8RRVPN has quietly rewritten its procurement script by awarding the Fatehgarh GSS package BOQ-wise instead of selecting a single turnkey L1. 8The result is a three-contractor mosaic carrying split responsibility for transformers, civil works and capacitor-bank integration. 8The deeper story is how this fragmentation reshapes risk, accountability and commissioning certainty.Details
8GUVNL’s latest BESS award sets a new benchmark for what storage developers must guarantee over a 12-year lifecycle. 8The capacity charges look simple, but the penalty architecture behind them reshapes risk, bankability, and augmentation economics. 8The real story is how thin the developer margin becomes once availability, RtE and degradation are enforced simultaneously.Details
8REC’s Mekhali 400 kV package has drawn a surprisingly stacked field of six sole bidders. 8But the real story lies in how aggressively the RFP pushes design, clearance and multi-corridor execution risks onto the developer. 8The tariff battle now hinges on how these players price that risk in the e-reverse auction.Details
8NTPC’s latest ash-handling award locks in a razor-thin price edge that exposes how intense the logistics competition has become. 8Guru Kripa Logistic emerges L1 by barely 2.7%, signalling a market operating at the edge of margin viability. 8The real story is how fixed-price ash transport under GeM is reshaping contractor risk for the rest of NTPC’s coal fleet.Details
KSEB’s Edamon GIS tender drifts through five extensions as civil–SAS complexity reshapes bidder strategy 8KSEB’s 400 kV Edamon GIS package has now slipped through five successive extensions, signalling a project still settling its technical and integration footing. 8The uploaded specifications point to a civil-heavy, SAS-dense scope that demands deeper OEM coordination than typical substation builds. 8The real tension lies in how vendors price uncertainty when the scope is stable but the timeline refuses to settle.Details
HVPNL pushes GIS-bay turnkey deadline to 22 December as multi-substation interfaces slow bidder readiness 8HVPNL has extended the GIS-bay augmentation tender to 22 December after bidders struggled to stitch together multi-node Siemens-GIS integration plans. 8The package spans eight substations and demands adapter engineering that few contractors can fast-track. 8The new timeline buys breathing room, but also raises questions about bidder depth in Haryana’s GIS market.Details
APSPDCL tightens contractor filters as SIP-26 feeder-segregation tender demands high credentials and full-chain EPC delivery 8APSPDCL’s latest RDSS segregation tender sets unusually steep qualification thresholds for a district-wide 11 kV feeder overhaul. 8The structure pushes the job firmly into mid-tier EPC territory while tightening compliance through Class-I local supplier norms. 8What this does to competition, pricing and execution risk becomes clear only once the financials open. APSPDCL tightens RDSS feeder-segregation playbook with a high-bar Rs 99-crore EPC package in Nandyal 8APSPDCL has issued an unusually demanding EPC tender for segregating 69 agricultural feeders in Nandyal. 8The PQ thresholds look more like transmission-project filters than conventional RDSS norms. 8The real story is what these barriers reveal about APSPDCL’s evolving risk appetiteDetails
For reference purposes the website carries here the following tenders: 8Tender for procurement of geared motor Details 8Tender for providing stub setting, concreting, tower erection, stringing of 230 kV SC line on DC tower Details 8Tender for providing stub setting, concreting, tower erection, stringing of 230 kV SC line Details 8Tender for inspection, checking of supply and return pipe lines of bearing cooling water, arresting leakages Details 8Tender for overhaul of ash slurry disposal pumps 1A1 and 1A3 pump capacity Details 8Tender for attending preventive maintenance of fuel oil pump house equipments Details 8Tender for procurement of 54 Mtrs straight pipe Details 8Tender for providing stub setting, concreting, tower erection, stringing of 230 kV SC line on DC tower Details 8Tender for providing stub setting, concreting, tower erection, stringing of 230 kV SC line on DC tower with zebra conductor Details 8Tender for providing stub setting, concreting, tower erection, stringing of 230 kV SC line Details 8Tender for providing stub setting, concreting, tower erection, stringing of 230 kV SC line on DC tower Details 8Tender for providing stub setting, concreting, tower erection, stringing of 230 kV SC line Details 8Tender for supply, installation, commissioning and training of 02 sets of automatic tester Details 8Tender for estimate for interconnection of 33 kV outgoing feeder Details 8Tender for work for renovation of 100 KVA, 21 Nos. 200 KVA and 10 Nos. 315 KVA DTR Details 8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details 8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substations Details 8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details 8Tender for work contract for AOH of boiler non pressure part Details 8Tender for rate contract for repairing of damaged defective power transformers Details 8Tender for supply of disc insulators Details 8Tender for restoration along with height raising of 220 kV transmission line Details 8Tender for supply for air motor Details 8Tender for strengthening work of crusher house Details 8Tender for supply of ERW SS 310 pipes Details 8Tender for replacement of buckled corroded Flat type top cover with new dished end type top cover of buffer hopper Details 8Tender for supply of single pole AB switch and HG fuse unit Details 8Tender for preventive maintenance and emergency breakdown works in EHT lines Details 8Tender for procurement of filter element for plate gap type filter cartridges Details 8Tender for expansion of (2 X 500 MW) project Details 8Design, fabrication, supply, installation, testing, commissioning with RMS 30 KW capacity grid connected solar PV power plant Details 8Design, fabrication, supply, installation, testing, commissioning of total 210 KW grid connected solar PV power plant Details 8Tender for work of various miscellaneous maintenance work Details 8Tender for erection, testing and commissioning of contingency start up power system Details 8Tender for service contract of OH BD and amp PM reactors Details 8Tender for work of electrical breakdown maintenance of towers Details 8Tender for routine, preventive/breakdown maintenance of HT/LT transformers Details 8Tender for supply of H.V. bushings of power transformers installed Details 8Tender for construction of 33 kV sub station Details 8Tender for construction of 33 kV GSS Details 8Tender for supply of earthing chain Details 8Tender for re-valdation of tower Details 8Tender for supply of gearbox of ball tube mills Details 8Tender for restoration of damaged diversion tunnel Details 8Tender for regarding purchase of detection alarm devices and servicing of fire detection alarm panel installed Details 8Tender for providing of new 30 MT electronic weigh bridge structures Details 8Tender for attending to preventive and breakdown maintenance works in coal mills Details 8Tender for overhauling of roller journal assembly and renewal of wornout grinding rolls of HP 803 mills Details 8Tender for supply of overhauling, repairing and maintenance work of 11 kV VCB S/S Details 8Tender for supply of overhauling, repairing and maintenance work of 11 kV VCB Details 8Tender for attending to preventive and breakdown maintenance works like renewal of wornout grinding elements Details 8Tender for attending to routine maintenance works and upkeeping of mills, feeders, coal pipes etc Details 8Tender for collecting of coal mill rejects from the mill chute, dumping Details 8Tender for attending to preventive and breakdown maintenance works like renewal of wornout grinding elements, ring roll setting, carrying out patch welding in coal pipes etc Details 8Tender for attending to routine maintenance works and upkeeping of mills, feeders, coal pipes etc Details 8Tender for augmentation of 132 kV substation Details 8Tender for miscellaneous electrical maintenance works Details 8Tender for annual rate contract for rewinding of LT motors and repairing of LED lights Details 8Tender for augmentation of 220kV substation Details 8Tender for supply of high mast LED light Details 8Tender for providing fire suppression system for the generators Details 8Tender for rerouting of feeder Details 8Tender for laying of 33kV UG cable in connection with construction of 33kV substation Details 8Tender for breakdown and regular overhauling works in scrapper feeders Details 8Tender for modular replacement of boiler hot reheat coil assemblies Details 8Tender for work of railway crossing by 11 kV 185 mm2 U/G XLPE cable Details 8Tender for erection of 66kV feeder bay Details 8Tender for work for repairing and reinsulation of faulty rotor poles Details 8Tender for estimate for interconnection of 33 kV feeder Details 8Tender for rate contract for supply of ISI marked AAAC rabbit and raccoon all aluminium alloy (AAA) conductors Details 8Tender for supply of rechargeable long range LED search light Details 8Tender for procurement of condenser water inlet and outlet bellows, installed Details 8Tender for procurement of critical spares of BFP recirculation valves for up gradation of existing Details 8Tender for work contract for routine maintenance of equipment and system installed Details 8Tender for procurement of spares for various types of gearbox Details 8Tender for procurement of hydrochloric acid HCL and caustic storage tank installed Details 8Tender for extension in the existing erector Details 8Tender for supply, installation, testing & commissioning for the modernization of lift Details 8Tender for supply and work for design, engineering, installation, erection and commissioning of complete belt weigher system and CMC for 3 years of various belt weighers Details 8Tender for supply of aluminum plain sheet & corrugated sheet Details 8Tender for supply of collecting electrodes for ESP Details 8Tender for supply of media filter for ACF and PSF and work of overhauling and replacing media Details 8Tender for repair and renovation of new dormitory at power station Details 8Tender for construction of 3 nos. 132kV by 110V PT foundations Details 8Tender for repairing and maintenance civil work at 33/11 kV sub-station Details 8Tender for supply, installation and commissioning of 5 No 6.6kV VCB panel Details 8Tender for service contract for upcoming overhauling of rotary air preheater, oil, coal and De-Nox burner Details 8Tender for works contract for the execution of various works Details 8Tender for setting up of 2000 MW energy storage capacity Details 8Tender for treatment/filling up of scouring/cavity developed beneath the existing concrete Details 8Tender for replacement of RCC structure by lattice type structure of various 400/220 kV equipments Details 8Tender for annual rate contract for servicing and overhauling of 11/22/33kV VCB poles & mechanisms of with required spares Details 8Tender for replacement of RCC structure by lattice type structure of various Details 8Tender for replacement of RCC structure by lattice type structure of various 220/132/110 kV equipments & BPI’s at various Details 8Tender for work of AMC for work of maintenance of switchyard Details 8Tender for work of overhauling / repairing of 11/22/33kV circuit breakers Details 8Tender for work of overhauling, servicing & supply of spares for 145kV circuit breakers Details 8Tender for attending daily/routine activities/defects, preventive maintenance, shutdown & emergency maintenance of electrical auxiliaries Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8Tata Power secures LOI for Jejuri–Hinjewadi Power Transmission Project Details 8Polycab expands presence in India’s EV charging ecosystem Details 8Panel flags 2-3 year coal mine clearance delays; seeks faster approvals Details 8Coal Remains India's Energy Backbone, House Committee Report Reaffirms 1.5 Bn Tonne Target For 2030 Details 8Coal Mining: Panel Urges Faster Green Clearances Details 8Indian Railways Scales Up Renewable Energy Use For Traction, Nears Full Electrification Of Broad Gauge Network Details 8Oyster Green Hybrid Three & Kshema Power Announce 350 MW, 220 kV Transmission and Substation Development in Madhya Pradesh Details 8Falling renewable costs alone won’t lower electricity bills; Govt working on action plan Details 8Assessing the effectiveness of India’s solar Production Linked Incentive scheme Details 8Kshema Power bags order for 33 kV 220 kV AIS power substation Details 8KETO Motors to Establish Electric Bus Manufacturing Facility in Telangana Details 8Kalpataru Projects International bags new orders worth Rs 2,003 crore Details 8Adani Group to invest up to Rs 12 lakh crore in India by 2031: Gautam Adani Details 8TotalEnergies sells 1.74% stake in Adani Green Energy for Rs 2,778 crore Details 8Maharashtra Government's Water Resources Department Inks MoUs For Hydroelectric Projects, Pouring Rs 23,800 Crore, Propelling 11,500 Jobs Details 8EPC stock jumps after securing 2,003 Crore orders, boosting its YTD order book to Rs 17,000 Crore Details 8Vedanta to invest Rs1 lakh crore in Rajasthan to ramp up output Details 8Union Power Minister: India’s ‘energy sector super highway’ will run through Raja Details 8Centre has no list of future project cancellations: Pralhad Joshi Details 8India Records Highest-Ever Nuclear Electricity Generation This Year Details 8Sharika Enterprises joins hands with Russian engineering pioneer ENS for Digital Power solutions in India Details 8OPTCL Secures Rs 1,685 Crore NABARD Loan to Strengthen Odisha Power Transmission Network Details 8India’s clean energy ambition takes full shape in the race to 500 GW Details 8ACME Solar appoints KR Thiyagarajan as President – EPC Details 8India gas consumption falls 7.5% in Jan-Oct amid monsoons, cheaper fuels Details You can also click on Newsclips for moreDetails
1. RTM’s weekly weighted MCP averaged Rs 3.51 /kWh 8Real-Time Market weighted MCP averaged Rs 3.51 /kWh for 2025-12-04 to 2025-12-10 (min Rs 2.80, max Rs 4.35). Inference: Higher cleared volumes mid-week alongside moderate price dispersion on IEX’s RTM panel. Why it matters: Signals a broadly liquid week with manageable imbalance costs for portfolios hedging with RTM.
2. DAM’s Sunday print slumped to Rs 2.58 /kWh 8Day-Ahead Market on 2025-12-07 printed a weighted MCP of Rs 2.58 /kWh (Rs 2,584.60/MWh). Inference: Lower weekend demand plus higher sell interest compressed the print; no ATC binds flagged on NLDC indices next days. Why it matters: Weekend price floor helps reduce procurement-cost averages for weekly portfolios.
3. Frequency held center with brief tails at dawn and early peak 8On 2025-12-10, mean frequency 49.993 Hz; FDI 19.1; max 50.269 Hz at 06:02; min 49.740 Hz at 07:17. Inference: Early-morning ramp before solar pickup; later stability aligns with AGC activity. Why it matters: Tight control reduces DSM volatility and balancing costs.
4. Ancillaries showed heavy net down-dispatch on TRAS 8On 2025-12-10, TRAS despatched +7,694 MWh (Up) and –32,115 MWh (Down); SRAS +5,765 / –6,061 MWh. Inference: Net down-bias consistent with over-commitment risk and stable frequency near 50 Hz. Why it matters: Indicates system preference to soak excess, shaping on-bar prices and DSM exposure.
5. No corridor reliability breaches flagged on 2025-12-10 8NLDC System Reliability Indices show 0 blocks / 0 hours violated across WR-NR, ER-NR, NR import, NEW-SR, NER import. Inference: Planned capacity and no (N-1) proxy binds kept network unconstrained. Why it matters: Unconstrained backbone ensures DAM/RTM prices reflect fundamentals, not rents.
6. Voltage deviations surfaced at 765 kV Ajmer; others stayed within band 8Ajmer 765 kV logged 2.57 % time outside IEGC band on 2025-12-10 (max 801 kV, min 765 kV, avg 781 kV). Inference: Local reactive management drove brief over-voltage windows; most nodes within limits. Why it matters: Even small VDI tails at 765 kV warrant tap/VAR diligence to avoid insulation stress.
7. Eastern region met evening peak cleanly with zero shortage 8Eastern Region supplied 22,967 MW at 19:00 with zero shortage on 2025-12-10; day energy 465.62 MU. Inference: Balanced availability and schedules at state peripheries sustained full coverage. Why it matters: Demonstrates robust ER balance on a business-day peak, lowering reliance on imports.
8. SCUC leaned on sub-Rs 3 /kWh ECR in multiple blocks 8D-1 SCUC for 2025-12-11 cleared units with ECR as low as 272.5 paise/kWh (blocks T49–T64). Inference: Economic dispatch prioritised low-ECR coal in mid-day blocks to compress balancing costs. Why it matters: Affirms merit-order discipline and moderates MCP when corridors remain open.
9. One large pithead station showed just 3.9 days of coal 8Rajiv Gandhi TPS reported 3.9 days of coal on 2025-12-09 against requirement 7.2 days (rail-fed). Inference: Stock drawdown outpaced receipts; exposes short-term supply risk if rail lags. Why it matters: Sub-week stock at a major station can tighten inter-regional balancing if prolonged. Click on Details for moreDetails
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days. Get the daily updates for : 8LNG 8Crude 8Chemicals 8Fertilizers 8LPG 8Ammonia 8Coal & Coke 8All tankers 8Bulk and Dry cargo Click on Reports for more.Details
8Operationally, the months show opposite energy balances: October’s decrements marginally exceed increments, but November shows increments far exceeding decrements, signalling a stronger reliance on SCED up-dispatch. Click on Details for moreDetails
8With TRAS-Emergency provisions now live for both inter-state IPPs and large RE stations, the period reveals a grid in which DSM, VARh and ancillary levers are increasingly intertwined, and behavioural discipline in a few states and plants can shift the entire region’s weekly cash flows. Click on Details for moreDetails
8In the RE corridors around Bhuj, Barsaita Desh, Morjar and other Gujarat–MP solar/wind hubs, the pattern is even starker: single-phase faults, no auto-reclose attempt, complete evacuation loss and “no representation” from project developers when the matter comes back Click on Details for moreDetails
8In the PVUNL event, a transient Y-phase fault on the Tenughat–PVUNL line is cleared by successful A/R, yet a main-2 relay at Patratu trips the 400-kV PVUNL–Patratu-1 line instantaneously in zone-3 because its time delay was left at 0 ms from earlier anti-theft operations. Click on Details for moreDetails
8How Balimela lost 370–390 MW twice in four days, first to a broken jumper and then to lightning-induced R-Y-earth faults, with all units tripping on overspeed/over-frequency as evacuation collapsed. Every further delay keeps a large block of flexible hydro at the mercy of first-fault contingencies and raises questions over Odisha’s ability to rely on this station for black-start or peaking support. Click on Details for moreDetails
8The Eastern Region that is running increasingly on protection “luck” rather than protection discipline. Correct tripping may have improved versus August, but spurious operations have now climbed to 55% of incidents in October, even as multiple 220-kV hubs So what is layered is fresh compliance pressure: SPS schemes must now see annual mock testing, hydro and HEP plants must demonstrate black-start readiness, and utilities are being named in colour-coded protection-performance tables month after month. Click on Details for moreDetails
8CEA data suggest ISTS transformer capacity additions are outpacing intra-state growth, improving north-western RE evacuation reliability ahead of FY 2026 peak targets. The trend underscores India’s grid transition towards high-voltage, multi-state interconnection. Click on Details for moreDetails
8The data indicates India’s power transmission build-out remains steady, anchored by HVDC and 400 kV corridor upgrades crucial for renewables integration. Click on Details for moreDetails
8November’s achievement was only 35 ckm against a target of 3,217 ckm, identical to October’s pattern (R2, cost optimisation and R6, clearance delays). This confirms continuing weak momentum in infrastructure TOT and BOOT models. Click on Details for moreDetails
8The slower execution tempo reflects seasonal and regulatory constraints rather than policy fatigue, keeping the sector’s expansion trajectory broadly intact. Click on Details for moreDetails
8The finding signals that monthly cost variation recovery under Regulation 87 is now fully institutionalised, with consumer-tariff impact visible in September and December billing cycles. Click on Details for moreDetails
8India’s coal mining clearance architecture—spanning environment, forest, and community approvals—remains complex and time-consuming, especially for private developers. With clearances taking up to 34 months for private blocks, a government committe calls for a calibrated balance between expeditious approvals and ecological responsibility, signalling a policy shift toward data-driven, transparent, and uniform clearance governance Click on Details for moreDetails
1) APCPDCL levies Rs.0.40/unit FPPCA for October 2025 as per APERC’s automatic monthly pass-through 8The company also noted that agricultural consumers’ component will be claimed from the state government as subsidy. The move marks another operational cycle under the new monthly automatic true-up framework notified by APERC.
2) APEPDCL’s September 2025 FPPCA shows steady procurement and falling unit cost as NTPC drawals normalise and IPPs step back 8The overall picture is one of tactical cost containment through dispatch optimisation rather than structural demand change. Click on Details for moreDetails
8Receivables, power-purchase provisions, and actuarial gaps keep pressure on the balance sheet. The combined result is a narrow improvement in gross income but continued erosion of reserves, indicating structural, not cyclical, stress Click on Details for moreDetails
8This synchronised adjournment effectively pauses further adjudication on renewable purchase and compliance obligations that have been contentious between industrial petitioners and the Jharkhand Renewable Energy Development Agency. Click on Details for moreDetails
NgEL hard-codes OEM-grade accountability into its Pudimadaka green hydrogen hub substation tender 8NgEL has released a turnkey GIS–transformer package that locks in modular, unmanned substation design as a baseline for its hydrogen hub. 8The qualification rules quietly reshape who is even allowed to bid. 8What this structure reveals about NgEL’s future hydrogen infra strategy sits behind the paywall.Details
KPCL tightens commercial posture as 2.50-lakh-MT coal-import tender shifts full price and quality burden to suppliers 8KPCL’s revised import tender sharply recalibrates the commercial landscape, anchoring bidders to a rigid firm-price structure. 8With quality-linked deductions, mandatory 18% GST loading, and a tougher PQR framework, the package effectively filters out marginal traders. 8The underlying shift is clear: suppliers must now shoulder far greater exposure to market volatility to remain competitive.Details
8A three-way financial contest ended with a decisive low-ball bid that reshapes BHEL’s logistics cost curve. 8The spread between bidders hints at radically different risk assumptions for Nepal’s terrain-driven hydro routes. 8What this does to execution margins — and whether it becomes precedent — is the real story behind the wallDetails
KSEB tightens specifications and delays bid window as Dhyuthi 2.0 Idukki package enters controlled-procurement mode 8KSEB has reshaped the Idukki Dhyuthi 2.0 tender through a trio of mid-cycle corrections. 8Technical parameters and vendor options have been locked down even as the bid window was pushed close to year-end. 8What this does to bidder strategy and risk allocation is now the real story.Details
For reference purposes the website carries here the following tenders: 8Tender for civil works related to construction of 2x5 MVAR capacitor bank at 132 kV sub station Details 8Tender for diversion of 220 kV underground line Details 8Tender for complete operation of power house Details 8Tender for supply, installation, testing and commissioning of auto trip console (ATC) and wireless dual tripping protection system Details 8Design, engineering, supply, erection, testing and commissioning of 220kV and 33kV GIS transformer/reactor bays along with associated works Details 8Tender for supply of hexagonal bolts nuts step bolts Details 8Tender for procurement of hardware for cluster expansion of integrated Details 8Tender for procurement of spares for pnuematic actuators and power cylinders installed Details 8Tender for procurement of critical spares of high capacity auxiliary Details 8Tender for procurement of spares of goods lift and thereafter installation Details 8Tender for construction of additional transformer and allied civil works at 66 kV S/S Details 8Tender for construction of all technical civil works Details 8Tender for construction of additional transformer and allied civil works Details 8Tender for construction of civil works for addl. 20MVA 66/11kV power transformer Details 8Tender for renovation/remodeling works for workers accommodation Details 8Tender for replacement and rerouting of 500 mm (20 inch Dia.) CI water pipeline Details 8Tender for centralized rate contract for procurement of high chrome mill shell liners for BBD 4760/4772 type coal mills installed Details 8Tender for construction of cement concrete link Details 8Tender for SITC of earth pits and earth strips at various oil storage tanks Details 8Tender for repairing and annual maintenance work of 33 kV O/D VCB Details 8Tender for construction of new HT line Details 8Tender for replacement of 33kV and 11kV line jumper Details 8Tender for repearing of 11VCB at 33/11kV S/S Details 8Tender for repearing and installation of LA, CT,33kV CP, VCB Details 8Tender for capital overhauling of HP,IP,LP turbine Details 8Tender for annual maintenance contract for maintenance of structural steel works Details 8Tender for servicing of integrated spindle of liechti G-mill twin CNC 5-axes machine Details 8Tender for supply of ACSR MOOSE conductor for switchyard Details 8Tender for supply of 200NB cast basalt pipe Details 8Tender for chain link fencing work Details 8Tender for procurement of 6.6kV 3500KW BFP motor Details 8Tender for BMC for C and I systems Details 8Tender for service contract for supply and application of paint on structural steel Details 8Tender for laying of 9500 meter pipes of 500 NB for balance work of garlanding for lagoon Details 8Tender for biennial contract for misc civil works Details 8Tender for procurement of 11 kV,1220 KW Make up water motor Details 8Tender for laying of HT cable Details 8Tender for as and when required, miscellaneous civil works Details 8Tender for construction of compound wall, plinth protection Details 8Tender for supply of gland packing ring & rope Details 8Tender for dismantling of existing rail track, strengthening of track foundation Details 8Design, supply, installation, testing, commissioning and replacement of 2MVA, 6600V/433V power transformer Details 8Tender for procurement of beater plate for coal mill Details 8Design, fabrication, supply, installation, testing, commissioning of solar based home light systems Details 8Design, fabrication, supply, installation, testing, commissioning of total 75 KW grid connected solar PV power plant Details 8Design, fabrication, supply, installation, testing, commissioning of total 270 KW grid connected solar PV power plant Details 8Design, manufacture, testing and supply of 2 Core 150 ohm HF cable 9360 meter Details 8Tender for manufacturing and supply of 33 kV out door vacuum circuit breaker Details 8Tender for procurement of potential transformer of various voltage class Details 8Tender for repairing of auxiliary steam header, and replacement of steam line Details 8Tender for procurement of 350 MM NB C.I. pipe Details 8Tender for supply of guarding cross arm Details 8Tender for increasing capacity of DTR (16 KVA to 25 KVA) and line strengthening work Details 8Tender for outsourcing activity for gen. routine Mtc. of RB and NRB, providing sanitation services Details 8Tender for creation of 2 no. 66 kV line Details 8Tender for construction of 25/31.5 MVA , 66/11 kV T/F Details 8Tender for fabrication and erection of steel structure shed along with associated civil works Details 8Tender for De-siltation of raw water pond Details 8Tender for empanelment of contractors and finalization of rates for execution of electrical works upto 11 kV HT /LT level Details 8Tender for estimate for new 1x5 MVA,33/11 kV S/s Details 8Tender for supply, installation, testing and commissioning of testing equipment, measuring equipment and machinery, transformer oil storage tank etc. Details 8Tender for rate contract for supply of various capacities of VRLA (SMF) battery bank or equivalent Details 8Tender for installation, testing and commissioning of 11 kV line, distribution transformer, LT line Details 8Tender for installation, testing and commissioning of LT line Details 8Tender for replacement of 250 KVA transformer Details 8Tender for work for releasing of HT and LT new service connections in 33/11 kV S/s Details 8Tender for work for releasing of HT and LT new service connections Details 8Tender for work for releasing of HT and LT new service connections in 33/11 kV S/s Details 8Tender for over haul of ash slurry disposal pumps ASP G1 G2 of Model AR 250 650 AM pump capacity 425 m3 hr including Details 8Tender for supply erection and commissioning of chilled water outlet pipe Details 8Tender for over haul of ash slurry disposal pumps Details 8Tender for supply & installation of bird flight diverter on 220 kV line Details 8Tender for purchase of HT stay and LT shackle insulator Details 8Tender for purchase of GI bolt for LT shackle insulator Details 8Tender for supply of spares for APM 2025-26, of powerhouse Details 8Tender for annual contract for transportation, loading, unloading, winching, turning & clearing, dismantling & erection of power transformers / ICTs / reactors Details 8Tender for procurement of agro residue-based biomass non-torrefied pellets Details 8Tender for services for internal inspection and overhauling of three phase 315 MVA generator transformer Details 8Tender for breakdown preventive maintenance and overhauling of bowl mills XRP803 and HP 803 raw coal feeders Details 8Tender for construction of 11 kV line Details 8Tender for increasing capacity of DTR (16 KVA to 25 KVA) and line strengthening work of 11 kV and LT line Details 8Tender for construction of 11 kV line to provide grid connectivity to solar plant Details 8Tender for supply and delivery of LT suspension clamp with bracket for (25-70) SQMM messenger wire for LT AB cable Details 8Tender for biennial maintenance contract for tit bit maintenance job Details 8Tender for procurement of insulation material for overhauling job Details 8Tender for roof treatment work Details 8Tender for rotation or replacement of dry fly ash conveying, BA slurry and FA slurry, BAOTP and FADP discharge pipe line Details 8Tender for procurement of GE formerly substation and bay controller and its spares for 400kV switchyard Details 8Tender for procurement of carb clad coated seat and gate/disc of rotary segregating valve Details 8Tender for procurement of spare materials for high intensity and low intensity aviation warning system Details 8Tender for procurement of hydraulic spares of tippler and side arm charger Details 8Tender for replacement of RCC structure by lattice type structure of various 400/220 kV equipments Details 8Tender for annual contract for transportation, loading, unloading, winching, turning & clearing, dismantling & erection of power transformers / ICTs / reactors Details 8Tender for work of servicing & overhauling along with providing & fixing of required spares of 33kV circuit breakers Details 8Tender for work of overhauling / repairing of 11/22/33kV circuit breakers Details 8Tender for work of overhauling / repairing of 11/22/33kV circuit breakers at various Details 8Tender for work of replacement of rusted MS tower leg joint plate Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8Report Flags Apple India Suppliers’ Lag on Renewable Energy Goals Details 8GIP eyes minority stake in Aditya Birla Renewables with Rs 3,000 Crore investment Details 8Green energy stock to buy now for an upside of 43%; Recommended by Motilal Oswal Details 8Kalpataru Projects International bags new orders worth Rs 2,003 crore Details 8Waaree Energies: 1 GW Solar Module Output Record Details 8The skills gap, not capital, is India’s real green energy bottleneck Details 8Karnataka Turns 3,500 Healthcare Centres Solar, Cuts Power Bills by 80% Details 8BlackRock fund to invest about $225 million in Aditya Birla Renewables Details 8Rooftop solar systems installed on nearly 24 lakh households Shripad Yesso Naik Details 8MERC and state discom imposed power tariff hikes by violating law: Cong MLA Details 8India’s Bargain Battery Bids Spark Big Fears For Energy Storage Future Details 8UP Government To Replace 11.32 Lakh Old Smart Meters With Prepaid Ones Under RDSS; Work To Be Completed By 2027 Details 8Tata Power Commissions 400 kV Koteshwar-Rishikesh Transmission Line Details 8Hydro project developers violating pacts, not employing locals, says J&KNC MP Ahmad Kichloo in RS Details 8Manoj Kumar Upadhyay Deputy Adviser – Energy Vertical, NITI Aayog Details 8India's solar push hits slowdown as transmission and demand gaps emerge Details 8Rewiring India’s Electricity Future: Watt’s Next for Jammu & Kashmir Details 8Reforming Distribution: Draft amendment bill seeks to bring in competition and ensure discom health Details 8Elara bets on NTPC, Power Grid; sees hydro sector on strong long-term path Details 8NLC India declares commercial operation of Unit-2 (660 MW) at NUPPL’s Ghatampur Power Project Details 8Towards One Nation, One Tariff: Policy suggestions for the power distribution segment Details 8Reforming Distribution: Promise and pitfalls of the Draft Electricity (Amendment) Bill, 2025 Details 8Block Deal: Power stock in focus after shares worth Rs 685 Crore exchange hands Details 8THDCIL Begins COD of 3rd Tehri PSP Unit, India’s First Variable-Speed Hydropower Details 8Cummins India Unveils Next-Generation Power Solutions at EXCON 2025 Details 8IndiGo Turbulence Revives Debate On Market Power And Monopoly Risks Details 8Elara bets on NTPC, Power Grid; sees hydro sector on strong long-term path Details 8India’s Renewable Generation Reaches 28.26 Per Cent So Far in 2025–26, Installed Capacity Stands at 49.63 Per Cent Details 8Strong Demand: Government schemes drive capacity addition Details 8India’s Ultra-Low Battery Storage Bids Spark Viability Concerns Details You can also click on Newsclips for moreDetails
1) DAM stayed mid-3s even without ATC binds 8The DAM weighted MCP averaged Rs 3.68/kWh during 2025-12-03 to 2025-12-09, with a low Rs 2.56/kWh (2025-12-07) and high Rs 4.24/kWh (2025-12-04). Inference: Prices moved across a wide band despite zero ATC/(N-1) corridor violations on 2025-12-09, pointing to supply–demand dynamics rather than inter-regional constraints. Why it matters: Portfolio hedges built on “transmission-bind = price spike” heuristics under-explain recent DAM variance, raising basis risk for short positions.
2) RTM printed a single cap-hour; rest cleared in the low-to-mid 3s 8On 2025-12-09, IEX RTM hit the Rs 10,000/MWh cap at 18:00–19:00 (Hour 18); the day’s weighted average was ~Rs 3.29/kWh, with min ~Rs 1.77/kWh. Inference: The lone cap spike coincided with tight evening supply (sell bids dipped relative to cleared volume), while frequency showed many out-of-band excursions the same day. Why it matters: One cap hour can distort intraday anchors without signalling system-wide scarcity, complicating RTM block-bidding strategies.
3) Southern Region met peak with zero shortage; frequency stayed near 50 Hz 8On 2025-12-09, SR met 47,282 MW at 19:00 with 0 MW shortage, frequency ~50.04 Hz; off-peak 36,012 MW also met with 0 MW shortage. Inference: This reliability outcome contrasted with CEA’s 2025-12-08 Southern thermal output running ~-23% vs annual target, implying non-thermal sources and/or interchange carried the slack. Why it matters: Planning margins increasingly hinge on flexible resources and net-interchange, not just thermal output against plan.
4) North-East 400-kV nodes showed perfect voltage discipline on 2025-12-08 8Multiple NER 400-kV nodes (e.g., Azara, Balipara, Misa) spent 100% of hours within 380–420 kV, with VDI = 0%. Inference: The next day’s national frequency still saw large out-of-band time, suggesting local voltage compliance does not guarantee all-India frequency stability. Why it matters: Reactive support and voltage control are working locally even as active-power balancing remains the stress point nationally.
5) Maintenance skew: large units out in the North and West even into December 8As of 2025-12-08, major units remained under planned/forced maintenance, e.g., Rihand 500 MW (overhauling), Talwandi Sabo 660 MW (boiler overhaul), Mahatma Gandhi TPS 660 MW (AM), Rajasthan APS 700 MW (forced major). Inference: Extended outages into December tighten evening flexibility even when inter-regional ATC shows no binds. Why it matters: Commitment stacks must discount nameplate capacity; outage persistence can widen DAM–RTM spreads during ramps.
6) PXIL RTM: near-zero liquidity except two evening cap blocks 8On 2025-12-09, only 17:00–18:00 and 18:00–19:00 cleared on PXIL RTM—both at Rs 10.00/kWh—while the rest of the day showed 0 MWh scheduled. Inference: Price discovery concentrated elsewhere (contrast with IEX’s continuous clears) underscores exchange-specific depth risk for RTM strategies. Why it matters: Participants depending on PXIL for intraday balancing face execution risk outside a couple of peak blocks.
7) Hydro Day-Ahead block was a no-show across exchanges on 2025-12-09 8HPDAM cleared 0 MWh on both IEX and HPX across all 24 hours on 2025-12-09, despite sizeable sell bids (IEX lists >5,000 MWh offered in many hours). Inference: Either buy-side interest was absent or hydro was monetised via other products; the result was no hydro-specific day-ahead liquidity. Why it matters: Without HPDAM depth, hydro flexibility won’t translate into transparent pre-dispatch prices.
8) Week’s softest DAM print came on Sunday; sell bids were the heaviest 8The lowest DAM MCP in the week was Rs 2.58/kWh on 2025-12-07, the same day sell bids peaked at ~596,981 MWh. Inference: A classic “Sunday surplus” suppressed MCP without any recorded corridor violations two days later—underscoring that surplus supply, not ATC, drove the trough. Why it matters: Weekend price curves warrant separate bid logic; copying weekday shapes leaves money on the table. Click on Details for moreDetails
8The combined result is a system under operational discipline but escalating structural obligations the classic MYT tension between efficiency gains and capital deepening. Click on Details for moreDetails
8The shift signals altered scheduling behaviour—likely driven by improved bilateral availability, moderated demand, or strategic risk-mitigation against exchange volatility. Click on Details for moreDetails
8The combined picture is one of incremental progress on core frequency metrics but a need to re-target mitigation efforts at a shifting cluster of 765 kV nodes and at the emerging ER–NR (N-1) pocket. Click on Details for moreDetails
8Across BSES Rajdhani’s licensed area, total recorded outage instances increased from 1062 in October to 1149 in November 2025, with the share of unplanned outages rising from 21 % to 26 %. Click on Details for moreDetails
8Deep true-up cuts reshape cost trajectory Key decisions around GCV relaxation, SHR norms, O&M allowances and coal mix optimisation will materially influence MSPGCL’s fixed and variable charges over the next five years. Click on Details for moreDetails
1) Rajasthan’s merit order stack stays flat as coal and gas costs only shuffle at the margins 8Rajasthan still relies on a relatively narrow band of low-cost coal and lignite units for economic supply, while liquid and RLNG peakers sit at the top as expensive insurance rather than everyday workhorses.
2) Rajasthan’s merit stack flattens at the margins as KTPS costs ease and CTPP charges creep up 8For Rajasthan’s utilities and regulators, the picture is of continuity with micro-adjustments: there is no upheaval in the merit order, but the evolving balance among KTPS, CTPP and SSCTPP will influence how much room the system has to optimise procurement around the cheapest coal-based power. Click on Details for moreDetails
8Eastern region VAR pool flips behaviour BSPHCL–JUVNL credits surge as GRIDCO turns payer and Bangladesh interface becomes a deep VAR sink The Bangladesh interface simultaneously deepens as a VAR drawal hotspot Click on Details for moreDetails
1) WR DSM costs halve but RE QCAs and Maharashtra keep burning money 8The structural tension is clear: tightening state-level discipline has not yet translated into disciplined renewables or a reduction
2) WR SCED flips from net credit in October to sharp payback by late November 8Western Region SCED behaviour between October and the last week of November shows a clean structural swing: the region moves from being a net gainer from the national SCED pool to a net payer, driven by heavier downward re-dispatch in the latest week.
3) WRPC ancillary revenues halve in a fortnight as SCUC windfall concentrates in a handful of NTPC coal stations 8Behaviourally, the data points to persistent over-commitment and corrective down-regulation at the VSTPS/Mouda/NSPCL cluster versus more surgical ancillary use around Solapur and the gas fleet – a structural tension with direct implications for tariff design and future capacity optimisation.
4) Gujarat’s VAR bill halves while Maharashtra and Mundra step up as Western Region’s compensators 8Overall, the fortnight reads like a quiet redistribution of VAR responsibilities, with Gujarat buying headroom, Maharashtra and key NTPC stations monetising more disciplined operation, and a handful of corridors (KSTPS–Korba (W), DNHDD interfaces, Raipur/Bhatapara ICTs) emerging as structural watch-points for WRPC.
5) WRPC tightens the noose on RE generators 8SVG, auxiliary supply and protection lapses pushed to December hard-stop with threat of curtailment and third-party audits For developers and OEMs, the story is no longer about “work in progress”; it is about whether they can meet the December 2025 compliance wall without triggering regulatory or commercial penalties. Click on Details for moreDetails
1) Rajasthan stress, islanding delays and testing mandates collide in back-to-back OCC meetings 8Underneath the bureaucratic language, the story is of a northern grid being asked to behave like a high-reliability, RE-heavy, code-compliant system while many states still plan like it is business as usual.
2) IEGC 2023 testing mandate turns modelling into a compliance battlefield 8By quoting Regulation 40 of IEGC 2023 in full and insisting on five-year testing plans via a central Google sheet, regulators are effectively shifting dynamic model validation from an engineering nice-to-have into a regulated obligation. The commercial subtext is that testing budgets, outage windows and vendor contracts for advanced studies will all need to be baked into utilities’ business plans – or they risk being caught non-compliant post-event.
3) New RE+Storage Procedures: The Next Battleground for Deviation Charges and Waivers 8The new procedure on scheduling, metering, deviation settlement, transmission-charge waivers and REC treatment for RE generators and energy storage systems pushes the northern region into the next phase of market design. For developers, this document will decide whether hybrid and storage projects can stack revenues efficiently or get tripped up by opaque deviation penalties and complex waiver conditions. Click on Details for moreDetails
1) AP & Kerala turn net gainers as RE portfolios still bleed and Talcher-II stays the weak link in SRAS. 8Reactive energy continues to be settled at 6 paise/kVArh under the new IEGC framework, keeping a low but steady financial signal layered on top of DSM and SRAS.
2) Are RE and hybrid portfolios structurally DSM-negative? 8This is what persistent data seems to be showing Click on Details for moreDetails
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days. Get the daily updates for : 8LNG 8Crude 8Chemicals 8Fertilizers 8LPG 8Ammonia 8Coal & Coke 8All tankers 8Bulk and Dry cargo Click on Reports for more.Details
APDCL tightens performance discipline as 15 MW Bamgaon solar bid shifts full evacuation and CUF risk to developers 8APDCL’s latest 15 MW solar tender looks simple on the surface but hides one of the toughest CUF and grid-interface regimes seen in the Northeast. 8Developers get clear land but carry the entire burden of evacuation, penalties, and long-term generation compliance. 8The clauses signal a shift toward high-accountability solar procurement in Assam.Details
NTPC’s switchyard tender drifts nearly a year as repeated scope resets and design freezes stall closure 8NTPC’s 400 kV GIS tender for Telangana STPP-II has slipped through fourteen extensions, stretching a February 2025 deadline into January 2026. 8The real story lies in the shifting protection and PMU architecture that repeatedly forced bidders back to the drawing board. 8What this means for project sequencing and EPC risk remains behind the paywall.Details
KPCL’s RTPS coal-movement tender slips twice as multimodal risk slows bidder readiness 8KPCL’s coal-logistics tender for RTPS has already undergone two deadline extensions in less than three weeks. 8Bidders appear cautious about the rail–sea–rail exposure and unresolved liability boundaries. 8The drift signals deeper uncertainties in multimodal coal assurance architecture.Details
NEEPCO’s TATO-II tunnels face a 149-day drift as PQ tightening reshapes the bidder field 8NEEPCO’s flagship Tato-II excavation package slid nearly five months as bidders struggled to meet sharpened PQ metrics. 8Geological severity, shaft-diameter requirements and cavern experience thresholds forced multiple rounds of clarifications and corrections. 8Behind the drift lies a deeper shift in how the promoter is reallocating execution risk upstream. Grid-grade storage with VGF and stacked guarantees raises entry bar for 500 MWh node 8CSPDCL is turning a single 125 MW/500 MWh BESS at Khedamara into a test of how far risk can be pushed onto developers under a VGF-backed scheme. 8The RfS blends MoP’s national storage blueprint with a dense web of securities, performance obligations, localisation rules and fire-safety demands that resemble transmission-grade risk, not a renewable add-on. 8The real story lies in how many serious players clear the PQCs and what storage-charge number survives both e-RA and CSPDCL’s final acceptance filter.Details
NTPC’s CISF township tender pushes unprecedented EPC-level risk onto contractors — Talaipalli project 8NTPC’s new CISF infrastructure package at Talaipalli compresses civil, electrical, utilities and statutory-clearance risks into a single EPC throat. 8The documents reveal unusually tight tolerances, strict CPWD conformance, and unpriced liabilities that contractors must absorb. 8Behind the polished township façade lies one of NTPC’s most risk-loaded mining-infrastructure tenders to date. MPPTCL delays bid window in 600 MW evacuation tender without easing any technical or commercial terms 8MPPTCL has quietly extended the bid window for its 600 MW evacuation package, but not a single clause has been softened. 8The shift gives bidders breathing room without altering scope, PQ or compliance obligations. 8Why the employer moved only the dates—and nothing else—reveals more than it seems.Details