All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Nov 2026
KPTCL awards Hanur 220 kV substation package at Rs 209.08 crore on a single bid, 24.3% above estimate
8The 24-month package for 2×150 MVA transformation, a 13.458 km 220 kV DC line and 58.733 km of 66 kV links went to M T Kumar after Amendment-I let bidders qualify through a tower-design consultant.
8An unclear GST basis for the award, conflicting time-extension clauses, ceiling-based tower payments and contractor-funded ROW compensation keep pricing and cash-flow risk with the contractor.
GUVNL's 1,500 MW RTC auction fills the requirement in only two of eight months
8The tender for 1,500 MW of RTC and 1,500 MW of non-solar power from 16 November 2026 to 30 June 2027 drew RTC tariffs of Rs 8.90–10.00/kWh, with volumes ranging from 75 MW in November to 1,500 MW in February and March.
8Anonymous "XX" entries, unreconciled overnight delivery windows, no recorded acceptance or PPA quantities and an unclear LC mechanism keep supply-adequacy risk with GUVNL.
GUVNL's non-solar power auction draws just 50 MW at Rs 29–35/kWh against a 1,500 MW requirement
8November and January drew no non-solar bids, and the other six periods recorded 50 MW each at up to 293.3% above the lowest RTC tariff, while RTC drew sources from Ambitious, Jindal, Tata, NVVN and PTC.
8Single-offer periods that need GERC consent, unidentified suppliers behind every non-solar price and no explanation of the weak response keep procurement risk with GUVNL.
PSPCL awards Kapurthala RDSS package to SKS Infra at Rs 88.94 crore after the auction flips the ranking
8SKS moved from L2 to L1 by undercutting ABI's Rs 89.24 crore opening bid by a single 0.1% decrement, leaving the award 28.8% above the Rs 69.06 crore estimate for HT/LT loss-reduction works in three divisions.
8An unexplained Rs 20.88 lakh post-auction cut, 3% versus 10% performance-security clauses, no steel-structure escalation and GIS-linked final payments keep working-capital risk with the contractor.
PSPCL awards Nawanshahar RDSS package to ABI Energy at Rs 101.38 crore with no fresh auction bids
8Package 14's three ranked offers clustered 29.2–32.8% above the Rs 78.74 crore estimate, and the 730-day award came in Rs 34.46 lakh below ABI's evaluated L1 for reasons the record does not give.
8Conflicting 3% and 10% security terms, a "sixty-five (60) days" payment clause, lot-rejection penalties and a 473-day gap between the NoA and the portal contract date keep cash-flow and compliance risk with the contractor.
Kashmirilal overtakes ABI by Rs 9.46 lakh to win PSPCL's Rs 94.47 crore Mahilpur package
8The reverse auction cut Kashmirilal's own bid by 4.4% but improved on the best opening offer by only 0.1%, leaving the Package 12 award 27.1% above the Rs 74.33 crore estimate.
8Quality penalties of up to 5% of contract price, 10-year latent-defect liability, conflicting 3% and 10% security clauses and GIS-linked final payments keep execution and liquidity risk with the contractor.
RECPDCL pushes YEIDA 400/220 kV GIS deadline to 25 November but keeps the 18-month schedule
8Amendment III adds eight days to the previous deadline for the UPPTCL project, 23 days later than the original, moving the reverse auction to 8 December and SPV transfer to 28 December with the Rs 5.28 crore bid bond and Rs 13.20 crore CPG unchanged.
8No stated reason, a 12-day LoI-to-transfer window against clause 2.15.3's ten days and payment tied to simultaneous commissioning keep revenue-timing and execution risk with bidders.
PSPCL awards Jalandhar-2 RDSS package to ABI Energy at 28% above estimate
8The Rs 87.10 crore award against a Rs 68.04 crore estimate is Rs 19 lakh below ABI's evaluated bid, with Mangal and Vindhya 7.4% and 8.3% higher.
8An unexplained price cut, conflicting award dates and steel left out of price adjustment keep margin and timeline risk with the contractor.
DVC clears GE Vernova, Siemens and Techno Electric for Rs 133.63 crore Durgapur switchyard rebuild after eight extensions
8The DTPS GIS bids closed 75 days late, after escalation caps were removed for power transformers and R. S. Infraprojects was rejected over its surety bond.
8A 92-month security period, no payment for extra cable trays and gaps between drawings and the BOQ keep engineering risk with contractors.
CSPDCL gives contractors a six-month exit in its Rs 1,193 crore fault-restoration tender
8The corrigendum raises the vehicle odometer limit from 30,000 km to 1 lakh km, and a separate amendment moves submission to 25 November.
8A wrong incentive example, conflicting penalty start dates and uncapped CSERC compensation keep performance and payroll risk with contractors.
CCL's Rs 467.16 crore Amrapali–Shivpur coal evacuation tender says no ePBG but demands 5% performance security
8The three-year GeM package for 32,000 TPD of loading, haulage and wagon loading carries a Rs 50 lakh EMD and 3% retention.
8Payment on railway weighment, ±30% volume swings and a draft work order that bars escalation keep utilisation and cash-flow risk with transporters.
NTPC's Rs 200 crore Kudgi ash-haul panel guarantees no work orders
8Up to five AST-01 contractors must match the L1 rate to haul ash up to 300 km, with each capped at Rs 40 crore of work.
8A minus 100% variation clause, measurement-linked payment and extra security for deep discounts keep volume and liquidity risk with transporters.
JPDCL draws 14 bidders for Rs 159.46 crore Kathua Rural RDSS package after cutting performance security to 6%
8Bids for the Billawar, Basohli and Ramkote package opened on 14 November after an eight-day extension, with security now accepted as BG or surety bond.
8Price-variation bills tied to available funds and dismantling with no extra payment keep cash-flow and pricing risk with contractors.
JPDCL's Kathua Urban RDSS opening lists a bid stamped after the deadline
8Ten bidders were admitted for the Rs 239.60 crore package, but Vijai Electricals' entry is timed at 16:41, after the 14:00 closing.
8Price-variation billing tied to available funds and a vendor list disclosed only after award keep execution and recovery risk with contractors.
GUVNL's short-term power auction draws only 50 MW at Rs 29/kWh for non-solar hours
8Offers met the full 1,500 MW RTC requirement only in February and March, with lowest quotes of Rs 8.90–9.66/kWh.
8Unnamed "XX" sources behind 900 MW and PPAs not yet signed keep supply-firmness risk with GUVNL.
WCL awards Rs 416.62 crore Kolarpimpri OB-and-coal contract to Chennai Radha at 17.5% below estimate
8The 1,490-day contract against a Rs 504.80 crore base covers 2.92 crore CUM of OB and 81.2 lakh tonnes of coal, with seven of nine bids reaching the financial stage.
8Payment for only 70% of OB before seam exposure, a PBG that works out to Rs 5.10 crore or Rs 20.83 crore depending on the clause and an undisclosed low-bid benchmark keep liquidity risk with the contractor.
RECPDCL moves Bikaner V Part C deadline to 30 November while Part B terms stand unchanged
8Amendment V shifts submission by 14 days but LoI and SPV transfer by only 11, leaving Part B's Rs 66.40 crore bid bond, Rs 166 crore CPG and 36-month scope untouched.
8No stated reason, a submission-to-transfer window cut to 28 days from 31 and a three-day document-to-LoI gap keep execution-readiness risk with bidders.
RECPDCL's Bikaner V Part C extension leaves the Rs 165.50 crore guarantee and commissioning lock intact
8The amendment puts bids 42 days past the original 19 October deadline for the Bulandshahr–Lucknow-II 765 kV package, which carries a Rs 66.20 crore bid bond and 36-month simultaneous commissioning.
8No reason for the delay, a pending CEA critical-element list and payment tied to prerequisite elements keep revenue-timing and financing risk with bidders.
RECPDCL's Bikaner V Part C amendment comes with a Part D RFP attached
8Amendment V extends submission by 14 days to 30 November and names the Part C SPV, but the cover and notification of the accompanying RFP identify Part D.
8Unreconciled package identity, no revision of bid or bond validity and a document-to-LoI window cut to three days keep compliance and document-control risk with bidders.
POWERGRID ties YEIDA GIS package award to winning the tariff bid first
8The SS206T package for a 400/220 kV GIS at YEIDA, an Aligarh extension and a 220 kV cable link closes on 23 November with 16-month completion and a Rs 235.13 crore turnover bar.
8Exclusive pre-bid association, an extra 10% equipment guarantee, indefinite NDA confidentiality and no relief if POWERGRID loses keep conditional-award risk with contractors.
POWERGRID's Talaricheruvu BESS tender leaves AP-BESS-12 out of its completion clause
8Three packages totalling 250 MW/1,000 MWh close on 18 November with 15-month completion and 12-year maintenance, with award depending on POWERGRID winning APPCC's 1,250 MW/5,000 MWh selection.
8A duplicated AP-BESS-11 entry, no degradation or augmentation terms and no stated EMD or PBG keep lifecycle and conditional-award risk with contractors.
POWERGRID lets substation contractors qualify for Andhra Pradesh battery storage packages
8The Talaricheruvu IFB accepts two 33 kV breaker bays, 50 MW of solar or wind, or 10 MWh of BESS as entry routes, with start-ups and MSEs meeting 80% of the financial bars.
812-year maintenance without usable-energy or replacement rules and no MoU terms on price validity keep performance and pricing risk with contractors.
POWERGRID gives BESS contractors seven days to bid and commit to exclusive association
8Document access for the three Talaricheruvu packages closes two days before the 18 November deadline, with one-day appeals, private openings and cancellation without liability.
8An NDA that hands improvements to POWERGRID, no reimbursement if the upstream bid fails and an undefined exclusivity period keep bid-cost risk with contractors.
CCL's Magadh coal-evacuation tender says no ePBG but demands 5% performance security
8The Rs 96.29 crore, two-year GeM package for 35,000 TPD of loading and short-haul transport closed on 9 November with a Rs 50 lakh EMD, 3% retention and ±30% volume variation.
Conflicting bid-splitting rules, no JV route below Rs 100 crore and no idle-time claims for lack of coal or unloading space keep utilisation risk with transporters.
PSPCL splits Rs 205.06 crore biomass pellet order for Lehra Mohabbat among 13 suppliers
8The reverse auction for 2.92 lakh MT a year at GHTP cut the opening best price by 0.9% to Rs 2.1896 per 1,000 kCal, with R.A.B. & Company taking 19.8% of the award value.
8An undisclosed allocation basis, a firm-price rule against variable-price wording, conflicting moisture-deduction methods and zero payment below 2,000 kCal keep quality and margin risk with suppliers.
BSPGCL cuts Kajra BESS commissioning to 12 months and opens bidding to foreign developers
8The amendments to the 125 MW/500 MWh BOOT tender halve financial closure to six months, cut the success charge to Rs 3 crore and allow bank guarantees for the Rs 25 crore PSD, against a Rs 13 crore EMD and Rs 32 crore PBG.
8A renewable-charging damages formula mixing kWh and Rs/MWh, a zero-shading rule, an 85% green-charging test and 30-day PSD top-ups keep charging-cost and compliance risk with developers.
RVUN extends Suratgarh supercritical O&M bids for the tenth time, to 1 December
8Corrigendum X pushes the Rs 180 crore, three-year contract 162 days past the original deadline, keeping the Rs 3.60 crore EMD, 1,108-person staffing and 5% performance guarantee unchanged.
8Guarantees of 85% availability and a 2,145.68 kcal/kWh heat rate against actuals of 80.52% and 2,464.92, a self-contradictory transition-KPI note, a sign error in the APC formula and 10% withheld monthly keep performance and liquidity risk with operators.
BHEL switches to a one-way indemnity in Mahi Banswara nuclear air-handling tie-up
8Revised MoU terms for the 4×700 MWe ASHVINI package replace mutual indemnity and change "to award" to "may issue" an order, alongside a Rs 3 crore EMD and a deadline pushed 47 days to 19 November.
8Unresolved seismic conflicts, bearing and belt choices left to detailed engineering, FOR-despatch versus site-delivery wording and payment tied to ASHVINI's receipt certificate keep pre-award and cash-flow risk with suppliers.
RECPDCL pushes Bikaner V Part A bids to 20 November without fixing its STATCOM rating
8Amendment VII names the SPV and moves all milestones 35 days past the original RFP dates for the 36-month package, which carries a Rs 73.72 crore bid bond and a Rs 184.30 crore CPG.
8No stated reason for the extension, a "2x+300" versus "2x±300 MVAr" mismatch, a document-to-LoI window cut to three days and payment tied to prerequisite elements keep interface and revenue-timing risk with bidders.
For daily newsletters and other free services, fill in your details: