All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Sep 2026

8Southern utilities repeatedly classified relay operations as correct when the regional load despatch centre called them failures or unwanted trips. The disagreement appears across a 31-event July table and matters beyond terminology: an incorrect label can hide the setting, communication or breaker problem that allowed an avoidable outage to spread. Details
8The northern grid absorbed 9,290 MW more average demand in July 2026 than a year earlier while renewable generation rose 37%, or about 73 MU a day. The paired movement is more useful than either number alone: demand growth was large, but the fastest supply change came from weather-dependent resources that also increased the region’s scheduling and evacuation burden. Details
8Bharat Petroleum’s proposed 9 MMTPA refinery and petrochemical complex in Andhra Pradesh has been held back after the appraisal committee found that its stated electricity requirement, the figure presented at the meeting and the grid approval did not agree. The discrepancy sits inside a Rs 1,03,408 crore project, turning what might look like a documentation error into a material clearance risk. Details
8Telangana’s monitored reservoirs entered September with 2,037.8 MU of equivalent hydro energy, almost double the 1,015.4 MU available a year earlier. The aggregate masks an even larger recovery at Nagarjuna Sagar, where live storage was nearly three and a half times last year’s level. Details
8European companies are recasting renewable power-purchase agreements as protection against electricity-price shocks, with current PPA prices around €60–85/MWh against stress-period spot prices of €120–150/MWh. Yet the apparent bargain has not accelerated every deal: some developers prefer the spot-price upside and lenders want commitments longer than buyers will sign. Details
8Two record-demand events produced radically different power-price outcomes in the United States: PJM’s real-time price approached $2,000/MWh during its July peak, while the Electric Reliability Council of Texas cleared its own record hour at $29.11/MWh. The comparison puts a measurable consumer consequence against the two markets’ very different renewable and battery build-outs. Details
8Sarda Energy & Minerals cut consolidated net debt from Rs 1,566 crore to Rs 215 crore as a full year from its 600 MW thermal acquisition lifted earnings. The same annual report shows debtor days rising by two-thirds, leaving a working-capital counterpoint to the power-led profit and deleveraging story. Details
8Adani New Industries’ manufacturing ecosystem has spent about Rs 4,850 crore of a Rs 9,481 crore expansion designed to take solar module and cell capacity to 10 GW. Revenue and the order book are growing, but profitability has already weakened and the export business remains exposed to US tariffs and trade remedies. Details
8BGR Energy Systems ended FY2025-26 with consolidated losses of Rs 1,291.72 crore and negative net worth of Rs 2,599 crore, almost twice the deficit a year earlier. Its annual report sets live nuclear and thermal contracts against a still-unresolved asset-reconstruction settlement and costs booked before customers have approved corresponding claims. Details
8A broken insulator on a 765 kV line near Jawaharpur caused about 972 MW of generation loss after a local earth fault also tripped four transformers and both generating units. The original fault was severe, but the wider outage came from delayed breaker opening and protection settings that the regional committee found sensitive enough to disconnect healthy equipment. Details
8Two 400/220 kV transformers at IndiGrid’s Sohna Road substation caught fire after a bus-charging fault remained uncleared for about 720 milliseconds, cutting roughly 396 MW of load. The incident did not end with the equipment failure: the regional operator also records delays in restoration and in obtaining status from the licensee for a substation supplying Gurugram. Details
8Rajasthan continued to inject surplus power into a high-frequency northern grid even while renewable plants were being backed down, according to the regional system operator. The imbalance reached about 4,000 MW on some occasions and persisted through five consecutive operating-committee reviews, turning a state portfolio problem into a wider grid-security concern. Details
8India could turn 151 coal units aged at least 35 years into the equivalent of a 24.2 GW flexible resource by 2030, a Central Electricity Authority panel has said. The proposal is presented as far cheaper than six-hour batteries, but the utilities asked to supply pilot plants have not done so and NTPC disputes the panel’s reading of equipment damage. Details
8Tata Power has asked for a 25-year licence to compete with Chhattisgarh’s incumbent distributor across Raipur and three adjoining tehsils, backing the bid with a five-year network plan that grows from two customers to nearly 14,000. The ambition is substantial, but the initial consumer base and proposed reliance on the incumbent’s wires expose the execution gap between a parallel licence and a functioning rival utility. Details
8Environment panel lines up 4.95 GW of thermal additions for one-day appraisal
8Coal panel’s September agenda spans 2-to-6 MTPA expansion and a 23 MTPA peak mine
8EESL signs 112 of 123 Andhra streetlight agreements for a 750,000-lamp programme
8Environment panel returns or defers four ethanol expansions over land, monitoring and hearing gaps
8ONGC wins one Ankleshwar drilling amendment as a larger 65-well change is returned
8Kodarma’s 100,000-tonne coal-tar plant gets an environmental recommendation Details
8Juniper’s two 200 MW FDRE projects carry a 44-paise tariff gap and common grid risk
8Juniper seeks 300 MW grid access before a PPA as IPO proceeds support its pipeline
8O2 solar ratings rise even as project leverage stays above six times EBITDA
8Repowering lifts a 40 MW solar group’s PLF, but leverage remains at 5.6 times
8Dans Energy’s 96 MW hydro plant improves output but remains inside a debt workout
8Greenergy’s ethanol revenue triples, but half its capacity still depends on fresh allocations
8SJVN completes Buxar Unit 2 trial, leaving commercial operation as the next gate
8Tata Renewables commissions 100 MW captive solar as 5.3 GW remains in the pipeline
8TARIL enters nuclear transformers with Kaiga 5 and 6 order, but discloses no value
8Indo Tech’s transformer award contains a Rs 1 crore disclosure mismatch
8AHAsolar wins consultancy for a 600 MW solar and 1,800 MWh storage project
8Coal India’s first renewable revenue arrives as its 9.5 GW target remains mostly unbuilt
8MSETCL extends IPO banker bids and sets a high experience bar
8AHAsolar’s revenue rises 59% and crosses from loss to profit
8Epic Energy grows revenue 14% while profit nearly halves and arbitration-backed revenue rises
8Tripura finds no eligible candidates for 24 reserved electrical-manager posts
8Meghalaya extends the Umiam spillway-bridge safety-audit tender to 11 September
8TGTRANSCO reserves a Rs 23.61 lakh Donthanpally fencing tender for SC contractors
8Bellary thermal station seeks Rs 36.54 lakh of water-treatment chemicals Details
8Northern renewable scheduling gap reaches 5.87 GW after a 5.1 GW May event
8Rajasthan renewable capacity runs ahead of its Phase III evacuation system
8Eastern electricity use grows 6.4% while peak demand rises only 0.3%
8IEX day-ahead price jumps 69% as bids rise and cleared volume falls
8PXIL clears barely a quarter of real-time demand at the Rs 10,000 ceiling
8Power-plant coal stocks fall 534,000 tonnes in two days while cover stays at 10 days
8India carries 51.9 GW of generation outage as evening shortage reaches 2.4 GW
8Southern generating outages reach 12,133 MW without a coal-shortage entry
8Kaiga-Guttur circuit returns three months after multiple towers collapsed
8Maharashtra shifts feasible farm feeders to an eight-hour daytime window
8GUVNL seeks 400 MW round-the-clock power at a Rs 10,000/MWh ceiling
8SECI opens pre-bid review for a short-term 50 MW/100 MWh storage contract
8Ajmer Discom reports 571,397 complaints and no compensation paid
8Western frequency response ranges from 0.21 to 1.00 across July generators
8IEX high-price day-ahead clears only 68.4 MWh at the Rs 20,000 ceiling
8India loses another 1.11 GW of available capacity in one day as gas use falls 4.8 points
8Northeast grid plan defers 29 September shutdown entries and says 31 need no outage
8Eastern grid weighs 10%-15% tariff penalties for spare transformers kept beyond three years
8NTPC’s solar data clock remains seven hours wrong after weekly notices since April
8Rajasthan’s weekly merit order spans Rs 1.54 to Rs 29.75 a unit
8Uttar Pradesh and Tamil Nadu lead September regional transmission bills
8West African mini-grids would need about 2.25 GWh of batteries by 2030 Details
8MNRE extends old rooftop-solar subsidy claims to 30 November but deletes uninstalled cases
8Rajasthan discoms say a 90-day GST-relief reconciliation is not practicable
8Andhra Pradesh adds 39.6 paise a unit for June power costs
8Jodhpur Discom sets June FPPAS at 4.42%, mostly absorbed by the standing surcharge
8CERC lowers NTPC’s availability norm to 83% for coal-hit years, subject to Supreme Court appeals
8CEA proposes “ramping blocks” after thermal plants face DSM charges while following dispatch
8CERC protects 270 MW at Kurnool after a loan letter missed the financial-close date
8Jalaun’s 1,200 MW solar park regains conditional connectivity after a 20-day finance delay
8Gujarat Ombudsman upholds Rs 24.35 lakh cable charge after a decade-long connection dispute
8Punjab removes the physical net-metering agreement for every rooftop-solar category
8Rajasthan orders the 12%-to-5% renewable GST benefit into tariffs and pending cases
8Bihar buyers challenge NTPC Mining’s Chatti-Bariatu coal-price case as CERC reserves its order
8CERC demands transaction-level proof for SEIL’s disputed Telangana invoice deductions
8Energyedge must obtain an independent audit before CERC considers a larger trading licence
8BESCOM’s July calculation points to a 23-paise-a-unit power-cost refund
8Kerala sets September fuel surcharge at two to three paise after a Rs 6.37 crore July variation
8Himachal regulator approves five small solar PPAs at Rs 3.45 a unit
8Himachal moves Salun hydro’s Rs 3.93 tariff start to the PPA date, rejecting a later claim
8Parliament panel calls the Power Ministry and BBMB for an “atmanirbhar” sector briefing
8Tamil Nadu Ombudsman cuts an electricity demand to Rs 8,656 but refuses compensation Details
SECI's Second Storage Rental Notice Repeats the Same 26-Day Mobilisation Squeeze
8SECI's near-identical 50 MW/100 MWh short-term storage tender pushes techno-commercial opening to 6 October 2026 while still demanding service commencement by 1 November — leaving less than four weeks to complete financial evaluation, e-reverse auction, LoA issuance, PBG verification and ESPA execution.
8Full Rs 6 crore PBG encashment for missing that start date remains the enforcement mechanism, with cross-reference errors scattered across Clauses 3.1, 13.9 and 15.3.

 

GSECL's Ukai ZLD Tender States Both 5% and 10% Performance Security in the Same Document
8GSECL's zero-liquid-discharge and water-reuse EPC package for Ukai TPS shows GeM's ePBG field at 5% for 47 months while the incorporated ATC separately demands a 10% security-cum-performance guarantee — a five-percentage-point gap that directly affects bank-limit planning from LOI onward.
8A 15-year capitalised power-consumption penalty stacked atop an incompletely described "zero liquid discharge" process (RO and UF are listed only as future improvements) leaves both the financial evaluation and the technical scope only partially defined.

GETCO's 1,507-Breaker Tender Extends 19 Days While the Portal Still Shows Old Dates
8GETCO's Rs 113.94 crore switchgear procurement — 95% concentrated in 66kV SF6 breakers — moved its technical opening from 9 to 28 September 2026 through Corrigendum 1, but the public portal continues displaying the original early-September schedule, creating a submission-control risk that bidders shouldn't dismiss as cosmetic.
8A five-times-manufacturing-capacity qualification test could effectively require certified annual output of 7,160 units from any bidder attempting the full 66kV lot alone.

 

BSPHCL's Bagasse Co-Gen Tender Cuts Its Term From 15 Years to 5 After Bidder Pushbac
8BSPHCL's 100 MW bagasse co-generation procurement slashed its contract tenure from 15 years to 5 and dropped the enforceable minimum PLF from 53% to 25% — corrections that acknowledge seasonal crushing realities — but then reversed a separate concession allowing multi-plant owners to submit project-wise bids, restoring the original single-application restriction without explanation.

 

BSPGCL's 150 MW Solar-Plus-Storage Tender Fixes a Doubled ESS Ratio That Nobody Caught
8BSPGCL's firm-and-dispatchable renewable procurement corrected its own PPA, which had originally required twice the battery capacity specified in the RfS — 1 MW/4 MWh instead of the intended 0.5 MW/2 MWh per MW of solar — while extending commissioning from 18 to 24 months and allowing the declared CUF to move downward for the first time, not just upward.

 

RVPN's Budhadeeth GSS Tender Discloses Coordinates But Withholds the Contour Sheet
8RVPN's Rs 50.55 crore turnkey substation package finally pinpointed its exact site location after bidder requests, but the promised contour and ground-level data needed to price foundations, drainage and earthwork remains deferred to "shortly" — leaving civil-cost estimation incomplete just weeks before an 18-month clock is set to start.
8A late-added, highly detailed capacitor-bank breaker specification arrived without any corresponding schedule relief.

 

UJVN's Chilla BESS Tender Raises Its Ceiling Tariff 3.8% But Won't Define When Batteries Get Dispatched
8UJVN's 90 MW/225 MWh storage project corrected its land location from the wrong district and lifted the capacity-charge ceiling to Rs 3,30,400/MW/month, yet still hasn't specified peak/off-peak windows, minimum dispatch notice, or whether scheduling will be day-ahead or real-time — leaving developers to size augmentation and degradation reserves against an undefined two-cycle-per-day operating profile on a site UJVN itself calls "tentative."

 

NTPC's Pudimadaka Green Hydrogen Water Plant Excludes O&M From Its Own Delay Penalty Cap
8NTPC's turnkey water-treatment package for NGEL's hydrogen hub quietly removed the five-year O&M contract value from the denominator used to calculate maximum delay-liquidated-damages exposure — reducing the theoretical LD ceiling — while separately introducing payment relief when NTPC's own delay blocks performance-guarantee testing for a full year.

 

Power Grid's 32-Item Tower Steel Award Shows a Tight L1-L2 Race and a Wide L3-L4 Split
8Power Grid's Rs 171.15 crore transmission-material award to Shilpa Steel separated from the second-place bidder by just 3.3%, but the gap widened to 19.2% by the fourth qualified bidder — a spread suggesting sharply different assumptions on steel, galvanising, prototype assembly and the 730-day execution commitment behind seemingly comparable headline totals.

 

NTPC's Rihand Transformer Tender Says "No Civil Work" While Its Own Spec Says Otherwise
8NTPC's replacement-transformer package for two 400 kV units flatly told a bidder "No Civil work is in scope of vendor," yet the underlying technical specification still assigns transformer and cooler-bank foundations to the supplier — a contradiction NTPC never formally repaired, leaving brownfield interface responsibility genuinely unclear before bid submission.

 

WBSETCL's Rs 339 Crore Transmission Award Shows an Unexplained Rs 4.60 Crore Price Drop
8WBSETCL's composite eight-project EPC award to Kalpataru Projects beat KEC by just 4.9% and Larsen & Toubro by 24.0%, but the winning bidder's evaluated price fell Rs 4.60 crore below its own comparative BOQ total for reasons the disclosed documents never reconcile — while a portal contract date two years after the actual letter of award adds a separate chronology puzzle.

 

WBSETCL's Transformer Auction Ends in a Rs 1 Lakh Photo-Finish, Then Adds 90 Days to Delivery
8WBSETCL's four-transformer procurement saw its reverse auction compress the top two bids to within Rs 1 lakh of each other on a Rs 33+ crore contract, yet the eventual purchase order quietly extended final delivery by 90 days beyond what the original tender demanded — a post-auction concession that shifts the traded value from pure price competition toward negotiated schedule relief.

 

NHPC's Haryana Rooftop Solar Tender Protects Good Bids From Bad Neighbors
8NHPC's 30.93 MWac government-rooftop RESCO tender inserted a new clause preventing a bidder's failure in one district or category from automatically disqualifying its otherwise-compliant bids elsewhere — a fix that kept nine of eleven original bidders in play for the eventual district-wise reverse auctions.

 

NTPC's Darlipali Ash Rate Contract Shows a Documented Award 54.5% Below Its Own Estimate
8NTPC's ash-to-road-construction logistics tender priced six equal Rs 22.75 crore contracts totaling Rs 136.50 crore against an original Rs 300 crore estimate — but with quantity deviation permitted down to zero and no guaranteed purchase orders, that headline gap may reflect discretionary allocation as much as aggressive pricing.

 

REC's YEIDA Transmission Tender Makes the Contractor Indemnify Risks It Never Created
8REC Power Development's Sector-28 YEIDA substation RFP requires the winning bidder to indemnify the seller against all past, present and future third-party claims tied to pre-closing project decisions — while the acquisition price for the project SPV remains blank until just 20 days before bid closure, and a stray reference sends the performance guarantee to CTUIL despite this being a purely intra-state UPPTCL project.

 

REC's Alkud-II Transmission RFP Finally Names Its Own Project Company
8A one-line amendment to REC's 765/400/220 kV Sangli transmission tender replaces every placeholder reference to "[Insert SPV name]" with "Alkud II Power Transmission Limited" — a housekeeping fix touching the RFP, TSA and SPA simultaneously, though the acquisition price, MERC-pending reverse-auction parameters and the project's all-or-nothing 24-month commissioning dependency remain unresolved.

Details
 For reference purposes the website carries here the following tenders:
 8Design, engineering, supply, erection, commissioning and testing of 2 nos 140 ton capacity pit less type in motion electronic rail weigh bridge Details
 8Tender for supply of MS grill and fabrication & epoxy paint of stairs, railing, structure Details
 8Tender for carrying out routine maintenance works of lighting in power house Details
 8Tender for works contract for heightening the pillar boxes Details
 8Tender for supply of tarpaulin sheet for covering of coal Details
 8Tender for work of servicing & repairing of window AC, split AC and water coolers Details
 8Tender for rate contract for removing, lifting, shifting, dismantling, servicing and overhauling of 2.3 kV /6.6 kV / 11 kV HT motors Details
 8Tender for construction of civil work for 02 No 132 kV bay Details
 8Tender for civil works related to construction of 1 No 33 kV bay Details
 8Tender for execution of bypass and restoration arrangements of 33 kV /22 kV /11 kV LT lines Details
 8Tender for procurement of spares for rotary feeder Details
 8Tender for construction of 11kV covered conductor line using PSC poles Details
 8Tender for re-babitting of thurst bearings pads of 40MW turbine Details
 8Tender for supply, erection, testing and commissioning of high light mast Details
 8Tender for reconstruction of the damaged geo green soil stabilization structure Details
 8Tender for supply, installation, testing and commissioning of energy meter Details
 8Tender for work of preventive maintenance of various 220 kV switchyard Details
 8Tender for carrying out maintenance works and all types of cable related works Details
 8Tender for supply, erection and commissioning of insertion type ultrasonic water flow meters Details
 8Tender for work of inspection, repairing / overhauling of existing piping hangers Details
 8Tender for work of attending leaky tubes, joint replacement and tube nest replacement Details
 8Tender for carrying out routine maintenance works for maintenance of uninterrupted power supply Details
 8Tender for construction using HT ABC Details
 8Tender for construction of 110 kV substation Details
 8Tender for routine maintenance and breakdown works of HT and LT motors and their related Details
 8Tender for biennial rate contract for civil maintenance of entrance cabin and loading point Details
 8Tender for supply, erection and commissioning of lighting poles Details
 8Tender for extension of 220kV substation Details
 8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details
 8Tender for regarding work of shifting of 11 kV feeder Details
 8Tender for ARC for erection of HT / LT / TC and maintenance work Details
 8Tender for procurement of LT three phase angle cross arm Details
 8Tender for carrying out routine maintenance works of HT/LT switchgear in RWPH 5 MVA power transformer Details
 8Tender for routine maintenance and breakdown works of HT motors LT motors Details
 8Tender for routine breakdown maintenance works of 230 kV grid bus yard power transformers Details
 8Tender for works contract for the routine maintenance of MRT equipments Details
 8Tender for carrying out maintenance activities of C&I equipments in unit Details
 8Tender for construction of damaged and U fencing to prevent encroachment at 220kV s/s Butari Details
 8Tender for construction of damaged and U fencing to prevent encroachment at 220kV s/s Details
 8Tender for outsourcing work of erection, testing and commissioning of 01 no new 66 kV substation Details
 8Tender for supply of LT XLPE insulated aerial bunched cables Details
 8Tender for supply of hot end and hot intermediate end baskets embedded with heating elements for air pre heater Details
 8Tender for requirement of leak off control valve with pneumatic actuator for turbine gland seal steam system Details
 8Tender for supply of cast basalt pipe fitting and pipes of various sizes Details
 8Tender for supply of different types of GTC sleeves for various pumps, clinker grinders Details
 8Tender for supply of 245kV current transformer (CT) Details
 8Tender for work of providing protection structure by erection of girder pole & tower angle to transmission tower’s Details
 8Tender for construction of electricity test lab Details
 8Tender for special maintenance and repair works of electricity sub-station Details
 8Tender for construction of store and other miscellaneous civil works at 33/11 kV substation Details
 8Tender for construction of 03 Nos store and other miscellaneous civil works at 33/11 kV substation Details
 8Tender for life enhancement works E and F Details
 8Tender for biennial maintenance contract for conservancy work Details
 8Tender for renovation of BAT supporting structures Details
 8Tender for biennial rate contract for repairing and servicing of ESP rapping system gear box Details
 8Tender for Supply, civil, erection, testing & commissioning for implementation of rapid restoration system for 3x105MVA, 400/220/33kV ICT II Details
 8Design, engineering, supply, erection, testing & commissioning of HVWS system for 4 nos. new SFC transformer Details
 8Tender for supply of ceramic blanket for 1X500 MW boiler unit Details
 8Tender for work of dismantling replacement / repairing of PF pipe, orifice & PF bend of coal mills Details
 8Tender for deputation of service engineer for quarterly servicing, maintenance & trouble shooting of PLC system & VFD drives of various auxiliaries Details
 8Tender for work of complete o/h of MS&HRH strainers, HP&IP stop and control valves Details
 8Tender for supply of submersible pump motor set capacity Details
 8Tender for supply and installation of an energy efficient lubricated rotary screw air compressor Details
 8Tender for work of supply and application of anti-corrosive paint on external surfaces of various structures, pipe lines & auxiliaries Details
 8Tender for services for carpentry, masonry, and plumbing works etc. and operation of drinking water supply system Details
 8Tender for supply of various spare of beater wheel Details
 8Tender for miscellaneous fabrication and steel work in various Details
 8Design, supply, installation, commissioning and maintenance of solar PV system for 5 years as a rooftop Keshod Details
 8Design, supply, installation, commissioning and maintenance of solar PV system for 5 years as a rooftop Kodinar Details
 8Design, supply, installation, commissioning and maintenance of solar PV system for 5 years as a rooftop Details
 8Design, supply, installation, commissioning and maintenance of solar PV system Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Coal India accepts resignation of ED Raja Sekhar Kinnera Details
 
8Coal India prepares to list MCL, SECL after board approval: B Sairam Details
 
8Power reforms need an urgent push Details
 
8Bangladesh wants Nepal’s power, but India holds the key Details
 
8Renewables Deliver Record One-Fifth of India’s Power in July Details
 
8What Are DISCOMs, India Power Distribution And Smart Meters Explained Details
 
8Haryana to oppose private parallel power distribution licence in Gurgaon, Nuh: Power Minister Details
 
8Transformer Maker Enters Nuclear Segment With Kaiga Project Order Details
 
8Sealmatic Eyes Growth from India’s Expanding Nuclear Sector Details
 
82 Green Energy Stocks With High Promoter Holding Details
 
8KMCC Infra Secures INR 244 Crore BSPTCL Order for 205 RKM Transmission Infrastructure in Bihar Details
 
8Motilal Oswal bets on Data centres, defence & transmission: Top 6 capital goods picks for FY27 Details
 
8How hydropower decline is reinforcing coal’s role as India’s flexible power source Details
 
8SJVN Completes 72-Hour Trial Run of 660 MW Buxar Unit-2; Commercial Operation Set to Begin Details
 
8India adds 6.6 GW of rooftop solar in H1 Details
 
8From solar to chips: Powering India's manufacturing rise Details
 
8Ceigall India commissions first 5 MW solar project under MSKVY 2.0 Details
 
8Tata Power Commissions 100 MW Group Captive Solar Project Details
 
8Waaree Renewable Technologies Wins 291 MWp Solar-BESS Project Details
 
8Global Solar PV Installations Forecast to Hit 638 GW by 2026 Details
 
8ONGC to invest Rs 1 lakh crore in deepwater exploration over next 5 years, reports 3 new discoveries Details
 
8India Solar Manufacturing: Module Glut and DCR Cell Shortages Details
 
8Solar-Plus-Storage Investments Hit $25 Billion in H1 2026 Details
 
8Westbridge Sells 225 MW Alberta Solar and Storage Project Details
 
8Fujiyama Power Adds 1 GWh Lithium Battery Capacity in Ratlam Details
 
You can also click on Newsclips for more Details

Showing 1–20 of 20 items