For reference purposes the website carries here the following tenders: 8Tender for supply of 36 kV bus isolator and 36 kV line isolator at various substation Details 8Tender for engineering, supply, erection and commissioning of 01 No. 132kV GIS feeder bay at existing 220kV GIS substation Details 8Tender for construction work of 01No. 220 kV GIS bay Details 8Tender for installation of 20.00 meter high mast light Details 8Tender for routine and preventive breakdown maintenance of all mech. parts of mono-rail electric hoist Details 8Tender for work of plugging of platen superheater tubes Details 8Tender for supply and erection of electrical smart power fence (ESPF) along Details 8Tender for manufactured fly ash brick Details 8Tender for supply, installation, commissioning and CAMC for real time data transmission Details 8Tender for rate contract for the procurement of sodium chlorite Details 8Tender for complete fabrication of boiler drum including suspension assembly Details 8Tender for construction of allied civil works at 33 kV sub station Details 8Tender for Re-construction of other allied civil works to prevent the 33 kV S/Stn Mehmra Details 8Tender for Re-construction of other allied civil works to prevent the 33 kV S/Stn Details 8Tender for supply, installation testing and commissioning for bifurcation of overloaded 11 kV feeder Details 8Tender for procurement of ISI marked 11 kV XLPE UG cable 300sqmm Details 8Tender for setting up of grid connected 88 MW ground mounted solar PV project Details 8Tender for setting up of grid connected 922.635 kW rooftop solar PV power project Details 8Tender for annual overhauling works (lower mechanical portion only) of motorized and pneumatic operated valves and gear boxes Details 8Tender for procurement of self-propelled fully mobile tyre mounted hydraulic mobile crane Details 8Tender for repair of aeration tank and digester tank Details 8Tender for supply, removal and installation of thermal insulations on pipes, equipments Details 8Design, detailed engineering, manufacture, supply, erection, testing and commissioning of 230/110kV AIS SS Details 8Design, detailed engineering, manufacture, supply of 400/230-110kV AIS substation Details 8Tender for entrusting works contract for carrying out all type of maintenance and breakdown activities by engaging additional gang at 400 kV GIS substation Details 8Tender for replacement of bare conductor by AB cable in 11 kV feeder Details 8Tender for replacement of bare conductor by AB cable Details 8Tender for work of carrying out the earthling audit (health assessment) of existing mat and earthling electrode (earth pit) at substation Details 8Tender for work of overhauling, oil leakage attending and testing of 100MVA, 11/230 kV generating transformer Details 8Tender for work of residual life assessment study of removed HP, IP & LP turbine rotors Details 8Tender for providing and laying G. I. pipe Details 8Tender for construction of winch foundation near bottom ash scraper Details 8Tender for providing and laying concrete & steel cover for unit 1 to 5 boiler side Details 8Tender for supply of various consumables, measuring instruments, Tools tackles, CPVC and fasteners items Details 8Tender for constructing 1175 m HT ABC Details 8Tender for conversion of the existing 33 kV overhead power line Details 8Tender for drawing dedicated 11kV feeder using covered conductor Details 8Tender for reconductoring of feeder using covered conductor Details 8Tender for AMC for specialized civil maintenance work Details 8Tender for supply of numerical relay communicable type and numerical differential relay Details 8Tender for erection new 33/11 kV S/s Details 8Tender for supply of three phase fully automatic meter testing bench Details 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects on control room at various 220kV / 66kV sub-stations Details 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects on control room at various 132kV / 66kV sub-stations Details 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details 8Tender for procurement of spares of control valve of condensate line Details 8Tender for procurement of AR/GR/exceller grade ammonia solution Details 8Tender for procurement of HACH make fine chemicals for analyser such as silica, sodium and chloride etc. Details 8Tender for work contract for repair and maintenance of disturbed dry stone pitching Details 8Tender for procurement of spares of SADC pneumatic actuators Details 8Tender for procurement of various keys and support plate of BHEL make turbine machine Details 8Tender for procurement of high pressure boiler tube bends installed at boiler Details 8Tender for purchase of 16 KVA, 3 phase aluminium wound energy efficient level-1 (star-1) completely self protected (CSP) distribution transformers Details 8Tender for new 10KM 11kV line Details 8Tender for shifting/height raising work of 220 kV S/C line Details 8Tender for civil works for augmentation of 31.5 MVA transformer at 132 kV GSS Details 8Tender for civil works for augmenation of 132/33 kV, 20/25 MVA transformer Details 8Tender for requirement of spares for hydraulic system boiler and turbine Details 8Tender for supply of 245kV current transformer Details 8Tender for supply of chains and sprocket for rotary breakers and travelling trippers Details 8Tender for work of 66kV SC on DC line from 66kV SStn Details 8Tender for annual contract providing, fixing and repairing of chain link fencing work Details 8Tender for supply of staircase step grills for crusher house Details 8Tender for construction of HT/LT line and erection of distribution transformer Details 8Tender for supply of and fixing of T and P Details 8Tender for supply of decentralized material Details 8Tender for maintenance, overhauling of different capacity of 11/0.4 kV DTRs in EDSD Jaspur-II Details 8Tender for maintenance, overhauling of different capacity of 11/0.4 kV DTRs Details 8Tender for supply of boiler tube and fittings for boiler Details 8Tender for supply of wall soot blower and oil gun spares for boiler Details 8Tender for supply, erection and commissioning of various accessories of conveyor belt Details 8Tender for shifting of 11 kV HT and LT OH line for construction of 2nd rail line Details 8Tender for electrical works for augmentation of capacity of PTR Details 8Tender for shifting of 11 kV HT and LT OH line for construction of 2nd rail line Details 8Tender for painting of different switchyard equipments alongwith equipment structures Details 8Tender for procurement of 400 sets of 11kV standalone complete set Details 8Tender for supply of V cross arm 4.5 feet Details 8Tender for supply of 7/2.50mm AAA weasel conductor Details 8Tender for supply of various spare/liners of beater wheel mill Details 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50 MVA, 132- 110/33 kV T/F Details 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50 MVA, 132- 110/33 kV T/F with allied civil works Details 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 25MVA, 132- 110/33 kV T/F Details 8Tender for work of overhauling / servicing of 245kV SIEMENS make circuit breakers Details 8Tender for work of overhauling / servicing of 145kV SIEMENS make circuit breakers Details 8Tender for work of annual maintenance contract (AMC) for servicing / maintenance of 1.5T & 2.0T split air conditioners available Details 8Tender for work of supply erection testing commissioning of 2x33kV bays at 220kV substation Details 8Tender for work of replacement of old and repaired 33kV current transformer for feeder Details 8Tender for work of application of RTV coating on 33 kV tertiary bushing,33kV PT, 33KV LA & support insulators Details 8Tender for day to day maintenance for civil assets in sub-station Details 8Tender for work of painting of 200MVA 220/132kV ICT's Details 8Tender for SITC (supply, installation, testing & commissioning) of cassette type inverter technology of split room air conditioning Details 8Tender for various civil maintenance work at control room & switchyard Details 8Tender for various civil maintenance works such as metal spreading, providing metal edging Details 8Tender for work of overhauling, servicing & repairs of 245kV/145kV Areva make circuit breaker at various EHV S/stns Details 8Tender for work of overhauling of ESP pass Details 8Tender for supply of different types & ratings of LT energy efficient induction motors Details 8Tender for supply of various types of bushings for 250 MVA, 420/15.75 kV, BHEL make generator transformers Details 8Tender for supply of MS grill and fabrication & Eepoxy paint of stairs, railing, structure Details 8Tender for ARC for supply erection and commissioning of of GI cable tray Details 8Tender for erection of equipment and structure, control wiring, yard lighting, control room wiring Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8Odisha, MP sign MoU to accelerate renewable energy push Details 8Jindal India Renewable Energy Signs 160 MW Wind Turbine Supply Agreement with SANY Wind Energy India for SECI RTC Project Details 8No solar, wind, renewable energy project within 1 km of international border, says Home Ministry Details 8Juniper Green Energy bags 230 MW project from SECI Details 8World’s first 16MW floating wind platform begins operation, changing offshore energy forever Details 8MNRE weighs support scheme for polysilicon to back 10 GW capacity in solar manufacturing Details 8RTC Renewable Tariff Falls To Rs 5.25, Boosting Clean Energy Push Details 8NLC India Q1 profit falls 48% to Rs 436 crore as deferred tax base effect weighs Details 8JSW Energy completes acquisition of 100% stake in Maruti Clean Coal & Power Details 8Coal Ministry Pushes Private Investment Through Mining Reforms Details 8Coal India Named Preferred Bidder for Gadadharpur Block Details 8Commercial Rooftop Solar: India’s New Clean Energy Driver Details 8Premier Energies Q1 FY 2027 slides: strong growth, expansion plans Details 8SECI Invites Bids For PMU Installation At 100 MW Solar With 40 MW/120 MWh BESS Project In Chhattisgarh Details 8India Plans PLI Scheme For Polysilicon Manufacturing To Reduce China Dependence Details 8Navgrun Announces 1.2 GW TOPCon Solar Wafer and Cell Facility Details 8NTPC Invites Bids For O&M And Security Services At 15 MW Solar Plant In Madhya Pradesh Details 8GERC Approves Rs 4.87/kWh Tariff for 250 MW FDRE Project Details 8Heelstone Acquires 188 MW Cypress Pointe Solar Project Details 8India Plans Incentives For Polysilicon Production Details 8One in Three Indian Power Firms Use AI; Adoption Seen Reaching 65% by 2030: Report Details 8India & Sri Lanka Discuss Bilateral Cooperation In Cross-Border Electricity Trade Details 8Coal supply for power sector comfortable in July: Govt Details 8AI Set to Become a Core Operating Capability in India’s Power Generation Sector; Adoption Seen Rising 65% by 2030: ENCIS Survey Details 8India sees 68 major renewable sector grid disturbances, generation losses of up to 7 GW Details 8Bihar lays the groundwork for its energy transition Details 8Rajiv Kumar Porwal: Director (System Operation), Grid-India Details 8Schneider Electric and BSES Rajdhani (BRPL) Partner to Deploy India’s First Sustainable Pure Air RMU Pilot Project Details 8Bihar Leads India in Smart Meter Rollout, Accounts for 70% of Prepaid Installations: Energy Secretary Details 8Refex Renewables Subsidiary Secures 80 MW Wind Power Project from SECI Details You can also click on Newsclips for moreDetails
8RVUN's Rs 127 crore Bodana solar-park tender says JV experience counts and, on a separate page, that JVs aren't allowed Amendment-2 flipped "Experience of JV/sub-let will not be considered" to "Experience of JV will be considered," but Clause 3.1(xi) barring joint-venture participation was never deleted — and a bidder asking about it was pointed back to the amendment. The same amendment cut water-treatment capacity from 150 to 15 lakh litres a day; Amendment-4 then cut the BOQ evaluation quantity for that item from 15,000 KL to 1,500 KL. Three extensions, 41 days. Prices are firm — Clause 75 bars escalation over 18 months.
8KSEB's 885 km ABC cable tender reaches financial opening with the bid mechanism disclosed and almost nothing else The record establishes a reverse-bidding "Tender cum Auction" for 11kV ABC of 120 sqmm and a 10 August opening, but delivery schedule, lot structure, consignee locations, inspection method, EMD, PBG, LD ceiling, warranty and whether the quantity can be split among suppliers are all absent from the published summary. Technical evaluation closed 6 August; no bidder names, count or rejection reasons appear.
8KSEB's transformer tender carries two different project values, and its qualification thresholds are pegged to whichever one applies The NIT and portal state Rs 72.163 crore; the pre-qualification committee minutes of 3 August state Rs 61.70 crore — a 14.5% gap with no corrigendum explaining it. Because minimum turnover is 75% of PAC, the entry barrier moves by roughly Rs 7.85 crore a year depending on which figure governs. Three of the five pre-qualified firms got in on undertakings to produce compliant type-test reports later; Kerala Electrical & Allied Engineering was disqualified on past KSEB performance.
8Arunachal's Rs 98.87 crore Pathar Camp substation lost three of five bidders on paperwork before price opening ABN Tower fell on unsigned bid pages, missing manufacturer authorisations, unsigned GTPs and an EHV-licence gap; two others failed on lead-partner experience, liquidity and licensing. The two survivors then quoted 21.1% apart. L1's evaluated Rs 98.75 crore sits 0.1% under the estimate, but its BOQ base is Rs 82.98 crore — and the 19.0% bridge between the two isn't broken out anywhere in the financial-opening record.
8MPPKVVCL cut 2.43 lakh meters from its Ujjain AMI tender and cut the value by a larger percentage than the quantity Volume fell 17.4% while the NIT amount fell 18.2%, from Rs 1,116.90 crore to Rs 913.62 crore, with no explanation of the composition behind the revised estimate — so bidders can't treat it as a pro-rata reset. Amendment-3 then confirmed the AMISP bears SMS charges at up to five messages per consumer per day across 11.58 lakh consumers, plus SIM, MPLS, bandwidth and static-IP costs, for ten years at a firm service charge. Four timetable resets, 29 days.
8BHEL's ACC tender forces bidders to allocate at least 10% of value to erection and commissioning, or it will rewrite the split itself Clause 3.3 blocks the standard tactic of loading value into supply to accelerate cash release — relevant because 20% of both supply and E&C value stays tied to air-tightness testing, trial run and PG acceptance. Evaluation also monetises each bidder's declared guaranteed power consumption and its own M30 RCC and reinforcement quantities. Rule 144(xi) land-border restrictions are expressly disapplied for this package.
8UJVNL's Chilla BESS tender funds 60 MWh of a 225 MWh project and asks bidders to pre-price the discount if more support arrives VGF covers 60 MWh at Rs 18 lakh/MWh — Rs 10.80 crore against a Rs 352.30 crore project — leaving 165 MWh to stand unsubsidised under a Rs 3,18,401/MW/month tariff ceiling. Clause 3.24 separately requires a sealed envelope stating the capacity-charge reduction offered for every additional 10 MWh that later becomes VGF-eligible. Land details are tentative and can be swapped without an extra claim.
8NTPC Mining's Banardih substation tender lets a bidder borrow its parent's balance sheet but not its parent's project record Clause 2.1.1 permits holding-company support to meet the Rs 36.90 crore turnover test, while the technical QR notes exclude experience belonging to a group, holding or subsidiary company — and separately exclude reference work the bidder executed through a JV or consortium. Completion period, PBG quantum, LD structure and payment milestones are not stated at NIT level.
8DVC's Rs 90.50 crore limestone tender can order the full 277,857 MT or none of it The GeM option clause allows ±25%, but Volume IV states "+25% to -100%" and says DVC "does not guarantee any off-take" — while each call-off must still be met within 15 days across a 365-day contract. Quality deductions run at 20% or 50% of basic price plus freight depending on how far CaO falls below 47%. Price comparison happens first; only the prospective L1 then faces techno-commercial scrutiny.
8NPCIL's Rs 128.22 crore engineering tender bars the winner from subcontracting the one activity the whole package is built around Cadmatic 3D modelling cannot be subcontracted, and bidders must already hold five qualifying 3D-platform licences and five piping-stress licences with live AMC, plus 200 engineering staff — 150 of them graduates — each with a year's tenure. Corrigendum C3 moved the pre-bid meeting to 7 August without moving the 10 August deadline, leaving three days between clarification and submission.
8NTPC REL reopened document access for its 600 MW Dhule tender 12 days before bids close and 34 days after the original cut-off Corrigendum 4 pushed the download window from 3 July to 6 August without touching the 18 August deadline, which itself had already moved twice from 22 July. Corrigendum 1 briefly recorded submission at 14:00 before later documents reverted to 15:00. Bid security stays flat at Rs 20 crore whether a bidder quotes 300 MW or 600 MW — and the scope clause cites document NRE-CS-5816 while the tender is numbered NRE-CS-5820.
8NREDCAP's Vijayawada WtE tender fixes the tariff and makes the subsidy ask the only thing bidders compete on Clause 21.2 evaluates financial proposals solely on quoted capital grant support, while the model PPA hard-codes Rs 7.50/unit subject to APERC approval. The authority guarantees 1,000 TPD of acceptable waste with damages at 30% of average per-ton gross revenue for shortfalls. Three separate securities stack up — Rs 16.24 crore, Rs 9.72 crore renewable annually, and Rs 25 lakh/MW — while Clause 3.3 describes construction running "from the COD" and Clause 18.5(e) writes 110% as "in excess of 10%."
8NTPC's Telangana ash-handling tender reversed its own crushing requirement from 8 mm to 25 mm after bidders questioned it Errata-01 corrected the intermediate-silo bottom ash size threefold; separate amendments moved the compressor fleet from 9 working plus 6 standby to 10 plus 5 without adding machines, cut bottom ash slurry from five streams to four, and raised conveyor rated capacity from 70 to 72 TPH with a new sub-120°C inlet criterion. Delay LD is Rs 30.73 lakh per day per facility. The deadline has moved 69 days across three extensions.
8RVPN's Dholpur EPC tie-up gives bidders a document-request deadline that falls on the same day bids are due Clause 5.0 says requests must come "up to 01 (One) day prior to bid submission deadline" and then names 3:00 PM on 17/08/2026 — the submission deadline itself — leaving potentially no gap between receiving the NDA-gated technical package and lodging a physical hard-copy bid. The pre-selected contractor must sign an exclusivity MOU and stay out of the same TBCB project before RVPN even submits its tariff bid. JV participation is marked "NOT APPLICABLE" and subsidiary or group credentials don't count.
8NPCIL's Rs 576.86 crore Gorakhpur tender narrows "similar work" to TAM and permeation grouting alone That single definition sets qualifying-work hurdles of roughly Rs 230.74 crore each for three works, Rs 288.43 crore each for two, or Rs 461.49 crore for one. Blocked or damaged TAM pipes must be reinstalled at contractor cost with no separate measurement, and grout is paid only against automated batching-plant records of accepted consumption. Two corrigenda moved the deadline 23 days and the pre-bid meeting 20 — without publishing a revised query cut-off.
8NTPC's North Karanpura AWRS tender issued three extension notices that don't say what the new dates are All three uploaded files are byte-identical and contain only the heading announcing an extension. Meanwhile Amendment 01 advanced the starter-dyke layout from Rev 4 to Rev 5 and added drawings, without narrating what changed — the geometry that drives pipeline routing and civil quantities. Two seepage pump houses are a minimum, not a number: more are required if actual dyke contours create additional accumulation points. Delay LD runs Rs 2,51,954 a day, with functional-guarantee LD capped separately at 12%.
8THDCIL's Sonbhadra DPR tender says on GeM that no performance security is needed and in its own conditions that 5% is ITC Clause 12.1 requires 5% of contract price including GST within 28 days of award; the GeM ePBG field reads "Required: No" — and GeM's disclaimer says conflicting buyer-added terms can be invalid. The same split runs through dispute resolution: GeM records arbitration and mediation as "No" while GCC Clause 8 sets out both, seated in Delhi. All ten named experts must be in place at bid stage, with no substitution through award.
8NREDCAP's Tirupati WtE tender is labelled an EPC price bid on the portal and is actually a grant-based concession The portal reads "Price Bid EPC" with 90-day validity; RFP Clause 2.6 requires 180 days and Clauses 21 and 28 make capital grant support the sole ranking variable. The PPA defines tariff as the figure "quoted by the bidder" while Article 2.2 fixes Rs 7.95/unit. DCA Clause 22.3(c) writes each of four grant instalments as 25% numerically and "twenty per cent" in words, and refers to a third project milestone that Schedule 5 doesn't contain.
8BHEL cancelled the reverse auction on its Korba West coal-handling tender the day after publishing it Corrigendum 1 changed clause 11.0 from "Applicable" to "Not Applicable," making the first sealed price final for a package running 42 months on one side and 58 on the other. The same corrigendum fixed a civil-PQR presentation where stray connectors made two RCC-volume thresholds read as cumulative rather than alternative. Bidders quote one lump sum, split 25:75 for ordering — after which BHEL may regroup the orders, and a breach on one can be treated as breach of the others.Details
8ICRA reaffirmed the Delhi distributor at AA+/Stable after distribution losses improved to 5.42%. The rating still depends on converting approved regulatory assets into cash and resolving a licence that expires in 2029.Details
8Ballia alone has Rs 202.62 crore of loss-reduction work and Rs 176.56 crore of smart-metering work, alongside 517 households still awaiting connection. The programme succeeds only when sanctioned spending becomes energised assets, accurate bills and fewer consumer complaints.Details
8CEA separately recorded 58,359.8 MW unavailable across 312,333.8 MW of monitored conventional capacity on 5 August. That broader total uses a different fleet definition, but it shows why return dates and repeated unplanned losses matter more than installed capacity alone.Details
8Both 660 MW units lost evacuation for seven hours and 26 minutes after a current transformer failed and protection opened healthy connections. JIPL has changed the hard-wired logic, but a tested selectivity check is still needed to show that the failure will remain contained next time.Details
8Rooftop installations stood at 446 MW against a 750 MW policy target while peak demand reached 8.7 GW by June. Panels can cut daytime purchases, but storage and flexible demand are needed after sunset.Details
8Four operating hydro, wind and solar assets failed value-in-use tests in FY2026. Naitwar Mori carries the largest rupee charge, while the portfolio percentages show sharply different degrees of damage.Details
8Implementation agreements for Luhri-I, Sunni Dam and Dhaulasidh remain unsigned while construction exposure has risen sharply. Interim court protection prevents coercive action for now, but it does not settle ownership or future commercial terms.Details
8The projected FY2027 distribution shortfall is Rs 1,972.93 crore larger than a year earlier. Kerala’s regulator must separate efficient costs from avoidable expenditure before deciding how quickly consumers should bear the increase.Details
8The June incident removed 1,237 MW for more than six hours after turbine-vibration and breaker protections operated. Investigators found earthing and relay inconsistencies that must be resolved without weakening genuine machine protection.Details
8NERLDC found Assam above its secure import limit for nearly five hours while the other Northeast import corridors remained within bounds. Prolonged violations reduce operating margin and may require more local injection, lower imports or changed dispatch.Details
8Uttar Pradesh’s expert panel has recommended first-phase environmental clearance for the Rs 2,693.68 crore plant. Its industrial promise now depends on whether large treatment and recycling systems can manage the proposed chemical and water load.Details
8India has completed only 38% of its two-year rooftop-solar installation goal 8Raigarh awaits BHEL as selected western coal units leave 40% operation unproved 8Orissa Steel’s 1,119 MW coal-power expansion reaches the study stage, not approval 8India's annual power exports pull in different directions 8SJVN misses a land milestone and leaves 50 MW without an EPC award 8KSEBL's Cherthala substation takeover remains tied up in land terms 8Telangana reservoirs reverse from scarcity to a strong hydro cushion 8Imported gas makes two Delhi power stations nearly twice as costly 8Samalkot equipment sale faces lender approval amid Rs 1,842 crore demandDetails
8India has 24.65 GW of pumped storage in the pipeline—but only 15.87 GW is being built 8Refex locks in an 80 MW wind tariff before land, finance and evacuation are secured 8CESC wins 175 MW at Rs 3.85, but construction risk now replaces auction risk 8ReNew’s solar rating improves even as output remains about 9% below design 8Amazon-linked wind project misses buyer and lender deadlines as land work lags 8JSW’s solar-wind-battery project is nearly a year late despite partial completion 8Avaada’s upgrade narrows the risk, but generation remains just below its benchmark 8India funds 13.8 GWh of batteries without setting an electrification target 8SECI seeks real-time visibility as Rajnandgaon’s solar-storage plant complicates grid control 8Jamui misses another solar deadline without an official completion notice 8Nawa solar slips nine months beyond SJVN's original promise 8Sonitpur misses successive targets without an official completion notice 8Delhi's tiny battery base confronts an 8,748 MW night peak 8Delhi's low distribution losses mask weak green-market participation 8SJVN’s construction pipeline nearly matches its operating fleetDetails
8Bhubaneswari mine stays 3.5 million tonnes below design despite a stronger quarterly run-rate 8India’s 62-day coal cushion may still fail at individual power plants 8Faster coal auctions have yet to produce faster mines 8Ageing coal plants enter a repair queue without public funding 8India’s large-hydro output fell 10.75% through July, tightening the value of dependable supply 8Two weeks of coal cover hides plant-level shortages 8India beat its daily power programme, but coal still supplied 77.5% of generation 8CEA’s 5.9 GW outage subset cannot show whether India’s wider shutdown burden has eased 8NTPC’s daily shortfall shows scale cannot erase station constraints 8Nuclear led conventional availability on 5 August, but one day cannot establish a fleet advantage 8Gujarat weighs turning ageing KLTPS units into grid stabilisers instead of retiring them 8Maharashtra, Gujarat and NTPC utilities tell WRPC that BHEL delays are holding up overhauls 8Western generators still lack uniform frequency controls as grid-response obligations tighten 8Missing generator models weaken studies before the next grid disturbance 8Weak reactive-power absorption is worsening high-voltage stress in western India 8Upper Sengulam hydro slips amid litigation and blasting opposition 8Luhri Stage I recovery still points to a 2030 finish 8Dhaulasidh nears civil completion while its state agreement remains unsigned 8Sunni Dam advances under an agreement the state has not signed 8Arun-3 transmission progress cannot erase a 2028 finish 8Buxar Unit 2 misses its July commissioning marker 8Buxar books Rs 521 crore of sales before tariff orders arriveDetails
8Biharsharif substation failure followed maintenance warnings that remained unresolved 8Santaldih’s first bus-splitting attempt ended in a total station failure 8Rain entered Dikchu’s gas monitor and twice cut off the same hydropower station 8One tower collapse kept Rongnichu hydropower off the grid for 18 days 8Faulty control logic caused two large load losses across Godda and Pakur 8Darbhanga’s transformer trips exposed an autoreclosing scheme set for the wrong fault 8Buxar’s backup relay tripped before the line protection it was meant to supportDetails
8One balanced power day does not prove India’s grid readiness 8India’s average frequency hides nearly a quarter of the day outside band 8Upward reserve dispatch jumped as India’s grid needed more generation than schedules supplied 8Secure national corridors do not prevent local voltage trouble 8Northeast frequency leaves the operating band for one-fifth of the day 8Telemetry gaps are leaving western grid operators partly blind 8Delayed black-start drills leave recovery plans unproved 8Bhopal’s islanding plan clears approval but still needs working controls 8Indore’s 600 MW islanding design returns for another study 8Northern generators seek overlapping autumn outages across more than 2 GWDetails
8Nearly two-thirds of sanctioned rural power connections remain unfinished 8India Energy Stack pilots begin without common standards 8Thousands of overloaded transformers put Haryana’s grid works under pressure 8Bihar’s Rs 11,707 crore grid support still leaves execution with its discoms 8Six PSPCL offices hold 55% of its unresolved audit backlog 8Solar takes 92.8% of MNRE’s budget while annual underspending persists 8Bioenergy receives 0.83% of MNRE’s budget despite a wider waste-to-energy promise 8Offshore wind ambition still lacks the spending record needed to prove momentum 8Small hydro remains trapped between old liabilities and a weak new-project pipeline 8Green Energy Corridor spending lags while renewable evacuation needs accelerate 8Green hydrogen funding is moving slower than the industrial demand it must create 8Renewable research gets only 0.6% of MNRE’s budget 8Parliament presses MNRE to coordinate a renewable transition fragmented across states 8National grid spending comes without transformer-failure or accident dataDetails
8POWERGRID buys the Krishnagiri corridor vehicle before the hard construction begins 8Rajasthan’s new renewable corridor is commissioned after the development risk has passed 8POWERGRID’s Rs 856.94 crore southern line upgrade must lift capacity without a new corridorDetails
8Three revised deviation accounts move lakhs without changing market rules 8A revised reserve-services account reopens payments after schedule corrections 8Avaada’s 350 MW grid bay enters licensing without an approval 8Tata Motors keeps 33 kV supply but must pay for upgrades 8Gujarat’s Rs 4.87 firm-renewable tariff puts dispatchability on trial 8INKEL says Kerala’s voltage rule is stranding renewable capacity 8Garda’s shared grid plan waits for a commissioning ruling 8MERC makes MSEDCL pay for the time value of delay 8Gujarat’s 360 MWh storage dispute leaves damages and deadline unresolved 8Bihar’s bagasse ruling will decide a 20-year revenue stream 8PSPCL’s unmapped tax balances make accurate municipal settlement impossible 8KSEBL’s power-purchase bill is rising faster than its sales cushion 8KSEBL’s carrying cost is turning old gaps into a new tariff problem 8Bihar discoms miss five reform proposals in the new Supply Code 8MSEDCL resolves Rs 18.44 lakh consumer delays only after escalation 8Kerala’s evening power auction tests the price of cover 8PXIL’s new trading engine launches into a market with no bids 8IEX core markets clear heavily while premium power finds no buyerDetails
8Premier Energies’ profit surge raises the stakes on simultaneous expansion 8G R Infra’s group growth masks a weaker standalone quarter 8Bajel’s order boom still depends on debt and margins 8Premier’s Rs 5,000 crore funding plan turns growth into a deployment test 8Ola’s dealer pivot moves service risk to third parties 8Coal India’s iron-ore bid opens a long road to diversification 8HCC’s flat profit cannot hide collapsing margins and audit doubts 8HCC’s rights-issue delay tests its promise to investors 8Reliance Power’s profit recovery cannot outrun defaults and forensic review 8Torrent’s renewable push runs into weak earnings and transmission delays 8Viviana’s 246% revenue surge leaves a Rs 1,313 crore order book to prove 8GEE enters NPCIL’s supplier list without winning any business 8JSW Mahanadi’s rating holds while its 2028 contract gap approaches 8Aditya Birla renewable debt shrinks while leverage stays high 8Failed technology keeps Rajasthan Sun Technique in default 8Dhursar avoids fresh impairment while audit qualifications remain 8Reliance Power faces three investigations with outcomes unresolved 8Reliance Power puts four project groups into discontinued operationsDetails
8DVC’s pollution controls cannot clear its stalled ash bottleneck 8Vrajesh’s 56 MW captive-power plan is deferred over unresolved site evidence 8Shree Radhe’s 25 MW captive plant wins a conditional clearance recommendation 8Shakambhari’s 484 MW captive plant advances with river and land questions attached 8Maa Kali’s 90 MW power plan moves forward beside homes and forest 8SRS Steel’s 35 MW captive plant clears the panel with strict pollution controls 8Siddhiriddhi’s 40 MW plant advances despite a heavy coal and ore logistics burden 8Jagdamba withdraws its 50 MW power proposal after errors in the filing 8Rajshri’s 37 MW captive project is deferred over its reliance on an estate clearance 8Nav Durga’s 51 MW expansion is returned over coal and groundwater demandsDetails
8Talcher Stage III slips as land, roads and materials block construction 8Kosi-Seemanchal grid reinforcements stretch into the 2030s 8Khavda collapse leaves state frequency accountability unresolved 8KSEBL's Rs 5,131 crore generation plan is cut to Rs 1,490 crore 8India's thermal pipeline includes 4,845 MW of stressed projects 8Premier opens a 5.6 GW module plant as execution shifts to ramp-up 8Namrup and Kudgi storage pilots wait for funding decisions 8Rajasthan's grid-support plan shrinks to two STATCOMs under review 8Thirteen state cyber proposals remain trapped at different approval stages 8Three Northeast grid-visibility projects remain trapped at different approval stages 8Punjab and Rajasthan islanding plans remain unfinished 8Bhivpuri's 2029 target still depends on forest and road clearances 8India's wave-energy ambition still has zero installed capacity 8SJVN’s 500 MW Khavda solar build enters its final-month delivery test 8Two contractors face a November test on SJVN's 200 MW project 8SJVN's 200 MW Phase XVII solar project slips to December 8Bagodra solar deadline moves fifteen months after earlier delay costs 8GUVNL Phase XIII slips fifteen months after liquidated damages 8SJVN's 260 MW Phase XIV solar project slips to June 2027 8Premier's 7 GW cell plant approaches trials after civil completion 8Premier’s 10 GVA transformer expansion enters its final-month delivery test 8Delhi's own generation share falls from 20% to 13% 8Delhi sanctions 3,521 smart meters but installs none 8Delhi tariff transparency stops at FY2023 8Mankulam's 40 MW hydro project stalls on an unaffordable bid 8KSEBL cancels one solar project while others miss expectations 8SJVN provides Rs 18 crore after Luhri-II's original design fails 8DVC biomass use stays tiny as Chandrapura rejects the fuel 8Vishnugad Pipalkoti tunnel progress reaches 85% 8Tapovan Vishnugad records a tunnel breakthrough with work unfinished 8Ramp limits expose a scheduling penalty trap for Maharashtra generators 8Supply disruption forces western generators to rewrite outage plans 8Western generators changed outage dates without required approvals 8Railway work exposes missing rules for generator evacuation outages 8Generators risk incentives because frequency-response data remain incomplete 8Forced outages leave western schedules above declared capability 8July partial outages remain poorly explained across western stations 8Chhattisgarh plants withhold 158 MW of downward flexibility 8Missing transformer settings weaken voltage and restoration planning 8Late event data undermines western frequency-response grading 8Haryana prepares for a three-day power-sector strike 8Etawah's clean reliability claim collides with Rs 887 crore of grid work 8Robertsganj remains on rostered power despite a Rs 411 crore push 8Tribal electrification totals leave 11,838 households on off-grid solar 8Centre leaves tribal supply-hour accountability with the states 8Bihar adds interstate capacity while local delivery waits 8India's transmission plan faces a land-compensation execution test 8Metro power questions receive national answers but no city results 8Uttar Pradesh awards 28 green-corridor projects with delivery still ahead 8Renusagar's 60 MW banking extension reaches UPERC 8Grasim banking pact reaches UPERC without disclosed capacity 8SJVN governance gaps reach the board and two key committees 8NTPC opens 135 engineering posts without evidence of a wider shortage 8Viviana's transformer plans lack cost and commissioning dates 8Viviana exits two subsidiaries without disclosing transaction value 8Reliance Power forfeits Rs 303 crore after warrants lapse 8LN Steel power plan is deferred after opposition and land gapsDetails
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance. Click on Reports for moreDetails
For reference purposes the website carries here the following tenders: 8Tender for EPC Package of power project Details 8Tender for biennial job contract for painting works Details 8Tender for Package cooling tower Details 8Tender for air condition system Details 8Tender for architectural works for renovation and modernisation at 6X60 MW Details 8Tender for supply of various patch cords and opticalconnectors/ attenuators Details 8Tender for procurement of mechanical seal of ECW pump Details 8Tender for procurement of insulation material for unit-1 boiler Details 8Tender for supply of ISI marked AAA rabbit conductor Details 8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details 8Tender for procurement of opacity/dust analyzer for measurement of dust concentration Details 8Tender for procurement of spares for IL makes pneumatic actuators and power cylinders Details 8Tender for procurement of 415V LT air circuit breakers of different capacity installed Details 8Tender for procurement of coupling for fan and motor shaft of PA and FD fan installed Details 8Tender for work of refurbishment reblading of ID fan impeller and fitting Details 8Tender for work contract for hotline tightness and PID testing work of 400kV and 220kV switchyard Details 8Tender for work contract for bushing gasket replacement of 220 kV station transformer Details 8Tender for procurement of spares of pneumatic actuator Details 8Tender for procurement of spares for transport air compressor ZA-6 for ash handling system Details 8Tender for supply of motors Details 8Tender for construction of switch house Details 8Tender for supply of MS plates and angle structures Details 8Tender for construction of anti-flood wall and water collection tanks to tackle water logging at 33 kV s/stn. Details 8Tender for assistance in shift operation of boilers, including their auxiliaries Details 8Tender for medium repair of RCF, replacement of PA fan impeller assembly Details 8Tender for establishment of centralized transmission asset management service Details 8Tender for civil works for installation of 6 KLD grey water treatment plant Details 8Tender for work of attending daily, routine defects, preventive, breakdown, shutdown and emergency maintenance of various auxiliaries Details 8Tender for procurement of beater plate for coal mill Details 8Tender for AMC for the work of maintenance, repairing & servicing of battery set, battery charger & reconditioning of battery cells at various substations Details 8Tender for rate contract for work of rewinding and repairing of various rating of LT motor, submersible pump and various Details 8Tender for supply of various MS / CS pipe, bends Details 8Tender for procurement of composite long rod polymer insulators Details 8Tender for supply of lighting arrester for 220kV & 400kV switchyard Details 8Tender for drawing 11kV covered conductor Details 8Tender for DP erection and HT cabling 33kV substation Details 8Tender for purchase of digital level meter Details 8Tender for attending leakages/seepages in various underground structures Details 8Tender for providing muffing on periphery of existing various steel structure of coal yard Details 8Tender for providing and fixing PUF panel operator cabin Details 8Tender for work of erection dismantling of 132kV/66kV/11KV equipment’s Details 8Tender for utilization of 6.50 lakh metric tonne dry fly ash Details 8Tender for operation and maintenance of 114 Nos power quality meter Details 8Tender for renewal of sophos firewall subscription Details 8Tender for demolishing of cement concrete rock fragments Details 8Tender for renovation and reconfiguration of through interior fit out works Details 8Tender for maintenance and repair work of power channel Details 8Tender for supply, erection & commissioning of 110 volt 500Ah lead acid tubular LM type battery set and automatic 110V/100 Amp. battery charger Details 8Tender for implementation of islanding scheme Details 8Tender for owners engineer and project management consultant (OE and PMC) for 22.5 MW hydro power project Details 8Tender for supply of 11 kV moving contact 400 Amps Details 8Tender for supply of ISI marked 33 kV aluminium conductor Details 8Tender for execution of deposit works, including the supply, erection, installation, testing, and commissioning of materials/equipment Details 8Tender for purchase of 25 kVA, 3 phase aluminium wound energy efficient level-1 (star-1) completely self protected (CSP) distribution transformers Details 8Tender for supply of ACSR rabbit conductor Details 8Tender for construction of 2x33 kV bay for water resource Details 8Tender for requirement of ASCO make spares Details 8Tender for supply of 0.30 LMT limestone Details 8Tender for auction for lifting and disposal of wet ash Details 8Tender for procurement of ABT and bidirectional features digital summation unit Details 8Tender for supply of TC fuse wire 18 SWG Details 8Tender for supply of TC fuse wire 16 SWG Details 8Tender for supply of TC fuse wire 14 SWG Details 8Tender for supply of TC fuse wire 12 SWG Details 8Tender for supply of bolts and nuts of size 88 x 16 mm Details 8Tender for supply of bolts and nuts of size 63x16mm Details 8Tender for construction of 110/33/11 kV outdoor control room Details 8Tender for erection of 110 kV DC line on DC tower with panther conductor Details 8Tender for construction of 110/33/11kV yard equipment plinths, cable trench Details 8Tender for procurement of grinding elements of 8.5E (9) coal mill Details 8Tender for evacuation of pond ash including Details 8Tender for supply and retrofitting of chinese brand chiller compressor unit of capacity Details 8Tender for laying of 11 kV 3C 300 Sq mm XLPE UG cable Details 8Tender for construction of 132 kV M/C transmission line Details 8Tender for repair with complete rewinding including dismantling, loading, unloading, to and for transportation, inspection, testing, and other allied works Details 8Tender for repairing dismantling and fixing cage of chain link cage around distribution transformer Details 8Tender for erection work of 66kV S/C line on D/C towers Details 8Tender for erection work of 66kV S/C line Details 8Tender for work of overhauling of diverter switch and drive mechanism box of the OLTC of the transformers Details 8Tender for work of feeder re-orientation at 110kV substation Details 8Tender for work of DGA testing of T/F oil and other tests of oil for ICT's & transformers Details 8Tender for supply of various types of cable & dismantling, ETC work of 245 & 145 kV circuit breakers Details 8Tender for supply of various types of cable & dismantling, ETC work of 36 kV circuit breakers at various S/Stns Details 8Tender for replacement of existing tower at 220kV 60 Deg new towers Details 8Tender for AMC for work of repairing & overhauling of OLTC of ICT/ transformer Details 8Tender for enhancement of transformation capacity of substation by providing 1x50MVA, 132/33kV PTR along with HV & LV bays and allied civil works Details 8Tender for enhancement of transformation capacity of substation by providing 1x50MVA, 132/33kV PTR along Details 8Tender for annual maintenance contract for repairs, overhauling of 33 kV CGL make VCB installed at various Details 8Tender for work of chemical washing of insulator strings manually by using high voltage insulator Details 8Tender for work of maintenance contract for attending emergency breakdown & allied maintenance of any EHV line Details 8Tender for AMC for work of repairing/overhauling with providing & fixing of spares for 33kV VCB at various EHV sub-stations Details 8Tender for work of auxiliary power supply for 400/220kV substation Details 8Tender for turnkey based contract for 11 kV AL-59 ACS medium voltage covered conductor (MVCC) with its accessories Details 8Tender for supply of wireless LCM kit for 220kV and 66kV class switchyard Details 8Tender for replacement of side & roof sheet of boilers, conveyor galleries Details 8Tender for rate contract for complete rewinding of LT(415V/230V) AC motors Details 8Tender for supply of switchgear spares Details 8Tender for job work for radiography of boiler tube weld joints Details 8Tender for work of attending the boiler tube leakages & various pressure part related misc. works Details 8Tender for works for turnkey based contract for 11 kV AL-59 ACS medium voltage covered conductor Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8Serentica Renewables commissions first phase of 1 GWh battery energy storage system in Bikaner Details 8Next phase of Green Energy Corridor to cover 10,000 ckm: Pralhad Joshi Details 8NHPC should accord top priority to 20,000 MW pumped storage pipeline: Parliamentary panel Details 8Views of Manohar Lal: “India’s power sector has made significant progress Details 8AI To Be Part Of India’s Power Generation, Adoption To Rise To 65% By 2030: ENCIS Study Details 8Coal supply for power sector adequate, July despatch up 18%: Coal Ministry Details 8Rajiv Kumar Porwal: Director (System Operation), Grid-India Details 8Coal Supply for Power Sector Comfortable in July: Govt Details 8India's Coal Stocks Enough for 62 Days as Supply Strengthens Details 8Breaking Data Silos: MoP’s draft framework standardises information sharing across the electricity value chain Details 8Loops Within Loops: India’s meshed power grid Details 8Picking up Pace: Leveraging the balancing, storage and ramping benefits of hydropower Details 8Maharashtra sugar mills earn over Rs 8,250 crore from ethanol and power generation Details 8Why privatising electricity distribution could be a mistake Details 8Why Power Grid Corporation of India Share Price Is Falling Details 8India’s EV industry to create 30-40 million jobs by 2030 Details 8India Inc Bets Big on Tech: Data Centres and AI Drive 56% of Massive Rs 26.75 Lakh Crore Capex Surge Details 8India’s EV sector could generate up to 40 million jobs by 2030 Details 8Sonbhadra: Uttar Pradesh’s Energy Capital Transforming in 2026 Details 8IIFL prefers CG Power, ABB India, Siemens and L&T to Cummins India Details 8CPDL Enhances Power Reliability in Sector-31C with 1000 kVA Transformer Augmentation Details 8Torrent Power: Why Is It Betting on Gas Plants When Everyone Else Is Chasing Renewables Details 8India’s Coal Stocks Reach 148 MT, 62-Day Power Buffer Secured Details 8Reliance Power Stock Update: Shares Jump 3% on Strong Q1 Results Details 8India Crosses 300 GW Renewable Capacity, Targeting 500 GW by 2030 Details 8Microsoft launches Hyderabad cloud region to power India's AI economy, strengthen enterprise adoption Details 8POWERGRID Approves Rs 856.94 Crore Transmission Upgrade Project in Tamil Nadu Details 8NTPC-SAIL JV Selects U-Solar Clean Energy for Rs 127.47 Crore 20 MW Floating Solar Project in Bhilai Details 8India's coal supply adequate, production rises by 7.51% in July Details 8First Coal Consignment from SCCL’s Odisha Mine Reaches Telangana, Marks Historic Milestone Details You can also click on Newsclips for moreDetails
8PFC Consulting's Lakadia–Vadodara 765kV ISTS tender opened bids 49 days after the date its own clause fixed The qualification notice records actual opening on July 17, with no reason assigned in the record. Six bidders cleared, but the top-50% formula alone would have cut the auction field to three — the minimum-four rule lifts it back to at least four. Line-side termination equipment sits inside this package while the GIS diameter it connects to belongs to a Khavda Phase-IV scheme.
8Power Grid won Krishnagiri REZ Phase-I at Rs 8,209.60 million a year, and no other number from the auction has been disclosed Five bidders reached initial-offer opening — Adani, Dilip Buildcon, PNC Infratech, Power Grid and Resonia — but the notices record only the winning tariff, leaving L2 and L3 spreads and the owner comparison invisible. The concession bundles two 765/400 kV substations, corridors to Doma, Raichur New and Sagar, a 300 MVAr STATCOM and spare bays sized for renewable growth well past the 4.5 GW being evacuated.
8RECPDCL's Kukshi–Alirajpur tender used a one-line amendment to attach Rs 40.11 crore of securities to a company it had not previously named Amendment-I replaces the placeholder "Name of the Project Specific SPV" across the RFP, TSA and SPA with Kukshi Alirajpur Transmission Limited — the breadth of the edit confirming the blank sat throughout the transaction architecture. No schedule of that company's assets, liabilities, approvals or litigation accompanies it, and the acquisition price still arrives only 20 days before the bid deadline.
8POWERGRID's 765kV GIS tender at Noida Sector-148 asks bidders to surrender competing routes into a project it hasn't won The pre-selected contractor signs an exclusive MOU and must withdraw from the same BPC project as bidder, subsidiary, partner or consortium member — while the execution contract materialises only if POWERGRID becomes the TSP. Document access closes August 31 against a September 2 bid deadline, with two days to cure a deficient NDA and one day to appeal a rejection.
8KPTCL's Ayyanahalli tender set its clarification deadline 30 minutes after bids closed The portal records receipt closing at 11:30 on 20 July and the clarification cut-off at 12:00 the same day, with the pre-bid meeting also at 11:30. Amendment-I, issued 3 August, then deleted the requirement that each consortium partner contribute 25% of the stipulated line quantity — a qualification relaxation issued with no revised submission date. No bidder attended the pre-bid meeting; the change came from two emails.
8BHEL's Koderma ash-handling EPC carries two documents giving opposite instructions on reverse auction The major-highlights sheet marks it applicable and cites NIT Clause 19.0; Clause 19.0 states it is not applicable, and five corrigenda passed without reconciling them. Corrigendum-X also collapsed the six-hour gap between closing and opening to zero, listing both at 11:00 on August 11, while a separate corrigendum deleted the MSME payment-timeline and LC note without naming a replacement clause. The tender reference itself appears as both KOD and KDM across the pack.
8BHEL splits the Koderma ash award into three work orders and gives the winner seven days to tell it how to divide the price Clause 35.0 requires a detailed price break-up within a week of LOA, after which separate orders issue for goods, erection and commissioning, and site-fabricated structures — with BOCW cess reimbursed on some components and borne by the contractor on others. Auxiliary power is capped at 350 kW with LD of USD 6,033 for each excess kW, and the portal records the tender value as zero.
8NTPC's Vindhyachal analyser-spares tender closes on the portal a full day before the deadline printed on its own notice The enquiry says bids should reach NTPC by 23:30 on the opening date by sealed envelope or registered post; the portal shuts electronic submission at 16:00 the previous day. EMD and PBG are both zero, but every part must interchange with the installed OXYMON equipment or be replaced free of cost — with no firmware or serial-range baseline stated for that test.
8CSPDCL's Jashpur transformer packages run a 60-day clock on work that depends on equipment the contractor doesn't supply The 63 kVA transformers stay in the utility's supply column while poles, insulators, arresters, earthing, cabling and civil inputs sit with the contractor, and no clause links completion to the date that equipment is issued. The Rs 3.09 lakh headline covers only the contractor's tax-exclusive BOQ against a Rs 5.48 lakh scheme estimate. Corrigenda go on the Pathalgaon project office notice board, not any digital channel.
8MPPKVVCL sealed the price bids on a Rs 1,329 crore metering tender and told the same bidders to quote again Reverse auction was never enabled on the original portal configuration, so a second limited tender was created solely to supply the missing price gateway — with the first BOQs expressly barred from opening. The fresh L1 becomes only the auction base, and the notice sets out no custody, archiving or audit rule for the superseded offers.
8MPPKVVCL's TS 1648 smart-metering tender lost half its field to technical evaluation and one more to a rule about a different lot Five of ten bidders fell — Aurawin on Rs 582 crore against a Rs 664.5 crore threshold, Infinite on 6 lakh meters against 8.44 lakh, Adani on a failed live demonstration. Iskraemeco was then excluded from price opening purely for being L1 in Lot 1, a restriction Corrigendum 4 extended to consortium and JV partners. EMD across all of it: Rs 1 lakh.
8DHBVN's Rs 148.21 crore RDSS package bars a contractor from sharing a store between adjoining circles Separate stores, storekeepers and round-the-clock security must be funded in each of seven operating circles, with no consolidation permitted even where the same firm holds both packages. Final erection payment also waits on asset data uploaded to the employer's GIS model, for which no validation turnaround is stated. Three extensions added almost 20 days to a 22-day original window.
8MPPKVVCL's SDAC award landed 0.5% under the owner estimate with a seven-year tail attached Synergy took it at Rs 255.24 crore against a Rs 256.59 crore estimate, with Ashida 1.9% behind — a two-bid contest after HKRP was rejected technically. Pre-bid requests for an aggregate cap covering LDs, SLA deductions, risk purchase and PBG invocation were answered "as per RFP", leaving multiple remedies potentially live against the same failure across 1,250 substations.
8KSEBL's Rs 255 crore Payyampally GIS tender rewrote its payment clause to hold 25% of every progressive bill for audit Corrigendum 9 replaced a flat 30-day term with 75% within 30 days after preliminary verification and the balance within 60 days after audit. Corrigendum 2 separately fixed a BoQ line describing 220 kV GIS as "3-400 kV, 4000 A" equipment. Requests to shorten the ten-year latent-defect tail, the 60-month defect period and the 180-day security validity were all refused; four extensions added 71 days.
8POWERGRID's 7TR-19-BULK transformer tender drops EMD and replaces it with a year's exclusion from future packages ITB 13.1 states bid security is not applicable; ITB 13.6 converts withdrawal, refusal of arithmetic corrections or failure to furnish performance security into one-year ineligibility. Losses carry LD at Rs 8–10 lakh per kW with outright rejection above 2%, and the 13 units' destinations are notified only before dispatch — while route surveys and any bridge or culvert modification stay in contractor scope with no cost ceiling.
8NTPC Green's Pudimadaka DM plant tender tells bidders what percentage of the price each schedule must carry Five-year O&M cannot fall below 16% of the package price, installation must sit between 20% and 25%, civil between 20% and 30%, and safety at no less than 2.5% — before any price comparison happens. Delay damages run at Rs 14,70,357 per day against a 5% cap, joint ventures and collaborators are barred outright, and the portal records no estimated contract value.
8UJVNL's Rs 259.60 crore hydro E&M tender deleted its rupee-value experience test and doubled the manufacturers a bidder may lean on Addendum II removed the Rs 103.84 crore / Rs 129.80 crore / Rs 207.68 crore similar-work thresholds; Addendum VI then let up to two OEMs jointly satisfy turbine and generator credentials. Addendum V opened the machine speed to 214.3 rpm alongside 187.5 rpm. Nineteen corrigenda and six addenda later, the deadline has moved 151 days — and Corrigendum 04's English and Hindi texts still carry technical-opening dates a month apart.
8DVC's Rs 1,336.26 crore Durgapur renovation gives the contractor 360 days and tells it to find the site conditions itself Across 105 pre-bid replies, DVC kept soil-resistivity assessment, site survey, layout preparation, cable sizing, remote-end PLCC commissioning and end-to-end E1 channel configuration inside bidder scope, and confirmed it will not supply the underground fibre between old and new control rooms — estimating 50-70 metres. No shutdown matrix exists for the live 220, 132, 33 and 25 kV systems the work cuts across. Three extensions have moved submission 34 days.
8TGTRANSCO's Rs 417.96 crore transformer tender caps price rises at 50% and lets price falls run uncapped Clause 14.8 limits positive IEEMA variation while imposing no floor on the negative side, and a late delivery is indexed to whichever date — scheduled or actual — favours the purchaser. Clause 35.1 permits a 50% swing in ordered quantity at award without touching unit rates, and Clause 56.1 allows deferral and restoration on three months' notice. The winner also posts a bank guarantee equal to the landed cost of two transformers purely to cover challenge testing. The pre-bid date printed in the tender table is April 16, 2025 — eleven months before the tender issued.Details
8Proposals under examination include Assam batteries, a vanadium flow system and NTPC's closed-Brayton-cycle storage project, showing how widely India is testing grid flexibility. The next test for Power System Development Fund is whether the opportunity represented by Rs 340 crore moves into contracts, finance and physical delivery.Details
8Developers say a connection-level security requirement is being applied bay by bay even though around 10 GW has already been commissioned. The significance of Gujarat's connection-guarantee regime extends beyond one transaction because Rs 12,000 crore, 60 GW, 10 GW can alter investment appetite, system planning or delivery risk.Details
8The procurement is designed to close part of a 2,832 MW gap left after earlier bidding under an approved 18,835 MW agriculture-feeder programme. For MSEDCL, the opportunity is substantial, but the case built around 2,269 MW, 2,832 MW, 18,835 MW still has to survive the commercial and execution tests that follow.Details
8Generation reached 14.60 BU after the group added 4,174 MW in a year, but its 60 GW ambition still requires a much larger execution step-up. The next test for NGEL is whether the opportunity represented by 10 GW, 4,174 MW, 60 GW moves into contracts, finance and physical delivery.Details
8The annual report exposes a large gap between winning projects and securing the agreements that turn them into financeable construction. The significance of NHPC extends beyond one transaction because 12,832 MW can alter investment appetite, system planning or delivery risk.Details
8The hydropower company expects roughly Rs 67,500 crore of debt needs over five years and says the existing Rs 60,000 crore ceiling could be breached in about three years. For NHPC, the opportunity is substantial, but the case built around Rs 70,000 crore, Rs 67,500 crore, Rs 60,000 crore still has to survive the commercial and execution tests that follow.Details
8The award leaves 505 MW of the tender unfilled even after 2,356.3 MW qualified technically, revealing the price boundary in a market still trying to rebuild momentum. The next test for SECI's 2 GW wind auction is whether the opportunity represented by 2 GW, 1,495 MW, 505 MW, 2,356.3 MW moves into contracts, finance and physical delivery.Details
8NHPC profit rises to Rs 4,220 crore after commissioning 1,850 MW, but construction pipeline keeps funding pressure high 8NHPC builds a pumped-storage pipeline of roughly 21 GW, but investigations and site approvals still separate pipeline from operating assets 8NHPC's 300 MW solar award remains caught between bustard protection and grid access, but another 349 MW is expected in FY2027 8NGEL starts a 2 GWh battery build-out in Kerala and Rajasthan, but contracts and commissioning will determine whether it becomes operating flexibility 8NGEL tests vanadium flow batteries alongside lithium storage, but bankability and operating evidence remain to be proved 8NGEL wins a 70,000-tonne green-ammonia award, but hydrogen cost, offtake and manufacturing readiness will decide its economics 8NGEL withholds its dividend despite profit growth because new projects need more equity than internal accruals can provide 8POWERGRID revenue reaches Rs 11,496.72 crore, but first-quarter profit eases to Rs 3,598.42 crore as earnings lag asset additions 8Siemens Energy posts record quarterly orders as Gamesa recovers, but the wind turnaround's durability remains central to the group result 8Urja Global proposes USD 500 million despite quarterly revenue of Rs 68.20 lakh and a Rs 18.77 lakh loss 8Ola and Axis Energy target 20 GWh of battery deployment by 2032, but the capacity remains envisaged rather than firmly awarded 8Waaree signs a related-party EPC contract for 210 MWp of solar, but the exchange filing does not disclose its value 8Welspun plans to expand from 45 MWp to 325 MWp by September, but transmission readiness and cash-flow conversion remain unproven 8Sunstream secures Rs 3.09 per unit for 100 MW of PM-KUSUM solar, but Rs 16.16 crore of approved central support remained unpaidDetails
8The power ministry backs only one year of bridge coal for MAHAGENCO, not the three years sought, as Gare Palma-II starts from a low base 8Barauni seeks another year of bridge coal as land delays hold back its captive Badam mine 8Uttarakhand seeks to keep coal linkage alive until March 2028, but its 1,320 MW procurement now targets power only from FY2031 8Tamil Nadu seeks to preserve coal for the 660 MW ETPS expansion, but the delayed PPP tender puts linkage validity at risk 8Chandrapura's planned 1,600 MW expansion seeks coal before a buyer, leaving its FY2032 target without a PPA 8Sinnar's 1,350 MW plant may restart after nearly a decade shut, but it still needs long-term coal and power buyers 8Government offices put rooftop solar on 24,376 buildings without a compulsory mandate 8Port hydrogen hubs cite Rs 85,000 crore of investment, but the first operating plant is only 5 MW and scalable to 10 MW 8West Bengal reaches 363.5 MW of solar capacity by June, but future growth depends on rooftop conversion, utility procurement and network readiness 8Madhya Pradesh commissions 2,608 MW of 4,208 MW sanctioned solar parks, but the remaining 1,600 MW still separates sanction from completion 8New small-hydro scheme targets 1,500 MW between FY2027 and FY2031, but environmental, hydrological and local-consent issues remain project specific 8Jharkhand and West Bengal carry an 872 MW solar-park pipeline, but their cited biomass capacity is only 19.1 MW 8Madhya Pradesh PM-KUSUM tariffs span Rs 2.94-Rs 3.25 per unit, showing why local land and network conditions prevent one farm-solar price 8Coal-gasification support rises from Rs 8,500 crore to Rs 37,500 crore, but eight earlier approvals show that sanctioned projects are not operating capacity 8Coal companies target 9.5 GW of renewable capacity by 2030, but their cited installed baseline is only 558 MW 8India's hydrogen-manufacturing awards await their first fully commissioned facility, and the official table still separates selection from operating production 8Nizamsagar's 2027 upgrade deadline remains, but none of the Rs 5.38 crore approved in 2017 has been released 8The Centre rejects a 15% free-power levy on interstate wind and solar, arguing that host-state benefits would raise tariffs 8PM Surya Ghar crosses 14.65 GW while applications far exceed completed systems 8BharatNet gets a single-window route for Rajasthan village connections, but applicants must still advance-fund the utility's demand notes 8Coal exchange names independent sampling agencies before trading starts, but grade and moisture disputes will test the market's credibility 8SJVN's 680 MW Attunli project returns for environmental appraisal, but the committee review is not a construction clearance 8New Ganderbal seeks to preserve clearance for 93 MW, but the long delay shows how approvals can expire before construction 8Torrent's 1,500 MW Patalkot pumped-storage project seeks study terms, but it remains far from construction approval 8A second battery-support scheme earmarks viability funding for 30 GWh, but sanctioned capacity still has to reach financial close and operation 8Model Solar Villages can receive up to Rs 1 crore each, but outcomes depend on durable assets, village demand and maintenance rather than awards alone 8Rooftop growth shifts grid spending toward local visibility, but the official response gives no single national integration cost 8Sawra Kuddu reports environmental compliance as tunnel works continue, but the 111 MW plant still needs independent performance checks 8India's all-lignite index jumps 14.9% in June, but a one-month surge does not establish a lasting fuel-cost trendDetails
8CERC keeps Rs 15 crore of ReNew Solar's guarantee while the developer says Rs 8.5 crore is excessive and ties up working capital 8CERC seeks equipment and grid evidence before deciding Adani's 333 MW change-in-law claim, leaving compensation unresolved 8SECI backs transfer of a 150 MW solar project and its grid rights, but approval must preserve connectivity obligations and contractual accountability 8Delhi High Court protection keeps Avaada's disputed connectivity alive, but the underlying case continues 8CERC reserves the Siang transmission case after finding an unexplained cost-and-tariff mismatch in the bidding record 8CERC reserves TANGEDCO's transmission-charge challenge, leaving the treatment of disputed drawal unresolved 8Adani's change-in-law compensation claims await CERC orders, leaving payment and carrying cost unsettled 8Karnataka utilities reopen coal-price and fly-ash benefits in their Adani dispute, but CERC has not decided the pass-through 8An Andhra power-contract proceeding pauses under a High Court order, preventing the regulator from reaching a premature conclusion 8CTUIL opens a route to reallocate vacant pooling-station bays, but applicants must still prove capacity, technology and compliance 8DCM Shriram asks Uttar Pradesh to clarify supplementary renewable contracts, but the issue now waits for a September hearing 8CERC keeps a capacity-charge dispute alive after an Andhra court intervention, but the challenged deductions remain unresolvedDetails
8MERC allows BEST to buy 220 MW of solar with 440 MWh of storage, but the contract must avoid an October cancellation deadline 8Haryana orders a 530 MWh battery retender by 30 September after the selected winner refused the earlier 500 MWh award 8Haryana reserves its ruling on green-energy banking, leaving the future value of surplus renewable power uncertain 8Haryana waits for a NISE study before fixing a 50 MW solar tariff, extending a dispute already returned on review 8Madhya Pradesh proposes reactive-power compensation for solar plants and prosumers, but payments and charges depend on the final mechanism 8Uttar Pradesh advances a data-centre distribution licence to public notice, but the order is procedural rather than a final grant 8Gujarat opens compliance proceedings under its 2025 renewable-purchase rules, moving the framework from notification to enforcement 8Gujarat fixes its FY2027 renewable-purchase benchmark, but three licensees receive no rate because required filings were absent 8A 243 MW Gujarat solar project seeks relief as its substation slips to 2027, making network-versus-developer delay the central dispute 8Torrent seeks more time for 280 MW of Gujarat solar, testing whether the developer should bear an evacuation-network delay 8Juniper commissions 100 MW of solar while 50 MW of wind remains delayed 8Defence restrictions push a 30 MW Gujarat hybrid project toward solar-only design, shrinking its technology mix after connectivity approval 8A Jamnagar developer offers a bank guarantee instead of open-access cash security, seeking utility protection without freezing project funds 8Gujarat weighs set-off for 516,202 units of green power injected in 2020, but procedural delay may erase their value 8Gujarat rooftop petitions test changing net-metering rules, as capacity increases, virtual metering and amendment dates complicate protections for older projects 8Jharkhand must recalculate DVC's tariff after remand, with a Rs 795.49 crore gap and surcharge treatment still disputed 8Chhattisgarh seeks comments on deviations in an 8 MW small-hydro contract before a September hearing 8Ajmer applies a 2.52% fuel surcharge after consumption, pushing power-purchase costs into customers' June bills 8Gujarat reserves its ruling on a 9 MW solar evacuation line, leaving unresolved who must pay for the infrastructure 8A 50 MW Gujarat wind project seeks a later supply date, placing responsibility for delay before the commission 8A Junagadh developer seeks until February 2026 for its final 4.7 MW, but Gujarat must judge partial completion against delay 8Gujarat hears connectivity relief for a 40 MW hybrid project, but the outcome depends on who caused the network delayDetails
8Western economic dispatch produces a net Rs 9.12 crore settlement for July, but plant-level gains and refunds show who benefited from centrally optimised schedules 8The western region sends Rs 275.68 crore to the northern deviation pool, exposing the financial scale of schedule imbalance 8The northern reactive-energy account pays Rs 1.304 crore while collecting Rs 0.618 crore, revealing uneven voltage-support outcomes 8Northern ancillary-service accounts pay some generators but penalise others, showing that reserve deployment alone does not guarantee revenue 8Thirteen deviation accounts are revised after a tariff factor falls to 75%, changing settlements retrospectively from January 8GE Vernova deviations delay a northern grid-control upgrade by eight to ten months, linking supplier performance to operator readiness 8The northern cyber forum flags missing BBMB audit evidence, exposing a gap between declared and tested security 8The Uri-I to Uri-II fibre link needs 10.456 km of access rights before it can improve grid communications 8India meets a 240,212 MW evening peak without shortage while nearly 49,736 MW remains unavailable 8Grid frequency stays above 50.05 Hz for 16.7% of the day, revealing periods when supply runs ahead of demand 8Bhutan and Nepal export power to India while Bangladesh draws more than 60 MU, underscoring opposite roles in regional electricity trade 8Day-ahead power price falls 25% to about Rs 3.27 per unit, but traded volume also eases roughly 3.4% 8APGENCO thermal plants run at a 63.26% August load factor, but several large units remained unavailable 8Sileru live storage falls to 26.53 TMCft from 56.03 TMCft, sharply reducing the basin's energy cushion 8NTPC produces 998.35 MU against a 968.15 MU programme as southern output offsets weaker northern generation 8Twenty-nine thermal plants remain critical as coal stocks reach 37.46 million tonnes against a 60.87 million-tonne norm 8A 765 kV Ariyalur-NCPS fault trips the line, but operators restore it by 10:09 pm the same eveningDetails
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance. Click on Reports for moreDetails
For reference purposes the website carries here the following tenders: 8Tender for civil work for transformer increasing capacity from 3x160 to 4x160 MVA and related bay Details 8Tender for work of providing and fixing of differential line protection relay Details 8Tender for civil work for construction of 01 No. 33 kV bay Details 8Tender for repair of plaster, painting and other misc. civil works Details 8Tender for civil work for construction of store shed other related civil works at 220 kV S/S Details 8Tender for construction of 2x40 MVA 132kV AIS S/S Details 8Tender for construction of balance works transit camp, store and other misc. civil works Details 8Tender for installation of additional earthing with shield wire and counterpoise type earthing of towers Details 8Tender for supply and retrofitment of control and relay panels Details 8Tender for procurement of hexa damper spacer with bolt and nut, washers etc. Details 8Tender for procurement of current to pressure convertor, air filter regulators and SS fittings Details 8Tender for work contract for ecological monitoring and survey covering Details 8Tender for construction of 110/33/11kV yard equipment plinths, cable trench Details 8Tender for erection of 110kV DC line on DC/MC tower Details 8Tender for construction of 110kV yard equipment plinths, cable trench, quarry dust filling, metal spreading and allied other civil works etc. Details 8Tender for work of rewinding / repairing of various capacity AC & DC motors Details 8Tender for purchase of bearing housing and spares for 6.6kV HT motor Details 8Tender for supply of porcelain solid core bus post insulators Details 8Tender for EPC package for development of 10 MLD DE-mineralistion plant Details 8Tender for repair and maintenance of civil works Details 8Tender for construction of store shed platform with ramp Details 8Tender for work of repair and dynamic balancing of shafts and impellers of 20 cumec pumps Details 8Design, supply erection commissioning and testing of water distribution system for natural draught cooling towers installed Details 8Tender for supply of various sizes of M S ERW pipes and bends Details 8Tender for supply of ACB & panel spares Details 8Tender for providing chain-link fencing Details 8Tender for assistance for day to day maintenance and cleaning work of fire hydrant, refilling and testing of fire extinguishers miscellaneous work etc. Details 8Tender for procurement of spares of pumps installed at CW pump house Details 8Tender for comprehensive repair and maintenance of control room including flooring, sanitary works Details 8Tender for construction of chemical earthing for tower along Details 8Tender for repair and maintenance of control room at 220/132/33 kV GSS Details 8Tender for construction of 01 no. storage warehouse Details 8Tender for construction of shed over HT and BH and other miscellaneous civil works Details 8Tender for supply, erection, testing & commissioning of 3 KM, 33 kV overhead line extending from 33/11 kV substation Details 8Tender for construction of protection wall along Details 8Tender for constructing of HT/OH feeder Details 8Tender for reconductoring with LT transformer Details 8Tender for construction of new 33kV bays at 16 nos GSS Details 8Tender for construction of new 33kV bays Details 8Tender for insurance coverage of material/ equipment lying at various stores/ transformer Details 8Tender for civil work for transformer augmentation of 132/33 kV 20/25 MVA T/F Details 8Tender for construction of foundations, cable trench, levelling and dressing, GSB for transformer track Details 8Tender for repairing of HP module of 250MW turbine Details 8Tender for supply of different type of Weir BDK make pneumatic as well as manual butterfly valves for CPU system Details 8Tender for work of Dog to panther conversion of 66kV line Details 8Tender for work of LILO of both circuit of 66 kV D/C line Details 8Tender for mechanical strengthening and H-frame painting of 66kV line Details 8Tender for manufacture, testing & supply of armoured ISI marked single core 11kV 300MM2 size stranded aluminium conductor Details 8Tender for erection/ dismantlement of towers, beams and busbars at various 220/132/66kV substation Details 8Tender for supply of electrical actuator for feed control valve Details 8Tender for work of routine, preventive, scheduled & breakdown maintenance in coal handling plant Details 8Tender for supply of consumable material Details 8Tender for supply and installation of lightning arresters in various distribution Details 8Tender for installation/replacement of old and defective DTR LT cable Details 8Tender for construction of 11/0.4 kV S/S and related HT/LT line Details 8Tender for supply of De centerlize material for 33/11 kV substation Details 8Tender for increasing capacity of transformers and construction of new transformers Details 8Tender for supply and installation of 990 KVA compact secondary substation Details 8Tender for supply of vaccume interepter for 11 kV VCB Details 8Tender for supply and installation of 990 KVA compact secondary substation Details 8Tender for supply and installation of 990 KVA compact secondary substation and other associated work Details 8Tender for earthing of DTRs at 11 kV Fulsunga and Bagwara feeder emanating from 33/11 kV S/s Details 8Tender for replacement of wesel conductor Details 8Tender for replacement of bare conductor by AB cable in 11 kV Siroli feeder Details 8Tender for replacement of bare conductor by AB cable Details 8Tender for replacement of wesel conductor with 11 kV AL- 59(ACS) 104.98 Sq.mm covered conductor Details 8Tender for reconstruction of 33 kV Sidcul line Details 8Tender for annual maintenance of lines, DTRs, etc., and redressal of consumer complaints along Details 8Tender for work of replacement of existing ACSR weasel conductor with rabbit conductor Details 8Tender for replacement of existing ACSR weasel conductor with rabbit conductor from the 33/11 kV sub-station Details 8Tender for replacement of existing bare LT conductor by LT aerial bunched (AB) cable, including dismantling of the existing conductor Details 8Tender for work of installation of distribution transformers, construction/augmentation of HT/LT lines Details 8Tender for work of providing and erecting additional electric poles Details 8Tender for increasing capacity from 100 KVA to 250 KVA transformers at various Details 8Tender for providing another 11 kV supply for ITDA and USDMA Details 8Tender for supply and retrofitting of LT incomer/tie breakers and modules Details 8Tender for supply, erection, testing and commissioning of 220V DC, 63 AH, KPH 63P, Ni-Cd type battery set Details 8Tender for supply, installation, commissioning and testing of new high bay LED lighting system Details 8Tender for interior repairing and maintenance of 18 nos. C/D-type Details 8Tender for biennial contract for engagement of EOT crane operators Details 8Tender for procurement of 04 Nos. 220 kV outdoor type current transformer Details 8Tender for procurement of 06 Nos. 220 kV outdoor type current transformer and 03 Nos. 220 kV capacitive voltage transformer Details 8Tender for dismantling reassembly and inspection including leakage repairing of water lubricated turbine guide Details 8Tender for manufacture, testing, supply and delivery of composite hardware fittings for ACSR weasel/rabbit conductor (30/50 sq mm) and Dog conductor Details 8Tender for supply, fabrication & erection of steel structure, erection of equipments, erection of earth mat, earth raisers, laying of control cable, end termination, etc Details 8Tender for supply, fabrication & erection of steel structure, erection of equipments, erection of earth mat, earth raisers, laying of control cable Details 8Tender for work of providing & fixing of manual operated gear box for 245/145/33/11kV isolators at various substations Details 8Tender for annual maintenance for civil assets Details 8Tender for annual maintenance for civil assets of 132 kV sub/stn Details 8Tender for metal spreading with earthing pipeline, repair of damaged compound wall renovation of control room with other miscellaneous civil works Details 8Tender for supply of hydraulic accumulator, bladder, Nitrogen charging kit & fittings for coal mill Details 8Tender for work of annual maintenance contract for work of repair, servicing, overhauling and maintenance of window/split air conditioner Details 8Tender for work of supply & installation of eDAQ (energy data acquisition) and automatic log sheet generation with real time data monitoring and trending system Details 8Tender for supply of spares and repairing, servicing & overhauling VCBs at various sub stations Details 8Tender for work of retrofitting of existing BPL make PLCC link of 132 kV line Details 8Tender for work of overhauling & servicing of 400 kV CB type GL316 spring operated mechanism at 400/220 kV substation Details 8Tender for dismantling old RCC concrete structure & erection of EHV equipments on new lattice type GI structure Details 8Tender for work of providing & fixing of additional jumpers on tension towers of the various lines Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8Inspiring India: Gujarat Woman's Solar Mission Earns PM Modi’s Praise, Invitation to I-Day Ceremony Details 8India's solar growth enters a new era Details 8Headsup B2B Signs INA Solar Distribution Deal, Targets Rs. 150 Crore Solar Revenue Details 8Delhi’s electricity transition challenges and opportunities: A SCOPE study Details 8Rayzon Green to Develop 9 MW Solar Project in Gujarat Details 8Oriana Power Invests INR 2.10 Crore In Wholly Owned Subsidiary For Solar Project Development Details 8Serentica Renewables Commissions First 200 MWh Phase of 1 GWh BESS in Rajasthan Details 8Top Undervalued Renewable Energy Stocks in India to Add to Your Watchlist Details 8KKHSOU organises awareness programme on Energy Conservation and Renewable Energy Details 8India’s Muft Bijli Solar Scheme Crosses 5 Million Household Milestone Details 8India needs to focus on grid integration of clean energy capacity, say experts Details 8Eastern Railway Freight Handling Rises as Coal Movement to Power Plants Surges Details 8India solar generation reaches 10.9% share as grid limits widen Details 8NSPCL Awards 20 MW Floating Solar EPC Contract in Chhattisgarh Details 8Odisha Targets 11 GW RE Details 8Building the next phase of India’s solar and battery revolution Details 8Why privatising electricity distribution could be a mistake Details 8Inox Wind wins Rs 1,600-crore order from NLC India for 200 MW wind project Details 8Tripura to solarise 5,000 drinking water pumps, eyes major cut in power bills Details 8ANUGYAN: IIT Hyderabad and CEEPL Launch India's First Nuclear Technology Orientation Programme Details 8Schneider Electric, BRPL Partner for India’s First Pure Air RMU Pilot Details 8Chhattisgarh Cabinet approves Rs 500 crore AI mission, BEML plant and key governance reforms Details 8Indian Railways Freight Loading Rises 9% to 141 MT in July Details 8Global Energy Storage Funding and M&A Roundup: Key Trends Details 8Rooftop solar power far exceeds government estimate: IEEFA Details 8India's Green Energy Shift: Focus Moves to Grid and Storage Details 8Monsoon disrupts life in Himachal Pradesh; 153 roads blocked, 191 power transformers down Details 8Valiant Communications Stock Hits 10% Upper Circuit After Bagging Rs 10.71 Crore Power Grid Order Details 8Odisha Eyes Electrical Equipment Manufacturing Boom; Joins Gujarat in Race to Woo High-Employment Sector at August Investor Meet| Special Report Details 8UP Supplementary Budget 2026-27: Yogi Govt’s Rs 59,019 Crore Plan Boosts Expressways, Power and Welfare Details You can also click on Newsclips for moreDetails
8Renewable plants, batteries and large electricity users would become more active participants in grid security under the draft 2026 connectivity standards.Details
8Evening market prices hit Rs. 10 a unit while the frequency-deviation index reached 27.6%, connecting system stress with the cost of last-minute power.Details
8The utility’s long-range portfolio is no longer mainly a coal build: renewables, batteries, hydro and nuclear become essential to the next 165 GW.Details
8Battery operations supplied Rs. 226 crore of quarterly revenue and reported a capex yield above 20%, offering rare evidence of storage economics at scale.Details
8PM Surya Sarovar moves floating solar from scattered projects toward a national programme, but reservoir and grid constraints will decide its value.Details
8More than 21 lakh loan applications were sanctioned under PM Surya Ghar; the remaining gap shows why approval is not the same as money reaching a household.Details
8Madhya Pradesh grants its PM MITRA textile park a 25-year power distribution licence 8Maharashtra keeps Rs 48 crore withheld as Warora transmission work slips to May 2028 8Madhya Pradesh orders a banking procedure after renewable applications remained pending 8Punjab opens a tariff case over the unquantified Mega Power benefit at Talwandi Sabo 8Uttar Pradesh begins a railway open-access case after a Supreme Court ruling 8Madhya Pradesh gives itself flexibility to set the electricity ombudsman's compensationDetails