All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Nov 2026
IOC, HPCL and BPCL tie at Rs 86.0043 crore for NTPC North Karanpura's 6,000 KL LDO supply
8All three oil marketing companies quoted identical totals, triggering an equal-rate quantity split for 365-day supply paid by 100% lot-wise advance with no EMD or CPG.
8A payment comparator written "between two Vendors", no split ratio, firm freight and a 7-day versus 15-day delivery clock keep margin and LD risk with suppliers.
MPMKVVCL splits Rs 94.00 crore transformer rate contract across seven makers, leaving 31 units of 5 MVA unplaced
8The award covers 86 of 117 5 MVA units at Rs 63.80 lakh each, 36.8% above the implied estimate, and all 46 10 MVA units after Suman Electricals cut its quote by 11.9%.
8Cancellation for convenience before inspection, upward price variation lost after supplier delay and 45-day payment without interest keep inventory and working-capital risk with manufacturers.
UPPTCL opens a rejected bidder's price bid for Prayagraj GIS substation 19 days late under High Court orders
8Safety Controls & Devices' packet for the Rs 102.16 crore 220/33 kV, 4×60 MVA package was opened on 17 November, after nine qualified bids were opened on 29 October.
8Feeder-bay counts of one, three and two, leftover Agra site references and a 3-month versus 45-day CPBG tail keep scope and guarantee risk with the EPC contractor.
UPPTCL seeks Rs 4 lakh survey and layout study for Gomti Nagar 220/132 kV GIS/AIS and bus conversion
8The very short e-tender closes on 25 November for layouts of a proposed 2×160 MVA installation and a double-main conversion of the existing yard, with a Rs 10 lakh turnover floor.
8A 24 versus 25 November deadline, three months versus 45 days for execution and undefined drawing-acceptance criteria keep redraw and working-capital risk with the consultant.
PFC invites Category A law firms to paper Rs 477.78 crore loan for Mahathi's Cuddalore port
8The limited GeM bid closes on 23 November for least-cost selection of lender's counsel on an 8.88 MTPA seaport whose concession bars mortgaging the site and facilities.
840% of an all-inclusive fee tied to the closing opinion, conflicting tests at exactly five assignments and rival tie-break rules keep fee and eligibility risk with bidders.
RECPDCL pushes YEIDA 400/220 kV GIS deadline to 25 November and squeezes the post-auction window
8Amendment III adds eight days to submission, moving the reverse auction to 8 December and SPV transfer to 28 December with the Rs 5.28 crore bid bond and Rs 13.20 crore guarantee unchanged.
8Three days to deliver originals after the auction, a 12-day LoI-to-transfer gap against a 10-day clause and commercial operation tied to Aligarh bays keep closing risk with bidders.
KPTCL reports Rs 241.47 crore secure-infrastructure award to ITI with no bid count or estimate
8The open, two-cover lump-sum package covers design, supply, integration and commissioning across substations and centralised locations, with 17 November shown as an indicative contract date.
8No stated contract period, site count, acceptance criteria or payment milestones keep integration and working-capital risk with the contractor.
RRECL clears 11 of 19 bids for Rs 99.77 crore PM E-Drive charging rollout after easing the revenue-share rule
8The seven-package tender covers 236 locations on a 10-year term, with H1 selection on revenue share per kWh and financial opening scheduled for 16 November.
8Escrow settlement left to contract signing, no subsidy timetable, no carve-out for DISCOM delays and a 150- versus 180-day bid-security mismatch keep liquidity risk with operators.
KPTCL awards Hanur 220 kV substation package at Rs 209.08 crore on a single bid, 24.3% above estimate
8The 24-month package for 2×150 MVA transformation, a 13.458 km 220 kV DC line and 58.733 km of 66 kV links went to M T Kumar after Amendment-I let bidders qualify through a tower-design consultant.
8An unclear GST basis for the award, conflicting time-extension clauses, ceiling-based tower payments and contractor-funded ROW compensation keep pricing and cash-flow risk with the contractor.
GUVNL's 1,500 MW RTC auction fills the requirement in only two of eight months
8The tender for 1,500 MW of RTC and 1,500 MW of non-solar power from 16 November 2026 to 30 June 2027 drew RTC tariffs of Rs 8.90–10.00/kWh, with volumes ranging from 75 MW in November to 1,500 MW in February and March.
8Anonymous "XX" entries, unreconciled overnight delivery windows, no recorded acceptance or PPA quantities and an unclear LC mechanism keep supply-adequacy risk with GUVNL.
GUVNL's non-solar power auction draws just 50 MW at Rs 29–35/kWh against a 1,500 MW requirement
8November and January drew no non-solar bids, and the other six periods recorded 50 MW each at up to 293.3% above the lowest RTC tariff, while RTC drew sources from Ambitious, Jindal, Tata, NVVN and PTC.
8Single-offer periods that need GERC consent, unidentified suppliers behind every non-solar price and no explanation of the weak response keep procurement risk with GUVNL.
PSPCL awards Kapurthala RDSS package to SKS Infra at Rs 88.94 crore after the auction flips the ranking
8SKS moved from L2 to L1 by undercutting ABI's Rs 89.24 crore opening bid by a single 0.1% decrement, leaving the award 28.8% above the Rs 69.06 crore estimate for HT/LT loss-reduction works in three divisions.
8An unexplained Rs 20.88 lakh post-auction cut, 3% versus 10% performance-security clauses, no steel-structure escalation and GIS-linked final payments keep working-capital risk with the contractor.
PSPCL awards Nawanshahar RDSS package to ABI Energy at Rs 101.38 crore with no fresh auction bids
8Package 14's three ranked offers clustered 29.2–32.8% above the Rs 78.74 crore estimate, and the 730-day award came in Rs 34.46 lakh below ABI's evaluated L1 for reasons the record does not give.
8Conflicting 3% and 10% security terms, a "sixty-five (60) days" payment clause, lot-rejection penalties and a 473-day gap between the NoA and the portal contract date keep cash-flow and compliance risk with the contractor.
Kashmirilal overtakes ABI by Rs 9.46 lakh to win PSPCL's Rs 94.47 crore Mahilpur package
8The reverse auction cut Kashmirilal's own bid by 4.4% but improved on the best opening offer by only 0.1%, leaving the Package 12 award 27.1% above the Rs 74.33 crore estimate.
8Quality penalties of up to 5% of contract price, 10-year latent-defect liability, conflicting 3% and 10% security clauses and GIS-linked final payments keep execution and liquidity risk with the contractor.
RECPDCL pushes YEIDA 400/220 kV GIS deadline to 25 November but keeps the 18-month schedule
8Amendment III adds eight days to the previous deadline for the UPPTCL project, 23 days later than the original, moving the reverse auction to 8 December and SPV transfer to 28 December with the Rs 5.28 crore bid bond and Rs 13.20 crore CPG unchanged.
8No stated reason, a 12-day LoI-to-transfer window against clause 2.15.3's ten days and payment tied to simultaneous commissioning keep revenue-timing and execution risk with bidders.
For daily newsletters and other free services, fill in your details: