's consolidated revenue overtakes standalone for the first time, at Rs 929.53 crore
8High Energy Batteries swings to a Rs 181.50 lakh quarterly loss as income falls 43 per cent
8High Energy Batteries reconstitutes its five-member audit committee from 25 July 2026
8Fire shuts part of Panasonic Energy India's Pithampur plant, with loss still unquantified
8NHPC gets Dr Bernadette Lyngdoh as woman independent director on a Ministry of Power nomination
8Jaiprakash Power Ventures loses independent director Vandana R. Singh to the six-year cap
8Karma Energy's promoter block votes its own MD's pay revision through on 74.7 per cent of equity
8ACME Solar discloses Rs 967.82 crore of new Crisil A+ subsidiary ratings outside Regulation 30
8Ravindra Energy's associate signs HPCL for truck battery swapping at 25,000-plus outlets
8Surana Solar's Q1 profit is almost entirely other income - Rs 635.54 lakh of a Rs 637.07 lakh pre-tax result

Ratings Watch

8CARE holds Chandrika Power at D on Rs 106.00 crore after term-loan default
8CARE reaffirms A-; Stable on Rajasthan IV 4B Power Transmission's Rs 4,615 crore
8ICRA upgrades Marine Electricals to A- and enhances limits to Rs 419.50 crore
8ICRA assigns A- to REL Wardha Solar 4's Rs 88.84 crore despite sub-1.0 coverage
8ICRA assigns A- (Stable) to Hexa Energy W5's Rs 83.75 crore term loan
8Juniper Green Energy's Rs 1,800 crore IPO is all fresh issue, opening 30 July
8SMIFS initiates on Techno Electric, whose order book has fallen five quarters running
8JSW MG Motor unveils MG ADAPT, a platform hedged across four powertrain types Details
8Northern Region's main defence scheme delivered 530 MW of relief as Rihand lost 2,300 MW
8NTPC's Singrauli SPS card date has not moved from December 2026 across four PSC meetings
8A 2,000 millisecond fault clearance took out all 2,300 MW at Rihand on 18 June
8Seven of the Northern Region's 25 grid events in June 2026 had no fault at all
8Northern Region under-frequency relays delivered about 42% of planned load relief on 13 May
8Punjab lost about 850 MW of load to an unwanted df/dt operation on 27 May
8NRPC makes 49.6 Hz battery disconnection a condition of first-time charging
8Three Tehri pumped-storage units took 22 forced outages in one month
8All 248 third-party protection audit observations in the Northern Region stand uncleared
8Rajasthan's RVPN logged 16 unwanted protection operations in June 2026
8About 37 of 141 Northern Region entities filed no June protection indices at all
8NRPC puts protection reporting on a new PARAM portal with one accountable officer per utility
8NRLDC asks the 70th PSC to approve tripping two 500 MW Rihand units on contingency
8Seven action items roll into the 70th PSC, the oldest live since January 2026
8A 765 kV Ghatampur–Rampur protection channel has been dead for 19 months
8ERLDC opened tie-lines after Bihar over-drew 1,055 MW at 49.49 Hz
8NTPC Kahalgaon Stage-I told to seek CERC exemption after four poor frequency responses
8POWERGRID has replaced 23% of 28,058 defective insulators on the Kolkata 765 kV corridor
8WBPDCL has not told the West Bengal despatch centre why Kolaghat Unit-3 burned on 18 June
8GRIDCO refuses NTPC's Rs 1.5 to 1.8 crore a month flue-gas charge at Darlipalli
8Eastern Region under-frequency load shedding is 276 MW short, Sikkim entirely
8A grid-security scheme has rolled for eight months and JSPL did not attend
8OCC tightens NHAI shutdown rules after a 22-day outage cut ER–SR transfer by 650 MW
8CERC lets ERLDC keep scheduling PVUNL's 2,400 MW Patratu station until June 2027
8ERLDC admits it has no data on any data centre in the Eastern Region
8ERPC minutes give two incompatible dates for NTPC Talcher Unit-2's overhaul
8ERPC fixes 20 August in Kolkata for the 242nd OCC with no agenda yet written
8The Northern Region owes Rs 360.48 crore in deviation charges for one July week
8NRPC re-bills February 2025 deviations, swinging Rs 11.94 crore against Haryana
8WRPC withdrew a settlement statement in two days after Goa proved the schedules were wrong
8The WR–ER interface alone carried Rs 241.32 crore of deviation charges in one week
8Western Region bills 4,314 MW of connectivity granted to plants that were never built
8MPPMCL and Haryana owe Jhabua Power Rs 4.25 crore for backing it down
8Western thermal stations delivered 76% of scheduled ramps and lost no return on equity
8NTPC Vindhyachal Stage I scored 0.02 on frequency response in May 2026
8Eight gas stations earned Rs 468.74 crore of ancillary payments at Rs 22.3 a unit
8The ancillary services market cleared no up-regulation at all in June 2026
8Renewable curtailment peaked at 19,281 MW in June with no compensation paid
8The deviation and ancillary pool closed June 2026 Rs 123.91 crore in deficit
8PSPCL and PSTCL mass leave extended from four days to six, 21–26 July 2026
8PSPCL declares the six-day mass leave dies non and records that consumer supply was disrupted
8PSPCL reinstates a suspended lineman to Protection Division Moga with Chargesheet C-62 still live
8PSPCL promotes three linemen to officiating junior engineer, all vacating 66 kV sub-station posts
8PSPCL promotes six ministerial staff off four June anchor orders still unwinding
8PSPCL moves six gazetted engineers, reshuffling three posts at GGSSTP Ropar by 31 July
8PSPCL puts 25 superintending engineers on a tentative seniority list
8PSPCL fixes a pro-rata method for duty-exemption refunds, conceding its field offices had differed
8PSPCL carries 5,904 unsettled audit paragraphs, the oldest marked "up to 3/80"
8PSPCL's 19-name Revenue Accountant panel requires certifying strike participation, issued on the dies non day
8KSEB publishes a provisional AEE (Electrical) gradation list, objections closing 31 August 2026
8KSEB's 171-name AEE degree-quota list is headed by an officer recorded as deceased
8KSEB's realised AEE quota split runs 81.8 to 18.2 against a mandated 75 to 25
8NBPDCL censures a junior electrical engineer after 388 connection applications from one camp went unactioned
8SBPDCL calls a 29-field HRMS form from headquarters staff by 27 July under a BSPHCL direction
8JVVNL adopts a pay-fixation re-verification that makes verifying officers personally liable
8The Power Ministry's consultative committee discussed parallel distribution licensing on 23 July
8Lok Sabha coal panel takes up its washed-coal draft report for adoption on 27 July
8Ministry of Steel, SAIL and NMDC summoned to brief the coal panel on 29 July Details
 For reference purposes the website carries here the following tenders:
 8Tender for attending roof leakage and special repair works Details
 8Tender for certain repair works Details
 8Tender for improvement work by providing paver block pavement Details
 8Tender for procurement of T&P for meeting emergency breakdown and other works in various Details
 8Tender for procurement of T&P for meeting emergency breakdown and other works in various transmission lines Details
 8Tender for developer for setting up of 265 MW/530 MWh standalone battery energy storage systems Details
 8Tender for setting up of 265 MW/530 MWh standalone battery energy storage systems Details
 8Tender for work of maintenance 33 kV and 11 kV incoming and outgoing VCB pannel Details
 8Tender for work of construction of 11 kV/L.T. line, double pole Details
 8Tender for erection and installation of 63MVA T/F along Details
 8Tender for increasing capacity of 132/33kV substation Details
 8Tender for construction of civil work of increasing capacity Details
 8Tender for civil construction works of 01 No 132 kV bay related civil works Details
 8Tender for civil maintenance upkeeping work at various volts transmission sub stations Details
 8Tender for replacement of existing ACSR panther conductor of approx. 96.90 Ckt km of 132 kV lines Details
 8Tender for complete repairing and overhauling of DG sets Details
 8Tender for installation and commissioning of modular type sewage treatment plant Details
 8Tender for repairing and replacement of water supply pipeline Details
 8Tender for foundation and slab for installation of the distribution transformer and distribution panel Details
 8Tender for repair and strengthening of existing hoarding structure Details
 8Tender for erection of new 6.6kV feeder Details
 8Tender for erection of 1.5 KM total 3 KM over head line Details
 8Tender for construction of preparatory com-plete isolation stoppings Details
 8Tender for misc work related Details
 8Tender for miscellaneous civil works Details
 8Tender for special estimate for painting of RHR gates (upper And lower) of bay Details
 8Tender for restoration of protection wall Details
 8Tender for annual / running and breakdown maintenance of pipe lines including Details
 8Tender for construction of new power house Details
 8Tender for annual maintenance for all three generating units Details
 8Tender for repair and renovation of project Details
 8Tender for protection works for hill slope stabilisation of right and left banks Details
 8Tender for slope protection of right bank hill slope Details
 8Tender for cladding of existing wire crate protection wall at switchyard Details
 8Tender for HT construction and reconductoring with 120 ABC Details
 8Tender for supply of materials Details
 8Tender for construction of 33/11 kV, 1x3.15 MVA sub station Details
 8Tender for outsourcing the job of operation and maintenance of H.T and L.T distribution network Details
 8Tender for procurement of sub station equipment for 2x6.3 MVA, 33/11 kV sub station Details
 8Tender for supply of 11 kV heat shrinkable termination kits, 11 kV heat shrinkable cable straight jointing Details
 8Tender for supply of LT distribution panel box suitable for 25KVA, 63KVA, 100 KVA , 250 KVA, transformer/sub station Details
 8Tender for work contract for preparation of scaffolding for insulation work Details
 8Tender for repair/maintenance of power house Details
 8Tender for construction of 33 kV S/S Details
 8Tender for supply, erection, installation, testing, and commissioning of materials/equipment Details
 8Tender for requirement of spares of CW and raw water chlorination system Details
 8Tender for procurement of poly aluminum chloride (high basicity PAC liquid) required Details
 8Tender for procurement of sulphuric acid Details
 8Tender for procurement of sodium hypochlorite required Details
 8Tender for procurement of liquor ammonia required Details
 8Tender for procurement of hydrazine hydrated lime (Grade-A) required Details
 8Tender for procurement of hydrated lime (Grade-A) required Details
 8Tender for work of 11kV line extension and installation of 100 KVA DTR Details
 8Tender for transformer installation with drawing UG cable Details
 8Tender for construction of 110kV substation Details
 8Tender for leasing of fiber optic network links Details
 8Tender for construction of 33 kV substation Details
 8Tender for construction of common facilities Details
 8Tender for biennial rate contract for lifting shifting of HT/LT motors Details
 8Tender for supply of 11kV VCB INC panel Details
 8Tender for procurement of 22 kV polymer composite pin insulators. Details
 8Tender for rate contract for the work of loading, transportation, unloading & stacking of all types of EHV equipment / material Details
 8Tender for supply & installation of e-DAQ (energy data acquisition) and automatic log sheet generation Details
 8Tender for work of radiator cleaning of convertor transformer & smoothing reactor Details
 8Tender for supply, installation & commissioning of neutral grounding reactor (NGR) for power transformer at various S/s Details
 8Tender for work of supply, installation, testing & commissioning (SITC) of dedicated infrastructure required Details
 8Tender for work of chemical washing (manually by using high voltage insulator cleaner and protector) of insulators strings Details
 8Tender for work of supply & installation of eDAQ (energy data acquisition) and automatic log sheet generation Details
 8Tender for annual maintenance contract (AMC) for the demonstration, preventive maintenance as well as repairing work including supply of required Details
 8Tender for work of providing & fixing of additional jumpers on tension towers of the various lines Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8How Renewable Diesel is Reshaping India’s Energy Landscape Details
 
8Coal overtakes gas in power generation Details
 
8India’s solar-wind output surges 25% as renewables overtake coal globally: IEA Details
 
8Inox Green signs O&M agreements for 639 MWp solar projects across India Details
 
8ONGC and Oil India sign JOA for three blocks awarded in OALP round IX Details
 
8Engineers India appointed as Project Management Consultant for Rs 1200 crore academic institute development Details
 
8Juniper Green Energy IPO Price Band Rs 214-225; Opens July 30 Details
 
8Industrialists urge TN government to fulfil long-pending industrial sector demands in budget Details
 
8The Difference Between a Battery Fire and a PCS Failure in a BESS Details
 
8APCPDCL synchronises 50,114 rooftop solar connections under PM Surya Ghar scheme Details
 
8Nuvama Forecasts 39% CAGR in India's ACC Demand Through 2030 Details
 
8Juniper Green Energy IPO: Price Band Set at Rs 215-225 Details
 
8ENGIE Achieves Financial Closure For 250 MW Khaba Solar Project In Rajasthan Details
 
8Sinovoltaics updates solar module manufacturer financial stability ranking Details
 
8Corrosion Costs India Rs 14 Lakh Crore Annually: Nomura Report Details
 
8IEX Q1 PAT Rises 11.7% YoY to Rs 134.8 Crore Electricity Volumes Up 15.9% Details
 
8Waaree Renewable Gets Award Letters For 800 MWac Solar EPC Contracts Totaling 1,082 MWp Details
 
8Coal overtakes gas in power generation Details
 
8Global Coal Use Hit A Record In 2025, Even As Coal Power Declined Details
 
8Winding Wires Surge as India Powers Up Electrification Boom: PhillipCapital Details
 
8Very proud of India's youth power: PM Modi in Mann Ki Baat Details
 
8India's next commodity cycle could be driven by scrap as organised metal recycling gains momentum Details
 
8NTPC Reports Strong Q1 FY27 Results, Profit and Margins Rise Details
 
8Nepal Meets Power Demand Without Imports As Exports Reach 22,102 MWh Details
 
8BEL, Coal India, Tata Power Q1 Results Today, July 27 Details
 
8India’s solar-wind output surges 25% as renewables overtake coal globally: IEA Details
 
8Adani Enterprises, GE Vernova, and 6 Other Stocks in Which SBI Group Bought Fresh Stakes in Q1 FY27 Details
 
You can also click on Newsclips for more Details
 For reference purposes the website carries here the following tenders:
 8
Tender for running works contract for the erection works of LT overhead feeder, HT overhead feeder, structure erection works, dismantling works Details
 
8Tender for procurement of 11 kV standalone structure material complete set Details
 
8Tender for empanelment of agencies for new 33/11kV substation, additional/augmentation of PTR Details
 
8Tender for annual work contract for various sample collection, preparation of chemical solution and dozing along Details
 
8Tender for repair and strengthening of plant Details
 
8Tender for R&M work in WR1 Details
 
8Tender for AMC for work of repairs of 220kV isolator, 100kV isolator and 22kV isolator and cable termination and joints at various Details
 
8Tender for work of supply, installation and commissioning of 100% hot redundancy based continuously available Details
 
8Tender for purchase of various capacity of 11kV HTMC with resign cast CTs & PTs Details
 
8Tender for installation, and commissioning of 1.1 kV AL59 ACS covered conductor Details
 
8Tender for construction of new control room on pile, cable trench Details
 
8Tender for supply and installation of number plate, danger plate, circuit plate, phase plate Details
 
8Tender for supply of various types of hardware fittings for 220kV and 400kV HVAC transmission lines Details
 
8Tender for supply, installation, testing and commissioning of 48V 525 AH or nearest higher capacity Details
 
8Tender for Bi-annual rate contract for shifting/modification work of existing various 66/132/220 kV class transmission lines Details
 
8Tender for rewinding mechanical repairing of four nos. of HT motors Details
 
8Tender for replacing of tongue rail, points and crossing sleepers and miscellaneous S and T works Details
 
8Tender for installation and commissioning of 1000mm. wide x 333 mtr. belt conveyor Details
 
8Tender for new installation of cradle guard and lighting arrestor Details
 
8Tender for providing temporary room in substation yard Details
 
8Tender for providing barbed wire fencing Details
 
8Tender for stop gap arrangement for annual comprehensive maintenance for civil works Details
 
8Tender for operation, maintenance and providing civil and electrical maintenance Details
 
8Tender for repairing of trailing cable jointing Details
 
8Tender for rewinding and repairing of different capacity and rating of LT electric motors Details
 
8Tender for construction of 32 nos RCC isolation stopping for sealing Details
 
8Tender for rewiring /renewal of wiring Details
 
8Tender for new construction of 33/11 kV sub station Details
 
8Tender for work of replacement of existing old/static/obsolete-technology busbar protection schemes at various EHV substations Details
 
8Design, fabrication, supply, installation, testing commissioning of 6 mtr solar high mast Details
 
8Design, fabrication, supply, installation, testing commissioning of solar street lights Details
 
8Tender for procurement of rockwool mattress, cladding sheet & alumminium sheet for insulation work Details
 
8Tender for R&M work of replacement of conventional insulators by silicon rubber insulators Details
 
8Tender for providing and installation of suction mouth and nozzle Details
 
8Tender for contract for miscellaneous civil works Details
 
8Tender for construction of new storage tanks with associated facilities Details
 
8Tender for supply, installation, testing and commissioning of transformer Details
 
8Tender for augmentation of 220 kV substation Details
 
8Tender for replacement of old and defective DTR LT cables Details
 
8Tender for electro-mechanical works of 3x100 MW Details
 
8Tender for running works contract for the erection works of LT overhead feeder Details
 
8Tender for running works contract for the erection works of LT overhead feeder, HT overhead feeder, structure Details
 
8Tender for running works contract for the erection works of LT overhead feeder, HT overhead feeder, structure erection works Details
 
8Tender for reconstruction of damaged bridge over Details
 
8Tender for maintenance of 400 kV D/C line from tower Details
 
8Tender for empanelment of agencies for restoration of distribution infrastructure during Details
 
8Tender for estimate for erection 33 kV line Details
 
8Tender for Est for 33 kV feeder Details
 
8Tender for procurement of various spares of air pre heaters PAPH and SAPH installed Details
 
8Tender for procurement of ESP spares for model FAA 9X45M 2X80150 2 ESP Details
 
8Tender for procurement of spares for chain link assembly installed Details
 
8Tender for supply and application/dosing for enhancement in coal flow ability Details
 
8Tender for procurement of spares of HPBP actuators Details
 
8Tender for work of providing & fixing of standalone / dedicated numerical over voltage protection relays Details
 
8Tender for rate contract for removing, lifting, shifting, dismantling and overhauling of 6.6 kV HT motors Details
 
8Tender for construction of RCC retaining wall Details
 
8Tender for work of complete overhauling / breakdown maintenance of C.W pumps Details
 
8Tender for supply of 100 Amp. L.T. distribution kiosks Details
 
8Tender for supply of 11kV polymer composite pin insulators Details
 
8Tender for supply of SAM pumps and spares Details
 
8Tender for supply of dynavane self-cleaning inertial seal air filter installed Details
 
8Tender for work of strengthening, fabrication and erection of steel structures Details
 
8Tender for procurement of boiler tube guard of economizer coil Details
 
8Tender for procurement of boiler tube guard of different sizes Details
 
8Tender for service contract for overhauling of high pressure valves Details
 
8Tender for procurement of 400 kV CT Details
 
8Tender for coal transportation and allied jobs Details
 
8Tender for supply of 40 numbers of service junction box and 40 numbers of LT distribution kiosk Details
 
8Tender for procurement of current transformers (132kV and 66kV C.T) Details
 
8Tender for release of new service connections of new HT line Details
 
8Tender for cleaning the disc insulators checking the tightness of bridgings and earth clamp condition of hardware fitting Details
 
8Tender for removal of the existing 200 MVA single phase transformer bank from 220kV substation Details
 
8Tender for constructing UG cable feeder Details
 
8Tender for interlinking of feeder Details
 
8Tender for construction of a new 220/66kV system at 220kV substation Details
 
8Tender for biennial rate contract for repairing, replacement, and maintenance of damaged, torn, and burnt NN fire resistant conveyor belts Details
 
8Tender for supply of submersible pump motor set capacity Details
 
8Tender for providing and laying of gunny bags at various towers of 132kV line Details
 
8Tender for stub strengthening and offshoot repair of 220kV line Details
 
8Tender for manufacturing, supply, testing and delivery of 11 kV VCBs SCADA compatible Details
 
8Tender for augmentation of conductor of 33 kV line from 33/11 kV sub-station Details
 
8Tender for work of providing and fixing of additional 33kV PT set along with bus section isolator Details
 
8Tender for work of overhead termination arrangement of hybrid bay at 132 kV S/S Details
 
8Tender for work of servicing & overhauling along with providing & fixing of required spares of 33kV circuit breakers Details
 
8Tender for work of providing by pass twin jumpering arrangement by boltless C type wedge connector to the jump at tension towers Details
 
8Tender for work of providing and fixing of nonconductive turbo wind driven conical bird guard for various EHV lines Details
 
8Tender for annual maintenance contract (AMC) for work of underground cables Details
 
8Tender for work of annual maintenance contract for various make air compressor for 132/220kV CBs at various EHV substations Details
 
8Tender for work of repair of faulty 33/11 kV CT’s & PT’s and repair of faulty / damaged station transformer available Details
 
8Tender for work of enhancement of existing corridor of 220kV line Details
 
8Tender for work of refurbishment, servicing and complete overhauling of hydraulic cylinder for clamping device of rotary wagon tipplers Details
 
8Tender for renovation & repairing with retrofitting work at various Details
 
8Tender for supply of various refurbished electronics modules Details
 
8Design, engineering, supply, erection, commissioning and testing of 2 nos 140 ton capacity pit less type in motion electronic rail weigh bridge Details
 
8Tender for work of penthouse roof restrengthening and repairing in boilers Details
 
8Tender for supply, installation, testing & commissioning of conversion of 66kV S/C line Details
 
8Tender for supply, installation, testing & commissioning of conversion of 220kV line Details
 
8Tender for supply, installation, testing & commissioning of conversion of 220kV D/C line Details
 
8Tender for supply, installation, testing & commissioning of conversion of 220kV line Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8The Missing Layer: Floating solar can unlock India’s untapped renewable potential Details
 
8Decoupling ambition meets supply-chain reality: China’s role in India’s solar squeeze Details
 
8BioEnergy Global 2026 set for New Delhi this July Details
 
8Global power demand to grow 3.6% in 2026 as renewables overtake coal: IEA Details
 
8Inox Wind and KP Energy sign strategic MoU to jointly develop 2.5 GW wind projects across India Details
 
8Chandigarh Shifts Rooftop Solar Focus To Private Homes After Govt Buildings Installations Details
 
8Adani Energy Secures Major Andhra Transmission Project, Takes Order Book Past Rs 80,000 Crore Details
 
8RattanIndia Power Q1 FY27 Net Profit Reaches Rs 44.36 Crore Details
 
8From Capacity to Reliability: Four Reforms for Powering Viksit Bharat 2047 Details
 
8India’s battery storage market faces volatility, seeks new growth Details
 
8India's energy transition enters a new phase as experts call for AI, storage and finance push Details
 
8Govt discusses parallel distribution licensing framework to give consumers choice of power supplier Details
 
8Balimela resumes power generation after PIP releases water for five days Details
 
8ACME Solar scales BESS capacity to 3.62 GWh Details
 
8Rays Power Infra Expands Power Infrastructure Footprint in Rajasthan, Commissions Critical 400 kV Grid Assets with Extra Voltage Transmission Line Details
 
8IEX rises after Q1 PAT climbs 12% YoY to Rs 135 crore Details
 
8Power Ministry discusses parallel distribution licensing framework to give consumers choice of electricity supplier Details
 
8India Power Demand Climbs 11% in July Amid Heatwave Details
 
8DVC Appoints IAS Officer Rajesh Pandey as 51st Chairman, Begins New Era of Growth and Innovation Details
 
8AI And Smart Grids Key To Affordable Power, Say Technical Experts At The SGSITS Details
 
8S&S Power Switchgear Bags Rs 8 Crore Order from Siemens Energy India Details
 
8Power Ministry Plans New Electricity Distribution Rules Details
 
8Adani AESL Wins Rs 8,500 Crore Big Green Hydrogen Transmission Project in Vizag, Andhra Pradesh Details
 
8RMC Switchgears Bags Rs 2.84 Crore Order from Jaipur Vidyut Vitran Nigam Details
 
8POWERGRID CMD Burra Vamsi Rama Mohan Gets 3-Month Extension as Director (Projects) Details
 
8REC Reports Strong Q1 FY27 Results; Profit Rises 23% to Rs 4,149 Crore, Board Declares Rs 4.25 Dividend Details
 
8NTPC subsidiary announces COD for solar project in Gujarat Details
 
You can also click on Newsclips for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8LPG
8Ammonia

8All tankers
8Bulk and Dry cargo

Click on Reports for more. Details
8IEX's day-ahead hit the ceiling at both peaks and the floor at noon on 23 July
8IEX green power cleared above grey on 23 July - a Rs 428 premium that flips the usual discount
8IEX's real-time market carried the whole country's spot power on 23 July - 190,887 MWh
8Contingency and intraday contracts pinned at the Rs 10,000 ceiling, bar the Western Region
8Green term-ahead was the only live green venue: DAC contracts cleared in the Rs 9,600–9,920 band all day
8PXIL's short-term segments sat dormant: its real-time and deviation markets both cleared nil on 23 July
8HPX real-time market drew bids but cleared nothing - a bids-only presence all week
8High-price day-ahead stayed dormant on both venues on 23 July
8The second exchange's green day-ahead stayed shut for a tenth straight day
8Exchange ancillary market cleared nil for a tenth day; reserves procured through regulated SCUC instead
8Intraday segment took buy bids but formed no price - 550 MWh of demand met no sellers
8WBSEDCL goes to reverse auction for 600 MW of September night-block power across three exchanges
8PXIL takes its trading portal down for two and a half hours in the early hours of 24 July Details
8India met a 231 GW peak on 23 July without dropping a megawatt anywhere
8The grid ran too high for seven hours of 23 July - too much power, not too little
8Operators switched off about 95,000 MWh of generation on 23 July - the grid had too much
8The West and East carried the country on 23 July while the North leaned on 418 MU of imports
8Surplus solar and light load pushed the Southern grid over-voltage for most of 23 July
8The North-East to Tripura corridor sat over its transfer limit for 56% of 22 July
8India leaned on Bhutan and Nepal for a net 24.8 MU import on 23 July
8Uttar Pradesh ran unscheduled load-shedding on 23 July though the region logged zero shortage
8Grid-India switched on a new 765 kV line into over-voltage Rajasthan on 23 July
8Karnataka and Tamil Nadu hit repeated ICT-overload emergencies on 23 July; Telangana ran high on voltage
8Monsoon floods knocked out much of Gujarat's EHV grid on 23 July, yet the West still met 60 GW
8A zero-shortage grid split the exchange price on 23 July
8The transmission committee cleared about Rs 15,000 crore of lines
8The Western grid's protection layer frayed across 54 spring disturbances Details
8Monsoon floods force mass EHV line openings across Gujarat's Western grid on 23 July
8About 50.6 GW sat out of grid on 22 July - forced outages more than double planned maintenance
8The West kept nearly 20 GW of generation switched off on 23 July and never missed it
8The South kept 11 GW out on 23 July, led by a badly degraded Neyveli fleet
8NTPC's Barh-2 and DVC's RTPS-2 lead 3,888 MW held out of the Eastern grid
8A cluster of UP and Punjab units tripped overnight on 22 July, Jawaharpur's twin 660 MW loss still out
8Two 400 kV double-circuits stay collapsed in Karnataka 60–70 days on
8NHPC's Teesta-III - all 1,200 MW - has now been forced out 21 months
8Some 33,884 MW has sat out of grid beyond a fortnight, much of it gas idled on costly fuel
8A further 6,105 MW has been stranded beyond a year
8Monsoon tube leaks run through NTPC's coal fleet - KSTPS-4 out fresh, Sasan-4 back on the same fault Details
8Coal-critical count eases to 27 plants on 22 July, but Damodaram Sanjeevaiah and Sasan still sit at 3%
8India's gas-fired fleet prints zero generation on 22 July as costly RLNG stays out of merit
8Coal India has tied up 617.7 million tonnes of long-term coal supply for power plants
8Coal-mining committee weighs 12 cases on 4-5 August - NCL's Jayant seeks a 30-to-38-MTPA jump
8Three more coal-mine cases reach the appraisal committee on 27 July Details
8Telangana's Krishna storage has crashed to 128 MU from 1,742 MU a year ago
8Four of Odisha's seven OHPC power houses generated nothing on 23 July as forced outages spread
8India's big reservoirs stay well short of full mid-monsoon, Bhakra 29 metres below its brim
8Sikkim's 1,200 MW Teesta-III stays dark into a 22nd month, keeping Eastern hydro minimal
8All 25 workers trapped at NHPC's Teesta-VI tunnel confirmed dead
8India plans 100 GW of pumped storage by 2035-36, with about 5 GW now seeking clearance Details
8Power-sector cases pile up - 1,193 pending at CERC, 2,911 at APTEL as on 30 June
8NGEL's Section 142 action against SECI reserved for order after both sides close arguments
8Jhajjar's claim that mandated biomass co-firing is a Change-in-Law cost is reserved for order
8GUVNL v Tata Power admitted - a 39-day 2024 force-majeure claim that could claw back capacity charges
8SJVN Green's GST change-in-law claim on its 1,000 MW Bikaner solar project admitted
8NRSS XXXVI keeps its shield: CERC continues interim protection against UPPCL's Rs 8.33 crore LD
8POWERGRID admitted to fold 28 transmission SPVs into two survivors under Section 17
8GUVNL v Adani adjourned sine die as fresh 1 June 2026 SPPAs await separate approval
8Bihar discoms' pilot-power compensation claims against PTC India adjourned Details
8GERC ties Essar's diverted-power claim to a set-off, replies due before the 701 MU crux
8GERC races a five-week clock to recompute Essar's delayed-payment charges on compound interest
8GERC adjourns Tarini's 16-year-old small-hydro tariff again as a fresh Supreme Court CUF order stays unuploaded
8UERC clears UPCL's Rs 8.16 crore Khatima 33 kV works but rebukes it for bidding before approval
8MERC throws out a Rs 5.82 crore tower-compensation claim as premature
8Uttarakhand Ombudsman bars UPCL from cutting a paying consumer's line at a third party's behest
8PSERC admits PSPCL's rooftop-solar rule change, sets a 12 August public hearing on Regulation 11.13
8KSERC lists a 6 August hearing on KSEB's per-kVA/kW charges, opening a consumer-facing tariff fight
8UPERC puts a full state grid code out for comment, hearing set for 1 September
8AVVNL stops buying 5 kVA single-phase transformers, upsizing to 10 kVA to pre-empt load growth
8MePDCL orders every stand-alone prepaid meter swapped for ADB-funded smart meters
8Power Ministry declines a uniform transmission RoW compensation policy, keeps no data on affected farmers
8Government lets four China-linked equipment makers back into power bids for two years
8Power Ministry reaffirms rural-electrification programmes closed in 2022 at 18,374 villages
8Power Ministry maps a Rs 24,819 crore Khavda–Nagpur HVDC for Gadchiroli-Chimur Details
8Wind-led renewables feed the grid 980 MU on 23 July; seven ISGS stations sit dark
8NTPC Green declares its first 64.76 MW at the 225 MW Khavda solar block commercial from 24 July
8SECI's rooftop Tranche-IX clears at Rs 2.94/kWh as Renergo sweeps nine of 14 RESCO projects
8MNRE sets the Bharat RE Summit for 2–5 November
8Grid-India confirmed as registry and meta-registry for India's carbon market under CCTS
8Haryana drafts a compressed-biogas policy targeting 43,000 TPD by 2047 on a Rs 2 crore/TPD subsidy
8EAC-PM's "Duck and Camel" paper puts the summer evening ramp near 74 GW and daily solar spill at ~24 GWh
8India's thermal build pipeline swells past ~13 GW at appraisal even as this year's additions stall
8Renewable installed capacity has overtaken coal: 236.5 GW against 224.2 GW
8India's storage pipeline hardens: a 100 GW pumped-hydro roadmap Details
8PFC clears the way to borrow up to Rs 9 lakh crore for the power build-out
8POWERGRID lifts its FY27 bond ceiling by Rs 5,000 crore to Rs 35,000 crore
8POWERGRID names R.M. Bansal and Chandra Wadhwa its joint cost auditors for FY27
8JSW Energy's Rs 4,000 crore QIP sits almost wholly unspent a quarter after the raise
8IREDA floats an RFP to raise a USD 100 million unsecured green ECB term loan
8IEX Q1 profit rises to Rs 135 crore as its gas-exchange arm IGX files to list
8ICICI Direct cuts TARIL to Reduce even as its order book hits a record Rs 6,630 crore
8NTPC is running behind its own plan this year, and the North is the drag
8Orient Electric rotates out S.R. Batliboi for Price Waterhouse as statutory auditor
8Patel Engineering books Rs 1.25 crore ex-gratia as all 25 Teesta-VI tunnel workers confirmed dead
8Ind-Ra upgrades JSW Energy Utkal's unsupported rating to AA-, affirms AA(CE)
8ICRA strips APRAAVA of its AAA, cutting it to AA+ after the Jhajjar thermal sale
8CARE keeps Lanco Vidarbha at 'D' with Rs 9,614 crore of bank facilities in default Details
8WRPC's weekly deviation account settles net Rs 11.53 crore in the Western pool's favour
8The Western grid saw 339 emergency ancillary dispatches in a week, nearly all backing plant down
8WRPC's 16th ISTS meeting adjudicates 13 disputed May trippings
8WRPC's ISTS slippage register runs across 8 developers - Khavda ICTs slip again, Sterlite's Goa line stuck since 2023
8IndiGrid's JTCL seeks Change-in-Law and Rs 18 crore for de-inducting a 765 kV line
8WRPC's protection committee tables 54 spring disturbances before its 29 July sitting
8The protection committee's oldest action items keep rolling - NTPC Lara's oscillation study open since the 163rd meeting
8CEA's transmission committee clears about Rs 15,000 crore of inter-state lines
8CEA issues Corrigendum-I to the 42nd NCT minutes, clarifying the Sasaram substation scope
8POWERGRID's Director (Projects) post stays vacant a fourth month as the CMD's charge is extended again
8President appoints an MNRE Joint Secretary to IREDA's board
8Coal India moves an HR manager from Eastern to Western Coalfields
8Government tells Parliament an integrated Ministry of Energy is "beyond the purview"
8PSPCL publishes tentative Chief Engineer seniority lists for Civil and Electrical cadres
8PSPCL calls disciplinary-case reports on about 142 engineers for a promotion-vetting drive
8PSPCL reaffirms that AEE promotees who have not cleared the DAE get no promotional increment
8PSPCL dismisses an East Zone clerk absent from duty since January 2020
8PSPCL posts a JE from leave to its NRSE & Thermal Design wing against a vacant post
8PSPCL deletes 8 of 10 clerk-trainees from an induction batch
8PSPCL deletes two entries from a 2025 regulation circular on a Board decision Details
8The answer to the evening-ramp problem is finally taking shape as a pipeline. The Central Electricity Authority's roadmap targets 100 GW of pumped storage by 2035-36, two viability-gap battery schemes together back 43.8 GWh with Rs 168 crore already disbursed, and the environment committee takes up about 5 GW of new pumped-hydro projects next week - Adani, ReNew, Jindal and Torrent among the developers. Details
8The Western region's protection papers, now backed by their full March-to-May annexure, catalogue 54 detailed grid disturbances and 48 inter-state line trips flagged for breaching reporting and protection standards - with disturbance recorders un-synchronised or never shared. The biggest were a 1,704 MW loss at JSW Mahanadi and 1,153 MW at Adani's Raipur; the most telling are the small ones, where a thrown wire or a stolen conductor blacks out a whole wind farm. Details
8Two 1,320 MW coal plants tell opposite credit stories on the same day. ICRA cut Aprava Energy - the former CLP India - from AAA to AA+ after it agreed to sell its Jhajjar thermal station, while CARE flagged Lanco Vidarbha Thermal's entire Rs 9,614 crore of bank facilities in default and marked the borrower non-cooperating. Ownership and cash flow, not the asset, decide which way a thermal plant's paper goes. Details
8The Indian Energy Exchange reported a June-quarter consolidated net profit of about Rs 135 crore, up 12%, on record traded volume of 37.5 billion units, and moved to spin its gas arm into the market: subsidiary Indian Gas Exchange has filed to list, and a SEBI order requires IEX to cut its stake from 47.3% to 25%. A new Indian Coal Exchange rounds out a push to trade every fuel, not just power. Details
8The disaster at NHPC's under-construction Teesta-VI hydro project in Sikkim is now final: all 25 workers trapped when the Samardung head-race tunnel gave way have been confirmed dead, the contractor Patel Engineering told the exchanges, and the company has announced ex-gratia of Rs 5 lakh to each family, about Rs 1.25 crore in all. It is the deadliest single incident on an Indian power project in years. Details
8The National Committee on Transmission cleared a slate of inter-state schemes worth roughly Rs 15,000 crore at its 42nd meeting - a Rs 4,378 crore Northern-grid STATCOM package, a Rs 3,673 crore Kadapa system and more - even as the Northern region set a 94 GW peak and reported transformers overloading at Bhiwani, Moga and Jhatikara. The build is chasing a grid that is already running hot. Details
8Grid-India's June operational report records installed renewable capacity at about 236.5 GW against coal's 224.2 GW - the crossover the sector has been approaching for two years is now on the books. Counting large hydro and nuclear, non-fossil sources make up 54.2% of a 548.86 GW national fleet, though coal still did roughly seven in ten units of actual generation. Details
8Expert appraisal committees are lining up more than 13 GW of fresh coal and lignite capacity - Vedanta's 5,600 MW, Jindal's 2,400 MW, a DVC–Coal India 1,600 MW joint venture and more - for environmental clearance over the next fortnight, on top of Torrent's Rs 22,915 crore ultra-supercritical proposal cleared for terms of reference this month. It is the forward book behind the country's stalled coal additions: the plants being started now for the demand of the 2030s. Details
8The Prime Minister's Economic Advisory Council has put hard figures behind the price split that has run all month: as rooftop and utility solar flood the middle of the day, the grid's evening pick-up - the "duck" turning into a steeper "camel" curve - now needs about 74 GW of ramp in a few hours, double what it was, while about 24 GWh of solar is curtailed daily for want of anywhere to put it. The paper's fix is storage and a market that pays for flexibility, not more megawatts. Details
8The IEX day-ahead market cleared about 150,767 MWh on 23 July at an average Rs 5,375 a MWh, but the average again hides a violently two-shape day: the price held at or near the Rs 10,000 ceiling through the overnight and evening windows and fell towards the floor in the solar-flooded early afternoon. The grid behind it was comfortable to surplus - a 231,045 MW peak met with essentially nil shortage - and the other two exchanges cleared nothing, leaving IEX to carry the entire national market. Details
8Heavy rain across South Gujarat, Kutch and Dadra & Nagar Haveli forced a run of extra-high-voltage lines out of service on 23 July, collapsed a 220 kV tower on the Pirana–Barjedi circuit and tripped both 765 kV buses at Vadodara on breaker-failure protection. The Western grid still met a 60,061 MW peak with no shortage and exported about 303 MU north and east - the weather hit the wires, not the supply. Details
8WBSEDCL's Rs 392-cr biennial PCC pole rate contract opens a promotional route for new Bengal makers but guarantees no minimum order
WBSEDCL's two-year rate contract for 8-metre and 9-metre PCC distribution poles carries an indicative Rs 392 crore value, yet commits to no minimum quantity for any empanelled maker. Alongside incumbents needing a 4,000-pole record, a promotional category lets factories in West Bengal enter through a 200-pole trial order before graduating. A converted EMD held as performance guarantee plus a 10% deduction from every bill lock up working capital across execution. Bids close 20 August 2026, with technical opening on 24 August.

 

8NTPC's 150 TPD CO2-to-green-urea EPC at Pudimadaka bundles carbon capture, hydrogen, nitrogen, ammonia and urea into one lump-sum package
NTPC's international EPC tender for a 150 TPD CO2-to-green-urea plant at Pudimadaka integrates five process blocks across two sites nearly 25 km apart, from licensing to guaranteed performance. Two technical amendments have lowered the CO2-capture block's minimum stable load from 50% to 40%, corrected stray "Rihand" references and deleted a redundant drawing. The deadline has moved twice, now 23 July 2026, signalling active pre-bid refinement of a technically demanding decarbonisation package. Bidders are pricing renewable-linked turndown, not just capital cost.

 

8GETCO's Rs 87-cr Mehsana HTLS reconductoring rewrites six commercial clauses through Amendment-I before bids close
GETCO's EPC package to convert 13 operational 66 kV lines in Mehsana Circle from ACSR DOG to equivalent HTLS conductor carries an estimated Rs 87 crore over a 12-month schedule. Amendment-I is embedded in the specification and reworks payment terms, liquidated damages, right of way, qualification, EMD return and price variation together. That makes commercial interpretation as decisive as the engineering scope, and bidders are told to price the revised terms from the outset. Bids close 14 August 2026, with physical submission by 21 August.

 

8NTPC's Pudimadaka LSTK bundles a 10 MLD water plant, fire system and 132/33 kV GIS into one contract with two-year O&M
NTPC's lump-sum turnkey tender at Pudimadaka combines a 10 MLD water treatment plant, fire-fighting system and 132/33 kV GIS substation under a single EPC contractor, with a mandatory 25-year design life and two years of comprehensive O&M. Eligibility is confined to Class-I local suppliers at 70% local content, needing Rs 225 crore of cumulative EPC experience including one Rs 75-crore job. Bid security is Rs 2 crore. The multidisciplinary scope favours large integrated EPC firms and pushes lifecycle reliability into the bid price.

 

88CSPGCL's Rs 3.49-lakh Marwa consultancy bundles a CGWA hydrological study with securing the groundwater NOC
CSPGCL's small but strategic consultancy for the 2×500 MW ABVTPS at Marwa asks one specialist to carry out a hydrological study and secure the CGWA No Objection Certificate for groundwater abstraction within the colony premises. By combining technical assessment with statutory approval, the utility places accountability for compliance execution — not just reporting — on the consultant. A date extension has reopened the window before bid opening. Submission and opening now fall on 31 July 2026.

 

8GETCO's Rs 109-cr Jambuva HTLS programme bundles twelve 66 kV corridors into one reconductoring package
GETCO's works tender to uprate twelve operational 66 kV lines in Jambuva Circle from ACSR DOG to equivalent HTLS conductor carries an estimated Rs 109.10 crore, retaining existing towers while raising ampacity. Bundling twelve live corridors into one contract makes outage planning, restoration and multi-site sequencing the real execution challenge, not conductor replacement alone. The scale raises the bar for smaller contractors and favours proven transmission EPC firms. Bids close 13 August 2026, with physical EMD by 20 August.

 

8POWERGRID's 765 kV Panipat GIS pre-bid tie-up ties a contractor to its TBCB tariff bid before the project is even won
POWERGRID's pre-bid tie-up for a 765/400 kV Panipat GIS substation and a 765 kV Pallu AIS extension pre-selects the lowest evaluated qualified contractor and binds it exclusively before POWERGRID files its Bikaner V tariff bid — with award contingent on POWERGRID winning the TBCB. Four qualification routes admit collaborators, parents and EPC partners, but Routes-2 and 3 demand an extra 10% collaborator guarantee. Turnover of Rs 502.91 crore and a 33-month clock apply. Bids close 19 August 2026.

 

8NPCIL and GSECL run parallel capability-led tenders: nuclear channel-temperature monitoring for MAPS and a QCBS PMC for Dharoi pumped storage
Two procurements at opposite ends of the value chain share one philosophy — capability over lowest price. NPCIL seeks end-to-end design, manufacture and commissioning of a computerised channel temperature monitoring system for MAPS, integrated with existing plant systems. GSECL, under QCBS, wants a project management consultant to prepare, evaluate and supervise its Dharoi pumped hydro storage project. Both carry 180-day validity; NPCIL closes 14 August 2026 and GSECL 21 August. One buys technology, the other project intelligence.

 

8SECI's 70 MW Ramagiri solar-plus-storage EPC makes a 25 MW/50 MWh battery an integral contract obligation, priced through reverse auction
SECI's single-package EPC tender pairs 70 MW of ISTS-connected solar at Ramagiri, Andhra Pradesh, with a 25 MW/50 MWh battery storage system, covering design through post-commissioning maintenance. A two-envelope evaluation is followed by an e-reverse auction, so commercial competitiveness decides the award once bidders clear technical qualification. The Rs 3.81 crore EMD raises the entry commitment, and success turns on managing battery integration without eroding margin. Bids close and open on 24 July 2026.

 

8PSPCL's Rs 10,000-cr bond mandate hires a merchant banker on firm mobilisation commitments, not advisory effort alone
PSPCL's RFP to appoint a transaction advisor cum merchant banker for raising Rs 10,000 crore through NCDs/bonds requires a firm commitment to mobilise at least Rs 2,000 crore — Rs 1,000 crore per phase — with payment linked to successful allotment. Evaluation is QCBS at 70:30, favouring execution track record and league-table standing over fee, and needs SEBI Category-I registration for five years. The deadline is extended to 29 July 2026, with technical bids opening 30 July.

 

8OPTCL's Rs 301-cr Meramundali–Mendhasal package pairs 400 kV HTLS reconductoring with substation works under one EPC contract
OPTCL's single-stage two-part tender replaces the existing Moose conductor with HTLS on the 400 kV Meramundali–Mendhasal D/C line and bundles associated substation modifications into the same package. At an estimated Rs 301.22 crore, it upgrades an operational corridor rather than building new, placing line and grid-interface responsibility under one contractor. The integrated scope raises the technical threshold and favours experienced EHV transmission EPC firms. Bidding runs through the OPTCL e-tender portal.

 

8POWERGRID invites early consortium partners for the ERES-47 TL05 765 kV Durgapur–Jeerat line before the TBCB bid
POWERGRID has floated an Expression of Interest to line up consortium partners for the 765 kV double-circuit Durgapur (new)–Jeerat (new) transmission line, Part-I, of the ERES-47 project ahead of tariff-based competitive bidding. Interested contractors must sign an NDA and submit the prescribed request letter to enter confidential technical discussions. The move signals early mobilisation of scarce EHV construction capacity before award. Detailed scope, qualification and commercial terms will follow in the bidding documents.

 

8GETCO's Rs 127-cr Dahej–Haldarwa 220 kV HTLS conversion flags six revised commercial clauses bidders must price before offering
GETCO's tender to convert 220 kV Dahej–Haldarwa Line-1 and Line-2 in Bharuch Circle from ACSR Zebra to equivalent HTLS conductor spans 119.251 circuit km at an estimated Rs 126.57 crore over 15 months. Amendment-I revises payment terms, liquidated damages, right of way, qualification, EMD return and price adjustment, and the notice explicitly warns bidders to study them before quoting. That makes commercial interpretation as weighty as engineering scope on a firm-price percentage contract. Bids close 18 August 2026.

Details
 For reference purposes the website carries here the following tenders:
 8Tender for supply & installation of power supply unit for battery charger Details
 8Tender for procurement of 5000sets 11kV 30KN strain disc hardware fittings for rabbit and weasel conductors Details
 8Tender for construction of balance compound wall at 230 kV feeder Details
 8Tender for work contract for laying of 33kV, 1x630 sq.mm XLPE UG cable Details
 8Tender for providing additional cable duct for erection of 230 kV bus bar protection panel Details
 8Tender for construction of fallen compound wall including fixing of MS "Y" angle with barbed wire Details
 8Tender for erection, testing, commissioning, trial operation & handing over of boiler and its auxiliaries Details
 8Tender for construction of protection wall at tower Details
 8Tender for supply of various sizes of hexagonal nuts and bolts, step bolts, spring washers Details
 8Tender for supply cum installation of new kiosk-based control and relay panel Details
 8Tender for supply of 36 kV PT accuracy 0.2S accuracy classes at various substations Details
 8Tender for regular operation and maintenance of electrical system Details
 8Tender for development, design and setup of 10 MLD water treatment plant Details
 8Tender for construction of monsoon flood damaged compound wall with retaining wall, yard metal, yard Details
 8Design, fabrication, supply, installation, testing commissioning of solar water heater at various Details
 8Design, fabrication, supply, installation, testing commissioning of 30 nos solar based LED street light systems Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 20 kW with net meter Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 25 kW with net meter Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 20 kW with net meter Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 20 kW Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 30 kW Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 30 kW with net meter Details
 8Tender for supply, installation, testing & commissioning of conversion of 66 kV Kheralu-Khanpur line Details
 8Tender for supply, installation, testing & commissioning of conversion of 66 kV line Details
 8Tender for work for hiring of BD155 or its equivalent capacity bull dozers for coal dozing/feeding & other works Details
 8Tender for supply of various sizes diaphragm valves Details
 8Tender for work contract for duct revival between ECO to air pre heater A and B flue gas duct Details
 8Tender for fabrication of general items seal oil tank bottom plate dome wall etc Details
 8Tender for renovation of room for setting up of laboratory for testing of biomass pellets Details
 8Tender for refurbishment / reconditioning works of ID Fan impellers Details
 8Tender for procurement of power quality meters Details
 8Tender for procurement of 1200 mm and 1500 mm wide conveyor belt. Details
 8Tender for repair and maintenance of damaged doors/windows of aluminium and allied works including Details
 8Tender for providing and fixing new fencing to separate the switchyard Details
 8Tender for transmission line Package- TL01 for design, engineering and construction of dedicated 400kV D/C transmission line with twin moose ACSR conductor Details
 8Tender for supply of 33kV 1250A outdoor vacuum circuit breaker Details
 8Tender for work for repairing of raincuts for bund protection Details
 8Tender for const. of 33 kV S/S Details
 8Tender for implementation of feeder data monitoring system Details
 8Tender for construction of store shed at 33 kV S/S Details
 8Tender for maintenance works of EHV equipment at various 400kV substation Details
 8Tender for requirement of spares of CW and ACW pumps installed Details
 8Tender for construction of control room, chain link mesh fencing, yard leveling and metaling, drilling tubewell and other civil work for new 33/11 kV S/s Details
 8Tender for construction of control room, chain link mesh fencing, yard leveling and metaling, drilling tubewell and other civil work Details
 8Tender for construction of control room, chain link mesh fencing, yard leveling and metaling, drilling tubewell and other civil work for new 33/11 kV S/s Details
 8Tender for construction of control room, chain link mesh fencing, yard leveling and metaling, drilling Details
 8Tender for appointment of an agency for development and operation of transformers, cables and conductors testing lab Details
 8Tender for procurement of filter elements of FRF regenerative system Details
 8Tender for annual work contract of loading of condition ash from the delivery points of ash silos Details
 8Tender for work contract for routine/preventive/breakdown maintenance of control and instrumentation equipment and its associated system Details
 8Tender for wheel wise load measurement Up gradation of existing 2 Nos. rail electronic in motion weigh bridge Details
 8Tender for work contract for routine maintenance of ESP Details
 8Tender for construction of 33/11 kV PSS Kandra Details
 8Tender for construction of 33/11 kV PSS Details
 8Tender for removal of the existing 200 MVA single phase transformer bank from 220kV substation Details
 8Tender for standardization of transformer station Details
 8Tender for shifting of electrical utilities Details
 8Design, manufacture, testing, supply and delivery of ACSR moose Details
 8Tender for work for dismantling of removal of old damaged corrugated sheet and fixing of corrugated 0.5 mm (roofing / cladding) Details
 8Tender for supply of various insulation materials for boiler Details
 8Tender for supply of various consumables, measuring instruments, Tools tackles, CPVC and fasteners items Details
 8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details
 8Tender for various maintenance works of wagon tippler Details
 8Tender for procurement of misc. electrical items Details
 8Tender for rate contract for one year for transportation carriage of materials Details
 8Tender for assistance in lifting/shifting and replacement of different HL/LT motors, replacement of bearing/coupling etc Details
 8Tender for biennial contract for various civil jobs Details
 8Tender for load testing and certification of 04 Nos. EOT cranes Details
 8Tender for manufacture, supply and ex-works delivery of 8m and 9m long PCC poles Details
 8Tender for procurement of 12 kV VCB switchgear panel set Details
 8Tender for construction of 11kV line Details
 8Tender for replacement/extra Ckt. of old/decrepit AB cable Details
 8Tender for supply of materials 11 kV line Details
 8Tender for construction of 11kV line Details
 8Tender for maintenance/ operation of 33/11 kV sub-stations, associated HT/LT lines Details
 8Tender for maintenance/ operation of 33/11 kV sub-stations Details
 8Tender for construction of other misc. civil works Details
 8Tender for maintenance/ operation of 33/11 kV sub-stations, associated HT/LT lines Details
 8Tender for supply of T&P equipment for mainteance of 33kV substations Details
 8Tender for work of annual maintenance contract for work of repair, servicing, overhauling and maintenance of window/split air conditioner Details
 8Tender for supply of spares and complete mechanism overhauling of 220kV & 132kV circuit breakers at various Details
 8Tender for construction of retention (protection) wall for the protection of tower Details
 8Tender for annual maintenance contract for overhauling/ servicing/ repairing of 33kV VCBs of various make at various EHV substation Details
 8Tender for work of servicing / overhauling of 145kV SF6 circuit breakers at various substations Details
 8Tender for rate contract for attending emergency breakdown and planned outage works on various 400 kV lines Details
 8Tender for Bi-annual maintenance & attending emergency breakdown work of 400kV transmission lines Details
 8Tender for work of overhauling of diverter switch and drive mechanism box of the OLTC of the transformers Details
 8Tender for work of strengthening of earth mat by providing and installation of enhanced chemical compound (EHCC) earthing electrodes Details
 8Tender for rate contract of excavation and laying of new power / control / telephone cables, replacement of faulty/damaged cables Details
 8Tender for providing and laying G. I. pipe Details
 8Tender for supply of fire water pump-3 with motor Details
 8Tender for supply, erection and commissioning of new street light poles with cable laying Details
 8Tender for work of dismantling replacement / repairing of PF pipe, orifice & PF bend of coal mills Details
 8Tender for repair, maintenance, and installation of plant/ systems/equipments Details
 8Design, supply erection commissioning and testing of water distribution system for natural draught cooling towers installed Details
 8Tender for supply of knife gate valve for ash handling plant Details
 8Tender for supply of LED flood light Details
 8Tender for supply, erection, testing, and commissioning of conversion of 66 kV line Details
 8Tender for supply, erection, testing, and commissioning of 132kV & 66kV equipments and materials Details
 8Tender for refurbishment / retrofitting of unit control desk (UCD) confirming Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8India on track to meet 2030 renewable energy target: Union MoS for New and Renewable Energy Details
 
8At Times Now event, Joshi spotlights wind solar energy advantages Details
 
8Suzlon Energy shares trade lower despite order win from Waaree Group Details
 
8Orient Cement Approves Q1 FY27 Results and Invests in Wind Power Firm Details
 
8Suzlon bags 201.6 MW wind energy order from Waaree Group for Andhra Pradesh project Details
 
8Experts Concerned, 81% Of SO? Emissions Around Delhi-NCR Come From Exempted Coal Plants Details
 
8Solar Urgency: India has made a smooth transition to green energy Details
 
8Power sector faces new challenges amid rising demand, says Manipur CM Details
 
8Indian Energy Exchange Reports 11.7% Growth in Q1 FY27 Consolidated Profit as Electricity Volumes Rise Details
 
8Adani Power's nuclear expansion depends on private-sector policy clarity Details
 
8India's Nuclear Mission Gains Major Momentum Details
 
8Global power demand to rise in 2026 and 2027, renewables outpace coal in power generation: IEA report Details
 
8Why Adani Green stocks are falling despite strong Q1 results Reasons Explained Details
 
8India targets 100 GW nuclear power capacity by 2047 Details
 
8Coal Stocks Fall To 13 Days As Power Demand Climbs Details
 
8India advances small reactor plans, targets five nuclear units by 2033 Details
 
8APGENCO felicitates Team India spinner Sree Charani Details
 
8India’s Data Centre Industry Set for Rapid Growth, Land and Power Remain Biggest Challenges: JM Financial Details
 
8REC stock reflects earnings recovery as borrowing costs reshape the outlook Details
 
8India Reaches 297 GW Clean Power; Eyes 500 GW Target by 2030 Details
 
8Coal Supplies 70% of India's Power As Demand Peaks at 270 GW Details
 
8IEA Forecasts 7% Electricity Demand Surge for India by 2026 Details
 
8Bondada Engineering gets CEA approval for energization for NLC India Renewable’s solar power project Details
 
8RattanPower Board To Review March Results On July 24 Details
 
8India Adds Record 6,057 MW Wind Power in FY26, Total Capacity Crosses 57,443 MW Details
 
8Adani Power Eyes 10 GW Nuclear Goal by 2035 Details
 
You can also click on Newsclips for more Details
8The IEX day-ahead market averaged Rs 5,249.71 a MWh on 22 July but sat pinned at the Rs 10,000 ceiling through the overnight and evening blocks and fell to Rs 1,379.70 in the solar-flooded early afternoon. None of it was scarcity - the grid met a 233,019 MW peak with essentially nil shortage; the crunch is the shape of the day, not a shortage of power. Details
8The Northern load-despatch pool's security-constrained unit-commitment account for 6–12 July shows Rs 46.28 crore paid to keep coal and gas units committed and run up, led by Rs 18.62 crore to NTPC's Dadri gas station. It is the same bill the Western and Eastern pools ran the same week - the cost of holding thermal ready while midday solar forces it down has now gone nationwide. Details
 1 2 3 >  Last ›

Showing 1–50 of 484 items