All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Oct 2026
DVC widens escalation cover on Rs 90.20 crore Chandrapura line diversion while design risk stays with the contractor
8Seven corrigenda have moved bidding by 63 days, split the award into goods and services contracts and added steel polygonal poles and MV cables to IEEMA price adjustment.
8The deeper issue is whether broader index relief can offset laying methods, bonding and pipeline separation still deferred to detail engineering under an unchanged 12-month programme.
MPPTCL opens eight-transformer trial route for new vendors but leaves price discovery with incumbents
8Corrigendum-II reverses the "Not Applicable" new-vendor clause on the 54-unit 132/33 kV tender, reserving about 15% for trial orders that use a Rs 1.00 placeholder quote and must match L1.
8The sharper question is whether a Rs 20.05 crore resource threshold and full EMD make one- or two-unit allocations commercially viable for newcomers.
POWERGRID locks in exclusive 765 kV Lucknow-II–Asana construction partner before winning the tariff bid
8TL03's pre-bid tie-up demands an exclusive MOU, bans tractor erection and makes the contractor responsible for any unlisted item needed for commissioning within 33 months.
8What is not disclosed is how release, bid-preparation cost and pricing will be treated if POWERGRID loses the upstream competition.
POWERGRID asks Pirpainti transformer supplier to commit exclusively before the transmission project is won
8TR52T covers 200, 100 and 80 MVA units at three Bihar substations, with a collaborator-backed qualification route carrying an extra 10% equipment guarantee.
8The open question is when the 22-month clock starts and how long price and production capacity must be held while the tariff outcome is pending.
RRECL makes cycle-loss promise decide both ranking and 40-year revenue on Rs 5,400 crore Rampura pumped storage project
8The 900 MW/5,400 MWh BOOT tender ranks bids on AFC × (1 + cycle loss), then fixes that declared loss for the full term, with excess losses billed at up to twice APPC.
8The deeper issue is whether bidders can price that commitment while the delivery point shifts between 400 kV and 765 kV Phagi and subsurface investigation remains incomplete.
RVPN's Rs 136.60 crore Lohawat line notice arrives with mismatched references and an off-formula bid security
8The turnkey 220/132 kV package cites two different specification numbers and demands Rs 2.742 crore security, about Rs 1 lakh above an exact 2%, while a sister package matches 2% precisely.
8The sharper issue is what the notice leaves unsaid on ROW, GSS readiness and delay relief across an 18-month survey-to-commissioning chain.
JVVNL makes past repair backlogs decide future share of 40,000 self-protected transformers
8The Rs 256.40 crore 16 kVA tender pairs tight loss ceilings with all-cause replacement, payment that depends on lab testing and now targets day 45 instead of day 30, and allocation cuts for unresolved repairs.
8The deeper question is whether uncapped IEEMA escalation is enough to offset the liquidity and warranty exposure a low bid must carry.
TGGENCO bundles Yadadri railway siding into one Rs 114 crore O&M contract but leaves unloading failures to the evidence trail
8The three-year package requires 382 deployed positions, 98% rake release within free time and a contractor-funded recovery fleet, while railway recoveries sit outside the 10% penalty cap.
8The sharper question is whether same-shift reporting can reliably separate siding failures from those of the separate unloading agency before deductions bite.
WBSETCL's C13 composite package pushes corridor compensation onto the contractor before a uniform auction cut
8The Raiganj LILO and Khatra 132 kV corridors demand standalone transmission, bay and HTLS credentials, with ROW costs priced upfront and every BOQ rate cut proportionately in reverse auction.
8The deeper issue is whether margins survive when the low-bid security wording and a 0.7 km route-quantity mismatch remain unreconciled.
SECI ties Gaya 60 MW solar O&M security to generation value while module scope stays contradictory
8The 84 MWp EPC-plus-O&M auction scales security to annual generation at Rs 3.60/kWh, retains interest-free retention for thin O&M pricing, and shows a portal EMD 100 times the contractual figure.
8The deeper issue is whether bidders can price a P75 output guarantee while the documents disagree on who procures the PV modules.
RVPN prices HTLS losses at Rs 1.68 lakh per kW on Lohawat lines with no bonus for beating them
8The four-line package evaluates offers at the highest-loss make quoted, makes performance and delay damages concurrent, and forces service charges to at least 15% of supply.
8The sharper question is how bidders price ACSR conductor obligations that the scope includes but the BOQs never schedule.
POWERGRID seeks exclusive Pallu–Panipat 765 kV partner on a scope that stretches to anything commissioning needs
8TL02 combines the tractor ban, composite mats and an entity-only 90 km experience test with 80% financial relief for start-ups and MSEs.
8What is not disclosed is how unlisted commissioning work, escalation and payment milestones will be priced before the conditional award becomes executable.
RRECL concedes service-charge relief on EV charging tender but pulls every rupee of customer fees into escrow
8The seven-package, Rs 99.77 crore PM E-DRIVE tender now allows pro-rata revenue-share cuts after regulatory reductions, limits staffing to carports and has moved closing by 40 days.
8The deeper issue is whether undefined escrow release and subsidy timing leave enough cash to sustain H1 revenue-share promises over 10 years.
RVPN rewires ACSR Panther allocation so L1 can win as little as 20% of 6,020 km
8Amendment 3 replaces local-enterprise preference with an MSE and 50% domestic-content matrix in which allocation follows the L1 bidder's category, while four extensions have moved closing by 50 days.
8The sharper question is whether matching L1 on a no-minimum-purchase rate contract leaves preferred suppliers any margin, with Rajasthan medium enterprises now dropped from the preference tranche.
NHPC refuses inspection concessions on Uri-I Stage-II gates as extension crosses a financial-document cutoff
8The Rs 88.57 crore Lot-II package keeps witnessed steel testing and the filling-in valve hold point, excludes GST from turnover and shifts closing into October.
8The deeper issue is how a 38-month contract reconciles with milestones running to month 44 from the civil works LOA.
UPPTCL's Prayagraj GIS tender gates supply payment on civil readiness while its scope names an Agra site
8The Rs 102.16 crore 220/33 kV substation links 70% supply payment to completed halls and trenches, caps high-priced items at benchmark rates and replaces arbitration with management-led resolution.
8The sharper question is how bidders price four transformer bays the BOQ requires but the technical scope describes as one.
NHPC stretches Link-3 bidding by 124 days but moves TBM delivery by only one month
8Corrigendum 8 on the Rs 2,253.97 crore Himachal water conveyance tender raises financial and concreting thresholds, eases gate qualifications and deletes the TRCM test, yet keeps TBM availability at December 2026.
8The deeper question is whether any bidder can be awarded, procure and mobilise a double-shield TBM in that window after a 21 October closing.
KPTCL admits GIS experience for Chokkasandra package as recorded award sits 27% above GST-exclusive estimate
8Amendment-I opens the AIS-only substation route to GIS credentials and tightens accessory testing for both cable sizes, while import queries get only "existing conditions prevail."
8What the record does not disclose is whether the Rs 90.36 crore award includes GST, which decides whether the gap reflects pricing or tax.
UHBVN squeezes 63 kVA transformer price below L1 and splits award with L3 while L2 gets nothing
8The negotiated Rs 1,14,500 rate cuts Century's bid by 1.4% and Vidhata's by 6.9%, splitting 37,648 minimum units roughly 60:40 even though Ganpati trailed L1 by just Rs 19.
8What is not disclosed is why the near-tied L2 received no allocation after qualifying.
Showing 1–4 of 4 items
For daily newsletters and other free services, fill in your details: