All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Sep 2026
NTPC Renewable's 600 MW Anantapur wind tender gives bidders a week more to price but no way to ask why
8Corrigendum No. 1 pushed submission to 22 September 2026 while leaving the 1 September query deadline untouched, so late-discovered ambiguity has nowhere formal to go.
8With Rs 50 crore bid security, ten-year comprehensive O&M and roads, pooling and evacuation all outside the WTG package, the unresolved issue is who carries commissioning delay at the boundary.
JdVVNL rewrites the BOQ a third time and swaps Bikaner territories between two RDSS packages
8Corrigendum 3 moved Dungargarh and Nokha into TNTW-796 while DD-I, DD-II and Khajuwala travelled the other way, settling the value at Rs 119.89 crore — a net movement of about 0.1%.
8That small headline change can conceal much larger line-item additions and deletions, which is precisely what bidders repeatedly queried before the revision.
AEGCL's Khumtai 400kV GIS tender carries a Rs 50 lakh EMD contradiction and a 12-month schedule gap
8The invitation and ITB 2.37.1 set two years for completion while SCC 8.2 requires 36 months, and the EMD reads Rs 5.5 crore in numerals against "Rupees Five Crore only" in words.
8Turnover and financial-resource thresholds carry the same numeral-versus-wording conflict, making eligibility itself uncertain before the 12 October closing.
GETCO's Viksit Gujarat @2047 adviser tender records two turnover thresholds twenty times apart
8The GeM page states Rs 48 crore while the RFP and buyer-added conditions demand Rs 1,000 crore, and submission and opening dates differ by a day between portal and document.
8With GST treatment also contradicted between two clauses, the tender risks producing technically incomparable bids priced on different assumptions.
GETCO's Rs 210.62 crore Bharuch cable package lets each approved OEM back only one bid
8Amendment-I restructured qualification into OEM, nominated-OEM and two-member JV routes, then barred any firm from appearing in different roles across competing bids.
8The contest may therefore be settled by early OEM alignment rather than by how many erection contractors can qualify.
KPTCL's Rs 131.92 crore Byadagi package reaches the market tagged as a computer lab
8The portal lists bid validity as 90 days against the signed document's 180, describes the scope as "Setting up of Computer Lab", and keeps the clarification window open 30 minutes after bids close.
8A Clause 3.2(e) heading referring to a 100 MVA transformer against a 160 MVA requirement compounds the risk of divergent qualification readings.
RRVUN cuts the coal experience bar by 6.25% and then quietly extends group credentials to technical qualification
8Amendment-I lowered the single-contract threshold from 1 million MT to 9,37,500 MT and admitted IPP supplies; Corrigendum-I then widened 100%-owned parent or subsidiary reliance from financial to both technical and financial PQR.
8JV and consortium participation stays barred, so the widening favours tightly held corporate groups rather than assembled bidding alliances.
WBSETCL's Sadarghat composite package republishes its evaluation clause with a broken cross-reference
8Amended ITB 28.2 now reads "DP = Differential price calculated according to0", severing the link to the calculation method in ITB 28.4, while the reverse-auction cross-reference disappears entirely.
8Reverse-auction clause 9 separately dispenses with additional security where L1 is "less than 20% of the estimated cost" — a literal reading that relaxes protection at the lowest prices.
NHPC raises generator efficiency loading 20.6% on the Rs 641.11 crore Uri-I Stage-II package
8The turbine equalisation rate moved from Rs 8.32 lakh to Rs 8.74 lakh per 0.1 percentage point, while the generator rate jumped from Rs 21.64 lakh to Rs 26.10 lakh.
8Cheaper machines with weaker guarantees can now lose their price advantage at evaluation, even before PLCC relocation and revised cooling-water scope are priced.
WBSETCL's 68 km Salboni 400 kV line tender resolves a 60 mm creepage conflict but keeps ROW with the contractor
8The pre-bid response directed bidders to the technical specification's 430 mm over the BOQ's 370 mm and issued a revised BOQ, while fixing conductor diameter at 28.62 mm and sag at 15.93 m.
8Tower-footing compensation, trees, crops and access remain contractor-priced with no escalation for court-driven delay, and the 24-month clock survives two extensions.
RRECL's 201 MW solar tender slips 63 days and then adds a letter of credit
8Four corrigenda moved submission from 14 July to 15 September 2026 while the nine-month commissioning obligation and 25-year term stayed fixed.
8The pre-bid addendum inserted a revolving monthly LC and replaced the client's first charge over liquidated assets with priority application of proceeds — a lender accommodation whose value depends on the still-ambiguous "Cover-1 & Cover-2" opening language.
HPSEBL extends its Rs 3.72 crore Kinnaur-Spiti PMC tender for the fifth time without explaining why
8Corrigenda I to V added 64 calendar days to both submission and technical opening while leaving scope, staffing, securities and the 246 man-month deployment untouched.
8The unresolved question is award mechanics: a 70:30 QCBS formula and an English e-reverse auction sit in the same document with no stated hierarchy.
GETCO shifts LD on the Rs 224.80 crore Dholera-II GIS package from the delayed portion to the whole contract
8SCC clause 41 now calculates 0.5% per week on the full contract price capped at 10%, recoverable across GUVNL group contracts, while requests to extend 30 months to 34 and to substitute PEB for RCC were refused.
8A local civil or commissioning slip can now generate package-wide exposure on a site carrying saline conditions, seismic zone 5 and cast-in-situ piling.
MePDCL splits Khasi Hills into six lots and hands four of them to one contractor
8The Rs 120.42 crore award concentrates Rs 82.12 crore, or 68.2% of L1 value, with a single firm across Lots 1, 3, 5 and 6.
8Lot 3 reached financial opening with one responsive bidder out of seven, leaving no L2 comparator to test whether that price was competitive at all.
NHPC rewrites force majeure and idling-cost recovery across both its hydro E&M packages
8The revised GCC Clause 37 adds terrorism, qualifying strikes and pandemic spread while removing the magnitude-7 earthquake threshold and express treatment of bandhs, lightning and unprecedented floods.
8Annex-A now caps compensable idling through a formula using 5% of composite contract price, with a 2% sub-cap on miscellaneous establishment expenditure and extended-warranty recovery at 2.25% per annum.
RVUN's Rs 1,125 crore coal tender is tagged emergency procurement without naming which rule applies
8The portal cites Rule 40(1), 43(6) or 43(7) but does not identify the provision invoked or the factual justification, and the original window ran just seven days from publication to submission.
8Coal grade, sampling agency, delivery duration, LD framework and PBG terms are absent from the published notice, leaving the commercial risk difficult to quantify before bidding.
WBSETCL's H1-elimination auction meets a 10% security stack that runs five years past commissioning
8The Sadarghat package removes the highest offer only where four valid price bids exist, so two or three qualified bidders all proceed to the auction intact.
8The winner must then carry separate 10% guarantees on GIS equipment for three years and transformers for five from the Taking-Over Certificate, with formal joint ventures barred.
APEPDCL grants 24 extra days on its Rs 143.32 crore SCADA package without touching a single execution obligation
8Three corrigenda moved submission from 1 September to 25 September 2026, but the 18-month implementation period, five-year FMS and 10% performance security stayed exactly where they were.
8What the extensions really concede is preparation time for a bidder pool that must satisfy two separate qualification streams and assemble OEM authorisations before it can quote.
RVPN's Rs 83.38 crore Shiv Enclave GIS package makes unlisted work the contractor's problem
8A 132/33 kV, 2x80 MVA GIS substation with a 4 km LILO cable arrangement carries a 545-day execution period and a 10% performance security, extended eight days by Corrigendum No. 01.
8The clause that matters is GCC 3.2, which absorbs reasonably inferable items into the contractor's scope without automatic additional payment.
NTPC puts 2,184 man-months of construction safety at Telangana Stage-II behind a 52-month firm-rate contract
8The consultant must field 47 personnel, run a 24/7 IP-camera control room and approve other agencies' JSA/HIRA documents across a 3 x 800 MW build.
8The commercial risk is not the Rs 5,000-per-day non-deployment penalty but firm rates through a unilateral 12-month extension, 5% retention and no interest on deferred payment.
TNPDCL asks for 5,000 distribution transformers while the protected BOQ shows a quantity of one
8The M-256 tender covers 5,000 units of 100 kVA, EEL-2 aluminium-wound transformers with a Rs 1,00,20,500 EMD, a ±25% quantity variation and a 60-month guarantee.
8The BOQ's "1.0 No." line and its residual civil-work text sit inside a spreadsheet bidders are forbidden to alter, converting a template artefact into a responsiveness risk.
JdVVNL's Rs 119.89 crore Bikaner package carries two completion periods inside the same document
8The NIT records eight months for supply, erection, testing and commissioning while Appendix 4 records nine, both against an unchanged nine-month total, with the portal and NIT also differing on the 22 September opening time.
8Performance security is quoted at both 180 days and 30 days beyond the defect-liability period, and guarantee charges turn on which one controls.
Bidder queries force JdVVNL to reopen the BOQ on its Rs 91.47 crore Bikaner DD package before bids close
8Corrigendum-3 supersedes the 14 August NIT, revising the BOQ, specifications, estimate and EMD to Rs 1.83 crore without publishing the superseded figures for comparison.
8The sharper problem is composition: JdVVNL's own estimate puts supply at 79.6% of value while ITB 37 treats supply above 70% of the quoted price as front-loaded and demands additional security.
Phalodi package climbs 0.7% across two corrigenda, with the entire increase landing in supply
8Between Corrigendum-I and Corrigendum-3, supply rose by Rs 38.89 lakh while erection fell by Rs 1.21 lakh, taking TNTW-792 to Rs 97,59,20,302.39 and EMD to Rs 1,95,18,407.
8No item-level change register accompanies the revision, and the portal and SBD still disagree on whether technical bids open at 11:00 am or 5:00 pm.
Jaisalmer's Rs 121.13 crore RDSS package stacks four separate security layers on one contractor
8Beyond the 10% performance security sit abnormal-bid security, supply-unbalancing security and a further 10% guarantee on major equipment running to 36 months after completion.
8With 77.4% of the estimate in supply and no pre-bid meeting scheduled, bidders must also decide whether the EMD instrument reads Rs 2,42,25,139 or Rs 2,42,25,140.
JVVNL withdraws the vendor-registration security waiver as it tenders 25,000 CSP transformers
8Appendix-A replaces EMD and SBG references with Bid Security and removes the relaxation that JVVNL registration alone previously conferred, on a Rs 16,025 lakh, 16 kVA programme.
8The allocation formula caps L1 at 20% and spreads half the quantity across other firms, making past repair performance an eligibility filter rather than a reference note.
Navkar Global Infra takes NTPC Mouda ash transport at 47.6% of base rates against 23 other accepted bidders
8The accepted percentage produces a Rs 142.80 crore contract value, a 52.4% discount to the Rs 300 crore estimate and far past NTPC's own 10% abnormally-low threshold.
8Section C nonetheless caps each shortlisted bidder at Rs 50 crore cumulative and guarantees no purchase order at all, separating the headline award from bankable work.
Churu package falls Rs 7.45 crore in Corrigendum-3 after rising in Corrigendum-1 TNTW-798 moved from Rs 132.60 crore to Rs 133.13 crore and then down to Rs 125.67 crore, with supply cut 6.5% against erection's 2.0%, and no clause-level reconciliation published.
8Bidders have ten calendar days from republication to reprice, while the portal and corrigendum differ by Rs 60 on an EMD that decides envelope-one compliance.
UJVN Limited raises its BESS tariff ceiling 3.8% but leaves 165 MWh outside VGF support
8The 90 MW/225 MWh Chilla project draws VGF on only 60 MWh, while the ceiling capacity charge moves to Rs 3,30,400/MW/month against the Rs 3,96,747 bidders sought.
8After 12 years the entire asset transfers to UJVN Limited without consideration, so residual value has to be recovered inside a capped tariff stream.
UJVNL puts 3x40 MW Sirkari Bhyol Rupsiabagar electro-mechanical works out at Rs 158.53 crore on a one-page notice
8The turnkey EPC package covers design through commissioning, but the notice carries no equipment configuration, battery limits, completion period, LD regime or security structure, while two corrigenda sit on the portal without disclosed content.
8A 47-day window with only 27 days after the pre-bid meeting leaves bidders pricing "other associated different works" without a responsibility matrix.
NTPC Barauni ash package caps compressor power at 1,050 kW with Rs 1.81 lakh payable for every excess kilowatt
8The dry fly ash augmentation contract carries Rs 6.09 lakh daily delay LD, a 12% performance-LD ceiling and a seven-day continuous trial, while amendments deleted the original scheme and layout drawings and pushed construction power onto the bidder.
8Geotechnical data arrived only through Annexure P after bidders had already priced foundations.
MSEDCL asks for 3,599 SCADA-ready RMUs while its own documents disagree on whether the breaker is 200 A or 400 A
8Section III specifies a 400 A vacuum circuit breaker with 400-200/1 CTs; the embedded 11 kV specification repeatedly says 200 A, a divergence that reaches type-test validity, protection coordination and price comparability across a Rs 387.52 crore package.
8The bid notice and portal also differ by 30 minutes on both submission and opening.
WBSETCL Package C3 lets bidders choose between lead and corrugated aluminium sheath on the same 220 KV cable
8Rather than amending the conflicting specification, the utility resolved KEC International's pre-bid query by transferring sheath selection to bidders while fixing the metallic-sheath fault level at 40 KA for one second.
8A revised BOQ landed on 6 May against an 11 May deadline, with residual formula errors left correctable during price evaluation.
NRPC's Rs 25,000 audit tender cannot decide whether it is a single-packet or two-packet bid
8The GeM configuration prescribes two packets and marks arbitration "No", while ATC Clause 1.1.1 mandates a single-packet process and Clause 4.5.2 installs an arbitrator appointed by NRPC's own Member Secretary.
8Force majeure thresholds inside the same document sit at three months and two months.
SECI ties 700 MW of solar to SEZ/EOU status and tells developers that losing it is neither Change in Law nor Force Majeure
8Clause 20.11 makes de-bonding, cancellation or suspension the developer's sole risk across a 25-year PPA whose ALMM exemption depends on that very status, with the Odisha C&I off-taker unnamed.
8SECI can still annul the process after tariff discovery if no buyer emerges.
RVUN seeks 12.5 lakh MT of coal in seven days, bars JVs and demands a single 1-million-MT contract record
8The Rs 1,125 crore Suratgarh tender requires turnover equal to the full estimate, net worth above Rs 375 crore and rail-loading access, while prohibiting consortiums that would normally combine coal, rail and balance-sheet strength.
8The portal flags it as emergency procurement without naming the rule invoked.
DHBVN admits five bidders on Palwal RDSS package 58 days after the scheduled technical opening
8Agarwal Electrical, Agarwal Traders, Century Infrapower, Laser Power & Infra and RP Infrapower cleared the fee, prequalification and technical stage on 3 September against a 7 July opening date.
8The Rs 133.62 crore turnkey scope still depends on feeder-wise BOQs to be surveyed and approved after award.
UJVNL extends Kulhal RMU bidding five times, moving the deadline 68 days without touching the 52-month schedule
8The Rs 110.57 crore turnkey package makes the contractor reconstruct the engineering baseline of a 1975 plant through reverse engineering, 3D scanning, CFD, FEA and residual-life assessment at its own risk.
8Manufacturer-backed qualification attracts 15% performance security instead of 10%, plus another 5% against the authorised scope.
JUSNL cuts consultancy turnover threshold by 22.9% after tendering against the wrong estimate
8The corrigendum reduces minimum average annual turnover from Rs 17.32 crore to Rs 13.35 crore and relevant-business revenue from Rs 4.33 crore to Rs 3.34 crore, correcting a base that mixed an excluding-GST figure with an including-GST estimate.
8The liquid-resource requirement and the conflicting bid-start and opening timestamps remain untouched.
NTPC prepays CSIR-SERC in full for Farakka structural assessment with no bank guarantee, LD or defect liability
8The single-tender consultancy waives EMD, security deposit, PBG, qualifying requirements and evaluation while NTPC additionally funds travel, boarding, local transport and PPE for the visiting scientists.
8Three extension instruments in the archive state neither the original nor the revised dates.
NHPC trims derived-rate overhead from 20% to 18.63% on Rs 267.94 crore Salal bypass tunnel
8Corrigendum 1 rewrote the insurance clause so NHPC funds the works policy while the contractor handles claims, deductibles and reinstatement, with up to 5% withholdable from running-account bills for incomplete claim information.
8Disclosed geology includes solution cavities, squeezing ground, rock burst, hot water and ingress above 6,000 litres per minute.
GSECL asks one consultant to write the Dharoi PSP contracts and then police them for 68 months
8The Rs 2.10 crore EMD, 75-mark technical threshold, 200 MW hydro reference and JV prohibition narrow the field before methodology scoring begins, while a "Stop Gap" clause lets
GSECL exclude declared periods from the completion count.
8The tender never states the project's installed capacity.
RRVPN rejects every pre-bid attempt to widen the field on Rs 125.98 crore Sawai Madhopur substation
8Requests to count bay-extension work, cut the four-substation threshold to two and drop bidder-level transformer experience were all answered with instructions to follow the existing PQR.
8Bids more than 15% below estimate attract additional security equal to half the unbalanced amount.
Only BHEL and LC Infra clear technical opening on UJVNL's Rs 1,024.45 crore Lakhwar EPC
8Both bids were admitted on 5 September after a single seven-day extension, leaving no redundancy if detailed evaluation eliminates either offer.
8Turnover thresholds rise from Rs 308 crore to Rs 820 crore for manufacturer-backed bidders, who also face 15% performance security and a lock on the named turbine and generator OEM.
WAPCOS excludes arbitration from its own Rs 1.50 crore transformation mandate while listing the Arbitration Act as applicable law
8Claims must pass an internal EIC or GM (HR) decision, a Departmental Review Committee and mediation before reaching the Delhi courts, with early filing treated as material breach.
8A corrigendum chain moved the pre-bid meeting from "not held" to an online session, then pointed to both August and September.
MAHAGENCO's Koradi skirt-board tender carries two qualification frameworks and two different carbides
8Turnover is required at both 30% and 100% of estimated cost, while experience is tested through a seven-year 40/50/80 formula in one schedule and a three-year plus 25%-order test in another.
8The subject line and panel description say tungsten carbide; the service-item text says modular silicon carbide.
UPPTCL taxes aggressive bidding on the Rs 102 crore Prayagraj GIS package with a sliding security ladder
8Every percentage point below benchmark adds performance security, rising to 1.00% per point beyond a 10% discount.
8Routine arbitration is deleted too, so undercutting costs cash and disputes run through internal committees.
8With no combined cap and no transformer delivery schedule, the question is how narrow the field gets by September 24.
TGTRANSCO's Sadashivpet–NIMZ line package carries a 22-RTU obligation the price schedule never mentions
8Clause 5.26.1 calls for 22 RTUs while the priced schedules cover just two SAS units for the NIMZ bays.
8A deemed-completeness clause and a one-way lump-sum correction rule push that gap onto the contractor.
8Whether a corrigendum lands before September 24 decides if it stays drafting noise or becomes scope.
MSEDCL's Rs 179 crore 22 kV cable tender pairs firm prices with a 100% extension option
8Prices for 7,34,000 metres stay firm with no commodity variation, yet MSEDCL can order the same quantity again on unchanged terms.
8Type-test validity is stated as both ten years and five, and IS 7098 appears in both its 1985 and 2011 editions.
8Even after the September 1 opening, the 50% cap on an out-of-state L1 means the lowest price will not settle the order book.
MSEDCL's Rs 98 crore 11 kV and 33 kV cable tender loosens drum lengths but keeps every commercial lever
8Clause 9.02 now allows 500 or 250 metre drums, but MSEDCL can still demand 250 metres wherever it chooses.
8The same type-test and IS 7098 conflicts recur, alongside a payment clock that starts only when a full monthly lot arrives.
8The open question is how many bidders sized their 20% minimum offer to real extrusion capacity.
GETCO rewrites the Tharad STATCOM engineering bargain across four extensions without touching the 24-month clock
8The Rs 244.54 crore package moved 80 days to September 17 while shifting to a 50°C rating and a 1.5% loss ceiling.
8In exchange, bidders take on oscillation proof, HVDC interaction studies and five years of post-guarantee interference liability.
8The reverse auction will show whether easier equipment thresholds get priced harder than open-ended network risk.
NHPC trims derived-rate margins and rewrites insurance on the Rs 268 crore Salal sediment bypass tunnel
8The contractor still funds reinstatement and faces 5% bill withholding if claim paperwork lags.
8Two extensions added 88 days to bidding but nothing to the 29-month execution period.
DVC holds the 12-month clock on Chandrapura's Rs 90 crore line diversion after four extensions and a late arrester spec
8Submission moved 42 days to September 14, with the lightning-arrester specification added only 11 days before that.
8Underground cable is half the estimate, yet the named cable contractor cannot be replaced after award.
8The issue is whether bidders load the uniform percentage or walk away from a schedule they called unworkable.
BHEL's Darlipali ash handling tender adds 50% more slurry pumps and a fixed hydraulic baseline while the 4,600 kW cap stays put
8Corrigendum 05 fixed wash-water and sludge duties and raised bottom-ash disposal pumps from six to nine.
8Four extensions took bids to September 10, but the 34-month schedule and US$5,245-per-kW damages never moved.
8The reverse auction will reveal whether cautious bidders lose to those assuming detailed engineering absorbs the gaps.
BHEL's Darlipali ash handling tender dates its experience cut-off nine months before its own NIT
8Annexure 1 reckons experience "as on 06/11/2025" against an NIT dated July 29, 2026.
8Milestone withholding, 5% delay LD and 12% performance LD stack on one counterparty with no interest on withheld sums.
8Whether the three qualification routes widen the field enough for a meaningful auction is the thing to watch.
NPCIL bolts a 15% import loading onto the Kudankulam 5 and 6 common services package after eight extensions
8Corrigendum-XII inserted high-seas-sale transfer, customs procedures and a 15% CIF loading 177 days after the original deadline.
8Corrigendum-XI separately enlarged chiller envelopes to 32 MT, reaching into foundations on a 1,278-day schedule.
8With BHEL, L&T, NCC and Tata Projects in the query record, the question is whether the loading reorders a small field rather than widening it.
BHEL's Korba West coal handling tender puts 75% of the price on land it does not expect until May 2027
8One lump sum splits 25:75 between internal and external CHP, with no compensation if the external land arrives late.
8Reverse auction was deleted a day after the NIT, but cross-default across every LOA leaves no contractual ring-fence.
8After five extensions to September 10, the open issue is how much contingency lands in Package B.
SECL's Gevra weighbridge consultancy asks five CPSUs to price 2,520 days against a portal that shows five years
8GeM displays five years, but the corrigenda fix 2,520 days of exposure backed by an 86-month ePBG.
8The PMC also runs a 20% imprest and pays contractors, with 45% of its Stage III fee tied to that role.
8With five invitees and no floor price, the question is whether the lowest percentage survives seven years.
NTPC's Rs 200 crore Kahalgaon pond ash contract offers five contractors a panel seat and none of them guaranteed work
8GeM says no bid splitting, but the ATC splits the contract five ways, caps each at Rs 40 crore and allows minus 100% quantity.
8Payment follows the lowest of three measurements before 5% reconciliation and 2% safety retention.
8The real test after the August 31 close is how many ranked bidders accept the discovered L1 across all six distance slabs.
For daily newsletters and other free services, fill in your details: