All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Nov 2026
RECPDCL ties full Nabinagar evacuation revenue to simultaneous commissioning
8The Bihar BOOT package for the Barun 400/220/132 kV GIS substation closes on 30 December, with Rs 250 crore net worth, a Rs 25 crore performance guarantee and COD on 30 November 2028.
8Progressive-versus-simultaneous commissioning wording, closing-account price adjustment, limited seller warranties and pre-closing claim restrictions keep revenue and acquisition risk with bidders.
TNPGCL's North Chennai FGD tender shows ten opening extensions and competing pre-bid dates
8The 3x210 MW semi-dry FGD EPC package, with a Rs 3.28 crore EMD and 24-month schedule, has moved its opening date 204 days, from 7 April to 28 October.
8A 3 December pre-bid date, references to "both units" and a desalination plant, conflicting lime-quality values and concurrent per-unit damages keep schedule and guarantee risk with bidders.
Tata Projects named for POWERGRID's ±800 kV Barmer-II–South Kalamb TL03 at Rs 690.23 crore
8The indicative award summary dated 2 November covers Part-III of the HVDC bipole line with a parallel metallic return, a 38-month completion period and seven firms listed.
8Missing L1–L3 prices, zero-value estimate fields and a lower-voltage experience gateway leave the award hard to benchmark, while exclusivity tied to POWERGRID's tariff bid kept commitment risk with contractors.
RVUNL extends Suratgarh O&M bids a ninth time with contract terms unchanged
8Corrigendum IX moves submission for the 2x660 MW supercritical plant's Rs 180 crore, three-year O&M tender to 25 November, 156 days after the original deadline.
8A 319 kcal/kWh heat-rate gap to benchmark, 10% payment retention, liabilities outside the LD cap and contradictory transition KPIs keep performance and cashflow risk with contractors.
BHEL tightens MoU terms on Mahi Banswara nuclear air handling tie-up after five extensions
8The pre-bid enquiry for AHUs, ACUs and FCUs across the 4x700 MWe units now closes on 12 November, 40 days after the first deadline, with a Rs 3 crore EMD and Class-I local supplier status.
8One-way indemnity, discretionary award wording, compulsory pass-through of negotiated price cuts and equipment choices deferred to engineering keep price and configuration risk with suppliers.
PFCCL sets 27 November deadline for Gadarwara–Mandsaur Part A and B after clarification window closes
8The corrigendum to the 25 September NIT gives both global BOOT schemes, covering 2x800 MW Gadarwara TPS-II and 1,500 MW of renewable power at Mandsaur PS, identical submission and opening dates.
A 15 October clarification cutoff 43 days before submission, no reopening mechanism and unchanged NIT terms keep late-query and interface risk with bidders.
BSPGCL cuts Kajra BESS commissioning to 12 months as bids move to 6 November
8Amendments to the 125 MW/500 MWh BOOT tender halve the financing period to six months, lower the success charge to Rs 3 crore and allow non-cash security.
8A zero-shading mandate, 85% renewable charging, developer-procured power and a kWh/MWh damages conflict keep execution and revenue risk with developers.
NTPC splits Sipat ash transport among six contractors at 20% below estimate
8The Rs 239.97 crore framework gives each contractor a Rs 39.995 crore ceiling at a matched 79.99% rate after 19 bids against a Rs 300 crore base.
8Low-rate security of up to about Rs 7 crore per contractor, no guaranteed orders and minus-100% variation keep volume and liquidity risk with the panel.
NTPC's Khargone ash tender conflicts on award split and bid validity
8The Rs 200 crore FY 2027–28 pond-ash rate contract targets AST-01 enlisted vendors with Rs 40 crore turnover and execution capability, covering destinations up to 300 km.
8GeM's no-splitting entry clashes with a five-bidder award, while no assured orders and payment tied to compacted-volume certification keep cashflow risk with contractors.
NTPC's Unchahar coal order to Mohit Minerals covers only half the tendered quantity
8The Rs 136 crore GeM contract buys 250,000 metric tonne at a landed Rs 5,440 per tonne, with nine bidders recorded against a 500,000-tonne requirement.
8The unexplained balance, 80/10/10 staged payment and steep deductions for low-GCV coal leave allocation unclear and keep quality and cashflow risk with the supplier.
Transrail reported as L1 at Rs 203.46 crore for POWERGRID's Tirunelveli–Udumalpet HTLS job
8The OH02 package covers about 130.56 km of 400 kV D/C reconductoring for 2,100 MVA over 18 months, with only one bid reported.
8Fixed-quantity buyback, work beside an energised circuit and a 12- or 36-month conductor warranty keep recovery and execution risk with the contractor.
Godavari's Rs 267.09 crore NTPC Telangana coal contract carries conflicting supply terms
8The 500,000-tonne order at Rs 5,341.80 per tonne follows 11 recorded bids, with two rejected technically and delivery running to 6 April 2027.
8GeM and bidding-document conflicts on rail delivery, GCV, moisture and 5% security, plus a Rs 21 lakh award-value gap, leave the operative terms needing reconciliation.
KSEBL opens price bids for Rs 106.64 crore Vengallur 220/110 kV GIS package
8Three bids reached techno-commercial evaluation for the 24-month TransGrid 2.0 EPC work after eight corrigenda, including three deadline extensions totalling 40 days.
8Rejected hybrid GIS experience, unresolved panel-count wording, transformer access concerns and discount-linked security keep qualification and interface risk with bidders.
NTPC ties Kudgi coal payments to station-end quality in 500,000-tonne tender
8The package sits within a 2.0 MMT, four-station procurement, requiring 3,550–4,000 Kcal/Kg coal by rail with a proposed 60:40 allocation between suppliers.
8GeM's no-ePBG entry conflicts with 5% security, while half-rate payment below minimum GCV and component-wise L1 matching keep margin and allocation risk with suppliers.
MPPGCL awards AKA Logistics coal liaison contract 5% above estimate after reverse auction
8The Rs 117.74 crore two-year order covers 200 lakh MT from SECL and WCL at Rs 49.89/MT, down 7.9% from AKA's opening offer.
8A 70% quality-linked fee, 20% combined security, landed-cost shortage recovery and a 42-day LOA date gap keep earnings and contract-administration risk with the contractor.
NPCIL awards BHEL Rs 95.58 crore MAPS-2 generator refurbishment on single tender
8The contract covers new stator winding materials, in-situ rewinding, rotor rehabilitation and commissioning, with site works due by 25 April 2029.
8A 180-day site clock inside a 910-day limit, separate defect-liability periods and no owner estimate leave schedule alignment and price reasonableness unresolved.
Showing 1–37 of 37 items
For daily newsletters and other free services, fill in your details: