All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Jul 2026
8NPCIL's Rs 12.49 lakh Agroha township consultancy ties 80% of its fee to regulator-controlled approval milestones Payment for environmental consents releases through stages like "information of approval or intent of approval" — a threshold the tender never precisely defines. The 270-day approval window can extend by 90 days only at NPCIL's discretion, not automatically. Dual NABET accreditation across two separate sectors is mandatory, narrowing the eligible consultant pool sharply below what the small contract value would suggest.
8RVUNL's Rs 358 crore LSHS fuel tender restricts bidding to refinery-owning petroleum manufacturers The qualification framework favours integrated producers over traders or intermediaries, prioritising supply-chain control over price competition. Bid security is fixed at Rs 7.16 crore, reinforcing the utility's preference for financially resilient, execution-proven suppliers. The structure signals a broader strategic-fuel procurement approach built around reliability rather than lowest cost.
8MSEDCL's Rs 972.17 crore Kalyan-Bhandup distribution tenders let the utility reject an entire transformer lot on one failed sample test The two turnkey packages combine survey, supply, construction, GIS mapping and asset-tagging under indivisible single-point contracts. MSEDCL can select any power transformer for destructive short-circuit testing at the contractor's expense. Quantity variation runs as wide as 50% per item, and a single Rs 300+ crore completed project is required just to qualify through the one-contract route.
8WBSETCL's 200 MVA transformer tender adopts Revision-8 of its technical specification, tightening protection and monitoring standards The update adds digital RTCC relay provisions, expanded conservator protection, revised bushing current-transformer arrangements and dual DC supply requirements. Commercial terms remain untouched — the entire revision is engineering-focused rather than a pricing or risk-allocation change. The tighter specification is likely to favour established manufacturers with strong design-validation and testing infrastructure over smaller, price-focused bidders.
8RECPDCL's Parli 765kV TBCB bid slips 37 days past its original deadline while the 24-month construction clock stays fixed
Amendment-III moves online submission to 2 September — the third date reset since the RFP's original 7 July closing. The Rs 21.88 crore bid bond and Rs 54.70 crore performance guarantee stand unchanged, and the winning developer still faces scheduled COD 24 months from the effective date. All principal elements — three 1,500 MVA ICTs, the 765kV LILO into the Warora–Parli corridor and two 400kV links — must commission together before 100% of the quoted 35-year tariff becomes recoverable.
8RECPDCL's 7,500 MW Lakadia Phase-II tender reaches its tenth amendment without touching a single technical clause
Amendment-X extends the bid deadline by a week, moving every downstream milestone — technical opening, reverse auction, LOI, SPV transfer — in step. The HVDC-ready substation, synchronous condensers, 36-month COD and all qualification and security terms remain exactly as the original RFP set them.
8RECPDCL's 14 GW-linked Nasik package gets its eighth amendment one day before the bid deadline
The amendment adds seven days for submission, but LoI shifts eight days against seven for SPV transfer — leaving just 11 days to convert a Rs 36 crore bid bond into a Rs 90 crore performance guarantee. Qualification stays at Rs 1,800 crore experience and Rs 720 crore net worth, with the 36-month COD untouched.
8GUVNL splits November's 1,000 MW into two 15-day blocks a day after the RFP went live
The corrigendum keeps the month's quantum and 720 hours intact but raises requisitions from six to seven, letting different suppliers and tariffs clear each half. The bid deadline stays put with no extra preparation time, and the penalty regime — 20% of tariff on excess shortfall, double-tariff damages for diverted capacity — applies unchanged to both blocks.
8SECI's 5,290 kW rooftop RESCO tender locks in 25-year fixed tariffs before developers can fully survey the buildings
Ceiling tariffs run from Rs 4/kWh to Rs 6.40/kWh across eight projects in six states, yet detailed site due diligence is allowed only after LoA and final capacity is fixed at PPA signing. PPAs sit with eight separate institutions rather than SECI, and the 2,000 kW IIT Mandi package adds zero-export, behind-the-meter complexity.
For daily newsletters and other free services, fill in your details: