All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Nov 2026
PSTCL awards Wadala Granthian 400 kV substation to MBH Power at Rs 86.78 crore after L2 wins the reverse auction
8R S Infraprojects opened lowest but finished 0.2% behind after the auction, and six corrigenda added 80 days to submission.
8Demolition and scrap pricing, a Rs 8.68 crore guarantee load and a split transformer contract keep interface and financing risk with the contractor.
MPMKVVCL splits Rs 122.32 crore conductor rate contract across six suppliers, with two taking 85.0% of the value
8Mahavir and Techno Fibre hold Rs 67.58 crore and Rs 36.39 crore, while ten bidders did not accept their LOIs.
8A 15-day versus 30-day security deadline and conflicting aluminium base dates keep cash and delivery risk with suppliers.
UPPTCL opens six price bids for the Sector-155 Noida 220/132/33 kV GIS after rejecting one admitted bidder
8Capital Electech moved from "Admitted" to "Rejected-Technical" with only a generic remark, 62 days before price opening.
8No estimate, security terms or interface schedule are on record, so scope and liability risk stays with the winning contractor.
NTPC North Karanpura seeks off-site transformer oil testing at PGCIL's Durgapur laboratory with a 24-hour urgent DGA line
8Ten urgent tests carry a 24-hour clock from sample submission, yet delay LD and performance security are marked inapplicable.
8Extension ceilings of three and six months and a conflicting agreement clause keep term and reconciliation risk with the laboratory.
NCL tenders a Rs 184.49 crore, 1,096-day Turra coal dispatch contract covering face loading, haulage and railway wagon loading
8The contractor moves 10.80 M.Te over an 11.607 km weighted lead, with idle-time claims barred and strata tonnage derived from survey minus weighment.
8A 5% PBG against a "No" ePBG field and two abnormally-low-bid options keep throughput and financing risk with the contractor.
MPPTCL extends bid deadline for Rs 316.16 crore Sabalgarh 400 kV substation and line package to 7 December
8Two extensions added 33 days, while a corrigendum clarified a third line-only route for performance qualification.
8A 24- versus 30-month schedule and a 0.1% excavation-compliance retention keep sequencing and cash-flow risk with the contractor.
SECI invites power traders to resell renewable capacity on a QCBS basis with a 75:25 weighting and one margin quote
8A single margin percentage covers 25-year sales and temporary resales, with Rs 60 lakh in performance security and a three-year framework.
8An undefined rupees-per-unit conversion in the encashment formula and two bid-validity clocks keep pricing and security risk with bidders.
POWERGRID tenders 11 single-phase 500 MVA, 765/400/33 kV autotransformers under Lot 8 with a Rs 332.71 crore auction benchmark
8Destinations stay open at bid time, with taking-over fixed at six units by month 23 and five by month 26.
8A 500 km freight basis, no credit for beating loss limits and cross-breach between supply and services contracts keep route and delivery risk with manufacturers.
POWERGRID invites bids to reconductor Gooty–Tumkur 400 kV D/C line with twin HTLS conductor against a Rs 123.24 crore indicative estimate
8The 104.18 km job runs beside an energised circuit and credits 1,262.662 km of removed ACSR Moose conductor to bidders.
8Daily LD of 0.05%, 36-month defect liability on three conductor routes and a Kolhapur–Ponda tower-spotting file keep scrap, security and design-data risk with contractors.
MPPTCL invites bids for five 500 MVA, 400/220/33 kV autotransformers under a pass-fail loss regime
8Loss ceilings of 90 kW no-load and 500 kW load carry no capitalisation, yet a first-unit 2% exception and penalties at double the evaluation cost apply.
8A 14th-month versus March 2027 delivery illustration and a 5% versus 10% guarantee keep schedule and security risk with manufacturers.
OMC tenders feasibility study and DPR for the 4.5 km Sasubohumali ghat road on a lump-sum fee
8Only panel firms with greenfield hill-road credentials can bid, yet the contract form makes the consultant answerable for executants' completion and payments.
8A 20% site-verification payment with no deadline and guarantee tails of three, four and 12 months keep liability and cash-flow risk with the consultant.
NHPC puts its 50 MW Lakhmana wind farm up for sale through a forward auction at a Rs 177 crore reserve
8Generation has averaged 30.2% below estimate, the PPA expired in 2019 and the incumbent O&M contract ends on 30 November 2026.
8A BOQ note seeking 25 years of O&M and a tax-inclusive quote, against an SCC that says otherwise, leaves bids on unequal bases.
BSPGCL tenders 491.903 MW of feeder-level solar across 206 substations with a contested 5 MWh battery clause
8Bid sheet Item 34(b) mandates storage from 2.5 MW while the RFP says the project excludes it, and the 60% minimum share leaves residual capacity unfillable at 52 of 60 qualifying sites.
8PBG encashment windows of six and 15 months keep pricing and security risk with developers.
APCPL awards Rs 350.67 crore Jharli coal supply to Tirupati Minerals at Rs 7,013.45 per tonne among six bids
8The GCV band cut to 3,550–4,000 kcal/kg matches the pricing base, and payment falls to 88.8% at 3,550 and 44.4% at 3,549.
8Station-end testing, adjusted tonnage for freight and a Rs 1 per tonne clause keep quality and working-capital risk with the supplier.
SECL bundles mine development, overburden removal and coal dispatch at Chhal into a Rs 2,703 crore, 4,018-day contract
8Bid dates slipped 22 days, 43.814 Ha of the first 50.06 Ha awaits resettlement, and 20% of the fleet must run on electric, CNG or LNG with no price variation.
8Lowest-of-three lead rules, steel-contamination recoveries and a 135- versus 122-month ePBG gap keep access, billing and guarantee risk with the contractor.
BHEL splits Raghunathpur boiler erection into two packages worth Rs 218.72 crore after L4 accepts a counteroffer
8Termico won Package A at Rs 109.4665 crore, while Indwell and Bhavani declined before P.E. Erectors took Package B at Rs 109.2488 crore.
8Four extensions, a B.1 qualification rewrite and an award 246 days after close keep validity and shared-facility risk with bidders.
GSECL seeks a 45 MLD effluent treatment EPC with two years of O&M at Ukai, ranked partly on power use
8Each extra kWh/day of guaranteed consumption adds Rs 18,055 to the evaluated price over a 15-year horizon.
8A 5% versus 10% guarantee, 46,920 m³/day of inflow against a 45 MLD plant and trial acceptance at 22.5 MLD keep design and security risk with the contractor.
RVPN admits nine bids for the Rs 143.63 crore Hathi Bhata 132/33 kV GIS after six deadline extensions
8Cable losses priced at Rs 2.96 lakh per kW, a fixed 1,800 m HDD quantity and item-rate deductions on overruns can reorder bids.
8An additional-security trigger below roughly Rs 122.09 crore and a 62-month kit guarantee keep civil and financing risk with the contractor.
For daily newsletters and other free services, fill in your details: