All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Jun 2026

 For reference purposes the website carries here the following tenders:
 
8Tender for supply of MS pipes Details
 
8Tender for supply of Sand and gravels for Sand filter media Details
 
8Tender for supply of electrical insulated Details
 
8Tender for supply of RIGIFLEX spacer coupling for ID fans Details
 
8Tender for supply of various non-metallic expansion joints Details
 
8Tender for annual contract of painting works in plant Details
 
8Tender for supply of tube shielding and bottom seal plates installed Details
 
8Tender for supply of knife gate valve of mill reject handling system Details
 
8Tender for supply of boiler tubes Details
 
8Tender for requirement of supply, erection, testing and commissioning of Mercury analysers for emission parameters Details
 
8Tender for supply of startup system control valves and actuators installed Details
 
8Tender for procurement of spares for cooling towers Details
 
8Tender for supply of journal shaft and assembly, journal head of HP-1103 bowl mill installed Details
 
8Tender for miscellaneous balance civil works Details
 
8Tender for providing and laying of clay tiles on roofs of various Details
 
8Tender for misc. balance works of NDCT with associated Details
 
8Tender for supply of glass wares, polythene wares and miscellaneous items Details
 
8Tender for annual work contract for routine, breakdown, capital maintenance and assistance in routine maintenance, annual shutdown & up keeping of C&I systems, instruments and equipment Details
 
8Tender for supply of portable and trolley mounted fire- extinguisher of different capacities Details
 
8Tender for empanelment of agencies for restoration of distribution infrastructure Details
 
8Tender for work of 33 kV line Details
 
8Tender for work of 33 kV line from 132/33 kV substation Details
 
8Tender for work of 33 kV line Details
 
8Tender for work of new 33 kV line from 33/11 kV substation Details
 
8Tender for work of new 33 kV line for feeder Details
 
8Tender for housekeeping contract for CTM plant of green chemical Details
 
8Tender for engagement of service provider for solid waste management Details
 
8Tender for construction of prefabricated Details
 
8Tender for supply cum erection, installation and commissioning of 550 AH tubular lead acid stationary battery bank sets Details
 
8Design, engineering, supply, erection, testing and commissioning of complete dry ash pressure conveying system Details
 
8Tender for improvement works to ESP control room Details
 
8Tender for balance work of construction of integrated Details
 
8Tender for supply of various types of power and control fuses Details
 
8Tender for supply of various types of bushings for 250 MVA, 420/15.75 kV, BHEL make generator transformers Details
 
8Tender for erection of 66kV Lilo to S/s line Details
 
8Tender for Re-routing HT line of feeder Details
 
8Tender for supply of covered conductor 11 kV 99 Sq.mm AAAC with accessories Details
 
8Tender for annual operation and preventive maintenance works, emergency maintenance work of 220/33 kV GIS Details
 
8Design, engineering, supply, erection, testing & commissioning, along with associated complete civil works & automation of 66kV GIS Details
 
8Tender for procurement of tower accessories for 400kV Tr. lines Details
 
8Tender for sorting, shifting, stacking of different type of spare tower parts Details
 
8Tender for constructing 11kV S.C line Details
 
8Tender for work of condenser tubes cleaning by high pressure water jetting with rotary nozzle method & bullet shot method Details
 
8Tender for work of design, fabrication, erection of L-6 conveyor structure Details
 
8Tender for reconstruction of the damaged boulder trap Details
 
8Tender for repair of 40 Nos of wicket gates (02 set ) of 77 MW francis hydro-turbine Details
 
8Tender for construction of PCC retaining wall in place of damaged retaining wall Details
 
8Tender for supply of special 414 TXM coupling set TXM-301865 & its gasket for pulverized fuel pipes Details
 
8Tender for procurement of 29000 Nos. of 9 m 400 Kg working load PSC poles Details
 
8Tender for procurement of 3000 Nos of 9 m 400 Kg working load PSC poles for effecting agricultural services in all distribution Details
 
8Tender for work of replacement of 132 kV BPI and 22kV transformer Details
 
8Tender for work of providing second PT source for 132kV and 33kV voltage level Details
 
8Tender for general civil work like rolling shutter overhauling, UPVC line Details
 
8Tender for work of removal of existing MS/CS pipe & fittings and fabrication, erection, testing & commissioning of new SS 316L pipe and fittings Details
 
8Tender for work of application of thermal insulation & aluminum cladding of various ducts, piping, valves Details
 
8Tender for work of refurbishment of various spares of CW pump Details
 
8Tender for work of overhauling / servicing of gear box, & rail alignment of gantry crane Details
 
8Tender for work of Re-tubing of tube nests of LP heater Details
 
8Tender for work of erection and commissioning of vortex finder in boiler Details
 
8Tender for miscellaneous civil works Details
 
8Tender for supply of bed material for CFBC boiler Details
 
8Tender for operation and maintenance of valves for water distribution Details
 
8Tender for providing RCC chamber with protection wall Details
 
8Tender for supply of various type of belt scraper for 500 MW coal handling plant Details
 
8Tender for supply of IE4 class LT motors Details
 
8Tender for procurement of spares for CW pumps of unit-6 during overhauling Details
 
8Tender for procurement of different spares for elevators Details
 
8Tender for service contract for fabrication and erection of safety platform and miscellaneous work Details
 
8Tender for procurement of spares for booster pump Details
 
8Tender for procurement of throat plate assembly for coal mill Details
 
8Tender for OH of air/flue gas duct, expansion joint Details
 
8Tender for service contract for OH job of coal burner, SADC and coal carrying pipe up to burner isolating gate and hangers Details
 
8Tender for procurement of 11 Nos. 420kV and 05 Nos. 245kV capacitive voltage transformer Details
 
8Tender for procurement of 70KL liquid ammonia Details
 
8Tender for construction of cable trench Details
 
8Tender for designing, manufacturing, testing & delivery of remote terminal units Details
 
8Tender for upgradation of 66kV SC to 110kV DC line Details
 
8Tender for construction of 220/110 kV substation Details
 
8Tender for capital work of 110kV substation Details
 
8Tender for implementation of network analysis solution Details
 
8Tender for replacement of existing of 11kV ACSR rabbit conductor Details
 
8Tender for annual maintenance work of 33/11 kV S/s Details
 
8Tender for supply of 33 kV jaw and blades Diff size lugs, isolator clamp and jaw and GI bolts and nut and washers Details
 
8Tender for work of supply, erection, testing commissioning of an additional of 1X25 MVA 220/33kV power transformer by 1X50 MVA 220/33kV TF Details
 
8Tender for work of supply, erection, testing commissioning of an additional 132/33 kV, 50 MVA power T/F along with HV, LV bay & 33kV bus extension Details
 
8Tender for work of supply, erection, testing commissioning of an additional 1X 25MVA 132/33kV power transformer along Details
 
8Tender for work of supply, erection, testing commissioning of an additional 1X 50MVA 220/33kV power transformer along Details
 
8Tender for work of supply, erection, testing commissioning of an additional 1X 25MVA 132/33kV power transformer along Details
 
8Tender for laying of underground cable Details
 
8Tender for erection, maintenance and dismantling work of overhead HT/LT line Details
 
8Tender for supply of pulverized fuel bends for coal mill Details
 
8Tender for work of ash lifting of ESP Details
 
8Tender for renovation of damaged staircase including S.S railing Details
 
8Tender for providing and fixing PUF panel operator cabin Details
 
8Tender for supply of plumbing materials Details
 
8Tender for work of penthouse sealing in boiler Details
 
8Tender for work of application of refractory in Re-suction ducts and beater wheel mill area with repairing and strengthening of all ducts Details
 
8Tender for supply of various sizes of MS ERW pipes, elbows and CS pipes installed Details
 
8Tender for supply, erection, commissioning of new street lights poles and dismantling of existing poles Details
 
8Tender for supply of fire sealing chemical and fire barrier mineral wool board system for sealing / coating for cable fire protection Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
Significant Participation of Nepali Companies in Transmission Line Development Details
 
8MCL holds consumers' meet to strengthen engagement with power sector companies Details
 
8The Policy Failures Holding Back India's Solar Energy Sector Details
 
8How The Hormuz Crisis Can Push India Towards Energy Transition Details
 
8India's ALCM Divide: The Real Numbers Behind the Solar Manufacturing Split Details
 
8Sterling and Wilson Renewable Energy JV secures $560 million solar-plus-storage project in Egypt Details
 
8SJVN signs PPAs with GUVNL to supply 658 MW of green hydropower from three Himachal projects Details
 
8SAEL Commences Development of Five GW Solar Cell and Module Manufacturing Hub Details
 
8Madhya Pradesh marks historic leap in renewable energy with inauguration of solar parks and morena BESS project Details
 
8Kalpataru Projects Wins Rs 2,957 Crore Orders Across Sectors Details
 
8Power sector: Antique picks NTPC, Adani Power, ACME Solar; here's why Details
 
8India Preparing 300 GW Power Capacity Next Year to Meet Rising Demand: Union Minister Manohar Lal Khattar Details
 
8Adani Power, NTPC, ACME Solar shares among Antique's top power sector picks Details
 
8India's Renewable Power Generation Jumps Nearly 19% in May, Solar Drives Growth Details
 
8India’s Energy Future Needs 2,000 GW More Power Capacity, Says Adani Green Details
 
8PFC and REC Announce Major Merger to Enhance Power Financing Capacity Details
 
8How The Hormuz Crisis Can Push India Towards Energy Transition Details
 
8Powered by reforms, India successfully met its all-time high energy demand of 271 GW: Khattar Details
 
8The Wind Turns: Signs of revival in the sector Details
 
8India’s nuclear sector opens to private investment, says YCP report Details
 
8India Power Demand Holds Above 250 GW; Grid Load Impacts Sector Details
 
8Power Ministry Unveils Draft Electricity Data Sharing Framework Details
 
8Rs 9 lakh crore grid expansion creates demand for an overlooked product. 2 stocks could benefit Details
 
8Renewables up 24%, emissions up just 0.9%: India charts a different energy path Details
 
8India's industrial output grows 5.1 pc in May, manufacturing, electricity sectors drive expansion Details
 
8Supreme Power Equipment Secures 11-Month Domestic Contract for 20 MVA Transformers in Karnataka Details
 
81,000% in 5 Yrs: Electrical Equipment Stock Betting Big on Data Centres, Grid Modernisation, and Renewables Details
 
8India targets 100 GW nuclear capacity by 2047, needs $210 billion investment, says report Details
 
8Power Grid Acquires 100% of Kakinada Transmission for Rs 20.50 Crore Details
 
8May IIP surges to 5.1% – Power output jumps 9%, manufacturing growth strong at 5.5% Details
 
You can also click on Newsclips for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8LPG
8Ammonia
8Coal & Coke
8All tankers
8Bulk and Dry cargo

Click on Reports for more. Details
8Single-point BOP model raises execution stakes in 3×800 MW thermal project
A large thermal expansion project has consolidated major BOP responsibilities into one EPC package.
The move transfers execution and performance risks to a single contractor and could influence bidder strategy and pricing.

8Option-clause revision strengthens procurement flexibility in major coal sourcing programme
A revised commercial framework expands buyer flexibility after contract award and changes execution expectations for suppliers. The amendment could influence bidding strategies and contract risk allocation in a large domestic coal procurement.

8Procurement structure tightens in 2.0 MMT coal sourcing programme
A revised procurement framework introduces greater post-award flexibility while safeguarding fuel supply continuity across multiple power stations. The changes could influence supplier strategy, contract execution and the design of future bulk coal sourcing tenders.

8GIS transmission package shifts execution risks beyond conventional EPC boundaries
A transmission package is doing more than adding another GIS substation to the grid. Several contractual and engineering provisions reshape how responsibilities, execution risks and bidder capabilities are distributed. The implications could influence how future transmission contracts are structured.

8Transformer procurement raises technical scrutiny for manufacturers
A new transformer procurement signals continued investment in transmission infrastructure. While the commercial scope appears straightforward, the qualification framework raises the competitive bar for manufacturers. The tender's engineering requirements could significantly influence supplier participation and bidding strategies.

8Coal procurement adopts flexible framework under consolidated bidding model
A new coal procurement package appears routine at first glance, but the commercial structure introduces greater buyer flexibility. The framework could reshape supplier competition and influence bidding strategies throughout the procurement process.

Details
8A razor-thin commercial contest has reshaped one of the year's largest transformer procurements.
8The pricing pattern reveals a changing competitive landscape among manufacturers and highlights intense competition during final price discovery.
8The outcome could influence bidding strategies in future utility tenders. Details
8A transformer procurement has revealed a highly competitive supplier landscape.
8The award provides an important pricing benchmark for future utility tenders while highlighting the intensity of market competition.
8The outcome could influence bidding strategies in similar contracts ahead. Details
8A large utility procurement introduces stricter execution and delivery provisions, potentially reshaping supplier obligations and contract management.
8The revised framework could influence bidder strategies and future procurement practices. Details
COAL PRODUCTION & STOCK

8India's thermal coal stocks at 58% of norm with 34 plants critical, CEA's 27 June report finds
The Central Electricity Authority's Daily Coal Stock Report for 27 June 2026 shows 190 monitored thermal plants (224,158 MW) holding 44.64 million tonnes of coal, just 58% of the 75.79-million-tonne normative requirement, with 34 stations at critical stock, including 26 on domestic coal, 6 on imports and 2 on washery rejects. Thinning stocks ahead of monsoon-disrupted supply raise the risk of fuel stress at vulnerable plants.

8Coal India's 23 June stock monitor flags 17 linked power plants at critical levels
Coal India Limited's Marketing & Sales Division coal-stock position as on 23 June 2026, compiled per the CEA report for plants with CIL and SCCL linkage, tracks total coal stock of about 39.1 million tonnes and identifies 17 plants in critical or supercritical status. The monitor governs rake allocation and supply prioritisation to keep linked generators adequately fuelled ahead of monsoon disruptions.

8CEA compiles cumulative coal-stock position for thermal plants through May 2026
The Central Electricity Authority's cumulative daily coal report for May 2026 consolidates plant-wise coal receipts, consumption and closing stocks across India's coal-fired fleet. The dataset tracks how stocks moved against requirement through the pre-monsoon stocking period, a core input for monitoring national fuel security ahead of peak-demand and monsoon-disruption risks for thermal generators across the country's entire fleet of plants.

8CEA reports plant-wise coal receipts and stocks for May 2026
The Central Electricity Authority's monthly coal report for May 2026 details thermal-station-wise consumption and closing stocks against sources including Coal India (CIL), SCCL, captive, e-auction and imports. The report flags stations running on thin stocks during the high-demand month, underpinning the government's ongoing coal-supply-monitoring and rake-allocation decisions for the power sector as a whole during the summer demand peak season.

8CEA tracks imported-coal use at Indian thermal plants for May 2026
The Central Electricity Authority's monthly imported-coal report for May 2026 captures import-based and blending coal consumption and stocks at thermal stations designed for or blending foreign coal. The data show the extent of import dependence during peak summer generation, a sensitive cost driver given global price swings and rupee movements affecting utility fuel costs across the country's entire thermal generation fleet.

GENERATION & PLF

8India's installed power capacity reaches 542,354 MW as on 31 May 2026; renewables top 230 GW
The location-wise regional summary of all-India installed capacity as on 31 May 2026 places total capacity at 542,354.17 MW, comprising 250,829.13 MW thermal (including 223,497.51 MW coal), 51,964.66 MW hydro, 230,780.38 MW renewable (RES) and 8,780 MW nuclear. The data show renewables now exceed coal in installed terms, with the West leading at 195,683 MW, followed by the North (145,277 MW) and South (143,874 MW).

8Western Region leads India with 195,683 MW installed capacity as on 31 May 2026
The state-wise installed-capacity report for the Western region as on 31 May 2026 totals 195,682.91 MW, including 94,070.40 MW thermal, 7,392 MW hydro, 90,980.51 MW renewable and 3,240 MW nuclear. Maharashtra, Gujarat and Madhya Pradesh anchor the region's heavy private-sector renewable build-out, with the West's nearly 91 GW renewables base reflecting the concentration of solar and wind capacity along the western corridor.

8Northern Region installed capacity at 145,277 MW as on 31 May 2026
The state-wise installed-capacity report for the Northern region as on 31 May 2026 totals 145,276.53 MW, comprising 57,580.96 MW thermal, 21,965.76 MW hydro, 63,509.81 MW renewable and 2,220 MW nuclear. The region's large hydro base and rapidly growing private renewables, over 56 GW in the private sector, shape its supply profile alongside continued reliance on imported central-sector power allocations from other regions.

8Southern Region holds 143,874 MW installed capacity, renewables near 72 GW
The state-wise installed-capacity report for the Southern region as on 31 May 2026 totals 143,873.64 MW, including 54,789.10 MW thermal, 13,596.15 MW hydro, 72,168.39 MW renewable and 3,320 MW nuclear. The region's renewable base of over 72 GW, the largest of any region, reflects deep solar and wind penetration across Tamil Nadu, Karnataka and Andhra Pradesh's installed generating fleet and capacity mix.

8Eastern Region installed capacity at 50,936 MW, coal-dominated as on 31 May 2026
The state-wise installed-capacity report for the Eastern region as on 31 May 2026 totals 50,935.88 MW, comprising 41,937.71 MW thermal (overwhelmingly coal), 5,987.75 MW hydro and 3,010.42 MW renewable, with no nuclear. The coal-heavy mix reflects the region's role as a pithead generation hub feeding the national grid, with renewables remaining a small share relative to other regions' installed capacity.

8North-Eastern Region installed capacity at 6,585 MW as on 31 May 2026
The state-wise installed-capacity report for the North-Eastern region as on 31 May 2026 totals 6,585.21 MW, including 2,450.95 MW thermal (largely gas), 3,023 MW hydro and 1,111.25 MW renewable. The hydro- and gas-weighted mix reflects the region's resource endowment, with the modest base underscoring continued dependence on inter-regional support and scope for further hydro development across the region in coming years.

8SRLDC's 28 June generation report maps station-wise output behind Southern grid's 1,242-MU day
The Southern Regional Load Despatch Centre's station-wise Generation Report for 28 June 2026 details output across the five states, from Jindal's Simhapuri thermal units to Greenko's pumped-storage operation, supporting the region's 1,242.62 MU of energy and 49,050-MW evening peak. The granular generation-mix data anchors scheduling, settlement and renewable-integration decisions for the southern grid's operators and participating state utilities on a day-to-day basis.

GAS & LNG

8CEA details gas supply to power stations for May 2026, splitting domestic and RLNG
The Central Electricity Authority's monthly fuel report for gas-based power stations for May 2026 tabulates domestic gas allocation (APM/non-APM and KGD-6), RLNG consumed (term, long-term and spot), and alternate fuels such as naphtha and HSD, in MMSCMD. The data reveal how much of India's stranded gas-fleet ran on costly imported LNG, with gas-based generation remaining a swing resource for peak and balancing support.

HYDRO & RESERVOIR

8Idukki at 707 ft, Mettur at 749 ft: SRLDC reservoir report tracks hydro storage on 28 June
SRLDC's Reservoir Report for 28 June 2026 records levels and energy content at major southern hydro reservoirs, with Idukki at 707.24 ft (versus 719.68 ft a year earlier), Mettur at 748.91 ft and Linganamakki at 531.82 ft, most sitting below year-ago levels ahead of the monsoon. Reservoir health directly governs hydro availability and the flexible generation used to balance the southern grid.
Details
PEAK DEMAND & POWER SUPPLY POSITION

8Southern grid meets 49,050-MW evening peak with zero shortage on 28 June, SRLDC reports
The Southern Regional Load Despatch Centre's Power Supply Position report for 28 June 2026 records an evening-peak (20:00) demand of 49,050 MW met in full across the five southern states and Puducherry, with day energy of 1,242.62 MU at a frequency of 50.03 Hz. Tamil Nadu (16,515 MW) and Karnataka (9,980 MW) led demand, and no state reported any shortage, underlining a comfortable supply-demand balance in the Southern Region despite peak-summer loads.

8Eastern Region meets 31,305-MW peak on 28 June; ERLDC flags minor 322-MW off-peak deficit
ERLDC's Daily Operation Report for the Eastern Region on 28 June 2026 shows an evening-peak demand of 31,305 MW met in full at 50.02 Hz, with day energy of 701.77 MU, though a small off-peak shortage of 322 MW appeared at 03:00 (50.04 Hz). DVC ran as a net injector, generating 108.27 MU, while Bihar drew 162.31 MU on schedule, tracking supply adequacy across the eastern states during summer operation.

8North-Eastern grid peaks at 3,593 MW with zero shortage on 28 June, NERLDC reports
The North Eastern Regional Load Despatch Centre's daily operation report for 28 June 2026 records an evening-peak demand of 3,593 MW met fully at 50.02 Hz and total day energy of 70.07 MU across the eight NE states. Assam led demand at 45.75 MU met, while Arunachal Pradesh drew just 3.27 MU, reflecting a deficit-free day in India's smallest regional grid.

8India's peak demand hits 264,768 MW on 27 June; energy met 5,806 MU with 2,867-MW shortage
GRID-INDIA's National Load Despatch Centre Power Supply Position report for 27 June 2026 records all-India maximum demand met of 264,768 MW (from NLDC SCADA) at 14:50, with energy met of 5,806 MU across the day. Regionally, peak demand met reached 93,029 MW (North), 74,721 MW (West), 63,597 MW (South), 33,035 MW (East) and 3,839 MW (North-East); peak shortage totalled 2,867 MW, concentrated in the western (1,850 MW) and southern (622 MW) regions, capturing pre-monsoon load stress.

8WRLDC publishes Western-Region power supply position for 28 June
The Western Regional Load Despatch Centre's Power Supply Position report for 28 June 2026 records evening-peak (20:00) and off-peak (03:00) demand met and shortages, alongside net energy consumption across western states. The report tracks how Maharashtra, Gujarat, Madhya Pradesh, Chhattisgarh and Goa met their loads, serving as the regional companion to the national daily supply-position ledger for that day's grid operations.

8Uttarakhand's June demand climbs to 63.18 MU on 26 June amid rising state generation
The Daily Power System Energy Report of Uttarakhand for June 2026 shows gross energy demand reaching 63.18 MU on 26 June, met by 22.31 MU of state generation and 23.07 MU of central share, with the balance from other sources. Demand rose steadily from 46.54 MU on 1 June, with state generation strengthening to over 22 MU by month-end, tracking the hill state's growing summer load and dependence on central-sector allocations.

8Uttarakhand meets 63.17-MU demand on 26 June with zero rostering despite Jwalapur constraint
Uttarakhand's actual supply and power-position report for 26 June 2026 shows total availability and demand met of 63.17 MU — 22.31 MU state generation, 23.07 MU central share, 17.15 MU power purchase/banking and 1.35 MU net IEX/PXIL drawal — with zero rostering. A transmission constraint flagged one-hour overloading of a 160 MVA transformer at 132 kV Jwalapur, though the state met full demand despite the localised network stress.

FREQUENCY & DEVIATION INDICES (FDI/VDI)

8Southern grid frequency averaged 49.968 Hz on 28 June, outside IEGC band 32.8% of the day
SRLDC's frequency profile for 28 June 2026 shows an average grid frequency of 49.968 Hz with a Frequency Deviation Index of 0.06, ranging from a low of 49.633 Hz to a high of 50.225 Hz. Frequency stayed within the tight 49.90-50.05 Hz band for 67.2% of the day but breached the IEGC band 32.8% of the time, about 7.87 hours, gauging grid discipline in the Southern Region amid fluctuating demand.

8North-Eastern grid frequency stayed outside IEGC band 39.2% of 27 June, NERLDC data shows
NERLDC's Daily Frequency Profile for 27 June 2026 reports the North-Eastern grid operating outside the IEGC band for 39.21% of the day, roughly 9.41 hours, with frequency averaging 49.95 Hz and swinging between 49.53 Hz and 50.22 Hz. The deviation metrics gauge frequency discipline in a region with a relatively small, hydro-heavy generation base that remains sensitive to demand swings.

8Eastern Region's 765-kV nodes held within voltage band all day on 27 June, ERLDC VDI shows
ERLDC's Voltage Deviation Index data for 27 June 2026 shows 765-kV substations such as Ranchi New, Angul and Gaya staying within the IEGC voltage band 100% of the time, with Ranchi New peaking at 788.99 kV against a 762.91-kV low. Stable extra-high-voltage levels are critical for secure bulk-power transfer across the eastern grid's transmission backbone during peak summer operation, with no breaches recorded at the monitored nodes.

8NERLDC tracks 400-kV voltage deviations across North-East substations for 27 June
The North Eastern Regional Load Despatch Centre's Daily Voltage Deviation Report for 27 June 2026 monitors 400-kV nodes against the 380-420 kV IEGC window, recording the share of time each substation ran below, within or above band. The node-wise voltage profile guides reactive-power management and equipment safety across the NER transmission system's substations and feeder lines, supporting the region's overall grid-security framework.

8NLDC logs national frequency profile for 28 June, tracking deviations around 50 Hz
GRID-INDIA's National Load Despatch Centre frequency profile for 28 June 2026 (Sunday) charts system frequency through the day against the IEGC operating band, with readings ranging up to about 50.30 Hz. The profile underpins frequency-response and deviation-settlement assessments, signalling the balance between generation and demand on India's synchronous grid across all five regions on a Sunday with lighter industrial load.

SYSTEM RELIABILITY & SECURITY

8Tripura corridor breached TTC limits 56.7% of 27 June, NERLDC system reliability report finds
The North Eastern Regional Load Despatch Centre's System Reliability Report for 27 June 2026 flags Total Transfer Capability (TTC) violations on the NER-Tripura import corridor for 56.67% of the day, about 13.6 hours, and on the NER-Assam corridor for 15.42%, about 3.7 hours, with utilities intimated for corrective action. Persistent TTC breaches point to transmission constraints limiting power imports into parts of the North-East.

8WRLDC reports Western-Region ATC and N-1 reliability indices for 28 June
The Western Regional Load Despatch Centre's Daily System Reliability Indices report for 28 June 2026 shows available transfer capability (ATC) was violated in 5 blocks (1.2% of time, 5.2 hours) for DNHDDPDCL, while Maharashtra, Gujarat, Madhya Pradesh, Chhattisgarh and Goa recorded zero ATC violations. The report also tracks the percentage of time N-1 security criteria were breached, gauging the operational security margin of the western grid.

8NLDC reports inter-regional corridor reliability indices for 28 June
GRID-INDIA's National Load Despatch Centre System Reliability Indices report for 28 June 2026 tracks the percentage of time available transfer capability was violated across inter-regional corridors, including WR-NR, with the listed corridor showing zero violations. The report monitors the loading security of India's inter-regional transmission links, complementing regional reliability reporting to give a complete national security picture for grid operators and planners.

8All-India angular spread map for 28 June benchmarks grid stress against Vindhyachal
The All-India Angular Spread report for 28 June 2026 measures voltage-phase-angle separation across key 400 kV nodes — including Agra, Bhachau, Chandrapur, Durgapur, Gazuwaka, Kolar, Korba, Talcher and Tehri — referenced to Vindhyachal. Wider angular spreads indicate higher transmission loading and reduced stability margin, making the snapshot a key diagnostic of grid stress across India's synchronous transmission network on a daily basis.

LOAD FORECAST

8Eastern Region day-ahead forecast error at 3.84% MAPE on 27 June, intraday sharper at 1.35%
GRID-INDIA's Eastern Regional forecasting report for 27 June 2026 records day-ahead demand-forecast accuracy of 3.84% MAPE (4.22% RMSE), improving to 1.35% MAPE on the intraday horizon, against actual demand peaking above 30,500 MW. Tighter forecasts reduce balancing costs and deviation penalties as variable renewables expand in the Eastern Region's generation mix, helping operators schedule reserves more precisely each day and limit costly last-minute corrections.

LINE & GENERATION OUTAGES

8Long-idle 400-kV Ramagundam line among planned outages in SRLDC's 28 June transmission report
The Southern Regional Load Despatch Centre's Transmission Outage Report for 28 June 2026 catalogues planned outages across the southern grid, including a 400-kV Ramagundam-Telangana STPP line on idle-charge status since March 2023. The element-wise outage and revival timelines are essential for managing transfer capability and congestion across the region's high-voltage transmission corridors and substations feeding the southern grid's power-evacuation network.

8Collapse of five 220-kV towers near Kushtagi keeps Gadag line out, SRLDC's 28 June report shows
SRLDC's Transmission Forced Outage Report for 28 June 2026 flags the 220-kV Gadag-Green Infra line forced out since 17 May 2026 after five transmission towers collapsed near Kushtagi, alongside a 400-kV Nagapattinam line affected by multiple collapsed towers. Such forced outages constrain power-evacuation corridors and highlight grid-resilience challenges from structural failures during the pre-monsoon period across the southern grid's transmission network.

8Over 1,400 MW of southern thermal capacity under overhaul in SRLDC's 28 June unit-outage report
SRLDC's Generating Unit Outage Report for 28 June 2026 lists major southern units offline, including NTECL's Vallur TPS (500 MW) and NTPC's Talcher Stage-II (500 MW) on annual overhauling, NTPC Ramagundam (200 MW) on annual maintenance and NLC's Neyveli TS-II (210 MW) on reserve shutdown. The planned outages, with revivals stretching into July 2026, shape available capacity and merit-order dispatch in the Southern Region.

86,128 MW of Eastern generation forced out on 28 June, ER-NPMC outage report shows
The Eastern Region's generation-outage report for 28 June 2026 tallies 6,128 MW of forced outages (4,678 MW central sector, 1,450 MW state sector) against 1,113.65 MW of planned outages, including GMR Kamalanga's 350-MW unit on annual overhaul. The scale of unplanned capacity loss highlights reliability pressures on the eastern thermal fleet during peak-summer operation across the region's generating stations and underscores maintenance backlogs at ageing units.

8Kaiga and MAPS nuclear units among long-duration Southern outages in 28 June NPMC report
The Southern Region's detailed NPMC outage report for 28 June 2026 lists long-running outages including NPCIL's Kaiga Unit-1 (220 MW, out since March 2025 for EMCCR/EMFR activities) and MAPS Unit-1 (220 MW), plus NTECL Vallur (500 MW) and NTPC Talcher (500 MW) on overhaul. The capacity-availability picture feeds scheduling and reserve planning across the southern grid's merit-order dispatch and reserve-margin calculations for the operator.

8Powergrid's planned-shutdown log shows 282-day Dehradun bay outage in 26-28 June window
The Planned Shutdown Report for 26-28 June 2026 details Northern-Region transmission elements under outage, including a 220-kV bay at Dehradun (POWERGRID) out 282 days for asset-management-plan work, plus bus-reactor and inter-connecting-transformer works at Bhadla, Bawana and Narela. The extended extra-high-voltage element outages reflect maintenance and augmentation reshaping the northern grid even as overall network availability is actively managed by the regional load despatch centre.

8WRLDC logs generating-unit outages across Western Region for 28 June
The Western Regional Load Despatch Centre's Generation Outage report for 28 June 2026 lists planned and forced outages of generating units across the region, with station, state, agency, unit capacity (MW), outage reason and expected revival dates, including units down for biennial overhaul. The report quantifies capacity unavailable to the western grid, a key input for assessing reserve adequacy and merit-order dispatch.

8WRLDC reports transmission-line outages in Western grid for 28 June
The Western Regional Load Despatch Centre's Line Outage report for 28 June 2026 enumerates planned and forced transmission-line and element outages across the western region, detailing voltage level, outage timing and reasons. The report maps network elements unavailable for power transfer, informing congestion management and contingency planning on one of India's most heavily loaded regional transmission grids during summer peak.

8PVVNL schedules planned feeder shutdowns across Meerut zone on 27 June
Paschimanchal Vidyut Vitran Nigam Limited (PVVNL), Meerut, issued a planned-shutdown schedule dated 26 June 2026 listing 27 June outages of rural feeders — such as Pali (10:00-14:00) in the Jahangirabad division of Bulandshahar — for maintenance and pole-replacement works. The schedule details affected areas including Raghunathpur, Pali and Nityanandpur, helping consumers across western Uttar Pradesh plan around routine distribution maintenance work.

8Uttarakhand reports minimal load-rostering in first fortnight of June 2026
Uttarakhand's rostering-details report for 1-15 June 2026 shows largely Nil load-shedding across rural feeders and towns of Haridwar, Udham Singh Nagar, Garhwal and Kumaon, with only isolated early-June curtailments. Most towns recorded full 24-hour running hours, signalling adequate supply during the period despite climbing summer demand in the hill state's power system and growing seasonal load on its distribution network.

REGIONAL ENERGY ACCOUNT (REA/REMC)

8SRLDC charts schedule-vs-drawal of southern states for 28 June to track grid discipline
The Southern Regional Load Despatch Centre's Schedule vs Drawal report for 28 June 2026 plots 15-minute block-wise scheduled drawal against actual drawal for Andhra Pradesh, Karnataka, Tamil Nadu and the other southern states. The deviation data feeds the Deviation Settlement Mechanism and signals how closely each state adhered to its day-ahead schedule, with financial implications under DSM for the region's utilities.

8All-India daily power supply position logged for 28 June across states and regions
The national daily power-supply-position report for 28 June 2026 tabulates state-wise demand met, shortages, frequency, drawal-schedule versus actual drawal and unscheduled interchange across all regions. The report tracks each control area's generation, central-share drawal and over/under-drawal against schedule, serving as the granular daily ledger underpinning grid-balancing and deviation-settlement across India's utilities and DISCOMs nationwide on each operating day of the year.

8All-India ISTS transmission loss set at 3.70% for 29 June-5 July week, NLDC notifies
GRID-INDIA's NLDC has fixed the all-India inter-State transmission system (ISTS) loss at 3.70% for the week of 29 June to 5 July 2026, computed from the previous week's special-energy-meter data under the CERC Sharing Regulations, 2020. The figure, derived from 19,172.80 MU of injection against 18,492.03 MU of drawal, sets the loss factor applied to all inter-State transactions for the week, directly affecting open-access and exchange settlements.

8Grid-India publishes 28 June ancillary-services and SCUC reserve profile
GRID-INDIA's Daily Report on Ancillary Services and Security Constrained Unit Commitment (SCUC) for 28 June 2026 details spinning up and down reserves against requirement and the SCUC-scheduled up/down quantities at the inter-state level, where reserve requirement is taken as half the total system requirement. The report shows how the operator marshalled reserves across 96 time-blocks, a daily readout of India's tertiary and reserve-management mechanisms.

8NTPC's Vindhyachal tops NLDC's 29 June SCUC schedule at 214.7 paise/kWh energy charge
NLDC's Format-2 SCUC schedule for 29 June 2026, published a day ahead, commits coal units in merit order by Energy Charge Rate, led by NTPC's Vindhyachal STPS Stage-4 (164.23 MW at 214.7 paise/kWh) and Kahalgaon Stage-2 (623.38 MW at 281.2 paise/kWh). The security-constrained unit-commitment list shapes which thermal stations run to keep the national grid secure and operating at least cost.

8Southern Region's 28 June system report: 49,050-MW peak met, frequency in band 67% of day
GRID-INDIA's Southern Region Daily System Operation Report for 28 June 2026 consolidates a peak demand met of 49,050 MW with zero shortage and 1,242.62 MU of energy, with frequency held within the 49.9-50.05 Hz band 67.2% of the time. State-level data shows Andhra Pradesh underdrawing about 2 MU and Tamil Nadu as the largest load centre, serving as the operational ledger for the southern grid's daily performance.
Details
CEA & GRID STANDARDS

8Meghalaya regulator extends public-comment window on draft 2026 state grid code to 8 July
The Meghalaya State Electricity Regulatory Commission (MSERC), via a public notice dated 26 June 2026, pushed back the deadline for stakeholder comments on the Draft MSERC (State Grid Code) Regulations, 2026 from 29 June to 8 July 2026, acting on a stakeholder request. The grid code, pre-published on 9 June 2026 under Section 86 of the Electricity Act, 2003, will govern operational standards for Meghalaya's transmission and distribution network, with the Commission warning that late submissions will not be entertained.

8WRPC circulates agenda for 16th Inter-State Transmission System meeting on commercial issues
The Western Regional Power Committee (WRPC) of the Central Electricity Authority circulated, on 27 June 2026, the agenda for the 16th Inter-State Transmission System (ISTS) meeting, addressing commercial and billing matters for transmission users in the western region. The agenda covers ISTS charges, losses and reconciliation issues that determine how transmission costs are apportioned among utilities, feeding into the periodic settlement framework governing India's pooled transmission network.
Details
DAY-AHEAD MARKET (DAM/GDAM/HPDAM)

8IEX day-ahead prices average Rs. 5.97/unit on 28 June as cleared volume hits 144 MU
The Indian Energy Exchange's Day-Ahead Market cleared 144,234.70 MWh, about 144.23 MU, on 28 June 2026 at an average market clearing price of Rs. 5,965.30/MWh (Rs. 5.97 per unit), with prices repeatedly touching the Rs. 10,000/MWh ceiling at peak hours. Purchase bids of 469,754 MWh far outstripped sell bids of 369,629 MWh, signalling a tight day-ahead market amid summer demand that benchmarks short-term power costs for DISCOMs and open-access consumers.

8Green day-ahead power clears at a Rs. 6.10/unit premium on IEX, 28 June snapshot shows
IEX's Green Day-Ahead Market settled at an average MCP of about Rs. 6,101.79/MWh (Rs. 6.10 per unit) on 28 June 2026, a premium over the conventional DAM's Rs. 5.97/unit, even as cleared green volumes stayed comparatively thin. The price signal indicates the value buyers place on renewable power as Renewable Purchase Obligation compliance tightens across states, reinforcing the exchange's role in clean-energy price discovery during the summer season.

8IEX High Price Day-Ahead Market sees near-zero clearing on 28 June despite 72,682-MWh sell bids
The High Price Day-Ahead Market on IEX recorded effectively no clearing on 28 June 2026, with purchase bids of just 970 MWh against 72,681.80 MWh of sell bids leaving market-cleared volume at zero. The HPDAM, intended for costlier flexible supply, drew little buyer interest, suggesting the conventional DAM and RTM met demand without recourse to premium segments that day, underscoring the niche role this exchange product still plays.

REAL-TIME MARKET (RTM)

8IEX Real-Time Market clears 180 MU on 28 June at Rs. 5.48/unit average
IEX's Real-Time Market cleared 179,709.48 MWh, about 179.7 MU, on 28 June 2026 at an average MCP of Rs. 5,483.49/MWh (Rs. 5.48 per unit), with purchase bids averaging 31,832 MW against sell bids of 14,689 MW and prices spiking to the Rs. 10,000/MWh cap. The robust real-time volumes, exceeding the day-ahead market, show utilities increasingly leaning on 15-minute balancing to manage summer load swings.

8Power exchange's RTM volume profile clears just 400 MWh at the price cap on 28 June
The RTM Market Volume Profile Report for 28 June 2026 shows only about 400 MWh cleared across four late-night 15-minute blocks, all at the Rs. 10,000/MWh ceiling, against sporadic small purchase bids. The minimal volumes on this exchange segment underline how concentrated real-time liquidity remains on the leading power exchange, IEX, by comparison, leaving this smaller platform with a marginal share of real-time trading activity.

TERM-AHEAD & GREEN TERM-AHEAD (TAM/GTAM)

8IEX Green Term-Ahead contracts trade at the Rs. 10/unit ceiling across 26-28 June window
IEX's Green Term-Ahead Market trade data for 26-28 June 2026 shows green daily and intraday contracts clearing at the Rs. 10,000/MWh (Rs. 10 per unit) price ceiling across roughly 495 contract entries, underscoring firm demand for term renewable power. The ceiling-bound prices point to scarcity pricing in the green short-term market as buyers move to lock in clean energy ahead of tightening Renewable Purchase Obligation deadlines for utilities.

8Conventional Term-Ahead power pins at the Rs. 10/unit cap across 2,300-plus IEX contracts, 26-28 June
IEX's Term-Ahead Market trade compilation for 26-28 June 2026 records more than 2,348 contract entries, about 683 on 28 June alone, with daily and contingency contracts repeatedly clearing at the Rs. 10,000/MWh ceiling. The persistent cap-level pricing across term products signals a tight short-term supply environment on the exchange during the summer peak, as buyers compete for firm power outside the day-ahead and real-time segments.

ANCILLARY & INTRADAY (ASDAM/IDAS/SCUC)

8No ancillary bids cleared on IEX's Ancillary Day-Ahead Market through 28 June, snapshot shows
The Ancillary Services Day-Ahead Market on IEX recorded zero TRAS bids and zero cleared volume across 26-28 June 2026, indicating that tertiary-reserve needs were met outside the exchange-based ancillary segment. The blank clearing reflects the still-nascent role of market-based ancillary procurement relative to the regulated TRAS/SRAS mechanism run by GRID-INDIA, which continues to handle the bulk of India's reserve management.

8Exchange's IDAS market sees no cleared volume on 28 June despite listed bids
The IDAS Market Volume Profile Report for 28 June 2026 shows no market-cleared volume across the day's 15-minute blocks, with purchase and sell bids failing to match. The empty clearing reflects thin liquidity in this intraday segment relative to the dominant day-ahead and real-time exchange platforms operating the same day, pointing to limited participant interest in this particular trading window.

8Grid-India's May 2026 ancillary report: SCUC charges hit Rs. 804 crore as reserves keep grid stable
GRID-INDIA's implementation report on the TRAS/SRAS/SCUC mechanism for May 2026 (4-31 May) shows Security Constrained Unit Commitment dispatching 1,724.43 MU up and 1,129.78 MU down, with net SCUC charges of Rs. 804.50 crore, by far the costliest reserve product. Tertiary reserves (TRAS) delivered 396.16 MU up and 1,226.33 MU down for net charges of Rs. 29.68 crore, while secondary reserves (SRAS) netted Rs. 13.05 crore, quantifying the rising cost of balancing the grid.

DEVIATION SETTLEMENT (DSM)

8PXIL's deviation-settlement market records nil clearing across 26-28 June window
Power Exchange India Limited's (PXIL) DSM Report for the 26-28 June 2026 window shows zero cleared buy and sell volumes at zero price across the 15-minute blocks reported. The flat results indicate negligible activity on PXIL's deviation-settlement-linked segment of the power market during the period, contrasting with the more active day-ahead and real-time trading recorded on rival exchanges over the same window.

EXCHANGE AUCTIONS & CIRCULARS

8HPX lists reverse auction 01040 for Rajasthan Urja Vikas to procure thermal power
Hindustan Power Exchange (HPX) circulated specifications (Circular HPX_RA_01011, dated 27 June 2026) for an any-day single-side reverse auction, Auction No. HPX/27062026/01040, with Rajasthan Urja Vikas and IT Services Limited as buyer of thermal energy. The auction timeline opens with sellers' interest-quantity submissions from 27 June and runs through 29 June 2026, reflecting continued spot procurement by Rajasthan's distribution arm to meet demand.

8HPX publishes second reverse-auction tender (No. 01041) dated 27 June
Hindustan Power Exchange (HPX) issued specifications for a further any-day single-side reverse auction, Auction No. HPX/27062026/01041, dated 27 June 2026, inviting sellers to bid into a buyer-initiated power-procurement contract on the exchange. The auction follows HPX's byelaws and business rules, adding to the day's spot-market procurement activity routed through the power exchange as buyers sought competitive thermal-power supply to meet near-term demand requirements.
Details
SOLAR POWER

8MNRE opens one-month window for stranded solar projects to commission on ALMM List-I modules
An MNRE Office Memorandum (No. 283/40/2026-Grid Solar) dated 23 June 2026 lets utility- and C&I-scale renewable projects installed before 1 June 2026, but stranded by the ALMM List-II deadline, be provisionally commissioned using ALMM List-I solar modules, provided developers have applied for List-II exemption on the DCR portal. The relaxation runs for one month from issuance and permits generation, injection, wheeling, banking and settlement under open access pending a final decision, without extending the 1 June 2026 ALMM List-II effective date.

8Gujarat floats conditional-commissioning undertaking for solar developers under MNRE's 23 June ALMM window
Gujarat's power utilities have issued a notarised undertaking template, on Rs. 300 stamp paper, operationalising MNRE's 23 June 2026 ALMM clarification for non-rooftop solar projects registered with GEDA and connected via GETCO/MGVCL. Developers must accept that projects commissioned on ALMM List-I modules will be disconnected from the grid without prior notice if their ALMM List-II exemption claim on the DCR portal is rejected, and must replace modules before reconnection, with no financial claims permitted against MGVCL.

ROOFTOP & DISTRIBUTED SOLAR (PM SURYA GHAR / KUSUM)

8Jaipur DISCOM issues net-metering SOP for rooftop solar under RDSS smart-metering rollout
Jaipur Vidyut Vitran Nigam Limited (JVVNL) has directed AMISP and UBS agencies to standardise installation of smart meters as net meters for solar-rooftop consumers across Rajasthan DISCOMs under the RDSS Smart Metering Program. The order, digitally signed on 24 June 2026, mandates a stock of at least 20 single-phase and 20 three-phase pre-configured net meters per division, one dedicated installation team per sub-division, and SLA-based monitoring of reverse-current alerts to prevent billing errors and revenue loss.

POLICY & INCENTIVES

8Amitabh Kant: India's 283 GW non-fossil fleet is an energy-security shield against a $180-billion import bill
In an opinion piece, former NITI Aayog CEO Amitabh Kant argues India must treat its energy transition as a core energy-security strategy after the Strait of Hormuz disruption exposed dependence on imported crude (85-90% of supply, roughly 5 million barrels a day) and a fossil-fuel import bill near USD 180 billion. He notes India has crossed 283 GW of installed non-fossil capacity, including over 154 GW of solar and 56 GW of wind, meeting its 50% non-fossil electricity target ahead of the 2030 deadline.
Details
RETAIL TARIFF REVISION

8Andhra's APCPDCL to levy Rs. 0.4047/unit fuel surcharge on April power in July 2026 bills
Under APERC Regulation No. 4 of 2005, the AP Central Power Distribution Company (APCPDCL) has computed a Fuel and Power Purchase Cost Adjustment (FPPCA) of Rs. 0.4047 per unit for April 2026, to be recovered uniformly from all consumer categories in July 2026 bills. The surcharge stems from the actual weighted-average power-purchase cost rising to Rs. 5.7861/unit against the approved base of Rs. 5.4233/unit, on 1,743.48 MU of purchases. Free-power categories such as agriculture will be claimed from the state government.

COMMISSION ORDERS (CERC/SERC)

8CERC approves Rs. 366-crore annual fixed charges for NTPC's 440-MW Tanda Stage-I in 2024-29 tariff order
In its 27 June 2026 order in Petition No. 702/GT/2025, CERC determined the 2024-29 tariff for NTPC Limited's Tanda Super Thermal Power Station Stage-I (four units of 110 MW each, totalling 440 MW) in Uttar Pradesh. The Commission allowed annualised annual fixed charges of Rs. 36,607.57 lakh for 2024-25, trimming NTPC's claim of Rs. 38,929.73 lakh, with sole beneficiary Uttar Pradesh Power Corporation Limited (UPPCL) bearing the cost across the five-year control period.

8CERC grants EKI Energy a Category-IV inter-state electricity trading licence
EKI Energy Services Limited disclosed that the Central Electricity Regulatory Commission has granted it an Inter-State Electricity Trading Licence in Category IV, authorising it to undertake power trading across state boundaries. The licence, disclosed under Regulation 30 of SEBI LODR, marks the carbon-credit specialist's formal entry into India's inter-state electricity trading market, widening EKI's energy-transition footprint beyond carbon offsets into physical power trade.

REGULATORY PETITION & REVIEW

8CERC disposes NVVNL cross-border connectivity petition as withdrawn in 25 June 2026 order
The Central Electricity Regulatory Commission, in its order dated 25 June 2026 in Petition No. 123/MP/2024, permitted NTPC Vidyut Vyapar Nigam Limited (NVVNL) to withdraw its plea invoking the Power to Remove Difficulty under Regulation 42 of the 2022 GNA Regulations. NVVNL told the four-member Commission chaired by Jishnu Barua that amendments to the GNA Regulations, 2022 and CBTE Regulations, 2019 had rendered most prayers infructuous, while retaining liberty to return on cross-border GNA liability and PPA-linkage questions.

8PSPCL moves PSERC for one-time settlement scheme for defaulting consumers in Petition 51 of 2026
Punjab State Power Corporation Limited (PSPCL) has issued a public notice inviting objections and suggestions on Petition No. 51 of 2026, filed before the Punjab State Electricity Regulatory Commission (PSERC) seeking a One-Time Settlement (OTS) Scheme for all categories of defaulting consumers except agricultural pumpset users, as they existed on 31 March 2025. The scheme, sought under Regulation 68 of the Supply Code-2024, could let chronic defaulters clear arrears on concessional terms, improving PSPCL's cash collections against its mounting receivables overhang.
Details
CAPACITY COMMISSIONING & COD

8POWERGRID commissions transmission for 3,500-MW Ananthapuram-Kurnool solar zones in Andhra Pradesh
Power Grid Corporation of India Limited has fully commissioned the Transmission Scheme for Solar Energy Zone in Ananthapuram (2,500 MW) and Kurnool (1,000 MW), Andhra Pradesh, with effect from 24 June 2026, with the Date of Commercial Operation notified on 25 June 2026. The project, built through POWERGRID Ananthpuram Kurnool Transmission Limited, evacuates 3,500 MW of solar capacity from two of Andhra Pradesh's largest renewable zones, strengthening grid evacuation for southern India's solar build-out.

8Adani Green crosses 19,985 MW as Khavda adds another 150-MW solar block
Adani Green Energy Limited told exchanges that its wholly-owned step-down subsidiary Adani Renewable Energy Eight Limited (ARE8L) operationalised a 150 MW solar power project at Khavda, Gujarat, with the decision taken at 10:42 p.m. on 27 June 2026. With this addition, AGEL's total operational renewable generation capacity reached 19,985.8 MW, alongside operational battery energy storage capacity of 3,366 MWh, keeping India's largest renewables developer on track toward 50 GW by 2030.
Details
DIVIDEND & BOARD DECISIONS

8POWERGRID board clears borrowing-limit hike to Rs. 2.2 lakh crore and $500-million ECB from Bank of Baroda
Power Grid Corporation of India Limited's board, meeting on 26 June 2026, approved raising the company's borrowing limit from Rs. 1,80,000 crore to Rs. 2,20,000 crore, subject to shareholder approval at the AGM. The board also cleared External Commercial Borrowings of up to USD 500 million from Bank of Baroda and an investment for upgrading the Udumalpet-Madurai 400 kV single-circuit line. The enhanced headroom positions the transmission major to fund a heavier capex pipeline as inter-state grid expansion accelerates.

8PFC board approves scheme of merger by absorption involving Power Finance Corporation
Power Finance Corporation Limited disclosed that its board, at a meeting on 28 June 2026, approved a scheme of merger by absorption involving the state-run power-sector lender, after considering recommendations of the Audit Committee and Committee of Independent Directors. The intimation references an Appointed Date, transfer of the undertaking on a going-concern basis, and issuance of shares to eligible shareholders under the scheme. The restructuring carries implications for PFC's consolidated balance sheet as a leading financier of India's generation and transmission projects.

8Indo Tech Transformers approves Rs. 360-crore capex to lift capacity to 50,000 MVA
Indo Tech Transformers Limited said its board on 26 June 2026 approved an additional capital expenditure of Rs. 360 crore to expand plant capacity to 50,000 MVA across transformers up to the 400 kV range, executable through FY2028-29. The move builds on earlier approved tranches of Rs. 75 crore, Rs. 25 crore and Rs. 35 crore taking capacity to 16,000, 20,000 and 25,000 MVA respectively. The expansion targets surging demand for grid transformers driven by renewable evacuation and transmission build-out.

8Onix Solar Energy to shift registered office within Mumbai from 1 July
Onix Solar Energy Limited said its board on 26 June 2026 approved shifting the registered office within Mumbai's local limits, from Office A-204 to A-308 at Rustomjee Central Park, Andheri East, effective 1 July 2026. The relocation does not change the Registrar of Companies' jurisdiction. The board meeting, which addressed the administrative change, ran from 12:00 to 12:45 p.m. on 26 June 2026.

FUND RAISING & CAPITAL

8Adani Energy Solutions calls 1 July board meeting to weigh equity and QIP fundraise
Adani Energy Solutions Limited gave prior intimation under Regulation 29(1)(d) of SEBI LODR that its board will meet on 1 July 2026 to consider raising funds through issuance of equity shares or other eligible securities, including via private placement, qualified institutions placement (QIP) or preferential issue. The proposal is subject to regulatory and shareholder approvals. A successful raise would bolster the Adani transmission-and-distribution arm's war chest for its expanding grid and smart-metering order book.

8Taylormade Renewables allots 10 lakh convertible warrants at Rs. 123.51 each on preferential basis
Taylormade Renewables Limited said its board on 26 June 2026 allotted 10,00,000 convertible warrants at Rs. 123.51 each (Rs. 10 face value plus Rs. 113.51 premium) on a preferential basis to two non-promoter allottees, Sukhdev and Sangitaben Punjabi, who paid Rs. 1,54,38,750 each as the 25% upfront amount. The issue follows BSE in-principle approval dated 12 June 2026. The capital raise supports the small-cap renewables player's growth plans.

8POWERGRID committee approves General Information Document for bond issuances
Power Grid Corporation of India Limited (BSE: 532898; NSE: POWERGRID) informed exchanges, under Regulation 30 of SEBI LODR, that its Committee of Directors for Bonds approved the General Information Document (GID) for raising funds through bonds. The GID is a precursor to placement-memorandum-based debt issuances, supporting the transmission utility's capex funding plans as POWERGRID expands its inter-state network and pursues a heavier capital expenditure pipeline across India's transmission corridors.

CREDIT RATING & ANALYST REPORT

8HPL Electric & Power discloses fresh India Ratings credit rating action
HPL Electric & Power Limited (BSE: 540136; NSE: HPL) made a disclosure under Regulation 30 of SEBI LODR regarding a credit rating action by India Ratings and Research on its bank facilities. The update on the electrical-equipment and smart-metering maker's credit standing is material for lenders and bondholders tracking its balance-sheet strength amid an ongoing metering order ramp-up, with the rating outcome bearing on the company's borrowing costs going forward.

8JSW Energy unit JSW Renew Energy Three bags 'IND A/Stable' rating
JSW Energy Limited (BSE: 533148; NSE: JSWENERGY) disclosed that India Ratings and Research (Ind-Ra), in a release dated 26 June 2026, assigned 'IND A/Stable' to the bank-loan facilities of JSW Renew Energy Three Limited, a step-down subsidiary. The rating supports financing for the renewables arm as JSW Energy expands its green-generation and storage pipeline, reflecting the parent group's continuing push into clean-power capacity addition.

8ICRA withdraws ratings on ACME Chittorgarh Solar Energy's bank facilities
ICRA has withdrawn the ratings assigned to the bank facilities of ACME Chittorgarh Solar Energy Private Limited (ACSEPL), in line with its policy on rating withdrawals; key rating drivers, liquidity and sensitivities were not captured as the instruments are being withdrawn. The action removes external surveillance on the solar SPV's debt, a development lenders to ACME-group project vehicles will note.

8ICRA withdraws 'B+ (Stable)' ratings on Energia Biofules LLP
ICRA has withdrawn the long-term [ICRA]B+ (Stable) ratings, tagged Issuer Not Cooperating, on the fund-based cash-credit and term-loan facilities of Energia Biofules LLP. The withdrawal follows the issuer's non-cooperation with the rating process, leaving the biofuels venture's debt without an active ICRA rating and removing a key surveillance signal that lenders had relied upon to monitor the entity's credit profile and repayment capacity over time.

8ICRA keeps K G N Electricals' Rs. 5-crore facilities in 'Issuer Not Cooperating' category
ICRA said the ratings on K G N Electricals continue to remain under the Issuer Not Cooperating category, with the long-term Rs. 5.00-crore fund-based limit at [ICRA]B+ (Stable) and short-term non-fund-based facilities at [ICRA]A4. The continued INC tag reflects the electrical contractor's failure to provide information for surveillance, a credit-monitoring red flag for its lenders that signals heightened risk around the firm's outstanding facilities.

8ICRA reaffirms TNPDCL bond rating at 'A-(CE) Stable', withdraws Rs. 20-crore NCD
ICRA reaffirmed the [ICRA]A-(CE) (Stable) rating on the non-convertible bond programme of Tamil Nadu Power Distribution Corporation Limited (TNPDCL) and withdrew the rating on a Rs. 20.00-crore NCD, noting Rs. 33.93 crore of the programme was partially repaid per schedule. The credit-enhanced (CE) rating reflects the structural support underpinning the Tamil Nadu DISCOM's market borrowings amid sector-wide distribution stress affecting state-owned power utilities.
Details
 For reference purposes the website carries here the following tenders:
 
8Tender for replacement of damage radiators of AHU/FAU and its allied accessories Details
 
8Tender for work of providing and fixing of GPS clock at various substations Details
 
8Tender for increasing capacity 2x40MVA and 1x63 MVA to 3x63MVA transformer Details
 
8Tender for supply and retrofitting of 400kV pantograph isolators Details
 
8Tender for supply, installation and commissioning of 250 kVA DG set Details
 
8Tender for supply, installation and commissioning of sensor-based wheel washing system for fly ash Details
 
8Tender for urgent procurement of CI fittings Details
 
8Tender for repairing of turbine bearing Details
 
8Tender for supply and ETC of two sets of battery banks, 220V/2000 AH, tubular (Lead-Acid), HDP-II, SAN container along with accessories Details
 
8Tender for supply of terminal studs with housing assembly of 420kV, 3150A, HCB isolator installed Details
 
8Tender for supply of spares of air compressor Details
 
8Tender for empanelment of agencies for restoration of distribution infrastructure during Details
 
8Tender for procurement of multifunction energy meter for 0.4kV bus and 6.6kV station bus Details
 
8Design, engineering, manufacture, factory testing, supply, transportation, supervision of installation and commissioning of 42 Nos. of 595.23kVAr cpacitor units Details
 
8Tender for shifting and utility relocation plan of electrical HT/LT lines DTRs Details
 
8Tender for providing fitting and fixing of cupboard or wardrobe shutter and shelves Details
 
8Tender for procurement of spares for EH oil pump installed Details
 
8Tender for procurement of filter element for MDBFP voith coupling and generator Details
 
8Tender for assistance in ESP control room operation in all three shift Details
 
8Tender for constructing 11 kV line with UG cable 300 sqmm Details
 
8Tender for laying of HT UG cable Details
 
8Tender for constructing 11kV UG cable Details
 
8Tender for construction of new 33 kV line Details
 
8Tender for development of distribution infrastructure Details
 
8Tender for work of tightening of jumpers of 400 kV D/C transmission line Details
 
8Tender for roof repair and fabrication works Details
 
8Tender for providing services for dam regulation control system and associated equipment Details
 
8Tender for procurement of cylinder head assy, liner and cylinder liner gasket kit Details
 
8Tender for service contract for overhauling of PA FAN FD Fan and ID Fan Details
 
8Tender for service contract for overhauling of high pressure valves Details
 
8Tender for work of overhauling / servicing of 145kV circuit breakers, at various S/stn. Details
 
8Tender for work of overhauling / servicing of 245kV circuit breakers, at various S/stn. Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
State-level climate exposure puts Rajasthan, Gujarat and Arunachal at center of India's renewable risk map: Report Details
 
8Texmaco Rail & Engineering bags 5-crore order from Mangalore Coal Terminal Details
 
8Egypt Targets 60% Renewable Electricity by 2040 Details
 
8PFC-REC merger gets board approval, creating India’s largest power sector NBFC Details
 
8Uttar Pradesh Tops India in Power Supply, Surpasses Maharashtra and Gujarat Details
 
8Bihar records its all-time high electricity demand of 9,068 MW on June 24 Details
 
8Govt-backed loans to drop by Tk15,108crore on power sector repayments Details
 
8India’s MSMEs Face Existential Threat from High Power Tariffs; Call for Structural Reforms Details
 
8Weekly economy wrap: Core sector slowdown, US trade talks shape policy week Details
 
8519 small hydel power units allotted, 386 cancelled: A Karnataka lesson for Centre Details
 
8India opens nuclear sector to private investment with $210b plan Details
 
8Govt prioritising renewable energy to rebuild power sector: Power Minister Details
 
8Sukhbir Badal hits out at AAP govt over 'power shortage'; says it failed farmers Details
 
8Stock Picks Today: HDFC Bank, CG Power, Astral, Eternal, Yes Bank, IT Companies, And More On Brokerages' Radar Details
 
8Govt prioritises renewable energy, steps up domestic gas exploration, minister tells parliament Details
 
8Millions of Indian reservoirs sat idle for decades, and now engineers are turning them into floating power plants Details
 
8Tata Motors Passenger Vehicles plans 4 new EVs, over 10 refreshes by FY31 Details
 
8Breaking: Torrent Power acquires Rajpura Thermal Plant for Rs 3,632.35 crore Details
 
8Torrent Power Buys Nabha Power, Adani Ports Upgraded; Pharma Faces USFDA Alerts Details
 
8India needs 2,000GW of new power capacity in near future Details
 
8REC and PFC Boards Approve Merger to Form INR 11 Lakh Crore Power Lender Details
 
8Power-surplus Punjab claim exposed on ground: BJP's Dhillon attacks CM Mann led AAP Govt Details
 
890% of Planned Indian Renewable Projects Face Climate Risk: Zurich Report Details
 
8Adani Green Commissions 150 MW Solar Project in Gujarat, Capacity Hits 19,985 MW Details
 
You can also click on Newsclips for more Details
 For reference purposes the website carries here the following tenders:
 8
Tender for work of various new electricity connection Details
 
8Tender for line laying shifting and other related works Details
 
8Tender for construction of different type electrical work Details
 
8Tender for hot spot scanning of 765 kV CKT-I and II transmission lines Details
 
8Tender for construction of 02 Nos. 220kV GIS feeder bay Details
 
8Tender for construction of new rain water harvesting Details
 
8Tender for proposed work high mast light and fencing work Details
 
8Tender for various repair works of control room and yard Details
 
8Tender for construction of tube well, water supply arrangement for earthing and miscellaneous civil works Details
 
8Tender for construction of power transformer pit and renovation of yard, repair control room at 33 kV S/S Details
 
8Tender for supply of 11/0.433 kV 160 kVA distribution transformers Details
 
8Tender for repair/ refurbishment of eroded hard coated 30X francis runners Details
 
8Tender for construction work of erection 33kV ground cable Details
 
8Tender for work of operation and maintenance of (2655KLD) sewage treatment plant Details
 
8Tender for work contract for complete operation and assistance in operation work of hydrogen generation plant Details
 
8Tender for annual work contract for providing assistance in collection, preparation and transportation of various coal samples Details
 
8Tender for work for refurbishment of roof structure of conveyor Details
 
8Tender for development and maintenance of horticulture work Details
 
8Tender for biennial rate contract for ash dyke maintenance work Details
 
8Tender for repair and strengthen of over the 1st raising of central ash dyke Details
 
8Tender for miscellaneous civil and maintenance works Details
 
8Tender for construction of lift room and providing & fixing of lift Details
 
8Tender for supply and E and C of station lighting system Details
 
8Design, fabrication, supply, installation, testing and commissioning with RMS of 170 kW cap.grid connected solar PV power plant Details
 
8Design, fabrication, supply, installation, testing and commissioning with RMS of 60 kW cap.grid connected solar PV power plant Details
 
8Design, fabrication, supply, installation, testing and commissioning with RMS of 120 kW cap.grid connected solar PV power plant Details
 
8Tender for construction of 2 Nos transformer bays and installation of 110/11 kV, 20 MVA transformers Details
 
8Tender for manufacture, testing and supply of 11kV cable termination kits of various sizes and types Details
 
8Tender for construction of new control room at 66kV S/Stn Details
 
8Tender for augmentation of 132 kV S/Stn Details
 
8Tender for engagement of agency for providing consultancy and monitoring services Details
 
8Tender for insulation and cladding work at turbine and boiler Details
 
8Tender for supply and spreading of gravel in bays at 132 kV sub station Details
 
8Tender for annual running contract of mtc. of and structures Details
 
8Tender for supply delivery and installation of curtains and blinds required Details
 
8Tender for supply of 33 kV 3 pin type AB switch 630 Amp Details
 
8Tender for repair reconstruction of damaged PCC lining Details
 
8Tender for facelifting of power house Details
 
8Tender for repair works of settled area near intake structure Details
 
8Design, engineering, supply, laying, jointing, testing and commissioning of 220kV D/C 1x1200 sq.mm. U/G XLPE cable Details
 
8Tender for conversion of existing 220/33/11 kV AIS into 400/220/33 kV GIS along Details
 
8Design, engineering, supply, erection, testing and commissioning of 400/220/66kV GIS sub-station Details
 
8Tender for De-siltation in front of intake mouth old intake pump house Details
 
8Tender for development with PCC including RCC in 400kV switch yard Details
 
8Tender for general civil maintenance works Details
 
8Tender for replacement of old existing eroded MS pipeline Details
 
8Tender for annual maintenance contract (AMC) for operation and maintenance of distribution network Details
 
8Tender for drawl of 1.095 KM 11kV 300SQMM UG cable Details
 
8Tender for construction of VCB, CT, station transformer, cable trench, pathway, PTR and switchyard Details
 
8Tender for construction work of 01(one) nos (QD-3) type tower Details
 
8Tender for supply, laying and spreading of crushed stone Details
 
8Tender for construction of 33kV indoor GIS feeder bays Details
 
8Tender for construction of 400 kV transmission line Details
 
8Tender for various regular preventative maintenance / emergency and breakdown works of various 220kV & 100kV substations Details
 
8Tender for work of health assessment of grounding system & soil resistivity measurement (earthing audit) of existing earth mat at various Details
 
8Tender for annual maintenance contract (AMC) for the demonstration, preventive maintenance as well as repairing work including supply of required spare of nitrogen injection fire protection systems Details
 
8Tender for work of servicing, repairing & overhauling of ABB Make 245 kV & 145 kV circuit breakers Details
 
8Tender for AMC for work of arresting oil leakages from the various joints of power transformers / ICTs & oil filled equipments Details
 
8Tender for work of Bi-annual (two year) maintenance contract for OPGW ADSS communication network Details
 
8Tender for erection and maintenance of HT,LT & TC Details
 
8Tender for balance erection work of 66kV link line Details
 
8Tender for Bi- annual rate contract for restoration of various 400kV class transmission lines Details
 
8Tender for Bi- annual rate contract for restoration of various 66kV class transmission lines Details
 
8Tender for Bi- annual rate contract for emergency power restoration work of 400/220/132/66kV lines Details
 
8Tender for supply of various types of clamp for 220 kV switchyard Details
 
8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes of various Details
 
8Tender for rate contract for work of removing, lifting/shifting, O/H & refitting of various sizes of LT motors Details
 
8Design, supply erection commissioning and testing of water distribution system for natural draught cooling towers Details
 
8Tender for ARC for erection and maintenance of HT, LT & TC Details
 
8Tender for work of constructions of new maintenance free earth pit Details
 
8Tender for rate contract for Work of laying of various size of cable Details
 
8Tender for erection, maintenance and dismantling work of overhead HT/LT line Details
 
8Tender for supply of various size of gate valves, diaphragm valve Details
 
8Tender for supply of fire system pumps Details
 
8Tender for supply of canopies for DCS panels Details
 
8Tender for supply of network cables for network maintenance Details
 
8Tender for supply, erection, testing and commissioning of 360 V DC, 515AH, KBH, Ni-Cd type battery set Details
 
8Tender for supply of various fasteners and consumables Details
 
8Tender for supply of ACB & panel spares Details
 
8Tender for supply, erection & commissioning and testing of emission control device/equipment (RECD) for 1500 KVA DG set installed Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8India-Seychelles trade and investment ties gain momentum with stronger connectivity and renewable energy cooperation Details
 
8India Advances Green Urea Mission with Industry Push Details
 
8Envision and Juniper launch India’s largest wind turbine Details
 
8Powerica Ltd incorporates wholly owned subsidiary Windfusion Renewable Details
 
8MNRE Amends Prototype Wind Turbine Guidelines, Allows Sale of Power To DISCOMs Details
 
8Alstom wins €107M rail locomotive maintenance contract Details
 
8Rs 37,500-crore coal-gasification scheme links incentives to competitive bids Details
 
8India Lines Up $100 Bn Investment In Green Energy, Still Lags Behind Its Asian Peers Details
 
8Coal’s unexpected comeback on Middle East conflict energy security fears Details
 
8Refex Industries bags Rs 21-crore ash transportation order Details
 
84 Mega Projects Worth Rs 47,600 Crore Announced in Odisha: Check the Companies Involved and Areas Set to Benefit Details
 
8Naresh Patel's Renewable Energy Journey Contributes to India's Clean Energy Growth Details
 
8India Leads BRICS Energy Cooperation With Smart Grid And Energy Storage Initiatives Details
 
8India set to become world’s No. 2 solar market; total capacity crosses 150 GW Details
 
8Building energy systems for the future Details
 
8TN power sector White Paper: TNEB debt hits Rs 2.47 lakh crore, but annual deficit plummets to Rs 933 crore Details
 
83 Stocks That Could Be the Biggest Winners as India Plans 500 GW of Renewable Energy Capacity by 2030 Details
 
8NLC India Raises Rs 500 Crore via Commercial Papers to Boost Short-Term Liquidity and Working Capital Details
 
8Is electricity the new oil Why firms are pushing towards electrification Details
 
8Freebies to continue but at what cost White paper reveals that debt of Tamil Nadu power sector crosses Rs 2.47 lakh crore but Vijay govt to continue provide ‘free electricity’ for farmers Details
 
8India Lines Up $100 Bn Investment In Green Energy, Still Lags Behind Its Asian Peers Details
 
8Adani Targets 10 GW Nuclear Capacity by 2035, Eyes Private Sector Nuclear Lead Details
 
8Why some states lag in rooftop solar installation despite PM Surya Ghar Details
 
8Strategic power projects in Ladakh to be completed by September Details
 
You can also click on Newsclips for more Details
COAL PRODUCTION & STOCK

8India's thermal coal stocks at 59% of normative on 24 June 2026 across 190 monitored plants, CEA reports
The CEA Fuel Management Division's Daily Coal Stock Report as on 24 June 2026 covers 190 thermal stations (224,158 MW), holding 75,790 thousand tonnes of coal — about 59% of the normative requirement — with several plants below critical thresholds. Of these, 22 plants are based on domestic coal and 6 on imported coal. The report is the principal early-warning tool for coal-supply stress at power plants heading into the monsoon season.

GENERATION & PLF

8Coal generation hit 3,951 MU on 24 June 2026, beating programme as gas and lignite lagged
The CEA's category-wise, fuel-wise generation report for 24 June 2026 shows coal output of 3,951.75 MU above the 3,718.95 MU programme, while lignite (83.13 MU) and natural gas (63.91 MU) fell short of plan. Year-to-date coal generation reached 328,859 MU. Coal stations ran at 81.43% of monitored capacity (89.42% of capacity online), with 20,025 MW of coal capacity under outage on the day.

8Northern Region thermal fleet 93.7% stabilised on 24 June 2026 as hydro lags at 77%, CEA data shows
The CEA's generation overview for 24 June 2026 shows Northern Region thermal capacity 93.69% online and nuclear at 100%, while hydro stayed at 77.36% of capacity. The Western Region thermal fleet ran at 91.17% of capacity. Northern Region total generation stood at 1,311.68 MU against a 1,317.64 MU programme, with a coal stock of 11,173 thousand tonnes. Low hydro availability reflects pre-monsoon reservoir conditions.

8India's monitored capacity availability stood at 268,730 MW online on 24 June 2026, CEA reports
The CEA's All India Capacity Availability summary for 24 June 2026 shows 268,730 MW online out of 312,334 MW monitored, with 43,603 MW under maintenance — including 25,323 MW on planned outage and 8,116 MW forced. The Western Region carried the largest monitored capacity at 104,702 MW. The data quantifies how much fleet capacity was actually available to the national grid on the day.

8NTPC stations ran 9.4% below Northern programme year-to-date as of 24 June 2026, CEA reports
The CEA's NTPC generation overview for 24 June 2026 shows Northern NTPC stations 9.40% below their year-to-date programme, at 16,028 MU actual versus 17,691 MU, while Southern NTPC ran 11.11% above programme. The CEA's station-wise report details output, available capacity, coal stock and outages plant by plant, from Faridabad CCPP to Koldam hydro, tracking the central generator's fleet performance.

8Multiple 660-800 MW supercritical units under maintenance on 24 June 2026, including Ghatampur and Adani Mundra
The CEA's maintenance report for thermal and nuclear units of 500 MW and above for 24 June 2026 lists outages including Ghatampur (660 MW) on coal-feeding failure, Adani Mundra TPP-III (660 MW) and Mundra UMPP (800 MW) on water-wall tube leakage. The focus on large units highlights their outsized impact on national availability, with supercritical set outages materially tightening supply during peak summer demand.

8CEA lists thermal units stranded over a year, including 125 MW Giral sets marked for scrapping
The CEA's report on thermal and nuclear units out of grid for more than one year as of 24 June 2026 lists long-stranded capacity such as Giral TPS Units 1 and 2 (125 MW each, likely to be scrapped) and Rithala and I.P. CCPP gas units idle since 2013-2019. The report quantifies effectively retired-but-not-decommissioned capacity and informs decisions on plant retirement and replacement planning.

8CEA logs recommissioning of five thermal units on 24 June 2026, including GH TPS and Ropar TPS units
The CEA's recommissioning report for 24 June 2026 records units returning to service, including GH TPS (Lehra Mohabbat) Unit-2 (210 MW) after an ash-handling fix and Ropar TPS Unit-4 (210 MW) after a water-wall tube leak repair. The log tracks capacity restored to the grid. Faster recoveries ease supply during peak demand periods and reduce the supply-demand gap across the northern region.

HYDRO & RESERVOIR

8Bhakra reservoir 123 ft below full on 24 June 2026 as CEA tracks national hydro storage
The CEA's Daily Hydro Reservoir report for 24 June 2026 shows Bhakra at 476.0 m against a full level of 513.59 m and Pong at 402.51 m versus 426.72 m full. Balimela reservoir stood at 1,461.1 ft (against a 1,516 ft full reservoir level) with average generation of 240.46 MW and equivalent energy of 5.77 MU. The pre-monsoon drawdown limits hydro flexibility and is key to assessing hydro reserve for peak management.

8Eastern Region day-ahead demand forecast error held at 4.66% MAPE on 24 June 2026
Grid-India's Eastern Region forecasting report for 24 June 2026 records a day-ahead Mean Absolute Percentage Error of 4.66% (RMSE 5.46%) and an intraday MAPE of 4.7% (RMSE 6.37%) against actual demand peaking above 30,300 MW. Accurate forecasts underpin economical scheduling and reserve planning in the east, with the metrics gauging the quality of demand prediction in a fast-growing regional grid.
Details
PEAK DEMAND & POWER SUPPLY POSITION

8Northern Region demand peaks at 86,513 MW on 25 June 2026 with just 350 MW shortage, NRLDC reports
Grid-India's NRLDC Daily Operation Report for 25 June 2026 shows the Northern Region evening peak demand met at 86,513 MW against a requirement of 86,863 MW, leaving a 350 MW shortage, with day energy of 1,983 MU. Uttar Pradesh (394.1 MU) and Rajasthan (269.67 MU, including 39.41 MU wind and 54.14 MU solar) led state generation, capturing peak summer stress on India's largest regional grid.

8Western Region demand tops 71,788 MW on 25 June 2026 with zero shortage, WRLDC data shows
The WRLDC Daily Operation Report for 25 June 2026 records a Western Region peak of 71,788 MW at 15:00 met with no shortage. Gujarat alone peaked at 22,778 MW and generated 362.1 MU, while Maharashtra contributed 400.7 MU and Madhya Pradesh demand reached 11,219 MW. The report confirms the western grid comfortably absorbed peak summer load on the day.

8Eastern Region meets 30,884 MW peak on 25 June 2026 without shortage, ERLDC reports
Grid-India's ERLDC Daily Operation Report for 25 June 2026 shows the Eastern Region evening peak demand met at 30,884 MW against an equal requirement, with day energy of 705.15 MU and zero shortage. DVC generated 99.92 MU of thermal power while Bihar drew 169.34 MU on schedule, showing a balanced eastern grid through the day.

8North-Eastern grid faces 115 MW shortfall as peak hits 3,719 MW on 25 June 2026
The NERLDC Daily Operation Report for 25 June 2026 records a North-Eastern Region peak of 3,719 MW met against a 3,834 MW requirement, leaving a 115 MW shortage, with day energy of 74.67 MU. Assam carried the largest load with 49.89 MU consumption, met largely through inter-regional drawal. The small shortfall highlights persistent supply gaps in the hydro-dependent north-east.

8Southern Region peak reaches 55,201 MW on 25 June 2026 with no shortage, SRLDC reports
The SRLDC Power Supply Position Report for 25 June 2026 shows a Southern Region evening peak of 55,201 MW met without shortage and day energy of 1,313.42 MU. Tamil Nadu led demand at 19,661 MW (439.61 MU), followed by Karnataka at 11,020 MW, with the region drawing 500.07 MU on schedule. Solar contributed 192.48 MU and wind 118.99 MU to the southern generation mix.

FREQUENCY & DEVIATION INDICES (FDI/VDI)

8National grid frequency within IEGC band 99.4% of 25 June 2026, NLDC profile shows
Grid-India's NLDC frequency profile for 25 June 2026 shows the national grid within the 49.7-50.2 Hz IEGC band 99.40% of the time and within the tighter 49.97-50.03 Hz band 30% of the day. Frequency sat between 49.9 and 50.1 Hz for the bulk of the day. The profile confirms robust frequency control across the synchronous grid on a peak summer day.

8Southern grid held near 49.982 Hz on 25 June 2026 but spent 23.8% of day outside IEGC band
SRLDC's frequency profile for 25 June 2026 reports an average of 49.982 Hz, a Frequency Deviation Index of 0.046 and a standard deviation of 0.068, with frequency ranging from 49.735 Hz to 50.272 Hz. The grid stayed within the tight 49.97-50.03 Hz band 30% of the time but was outside the IEGC band 23.77% of the day — approximately 5.71 hours — indicating tighter frequency management challenges in the south versus the national grid.

8ERLDC reports 765kV buses within voltage band 100% of 24 June 2026
Grid-India's ERLDC Voltage Deviation Index data for 24 June 2026 shows key 765kV substations such as Ranchi New (average 773.37 kV) and Angul staying within the IEGC voltage band 100% of the time, with zero deviation hours. The VDI tracks voltage quality across eastern extra-high-voltage nodes, with stable voltage critical for equipment safety and reactive management across the eastern grid.

SYSTEM RELIABILITY & SECURITY

8NLDC reports zero ATC and N-1 violations across inter-regional corridors on 25 June 2026
Grid-India's NLDC System Reliability Indices report for 25 June 2026 records zero ATC violations and zero N-1 criteria breaches across all inter-regional corridors, including WR-NR, ER-NR and NEW-SR. The clean sheet signals comfortable inter-regional transfer headroom and reflects a secure national transmission network on the day.

8WRLDC flags DNHDDPDCL ATC violations in 30 blocks on 25 June 2026 while major states stay clean
Grid-India's WRLDC Daily System Reliability Indices report for 25 June 2026 shows zero ATC violations for Maharashtra, Gujarat, Madhya Pradesh, Chhattisgarh and Goa, but DNHDDPDCL breached available transfer capability in 30 blocks — 7.5% of 15-minute intervals, representing 31.2% of hours. The report highlights localised congestion in the western grid even as the broader system recorded zero N-1 contingency breaches.

8NLDC's May 2026 report shows all-India peak demand hit 270,820 MW against 542,354 MW installed capacity
Grid-India's NLDC Monthly Operational Report for May 2026 records an all-India maximum demand met of 270,820 MW on 21 May 2026, met across a total installed capacity of 542,354 MW that includes 230,780 MW of renewables and 250,829 MW of thermal. The 78-page report details region-wise installed capacity, daily demand profiles, diversity factors and the REC mechanism, providing the definitive monthly scorecard for India's grid and renewable transition.

LINE & GENERATION OUTAGES

814 southern thermal units, including two 800 MW sets, tripped on 25 June 2026, SRLDC outage log shows
SRLDC's reservoir-and-outage report for 25 June 2026 lists 14 thermal unit outages, including 800 MW units at Vijayawada, Yeramarus and Krishnapatnam tripping on boiler-tube leakage, plus a 600 MW Coastal Energy unit out since 20 June. Major reservoirs such as Idukki (707.44 m) and Srisailam (250.55 m) sat below last year's levels, spotlighting both forced outages and depleted hydro storage in the south.

82,948 MW of central-sector southern capacity under planned outage on 25 June 2026, SRLDC reports
SRLDC's Generating Unit Outage Report for 25 June 2026 shows 2,948 MW of central-sector capacity under planned outage, including a 500 MW Vallur unit on annual overhaul till 23 July and stranded LANCO Kondapalli units under NCLT since 2016. State-sector outages include Srisailam LBPH (4x150 MW) and Sharavathi units on annual overhaul, mapping the scheduled maintenance shaping southern generation availability.

8Eastern Region carries 513.65 MW of planned generation outages on 25 June 2026, NPMC report shows
The Eastern Region NPMC generation outage report for 25 June 2026 lists 513.65 MW of planned outages — 350 MW in the central sector (a GMR-KEL 350 MW unit on annual overhaul) and 163.65 MW in the state sector (OHPC hydro units at Burla, Hirakud and Balimela). The report distinguishes planned from forced outages across the eastern grid and feeds availability planning for the region.

8WRLDC tracks hundreds of transmission line outages across western grid on 25 June 2026
Grid-India's WRLDC Line Outage Report for 25 June 2026 spans 16 pages of 765kV, 400kV and 220kV line outages across the Western Region, listing element names, outage times and restoration status. The granular record helps operators manage congestion and contingency risk and is essential reading for transmission planners in the west during the peak summer demand period.

OCC MEETINGS & OUTAGE PLANNING

8Eastern Region peak demand climbs 9% to 34,875 MW in May 2026, 240th OCC minutes reveal
Minutes of the 240th Operation Coordination Committee meeting held on 12 June 2026 record Eastern Region energy consumption of 19,578 MU (up 2.9% year-on-year) and peak demand of 34,875 MW (up 9% over May 2025), even as approximately 25.4 GW of thermal capacity sat under outage nationally. The ERPC-chaired meeting tracked frequency response, 400kV and 220kV transmission upgrades and UVLS load identification of 300-400 MW in Odisha.

REGIONAL ENERGY ACCOUNT (REA/REMC)

8NRPC releases Ancillary Services and SCUC accounts for Northern Region, Week 11 of FY 2026-27, payment due 2 July 2026
The Northern Regional Power Committee published the Ancillary Services Account and Regional SCUC Account for Week 11 (8-14 June 2026), including a revised SCUC account for Week 9, with payment due 2 July 2026. The statement settles costs of Security Constrained Unit Commitment and ancillary reserves used to balance the grid, funding the standby generation that keeps the northern grid secure during demand swings.

8NERPC pegs reactive energy charge at 6.0 paise/kVARh for North-Eastern grid, week of 8-14 June 2026
The North Eastern Regional Power Committee released the Provisional Reactive Energy Account for 8-14 June 2026, with charges governed by CERC IEGC Regulation 2023 at 6.0 paise/kVARh effective 1 October 2025, escalating 0.5 paise per year. The 24-table statement details payables and receivables between beneficiaries and the regional pool, steering utilities toward disciplined voltage support in the north-east.

8NERPC settles secondary and tertiary reserve ancillary services for north-east, 8-14 June 2026
The North Eastern Regional Power Committee circulated the Provisional SRAS and TRAS account statement for 8-14 June 2026, settling payments to and from providers via the Regional Deviation & Ancillary Service Pool Account operated by NERLDC. The statement compensates generators providing secondary and tertiary frequency-response reserves, central to keeping north-eastern region frequency within the IEGC band.

8NLDC SCUC commits Darlipali, Talcher and Vindhyachal units for 26 June 2026 at ECRs up to 222 paise/kWh
Grid-India's NLDC Security Constrained Unit Commitment table for 26 June 2026 directs units including Darlipali (467.16 MW, ECR 115.9 p/kWh), Talcher (510.92 MW, 130.4 p/kWh) and multiple Vindhyachal stages (up to 222.1 p/kWh) to remain committed, ensuring must-run security despite economics. The schedule shapes the national despatch stack for the day.
Details
MINISTRY OF POWER

8Ministry of Coal unveils Rs. 37,500-crore scheme to push 100 MT coal gasification by 2030
The Ministry of Coal has approved a 'Scheme for Promotion of Surface Coal/Lignite Gasification Projects' carrying a total financial incentive of Rs. 37,500 crore, offering up to 20% of plant-and-machinery cost to selected applicants. The scheme is open to PSUs, private firms, JVs and consortiums of up to three companies setting up new gasification plants, targeting 100 million tonnes of coal gasification by 2030 to cut import dependence on LNG, urea, ammonia, methanol and other petrochemicals.

MNRE & BEE

8Lok Sabha Energy Committee to review India's wind power sector with MNRE and NIWE on 1 July 2026
The Standing Committee on Energy (2025-26) will meet at 11:30 AM on 1 July 2026 in Parliament House Annexe to take up 'Assessment of Wind Energy Sector in the Country'. Representatives of MNRE and the National Institute of Wind Energy will brief members. The sitting signals fresh parliamentary scrutiny of wind capacity addition as India chases its renewable targets.

8Parliamentary panel summons Ministry of Steel and RINL over steel-plant environmental issues on 3 July 2026
The Lok Sabha Standing Committee on Coal, Mines and Steel (2025-26) will sit at 11:00 AM on 3 July 2026 to hear the Ministry of Steel on 'Environmental Issues related to Steel Plants', followed by a 12:00 PM review of the functioning of Rashtriya Ispat Nigam Limited. The twin agenda places both pollution compliance and the troubled state steelmaker under direct legislative review.

TENDERS & PROCUREMENT (GEM/NIT)

8MePTCL extends Mawlai GIS tender to 1 July 2026 for 132/33kV substation upgrade to 3x50 MVA
Meghalaya Power Transmission Corporation Ltd has extended the bid submission date for its 132kV and 33kV indoor GIS tender (Bid ID MePTCL/CE(T)/NESIDS-OTRI 132 & 33kV MAWLAI GIS/2026) from 23 June to 1 July 2026 at 11:00 hrs. The project augments the 132/33kV Mawlai substation from 3x20 MVA to 3x50 MVA with 132kV bus-bar re-engineering under the NESIDS-OTRI scheme, strengthening transmission capacity in the Shillong area.

8APSPDCL opens direct recruitment for 135 Assistant Executive Engineer posts across 9 Andhra districts
The Southern Power Distribution Company of A.P. Ltd issued Notification No. 1/2026 on 25 June 2026 inviting online applications for Assistant Executive Engineer posts — 125 Electrical, 6 Civil and 4 Telecom — across nine districts under its jurisdiction. APSPDCL stressed a zero-tolerance, merit-only process under Articles 14 and 16 of the Constitution, warning that any external influence will trigger permanent disqualification, strengthening engineering capacity at one of Andhra Pradesh's largest distribution utilities.
Details
DAY-AHEAD MARKET (DAM/GDAM/HPDAM)

8IEX Day-Ahead prices hit Rs. 10,000/MWh in early blocks of 25 June 2026 before easing below Rs. 1,200
The IEX Day-Ahead Market snapshot for 25 June 2026 shows market clearing prices peaking at the Rs. 10,000/MWh ceiling in the first blocks before falling toward Rs. 1,148/MWh around midday solar hours, on cleared volumes near 5,000-10,000 MW per block. The day cleared 163,755.96 MWh at an average MCP of Rs. 4,566.76/MWh. The wide intraday price swing reflects solar-driven daytime surpluses reshaping hourly spot prices, with the weekly average holding near Rs. 4,122/MWh.

8IEX Green Day-Ahead Market weekly prices averaged around Rs. 6,000/MWh to 26 June 2026
The IEX Green Day-Ahead Market weekly snapshot (19-26 June 2026) shows daily green market clearing prices near Rs. 6,500/MWh with solar and non-solar segments cleared separately, on cleared volumes in the low-thousands of MWh per day. Earlier in the day on 25 June, prices fell from the Rs. 10,000/MWh ceiling in hour one to around Rs. 7,100/MWh in subsequent hours, on cleared volumes of 450-565 MWh. The green premium remains well above conventional Day-Ahead Market levels.

8IEX High-Price Day-Ahead Market cleared just 200.5 MWh in the week to 26 June 2026 at Rs. 20,000/MWh
The IEX HPDAM weekly snapshot (19-26 June 2026) shows total clearing of only 200.5 MWh against sell bids of nearly 495,000 MWh, with the rare trades priced at Rs. 20,000/MWh. On 25 June alone, sell bids peaked near 3,268 MWh per hour with no purchase bids and zero clearing through the day. The minimal clearing confirms scarce demand for high-priced power and reflects a comfortable supply environment through late June.

REAL-TIME MARKET (RTM)

8IEX Real-Time Market cleared 175,059 MWh at Rs. 4,711/MWh on 25 June 2026
The IEX Real-Time Market weekly snapshot (19-26 June 2026) shows 25 June clearing 175,058.86 MWh at an MCP of Rs. 4,710.99/MWh, with daily prices across the week spanning Rs. 4,074 to Rs. 6,358/MWh. Early blocks on 25 June cleared at the Rs. 10,000/MWh ceiling, with prices easing to around Rs. 3,855/MWh by hour one. RTM volumes rivalled the day-ahead market, underscoring its growing role in near-real-time trading.

8PXIL Real-Time Market cleared 2,550 MWh at Rs. 10,000/MWh ceiling on 25 June 2026
PXIL's daily RTM profile for 25 June 2026 records 2,550 MWh cleared at a weighted Rs. 10,000/MWh, part of a week in which daily volumes ranged from under 900 MWh to over 10,900 MWh, consistently at the price ceiling. Early blocks cleared 75-175 MWh at the Rs. 10,000/MWh ceiling before activity tapered. The persistent ceiling pricing on PXIL reflects scarcity-driven bidding on the platform through late June.

8HPX Real-Time Market reported nil clearing across 25 June 2026 blocks and through the week to 26 June
The Hindustan Power Exchange Real-Time Market snapshots for 25 June 2026 record zero purchase bids, sell bids and clearing across all 15-minute and hourly blocks. The HPX weekly snapshot (17-26 June 2026) also records near-zero cleared volume across the period, contrasting sharply with IEX's 175,059 MWh cleared on 25 June. The flat data highlights the thin liquidity on the newer exchange's real-time segment.

TERM-AHEAD & GREEN TERM-AHEAD (TAM/GTAM)

8IEX Term-Ahead Market logs daily-contract trades across NR, SR and WR on 25 June 2026 at Rs. 10,000/MWh ceiling
The IEX Term-Ahead Market trade details for 25 June 2026 record Daily Contract trades across northern, southern and western regions, with many blocks clearing at the Rs. 10,000/MWh ceiling on small volumes. The 13-page record tracks forward physical trades on the exchange. TAM lets participants lock in delivery from a day to months ahead, providing a hedging alternative to spot market procurement for power buyers.

8IEX Green Term-Ahead Market records green daily-contract trades for 25 June 2026 at Rs. 10,000/MWh
The IEX Green Term-Ahead Market trade details for 25 June 2026 list green daily-contract trades clearing at the Rs. 10,000/MWh ceiling on modest volumes, enabling buyers to source renewable power on a forward basis. GTAM helps obligated entities meet renewable purchase obligations outside long-term PPAs, providing a market-based route for green power procurement.

ANCILLARY & INTRADAY (ASDAM/IDAS/SCUC)

8IEX Ancillary segment drew up to 6,100 MWh of purchase bids in the week to 26 June 2026 but cleared negligibly
The IEX IDAS weekly volume profile (19-26 June 2026) shows scattered purchase bids of up to 6,125 MWh and sell bids of up to 428 MWh, with negligible clearing across the period. On 25 June itself, sell bids of up to 140.5 MWh in morning hours found no matched clearing. The IEX Ancillary Services Day-Ahead Market also recorded nil clearing through the week, indicating reserves were met through other mechanisms.

DEVIATION SETTLEMENT (DSM)

8NRPC bills northern utilities for Week-11 deviation charges; payment due 5 July 2026
The Northern Regional Power Committee released the Statement of Deviation Charges for Week 11 (8-14 June 2026) of FY 2026-27 under the CERC Deviation Settlement Mechanism, with payment due on or before 5 July 2026. The 32-page settlement allocates deviation payables and receivables among northern region constituents based on real-time frequency-linked drawal and injection, penalising grid indiscipline and rewarding entities that help maintain frequency near 50 Hz.

8NERPC issues provisional Deviation Settlement for North-Eastern grid for 8-14 June 2026
The North Eastern Regional Power Committee, on 24 June 2026, circulated the Provisional Deviation Settlement Mechanism statement under the ABT regime for 8-14 June 2026. The statement computes deviation charges payable to or by north-eastern region constituents under the CERC Deviation Settlement and Related Matters Regulations, enforcing scheduling discipline across the seven north-eastern states.

EXCHANGE AUCTIONS & CIRCULARS

8HPX opens two single-side reverse auctions for Uttarakhand Power Corporation covering solar, hydro and thermal with no ceiling price
Hindustan Power Exchange issued two circulars on 25 June 2026 for Any-day(s) Single Side Reverse Auctions on behalf of Uttarakhand Power Corporation Limited, sourcing solar, hydro and thermal energy — and in the second auction non-solar as well — at a regional delivery point with no ceiling price. The back-to-back auctions widen UPCL's competitive sourcing options and reflect growing DISCOM reliance on exchange-based procurement to manage cost and supply.
Details
SOLAR POWER

8India's renewables generate 1,198 MU in a day; June clean-energy output tops 26,700 MU, CEA reports
The CEA's Daily Renewable Generation Report for 24 June 2026 records all-India renewable output of 1,198.12 MU — comprising 603.92 MU solar, 566.40 MU wind and 27.80 MU from biomass, bagasse and small hydro. Cumulative June 2026 generation reached 26,717.03 MU, with solar (14,931.65 MU) outpacing wind (11,114.18 MU). The figures track the rising share of variable renewables that the grid must now absorb daily.

8Borosil Renewables wins DSIR recognition for in-house solar-glass R&D unit
Borosil Renewables Limited informed exchanges on 25 June 2026 that the Department of Scientific and Industrial Research, under the Ministry of Science and Technology, has accorded recognition to its in-house R&D unit. As India's only solar-glass manufacturer, the recognition supports indigenisation of a critical solar-module input and can unlock R&D-linked fiscal benefits as domestic solar manufacturing scales up.

8SECI schedules 3 July site visit for 70 MW solar + 25 MW/50 MWh BESS project at Ramagiri, Andhra Pradesh
SECI has fixed a joint site visit for 3 July 2026 and a hybrid pre-bid meeting for 6 July 2026 for its BoS tender (No. SECI/C&P/OP/11/0002/26-27) covering a 70 MW ISTS-connected solar PV project paired with a 25 MW/50 MWh battery system at Ramagiri, Sri Sathya Sai District, Andhra Pradesh. The EPC scope excludes PV modules and runs from design and supply through commissioning and maintenance.

WIND & HYBRID POWER

8MNRE amends prototype wind turbine rules, caps synchronisation at 3 turbines and switches RLMM to 'ALM (Wind)' list
In an Office Memorandum dated 25 June 2026, MNRE amended its 12 June 2025 'Revised Guidelines for installation of prototype wind turbine models'. Para 5 now allows a maximum of three turbines per prototype model for synchronisation and commissioning, with scheduled power purchasable by DISCOMs at a mutually agreed or CERC/SERC-regulated tariff. Para 8 replaces the RLMM eligibility reference with inclusion in the new 'ALM (Wind)' list, tightening the pathway from prototype testing to serial production.

STORAGE & GREEN HYDROGEN

8Servotech bags BEE 5-star rating for 60 kW and 120 kW DC EV chargers at 97% efficiency
Servotech Renewable Power System Ltd announced on 25 June 2026 that its ST-EVDC60KW and ST-EVDC120KW DC fast chargers secured the Bureau of Energy Efficiency's top 5-star rating under the EV Charger Star Labelling Programme, achieving a weighted-average energy efficiency of 97%. The certification places the models in the highest efficiency category and strengthens Servotech's competitive position as India builds out fast-charging infrastructure for electric mobility.
Details
OPEN ACCESS & WHEELING CHARGES

8Transmission loss for open-access users eased to 2.20% from 26 June 2026
A transmission loss notification effective 26 June 2026 to 25 July 2026 sets the applicable loss for open-access users at 2.20%, down 10 basis points from 2.30% for the previous 26 May–25 June period. TGTRANSCO's May 2026 statement records total input of 7,091.57 MU against losses of 155.97 MU, giving a 2.20% loss level. The reduction marginally lowers wheeling costs for open-access consumers and industrial buyers in Telangana.

COMMISSION ORDERS (CERC/SERC)

8NRPC issues Amendment-I to June 2026 Regional Transmission Deviation Account after CERC Fourth Amendment
The Northern Regional Power Committee, on 25 June 2026, issued Amendment-I to the Regional Transmission Deviation Account for the June 2026 billing month (billing period April 2026). The revision implements the CERC (Sharing of Inter-State Transmission Charges and Losses) Fourth Amendment Regulations, 2025 and accounts for the high-flow season for April 2026 generating stations. Affected entities have 15 days to flag discrepancies, directly influencing transmission charge sharing among northern utilities.

OMBUDSMAN & CONSUMER GRIEVANCE

8Uttarakhand Electricity Ombudsman orders no disconnection in Pacific Estate connection dispute against UPCL
In Representation No. 07/2026 (Award dated 16 June 2026), the Electricity Ombudsman, Uttarakhand examined Avani Sharma's appeal against Uttarakhand Power Corporation Ltd for refusing an independent domestic connection at Flat D-102, Pacific Estate, Dehradun. The Ombudsman directed that the complainant's supply not be disconnected, invoking the UERC order dated 7 October 2024 and reinforcing consumer rights under Section 2(15) of the Electricity Act, 2003.

8Uttarakhand Ombudsman rules on long-pending billing dispute against UPCL over Rs. 52,274 bill in Roorkee
The Electricity Ombudsman, Uttarakhand decided Representation No. 18/2026 (Award dated 24 June 2026) filed by Tezpal Singh Saini against UPCL's Urban Division, Roorkee, challenging revised billing for 1 July 2007 to 12 July 2012 using average consumption of 45,386 units. The dispute spans a connection released in 2012, a Rs. 52,274 bill paid in 2017, and years of non-receipt of bills, underlining DISCOM accountability on long-pending billing and connection-transfer grievances.

8Tamil Nadu Electricity Ombudsman decides agricultural service connection dispute in Order 07 of 2026
The Tamil Nadu Electricity Ombudsman, Chennai issued Order No. 07 of 2026 in an appeal against TANGEDCO concerning entitlement to agricultural service connections, where TNERC Supply Code rules permit one agricultural connection per well or bore well within a survey field number. The order interprets the conditions under which independent wells qualify for separate connections, carrying precedent value for farm-sector consumers seeking new agricultural connections across Tamil Nadu.
Details
WORK ORDERS & SUPPLY CONTRACTS

8Suzlon crosses 1 GW partnership with Tata Power after new 400 MW DevCo-led EPC order
Suzlon Energy Limited disclosed to BSE and NSE that it has crossed a cumulative 1 GW partnership with Tata Power following a fresh 400 MW DevCo-led EPC order received on 25 June 2026. The milestone deepens one of India's largest wind alliances and adds materially to Suzlon's order book. It signals continued momentum in onshore wind capacity addition as India pursues its renewable targets.

8SECI lists 2,700 MW of solar-plus-storage for sale as ISTS Tranche-XX/XXI tariffs discovered near Rs. 2.86-3.13/kWh
SECI's power-available-for-sale note dated 25 June 2026 offers 1,200 MW under ISTS Tranche-XXI (Solar+BESS) at discovered tariffs of Rs. 3.12-3.13/kWh — including NLC India Renewables (600 MW) and Engie Energy India (200 MW) — and 1,500 MW under Tranche-XX at Rs. 2.86-2.87/kWh, led by Shivalaya Construction (600 MW) and SAEL Industries (300 MW). A SECI trading margin of Rs. 0.07/kWh applies, with peak-hour supply obligations baked into the PPAs.

EQUITY & STAKE ACQUISITION

8Torrent Power completes Rs. 3,632-crore acquisition of 100% of L&T's Nabha Power
Torrent Power Limited disclosed on 25 June 2026 that it completed the acquisition of 100% of the equity and convertible instruments of Nabha Power Limited from L&T Power Development Limited for a total consideration of Rs. 3,632.35 crore, following CCI approval. Nabha Power Limited owns the 1,400 MW Rajpura thermal plant in Punjab. The deal expands Torrent's thermal generation footprint and marks a significant ownership change in north India's coal fleet.

8L&T exits power generation, divests Nabha Power to Torrent for Rs. 3,632 crore
Larsen & Toubro confirmed on 25 June 2026 that its subsidiary L&T Power Development Limited completed the divestment of 100% of Nabha Power Limited to Torrent Power for Rs. 3,632.35 crore (post closing adjustments), against Nabha Power Limited's net worth of Rs. 157.92 crore as on 31 March 2026. The sale marks L&T's exit from thermal power ownership, crystallising a substantial gain and sharpening the engineering major's focus on its core EPC and services businesses.

8Kalpataru Projects completes full exit from Kohima-Mariani Transmission, selling final 26% to Apraava
Kalpataru Projects International Limited informed exchanges on 25 June 2026 that it has completed the sale of its balance approximately 26% equity in Kohima-Mariani Transmission Limited to Apraava Energy Private Limited, having earlier divested approximately 48%. The transaction transfers Kalpataru Projects International Limited's entire stake in the inter-state transmission asset to Apraava Energy. The exit monetises a built-and-operated transmission line and frees capital for its core EPC pipeline.

8Adani Power forms nuclear arm 'Progressive-UP Atomic Energy' as step-down subsidiary
Adani Power Limited disclosed on 25 June 2026 that its wholly owned subsidiary Adani Atomic Energy Limited has incorporated a new step-down wholly owned subsidiary, Progressive-UP Atomic Energy Limited, on the same day. The move signals Adani Power's formal entry into nuclear power development and positions the group to participate as India opens civil nuclear generation to private players.
Details
ANNUAL RESULTS

8Adani Green operational capacity jumps 35% to 19.3 GW in FY26 as revenue hits Rs. 11,602 crore
Adani Green Energy Ltd reported FY26 revenue from power supply of Rs. 11,602 crore, up 22% year-on-year, with EBITDA of Rs. 10,865 crore (up 23%) and cash profit of Rs. 5,399 crore (up 11%). Operational renewable capacity rose 35% to 19.3 GW. The company reaffirmed its 50 GW target by 2030, anchored by mega-sites at Khavda, Gujarat and Jaisalmer, Rajasthan, underscoring its position as India's largest renewable developer.

8IL&FS Engineering swings to Rs. 0.19-crore pre-tax profit in FY26 on revenue of Rs. 187.92 crore
IL&FS Engineering and Construction Company Limited reported FY26 revenue from operations of Rs. 187.92 crore, down from Rs. 321.38 crore, and total income of Rs. 257.77 crore. The company swung to a profit before tax of Rs. 0.19 crore from a loss of Rs. 4.92 crore a year earlier. The 37th AGM is scheduled for 31 July 2026 via video conferencing, marking a notable recovery at the once-troubled IL&FS group company.

CREDIT RATING & ANALYST REPORT

8CARE reaffirms 'A-/Stable' on ReNew's 7.8 MW Maharashtra solar SPV backed by Rs. 3.26/unit 25-year PPA
CareEdge Ratings reaffirmed a 'CARE A-; Stable' rating on Rs. 22.94 crore of bank facilities of ReNew Green (MHK Two) Private Limited, citing its 7.8 MW AC (10.9 MW DC) group-captive solar plant in Maharashtra that clocked a 24.21% PLF in FY26. The plant sells full capacity to CIE Automotive India under a 25-year PPA at a fixed Rs. 3.26/unit. The rating flags a key risk from the MERC March 2026 banking order — stayed by APTEL — that could affect cash flows.

8ICICI Securities rates Exide Industries 'BUY' with Rs. 480 target as Q4 PAT climbs 23% to Rs. 312 crore
An ICICI Securities update reiterates a BUY on Exide Industries with a Rs. 480 target (20% upside over 12 months) against a CMP of Rs. 400. Exide's Q4 FY26 standalone revenue rose 9.4% year-on-year to Rs. 4,551 crore with PAT up 23% to Rs. 312 crore. Total investment in its 12 GWh lithium-ion cell venture Exide Energy Solutions reached approximately Rs. 4,800 crore, framing Exide as a key play on India's battery-storage and EV-cell localisation.

8Prabhudas Lilladher sees Vedanta Power tripling coal capacity to 12 GW by FY33; EBITDA to more than double
A Prabhudas Lilladher update on Vedanta Power (CMP Rs. 44, Not Rated) says the company plans to expand coal-based capacity from 4.2 GW in FY26 to 12 GW by FY33, targeting a top-three position among private thermal producers. EBITDA is expected to more than double over FY26-FY28E, with approximately 90% of incremental EBITDA from the 1.2 GW Athena project. The company is valued at a market cap of Rs. 170.53 billion, signalling continued private appetite for coal capacity.

8Statkraft pitches 70 TWh renewable portfolio and BBB+ Fitch rating in June 2026 credit investor update
Statkraft AS released its Credit Investor Presentation for June 2026, highlighting approximately 70.0 TWh of renewable energy generation and a BBB+ (stable) rating from Fitch, with a stated target of A- from S&P. The Norwegian state-owned utility is one of Europe's largest renewable generators and an active player in Indian renewables. The presentation supports its debt-investor outreach as it funds further clean-energy growth.
Details
 For reference purposes the website carries here the following tenders:
 
8Tender for periodical maintenance of structural steel work and allied works Details
  8Tender for centralized rate contract for two years for supply of various types of spare parts of CHP of different plants Details
  8Tender for extension of active solid waste storage facility and miscellaneous works Details
  8Tender for procurement of coupling assemblies and spares of couplings Details
  8Tender for two year annual rate contract for panel fencing around well Details
  8Tender for implementation of fugitive dust suppression system Details
  8Tender for supply, erection, testing and commissioning of stage 2 MOV actuators Details
  8Tender for allocation of dry fly ash Details
  8Tender for contract for engaging an exclusive agency for assembly, welding, and grinding Details
  8Tender for framework agreement (FA) of NSPBD busduct fabrication and assembly (inhouse) Details
  8Tender for annual maintenance contract for service of different types of 43 Nos. air conditioners installed Details
  8Tender for civil ramp slope improvement and other civil works Details
  8Tender for repair along with HP-HVOF coating of 02 set damaged guide vanes of 130 MW francis turbine Details
  8Tender for construction of PCC retaining wall in place of damaged retaining wall Details
  8Tender for civil maintenance of power house, Dam, MAT and switchyard structures Details
  8Tender for fencing by chain link of O and M store and railway siding store and other miscellaneous works Details
  8Tender for installation of new 33 kV /11 kV combined CTPT unit (0.2 accuracy class) for double metering Details
  8Tender for installation of new 11 kV 0.2s Class CT PT with meter Details
  8Tender for installation of new 11 kV 0.2s Class CT PT with meter replacement of 33 kV 0.5s Class CT PT Details
  8Tender for installation of new 11 kV 0.2s Class CT PT with meter Details
  8Tender for installation of additional pole Details
  8Tender for De-stringing of existing panther conductor and restringing and supply of ACSR conductor (using existing disc insulators) along with all accessories Details
  8Tender for shifting dismantling of 33kV feeder for construction of new 33kV feeder Details
  8Tender for supply, installation, testing, and commissioning of a new LT MCC panel Details
  8Tender for procurement of 86400 Nos. of 8 m 200 Kg working load PSC poles Details
  8Tender for award of contract for system strengthening works for survey, installation, testing and commissioning of new 3.15 MVA / 5 MVA / 8 MVA 33/11kV substation Details
  8Design, engineering, supply, construction, erection, testing, commissioning and maintenance of 70 MW ISTS connected solar PV power project Details
  8Tender for supply of network cables for network maintenance Details
  8Tender for supply, erection, testing and commissioning of 360V DC, 515AH, KBH, Ni-Cd type battery set Details
  8Tender for supply of various fasteners and consumables Details
  8Tender for supply, erection & commissioning and testing of emission control device/equipment (RECD) for 1500 KVA DG set installed Details
  8Tender for supply of various consumables items Details
  8Tender for rate contract for supply of BIS certified EEL-III (old)/ EEL-II (new), conventional 11/0.433kV, 200 KVA, CRGO core, DTRs Details
  8Tender for empanelment of agencies for restoration of distribution infrastructure during Details
  8Tender for procurement of critical spares of TG set for AOH Details
  8Tender for procurement of gear box model U600, fluid coupling Details
  8Tender for work contract for repairing and strengthening of taper duct of ESP inlet and outlet Details
  8Tender for work contract for AOH of TG auxiliaries Details
  8Tender for procurement of spares for instrument air compressor installed Details
  8Tender for construction of complaint centre at 33 kV S/stn. Details
  8Tender for supply of heat shrinkable type 33kV & 11kV outdoor cable Details
  8Tender for supply of LT XLPE insulated aerial bunched cables Details
  8Tender for supply of 11kV CT PT set Details
  8Tender for various repair works of control room and yard Details
  8Tender for supply of spares of trunnion shaft assembly of HP-1103 bowl mill Details
  8Tender for repair and maintenance of railway track Details
  8Tender for providing consultancy services for strengthening of bunkers and its supporting structures Details
  8Tender for annual rate contract for transportation of heavy equipment and machinery Details
  8Tender for grouting of exterior walls of power house Details
  8Tender for repair and renovation of lodging Details
  8Tender for work of HT pole Details
  8Tender for maintenance work of overhead HT/LT line, TC & HT/LT AB cable Details
  8Tender for construction of 11 kV line Details
  8Tender for special watching guarding of 132 kV D/C transmission line Details
  8Tender for repair, laying and jointing of conveyor belts and pulley laggings of conveyor system Details
  8Tender for installation of new 33 kV 0.2s class CT PT with meter replacement of 33 kV 0.5s class CT PT to 33 kV 0.2s class CT PT Details
  8Tender for installation of new 11 kV 0.2s class CT PT with meter Details
  8Tender for supply of LT PVC cable 2x6 Sq.mm (Armoured) 1500Km Details
  8Tender for procurement of different capacities of LED light Details
  8Tender for procurement of air seal ring lower and upper for unit#3 coal mill Details
  8Tender for procurement and retrofitting of 415 volt air circuit breakers Details
  8Tender for service contract for central AC system Details
  8Tender for procurement of RCCB of different rating for replacement of existing MCB Details
  8Tender for BMC for round-the-clock operation Details
  8Tender for supply and retrofitting of 245kV pantograph isolators and 245kV centre break isolator Details
  8Tender for comprehensive biennial maintenance contract for room, tower and duct-able air conditioner systems Details
  8Tender for supply, fabrication, galvanizing & erection of steel structure & equipments, AB switches provision of earthing arrangements, providing bus bars, jumpers and droppers, laying of control cable Details
  8Tender for supply, fabrication, galvanizing & erection of steel structure & equipments, AB switches Details
  8Tender for replacement of bare ACSR conductor Details
  8Tender for supply, erection and commissioning of LT ACB 800 Amp. for 250/400 KVA DTRs Details
  8Tender for supply of LT PVC cable 4x10 Sq.mm (Un-armoured) 300Km Details
  8Tender for supply of LT XLPE AB cable 3x25 plus 1x25Sq.mm 500Km Details
  8Tender for construction of RCC retaining and gabions wall Details
  8Tender for work of providing & fixing of counter poise & pipe type earthing for 400kV transmission lines Details
  8Tender for supply, installation, testing and commissioning of lift/ elevators Details
  8Tender for work of overhauling, servicing & repairs of 245kV/145kV circuit breaker at various Details
  8Tender for dismantling of old deteriorated compound wall & construction of new compound wall for the dismantled portion along with height raising of low heighted existing Details
  8Tender for various civil maintenance work Details
  8Tender for work of transportation, winching, loading & unloading of power transformers / accessories from various Details
  8Tender for procurement of 33kV circuit breaker Details
  8Tender for work of overhauling, servicing, repair, and maintenance of 220kV & 132kV CBs at various EHV substations Details
  8Tender for providing water proofing treatment by shield of 2mm DFT Details
  8Tender for annual maintenance contract (AMC) for the work of repair/overhauling/servicing & alignment of various make 220kV, 132kV & 33kV isolators installed Details
  8Tender for Turnkey based contract for conversion of existing 11 kV over head HT line into under ground cable network with ring main system (Package-10) Details
  8Tender for Turnkey based contract for conversion of existing 11 kV over head HT line into under ground cable network with ring main system (Package-06) Details
  8Tender for Turnkey based contract for conversion of existing 11 kV over head HT line into under ground cable network with ring main system (Package-05) Details
  8Tender for Turnkey based contract for conversion of existing 11 kV over head HT line into under ground cable network with ring main system (Package-04) Details
  8Tender for Turnkey based contract for conversion of existing 11 kV over head HT line into under ground cable network with ring main system (Package-03) Details
  8Tender for Turnkey based contract for conversion of existing 11 kV over head HT line into under ground cable network with ring main system (Package-02) Details
  8Tender for Turnkey based contract for conversion of existing 11 kV over head HT line into under ground cable network with ring main system (Package-01) Details
  8Design, supply, fabrication, and erection work of 10,000 M3(cubic meter) capacity Details
  8Tender for work of erection of 11kV outdoor support structure with providing and fixing of outdoor 11kV bus material Details
  8Tender for work of replacement of spacer cum dampers various Details
  8Tender for supply, erection, testing & commissioning of LILO of both circuits of 220kV D/C line Details
  8Tender for erection, maintenance and dismantling work of overhead HT/LT line, TC & HT/LT AB cable Details
  8Tender for work of carrying out actual load test and certification, overhauling and supply of recommended spares for EOT cranes installed Details
  8Tender for supply of cup valve spares Details
  8Tender for supply of positioner for control valves Details
  8Tender for supply of switchgear spares Details
  8Tender for work of shifting of S/C 66kV lines Details
  8Tender for work of installation of mesh type earthing at 66kV switchyard of 400kV sub-station Details
  8Tender for Bi-annual rate contract for erection of 66 kV TR bay/feeder bay, breaker Details
  8Tender for work of installation of mesh type earthing at 66kV switchyard Details
  8Tender for erection, dismantaling and maintenance of HT/LT and transformer Details
  8Tender for fabrication dismantling erection strengthening modification of various chutes hoppers wagon tipplers belt conveyors crusher houses Details
  8Tender for work of strengthening of conveyor gantries, trestles, columns, towers, tail end / drive head structure of various conveyor belts and various Details
  8Tender for procurement of 6.6/0.415 kV feeder protection numerical relays Details
  8Tender for supply & commissioning of various suspension magnet with its control panel Details
  8Tender for supply of carpentry materials Details
  8Design, engineering, manufacturing, supply, erection, testing & commissioning of ±125 MVAR STATCOM Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
890% of India's renewable energy portfolio faces high climate risk by 2030: Report Details
 
8India’s Renewable Energy Sector:Need to invest in climate resilience Details
 
8Climate resilience investment could avert $28 billion in losses across India’s renewable energy pipeline Details
 
8India Targets Local Manufacturing of Solar and Green Hydrogen Parts Details
 
8India cuts reliance on imported coal as local supplies rise Details
 
8Coal India begins output at 1.4-Mtpa mine Details
 
8plans to value its coal reserves in rupees: What does it mean Details
 
8When silence replaces process: PESB's transparency deficit and questions on NCL CMD selection it can’t ignore Details
 
8$24.6 bn clean energy financial flows to developing nations in 2024: UN rpt Details
 
8India’s Solar Boom Fuels Green Jobs And Cleaner Communities Details
 
8Solar industry’s shift from silver presents potential barrier for panel recycling Details
 
8Sunkonnect’s Sunsol targets 2 GW solar rollout in India by 2030 Details
 
8ALMM 2.0 Pushes India's Solar Localisation Upstream Details
 
8Suzlon bags wind turbine, EPC order for 400-MW project in Andhra Pradesh Details
 
8Ratul Puri on Renewable Energy, Battery Storage and India's Evolving Power Sector Details
 
8Power sector faces cost pressure from rising aluminium, copper prices Details
 
8BRICS Energy Ministers Back Stronger Cooperation at India-Led Meeting Details
 
8Why adding more solar and wind energy doesn't eliminate the need for gas Details
 
8TN power debt at Rs 2.5 lakh crore; govt promises to fix sector Details
 
8India Can Tap $1.2 Trillion in Institutional Capital For Green Transition: Report Details
 
8Adani Power subsidiary incorporates Progressive-UP Atomic Energy Limited Details
 
8After infrastructure and green energy push, Adani Group eyes its next big energy bet Details
 
8Energy department to fill 629 AEE posts in Andhra Pradesh Details
 
8Yash Highvoltage Approves Rs 151 Crore Preferential Issue to Expand High-Voltage Transmission and Power Equipment Manufacturing Capabilities Details
 
8India’s Coal Stocks at Power Plants Reach 42 MT Amid Surging Demand Details
 
8Jefferies top power sector picks: Upgrades Siemens Energy, initiates coverage on GE Vernova T&D Details
 
8ACPET and Tata Power-DDL Partner to Accelerate Research and Innovation for India’s Energy Transition Details
 
8Atmastco Bags Rs 57.33 Crore Order from L&T MHI Power Boilers for Adani Projects Details
 
8Torrent Power Finalizes Rs 3,632 Crore Nabha Power Acquisition Details
 
8RailTel Secures Rs 29.84 Crore SD-WAN Order from AP Power Utility Details
 
You can also click on Newsclips for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8LPG
8Ammonia

8All tankers
8Bulk and Dry cargo

Click on Reports for more. Details
COAL PRODUCTION & STOCK

8India's coal resources touch 4,00,715 million tonnes as on April 2025; Odisha leads with 1,00,975 MT
India's total geological coal resource stands at 4,00,715.45 million tonnes (for seams 0.90 m and above, to 1,200 m depth) as assessed on 1 April 2025 by GSI, CMPDI, MECL, SCCL and others. Odisha holds the largest share at 1,00,975.78 MT, followed by Jharkhand (93,254.06 MT) and Chhattisgarh (85,263.22 MT), with Gondwana coalfields accounting for 3,99,020.80 MT.

8CEA coal-stock report (23 June): 190 thermal stations at 224,158 MW hold stocks at just 60% of norm, 32 critical
The Central Electricity Authority's (CEA) Daily Coal Stock Report as on 23 June 2026 covers 190 thermal stations totalling 224,158 MW, showing aggregate coal stock at about 60% of the normative requirement, with 32 plants flagged as critical. State fleets varied widely - Haryana's HPGCL held 717,100 tonnes (73% of norm) while Punjab's PSPCL sat at 139% - a key gauge of fuel security as summer demand peaks.

8Coal India posts record 67.99 MT November output, pays Rs. 8,131 crore dividend to government in FY26
Coal India Limited's highest-ever November production of 67.99 MT in 2025 (up 1.2% year-on-year from 67.18 MT) and cumulative output of 453.51 MT during April–November 2025 came at 86.3% of the pro-rata Annual Action Plan target. CIL paid a Rs. 5.15 per share dividend totalling Rs. 3,173.81 crore for FY25, with the Centre's share of Rs. 2,003.73 crore contributing to a total dividend of Rs. 8,131.64 crore paid to the government in FY26.

8Coal Ministry ramps exploration drilling to 2.57 lakh metres in FY25, a 48% over-achievement under CMPDI push
CMPDI as nodal agency for detailed drilling and regional exploration achieved promotional block drilling of 2.57 lakh metres in 2024-25 against a 2.20 lakh-metre target - a 48% over-achievement - though FY26 logged only 0.76 lakh metres up to November 2025. The reforms aim to enlarge proven reserves and accelerate coal-block readiness for commercial mining, as reported in the Ministry of Coal Annual Report 2025-26.

8Coal Ministry's FY27 budget jumps to Rs. 4,390 crore at Budget Estimate, driven by coal and lignite exploration scheme
The Ministry of Coal's Financial Outlays and Outcomes chapter shows the Ministry utilised Rs. 850.88 crore (97.66% of revised estimate) in 2024-25 and Rs. 675.86 crore up to December 2025 against a revised estimate of Rs. 1,241.20 crore. For FY27, the allocation rises to Rs. 4,390.32 crore at Budget Estimate, of which Rs. 4,301.00 crore is earmarked for central-sector schemes - a major scale-up of exploration and development funding.

GENERATION & PLF

8APGENCO's thermal fleet logs 65% PLF on 23 June; state genco operates 6,389 MW across coal, hydro and solar
Andhra Pradesh Power Generation Corporation Ltd (APGENCO) reported daywise generation particulars as on 23 June 2026, with its 4,210 MW thermal fleet - anchored by the 2,560 MW Dr. Narla Tatarao TPS (Vijayawada) and the 1,650 MW Rayalaseema TPP - generating 1,518.15 MU month-to-date at 65.33% plant load factor. APGENCO's total installed base of 6,389 MW spans thermal, hydel and 405.4 MW of solar, with FY cumulative generation of 6,428.16 MU.

8India's coal demand hits 1,267 MT in FY25, projected to climb to 1,491 MT by FY27, Coal Ministry reports
The Ministry of Coal Annual Report 2025-26 records overall coal demand of 1,267.13 MT in 2024-25 - led by power (utility) at 905.78 MT - with all-India production of 997.25 MT (provisional) in FY24. Sector-wise projections see total demand rising to 1,443.65 MT in 2025-26 and 1,491.23 MT in 2026-27, reaching 1,610.53 MT by 2028-29, framing the supply ramp-up needed to power India's growing economy.

8India allocates 209 coal mines under CM(SP) and MMDR Acts; 60 now in production for commercial mining
The Ministry of Coal Annual Report 2025-26 reports 139 mines allocated under the CM(SP) Act, 2015 - 87 via auction and 52 via allotment - and a further 70 under the MMDR Act, totalling 209 allocations, of which 60 mines are now under production and 74 have secured mine-opening permission. The data marks the steady opening of India's coal sector to commercial miners following the Supreme Court's 2014 de-allocation of 204 mines.

E-AUCTION & PRICING

8Coal India consolidates e-auction into single window; Q4 FY26 steel-sector offtake met at 60% of target
Coal India Limited has merged its erstwhile exclusive NRS and spot e-auction windows into a single e-auction window serving the Power and Non-Regulated Sectors alike, while MSMEs needing under 10,000 tonnes a year are routed through State Nominated Agencies under NCDP 2007. Sector-wise CIL offtake data for January–March 2026 shows the steel sector receiving 2.30 MT against an Annual Action Plan target of 3.84 MT - about 60%.

8MSEDCL's June merit-order stack ranges from Rs. 2.72 per kWh cheap coal to Rs. 24.89 per kWh gas peakers
The Merit-Order Dispatch (MoD) variable-charge stack for MSEDCL for June 2026 (R0), effective 16 June to 15 July 2026 under MERC's State Grid Code Regulation 2020, ranks generating stations by variable cost - from the cheapest IPP coal imports around Rs. 2.72–2.74 per kWh (such as Jindal Power and Sai Wardha) up to the costliest gas station, KAWAS (LQ), at Rs. 24.89 per kWh.
Details
PEAK DEMAND & POWER SUPPLY POSITION

8All-India demand met peaks at 250,529 MW on 24 June as NLDC logs just 0.56 MU energy shortage
Grid-India's National Load Despatch Centre (NLDC) reported peak all-India demand met of 250,529 MW at 15:00 hrs on 24 June 2026, with the 20:00 evening peak at 244,283 MW against a 244,383 MW requirement - a shortage of just 100 MW, entirely in the Northern Region. Day energy met totalled 5,653 MU against an energy shortage of only 0.56 MU, with wind contributing 567 MU, solar 603 MU and hydro 452 MU.

8Northern region demand hit 85,401 MW on 24 June with a 100 MW evening-peak shortfall: NRLDC
The Northern Regional Load Despatch Centre's daily operation report for 24 June 2026 logged evening-peak demand met of 85,401 MW (frequency 50.074 Hz) against an 85,501 MW requirement - a 100 MW shortage making the Northern Region the sole deficit zone nationally - with off-peak demand of 79,245 MW and day energy of 1,966 MU. Uttar Pradesh consumed 679.43 MU, Rajasthan 337.03 MU and Punjab 353.9 MU.

8Southern region met 55,324 MW peak with zero shortage on 24 June even as 500 MW units tripped, SRLDC reports
The Southern Regional Load Despatch Centre (SRLDC) 24 June 2026 operations report shows evening-peak demand met of 55,324 MW (frequency 50.09 Hz) with zero shortage, off-peak demand of 48,075 MW and day energy of 1,319.11 MU. Unit outages included Ramagundam Unit 5 (500 MW) on a boiler-tube leak, Meenakshi Energy Stage-2 (350 MW) on flame failure and Raichur TPS Unit 6 (210 MW) - all absorbed without supply curtailment.

8Western region served 68,330 MW peak on 24 June as DNHDDPDCL corridor breached ATC 36.5% of the day
The Western Regional Load Despatch Centre (WRLDC) reports for 24 June 2026 show western-region evening-peak demand met of 68,330 MW (frequency 49.99 Hz) with zero shortage, off-peak demand of 62,295 MW and day energy of 1,610.1 MU. The regional reliability annex flags the DNHDDPDCL import path violating its Available Transfer Capability in 8.8% of blocks (equivalent to 36.5% of hours).

8Eastern region met 31,346 MW peak on 24 June as 3,333 MW of central generation sat on forced outage
The Eastern Regional Load Despatch Centre (ERLDC) report for 24 June 2026 records evening-peak demand met of 31,346 MW (frequency 50.07 Hz) with zero shortage and day energy of 686.59 MU. The NPMC generation-outage register shows 513.65 MW of planned outages and 3,333 MW of central-sector forced outages, while the eastern-region day-ahead demand forecast held a tight 3.82% MAPE.

8North Eastern region peaked at 3,882 MW on 24 June with zero shortage, NERLDC reports
The North Eastern Regional Load Despatch Centre (NERLDC) report for 24 June 2026 logs evening-peak demand met of 3,882 MW (frequency 50.07 Hz) with zero shortage and day energy of 70.87 MU, with Assam the largest load at 46.77 MU. Companion frequency-deviation, system-reliability (TTC) and 400 kV voltage-deviation indices for 23 June 2026 confirm the region held its frequency, transfer limits and substation voltages within mandated IEGC bands.

8Maharashtra demand peaks at 27,669 MW on 23 June as daily state generation tops 416 MU; wind and solar add 76 MU
The State Load Despatch Centre, Airoli (MSETCL), daily system report for 23 June 2026 shows Maharashtra's morning peak demand met at 27,669 MW (MSEDCL's share 23,477 MW), with grid frequency at 49.93 Hz, while total state generation reached 416.337 MU for the day and 9,962.467 MU month-to-date. Wind contributed 48.561 MU and solar 27.406 MU on the day.

8Maharashtra records zero load-shedding across all 24 hours on 22 June, distribution data shows
The load-shedding statement for 22 June 2026 reports nil planned and distress load-shedding across Maharashtra for every hour of the day, with both non-agricultural distress shedding and planned DCL-group shedding logged at 0 MW throughout and a total of 0.000 MU shed. The zero-shedding day signals adequate generation availability and a balanced demand-supply position in the state's distribution network during the pre-monsoon period.

8Maharashtra SLDC logs 31.35 MU from Parli wind and a diverse IPP fleet in 22 June daily generation report
The State Load Despatch Centre, Airoli (MSETCL), released its daily and progressive generation statement for 22 June 2026, capturing station-wise output across MSPGCL hydro and thermal, Parli wind (31.35 MU for the day, 811.59 MU monthly), Tata and Adani (APML) units, and captive and solar sources, including JSWEL, VIPL, Dhariwal and JPL. The report feeds Maharashtra's real-time balancing of its large, multi-source generation portfolio.

FREQUENCY & DEVIATION INDICES (FDI/VDI)

8National grid frequency averaged 49.985 Hz on 24 June, held within IEGC band approximately 80% of the day: NLDC
The NLDC frequency profile for 24 June 2026 recorded an average grid frequency of 49.985 Hz with a standard deviation of 0.0572 Hz, peaking at 50.197 Hz at 18:02 and dipping to 49.758 Hz at 16:41. Frequency stayed within the tight 49.90–50.05 Hz band about 80.35% of the time, with the Frequency Variation Index at 0.0349 - the clearest sign of a well-balanced supply-demand match across India's single synchronous grid.

SYSTEM RELIABILITY & SECURITY

8ER-NR transfer corridor breached ATC limits 12.5% of the time on 24 June, NLDC reliability report finds
The NLDC National System Reliability Indices report for 24 June 2026 found the East-to-North (ER-NR) transmission corridor exceeded its Available Transfer Capability in 12 blocks (three hours, 12.50% of the day) and breached the N-1 security criterion 2.08% of the time, while corridors including WR-NR, NEW-SR and NER-Import recorded nil violations. Persistent ATC breaches on the ER-NR path signal congestion as surplus eastern generation pushes toward the power-hungry north.

8NLDC tracks rotor-angle separation across 20-plus grid nodes referenced to Vindhyachal on 24 June
The All-India Angular Spread report for 24 June 2026 monitors the phase-angle separation of major 765/400 kV nodes - including Agra, Kolar, Talcher, Korba, Moga, Purnea, Pavagada and Bawana - with respect to the Vindhyachal reference bus through every hour of the day. A widening angular spread across the synchronous grid is an early-warning indicator of transmission stress and potential loss of stability.

LOAD FORECAST

8SRLDC forecasts southern demand cycling toward the 60,000 MW band through the 25 June–1 July week
The Southern Regional Load Despatch Centre's (SRLDC) day-ahead forecast for 25 June 2026 and week-ahead forecast for 25 June to 1 July 2026 project southern-region demand swinging between a roughly 40,000 MW off-peak trough and a peak in the 60,000 MW band. Accurate load forecasting drives generation scheduling, ancillary-reserve planning and day-ahead or real-time power-exchange procurement for southern utilities as the monsoon reshapes the demand curve.

REGIONAL ENERGY ACCOUNT (REA/REMC)

8Wind and solar met over 35% of India's daytime power demand on 23 June, NLDC's Renewable Centre reports
Grid-India's NLDC Renewable Energy Management Centre (REMC) reported that combined variable renewable energy (wind plus solar) met about 35.16% of all-India demand during solar hours (06:00–18:00) on 23 June 2026, with VRE contribution peaking near 86,197 MW. Solar alone supplied around 62,394 MW (25.45%) and wind about 23,803 MW (9.71%) at the height of the daylight window.

LINE & GENERATION OUTAGES

8BSES Rajdhani schedules maintenance shutdowns across Dwarka, Tilak Nagar and IIT Delhi areas on 25 June
BSES Rajdhani Power Limited (BRPL) published its maintenance shutdown schedule for 25 June 2026, listing planned outages of one to two hours across divisions including Palam, Tagore Garden, Nizamuddin, Hauz Khas, Mundka, Uttam Nagar and Janakpuri for LT-network upgradation, 11 kV feeder maintenance, transformer civil work and new cable laying. Affected pockets span Sector 8 Dwarka, Tilak Nagar and IIT Delhi (Hauz Khas).

8Odisha DISCOM lists 200-plus planned outages for 26 June across Bhubaneswar, Cuttack and Angul circles
The outage information schedule for 25–26 June 2026 details more than 200 planned 11 kV and 33 kV interruptions across Odisha distribution circles - concentrated in BBSR, Cuttack, Dhenkanal, Angul, Paradeep and Jajpur - for pole erection, burnt-cable replacement, tree trimming and routine maintenance. Most works are scheduled in morning hours as the utility undertakes pre-monsoon network upkeep.

8PVVNL Meerut lists planned 4-hour feeder shutdowns across Ghaziabad on 25 June for network upgrades
Paschimanchal Vidyut Vitran Nigam Limited (PVVNL), Meerut, published its planned-shutdown schedule for 25 June 2026, including four-hour outages from 11:00 to 15:00 on urban feeders in Govindpuram and city areas for ABC cabling, transformer erection and 11 kV or LT line works under its 2025-26 business plan. The notices flag temporary supply interruptions in parts of western Uttar Pradesh.

8MahaTransco issues transmission-works notices for Chhatrapati Sambhajinagar region on 23 June
Maharashtra State Electricity Transmission Company (MahaTransco/MSETCL) issued public notices dated 23 June 2026 from its Chhatrapati Sambhajinagar transmission circle regarding 132 kV substation and line works. The notices advise stakeholders of planned transmission activity affecting the Marathwada region's high-voltage network, as part of the utility's ongoing maintenance and upgrade programme.

8CEA Daily Generation Report (23 June): 312,334 MW monitored, 41,766 MW under outage, hydro generation down 15%
The Central Electricity Authority's (CEA) Daily Generation Report for 23 June 2026 - spanning 17 sub-reports on all-India and region-wise generation, capacity availability and unit maintenance - shows 312,333.79 MW of monitored capacity with 270,568.28 MW online and 41,765.50 MW under outage, including 23,179.67 MW on forced outage. All-India hydro generation ran about 15% below schedule in the Northern Region, highlighting pre-monsoon grid stress.

SYSTEM RELIABILITY & SECURITY

8Grid-India holds spinning reserves and SCUC commitments to secure the national grid on 24 June
Grid-India's Daily Report on Ancillary Services and Security-Constrained Unit Commitment (SCUC) for 24 June 2026 tracks spinning up and down reserves against requirement - the inter-state reserve requirement is taken as half the total system requirement - alongside SCUC up or down schedules through the day's 96 time-blocks. These reserves are the grid's first line of defence against sudden generation loss or demand surges.

8NLDC's 25 June economic despatch commits coal at 116 paise per kWh while LNG plants at 2,372 paise per kWh stay idle
The NLDC Security-Constrained Unit Commitment (SCUC) merit-order table for 25 June 2026 commits the cheapest stations first, led by Darlipali at an energy charge rate (ECR) of 115.9 paise per kWh, followed by Talcher and Korba Stage-3. Costly gas or LNG units such as Faridabad-LNG (2,372 paise per kWh), Anta-CRF and Auraiya-CRF were left uncommitted, directly shaping the wholesale cost of power that flows through to consumer tariffs.
Details
MNRE & BEE

8Ministry of Coal's FY27 output-outcome framework sets Rs. 21-crore R&D outlay, targets six new research projects
The Ministry of Coal's Output-Outcome Monitoring Framework (OOMF) 2026-27 links budget outlays to measurable targets under Demand No. 9, allocating Rs. 21.00 crore to coal-sector R&D with a goal of sanctioning six new research projects and completing eight ongoing ones in the financial year. Outcome indicators include new technological innovations adopted by industry, peer-reviewed research papers and patents registered.

8Ministry of Coal's FY27 Demands for Grants (Demand No. 9) tabled, anchored by Rs. 4,390-crore exploration push
The Ministry of Coal's Detailed Demands for Grants for 2026-27 (Demand No. 9) sets out budgetary provisions for India's coal sector, headlined by a sharply higher Central Sector allocation for coal and lignite exploration pegged at Rs. 4,390.32 crore at Budget Estimate - up from a revised estimate of Rs. 1,241.20 crore in 2025-26. The document details object-head-wise provisions and individual works costing Rs. 5 crore and above.

CEA & GRID STANDARDS

8Southern Regional Power Committee adopts minutes of 143rd Protection Coordination Sub-Committee meeting
The Southern Regional Power Committee (SRPC) circulated the minutes of the 143rd Protection Coordination Sub-Committee (PCSC-143) meeting held on 8 June 2026 (Ref: SRPC/SE(PC&SS)/143PCSC/2026, dated 23 June 2026). The committee reviews relay settings, protection coordination and disturbance analysis across the southern grid - technical housekeeping that guards against cascading tripping and improves fault response.

TENDERS & PROCUREMENT (GEM/NIT)

8Meghalaya transmission utility sets 25 June pre-bid meet for HTLS re-conductoring of 28.96-km, 132 kV line
Meghalaya Power Transmission Corporation Limited (MePTCL) notified a pre-bid meeting on 25 June 2026 for its tender to re-conductor and strengthen a 132 kV single-circuit line spanning 28.96 circuit-km using High-Temperature Low-Sag (HTLS) conductors and related services. The upgrade, for which the tender was published on 12 June 2026, aims to boost power-transfer capacity and reliability across Meghalaya's transmission network.

8NTPC School of Business opens IIM-Ahmedabad-mentored energy PGDM for Rajasthan DISCOM officers; fee tops Rs. 18.30 lakh
The NTPC School of Business's 18-month AICTE-approved PGDM (Executive) in Energy Management for 2026-27 and 2027-28 invites applications from officers of Rajasthan utilities RVPNL, RVUNL, JVVNL, JDOVVNL and AVVNL aged up to 53 as on 30 June 2026. Mentored by IIM Ahmedabad, the programme comprises 12 months of classroom study, six months of project work and a two-week international immersion, at a fee exceeding Rs. 18,30,000.

8JVVNL nominates 16 engineers for REC's RDSS quality-monitoring workshop in Jaipur on 25 June
Jaipur Vidyut Vitran Nigam Limited (JVVNL), by order dated 24 June 2026, nominated 16 executive engineers handling the Revamped Distribution Sector Scheme (RDSS) across circles including Sawai Madhopur, Dausa, Kota, Baran, Bundi, Bharatpur and Alwar to attend a workshop on 'Quality Monitoring under RDSS' on 25 June 2026 at Hotel Royal Orchid, Jaipur, organised by REC's Regional Office.
Details
DAY-AHEAD MARKET (DAM/GDAM/HPDAM)

8Day-ahead power prices slam into Rs. 10,000 per MWh ceiling for 24 June delivery as summer demand bites
The Day-Ahead Market (DAM) snapshot for 24 June 2026 delivery shows the market clearing price hitting the Rs. 10,000 per MWh ceiling across numerous 15-minute blocks, with daily cleared volume aggregating to roughly 1.18 million MW summed over the day's 96 blocks - approximately 295 GWh. The ceiling-price clearing signals tight demand-supply balance on the national grid during the pre-monsoon peak, raising short-term power-procurement costs for distribution utilities.

8Green Day-Ahead Market clears approximately 29,377 MWh of solar-heavy volume for 24 June at up to Rs. 10,000 per MWh
Green Day-Ahead Market (GDAM) snapshots for 24 June 2026 show cleared green volume of roughly 29,377 MWh - led by solar at about 18,566 MWh with the balance non-solar or hydro - with the green market clearing price reaching the Rs. 10,000 per MWh ceiling in several blocks. The data tracks the growing role of exchange-traded renewable power in helping DISCOM meet demand and RPO targets in a tight market.

8High-Price Day-Ahead Segment sees no clearing on 24 June despite approximately 63,918 MWh of sell bids
High-Price Day-Ahead Market (HPDAM) snapshots for 24 June 2026 record no cleared volume despite sell bids of about 63,918 MWh, as buy bids did not materialise at the segment's elevated price band. The HPDAM - designed for costlier sources such as imported gas and battery storage - reflects how price-capped demand limits offtake from high-cost generation even on a tight-supply day.

8Hindustan Power Exchange lists two reverse auctions for CSPDCL power procurement at Rs. 10,000 per MWh ceiling
Hindustan Power Exchange (HPX) issued circulars on 24 June 2026 for two any-day single-side reverse auctions (HPX/24062026/01036 and HPX/24062026/01037), each with Chhattisgarh State Power Distribution Company Limited (CSPDCL) as buyer and a ceiling price of Rs. 10,000 per MWh. The auctions let the Chhattisgarh DISCOM competitively source short-term power to meet demand during the pre-monsoon peak.

REAL-TIME MARKET (RTM)

8Real-Time Market swings from Rs. 2,790 to Rs. 10,000 per MWh on 24 June as grid tightens
Real-Time Market (RTM) snapshots for 24 June 2026 show market clearing prices ranging from about Rs. 2,790 per MWh in early-morning blocks up to the Rs. 10,000 per MWh ceiling during peak blocks, with cleared volumes aggregating in the hundreds of thousands of MW-blocks across sessions. The intraday price volatility underscores how utilities lean on real-time trades to balance load when day-ahead schedules fall short, at premium cost.

TERM-AHEAD & GREEN TERM-AHEAD (TAM/GTAM)

8IEX Green Term-Ahead Market trades daily green contracts at the Rs. 10,000 per MWh ceiling on 24 June
Green Term-Ahead Market (GTAM) trade details at the Indian Energy Exchange (IEX) for 24 June 2026 show daily-contract green-power trades across 96 blocks clearing at the Rs. 10,000 per MWh ceiling, with small bilateral volumes matched block by block. The term-ahead green trades let buyers lock renewable supply for delivery, complementing day-ahead procurement and RPO compliance routes in a tight power market.

8IEX Term-Ahead Market sees daily and intraday contracts clear at Rs. 10,000 per MWh on 24 June
Term-Ahead Market (TAM) trade details at IEX for 24 June 2026 show daily and intraday contracts across regions clearing at the Rs. 10,000 per MWh ceiling, with block-wise prices in low double digits for some intraday tenors. The TAM data captures how utilities and open-access consumers hedge short-term requirements ahead of delivery, with ceiling-price clearing underscoring the continued stress on India's power balance.

ANCILLARY & INTRADAY (ASDAM/IDAS/SCUC)

8Ancillary-Services Day-Ahead Market logs nil clearing for 24 June delivery
Ancillary Services Day-Ahead Market (ASDAM) snapshots for 24 June 2026 show zero cleared volume and bids across all 15-minute blocks. The flat ancillary-market result indicates that day-ahead reserve requirements were met through other mechanisms, with no exchange-cleared ancillary procurement for the delivery date, even as mainstream DAM prices hit the Rs. 10,000 per MWh ceiling in several blocks.

8Intra-Day Auction Segment shows nil clearing for 24 June delivery
The IDAS (Intra-Day Auction Segment) Market Volume Profile Report for 24 June 2026 shows no purchase bids, sell bids or cleared volume across the day's time blocks. The flat intraday-auction result indicates traders relied on continuous real-time and day-ahead routes rather than the auction segment for the delivery date, even amid the tight supply that pushed mainstream market prices to the ceiling.

DEVIATION SETTLEMENT (DSM)

8ERPC issues eastern-region DSM, SRAS, TRAS and SCUC settlement account for 8–14 June 2026
The Eastern Regional Power Committee (Ministry of Power) released its Deviation Settlement Mechanism (DSM) along with SRAS, TRAS and SCUC settlement account for the week of 8–14 June 2026 (Ref: ERPC/COMMERCIAL/DSM-26/591, dated 24 June 2026). The statement settles grid-balancing payments and charges among eastern-region utilities and generators, enforcing scheduling discipline and frequency support that underpin grid security in the region.

8WRPC publishes western-region DSM settlement statements for the week of 8–14 June 2026
The Western Regional Power Committee (WRPC), under the Central Electricity Authority, issued ABT-based DSM settlement statements for the week of 8–14 June 2026 (Ref: WRPC/Comml.-I/4/ABTDSM/2026, dated 23 June 2026). The settlement allocates deviation charges and credits across western-region states and generators, financially disciplining real-time scheduling deviations that affect grid frequency and reliability.

8ERPC settles eastern-region reactive energy (VARh) charges for 8–14 June 2026
The Eastern Regional Power Committee published reactive-energy (VARh) charges for the week of 8–14 June 2026 (Ref: ERPC/COMMERCIAL/VARH/2026/592, dated 24 June 2026), with detailed block-wise data accompanying the order. Reactive-energy settlement incentivises utilities to maintain voltage within band by drawing or injecting reactive power, a low-cost lever for voltage stability across the eastern grid.

8PXIL deviation-settlement report shows sell-side clearing up to 650 MW at Rs. 10,000 per MWh on 24 June
Power Exchange India Limited's (PXIL) DSM report for 24 June 2026 records cleared sell volumes rising to 600–650 MW in late-evening blocks priced at Rs. 10,000 per MWh, with most daytime blocks showing nil clearing. The deviation-settlement data reflects how generators and utilities monetise imbalance volumes at exchange-discovered prices during high-demand evening hours on the national grid.

8Block-wise DSM dataset details grid deviations for 8–14 June 2026 across 44 sheets
A 44-sheet block-wise Deviation Settlement Mechanism (DSM) dataset for 8–14 June 2026 compiles 15-minute deviation, frequency and charge data underpinning regional grid-balancing settlements. The granular dataset is the raw basis for DSM payments that discipline scheduling accuracy and frequency response across India's synchronous grid, covering all regional constituents for the seven-day period.

8ERPC issues revised bilateral regional energy accounting for April 2026
The Eastern Regional Power Committee released the Revised Regional Energy Accounting (REA) for bilateral energy transactions in the Eastern Region for April 2026 (Ref: ERPC/COM-I/REA/2025-26/590, dated 24 June 2026). The revision trues up scheduled-versus-actual bilateral energy exchanges among eastern utilities for the month, forming the audited basis for inter-state energy settlement and billing between regional constituents.

8ERPC releases revised eastern-region energy accounting for April 2026
The Eastern Regional Power Committee issued the Revised Regional Energy Accounting (REA) of the Eastern Region (excluding Rangit & Teesta-V HPS and Patratu STPS) for April 2026 (Ref: ERPC/COM-I/REA/2026-27/588, dated 24 June 2026). The REA reconciles drawals and injections across eastern states and central stations, forming the audited basis for monthly energy settlement among regional constituents.

8ERPC publishes revised SCED settlement account for April 2026
The Eastern Regional Power Committee issued a revised Security Constrained Economic Despatch (SCED) settlement account for the period 1–30 April 2026 (Ref: ERPC/COMM/SCED/2026-27/589, dated 24 June 2026). SCED settlement compensates generators dispatched out of merit for grid-wide cost optimisation, distributing resulting savings and charges across beneficiaries in the national economic-despatch framework.
Details
SOLAR POWER

8SECI floats tender for 70 MW solar plus 25 MW/50 MWh battery project at Ramagiri, Andhra Pradesh; EMD set at Rs. 3.81 crore
Solar Energy Corporation of India (SECI) issued Tender No. SECI/C&P/OP/11/0002/26-27, dated 24 June 2026, for design, engineering, supply, construction and commissioning of a 70 MW ISTS-connected solar PV project paired with a 25 MW/50 MWh battery energy storage system (BESS) at Ramagiri, Sri Sathya Sai district, Andhra Pradesh, bundled with five years of O&M. The balance-of-system package carries an earnest money deposit of Rs. 3,81,24,000.

8SECI releases four-part schedule-of-rates pricing template for 70 MW Ramagiri solar-plus-storage tender
The Schedule of Rates format accompanying SECI's 70 MW solar-plus-BESS Package-1 tender at Ramagiri, Andhra Pradesh, provides the pricing structure - SOR-1, SOR-2 and SOR-3 feeding into a Grand Total Summary (Schedule 4) - that bidders must complete to arrive at their evaluated bid value. The standardised rate schedule ensures uniform price submissions for the balance-of-system works bundled with five years of O&M.

8SECI mandates integrity pact for 70 MW solar tender bidders to bar corruption in award process
As part of its 70 MW solar-plus-BESS tender package at Ramagiri, SECI requires every bidder and all members of any joint venture or consortium to sign an integrity pact committing to full compliance with anti-corruption norms through the contract award. The pact, monitored by an Independent External Monitor, binds both SECI and bidders to transparent conduct, reinforcing governance in the agency's high-value renewable-project tendering.

8SECI issues standard clarification-seeking format for bidders on 70 MW solar-plus-BESS tender
SECI published the prescribed format for prospective bidders to seek clarifications on its 70 MW solar PV with 25 MW/50 MWh BESS tender, requiring queries to be submitted against specific RfS clauses and page references in a single structured template. The form streamlines the pre-bid query process for the Ramagiri, Andhra Pradesh project, ensuring all clarifications are logged uniformly ahead of bid submission and minimising procurement ambiguity.

WIND & HYBRID POWER

8WRPC notifies transmission deviation charges on western-region RE generators for June 2026 billing
The Western Regional Power Committee issued, on 24 June 2026, Regional Transmission Deviation Charges for the June 2026 billing month applicable to renewable-energy generators in the Western Region, addressed to utilities including GUVNL, GETCO, MP Power, CSPDCL and wind IPPs such as Nani Virani Wind Energy. The charges penalise over- and under-injection against granted network access, tightening forecasting discipline for variable renewable generators on the western grid.

STORAGE & GREEN HYDROGEN

8UK's DESNZ releases interim safety specification for plug-in solar devices to enable balcony solar
The UK Department for Energy Security and Net Zero (DESNZ) published Version 1.0 (June 2026) of its Plug-in Solar Device Interim Product Specification, setting technical and safety requirements for plug-in solar PV devices, developed with Ofgem, the Energy Networks Association and the G98 working group. The standard paves the way for consumer 'plug-in' balcony solar in Britain - a fast-growing distributed-generation segment in Europe - by defining safe home-circuit and grid connection rules.

ROOFTOP & DISTRIBUTED SOLAR (PM SURYA GHAR / KUSUM)

8Servotech Renewable unveils Sunfarm-series VFD solar pump controllers for agri-solar market
Servotech Renewable Power System Ltd (NSE: SERVOTECH) launched its Sunfarm-series VFD solar pump controllers, targeting India's solar-powered irrigation segment under schemes such as PM-KUSUM. The product extends the listed clean-energy manufacturer's portfolio across solar, BESS and EV charging, positioning it in the high-growth solar water-pumping market that supports farm electrification and diesel displacement across rural India.

POLICY & INCENTIVES

8Research paper maps India's solar-BESS-EV 'infrastructure paradox' against 30/70/80% EV targets
A 2026 paper in the International Journal for Multidisciplinary Research by Indira Priyadarsini Vangala examines the integration of solar generation with BESS and policy evolution in India's electric-mobility sector, benchmarked against national targets of 30% electrification of private cars, 70% of commercial vehicles and 80% of two- and three-wheelers. The analysis highlights the grid-infrastructure and storage build-out needed to charge a rapidly electrifying vehicle fleet from clean power.

8Global SDG7 report: over 650 million still lack electricity and 2 billion lack clean cooking in 2024
The Tracking SDG7: The Energy Progress Report 2026 - a joint product of the IEA, IRENA, UN Statistics Division, World Bank and WHO - finds that as of 2024 more than 650 million people lacked access to electricity and about 2.0 billion lacked clean cooking fuels and technologies, even as renewables expanded. The report frames the scale of the gap to universal modern energy by 2030, with investment needs concentrated in Sub-Saharan Africa and Asia.
Details
RETAIL TARIFF REVISION

8Chhattisgarh regulator approves 6.23% power tariff hike for CSPDCL, caps FY27 revenue at Rs. 28,347 crore against Rs. 32,522-crore demand
The Chhattisgarh State Electricity Regulatory Commission (CSERC), in its 15 June 2026 order (Petition No. 103/2025-T), approved an average tariff increase of 6.23% - about 42 paise per kWh - across all consumer categories for CSPDCL for FY27, far below the 24% hike sought. The Commission set net annual revenue requirement for recovery at Rs. 28,347.45 crore versus the Rs. 32,522.27 crore claimed, and trimmed the carried-forward revenue gap to Rs. 2,778.77 crore.

8CSERC notifies FY27 tariff schedule from 1 July: domestic power to cost Rs. 4.40–8.80 per unit, EV charging fixed at Rs. 7.13 per unit
CSERC's Tariff Schedule for FY27, effective 1 July 2026, sets domestic (LV-1) energy charges on a rising slab from Rs. 4.40 per unit for the first 100 units to Rs. 8.80 per unit above 600 units, with EV charging stations billed at a flat Rs. 7.13 per unit. Non-domestic single-phase rates run up to Rs. 9.10 per unit, while three-phase consumers above 15 kW face Rs. 8.40 per unit plus a Rs. 210 per kW per month demand charge.

OPEN ACCESS & WHEELING CHARGES

8Karnataka regulator extends standby-meter deadline for all open-access generators to 31 December 2026
The Karnataka Electricity Regulatory Commission, in an order dated 24 June 2026 (O.P. No. 12/2026), extended the deadline for all open-access generators to install standby meters by six months to 31 December 2026, pushing back the earlier 30 June 2026 cut-off set in O.P. No. 31/2025. The extension gives solar and other open-access generators across Karnataka additional time to comply with metering norms essential for accurate energy accounting and settlement of open-access transactions.

8Uttarakhand regulator takes up Galwalia Ispat's challenge to open-access surcharges and green cess levied by UPCL
The Uttarakhand Electricity Regulatory Commission has admitted Petition No. 26 of 2026 by M/s Galwalia Ispat Udyog (P) Ltd, contesting the additional surcharge, cross-subsidy surcharge, electricity duty and green cess imposed by Uttarakhand Power Corporation Limited (UPCL) on power purchased through open access from IEX and under a group-captive arrangement. The outcome will bear on the economics of open-access and captive power for industrial consumers in Uttarakhand.

COMMISSION ORDERS (CERC/SERC)

8KSERC allows KINESCO to pursue takeover of Hi-Tech Park 110 kV substation in interim order under OP 29/2024
The Kerala State Electricity Regulatory Commission, via an interim order dated 19 June 2026 in Petition OP 29/2024, addressed KINESCO Power and Utilities Pvt Ltd's plea to take over and operate the 110 kV substation at Hi-Tech Park, Kalamassery. KINESCO - a 100% KINFRA subsidiary licensed to distribute power across five KINFRA industrial parks - is contesting arrangements with KSEB Ltd over the asset, with hearings held on 24 October 2024 and 20 May 2026.

8Bihar regulator launches suo-motu proceeding to frame new Electricity Supply Code 2026
The Bihar Electricity Regulatory Commission (BERC) initiated suo-motu proceeding SMP-06/2026 to formulate a new BERC (Bihar Electricity Supply Code), 2026, with stakeholders including the Bihar Sugar Mills Association and Magadh Sugar & Energy Ltd invited to participate. A refreshed supply code will reset the rules governing connections, metering, billing and consumer-discom obligations across Bihar, directly affecting service standards and dispute resolution.

8UP regulator hears NPCL's bid to procure 300 MW from wind-solar hybrid project via competitive bidding
The Uttar Pradesh Electricity Regulatory Commission (UPERC) is examining Petition No. 2309 of 2025 filed by Noida Power Company Limited (NPCL) under Section 86(1) of the Electricity Act, 2003, seeking approval for long-term procurement of power from a 300 MW wind-solar hybrid project through tariff-based competitive bidding, along with sought deviations from August 2023 hybrid bidding guidelines. Approval would lock in firm renewable supply for NPCL's Greater Noida licence area.

8Bihar regulator rules on Shree Cement's plea to carry forward FY21 RPO shortfall to FY22
The Bihar Electricity Regulatory Commission (BERC) issued a final order in Case Nos. 01/2022 & 02/2022 on Shree Cement Ltd's petition seeking to carry forward its Renewable Purchase Obligation for FY21 to FY22 under the BERC RPO and REC Framework Regulations, 2010. The ruling, involving the Bihar Renewable Energy Development Agency and North Bihar Power, affects how captive and industrial consumers meet green-energy procurement targets and the compliance flexibility available to them.

OMBUDSMAN & CONSUMER GRIEVANCE

8Kerala electricity ombudsman dismisses Srilakshmi Electrosmelters' Rs. 22.80-crore tariff appeal filed 9 years after deadline
The State Electricity Ombudsman, Kerala, on 23 June 2026 dismissed Appeal Petition P/025/2026 by M/s Srilakshmi Electrosmelters (P) Ltd - a former 1,975 kVA HT consumer at Erumathala, Aluva - ruling it non-maintainable as it was filed on 22 April 2026, more than 9 years after the CGRF's 29 December 2016 order, against a 30-day window. KSEB Ltd had pegged total dues at Rs. 22,80,47,677, including energy-theft arrears from a 2004 meter-tampering case.
Details
CAPACITY COMMISSIONING & COD

8ERPC revises eastern-region power shares as Patratu Unit 2 (800 MW) declares COD from 25 June 2026
The Eastern Regional Power Committee issued revised share allocations of Central Generating Stations and Bhutan hydro stations following the Commercial Operation Date of Unit 2 (800 MW) of Patratu STPP Phase-I (3x800 MW), effective 00:00 hrs on 25 June 2026, per PVUNL's letter dated 23 June 2026. The addition of 800 MW from the Patratu Vidyut Utpadan Nigam - an NTPC-Jharkhand joint venture - reshuffles beneficiary entitlements across eastern states.
Details
FUND RAISING & CAPITAL

8SECI invites banks for Rs. 1,000-crore unsecured foreign-currency loan citing AAA rating and Rs. 18,447-crore FY26 revenue
Solar Energy Corporation of India (SECI) floated an Expression of Interest (Ref: SECI/FA/ECB/9064, dated 24 June 2026) for an unsecured external commercial borrowing or foreign-currency term loan equivalent to roughly Rs. 1,000 crore, with a 5-year bullet-repayment tenor and a minimum ticket of Rs. 250 crore. SECI, rated AAA (Stable) by ICRA and CARE, reported FY26 revenue of Rs. 18,447 crore, net worth of Rs. 3,778 crore and profit after tax of Rs. 579 crore. Bids close 15 July 2026, with USD hedging pegged at 1.50% p.a. for evaluation.

8SECI annuls earlier Rs. 1,000-crore ECB EOI of 12 June, issues fresh tender with revised terms
Solar Energy Corporation of India annulled with immediate effect its Expression of Interest dated 12 June 2026 for arranging an ECB or foreign-currency term loan of Rs. 1,000 crore, superseding it with a fresh EOI (Ref: SECI/FA/ECB/9064). Proposals submitted against the cancelled EOI will not be evaluated and confer no preference in the new process, requiring all lenders to bid afresh. The procedural reset applies to SECI's Rs. 1,000-crore fund-raise for renewable-energy scaling.

8SECI extends bid deadline to 6 July for Rs. 800-crore non-fund-based credit facility after corrigendum
Solar Energy Corporation of India issued a corrigendum (SECI/FA/NFB/9057/Corrigendum/01) on 24 June 2026 extending the submission deadline for its invitation of quotation for non-fund-based credit facilities - comprising letters of credit, bank guarantees and SBLCs - aggregating up to Rs. 800 crore, from 26 June 2026 to 6 July 2026. All other terms of the original RFP dated 11 June 2026 remain unchanged. The facility supports SECI's bank-guarantee and letter-of-credit requirements as it scales renewable procurement.

8Torrent Power raises Rs. 3,800 crore via private placement of 3.8 lakh NCDs on 24 June
Torrent Power Limited (BSE: 532779; NSE: TORNTPOWER) issued and allotted Series 15 of 3,80,000 secured, rated, listed, redeemable non-convertible debentures aggregating Rs. 3,800 crore on a private-placement basis on 24 June 2026. The large debt raise strengthens the integrated power utility's funding for generation, transmission and distribution capex, and signals continued investor appetite for highly rated power-sector paper.

CREDIT RATING & ANALYST REPORT

8Motilal Oswal reiterates 'Buy' on Waaree Energies with Rs. 3,825 target, citing 26% upside
In a 23 June 2026 update, Motilal Oswal Financial Services maintained a 'Buy' rating on Waaree Energies at a current market price of Rs. 3,034, with a target of Rs. 3,825 implying 26% upside and a market cap of about Rs. 872.7 billion. The note flags that commercial-and-industrial, rooftop and PM-KUSUM segments now account for over half of Waaree's annual solar installations, signalling strong demand visibility across India's solar ecosystem.

8CARE reaffirms 'A; Stable' on ReNew Photovoltaics, rates Rs. 4,783-crore facilities
CARE Ratings reaffirmed its 'CARE A; Stable' long-term and 'CARE A1' short-term ratings on Renew Photovoltaics Private Limited's bank facilities, covering Rs. 2,118.86 crore of long-term facilities (reduced from Rs. 2,546 crore) and Rs. 2,665 crore of long-term or short-term facilities (enhanced from Rs. 1,410 crore). The reaffirmation supports the ReNew group entity's access to project debt as it scales solar manufacturing and generation capacity.

8CARE reaffirms 'A-; Stable' on ReNew Green (MHH One) for Rs. 57.78-crore facilities backing 18 MW solar project
CARE Ratings reaffirmed 'CARE A-; Stable' on the Rs. 57.78-crore long-term bank facilities (reduced from Rs. 58.28 crore) of Renew Green (MHH One) Private Limited, which operates an 18.00 MW solar project. The rating reflects steady cash flows from the long-tenor PPA-backed asset, underpinning the ReNew group's financing of its distributed solar portfolio.

8ICRA keeps Darjeeling Power's Rs. 23.53-crore facilities at 'B+' under issuer-non-cooperating tag
ICRA continued its [ICRA]B+(Stable) rating on Darjeeling Power Private Limited (erstwhile Darjeeling Power Limited) under the 'Issuer Not Cooperating' category, covering Rs. 0.78 crore of cash credit and Rs. 22.75 crore of term loans. The non-cooperation flag, driven by inadequate information from the borrower, signals heightened credit-monitoring risk for lenders to the power entity.

EARNINGS CALL & ANALYST MEET

8Torrent Power schedules analyst and investor meetings under SEBI LODR days after Rs. 3,800-crore NCD issue
Torrent Power Limited (BSE: 532779; NSE: TORNTPOWER) intimated the schedule of analyst and investor meetings under Regulation 30 of the SEBI LODR Regulations on 24 June 2026. The interactions, disclosed days after the company's Rs. 3,800-crore NCD issuance, are expected to offer the market insight into the utility's generation, distribution and renewable growth plans for the current financial year.

8Jakson Group profiles Rs. 9,000-crore FY26 revenue, 1.3 GWp renewable IPP and 6.5+ GWp EPC portfolio
Diversified energy player Jakson Group reported FY26 revenue of over Rs. 9,000 crore (about USD 960 million) in a corporate presentation, alongside a renewable IPP portfolio of approximately 1.3 GWp, more than 6.5 GWp of renewable EPC executed and 3.5+ GWp of solar O&M under management. The group holds CRISIL ratings of AA (long-term) and A1+ (short-term), spanning solar modules and cells, distributed energy and biofuels.

8Adani Enterprises holds 34th AGM, showcases incubator portfolio spanning approximately 18,150 MW and multi-GW green pipeline
Adani Enterprises Limited held its 34th Annual General Meeting on 24 June 2026, presenting business, operational and financial highlights across its 'responsible incubator' portfolio that includes large thermal and renewable assets and a multi-GW green-energy pipeline totalling approximately 18,150 MW. The AGM update signals the conglomerate's energy-transition strategy, capex priorities and ESG commitments amid its expansion across India's power and infrastructure value chain.
Details
 For reference purposes the website carries here the following tenders:
 8Tender for supply of power and control cables Details
 8Tender for supply of various equipment for power house Details
 8Design, fabrication, supply, installation, testing and commissioning with RMS of otal 07 nos solar high mast (9 Mtr) and 20 kW cap. of grid connected SPV plant Details
 8Design, fabrication, supply, installation, testing and commissioning with RMS of 10 kW cap.grid connected solar PV power plant Details
 8Design, fabrication, supply, installation, testing and commissioning of total 50 KW grid connected solar PV power plant Details
 8Design, fabrication, supply, installation, testing and commissioning of total 19 KW grid connected solar PV power plant Details
 8Design, fabrication, supply, installation, testing and commissioning of total 156 KW grid connected solar PV power plant Details
 8Tender for urgent need for carrying out civil works at switchgear steel store Details
 8Tender for annual maintenance contract (AMC) for the work of repair/overhauling/servicing & alignment of various make 220kV, 132kV & 33kV isolators installed Details
 8Tender for supply of various instruments Details
 8Tender for supply and installation of energy saving BLDC ceiling fan Details
 8Tender for hot line stringing of 66 line Details
 8Tender for procurement of T and P (chain pulley blocks, triffor ) for various Details
 8Tender for procurement of journal assy. bearings for HP 803 mills installed Details
 8Tender for new 66kV SC on DC line from 66kV substation Details
 8Tender for construction of addl 160MVA TF allied foundations and allied civil works Details
 8Tender for new 66kV SC on DC line Details
 8Tender for project management consultancy services for up-gradation of instrumentation system of CPP units Details
 8Tender for procurement of lube oil pump for coal mill HP-1103 Details
 8Design, supply, installation, testing and commissioning of carbon dust collection system with control gear and all accessories Details
 8Tender for maintenance work of overhead HT/LT line, TC & HT/LT AB cable Details
 8Tender for Bi-ARC emergency restoration work of 66kV/132kV/220kV transmission line Details
 8Tender for supply of PF pipe collar, victaulic coupling & MRC spares Details
 8Tender for water proofing treatment at various 33 kV S/S Details
 8Tender for deepening and repairing of boring of tubewell and urgent renovation of water supply arrangement Details
 8Tender for P and F fencing and steel fencing around 11/0.4 kV transformer Details
 8Tender for various civil works for repairing, deepening and maintenance of Bore wells with submersible pump Details
 8Tender for construction of control room water supply arrangement and other civil works Details
 8Tender for raising and construction of replacing fencing at 132 kV GSS Details
 8Tender for civil work for transformer augmentation of 220/132 kV 100 MVA T/F Details
 8Tender for R and M of yard with providing gravelling and interlocking tiles in 132 kV yard Details
 8Tender for construction of control room with development work, parking, store shed, fencing work, water supply system and water harvesting system Details
 8Tender for construction of foundations, cable trench, levelling and dressing, GSB for transformer Details
 8Tender for repairing reconditioning work of grinding roller liner Details
 8Tender for annual work contract for the work of annual, routine and breakdown electrical maintenance works Details
 8Tender for annual work contract for the work of supply and application of insulation in boiler and turbine Details
 8Tender for annual work of providing cuplock metallic scaffolding inside the boiler furnace including Details
 8Tender for annual contract for routine, breakdown, capital maintenance of power transformers, service transformers Details
 8Tender for annual work of sample collection, testing, solution preparation, transportation of various chemicals, chlorine gas tonners Details
 8Tender for annual work contract for the work of routine, breakdown and annual maintenance work of boiler pressure part Details
 8Tender for annual work contract for routine breakdown maintenance work of 132kV line from CTPP switchyard Details
 8Tender for annual work contract for routine breakdown maintenance work of DM plant CCW CST pump house Details
 8Tender for annual contract for routine breakdown and capital maintenance of protection system Details
 8Tender for supply of valve outlet and valve adapter ceramic lined Details
 8Tender for procurement of various types of level transmitters and flow transmitters installed Details
 8Tender for annual contract for capital and routine maintenance of boiler pressure part Details
 8Tender for annual contract of running plant Details
 8Tender for requirement of temperature transmitters installed Details
 8Tender for supply of radial seals, axial seals, circumferential seals and other seals of Air pre heater Details
 8Tender for supply of limit switches installed Details
 8Tender for general fabrication contract for ash handling plant Details
 8Tender for procurement of IE3 motors Details
 8Tender for construction of central store storage sheds Details
 8Tender for repair of damaged R walls Details
 8Tender for procurement of essential spares for 105 MW Details
 8Tender for procurement of GT common kiosk panel Details
 8Tender for procurement of spares for HP bypass actuators Details
 8Tender for procurement of spare parts of stacker reclaimer installed Details
 8Tender for annual general repair and maintenance work of BTG/other auxiliary Details
 8Tender for constructing 1500m HT OH using Details
 8Tender for painting the radial gate and hoist structure Details
 8Tender for work for providing tower protection Details
 8Tender for procurement of electrical consumable materials Details
 8Tender for work of fabrication and fitting fixing of GCI open storage shed for improving of storage and handling capacity Details
 8Tender for supply, installation, testing and commissioning for carrying out the work of replacement of burnt LT armored cables and damaged pillar boxes Details
 8Tender for supply, installation, testing and commissioning for carrying out the work of fencing of 366 Nos. transformers Details
 8Tender for standardisation of transformer structures Details
 8Tender for supply laying termination testing and commissioning 12 fibre ADSS cable Details
 8Tender for constructing 2km HT line Details
 8Tender for construction of 110 kV substation Details
 8Tender for replacing damaged yard fencing Details
 8Tender for construction of 110 kV substation Details
 8Tender for work for attending various electrical defects, shifting of materials, and carrying out electrical maintenance activities Details
 8Tender for work of thermal insulation & aluminum/GI sheet cladding of various Details
 8Tender for procurement of different type RAC machines Details
 8Tender for supply and retrofitting of chinese brand chiller compressor unit of capacity Details
 8Tender for manufacture, testing, supply and delivery of 12 kV outdoor SF6 insulated 3 way RMU consisting of switchgear with vacuum interrupter and metering unit Details
 8Tender for supply of tarpaulin sheet for covering of coal Details
 8Tender for rate contract for annual maintenance contract for optical fiber network Details
 8Tender for work of overhauling of 132kV/220 kV CB poles Details
 8Tender for work of installation of 400 kV ,1x125 MVAr bus reactor along with bay Details
 8Tender for scheme of retrofitting of existing old quadruple break SF6 circuit breakers Details
 8Tender for work of providing and fixing of nonconductive turbo wind driven conical bird guards Details
 8Tender for procurement of 36 kV 1600A, having short circuit breaking capacity of 31.5 KA, 3P, VCB along Details
 8Tender for supply, civil, ETC works of 3 x 167MVA 400/220/33kV ICT along with HV/LV bays Details
 8Tender for attending emergency breakdown work & annual routine maintenance of 220/132/110kV various EHV lines Details
 8Tender for work of providing and fixing of additional 33kV PT set along Details
 8Tender for work of providing pipe type earthing and counterpoise earthing at various Details
 8Tender for work of complete overhauling of 400kV ABB make breakers pole Details
 8Tender for erection and mainteance of HT/LT/TC work Details
 8Tender for providing and laying underground cabling and jointing work Details
 8Tender for work of dye penetrant test (DPT), magnetic Details
 8Tender for work for emergency replacement, lifting & shifting, O/H and dismantling of 6.6 kV HT motors Details
 8Tender for construction of RCC retaining wall Details
 8Tender for supply of electrical hand gloves for max working voltage Details
 8Tender for turnkey based contract for 11 kV AL-59 ACS medium voltage covered conductor (MVCC) with its accessories (Package-03) Details
 8Tender for turnkey based contract for 11 kV AL-59 ACS medium voltage covered conductor (MVCC) with its accessories (Package-02) Details
 8Tender for turnkey based contract for 11 kV AL-59 ACS medium voltage covered conductor (MVCC) with its accessories (Package-01) Details
 8Tender for construction of structure and equipment foundation proposed new 66kV switch yard Details
 8Tender for supply, installation commissioning, & testing of soft starter with major/minor modification in existing panels for various motors Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Mospi proposes framework to assign monetary value to India's coal reserves Details
 
8India Nears 50% Domestic Coal Use at Import Dependent Power Plants Details
 
8Lauritz Knudsen Powers Over 50 GW of Solar Capacity Across India and Global Markets Details
 
8Loom Solar Crosses Rs 1,000 Crore Turnover in India, Strengthens Position in Fast-Growing Solar Manufacturing Sector Details
 
8UTL Solar Expands Module Manufacturing Capacity to 3.5 GW Amid Rising PM-KUSUM Demand Details
 
8From waste to wealth: Chhattisgarh CBG policy, ICAR innovation signal India’s growing rural bioeconomy Details
 
8SunAP Ecopower to Host Solar Installers Meet 2026 with Novasys and Feston to Showcase Advanced Solar and Energy Storage Solutions Details
 
8Waaree Energies targets Rs 1 trillion revenue by 2030; Motilal Oswal sees 26% upside Details
 
8Solarium Green Energy Bags Rs 186 Crore 50 MW Solar EPC Subcontract Under MAHAGENCO Details
 
8Meghalaya steps up power sector reforms, accelerates rooftop solar push Details
 
8What the ALMM mandate means for India’s industrial competitiveness Details
 
8Roofsol Secures Rs2.6 Billion Investment from Aseem Infra to Scale Distributed Solar Projects and Drive C&I Growth Details
 
8WTO To Set Up Panel On China’s Complaint Against India Over Solar & IT Goods Details
 
8Haryana govt’s ‘solar energy promotion scheme’ to benefit lakhs of consumers Details
 
8Juniper Green Commissions India's largest Wind Turbine By Rotor Diameter Details
 
8No power tariff hike for next three years: Minister Gottipati Ravi Kumar Details
 
8Delhi govt's massive crackdown against power theft yields encouraging results: Minister Sood Details
 
8Lucknow fire: UP power employees’ body slams ‘unjustified’ suspension of official Details
 
8Govt extends Section 11 directions for Tata Power's Mundra plant till Sept Details
 
8Envision Energy and AMEA Power expand Egypt wind portfolio to 1 GW Details
 
8Sampann Utpadan sells wind energy segment for Rs 2.45 crore Details
 
85 Power Stocks in India with Strong Order Books Details
 
8India raises domestic coal use to over 50% at import-based power plants Details
 
8India boosts domestic coal use at import-based power plants Details
 
8Adani Group Enters Atomic Energy, Eyes 10 GW By 2035 Details
 
You can also click on Newsclips for more Details
COAL PRODUCTION & STOCK

8CEA's daily coal-stock report flags critical-stock thermal plants as on 22 June 2026
The Central Electricity Authority's Fuel Management Division daily coal stock report as on 22 June 2026 tracks coal stock in days against normative requirement at 85% PLF for monitored thermal stations, flagging plants with critical stock. PSPCL's fleet, for instance, ran at 55% PLF with 141% of normative stock, while several utilities sat below the critical threshold; the report is the key early-warning tool for coal-supply adequacy at power plants ahead of peak demand.

8Coal India reports plant-wise coal stock and dispatch status as on 22 June 2026
Coal India Limited's Marketing & Sales Division status report as on 22 June 2026 details coal stock, receipt and dispatch at power plants in the revised format. The data show supply performance to thermal stations from the country's dominant coal producer and complement the Central Electricity Authority's stock monitoring in assessing fuel security at generating stations ahead of high summer demand.

GENERATION & PLF

8CEA's daily generation report shows the western region 0.9% above and the north 6.6% below target on 21 June
The Central Electricity Authority's daily generation report for 21 June 2026 gives region-wise generation versus programme, with the western region generating 1,670.95 MU (up 0.86%) and the northern region 1,290.29 MU (down 6.56% against a 1,317.64 MU programme). Monitored capacities stand at 104,702 MW (west), 82,527 MW (north) and 71,705 MW (south), and the deviations highlight which regions ran ahead of or behind plan on the day.

8CEA's fuel-wise report shows the 251,489 MW thermal fleet generated 4,786 MU on 21 June 2026
The Central Electricity Authority's category- and fuel-wise daily generation report for 21 June 2026 shows total thermal monitored capacity of 251,489 MW and all-fuel monitored capacity of 312,334 MW, generating about 4,786 MU on the day against a 4,654 MU programme, excluding renewables. The fuel-wise split tracks coal, gas, hydro and nuclear contributions and frames the conventional-fuel base underpinning the national grid at peak demand.

8CEA reports thermal and nuclear units out of grid for over 15 days, including Pragati CCPP's 104.60 MW unit
The Central Electricity Authority's daily generation report for 21 June 2026 lists thermal and nuclear units out of the grid for more than 15 days during 2026-27, such as Pragati CCPP Unit-1 (104.60 MW), idle since July 2025 on low system demand and costly fuel. Prolonged outages signal stranded or uneconomic capacity, and the list helps planners identify chronic availability gaps in the monitored fleet.

8WRPC publishes March 2026 thermal generator performance for western stations like the 1,600 MW Gadarwara
The Western Regional Power Committee released a revised generator performance statement for March 2026 covering western-region thermal units including Mauda, Vindhyachal, Solapur, Gadarwara, Khargone and NSPCL, with installed capacity, gross and net generation, heat rate, auxiliary consumption and availability. Super-critical units such as the 1,600 MW Gadarwara and 1,320 MW Solapur are tracked against normative benchmarks, underpinning fixed-charge recovery and incentive or penalty settlement for central generators serving the region.

HYDRO & RESERVOIR

8SRLDC's reservoir report pegs Idukki at 707.44 ft on 23 June, tracking southern hydro storage
GRID-INDIA's SRLDC reservoir report for 23 June 2026 lists levels, energy content and inflows for southern reservoirs, including Idukki at 707.44 against 717 a year earlier, Donkarai at 313.91 and Idamalayar at 137.68. Reservoir levels determine the dispatchable hydro available for peaking and balancing, and the data matter for monsoon-season hydro planning across the southern grid as inflows build, with storage levels and energy content guiding how much hydro can be banked for peak hours versus released for immediate generation.

8Odisha hydro stations average 365 MW as Balimela and Mukhiguda lead the 22 June reservoir report
The reservoir generation report dated 22 June 2026 shows Odisha's hydroelectric fleet averaging 365.25 MW, equivalent to 8.766 MU, led by Balimela at 203.17 MW (peak 379 MW) and Upper Indravati at Mukhiguda at 133.54 MW (peak 430 MW). Several units were offline for renovation or maintenance, including Balimela units 5 and 6, while Rengali and Machkund recorded nil generation, with Balimela's reservoir at 1,462.4 ft against a full level of 1,516 ft.
Details
PEAK DEMAND & POWER SUPPLY POSITION

8All-India peak demand hits 247,180 MW on 23 June with zero shortage; energy met at 5,622 MU
GRID-INDIA's NLDC national daily power supply position report for 23 June 2026 records all-India maximum demand met of 247,180 MW at 22:41 hrs, with nil peak shortage and total energy met of 5,622 MU. Region-wise peaks were 89,431 MW (north), 72,711 MW (west), 58,730 MW (south), 30,681 MW (east) and 3,711 MW (north-east), with the system held within the IEGC frequency band most of the day, confirming comfortable supply adequacy at peak summer demand.

8NRLDC's daily report tracks the northern grid toward an 89,431 MW peak on 23 June 2026
GRID-INDIA's NRLDC daily operation report for 23 June 2026 details the northern region's power supply position, with maximum demand met of about 89,431 MW, the highest of all regions, alongside evening-peak, off-peak and day-energy figures, demand met, shortage and frequency. The report is the definitive daily record for the country's largest demand region and anchors state-wise scheduling and settlement across the northern grid.

8WRLDC's power supply position shows the western grid peaking near 72,711 MW on 23 June 2026
GRID-INDIA's WRLDC power supply position report for 23 June 2026 details the western region's demand met, shortage, frequency and state-wise schedules and drawals for Gujarat, Maharashtra, Madhya Pradesh, Chhattisgarh, Goa and the union territories, with maximum demand met around 72,711 MW on the day. The report anchors western-grid operations and inter-state settlement for the country's most industrial region, where heavy thermal and fast-growing renewable capacity must be balanced through the day.

8Southern grid meets a 55,134 MW evening peak with zero shortage on 23 June; day energy at 1,277 MU
GRID-INDIA's SRLDC power supply position report for 23 June 2026 shows the southern region meeting an evening-peak demand of 55,134 MW at 50.09 Hz with nil shortage and net day energy of 1,277.47 MU. State-periphery details cover Andhra Pradesh, Karnataka, Tamil Nadu, Telangana, Kerala and Puducherry schedules, drawals and unscheduled interchange, confirming the southern grid's adequacy and balanced inter-state exchange.

8ERLDC's power supply position shows the eastern grid peaking around 30,681 MW on 23 June 2026
GRID-INDIA's ERLDC daily operation report for 23 June 2026 details the eastern region's evening-peak, off-peak and day-energy figures, with demand met, shortage and frequency for Bihar, Jharkhand, Odisha, West Bengal, Sikkim and DVC, and maximum demand met of about 30,681 MW on the day. The report is the core daily record for eastern-grid operations, a region that exports surplus coal-based power to the rest of India.

8NERLDC's power supply position shows the north-east peaking near 3,704 MW on 23 June 2026
GRID-INDIA's NERLDC daily operation report for 23 June 2026 details the north-eastern region's evening-peak demand met of about 3,704 MW with state-wise schedules and drawals for Assam, Meghalaya, Tripura, Manipur, Nagaland, Mizoram and Arunachal Pradesh. Despite its small size, NER balancing is sensitive given limited generation and long transmission links, and the report anchors regional operations and settlement, tracking how the power-deficit region drew scheduled support from the rest of the national grid on the day.

8CEA-NRPC LGBR projects a northern peak of 98,600 MW in FY27 with a 5.3% surplus but mid-year energy deficits
The Northern Regional Power Committee circulated the FY27 anticipated power supply position from CEA's Load Generation Balance Report dated 2 June 2026, projecting a regional peak demand of 98,600 MW against 1,03,780 MW availability, a 5.3% (5,180 MW) surplus, and annual energy of 5,56,767 MU against 5,74,787 MU available. Despite the headline surplus, it flags monthly energy deficits in June (-4.8%), July (-5.1%) and September (-3.8%) 2026, guiding outage planning and procurement for northern states.

FREQUENCY & DEVIATION INDICES (FDI/VDI)

8Southern grid averaged 50.007 Hz on 23 June but strayed outside the IEGC band 22% of the day
GRID-INDIA's SRLDC frequency report for 23 June 2026 records an average frequency of 50.007 Hz with a standard deviation of 0.053 and a frequency deviation index of 0.028, while the grid was outside the IEGC band 21.94% of the time, about 5.27 hours. Frequency peaked at 50.224 Hz at 13:05 and dipped to 49.82 Hz at 16:43, gauging how tightly the southern grid held nominal frequency through the day.

8SRPC certifies frequency response performance of the Udupi (Adani Power-UPCL) plant for May 2026
The Southern Regional Power Committee issued the May 2026 certificate of average monthly frequency response performance for the Adani Power-UPCL Udupi plant, based on KPTCL data for events on 13 and 15 May 2026. The FRP accounting verifies whether the generator delivered the required primary frequency response, a core grid-discipline requirement for holding 50 Hz, and feeds compliance monitoring under the ancillary-services framework.

LOAD FORECAST

8ERLDC's demand forecast for 22 June achieves 1.37% intraday accuracy by MAPE
GRID-INDIA's ERLDC forecasting-error report for 22 June 2026 records a day-ahead mean absolute percentage error of 2.95% (RMSE 3.6%) and an intraday MAPE of just 1.37% (RMSE 1.83%) for eastern-region demand. Tight forecast accuracy improves scheduling, reduces deviation costs and aids reserve planning, and the metrics benchmark the operator's predictive performance against tolerance norms, with lower error directly cutting the deviation charges utilities pay for departing from schedule.

8SRLDC forecasts the southern demand curve toward the 60,000 MW range for 24 June 2026
GRID-INDIA's SRLDC demand forecast for 24 June 2026 projects the southern region's load profile through the day, peaking in the 55,000-60,000 MW range. Accurate day-ahead forecasts underpin scheduling, reserve planning and market bidding, and the forecast guides southern utilities' next-day procurement decisions amid high summer demand and rising renewable variability, and it shapes how much power southern states schedule, bank or buy on the exchanges for the following day.

LINE & GENERATION OUTAGES

8SRLDC logs forced transmission outages on 23 June, including a 400 kV Karaikudi-Kayathar trip
GRID-INDIA's SRLDC transmission forced outage report for 23 June 2026 lists unplanned line trips, including the 400 kV Karaikudi-Kayathar-2 line of TANTRANSCO that tripped on an R-Y fault at 16:59 on 22 June and revived at 00:05 on 23 June. Forced outages stress alternate corridors and can constrain power transfer, and the log helps operators and owners prioritise fault rectification on the southern grid.

OCC MEETINGS & OUTAGE PLANNING

8NRPC's 244th OCC finalises the northern outage programme, reviewing NTPC Anta unit shutdowns
The Northern Regional Power Committee's 244th Operation Coordination Committee issued its approved outage programme dated 17 June 2026, clearing and rejecting requested shutdowns of generating units and transmission elements across the northern grid. Requests reviewed included overhauling of NTPC's Anta GPS units of about 88.71 MW each, several deferred to later LGBR weeks to preserve adequacy, coordinating maintenance windows for NTPC, state and ISTS assets through the planning horizon.

8SRPC circulates minutes of its 58th meeting and 55th technical coordination committee
The Southern Regional Power Committee circulated the minutes, reference SRPC/MS/MN-58/2026, of its 58th meeting and 55th technical coordination committee to southern-region utilities. The minutes record decisions on grid operation, protection and coordination matters that shape reliable operation of the southern grid, including outage planning, metering and commercial issues among constituent states and central generators, formalising actions agreed at the meeting and tracking compliance with earlier directions across the southern grid.

REGIONAL ENERGY ACCOUNT (REA/REMC)

8SRPC issues the regional energy account for May 2026, allocating ISGS generation to southern states
The Southern Regional Power Committee released the 103-page regional energy account for May 2026, allocating station-wise inter-state generating station energy from NTPC, NLCIL, NTECL, NTPL and IPPs such as SEIL to beneficiaries Andhra Pradesh, Telangana, Karnataka, Kerala, Tamil Nadu, Puducherry and Goa. The REA is the authoritative monthly settlement of scheduled and actual energy that determines payments among southern-grid generators and DISCOMs.

8SRPC issues its 16th reactive-energy (MVAR) statement for the southern grid in June 2026
The Southern Regional Power Committee issued its 16th reactive-energy (MVAR) statement, reference SRPC/SE(O)/16th MVAR/2026-27, dated 18 June 2026 to constituent utilities. The statement accounts for reactive-energy exchanges and the charges that incentivise voltage support across the southern grid, a key lever for power quality and stability as renewable penetration rises and reactive-power management becomes more demanding, with the statement determining the reactive-energy charges payable or receivable by each constituent utility for the month.

8WRPC releases the June 2026 transmission charges and availability statement for the western grid
The Western Regional Power Committee issued its transmission availability and charges statement for June 2026 to constituents including GUVNL, GETCO, MP Power, Chhattisgarh, Maharashtra, Goa and Daman, along with ISTS generators. The statement settles inter-state transmission charges based on element availability, central to cost allocation across western-region utilities and to revenue recovery for transmission licensees in the region, with charges apportioned among DISCOMs and generators in proportion to their use of the inter-state network.

8WRPC settles June 2026 reactive-energy (VAR) charges across western region utilities
The Western Regional Power Committee issued its 140-page reactive-energy charge statement for June 2026 to western-region constituents GUVNL, GETCO, MP, Chhattisgarh, Maharashtra, Goa and Daman, covering reactive-power drawal and injection settlement. The accounting incentivises utilities to hold voltage within band, supporting grid stability as variable renewables grow in the region and reactive-power flows become harder to manage, with the statement fixing each utility's reactive-energy payment or credit for June 2026.

8WRPC issues deviation settlement statements for 8-14 June 2026 across the western region
The Western Regional Power Committee issued deviation settlement statements for the week of 8-14 June 2026 for western-region entities and stations including Gandhar, Khargone, NSPCL and Vindhyachal, settling charges for deviations from schedule and reflecting WR-SR interchange. The statement enforces grid discipline by pricing real-time deviations under the ABT and DSM framework, with payments pooled and disbursed through the regional account.

8SRPC reissues revised DSM settlement for southern entities spanning April 2025 to May 2026
The Southern Regional Power Committee circulated revised deviation settlement statements covering multiple weeks from 28 April 2025 to 31 May 2026, after SRLDC revised schedule files for entities such as Karnataka, Andhra Pradesh, Tamil Nadu, Greenko PSP, Serentica Gadag and NTPC Simhadri. The revisions reconcile deviation charges under the applicable DSM regulations, ensuring accurate cost settlement for southern-grid constituents and renewable developers.
Details
MINISTRY OF POWER

8Tata Power's Mundra plant gets Section 11 direction extended to 30 September 2026
The Tata Power Company Limited disclosed that the Ministry of Power extended the validity of directions issued under Section 11 of the Electricity Act, 2003 for its imported-coal Mundra thermal plant, from 30 June 2026 to 30 September 2026. The extension keeps the 4,000 MW-class plant generating to meet grid demand despite high fuel costs, a market-relevant signal of continued policy support for stressed imported-coal capacity feeding the western grid.

CEA & GRID STANDARDS

8CSERC releases 201-page draft Chhattisgarh grid code 2026, inviting comments by 17 July
The Chhattisgarh State Electricity Regulatory Commission, vide notification No. D-28/CSERC/2026 dated 22 June 2026, published the draft Chhattisgarh State Electricity Grid Code, 2026 to replace the 2011 code and align the state with CERC's IEGC Regulations, 2023. The 201-page enforceable interface document covers scheduling, deviation settlement, ancillary services and a state pool settlement mechanism, including renewable generators below and above 50 MW; comments are invited by 17 July 2026 with a hearing on 22 July 2026.

8MPERC notifies first amendment to MP grid code, capping infirm-power injection at 45 days for renewables and storage
The Madhya Pradesh Electricity Regulatory Commission, vide No. MPERC/2026/1024, notified the first amendment to the Madhya Pradesh Electricity Grid Code (Revision-III), 2024, effective on gazette publication. It limits injection of infirm power to 45 days from first energisation for renewable generating stations and storage, versus one year for conventional plants, with extensions up to three months by SLDC/RLDC and beyond by the Commission, and redefines the trial-run rule to four hours cumulative in a single day, speeding renewable and storage integration.

TENDERS & PROCUREMENT (GeM/NIT)

8MNRE floats GeM tender to hire management consultants on a two-year contract; bids close 13 July 2026
The Ministry of New and Renewable Energy issued a GeM tender to hire milestone- and deliverable-based management consultants, including a team lead, programme manager, IT expert and executive assistant on onsite engagement, for a two-year contract, with bids closing 13 July 2026 at 5:00 PM. The tender requires a minimum average annual turnover of Rs. 1,000 lakh, with MSE and startup relaxations, and two years of similar experience, pointing to MNRE strengthening programme-management capacity for its renewable push.
Details
DAY-AHEAD MARKET (DAM/GDAM/HPDAM)

8Day-ahead market clears 147,709 MWh for 23 June as prices touch the Rs. 10,000/MWh ceiling
The Day-Ahead Market snapshot for 23 June 2026 shows total scheduled volume of 147,709.25 MWh against purchase bids of 402,031 MWh and sell bids of 439,419 MWh, with the market-clearing price hitting the Rs. 10,000 per MWh ceiling in several morning blocks. The repeated ceiling hits reflect tight demand-supply during peak summer, and DAM clearing sets the reference price for short-term power across India.

8Green day-ahead market clears solar, non-solar and hydro blocks for 23 June 2026
The Green Day-Ahead Market snapshots for 23 June 2026 detail 15-minute clearing of solar, non-solar and hydro renewable power, listing purchase and sell bids, market-clearing volumes and market-clearing prices in Rs. per MWh segment-wise. The dedicated green segment lets DISCOMs and C&I buyers procure renewable energy competitively on the exchange, advancing market-based clean-power trade, with the day's blocks showing continued liquidity in segregated solar, non-solar and hydro products.

8High-price day-ahead market clears premium-segment supply for 23 June 2026
The High-Price Day-Ahead Market snapshots for 23 June 2026 record purchase and sell bids, market-clearing volume and price for the premium segment that allows clearing above the normal price cap for high-cost generation. The data show how costly back-up supply was priced and scheduled when cheaper sources were exhausted during peak summer demand, an increasingly important mechanism for meeting load at the margin.

REAL-TIME MARKET (RTM)

8Real-time market prices hit the Rs. 10,000/MWh ceiling in 36 blocks on 23 June 2026
The Real-Time Market snapshots for 23 June 2026 show the market-clearing price reaching the Rs. 10,000 per MWh ceiling in 36 fifteen-minute blocks, with cleared volumes around 4,197 MW in peak blocks. The repeated ceiling hits signal acute real-time scarcity during high summer demand. RTM lets utilities balance positions close to delivery, and the elevated prices flag stressed supply on the national grid.

TERM-AHEAD & GREEN TERM-AHEAD (TAM/GTAM)

8IEX term-ahead market posts contract-wise trades for 23 June 2026
The Indian Energy Exchange Term-Ahead Market trade details for 23 June 2026 report contract-wise buy and sell prices, highest, lowest, average and weighted-average values and total traded volumes across forward delivery periods. TAM lets participants hedge and procure power for future days and weeks, and the data show the depth of term-based trading on the exchange beyond the day-ahead window.

8IEX green term-ahead market posts renewable trades for 23 June 2026
The Indian Energy Exchange Green Term-Ahead Market trade details for 23 June 2026 report contract-wise highest, lowest, average and weighted-average prices alongside total traded volumes for renewable power. GTAM enables forward procurement of green energy beyond the day-ahead window, helping buyers lock in clean-power supply, and the trade data signal the depth of term-based renewable trading on the exchange as buyers increasingly use forward contracts to meet renewable purchase obligations.

ANCILLARY & INTRADAY (ASDAM/IDAS/SCUC)

8NLDC's SCUC schedule for 24 June commits Darlipali, North Karanpura and Vindhyachal at 116-215 paise/kWh
GRID-INDIA's NLDC security-constrained unit commitment schedule for 24 June 2026, published on 23 June at 1500 hrs, lists committed stations with scheduled MW and energy charge rates, including Darlipali at 467.16 MW (115.9 paise/kWh), North Karanpura STPS at 809.02 MW (212.7 paise/kWh) and Vindhyachal Stage-4 at 236.38 MW (214.7 paise/kWh). SCUC optimises which units run to meet demand at least cost while respecting network constraints, directly shaping next-day despatch economics.

8Ancillary services day-ahead market details reserve procurement for 23 June 2026
The Ancillary Services Day-Ahead Market snapshots for 23 June 2026 list 15-minute bids, cleared volumes and weighted-average prices in Rs. per MWh for reserve procurement, with many blocks showing nil clearing. ASDAM helps grid operators secure balancing reserves through the market, and the data reflect the still-emerging market for grid-support services that backstop frequency and balancing on the national grid.

8Intra-day auction session reports capture the 23 June 2026 volume profile
The Intra-Day Auction Session daily reports for 23 June 2026 compile 15-minute purchase bids, sell bids, market-clearing volumes and prices for the intra-day segment. Intra-day auctions let participants adjust positions within the delivery day, and the volume profile records how the segment cleared, complementing day-ahead and real-time products in the short-term power market and giving participants an extra window to correct positions before delivery on 23 June 2026.

DEVIATION SETTLEMENT (DSM)

8PXIL's DSM report logs cleared buy-sell volumes for 23 June 2026
Power Exchange India Limited's Deviation Settlement Mechanism report for 23 June 2026 records 15-minute cleared buy and sell volumes in MW and prices in Rs. per MWh on its platform. The data feed deviation settlement and balancing for participants and reflect PXIL's role in short-term power trade alongside the larger Indian Energy Exchange, supporting price discovery for real-time imbalances and giving generators and DISCOMs an alternative venue to the dominant exchange for settling deviations on the day.

EXCHANGE AUCTIONS & CIRCULARS

8HPX opens two reverse auctions for Damodar Valley Corporation on 23 June 2026
The Hindustan Power Exchange notified members of two any-day single-side reverse auction contracts, Auction Nos. HPX/23062026/01034 and HPX/23062026/01035, initiated and published on 23 June 2026 with Damodar Valley Corporation as the buyer. The reverse auctions let DVC procure power competitively through the exchange platform, reflecting growing use of short-term market mechanisms by large utilities to optimise power-purchase costs, with reverse auctions allowing a single buyer like DVC to invite competing sell offers and drive down its short-term procurement price.
Details
SOLAR POWER

8NISE pegs India's floating solar potential at 102 GW in new MNRE map for June 2026
The National Institute of Solar Energy, under MNRE, released a June 2026 assessment putting India's total floating solar PV potential on feasible waterbodies at about 102.18 GW. The state-wise map shows the largest pockets exceeding 15 GW, with several states in the 10-16 GW band, around 16.28, 14.89, 13.69, 12.81 and 10.72 GW, framing reservoirs and water bodies as a major untapped resource that can add capacity without competing for scarce land.

8CEA's daily renewable report pegs all-India output at 624 MU solar and 557 MU wind on 23 June
The Central Electricity Authority's Renewable Project Monitoring Division daily renewable generation report for 23 June 2026 records all-India output of about 624 MU solar and roughly 557 MU wind on the day, with cumulative June 2026 renewable generation nearing 25,519 MU. The state- and region-wise figures, in MU net, track India's clean-energy ramp-up against monthly targets and feed planning for renewable absorption and conventional back-down across the grid.

WIND & HYBRID POWER

8NLC India and Indian Oil sign MoU for Tamil Nadu renewable JV spanning solar, wind, hybrid and storage
Navratna CPSE NLC India Limited signed a Memorandum of Understanding with Indian Oil Corporation Limited on 22 June 2026 in New Delhi to form a joint venture for large-scale renewable projects in Tamil Nadu, covering solar, wind and hybrid power with or without battery and pumped storage. The JV will supply green power to third-party C&I consumers, DISCOMs, exchanges and e-mobility, and may extend to green synthetic fuels and the solar-module value chain, advancing India's net-zero goals.

8NLDC's REMC logs 32% VRE share in peak demand on 22 June as the all-time wind-solar record hits 97,629 MW
GRID-INDIA's National Load Despatch Centre REMC report for 22 June 2026 shows variable renewable energy (wind plus solar) contributing up to 80,333 MW, about 32.06%, of all-India demand met during solar hours, against a daily peak demand near 250,554 MW. It records the all-time-high VRE generation of 97,629 MW (9 June 2026) and the highest-ever VRE penetration of 40.96% (5 March 2026), excluding rooftop and off-grid solar, underlining how fast renewables are reshaping the generation mix.

STORAGE & GREEN HYDROGEN

8Ola Electric becomes first Indian firm to win BIS certification for its indigenous 46100 LFP cell
Ola Electric Mobility Limited announced on 23 June 2026 that its wholly owned subsidiary Ola Cell Technologies received BIS certification for an indigenously developed 46100 LFP (lithium iron phosphate) cell, making Ola the first Indian company to achieve the milestone. The certification strengthens India's battery-manufacturing localisation and the company's EV supply-chain self-reliance, a strategically significant step for domestic cell production that underpins both mobility and stationary storage.

8SRPC drafts battery energy storage guidelines for the southern grid after KSEBL-hosted stakeholder meet
The Southern Regional Power Committee has prepared draft Guidelines for Battery Energy Storage Systems covering operational, protection and telemetry aspects, following a hybrid-mode stakeholders' meeting on 15 May 2026 hosted by KSEBL at Moolamattom, Idukki. Participants from SRLDC, NTPC, SLDCs, STUs and GENCOs agreed BESS integration by southern states is essential to mitigate the variability of growing renewable generation, and the framework aims to standardise how storage assets are despatched, protected and monitored.

POLICY & INCENTIVES

8KERC halves deviation charges for wind-solar generators in new 2026 DSM rules as state RE capacity hits 22,046 MW
The Karnataka Electricity Regulatory Commission notified the KERC (Forecasting, Scheduling, Deviation Settlement Mechanism for Wind, Solar and WS-Hybrid) Regulations, 2026 (No. KERC/WS(DSM)/2026-27/2150 dated 19 June 2026), aligning forecasting with the Karnataka grid code. It cut deviation charges to 50% and capped them at 3 paise per unit of annual generation while tightening the tolerance band. Karnataka now carries about 22,045.69 MW of installed RE (solar 10,585.84 MW, wind 7,870.81 MW, hybrid 738.30 MW) against 1,55,074 MW potential.
Details
RETAIL TARIFF REVISION

8UPERC caps June 2026 fuel surcharge at 10% against UPPCL's 20.61%, bars one-time NTPC arrears
The Uttar Pradesh Electricity Regulatory Commission, in Petition No. 76 SM of 2026, recorded that UPPCL had determined a Fuel and Power Purchase Adjustment Surcharge of 20.61% for June 2026 but levied only 10% on consumers under the cap in Regulation 16.1(4) of the UPERC MYT Regulations, 2025. The Commission directed that from the next cycle, prior-period one-time costs such as APTEL-mandated NTPC arrears and CTU dues be excluded from the monthly surcharge and routed through true-up, shielding consumers from lumpy legacy charges.

OPEN ACCESS & WHEELING CHARGES

8GERC sets Rs. 5,200-6,300 per kVA charges for new underground HT connections across Gujarat DISCOMs
The Gujarat Electricity Regulatory Commission, in Petition No. 2191 of 2023 dated 22 June 2026, approved a per-kVA charging methodology for new HT connections and load extensions served through 11/22 kV underground networks up to 11.86 km, on a petition by PGVCL with GUVNL, UGVCL, MGVCL and DGVCL. It fixed Rs. 5,200 per kVA for loads up to 500 kVA and Rs. 6,300 per kVA above 500 kVA, below the Rs. 6,988 sought, applicable uniformly to all state DISCOMs.

COMMISSION ORDERS (CERC/SERC)

8CERC grants NUPPL 85% interim tariff for the 1,980 MW Ghatampur thermal plant through March 2029
The Central Electricity Regulatory Commission, in I.A. No. 37/2026 in Petition No. 370/GT/2025 dated 22 June 2026, allowed NLC India-UPRVUNL joint venture Neyveli Uttar Pradesh Power Limited an interim tariff of 85% of claimed annual fixed charges for Unit-1 (COD 12 December 2024) and Unit-2 (COD 9 December 2025) of the 1,980 MW (3x660 MW) Ghatampur supercritical plant. Interim charges run from about Rs. 456 crore in 2024-25 to Rs. 2,515 crore in 2028-29, pending a final prudence check against the Rs. 21,780.94 crore sanctioned cost.

8CERC sets NHPC's Uri-II tariff for 2024-29, fixing annual charges near Rs. 451 crore for the 240 MW plant
The Central Electricity Regulatory Commission, in Petition No. 650/GT/2025 dated 22 June 2026, trued up 2019-24 tariff and set 2024-29 tariff for NHPC Limited's 240 MW (4x60 MW) Uri-II hydro project at Salamabad, Jammu & Kashmir. It approved annual fixed charges of about Rs. 451.22 crore for 2024-25, easing to roughly Rs. 396.55 crore by 2028-29, on a closing capital cost of around Rs. 2,529 crore and design energy of 1,123.77 MU, fixing northern-grid hydro costs for the control period.

8JSERC orders Rishi Cement to pay JBVNL Rs. 42.44 lakh, closing a billing dispute dating to 1991
The Jharkhand State Electricity Regulatory Commission, in an order dated 18 June 2026 in Case No. 08 of 2017, ruled that M/s Rishi Cement Company Limited must pay Jharkhand Bijli Vitran Nigam Limited Rs. 42,43,725 within two months, settling objections remanded by APTEL in October 2024. After a chartered-accountant evaluation of billing from 1991 to 2009, the Commission fixed a balance of Rs. 68.04 lakh payable, netted against Rs. 59.57 lakh of ombudsman-ordered reliefs, ending a dispute running over three decades.

8UPERC orders pass-through of GST cut from 12% to 5% on solar-wind gear to PM-KUSUM consumers
In a suo motu order in Petition No. 75 SM of 2026, the Uttar Pradesh Electricity Regulatory Commission held the reduction in GST on renewable devices from 12% to 5% a 'change in law' event, directing the resulting capital-cost fall be passed to UPPCL and end consumers. The ruling covers PPAs under PM-KUSUM Component-C2 feeder-level solarisation, where developers were picked on 25-year tariffs, and requires UPPCL and developers to recompute per-kWh tariffs from actual invoices and GST paid.

TRANSMISSION LICENSING & ORDERS

8HPERC approves Rs. 75.50 crore capital cost for HPPTCL's 220/132 kV Mazra substation
The Himachal Pradesh Electricity Regulatory Commission, in an order dated 23 June 2026, set the aggregate revenue requirement and annual transmission charges for three HPPTCL assets commissioned on 27 March 2024: the 220/132 kV, 2x80/100 MVA Mazra substation, the 220 kV double-circuit Mazra-Karian line and a LILO of the 132 kV Kurthla-Bathri line. It approved the substation's capital cost at Rs. 75.50 crore against a Rs. 87.16 crore DPR estimate and the line at Rs. 14.46 crore after a prudence check, feeding Himachal's pooled wheeling charges.

OMBUDSMAN & CONSUMER GRIEVANCE

8Kerala electricity ombudsman gives KSEBL three options to shift a line off a 5-cent plot in a Rs. 61,692 dispute
The State Electricity Ombudsman, Ernakulam, on 22 June 2026 partly allowed Smt. Sreedevi's appeal (P/024/2026) against KSEB Limited over an LT three-phase line and post crossing her roughly 5-cent plot at Thuravoor. Rejecting KSEBL's stud-support plan inside the plot, the ombudsman let the consumer pick among three options, a stud-supported pole, a concrete pole on a pedestal, or two spans of underground cable, with the revised cost on a base estimate of Rs. 61,692 borne by the appellant under Regulation 95 of the Supply Code, 2014.

8Tamil Nadu electricity ombudsman closes Chennai consumer's appeal after TNPDCL refunds surrendered-connection dues
The Tamil Nadu Electricity Ombudsman on 23 June 2026 closed Appeal Petition No. 09 of 2026 filed by Mylapore consumer Thiru K. Bhaskaran against TNPDCL, after the appellant withdrew it on 16 June 2026 saying his grievances were resolved. The petition, received on 17 February 2026, had alleged delayed tariff conversion, a disputed testing fee and excess billing; the licensee credited the refundable amount for surrendered service connections to his account, showing how field-level engagement can settle disputes before a full hearing.
Details
WORK ORDERS & SUPPLY CONTRACTS

8POWERGRID wins TBCB bid for WR-ER inter-regional scheme with 765 kV lines across three states
Power Grid Corporation of India Limited received the Letter of Intent on 16 June 2026 as successful bidder under Tariff Based Competitive Bidding for the 'WR-ER Inter-Regional Network Expansion Scheme Part-A' on a build, own, operate and transfer basis. The project comprises two new 765/400 kV substations in Jharkhand and Chhattisgarh, extensions in Chhattisgarh and West Bengal, and 765 kV and 400 kV lines across Jharkhand, Chhattisgarh and Odisha, expanding POWERGRID's regulated asset pipeline.

8Solarium Green Energy bags Rs. 186.5 crore LoA for 50 MW AC solar project under MAHAGENCO
Solarium Green Energy Limited disclosed a Letter of Award dated 22 June 2026, as a sub-contractor, for end-to-end EPC plus three years of operation and maintenance on a 50 MW AC / 65 MW DC solar PV project in Maharashtra under a Maharashtra State Power Generation Company (MAHAGENCO) scheme. The order is valued at about Rs. 186.525 crore excluding GST, strengthening the company's renewable-EPC order book and revenue visibility over the execution period.

CAPACITY COMMISSIONING & COD

8NTPC declares COD of 800 MW Patratu Unit-2, lifting group capacity to 90,857 MW
NTPC Limited declared Unit-2 (800 MW) of the Patratu STPP Phase-1 (3x800 MW) of subsidiary Patratu Vidyut Utpadan Nigam Limited (PVUNL) on commercial operation from 00:00 hrs of 25 June 2026. With this, NTPC group's total installed capacity rises to 90,857 MW and commercial capacity to 89,777 MW. The addition advances NTPC's thermal build-out in Jharkhand and is material to the utility's generation volumes and earnings trajectory.
Details
QUARTERLY RESULTS

8GIFT Power's Q4 FY26 sales rise 25% to Rs. 14 crore as GIFT City power purchases climb to 17.56 MU
GIFT Power Company Limited's Q4 FY26 regulatory information report to GERC shows power purchases of 17.559 MU, up 24% year-on-year, serving 1,995 consumers at GIFT City, with cumulative FY26 purchases of 72.594 MU. Quarterly sales rose 25% to Rs. 14 crore (cumulative Rs. 57.80 crore), while T&D loss stayed low at 2.70% and the average cost of supply eased about 9% to Rs. 8.73 per kWh, reflecting rising demand at Gujarat's finance hub.

8UGVCL's solar purchases more than double to 266 MU in Q3 FY26 as billing tops Rs. 4,720 crore
Uttar Gujarat Vij Company Limited's Q3 FY26 regulatory information report to GERC shows total procurement of 8,264.43 MU (cumulative 25,003.17 MU), with solar purchases surging about 125% year-on-year to 266.42 MU. The DISCOM sold 7,627.90 MU, billed Rs. 4,720.77 crore (cumulative Rs. 14,660.32 crore) and realised about 89.83% of billed amounts, while T&D loss was 6.56% and average cost of supply Rs. 5.70 per kWh, signalling a deepening clean-energy mix.

DIVIDEND & BOARD DECISIONS

8PFC board to take up PFC-REC merger scheme on 28 June 2026 under Sections 230-232
Power Finance Corporation Limited informed the exchanges on 23 June 2026 that its board will meet on 28 June 2026 to consider and approve the scheme of merger between PFC and subsidiary REC Limited and their shareholders and creditors, under Sections 230-232 of the Companies Act, 2013. The proposed amalgamation of the two Maharatna power-sector financiers would create a single dominant lender to India's power and infrastructure sectors, a landmark move for investors in both stocks.

FUND RAISING & CAPITAL

8PFC prices USD 300 million 5.32% notes due 2031 under its USD 8 billion GMTN programme
Power Finance Corporation Limited launched and priced USD 300 million of 5.32% notes due June 2031 on 22 June 2026 under its USD 8 billion Global Medium Term Note programme, with interest payable semi-annually in U.S. dollars. The dollar issuance diversifies PFC's funding for on-lending to the power sector and sets a fresh pricing benchmark for Indian power-finance paper offshore, a development relevant to fixed-income investors tracking Maharatna PSU credit.

8POWERGRID board to weigh USD 500 million ECB fundraise on 26 June 2026
Power Grid Corporation of India Limited told the exchanges on 23 June 2026 that its board will meet on 26 June 2026 to consider raising foreign-currency funds through External Commercial Borrowings of up to USD 500 million from domestic or foreign banks. The move signals fresh overseas borrowing by India's largest transmission utility to fund its capital-expenditure programme, with the trading window shut from 24 June until 48 hours after Q1 results, and is material to bondholders and POWERGRID's cost of capital.

CREDIT RATING & ANALYST REPORT

8CRISIL reaffirms Hitachi Energy India's AAA long-term rating on Rs. 6,000 crore bank facilities
Hitachi Energy India Limited disclosed that CRISIL Ratings reaffirmed its long-term rating at CRISIL AAA/Stable and reassigned its short-term rating at CRISIL A1+ on Rs. 6,000 crore of bank facilities. The top-tier rating affirms the grid-technology major's credit strength and access to low-cost funding amid a strong order pipeline in transmission and grid automation, a positive signal for investors and lenders.

8ICRA reaffirms KEI Industries at AA+/A1+, rating Rs. 3,680 crore of bank lines
ICRA reaffirmed KEI Industries Limited's long-term and short-term ratings at AA+ (Stable)/A1+ on Rs. 3,680 crore of fund- and non-fund-based bank facilities, raised from Rs. 3,310 crore, plus Rs. 130 crore of additional lines and Rs. 40 crore of commercial paper at A1+. The reaffirmation underscores the cables and wires maker's strong financial profile and order book, supporting its capacity expansion and working-capital access.

8CRISIL upgrades TD Power Systems to AA-/A1+ on Rs. 488 crore of facilities
TD Power Systems Limited disclosed that CRISIL Ratings, via communication dated 22 June 2026, upgraded the long-term rating on its Rs. 488 crore of bank facilities to CRISIL AA-/Stable and the short-term rating to CRISIL A1+. The upgrade reflects improving credit metrics at the generator and electrical-machines manufacturer and is expected to ease the company's cost of borrowing as it scales exports and domestic supply.

8CARE puts Maruti Clean Coal's Rs. 785 crore facilities on watch positive after 100% stake-buy move
CARE Ratings placed Maruti Clean Coal and Power Limited's Rs. 735.11 crore long-term bank facilities (CARE BBB) and Rs. 50.34 crore long/short-term facilities (CARE BBB/A3+) on Rating Watch with Positive Implications. The action follows a share-purchase agreement by Kolahai Infotech and SFI Parcel Services to acquire a 100% stake in the company, subject to Government of Chhattisgarh approval for transfer of the associated power assets, signalling a possible upgrade if the deal completes.

8ICRA keeps Supreme Solar Systems at B+ under 'issuer not cooperating'
ICRA retained the long-term rating of Supreme Solar Systems at B+ (Stable) but kept it in the 'Issuer Not Cooperating' category on its cash-credit and term-loan facilities, citing inadequate information from the company. The status flags heightened information risk for lenders and counterparties dealing with the solar water-heater maker and limits the agency's ability to refresh its credit view, and counterparties are advised to seek updated disclosures before extending fresh exposure to the company.
Details
 For reference purposes the website carries here the following tenders:
 
8Tender for renovation of control room others allied civil work 132/33 kV sub- station Details
 
8Tender for supply, installation, configuration, testing, commissioning and maintenance of next generation firewalls Details
 
8Design, fabrication, supply, installation, testing and commissioning of 7.5 HP DC 5 HP DC 01 no. 03 HP DC 06 nos. of solar water pumping system Details
 
8Tender for integration of bus bar protection scheme with 220/132kV, 100MVA T/F Details
 
8Tender for supply of material, erection, testing and commissioning for augmentation of 72 Nos. existing 33 kV sub-stations Details
 
8Tender for construction of brick edging, IPB path, PCC in yard and allied civil works Details
 
8Tender for construction of plinth protection brick wall, earth work and allied civil works Details
 
8Tender for supply of material, erection, testing and commissioning (including civil works) of 27 no. 33 kV substations Details
 
8Tender for supply of material, erection, testing and commissioning (including civil works) of 27 no. 33 kV substations Details
 
8Tender for construction of corridor for ash pipe line Details
 
8Tender for proposed external electrical connection Details
 
8Tender for procurement of rigid spacer 450mm suitable for twin moose conductor Details
 
8Tender for casting of RCC slabs for trenches Details
 
8Tender for various repair works of control room and yard Details
 
8Tender for renovation of control room, yard development at 33 kV S/S Details
 
8Tender for renovation of control room, roof leakage treatment Details
 
8Tender for constuction of transformer and VCB foundation and strengthing of existing transformer Details
 
8Tender for construction of borewell and water supply arrangement at 33 kV S/S Details
 
8Tender for supply of 166 nos surge counter of 198 kV and 120 kV LA for various Details
 
8Tender for requirement for drain flash tank pump without motor Details
 
8Tender for supply of 11 kV polymer DO fuse unit Details
 
8Tender for procurement of spare of CEMS system Details
 
8Tender for providing vitrified tiles in floors Details
 
8Tender for procurement of flexible trailing power cable for stacker reclaimer Details
 
8Tender for spares of ash slurry pump, drain sump pump , seal water pump Details
 
8Tender for work of EHV bays strengthening for capacity Details
 
8Tender for setting up of 15 MW grid-connected rooftop solar PV projects Details
 
8Tender for construction of pit room Details
 
8Tender for civil works for front Details
 
8Tender for rate contract for the sodium chlorite Details
 
8Tender for construction of sheds, lift shafts and allied civil works Details
 
8Tender for work of dismantling replacement / repairing of PF pipe Details
 
8Tender for supply of MS hot dip galvanized coating grills for boiler Details
 
8Tender for routine, preventive and breakdown maintenance work of complete air conditioning system Details
 
8Tender for work of repairing of various pulleys of conveyor belts Details
 
8Tender for work of analysis of coal, fly-ash Details
 
8Tender for rate contract for the work of online, preventive and breakdown maintenance for DM plant Details
 
8Tender for maintenance works routine / schedule / preventive / breakdown / overhauling of air compressors Details
 
8Tender for biennial maintenance contract for conservancy work Details
 
8Tender for cleaning and maintenance of switch yard, roofs Details
 
8Tender for laying of LTUG line Details
 
8Tender for annual rate contract for civil repair and maintenance Details
 
8Tender for various civil works for renovation of 33/11 kV substation Details
 
8Tender for supply of required materials Details
 
8Tender for augmentation of capacity of overloaded transformers Details
 
8Tender for replacement work of damaged distribution transformers (DTRs) Details
 
8Tender for construction of HT/LT line and erection of distribution transformer Details
 
8Tender for special maintenance and repair of misc. civil works at 33/11 kV S/S Details
 
8Tender for special M and R of old and other misc. civil works Details
 
8Tender for supply of 13 meter long steel tubular pole Details
 
8Tender for supply of 9meter long steel tubular pole Details
 
8Tender for providing and laying G. I. pipe Details
 
8Tender for replacement of baskets of rotary air preheater Details
 
8Tender for supply of IT material for maintenance Details
 
8Tender for restoration/repair of the damaged access Details
 
8Tender for development of transmission line Details
 
8Tender for supply, installation, testing and commissioning of floating log boom barrier system Details
 
8Tender for repair and maintenance of control room at 220/132 kV GSS Details
 
8Tender for procurement of spare material for relay panel and power transformer Details
 
8Tender for execution of protective work for safety of existing tower foundation Details
 
8Tender for refurbishing of existing plate earthing system with earth-mat Details
 
8Tender for procurement of special testing kits for sub station equipments Details
 
8Tender for SITC of complete heating system Details
 
8Tender for laying 11kV UG cable Details
 
8Tender for reconductoring of 11kV feeder Details
 
8Tender for renovation of chain link fencing around Details
 
8Tender for repair and mtc civil works Details
 
8Design, manufacture, testing, inspection, packing and delivery of ISI marked multi core 1.1 kV LT XLPE insulated Details
 
8Tender for work of removal, supply and application of spray thermal insulation on drive turbines Details
 
8Tender for work of overhauling & re-commissioning of R.O. feed pumps Details
 
8Tender for work of replacement of rusted tower Details
 
8Tender for supply, installation, design, engineering, erection, commissioning & testing of 220 V, minimum 500 AH nickle-cadmium DC battery sets Details
 
8Tender for supply, erection and commissioning of new street light poles Details
 
8Tender for site survey including underground utility Details
 
8Tender for AMC for the work of maintenance, servicing & repairing of 220/110/48V battery charger & battery sets available Details
 
8Tender for augmentation of substation by providing additional T/Fs & replacement of T/Fs Details
 
8Tender for enhancement of transformation capacity of substation Details
 
8Tender for work of installation of 1X125MVAR 400kV bus shunt reactor with allied bay Details
 
8Tender for enhancement of transformation capacity of substation by providing 1x100MVA, 220/132kV ICT along Details
 
8Tender for work of annual maintenance contract for work of overhauling / servicing & alignment of various make 220 kV, 132 kV & 33 kV isolator installed Details
 
8Tender for annual maintenance for civil assets Details
 
8Tender for replacement of existing 220kV, 1250A wavetraps by 220kV, 2000A wavetraps Details
 
8Tender for site survey including underground utility verification using Details
 
8Tender for supply, erection, testing, and commissioning of 220kV & 66kV equipment’s & materials Details
 
8Tender for site survey including underground utility Details
 
8Tender for extension of existing shed and store, construction of new shed Details
 
8Tender for two year complete cover warranty maintenance contract (CMC) for ring main units Details
 
8Tender for repair, maintenance, and installation of plant/ systems Details
 
8Tender for repair, maintenance, and installation of plant/ systems/equipments Details
 
8Tender for construction of foundation, cable trench, chain-link fencing wall Details
 
8Tender for construction of new 66kV control room feeder cable Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
New coal exchange rules set to regulate trading, formalise market structure Details
 
8BHP: Time to get real about steel technology change and met coal Details
 
8Bharat Coking Coal, CMPDI: How Coal India's listed subsidiaries have performed vs their IPO issue prices Details
 
8The coal baron who could transform steel and methane together Details
 
8India Shifts 5.7 GW of Import-Based Power Capacity to Domestic Coal Details
 
8Birla Corporation Kickstarts Commercial Production at Bikram Coal Mine Details
 
8Ambit revamps model portfolio: Adds Axis Bank, L&T, Ather Energy; drops Tata Motors, Coal India Details
 
8OREDA, NLC sign pact for 1,000 MW green energy projects in Odisha Details
 
8RRECL Unveils New Logo, Reinforces Commitment To Rajasthan’s Green Energy Future Details
 
8DEE Development Engineers Secures Rs 64 Crore Windmill Tower Order Details
 
8India Eyes Near-Complete EV Component Localisation By 2030: Report Details
 
8Loom Solar, India's Perennial Solar Startup, Crosses Rs 1000 crore Milestone Details
 
8India power sector outlook positive as demand and capex cycle drive growth Details
 
8PFC raises $300 million via dollar denominated bonds Details
 
8NLC India Signs MoU with Indian Oil for Renewable Energy JV in Tamil Nadu Details
 
8Tsuyo Manufacturing appoints new sales and service head Details
 
8Top 4 Stocks to Benefit from India’s Rising Power Demand and Aggressive Capacity Expansion Details
 
8Power sector outlook in India remains positive on strong demand, policy support: Report Details
 
8India Power Sector Reform: From Fixing Shortages to Giving People Choice Details
 
8India's Power Grid Under Strain After Hitting 500 GW Milestone Details
 
8NTPC Adds 800 MW Capacity with Patratu STPP Unit#2 Commercial Operation Details
 
8Power Finance Corporation Launches $300 Million Global Bond Issue at 5.32% Coupon Under GMTN Programme Details
 
8GERC Allows Force Majeure for Right-of-Way Delays in Wind Projects Details
 
8India Launches Anti-Dumping Probe on Electrical Steel Imports Details
 
8India’s EV Localisation Faces Hurdles Amid High Import Reliance Details
 
You can also click on Newsclips for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8LPG
8Ammonia
8Coal & Coke
8All tankers
8Bulk and Dry cargo

Click on Reports for more. Details
GENERATION & PLF

8India generates 5,048 MU on 20 June, beating programme by 8%; coal supplies 4,175 MU as hydro slips below plan — CEA
The Central Electricity Authority's All-India Daily Generation Report for 20 June 2026 — spanning 17 sub-reports — records actual generation of 5,048.38 MU against a 4,652.50 MU programme from a monitored capacity of 312,233.79 MW. Coal led with 4,174.50 MU, followed by hydro 477.34 MU (below its 563.77 MU plan amid the pre-monsoon draw-down), nuclear 185.21 MU, natural gas 89.30 MU, lignite 84.51 MU and 36.38 MU of Bhutan imports.

8Karnataka's thermal fleet logs mixed May; Bellary's 1,700 MW runs at 76.7% PLF while Yermarus lags at 59%
May-2026 station reports from Karnataka Power Corporation Limited and Raichur Power Corporation Limited show the 1,700 MW Bellary TPS leading with net generation of 909.91 MU at a 76.72% plant load factor, the 1,720 MW Raichur TPS at 621.41 MU and 63.5% PLF, and the 1,600 MW Yermarus TPS at 649.10 MU and a softer 58.99% PLF. Multiple forced outages logged across the units illustrate the variable availability of the State's coal-based baseload.

8GSECL files half-yearly environmental compliance for entire thermal fleet, from 2x250 MW lignite units to new 800 MW supercriticals
Gujarat State Electricity Corporation Limited submitted Oct-2025 to Mar-2026 half-yearly Environmental Clearance compliance reports to the MoEF&CC between 19 and 22 June 2026 covering its full thermal fleet: the 2 x 250 MW Bhavnagar Lignite TPS, the 2 x 250 MW Sikka STPS Units 3 & 4, Wanakbori Units 7 and 8 — including the 1 x 800 MW Extension Unit 8 — Ukai Units 6 and 7 with a 1 x 800 MW supercritical, the 75 MW KLTPS Unit-4, and Dhuvaran, Utran gas stations plus Gandhinagar GTPS.

8RVUNL's Suratgarh supercritical units 7 & 8 file May-2026 environmental status report to CEA
Rajasthan Rajya Vidyut Utpadan Nigam Limited's Suratgarh Super Critical Thermal Power Station (Units 7 & 8) forwarded its May-2026 Environmental Status Report to the Central Electricity Authority in a letter dated 20 June 2026. The mandatory filing documents the coal-based supercritical station's environmental parameters and keeps the central monitoring loop current for one of Rajasthan's newest large thermal units.

COAL PRODUCTION & STOCK

824 thermal plants flagged on critical coal stock in CEA's 21 June report even as some utilities hold surpluses
The Central Electricity Authority's Daily Coal Stock Report as on 21 June 2026 flags 24 thermal stations on critical coal stock, with sharp contrasts across utilities: CSPGCL plants held 168% and PSPCL 142% of normative requirement, while GSECL stood at just 35%, UPRVUNL 48% and RRVUNL 55%. The daily monitoring is the frontline indicator of fuel-supply risk to coal-fired generation during the high-demand summer window.

8Coal India's 21 June stock map tracks linkage plants in critical and super-critical zones nationwide
Coal India Limited's Marketing & Sales Division reported the coal-stock position as on 21 June 2026 for power plants holding coal linkage with CIL and Singareni Collieries, classifying numerous stations as critical or super-critical against the CEA's revised monitoring methodology. The bulletin lets the coal major and generators jointly prioritise rakes to the most fuel-short plants and pre-empt generation cuts during the summer peak.

8MSPGCL's May coal burn diverges from MERC-approved plan as Chandrapur units lean on raw coal
Maharashtra State Power Generation Co. Ltd's fuel-utilisation comparison for May 2026, filed under the MERC MYT Regulations 2024 and the MTR order in Case No. 187 of 2024, shows station-wise deviations from the approved Fuel Utilisation Plan: Chandrapur Units 3-7 consumed 0.6202 MMT against a 0.6460 MMT plan, with washed coal diverted to other stations and greater use of raw coal against imported and washed grades.

HYDRO & RESERVOIR

8Hydro Reservoir Bulletin for 21 June logs levels and output from Balimela and other stations amid pre-monsoon draw
The 21 June 2026 Reservoir Generation Report tabulates full-reservoir and minimum-draw-down levels, present versus previous-day storage, average generation in MW, equivalent energy in MU, peak output and water utilised for stations including Balimela HEP. The data tracks how much dispatchable hydro headroom remains before the monsoon refills reservoirs — a key swing factor in balancing the grid during the current high-demand period.

E-AUCTION & PRICING

8Rajasthan's 22-28 June merit order spans Rs 4.72/kWh coal to Rs 27.78/kWh gas, guiding cheapest-first despatch
Rajasthan Urja Vikas and IT Services Limited's Merit Order Dispatch list for 22-28 June 2026 ranks stations by delivered tariff inclusive of all-India transmission losses, from costly liquid-fuel and gas plants such as Dadri LIQ at Rs 27.78/kWh and Anta CRF at Rs 23.17/kWh down to economical coal stations like KTPS Units 1-7 at Rs 4.72/kWh and STPS Units 1-6 at Rs 5.12/kWh. The ranking dictates which contracted plants the State draws on first, directly influencing power-purchase cost for Rajasthan's discoms.

8MSPGCL publishes June merit-order variable charges, effective 16 June to 15 July, under State Grid Code
MSPGCL released its Merit Order Dispatch (MoD) stack of variable charges for June 2026, effective 16 June to 15 July 2026 and prepared under Clause 33 of the Maharashtra State Grid Code Regulation 2020. The discom-wise ranking of generating stations by ascending variable cost determines the despatch order across Maharashtra's fleet and shapes the energy cost ultimately recovered from distribution licensees across the State.
Details
PEAK DEMAND & POWER SUPPLY POSITION

8India's peak demand hits 250,554 MW at 14:58 on 22 June with zero shortage; grid meets 5,626 MU in a day — NLDC
Grid-India's National Load Despatch Centre reported an all-India maximum demand met of 250,554 MW (on SCADA) at 14:58 on 22 June 2026, with the 20:00 evening peak across regions totalling 242,748 MW and no unserved demand. Region-wise energy met was 1,894 MU in the North, 1,731 MU in the West, 1,286 MU in the South, 649 MU in the East and 66 MU in the North-East — an all-India total of 5,626 MU, with frequency hugging 50 Hz through the day.

8Northern Region tops 85,350 MW evening peak on 22 June with no shortage; day energy reaches 1,894 MU — NRLDC
Grid-India's Northern Regional Load Despatch Centre reported an evening-peak demand met of 85,350 MW at 20:00 and an off-peak of 74,571 MW at 03:00 on 22 June 2026, both fully served, with day energy of 1,894 MU and frequency between 50.034 and 50.045 Hz. As the country's largest demand region heading into peak summer, the North's shortage-free day underscores adequate availability across its constituent states.

8Western Region meets 70,848 MW evening peak and 1,731 MU on 22 June as WRLDC logs day's generation and line outages
The Western Regional Load Despatch Centre's daily operation report shows the West meeting a 20:00 evening peak of 70,848 MW (76,629 MW at its SCADA maximum) and day energy of 1,731 MU on 22 June 2026, the second-largest regional block after the North. Accompanying WRLDC generation-outage and line-outage registers catalogue the units and transmission elements out of service that day, forming the granular backdrop to the region's supply-demand balance.

8Southern Region serves 53,927 MW peak and 1,286 MU on 22 June with frequency steady at 50.05 Hz — SRLDC
Grid-India's Southern Regional Load Despatch Centre reported an evening-peak demand met of 53,927 MW and an off-peak of 44,801 MW on 22 June 2026, both with zero shortage and frequency at 50.05 Hz, for day energy of 1,286 MU. Within the region, state demand-met peaks included roughly 18,016 MW in Andhra Pradesh, 11,503 MW in Karnataka and 9,358 MW in Telangana, illustrating the South's balanced summer supply.

8Eastern Region holds 29,011 MW peak on 22 June; day-ahead forecast error runs 6.56% as GMR unit stays in overhaul — ERLDC
The Eastern Regional Load Despatch Centre reported the East meeting a 29,011 MW evening peak and 26,788 MW off-peak on 22 June 2026 with day energy of 649 MU and no shortage. Supporting reports show a 350 MW GMR coal unit in Odisha under annual overhauling from 21 June, a day-ahead demand-forecast MAPE of 6.56% (RMSE 7.47%) improving to 1.41% intraday, and 400 kV substation voltage-deviation tracking.

8North Eastern Region peaks at 3,612 MW on 22 June; NERLDC tracks frequency deviation, TTC breaches and 400 kV voltages
Grid-India's North Eastern Regional Load Despatch Centre reported the region meeting a modest 3,612 MW evening peak and 2,302 MW off-peak on 22 June 2026 with day energy of 66 MU, frequency near 50.03-50.04 Hz and no shortage. Companion NERLDC reports for 21 June cover the daily frequency-deviation index, total-transfer-capability violation reporting and the voltage-deviation profile of 400 kV substations — the reliability diagnostics for India's smallest demand region.

FREQUENCY & DEVIATION INDICES (FDI/VDI)

8All-India grid frequency stays inside the band on 22 June, peaking at 50.25 Hz as angular spread holds stable
The NLDC frequency profile for 22 June 2026 shows the all-India grid frequency contained within the 49.90-50.05 Hz operating band for most of the day with a maximum around 50.25 Hz, while the companion All-India Angular Spread report maps phase-angle separations referenced to Vindhyachal across nodes from Alipurduar to Thrissur. Together the metrics gauge how tightly the synchronous grid held together — a core indicator of system security during peak summer.

8Southern grid holds 50.019 Hz average on 22 June with Frequency Deviation Index of 0.032; SRLDC publishes drawal and next-day forecast
SRLDC's frequency report for 22 June 2026 shows the southern grid averaging 50.019 Hz with a standard deviation of 0.057, a Frequency Deviation Index of 0.032 and a peak of 50.253 Hz at 18:03, staying within the IEGC band 99.5% of the time. Accompanying schedule-versus-drawal charts for Andhra Pradesh, Karnataka, Kerala and Puducherry, the SR demand forecast for 23 June, and the consolidated daily system-operation workbooks round out the region's performance record.

8NERLDC's May frequency-response scorecard: Bongaigaon tops at 1.00, Subansiri Lower 0.85, several hydro stations at zero
The North Eastern Regional frequency-response performance report (Beta) for May 2026 rated Bongaigaon TPP a perfect 1.00, Subansiri Lower HEP 0.85, Panyor HEP 0.81 and Kameng HEP 0.68, while Doyang, Kopili and Pare hydro stations registered 0.00. The Beta metric gauges how effectively each station arrests grid-frequency excursions, feeding into ancillary-service obligations and incentives in the North East.

SYSTEM RELIABILITY & SECURITY

8NLDC flags ER-NR corridor ATC breaches in 14 blocks on 22 June, while all other inter-regional links stay clean
Grid-India's national System Reliability Indices report for 22 June 2026 recorded available transfer capability (ATC) violations only on the East-to-North corridor — 14 time blocks, or 3.50% of blocks and 14.58% of hours — with the WR-NR, NR-import, NEW-SR and NER-import corridors logging zero violations. The metric tracks how often scheduled flows strained corridor limits, a flag for transmission congestion that can constrain cheaper power reaching deficit zones.

8WRLDC's daily reliability report tracks state-wise ATC violations across the Western grid for 22 June
The Western Regional Load Despatch Centre's daily System Reliability Indices report for 22 June 2026 tabulates, state by state, the percentage of time available transfer capability was violated, along with the number of blocks and hours affected. The index is an early-warning gauge of intra-regional congestion that can force costlier despatch within the western states and trigger higher exchange prices for buyers in the region.

815th ISTS Licensee Meeting scrutinises April tripping of POWERGRID and private transmission assets in Western Region
Papers for the 15th ISTS Licensee Meeting — held on 28 May 2026 and minuted with a full attendance annexure spanning WRPC, POWERGRID, WRLDC and IndiGrid officials — cover action-taken reports, scrutiny of PGCIL and ISTS-licensee tripping for April 2026, monitoring of Western Region inter-state transmission projects, and insulator-replacement plans. The forum is a key reliability check on the private and public transmission licensees underpinning the western grid.

LOAD FORECAST

8NLDC issues all-India day-ahead demand forecast under IEGC Article 31.2(i) for 22 June operations
The National Load Despatch Centre circulated its daily all-India demand forecast on 22 June 2026 as mandated by Article 31.2(i) of the Indian Electricity Grid Code, 2023. The projection anchors generators' scheduling and inter-regional power flows, letting utilities line up generation and avoid shortfalls during the high-demand window as the grid handles summer peak conditions across all five regions.

TRANSMISSION CAPACITY (TTC/ATC)

8Grid-India's planned-shutdown register lists transmission elements taken out for maintenance on 22 June
Grid-India published its Planned Shutdown Report for 22 June 2026, enumerating the transmission elements scheduled out of service for maintenance and the windows involved. Coordinated planned outages let utilities maintain ageing lines and substations without compromising security, but they also tighten transfer margins that the system operator must manage around peak demand with 250,554 MW met on the same day.

LINE & GENERATION OUTAGES

8SRLDC's 22 June outage registers flag Vijayawada ICT-2 trip and idle Ramagundam-Telangana lines among forced and planned outages
The Southern Regional Load Despatch Centre's transmission and unit-outage reports for 22 June 2026 record forced outages — including the 400/220 kV Vijayawada ICT-2 transformer that tripped on a bushing failure and revived at 13:32 — alongside planned outages including idle-charged 400 kV Ramagundam-Telangana STPP lines, and generating-unit outages like Lanco Kondapalli (LKPPL) and Neyveli units under no-schedule or reserve shutdown.

OCC MEETINGS & OUTAGE PLANNING

8NLDC's Security-Constrained Despatch commits Talcher, Sipat, LARA and Korba units for 23 June at ECRs from 130 paise/kWh
Grid-India's Security Constrained Unit Commitment schedule, published on 22 June for the 23 June operating day, directed specific central-sector units to run on reliability grounds — including Talcher (501.96 MW, ECR 130.4 paise/kWh), Sipat STPS Stage-2, LARA (785.45 MW), Korba Stage-3 and multiple Vindhyachal stages — while the daily Ancillary Services and SCUC report tracked the up- and down-spinning reserve profile. The commitments show how the system operator keeps reserves and must-run capacity in place to secure the grid.

REGIONAL ENERGY ACCOUNT (REA/REMC)

8NERPC reactive-energy settlement: Ranganadi to receive Rs 4.60 lakh, Palatana Rs 3.22 lakh for first June week
The North Eastern Regional Power Committee's Reactive Energy (VArH) Charge Statement for 1-7 June 2026 details payments to and from the VAr pool: Ranganadi is receivable Rs 4,60,195 and Palatana Rs 3,22,183, while AGBPP is payable Rs 53,026 and Nagaland Rs 13,476. The weekly accounting prices voltage-support service across the region's generators and states, underpinning ancillary-service incentives in the North East.

8NERPC SCUC account shows BGTPP owed Rs 1.05 crore refund as security-constrained dispatch reshapes June schedules
The NERPC Security Constrained Unit Commitment (SCUC) weekly statement for 1-7 June 2026 records net charges and refunds where actual dispatch deviated from schedule: BGTPP is set for a net refund of about Rs 1.05 crore on decremented generation, while AGTCCPP carries a net payable of around Rs 55.26 lakh on incremental output. The settlement quantifies the cost of running units out of merit to keep the regional grid secure.

8NERPC's secondary reserve settlement pays BGTPP Rs 24.4 lakh for 509.55 MWh of up-regulation in early June
The North Eastern Regional Power Committee's SRAS settlement for 1-7 June 2026 shows BGTPP providing net up-regulation of 509.55 MWh for total charges of Rs 24.41 lakh, against down-regulation by Loktak and Kopili, leaving a regional net of -247.20 MWh and Rs 17.79 lakh in settled charges plus incentives. The Secondary Reserve Ancillary Service accounts reveal how flexible generators are being compensated to balance the North Eastern grid in real time.

8SRLDC logs station-wise generation and reservoir levels for 22 June, with Idukki at 707 m and Bellary TPS at 1,493 MW
The Southern Regional Load Despatch Centre's generation report for 22 June 2026 details station-wise output across the southern states — including Bellary TPS net 1,493 MW (35.83 MU), Bhadradri TPS 501 MW and Jindal Simhapuri net 314 MW — alongside a reservoir report tracking hydro storage at key dams such as Idukki (707.37 m, 512.99 MU energy content), Linganamakki (532.12 m) and Kakki (947.39 m).
Details
CEA & GRID STANDARDS

8CEA tracks 43,360 MW of thermal capacity under construction across 32 supercritical projects in May status report
The Central Electricity Authority's Broad Status Report of under-construction thermal projects for May 2026 counts 32 supercritical projects (57 units) totalling 43,360 MW in the construction pipeline, of which 24 projects (44 units, 34,500 MW) use ultra-supercritical technology. The compilation excludes five stressed projects (9 units, 4,845 MW) and two on-hold TNPGCL projects — Uppur SCTPP (2 x 800 MW) and Ennore Expansion TPP (1 x 660 MW) — against an installed base of about 542,354 MW.

8Grid-India sets all-India ISTS transmission loss at 3.66% for 22-28 June, shaping inter-state power costs
Grid Controller of India's National Load Despatch Centre notified an all-India inter-state transmission loss of 3.66% for the week 22-28 June 2026, computed on a Monday-to-Sunday average from the previous week's scheduling and metering data under the CERC (Sharing of Inter State Transmission Charges and Losses) Regulations, 2020. The weekly loss factor directly adjusts the energy that buyers must over-inject to deliver scheduled power across regions.
Details
DAY-AHEAD MARKET (DAM/GDAM/HPDAM)

8Day-Ahead Market clears 1.14 million MWh over 16-23 June as prices spike to the Rs 10,000/MWh cap on peak blocks
The Day-Ahead Market snapshot for 16-23 June 2026 shows cleared volume of 1,142,318.49 MWh against purchase bids of about 3.61 million MWh and sell bids of 3.44 million MWh, with daily market-clearing prices ranging from Rs 4,289 to Rs 6,398/MWh (weighted Rs 3,775-4,583/MWh). On 22 June, tight supply pushed several 15-minute blocks to the Rs 10,000/MWh price ceiling, underscoring how summer peak demand is straining the short-term power market.

8Green Day-Ahead Market stays active through 23 June, channelling renewable power into the short-term pool
The Green Day-Ahead Market snapshot covering the week to 23 June 2026 records continued purchase and sell bidding for renewable energy, with hourly clearing volumes and prices tracked alongside daily maxima and minima. The dedicated green segment lets buyers meet renewable-purchase obligations through the exchange, reinforcing market routes for clean power during the peak-demand window when RE is competing with conventional supply.

8High Price Day-Ahead Market clears 654.5 MWh as bids touch the Rs 20,000/MWh ceiling in late-June trading
The High Price Day-Ahead Market snapshot to 23 June 2026 shows cleared volume of 654.50 MWh with clearing prices spanning roughly Rs 15,000 to the Rs 20,000/MWh cap — the premium segment that lets generators with costly fuel recover above the standard price ceiling. Its activity signals episodes of acute scarcity pricing during the peak-demand spell, with sell-side participants leveraging the elevated ceiling to cover high variable costs.

REAL-TIME MARKET (RTM)

8Real-Time Market repeatedly hits the Rs 10,000/MWh cap through mid-June as buyers chase last-minute power
Real-Time Market data for the week to 23 June 2026 shows the segment clearing at the Rs 10,000/MWh ceiling on multiple delivery days — for instance purchase bids of 51,105 MWh on 20 June against far smaller cleared volumes — as distribution utilities turned to the 30-minute market to cover shortfalls. The persistent cap-hitting points to a market squeezed by summer load and limited sell-side liquidity in the real-time window.

TERM-AHEAD & GREEN TERM-AHEAD (TAM/GTAM)

8IEX Term-Ahead and Green Term-Ahead desks book bilateral blocks on 22 June, with green contracts near Rs 2,920/MWh
Trade data from the Indian Energy Exchange for 22 June 2026 shows activity in the Term-Ahead Market (TAM) and Green Term-Ahead Market (GTAM), with daily and weekly delivery contracts changing hands — green day-ahead-contingency trades clearing around Rs 2,920/MWh and term contracts logged at price points up to Rs 10,000/MWh. The term desks let participants lock supply and prices days to weeks ahead, complementing the spot markets during the demand peak.

ANCILLARY & INTRADAY (ASDAM/IDAS/SCUC)

8PXIL's intra-day, DSM and ancillary segments see thin-to-nil clearing across mid-to-late June
Power Exchange India Limited's reports for the period to 23 June 2026 show subdued activity in its shorter-horizon and ancillary segments: the Intra-Day (IDAS) market logged scattered, largely uncleared bids such as 6,125 MWh on 20 June, the DSM report showed nil clearing for 22 June, and the Tertiary Reserve Ancillary (TRAS/ASDAM) segment recorded zero cleared volume from 14 to 23 June. The pattern shows liquidity concentrating in day-ahead and real-time markets while ancillary clearing stayed dormant on the platform.

EXCHANGE AUCTIONS & CIRCULARS

8Hindustan Power Exchange opens five reverse auctions on 22 June; Rajasthan seeks thermal power, West Bengal buys solar
The Hindustan Power Exchange (HPX) published five single-side reverse-auction circulars on 22 June 2026 (auction numbers HPX/22062026/01028 through 01032). Rajasthan Urja Vikas and IT Services Limited floated four auctions to procure thermal energy, while West Bengal State Electricity Distribution Company sought solar power in the fifth. The back-to-back tenders illustrate how state utilities are leaning on exchange-based competitive auctions to cover summer demand and renewable-purchase obligations.
Details
SOLAR POWER

8India's renewables deliver 1,025 MU in a single day; solar tops 629 MU as June tally crosses 23,000 MU — CEA
The Central Electricity Authority's Daily Renewable Generation Report for 21 June 2026 shows all-India renewable output of 1,025.05 MU for the day — solar 629.34 MU, wind 365.94 MU and biomass and other sources 29.77 MU. Cumulative June generation reached 23,219.21 MU, led by solar at 13,066.32 MU and wind at 9,564.77 MU. Pavagada (2,050 MW) produced 9.68 MU and NP Kunta (1,400 MW) 6.12 MU on the day, while RE from inter-state generating stations added 417.85 MU.

8Empower India announces push into digital solar solutions to tap India's fast-growing renewable market
Empower India Limited (BSE: 504351, scrip 'EMPOWER') issued a press release dated 22 June 2026 announcing an expansion into digital solar solutions aimed at capturing India's fast-growing renewable-energy demand. The diversification signals the listed company's intent to build a presence in the rooftop and distributed-solar value chain, positioning it to compete for commercial and residential offtake as grid-connected solar capacity scales up across the country.

POLICY & INCENTIVES

8CERC extends comment window on draft Connectivity & GNA (Fourth Amendment) Regulations in 22 June notice
In a public notice dated 22 June 2026, the Central Electricity Regulatory Commission extended the last date for stakeholder comments on the draft CERC (Connectivity and General Network Access to the inter-state Transmission System) (Fourth Amendment) Regulations, 2024. The move responds to stakeholder requests and keeps open a rule-making exercise that governs how generators and consumers secure access to the inter-state grid — a foundational framework for new RE capacity addition.

8OERC pre-publishes draft Transmission Tariff Regulations 2026, extends stakeholder comment deadline to 23 June
The Odisha Electricity Regulatory Commission, exercising powers under Section 181 of the Electricity Act, 2003, has pre-published the draft OERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2026 and, via a notice dated 20 June 2026, extended the deadline for public and stakeholder suggestions from 30 May to 23 June 2026. The finalised framework will set how transmission charges are computed in the State over the coming control period.

8JERC for Goa & UTs floats draft transmission-licence conditions for UT Engineering-Department electricity wings
The Joint Electricity Regulatory Commission for Goa and Union Territories issued, under Section 181 of the Electricity Act, 2003, a draft regulation prescribing specific conditions of transmission licence applicable to the Electricity Wing of the Engineering Department of Union Territories. The notice formalises licensing obligations for UT-run transmission utilities, setting out conditions that shape how these agencies plan, build and recover costs for their transmission networks.
Details
 1 2 3 >  Last ›

Showing 1–50 of 285 items