All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Sep 2026
KSEBL Vengallur 220/110 kV GIS package stretches bidding by 40 days while hybrid GIS experience stays excluded
8Kerala State Electricity Board Limited has shifted the Rs 106.64 crore TransGrid 2.0 EPC deadline three times, with bids now due on 26 September 2026.
8Beneath the schedule relief sits a heavier post-award burden of 10% performance security, a 2% OEM guarantee and a 60-month defect-liability tail.
DVC remote-operation TAMS tender cuts execution from 18 to 12 months as Rs 98.81 crore package takes a two-week extension
8Damodar Valley Corporation has moved bid submission for its centralised transmission asset management system to 23 September 2026 after four corrigenda, including a full technical-volume replacement.
8The sharper question is how integrators will price a 10-substation rollout that must scale to 90 substations across a seven-year lifecycle.
NTPC REL 672 MW Solapur wind turbine tender drifts 520 days past its first deadline after 21 corrigenda
8NTPC Renewable Energy Limited now expects bids for 224 turbines on 9 October 2026, against an original May 2025 submission date.
8The RLMM-to-ALMM (Wind) transition and a Rs 50 crore bid security raise questions over how many bidders can still sustain the chase.
AEGCL Umrangshu Rs 554 crore term-loan EOI strips land from mortgage security before granting lenders 14 more days
8Assam Electricity Grid Corporation Limited has shifted proposals for its 400/132 kV substation financing to 28 September 2026 following Corrigendum-I.
8With fee waivers, a fixed 15-year spread and no prepayment charges, the true cost of narrower collateral may surface through covenants rather than rates.
NTPC Telangana 0.5 MMT coal bid carries a GeM-versus-contract split on performance security and quantity flexibility
8The GeM summary marks ePBG as not required, while ITB Clause 22.0 imposes a 5% performance bank guarantee within 28 days of award.
8Sequential station-wise price opening and a near-total write-off below 2,200 Kcal/Kg turn the contest into a test of delivered-quality control.
WBSEDCL Alipurduar Rs 125.33 crore underground cabling tender couples supply and erection through cross-fall LD
8West Bengal State Electricity Distribution Company Limited has set 28 October 2026 as the bid deadline for converting the town's overhead network under SASCI.
8Selective IEEMA protection leaves civil works, reinstatement and logistics firm, raising the stakes of urban-interface pricing.
NTPC Simhadri coal tender retains 16 September deadline as C4 corrigendum labels itself Corrigendum-2
8Two superseding corrigenda have replaced every buyer-added term on the 500,000 MT GeM bid while shifting the operative amendments into linked documents.
8Overlapping 25% and ±20% quantity controls and conflicting payment timelines leave bidders reconciling document hierarchy before pricing coal.
UJVN Muwani 15 MW small hydro BOOT tender opens with a one-day conflict between portal and NIT deadlines
8The tender portal shows 5 October 2026 as the closing date, while the NIT fixes bid submission at 1500 hours on 6 October.
8Beyond that procedural gap, the conditional DPR obligation leaves developers uncertain whether they inherit early-stage study risk as well.
PTCUL Kumaon Package-2 bundles five 80 MVA transformers across four live substations on one 18-month clock
8Power Transmission Corporation of Uttarakhand has scheduled bid submission from 7 October to 19 October 2026, with an EMD of Rs 1.27 crore.
8No idling compensation, a five-year transformer security tail and a bar on transport claims point to a narrow field of balance-sheet-strong EPC players.
WAPCOS Hasdeo Bango-Rouni geophysical survey tender runs a seven-day window with back-to-back payment exposure
8WAPCOS Limited has invited shortlisted firms to bid by 22 September 2026 for 11,385 m of SRT and ERT investigations at two Chhattisgarh pumped-storage sites.
8Conflicting opening dates, quantity limits and payment terms across GeM and the contract could turn a technical survey into a precedence dispute.
TNPGCL Udangudi fly-ash auction sets a Rs 737/MT floor across five parallel lots totalling 10.9 lakh MT a year
8Tamil Nadu Power Generation Corporation Limited will open technical bids on 17 October 2026 for its two-year forward e-auction, implying a Rs 160.78 crore reserve value.
8Missing lifting KPIs, outage relief and silo-allocation rules, together with stray civil-work entries in the BOQ, leave bidders pricing evacuation risk blind.
WBSEDCL five-town Rs 638.42 crore underground cabling programme launches amid conflicting NIT and pre-bid dates
8Packages covering Contai, Egra-Nandigram, Jalpaiguri, Balurghat and Suri share a 28 October 2026 bid deadline and aggregate EMD of Rs 12.77 crore.
8The pre-bid meeting appears as both 24 and 28 September, while cumulative qualification tests make multi-package bidding capital-intensive.
TNPDCL 3,500-unit transformer rate contract allows an L1 new entrant to take the entire quantity
8Tamil Nadu Power Distribution Corporation Limited will close bids for 100 kVA, 22 kV/433 V copper-wound transformers on 14 October 2026, with an EMD of Rs 1.75 crore.
8Waived experience and turnover criteria widen access, but a 60-month guarantee, lot-level rejection and no arbitration concentrate risk on the winner.
NTPC REL 215 MW Madhya Pradesh wind tender closes document procurement three days before its pre-bid meeting
8NTPC Renewable Energy Limited has set a Rs 20 crore EMD and a 9 October 2026 bid deadline under an undefined "Premium" bidding system.
8With the evaluation mechanism marked "Not Applicable," bidders must commit substantial security before knowing how offers will be ranked.
WAPCOS asks next SAP integrator to take over earlier ERP at risk and cost in Rs 19.5-crore fixed-price bid
8WAPCOS's S/4HANA, Ariba and SuccessFactors programme for WAPCOS and NPCC combines unlimited licences, a T+15 takeover of the previous contractor's work and a 240-day go-live into one total-value contest.
8The deeper question is how SAP Platinum and CMMI Level V bidders will price inherited technical debt the tender never discloses, while 45-day payment terms and mediation-first disputes squeeze their cash.
NTPC opens three entry routes for Telangana Stage-II chimneys but secures consortium interfaces with an extra 2% guarantee
8NTPC's Rs 156.22-crore chimney package for the 3x800 MW Telangana STPP admits direct specialists, collaborator-backed civil majors and two-member consortiums, but bars any partner from supporting a rival bid.
8The real test is whether a separately secured integration guarantee and lead-partner joint liability make scarce chimney specialists the decisive currency of this contest.
NTPC Unchahar switchgear bidders inherit brownfield survey risk as legacy GA drawings go missing
8NTPC's stage-I LT switchgear replacement across 17 boards and 28 panels excludes Ethernet and bus trunking but keeps structural supports and chequered plates firmly in vendor scope.
8With the old GA drawings unavailable and the HMI, site HV test and e-BG instructions unresolved, the sharper question is how consistently evaluators will apply clarifications that answered by cross-reference rather than a clear yes or no.
NHPC turns Rs 106.72-crore runner refurbishment into a no-commitment capacity option across ten hydro stations
8NHPC's 36-month rate contract fixes HP-HVOF coating, 3D scanning and weight-based repair rates from Salal to Dhauliganga, yet guarantees no call-off and can be foreclosed without reasons.
8The harder question is how specialists will price frozen transport and scanning rates, a 5% arbitration cash deposit and a technical-opening date that reads 28 November in the NIT but 28 October on the portal.
UPPTCL widens Mirzapur 765 kV EPC gate to 400 kV credentials while tightening the cashflow corridor
8UPPTCL's Rs 500.93-crore package for the Mirzapur pooling substation and Bara bays now accepts 400 kV AIS experience and LLP bidders, after four extensions pushed the deadline out by 73 days.
8The sharper question is whether benchmark-capped Stage-I payments, whole-project Stage-II gates and a deleted oil-filtration line still live in the BOQ will load risk premiums into prices.
RVPN's Rs 208.8-crore Panther conductor rate contract lets L1 win on price but lose volume
8RVPN's two-year procurement of 6,020 km of ACSR Panther guarantees no minimum offtake, and Amendment 3 can cut an outside-Rajasthan L1's initial share to 20% while local suppliers are invited to match its price.
8The deeper question is whether bidders will chase a clearing price they may never convert into orders, with a "54+7" versus "30+7" drafting conflict sitting inside the PQR.
NTPC's Telangana chimney terms pair uncapped escalation with open-ended security powers
8The detailed bidding documents for the 275-metre Telangana STPP Stage-II chimneys add uncapped price adjustment, LD of Rs 19.53 lakh per week per milestone and a BOQ spreadsheet that overrides the price schedule.
8The sharper question is whether a duplicated ITB 27.5, one version of which grants an undefined discretionary right to demand additional security, will erode the contingency relief that escalation protection was meant to deliver.
DVC concedes on GIS class and transformer escalation after 68-day DTPS switchyard delay but keeps civil quantity risk
8Across seven extensions, DVC's Rs 133.63-crore DTPS switchyard modernisation moved the 33 kV GIS to LSC 2A-PM, removed the escalation ceiling on power and auxiliary transformers and floated a 21-month schedule.
8The real question is whether indicative civil quantities, a 92-month security tenor and conflicting 360-day, 18-month and 21-month durations will be priced conservatively or left to post-award claims.
Madhya Pradesh's Kukshi–Alirajpur TBCB ties transmission revenue to a single commissioning chain
8REC PDCL's 35-year BOOT concession for new substations at Kukshi and Alirajpur makes Alirajpur tariff dependent on Kukshi commissioning, and the TSP must fund design and O&M for bays at MPPTCL and Ambaja.
8The deeper question is how reverse-auction bidders will price Rs 40.11 crore of securities, an undisclosed SPV acquisition price and an SPA indemnity covering historical third-party claims.
WBSETCL grants 60 more days on 315 MVA transformers but holds its 12% escalation cap under reverse auction
8WBSETCL has stretched delivery of two 400/220/33 kV auto transformers to 360 and 420 days and named four tentative substations after Toshiba and BHEL challenged the lead times.
8The sharper question is whether H1-elimination bidding, a fixed-rate 50% repeat-order option and a 60-month defect-liability period leave enough contingency for commodity volatility the owner refused to share.
TPTL rewrites 132 kV LILO tender into a CFC-only HTLS contest with lifecycle-loss loading
8TPTL's Rs 18.38-crore Surjamaninagar–Bodhjungnagar package now prescribes a hybrid carbon-and-glass-fibre composite core rated at 800 A and loads ohmic losses at Rs 3,30,220 per kW.
8The real test is whether a loss-formula length that doesn't reconcile with the BOQ, conflicting sag and shutdown wording and a retreat from technology-neutral eligibility invite evaluation challenges.
EPI pushes Mormugao cruise terminal completion onto the contractor's balance sheet with pay-when-paid terms
8EPI's Rs 82.07-crore balance-work tender for Mormugao Port removes mobilisation and secured advances, ties RA payments to MPA receipts and demands Building No. 1 be operational within six months of a 15-month term.
8The harder question is how bidders will price client-valued inherited inventory, CRZ uncertainty and contractor-funded TPQA after three extensions left the risk architecture intact.
RVUN extends Rs 358-crore LSHS tender by 42 days without touching its refiner-only gate
8RVUN's one-year rate contract for 37,600 MT of LSHS across six Rajasthan thermal stations evaluates L1 plant-wise on landed rail price, with a fixed differential against IOCL's ex-Panipat benchmark.
8The sharper question is whether three postponements signal a thin refinery field resisting full-value turnover tests, 50% quantity swings and diversion rights that the corrigenda left untouched.
Addendum-VI reverses Zone VI error and switches Sirkari Bhyol turbine bearings to oil lubrication
8UJVNL has restored the project's IIT Roorkee-derived Zone V seismic basis after an intervening addendum wrongly cited Zone VI, and in the same document replaced water-lubricated guide bearings with babbitted oil-lubricated units with water cooling.
8The bearing change reaches cooling circuits, oil handling, monitoring and maintenance philosophy, so the harder question is how much lifetime auxiliary-system cost bidders must now carry into a 48-month fixed package.
NTPC issues second corrigendum on Simhadri 0.5 MMT coal without resolving 25% versus 10% quantity conflict
8Corrigendum C4 of 11 September supersedes C1 and the original buyer-added terms for the Rs 2 crore EMD Simhadri lot, retaining the right to move ordered quantity by up to 25% at award and again during the contract.
8Technical Specification Clause 3 still carries a plus or minus 10% station band, and with the GeM summary recording no ePBG against ITB Clause 22.0's mandatory 5% PBG, bidders must price a maximum volume and security exposure the documents do not settle.
UPPTCL deletes 'provided by UPPTCL' from transformer rows, forcing Noida GIS bidders to price erection
8Corrigendum-1 has replaced the BOQ for the Rs 112.05 crore Sector-155 substation, removing the entry that let bidders leave installation of the 160 MVA and 63 MVA owner-supplied transformers unpriced, and redefining 33 kV termination kits by interface rather than indoor or outdoor location.
8Submission moved a week to 17 September, but the real exposure is that the contractor now prices commissioning around equipment whose manufacture and delivery stay with UPPTCL, with no project-specific relief formula for late handover.
UPRVUNL converts 640 MW Rihand-Obra pumped storage from BOO to zero-consideration handover after 40 years
8The corrigendum replaces extendable BOO ownership with compulsory transfer to UPRVUNL 40 years from SCOD, in good running condition, free of liens and without transfer price or compensation, while the PBG moves to 5% of the Rs 3,953 crore estimate at Rs 197.65 crore and stays live until 12 months after actual commissioning.
8With nine extensions pushing bids to 12 October and forfeiture possible where the developer's own DPR finds the project infeasible, the test is how banks price terminal transfer beside pre-construction feasibility risk.
OPTCL opens Rs 301 crore HTLS reconductoring with two different estimates in its own records
8The Meramundali–Mendhasal package requires dismantling twin AAAC Moose and stringing twin HTLS on the live 400 kV double-circuit line, plus equipment and bus upgrades at both grid-substation ends, with bids closing 9 October.
8The signed notice states Rs 301,22,38,089 while the portal header reads Rs 3,01,26,70,182, and with outage allocation, tower adequacy and scrap responsibility all unspecified, bidders face a package whose basic commercial reference point is unreconciled.
POWERGRID ties 765kV GIS package SS 185T to a TBCB outcome bidders cannot influence
8The Orai, Patran and Agra extension package requires an exclusive MOU with the lowest evaluated qualified bidder, who receives a contract only if POWERGRID wins the upstream tariff-based bid, while exclusivity bars that bidder and connected entities from supporting rival TSPs.
8Four qualification routes admit manufacturers, collaborator and parent-backed Indian plants and EPC bidders, but with a further 10% ex-works guarantee on Routes 2 and 3 and no quantified compensation if POWERGRID loses, broad access on paper may still leave OEM gatekeeping intact.
NTPC builds six-contractor panel for Rs 300 crore Barh pond ash haulage with no purchase-order guarantee
8The 2026-27 rate contract splits work among up to six AST-01 vendors matching a single L1 price, one part reserved for an SC/ST MSE bidder, with roughly Rs 20 crore placed sequentially and Rs 50 crore as the cumulative ceiling per contractor.
8Payment follows compacted ash certified by the receiving road authority rather than trips or weighbridge tonnage, and with variation from minus 100% to plus 20%, panel entry buys eligibility rather than revenue.
GPCL risk-management RFP carries three submission deadlines and a hard copy that overrides the portal
8The ERM consultancy for GPCL's renewable, BESS, green hydrogen, mining and transmission portfolio records online closing at 18:00 on 21 September on the portal, 3 October in Chapter 1 and physical receipt on 6 October, with clause 5.3.2 giving the posted copy precedence.
8The QCBS 70:30 structure is designed to protect technical quality, but a compliant bidder could still be rejected for following one official instruction over another unless GPCL clarifies which date and channel govern.
MPPTCL bars partial bids on Rs 316 crore Sabalgarh package spanning substation, 34 km line and LILO
8TR-28/2026 bundles a new 400 kV substation, a Quad Moose double-circuit link to Morena Pooling and about 21 km of 220 kV LILO into one indivisible turnkey award, with 30-month and 24-month completion tracks and no rainy-season relief, while three 500 MVA and two 200 MVA transformers and two 125 MVAR reactors stay outside contractor supply.
8Price variation reaches only selected equipment and civil work, so reverse-auction pressure will meet a large block of fixed-price and deemed-inclusion exposure.
NTPC Lara mine-filling tender contradicts itself on diesel escalation and soil-cover thickness
8The Rs 255.06 crore package moving 20 lakh MT of ash into the Bishrampur and Dugga pits says no extra payment for fuel-rate changes at condition 2(h), then indexes 25% of contract price to diesel at Clause 14, while Scope Clause 1 fixes a 500 mm soil cap against Payment Clause 9(i)'s 300-500 mm band.
8With quantity variable from minus 100% to plus 20% across a six-way split and no order-of-precedence statement, both conflicts sit directly on the lump-sum price.
APCPL admits Talabira coal in one clause and excludes OCPL in another for 5 LMT Jhajjar buy
8The invitation for bids for the Rs 5 crore EMD package bars coal from CIL, SCCL, OCPL and NTPC group mines, while Technical Specification Clause 2 expressly permits OCPL and Talabira sources including the NLCIL captive mine.
8A second gap sits between Annexure-B1's 4,300 Kcal/kg ceiling and Clause 11's payment cap at 4,000 Kcal/kg, leaving a bidder unable to know whether its declared source qualifies or its better coal can be monetised.
MSEDCL grants nine days on Rs 97.87 crore cable tender but holds firm price against five bidders
8Shriram Cables, Torrent Electricals, Dynamic, KEI and Tirupati each sought price variation on the 33 kV and 11 kV 300 sq.mm HT XLPE package, and MSEDCL answered every request with "as per tender documents," also refusing KEI's three-month first-lot request and Tirupati's insurance surety bond proposal.
8Bidding moved from 1 September to 10 September, leaving a nine-month firm-price delivery, a 20% two-month mobilisation obligation and 1% weekly LD untouched.
OPTCL forces single award across Palaspanga and Barbil while its notice repeats the EMD as the estimate
8The Rs 315.27 crore package makes Lot-I and Lot-II one indivisible contract covering GIS at both stations, 1.2 Rkm of underground cable and roughly 69.2 Rkm of 220 kV overhead line including Twin Moose on 400 kV towers, all in 24 months.
8The opening notice states the estimate as Rs 3.15 crore, exactly the EMD figure, and Table-A carries 10 August against the portal's 11 August, leaving bidders to rely on portal precedence for basic commercial approvals.
HPPCL seeks green hydrogen offtakers for 1 MW Dabhota plant without naming volume, purity or delivery point
8The EOI sets a Rs 1 EMD, zero form fee and Rs 2,360 processing charge, with closing on 13 August and cost opening one hour later, but does not state saleable output, pressure, metering ownership, custody transfer or contract tenure.
8Classified simultaneously as procurement of services and miscellaneous works with a scheduled cost opening, the notification leaves respondents unsure whether they are quoting a purchase price, a service charge or a bundled logistics proposition.
NTPC leaves three quantity formulations live across its 2.5 MMT five-station coal package
8The Telangana lot under CS-0011-011(10)-9 now carries a plus or minus 20% variation in the revised detailed document, plus or minus 10% in the separate technical specification and a 25% GeM option clause at both order placement and during contract.
8Sequential station opening means a bidder's later price bids stay unopened once it reaches its declared Annexure-TC-10 limit, making award appetite a live competitive variable before any price is compared.
NTPC cuts Tanda coal ceiling to 3,700 Kcal/kg while lifting initial payment to 80%
8Revised Annexure-B1 pulls the GCV envelope down from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal caps of 12% and 14%, and the GCV challenge window contracts from ten working days to seven calendar days with a ±71.7 Kcal/kg admissibility threshold.
8The move from 50% to 80% initial payment is the clearest contractor gain in the package, but it arrives alongside ±20% quantity variation, station diversion rights and a source pool narrowed by the tighter specification.
Nabinagar sits last in NTPC's price-opening order, exposing it to a thinner field
8Corrigendum-1 leaves the 16 September dates unchanged for the 0.5 MMT lot and fixes the opening sequence as Telangana, Simhadri, Mouda, Tanda and Nabinagar, with bid security shown at Rs 10 crore for five stations against a visible overwritten Rs 8 crore in ITB Clause 7.1.
8Because bidders reaching their declared award ceiling drop out before later envelopes are opened, the last station in the queue may face the weakest price competition regardless of its own economics.
NHPC inserts a missing crane chapter and cuts turbine efficiency threshold to 94% at Dulhasti Stage-II
8Corrigendum No. 1 added the absent Chapter 18 covering two 190/30-tonne powerhouse cranes and three others, Corrigendum No. 5 rewrote the cooling-water and HVAC chapters and lowered the non-responsiveness threshold from 94.5% to 94%, and price-adjustment indices moved from 2011-12 to 2022-23.
8Four extensions have taken submission from 24 July to 28 September on the Rs 496.90 crore package, yet unit commissioning stays fixed at months 43 and 44 from the civil zero date.
UJVNL lets two OEMs cover turbine and generator at Tiuni Plasu after 18 extensions
8Addendum-II moved qualification from turbine and generator to turbine "and/or" generator and deleted the contract-value experience thresholds, and Addendum-VI then allowed as many as two manufacturers, with force-majeure substitution limited to BHEL, Voith Hydro, Andritz Hydro and General Electric.
8Addendum-III deleted air-gap, partial-discharge and vibration monitoring and cut excitation redundancy from n+n to n+1, so the widened front door arrives with a thinner reliability margin and a Rs 260 crore turnover test for manufacturer-backed bidders.
JERC bars consultants holding two of three earlier awards from Chandigarh STU-SLDC tariff work
8The Rs 18 lakh QCBS assignment covering business plans, MYT petitions, mid-term review and true-ups to FY 2029-30 excludes firms already awarded two of three specified JERC bids, while demanding ten years of experience, 20 assignments worth Rs 1 crore and two staff stationed at the Commission.
8Corrigendum C3 warns that a participation fee can render the bid null and void, even though the underlying RFP still requires a Rs 10,000 processing fee and advance hard copies.
SECI moves Ramagiri wind auction to cost per certified MU and drops turbine floor to 2.7 MW
8Amendment-01 rewrites ITB Clause 32.4.1 so bids rank on EBV divided by NIWE-certified ten-year P90 generation, with the denominator locked before the reverse auction and only price free to move, while the power-curve pass mark falls from 98% to 95% and the 96-hour test threshold from 98% to 96%.
8Repeated STPT failure no longer triggers WTG rejection and refund with 13% interest but a generation-linked LD at Rs 4.5 per kWh, leaving yield certification quality as commercially decisive as the EPC quote.
NPCL wants 300 MW RTC with 90% availability in six peak hours it picks day-ahead
8The 25-year BOO procurement requires a declared annual CUF of at least 75% held within plus or minus 10%, 50% of contracted capacity in every off-peak 15-minute block and 90% across six peak hours selected by NPCL on a day-ahead basis, with shortfall damages at 1.5 times tariff.
8Configuration and delivery points may change until financial closure but bring no SCSD relief, so the 24-month schedule and daily PBG encashment will likely surface as a firmness premium in the discovered tariff.
NTPC narrows Mouda coal window to 3,700 Kcal/kg as second corrigendum lands five days before bids close
8Corrigendum C4 of 11 September supersedes C1 for the 5 lakh MT package, while the revised document cuts maximum GCV from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal 12% and 14% caps, and moves payment from 50:40:10 to 80:10:10 with sampling charges down to Rs 2.97 per MT.
8GeM records no ePBG and no arbitration against Clause 22.0's 5% security and a Delhi-seated GCC arbitration, leaving document precedence to carry more commercial weight than the headline tonnage.
Odisha Coal and Power Limited caps Tangardihi North's exploration phase at Rs 25 crore and ranks bidders on 397 million tonnes
8A Phase I quotation above the ceiling is reduced to Rs 25 crore rather than improving the evaluated position, while the Base Mining Charge is multiplied across a comparison quantity that detailed drilling has yet to confirm.
8Around 14,000 metres of exploration sits inside the same contract whose 25-year operating commitment depends on what that drilling finds.
WAPCOS gives three masked bidders ten days to respond to a five-year strategy mandate classified as an emergency
8The Rs 1.50 crore QCBS assignment weights technique at 80%, with 60 of 100 technical marks resting on named expert CVs and a presentation.
8Arbitration and consensual ADR are excluded entirely, leaving employer-controlled internal review, mediation and Delhi civil courts as the dispute route.
Gujarat Energy Transmission Corporation Limited's Navsari cable tender lists 193,186 metres of 66 kV cable against a 24,218-metre route survey
8The Rs 98.48 crore item-rate package also carries six foundation categories each showing eight tower foundations while the total tower-erection quantity is also eight, leaving the BOQ open to interpretation before pricing.
8Amendment no. 1 moves delay damages from the delayed portion to 0.5% of the entire contract price per week, capped at 10%, or roughly Rs 9.85 crore plus GST.
Maharashtra State Electricity Transmission Company Limited puts a Rs 73.19 lakh breaker overhaul across 12 substations without a breaker count
8The notice covers spares supply and complete mechanism overhauling of CGL-make 132 kV breakers at sites spanning both 132 kV and 220 kV yards.
8Mechanism types, spare schedules, outage duration, testing protocol, warranty and completion period are not specified in the document, leaving the estimate impossible to test against actual scope.
NTPC Renewable's 600 MW Anantapur wind tender gives bidders a week more to price but no way to ask why
8Corrigendum No. 1 pushed submission to 22 September 2026 while leaving the 1 September query deadline untouched, so late-discovered ambiguity has nowhere formal to go.
8With Rs 50 crore bid security, ten-year comprehensive O&M and roads, pooling and evacuation all outside the WTG package, the unresolved issue is who carries commissioning delay at the boundary.
JdVVNL rewrites the BOQ a third time and swaps Bikaner territories between two RDSS packages
8Corrigendum 3 moved Dungargarh and Nokha into TNTW-796 while DD-I, DD-II and Khajuwala travelled the other way, settling the value at Rs 119.89 crore — a net movement of about 0.1%.
8That small headline change can conceal much larger line-item additions and deletions, which is precisely what bidders repeatedly queried before the revision.
AEGCL's Khumtai 400kV GIS tender carries a Rs 50 lakh EMD contradiction and a 12-month schedule gap
8The invitation and ITB 2.37.1 set two years for completion while SCC 8.2 requires 36 months, and the EMD reads Rs 5.5 crore in numerals against "Rupees Five Crore only" in words.
8Turnover and financial-resource thresholds carry the same numeral-versus-wording conflict, making eligibility itself uncertain before the 12 October closing.
GETCO's Viksit Gujarat @2047 adviser tender records two turnover thresholds twenty times apart
8The GeM page states Rs 48 crore while the RFP and buyer-added conditions demand Rs 1,000 crore, and submission and opening dates differ by a day between portal and document.
8With GST treatment also contradicted between two clauses, the tender risks producing technically incomparable bids priced on different assumptions.
GETCO's Rs 210.62 crore Bharuch cable package lets each approved OEM back only one bid
8Amendment-I restructured qualification into OEM, nominated-OEM and two-member JV routes, then barred any firm from appearing in different roles across competing bids.
8The contest may therefore be settled by early OEM alignment rather than by how many erection contractors can qualify.
KPTCL's Rs 131.92 crore Byadagi package reaches the market tagged as a computer lab
8The portal lists bid validity as 90 days against the signed document's 180, describes the scope as "Setting up of Computer Lab", and keeps the clarification window open 30 minutes after bids close.
8A Clause 3.2(e) heading referring to a 100 MVA transformer against a 160 MVA requirement compounds the risk of divergent qualification readings.
RRVUN cuts the coal experience bar by 6.25% and then quietly extends group credentials to technical qualification
8Amendment-I lowered the single-contract threshold from 1 million MT to 9,37,500 MT and admitted IPP supplies; Corrigendum-I then widened 100%-owned parent or subsidiary reliance from financial to both technical and financial PQR.
8JV and consortium participation stays barred, so the widening favours tightly held corporate groups rather than assembled bidding alliances.
WBSETCL's Sadarghat composite package republishes its evaluation clause with a broken cross-reference
8Amended ITB 28.2 now reads "DP = Differential price calculated according to0", severing the link to the calculation method in ITB 28.4, while the reverse-auction cross-reference disappears entirely.
8Reverse-auction clause 9 separately dispenses with additional security where L1 is "less than 20% of the estimated cost" — a literal reading that relaxes protection at the lowest prices.
NHPC raises generator efficiency loading 20.6% on the Rs 641.11 crore Uri-I Stage-II package
8The turbine equalisation rate moved from Rs 8.32 lakh to Rs 8.74 lakh per 0.1 percentage point, while the generator rate jumped from Rs 21.64 lakh to Rs 26.10 lakh.
8Cheaper machines with weaker guarantees can now lose their price advantage at evaluation, even before PLCC relocation and revised cooling-water scope are priced.
WBSETCL's 68 km Salboni 400 kV line tender resolves a 60 mm creepage conflict but keeps ROW with the contractor
8The pre-bid response directed bidders to the technical specification's 430 mm over the BOQ's 370 mm and issued a revised BOQ, while fixing conductor diameter at 28.62 mm and sag at 15.93 m.
8Tower-footing compensation, trees, crops and access remain contractor-priced with no escalation for court-driven delay, and the 24-month clock survives two extensions.
RRECL's 201 MW solar tender slips 63 days and then adds a letter of credit
8Four corrigenda moved submission from 14 July to 15 September 2026 while the nine-month commissioning obligation and 25-year term stayed fixed.
8The pre-bid addendum inserted a revolving monthly LC and replaced the client's first charge over liquidated assets with priority application of proceeds — a lender accommodation whose value depends on the still-ambiguous "Cover-1 & Cover-2" opening language.
HPSEBL extends its Rs 3.72 crore Kinnaur-Spiti PMC tender for the fifth time without explaining why
8Corrigenda I to V added 64 calendar days to both submission and technical opening while leaving scope, staffing, securities and the 246 man-month deployment untouched.
8The unresolved question is award mechanics: a 70:30 QCBS formula and an English e-reverse auction sit in the same document with no stated hierarchy.
GETCO shifts LD on the Rs 224.80 crore Dholera-II GIS package from the delayed portion to the whole contract
8SCC clause 41 now calculates 0.5% per week on the full contract price capped at 10%, recoverable across GUVNL group contracts, while requests to extend 30 months to 34 and to substitute PEB for RCC were refused.
8A local civil or commissioning slip can now generate package-wide exposure on a site carrying saline conditions, seismic zone 5 and cast-in-situ piling.
MePDCL splits Khasi Hills into six lots and hands four of them to one contractor
8The Rs 120.42 crore award concentrates Rs 82.12 crore, or 68.2% of L1 value, with a single firm across Lots 1, 3, 5 and 6.
8Lot 3 reached financial opening with one responsive bidder out of seven, leaving no L2 comparator to test whether that price was competitive at all.
NHPC rewrites force majeure and idling-cost recovery across both its hydro E&M packages
8The revised GCC Clause 37 adds terrorism, qualifying strikes and pandemic spread while removing the magnitude-7 earthquake threshold and express treatment of bandhs, lightning and unprecedented floods.
8Annex-A now caps compensable idling through a formula using 5% of composite contract price, with a 2% sub-cap on miscellaneous establishment expenditure and extended-warranty recovery at 2.25% per annum.
RVUN's Rs 1,125 crore coal tender is tagged emergency procurement without naming which rule applies
8The portal cites Rule 40(1), 43(6) or 43(7) but does not identify the provision invoked or the factual justification, and the original window ran just seven days from publication to submission.
8Coal grade, sampling agency, delivery duration, LD framework and PBG terms are absent from the published notice, leaving the commercial risk difficult to quantify before bidding.
WBSETCL's H1-elimination auction meets a 10% security stack that runs five years past commissioning
8The Sadarghat package removes the highest offer only where four valid price bids exist, so two or three qualified bidders all proceed to the auction intact.
8The winner must then carry separate 10% guarantees on GIS equipment for three years and transformers for five from the Taking-Over Certificate, with formal joint ventures barred.
For daily newsletters and other free services, fill in your details: