All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Jul 2026

 For reference purposes the website carries here the following tenders:
 8Tender for development of railway siding for loading of pond ash Details
 8Tender for interconnection of 400kV line Details
 8Tender for supply, installation testing and commissioning of differential numeric relays at various Details
 8Tender for supply of TLSA for the transmission lines Details
 8Tender for work of 33 kV new substation Details
 8Tender for construction of 33 kV UG line Details
 8Tender for civil works for construction of 132 kV bays Details
 8Tender for selection of agency for providing application management services Details
 8Tender for procurement of spares of various rating motors HT motors Details
 8Tender for work of repairing of foundation bolts of rotary breakers Details
 8Tender for procurement of HS straight joint kit, HS outdoor and HS indoor termination kit for 11 kV 3 X 120 sqmm XLPE cable Details
 8Tender for procurement of 11 kV standalone structure materials complete set Details
 8Tender for R&M of AEP gear boxs Details
 8Tender for Package- 3 engineering procurement, supply, installation, testing & commissioning of electro- mechanical components for 640MW (8X80 MW) Details
 8Tender for work of bus strengthening from single panther conductor Details
 8Tender for procurement of non ferric alum commercial grade. Details
 8Tender for erection of 3.3kV overhead line Details
 8Tender for various pipeline related jobs (installation of pump, etc) along with associated electrical works Details
 8Tender for maintenance of 11kV, 3.3kV and 550V OH line Details
 8Tender for annual miscellaneous preparatory civil works for various Details
 8Tender for civil maintenance of ash dyke Details
 8Tender for maintenance of horticulture and landscape works Details
 8Tender for supply of R-22 refrigerant gas for AC plant system Details
 8Tender for supply of various types of clamp for 220 kV switchyard Details
 8Design, fabrication, supply, installation, testing, commissioning of ongrid solar ground mounted project with net meter and RMS capacity of 140 kW Details
 8Tender for repair of damaged platform, plinth surface, drain, railing Details
 8Tender for construction of 33kV underground line Details
 8Tender for supply of ferric alum Details
 8Tender for construction of new 33 /11 kV sub station Details
 8Tender for supply, erection, installation, testing, and commissioning of materials/equipment Details
 8Tender for supply of programmable multi function digital panel meters for switchyard and protection control panels Details
 8Tender for extension of drainage at 110kV substation Details
 8Tender for construction of 11kV new feeder from 110kV S/s Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for resurfacing of road inside substation, extension of road to 11kV yard Details
 8Tender for utility shifting of transformers and RMU Details
 8Tender for procurement of spare of mechanical seal of booster pump Details
 8Tender for procurement of carb clad/Tibo. sol coated rotary segregating valve assembly for buffer hopper Details
 8Tender for procurement of spares of DMCW (TG and SG) pumps Details
 8Tender for procurement of ABT compliant energy meters of 0.2s accuracy Details
 8Tender for procurement of spares for gas analyser Details
 8Tender for renewal and replacement of damaged water supply/sanitary paint electrical wiring Details
 8Tender for procurement of special steel sail hard/TISCRAL or equipment 6mm carbon steel for gas ducts. Details
 8Tender for supply and delivery of 61 Nos. guide vane seal Details
 8Tender for procurement of 4-inch PRV for unit 5 conveying line Details
 8Tender for biennial maintenance work of of water distribution line Details
 8Tender for biennial maintenance contract for electrical maintenance including illumination system Details
 8Tender for biennial maintenance contract for overall illumination maintenance jobs Details
 8Tender for procurement of electrical spare parts items Details
 8Tender for replacement of existing 11 kV ACSR conductor with 11 kV Dog conductor Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for laying, erection, testing and commissioning of 132kV 1Cx800 sq.mm XLPE cable Details
 8Tender for Bi-annual contract for work of loading, unloading, stacking of any material Details
 8Tender for work of erection dismantling of 132kV/66kV/11kV equipment’s, structures, control wiring Details
 8Tender for ARC for HT/LT/TC erection and maintenance works Details
 8Tender for work biannual AMC of repairing / refurbishing, servicing & overhauling of 400KV & 220kV isolator along Details
 8Tender for annual battery maintenance work at various substations Details
 8Tender for annual maintenance contract for attending emergency / breakdown / planned maintenance works of 220kV & 132kV sub stations Details
 8Tender for work of replacement of old battery set by new battery set Details
 8Tender for various regular preventative maintenance / emergency and breakdown works of various 220kV & 100kV substations Details
 8Tender for supply of spares and repairing, servicing & overhauling VCBs at various sub stations Details
 8Tender for annual maintenance contract for the work of repairing, overhauling, servicing, maintenance & alignment of 220/132/33kV isolators Details
 8Tender for dismantling of existing damaged compound wall & reconstruction of compound wall at 132kV S/Stn Details
 8Tender for supply, installation, testing & commissioning of 2 TR split type variable speed inverter Details
 8Tender for work of establishment of 220/22kV GIS substation Details
 8Tender for establishment of 220/33kV substation along Details
 8Tender for work of LILO of 220kV line Details
 8Tender for supply of various types of contactors for LTMCC of 500 MW Details
 8Design, supply, installation, commission and maintenance of solar PV system Details
 8Tender for Bi-annual rate contract for erection of 66 kV line feeder bay / transformer bay for various sub-stations Details
 8Tender for purchase, erection, including foundation of conductor/cable measuring machine Details
 8Tender for work of replacement of insulator or SRI work of attending the fault or broken conductor and/or snapping from tower/gantry Details
 8Tender for work of overhauling, oil leakage attending and testing of 100MVA, 11/230 kV generating transformer Details
 8Tender for rate contract for repairing of failed / damaged / distribution transformers Details
 8Tender for supply, of LED flood lights 240 Watts Details
 8Tender for work of removal, supply and application of spray insulation of steam turbines Details
 8Tender for supply of mill discharge first piece after MPO for coal mill Details
 8Tender for supply of tubes, end plates & baffles and work Details
 8Tender for work of preventive maintenance, shutdown & emergency maintenance of IAC/SAC compressor, air washery fan/pump motor, ACW/FCW motor Details
 8Tender for work of dismantling replacement / repairing of PF pipe, orifice & PF bend of coal mills Details
 8Tender for work of replacement of various spares of drive system of wagon tippler Details
 8Tender for work of fabrication/ removal/ repairing /erection of metallic expansion bellows at various Details
 8Tender for supply of various spares for SWAS system of boiler Details
 8Tender for supply of various instruments for CHP Details
 8Tender for supply and replacement of NDCT components for 1x 800 MW Details
 8Tender for procurement of 6.6/0.415 kV feeder protection numerical relays Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8ECL CMD calls for balanced energy transition, says coal remains key to India's energy security Details
 
88 core industries index to become 9 as government adds iron ore Details
 
8West Bengal Energy Transition Shapes Coal Future Details
 
8India rebases its core sector index to 2022-23 on 20 July, and the same output will print a different growth number Details
 
8Iron Ore Joins India''s Core Sector Index, Total 9 Industries Details
 
8Index of Core Industries set to get an upgrade with revised base year and weights Details
 
8India Adds 30.6 GW Renewable Energy Capacity in H1 2026, Solar Leads Growth: Pralhad Joshi Details
 
8India's renewable energy capacity additions rose 25% in H1 2026 Details
 
8India’s renewable energy sector set for ‘transformational’ growth Details
 
8Adani Group breaks into India’s Top 10 most valuable brands; Adani Power leads energy sector Details
 
8Manju Gupta: Executive Director, Power Grid Corporation of India Limited Details
 
8Industry experts flag AI skills gap in clean energy sector Details
 
8Pinarayi Vijayan warns of protests if Kerala government sets up nuclear power plant Details
 
8Unlocking Efficiency: Building a unified power market through market coupling Details
 
8Advancing India’s sustainable industrial economy through clean energy Details
 
8FM Report: Power-Generation Risks Mount as Electricity Demand Soars Details
 
8Nuclear Ambitions: Building capacity for a low-carbon future Details
 
8Aryaman Vikram Birla targets 20 GW renewable capacity in medium term; plans to back growth with battery storage Details
 
8POWERGRID Invites Bids For 250 MW/1000 MWh Battery Energy Storage System Project Across India Details
 
8India a step closer to its first demonstration-scale geothermal power project Details
 
8India to Open Thorium Sector to Private Firms Details
 
8Assam govt plans Rs 77,353 crore power push Details
 
8Sanjay Ghodawat Group and Nordstar Estates Join Forces to Power India’s High-Growth Real Estate Markets Details
 
8Laser Power & Infra secures Rs 4.15 crore HPSEBL order for HTLS conductors Details
 
8Ratul Puri on Building Integrated Energy Solutions for India’s Rising Power Demand Details
 
8NTPC Appoints Dr. Som Nath Sachdeva as Non-Official Independent Director for Three-Year Term Details
 
8Laser Power & Infra Locks in 10% Upper Circuit Again After Heavy Institutional Buying on Listing Details
 
8Walchandnagar Industries, BHEL, L&T shares in focus as NTPC-NPCIL JV floats Rs 28,000 crore tender for Rajasthan Nuclear Power Project Details
 
You can also click on Newsclips for more Details
8Day-ahead and real-time prices at fresh highs
Day-ahead cleared Rs 7,284/MWh for 17 July (Rs 7,049 for the 16th; Rs 2,490 on 12 July); real-time averaged Rs 7,723/MWh on 16 July before easing to Rs 6,911; green day-ahead firmed to Rs 7,024. Night blocks repeatedly hit the Rs 10,000 ceiling. Cleared volumes were ordinary (day-ahead 148,764 MWh for the 17th); the move is on price, driven by an evening buy-side scramble, not by volume.

8Demand near an all-time high
Maximum demand met 270,203 MW on 16 July, against the 270.8 GW national record of 21 May; energy met 6,002 MU. A monsoon peak this close to a heatwave peak is the demand signal behind the price move.

8Term-ahead and intraday markets pinned to the ceiling, clearing only in the evening
IEX term-ahead and green term-ahead contracts traded thin and mostly at the Rs 10,000 ceiling, with genuine clearing only in round-the-clock products (term-ahead round-the-clock West cleared 2,640 MWh at about Rs 7,953). The intraday segment cleared nothing all day. Real-time cleared only from about 19:30, and the PXIL deviation market only between 20:30 and 23:00 - buyers paying the ceiling, then Rs 5,500 - confirming the scarcity is a post-solar evening event.

8High-price and ancillary day-ahead segments did not clear
The high-price day-ahead market drew a sell-only book of about 72,000 MWh with no matching demand and no clearing price for a second running day; the ancillary-services day-ahead segment saw no bids and no activity all week. The unused sell-side capacity is another marker of daytime surplus.

8GUVNL floats a 400 MW reverse auction across three exchanges
Hindustan Power Exchange circular HPX_RA_01056 (16 July) sets a single-side reverse auction for Gujarat Urja Vikas Nigam - three tranches of 400 MW covering 23–31 July, August and September, ceiling Rs 10,000/MWh, energy of any type - with the e-auction on 18 July; parallel auctions run on IEX and PXIL. A large discom buying blocks two to three months out is the mirror image of the evening-peak tightness.
Details
8Frequency ran low, not high
On 16 July the frequency was inside the 49.9–50.05 Hz band 64.3 percent of the time, but it spent almost twice as long below the band (23.3 percent) as above it (12.4 percent), touching a low of 49.508 Hz at 06:18. After weeks of running high on surplus, a day that dips low points to tighter mornings and a stretched evening ramp rather than pure oversupply.

8The grid was net backing down, with costly gas left idle
Ancillary services backed generation down by a net 4,565 MWh on 16 July (31,543 down against 26,978 up), and NLDC's unit-commitment table shows eight RLNG-gas stations committed but scheduled at zero. The system was comfortable on energy through the day; see Story 1.

8A busbar-protection event at Vemagiri cost 1,400 MW for fourteen minutes
At 11:52 on 16 July a jumper cut on a 220 kV bus-coupler at Vemagiri (Andhra Pradesh) operated the busbar protection, tripping the Vemagiri transformers and then Guddigudem's on load transfer, for a load loss of about 1,400 MW; supply was restored by 12:06. A short, sharp reminder that single-point bus faults still take large blocks off instantly.

8National corridors clean, but Tripura's import path ran over its limit for nearly 20 hours
Nationally, inter-regional transfer and N-1 criteria showed zero violations on 16 July. Inside the North-East, though, the Tripura import corridor breached its available transfer capability for 19.7 hours on 15 July (82 percent of the day) and the Assam corridor for five - the chronic evacuation constraint behind the region's defence-scheme strain (see Story 4).

8A southern bus ran persistently over-voltage at Cuddapah
The 765 kV bus at Cuddapah spent 38 percent of 16 July above 800 kV, peaking at 813 kV - the day's largest voltage deviation, with smaller high-voltage excursions at Nizamabad, Maheshwaram and two Gujarat buses. Light evening loading on a high-voltage backbone with reactive support lagging; no low-voltage violations were recorded nationally.

8Weak primary frequency response from two North-East stations
NERLDC's June frequency-response scorecard rates Doyang hydro at 0.02 and Palatana gas at 0.21 on a scale to 1.0 - near-absent governor response - while Bongaigaon and Kopili scored a full 1.0. Poor primary response from large machines is what forces the ancillary market to do more of the second-by-second balancing.

8Eastern demand was chronically under-forecast
ERLDC's day-ahead load forecast for 16 July ran a mean error of 7.5 percent and under-called actual demand by up to about 3,900 MW through the midday blocks; the intraday forecast was tight at 1.4 percent. Day-ahead under-forecasting in a rising-demand month feeds straight into next-day exchange buying.

8A CT burst at Biharsharif cascaded to a 110 MW blackout when a breaker failed to open
On 26 June a current-transformer burst at Biharsharif faulted the bus, and the bus-coupler breaker's pole failed to open mechanically - so the fault spread to the second bus and cascaded to a 110 MW blackout, with the disturbance recorder found not time-synchronised. A single CT failure turning into a station blackout is exactly the latent mechanical defect a protection audit is meant to catch.

8Santaldih lost 225 MW when a bus-shift flashed over mid-operation
On 4 June a heavy flashover during a live shift of a unit from one bus to another at Santaldih operated the busbar differential and tripped the whole switchyard, losing 225 MW of generation and 92 MW of load. The committee's lesson is blunt: finish the feeder rearrangement before splitting a bus, not during it.

8Godda and Pakur lost load twice as healthy lines tripped with the faulted ones
Two events at Godda/Pakur (17 and 25 June, 168 and 216 MW of load lost) saw faults on the Madanpur lines simultaneously trip healthy parallel circuits; the Jharkhand utility must explain why an auto-reclose did not operate and segregate its special-protection outputs. Sympathetic tripping of sound lines is the signature of a protection-coordination gap.

8A Buxar transformer tripped on a setting that breaks the region's protection rule
On 11 June a Buxar transformer tripped on a standby-earth-fault element set to a fixed one-second delay rather than the eastern region's inverse-time philosophy - a settings mismatch the operator has asked the utility to correct. Small on its own, it is the kind of non-standard setting that turns an external fault into an unnecessary trip.

8Generation ran above programme on 15 July, but hydro is lagging
CEA's daily generation report puts all-India output at 5,020 MU on 15 July against a 4,485 MU programme. Year-to-date, eastern hydro is 32 percent below target and north-eastern 12 percent below, while northern nuclear runs 18 percent short - the shortfalls that a monsoon is supposed to be curing.

8Darbhanga went dark on 29 June though the fault cleared in under 100 milliseconds
At Darbhanga on 29 June a phase-to-earth fault cleared in under a tenth of a second, yet both 220 kV lines and both 400/220 kV transformers tripped together and the station went dark. The phasor records show the fault was cleared fast, so why healthy elements tripped with it is unexplained, and the two transmission utilities' reports are still awaited - the signature of a protection-logic fault rather than the fault itself.

8A north-eastern voltage problem is now spilling into Bhutan's grid
Chronic low voltage around Rangia in Assam - worse whenever a Bongaigaon–Rangia circuit is out - has Assam pulling so much power through a 132 kV tie to Motanga that it stresses the Bhutan system, whose operator has asked to open the tie from its end. The region's voltage weakness now crosses an international border, and the fix - a 400/220 kV substation at Rangia - is still pending.

8A Nagaland protection scheme keeps shedding load with no fault to answer for
Unequal loading on two parallel 132 kV lines at Dimapur keeps pushing one phase over the special-protection-scheme pickup, shedding load three times in late June and early July with no actual fault; the root cause is still not found. A defence scheme that fires on a loading imbalance is itself a reliability risk, not a safeguard.
Details
8About 44 large units are out across the north and west - yet demand was met with under 1% shortage
Roughly 44 units of 200 MW or more were out on 16 July across the Northern and Western regions - a routine mid-monsoon overhaul-and-forced tally, not a stressed one. The registers supplied cover only those two regions; eastern, southern and north-eastern unit registers were not in the day's file set (see end-note).

8A nuclear unit trips at Kakrapar on a generator-seal fault
Kakrapar-1 (KAPS-1, 220 MW, NPCIL) tripped at 10:34 on 15 July on a generator seal problem and remained out, expected back on 18 July - the fresh nuclear item of the day. Rajasthan's RAPS-A Unit-1 (100 MW) stays down on long-term decommissioning.

8Fresh forced trips on 16 July add about 2,500 MW
New forced outages, all boiler or mechanical: Jindal's JPL Stage-II Unit-1 (600 MW, Chhattisgarh) on an air-preheater gearbox fault, RKM Powergen Unit-2 (360 MW) on a boiler leak, Rosa-4 (300 MW, UP) on a boiler-tube leak, Rajwest Unit-4 (135 MW, Rajasthan), and Kota-4 (210 MW) which re-tripped at 22:59 after reviving earlier in the day; a day earlier Adani's two Raipur units (685 MW each) went out on a flame-off and a condenser leak. About 2,500 MW of fresh loss - the ordinary attrition of a monsoon fleet, not a coal or grid problem.

8More capacity came back than tripped, led by Gadarwara's 800 MW
Back on the bar overnight: NTPC's Gadarwara-1 (800 MW) - the largest single return - Adani Mundra-8 (660 MW), Bhusawal-6 (660 MW), DGEN-1 (400 MW), and JP Bina-1, Gujarat's STPS-4 and the north's Chhabra-3 (250 MW each). The returns outweighed the fresh trips, cushioning the 16 July evening peak.

8Long-standing forced outages still out, some since April
Still dark from earlier: in the north, both Ghatampur units (660 MW each, UP, coal-feeding), OBRA-C Unit-1 (660 MW), Anpara-C Unit-2 (600 MW), Harduaganj-9 (250 MW) and Ropar-3 (210 MW); in the west, Adani Tiroda-5 (660 MW), Vedanta-1 (600 MW, out since April), Chandrapur-7 (500 MW), Jaigad-1 (300 MW), LANCO-1 (300 MW), BLTPS-2 (250 MW), three Wanakbori units (210 MW each) and Sanjay Gandhi-4 (210 MW, since April). Teesta-III's 1,200 MW remains out since the October 2023 cloudburst.

8The monsoon overhaul slate - about a dozen large units on planned outage
On annual or capital overhaul at 200 MW and above: in the west, NTPC's Solapur-1 and Sipat-3 (660 MW each), Jindal's JPL Stage-II Unit-2 (600 MW), Jhabua-1 (600 MW), Adani Mundra-6 (660 MW), Bhusawal-5 (500 MW), GMR Warora-1 and SKS-1 (300 MW each), and a cluster of 200-250 MW units in Gujarat, MP and Chhattisgarh (Korba-East DSPM-2, Korba-West-2, Amarkantak-5, Khaperkheda-4, Ukai-3, VSTPS-4); in the north, NTPC's Singrauli-3 (200 MW). Overhauls are timed to the low-demand monsoon by design.

8The western grid is carrying two systemic HVDC/UHV outages
The Chandrapur–Padghe HVDC bipole is running on a single pole while the other is shifted from ground- to metallic-return, and the parallel 400 kV Chandrapur–GCR “HVDC-2” line has been out since 6 September 2025 - roughly ten months. At Bina, both 1200 kV transformers are out, one since 2017. A 765 kV Akola–Koradi line came back on 16 July after a roughly 20-day tower-collapse outage.

8A cluster of northern tower-collapse lines from May–June is still out
Several 400 kV double-circuits in Uttar Pradesh and Rajasthan - Bareilly–Unnao, Orai–Paricha, Banda–Rewa Road, Rajwest–Pachpadra, Harduaganj/Aligarh–Sikandrabad - remain out from storm tower collapses in late May and June, thinning the northern transmission margin just as demand peaks.

8Repeated tripping flagged as a maintenance signal
In the North-East the 132 kV Loktak–Rengpang line tripped 18 times in May–June and five more times in July; in the east, 220 kV Daltonganj–Chatra tripped five times and two 400/765 kV corridors three times each in June. Repeat trips on the same element are the register's early warning of a defect that inspection has not yet caught.
Details
8Chhattisgarh's negative fuel-cost adjustment
CSPGCL's four stations filed about Rs 31.7 crore of negative fuel-cost adjustment for April on cheaper, higher-heat domestic coal - a deflationary signal for state tariffs and the sharp end of coal out-competing gas.

8Coal stocks ease to about 13.5 days; 28 plants critical, Niwari empty
National coal stock was about 42.1 million tonnes on 16 July, roughly 13.5 days and down marginally on the day as consumption outran receipts; 28 plants sat below a quarter of normative stock. Niwari (MP) is effectively empty at under a day, Damodaram Sanjeevaiah (Andhra, 2,400 MW) at 6 percent and Sasan at 7 percent - the usual import-dependent and end-of-line plants, not a system-wide squeeze.

8MahaGenco is cutting imported coal to save money
Maharashtra's generator reports burning “more raw domestic coal against imported/washed coal” across its fleet and holding imported coal below plan “for cost optimization” - the same economics as Chhattisgarh's, playing out as a deliberate switch away from costly imports while domestic coal is abundant.

8The gas fleet stayed switched off on price
Across the merit order, RLNG stations from Kawas and Gandhar to RGPPL and Faridabad were committed for grid support but scheduled at zero, the costliest at about Rs 24.86 a unit against pithead coal near Rs 1.43 - roughly seventeen times. Gas remains a stand-by the system can rarely afford to run; see Story 1.

8Ministry of Coal opens bidding on its Rs 37,500 crore coal-gasification scheme
A Ministry of Coal notice dated 16 July calls a pre-application conference on 20 July under the Rs 37,500 crore scheme to promote surface coal- and lignite-gasification projects, following its 7 July request for proposals - the government's push to turn some of that abundant domestic coal into gas and chemicals rather than only power.
Details
8Telangana's big Krishna reservoirs stay far below last year
Telangana's generation utility reports Srisailam at 41.6 TMC on 17 July against 195.6 a year earlier, and Nagarjunasagar and the Krishna basin as a whole well down; total useful storage of 246 TMC translates to only about 131 MU of stored energy. Two weeks into the story (see 16 July edition), the state's hydro cushion for the coming lean season is still not filling.

8Flash floods knock out Panyor Lower's 405 MW
All three 135 MW units of NEEPCO's Panyor Lower project in Arunachal Pradesh have been under forced outage since 24 June after flash floods, with restoration dates still sought - a monsoon that is flooding the north-east while leaving the Krishna basin short.

8Sikkim's Dikchu is running one fault away from a full evacuation loss
Dikchu (Sikkim) is running on a single 400/132 kV transformer with its second bus out since August 2025 - not N-1 compliant, a state the eastern committee calls a serious concern - and it tripped twice in late June on moisture in an SF6 gas-density monitor. Any fault on the lone transformer now takes the whole station's output off the grid.

8A tower collapse and a coming Loktak shutdown tighten eastern-hills hydro
A dead-end tower collapsed at Rongnichu on 18 June, taking both circuits and about 104 MW out for roughly eighteen days, and the Loktak power station faces a full renovation shutdown from November to April. Eastern-hills hydro is patchy now and set to tighten further over winter.

8Solar carried 16 July and faded at dusk - the daily shape behind the evening price
CEA's renewable bulletin puts all-India green generation at 1,137.65 MU on 16 July (solar 645, wind 459); all-India hydro generation was about 662 MU. Solar carries the day and fades at dusk - the daily shape behind the evening-peak price.
Details
8Pace Digitek connectivity restored
Petition 241/MP/2026 - the wave's first decided order, condoning a two-day bank-guarantee delay and setting aside CTUIL's closure of the 100 MW application.

8NTPC's GST change-in-law on 1,990 MW of solar is reserved
In Petition 365/MP/2025 (NTPC v IREDA and others) the Commission reserved for order NTPC's claim that a higher GST rate, and the consequent rise in usage charges on 1,990 MW of solar projects, is a change-in-law event under the power-usage agreements. Reserved, not decided - but a large sum turns on it.

8GUVNL–Adani Mundra part-load compensation reserved with pointed directions
The connected Petitions 469 and 252/MP/2024 over Adani Power's part-load compensation claims for Mundra (FY22–FY25) were reserved after argument, but the Commission directed Adani to justify its reliance on the MB Power precedent absent any supplementary agreement, to place SLDC verification of operational data, and to reconcile its claim with a 2022 settlement deed barring further change-in-law claims on energy charges. The directions signal the questions the eventual order will turn on.

8Avaada's Bhadla connectivity-split plea adjourned
In Petition 240/MP/2024, Avaada Energy's request that CTUIL split its 1,000 MW connectivity across margins at Bhadla-II, III and IV was adjourned to 25 August at CTUIL's instance - another strand of the connectivity contest, still unheard on merits.

8Adani Energy's short-term dues claim against Telangana adjourned
Petition 239/MP/2024, Adani Energy's recovery of outstanding dues and late-payment surcharge for short-term supply to Telangana, was adjourned to 10 September to hear reply and rejoinder together.

8A solar developer's cess claim against SECI adjourned
In Petition 150/MP/2026, Eden Renewable Alma's change-in-law claim for the 20 percent agriculture-infrastructure cess imposed on imported modules from February 2025 was adjourned to 15 September, the Tamil Nadu discom yet to file its reply.

8AMPIN Energy's trading-licence upgrade admitted
Petition 303/TD/2026 seeking to move AMPIN Energy Markets from a Category-V to a Category-IV inter-state trading licence was admitted, with the Commission requiring a special balance sheet as at a date within 30 days of filing - a routine but citable licensing step for a growing trader.
Details
8Punjab freezes PSPCL's forced 11 kV–66 kV migration
PSERC granted interim status-quo to Rana Sugar and Golden Sandhar Mills (Petitions 48 and 49 of 2026) and conditionally admitted PSPCL's 250 MW SAEL solar tariff (Petition 56 of 2026).

8Two more PSPCL consumer disputes adjourned
PSERC also took up a rooftop-solar capacity-and-tariff plea from Shree Ganesh Edibles (Petition 41 of 2026) and Indian Sucrose's claim for interest on a wrongly-adjusted Rs 2.18 crore of line/bay charges refunded after an APTEL order (Petition 47 of 2026); both were adjourned on admission, with PSPCL raising a maintainability objection in the latter.

8Gujarat's transmission-bidding threshold review withdrawn - the new rules already set it
GERC allowed Gujarat Energy Transmission Corporation to withdraw its review (Petition 2209/2023) seeking to raise the competitive-bidding threshold for intra-state transmission from Rs 100 crore to Rs 250 crore, because the 2024 multi-year-tariff regulations already set that threshold - competitive bidding now applies at 220 kV and above or above Rs 250 crore. The review is disposed of; the substance is already law.

8GERC reserves orders in the Dipak Textile and Shivalakha Solar disputes
GERC reserved orders in Dipak Textile's complaint against DGVCL and in a long-running Shivalakha Solar (formerly Solar Semiconductor) dispute with GUVNL under a 2010 power-purchase agreement, the latter heard with the petitioner absent.

8Meghalaya calls a hearing on its draft State Grid Code
MSERC will hear comments on the draft Meghalaya State Grid Code Regulations 2026 on 24 July, having taken written submissions to 8 July - a small state formalising the grid discipline the larger ones already run under.

8Rajasthan's docket fills with must-run and transmission-licence disputes
RERC's schedule for 21–27 July lists Adani Solar Energy Jodhpur Three's 300 MW must-run backing-down compensation claim against the state load despatcher, two smaller must-run claims, three petitions for separate transmission licences under the tariff-based route (Thar, Barmer and Hadoti Power Transmission), and EESL's non-disbursement complaints against the Rajasthan discoms - a calendar of listings, not rulings.

8Goa-and-UT regulator moves on ease-of-doing-business supply-code changes
JERC disposed of DNH and DD Power Corporation's petition to amend the electricity supply code for Dadra & Nagar Haveli and Daman & Diu - self-certification for low-tension inspections, slab-wise fixed service-line charges, three- to seven-day connection timelines and a higher low-tension ceiling - directing its staff to draft and publish an amendment aligned to the 2023 central safety rules.

8PSPCL asks Punjab to loosen its fuel-surcharge trigger to unlock borrowing room
In a petition read only after OCR - its filename disguised it as a CEA report - PSPCL asks PSERC to amend the fuel and power-purchase adjustment surcharge rules, moving the carry-forward trigger from 40 paise a unit to 20 percent of the variable tariff component, in line with the central 2022 rules. The prod is financial: the Ministry of Power made this alignment a condition for additional state borrowing room of up to 0.5 percent of GSDP. Carry-forward would be capped at two months, cost SBI's benchmark lending rate plus 150 basis points, and any excess recovery be clawed back at 1.2 times - a small rule change with a direct line to the state's fiscal space.
Details
8Gujarat renewables curtailed for grid security
About 8.85 million units of Gujarat wind and solar - up to 2,859 MW of solar and 1,027 MW of wind - were curtailed on 15 July “in view of the system requirement and grid security,” the clearest single sign that the daytime surplus is real and being managed by backing renewables down (see Story 1).

8Coal India brings 200 MW of Khavda solar online
Coal India commissioned 200 MW of a 300 MW solar project at Khavda, Gujarat, certified on 15 July - a Maharatna coal major diversifying into the same renewable-heavy hub whose grid behaviour the committees keep flagging.

8ACME Solar closes Rs 2,646 crore of funding for a firm-power project
ACME Solar raised Rs 2,646.64 crore of 20-year project finance from REC for a 450 MW / 1,800 MWh assured-peak-power (solar-plus-storage) project, on a 25-year SJVN power-purchase agreement at Rs 6.74 a unit - a concrete financing close for the firm, dispatchable renewables the evening peak actually needs.

8SECI seeks bulk buyers for long-term renewable power
SECI's expression of interest dated 17 July invites bulk power off-takers into long-term renewable procurement - minimum 50 MW, an investment-grade credit floor, pre-bid meeting on 24 July - testing corporate and captive appetite to sign the long tenors that underwrite new build.

8Draft CAFE-III fuel-economy norms out for consultation
The Ministry of Power, with the Bureau of Energy Efficiency, has circulated draft Corporate Average Fuel Economy norms for passenger cars covering FY28 to FY32, with comments due by 6 August - the demand-side lever that, over time, shifts transport energy toward the grid.

8A nationwide power-quality metering push takes shape
Grid-India's draft harmonics-measurement guidelines, moving through the regional committees, would require power-quality meters at new inter-state substations from April 2027 and across existing ones by March 2030, aimed at wind, solar, storage and HVDC installations of 50 MW and above - the monitoring backbone for an inverter-heavy grid.

8Renewables came in below schedule on 15 July, wind the main shortfall
All-India renewable output tracked by the management centre was 1,110 MU against 1,186 scheduled on 15 July, with wind the bulk of the miss - the forecasting gap the grid then has to close in real time, and part of why the evening market runs tight.

8An energy-savings-insurance idea to unstick efficiency finance
An OECD–BEE roadmap proposes an energy-savings-insurance scheme - insurance backing for guaranteed-savings efficiency contracts - to de-risk investment in industrial clusters such as foundries and textiles. A financing concept, not yet a programme, but aimed squarely at India's thinly-tapped energy-service-company market.
Details
8BHEL's power business turns from loss to profit
Standalone Q1 profit of Rs 381.91 crore on 40 percent higher revenue, the power segment swinging from a Rs 510 crore loss to a Rs 563 crore profit; the results also flag a board still without an independent director.

8Borosil Renewables turns profitable
Standalone profit Rs 87.71 crore, 35 percent margins on anti-dumping-lifted glass prices; the headline consolidated jump is a base effect from the German exit.

8Sterling & Wilson back in profit with a record book
Consolidated profit Rs 68 crore, order value at a post-pandemic high of Rs 13,024 crore led by the Egypt solar-and-storage venture.

8GE Power India to demerge Durgapur into JSW Energy
GE Power India will demerge its Durgapur manufacturing works to JSW Energy, with shareholders getting 10 JSW Energy shares for every 139 held and no dilution of GE Power India itself. The unit lost about Rs 27 crore a year and is backed by a five-year services agreement; the parent's own turnaround is real - net worth up eight-fold to Rs 483 crore, EBITDA from minus Rs 251 crore to plus Rs 277 crore over three years, and an ICRA upgrade to BBB+. A portfolio clean-up that hands JSW a power-equipment capacity and lets GE Power India shed a chronic loss-maker.

8Polycab's quarter strong on cables and solar
Polycab reported consolidated revenue up 39 percent to Rs 8,210 crore and profit up 33 percent for the June quarter, with its fast-moving electrical-goods arm up 71 percent and solar products more than doubling; international wires and cables fell 13 percent. A cables-and-FMEG major whose fastest-growing line is now solar hardware.

8Exide pours another Rs 100 crore into its cell subsidiary
Exide subscribed a further Rs 100 crore of equity in Exide Energy Solutions, taking cumulative investment in the lithium-cell gigafactory to Rs 4,902 crore. The subsidiary still turned in a Rs 248 crore loss on Rs 158 crore of revenue in FY26 - the capital drain into domestic cell-making continues ahead of the revenue.

8Rajesh Power Services wins Odisha and Gujarat cabling orders
The Ahmedabad T&D contractor reported June-quarter revenue of Rs 436.62 crore and an order book of Rs 3,741.79 crore, entering Odisha with a Rs 211.68 crore underground-cable order from OPTCL and adding Rs 653.12 crore of PGVCL cabling work; CRISIL reaffirmed its A- rating and revised the outlook to Positive.

8NHPC gets a new independent director
NHPC appointed Dr Bernadette Lyngdoh as a non-official woman independent director for three years, on a Ministry of Power nomination dated 16 July - filling one of the board seats that public-sector companies are routinely short of (see BHEL, Story 7).

8Results diary
NTPC Green, Orient Green and Transformers & Rectifiers report on 21–22 July - All three have called board meetings and earnings calls for their June-quarter results on 21–22 July - the next cluster of power-sector numbers due.

Ratings Watch

8Two Punjab and Rajasthan solar SPVs lose their ratings after repaying
CARE withdrew its long-term ratings on Solaire Power (20.25 MW, Punjab) and Pokaran Solaire (4.76 MW, Rajasthan) after both repaid their term loans in full and obtained no-dues certificates. Both had held an AA-plus rating - a reminder that a strong rating can simply disappear when the debt is gone, not because credit deteriorated.

8CRISIL lifts Rajesh Power's outlook to positive on a swelling order book
CRISIL reaffirmed Rajesh Power Services at A- and moved the outlook to Positive - on a Rs 3,742 crore order book swelled by the company's entry into Odisha and fresh PGVCL cabling work (see 24.7). The order momentum, more than the rating notch, is the story.

8A Nepal hydro rating reaffirmed
Infomerics reaffirmed Upper Solu Hydro (23.5 MW, Nepal) at BBB-minus on a standalone basis, on improved generation and margins under its power-purchase agreement with the Nepal utility - a small cross-border data point in the ratings file.
Details
8Eastern protection panel reviews June's big trips - and finds most utilities skip their protection filings
The ERPC's 160th Protection Coordination Committee (21 July) reviews the month's generation losses and trippings - see Stories 3 and 4 for the two largest - and flags that June protection-performance indices came from only eight of the region's utilities, and that no utility has commented on the draft harmonics guidelines. The recurring theme is protection settings and disturbance-recorder discipline that several utilities are slow to fix.

8North-East committee: capital islanding schemes still not designed
The NERPC's 240th operation-coordination meeting (24 July) records that islanding schemes for Shillong, Imphal and Kohima have still not been devised, that automatic generation control is pending plant-by-plant on old controls and high machine vibration, and that most states are still not submitting resource-adequacy and reactive-power data in the prescribed form - the administrative under-belly of the defence-scheme gaps in Story 4.

8The west backed down 720,000 MWh of surplus in a week - 22 times what it called up
The WRPC's weekly operational files for 6–12 July show emergency reserves backing generation down by about 720,000 MWh against only 32,000 MWh called up - surplus on a scale that needed sustained backing-down, with Mundra supplying roughly 60 percent of the little up-reserve used. Quantum, not cost; but it is the week-long backdrop to this edition's price and curtailment story.

8A Kerala grid-telecom link is still down after a Kochi refinery accident
The SRPC's 72nd communication-equipment outage meeting (23 July) reviews telecom and SCADA link outages, flagging a Kerala fibre link damaged in an accident at the Kochi refinery and a Tamil Nadu remote-terminal-unit retrofit as the rolling reliability breaches - the unglamorous plumbing that grid operators depend on.

8The grid shifts to 15-minute demand data - changing how peak-demand records are set
From the last week of July the north-eastern operator moves its power-supply-position data from hourly to 15-minute blocks, aligning with the framework that will govern how all-time-high demand records are set and measured - a small data change with a direct bearing on the record-watching in Story 2.

8A dismantled breaker at Kolasib turns a maintenance lapse into an availability dispute
At Kolasib in Mizoram a 132 kV line tripped on 5 July and could not be restored for over fifteen hours because the substation's transfer-bus-coupler breaker was found completely dismantled. POWERGRID, which maintains the bay, now wants the line treated as deemed available for the outage - a maintenance failure becoming a commercial dispute with the state owner.

8North-eastern transmission is strung thin, with fixes still pending
A 132 kV line at Lekhi–Chimpu in Arunachal has been out since May 2025 after a tower nearly collapsed, and the Assam and Tripura corridors repeatedly run over their transfer limits (see 17.4). The committee's remedies - new substations at Sonapur, Rangia and Gossaigaon and reconductoring in Tripura - are all still pending, which is why the region keeps leaning on its defence schemes (see Story 4).
Details
8Day-ahead power for 17 July cleared at Rs 7.28 a unit, a fresh weekly high and about three times the Rs 2.49 of five days earlier, with night blocks pinned to the Rs 10,000 ceiling. Yet through the daylight hours the grid was backing down surplus generation, curtailing Gujarat renewables and leaving costly gas fully committed but unscheduled - the scarcity was concentrated in the hours after the sun went down. Details
8The grid met a maximum demand of 270,203 MW on 16 July, just 600 MW short of the 270.8 GW all-time peak set during May's heatwave, and held the national shortage below one percent. But the shortfall was not evenly shared: Haryana lost nearly 15 million units, Uttar Pradesh resorted to unscheduled load-shedding and Kerala carried a southern pocket. Details
8The Eastern region's protection committee has traced June's two largest generation losses to equipment inside the plants, not the grid: at NTPC's North Karanpura two relays disagreed and blocked auto-reclose after a nearby line fault, tripping all three 660 MW units; at Jindal's Derang plant a protection scheme wired to hard-trip both generators fired on a single CT failure. Both faults were the plant's own, and both fixes are now identified. Details
8When both transformers at Bongaigaon tripped on 3 July, the automatic load-shedding scheme operated in two stages and shed about 102 MW - but the surviving transformer was already loaded to 212 percent, and it tripped anyway. The episode, alongside capital-city islanding schemes still not designed, shows the region's last-resort defences are being outrun by its constraints. Details
8In the first order to actually decide one of the connectivity disputes crowding the Commission, CERC condoned a two-day delay in furnishing bank guarantees and set aside CTUIL's letter closing Pace Digitek's application. The 100 MW project, with Rs 557.62 crore already committed, keeps its grid access - and the ruling gives every developer fighting a revocation a precedent to cite. Details
8The Chhattisgarh generator filed a negative fuel-cost adjustment of about Rs 31.7 crore for April across its four stations, crediting consumers because the coal it actually burned cost roughly Rs 200 a tonne less than the tariff allowed and carried more heat. It is the sharp end of a wider shift: domestic coal is beating both its own tariff norm and, by a distance, gas. Details
8The state-owned equipment maker turned a Rs 455 crore year-earlier loss into a Rs 382 crore standalone profit for the June quarter, as its power segment swung from a Rs 510 crore loss to a Rs 563 crore profit on a 40 percent jump in revenue. The order book that had swelled faster than BHEL could build is finally converting into earnings. Details
8India's only listed solar-glass maker posted a Rs 88 crore quarterly profit against a Rs 272 crore loss a year ago, with margins at 35 percent, as duties on Chinese and Vietnamese glass lifted prices and the loss-making German subsidiaries were deconsolidated. The eye-catching headline - consolidated EBITDA up 104 percent - is mostly a base effect, and revenue actually fell from the prior quarter. Details
8The solar EPC contractor returned to a Rs 68 crore consolidated profit after a loss the previous quarter, and lifted its unexecuted order value to a post-pandemic record of about Rs 13,000 crore. The marquee win is a half-share of a USD 560 million project in Egypt pairing 1,000 MW of solar with 600 MWh of batteries - its first big storage-integrated order in the region. Details
8PSERC admitted disputes from Rana Sugar and Golden Sandhar Mills and granted interim status-quo, barring the utility from any coercive action or further recovery while it forces industrial consumers to surrender their 11 kV connections. In the same sitting it took up PSPCL's own 250 MW solar tariff - and demanded proof the tender followed the competitive-bidding rules. Details
 For reference purposes the website carries here the following tenders:
 8Tender for protection work of scouring pile foundations of 132kV DC transmission lines towers Details
 8Tender for supply of 765 kV CTs for various substations Details
 8Tender for procurement of current transformers (CT) along with terminal connectors Details
 8Tender for fabrication of super heater and economizer coils Details
 8Tender for supply and installation of submersible borewell pumps in existing bore wells Details
 8Tender for work of erection of 66kV Lilo to S/s line Details
 8Tender for carriage of stock material Details
 8Tender for construction of C type tower Details
 8Tender for extension of SGR at 33 /11 kV sub station Details
 8Tender for construction of 33 kV bay Details
 8Tender for installation of 20.00 meter high mast light Details
 8Tender for repairing and rewinding of three (03) nos. 110KW, and three(03)nos. 150KW induction motors Details
 8Tender for urgent provision of fencing Details
 8Tender for improvement of water supply system by providing chlorination system Details
 8Tender for complete repairing of two nos. 275 HP, 3.3kV, 3 phase auto transformer starter panel Details
 8Tender for maintenance of pumps and its all pipe line Details
 8Tender for construction of temporary reserve station Details
 8Tender for construction of 75 Nos. fly ash ventilation stoppings Details
 8Tender for repair and extension of shed with allied misc. works Details
 8Tender for supply of spares for desiccant type air dryer of braking system of all six generating units Details
 8Tender for new 33/11kV S/s Details
 8Tender for procurement of spare battery cell and buy back of old batteries Details
 8Tender for supply, installation, testing and commissioning of new electrical feeder panel Details
 8Tender for procurement of MTL make safety spares Details
 8Tender for Bi-ARC for work of attending UG cable fault for 66kV class XLPE corrugated/ poly AL cable various lines Details
 8Tender for attending leakages/seepages in various underground structures Details
 8Tender for aug. of 11/0.433 kV 250kVA transformer to 11/0.433kV 630 kVA S/Stn. Details
 8Tender for procurement of steel tubular poles Details
 8Tender for aug. of 400 KVA 11/0.4 kV S/Stn. Details
 8Tender for procurement of various rating battery banks for various substation Details
 8Tender for supply of allied material for electrical material required Details
 8Tender for supply of 245kV class centre break isolators with and without earth switch Details
 8Tender for sale of 1,00,000 MT dry fly ash Details
 8Tender for procurement of SOC solution for IT and OT system Details
 8Tender for construction of one 33kV feeder Details
 8Tender for renovation/construction of 1(one) number of 2-unit 132 kV GSS Details
 8Tender for slope protection measures Details
 8Tender for supply of TC fuse wire 12 SWG Details
 8Tender for supply of LT straight joint kit (HS type) for 1.1KV 4X240 sqmm UG cable and 4x120 sqmm UG cable Details
 8Tender for supply of HS type outdoor termination kit for 11kV 3X300 and 3X120 sqmm Details
 8Design, engineering, supply construction, erection, testing, commissioning and maintenance of 45.6 MW ISTS connected wind power project Details
 8Tender for erection work of LILO to proposed 66kV sub-station Details
 8Tender for roof top rain water harvesting Details
 8Tender for work of dye penetrant test (DPT), magnetic particle inspection Details
 8Tender for erection work of 66kV D/C tower line Details
 8Tender for fabrication dismantling erection strengthening modification of various chutes hoppers wagon tipplers belt conveyors crusher houses Details
 8Tender for supply of staircase step grills for crushe house Details
 8Tender for biennial rate contract for attending running repairs, scheduled, preventive & breakdown maintenance with overhauling of 08 nos. bulldozers Details
 8Tender for supply of spares for stage 3 bootom feed gate pnematic systems Details
 8Tender for supply and replacement works of S-panel tubes Details
 8Tender for procurement of special purpose welding electrodes Details
 8Tender for electrical works of ash dyke seepage water pumping system Details
 8Tender for misc. civil works Details
 8Tender for supply of various size of gate valves, diaphragm valve, NRVs, rubber sheet Details
 8Tender for Bi-Aannual ARC for erection of 66kV S/S equipment, structures, control wiring etc. Details
 8Tender for detailed survey of various EHV lines Details
 8Tender for procurement of thermodynamic steam trap with inbuilt strainer and various size of NRV installed Details
 8Tender for work operation and maintenance along with CMC of CAAQMS installed Details
 8Tender for utility shifting in connection Details
 8Tender for capital work of 110kV substation Details
 8Tender for outsourcing of ETC of new 66 kV substation with 01 No 20 MVA power transformers along Details
 8Tender for supply of scraper bar for scraper chain conveyor system Details
 8Tender for new construction of 33/11 kV sub station Details
 8Tender for construction of yard foundation cable Details
 8Tender for annual contract of hotline washing of porcelain type post insulators, CBs, CTs, CVTs, gantry string insulators of both 220 kV and 400 kV switchyard Details
 8Tender for supply, engineering, installation, testing and commissioning for retrofitting of micro- processor based belt watch system Details
 8Tender for day to day repair and maintenance of sanitary fittings and water supply fittings Details
 8Tender for R and M of permanent colour coated and corrugated G.I. sheets Details
 8Tender for requirement of single span drive shaft made from advanced composite material Details
 8Tender for repairing and overhauling of transmission assembly Details
 8Tender for supply of various fly ash spares Details
 8Tender for procurement of roller journal bearings upper and lower of mill XRP 1003 Details
 8Tender for work of earth mat construction work for new circuit bench 33kV sub-station Details
 8Tender for work of supply and installation of lugs Details
 8Tender for work of installation of self-adhesive insulated waterproof bitumen sheet membrane on electric poles Details
 8Tender for work of installation of self-adhesive insulated waterproof Details
 8Tender for construction of wire mesh gablion wall to protect pole plinth from flood of 33 kV line Details
 8Tender for supply of various MS / CS pipe, bends, tee, reducer, and flanges Details
 8Tender for work of servicing/overhauling/repairing /testing of 6.6kV HT VCBs & 415V LT ACBs of various rating Details
 8Tender for work of replacement of old centralized HVAC system Details
 8Tender for procurement of 220kV cable joints for various EHV underground (UG) cables Details
 8Tender for work of supply installation and commissioning of wireless announciation and microcontroller window Details
 8Tender for work for supply of 24" transformer cooling fans & contactor, timer & relay Details
 8Tender for work of arresting of porcupine movement by fire retardant coating of control cables Details
 8Tender for establishment of 220/132/33kV substation Details
 8Tender for procurement of 33kV, 1600-800/1A, 26.2kA, 4C, 0.2s Class CT Details
 8Tender for providing and erecting profile sheet weather shed to control room & other miscellaneous civil work at 220/22 kV substation Details
 8Tender for procurement of 220kV cable joints for various EHV underground (UG) cables Details
 8Tender for work of chemical washing of disc insulator strings of various Details
 8Tender for work of rectification of findings observed in health analysis of existing earthing system Details
 8Tender for work of erection, testing & commissioning of 132kV equipment, structure, control wiring, earthing etc. Details
 8Tender for supply of network cables for network maintenance Details
 8Tender for supply and works for providing e-urja connectivity extension for new silo control room, way bridges Details
 8Tender for Bi -annual rate contract for restoration work of various 132kV & 220kV class transmission lines Details
 8Tender for Bi-annual rate contract for erection of 66kV transmission lines Details
 8Tender for erection and maintenance of HT/LT/TC work Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects on control room at various 66kV substations Details
 8Tender for Bi-annual rate contract for the work of augmentation of EHV transformers and associated works Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8India Mining Week: MoS Dubey invites industry as India unveils new critical mineral blocks Details
 
8Caliber Mining IPO Review: A Contract Mining Play Riding on Coal India, Should You Bet Details
 
8Bharat Coking Coal FY26 Profit Drops 89%; IPO Completed January 2026 Details
 
8A New Awakening for Coal Gasification in India Details
 
8From import dependence to global competitiveness: India’s solar manufacturing story Details
 
8Huawei launches FusionSolar 9.0 Smart PV Solution Details
 
8Kurnool’s 600 MW Solar Asset Reflects SAEL’s Growing Footprint in Large-Scale Renewables Details
 
8Borosil Renewables unveils Q1 FY27 performance in investor presentation Details
 
8Servotech Renewable secures 900 kW hybrid solar rooftop project from UPSRLM Details
 
8Waaree Energy Storage Solutions begins production at BESS container manufacturing facility Details
 
8ACME Solar raises project funding of Rs 2646 crore from REC Details
 
8Lack of rains, low water levels in dams resulting in power cuts in Kerala: Minister Details
 
8Sterling & Wilson falls 9% post Q1 results; profit up 69%, revenue down 10% Details
 
8Kundankulam data leak: NPCIL says nuclear safety or security systems not exposed Details
 
8Power export to India increased upto 1,650 megawatts Details
 
8Top 10 Adani Shares List to Watch Out For in 2026 Details
 
8Unlocking Efficiency: Building a unified power market through market coupling Details
 
8In the Arunachal Pradesh mountains, India is looking to tap geothermal energy Details
 
8India's non-coking coal imports fall further in Jan-Jun'26 on robust domestic supply, rising renewables output Details
 
8India's energy storage capacity expected to rise more than tenfold by FY2035-36: MoSPI Details
 
8PAIMANA Dashboard Expands to Track India's Infrastructure Growth Details
 
8Ambit Capital Power Play: ‘Buy’ on NTPC and Suzlon, ‘Sell’ Tata Power as battery costs reset Details
 
8Ratul Puri on Building Integrated Energy Solutions for India's Rising Power Demand Details
 
8BHEL Posts Rs 377 Crore Profit in Q1 as Power Orders Rise Details
 
8Coal India commissions 200 MW of Khavda solar project, strengthens renewable energy push Details
 
You can also click on Newsclips for more Details
8About 40,000 MW sat out across four regions at the seasonal peak
Combined outages on 15 July were roughly 16,990 MW in the West, 11,025 in the South, 6,122 in the North and 5,752 in the East - about 22,240 MW of it forced, the rest planned. The grid still met near-266 GW comfortably, so the margin held; but a fifth of the fleet being unavailable on a peak day is the figure to watch as demand climbs.

8The West carried a cluster of fresh trips
Both units of Adani's Raipur plant went out on 15 July (1,370 MW, on coal-mill and condenser faults), three Wanakbori units are down together (630 MW, Gujarat), and NTPC's Gadarwara-1 (800 MW) stays out on a boiler-tube leak. None alarming on its own; together they are why the West carried the largest outage load.

8Fresh trips in the East and South too
Odisha's OPGC-3 (660 MW) and Bengal's Sagardighi-5 (660 MW) tripped on 14 July; in the South, Vallur-1 (500 MW), SEIL-2 (660 MW) and Mettur-5 (600 MW) went out on boiler and cooling-water faults. Ordinary forced outages for fleets this size - logged so whoever tracks any of these plants finds it.

8Rajasthan's Kota station lost three units in a single day
Kota TPS units 1, 4 and 7 (about 515 MW combined) were all out on 15 July on vibration and boiler faults - and Unit 4 is a small story in itself: it returned that afternoon after ten days out, then tripped again the same night. It reads as a station running ageing units hard.

8UP's Ghatampur plant has both new units down on coal-feeding faults
Ghatampur units 2 and 3 (1,320 MW together, NUPPL) remain out since mid-to-late June on coal-feeding problems - not a fuel shortage but a materials-handling failure at a brand-new supercritical station, which is the more troubling kind.

8Telangana's Yadadri has both units out, one on coal
Yadadri-4 (800 MW) is out on a coal shortage and Yadadri-1 (800 MW) on overhaul: 1,600 MW of the state's newest coal capacity idle just as its hydro collapses.

8The most useful return of the day: Kudankulam's 1,000 MW nuclear unit is back
Kudankulam-1 returned on 15 July after about a week out on generator protection - a full gigawatt of firm, must-run capacity back on the bar as the evening peak runs high.

8A first repair from the 2023 Sikkim flood: Teesta HPS Unit 3 is back after nearly three years
NHPC's 170 MW Teesta HPS Unit 3, dark since the October 2023 glacial-lake-outburst disaster, resumed on 15 July - the first restoration milestone from that catastrophe, even as the 1,200 MW Teesta-III complex next door stays fully out. Small in megawatts, large in what it signals about the long road back.

8A Kakrapar nuclear unit is out on a seal fault, back in three days
KAPS-1 (220 MW) tripped on 15 July on a generator-seal problem, return expected 18 July - a short, specific fault, logged because nuclear trips remove firm capacity.

8Two whole hydro stations are dark, one in the South's water-short belt
Telangana's Srisailam left-bank station (six units, 900 MW) is entirely out on overhaul and a long forced outage, and Tamil Nadu's Kadamparai pumped-storage station (four units, 400 MW) is fully down on earth faults into 2026-27. With Srisailam's reservoir near empty (Story 5), the region is short of both the water and the machines.

8The long-dark fleet still on the books
Beyond Teesta-III (1,200 MW since 2023), a string of units has been out for years: Raichur-1 (210 MW, not due back until 2027), Tuticorin's two units (since a 2025 fire), MAPS-1 (220 MW nuclear, since 2018), and LANCO's LKPPL station (732 MW, under insolvency since 2016). None is new, but together they show how much built capacity the system carries as dead weight.

8India's oldest reactor is being retired
RAPS-A Unit 1 (100 MW, Rajasthan), out since 2004, is recorded as awaiting regulatory clearance for decommissioning. Tiny in megawatts, but it marks the formal end of India's first commercial reactor unit.

8On the wires: a three-week-old tower collapse and a fresh disturbance at a 765 kV hub
The 765 kV Akola–Koradi line has been out since a 26 June tower collapse - the longest-standing material transmission fault in the set - and on 15 July a wider disturbance hit the Wardha 765 kV station, taking out the Nizamabad–Wardha inter-regional line (still out) and briefly the Wardha–Raipur circuit; a Sipat ICT has been out about nine days. These are the backbone elements to track until restored.

8The maintenance calendar and the routine tail
Big units due back soon include Gadarwara-1, Ghatampur-2, Vallur-1 and Talcher ST-2 (16 July) and Yadadri-4 (20 July); nuclear returns run KAPS-1 (18 July), Kaiga-1 (September) and MAPS-1 (December). Below the line sit about 42 small units (~2,750 MW), overwhelmingly ageing gas-turbine peakers stranded on costly gas or expired PPAs, not grid events - recorded internally rather than as stories.
Details
8Exchange power prices nearly tripled in a week without a real shortage
The real-time price reached about Rs 7.36 a unit for 16 July, up from Rs 2.75 on 9 July, with the day-ahead near Rs 6.53 for 15 July. The point of the lead is that the grid had power to spare while the exchange tightened; the mechanism sits there.

8The green day-ahead market hit its Rs 10 ceiling - clean power was the tightest of all
On 15 July the green day-ahead segment cleared at its Rs 10-a-unit cap, buyers bidding for about 197,000 MWh against only 37,000 MWh offered. That imbalance is the real signal: when the system tightens in the evening it is firm and green capacity that runs short, not the day-time solar that floods the market at noon.

8PXIL opens a high-price window aimed at imported-fuel and battery sellers
Its new AnydaySSC product (Circular 483, effective 15 July) is a single-side reverse auction open only to imported-coal, imported-gas and battery sellers. It is a small structural move with a clear purpose - give costly-but-flexible capacity a place to sell when the system needs it, the same logic as the high-price day-ahead market.

8Andhra's discom is buying peak power on the exchange right through August
APCPDCL floated five reverse auctions on the Hindustan Power Exchange for late July and August - about 400 MW round-the-clock plus separate evening-peak blocks. Coming after UP and West Bengal did the same last edition, it says southern demand is running ahead of supply after dark, and discoms would rather lock in firm blocks now than chase the spot price later.

8SECI has a big, cheap block of renewables on offer - but firming it costs three times as much
SECI's sheet lists about 8,276 MW of solar and hybrid capacity open to buying utilities from Rs 2.42 a unit, while assured evening-peak renewable power clears near Rs 8. The gap is the whole story of the transition in one line: day-time green energy is cheap and plentiful; green power you can count on after sunset still costs three times more.
Details
8Summer-scale demand near 266 GW, met with almost no shortfall
Demand held near 266 GW on 14 and 15 July, high for mid-monsoon, yet the energy shortfall was just 0.19%. The grid took a peak-season load in the rains in its stride; the strain was on price, not supply.

8A clean grid nationally, with one stubborn corner in the North-East
Frequency stayed in band and every monitored 400/765 kV substation and inter-regional corridor showed zero violation on 15 July. The exception was small but recurring: the Tripura import corridor ran over its limit for about 18 hours on 14 July. It does not threaten the national grid, but it does mean Tripura keeps leaning on a link that has no headroom left.

8On a record-demand day the grid spent more time holding plants back than calling them up
Down-regulation ran to about 42,700 MWh against 20,300 MWh of up-regulation on 15 July. For a peak day, that is the tell that the tightness showing up in the exchange price was commercial, not a physical shortage of energy.
Details
8India opens registration for its first coal exchanges
The structural fuel story of the day: coal moving, over time, toward market-based trading with discovered prices.

8Even at peak demand, the costly gas fleet stayed switched off
The merit-order schedule for 16 July left imported-gas stations - Gandhar, RGPPL, Dadri gas and others - at zero MW, and RGPPL's Ratnagiri units have been idle since 28 June on low system demand. On a record-demand day, expensive gas was simply not needed - which is why the scarcity the price implied was not there in the fuel stack.

8Delhi's fuel-cost pass-through jumps and turns automatic
May's surcharge broke the old 10% cap; the mechanism is now formula-driven. A direct consumer-bill consequence.
Details
8Telangana's Krishna reservoirs are almost empty in the monsoon
Stored hydro energy down about 92% year-on-year, pushing the state onto thermal and the exchange.

8The wider reservoir picture is behind last year, north and south
CEA's bulletin has Srisailam, Bhakra, Tehri and Idukki all below their year-ago levels, with Hirakud the exception, running slightly ahead on heavy inflow. It is a slower, broader version of the Telangana story: the monsoon refill is lagging across several basins, which trims the cheap hydro the system can lean on later in the year.

8Odisha's hydro is steady, but building no cushion
OHPC generation held around 512 MW on 14 July with most reservoirs marginally below last year - no alarm, but no buffer forming either as the season wears on.
Details
8The day's biggest tariff order: Meja Thermal's fixed charges trued up near Rs 2,040 crore a year
The CERC finalised the 2019-24 tariff for the 1,320 MW Meja plant (NTPC–UPRVUNL), settling annual fixed charges at about Rs 2,040 crore for 2023-24, with an earlier year trued slightly down. For UP, Rajasthan and Punjab, who buy Meja's power, this fixes a large slice of what they pay for baseload for years - the most consequential number in the day's docket.

8The wires for a Karnataka renewable zone get their financing cleared
The CERC approved security-creation for a Rs 927 crore inter-state project - the Bijapur RE-zone evacuation line, a G R Infraprojects SPV - covering about Rs 714 crore of term loans. A small procedural order with a real signal: the transmission that renewable zones depend on is getting financed and built, which is usually the piece that lags the panels.

8A North-East transmission scheme is abandoned after the solar project behind it collapsed - leaving a compensation fight
The CERC had already cleared NERGS-I as eligible - a new 400 kV switching station at Bokajan, Assam, looping in the Misa–New Mariani line, awarded to Techno Electric under competitive bidding. It has now been closed as infructuous, not refused: the 750 MW Bokajan solar project it was built to evacuate fell apart after the Centre withdrew its ADB loan and Assam suspended the project, and APDCL surrendered the connectivity in June. Nothing was built, but real money was spent - the developer claims about Rs 28.5 crore already incurred (APDCL admits only about Rs 5 crore) plus Rs 40.8 crore of lost opportunity, and is fighting the central transmission utility over who pays, while APDCL separately wants a Rs 214 crore bank guarantee released. It is a clean illustration of the risk in building transmission ahead of generation: when the plant dies, the wires strand, and the bill has no obvious owner.

8A legacy transmission line's charges fall as it finishes depreciating
POWERGRID's Tanakpur system - the 1992-vintage 220 kV Tanakpur–Bareilly line - had its charges settled at about Rs 3.7 crore for 2024-25, dropping to about Rs 2.2 crore from 2025-26. The fall is not the debt running off (the asset carries no loan interest at all); it is because the line becomes fully depreciated at the end of 2024-25 and its allowed equity return is capped once it passes its useful life. A minor, uncontested order on an old asset shared by fifteen northern beneficiaries - logged for completeness, and to get the reason right.

8NTPC's 1,000 MW Rihand-III tariff is reserved for orders
The CERC has reserved its ruling on the Rihand Stage-III tariff (NTPC v UPPCL) - a large order to watch when it lands, given the plant's size and UP's exposure to it.

8NLCIL's Talabira coal-cost truing-up is put off to 24 September
The CERC deferred NLCIL's petitions on the input price of Talabira coal - which feeds its stations, with Tamil Nadu beneficiaries - directing more cost and O&M detail first. Procedural, but it decides a real slice of NLCIL's station tariffs.

8Two 1,000 MW NTPC/NLC blocks have their tariffs adjourned for more data
The CERC put off tariff proceedings for NLC Tamil Nadu Power (1,000 MW) and NTPC's Sipat Stage-II (1,000 MW), directing the generators to answer technical-validation queries before their 2019-24 true-ups and 2024-29 tariffs are settled. Routine housekeeping, but it decides a real slice of what Tamil Nadu and the central and western discoms pay for baseload - logged, with the subject corrected: these are tariff matters, not commissioning-date extensions.

8When does a 70 MW connection start paying? Welspun's case turns on a two-day notice
Welspun sought to push its connectivity start date back a year, blaming POWERGRID's delayed Bhachau substation augmentation in Kutch. The CERC has reserved orders, and the live question is narrow but real: whether the central transmission utility breached the mandatory three-month notice under the general network-access rules when it made the 70 MW renewable connection chargeable from 4 March with only two days' notice. The utility argues that joint-committee minutes served as notice; Welspun says liability cannot begin until the connection was actually usable. The rupees are modest, but the ruling will set how strictly that notice period is enforced for every delayed renewable connection.

8Sprng Vayu fights to keep 106 MW of wind connectivity revoked after missed milestones
The developer wants to use about 106 MW, in two tranches, that the CERC revoked on 25 February for missing connectivity milestones - leaning on the Commission's own March order that lets sufficiently-advanced developers retain revoked connectivity against compensation. That relief is itself under partial stay at APTEL, where other developers are challenging the compensation levy, so the outcome here feeds straight into the wider connectivity-revocation battle. The Commission has expedited the case, and even asked why revocation took nine months. Listed 20 July.

8Tata Power's Section 11 compensation claim against GUVNL rolls on
The dispute over how much Tata Power should be paid for supply it was directed to make in 2023 under Section 11 is adjourned to 20 August, with GUVNL's review still pending - a long-running imported-coal compensation fight.

8A narrow Haryana-discom review over about a Rs 6 crore difference
Haryana's discoms want a February order corrected, contesting a principal figure of Rs 711 crore against Rs 718 crore claimed - small in the round, but the kind of number a discom will still chase.

8A solar SCOD-extension plea stalls on a jurisdiction objection
TP Saurya's bid to extend the commissioning dates of its Neemuch solar units is held up by a jurisdiction objection from the MP power company - status quo for now.

8SECI chases Jharkhand's discom for unpaid solar dues
SECI has asked the CERC to make Jharkhand's JBVNL pay outstanding principal and late-payment surcharge for solar supplied under a 2018 agreement, and to sign a supplementary contract. The two sides read the tariff differently - SECI as the mapped project rate of about Rs 2.53 a unit, within the contract cap, the discom as a pooled rate across all its solar - and the Commission has first asked them to settle whether it or the state regulator has jurisdiction. Small in the round, but it is the familiar discom-payment problem that keeps renewable developers' receivables stuck. Listed 20 August.
Details
8UP clears the way to penalise about 200 renewable-purchase defaulters
UPERC (suo-motu 71SM/2025) let UPNEDA issue one final notice, after which continuing defaulters face penal proceedings under Section 142 - only 273 of 472 obligated entities had filed their FY2025-26 data. It is the step that turns a toothless compliance drive into one that can actually fine; the consequence, not the count, is the story.

8A cold store may feed one unit from another's meter across a public road
UPERC (KBGB Agritech, 2303/2025) held that Supply Code Clause 4.46(a) carries its own exemption power, and let a multi-unit consumer run its own cable between two units split by a road, on revenue-neutral terms. Marked "not a precedent," it will be cited as one anyway - a clean, reasoned ruling other multi-unit consumers can lean on.

8Delhi's quarterly power-cost petitions are dropped as the mechanism turns automatic
The three discoms' PPAC petitions were disposed as infructuous under the amended regulations; the consumer-bill consequence is in the lead.

8Adani Green's Rs 4.79-a-unit Karnataka tariff survives a final challenge
APTEL dismissed the Karnataka discom CESC's review petitions against the 2024 verdict that gave Adani Green a force-majeure extension, a Rs 4.79/unit tariff and a refund of liquidated damages. With the Supreme Court already having turned CESC away, the discom is out of options and the tariff stands firm.

8A discom can't dock one contract's dues from another's bills, APTEL rules
In a dispute over a 2013 Karnataka PPA, APTEL held that a trader carries a generator's scheduling and deviation risk only if the contract says so, and struck down a discom's move to set off Rs 1.56 crore from unrelated invoices. The sums are small; the principle - no cross-contract set-off - is what traders and lenders will hold onto.

8APTEL may send an Andhra wind-tariff order back, calling the regulator's ruling 'perfunctory.'
Hearing Green Infra Wind Solutions' appeal, APTEL called APERC's 2021 order cryptic and without reasons, and has asked the parties to show cause on 5 August why it should not be remanded for a fresh, reasoned decision - a proposed remand, not yet ordered. The developer was contracted at Rs 4.84 a unit but has been paid an interim Rs 2.43. It keeps a long-running Andhra renewable-payment fight alive and signals the tribunal's impatience with the state regulator.

8Two Delhi waste-to-energy PPAs are a week from sign-off
DERC reserved orders on power-purchase agreements for the Narela-Bawana and Ghazipur municipal-waste plants, directing the parties to finalise within a week. Small in megawatts, but it advances Delhi's waste-to-energy offtake, which has crawled.

8The rest of the state docket
UPERC is weighing whether Jaypee's Noida township must convert to multi-point supply (next 20 August) and whether "EMI" on rescheduled genco dues must carry interest (Bajaj Energy/LPGCL, listed today); routine UPPCL hearing notices go to mid-August.
Details
8India added a record amount of renewables in 2025 - almost all of it solar
IRENA's 2026 data puts India's additions at about 46 GW for the year, nearly 38 GW of it solar, taking capacity to 250.5 GW and keeping India third in the world. The pace of solar is the headline; the thinness of everything else - wind, storage, firm capacity - is the footnote that matters more each month.

8A record hour for renewables, and the same week's reminder of their limits
Wind and solar met a record 42.79% of demand at one point on 13 July, yet two days later undershot their own schedule by about 102 MU, and Gujarat curtailed thousands of megawatts to hold the grid steady. The record and the miss are one story: plenty of renewable energy when the weather cooperates, and a firming-and-forecasting gap when it doesn't.

8MNRE tightens the gate on new wind-turbine models
An MNRE memo bars commercial deployment of wind-turbine models not yet on the approved ALMM list, allowing only pre-enlistment test prototypes. It pulls wind OEMs toward the same list-based discipline solar already lives under - a small rule with real bite for anyone trying to field a new machine.

8Courts leave a set of renewable generators under the older deviation rules - for now
High courts in Karnataka and Madras have directed that CERC's 2014 deviation-settlement regulations, not the stricter 2024 ones, apply to certain renewable generators pending further orders. It reads as technical, but which regime applies decides real money for RE plants managing grid-support penalties.
Details
8Adani Power's 25-year, 1,600 MW Maharashtra supply deal
The biggest single commitment of the day, coal linkage included.

8GIPCL's Rs 6,000-crore lignite plan and possible equity raise
A rare, detailed roadmap from a state genco.

8EMMVEE's first results as a listed company are strong
The Karnataka solar manufacturer reported Q1 revenue of Rs 1,555 crore (up 51%) and PAT of Rs 380 crore (more than double), with a record margin and a 9.9 GW order book. It is a clean read on how well domestic module makers are doing under ALMM protection: the demand is there and the margins are widening.

8Sterling and Wilson takes Shell to arbitration over an Australian solar farm
The company's Australian subsidiary has filed for arbitration against Shell's Australian arm in London (LCIA) over the Gangarri solar project's EPC and O&M contracts, claiming - depending on scope - about AUD 28 million plus USD 1.6 million (roughly Rs 170 crore), or on a reduced reading about AUD 21 million plus the same USD claim (nearer Rs 130 crore). For a company its size the sum is meaningful but not defining; the more telling part is the recurring execution risk in its overseas order book.

8IEX moves to unlock its gas-exchange stake
IEX's associate, the Indian Gas Exchange, filed its draft IPO papers, with an offer-for-sale of up to about 16.7 million shares that includes IEX trimming its holding - a value-unlocking event to track as the listing proceeds.

8A small solar-cell maker's headline profit jump is mostly a standalone effect
Onix Solar reported standalone Q1 profit about 20 times a year earlier - about Rs 21 crore against Rs 1 crore - but on a consolidated basis the jump is only about three times, and consolidated revenue actually fell year on year. The standalone spike came largely from an inventory drawdown rather than trading, so it flags an accounting quirk more than real momentum. Worth a watch as it builds out cell manufacturing, but the group numbers are the ones to read.

8India's installed capacity crosses 54% non-fossil
The milestone, and why the capacity share flatters the evening-peak reality.

8Kalpataru confirms a dividend but draws institutional pushback on two resolutions
At its AGM, Kalpataru cleared a Rs 11 dividend, but its resolution seeking authority under Section 180(1)(a) - to dispose of the undertaking or create security, not to raise borrowing limits - passed with only about 87% institutional support, and a director's re-appointment drew about 9% of institutional votes against. Minorities, but notable ones for a company leaning on debt to grow.

8Borosil Renewables takes a small warrant-conversion inflow
The solar-glass maker allotted shares on warrant conversion for about Rs 12 crore - routine, and small for the company, noted for the record.

8Results diary
Board meetings to approve Q1 results: Bharat Coking Coal (21 July), IEX (23 July, with an analyst meet the next day) and Coal India (27 July, with a possible interim dividend).

Ratings Watch

8Macquarie exits Vibrant Energy; Inox's group takes over and repays the lenders
ICRA withdrew four ratings after the change of control.

8A captive-solar pool holds its rating, but a regulatory cloud sits over it
CARE reaffirmed CARE A- on the nine-company, 100 MW Maharashtra restricted group backed by Partners Group. The live risk is not the assets but a stayed Maharashtra banking-charge order: about 16% of the group's output is banked by off-takers, so an adverse final ruling could hurt. The rating is steady; the regulation is the variable.

8A North-East distribution franchisee stays in default
Feedback Energy Distribution (Meghalaya and Tripura) remains at CARE D on about Rs 319 crore of facilities and has gone non-cooperating with two agencies - a distress marker in the franchisee model, small in absolute terms but total for this company.
Details
8Nearly 9,000 MW lost at Khavda in May, with safeguards missing
The compliance failure, not just the trip, is the point.

8The eastern grid operator opened tie-lines by hand in June
A last resort used because the automatic defences still aren't ready.

8Ancillary and deviation settlements: mostly housekeeping, one cost that bites
June's spot-despatch accounts left generators owing the pool modest net sums - about Rs 32 crore in the South, Rs 15 crore in the North, small money in system terms. A Rs 1,281 crore retrospective figure sounds huge but is a billing re-computation being unwound, not new money. The number that actually matters is the East's part-load compensation: Farakka alone is owed about Rs 147 crore for running below efficient load - a real, recurring cost of keeping thermal flexible for the renewables.

8A Rajasthan solar corridor is one contingency from losing all its generation
NRPC's 245th operations committee flagged that a 765 kV Bhadla–Sikar outage would, under a single further fault, "lose all the generation" on the corridor, and warned of August export curtailments up to about 4,000 MW on Rajasthan lines still under construction. It is the transmission-lag problem in miniature: the panels are up, the wires to move them safely are not.

8Parliament and people
The Lok Sabha Standing Committee on Energy meets 23 July for a briefing by MNRE on the Green Energy Corridor renewable-evacuation programme; other PSU board moves in the day's filings were routine.
Details
8The real-time market price climbed from about Rs 2.75 a unit on 9 July to Rs 7.36 on 16 July, and the green day-ahead market hit its Rs 10 ceiling on 15 July. Yet the physical grid had power to spare - costly gas stayed switched off, wind and solar were backed down, and the system spent the day regulating downward. Details
8The Ministry of Coal opened the online registration portal for coal exchanges on 15 July, backed by the 2025 mining-law amendment and the new Coal Exchange Rules. It is the first step toward buying and selling coal on a market with price discovery and settlement, instead of only through allocations and long-term contracts. Details
8Adani Power has signed a 25-year agreement to supply 1,600 MW to Maharashtra's MSEDCL from a new 2×800 MW ultra-supercritical plant, with coal allotted under the government's SHAKTI policy. It locks in a quarter-century of assured revenue and confirms the group's next big thermal build. Details
8Delhi's regulator has moved the power-purchase cost adjustment from case-by-case approval to an automatic formula, and disposed of the discoms' pending quarterly petitions. In the first month under it, May's surcharge worked out well above the old 10% ceiling - 25% at BSES Rajdhani before the commission capped recovery at about 18%. Details
8Telangana's usable Krishna-basin storage is down about 92% from a year ago - Srisailam holds roughly 10 TMC against 184 last year. With this little water this deep into the monsoon, the state is leaning on thermal and the exchange to keep the lights on. Details
8A disturbance at the Khavda renewable complex on 13 May tripped 17 high-voltage lines and knocked out about 8,963 MW of renewable generation almost instantly, dragging the national frequency down to 49.39 Hz. A committee review now finds most wind plants there did not provide the fast frequency response the grid code requires. Details
8When four eastern states overdrew heavily on 26 June and ignored repeated warnings, the region's operator opened interconnecting tie-lines as a last resort. The same committee papers show none of the East's five islanding and black-start schemes is yet operational. Details
8Non-fossil sources now make up 54.18% of India's installed power capacity, 297,369 MW of 548,858 MW at end-June. Yet of the 6,504 MW added in June, all but 760 MW was renewable - the thermal fleet has almost stopped growing, even as it still carries the evening peak. Details
8ICRA withdrew its ratings on four Vibrant Energy captive-renewable companies on 15 July, all after a March change of control. Macquarie's roughly 93% stake has passed to the INOXGFL group, and the banks have been paid off. Details
8On its Q4 call, GIPCL guided to Rs 6,000 crore of capex for a new 750 MW lignite plant, said blended EBITDA should reach Rs 950–1,000 crore as its Khavda solar ramps up, and flagged a possible equity raise. It is also repurposing gas units that have sat idle for six years into battery storage. Details
 For reference purposes the website carries here the following tenders:
 8Tender for reconductoring using covered conductor Details
 8Tender for empanelment of agencies for new 33/11kV substation, additional /augmentation of PTR Details
 8Tender for supply of tube modules Details
 8Tender for supply and installation of industrial AC for Kiosk Details
 8Tender for supply of 750 Nos jumper cone for 500 kV ACSR bersimis conductor Details
 8Tender for repair restoration of damaged existing protection works Details
 8Tender for replacement of damaged parts of HVAC system Details
 8Tender for civil foundation works for installation of 08 nos of 33 kV outdoor bay along with 33 kV second main bus Details
 8Tender for fabrication, galvanizing, testing, supply and delivery at site of 33 kV structure Details
 8Design, manufacture and supply of energy efficient distribution transformer Details
 8Tender for rerouting and reconductoring of 11kV line Details
 8Tender for constructing 11 kV double circuit line Details
 8Tender for manufacturing, testing and supply of ISI marked 11 kV XLPE underground cable 300 sqmm Details
 8Tender for supply of hot dip galvanised steel stay sets Details
 8Tender for construction of yard foundation cable Details
 8Design, engineering, supply, erection, testing and commissioning of 220kV and 33kV GIS transformer/reactor bays along with associated works Details
 8Tender for work of wire netting and roof bolt support Details
 8Tender for additional electrical work Details
 8Tender for supply of various insulation materials for boiler Details
 8Tender for supply of neoprene rubber seals for annual maintenance of gates Details
 8Tender for work of complete overhauling of 20 cumecs capacity pump Details
 8Tender for laying of 11kV UG cable Details
 8Tender for rate contract for work of laying of various size of cable Details
 8Tender for supply, installation, testing and commissioning of secondary cooling centrifugal water pump motor set of power house Details
 8Design, engineering, procurement and construction of power house and associated works for 640 MW ISP OSP pumped storage project Package Details
 8Tender for supply of matching material Details
 8Tender for supply of matching material for maintainance Details
 8Tender for shifting and dismantling of 33kV feeder Details
 8Design, manufacture, testing and supply of 33 kV outdoor vacuum circuit breaker Details
 8Tender for overhauling of 132/3.3 kV, 7.5 MVA station transformer and 132/11kV, 48 MVA generator transformer Details
 8Tender for supply and commissioning contract of 100TR water cooled chiller Details
 8Tender for supply of DSS pumps with installation and commissioning supervision services Details
 8Tender for electrical works for capital items Details
 8Tender for laying of HDPE pumping main, with 355 mm OD HDPE pipes supplied Details
 8Tender for general civil work like rolling shutter overhauling, UPVC line Details
 8Tender for routine, preventive and breakdown maintenance work of complete air conditioning system Details
 8Tender for repair of defects of existing PU coating of NDCTs Details
 8Tender for procurement of sam turbo water pumps spares Details
 8Design, supply, erection, commissioning and testing of control system Details
 8Tender for waterproofing and allied work on bunker floor terrace Details
 8Tender for procurement of high alumina castable refractory grade A and P and ceramic insulation pad for boiler Details
 8Tender for supply of LTSH and economizer coils for boiler Details
 8Tender for supply of various types of pressure and temperature switches Details
 8Tender for supply & commissioning of various suspension magnet with its control panel at coal handling plant Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
 8Tender for work of providing service of online oil purification / filtration of servo mesh SP-320 oil of coal mill Details
 8Tender for work of rubber lining of various equipments, pipes and fittings Details
 8Tender for supply of various consumables items Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for overhauling and refurbishment of 03 nos. cartridges of boiler feed pump Details
 8Tender for biennial maintenance contract for miscellaneous civil work Details
 8Tender for servicing of different equipments during Details
 8Tender for overhauling repair maintenance of all hoisting arrangement of rope drum motors Details
 8Tender for shifting of 33 kV line etc Details
 8Tender for work for shifting & construction of H.T. & L.T. line Details
 8Tender for erection of 1.1 Kms S/C 33 kV line with ACSR DOG conductor Details
 8Tender for supply of LT three phase X arm channel Details
 8Tender for supply of LT metal parts Details
 8Tender for reconductoring, conversion and constructing LT line with LT ABC Details
 8Tender for constructing 2km new LT line and 2km conversion of 2wire OH line to 4wire OH line Details
 8Tender for construction of cable trench work at 110kV substation Details
 8Tender for supply of coverd conductor 11kV 99 sq.mm AAAC with accessories Details
 8Tender for procurement of pilot based small scale standalone decentralized battery energy storage systems Details
 8Tender for procurement of pilot based small scale standalone decentralized battery energy storage systems including 15 year O and M for 12 MW 48 MWh at identified 33 kV/ 11 kV grid substations Details
 8Tender for new construction of 33/11 kV sub station Details
 8Design, manufacture, testing at manufacturer works supply and delivery of ACSR panther Details
 8Tender for supply and delivery of flat twin core LT, PVC cables of size Details
 8Tender for O&M of hydel channel Details
 8Tender for work of overhauling of 132KV/220 kV CB poles Details
 8Tender for work of providing & fixing of main switch fixed contact assembly for 220 KV, 2000A, double break isolator Details
 8Tender for annual maintenance contract for the work of refilling & providing new spares for existing fire extinguishers available Details
 8Tender for replacement of RCC structure by lattice type structure of various 400/220 kV equipments Details
 8Tender for work of providing & fixing of fire bucket stand with shed and fire buckets at various 220kV & 132kV substation Details
 8Tender for providing water proofing treatment by shield of 2mm DFT Details
 8Tender for rate contract for the work of overhauling and servicing of 420 kV, 245 kV & 145 kV circuit breaker Details
 8Tender for work of measurement of tower footing resistance of 220/132kV lines Details
 8Tender for work of anti-corrosive coating/painting with chemical resistive coating/painting of power transformers Details
 8Tender for work of supply, installation, testing and commissioning of advanced ESE type LCAT system Details
 8Tender for work of supply, installation, testing and commissioning (SITC) of intelligent addressable hot redundancy based continuously available Details
 8Tender for work of providing & fixing of manual operated gear box for 245/145/33/11kV isolators Details
 8Tender for establishment of 132/33kV substation Details
 8Tender for supply and application of industrial epoxy coating in condenser tube sheet & water box Details
 8Tender for supply of hydraulic accumulator, bladder, nitrogen charging kit & fittings Details
 8Tender for supply of PF pipe collar, victaulic coupling & MRC spares Details
 8Tender for work of repairing of various pulleys of conveyor belts Details
 8Tender for misc. civil work Details
 8Tender for miscellaneous civil works Details
 8Tender for supply of portable cabin for weighbridge Details
 8Tender for work of overhauling & servicing of 6.6 kV VCBs, VCs & 415 V ACBs of various Details
 8Tender for supply of various types of bushings for 250 MVA, 420/15.75 kV, generator transformers Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8SECI Awards 2 GW Wind Tender to 12 Developers at Tariffs of Rs. 3.78–3.85/Unit Details
 
8India adds record 29 GW solar, wind in first half of 2026 Details
 
8Ayana Renewable Wins 50 MW Wind Project in SECI Tender at Rs 3.85/kWh Details
 
8Gujarat Dominates India’s Rooftop Solar And Wind Landscape Details
 
8Stricter Grid Rules May Slow Renewable Energy Investments In India – Report Details
 
8Power demand in TN hits record 21,724 MW in unusual July surge Details
 
8Tougher grid penalties threaten solar, wind investment returns Details
 
8Energy Security and Climate Realism Usher in Coal’s Rise Details
 
8What is behind-the-meter power and how is it reshaping the data centre industry Details
 
8The real risk of the energy transition is delaying it: Lessons from India Details
 
8India's clean energy boom: Why the City should be paying attention Details
 
8India's Power Grid Is a New Site Selection Variable Details
 
8Power export to India increased upto 1,650 megawatts Details
 
8El Nino effect severely impacts India's hydropower generation, pushing up power demand and coal reliance Details
 
81,890 smart meters installed in Peren division: Power Department Details
 
8MHI’s 10 GWh battery tender opens new growth market for India’s BESS sector Details
 
8AMPIN Energy Transition signs PPA for 199 MW/800 MWh FDRE project Details
 
8Arunachal Signs MoU with Norway for India’s First River Kinetic Energy Project Details
 
8Nepal to export 550MW more electricity to India under new agreement Details
 
8Prototype Fast Breeder Reactor (PFBR) At Kalpakkam Achieves First Criticality: What It Means For India’s Nuclear Energy Plans Details
 
8India Weighs Opening Thorium Sector To Private Firms To Power Nuclear Energy Push: Report Details
 
8Files relating to India’s largest nuclear power plant Kudankulam exposed in data breach Details
 
8The 3 power EPC giants holding Rs 1.18 lakh crore in unexecuted orders Details
 
8DVC Appoints IAS Rajesh Pandey as Chairman for 5 Years Amid Power Sector Expansion Plans Details
 
8India Adds Record 29 GW Renewable Capacity in H1 2026 Details
 
8India Invites Bids for 10 GWh Grid-Scale Battery Manufacturing Details
 
8Power Stock Jumps 17% After Reporting 254% Revenue Growth in Q1 FY27 Details
 
8India Eyes Geothermal Expansion Through Baker Hughes Pact Details
 
8Adani Power Stock Update: Share Price Slips 1.25% Intraday Details
 
You can also click on Newsclips for more Details
8APDCL puts 3,002 transformers through non-stop quality checks before it pays Assam's power distribution company wants to buy 3,002 energy-saving transformers, worth about Rs 96 crore. Before paying, it can inspect the factory, re-test units in a lab, and even cut open random finished pieces — and if the mass units don't match the approved sample, the whole lot is rejected. The maker also faces fixed prices and delayed payment, which locks up its money.

 

8RVPN wants bidders to plan for 6,020 km of conductor, but won't promise to buy that much Rajasthan's transmission utility is buying ACSR conductor (the wire strung on power lines) on a rate contract worth about Rs 208 crore. Most bidders must quote for the full 6,020 km, yet the utility can order far less — so a supplier may build capacity and stock that never gets used. A price formula covers aluminium and steel changes, but freight and interest costs are left with the supplier.

 

8JdVVNL puts 600 MWh of batteries across 150 substations and makes private firms run them for 15 years Jodhpur's power distribution company wants battery storage — but instead of one big site, it is placing 150 small units (1 MW/4 MWh each) inside its local grid, worth about Rs 630 crore. A private developer must build, own, and run each plant for 15 years and earns only through a bid-decided rate. The hard part is not the day-one cost but keeping the batteries healthy for 15 years.

 

8KPTCL packs a substation, 90 km of lines and 7 bays into one job — and no one showed up to the pre-bid meeting Karnataka's transmission utility wants one contractor to build a new substation plus nearly 90 km of power lines and 7 connection bays, worth about Rs 143 crore, in 24 months including the monsoon. At the pre-bid meeting — where bidders usually ask questions — nobody attended, an early sign of weak interest. A key clause explaining how the quoted rate applies to each item was also quietly deleted.

 

8MPPGCL opens price bids for a job to watch its coal from the mine all the way to the plant Madhya Pradesh's power generation company wants a contractor to supervise coal at NCL mines — check quality, cut down shortages, and track it by rail up to the power stations. The tender has now reached the price-opening stage, but the papers don't show how much of the shortage loss the contractor must bear. That single point decides whether this is a light watchdog job or a heavy money risk.

 

8MPPGCL makes its coal agent pay for shortages, not just report them
Madhya Pradesh's power generation company wants one contractor to handle about 200 lakh MT of coal over two years — loading, quality, and rail movement — all for one rate, worth about Rs 112 crore. The catch: if monthly transit loss crosses 0.80%, the cost of the missing coal is recovered from the contractor. That loss can be far bigger than the fee the contractor earns.

 

8NEEPCO's 240 MW hydro project changed 18 times before bids closed
NEEPCO wants one contractor to build the full machinery of a 240 MW hydro plant in Arunachal Pradesh (three 80 MW units) and link its controls with the downstream Tato-I plant. The tender was changed 18 times, showing the scope was still not settled even as bids came in. A contractor who quotes low could lose money once the complex linking work begins.

 

8NTPC Green changes a 3,300 MWh battery tender six times, one change coming after the first deadline NTPC Green Energy wants a contractor to build one of India's largest battery storage systems, next to the big Khavda solar plant. The deadline moved eight days, and the sixth change came a day after bids were first due — so bidders must recheck which papers and specs still apply. With so many changes, missing one updated document could sink a bid.

Details
8UPPTCL's Rs 80.47-cr Sirsira GIS tender reworks eligibility, experience and pricing units before bids open on 30 July
Four corrigenda have reshaped UPPTCL's turnkey 400/220/132 kV GIS substation tender at Sirsira, Raebareli, well beyond a date change. LLPs are now expressly eligible, and qualifying experience has been split by voltage and technology. Several 245 kV GIS bay items shift from "No." to "Set," recasting how complete packages must be priced. With the deadline now 30 July 2026 and a 10% CPBG on GST-inclusive value, the pricing contest is already under way.

 

8GETCO's Rs 245-cr Sagapara STATCOM ties bidders to station-level guarantees before a reverse auction sets the price
GETCO's turnkey ±125 MVAR STATCOM at the 220 kV Sagapara substation has been extended , but the technical addendum matters more than the date. Losses are dropped from bid evaluation yet remain a binding CEA-aligned design duty. 98% guaranteed availability and forced-outage limits now attach to the whole station, not just the converter. With four qualification routes and a reverse auction to follow, the contest is how far bidders will underwrite network risk.

 

8BHEL's coal-and-limestone handling EPC for the Lakhanpur ammonium-nitrate project moves the goalposts repeatedly before bids close
BHEL's EPC package for the coal and limestone handling plants at BCGCL's coal-to-2,000 TPD ammonium nitrate complex has shifted its deadline four times to 22 July 2026. Two sampling units were relocated onto conveyors and 100% standby capacity was mandated. A fresh 827-page electrical and C&I revision now binds the bidder without added cost or time, while a stricter-clause-prevails rule pushes interpretation risk onto the contractor. A 27-month build plus five-year O&M make this a lifecycle exposure, not a supply order.

 

8RVPN's Rs 208-cr Panther conductor rate contract makes bidders qualify for 6,020 km while guaranteeing no minimum purchase
RVPN's rate contract for 6,020 km of ACSR Panther conductor carries an estimated value of Rs 208.82 crore, yet guarantees no minimum call-off while requiring most bidders to quote the full quantity. A raw-material formula protects aluminium and steel but leaves freight, financing and conversion costs exposed. Delivery can also be rescheduled at the utility's discretion. A drafting conflict between "30+7" and "54+7" strand construction sits unresolved, and bidders should clear it before submission on 19 August 2026.

 

8AEGCL's five-substation transformer package bars joint ventures and offers no advance, turning delivery into a working-capital test
AEGCL's Package T-4 for 132/33 kV, 50 MVA transformers across five substations has been extended to 23 July 2026. Pre-bid clarifications trimmed scope — no parallel-operation duty, no BDV or DGA kits, no water-spray fire system. But AEGCL held firm on the terms that hurt: no advance payment, a 10% performance security, a five-year warranty and LD calculated on the whole contract price. With joint ventures prohibited, a single well-capitalised OEM must carry manufacturing, logistics and multi-site commissioning alone.

 

8MAHAGENCO's 300 MW Phase-II solar bundles land, evacuation and ten-year O&M into one contract, anywhere in Maharashtra
MAHAGENCO's 300 MWAC Phase-II ground-mounted solar programme places land, full EPC, evacuation to an MSETCL substation and ten years of O&M under one contractor, with each bidder capped at 100 MWAC. Three qualification routes widen entry, but per-MW financial thresholds and a fixed 15 MWAC operating reference filter out smaller players. A frozen three-member consortium must survive past the O&M term, turning a bidding group into a decade-long commitment. A reverse auction will then compress the price against very different site assumptions.

 

8BHEL locks in a balance-of-system partner for NTPC REL's 1,200 MW Anantapur solar before it has even won the job
BHEL's Solar Business Division is selecting a balance-of-system partner for a 1,200 MW project at Anantapur, owned by NTPC REL, before the main award is secured. The capacity is split into two 450 MW blocks and one 300 MW block. Prices stay firm to completion with no escalation, yet any reduction BHEL concedes to its customer must pass straight through to the vendor. With modules and trackers procured separately and reverse auction ruled out, bidders carry pre-award risk over an outcome they don't control.

 

8BHEL widens the entry gate for its Bandhabal cryogenic ASU but tightens the lifecycle guarantees behind it
BHEL's global tender for a cryogenic air separation unit serving a 2,000 TPD coal-to-ammonium nitrate project at Bandhabal, Jharsuguda, has lowered its qualifying reference from 1,000 to 500 TPD oxygen. It also stretched the look-back to 15 years and cut the operating record to one year, clearly widening the vendor pool. But 98% guaranteed availability, utility-overconsumption damages and a 21-month completion deadline push reliability risk deep into the contractor's account. With the deadline now 31 July 2026, bid quality will matter more than headline price.

 

8NTPC's two-transformer Rihand package tightens the entry gate with local-content, conflict-of-interest and insolvency tests
NTPC's package for two 201.67 MVA, 20/400 kV generator transformers at Rihand Stage-I restricts bidding to Class-I local suppliers at 60% local content. Declared reference plants are locked against later substitution, and eligibility stays under review up to award through conflict-of-interest and insolvency clauses reaching parents and technology providers. No owner estimate is published, leaving the Rs 1 crore EMD and 10% security without a benchmark. Bidders carry a 180-day price hold and only partial change-in-law relief on a bidirectional design.

 

8UJVNL's Rs 110-cr Kulhal RMU gives bidders more time but no relief from a 25% turbine-performance penalty on a 1975-vintage station
UJVNL's turnkey renovation of the 3×10 MW Kulhal hydro station has been pushed to 14 August 2026 — its third extension, adding 29 days in all. Yet the corrigendum touches only the calendar. The risk transfer stands: reverse engineering, refurbishment and integration of a five-decade-old plant under one contractor, with turbine-performance LD reaching 25% of the turbine package. Security is heavier too — 15% versus 10% — for bidders leaning on manufacturer credentials, so more time brings no softening of the exposure.

Details
8A nine-engine opening rewrites the technology contest
A revised engine configuration has widened the field, but the most difficult obligations have become sharper rather than easier. Hydrogen testing, tighter emission guarantees and remote-island logistics now converge inside a single EPC risk envelope. The decisive issue lies in which bidders can turn that flexibility into a bankable and technically defensible offer.

8A ten-package land exercise puts 303.50 km of transmission corridors on a 15-day valuation clock
Three Gujarat packages reveal a procurement structure designed to accelerate decisions across hundreds of transmission-line locations. The commercial contest will not be governed by L1 pricing alone, as award sequencing and capacity controls alter how bidders can pursue the work. The most consequential risk sits inside the interaction between rapid delivery, variable quantities and fragmented district-level valuations.

8Rs 315 crore transmission package signals a broader grid expansion strategy while raising execution stakes
A seemingly routine transmission package conceals a procurement structure that reshapes execution responsibility far beyond conventional EPC contracts. The engineering choices and commercial framework point towards a much larger strategic objective than simple capacity addition. The implications extend well beyond this project and could influence how similar transmission packages are structured in the coming years.

8Large-scale PCC pole procurement sharpens execution standards as logistics, manufacturing depth and financial discipline emerge as decisive competitive differentiators
A routine distribution-material procurement quietly introduces commercial signals that extend far beyond concrete poles. Several provisions reshape how manufacturers will compete on execution capacity, financial strength and delivery assurance rather than price alone. The document hints at a procurement philosophy that could influence future utility sourcing decisions across Rajasthan.

8Final commissioning strategy tightens execution accountability as critical power project enters its decisive phase
The procurement is built around far more than routine commissioning activities. Several contractual provisions quietly reshape execution risk, commercial exposure and project responsibility in ways that deserve closer examination. The implications extend well beyond this individual package and could influence how similar projects are procured going forward.

8Qualification rules evolve as execution accountability remains firmly intact
A series of amendments quietly reshaped who can compete without altering who ultimately carries project risk. The revised framework broadens access while tightening accountability in unexpected ways. The implications extend well beyond a routine hydroelectric EPC procurement.

8Rs 1,723 crore pumped-storage EPC package sets the stage for a high-stakes contest where execution strategy may matter as much as price
A major pumped-storage package is reshaping the balance between engineering responsibility and commercial competition. The bidding framework introduces several provisions that could influence both pricing behaviour and execution strategy. What ultimately determines the winning advantage extends well beyond the quoted number.

8Repeated technical clarifications reshape EPC execution while commercial discipline remains firmly intact
Successive revisions have quietly altered the engineering assumptions behind this EPC package without changing its contractual backbone. The most consequential developments are buried inside technical clarifications rather than headline corrigenda. Their combined impact could influence pricing, execution strategy and bidder competitiveness far beyond the formal amendments.

8Rs 109 crore transformer tender places factory output under a five-year performance test
A large indoor-transformer procurement has been corrected after a value description magnified its apparent scale by 100 times. Behind the revised amount sits a contract that tests every supplied unit for losses and can reject an entire lot over one sampled failure. The decisive risk is buried not in the headline quantity, but in the interaction between rate matching, long guarantees and post-delivery quality control.

Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8LPG
8Ammonia
8Coal & Coke
Click on Reports for more. Details
8Telangana's usable Krishna-basin storage stood at about 39.6 TMC on 15 July 2026, roughly 86% below the same date last year, with Srisailam live storage collapsed to 10.3 TMC from 170.1 TMC and Nagarjunasagar at 6.2 TMC from 90.4 TMC. So little water this deep into monsoon shifts more of Telangana's July load onto thermal and market power, a hydro shortfall that dovetails with the state's coal-hit Yadadri outages and the firm exchange prices. Details
8Uttar Pradesh Power Corporation (for September) and West Bengal's WBSEDCL (for August) each issued single-side reverse-auction circulars on the Hindustan Power Exchange - and, per the circulars, in parallel on IEX and PXIL - weighted toward evening-peak blocks. Two large state utilities lining up short-to-medium-term peak power through competitive auctions signals discoms bracing for the same evening-ramp scarcity now visible in the spot market. Details
8GERC has once more extended the flat Rs 1.50 per unit banking charge for green open-access consumers - to 31 August 2026 - and rejected industry's demand for a lower 8% in-kind banking charge, while still not putting in place the cost-based framework the Forum of Regulators model and stakeholders have sought since 2024. An 'interim' arrangement renewed repeatedly is now the de facto regime for Gujarat's green open-access economics. Details
 1 2 3 >  Last ›

Showing 1–50 of 340 items