All content in this website is sourced legitimately

archiveForm.jsp
Archives
All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Year: Month:

Jul 2018
Jul 19 : Upcoming opportunities in the Power Sector

8Project Name: Super-Critical Thermal Power Brownfield Project
8Project Cost: 8000 crores
8Project Description: Owner along with an EPC contractor is carrying out the construction activities of the switch-yard area in a  brownfield 1980 MW super-critical complex at the existing thermal power facility. Currently, the project consultant has completed the site survey and selection of the area for implementation of an FGD. Further bids are expected soon.
8Project Event: RFQ for design, engineering, supply, erection, testing, and commissioning of a flue gas desulphurization system is expected by the end of August 2018.
8Expenditure Approval: 2014
8RFQ Date: 26/Aug/2018
8Release Date: 28/Aug/2018
8Start Date: 31/Dec/2014
8Completion Date: Dec/2018
Click here for more information

8Project Name: Greenfield Super Thermal Power Project
8Project Cost: 15000 crores
8Project Description: Promoter along with BTG and ESP contractor is carrying out the construction activities in a 1320 MW greenfield super-critical thermal power plant. Further RFQs are expected soon.
8Project Event: RFQ for procurement of mobile crane and crane of capacity 30 MT and 20 MT respectively is expected by the mid-August 2018, instead of July.
RFQ for the supply, installation, erection, and commissioning of a flue gas desulphurization unit (FGD) is expected in the August 2018.
RFQ for an annual maintenance contractor of uninterrupted construction power worth Rs. 2 crores is expected by the mid-August 2018.
8Expenditure Approval: Q1:2013
8RFQ Date: 18/Aug/2018
8Release Date: 20/Aug/2018
8Start Date: Q3:2013
8Completion Date: Q3:2019
Click here for more information

8Project Name: Greenfield Thermal Power Project
8Project Cost: 830 crores
8Project Description: The owner along with an EPC contractor is carrying out mechanical completion activities in a 1600 MW thermal power station. Further bids are expected soon.
8Project Event: RFQ for balance civil works for erection and commissioning of FGDs is expected by the end of August 2018.
8Expenditure Approval: Jan/2008
8RFQ Date: 22/Aug/2018
8Release Date: 25/Aug/2018
8Start Date: Q3:2008
8Completion Date: Sep/2018
Click here for more information   Details

Jul 19 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Tender for Balance Civil works of Ash Handling System, AWRS System & Development of Fly Ash Silo Area Details
8Supply, Installation & Commissioning of Equipment for Set Up of Pilot Scale Test Facility for Air Cooled Condenser Details
8Supply, Fabrication and Erection of 04 Nos. Fly Ash Silo Details
8Tender for Supply of HRC Fuse with Base Details
8Tender for Purchase of 645 Nos. of 11 KV CT/PT Outdoor units Details
8Supply of LT Areal Bunched Cables Details
8Tender for the Supply of Traveling water screen suction header accessories Details
8Supply and Erection of Materials for Strengthening of Seal Trough in North and south side of Bottom Ash Hopper Details
8Construction of 132 KV Line Bay at 220 KV S/S Details
8Tender for the Work of Restringing of Conductor of various EHV Lines Details
8Supply of Accessories required for HT Aerial Bunched Cable Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
 
8High coal prices, weak rupee leading to a crisis in power generation firms Details
 
8France’s Engie appoints Rothschild to find a buyer for Indian solar biz Details
 
8Exclusive: General Electric's power unit faces threat in Saudi Arabia Details
 
8Saudi Electricity Co in talks for international bond issue - sources Details
 
8LG Chem to build $1.8 bln EV battery plant in China Details
 
8Tata Power launches EV stations in Hyderabad Details
 
8China's CGN acquires 75 percent of Swedish wind farm: Xinhua Details
 
8 BYPL signs agreement to source 100 MW wind power Details
 
8Godawari Power gets 1.15 lakh MT of long-term coal supply Details
 
8No coal shortage for power sector: Goyal Details
 
8India's coal demand rose 7.5 per cent to 900 million tonnes in 2017-18: Piyush Goyal Details
 
8Government looks to sell viable infrastructure projects to private companies Details
 
8London Metal Exchange moves further towards launch of battery-grade lithium contract Details
 
8No power score: Telangana discoms 'moderate' on cost, billing Details
 
8JMC to invest Rs 100cr in LED street lights to save energy Details
 
8Uttar Pradesh government subsidises rooftop solar plants Details
 
8Enforcement Directorate files charge-sheets in seven coal scam cases Details
 
You can also click on Newsclips for more
  Details

Jul 19 : Power Sector : Briefs

8R&M of air preheater and fans is coming up in a 500 MW thermal power station: Find out the project owner.
8Annual Maintenance Contractor of ESP and related ducts required in a 500 MW thermal power station: Find out the project owner
8Annual Maintenance Contractor of air preheater required in a 1200 MW thermal power station: Find out the project owner
8SECI likely to extend the RFQs for RFS bidding for the solar PV Project in Assam: Find out the issue.
Click on details   Details

Jul 19 : Gas based power becomes too expensive: 10 units shut down

An operator has shut down 10 gas-fired units as the cost of power made it ineligible under the merit order power offtake system
8Coal fired power and hydropower seems to have plugged the gap for now
8Find out more on what is going on
Click on Details for more   Details

Jul 18 : Software Updates : Power Projects

8Project Name: Super-Critical Thermal Power Expansion Project
8Project Cost: 8000 crores
8Project Description: Owner along with BTG and BOP contractor are carrying out construction activities for a 660 MW super-critical thermal power expansion unit at its existing thermal power complex. Further bids are expected soon.
8Project Event: RFQ for design, supply, installation, construction, and commissioning of an FGD unit is expected by August 2018.
8Expenditure Approval: 2017
8RFQ Date: Aug/2018
8Release Date: Aug/2018
8Start Date: Jan/2016
8Completion Date: 2019
Click here for more information

8Project Name: Thermal Power Station - Long-Term Contract
8Project Cost: 3 crores
8Project Description: Promoter is getting delayed in lack of clearance from the site office for a long-term maintenance contract (LTC) for the coal handling plant equipment for the 3000 MW Thermal Power Station. Further bids are expected soon.
8Project Event: RFQs for LTC for a coal handling system equipment are expected by end of August 2018, instead of June 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 25/Aug/2018
8Release Date: 27/Aug/2018
8Start Date: Oct/2018
8Completion Date: Oct/2021
Click here for more information

8Project Name: Thermal Power Station - FGD Addition
8Project Cost: 830 crores
8Project Description: The owner is planning to install FGDs in 700 MW thermal power station. Tenders for the same is expected soon.
8Project Event: RFQ for supply, installation, construction, and commissioning of FGDs is expected by the Q4 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Q4:2018
8Release Date: Q4:2018
8Start Date: 2020
8Completion Date: 2022
Click here for more information   Details

Jul 18 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Design, Engineering, Supply, Erection, Testing and Commissioning of 02 Nos. Grizzly Feeders in CHP Details
8Tender for Purchase of Pumps for cooling system of Power House Details
8Supply, Installation & Commissioning of Continuous Ambient Air Quality Monitoring Stations Details
8Tender for Diversion work of 220kV DCDC line on turnkey basis Details
8Tender for the work of Shifting/Diversion of 220 kV D/C Line Details
8Tender for the work of Shifting/Diversion of 132 kV D/C Line Details
8Tender for Replacement of ACSR Wolf conductor in 132 KV double circuit line by HTLS conductor Details
8Tender for Stringing of second circuit of 132 KV transmission line with HTLS conductor Details
8Biannual rate contract for transformer bay Erection work & 66KV Bus Strengthening with buyback of Old Scrap Details
8Biannual rate contract for transformer bay Erection work & 66KV Bus Strengthening Details
8Tender for Annual Maintenance Contract of Battery at various Substations Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Allahabad HC to hear power generation companies’ plea against RBI circular on Aug 2 Details
8Electric vehicles have the potential to fuel India’s growth Details
8In the Sahel, solar power can help ward off extremism: official Details
8Bhushan Power Case: Wait till we rule on IBC – Supreme Court to NCLT Details
8Surprise! India now has too much electricity and it has a cost Details
8Mytrah Energy bags Maharashtra wind power project Details
8Rs 10,000 crore project to check power theft, electrify villages in UP Details
8India’s renewable energy investments topple fossil-fuel for the first time in 2017: IEA Details
8Bihar to soon conduct survey for solar power generation in flood-prone areas Details
You can also click on Newsclips for more
  Details

Jul 17 : Software Updates : Power Projects

8Project Name: Greenfield Supercritical Thermal Power Plant
8Project Cost: 20000 crores
8Project Description: Owner along with a project consultant is undertaking detailed project report activities in a 1600 MW super-critical thermal power plant. Further RFQs are expected soon.
8Project Event: EoI for a balance of plant package is expected by August 2018.
 RFQs for steam generator and steam turbine generator are expected by September 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Aug/2018
8Release Date: Aug/2018
8Start Date: 2020
8Completion Date: 2024
Click here for more information

8Project Name: Thermal Power Station - AMC contractor
8Project Cost: 3 crores
8Project Description: A JV company is preparing the bid document for an annual maintenance job contract for boiler & its auxiliaries and electrical and C&I equipment for a 2000 MW thermal power station. Further bids are expected soon.
8Project Event: RFQs for an annual maintenance contractor of boiler & its auxiliaries and electrical and C&I equipment are expected by end of August 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 25/Aug/2018
8Release Date: 28/Aug/2018
8Start Date: Q4:2018
8Completion Date: Q4:2019
Click here for more information

8Project Name: Thermal Power Station - Installation of FGD
8Project Cost: 730 crores
8Project Description: A joint venture company is planning to install FGD in 1320 MW thermal power station. Tenders for the same is expected soon.
8Project Event: RFQ for the supply of FGD (Flue Gas Desulphurisation) system main package and its electrical power supply package is expected by mid August 2018.
8Expenditure Approval: 2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q2:2020
8Completion Date: Q3:2021
Click here for more information   Details

Jul 17 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply, Installation & Commissioning of Digitally Communicable Transformer Auxiliary Monitoring System Details
8Tender for Construction of LILO on 132kV line Details
8Tender for the Supply of Mill Separator top assembly (without Deflector control and classifier assembly) Details
8Annual overhaul of Air Pre Heater- A pass and its lube oil system Details
8Tender for the Supply of Roller Journal assembly (in assembled condition) without Grinding Rollers Details
8Tender for Procurement of Bends for Hot Re-Heater Coils Details
8Tender for Replacement of Generator Protection Panels Details
8Survey, Design, Supply, Civil Works, Installation, Testing & Commissioning of 33/11 KV GIS Grid Substation on Turnkey Basis Details
8Survey, Design, Supply, Installation, Testing & Commissioning of 33/11 KV GIS Grid Substation on Turnkey Basis Details
8Tender for Erection/Dismantling/Maintenance of HT/LT Line Details
You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8NCLAT stays voting by Bhushan Power & Steel lenders on finalising bids Details
 
8Power plant will be built to meet power needs of Gautam Budh Nagar: Mahesh Sharma Details
 
8Electricity investments surpass oil, gas for second year running: IEA Details
 
8Indonesia to raise 2018 energy subsidies to keep fuel, power prices unchanged Details
 
8Warm weather could mean output cuts at German nuclear plants: traders Details
 
8Commerce Ministry recommends safeguard duty on Chinese solar cells, modules Details
 
8KP Energy, GE India tie up for 300 MW wind power project in Gujarat Details
 
8Mahagenco’s piped conveyors to get coal cleanly to its plants Details
 
8Indian Army inaugurates first mega solar power plant in Ambala Cantonment Details
 
8Essel plant to generate power from waste in Maharashtra Details
 
You can also click on Newsclips for more
  Details

Jul 16 : Power Sector Briefs

8Supply of a valve assembly required in a 1200 MW thermal power station: Find out the project owner.
8Tata Power to soon start construction work for a 250 MW of Solar Project at the Pavagada Solar Park: Find out upcoming opportunities.
Click on details   Details

Jul 16 : Software Updates : Power Projects

8Project Name: Super-critical Thermal Power Expansion Project
8Project Cost: 7000 crores
8Project Description: Promoter is planning to re-tender an EPC contract in a super-critical expansion thermal power plant at its existing facility. Further bids are expected soon.
8Project Event: RFQs for balance works on an EPC basis are expected by September 2018.
8Expenditure Approval: 2014
8RFQ Date: Sep/2018
8Release Date: Sep/2018
8Start Date: Jul/2014
8Completion Date: 2020
Click here for more information

8Project Name: Thermal Power Station Maintenance Project
8Project Cost: 6 crores
8Project Description: Owner has planned a 35-day annual overhaul in the 3000 MW thermal power station. The scope of work in the overhaul includes replacement of GRP fan blades, replacement of air preheater regenerative baskets, among others
8Project Event: RFQs for the required overhaul are expected by the August 2018.
Click here for more information

8Project Name: Greenfield Hydro Power Project
8Project Cost: 2500 crores
8Project Description: The owner is undertaking site survey activities for a 360 MW hydropower project. Further bids are expected soon.
8Project Event: RFQs for drilling and drifting works are expected by October 2018.
8Expenditure Approval: 2019
8RFQ Date: Oct/2018
8Release Date: Oct/2018
8Start Date: 2020
8Completion Date: 2024
Click here for more information   Details

Jul 16 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply of 245 KV Current Transformers with Terminal connectors and Junction Boxes Details
8Construction of 132/33kV Substation with SAS on turn-key basis Details
8Supply of 245 KV Capacitor Voltage Transformers with Terminal connectors and Junction Boxes Details
8Tender for Procurement of Insulating Mat for HT, LT Switchgear Details
8Annual Maintenance Contract for HVAC System Details
8Tender for the work of Installation of Solar Powered Pumps along with Construction of Pump House Details
8Purchase of Total Station Along with Accessories for Power Station Details
8Supply and Erection of primary air coal pipe reducer and spool piece Details
8Tender for 132 KV Switchyard Extension Package Details
8Tender for manufacture, testing, supply and delivery of 11KV Combined CT & PT(oil cooled type) Details
8Tender for the Work of supply, erection, testing & commissioning of 33kV Switchyard Details
8Tender for the Work of Repairing & Overhauling of Station transformers Details
8Annual Maintenance of 03 Nos of hydro- Generating Units Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8CleanMax Solar plans to raise $100 million Details
8Microgrids: Small steps can make a big impact Details
8Power woes push up coal imports Details
8Total global corporate funding in solar sector at $5.3 billion in January-June this year: Report Details
8Tech startups are helping India’s creaky power sector cope with the renewable energy boom Details
8ACME bags 600 MW solar power project Details
8DMRC to get green power from Rewa solar plant in two months Details
8Assam CM hands over Barak Valley coal scam to CBI Details
8Maharashtra govt to spend Rs 7,300 crore on repair of electricity poles Details
8NGOs hail Nippon Life for dropping coal finance Details
8Rs 1 crore ISRO's lithium ion cell technology gets overwhelming initial response Details
8Revamp of coal auction rules: Business-friendly reforms on cards Details
8Extra tariff enough penalty for power misuse: Delhi electricity regulator Details
8China June coal output dips to lowest since October Details
8Hybrid power unit set up at Vidyut Bhavan in Patna Details
8Gujarat power utility GUVNL scraps 500 MW wind power tender Details
You can also click on Newsclips for more
  Details

Jul 13 : Software Updates : Power Projects

8Project Name: Greenfield Hydroelectric Project
8Project Cost: 1000 crores
8Project Description: Owner's 80 MW greenfield hydel project is getting delayed. Owner will come out in package wise mode of tendering.
8Project Event: RFQs for civil and hydro-mechanical works are expected by the Q1 2019, instead of Q3 2018.
8Expenditure Approval: Q3:2019
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: 2020
8Completion Date: 2025
Click here for more information

8Project Name: Thermal Power Station - FGD Addition
8Project Cost: 300 crores
8Project Description: Owner has obtained financial approval for installation of an FGD in the 2000 MW thermal power station. Further bids are expected soon.
8Project Event: RFQs for the design, supply, installation and commissioning of an FGD are expected by December 2018.
8Expenditure Approval: Q2:2018
8RFQ Date: Dec/2018
8Release Date: Dec/2018
8Start Date: 2020
8Completion Date: 2022
Click here for more information

8Project Name: Thermal Power Station - Dismantling
8Project Cost: 30 crores
8Project Description: Promoter is preparing a closure report to retire and dismantle units in the 500 MW thermal power plant as they had aged more than 25 years. Tenders for civil work and dismantling services of various equipment are expected soon.
8Project Event: RFQs for dismantling services are expected by the November 2018, instead of Q2 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Nov/2018
8Release Date: Nov/2018
8Start Date: Q3:2019
8Completion Date: Q4:2020
Click here for more information   Details

Jul 13 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
 
8Annual Maintenance contract for Electrical maintenance of Internal & External CHP Details
 
8Tender for supply of 33KV Capacitor Bank along with associated equipments & Spares Details
 
8Expression of Interest (EOI) for FGD System Main Package at 2 X 525 MW Power Plant Details
 
8Expression of Interest (EOI) for Electrical Power Supply Package for FGD Details
 
8Expression of Interest (EOI) for FGD (Flue Gas Desulphurization) System Main Package Details
 
8Annual Maintenance of Generator, Turbine and its auxiliaries Details
 
8Annual Maintenance contract for Main Plant & Offsite Lighting Details
 
8Supply of Hydraulic Motor (Drive) Details
 
8Construction of 400/220/132kV GIS Substation with SAS on turn-key basis Details
 
8Tender for Construction of new 3 Nos 33 kv feeder bays and allied civil works Details
 
8Supply and installation of 03 Nos. Steam Turbine Generator & Auxiliaries Package for Super critical Thermal Power Project Details
 
8Tender for Arrangement of 11KV Ring Main Distribution System Details
 You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8Banks mull AMC route for NPAs with Rs 1-2k-cr debt Details
 
8Jharkhand coal scam: Court orders framing of additional charge of abetment of bribery against Naveen Jindal Details
 
8Adani Power plans to raise up to Rs 5,000 cr to fuel biz expansion, growth Details
 
8Solar capacity additions at a fast pace may add to economic woes Details
 
8Tata Steel, Liberty House, or JSW Steel, who will win Bankrupt Bhushan Power under IBC? Lenders to take call Details
 
8China June coal imports jump 18 percent as utilities speed buying Details
 
8Apple launches $300 million green energy fund in China Details
 
8GE commissions first leg of grid-stabilisation system for PowerGrid Details
 
8Low coal stocks likely to hit power generation in Haryana Details
 
8Approval for rooftop solar power projects on Delhi municipal buildings Details
 
8EU court dismisses Austrian case against UK nuclear power plant Details
 
8Electric vehicle surge poised to test U.K. grid for decades Details
 
You can also click on Newsclips for more
  Details

Jul 12 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply of hydraulic motor for side arm charger in CHP Details
8Supply of Lube Oil Filter Differential Pressure Transmitter and Reducer Filter DP Transmitter Details
8Tender for the work of Complete re-tubing/re-conditioning of Stator Water Cooler heat exchanger & Bearing Cooling Water heat exchanger Details
8Supply of 36 KV CT & 36 KV PT along with Jn. Boxes & Terminal connector Details
8Supply of 36 KV Bus Isolators & 36 KV Line Isolators for various Sub-Stations Details
8Supply of various sizes MS Flat & GI Flat at various Sub-Stations Details
8Tender for construction of 132/33 KV Substation with SAS on Turnkey basis Details
8Tender for manufacturing, Testing and Supply of 66/11 KV Transformers Details
8Procurement of spares for Rotary twin lobe Air Blower Details
8Procurement of mixing pot for ECO hoppers of Ash Handling System Details
8Procurement of Various Sizes of Valves for Bottom Ash Handling System Details
8Tender for the procurement of Hammer rings for Secondary crusher Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
 
8Govt looks at energy-efficient ways to tackle climate change Details
 
8EESL signs pacts with Discoms to install 10 lakh smart meters in Haryana Details
 
8Bangladesh unveils $5.8 billion energy investment, two JV's with General Electric Details
 
8Bajaj Hindusthan to sell 17.51% stake in group's power firm LPGCL Details
 
8MP CM Shivraj Singh Chauhan inaugurates NTPC's Rs 1,500 crore solar plant Details
 
8Costly land pushes solar tariff to Rs 3.48 per unit for 1 GW auction in UP Details
 
8ABB wins $150 million order for world's biggest offshore wind farm Details
 
8Bangladesh looks at India to fulfil its ‘power for all’ promise Details
 
8Maharashtra government bats for solar projects on large dams Details
 
8India's shift to green economy could add 3 million jobs by 2030: Report Details
 
8Floating solar plants may lose viability in India due to cost pressure Details
 
8Solar power tariffs rise by more than a rupee in latest auction Details
 
8EESL scraps second tender for procurement of 10,000 electric cars Details
 
8BlackRock plans its largest ever alternative investment fundraiser for energy infra Details
 
8Sterlite Power bags $1 billion power transmission projects in Brazil Details
 
8Electric vehicles could lift UK peak power demand by 5-8 GW by 2030-National Grid Details
 
You can also click on Newsclips for more
  Details

Jul 11 : Software Updates : Power Projects

8Project Name: Greenfield Pumped Storage Project
8Project Cost: 2000 crores
8Project Description: Owner has submitted an application to the district forest officer level for the forest clearance of a 800 MW Pumped Storage Plant. Further bids are expected soon.
8Project Event: RFQ for EPC contractor is expected to be floated by the Q4 2018, instead of Q2 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Q4:2018
8Release Date: Q4:2018
8Start Date: Q3:2019  
8Completion Date: Q4:2023
Click here for more information

8Project Name: Super Thermal Power Maintenance Project
8Project Cost: 10 crores
8Project Description: Promoter has planned a 47-day scheduled capital overhaul in the 4000 MW thermal power plant. The project envisages overhauling of ESP and air pre heater basket replacement. The mandatory job includes repair of gas distribution screens, removal of damaged supporting frame including support pipes, supply of new basket for air pre heater, jet cleaning after installation of new basket, among others.
8Project Event: RFQs for capital overhaul are expected by the August 2018.
Click here for more information

8Project Name: Greenfield Pumped Storage Project
8Project Cost: 6340 crores
8Project Description: The owner is going to hire consultant for the preparation of DPR for a 2500 MW pumped storage hydro power project. Tenders for the same is expected soon.
8Project Event: RFQs for a consultant for preparation of the detailed project report are expected by September 2018.
8Expenditure Approval: Q4:2018
8RFQ Date: Sep/2018
8Release Date: Sep/2018
8Start Date: Q2:2020
8Completion Date: Q3:2025
Click here for more information   Details

Jul 11 : Power Sector Briefs

8Maintenance contractor requirement is coming up in a 630 MW thermal power station in Chennai : Find out the project owner.
8Business opportunities for major solar power developers : RFQs in October 2018
Click on details
  Details

Jul 11 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Tender for Annual contract for the works of Testing of oil of Power T/F Details
8Tender for Balance work of 01 No. of 132kV end /line bay along with supply, erection, testing commissioning works for 132kV SCDC line Details
8Tender for Procurement of 03 nos test set for measurement of resistivity & dissipation factor of Transformer oil Details
8Annual Contract for Operation and Maintenance work of Entire Ash handling System & Associated work Details
8Tender for Supply of MS Pipe for TPS Details
8Purchase of Spares and VVVF Drives of EOT Cranes installed in Power House Details
8Tender for Supply of 220 MVA Auto Transformer Details
8Tender for Supply of 160 MVA Auto Transformer Details
8Tender for the work of Renovation & Modernisation of 6.6 KV Switchgear Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
 
8Auction for Wind energy capacity of close to 2,000 MW goes undersubscribed Details
 
8Big move towards reducing air pollution! Delhi to get 1,000 e-buses Details
 
8KEC International bags order worth Rs 1,357 crore Details
 
8Hartek Power bags order from HSIIDC Details
 
8China's SPIC targets 8 GW overseas power capacity by 2020 Details
 
8Seminar on business opportunities in India's solar sector held in China Details
 
8Oil major Eni pulls out of race for RTR solar assets in Italy Details
 
8Vadodara airport to switch to solar power soon to cut down electricity cost Details
 
8Indonesia's SMI raises 1.5 trillion rupiah in bonds to fund green projects Details
 
8BMW, Great Wall Motor join hands to make electric MINIs in China Details
 
8Gujarat govt sets up rescue team for Tata, Adani, Essar power projects Details
 
8Bhushan power lenders choose Tata's bid Details
 
8Tata Power to set up 250-Mw solar power project in Karnataka Details
 
8Solar power comes to the rescue of 1,617 schools without electricity in Aurangabad Details
 
8World Coal Association announces leadership transition Details
 
8Thermal power plants, not Sterlite major source for SO2 emissions in Tuticorin Details
 
You can also click on Newsclips for more
  Details

Jul 10 : Power Sector Briefs

8Power Purchase agreement cancelled in a 1200 MW thermal power station : Find out the project owner.
Click on details for more   Details

Jul 10 : Software Updates : Power Projects

8Project Name: Greenfield Pumped Storage Project
8Project Cost: 1500 crores
8Project Description: A JV company is continuing with S&I for a 300 MW pumped storage scheme. Further bids are expected soon.
8Project Event: RFQs for consultancy services for preparation of detailed project report are expected by September 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Sep/2018
8Release Date: Sep/2018
8Start Date: Q2:2021  
8Completion Date: Q4:2025
Click here for more information

8Project Name: Super Thermal Power Maintenance Project
8Project Cost: 10 crores
8Project Description: Owner has planned a 40-day capital overhaul in the 3000 MW thermal power plant. The job requirement includes air pre-heater guide bearing replacement, replacement of nozzles in pre-heater, supply of corroded water tubes, checking and cleaning of condensate pumps, among others.
8Project Event: RFQs for the required capital overhaul are expected by the August 2018.
Click here for more information
  Details

Jul 10 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
 
8Tender for Supply, erection and commissioning of single stage oil injected Rotary Screw Compressor Details
 
8Tender for procurement of 185 Sq mm PVC Cable Details
 
8Operation and Routine maintenance of Recovery water system (Mechanical & Electrical Portions) Details
 
8Tender for the Supply of Seal and Seal Runner Assembly for HP 803 Bowl Mills Details
 
8Supply of M S Channel ISMC 100 X 50 Having 12 Mtrs. Length Details
 
8Tender for Supply of Spares of Heat Exchanger Details
 
8Supply, Installation and Commissioning of 1000 KVA Transformer Details
 
8Tender for Providing services for running, operation and maintenance of Hydro-mechanical Components Details
 
8Round the clock Operation of E&M Plant and Machinery at Power House, Transformer Cavern, Valve House and Switchyard of H.E. Project Details
 
8Supply, Erection, Testing & Commissioning of 1No. 50 MVA, 11/220 kV, Three Phase Transformer Details
 
8Supply and Retrofitting of Differential Relay, Distance Protection Relay, Over Current/Earth Fault Relay and Master Trip Relay Details
 
8Tender for manufacture, testing, supply and delivery of ACSR Panther Conductor Details
 
8Procurement of PVC Nozzles, Adaptor and M.S. Pipes Details
 
8Biennial Maintenance contract for ASH DYKE Details
 
8AMC for LT Panels and Operation Services of Electrical Equipments Details
 You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8Icra pegs Rs 85k crore subsidy dependence for discoms in FY19. Details
 
8Working on lithium-ion technology for EVs: Exide. Details
 
8Goyal asks Coal India to ensure supply for power sector Details
 
8CEA supports imports for thermal power plants to tide over coal shortage Details
 
8Amity University installs on-site solar plants at its campuses Details
 
8Focus on meeting demand, Goyal to Coal India Details
 
8Nod for Bangladesh's 2nd 1,200 MW n-power plant Details
 
8Solar cooking facilities for every rural household in 4-5 years: Piyush Goyal Details
 
8Global solar power investments set to fall in 2018; down 19 per cent in first half Details
 
8Power Corporation yet to pay Rs 800 crore dues to mills, farmers bear brunt Details
 
8Proposed FPPCA charges under power panel's lens Details
 
8Thermal plants in Telangana did not follow emission regulations Details
 
8Delhi records highest-ever power demand at 6,998 Megawatt Details
 
You can also click on Newsclips for more
  Details

Jul 09 : Software Updates : Power Projects

8Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 5000 crores
8Project Description: Owner along-with EPC contractors are undertaking excavation activities for a 600 MW greenfield hydro power project. Further bids are expected soon.
8Project Event: RFQs for material handling, erection, testing and commissioning works of electro-mechanical works are expected by the end July 2018.
8Expenditure Approval: 2012
8RFQ Date: 20/Jul/2018
8Release Date: 23/Jul/2018
8Start Date: 2014  
8Completion Date: 2021
Click here for more information

8Project Name: Thermal Power Plant - Installation of FGD
8Project Cost: 500 crores
8Project Description: Promoter has selected consultant for carrying out site survey and preparing a feasibility report for installation of an FGDs in the 1200 MW thermal power station. Further bids are expected soon.
8Project Event: RFQs for design, supply, transportation, construction, erection and commissioning of flue gas desulphurisation units are expected by the Q4 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Q4:2018
8Release Date: Q4:2018
8Start Date: 2020 
8Completion Date: 2022
Click here for more information

8Project Name: Thermal Power Plant - FGD Addition
8Project Cost: 820 crores
8Project Description: A subsidiary company has obtained financial approval for the installation of an FGD in the 2400 MW thermal power station. Tenders for the same is expected soon.
8Project Event: RFQs for supply and installation of an FGD is expected by August 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Aug/2018
8Release Date: Q3:Aug/2018
8Start Date: Q2:2019
8Completion Date: Q4:2021
Click here for more information   Details

Jul 09 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Tender for Procurement of Condenser Tubes Details
8Design, Supply, Testing & commissioning of Grid Tied Solar PV System Details
8Supply, Installation and commissioning of 1MWp Grid Connected Floating Solar PV System Details
8Design, Supply, Installation, commissioning and O&M of 750KWp Rooftop Solar System Details
8Tender for Construction of 33 KV line on turnkey basis Details
8Design, Supply, Installation, Testing & commissioning of 132 kV, 2X15 MVAR Capacitor Banks at 132 kV Visarwadi Substation Details
8Design, Supply, Installation, Testing & commissioning of 132 kV, 2X15 MVAR Capacitor Banks at 132 kV Parola Substation Details
8Design, Supply, Installation, Testing & commissioning of 132 kV, 2X15 MVAR Capacitor Banks along with Associated HV Bays & civil works Details
8Tender for Replacement of existing Porcelain Disc Insulators of 400KV Line by Antifog Long Rod Porcelain insulators Details
8Design, Supply, Installation, Testing & commissioning of 132 kV, 2X15 MVAR Capacitor Banks along with Associated HV Bays Details
8Tender for the work of LILO on 132 KV line Details
8Design, Supply, Installation, Testing & commissioning of 132 kV, 2X15 MVAR Capacitor Banks Details
8Tender for the Work of increasing of ground clearance of various 220kV & 132kV Lines Details
8Overhauling of coal burner assemblies, burner tilting mechanism, renewal of wornout and defective coal compartment assemblies Details
8Supply of Pure rayon grade Caustic Soda Lye Details
8Tender for Procurement of 11KV and 33KV Control and Relay Panel Details
8Survey, Supply, Erection, Testing and Commissioning of 11KV line Line & Associated works at West District Details
8Survey, Supply, Erection, Testing and Commissioning of 11KV line Line & Associated works at North District Details
8Survey, Supply, Erection, Testing and Commissioning of 11KV line Line & Associated works at Khowai District Details
8Survey, Supply, Erection, Testing and Commissioning of 11KV line Line & Associated works at Gomati District Details
8Survey, Supply, Erection, Testing and Commissioning of 11KV line Line & Associated works at Dhalai District Details
8Tender for Repair/Overhauling of 02 No. HT Motor Details
8Procurement of Shaft Seal Rotating Face Ring with Hard Facing for HPS Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Rajasthan: Solar energy is now the preferred source of power Details
8Thoothukudi no longer promising power generation hub of South India Details
8Pilot scheme for plants sans PPAs elicits tepid response Details
8Govt should exempt solar units under SEZ from safeguard duty Details
8Himachal gives subsidy on rooftop solar installations Details
8Six UP cities can generate 11.4 GW of solar power Details
8Punjab & Haryana power utilities improve grading Details
8Govt mulls setting up electric vehicle target for state public transporters Details
8Fortum launches charging stations for electric vehicles in Hyderabad Details
8India, Bhutan reaffirm commitment to hydropower cooperation (Roundup) Details
8Telangana power generation utility spent Rs 800 crore on repairs Details
82 smart city projects get administrative nod Details
8India plans to cut emission from old power plants to national standards by 2022 Details
8Power Ministry mulls Rs 50 crore reward for discoms under Saubhagya Details
8If you are not competitive in solar manufacturing, you should not attempt it: Amitabh Kant Details
8Dwindling rain leads to increase in demand for power in Punjab Details
8Federal judge fines Chinese wind turbine maker $1.5 million Details
8Adani Solar gets global recognition on durability and reliability Details
81.5 lakh farmers to get grant for solar pumps: Haryana Minister Details
8Solar tariffs show upward trend again; rise to Rs 2.71 in SECI auction Details
You can also click on Newsclips for more
  Details

Jul 06 : Upcoming business opportunities in the power sector

8Project Name: Greenfield Thermal Power Station
8Project Cost: 20000 crores
8Project Description: Owner along with an EPC contractor is undertaking land development activities for a 1980 MW super-critical coal based greenfield Super Thermal Power Plant. Further RFQs are expected soon.
8Project Event: RFQs for civil and architectural works required for the coal handling plant and ash handling plant are expected by August 2018.
8Expenditure Approval: Q2:2014
8RFQ Date: Aug/2018
8Release Date: Aug/2018
8Start Date: Q3:2018  
8Completion Date: Q2:2024
Click here for more information

8Project Name: Thermal Power Station Addition Project
8Project Cost: 250 crores
8Project Description: A subsidiary company is planning to come out with an ash water re-circulation package in the 800 MW thermal power station. Further RFQs are expected soon.
8Project Event: RFQs for an ash water re-circulation package are expected by the August 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Aug/2018
8Release Date: Aug/2018
8Start Date: Q4:2018  
8Completion Date: Q1:2020
Click here for more information

8Project Name: Thermal Power Project - Installation of SNCR
8Project Cost: 2500 crores
8Project Description: A subsidary company is planning to install a Selective Non-Catalytic Reduction System (SNCR) for the removal of harmful NOx gases in the 1820 MW thermal power complex. Tenders for the same is expected soon.
8Project Event: RFQs for the design, engineering, supply, installation and commissioning of SNCR system are expected to be out by the August 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Aug/2018
8Release Date: Aug/2018
8Start Date: Q3:2019
8Completion Date: Q3:2021
Click here for more information   Details

Jul 06 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Tender for Procurement of Electromatic Relief Valve with Actuator and isolation Valve Details
8Tender for Supply of P. Bends for Coal Mills Details
8Tender for Supply of ESP Spares for TPS Details
8Tender for Various Civil Works at 132kv substation Details
8Tender for Replacement of LT MCC Package Details
8Supply of spares for PLC Spares installed at TPP Details
8Tender for Supply of Toothed Ring Hammers Details
8Tender for Replacement of failed water wall tubes Details
8Tender for Supply of feeder control & Relay Panels Details
8Tender for supply of Boiler Maintenance Platforms Details
8Tender for Civil packages for Transmission & Distribution division Details
8Tender for Balance civil works at TPS Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
 
8Stressed power assets: Impractical to comply with RBI circular, say banks Details
 
8Renewable energy sector employed 4.3 lakh people in 2017: Report Details
 
8Power plants, brick kilns may miss clean air action plan deadline Details
 
8Madhya Pradesh to cut power bills for unorganised labourers Details
 
8Karnataka budget: Power consumers in for nasty shock Details
 
8Volvo cars to bring hybrids, plug-in EVs to Indian market Details
 
8DERC chief takes oath of office; non-committal on not hiking power tariff Details
 
8India looks to acquire lithium, cobalt mines abroad Details
 
8Vattenfall to invest $2.3 bln in grid over the next five years Details
 
8Govt plans to make local manufacturing a key element for large solar power projects Details
 
8ABB India plans expansion of factories to cater to railways' demands Details
 
8China considering further reduction in electric-vehicle subsidies Details
 
8Improving demand-supply situation may lead to re-rating of power companies Details
 
8China's Wintime Energy defaults on bond payments, triggers cross-guarantee Details
 
8Italy's Enel puts wind, solar farms in Brazil on the block -report Details
 
You can also click on Newsclips for more
  Details

Jul 05 : Software Updates : Power Projects

8Project Name: Pumped Storage Hydro Power Greenfield Project
8Project Cost: 7000 crores
8Project Description: Owner has been granted environment clearance for a 1500 MW Pumped Storage Plant. Package wise bids are expected.
8Project Event: RFQs for civil and H&M works are expected by August 2018.
8Expenditure Approval: Q4:2018
8RFQ Date: Aug/2018
8Release Date: Aug/2018
8Start Date: Q2:2019  
8Completion Date: Q3:2024
Click here for more information

8Project Name: Thermal Power Station Maintenance Project
8Project Cost: 15 crores
8Project Description: Promoter's bids for a 45-day scheduled annual overhaul in 3000 MW thermal power plant is getting delayed due to lack of preparation of Notice Inviting Tender document. The mandatory job includes refurbishment of pressure parts of boiler, replacement of turbine rotating blades, burner refurbishment, replacement of air preheater (APH) basket, replacement of radial, axial and rotor post seals of air preheater, sector plates in air preheater which gets corroded during operation, among others.
8Project Event: RFQs for required equipment for the overhaul are expected by the end of July 2018.
Click here for more information

8Project Name: Thermal Power Station - Dismantling
8Project Cost: 83 crores
8Project Description: The owner is planning to retire and dismantle all the plants of 340 MW coal based thermal power station as it has aged more than 25 years. Further bids are expected soon.
8Project Event: RFQ for dismantling services of various equipment is expected by October 2018.
8Expenditure Approval: 2018
8RFQ Date: Oct/2018
8Release Date: Oct/2018
8Start Date: Q2:2019
8Completion Date: Q3:2020
Click here for more information   Details

Jul 05 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply of Spares for Air Pre Heater Details
8Supply of Spares for Ball Tube Mill Details
8Tender for the work of Rewinding of LT Motors (up to 160KW) Details
8Tender for the work of Complete rewinding of 02 No. 6.6 KV / 0.4 KV Transformer Details
8Design and Supply of Standby HS Pumping Unit along with accessories for Thrust Bearing at Power Station Details
8Tender for Balance works for Air Conditioning System Package for TPP Details
8Tender for the work of Refurbishment of Shaft and Impeller of ID Fan of Stage-2 at TPS Details
8Tender for the work of Refurbishment of Shaft and Impeller of ID Fan of Stage-1 at TPS Details
8Design, Supply, erection & Commissioning of Railway Wagon Loading System for TPS Details
8Supply, installation, testing and commissioning of breaker failure protection relays Details
8Tender for construction of 132/33 KV Substation on Turnkey basis Details
8ARC for CW Chemical treatment of TPS Details
8Operation and Maintenance of 11KV & 415V Distribution Sub-Stations Details
8Tender for Non-Comprehensive Annual Operation & Maintenance Contract of 33/11KV, 2x5MVA Substation Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
 
8Coal India asks thermal plants not to limit intake to avert future crisis Details
 
8Serbian EPS signs deal to finish hydro plant overhaul Details
 
8China's ZNShine Solar wins 37.5-MW module order in India Details
 
8Not just cars, Suzuki to bring in electric bikes Details
 
8ERC extends discounted electricity to all night firms Details
 
8Vedanta, BHEL, Grasim, Power Grid, Reliance Power hit 52-week low Details
 
8Renewable energy push in sunny Arizona draws political fight Details
 
8Green Climate Fund meeting 'disappointing', chief quits Details
 
8Gujarat HC notice to govt on allotment of village land for windmill projects Details
 
8Coal imports by power sector in April-May down 15 per cent: Piyush Goyal Details
 
8HC notice to Mahagenco over coal sale to private power cos Details
 
8Tripura govt seeks VAT waiver of ONGC Tripura Power Company to be examined Details
 
8EESL to retro-fit energy efficient appliances in 400 Delhi schools Details
 
8UAE further delays launch of first nuclear power reactor Details
 
8 S.Korea's summer power supply seen stable on higher nuclear power generation Details
 
8 ICICI Prudential AMC buys shares in NTPC; holding up over 5 per cent Details
 
8Saudi Arabia's PIF takes 15.2 pct direct stake in ACWA Power Details
 
8Volvo Cars to manufacture electric vehicles in India Details
 
You can also click on Newsclips for more
  Details

Jul 04 : Power Sector Briefs

8Chhabra thermal power plant: Stake over by NTPC delayed.
Click on details
  Details

Jul 04 : Software Updates : Power Projects

8Project Name: Greenfield Thermal Power Project
8Project Cost: 5000 crores
8Project Description: Owner has been granted environment clearance for a 660 MW coal based thermal power plant. Further bids are expected soon.
8Project Event: RFQs for an EPC package are expected by September 2018.
8Expenditure Approval: Q4:2017
8RFQ Date: Sep/2018
8Release Date: Sep/2018
8Start Date: 2020  
8Completion Date: 2024
Click here for more information

8Project Name: Super Thermal Power Maintenance Project
8Project Cost: 5 crores
8Project Description: Promoter has planned a 35-day scheduled boiler overhaul in the 3000 MW thermal power station. The mandatory jobs includes replacement of boiler pressure parts, checking of generator rotor, replacement of guide bearings of turbine, among others.
8Project Event: RFQs for overhaul of equipment are expected by the August 2018.
Click here for more information

8Project Name: Thermal Power Station : FGD Addition Project
8Project Cost: 300 crores
8Project Description: The owner is planning to install an Flue Gas Desulphurization Unit (FGD) for a 2000 MW thermal power complex in order to comply with environmental norms. Tenders for the same are expected soon.
8Project Event: RFQs for hiring a consultant for site survey and preparation of feasibility report is expected by the end of July 2018.
8Expenditure Approval: 2017
8RFQ Date: 27/Jul/2018
8Release Date: 29/Jul/2018
8Start Date: Q4:2019
8Completion Date: Q3:2022
Click here for more information   Details

Jul 04 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Tender for the Supply of Power Transformer Details
8Tender for the work of Maintenace of ST-1 Mills, Feeders & PF Piping System Details
8Annual Maintenance Contract of Milling System Details
8Biennial Rate contract for Maintenance of C&I Equipment Details
8Supply of Synchronizing Relay & Potential Transformer Details
8Tender for Procurement of Conveyor Belt Details
8ARC for fixed routine /preventive maintenance works of auxiliaries of turbo generator Details
8Supply of Filter Bags for AHP Details
8Supply of Caustic Soda Lye at TPP Details
8Tender for the Supply of 36" Centre Distance Worm Gear & Worm Shaft assembly Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Power sector in a limbo: Top posts in Coal India lying vacant. Details
8Not enough coal, Delhi on verge of blackout, claims minister. Details
8Coal-starved Mahagenco selling coal to private cos Details
8No more hefty electricity bills! You might have to pay almost nothing for power if this solar model works Details
8Energy sector: State seeks special support Details
8Will monsoon aggravate fuel challenges for thermal sector? Details
8Gujarat tops power distribution companies annual ranking again Details
8After missing 1st-quarter targets, Coal India is facing criticism yet again Details
8Rooftop solar power panels can cut 95 per cent of bill: Study Details
8Goa CM Parrikar meets power dept over solar policy roll-out Details
8Adani Green Energy to raise $500 million via dollar-bonds Details
8German engineering group warns of drop in new wind power projects Details
8Two million new jobs to be offered in wind energy sector by 2022: Suzlon Chairman Tulsi Tanti Details
8China to cut coal use, curb steel in 2018-2020 pollution plan Details
8GE bags $72.4 million orders from BHEL for boiler equipment Details
8Hope flickers for troubled power projects in Gujarat Details
8Himachal seeks Centre's intervention over power arrears with neighbours Details
8State power ministers resolve to electrify all households by Dec-end: Singh Details
8Punjab power utility to pay Rs 446 cr to private firms for electricity not drawn Details
8Air conditioning could add to global warming woes: Study Details
You can also click on Newsclips for more
  Details

Jul 03 : Software Updates : Power Projects

8Project Name: Greenfield Super Thermal Power Station
8Project Cost: 15000 crores
8Project Description: Owner is going on with the construction activities in a 1980 MW greenfield super-critical thermal power plant. Further bids are expected soon.
8Project Event: RFQs for the balance of plant (BoP) package are expected by the August 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Aug/2018
8Release Date: Aug/2018
8Start Date: Q2:2019  
8Completion Date: Q3:2023
Click here for more information

8Project Name: Greenfield Super Thermal Power Project
8Project Cost: 15000 crores
8Project Description: Promoter along with BTG and ESP contractor is carrying out the construction activities in a 1320 MW greenfield super-critical thermal power plant. Further RFQs are expected soon.
8Project Event: RFQs for procurement of mobile crane and crane of capacity 30 MT and 20 MT respectively are expected by the end of July 2018.
RFQs for the supply, installation, erection and commissioning of a flue gas desulphurisation unit (FGD) are expected in the August 2018.
8Expenditure Approval: Q1:2013
8RFQ Date: 25/Jul/2018
8Release Date: 28/Jul/2018
8Start Date: Q3:2013   
8Completion Date: Q3:2019
Click here for more information

8Project Name: Thermal Power Station : FGD Addition Project
8Project Cost: 820 crores
8Project Description: The owner is planning to install a Flue Gas Desulphurization Unit (FGD) for a 2300 MW thermal power complex in order to comply with environmental norms. Tenders for the same are expected soon.
8Project Event: RFQs for design, supply, engineering, construction and commissioning of FGD are expected by the end of August 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Aug/2018
8Release Date: Aug/2018
8Start Date: Q3:2019
8Completion Date: Q1:2021
Click here for more information   Details

Jul 03 : Power Sector Briefs

8Maintenance contractor in a 840 MW thermal power station : Find out the project owner.
8NTPC to acquire stressed 720 MW thermal power station : Find out more
Click on details
  Details

Jul 03 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Procurement of SF6 Gas Handling Cart and SF6 Gas Leakage detector Details
8Tender for the work of Operation of Bed Ash Handling system of 2X125MW CFBC Boiler Details
8Construction of l32kV 2-Phase Line on D/C Towers Details
8Supply of Transformer Oil Filtration Machine Details
8Design, Supply, Testing & Commissioning of 1 No. 30MVA, 11/132KV Generator Transformer Details
8Laying of tower foundations ,Erection of towers and stringing & sagging of conductor with earth wire for 66 KV D/C line Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
 
8SC poser to Delhi govt on proposal to purchase electric buses Details
 
8A sustainable switch to renewables Details
 
8Railway Energy Management Co Ltd float Tender for 54 MW Wind Power Projects in Maharashtra Details
 
8India can export up to 5 GW wind energy by 2022: Tulsi Tanti Details
 
8Delhi: Hydrogen buses over electric? Explore, says SC Details
 
8Introduction of EVs will have adverse impact: Forging industry Details
 
8Norway adopts new power grid regime from 2019 Details
 
8Raj thermal plant shuts 5 units amid weak power demand Details
 
8Weavers to get solar charkhas, khadi benefits Details
 
8Bosnia invites bids for first large-scale solar power plan Details
 
8Japan aims for 24% renewable energy but keeps nuclear central Details
 
8Australian Newcastle spot coal prices hit $120 for 1st time since 2012 Details
 
8NTPC, CIL see output rise with June quarter growth Details
 
8Solar tariffs once again hit all-time low of Rs 2.44 a unit at SECI auction Details
 
8Centre asks states to use allocated funds for electrification of all households by Dec Details
 
You can also click on Newsclips for more
  Details

Jul 02 : Download Tenders and Newsclips

For reference purposes the website carries here the following tenders: 
8Supply of complete assembly of Gear Box for various drives of crawler mounted Reclaimer Machine Details
8Supply of 6.6KV HT motor for coal mill Details
8Supply of various spares for Ash handling plant Details
8Tender for the Work of AMC for 220 V, 110 V, 48 V battery set and charger at various EHV sub-stations Details
8Tender for the Work of maintenance contract for attending emergency breakdown and allied maintenance on any EHV line Details
8AMC for attending emergency breakdown and urgent works on various 220 kV EHV lines Details
8Tender for Procurement of various type of Valve for TPS Details
8Tender for the Work of complete/Capital Overhauling/servicing of pneumatic drive mechanism, Interrupter & Pole Details
8AMC for attending emergency breakdown and urgent works on various 132 kV EHV lines Details
8Supply of HS Straight joint kit and HS Outdoor termination kit for 11KV XLPE cable Details
8Procurement of Final Re-Heater Coil Pitch Arrester & Supply and Erection of Turn over Panel clip Details
8Manufacturing and Supply of Floaters and Accessories for 1 MWp Floating Solar PV Plant Details
8Design, Engineering, Supply, Erection, Testing and Commissioning works in connection with installation of 2 nos. 50MVA, 220/33KV Power Transformers Details
8Tender for Providing support services for running and maintenance of Gauge & Discharge site Details
8Tender for conversion of HT and LT overhead networks into under ground cabling system Details
8Supply of Collecting Electrodes for ESP Details
8Supply of Emitting Electrodes for ESP Details
You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8Coal India's supply to power plants up 15% in April-June period Details
 
8Bangladesh is keen on buying renewable power from India Details
 
8SC extends time till April 2022 for setting up of facility at Kudankulam plant Details
 
8KTPS seventh phase power supply begins Details
 
8South Korea's KEPCO shortlisted to bid for Saudi nuclear project Details
 
8Egypt says to start building nuclear plant in next 2 years Details
 
8Power ministers meet this week to discuss e-vehicle charging, prepaid metres Details
 
8NTPC takes equity stake in two Bihar state power projects for Rs 21 billion Details
 
8New solar power goal lands Chandigarh in a corner Details
 
8India to annually auction 40 GW renewables till 2028 Details
 
8India will be at centre of 'sunshine countries' of ISA: Prabhu Details
 
8Denmark to construct three new offshore wind farms by 2030 Details
 
8 SWPL, Adani gets pollution board nod for coal handling at MPT Details
 
8Raise irrigated area to protect country from climate change risks: CEA Details
 
8Tata Power commissions 100 MW solar power capacity in AP Details
 
8Shimla to host State Power Ministers' conference as deadline looms Details
 
855% of consumer plaints pending at power dept Details
 
8BESCOM asks 110 green energy developers to pay transmission charges Details
 
8Coal India production reaches 44.88 mt in June, misses target by 7.9mt Details
 
8Sponge iron firms pay 80% more on coal for long term Details
 
8Arnold Schwarzenegger mocks Donald Trump on coal policy Details
 
8Norway's REC Silicon lays off nearly 40 pct of workers at US plant Details
 
8NABARD sanctions over Rs 735 cr for solar, irrigation projects in Bengal Details
 
8Panasonic to consider more investment in Tesla's Gigafactory if asked -Exec Details
 
You can also click on Newsclips for more
  Details

<< Back