All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Sep 2026

UJVNL rebuilds Sirkari Bhyol cost base, lifting estimate 53.3% and EMD 80.5% before bids open
8UJVN Limited has taken its 3x40 MW electro-mechanical package from Rs 158.53 crore to Rs 243.05 crore through Addendum-I, pushing turnover, working-capital, comparable-work and bid-capacity thresholds up in step, while EMD climbed twice to Rs 5.7385 crore.
8With seven addenda, 24 corrigenda and 21 closing extensions taking submission 266 days past the original date, the question is whether the revisions produced a bankable package or simply concentrated participation among a handful of well-capitalised hydro specialists.

 

Addendum-VI reverses Zone VI error and switches Sirkari Bhyol turbine bearings to oil lubrication
8UJVNL has restored the project's IIT Roorkee-derived Zone V seismic basis after an intervening addendum wrongly cited Zone VI, and in the same document replaced water-lubricated guide bearings with babbitted oil-lubricated units with water cooling.
8The bearing change reaches cooling circuits, oil handling, monitoring and maintenance philosophy, so the harder question is how much lifetime auxiliary-system cost bidders must now carry into a 48-month fixed package.

 

NTPC issues second corrigendum on Simhadri 0.5 MMT coal without resolving 25% versus 10% quantity conflict
8Corrigendum C4 of 11 September supersedes C1 and the original buyer-added terms for the Rs 2 crore EMD Simhadri lot, retaining the right to move ordered quantity by up to 25% at award and again during the contract.
8Technical Specification Clause 3 still carries a plus or minus 10% station band, and with the GeM summary recording no ePBG against ITB Clause 22.0's mandatory 5% PBG, bidders must price a maximum volume and security exposure the documents do not settle.

 

UPPTCL deletes 'provided by UPPTCL' from transformer rows, forcing Noida GIS bidders to price erection
8Corrigendum-1 has replaced the BOQ for the Rs 112.05 crore Sector-155 substation, removing the entry that let bidders leave installation of the 160 MVA and 63 MVA owner-supplied transformers unpriced, and redefining 33 kV termination kits by interface rather than indoor or outdoor location.
8Submission moved a week to 17 September, but the real exposure is that the contractor now prices commissioning around equipment whose manufacture and delivery stay with UPPTCL, with no project-specific relief formula for late handover.

 

UPRVUNL converts 640 MW Rihand-Obra pumped storage from BOO to zero-consideration handover after 40 years
8The corrigendum replaces extendable BOO ownership with compulsory transfer to UPRVUNL 40 years from SCOD, in good running condition, free of liens and without transfer price or compensation, while the PBG moves to 5% of the Rs 3,953 crore estimate at Rs 197.65 crore and stays live until 12 months after actual commissioning.
8With nine extensions pushing bids to 12 October and forfeiture possible where the developer's own DPR finds the project infeasible, the test is how banks price terminal transfer beside pre-construction feasibility risk.

 

OPTCL opens Rs 301 crore HTLS reconductoring with two different estimates in its own records
8The Meramundali–Mendhasal package requires dismantling twin AAAC Moose and stringing twin HTLS on the live 400 kV double-circuit line, plus equipment and bus upgrades at both grid-substation ends, with bids closing 9 October.
8The signed notice states Rs 301,22,38,089 while the portal header reads Rs 3,01,26,70,182, and with outage allocation, tower adequacy and scrap responsibility all unspecified, bidders face a package whose basic commercial reference point is unreconciled.

 

POWERGRID ties 765kV GIS package SS 185T to a TBCB outcome bidders cannot influence
8The Orai, Patran and Agra extension package requires an exclusive MOU with the lowest evaluated qualified bidder, who receives a contract only if POWERGRID wins the upstream tariff-based bid, while exclusivity bars that bidder and connected entities from supporting rival TSPs.
8Four qualification routes admit manufacturers, collaborator and parent-backed Indian plants and EPC bidders, but with a further 10% ex-works guarantee on Routes 2 and 3 and no quantified compensation if POWERGRID loses, broad access on paper may still leave OEM gatekeeping intact.

 

NTPC builds six-contractor panel for Rs 300 crore Barh pond ash haulage with no purchase-order guarantee
8The 2026-27 rate contract splits work among up to six AST-01 vendors matching a single L1 price, one part reserved for an SC/ST MSE bidder, with roughly Rs 20 crore placed sequentially and Rs 50 crore as the cumulative ceiling per contractor.
8Payment follows compacted ash certified by the receiving road authority rather than trips or weighbridge tonnage, and with variation from minus 100% to plus 20%, panel entry buys eligibility rather than revenue.

 

GPCL risk-management RFP carries three submission deadlines and a hard copy that overrides the portal
8The ERM consultancy for GPCL's renewable, BESS, green hydrogen, mining and transmission portfolio records online closing at 18:00 on 21 September on the portal, 3 October in Chapter 1 and physical receipt on 6 October, with clause 5.3.2 giving the posted copy precedence.
8The QCBS 70:30 structure is designed to protect technical quality, but a compliant bidder could still be rejected for following one official instruction over another unless GPCL clarifies which date and channel govern.

 

MPPTCL bars partial bids on Rs 316 crore Sabalgarh package spanning substation, 34 km line and LILO
8TR-28/2026 bundles a new 400 kV substation, a Quad Moose double-circuit link to Morena Pooling and about 21 km of 220 kV LILO into one indivisible turnkey award, with 30-month and 24-month completion tracks and no rainy-season relief, while three 500 MVA and two 200 MVA transformers and two 125 MVAR reactors stay outside contractor supply.
8Price variation reaches only selected equipment and civil work, so reverse-auction pressure will meet a large block of fixed-price and deemed-inclusion exposure.

 

NTPC Lara mine-filling tender contradicts itself on diesel escalation and soil-cover thickness
8The Rs 255.06 crore package moving 20 lakh MT of ash into the Bishrampur and Dugga pits says no extra payment for fuel-rate changes at condition 2(h), then indexes 25% of contract price to diesel at Clause 14, while Scope Clause 1 fixes a 500 mm soil cap against Payment Clause 9(i)'s 300-500 mm band.
8With quantity variable from minus 100% to plus 20% across a six-way split and no order-of-precedence statement, both conflicts sit directly on the lump-sum price.

 

APCPL admits Talabira coal in one clause and excludes OCPL in another for 5 LMT Jhajjar buy
8The invitation for bids for the Rs 5 crore EMD package bars coal from CIL, SCCL, OCPL and NTPC group mines, while Technical Specification Clause 2 expressly permits OCPL and Talabira sources including the NLCIL captive mine.
8A second gap sits between Annexure-B1's 4,300 Kcal/kg ceiling and Clause 11's payment cap at 4,000 Kcal/kg, leaving a bidder unable to know whether its declared source qualifies or its better coal can be monetised.

 

MSEDCL grants nine days on Rs 97.87 crore cable tender but holds firm price against five bidders
8Shriram Cables, Torrent Electricals, Dynamic, KEI and Tirupati each sought price variation on the 33 kV and 11 kV 300 sq.mm HT XLPE package, and MSEDCL answered every request with "as per tender documents," also refusing KEI's three-month first-lot request and Tirupati's insurance surety bond proposal.
8Bidding moved from 1 September to 10 September, leaving a nine-month firm-price delivery, a 20% two-month mobilisation obligation and 1% weekly LD untouched.

 

OPTCL forces single award across Palaspanga and Barbil while its notice repeats the EMD as the estimate
8The Rs 315.27 crore package makes Lot-I and Lot-II one indivisible contract covering GIS at both stations, 1.2 Rkm of underground cable and roughly 69.2 Rkm of 220 kV overhead line including Twin Moose on 400 kV towers, all in 24 months.
8The opening notice states the estimate as Rs 3.15 crore, exactly the EMD figure, and Table-A carries 10 August against the portal's 11 August, leaving bidders to rely on portal precedence for basic commercial approvals.

 

HPPCL seeks green hydrogen offtakers for 1 MW Dabhota plant without naming volume, purity or delivery point
8The EOI sets a Rs 1 EMD, zero form fee and Rs 2,360 processing charge, with closing on 13 August and cost opening one hour later, but does not state saleable output, pressure, metering ownership, custody transfer or contract tenure.
8Classified simultaneously as procurement of services and miscellaneous works with a scheduled cost opening, the notification leaves respondents unsure whether they are quoting a purchase price, a service charge or a bundled logistics proposition.

 

NTPC leaves three quantity formulations live across its 2.5 MMT five-station coal package
8The Telangana lot under CS-0011-011(10)-9 now carries a plus or minus 20% variation in the revised detailed document, plus or minus 10% in the separate technical specification and a 25% GeM option clause at both order placement and during contract.
8Sequential station opening means a bidder's later price bids stay unopened once it reaches its declared Annexure-TC-10 limit, making award appetite a live competitive variable before any price is compared.

 

NTPC cuts Tanda coal ceiling to 3,700 Kcal/kg while lifting initial payment to 80%
8Revised Annexure-B1 pulls the GCV envelope down from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal caps of 12% and 14%, and the GCV challenge window contracts from ten working days to seven calendar days with a ±71.7 Kcal/kg admissibility threshold.
8The move from 50% to 80% initial payment is the clearest contractor gain in the package, but it arrives alongside ±20% quantity variation, station diversion rights and a source pool narrowed by the tighter specification.

 

Nabinagar sits last in NTPC's price-opening order, exposing it to a thinner field
8Corrigendum-1 leaves the 16 September dates unchanged for the 0.5 MMT lot and fixes the opening sequence as Telangana, Simhadri, Mouda, Tanda and Nabinagar, with bid security shown at Rs 10 crore for five stations against a visible overwritten Rs 8 crore in ITB Clause 7.1.
8Because bidders reaching their declared award ceiling drop out before later envelopes are opened, the last station in the queue may face the weakest price competition regardless of its own economics.

 

NHPC inserts a missing crane chapter and cuts turbine efficiency threshold to 94% at Dulhasti Stage-II
8Corrigendum No. 1 added the absent Chapter 18 covering two 190/30-tonne powerhouse cranes and three others, Corrigendum No. 5 rewrote the cooling-water and HVAC chapters and lowered the non-responsiveness threshold from 94.5% to 94%, and price-adjustment indices moved from 2011-12 to 2022-23.
8Four extensions have taken submission from 24 July to 28 September on the Rs 496.90 crore package, yet unit commissioning stays fixed at months 43 and 44 from the civil zero date.

 

UJVNL lets two OEMs cover turbine and generator at Tiuni Plasu after 18 extensions
8Addendum-II moved qualification from turbine and generator to turbine "and/or" generator and deleted the contract-value experience thresholds, and Addendum-VI then allowed as many as two manufacturers, with force-majeure substitution limited to BHEL, Voith Hydro, Andritz Hydro and General Electric.
8Addendum-III deleted air-gap, partial-discharge and vibration monitoring and cut excitation redundancy from n+n to n+1, so the widened front door arrives with a thinner reliability margin and a Rs 260 crore turnover test for manufacturer-backed bidders.

 

JERC bars consultants holding two of three earlier awards from Chandigarh STU-SLDC tariff work
8The Rs 18 lakh QCBS assignment covering business plans, MYT petitions, mid-term review and true-ups to FY 2029-30 excludes firms already awarded two of three specified JERC bids, while demanding ten years of experience, 20 assignments worth Rs 1 crore and two staff stationed at the Commission.
8Corrigendum C3 warns that a participation fee can render the bid null and void, even though the underlying RFP still requires a Rs 10,000 processing fee and advance hard copies.

 

SECI moves Ramagiri wind auction to cost per certified MU and drops turbine floor to 2.7 MW
8Amendment-01 rewrites ITB Clause 32.4.1 so bids rank on EBV divided by NIWE-certified ten-year P90 generation, with the denominator locked before the reverse auction and only price free to move, while the power-curve pass mark falls from 98% to 95% and the 96-hour test threshold from 98% to 96%.
8Repeated STPT failure no longer triggers WTG rejection and refund with 13% interest but a generation-linked LD at Rs 4.5 per kWh, leaving yield certification quality as commercially decisive as the EPC quote.

 

NPCL wants 300 MW RTC with 90% availability in six peak hours it picks day-ahead
8The 25-year BOO procurement requires a declared annual CUF of at least 75% held within plus or minus 10%, 50% of contracted capacity in every off-peak 15-minute block and 90% across six peak hours selected by NPCL on a day-ahead basis, with shortfall damages at 1.5 times tariff.
8Configuration and delivery points may change until financial closure but bring no SCSD relief, so the 24-month schedule and daily PBG encashment will likely surface as a firmness premium in the discovered tariff.

 

NTPC narrows Mouda coal window to 3,700 Kcal/kg as second corrigendum lands five days before bids close
8Corrigendum C4 of 11 September supersedes C1 for the 5 lakh MT package, while the revised document cuts maximum GCV from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal 12% and 14% caps, and moves payment from 50:40:10 to 80:10:10 with sampling charges down to Rs 2.97 per MT.
8GeM records no ePBG and no arbitration against Clause 22.0's 5% security and a Delhi-seated GCC arbitration, leaving document precedence to carry more commercial weight than the headline tonnage.

Details
 For reference purposes the website carries here the following tenders:
 8Tender for service hiring for servicing of C&S LT breakers during Details
 8Tender for services for unit 7 cooling water tunnel Details
 8Tender for procurement of tube super Details
 8Tender for additional support services for boiler rotary parts, ESP & duct damper Details
 8Tender for cooling water treatment Details
 8Tender for one year outline agreement for refilling of empty hydrogen cylinders Details
 8Tender for handling and transportation of coal Details
 8Tender for contract of supply and application of paint on structure steel in boiler Details
 8Tender for procurement of grinding roll and bull ring segment assy of bowl mill Details
 8Tender for installation and commissioning of energy chain for paddle feeder Details
 8Tender for complete manufacture of silencer, suction hood, roof Details
 8Tender for procurement of pipe fitting items. Details
 8Tender for work of levelling and metalling in subStations Details
 8Tender for renovation of R and M renovation of various 33/11 kV sub-station Details
 8Tender for award A rate contract for supply of 33 kV metering equipments Details
 8Tender for annual maintenance contract for the miscellaneous civil work Details
 8Tender for establishment of green hydrogen renewable energy and energy storge laboratory Details
 8Tender for procurement of 220/132/66kV polymer insulator strings Details
 8Tender for procurement of marshaling kiosk 300TB Details
 8Tender for construction of new complaint center in existing 33 kV S/Stn Details
 8Tender for construction of new complaint center and other civil works at 33 kV s/stn Details
 8Tender for const. of 2 No. 220 kV bays for LILO of MISS line Details
 8Tender for addition/alteration of swich house Details
 8Tender for supply, installation, configuration, integration, testing, commissioning and maintenance of point-to-point (P2P) wireless network along with VPN services and network Details
 8Tender for repair and replacement of RHR gate Details
 8Tender for providing and fixing 80 mm thick paver block along right side Details
 8Tender for ash handling plant Details
 8Tender for supply of idler frame Details
 8Tender for repair of damaged safety wall provided at up hill side slope to protect control room and intake structure Details
 8Tender for rate contract for repair/refurbishment and coating of runners Details
 8Tender for renovation and extension of existing temporary store Details
 8Tender for construction of 01 x 33kV feeder bay at 132kV substation Details
 8Tender for work of capacity enhancement of 132kV bus from single moose to twin moose at 132kV substation Details
 8Tender for providing and replacement of insulator string and other accessories at 132kV line Details
 8Tender for procurement and installation of different types of pumps Details
 8Tender for supply and installation of C wedge connectors in switchyard Details
 8Tender for biennial maintenance contract for miscellaneous civil work Details
 8Tender for procurement of grinding elements of 8.5E ,10 coal mill Details
 8Tender for procurement of network materials Details
 8Tender for construction of foundations for one number 220 kV bay Details
 8Tender for work of anticorrosive treatment and painting of various T/Fs & ICTs at various S/Stn Details
 8Tender for work of Bi-annual maintenance contract for internal inspection, attending oil leakages through HV & LV bushing with oil filtration & other TF related accessories/activities Details
 8Tender for providing tack welding to tower nuts & bolts of 400kV transmission line towers Details
 8Tender for work of providing and fixing of high voltage busbar insulation tape at various substation Details
 8Tender for work of hot line stringing of 0.2 panther single conductor on D/C towers Details
 8Tender for work of supply & installation of fire protection screen cum water, rodent protection system, advanced cable transit system Details
 8Tender for work of shifting of control room at 220kV and 132kV ECR substations Details
 8Tender for work of 2x33 kV bays along with allied works at 220kV S/s Details
 8Tender for work of annual maintenance contract (AMC) for work of repair of ABT PC monitor installation of ABT meter Details
 8Tender for work of annual maintenance contract (AMC) for work of repair of ABT PC monitor installation of ABT meter, DCU installation and up gradation of ABT PC CPU along Details
 8Tender for supply of scraper guard assembly for coal mill XRP-783 Details
 8Tender for supply and installation of an energy efficient lubricated rotary screw air compressor Details
 8Tender for supply of taper lock pulley for ash handling plant Details
 8Tender for work of replacement of CT/PT/CVT & LA of 220kV / 400kV switchyard Details
 8Tender for work of misc pressure part related activity of boiler stage Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Coal supply to Punjab power plants remains adequate, state needs to improve offtake from mines, says ministry Details
 
8Illegal coal mine collapses in Jharkhand's Dhanbad, at least 2 dead; several feared trapped Details
 
8India's semiconductor sector draws $1.4 bn funding, half of it since 2025 Details
 
8NMDC targets 100 million ton production capacity by decade end Details
 
8BCCL Intensifies Crackdown on Illegal Mining in Kantapahari Details
 
8POWERCON Group adds 22-year wind energy veteran to leadership team Details
 
8Smart tech powers India's energy needs Details
 
8Rare Split At CERC Over Safeguard Duty Benefit To A 390 MW Hybrid RE Project Details
 
8India LNG Costs Surge, Exposing Asia’s Fragile Energy Model Details
 
8Chandigarh Administration eyes solar plants at 8K private houses by March next Details
 
8Private sector can help India exceed 100 GW nuclear target by 2047: Bajaj Energy official Details
 
8Gas-based power output rises 80% amid evening supply shortfall Details
 
8Power shortage deepens in Keralam as KSEB explores costly purchases Details
 
8TNEB procures additional 2,000 MW power to ensure uninterrupted supply Details
 
8Why Kerala is facing power cuts, and why the crisis has become a political fight Details
 
8Coal Supply To Punjab Power Plants Remains Adequate, Says Ministry Details
 
8Opposite signals in NTPC, BHEL: Kotak Institutional Equities report Details
 
8Rural Andhra Pradesh reels under power outages Details
 
8Coal crunch, high demand trigger power cuts in Punjab Details
 
8India’s Data Centre Boom Is Rewriting Its Infrastructure Needs Details
 
8Adani’s unit resumes power supply as Rampal’s unit shuts down Details
 
8Report flags silt crisis, operational lapses at BBMB's Dehar power house Details
 
8MCA-Nepal completes 18-km transmission line construction to Nepal-India border Details
 
8The physical and financial losses in Nigeria’s power sector Details
 
8Cement Decarbonisation Gains Pace as India’s Urban Buildout Expands Details
 
You can also click on Newsclips for more Details
 For reference purposes the website carries here the following tenders:
 8Tender for supply of scraper guard assembly for coal mill XRP-783 Details
 8Tender for work of transportation installation and commissioning of emergency restoration system ERS tower of 132 kV line Details
 8Tender for increasing capacity work from (2x40) MVA to (2x63) MVA T/F and other associated work Details
 8Tender for work of revetment on tower No. 22 of 132 kV line Details
 8Tender for civil work for construction of 02 No. 132 kV line Details
 8Tender for annual maintenance contract for the miscellaneous civil work Details
 8Tender for procurement of 132 kV C and R panels Details
 8Tender for procurement of blades for stationary portion Details
 8Tender for procurement of spares for collector tank and nozzle for hydro ejector installed Details
 8Tender for procurement of different size of silica gel breather Filled with deep blue silica gel for various HT and LT transformers and bus ducts Details
 8Tender for supply, erection, installation, reinstallation, testing, commissioning, integration with the existing and upcoming SCADA-DMS/ADMS systems Details
 8Tender for supply of LT XLPE insulated single core cable Details
 8Tender for annual maintenance contract (AMC) for maintenance of OPGW network installed Details
 8Tender for supply of HVIC Ssilicon RTV coating (supply and application) on equipment Details
 8Tender for biennial maintenance contract of inter plant Details
 8Tender for CEMS EQMS parameters data transmission and direct connectivity Details
 8Tender for assembly of gas turbine rotor with the supply of consumables Details
 8Tender for repair of defects of existing PU coating Details
 8Tender for water proofing treatment on roof Details
 8Tender for repair and renovation of balance portion of CISF barrack Details
 8Tender for air seal application contract Details
 8Tender for proposal for repair of RCC pits Details
 8Tender for installation and fitting of concertina coil above Details
 8Tender for job A overhauling of LP turbine blade Details
 8Tender for fuel oil handling and storage system Details
 8Tender for supply, erection, commissioning and O&M of construction power supply system package Details
 8Tender for construction of auditorium structural shed and associated civil and electrical works Details
 8Tender for procurement of fixed contact for 11kV AB switch 200Amps Details
 8Tender for procurement of LT 3phase channel cross arm Details
 8Tender for conversion of the existing 33 kV overhead power line Details
 8Tender for yard fencing and metalling for existing transformers Details
 8Tender for addition/alteration of switch house and allied civil works at 132 kV S/S Details
 8Tender for procurement of H.T. nuts and bolts Details
 8Tender for procurement of spares for FD fans Details
 8Tender for procurement of clarified water pumps Details
 8Tender for procurement and replacement of various types of fire extinguishers Details
 8Tender for operation and maintenance of ash handling system Details
 8Tender for treatment of slope stability measures on upstream side Details
 8Tender for establishing three more EWS-PA system sites in the downstream Details
 8Tender for repair of 24 sets of guide roller wheel assemblies for intake service gate Details
 8Tender for water proofing treatment of A-type Details
 8Tender for procurement of 25,000 Nos. of 4G IOT SIMs along with the technical supporting Details
 8Tender for supply, erection, testing and commissioning of 630KVA, 33/0.4kV three phase station transformer along with associated works at 220kV S/s Details
 8Tender for thermo vision (hotspot) scanning of various 220kV and 132kV transmission lines Details
 8Tender for replacement of damaged conductor spans, rectification of loose conductor spans and other associated works Details
 8Tender for strengthening of iron mesh fence, repairing and construction of trenches and trench covers, rearrangement and dressing of various kinds of cables Details
 8Tender for replacement of old, damaged and malfunctioning 33kV bus isolators and 33kV line isolators Details
 8Tender for replacement of broken/punctured/damaged disc insulators in various transmission lines Details
 8Tender for replacement of bare conductor by covered conductor ACS AL59 104.98 Sq.MM Details
 8Tender for replacement of bare conductor by covered conductor Details
 8Tender for replacement of bare conductor by covered conductor ACS AL59 104.98 Sq.MM Details
 8Tender for replacement of bare conductor by covered conductor Details
 8Tender for turnkey construction of 1 (one) no. of 132/33kV, 50MVA transformer bay Details
 8Tender for providing new service connection Details
 8Tender for supply of 33kV VCB with GI mounting structure Details
 8Tender for annual rate contract (ARC) for operation & maintenance work of hydro pneumatic type wet ash handling system Details
 8Tender for supply of spares of coal mills Details
 8Tender for extension of control room at 132 kV S/Stn Details
 8Tender for supply of material, erection for renovation/modernization/upgradation/augmentation/bifurcation of the existing 11 kV feeders Details
 8Tender for const. of complaint center in existing 33 kV S/Stn Details
 8Tender for procurement of numerical transformer differential relay Details
 8Tender for repair of plant main gate Details
 8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing Details
 8Tender for turnkey execution of design, supply, installation, testing & commissioning of RTCC panels of transformers Details
 8Tender for supply of mill outlet ventury assembly Details
 8Tender for repair and strengthening of cage ladders and replacement of top hand railing Details
 8Tender for repair of power at 132kV S/Stn. Details
 8Tender for replacement and rotation of various sizes of CI/MS ERW ash disposal pipelines Details
 8Tender for procurement of 66kV SF6 Gas circuit breaker Details
 8Tender for procurement of 33kV CT 11kV NCT 66kV NCT Details
 8Tender for repair and maintenance of roof Details
 8Tender for shifting of transmission line Details
 8Tender for waterproofing and allied work on bunker floor terrace Details
 8Tender for works contract for loading /unloading of line materials Details
 8Tender for supply of 200 5A CT coil 0.5s class accuracy Details
 8Tender for asssisting for maintenance of 6.6 kV ABB make SF6 H.T breakers, panels Details
 8Tender for complete preventive maintenance of LT breakers HT breakers HT panels LT panels LT modules in 66 kV switchgear Details
 8Tender for supply of M.S.stay clamp for 8.0Mtr PSC pole Details
 8Tender for O& DM water production system operation, sampling, conditioning, chemical analysis and equipment Details
 8Tender for repair rectification of eroded tubes in LTSH coil and other allied works Details
 8Tender for procurement of clarified water pumps of stage Details
 8Tender for construction of all technical civil works Details
 8Tender for construction of all technical civil works at new 66 kV sub-station Details
 8Tender for miscellaneous support service job Details
 8Tender for service contract for servicing, overhauling and replacement of damaged spare parts of EOT cranes installed Details
 8Tender for supply and delivery of non centralized local materials Details
 8Tender for shifting and diversion of existing 33kV line Details
 8Tender for renovation of serampore divisional store Details
 8Tender for replacement of age old and trouble prone 26 Nos street light poles Details
 8Tender for work for replacement of suspension/ tension conventional insulator by SRI on 220kV class lines Details
 8Tender for annual rate contract for providing expert services for troubleshooting of AC/DC equipments and control/ protection system Details
 8Tender for providing and fixing of multifunction digital energy meters Details
 8Tender for work of repair of faulty 33/11 kV CT’s & PT’s and repair of faulty / damaged station transformer available Details
 8Tender for supply 8. retrofitting of 5Nos. of numerical distance relays Details
 8Tender for work of chemical cleaning of insulators Details
 8Tender for supply of pre selector of tap selector of converter transformer Details
 8Tender for procurement of 36 kV 1600A, having short circuit breaking capacity of 31.5 KA, 3P, VCB along with support structure Details
 8Tender for repairs of BHEL make radiators & replacement of radiators in 298.6 MVA BHEL make converter transformer Details
 8Tender for execution of the pilot project on AGC-enabled battery energy storage system Details
 8Tender for Bi-annual work of fabrication of 66kV 'H' Frame structure and accessories for various 'H' Frame line Details
 8Tender for Bi-annual rate contract for shifting/modification work of existing various 66/132/220 kV class transmission lines Details
 8Tender for survey, design, supply, installation, commission and maintenance of solar PV system for 5 years as a rooftop Details
 8Tender for survey, design, supply, installation, commission and maintenance of solar PV system Details
 8Tender for laying of underground cable, fault finding & rectification work Details
 8Tender for maintenance of HT, LT line & TC work for DESHOTAR Details
 8Tender for maintenance of HT, LT line & TC work for KHEROJ Details
 8Tender for maintenance of HT, LT line & TC work Details
 8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Rajneesh Shrotriya Chief Technology Officer, Renewable Business, Sterling & Wilson Renewables Limited Details
 
8India’s CEA proposes mandatory BESS for new solar, storage Details
 
8Better Renewable Energy Stock: Inox Wind vs Suzlon Energy Details
 
8India Power Demand Doubles as Installed Capacity Hits 552 GW Details
 
8Views of Manohar Lal: “India’s power sector has made significant progress” Details
 
8Why India’s industrial sector is looking beyond the grid for energy security Details
 
8India’s Solar Capacity Crosses 168 GW As 2026 Installations Near 34.45 GW By August 2026 Details
 
8Russia's Rosatom offers nuclear power plants to India for 100 GW target Details
 
8Gaining Momentum: Developers’ perspective on the wind power sector Details
 
8GESCOM Floats Tender for 60.3 MW Distributed Solar Projects Details
 
8A Diversified Mix: Renewables remain central to India’s power capacity expansion Details
 
8Big Shift: Growing role of electricity in the future energy mix Details
 
8Premier Energies, RCT India Sign JV for 12 GWh BESS Plant Details
 
8Kerala power crisis deepens as CM calls emergency meet amid opposition protests Details
 
8Tapping Water Bodies: PM-Surya Sarovar Yojana gives a fresh impetus to the segment Details
 
8Orders Worth Over Rs 94 Crore Bagged By DEE Development Engineers Details
 
8India’s power capacity surges as demand nearly doubles Details
 
8India Coal Supply Tightens as 59 Power Plants Face Fuel Crisis Details
 
8India’s power demand doubles in a decade as installed capacity reaches 552 GW Details
 
8Jefferies’ power play: 6 stocks with up to 43% upside; JSW Energy, Adani Energy among top picks Details
 
8Coal India Boosts Daily Production 40% to 1.91 MT as Coal Evacuation Gains Strong Momentum Details
 
8Transmission upgrades, coal flexibilisation: How India is planning to unlock green power Details
 
8SJVN to Begin Commercial Operation of 660 MW Unit-II at Buxar Thermal Power Project on September 12 Details
 
8India Power Crisis: 58 Thermal Plants Running on Critically Low Coal Stocks Details
 
8India’s Coal Stock Problem Exposes a Power-System Bottleneck Details
 
8Ceigall India acquires Jam Khambhaliya Jamnagar Power Transmission for Rs. 5,00,000 Details
 
You can also click on Newsclips for more Details
SJVN's Rs 6.31 lakh Attunli quarry consultancy carries two turnover thresholds and two payment cycles in the same package
8The GeM bid field records Rs 2 lakh minimum average turnover while ATC Clause 7.0 and the underlying MQR approval both fix it at Rs 1.61 lakh, and payment is promised within 45 days in one layer and 30 days in another.
8A retender that reaches the market with competing qualification and cashflow provisions leaves evaluators, not the document, deciding which figure governs.

Jaipur Vidyut Vitran Nigam Limited cuts qualification thresholds by nearly a quarter and the completion period by three months in the same amendment
8Amendment-1 lowered the single-contract experience test from Rs 109.77 crore to Rs 85.036 crore, MAAT from Rs 47.05 crore to Rs 36.444 crore and EMD from Rs 3.14 crore to Rs 2.4296 crore, correcting a table built on a higher base than the disclosed Rs 121.48 crore estimate.
8The same package compressed execution from 12 months to nine and moved milestones from 33.33% per quarter to 25% every two months, pairing easier entry with harder delivery.

Damodar Valley Corporation withdraws a 627-page technical volume mid-tender, then removes six months from the implementation clock
8Corrigendum 2 replaced Volume-II in its entirety and barred reliance on the earlier version, while
Corrigendum 3 moved completion from 18 months after agreement to 12 months after Letter of Award.
8Bidders gained a 14-day submission extension to revalidate OEM commitments, licences, spares and lifecycle costs against a specification that had changed underneath them.

UJVN Limited invites tariff bids for a 90 MW/225 MWh battery near Chilla without disclosing degradation, dispatch or interconnection terms
8The notice fixes capacity, a 2.5-hour configuration, BOOT delivery and partial VGF support through PSDF, but chemistry, augmentation obligations, charging-energy responsibility and payment security are not specified in the document.
8The obligation being priced is preservation of 225 MWh over the concession, and the notice alone does not show who carries the replacement cost.

NREDCAP's Rs 324.70 crore Vijayawada waste-to-energy tender is labelled EPC on the portal and DBFOT in the RFP
8The portal records a 90-day bid validity and an EPC form of contract, while the RFP requires 180 days and describes a 22-year concession carrying financing, operating and handback obligations.
8The guaranteed daily waste quantity is to be settled only after selection, even though bidders must quote their capital grant requirement now.

Transmission Corporation of Andhra Pradesh Limited moves its MPLS-TP estimate from zero to Rs 139.44 crore after issuing the tender
8Bid security rose from Rs 3 crore to Rs 8,78,87,230, the turnover test fell from Rs 200 crore to the corrected ECV, and the equipment count was reconciled from 421 units to 463 including 42 spares.
8Whether the 40% supply and 20% performance qualification tests apply to 421 or 463 units is left unstated, and that denominator decides who qualifies.

NHPC extends its Rs 5,541.23 crore Kamala Lot-1 dam package six times and defers gate-supplier qualification until after award
8Corrigendum No. 2 allows the hydro-mechanical subcontractor's experience to be evaluated during execution, provided documents arrive at least six months before that portion begins.
8Dedicated muck-disposal Zones 6A-1 and 6A-2 were simultaneously deleted, leaving Lot-1 sharing Zones 6B and 6C with the adjoining package.

APTRANSCO's live portal and its own corrigendum state different bid securities for the same MPLS-TP submission
8The portal continues to show zero ECV and Rs 3 crore EMD under tender ID 983294, while the corrigendum heading carries tender ID 968960 and fixes security at Rs 8,78,87,230.
8Two EMD figures and two tender IDs cannot govern one submission, and no consolidated corrigendum establishing hierarchy has been issued.

Odisha Power Transmission Corporation Limited's Rs 104.43 crore Baisinga package prints both 70:30 and 80:20 supply payment terms
8The payment schedule retains "Seventy percent (70%) Eighty Percent (80%)" and the corresponding balance wording, leaving no settled basis for working-capital modelling.
8Alongside it sit a 10% contract performance security and a separate 10% security on the taxable value of critical equipment, running 60 months for transformers, reactors, SAS and cables.

OPTCL lifts the Baisinga site-receipt payment from 70% to 80% while carrying a stray Parjang substation reference into the scope
8Bay-erection payment correspondingly falls from 20% to 10%, accelerating equipment cashflow but reducing the amount secured against physical erection progress.
8The package also shows CPC-22/2025-26 inside an IFB governed by CPC-67/2025-26 and a 17-day portal extension with no matching hard-copy deadline.

Assam Electricity Grid Corporation Limited's Khumtai 400kV upgrade states 24 months in the IFB and 36 months in the SCC
8The portal records 730 days and ITB 2.37.1 says two years, but the SCC expressly prevails over the GCC where they conflict.
8Clause 4.2.2(b) separately gives the turnover threshold as Rs 367 crore in figures and Rupees Three Hundred Sixty Crore in words, a Rs 7 crore gap in a financial qualification test.

Bharat Heavy Electricals Limited asks a GIS OEM to commit prices and guarantees for a contract it has not yet won
8The tie-up converts into a purchase order only if BHEL secures the DTL Tikrikhurd award, while the OEM carries firm pricing across a 21-month supply schedule and a 60-month defect period extendable to 84 months.
8Guarantee exposure stacks at 10% to BHEL, 2% to DTL and a further 10% for Route-2 or Route-3 qualification, before a five-year latent-defect tail begins.

Gujarat Energy Transmission Corporation Limited shifts Godadara GIS delay damages from the delayed portion to the entire contract price
8SCC Clause 41.0 now charges 0.5% per week on the full Rs 115.67 crore package, capped at 10% plus GST, even where the delay originates in one workstream.
8The same amendment offers interest-bearing advances that reduce subsequent progress payments from 80% to 70% on supply and 90% to 80% on erection.

NTPC Renewable Energy Limited holds its 813 MW Bellary wind bid open for 146 days while leaving the query window closed since April
8Ten corrigenda moved submission from 1 May to 24 September 2026, but the pre-bid deadline of 20 April 2026 was never reopened.
8Corrigendum No. 4 separately widened financial qualification to count turnover from a business acquired through slump sale or demerger, subject to auditor certification and continuity evidence.

Odisha Coal and Power Limited caps Tangardihi North's exploration phase at Rs 25 crore and ranks bidders on 397 million tonnes
8A Phase I quotation above the ceiling is reduced to Rs 25 crore rather than improving the evaluated position, while the Base Mining Charge is multiplied across a comparison quantity that detailed drilling has yet to confirm.
8Around 14,000 metres of exploration sits inside the same contract whose 25-year operating commitment depends on what that drilling finds.

WAPCOS gives three masked bidders ten days to respond to a five-year strategy mandate classified as an emergency
8The Rs 1.50 crore QCBS assignment weights technique at 80%, with 60 of 100 technical marks resting on named expert CVs and a presentation.
8Arbitration and consensual ADR are excluded entirely, leaving employer-controlled internal review, mediation and Delhi civil courts as the dispute route.

Gujarat Energy Transmission Corporation Limited's Navsari cable tender lists 193,186 metres of 66 kV cable against a 24,218-metre route survey
8The Rs 98.48 crore item-rate package also carries six foundation categories each showing eight tower foundations while the total tower-erection quantity is also eight, leaving the BOQ open to interpretation before pricing.
8Amendment no. 1 moves delay damages from the delayed portion to 0.5% of the entire contract price per week, capped at 10%, or roughly Rs 9.85 crore plus GST.

Maharashtra State Electricity Transmission Company Limited puts a Rs 73.19 lakh breaker overhaul across 12 substations without a breaker count
8The notice covers spares supply and complete mechanism overhauling of CGL-make 132 kV breakers at sites spanning both 132 kV and 220 kV yards.
8Mechanism types, spare schedules, outage duration, testing protocol, warranty and completion period are not specified in the document, leaving the estimate impossible to test against actual scope.

Details
 For reference purposes the website carries here the following tenders:
 
8Tender for fuel oil pump house, fuel oil forwarding pump house, 765 kV switch yard, cooling water pump house Details
 
8Tender for civil work for construction of 01 no. 220 kV feeder bay Details
 
8Tender for construction of foundation for 33kV TSS bay and related civil works at 132 kV sub station Details
 
8Tender for construction of foundation for 33kV bay Details
 
8Tender for supply, installation, testing and commissioning of smoke and heat extraction system, ventilation system, gas suppression system Details
 
8Tender for restoration upgradation and reutilization of diesel generator sets 750 kVA for emergency power supply Details
 
8Tender for aluminium cladding/corrugated sheet at duct, boiler Details
 
8Tender for augmentation of DFA transportation system Details
 
8Tender for supply and installation of fills for stage 2 cooling tower Details
 
8Tender for painting of pipe rack structures Details
 
8Tender for mechanical R and M of 24 cells of CT 5A and 5B Details
 
8Tender for procurement of LT motor Details
 
8Tender for procurement of 950 KW CW motor Details
 
8Tender for SITC of solar high mast system Details
 
8Tender for procurement of St 1 CW pump thrust bearing pad Details
 
8Tender for transportation of 1.08 LMT (One LAc eight thosunad metric tones) of coal Details
 
8Tender for availing OEM supervisory service for bushing gasket replacement of BHEL Make 220kV station transformer Details
 
8Tender for supply of submersible pump motor set capacity Details
 
8Tender for annual rate contract for onsite maintenance of 11/0.250 KV, 1-phase & 11/0.433 kV 3-phase distribution transformers of various Details
 
8Tender for special repair of damaged inverted concrete lining of flip buckets Details
 
8Tender for supply of recessed mounted LED lights and LED tube rods for powerhouse Details
 
8Tender for procurement of solenoid operated valves (SOV) and spare repair kits installed Details
 
8Tender for work order for annual work contract for assistance in operation of the equipments of turbine boiler WT plant Details
 
8Design, manufacture, testing at manufacturers works, packing, forwarding, delivery at site of 110kV composite insulated Details
 
8Tender for constructing additional circuit 11kV OH with covered conductor Details
 
8Tender for capacity enhancement of existing 1x12.5MVA, 110/11kV transformer Details
 
8Tender for installing new 200MVA ,220/110kV transformer Details
 
8Tender for supply and application of metal protective compound for various pipe lines Details
 
8Tender for procurement of roller bearings quantity Details
 
8Tender for supply of current transformer Details
 
8Tender for construction of a new control room at 33/11 kV existing Details
 
8Tender for outsourcing of internal audit function Details
 
8Tender for centralised rate contract for supply of different size conveyor belts for coal handling plant Details
 
8Tender for construction of drainage canals Details
 
8Tender for annual rate contract for repair and maintenance works Details
 
8Tender for repair and maintenance including miscellaneous works Details
 
8Tender for construction of main entrance gate Details
 
8Tender for construction of cement concrete pavement around the cooling tower Details
 
8Tender for supply of assorted size of MS grill for repairing of platform of ash slurry line Details
 
8Tender for rate contract for work of rewinding and repairing of various rating of LT motor, submersible pump and various auxiliary Details
 
8Design, engineering, supply, erection, testing and commissioning and comprehensive O&M for 5 five yeras for 1000 KWP DC capacity rooftop solar PV power system Details
 
8Tender for manufacture, testing, supply, and delivery of 45kg mechanical foam type fire extinguishers trolley mounted, conforming Details
 
8Tender for supply/installation and commissioning of fire extinguishers Details
 
8Tender for supply of journal bearing for HP803 bowl mills Details
 
8Tender for supply of 25KVA/22kV/433V energy efficient level-1 distribution transformers Details
 
8Tender for sale of ferrous and non-ferrous scraps such as M.S. miscellaneous scrap Details
 
8Tender for attending to routine maintenance minor breakdown works in air conditioning and ventilation system Details
 
8Tender for supply of 11kV AB switch for double pole structure Details
 
8Tender for construction of 33kV S/S Details
 
8Tender for rate contract for supply of various items for repair of failed distribution transformers Details
 
8Tender for survey, design, supply, installation, commission and maintenance of solar PV system Details
 
8Tender for annual contract for operation and maintenance of on line coal sampler Details
 
8Tender for sprinkling of water over roads in and around plant Details
 
8Tender for service contract for reclamation of chusher rotor Details
 
8Tender for insulation and refractory work Details
 
8Tender for overhauling of draft fans, gates and dampers Details
 
8Tender for procurement of 11 (Eleven) Nos 132kV CVTs Details
 
8Tender for biennial operation and maintenance of 1089kWp grid connected rooftop solar photovoltaic power plant Details
 
8Tender for procurement of spares of fly and bottom ash evacuation system Details
 
8Tender for provision of concertina fencing over Details
 
8Tender for round the clock maintenance for routine breakdown and preventive maintenance of 4 X 9 MW and 2 X 4 MW TG sets with all auxiliaries 66 kV switchyard Details
 
8Tender for shifting and diversion of existing of 11kV line Details
 
8Tender for annual maintenance work of unit-II of SHP Details
 
8Tender for supply and installation of fault passage indicator Details
 
8Tender for replacement of weasel conductor with 11 kV AL- 59(ACS) 104.98 Sq.mm covered conductor Details
 
8Tender for replacement of weasel conductor Details
 
8Tender for replacement of weasel conductor with 11 kV AL- 59(ACS) 104.98 Sq.mm covered conductor Details
 
8Tender for supply and installation of fault passage indicator Details
 
8Tender for work of LILO arrangement of 132kV line Details
 
8Tender for balance work of conversion of 220kV SCSC to 220kV MCMC line Details
 
8Tender for procurement of various communication cards of FOTE panels Details
 
8Tender for annual battery maintenance work at various substations Details
 
8Tender for work of servicing & overhauling along with providing & fixing of required spares of 245kV circuit breakers at various Details
 
8Tender for annual maintenance contract for repairs, overhauling of 33 kV various VCB installed Details
 
8Tender for replacement of existing street light poles along Details
 
8Tender for additional 1 X 100MVA, 220/22-22kV kV T/F along Details
 
8Tender for work of construction of revetment/protection wall Details
 
8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50 MVA, 132- 110/33 kV T/F with allied civil works Details
 
8Tender for replacement of old NIFPS cabinet of ICT 1 & ICT 2 Details
 
8Tender for AMC the emergency breakdown work, outage oriented work & non- outage oriented work at various 220kV & 132kV substations Details
 
8Tender for augmentation of substation by providing additional 1X50 MVA 132/33kV PTF along Details
 
8Tender for augmentation substation by additional 1 x 50 MVA 132/33 kV transformer along with HV AIS bay Details
 
8Tender for supply of MS ERW pipes, bends and valves for cooling system Details
 
8Tender for supply of various fasteners and consumables Details
 
8Tender for repairing/overhauling of high energy drain valve and other low/medium/ high pressure Details
 
8Tender for work of complete overhauling / breakdown maintenance of C.W pumps Details
 
8Tender for supply of various lighting LT cables for electrical fuel section Details
 
8Tender for supply of 33kV 1Cx500 sq.mm XLPE aluminum armour cable. Details
 
8Tender for supply, erection, testing and commissioning of 220 kV 1C x 1200 sq. mm aluminum conductor XLPE underground cable Details
 
8Tender for supply, laying, erection, testing and commissioning of 66kV 1Cx630 sqmm XLPE cable Details
 
8Tender for providing and customized dosing operation of chemical material for wet coal flowability solution Details
 
8Tender for work of applying polyamine base glass flake renforced anticorrosive protective coating Details
 
8Tender for renovation work of wagon tippler 3-4 roof cladding, drive pit Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:  
 
8India needs patient capital to boost small hydro projects: MNRE Secretary Details
 
8IEA sees India’s coal demand rebounding after 2025 dip Details
 
8Bhupender Gupta gets six-month extension as CMD of SJVN Details
 
8Power and energy: How costs can be reduced at every stage of the supply chain Details
 
8Power stocks: Nuvama picks ACME Solar, NTPC, Power Grid; check target prices Details
 
8West Bengal AAR says actual-cost electricity recovery not liable to GST Details
 
8India’s Power Demand Hits Record 169 BU In August, Rises 12.8% YoY: Crisil Details
 
8Cummins India Gears Up for a Revolutionary Power Showcase at bauma CONEXPO Details
 
8India to lead global coking coal demand growth while reducing import of thermal coal: IEA Details
 
8Premier Energies expands beyond solar with 12 GWh battery storage plant in Telangana Details
 
8DEE Development Engineers’ Order Book Reaches Rs 2,435.61 Crore Details
 
8Agrivoltaics To Turn Indian Farmers Into Urjadatas, Says Pralhad Joshi Details
 
8Global Coal Demand Expected to Increase by 2026, India’s Consumption Forecasted to Rise at 4.2% Details
 
8NTPC Invites EoIs for Sodium-Ion Battery Storage Pilots Details
 
8Infineon, SolarEdge step up 800 VDC AI data centers protection Details
 
8August power demand hits record 169 BU; non-solar prices surge 33% Details
 
8New Industrial Revolution: Six Sectors Set to Power India’s Next Great Economic Leap Details
 
8Small Hydro Power has a distinctive role in India’s clean energy transition: Shri Shripad Yesso Naik Details
 
8Bihar's Big Solar Push: Free Rooftop Power for 2.5 Lakh Poor Families by October Details
 
8India’s Push for Small Hydro Power: A Green Energy Initiative Details
 
8Global Coal Demand to Hit Record 8.94 Billion Tonnes in 2026 as China, India and ASEAN Drive Consumption Details
 
8Electricity, not oil, should define growth Details
 
8Shakti Pumps surges 6%: Bags Rs 235.92 crore order for 10,000 solar pumps in Maharashtra Details
 
8GPI appointed as an authorized distributor of FG Wilson Generator Sets in India Details
 
8BEE Showcases Commercial Electric Cooking Solutions to Accelerate India’s Transition from LPG to Electricity Details
 
8India’s Tech Manufacturing Push Is Reshaping Its Urban Economy Details
 
8AI power demand + data localisation: The twin forces behind India’s data center boom Details
 
8From solar to aerospace, Jefferies highlights growth hotspots of the India story Details
 
You can also click on Newsclips for more Details
8Three bulk-transmission circuits in the southern grid tripped between 17:59 and 18:02 on 9 September, with over-voltage recorded against every event. Details
8CareEdge has reaffirmed SECI’s CARE AAA; Stable rating on Rs 600 crore of bonds after power-sale tie-ups reduced an earlier 8 GW stranded renewable pool by about half, leaving roughly 4 GW still awaiting buyers. Details
8The two 220 kV lines serving Tarapur Units 1 and 2 tripped nineteen times from February 2026, and the Bhilad feeder remained unavailable after a 22.81 kA fault close to the switchyard. Details
8APTEL has ruled that Haryana’s annual tariff determination for the Jind and Fatehabad biomass projects cannot be capped at the bidding-stage ceiling tariff, preserving annual fuel-price escalation after applying the discounts offered by the developers. Details
8Larsen & Toubro has allotted Rs 500 crore of tokenised non-convertible debentures on NSDL’s distributed-ledger platform, pairing a conventional three-year corporate bond with settlement through a central bank digital currency wallet. Details
8The southern region met a 54,951 MW peak on 9 September but recorded a 3,827 MW shortage while 12,808 MW of central- and state-sector generation was unavailable. Details
8Two 400 kV JSW Mahanadi–Champa circuits have remained on an Emergency Restoration System for more than three months, with seven later incidents and a 600 MW unit tripping during each line trip. Details
8Suratgarh Super Thermal Power Station’s August return records average particulate matter above the applicable norm at all six 250 MW units, alongside specific water consumption of 5.678 cubic metres per MWh against a 3.5 norm. Details
8The Appellate Tribunal for Electricity has extended the scheduled commissioning date of ACME Kudligi Solar Energy’s 20 MW Karnataka project to its actual commissioning on 30 May 2020, holding that delayed availability of KPTCL’s Kudligi substation was a force-majeure event attributable neither to the developer nor its project. Details
8Western grid operators linked an average 5,424 MW of partial thermal outages mainly to wet or poor coal and coal-feeding constraints, while the committee agenda recorded another 1,260 MW in long forced outages during a period of national evening demand as high as 243 GW. Details
8Japan Halves Ammonia Subsidy as Co-Firing Economics Deteriorate
8Australia’s Free Midday Power Could Save EV Households AUD 731–2,257 a Year
8South Korea Targets 55 GW Offshore Wind After Building Only 365 MW in a Decade Details
8Only 1,605 MW Hydro Scheme Remains Under CEA Examination Details
8NCL Doubles Rail Loading as Monsoon Constraints Ease
8IEA Sees India Coal Demand Rising 4.2% to 1.353 Billion Tonnes in 2026
8Sixty-One Coal Plants Fall Below One-Quarter of Normative Stock Details
8Noida Power Seeks Five Blocks From 25 MW Round-the-Clock to 75 MW Evening Supply
8India’s Solar Output Hits 85,012 MW Record, Then Demand Peaks Later
8Chhattisgarh Keeps Discom-Led Surplus Sales After 43-Paise Cost Warning
8IEX Real-Time Power Costs 58% More Than Day-Ahead Energy
8CEA Lists 6,352 MW of Hydro as Dropped or Likely to Be Dropped
8Forced Maintenance Removes 34.19 GW from Monitored Generation Fleet
8Grid Frequency Sits Outside IEGC Band for 26.4% of 9 September
8Ancillary Services Deliver 51,017 MWh Up and 29,347 MWh Down
8HP-DAM Clears Only 38 MWh at Rs 20 per Unit
8Day-Ahead Price Falls to Rs 5.186 per Unit as Volume Declines
8NLDC Lists Below-Minimum Schedules at Energy Charges of Rs 2.114–5.613 per Unit
8Bina–Guna line stays out after six unsuccessful charging attempts
8Battery-charger restoration trips four transformers and cuts 300 MW at Kharadpada
8Mumbai’s islanding control faces an 18-month nuclear link and a 24-month SCADA cycle
8WRPC reports 158 MW of unused thermal backdown in Chhattisgarh after two years of discussion
8Western reserve account records Rs 23.26 crore due in shortfall service, then reverses under emergency dispatch
8Northern deviation ledger records Rs 100.24 crore receivable against Rs 64.37 crore payable
8Eastern SCED account records a net Rs 27.14 crore due to generators for August
8ERPC revision puts 30,371.18 MWh against WBSEDCL bilateral schedule
8Punjab owes Rs 46.97 lakh as Uttar Pradesh is due Rs 28.25 lakh in reactive account
8Northern SRAS ledger records Rs 63.44 lakh due to NTPC as some stations show zero daily performance
8ERPC reopens June regional accounting after revised schedule files
8JP Nigrie completes AGC closed-loop tests at 1% a minute
8Lakadia records two incorrect switching operations in one night
8Nine special-energy meters remain pending for replacement or repair
8WRPC asks generators to justify conservative frequency-trip settings Details
8APAR’s Rs 2,500 Crore QIP Drives Rating Upgrade, but Rs 8,520 Crore Working Capital Persists
8Kalpataru Backs Swedish Unit’s Rs 2,324 Crore IPO Valuation
8Adani Power Presents 23.72 GW Locked-In Capacity Against 18.33 GW Operating Base
8Siemens Rail Automation Merger Clears Shareholder-Meeting Stage
8GE Vernova T&D Places Rs 10 Dividend Before Shareholders
8Schneider Faces Rs 3.52 Crore GST Demands Plus Interest and Rs 35.18 Lakh Penalty
8Orient Green Gets BBB Ratings Across Rs 595 Crore of Subsidiary Facilities
8JSW Energy Retains AA; Stable Ratings and Adds Proposed Debt Capacity
8Onix Solar Investor Cuts Holding to 4.08% From 7.67%
8NHPC Receives Independent ESG Score of 48
8Vedanta Links Rs 21,000 Crore Metals Spend to EV Supply Chain
8Siemens Energy India Brokerage Forecasts Capacity-Led Growth at a High Valuation
8Southern grid lists 22 generating units without completed PSS tuning evidence Details
8Power Mech Wins Rs 970 Crore Vedanta O&M Order, With Rs 80 Crore Conditional Work
8Enviro Infra Gets Rs 224.19 Crore Wind EPC Mandate on a March 2027 Clock
8L&T Wins ONGC Offshore Package for Four Platforms and Subsea Works
8REC Transfers Musalgaon Transmission SPV to Maharashtra Utility for Rs 20.90 Lakh
8SECI Seeks Two Delhi Farms for 27-Year Agri-PV Leases
8TGTRANSCO Extends Tender for 116 Surge Monitors to 18 September
8TGTRANSCO Plans Lift Around a 25-Year-Old Building
8UPNEDA moves three government-building solar tenders by one week
8Khargone Unit 2 seeks January overhaul after critical spares miss approved window Details
8APTEL Sends Rs 82.58 Crore Force-Majeure Claim to Full Bench
8APTEL Upholds Rs 58.71 Crore Completion Cost for Vallur Transmission Line
8Himachal Regulator Reserves Orders on Four Small Solar PPAs
8PSPCL Warns Court Non-Appearance Will Trigger Disciplinary Action
8Kerala Corrects Efficiency Formula in Draft MYT Regulations
8UGVCL Raises Base FPPAS to Rs 2.45 per Unit and Adds 3.99% Variable Charge Details
 For reference purposes the website carries here the following tenders:
 8Tender for supply of aluminum bronze and MS flats required Details
 8Tender for supply of gate valve PN64 for bypass lines Details
 8Tender for supply of hydraulic tools torque wrenches, hydraulic pump and bolt tensioner Details
 8Tender for supply of fasteners for the turbine assembly Details
 8Tender for procurement of PLC system spares for stacker and reclaimer Details
 8Tender for replacement of CLR polymer insulators Details
 8Tender for supply of GI nuts and bolts with washer Details
 8Tender for construction of impervious liner in ash dyke Details
 8Tender for construction of rainwater harvesting facility Details
 8Tender for biennial civil maintenance and misc works of plant Details
 8Tender for sheeting and miscellaneous civil work for existing shed Details
 8Tender for award of contract for system strengthening works for survey installation testing and commissioning of new 5MVA 33 /11kV substation Details
 8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details
 8Tender for complete engineering, design, supply, erection, commissioning and testing of Variable frequency drive VFD system Details
 8Tender for procurement of 220V DC RXM relay, opening and closing buffer and limit switch for MV switchgear Details
 8Tender for annual operation of 02 Nos tube well pumps and water supply including watch and ward of pumps Details
 8Tender for operation of control room of beehar barrage including watching and recording of water level Details
 8Tender for supplying and installation of 100 MT fully electronic modular welded design type pit less weighbridge Details
 8Tender for procurement of various spares for SWAS system Details
 8Tender for strengthening of the existing plate and pipe earthing Details
 8Design, manufacture, testing, supply installation and commissioning of 33/11 kV containerized substation comprising of 33 kV RMU, 11kV AIS including supply of cable termination kits Details
 8Tender for fabrication and supply of galvanised steel yard structures for substations Details
 8Tender for RMU associated UG cable Details
 8Tender for supply of MCCB for 160 Amp and 200Amp suitable for LTDB Details
 8Tender for construction of internal grid roads at 220 kV substations Details
 8Tender for contract for fishing of pond Details
 8Tender for procurement of 200KVA station transformer Details
 8Tender for work of replacement of deteriorated H-frame and mechanical strengthening and stub strengthening work of 66kV line Details
 8Tender for providing RCC pavement in HPS switchyard Details
 8Tender for supply of mill internal spares Details
 8Tender for supply, installation and commissioning of FRP street light poles Details
 8Tender for rate contract for retrofitting and strengthening of machine foundations Details
 8Tender for supply of heat shrinkable type straight joint kits suitable for 11kV, 3 x 300 sqmm cable Details
 8Tender for procurement of 1000 Nos tapping channel cross arm Details
 8Tender for supply of outer and inner sleeve for LT 4x240sq.mm cable. Details
 8Tender for supply of 11kV polymer composite PIN insulator Details
 8Tender for supply of 11 kV standalone complete set of structure materials Details
 8Tender for supply of 11kV polymer composite DISC insulator Details
 8Tender for earth work excavation, stub setting, concreting, supply, transport and erection of 110 kV DC line on DC tower Details
 8Tender for rectification replacement of defective tubes in LTSH coils economizer hanger Details
 8Tender for rectification replacement of defective rear arch goose neck bends tubes and water wall reducer tubes and allied works Details
 8Tender for providing transformer plinth, structural plinths, cable duct, fire protection wall & AH , VC , WC tower arrangements Details
 8Tender for manufacture and supply of 7/2.5 mm GI stranded wire Details
 8Tender for repairing of dam site internal road from dam control room along power channel Details
 8Tender for fabrication, supply and erection of 415V AC, 50KA, LT AC panel Details
 8Tender for work of replacement of existing 0.2 ACSR panther conductor along Details
 8Tender for work of providing & fixing of maintenance free earthing and renovation of existing earthing system Details
 8Tender for miscellaneous fabrication and steel work in various Details
 8Design, engineering, supply, erection, testing, commissioning of 20 KWp rooftop solar PV power project Details
 8Tender for supply of 110HP ATS (2+1 MCC) control starter panel Details
 8Tender for Bi-nnual rate contract for erection of 66kV transmission lines Details
 8Tender for conversion of exist. 66kV S/C H-frame line to S/C panther line Details
 8Design, supply, installation, retrofitting, testing and commissioning of 220kV bus bar panel/scheme, 220 kV bus coupler relay Details
 8Tender for supply of dry calcium carbonate powder Details
 8Tender for supply of contactors Details
 8Tender for miscellaneous civil works Details
 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metal-clad draw-out type VCB panels Details
 8Tender for procurement of different hardware for 132kV and 220kV transmission lines Details
 8Tender for work of capacity enhancement of 132kV bus from single moose to twin moose Details
 8Tender for providing and replacement of insulator string and other accessories at 132kV lines Details
 8Tender for annual routine maintenance preventive and breakdown of 220kV lines Details
 8Tender for annual maintenance contract preventive of 220kV and 132kV transmission lines Details
 8Tender for special repair and maintenance of project Details
 8Tender for procurement of complete pulley assembly Details
 8Tender for common procurement of HT fasteners nut, bolt and washers Details
 8Tender for biennial contract for repairing and maintenance of sanitary and plumbing works in and around plant Details
 8Tender for service contract for round the clock operation of BOBR rakes unloading and paddle feeder operation job Details
 8Tender for biennial mechanical maintenance contract of coal handling plant Details
 8Tender for procurement of 11 Nos. 420kV and 05 Nos. 245kV capacitive voltage transformer Details
 8Tender for OH of air/flue gas duct, expansion joint Details
 8Tender for repair and maintenance of the flume line along with other associated civil works Details
 8Tender for diversion of 11kV feeder Details
 8Tender for supply of rubber item & consumable items for ash handling plant Details
 8Tender for supply of various protective shields, guide pipes Details
 8Tender for work of cleaning of bus ducts/MCCs, actuator overhauling, and cable dressing works Details
 8Tender for various civil maintenance work of switchyard & other allied civil works Details
 8Tender for annual maintenance contract (AMC) for work of overhauling / servicing & alignment of various make 220kV, 132kV & 33kV isolators installed Details
 8Tender for augmentation of substation by providing of 1X25 MVA 132/33kV T/F along with HV&LV bays Details
 8Tender for work of augmentation of substation by addition of 25MVA, 132/33kV power transformer along Details
 8Tender for supply of various types of cable & dismantling, ETC work of 36 kV circuit breakers at various S/Stns Details
 8Tender for work of radiator cleaning of convertor transformer & smoothing reactor Details
 8Tender for biennial maintenance contract for the work of replacement of failed / sick substation equipments Details
 8Tender for work of replacement of old earthing pipeline and sanitary related maintenance works of Qtr and CR at 132kV S/Stn Details
 8Tender for work of servicing / overhauling of operating mechanism of 245kV kV& 400kV SF6 circuit breakers Details
 8Tender for supply of spares & complete mechanism overhauling of 132kV circuit breakers at 132kV S/s Details
 8Tender for work of providing & fixing of sheet moulding compound (SMC) chequered sheet cable trench covers for indoor application Details
 8Tender for work of health assessment of grounding system and soil resistivity measurement (earthing audit) of existing earth mat at various S/Stns Details
 8Tender for work of supply, erection, testing commissioning of an additional 1X 25MVA 132/33kV power transformer along Details
 8Tender for work of supply, erection testing and commissioning of additional 132/33 kV, 50 MVA power T/F along with HV, LV bay & 33kV bus extension Details
 8Tender for work of servicing, repairing & overhauling of ABB make 245kV & 145 kV circuit breakers Details
 8Tender for work of supply of 22/33 kV circuit breaker Details
 8Tender for augmentation of substation by providing additional 1X50 MVA 132/33 PTF along with HV& LV bays Details
 8Tender for augmentation of transformation capacity by additional transformer 132/33 kV, 1 X 50 MVA at 132kV S/stn Details
 8Tender for dismantling old RCC concrete structure & erection of EHV equipments on new lattice type GI structure at 220kV substation Details
 8Tender for supply, erection & commissioning of 10 MVA, 66/11 kV step down transformer at switchyard Details
 8Tender for supply, installation & commissioning of automated chlorine dioxide (ClO2) generation system Details
 8Tender for supply of various consumable items required for routine maintenance/AOH Details
 8Tender for providing waterproofing treatment on terrace Details
 8Tender for providing and fixing PVC water tank Details
 8Tender for dismantling of existing rail table assembly and erection, alignment, testing & commissioning of new rail table assembly of wagon tippler Details
 8Tender for erection and maintenance of HT/LT/TC work Details
 8Tender for providing & laying underground cabling & jointing work Details
 8Tender for conversion of existing 11kV bar conductor line Details
 8Tender for BRC for work of rewinding and overhauling of 11kV HT motors Details
 8Tender for supply of various insulation materials for boiler Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India Has the Sun, But Where Is Its Concentrated Solar Industry Details
 
8Geothermal Energy: A New Chapter In India’s Clean Energy Journey Details
 
8Enviro Infra Ltd secures 190 INR-Crore wind power project order from Tata Power Details
 
8REIL Invites Bids For 15 MWp Rooftop Solar Projects Under RESCO Model Details
 
8Gains for power stocks depend on execution, valuations Details
 
8India’s power demand hits record August high as heat and weak monsoon stretch grid Details
 
8CRISIL: Power Sector Investments to Drive 100–200 bps Revenue Growth for Large EPC Companies to 9–10% Details
 
8India's Rs 9,150b power grid push could drive new aluminium demand Details
 
8Mahatransco IPO Takes Shape as Maharashtra Power Utility Eyes Rs.10,000-Crore Share Sale Details
 
8Nepal floods halt contentious hydropower exports to Bangladesh via India Details
 
8ISMA Conference 2026: Sugar industry eyes green hydrogen, SAF and CBG to power India’s energy security Details
 
8Solis Marks India Milestone with First EverCore 1.04 MWh Energy Storage Deployment in Chennai Details
 
8Geothermal Energy: India’s quiet bet on a new renewable asset class Details
 
8Windergy India 2026 to Spotlight India’s Wind Manufacturing and Export Potential Details
 
8Renewable Energy Funding and M&A Roundup: Key Global Trends Details
 
8Northern Coalfields improves operational performance with retreating rains Details
 
8ICRA: Cement Companies to Expand Green Power Capacity to 6 GW by FY2028 Details
 
8Coal India output jumps 40% as rains ease; power-sector supplies rise 27% Details
 
8CIL Accelerates Coal Output as Monsoon Eases, Power Sector Dispatch Jumps 24% Details
 
8India Power Demand Hits 260 GW, Strains Coal Supply Details
 
8India Launches Rs 2 Crore Solar Heat Scheme to Cut Industrial Fossil Fuel Use Details
 
8Cement majors line up Rs 13,000 crore green power push; capacity to rise 50% by FY28 Details
 
8Cummins India to showcase integrated power solutions at bauma CONEXPO India 2026 Details
 
8Power Finance Corporation appoints joint statutory auditors for FY 2026-27 Details
 
8SECI Aggregates MSME Power Demand to Cut Renewable Costs Details
 
8Power Mech Bags Rs 970 Crore O&M Order From Vedanta Power's Sakti Thermal Plant Details
 
8DEE Development Engineers reports a total order execution of Rs 87.37 crores for August 2026 Details
 
You can also click on Newsclips for more Details
NHPC's Rs 496.90 crore Dulhasti Stage-II E&M package gains a full crane chapter and loses half a point of turbine efficiency
8A post-publication corrigendum inserted four EOT crane installations with tandem rotor lifting and an obligation to raise capacity without extra cost, while the responsiveness threshold fell from 94.5% to 94%.
8Four closing-date extensions have stretched the bid window without touching the 38-month execution clock, leaving the question of whether relaxed efficiency can offset unpriced interface quantities.

NTPC Renewable's 600 MW Anantapur wind tender gives bidders a week more to price but no way to ask why
8Corrigendum No. 1 pushed submission to 22 September 2026 while leaving the 1 September query deadline untouched, so late-discovered ambiguity has nowhere formal to go.
8With Rs 50 crore bid security, ten-year comprehensive O&M and roads, pooling and evacuation all outside the WTG package, the unresolved issue is who carries commissioning delay at the boundary.

 

JdVVNL rewrites the BOQ a third time and swaps Bikaner territories between two RDSS packages
8Corrigendum 3 moved Dungargarh and Nokha into TNTW-796 while DD-I, DD-II and Khajuwala travelled the other way, settling the value at Rs 119.89 crore — a net movement of about 0.1%.
8That small headline change can conceal much larger line-item additions and deletions, which is precisely what bidders repeatedly queried before the revision.

 

AEGCL's Khumtai 400kV GIS tender carries a Rs 50 lakh EMD contradiction and a 12-month schedule gap
8The invitation and ITB 2.37.1 set two years for completion while SCC 8.2 requires 36 months, and the EMD reads Rs 5.5 crore in numerals against "Rupees Five Crore only" in words.
8Turnover and financial-resource thresholds carry the same numeral-versus-wording conflict, making eligibility itself uncertain before the 12 October closing.

 

GETCO's Viksit Gujarat @2047 adviser tender records two turnover thresholds twenty times apart
8The GeM page states Rs 48 crore while the RFP and buyer-added conditions demand Rs 1,000 crore, and submission and opening dates differ by a day between portal and document.
8With GST treatment also contradicted between two clauses, the tender risks producing technically incomparable bids priced on different assumptions.

 

GETCO's Rs 210.62 crore Bharuch cable package lets each approved OEM back only one bid
8Amendment-I restructured qualification into OEM, nominated-OEM and two-member JV routes, then barred any firm from appearing in different roles across competing bids.
8The contest may therefore be settled by early OEM alignment rather than by how many erection contractors can qualify.

 

KPTCL's Rs 131.92 crore Byadagi package reaches the market tagged as a computer lab
8The portal lists bid validity as 90 days against the signed document's 180, describes the scope as "Setting up of Computer Lab", and keeps the clarification window open 30 minutes after bids close.
8A Clause 3.2(e) heading referring to a 100 MVA transformer against a 160 MVA requirement compounds the risk of divergent qualification readings.

 

RRVUN cuts the coal experience bar by 6.25% and then quietly extends group credentials to technical qualification
8Amendment-I lowered the single-contract threshold from 1 million MT to 9,37,500 MT and admitted IPP supplies; Corrigendum-I then widened 100%-owned parent or subsidiary reliance from financial to both technical and financial PQR.
8JV and consortium participation stays barred, so the widening favours tightly held corporate groups rather than assembled bidding alliances.

 

WBSETCL's Sadarghat composite package republishes its evaluation clause with a broken cross-reference
8Amended ITB 28.2 now reads "DP = Differential price calculated according to0", severing the link to the calculation method in ITB 28.4, while the reverse-auction cross-reference disappears entirely.
8Reverse-auction clause 9 separately dispenses with additional security where L1 is "less than 20% of the estimated cost" — a literal reading that relaxes protection at the lowest prices.

 

NHPC raises generator efficiency loading 20.6% on the Rs 641.11 crore Uri-I Stage-II package
8The turbine equalisation rate moved from Rs 8.32 lakh to Rs 8.74 lakh per 0.1 percentage point, while the generator rate jumped from Rs 21.64 lakh to Rs 26.10 lakh.
8Cheaper machines with weaker guarantees can now lose their price advantage at evaluation, even before PLCC relocation and revised cooling-water scope are priced.

 

WBSETCL's 68 km Salboni 400 kV line tender resolves a 60 mm creepage conflict but keeps ROW with the contractor
8The pre-bid response directed bidders to the technical specification's 430 mm over the BOQ's 370 mm and issued a revised BOQ, while fixing conductor diameter at 28.62 mm and sag at 15.93 m.
8Tower-footing compensation, trees, crops and access remain contractor-priced with no escalation for court-driven delay, and the 24-month clock survives two extensions.

 

RRECL's 201 MW solar tender slips 63 days and then adds a letter of credit
8Four corrigenda moved submission from 14 July to 15 September 2026 while the nine-month commissioning obligation and 25-year term stayed fixed.
8The pre-bid addendum inserted a revolving monthly LC and replaced the client's first charge over liquidated assets with priority application of proceeds — a lender accommodation whose value depends on the still-ambiguous "Cover-1 & Cover-2" opening language.

 

HPSEBL extends its Rs 3.72 crore Kinnaur-Spiti PMC tender for the fifth time without explaining why
8Corrigenda I to V added 64 calendar days to both submission and technical opening while leaving scope, staffing, securities and the 246 man-month deployment untouched.
8The unresolved question is award mechanics: a 70:30 QCBS formula and an English e-reverse auction sit in the same document with no stated hierarchy.

 

GETCO shifts LD on the Rs 224.80 crore Dholera-II GIS package from the delayed portion to the whole contract
8SCC clause 41 now calculates 0.5% per week on the full contract price capped at 10%, recoverable across GUVNL group contracts, while requests to extend 30 months to 34 and to substitute PEB for RCC were refused.
8A local civil or commissioning slip can now generate package-wide exposure on a site carrying saline conditions, seismic zone 5 and cast-in-situ piling.

 

MePDCL splits Khasi Hills into six lots and hands four of them to one contractor
8The Rs 120.42 crore award concentrates Rs 82.12 crore, or 68.2% of L1 value, with a single firm across Lots 1, 3, 5 and 6.
8Lot 3 reached financial opening with one responsive bidder out of seven, leaving no L2 comparator to test whether that price was competitive at all.

 

NHPC rewrites force majeure and idling-cost recovery across both its hydro E&M packages
8The revised GCC Clause 37 adds terrorism, qualifying strikes and pandemic spread while removing the magnitude-7 earthquake threshold and express treatment of bandhs, lightning and unprecedented floods.
8Annex-A now caps compensable idling through a formula using 5% of composite contract price, with a 2% sub-cap on miscellaneous establishment expenditure and extended-warranty recovery at 2.25% per annum.

 

RVUN's Rs 1,125 crore coal tender is tagged emergency procurement without naming which rule applies
8The portal cites Rule 40(1), 43(6) or 43(7) but does not identify the provision invoked or the factual justification, and the original window ran just seven days from publication to submission.
8Coal grade, sampling agency, delivery duration, LD framework and PBG terms are absent from the published notice, leaving the commercial risk difficult to quantify before bidding.

 

WBSETCL's H1-elimination auction meets a 10% security stack that runs five years past commissioning
8The Sadarghat package removes the highest offer only where four valid price bids exist, so two or three qualified bidders all proceed to the auction intact.
8The winner must then carry separate 10% guarantees on GIS equipment for three years and transformers for five from the Taking-Over Certificate, with formal joint ventures barred.

Details
8India met the day’s solar-assisted peak, but the non-solar peak still showed a 4,965 MW shortage, exposing the different system challenge after sunlight fades. Details
8The NCLT rejected an insolvency petition against EKI Energy after finding a pre-existing carbon-credit pricing and payment dispute; the ruling does not decide the underlying commercial claim. Details
8The daily weighted price stayed far below Rs 10 even though 64 of 96 settlement blocks cleared at that level, revealing a sharp concentration of lower-priced volume in the remaining hours. Details
8NLC’s operating cash generation fell sharply while capital spending exceeded it and group borrowings rose above Rs 27,800 crore, sharpening the funding question behind its expansion programme. Details
8Solarworld wants to redirect Rs 420 crore of unused IPO proceeds from a 1.2 GW cell plan into a 2.4 GW joint-venture project already under construction. Details
8Southern grid operators report renewable curtailment of about 3,900 MW around a heavily loaded corridor whose second circuit is expected only around the end of 2026. Details
8GVK Power’s creditors have rejected two restructuring plans and moved toward asset-wise sales against admitted financial claims of about Rs 15,945 crore. Details
8Coal-gasification support can cover 20% of eligible machinery cost, but milestone security and steep delay reductions make execution timing decisive for applicants.
8Force-majeure periods are excluded from the delay clock. Details
8A tribunal bench has questioned whether force-majeure relief includes money and referred the issue for an authoritative ruling, leaving an Rs 82.58 crore transmission claim unresolved. Details
8NLC’s auditor has identified inadequate mining land as a material uncertainty over the Neyveli operation’s ability to continue, while management says contingency mining can sustain output at additional cost. Details
8Empower profit rises to Rs 18 crore as operating cash turns negative
8Empower seeks five-year auditor appointment after reporting lapses
8Empower’s standalone and group audits give conflicting accounts of edit logs
8XL Energy’s Rs 3.08 crore loss adds to unresolved debt accounting
8XL Energy’s share restructuring awaits exchange action as relisting appeal continues
8XL Energy records governance gaps beyond its transition window
8XL Energy seeks corrective director vote and approval for new manager
8NHPC names three joint auditors for FY27
8POWERGRID appoints four joint statutory auditors for FY27
8IRCON appoints Vinod Singhal & Co LLP for FY27 audit
8BHEL adds S Venkatram as auditor for Ranipet and southern power sector
8Alaknanda's full-year profit rose to Rs 285 crore, GVK report says
8Alaknanda's Rs 30 crore interest dispute with BHEL remains in appeal
8GVK's Rs 1,383 crore loss follows loss of control over its energy subsidiary
8Alaknanda issued Rs 2,031 crore of debentures before prepaying its term loan
8Gautami lenders received Rs 200 crore against Rs 2,760 crore of claims
8GVK reports water-tax relief for Alaknanda, with refund proceeds subject to pass-through
8Ratle's Rs 290 crore arbitration receivable remains tied to lender settlement
8GVK carries Rs 117 crore of SEZ land while title-document dispute remains unresolved
8GVK auditor flags financial-asset test; company disputes need for NBFC registration
8GVK discloses gaps in accounting audit trails
8GVK seeks three more years for unpaid whole-time director
8GVK proposes five-year renewal for T R Chadha as statutory auditor
8GVK Coal (Tokisud) Company Private Limited entered insolvency in May, annual report says
8Empower reports April change in managing director and finance chief
8Empower auditor lists Rs 6.04 crore in tax disputes despite nil income-tax contingency note
8Alaknanda report retains Rs 131 crore royalty dispute under pending review
8Alaknanda tariff disclosure shows competing appeals over capacity-cost recovery Details
8Solarworld carries Rs51.51 crore SJVN receivables as Rs219.34 crore claim awaits adjudication
8Solarworld's module business reports Rs15.21 crore segment loss in its first revenue year
8Znshine bank statements show creditor differences as Solarworld discloses audit-trail limits
8Coal-gasification support combines product caps with a ranked allocation contest
8Coal-gasification applicants face security and recovery conditions beyond selection Details
8Zelio seeks three separate Rs1,000 crore financial authorities
8Zelio puts Arya leadership and remuneration proposals before shareholders
8Zelio proposes five-year renewal of Jagsir Singh as secretarial auditor
8RMC wins Rs14.99 crore Maharashtra solar-pump allocation
8Siemens names Aditya Ramkrishna to lead Digital Industries from October1
8Amara Raja schedules Tata Mutual Fund management meeting for September11
8Taylormade proposes five-year renewal for CMD Dharmendra Gor
8Taylormade proposes Surana and Kothari for five-year secretarial-audit term
8Taylormade board recommends no FY2025–26 dividend
8Orient Electric schedules Axis Capital investor conference participation
8Kirloskar Electric relieves HR vice-president Sukanya Reddy after resignation
8KP Energy wins Emmvee captive-hybrid LOI for Karnataka
8CG Power secures conditional stay on disputed tax demand
8CAG appoints SCV & Co as Engineers India auditor for FY2026–27
8CESC incorporates two renewable-power companies with Rs1 lakh capital each
8NIRL receives 200 MW award under SJVN wind selection
8NLC sets September22 shareholder deadline ahead of final-dividend vote
8CAG appoints five firms to NTPC's FY2026–27 audit
8CAG names G S Mathur and S K Mehta as REC statutory auditors
8LIC crosses 5% REC holding after market purchase
8Suzlon wins Ayana wind EPC order in Madhya Pradesh
8Torrent commissions 322 MWp of Nashik agricultural-feeder solar
8GE Power India receives Odisha GST demand and considers appeal Details
8Solarworld seeks fivefold rise in borrowing authority to Rs5,000 crore
8Solarworld puts Rs65,000 cost-audit fee to shareholder ratification
8Solarworld seeks Mangal Chand Teltia reappointment at September AGM
8NLC signs NPCIL nuclear-development MoU and prepares PHWR feasibility
8NLC-Rajasthan venture develops 375 MW lignite project through feasibility packages
8NIRL-Assam venture identifies sites for 1 GW green-energy programme
8NIRL-Rajasthan venture receives land parcels for 2 GW programme
8NIRL and PTC sign agreement for 500 MW first-phase renewable venture
8NIRL-MAHAPREIT green-energy agreement awaits venture formation
8NLC signs Indian Oil MoU for Tamil Nadu renewable joint venture
8NLC and CSIR-CECRI agree critical-mineral extraction collaboration
8NLC signs TEXMiN memorandum for critical-mineral exploration research
8NLC and IREL agree cooperation on critical-mineral assets
8NLC and KABIL sign global critical-mineral project agreement
8NLC agrees proof-of-concept carbon-capture work with IIT Madras
8NIRL secures SECI solar-plus-storage award
8NIRL receives 600 MW Bundelkhand solar award
8NIRL records August SECI award for 200 MW wind
8NIRL wins 900 MW Gujarat solar award with GUVNL offtake Details
8NLC 03 - CTUIL revocation leaves NLC's 200 MW Gujarat solar project waiting for connectivity and land
8NLC 04 - Boiler technology tie-up becomes the immediate hurdle for NLC's 1,000 MW Neyveli expansion
8NLC 05 - Ghatampur's third unit enters service as another cost revision awaits government approval
8NLC 06 - NUPPL's BGR support exposure grows as risk-and-cost advances receive full provisions
8NLC 07 - Pachwara begins coal production, but Ghatampur still needs bridge supply through ramp-up
8NLC 08 - Talabira'sRs 27,213 crore power project shows a wide gap between financial and physical progress
8NLC 09 - NLC pays SECI under hybrid scheme while solar land and wind works lag
8NLC 10 - NIRL's 1,430 MW transfer is complete in accounts, with title and contract handovers still pending
8NLC 11 - Renewable spending surges while NLC's segment result falls 15%
8NLC 12 - NLC's 39% profit increase rests on a much smaller tax charge and regulatory movements
8NLC 13 - Talabira mining-charge dispute carriesRs 463.53 crore provision
8NLC 14 - NLC's inventory audit gap covers aRs 1,612 crore standalone stock balance
8NLC 15 - Bithnok and Barsingsar revival talks leave old capital and contractor claims unresolved
8NLC 16 - NLC recordsRs 379 crore mineral-land-tax recovery through lignite energy charges
8NLC 17 - NLC releasesRs 417.63 crore TPS-I interest liability while TANGEDCO appeal remains pending
8NLC 18 - TPS-II tariff remand yieldsRs 128.41 crore liability reversal and fresh interest accrual
8NLC 19 - Kerala linked-mine tax case addsRs 85.06 crore interest to NLC's income
8NLC 20 - Inclusion of Mine-II Expansion in pooled lignite pricing producesRs 166.98 crore interest income
8NLC 21 - NLC retainsRs 411.57 crore liability as discom tax-recovery disputes move to CERC
8NLC 22 - Barsingsar moves to lower petitioned fuel price and reversesRs 30.79 crore provision after credits
8NLC 23 - NLC carriesRs 500 crore of O&M and special-cost tariff assets awaiting recovery
8NLC 24 - NLC's ageing thermal fleet records weaker availability even after a unit modification
8NLC 25 - Surrendered power rises as NLC's exchange sales recover only a fraction of unused supply
8NLC 26 - NLC faces nearly 4,950 retirements over five years as recruitment and regularisation continue
8NLC 27 - NLC's board-composition gaps leaveRs 59.59 lakh of exchange fines unpaid
8NLC 28 - Three worker fatalities keep NLC's safety improvements under scrutiny
8NLC 29 - NLC's absolute emissions rise 5% while revenue-based intensity improves
8NLC 30 - Tamil Nadu storage project moves into EPC execution under a 12-year service agreement
8NLC 31 - NLC's Odisha renewable JV plan combines wind and pumped storage under a 1 GW programme
8NLC 32 - NLC's coal pipeline moves into MDO procurement, with mine clearances still decisive
8NLC 33 - NLC advances phosphate and critical-mineral blocks into exploration work
8NLC 34 - NLC's overburden-to-sand programme gains a 1 million-tonne plant and state disposal permission
8NLC 35 - NLC's decommissioned TPS-I sale deliversRs 89.34 crore annual profit as dismantling proceeds in stages
8NLC 36 - NTPL seeks dividend exemption after payout falls below the stated minimum
8NLC 37 - NLC and NALCO sign 1,080 MW captive-power venture agreement for smelter expansion
8NLC 38 - NCRTC captive-solar venture reaches land identification and balance-of-system tender
8NLC 39 - NLC's green-hydrogen pilot moves through EPC execution before production can be tested
8NLC 40 - NLC targets 2027 rare-earth pilot using lignite fly ash
8NLC 41 - Barsingsar solar starts billing atRs 2.45 while GST-change claim takes a separate route
8NLC 42 - Khavda and Pugal solar projects face different equipment milestones before commissioning
8NLC 43 - NLC's 450 MW NTPC hybrid award still awaits its long-term PPA
8NLC 44 - NIRL places 200 MW wind EPC order with Inox after SJVN award Details
8Singla Forging gets protection from coercive furnace-charge recovery
8Shri Krishna Forgings wins interim protection in furnace-charge case
8HPERC gives P&G two more weeks in renewable-obligation verification
8Pathania’s 250 kW solar PPA petition listed for consideration
8DVC seeks November thermal, hydro and non-solar supply through auctions
8PXIL circular limits liability to affected fees or Rs 10 lakh
8PSPCL seeks reconciliation of Rs 19.47 crore in connection collections
8PSPCL calls for August processing-fee reconciliation
8PSPCL schedules pay-arrears audit across three divisions
8PSPCL assigns faculty for smart-metering and loss-reduction training
8PSPCL nominates 65 staff for September SBS training
8Guna completes ten substations and approves 61 further network works
8Guna reports Rs 85.77 lakh in daytime smart-meter rebates
8September Lok Adalat offers conditional relief on electricity assessments
8PVVNL schedules September 9 shutdowns for network works
8The Lodhi expansion deferred with higher solar-capacity requirement
8ISIC expansion needs fuller solar and backup-power submissions
8Nagaland House redevelopment held for solar and backup details
8Maharashtra agenda lists transfer of 40 MW cogeneration clearance
8SECI reiterates mandatory site certificate for NIWE rooftop bid Details
8IMP Powers restarts transformer production as net working capital remains negative
8TGGENCO reservoir energy potential falls 58% as Nagarjunasagar drops 74%
8CEA reports all-India August coincident peak fully met while Uttarakhand missed 13.2% of its peak
8Solarworld builds a Rs 2,813 crore order book while adding module and storage manufacturing capacity
8East–West settlement accounts for 96% of Eastern Region deviation-settlement receivables
8POWERGRID’s Rs 8 crore Dynamic Line Rating pilot faces Rs 4.6 crore pre-GST relocation quote

STATE REGULATOR NEWS

8KSERC opens consultation on 2026 multi-year tariff regulations for 29–30 September

GRID AND MARKET DEVELOPMENTS

8POWERGRID expects August 2028 operation for Udumalpet–Madurai upgrade amid continuous single-contingency violations
8SRPC considers Yelahanka gas plant for voltage support around Bengaluru
8Southern states split over new reserve shut-down option for thermal units
8Adani transmission arm seeks early commercial operation to recover charges before prerequisite elements finish
8POWERGRID proposes joint refurbishment of both 500 MW Vizag HVDC poles
8NLCIL says Thermal Power Station II units may shut below 50% of maximum continuous rating Details
8Emergency reserve dispatch gives Eastern pool a Rs7.04crore net receivable
8Eastern SCUC pays out Rs73.30lakh despite more downward than upward scheduling
8SRAS incentives almost offset Eastern generators' energy refunds Details
8Three Pothencode insulator failures trigger a root-cause and condition review
8Pothencode protection scheme awaits end-to-end test evidence after entering service
8Southern underfrequency shedding plan rises to 15,875 MW with implementation still under discussion
8July frequency event prompts checks for premature underfrequency relay operation
8Southern grid review flags a possible 3,000 MW export-capability loss during high renewable output
8BHAVINI startup network arrangements return for clarification after temporary line charging
8Staggered irrigation supply cuts Andhra Pradesh evening peak by about 400 MW
8Talcher–Kolar spare-transformer list includes three units still requiring deployment or repair
8JSWEL compensator purchase moves toward order with delivery expected around year-end
8Tamil Nadu's 528 MVAr capacitor plan awaits revised-cost approval before retender
8Neyveli transformer works require a retender after bidder fails qualification
8Puducherry's 35 MW battery project awaits administrative approval before award
8Ariyalur–North Chennai line faces an all-insulator replacement proposal after decapping
8NHAI readiness pushes Janagaon–Julurupadu diversion from September to November
8Emergency restoration equipment remains below stated utility norms as orders run into 2027
8Tamil Nadu and Puducherry load despatch staffing stands well below stated norms
8Tamil Nadu's August deviations bring fresh follow-up after a 1,066-block overdrawal quarter
8Long-running reactor repairs remain tied to imported parts and approval decisions
8Ennore SEZ units carry August and October 2027 commissioning expectations
8Tamil Nadu plans an 800 MW Thoothukudi project using Uppur materials and Udangudi facilities
8Yermarus reactor proposal shifts toward tariff recovery after eight-year delay
8Edayarpalayam reactor package moves to retender after contract termination
8Automatic demand-management performance faces corrective review after months of inadequate response
8June black-start exercise count is zero as SRPC retains a December completion target
8Andhra Pradesh moves SAMAST toward internal funding while PSDF response remains pending
8Ramagundam stage-I AGC gap narrows to unit 1 after April implementation on units 2 and 3
8Tamil Nadu awards AGC tenders covering 1,800 MW at North Chennai-II and Mettur-II
8Sharavathi and Varahi AGC tests leave the commercial mechanism as the next decision
8PGCIL replacement proposal calls for studies on seven reactors and five transformers
8Kalpakka–Gazuwaka loading restrictions put clamps and jumpers under review
8Kasargode GIS commercial-operation timing remains linked to a right-of-way-delayed line
8Ennore expansion moves through approved bidding route without a recorded award Details
8MSETCL transmission availability certified at 90.20% for July
8Lakadia Vadodara July availability falls below its cumulative measure
8Mumbai Urga Marg July availability stands at 94.79%
8Raipur Pool Dhamtari records full July availability with cumulative figure still at 86.866%
8POWERGRID western AC availability certified at 99.71% for July
8Western DSM account shows Rs 343.09 crore payable to the eastern region
8Chhattisgarh and Maharashtra carry the largest state DSM payables in western account
8Maharashtra and Gadarwara lead reactive-account credits in the western region Details
8Ranganadi availability stands far below the hydro stations beside it in August account
8Subansiri account separates 81.16 million free units from saleable energy
8Kameng merchant allocation accounts for more than half its August schedule
8Agartala combined-cycle availability remains below 30% in August
8Assam gas station's load factor trails its availability in August
8Bongaigaon has high availability but 231,240 MWh of cumulative unrequisitioned entitlement
8Palatana August availability exceeds its cumulative level but remains below norm
8Assam imports bilaterally while recording net IEX sales in August account
8Meghalaya's temporary-access sales far exceed purchases in August schedule Details
8Southern region accounts for more than the net renewable scheduling shortfall
8Grid frequency stays outside the reported operating band for almost six hours
8Maheshwaram voltage exceeds 800 kV for more than a third of the day
8Bellary’s 700 MW unit trips while southern plants restore 3,080 MW
8All four Kadamparai units remain on forced outage in September operating record
8Tripura transfer corridor exceeds available capacity for 17.5 hours
8Bongaigaon and Balipara reactor replacements remain under shutdown
8Chuzachen’s 110 MW shuts on silt after earlier evacuation interruptions
8Eastern intraday demand forecast improves daily accuracy but misses evening ramp
8Nine gas plants show zero schedules in NLDC’s 9 September commitment table
8Kayamkulam’s reserve-shutdown units require 45 days’ fuel notice
8Selected southern transmission report records six restorations on 8 September
8Southern major reservoirs hold 35% less stored energy than a year earlier
8Koppal RenewOjas battery records 75 MW discharge peak in the evening
8Udangudi records 9.76 million units while still labelled infirm generation
8Kudankulam transformer awaits priority replacement of all three high-voltage bushings
8Northern reservoirs show a 21% reduction in reported stored energy
8Rajasthan corridor exceeds available transfer capability for 28.47% of the day
8Subansiri Lower supplies a quarter of northeastern regional-entity generation
8Lower Kopili records 1.31 million units under an infirm-generation label
8Tehri pumped storage records evening output but negative net daily energy
8Neemba Renew Surya Vihaan produces 70% less energy than scheduled
8Bihar account receives 63% of ERPC weekly reactive-energy receivables
8Weekly reactive balances conceal daily reversals at West Bengal and DVC
8Gas-fired generation falls 40% in a day as Ratnagiri output contracts
8Hydro trails annual programme by 10 billion units while total generation stays ahead
8Loktak stored energy falls 17% between consecutive CEA reservoir reports
8Parbati-II output nearly vanishes as two hydro stations lose 13.6 million units in a day
8Korba output rebounds 69% as more units return after a 2,100 MW trip
8Sasan remains 68% below daily generation programme as coal stocks reach 7% of norm
8Ghatampur generation falls 35% after another day of unit disruptions
8Two Teesta stations account for 95% of the Eastern hydro programme gap
8Rajasthan reactor 8 carries more programme than the nuclear station’s entire shortfall
8Raghunathpur unit 2 records a 91% generation-programme shortfall
8Vedanta’s Chhattisgarh unit trails generation programme by 92% despite ample coal stock
8All seven RRVUNL coal-stock entries are critical in CEA’s September 7 report
8Three critical Andhra plants hold twice as much coal at ports as at their stations
8Coal buffers diverge sharply between Adani’s Mundra units and Mundra UMPP
8Toranagallu reports zero closing coal stock despite receiving and burning fuel
8Butibori and Pathadi coal buffers shrink below a day on reported consumption measures
8JSWEUL falls 7.4% short of its weekly schedule
8Teesta's final-day shortfall reverses six days of positive deviation Details
8PXIL real-time buyers found no matching supply for three consecutive delivery days
8PXIL's day-ahead spot report records bids without matching sellers
8IEX real-time power returned to Rs 10 from 16:45 to midnight
8IEX high-price market cleared only 358 MWh, all at Rs 20 per unit
8IEX green day-ahead price rose 22% as cleared volume fell 23%
8IEX's green term-ahead trades show a wide price range across contract series
8Thirty-one contracts accounted for three-quarters of IEX's daily term-ahead trading Details
 For reference purposes the website carries here the following tenders:
 8Tender for procurement of spare parts of S/R and ERH vibro feeder installed Details
 8Tender for work contract for rebabbiting of white metal ID FD PA fan bearings Details
 8Tender for supply of 33 kV vacuum circuit breaker pole of various Details
 8Tender for supply, installation and commissioning of new M.S. pipeline Details
 8Tender for construction of watch towers Details
 8Tender for supply,erection, testing & commissioning of 220kV 1Cx1200 Sq.mm,2x(3+0) copper conductor Details
 8Tender for fencing work of ACC and rainwater harvesting pond Details
 8Tender for construction of biomass pellet storage facility Details
 8Tender for balance civil works of CHP package Details
 8Tender for biennial work for dredging of the barrage basin Details
 8Tender for supply and apply of marine grade paints with rust converter Details
 8Tender for supply, erection, testing and commissioning of 132kV 2x(3+0) 1Cx800sq.mm U/G cable Details
 8Tender for supply, laying, erection, testing and commissioning of 66kV, 1CX630 sqmm XLPE cable Details
 8Tender for augmentation of transformation capacity by providing additional 1x50MVA, 132/33kV PTR along with HV & LV bays Details
 8Tender for work of providing & fixing of silica gel breather & supply of blue silica gel for various EHV TF/ICT at various Details
 8Tender for augmentation of transformation capacity by providing additional 1x50MVA, 132/33kV PTR along Details
 8Tender for enhancement of transformation capacity of substation by providing 1x100MVA, 220/132kV ICT along Details
 8Tender for supply of various size of tool holders and its spares of various lathe machines Details
 8Tender for procurement of curved tooth connecting coupling Details
 8Tender for work of stub strengthening tower of 220kV line Details
 8Tender for cleaning of confined hot water duct in natural draft cooling tower Details
 8Design, engineering, supply, erection, testing, commissioning and comprehensive operation & maintenance for 5 (five) years for 65 KWp rooftop solar PV power project Details
 8Tender for supply of plumbing materials Details
 8Tender for rate contract for retrofitting and strengthening of machine foundations Details
 8Tender for maintenance and miscellaneous works Details
 8Tender for internal and external painting of wall and structural steel including water proofing treatment Details
 8Tender for work of welding of carbon steel, stainless steel and alloy steel pipeline and structural work Details
 8Tender for work of insulation and rolling shutters maintenance work Details
 8Tender for replacement/revamping of conventional FLP/old FLP LED light fittings Details
 8Tender for replacement of deteriorated tower and stub strengthening of D/C 220kV line Details
 8Tender for construction of 05 no. bunkers Details
 8Tender for sample collection at various for coal Details
 8Tender for running contract for carrying out the O and M works, improvement works and capital works, maintenance works and DCW works Details
 8Tender for annual maintenance of unit no.1 and 2 at power house Details
 8Tender for supply and application of coating material on different underwater parts Details
 8Tender for replacement of existing 11 kV ACSR conductor with 11 kV AAAC, AL-59, 99 sq.mm covered conductor Details
 8Tender for annual maintenance of 33/11kV line and all distribution transformer Details
 8Tender for replacement of existing ACSR Zebra conductor by HTLS conductor Details
 8Tender for construction of 4 (Four) Nos. of new tower and associated work Details
 8Tender for upgradation of existing 220/132/33kV GIS at 400kV level with transformation capacity Details
 8Tender for rerouting 11kV line using covered conductor Details
 8Tender for constructing 11kV line using covered conductor Details
 8Tender for Re-constructing using HT covered conductor Details
 8Tender for restoration of unit-I including SITC of couplings Details
 8Tender for ETC of boiler and PCP at 2X660 MW Details
 8Tender for supply of tie bar of rail track system Details
 8Tender for providing and laying G. I. pipe Details
 8Tender for providing and laying concrete & steel cover for unit 1 to 5 boiler side Details
 8Tender for R/M of control room with roof treatment at 220/132/33kV G.S.S Details
 8Tender for procurement of various type of control transformers Details
 8Tender for providing & fixing safety showers and sintex tank including other miscellaneous civil works Details
 8Tender for providing muffing on periphery of existing various steel structure of coal yard Details
 8Tender for rate contract for supply of travelling water screen (TWS) system Details
 8Tender for work of providing & fixing of LED lights in switchyard Details
 8Tender for supply of IBR-approved electrically operated butt-weld end gate valve assemblies, complete with actuators, bypass valve Details
 8Tender for supply of cooling water treatment chemicals compatible with on line monitoring and auto chemcal addition control system Details
 8Tender for supply and works for online ABT energy metering monitoring system Details
 8Tender for work of retrofitting of existing BPL make PLCC link of 132 kV line Details
 8Tender for annual maintenance contract (AMC) for the various emergency breakdown & planned outage work of 400 kV,220 kV,& 33 kV bays along Details
 8Tender for annual work contract for material handling and housekeeping in 02 Nos. store shed Details
 8Tender for procurement of GTC journal sleeves for coal mill XRP-903 Details
 8Tender for procurement of insulation protection aluminum sheet (Cladding Sheet) for routine maintenance and AOH of boiler Details
 8Tender for replacement of damaged/worn out various size fire hydrant and spray pipelines Details
 8Tender for procurement of spares for plant air compressor model Details
 8Tender for procurement of various erosion protection sleeves (shield) and other spares for boiler Details
 8Tender for raising of temporary path connecting ram setu at ash dyke Details
 8Tender for providing and laying factory made 80 mm thick cement concrete paver block Details
 8Tender for procurement of 3300KM of ACSR rabbit conductor Details
 8Design, manufacture, testing, supply and delivery of 15kV NCTs of various ratios Details
 8Tender for procurement of 2000 meters, 900NB MS pipe for new intake pipe line Details
 8Tender for procurement of grinding elements (grinding roll, bull ring segment, air port ring assembly ) of bowl mill Details
 8Tender for service contract for OH of boiler Pr. parts (unit #5) and replacement of platen superheater coil Details
 8Tender for repairing of PA fan silencer and canopy during overhauling Details
 8Tender for procurement of 80 MT liquid chlorine Details
 8Tender for laying of 3C 33kV 400 SQ MM XLPE UG cable Details
 8Tender for manufacture, testing, supply and delivery of 33 kV O/D live tank /dead tank oil immersed CT with CTR Details
 8Tender for operation and maintenance of 11 kV, LT lines Details
 8Tender for operation and maintenance of 11 kV, LT lines and sub-stations Details
 8Tender for supply of decentralize material Details
 8Tender for rate contract for internal inspection of T/F or ICT & for attending oil leakages by replacement of gasket & miscellaneous /auxiliary parts of various capacities ICT & power T/F at various Details
 8Tender for construction of peripheral RCC compound wall at 220 kV substation Details
 8Tender for procurement of PLCC cards of ETL/41/42 for establishing MMR PLCC LTS network. Details
 8Tender for supply of various types of cable & dismantling, ETC work of 245 & 145 kV circuit breakers at various S/Stns Details
 8Tender for chemical washing of disc/PLRI strings of various 400 kV Tr. lines Details
 8Tender for supply, civil, ETC works of 3 x 167MVA 400/220/33kV ICT along with HV/LV bays, 400/220kV bus extension Details
 8Tender for day to day maintenance for civil assets Details
 8Tender for day to day maintenance for civil assets in sub-station Details
 8Tender for second circuit stringing on 132kV line Details
 8Tender for various civil maintenance work for upkeepment of 132 kV S/Stn Details
 8Tender for upgradation of substation by replacement of old C&R panels, battery set battery charger Details
 8Tender for supply, civil, ETC works of 400kV 1x125MVAr 3ph bus reactor with NGR along Details
 8Tender for procurement of 75Ohm unbalanced I-lF cable Details
 8Tender for work of establishment of 132-110/33 kV s/s Details
 8Tender for work of enhancement of existing corridor of 220kV line Details
 8Tender for augmentation for enhancement of transformation capacity of ss by addition of ICT’s Details
 8Tender for work of supply and application of anti-corrosive paint/coating on external Surface of various steel structures, pipelines and auxiliaries Details
 8Tender for supply of air blower, pump and sludge panel & its accessories Details
 8Tender for work of safety related miscellaneous fabrication work at various Details
 8Tender for supply of various boiler tubes bends Details
 8Tender for supply and application of plastic refractory in various of boiler Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
NMDC to begin commercial coal production next quarter Details
 
8Mahanadi Coalfields sustains over 200 MT annual coal production and dispatch: Govt Details
 
8Coal Gasification Scheme Tests India’s Industrial Transition Details
 
8CMPDI in focus as coal gasification scheme draws 7 applications, with Adani and NTPC among applicants Details
 
8Reddy rules out coal shortage despite 58 power plants reporting critical stocks Details
 
8Indian sponge iron at two-year high, boosted by costly coal imports, domestic shortages Details
 
8From India to Germany: Populating the green energy workforce Details
 
8Can India’s solar farms become living laboratories for clean-tech innovation Details
 
870% of Karnataka's power demand met by renewables, says state energy minister Details
 
8India’s regulator proposes mandatory co-located storage for new solar, wind projects Details
 
8The Looming Energy and Water Burden of India’s Data Centres Details
 
8NLC India Subsidiary NIRL Gets LOA For 200 MW Wind Project From SJVN Details
 
8Tata Power Solar of crosses 500,000 rooftop solar installations Details
 
8Why GE Vernova T&D India Share Price is Rising Details
 
8Suzlon Secures 200 MW Wind Order From Ayana Renewable Power Details
 
8Saubhagya Scheme Legacy: Impact on Power Sector Financials Details
 
8Solar, battery storage and $1 billion: Inside Madhya Pradesh’s new ADB-backed energy push Details
 
8India Holds 123 Million Tonnes Coal; 23-Day Buffer at Plants Details
 
88 Cable & Wire Stocks With Order Books Up to Rs 26,665 Crore to Keep on Your Radar Details
 
8Torrent Green Energy Commissions 322 MWp Decentralized Solar Capacity Across 50 Sites In Nashik Details
 
8India’s Data Center Expansion Faces Water, Power, and Currency Headwinds Details
 
8Seven Applicants for Rs 37,500-Crore Coal Gasification Scheme Details
 
8From 3 lakh to 5 lakh: Tata Power Solaroof scales rooftop solar across residential, C&I segments Details
 
8India has 124 MT coal stocks, adequate for 51 days: Reddy Details
 
8Our EPC-Led Approach Enables Us To Deliver Future-Ready Infrastructure Solutions: JAKSON Infra Details
 
8NTPC Vindhyachal ED Kishore Kumar Hota honoured with ‘Leader of the Year’ award Details
 
8Odisha approves Rs 15,949 crore power grid investment for future demand Details
 
8Gaining Momentum: Developers’ perspective on the wind power sector Details
 
8India’s Energy Storage Requirement to Reach 411 GWh by FY32 Details
 
You can also click on Newsclips for more Details
RRVUN's Rs 1,125 crore Suratgarh coal tender sets a three-month delivery clock against a 365-day portal period
8The tender seeks 12.5 lakh MT of domestic coal at 3 lakh–4.5 lakh MT a month, yet Clause 2.28 fixes completion at three months while the portal records a 365-day work period.
8The unresolved question is how bidders price a schedule RRVUN can defer or cancel without admitting a claim, against coal that earns Rs 1 per MT once ash crosses 34% or GCV falls below 4,000 Kcal/kg.

 

APEPDCL grants 24 extra days on its Rs 143.32 crore SCADA package without touching a single execution obligation
8Three corrigenda moved submission from 1 September to 25 September 2026, but the 18-month implementation period, five-year FMS and 10% performance security stayed exactly where they were.
8What the extensions really concede is preparation time for a bidder pool that must satisfy two separate qualification streams and assemble OEM authorisations before it can quote.

 

RVPN's Rs 83.38 crore Shiv Enclave GIS package makes unlisted work the contractor's problem
8A 132/33 kV, 2x80 MVA GIS substation with a 4 km LILO cable arrangement carries a 545-day execution period and a 10% performance security, extended eight days by Corrigendum No. 01.
8The clause that matters is GCC 3.2, which absorbs reasonably inferable items into the contractor's scope without automatic additional payment.

 

NTPC puts 2,184 man-months of construction safety at Telangana Stage-II behind a 52-month firm-rate contract
8The consultant must field 47 personnel, run a 24/7 IP-camera control room and approve other agencies' JSA/HIRA documents across a 3 x 800 MW build.
8The commercial risk is not the Rs 5,000-per-day non-deployment penalty but firm rates through a unilateral 12-month extension, 5% retention and no interest on deferred payment.

 

TNPDCL asks for 5,000 distribution transformers while the protected BOQ shows a quantity of one
8The M-256 tender covers 5,000 units of 100 kVA, EEL-2 aluminium-wound transformers with a Rs 1,00,20,500 EMD, a ±25% quantity variation and a 60-month guarantee.
8The BOQ's "1.0 No." line and its residual civil-work text sit inside a spreadsheet bidders are forbidden to alter, converting a template artefact into a responsiveness risk.

 

JdVVNL's Rs 119.89 crore Bikaner package carries two completion periods inside the same document
8The NIT records eight months for supply, erection, testing and commissioning while Appendix 4 records nine, both against an unchanged nine-month total, with the portal and NIT also differing on the 22 September opening time.
8Performance security is quoted at both 180 days and 30 days beyond the defect-liability period, and guarantee charges turn on which one controls.

 

Bidder queries force JdVVNL to reopen the BOQ on its Rs 91.47 crore Bikaner DD package before bids close
8Corrigendum-3 supersedes the 14 August NIT, revising the BOQ, specifications, estimate and EMD to Rs 1.83 crore without publishing the superseded figures for comparison.
8The sharper problem is composition: JdVVNL's own estimate puts supply at 79.6% of value while ITB 37 treats supply above 70% of the quoted price as front-loaded and demands additional security.

 

Phalodi package climbs 0.7% across two corrigenda, with the entire increase landing in supply
8Between Corrigendum-I and Corrigendum-3, supply rose by Rs 38.89 lakh while erection fell by Rs 1.21 lakh, taking TNTW-792 to Rs 97,59,20,302.39 and EMD to Rs 1,95,18,407.
8No item-level change register accompanies the revision, and the portal and SBD still disagree on whether technical bids open at 11:00 am or 5:00 pm.

 

Jaisalmer's Rs 121.13 crore RDSS package stacks four separate security layers on one contractor
8Beyond the 10% performance security sit abnormal-bid security, supply-unbalancing security and a further 10% guarantee on major equipment running to 36 months after completion.
8With 77.4% of the estimate in supply and no pre-bid meeting scheduled, bidders must also decide whether the EMD instrument reads Rs 2,42,25,139 or Rs 2,42,25,140.

 

JVVNL withdraws the vendor-registration security waiver as it tenders 25,000 CSP transformers
8Appendix-A replaces EMD and SBG references with Bid Security and removes the relaxation that JVVNL registration alone previously conferred, on a Rs 16,025 lakh, 16 kVA programme.
8The allocation formula caps L1 at 20% and spreads half the quantity across other firms, making past repair performance an eligibility filter rather than a reference note.

 

Navkar Global Infra takes NTPC Mouda ash transport at 47.6% of base rates against 23 other accepted bidders
8The accepted percentage produces a Rs 142.80 crore contract value, a 52.4% discount to the Rs 300 crore estimate and far past NTPC's own 10% abnormally-low threshold.
8Section C nonetheless caps each shortlisted bidder at Rs 50 crore cumulative and guarantees no purchase order at all, separating the headline award from bankable work.

 

Churu package falls Rs 7.45 crore in Corrigendum-3 after rising in Corrigendum-1 TNTW-798 moved from Rs 132.60 crore to Rs 133.13 crore and then down to Rs 125.67 crore, with supply cut 6.5% against erection's 2.0%, and no clause-level reconciliation published.
8Bidders have ten calendar days from republication to reprice, while the portal and corrigendum differ by Rs 60 on an EMD that decides envelope-one compliance.

 

UJVN Limited raises its BESS tariff ceiling 3.8% but leaves 165 MWh outside VGF support
8The 90 MW/225 MWh Chilla project draws VGF on only 60 MWh, while the ceiling capacity charge moves to Rs 3,30,400/MW/month against the Rs 3,96,747 bidders sought.
8After 12 years the entire asset transfers to UJVN Limited without consideration, so residual value has to be recovered inside a capped tariff stream.

Details
 For reference purposes the website carries here the following tenders:
 
8Tender for erection of 66kV SS equipment, structures, control wiring Details
 
8Tender for erection of 66kV SS equipment, structures, control wiring, yard lighting Details
 
8Tender for provision of balance steel reinforcement for construction of 110/33kV indoor 110/33kV substation. Details
 
8Tender for conducting tube thickness survey in first and second pass Oxide scale Thickness Measurement in Super heater, Reheater Details
 
8Tender for procurement of 100KVA/11KV/433V energy efficient level-2 aluminum wound distribution transformers Details
 
8Tender for supply, installation, testing and commissioning of 11kV to 415V ,315KVA LT transformer Details
 
8Tender for supply of 400 kV and 220 kV CVTs for various substations Details
 
8Tender for earthing of switchyard gantries Details
 
8Tender for supply, installation, and commissioning of tower/floor-mount split air conditioners for the control room, battery room Details
 
8Design, engineering, manufacturing, testing, supply, stringing, installation, testing and commissioning etc. for construction of LILO of 220 kV line Details
 
8Tender for biennial electrical & mechanical maintenance for machine Details
 
8Tender for work of new 66kV switchyard with single zebra bus with section isolator along Details
 
8Tender for work contract for carry out cleaning of algae removal from the trash rack of CV, VT & MV pumps Details
 
8Tender for Re-conductoring HT line Details
 
8Tender for constructing new 11kV UG cable Details
 
8Tender for shifting of new sewage pipeline inside plant Details
 
8Tender for fixing of PVC chain link fencing Details
 
8Tender for grouting work at conveyor 2A side wall Details
 
8Tender for biennial maintenance contract for civil works Details
 
8Tender for operation and maintenance of garbage PIT Details
 
8Tender for CAMC for real-time environmental data transmission Details
 
8Tender for job contract for supply and laying of coir geotextile Details
 
8Tender for providing and fixing of precoated galvanized iron profile sheet roofing Details
 
8Tender for civil repair and maintenance works of CE (PRG) shed Details
 
8Tender for standardisation of transformers Details
 
8Tender for erection of tower material/ tower structure, beams, bus bars for various 220/132kV sub stations Details
 
8Tender for technological upkeep of silo and fly ash bagging machine Details
 
8Tender for restoration of damaged protection work Details
 
8Tender for providing and laying of external water supply pipeline Details
 
8Tender for repairing of floor tiles at hydro power Details
 
8Tender for construction of new protection wall for protection of tower Details
 
8Tender for repair and painting work of 220kV GIS substation Details
 
8Tender for puncture insulator detection (PID) of insulator string of various towers of 132kV line Details
 
8Tender for replacement of old 110 Volt 300AH battery bank and battery charger at 132kV S/s Details
 
8Tender for new turfing at newly constructed 132kV TBC bay and strengthening of pathway Details
 
8Tender for procurement and replacement of old 33kV circuit breakers Details
 
8Tender for shifting of 33 kV line Details
 
8Tender for supply, dismantling and erection of 33kV isolators Details
 
8Tender for supply of control panel spares of pump house Details
 
8Tender for miscellaneous civil works for water supply Details
 
8Tender for collection, transportation and treatment of industrial liquid effluent inclusive of disposal of sludge generated Details
 
8Tender for new 33 by 11 kV sub-stations augmentation or addition capacity including associated line Details
 
8Tender for new 33 by 11 kV sub-stations Details
 
8Tender for interlinking 11kV line Details
 
8Tender for stringing new HT feeder using ABC 150 sq.mm Details
 
8Tender for upper hydro electric project 1x24 MW powerhouse Details
 
8Tender for capacity enhancement of 110kV DC line Details
 
8Tender for upgradation of 33kV substation Details
 
8Tender for work contract for annual maintenance work of various types of cranes installed Details
 
8Tender for procurement of various HYDAC make filters installed Details
 
8Tender for procurement of 33kV polmer insulator strings Details
 
8Design, manufacture, testing, supply and delivery of 220kV PTs and 220kV CTs of various ratio Details
 
8Tender for shifting of 66kV line Details
 
8Design, manufacture, testing, supply and delivery of 66kV 2000A isolators with earth switch with solid core insulators Details
 
8Tender for supplying, laying and compaction of good earth at 66kV S/S Details
 
8Tender for construction of additional foundations for 1 no 66 kV line bay Details
 
8Tender for rate contract for removing, lifting, shifting, dismantling and overhauling of 6.6 kV HT motors Details
 
8Tender for ARC for erection of HT / LT / TC and maintenance work Details
 
8Tender for work of overhauling of air-preheater Details
 
8Tender for supply of various fasteners and consumables Details
 
8Tender for supply of filled hydrogen gas cylinder with own transportation for mechanical operation for all units Details
 
8Tender for repairing & maintenance work of ash pond Details
 
8Tender for procurement of seal kit sets for scoop actuator and air line Details
 
8Tender for procurement of HART calibrator required for calibration purpose Details
 
8Tender for procurement of different alloy CI pipe bends and fittings Details
 
8Tender for procurement of different sizes MS ERW pipe Details
 
8Tender for procurement of several LT 415V power cable Details
 
8Tender for procurement of different submersible pumps Details
 
8Tender for Bi-annual rate contract for U4 B and A equipment Details
 
8Tender for supply and delivery of non centralized local materials like 33kV line Details
 
8Tender for construction of electricity test lab Details
 
8Tender for construction of protection wall and other misc.civil works at 33/11 kV S/S Details
 
8Tender for construction of electricity test lab Details
 
8Tender for establishment of 220/33kV substation Details
 
8Tender for interconnection by link line between 220kV line Details
 
8Tender for work of procurement of HV critical spares (11/22/33kV CT’s, PT’s & LA’s) for various EHV substations Details
 
8Tender for replacement of 1x 25MVA 132/33kV TF by 1X50MVA 132/33kV transformer along Details
 
8Tender for ARC of work of erection, testing & commissioning of 66kV feeder bay, transformer bay Details
 
8Tender for work of cleaning of bus ducts/MCCs, actuator overhauling, and cable dressing works Details
 
8Tender for biennial rate contract for ash handling plant Details
 
8Tender for supply of riser duct liners of beater wheel mill Details
 
8Tender for supply of electrical actuator for ID Fan & PA Fan IGV for 200 MW Details
 
8Tender for supply, dismantling and commissioning of new acid tank (H2SO4 -Concentration 98%) with accessories Details
 
8Tender for supply of MS grill for walkways of boiler & coal mill Details
 
8Tender for work of removal of old damaged refractory, application of the new castable refractory/ fire brick lining in bottom ash hopper & fabrication work Details
 
8Tender for ARC for erection of HT / LT / TC and maintenance work Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
CIL's daily coal production rises 35% Details
 
8India tenders 700MW of solar capacity for C&I offtake Details
 
8Kajaria Ceramics Inks 20 MW Wind-Solar PPA with Sunsure Details
 
8Solis Commissions 1.04 MWh EverCore BESS in Chennai Details
 
8MENA Renewable Energy Capacity Surges to 16 GW in 2025 Details
 
8Solar Manufacturing In UP Gets A Fillip, Alpex Solar Set To Become Second Cell Maker From State Details
 
8India’s non-fossil fuel power capacity crosses 300 GW mark Details
 
8India’s Thermal Power Demand Rises Amid Renewable Shift Details
 
8Siemens Energy India: SF6-Free Circuit Breaker for Cleaner Grid Details
 
8Bhakra Nangal Dam Declared Safe as India Pushes for Atmanirbhar Power Sector Details
 
8Coal Loading to Power Sector Rises to 444 Rakes: Government Details
 
8India Ramps Up Rail Coal Deliveries as Power Plant Stockpiles Dwindle Details
 
8Coal ministry steps up supplies as rake loading rises 20% in four days Details
 
8Siemens Energy India Commissions Its First 145kV SF6-Free Circuit Breaker Details
 
8Urgently augment power generation’: Punjab engineers write to Bhagwant Mann Details
 
8Corrective supply steps on to tackle stock situation, says CoalMin Details
 
8NTPC Limited Strengthens Supplier Ecosystem with Velocious Details
 
8CIL Accelerates Coal Output as Monsoon Eases, Power Sector Dispatch Jumps 24% Details
 
8Coal India, SCCL Boost Power Sector Coal Supply as Daily Rake Loading Climbs to 444, Up 74 Rakes Details
 
8Coal Loading For Power Sector Maintains Steady Upward Momentum, Government Highlights Consistent Growth Trend Details
 
8GE Vernova T&D India Declared L1 Bidder for 6000 MW HVDC Project by Power Grid Details
 
8Adani Power Leads Thermal Sector in NSE Sustainability ESG Rating Details
 
8Coal loading to power sector shows consistent upward trend: Govt Details
 
8Adani Power: Investor Presentation Highlights Sep 2026 Growth Strategy Details
 
8ADB, Madhya Pradesh Partner To Unlock $1 Billion For Green Energy Details
 
8Coal Supply to Power Plants Improves as Rake Loading Rises Details
 
8Punjab Power Output Dips Despite 117% Coal Stock at PSPCL Plants, Centre Says Supply Isn’t the Issue Details
 
You can also click on Newsclips for more Details
 1 2 3 > 

Showing 1–50 of 111 items