All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Aug 2026

8The Southern Region carried a 13% jump in July peak demand with a sharply smaller hydro cushion. Its operating committee also records the grid outside the permitted frequency band for more than a quarter of the month. Details
8The annual energy account reports distribution losses of 7.9%. Weak collections lift the combined technical and commercial loss to 24.7%, while more than 1.2 million consumers and every listed distribution transformer remain unmetered. Details
8Uttarakhand’s regulator has approved a replacement power line to Kedarnath only after the utility awarded the work. The new line follows the loss of underground cables from a government-funded project that had operated for about seven months. Details
8India’s central regulator has fixed generic tariffs for small hydro and biomass projects for the current control year. Developers won the tariff order but lost their attempt to reset capital costs, maintenance allowances and financing assumptions. Details
8The power ministry wants the control-room systems that run the grid to stop being imported after this decade. The committee designing that transition says current local content is still below 20%, with hardware carrying three-quarters of system cost. Details
8Monday turned the price warning from the previous edition into a physical shortage. India’s reported peak shortfall rose to 1,513 MW from 200 MW on Sunday, while the next day’s exchange auction eased only to Rs 6.82 a unit. Details
REGULATORY ORDERS AND PROCEEDINGS

8CERC keeps Adhunik’s disputed invoices under interim protection while the case is adjourned
8CERC asks for more evidence on Athena Jaipur Solar’s reactive-power change claim
8DB Power settles an Rs 11.22 crore payment case through six instalments
8Mundra power disputes remain paused while APTEL reviews related issues
8JSW’s request to excuse delay at a 540 MW wind project remains undecided
8POWERGRID seeks 748 extra days and Rs 438.82 crore for the Sikar system
8Kreate Energy’s licence-revocation case waits for an appellate ruling
8SECI opens a GST compensation case for a 300 MW solar project
8Khandukhal Rampura transmission relief remains pending after another adjournment
8Adani Green’s claim for transmission charges and lost generation stays at pleading stage
8Khaba Renewable’s 90-day connectivity extension request is reserved for order
8Jharkhand’s renewable-payment case gets more time for clarification
8Datta Power wins an urgent hearing before its grid access expires
8POWERGRID seeks 673 extra days and Rs 151.07 crore for Aligarh Sikar works
8NLC’s 200 MW Bhuj solar case keeps its interim protection
8Tata Power Delhi starts a damages case over delayed SECI solar supply
8Buxar seeks Rs 82.04 crore for 401.87 million units of pre-commercial power
8Gujarat asks a captive-power surcharge dispute to complete its written record
8Gujarat allows inspection of Kundan Solar after module replacement raises capacity questions
8Hindalco’s renewable-obligation case remains open for updated compliance data
8Paryapt Solar’s safeguard-duty claim moves to account reconciliation
8UPERC gives Ayesha Steel one last chance to support its load-reduction request
8Punjab publishes an RPO-surplus order without the decision in the supplied copy

COMPANIES AND FINANCE

8Yuva Bio Energy’s 12-tonne CBG plant starts with stretched liquidity
8Inox Renewable allots 4.90 crore shares under its approved demerger

GRID AND MARKET PULSE

8Generation outages remain above 48,000 MW with state units carrying the larger share
8Eastern imports into the North exceed their operating limit for five blocks
8Western 765 kV voltages stay high at Banaskantha for almost three hours Details
8Thirty-eight coal plants hold critical stocks as the national pile reaches half its norm Details
8Kerala proposes a full tariff framework for batteries and pumped storage
8Gujarat gives a 20 MW hybrid project thirty days to finish connection formalities
8Andhra consumers face a 40 paise fuel-cost adjustment in September bills Details
8POWERGRID wins a 7,500 MW Gujarat evacuation system at Rs 822.91 crore yearly
8L&T wins a 6 GWh Middle East battery order worth Rs 5,000–10,000 crore
8Insolation wins nine Maharashtra solar projects requiring about Rs 425 crore
8Khavda transmission line reaches AAA while refinancing introduces a five-year put risk Details
8RECPDCL's Nasik-Pimpalgaon Transmission Tender Draws a Five-Way Field With Zero Consortium Bids REC's TBCB process for the 765/400/220 kV Nasik substation and its two evacuation corridors qualified five bidders — Adani Energy Solutions, Ceigall India, Dilip Buildcon, Power Grid and Resonia — all bidding solo with 100% equity, bypassing the consortium route entirely. A single 36-month COD ties all six project elements together for tariff recovery, meaning a delay in any one bay or reactor can block revenue across the whole package.

8RECPDCL's Lakadia REZ Mega-Tender Rejects Dilip Buildcon While Six Others Clear a Rs 4,506 Crore Bar RECPDCL's Gujarat renewable-evacuation package — featuring a 7,500 MW pooling station, synchronous condensers and space reserved for a future 6,000 MW HVDC terminal — qualified six of seven bidders, with Dilip Buildcon rejected as non-responsive without a disclosed reason. The qualified-bidder notice arrived 42 days late against the original schedule, and only four of the six will advance to the reverse auction.

8PFC's Rundh Gidawara 765 kV Tender Ties 100% Tariff Recovery to Simultaneous Commissioning of Every Element PFC Consulting's Alwar substation RFP demands a 30-month build-own-operate-transfer delivery where the developer can't monetise any single completed asset until the whole interdependent system — GIS station, 765 kV line, LILO and 400 kV connection — goes live together. The acquisition price for the SPV won't even be disclosed until 20 days before bid closure, leaving bidders to finalize financing on short notice.

8PFC's Bhojrajka Substation Tender Launches With Its Own SPV Still Unnamed PFC Consulting's Rajasthan RFP for the 400/220 kV Bhojrajka station bundles a new double-circuit line, two voltage-level LILO programmes and works inside an existing 765 kV station — all under one 30-month deadline — while the project-specific SPV remains listed as "under incorporation" in the very clauses that require its acquisition. A 15-minute discrepancy between the Hindi invitation and the English RFP over technical-bid opening time (15:45 vs 15:30) adds a small but avoidable procedural risk.

8POWERGRID's 765 kV Transformer Award Lands 15% Below Its Own Reverse-Auction Estimate BHEL won POWERGRID's Rs 514.56 crore Lot-7 bulk transformer package at a price Rs 90.59 crore below the Rs 605.15 crore indicative benchmark, with the tender notably replacing cash EMD with a bid-securing declaration backed by a one-year ineligibility threat. Twenty-three single-phase 500 MVA units must ship in phased batches, with cross-defaulted supply and services contracts ensuring that any site-side slippage carries consequences across the whole award.

8NTPC's Great Nicobar Substation EPC Slips 80 Days While a Daily Rs 37 Lakh Penalty Clock Stays Fixed NTPC's twin 132/33 kV substation package for Gandhinagar and Campbell Bay saw its bid deadline pushed three times — ultimately by 80 calendar days — without any corresponding extension to the underlying 24-month completion period. Materials must reach two remote island locations reachable mainly by ship and helicopter, while the daily delay-damage rate of Rs 37.03 lakh starts ticking from day one of any slippage.

8TNPGCL's North Chennai FGD Retrofit Tender Pushes Its Opening Date Back 164 Days Across Eight Corrigenda TNPGCL's flue-gas desulphurisation package for three 210 MW units at North Chennai has seen its tender-opening date slide from 7 April to 18 September 2026 through eight separate corrigenda, alongside five postponements of the pre-bid meeting. The 24-month execution clock remains untouched despite the extended runway, and price escalation has been deleted entirely from the contract.

8Raipur's Korba West Consultancy Tender Reveals a Coal Handling Plant Built Ahead of Its Environmental Clearance E.D. (Project), Raipur has floated a consultancy assignment to amend the environmental clearance for HTPS Korba West after land was already acquired for the coal handling plant — meaning physical site development appears to have outpaced the regulatory approval it depends on. The notice discloses no land quantum, deliverables, timeline or liability terms, leaving the assignment's real scope entirely undefined.

8RVUNL's Suratgarh O&M Tender Can't Decide If It's a Three-Year or Five-Year Contract RVUNL's Rs 180 crore comprehensive O&M package for the 2x660 MW Suratgarh plant states a three-year term in its NIT and portal listing, while six separate annexures independently declare a five-year duration — a contradiction that survives five deadline extensions spanning 115 days. Performance penalties for DSM charges, demurrage and environmental notices sit entirely outside the tender's headline 10% liquidated-damages cap.

8TGGENCO's Srisailam Generator Replacement Ties 45% of Payment to a 72-Hour Test Run TGGENCO's brownfield replacement of a 150/175 MW generator-motor at SLBHES requires the new machine to fit precisely around a retained MELCO-era turbine, brackets and excitation system, with commissioning-linked payment retention rising from 40% to 45% if delivery slips. The bid security's own claim period contradicts itself — one clause says three months, another says six.

8WBSETCL's Salboni HTLS Line Tender Rewrites Its Price-Comparison Formula Mid-Bid WBSETCL's 68 km, 400 kV HTLS transmission package extended its bid deadline by 14 days while simultaneously replacing its bid-comparison clause with a new formula that converts technical deficiencies directly into rupee penalties on the evaluated price. A conflicting insulator creepage-distance requirement (370mm vs 430mm) was resolved in favour of the stricter technical specification through a revised BOQ.

8NTPC's Ramagundam Transformer Replacement Halves Its Site-Execution Window to Add Factory Time NTPC's replacement of two 250 MVA auto-transformers with 500 MVA units at Ramagundam kept the overall 30-month deadline fixed but reallocated it — supply time grew from 24 to 27 months while erection and commissioning shrank from six months to just three. A parallel concession lets bidders skip a costly dynamic short-circuit test if they can prove design similarity to a previously validated 500 MVA unit.

8BSPGCL's Kajra BESS Tender Hands Over Land But Leaves Battery Chemistry and Degradation Undefined Bihar State Power Generation's 500 MWh, four-hour standalone battery storage tender under a build-own-operate-transfer model provides the Kajra site but discloses no chemistry, augmentation obligation, availability standard or tariff-payment mechanism in the notice itself. A Rs 13 crore EMD plus a Rs 15 lakh non-refundable processing fee creates a steep entry cost before any of that technical risk is even resolved.

8NRPC's Rs 25,000 Audit Tender Can't Agree With Itself on Bidding Structure or Arbitration Northern Regional Power Committee's tiny financial-audit engagement for FY 2025-26 shows GeM's portal declaring a "Two Packet Bid" while the tender's own ATC clause insists on a single-packet process — and GeM separately marks arbitration as "No" even as the underlying contract conditions prescribe a full NRPC-appointed arbitration mechanism. Despite the negligible Rs 25,000 estimate, a bid-security declaration carries a two-year non-responsiveness penalty for withdrawal or default.

8AEGCL's Sarusajai GIS Conversion Tender Locks Prices Firm for 730 Days With No Escalation Relief AEGCL's Rs 455.90 crore turnkey conversion of a live 220/132/33 kV AIS substation to GIS technology declares prices "firm" and explicitly excludes price adjustment "on any account," despite a two-year execution period exposed to steel, copper and GIS-component volatility. A five-year extended guarantee on the GIS equipment itself is backed by security equal to 20% of that equipment's cost — layered on top of the standard 10% performance guarantee.

8NSPCL's Tax-Law Migration Tender Reappears With Wider Scope and the Same Unresolved Contradictions NSPCL's republished consultancy tender for migrating to the Income-tax Act, 2025 now requires validating the correctness of historical tax positions — not just forward-looking compliance — while GeM's portal says no EMD and no arbitration are required even as the underlying GCC clauses impose a 5% performance guarantee and a full arbitration mechanism. Two separate clauses set the Class-I local-content threshold at both 50% and 60%, leaving basic eligibility unsettled.

8Raipur's Korba West Environmental Consultancy Notice Repeats Itself Without Adding a Single New Detail A near-identical restatement of E.D. (Project), Raipur's HTPS Korba West environmental-clearance consultancy still fails to disclose the additional land area, the coal handling plant's revised footprint, or any deliverable, timeline or liability term — confirming that the underlying regulatory-sequencing question remains as open as the assignment's scope itself. Details
 For reference purposes the website carries here the following tenders:
 
8Tender for construction of 2x401x63MVA MVA 132kV S/S Meerut Details
 
8Tender for construction of 2x40 MVA 132kV S/S Budaun Details
 
8Tender for construction of 132kV SC line Details
 
8Tender for construction of LILO of 220kV DC line Details
 
8Design, engineering, manufacture, factory testing, supply, transportation, supervision of installation and commissioning of 33kV and 11kV RMUs for 33kV substation Details
 
8Tender for construction of new concrete retaining wall adjacent to the existing concrete retaining wall at switchyard Details
 
8Tender for standardization of transformer station Details
 
8Tender for rerouting of HT line Details
 
8Tender for stringing high tension 33kV covered conductor, shifting and modification of the existing 11 kV, and low tension (LT) electrical distribution network Details
 
8Tender for river training works at headworks for protection of water conductor Details
 
8Tender for selection of agency for providing facility management services for operation, maintenance, monitoring and management of SCADA infrastructure Details
 
8Tender for repairing of Two Nos. 50 MVA three phase 132/33 kV power transformer Details
 
8Tender for AMC for regular maintenance work, outage work and attending emergency breakdown work of 220 kV & 400 kV transmission lines Details
 
8Tender for construction of 33kV S/S Details
 
8Tender for construction of civil foundation for transformer bay, CTR, cooling bank and gravelling work Details
 
8Tender for transformer augmentation work of 132 kV transformer and 132/33 kV bay at 132 kV GSS Details
 
8Tender for construction of civil foundation for transformer bay, CTR, cooling bank for 160 MVA transfer Details
 
8Tender for augmentation of 160 MVA transformer at 220 kV GSS Details
 
8Tender for augmentation of 31.5 MVA transformer and associated civil work at 132 kV GSS Details
 
8Tender for transformer augmentation work of 132 kV transformer and 132/33 kV bay Details
 
8Tender for construction of 2 No. 132 kV bay at 132 kV GSS Details
 
8Tender for contract for the work of complete operation, maintenance and housekeeping of coal handling plant Details
 
8Tender for procurement of automatic measurement kit Details
 
8Tender for supply, design, erection, retrofitting and commissioning of 400 kV circuit breakers in switchyard Details
 
8Tender for annual maintenance contract (including preventive maintenance) of underground / overhead OFC links Details
 
8Tender for supply, erection and commissioning of special protection scheme for 400/220kV 315 MVA ICT-1 and 400/220kV, 315MVA ICT-2 at 400kV S/Stn Details
 
8Tender for supply and supervision of ETC of 72.5kV circuit breakers Details
 
8Tender for supply, I and C of oil filtration machine along with spare Details
 
8Tender for procurement of outlet turret complete with wearing plate, turret cone and top cover of 8.5 E9 coal mills Details
 
8Tender for procurement of electrical actuators and spare parts Details
 
8Tender for work contract for disposal of spent mineral wool through common hazardous waste-treatment, storage disposal facility Details
 
8Tender for work contract for overhauling of battery banks Details
 
8Tender for miscellaneous repair and civil maintenance work including sanitary works, water supply maintenance works Details
 
8Tender for roof treatment of different type Details
 
8Tender for biennial contract for civil maintenance works Details
 
8Tender for hiring of coil tubing and pumping services Details
 
8Tender for procurement of LT three phase channel cross arm Details
 
8Tender for procurement of LT three phase angle X arm Details
 
8Tender for procurement of LT GI pin Details
 
8Tender for procurement of 33kV 1 x 630sq mm UG XLPE aluminium power cable. Details
 
8Tender for procurement of cast basalt lined MS pipes Details
 
8Tender for procurement of 22 kV structure material for 9 Mtr PSC pole Details
 
8Tender for enhancement of existing 110/33kV power transformer capacity Details
 
8Tender for procurement of seal kit for the brake jack assembly of generators Details
 
8Tender for supply, installation & commissioning of new saftey guard for various auxiliaries Details
 
8Tender for erection of 66kV SS equipment, structures, control wiring, yard lighting Details
 
8Tender for work of misc pressure part related activity of boiler Details
 
8Tender for supply of various boiler tubes bends Details
 
8Tender for work of preventive maintenance, shutdown & emergency maintenance of IAC/SAC compressor, air washery fan/pump motor Details
 
8Tender for erection work of 66kV line Details
 
8Tender for supply, installation & commissioning of 5-star energy efficient inverter based split Details
 
8Tender for creation of 1 no. 33kV line bay to accommodate 33kV S/Stn Details
 
8Tender for ARC of coal mill and gravimetric feeders etc. Details
 
8Tender for ARC for cleaning, removal of garbage and ash from boiler and its auxiliaries Details
 
8Tender for providing additional 01 no. 100 MVA 220/132kV T/F Details
 
8Tender for procurement of special purpose welding electrodes Details
 
8Tender for survey, design, fabrication, supply, laying of foundation, erection and commissioning of 66 kV monopole line Details
 
8Tender for erection, testing & commissioning work of 66kV equipments Details
 
8Tender for removal/transportation of silt, mud and water algae from cooling tower, CW system and various Details
 
8Tender for repair and HP-HVOF coating of 01 No runner of 77 MW francis hydro-turbine Details
 
8Tender for procurement of different dia pipe and pipe fittings Details
 
8Tender for biennial maintenance contract for pest control and rodent control activities Details
 
8Tender for procurement of spares for complete coal nozzle assembly Details
 
8Tender for procurement of different types of spares of vibrating feeder and flats for APH and auxiliaries Details
 
8Tender for procurement of dry ashing spares for overhauling Details
 
8Tender for service contract for round the clock operation of in-plant rail movement control cabin Details
 
8Tender for procurement of 33/33 kV, UE, 3C x 185sqmm, XLPE cable Details
 
8Tender for Bi-annual rate contract for jointing and repairing of conveyor belt and drum rubber lagging Details
 
8Tender for procurement of throat plate assembly for coal mill Details
 
8Tender for procurement of BA crusher and jet pulsion pump Details
 
8Tender for stability testing of concrete and steel structures within the plant Details
 
8Tender for erection and commissioning of cast basalt MS pipe line Details
 
8Tender for supply, fabrication & erection of steel structure, erection of equipment?s, erection of earth mat, earth raisers, laying of control cable Details
 
8Tender for attending the breakdown maintenance works in ash slurry lines Details
 
8Tender for supply of various type of tarpaulin, transparent plastic sheet & miscellaneous materials for various Details
 
8Tender for erection and maintenance of HT/LT/TC work Details
 
8Design, engineering, supply, erection, testing, commissioning and comprehensive operation & maintenance for 5 (five) years for 1140 KWp rooftop solar PV power project Details
 
8Tender for erection and maintenance of HT/LT/TC work Details
 
8Tender for installation of double circuit AB cable Details
 
8Tender for replacement of existing of 11kV ACSR rabbit conductor with 11kV AAAC covered conductor Details
 
8Tender for replacement of existing of 11kV ACSR rabbit conductor Details
 
8Tender for replacement of existing of 33kV DOG conductor Details
 
8Tender for works related to leakage in forebay No. 01 and epoxy grouting in draft tube Details
 
8Tender for providing & fixing of chain link cage around distribution transformer Details
 
8Tender for various civil maintenance work for upkeepment of 132kV and 220kV S/Stn Details
 
8Tender for various civil maintenance work for upkeepment of RTC, 400 kV and 132kV S/Stn Details
 
8Tender for various civil maintenance work for upkeepment of 132 kV, 220 kV S/stn Details
 
8Tender for turnkey based contract for conversion of existing of 11kV HT line Details
 
8Design, engineering, supply, erection, testing, commissioning and comprehensive operation & maintenance for 5 (five) years for 1000 KWp rooftop solar PV power project Details
 
8Tender for turnkey based contract for conversion of existing of 11kV HT line Details
 
8Tender for turnkey based contract for conversion of existing of 11kV HT line network Details
 
8Tender for turnkey based contract for conversion of existing of 11kV HT line Details
 
8Tender for ARC work of erection of 66kV equipment, structures, control wiring, yard lighting etc. Details
 
8Tender for construction of double circuit cable trench Details
 
8Tender for work of providing services for loading, unloading, shifting and stacking of materials Details
 
8Tender for biennial work contract for maintenance of ash handling plant Details
 
8Tender for work of replacement / fitting of M.S. / GI grills, hand railing and misc. fabrication and other safety related works Details
 
8Tender for work of routine and preventive / breakdown maintenance activities & miscellaneous works Details
 
8Tender for supply of high pressure valves (IBR approved) for boiler Details
 
8Tender for supply of relay testing kit for different type testing generator relay panel, distance protection testing, 6.6kV/415V relay testing Details
 
8Tender for supply of various types of clamp for 220 kV switchyard Details
 
8Tender for purchase, erection, including foundation of conductor/cable measuring machine Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Flender opens new wind generator plant in Chennai Details
 
8Suzlon to launch Rs 10K crore wind power projects Details
 
8India’s Solar Generation Jumps 49% in July; Wind Output Rises 5% Details
 
8KELTRON Invites Bids For Solar Power And Street Light Projects Across North And East India Details
 
8India needs a grid revolution Details
 
8How ReNew Cuts Carbon Emissions & Grows Clean Power in India Details
 
83 Strong Undervalued Power Stocks in India to Watch in August 2026 Details
 
8India’s Power Capacity Push Strengthens Data Centre And Technology Investment Case: Piyush Goyal Details
 
8India Adds Record 3 GW Open-Access Solar in Q2 2026 Details
 
8Vikas Poddar Appointed Chief Financial Officer at Torrent Power Details
 
8Emerson software supports India’s largest battery energy storage system Details
 
8Talabira II & III coal mine records highest-ever production of 19.14 MT in FY 2025-26 Details
 
8Rongjie Energy Signs MOU with JSW Energy for 5 GWh Energy Storage Systems Details
 
8India’s Electrical and Electronics Sector Steps Up R&D Investment Details
 
8SECI Discovers Rs 5.99/kWh Tariff for 4-Hour Peak Power Details
 
8Could India Become a Perennial Market for Nepali Electricity Details
 
8Lineage Power Secures 100 MWh BESS Order from Kalpa Power Details
 
8Jefferies’ power play: 8 stocks with up to 43% upside; JSW Energy, Adani Energy top picks Details
 
8India Crosses 300 GW Clean Energy Capacity Milestone Details
 
8India AI Data Centres to Drive 191 TWh Power Demand, Creating Huge Renewable Energy Opportunity Details
 
8Tata Power Renewables Commissions 190.5 MW Solar FDRE Project in Rajasthan Details
 
8NLC India’s Talabira II & III Mine Achieves Record 19.14 MT Coal Production in FY 2025-26 Details
 
8NHPC Advances 2,000 MW Subansiri Lower Project as Rotor Assembly Begins for 250 MW Unit 7 Details
 
8Gujarat Industries Power Co. reports Rs 402.41 Crore profit, recommends Rs 4.10 dividend Details
 
8Rajasthan targets 125 GW renewable capacity by 2030, steps up push for fresh investment Details
 
8Bharat Heavy Electricals announces senior management change as Rs 50 crore contract gains attention Details
 
8India Proposes New Power Export Charge for Bangladesh Details
 
You can also click on Newsclips for more Details
81. UJVN's Rs 1,024 Crore Lakhwar Hydro EPC Tender Gives Bidders Just 32 Days for a 300 MW Package UJVN's electro-mechanical EPC notice for the 3x100 MW Lakhwar project sets a bid window running from 24 July to 25 August 2026 — unusually tight for a package of this scale and technical breadth. The notice doesn't specify EMD, PBG, reverse auction or qualification thresholds, leaving bidders to price against an incomplete risk picture. A tender-list webpage compounds the confusion by showing the pre-bid date as the closing date.

82. UJVN's Lakhwar Hydro Tender Extends by a Week as a 15% Security Premium Locks In for Manufacturer-Backed Bidders Corrigendum No. 1 pushes UJVN's Rs 1,024.45 crore Lakhwar EPC deadline from 25 August to 1 September 2026, giving bidders more time to assemble OEM authorisations and financial evidence. Beneath the schedule relief sits a steeper security structure: performance security rises from 10% to 15% where qualification relies on manufacturer credentials, on top of a Rs 20.50 crore EMD and a 270-day bid-validity clock.

83. UJVN's Tiuni Plasu Hydro Tender Rewrites Its Own Rules Across Six Addenda and 181 Days UJVN's Rs 259.60 crore EPC package for the 2x36 MW Tiuni Plasu HEP has seen its bid deadline move from 12 March to 9 September 2026 while addenda deleted contract-value experience thresholds, doubled the permitted OEM count from one to two, and quietly removed dedicated vibration and partial-discharge monitoring even as guaranteed output rose. The qualification bar simultaneously shifted from project pedigree to a steep Rs 260 crore turnover test for manufacturer-backed bidders.

84. UPPCL's Undefined GeM Bid Demands Rs 148 Crore Turnover for 13 Mystery Units UPPCL's GeM tender for the 132 kV Martinpurwa substation names a Rs 148.20 crore turnover threshold and a 180-day bid-validity lock, but never discloses what the 13 procured units actually are — no ratings, technical scope, EMD, PBG or delivery terms appear anywhere in the record. Bidders are being asked to commit capital and pricing certainty against a near-total information vacuum.

85. RVPN's Ajmer GIS Tender Turns a 15%-Below-Estimate Bid Into an Automatic Security Penalty This companion filing on RVPN's Hathi Bhata substation tender details how ITB Clause 32.1 charges additional security equal to 50% of the shortfall the moment a bid drops more than 15% below the Rs 143.63 crore estimate — while a parallel 15% floor on erection and civil pricing blocks the opposite strategy of front-loading supply value. Railway-block charges beyond two hours also shift onto the contractor, adding a live-line execution risk to an already interface-heavy GIS-and-cable package.

86. RVPN's Jaipur GIS Tender Shows a Rs 50 Lakh Gap Between Its Own Estimate and the Portal Figure RVPN's Shiv Enclave substation package lists Rs 83.38 crore in the bid document against Rs 83.88 crore on the state procurement portal — a discrepancy that needs resolving before price evaluation can proceed cleanly. Layered on top is a 15% anti-skew pricing floor, loss-capitalised cable and transformer evaluation, and a threshold-triggered additional security mechanism nearly identical to RVPN's sister tenders.

87. OPTCL's Kalahandi Transmission Tender Can't Decide If Completion Takes 18 or 24 Months OPTCL's Rs 104.02 crore Padepadar-Mukhiguda package states "18 months" numerically in one clause while spelling out "twenty four" months in words in the very same provision, with a separate clause independently confirming 24 months. The document also mislabels the interconnected substation's voltage class and leaves PBG, LD and bid-validity terms undisclosed — turning basic schedule interpretation into a pre-bid clarification priority.

88. JdVVNL's Jaisalmer RDSS Tender Makes GIS Data Entry Part of Physical Completion TNTW-795's Rs 120.42 crore turnkey package requires contractors to geotag every new or upgraded asset on JdVVNL's platform "without additional payment" as a condition of payment release, on top of layered security for abnormally low or supply-heavy bids. A portal-versus-SBD mismatch over bid-opening time — 11 am against 5 pm — adds a procedural wrinkle bidders can't safely ignore.

89. JdVVNL's Churu RDSS Tender Shrinks Its Effective Bidding Window by Quietly Moving the Publication Date TNTW-798's Rs 133.13 crore package states an RFB release of 14 August 2026, but the procurement portal shows publication only on 20 August — cutting roughly six days from the nominal bidding period. Three different technical-opening times appear across the tender set (11 am, 3 pm, 5 pm), while individual BOQ quantities can swing by plus or minus 50% after award.

810. MSEDCL's Rs 387 Crore SCADA-Ready Switchgear Tender Can't Agree on Its Own Breaker Rating MSEDCL's 3,599-unit ring-main-unit procurement describes a "400 ampere" vacuum circuit breaker in its headline section while the detailed specifications repeatedly call for 200 Amps — a conflict that directly affects fault-duty design, CT coordination and price. Type-test validity windows (5 years vs 10 years) and turnover thresholds (30% vs 60%) diverge just as sharply between the two document layers.

811. JdVVNL's Bikaner RDSS Tender May Have Double-Counted Feeders From a Neighbouring Package TNTW-796's Rs 120.01 crore package lists feeder-bifurcation entries under SDGH and Nokha even though those locations are separately assigned to sister tender TNTW-797 — a package-boundary ambiguity that could distort quantity pricing and survey planning. A descending-value, multi-package bid-capacity mechanism across eight concurrent RDSS tenders also means winning one package can block a bidder's access to financial opening on others.

812. OPTCL's Puri Underground Cable Tender Can't Settle Whether It's a One-Stage or Two-Stage Bid OPTCL's Rs 121.99 crore Samagara-Samuka 132kV cable-and-bay package calls itself a "single stage two part system" in the IFB while the procurement portal labels it "Two Stages" — a live classification conflict alongside a document-availability window that moved five days without any identified corrigendum. Route length, jointing method, protection integration and completion period are all left undefined at notice stage.

813. RPCL's Rs 188.80 Crore Yeramarus Coal Tender Swaps a Declared Grade for a Destination-Tested GCV Benchmark An addendum replaces "G8 grade" with "GCV 5050 Kcal/Kg (ARB)" across RPCL's domestic coal-supply pricing schedule — making unloading-end calorific measurement, not mine-side grade declaration, the operative commercial benchmark. The mechanism ignores any GCV surplus above 5050 while penalising shortfall, and a Rs 377.60 crore turnover threshold keeps the bidder pool narrow.

814. NTPC's Mouda Ash-Evacuation Tender Lets the Utility Cut Contracted Volume to Zero NTPC's Rs 83.17 crore pond-ash tender for Nagpur permits total contract variation from minus 100% to plus 20%, meaning a contractor can mobilize a full fleet within 15 days and still see the entire order disappear without compensation. A mandatory 50:50 split between two vendors and a 10%-below-estimate security trigger complete a tightly engineered risk-transfer package.

815. KPCL's Bellary Coal Tender Corrects a Grade-Mismatch Flaw But Halves the Supplier's Challenge Window KPCL's addendum aligns its Bellary coal price schedule with the same GCV 5050 Kcal/Kg (ARB) benchmark used at Yeramarus, closing a gap between declared grade and destination-tested acceptance. In the same breath, the referee-sample objection period shrinks from 14 days to seven, and post-award mine substitution is permitted only at a rate capped at the original quote — leaving suppliers with logistics flexibility but no corresponding price protection.

816. NTPC's Telangana Stage-II BOP Tender Adds a Full Flue-Gas Duct Scope Mid-Bid and Bills Consortiums an Extra 2% NTPC's international competitive package for Telangana Stage-II (3x800 MW) saw two deadline extensions totalling 40 days while Technical Amendment No. 02 converted "Nil" placeholders into a complete flue-gas ducting scope from the ID fan outlet to the chimney. Consortium bidders now face a dedicated 2% system-integration security on top of the standard 10% performance guarantee, aimed squarely at interface failure between the newly expanded balance-of-plant scope and the steam-generator package.

817. NTPC REL's 300 MW Nokhra Solar Tender Absorbs 60 Days and 12 Amendment Instruments Before Bid Close NTPC Renewable Energy's Nokhra solar EPC package saw its deadline move from 22 June to 21 August 2026 while accumulating seven corrigenda and five addenda — a volume of post-issue intervention suggesting the technical baseline was still being finalised well after the tender's original launch. A Rs 20 crore EMD locks in serious bidders even as completion schedule, LD structure and grid-interface boundaries remain undisclosed.

818. JPDCL's Udhampur-Chenani Tender Is Titled a "DPR" But Its BOQ Demands a Full 67 km Turnkey Line JPDCL's Rs 538.15 lakh notice calls for a "DPR for laying of 33 kV alternate line," yet the underlying BOQ requires 440 poles, 67 km of ACSR conductor and complete survey-to-energisation delivery — a title-versus-scope mismatch serious enough to distort how bidders price the job. An undisclosed formula lets JPDCL demand extra security from any bid 15% or more below its Rs 538.15 lakh estimate, with no stated ceiling.

819. OPTCL's Balasore-Chandipur Cable Tender Repeats the Same Portal-vs-Notice Date Conflict Seen Elsewhere OPTCL's Rs 147.97 crore underground 132kV package between Balasore and Chandipur shows a five-day gap between its notice's stated document-availability start and the portal's actual opening, while "single stage two part" and "Two Stages" again appear as conflicting descriptions of the same bidding structure. Route length, jointing design, outage coordination and completion period remain undefined at notice stage, just as in OPTCL's other underground-cable tenders.

820. OPTCL's Narendrapur-Chhatrapur Cable Tender Leaves Just One Hour Between Bid Closing and Opening This Rs 102.39 crore underground 132kV package carries the same notice-versus-portal date mismatch as OPTCL's other cable tenders, but adds a tighter operational squeeze: bid closing at 14:00 and techno-commercial opening at 15:00 on the same day, leaving virtually no buffer to resolve last-minute submission issues. Two live-substation bay extensions again sit inside the turnkey scope without a disclosed interface matrix.

821. OPTCL's 400 kV HTLS Reconductoring Tender Bundles Line Upgrade With Substation Bus Work Under One EPC OPTCL's Rs 301.22 crore Meramundali-Mendhasal package requires replacing twin AAAC Moose conductors with High Temperature Low Sag conductors while simultaneously upgrading equipment and bus systems at both substation ends — concentrating tower-adequacy, thermal-clearance and terminal-compatibility risk in a single contractor. The tender's document-download window closes just 15 minutes before bid submission, and the same one-stage/two-stage labelling conflict from OPTCL's other packages reappears.

822. NTPC's North Karanpura Ash-Water Tender Fixes a Pipeline's Minimum Length But Not Its Maximum NTPC's AWRS package for the 3x660 MW plant instructs bidders to price "3.5 km or actual, whichever is maximum" for the return-water pipeline — locking in a pricing floor while leaving the upper bound entirely open pending detailed engineering. A late-added requirement to bury 11 kV lines wherever they cross higher-voltage transmission corridors surfaced only after bidder questioning, adding an unpriced electrical-scope change deep into the bidding cycle.

823. NTPC Mining's Chatti Bariatu Coal-Handling Award Closes 16.6% Below Its Nearest Rival BTL EPC Limited won NTPC Mining's Rs 200.31 crore coal-handling contract at a price 16.6% below L2 and 26.1% below L3, after amendments doubled the magnetic-separator count, raised pipe-conveyor clearance from 3 to 5.5 metres, and shifted fire, dust-suppression and auxiliary water sourcing from existing infrastructure onto contractor-developed borewells. The wide L1-L2 gap raises the question of whether the winning bid fully priced in the expanded utility and interface risk transferred through those late technical changes.

Details
 For reference purposes the website carries here the following tenders:
 8Tender for service contract for framework agreement for assistance in miscellaneous work Details
 8Tender for erection testing commissioning trial operation and handing over of electrostatic precipitator of unit 7 at 1x800 MW Details
 8Tender for major overhaul of turbine and generator Details
 8Tender for supply of 25000 sets of 30KN strain disc hardware (metal parts for rabbit and weasel conductor) Details
 8Tender for supply of 500 sets of 22kV AB switch with PT insulator Details
 8Tender for procurement of various electrical materials for electrical maintenance work Details
 8Tender for replacement of 33 kV GIS C.T. at 132 kV S/S Details
 8Tender for civil works for construction of 01 No. 132 kV line Details
 8Tender for civil works related to increasing capacity 2x160 1x100 MVA to 3x160 MVA at 220 kV sub station Details
 8Tender for civil works related to increasing capacity 2x40 1x63 MVA to 3x63 MVA 1 No 132 KV bus couplar bay Details
 8Tender for construction of 132kV main bus bar extension throught XLPE cable, 132kV switchyard Details
 8Tender for upgradation of the existing SAS based 132kV GIS substation to 220kV GIS substation Details
 8Tender for construction of 220 kV DC with Zebra equivalent HTLS conductor line Details
 8Tender for construction of UG 132 kV TSS line Details
 8Tender for construction of 132 kV DC line Details
 8Tender for connecting and extending the pipeline Details
 8Tender for procurement of caustic soda lye Details
 8Tender for complete residual life assessment of boiler Details
 8Tender for site enabling works package Details
 8Tender for supply, installation and commissioning of FOTE system Details
 8Tender for assistance in the execution of various works Details
 8Tender for repair and maintenance of damaged portion of bypass Details
 8Tender for annual maintenance contract (AMC) of external firewall installed Details
 8Tender for procurement of tools and plants for transmission line Details
 8Tender for diversion of 400kV D/C TL line Details
 8Tender for construction of coal lab Details
 8Tender for repair of 40/50 MVA 132/33kV power transformer Details
 8Tender for procurement of 400kV CVT Details
 8Design, supply, erection and commissioning of mono rail for lifting arrangement of drainage and dewatering system Details
 8Tender for annual maintenance of generating units of 31.4 MW turbines and generators assemblies Details
 8Tender for annual civil maintenance and repair works of barrage Details
 8Tender for purchase of 45ton gantry crane with lifting beam Details
 8Tender for supply, erection and commissioning of battery bank and battery charger at substations Details
 8Tender for repair of damage drains to safeguard machinery including damaged brest walls Details
 8Tender for erection/ construction of tin shed for the DG set and storage of spare transformers lying Details
 8Tender for construction of new 110kV bay for the erection of 25MVAr capacitor bank at 110kV substation Details
 8Tender for laying of HT UG cable Details
 8Tender for empanelment of agencies for new 33/11 kV substation, additional /augmentation of PTR at existing 33/11 kV S/s, HT lines, LT lines Details
 8Tender for procurement of lubricating oil pump installed in 8.5 E9 ABL make coal mills Details
 8Tender for procurement of electrical actuators and spare parts Details
 8Tender for procurement of collecting electrode of ESP Details
 8Tender for excavation, loading and transportation of pond ash Details
 8Tender for complete rewiring of A, B and C type Details
 8Tender for restructuring of old 400kV system of PH 3, up gradation existing SCADA system of 400 kV system Details
 8Tender for procurement of bibby resilience coupling and spare grid spring for PA, SA fan and coal mill gear box Details
 8Tender for proposal for procurement of complete HP valves and various recommended spares of valves installed Details
 8Tender for procurement of lubricating oil pump installed in 8.5 E9 ABL make coal mills Details
 8Tender for work of soil investigation at ash pipeline Details
 8Tender for supply and on-site fabrication and installation of 03 sets of upper turbine cover relieving pipe along Details
 8Tender for routine repair maintenance and occasional breakdown maintenance of hydro mechanical and electrical equipments Details
 8Tender for procurement of bladders with seal kits for various accumulators installed Details
 8Tender for procurement of spare BTS 2000 relay used in bus transfer scheme of 11kV unit switch gear installed Details
 8Tender for procurement of triple screw pump assembly for coal mill lube oil system Details
 8Tender for in-situ drilling, tapping and plugging work on embedded draft tube for assembly of upper and lower loose flanges on draft tube of 250 MW francis turbine Details
 8Tender for procurement of different type of MCBs & MCCBs Details
 8Tender for operation & comprehensive maintenance of existing SBR based 0.4 MLD sewage treatment plant Details
 8Tender for procurement of capacitive voltage transformers (CVT) and potential transformer Details
 8Tender for procurement of lighting arrestor (LA) or surge arrestor (high class) for different Voltage level Details
 8Tender for procurement of 33 kV circuit breaker (CB) for different Details
 8Tender for construction of 33 kV s/s Details
 8Tender for new 33 by 11 kV sub-stations augmentation or addition capacity including associated line Details
 8Tender for supply of insulation resistance tester Details
 8Tender for earthing of power transformer at 33 kV S/S Details
 8Tender for construction of tubewell for power earthing and water supply arrangement Details
 8Tender for renovation of electric fitting and yard lights at various Details
 8Tender for construction of 33kV S/S Details
 8Tender for hiring, erection and dismantling of M.S. cup lock type scaffolding Details
 8Tender for requirement of sodium hexa meta phosphate Details
 8Tender for supply of spares for pumps at AHP Details
 8Tender for supply of LT shackle and metal parts Details
 8Tender for supply of LT single phase channel cross arm, LT three phase channel cross Details
 8Tender for supply of 11 kV single pole standalone structure material complete set Details
 8Tender for supply of LT MS 4 way pillar boxes Details
 8Tender for giving of LT/HT SC line Details
 8Tender for restoration of 132 kV GIS sub station and its associated transmission line Details
 8Tender for work of nano technology based acid and alkali resistant nano-modified anti corrosive coating on transmission tower Details
 8Tender for work of chemical washing of Disc/PLRI strings of various 400 kV Tr. lines Details
 8Tender for work of supply and installation of advance multi cable transit system Details
 8Tender for creation of 400/220 kV switchyard Details
 8Tender for establishment of 220/22 kV substation Details
 8Tender for work of removal, supply and application of spray thermal insulation on drive turbines Details
 8Tender for biennial rate contract for repairing, replacement, and maintenance of damaged, torn, and burnt NN fire resistant conveyor belts Details
 8Tender for ARC work of erection of 66kV equipment, structures, control wiring, yard lighting etc. Details
 8Tender for erection of equipment and structure, control wiring, yard Details
 8Design, supply, erection, testing & commissioning of conversion work of existing 132kV S/C line Details
 8Tender for stub strengthening of 220kV D/C line Details
 8Tender for supply of MS grill for walkways of boiler & coal mill Details
 8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes Details
 8Tender for supply of various ratings LT motor Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8India needs rapid battery storage expansion as renewable capacity rises Details
 
8India hits $0.068/kWh tariff in 4-hour peak renewable power tender Details
 
8Telangana accounts for 70 pc of major coal mine mishaps in India Details
 
8Prakash Industries secures environmental clearance for Bhaskarpara Coal Mine expansion Details
 
8India’s coal fleet must learn to flex or its solar boom will keep hitting a wall Details
 
8Govt weighs supply-profile tweaks to rescue stalled RE bids Details
 
8Chhattisgarh to emerge as leading State in Solar Energy: Chief Minister Sai Details
 
8India's Solar Cell Imports Hit $3 Billion, Sparking Industry Woes Details
 
8Acme Solar, PTC Industries in Focus After MarketSmith Report Details
 
8SaurEnergy Explains- What It Actually Takes to Power a Gigawatt Data Centre Details
 
8Floating solar: Can it be India’s next renewable energy success story Details
 
8Chhattisgarh CM Vishnu Deo Sai discusses solar boost at Samvad 2026 Details
 
8Nuclear energy could power India’s future Details
 
8Power sector at tipping point as SC takes up DERC plea today Details
 
8Rising FDRE, RTC volumes to drive electricity futures market growth Details
 
8Tariff, technology & FDI: India Inc flags key concerns in draft nuclear rules Details
 
8World Wisdom Forum : J&K’s youth power key to India’s development story: LG Details
 
8Tata Steel Ludhiana Secures India’s First BIS Certification For Octagonal Billets Details
 
8BERC panel proposes Tk 6.48 solar power tariff for MPPs Details
 
8The physical and financial losses in Nigeria’s power sector Details
 
8Mukul Agarwal and Madhusudan Kela back these 2 recently listed power microcaps Details
 
8Power Sector: Jefferies Bullish on Private Players, Picks Adani Energy and JSW Energy as Top Bets Details
 
8Insolation Green Energy Pvt Ltd receives 9 contracts of solar power projects from MSEDCL Details
 
8Govt weighs supply-profile tweaks to rescue stalled RE bids Details
 
8India Targets 'Electro State' Shift With 300 GW Milestone Details
 
8The Real Crisis Is Not Electricity, But Energy Details
 
8Hyundai Motor India Share: Nomura Maintains Buy, Sees 25% Upside on New Launch Pipeline Details
 
8Defence Minister Rajnath Singh sets sights on global shipbuilding: Can India become the next maritime power Details
 
You can also click on Newsclips for more Details
8The ERPC order records Bihar's firm entitlement in Farakka I&II at 0.000%, relinquished, and hands Punjab a 20.585% firm share it never previously held. The transfer runs 39 days, from midnight on 23 August, and moves central power from a state that stopped wanting it to the state with the window's worst evening shortfalls. Details
8The August investor presentation aggregates what no state discom tender shows alone: of 20,920 MW of thermal PPAs awarded under recent SHAKTI-linked state rounds, 13,945 MW went to Adani Power - including every megawatt awarded by Bihar, UP, Maharashtra and Assam. The same deck records FY26 EBITDA and profit lower than a year earlier, and a 42,050 MW target that rests on capacity not yet built. Details
8ICRA reaffirmed both Axis Wind Farms SPVs on the strength of their ultimate parent, not their counterparty. The rationales document a payment regime in which the better the wind year, the more free power Andhra Pradesh's discom receives - a dispute now before the AP High Court. Details
8The Q1 FY27 numbers show a company growing at 125% with its best-ever margin; the transcript shows a lead-acid battery plant at Bawal written down by Rs 143.6 crore after a fire, and a restart that waits on the insurer. The stop-gap, disclosed only in the call: rent someone else's operating battery plant, with a deal expected in about a month. Details
8The covering letter announces a routine subsidiary acquisition; Annexure A discloses that promoter Dr Faruk G. Patel personally holds 8.95% of the target being bought with the group's paper. The target, incorporated in November 2021, took its revenue from Rs 30.62 crore to Rs 213.98 crore in two years. Details
8NLDC's Sunday bulletin reports a 200 MW evening shortfall, confined to the Northern Region - the mildest reading of the three-day window. Every forward-looking instrument for Monday says the opposite: buy bids at twice the sell volume, a clearing price up 28% in a day, term-ahead trades at the Rs 10 cap, and the costliest fleet on the system scheduled hours in advance. Details
8The notified Sixth Amendment reduces what renewable open-access consumers pay for parking surplus power with the grid, from the Rs 1.50 a unit charged since February 2024. The two decisions that will be felt longest sit below the headline rate: a proviso that zeroes the charge for any discom that fails to file sworn data, and a Statement of Reasons that forecloses every refund claim for the past two and a half years. Details
8Seventeen GSECL solar projects built under Gujarat's 2019 land-subsidy scheme are feeding the grid with no tariff determined and no payment received, and the state generator now wants 95% of its claim provisionally. The Commission's answer was to put GUVNL, the buyer, on the stand: claimed tariffs exceed the Rs 1.50 a unit both parties once confirmed, capital costs run past the Rs 4 crore per MW the scheme assumed, and no independent prudence check was ever done. Details
UP's regulator clears a Rs 4,239.50 crore wires slate and repairs its 4,000 MW hydro tender

8UPERC approves 24 transmission schemes worth Rs 4,239.50 crore - and trims the YEIDA substation by the Rs 22 crore it was double-counted
8UPERC rewrites three clauses of UPPCL's 4,000 MW hydro tender - bidders lose the right to guess their own transmission cost
8Dhariwal's Rs 38.93 crore substitute-coal claim against Noida Power is admitted - Rs 11.38 crore of it still unpaid
8PVVNL asks UPERC to keep India's interstate blockchain power-trading pilot alive - hearing 27 August

Bihar's regulator writes two consumer checks into the smart prepaid rollout

8Chargeable service-cable replacement now needs a JE's signature - BERC closes the SOP it ordered in December
8Prepaid arrears in Bihar will be recovered over 12 to 24 months by slab, effective immediately

Two benches tip their hands while the cases stay open

8KSERC records that INKEL's stuck wind "merits priority" - and sends KSEB's chief engineers to the next hearing
8Tarini's 16-year-old small-hydro tariff case now runs on a Supreme Court clock - with an expert-appointment fight inside it

A connectivity swap approved, a supply code redrafted

8WBERC lets the Sprng group swap the grid connection behind CESC's 100 MW hybrid PPA - tariff and CUF untouched
8Karnataka proposes one supply code to replace six - with a doubled EV-charging mandate and outage counts printed on bills Details
A doubled top line meets its depreciation bill

8Insolation's revenue doubles to Rs 745 crore; profit falls 12% as the expansion's interest and depreciation land

Governance signals from the annexures

8One in four institutional votes opposed Harsh Goenka's commission at KEC's AGM - the resolution still passed with 90.43%
8IREDA removes its entire Projects-wing senior management layer in one board stroke - no successors named
8Refex Renewables' promoter block consolidates into one entity at 74.87% - a whisker under the ceiling

Distress, data centres and an IPO reprice the mid-market

8India Power Corporation's creditors meet today to re-publish the invitation for resolution bids
8A hyperscale Hyderabad data centre orders Rs 52.86 crore of cables from Diamond Power - its data-centre book passes Rs 575 crore
8Lumino Industries opens a Rs 700 crore IPO this week on a Rs 3,149.88 crore order book
8Vedanta Aluminium hands S&S Power's subsidiary its largest-ever order - "more than Rs 50 crore" is all the filing says Details
Firm power and wires print their auction prices

8NTPC's renewable arm takes 500 MW of SECI's assured-peak tender at Rs 6.00 a unit
8The Bajaj–NIIF transmission venture lands its first competitive win - 270 km of 765 kV works for Gujarat's renewable corridor

Rooftop procurement, priced by mode

8UPNEDA floats 16 MW of government-building solar at Rs 104.37 crore - storage doubles the price per megawatt Details
Scarcity pricing spreads while the other market rooms stay empty

8The Rs 10 ceiling now binds nine hours a day - and the market built for exactly this cleared zero all weekend
8Delhi, Rajasthan and UP go shopping for peak blocks - reverse auctions running from tonight through October

The north's evening problem, measured in shed load and empty reservoirs

8Punjab shed 1,210 MW on Saturday evening as northern reservoirs run 23% below last year

Sunday's renewable slump flipped the balancing books

8Wind and solar fell 157 million units in a day - reserves swung from 7,000 MW of down-regulation to 8,000 MW up

The part-load bill lands on Bengal

8Backing down ER thermal has cost Rs 163.58 crore in four months - West Bengal owes the largest single line Details
Cover thins at the plants while one state's coal turns cheaper

8Plant coal cover holds at 53% of the norm with 32 plants critical - and the daily report itself went missing on Sunday
8Cheaper coal hands Chhattisgarh's consumers back Rs 25.48 crore for May

Telangana's water bank is half empty

8Telangana enters peak season with 1,087.7 million units of hydro energy in storage - down 45% on last year, and Nagarjunasagar down 73% Details
Captive power waits at the appraisal table

8Hindalco's 300 MW captive expansion is deferred for more data - the EAC wants its unbuilt 2012 clearance explained
8Two pumped-storage projects totalling 2,800 MW reach the hydro appraisal committee on 31 August Details
MNRE gives time on war risk and lists new cell capacity

8Renewable projects get up to four months of force-majeure time for the West Asia situation - but no blanket extension
8The ALMM cell list adds 9.8 GW in one revision - Waaree, Avaada and EMMVEE enter with TOPCon capacity

CEA's own tables undercut two flagship timelines

8A scheme 99.8% complete has no money for FY27 - and MoP quietly deleted two J&K works from another
8FY27's thermal additions stand at 2,260 MW of a 7,300 MW target - with a Rs 40,413 crore cost overrun on the fleet under build

A ten-day lifeline flows west to north

8Uttarakhand gets 100 MW from the western unallocated pool - for exactly ten days, then the map snaps back Details
REGULATORY ORDERS AND PROCEEDINGS

8Haryana's FY15–FY17 tariff remand stalls on the utilities' own unfiled compliance
8HPPC's review against GI Hydro moves to arguments on 12 October
8Lumax and Cleanmax's open-access settlement claim gets a reply timetable
8Exide's companion open-access petition runs on the same clock
8ASK Automotive's challenge to deviation charges reaches arguments on 28 September
8UPPCL's excess-energy-charge claim against Prayagraj Power waits till 13 October
8Dhariwal's Rs 4.99 crore change-in-law true-up against Noida Power is admitted
8Garda Solar's shared-evacuation test case is preponed to 17 September
8Amplus RJ Solar withdraws its 100% banking fight - the 2024 regulations resolved it
8The companion Amplus Solar Shakti petition dies the same death

COMPANIES AND RESULTS

8MSEDCL takes its twice-lost JSW dispute to the Supreme Court
8NHPC's Jalpower merger hearing is postponed with no new date
8Power Mech files the resignation letter it omitted two weeks ago
8Epic Energy allots 1,98,000 shares on warrant conversion, collecting Rs 74.25 lakh

PROJECTS AND TENDERS

8REC's Luhri transmission SPV goes to Terralight for Rs 4.13 crore all-in

GRID AND MARKET PULSE

8This week's inter-state transmission loss is 3.21% - solar-hour blocks run above 4%
8The outage fleet holds near 49,000 MW as Kudgi, Bellary and JIPL return
8India stayed a net importer from Nepal all weekend

FUEL AND SUPPLY

8Hirakud spills through 15 gates while Odisha's hydel fleet averages 765 MW
8Jayant's jump to 38 million tonnes clears its first, earliest gate Details
 For reference purposes the website carries here the following tenders:
 8Tender for stub strengthening of 66kV line on 132kV tower Details
 8Tender for mechanical & stub strengthening of 66kV S/C H frame / tower line Details
 8Tender for work of providing maintenance free treated earth electrodes Details
 8Tender for biennial maintenance works (masonry & carpentry) Details
 8Tender for biennial maintenance works (masonry & carpentry) to RB’s Details
 8Tender for biennial maintenance works (masonry & carpentry) to RB’s and NRB’s Details
 8Tender for construction of bridge across Details
 8Tender for purchase for solar projects Details
 8Tender for providing assistance in miscellaneous jobs Details
 8Tender for R&M of supply and apply of insulation Details
 8Tender for Package of HVAC system of 4x111 MW Details
 8Tender for supply and installation of new street light pole and lights Details
 8Tender for work of installation of addl 315 KVA DTR Details
 8Tender for work for 11 kV line bare to covered conductor Details
 8Tender for survey installation testing and commissioning of new 33/11kV substation Details
 8Tender for construction of new 33/11 kV substation Details
 8Tender for work for installation of addl DTR 19 No. 200 KVA, 05 No. 315 KVA with LT line and 11 kV line Details
 8Tender for rate contract for supply of various size of LT aerial bunched cable with insulated messenger wire Details
 8Tender for construction of new control room, cable trench, junction box Details
 8Tender for procurement of TG spares set for 210 MW turbine Details
 8Tender for RCC flooring work for newly proposed electrical site store Details
 8Tender for procurement and erection of rigid type discharge electrode made of formed pipe with fixing clamp/ fasteners Details
 8Tender for biennial work contract for routine maintenance as well as preventive and predictive maintenance of various auxiliaries, equipment and systems installed Details
 8Tender for biennial maintenance contract of elevators installed Details
 8Tender for procurement of complete gearbox of gearbox installed in LP vacuum pumps Details
 8Tender for work contract for supply cum application of pad type ceramic fiber blanket insulation for HP and IP turbine Details
 8Tender for procurement of spare parts of compressor hub assembly and carbon brush holder bracket assembly for 588MVA,21kV turbo generator installed Details
 8Tender for procurement of critical spares for instrument air compressors Details
 8Tender for procurement of local PVR cabinet with PVR10 electronic positioner module interface module Details
 8Tender for work contract for re blading of impeller and refurbishment of journal portion Details
 8Tender for work contract of routine maintenance of boiler firing and coal feed system, complete fan group along Details
 8Tender for procurement of spares for 36 gravimetric raw coal feeder Details
 8Tender for procurement of spares for condensate extraction pump Details
 8Tender for supply of electrical actuator for ID Fan & PA Fan Details
 8Tender for procurement of beater plate for coal mill Details
 8Tender for repair of damage and old granite/marble flooring, water proofing treatment and other miscellaneous work Details
 8Tender for supply and installation of crash rated hydraulic bollards Details
 8Tender for work of Bi-annual AMC for planned and breakdown/ emergency substation maintenance work along with spares Details
 8Tender for construction of HT line Details
 8Tender for construction of 2X5 MVA 33/11 kV substation Details
 8Tender for construction of 2X5 MVA 33/11 kV substation, its 33kV line Details
 8Tender for supply of various types lighting arrestors and isolator blades Details
 8Tender for supply of various types clamps, connectors and LED lights at 220kV sub-station Details
 8Tender for construction of complaint centre allied civil works at 33 kV S/Stn. Details
 8Tender for various civil works along with renovation of switch house Details
 8Tender for ARC for De-weeding of raw water pond Details
 8Tender for repair of damage drains to safeguard machinery including damaged brest walls Details
 8Tender for procurement of spare material Details
 8Tender for supply, erection & commissioning of 5 Nos RTU in 33/11kV indoor substation Details
 8Tender for work of 66kV line Details
 8Tender for repair of old U-fencing at 220kV s/s Details
 8Tender for outsourcing work of ETC of new 66 kV S/S Details
 8Design, manufacture, testing, supply and delivery of 220kV isolators and 220kV isolators with earth switch and spare 220kV solid core insulators Details
 8Tender for work of rewinding / repairing of various capacity AC & DC motors Details
 8Tender for procurement of various size of MS bolt and nuts, MS washer Details
 8Tender for procurement of 11kV AB switch with PT insulator Details
 8Tender for procurement of moving contact for 11kV AB switch Details
 8Tender for running works contract for the erection works of LT overhead feeder, HT overhead feeder, structure erection works Details
 8Tender for shifting of existing HT/ OH line convert into HT 3C X 300 Sq.mm UG cable Details
 8Tender for supply and erection of new earth pit with earth mat Details
 8Tender for R&M work of erection, commissioning of new feeder bay HV & LV equipment’s, testing, earthing, control wiring etc. Details
 8Tender for work of erection, commissioning of equipments, testing, control wiring etc Details
 8Tender for R&M work of mechanical and stub strenghtning, painting work of 66kV line Details
 8Tender for procurement of complete enclosure for feed gate for overhauling Details
 8Tender for procurement of different sizes of MS pipe Details
 8Tender for procurement of 100 MT caustic soda flakes Details
 8Tender for biennial maintenance contract of Ten (10) nos. elevators Details
 8Tender for annual contract for the job for engagement of backhoe cum loader Details
 8Tender for procurement of tandelta kit and transformer test kit Details
 8Tender for landslide stabilization and rockfall protection works Details
 8Tender for erection of 33 kV line with 3Cx400 Sqmm XLPE UG cable Details
 8Tender for work of checking the online health monitoring of CTs, PTs, Las and work Details
 8Tender for hotspot scanning of various transmission lines Details
 8Tender for annual contract for miscellaneous work Details
 8Tender for replacement of failed and burnt transformer, CTPT Details
 8Tender for replacement of failed and burnt transformer Details
 8Tender for supply of various MS / CS pipe, bend Details
 8Tender for supply of various lighting LT cables for electrical fuel section Details
 8Tender for supply of carbon steel, mild steel, alloy steel pipes and its fittings Details
 8Tender for supply of various consumables, measuring instruments, Tools tackles, CPVC and fasteners items Details
 8Tender for dismantling old damaged UCR compound wall & constructing RCC CW at various Details
 8Tender for miscellaneous civil works for 400/220/100kV substations and switchyards Details
 8Tender for repairs of BHEL make radiators & replacement of radiators in 298.6 MVA BHEL make converter transformer Details
 8Tender for work of monkey patrolling of S/C & D/C towers Details
 8Tender for work of Bi-annual maintenance contract for internal inspection, attending oil leakages through HV & LV bushing with oil filtration & other TF related accessories/activities Details
 8Tender for work of annual maintenance contract (AMC) for line maintenance works & attending emergency breakdown of various EHV lines Details
 8Tender for work of providing & fixing of manual operated gear box for 245/145/33/11kV isolators at various substations Details
 8Tender for procurement of various types of spare (relays) of converter transformer Details
 8Tender for supply, installation, testing, commissioning of fully, inverter centralized HVAC Air conditioning system Details
 8Tender for work of carrying out earthing audit (health assessment) of existing earth mat Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
 8Tender for work of applying polyamine base glass flake renforced anticorrosive protective coating Details
 8Tender for supply of control panel spares of pump house Details
 8Tender for work of repairing of various pulleys of conveyor belts Details
 8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details
 8Tender for HT/LT/TC erection and maintenance work Details
 8Tender for supply of electrical actuator for feed control valve Details
 8Tender for work of overhauling of ESP pass Details
 8Tender for misc. civil works Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
Rising demand, Make in India focus driving manufacturing growth in India, but speed bumps need to be addressed, say experts Details
 
8IWTMA Flags State-Level Bottlenecks to India’s 10 GW Annual Wind Growth Target Details
 
8Govt mulls capex-based subsidy support to add 30 GW Polysilicon manufacturing capacity by 2030 Details
 
8Aegeus Technologies lists on SME Index as Brigade REAP pioneer Details
 
8India must integrate the working of its renewable energy sector with its coal-based power sector for successful energy transition, says new CSE study Details
 
8Telawne Power Equipments Expands Operational Footprint by 61,837 Sq. Ft. to Support Global Power Infrastructure Growth Details
 
8Decoding Power Generation Economics: Thermal vs. Renewable Energy Details
 
8Renewable Energy in India: Growth Story, Policy Push & What's Next Details
 
8Vedanta Power Puts Energy Efficiency at the Heart of a Cleaner Energy Transition Details
 
8India Solar Open Access Capacity Surges 42% YoY Details
 
8RECPDCL Hands Over Luhri Power Transmission Ltd to Terralight Solar Energy Details
 
8US nuclear industry set to make detailed submissions to India on SHANTI Act Details
 
83 Fundamentally Strong Infrastructure Finance Stocks in India Details
 
8India’s data-centre capacity quadrupled to 1.7GW in six years; AI boom set to drive 8x power demand by 2035: BNEF Details
 
8Sustainability and Energy Practitioners’ Association launches student cell Details
 
8Oriana Power Wins 31.42 MWp Solar EPC Contract in Bihar Details
 
8Hosts One-Day Conference in Kolkata to Deliberate on Emerging Reforms in Indian Power Market Details
 
8Pranos Fusion is building the machinery India would need to generate power from fusion Details
 
8Power Semiconductors: India’s Pathway From Market Lag to Manufacturing Hub Details
 
8India’s Renewable Energy Breakthrough: Firm Power Challenges Coal on Price and Reliability Details
 
8India’s core sector scorecard: Core sectors propelling Indian economy vs those pulling it down Details
 
8India’s Energy Strategy: CSE Pitches ‘Flexible Coal’ To Balance Renewables Details
 
8Power Grid Corporation secures Rs 822.91 crore tariff-based project in Gujarat Details
 
8NTPC Renewable Energy Floats Tender for 600 MW Wind Power Project in Andhra Pradesh Details
 
8Indian NBFCs See Strong Q1 Profit Growth Amid Mixed Segment Trends Details
 
8PFC Shines Five Gold Awards at ASSOCHAM Corporate Bond Market Summit 2026 Details
 
8AI capex slowdown could derail India's cyclical recovery, weigh on growth: Nuvama Details
 
8FPIs Pump Rs 4,393 Crore Into Auto Stocks In August H1 Details
 
You can also click on Newsclips for more Details
81. NTPC's Talcher Ash-Backfill Tender Forces a Mandatory 50:50 Split and a Diesel Clause That Contradicts Itself NTPC's Rs 84.81 crore GeM tender for ash backfilling mandates splitting the award between two agencies rather than letting L1 take it all. A 10%-below-estimate discount triggers immediate Additional BG liability, while the diesel price-adjustment clause states two different base dates in the same document. Payment hinges on the lower of two measurements plus full daily digital proof — physical delivery alone won't guarantee payment.

82. MCL's Rs 641 Crore Bharatpur Coal Contract Leaves Bidders Guessing Who Controls the Split GeM's portal says "bid splitting not applied" and "ePBG: No," while MCL's own NIT and ITB preserve the right to split work and separately mandate 5% Performance Security. Bidders must quote one percentage for the whole scope without knowing if it survives intact. The gap between portal flags and contractual language creates real interpretation risk before a rupee is bid.

83. ECL's Five-Year Mine Contract Closes 14% Above Estimate on a Dewatering-Plus-Highwall Bundle Eastern Coalfields awarded Rs 450.99 crore against a Rs 395.46 crore base — a 114.04% premium — for a package combining 90-day emergency dewatering, specialist highwall coal extraction and conventional OB handling. Eight bidders competed, three were rejected technically. The premium suggests the market priced integration risk rather than racing to the bottom.

84. NTPC REL's 600 MW Wind Tender Locks Full Documents Behind a Signed NDA Bidders must execute a confidentiality agreement just to download NTPC Renewable Energy's complete Anantapur wind bidding package. Turnover qualification scales directly with quoted capacity up to a 660 MW ceiling, while ten years of comprehensive O&M sits behind a Rs 50 crore bid security. The real competition is as much about lifecycle bankability as turbine price.

85. SJVN Green Energy's 1000 MW Solar Tender Hides a Security Gap Worth Up to Rs 100 Crore SGEL's turnkey solar-with-land EPC package demands a 28-year lease and mandatory Punjab grid connectivity even for Rajasthan-sited projects. Beneath that sits a stark mismatch: the NIT specifies Rs 10 lakh/MWac bid security while the portal shows a flat Rs 10 lakh figure. The NIT's own precedence clause resolves it — but only for bidders who read closely enough to notice.

86. JdVVNL's Phalodi RDSS Corrigendum Reveals a Supply Split That Breaks Its Own Rule Corrigendum-1 discloses the package is roughly 84.5% supply and 15.5% erection — comfortably above the 70% threshold that JdVVNL's own ITB 37 treats as evidence of an unbalanced bid. A contractor pricing in line with the owner's own cost structure risks triggering additional security meant to catch aggressive front-loading, not honest estimation.

87. RVPN's Ajmer GIS Tender Turns Cable Efficiency Into a Priced Commercial Variable RVPN's Rs 143.63 crore Hathi Bhata package pairs a new GIS substation with 6.99 km of underground EHV cable, then capitalises cable losses directly into bid evaluation. A cheaper but less efficient cable can lose its apparent price advantage once losses are monetised. Eighteen months and a stepped delay-recovery regime leave little room for interface slippage.

88. RVPN's 220 kV Jaipur Cable Tender Polices Underpricing and Front-Loading in One Move The Rs 128.54 crore NPH-VKIA package requires civil and erection charges to stay above 15% of quoted supply value while punishing bids more than 15% below estimate with additional security. Final cable route and drum lengths aren't even fixed until two months after award. Manufacturing and route engineering must overlap inside an already tight 15-month schedule.

89. MSEDCL's Rs 155.85 Crore Conductor Tender Keeps Every Lever in the Utility's Hands Bidders can quote as little as 20% of tendered quantity, but MSEDCL alone controls size mix, dispatch timing, supply withholding and reallocation of undelivered volumes. Pricing is firm for nine months with no broad escalation cover. Manufacturers are effectively bidding against an operating schedule, not just a headline rate.

810. JdVVNL's Bikaner RDSS Tender Can't Agree Whether Commissioning Takes Eight or Nine Months TNTW-797's bidding document allocates eight months to supply-erection-commissioning after survey, while Appendix-4 separately states nine months for the identical activity — both claiming a nine-month total. Since liquidated damages attach directly to the completion baseline, this isn't cosmetic drafting; it's an unresolved trigger point for future disputes.

811. UPCL's Rs 262 Crore Uttarakhand Tender Qualifies Bidders Through Their Breaker Supplier UPCL's 12-substation package requires PMA vacuum circuit breakers from an OEM with 2,000+ units supplied and 200 operating for a year — effectively vetting the EPC contractor through its equipment partner. A five-year AMC and layered security push the real capital commitment well past the headline construction figure. Twelve dispersed sites with line lengths up to 14 km each carry distinct execution risk.

812. RVPN's NPH-VKIA Cable Tender Offers a Rare Schedule Concession on Clearances Alongside its usual anti-skew and loss-capitalisation controls, RVPN grants penalty-free time extensions where statutory clearance or ROW delays are properly documented and pursued. It's a partial counterweight to a tender that otherwise stacks financial pressure onto bidders at every turn. The balance still favours the owner, but not entirely.

813. RVPN's Shiv Enclave GIS Tender Extends Cable-Joint Guarantees to 62 Months Post-Commissioning The Rs 83.38 crore Sanganer package layers three separate security instruments: project-level performance guarantee, transformer-specific security, and an extended guarantee on cable termination and jointing kits. That last layer survives more than five years after commissioning. Interface risk with the existing Mansarovar-Sanganer network runs just as deep as the equipment specification.

814. NSPCL's Durgapur Mill Tender Slips 115 Days as Spares Quantities Flip-Flop NSPCL's coal-pulveriser R&M package has moved its bid deadline across at least 11 revisions, from May to August 2026. Mandatory pump-assembly spares were cut from 24 to 3 units, then explicitly restored to 24 "as per the Original BOQ." Bidders are pricing a brownfield boiler-integration risk against a specification still being rewritten deep into the bidding window.

815. TGTRANSCO's Rs 405 Crore Transformer Tender Makes Factory Capacity the Real Contest TGPMM26-14 splits 46 transformers into four reverse-auctioned lots, each demanding one unit per month after the first delivery. Collaboration-only manufacturers face bank guarantees up to 20% of contract value. Price variation is capped upward at 50% but uncapped downward — asymmetry that favours the buyer throughout.

816. TGTRANSCO's Sister Transformer Tender Lets Itself Swing Quantities by Half, Penalty-Free TGPMM26-15's Rs 339.49 crore procurement allows TGTRANSCO to alter ordered quantities by up to 50% both at award and mid-execution without renegotiating unit prices. Combined with lot-wise reverse auction, bidders must reserve manufacturing slack they can never contractually price in. The same asymmetric price-variation ceiling as its companion tender applies.

817. NSPCL's Coal-Mill Tender Tightens Wear Guarantees While Its Spares List Yo-Yos Beyond the schedule churn, NSPCL removed a wear-life correction formula entirely and now requires mills to hit 90% capacity even near end-of-life grinding elements. The wear-guarantee demonstration population shrank from three units to two. Meanwhile mandatory spares swung from 24 to 3 and back to 24 across successive amendments.

818. UPRVUNL's Jawaharpur Gypsum Auction Stretches Its Runway Five Months, Refuses to Fix Quality UPRVUNL's two-year, 3.92 lakh MT FGD-gypsum sale pushed its auction date from February to July 2025, giving buyers far more time to inspect and plan. But the material stays strictly "as available" with no chemistry, moisture or purity specification stated anywhere. Quality risk sits entirely with the buyer under caveat emptor terms.

819. BHEL's Darlipali Ash-Handling EPC Keeps One Contractor Liable Across Orders It Can't Shape BHEL's turnkey package for NTPC Darlipali splits one LOA into supply, service and civil work orders that BHEL can regroup at will post-award. A breach under any single order automatically triggers breach under all of them. Milestone withholding at 25 and 31 months squeezes cashflow well before final delay liability is even settled.

820. BHEL's Korba West EPC Drops Reverse Auction After 121 Queries Expose a Moving Target BHEL's combined coal, biomass and mill-reject handling package for Korba West pushed its deadline three times while revised flow diagrams kept arriving through the pre-bid process. Reverse auction was scrapped by corrigendum mid-cycle. One-point EPC accountability spans a 58-month schedule with cross-default rules linking every work order's fate to the others.

821. NTPC's Telangana Switchyard Tender Contradicts Itself on Whether Physical Bank Guarantees Are Even Legal NTPC extended its bid deadline by 47 days while stripping a planned 24x7 safety control room as a "small package" cost cut. One amended clause bans physical BGs outright; another, added in the same round, explicitly allows them. With GIS pricing held firm over 50 months, that contradiction is now a live bid-responsiveness risk.

Details
 For reference purposes the website carries here the following tenders:
 8Tender for supply, dismantling and commissioning of new acid tank (H2SO4 -concentration 98%) with accessories Details
 8Tender for supply and ETC of 14 number 30 M lighting mast Details
 8Tender for re rubber lining of tanks pipes Details
 8Tender for work of diversion of 220 kV DC line Details
 8Tender for shifting height raising of 220kV line Details
 8Tender for civil construction work for increasing capacity from 2/40MVA to 3/40MVA T/F Details
 8Tender for construction of civil work 01 No 40 MVA 132/33 kV transformer bay Details
 8Design, engineering, manufacturing, testing, supply, stringing, installation, testing and commissioning etc. for construction of 132 kV and 220 kV transmission lines on ACSR panther/Zebra conductor Details
 8Tender for construction of 220kV GIS substation Details
 8Tender for construction of 132 kV transmission lines Details
 8Tender for EPC package with land for development of grid-connected solar PV projects Details
 8Tender for repair works at various project Details
 8Tender for balance civil and architectural works of main plant FGD civil works Details
 8Tender for supply erection and commissioning of 20 torch panel welding machine Details
 8Tender for centralized rate contract for two years for supply of various types of HT fasteners Details
 8Tender for replacement and SITC with five years comprehensive AMC of weather monitoring systems Details
 8Tender for supply of 245kV class centre break isolators with and without earth switch Details
 8Tender for rate contract for work of rewinding and repairing of various rating of LT motor, submersible pump and various Details
 8Tender for assistance in carrying out miscellaneous routine works for preventive maintenance of 220kV S/s Details
 8Tender for supply and erection of window type industrial air conditioner and split type air conditioner at 220kV S/s Details
 8Tender for supply of illumination items Details
 8Tender for providing service for dam regulation control system and associated equipment Details
 8Tender for upgradation/replacement of existing substation automation system at 132kV GSS Details
 8Tender for work of painting of boiler and its auxiliaries Details
 8Tender for supply of baskets of air pre-heater Details
 8Tender for erection work of 66kV line Details
 8Tender for supply, erection, testing and commissioning of 220V DC, 63 AH, KPH 63P, Ni-Cd type battery set Details
 8Tender for supply andapplication of metal protective compound for various pipe lines Details
 8Tender for work of routine, preventive, scheduled & breakdown maintenance in coal handling plant Details
 8Design, engineering, manufacturing, supply, erection, testing & commissioning of 132kV and 33kV equipments Details
 8Tender for fabrication work of weather protective shed/canopy on foundations of boiler side HT & LT motors Details
 8Tender for supply of various insulation materials for boiler Details
 8Tender for supply of wireless LCM kit for 220kV and 66kV class switchyard Details
 8Tender for extension of control room for providing 11kV feeder bay for 3MW solar project Details
 8Tender for upgradation of 33kV substation Details
 8Tender for annual contract for civil maintenance works Details
 8Tender for replacement of the firefighting system Details
 8Tender for construction of new control room at 66kV S/Stn Faridabad. Details
 8Tender for overhauling of rotary air preheaters Details
 8Tender for overhauling of fans and associated ducting during forthcoming overhauling of 600MW unit Details
 8Tender for construction of new control room at 66kV S/Stn Nuh Details
 8Tender for construction of new control room at 66kV S/Stn Details
 8Tender for annual maintenance contract of ash dyke I and II and raw water reservoir Details
 8Tender for work of 66kV substation Details
 8Tender for laying HT UG cable including installation of RMUs supply and laying of LT UG cable Details
 8Tender for reconductoring existing OH lines with LT ABC cable Details
 8Tender for providing chain link fencing for the compound of 66kV substation Details
 8Tender for construction of 33 kV s/s Details
 8Tender for supply of 33 kV U/G XLPE 3x300 Sqmm cable Details
 8Tender for supply and erection of 33kV 10km O/H line Details
 8Tender for procurement pilot based small scale standalone decentralized battery energy storage systems BESS systems along Details
 8Tender for construction of 33 kV substation Details
 8Tender for establishing of 220kV single circuit between 220kV GSS Details
 8Tender for construction of 132/33 kV, 2x50 MVA GIS substation Details
 8Tender for construction of 132/33 kV, 2x80 MVA GIS substation Details
 8Tender for const. of 1 No. of 132 kV solar bay Details
 8Tender for const. of foundation for III transformer and associated bays at 132 kV GSS Details
 8Tender for requirement of MIL make control valves (boiler gun corners) for boiler Details
 8Tender for requirement of spares of new allenberry works make speed reducer Details
 8Tender for operation and maintenance of weighbridge, other associated work Details
 8Tender for carrying out vulnerability assessment of IT and OT system and maintaining Details
 8Tender for manufacture, testing, supply & delivery of 1000 nos. SCADA-compatible 11kV vacuum circuit breakers Details
 8Tender for procurement of 66kV control and relay panels Details
 8Tender for procurement of spares for boiler blow down (BBD) pump installed Details
 8Tender for procurement of miniature circuit breakers MCBs, MCCBs and RCCBs of different ratings installed Details
 8Tender for biennial work contract for round the clock preventive and breakdown maintenance of boiler pressure part and its auxiliaries Details
 8Tender for procurement of spares of bomb calorimeter PARR 6400 installed Details
 8Tender for work contract for erection and dismantling of DT, structure, pillar Details
 8Tender for work contract for erection and dismantling of DT, structure, pillar, laying of HT & LT cable Details
 8Tender for erection and maintenance of HT/LT & TC Details
 8Tender for supply, installation and commissioning of bottom ring rail and top ring rail Details
 8Tender for rate contract for executing emergency maintenance jobs Details
 8Tender for procurement of PH and DO probe for SWAS system Details
 8Tender for overhauling servicing for electrical integrals of MOV actuators Details
 8Tender for procurement of 1200 MM conveyor belt Details
 8Tender for procurement of PA fan motor Details
 8Tender for supply of LT distribution box Details
 8Tender for supply loading at factory transportation of TC fuse wire various Details
 8Tender for annual contract for repair and maintenance and up-keeping of water supply system Details
 8Tender for supply of 9kV 10KA polymer lightning arrester Details
 8Tender for procurement of PLCC cards of ABB make ETL/41/42 for establishing MMR PLCC LTS network Details
 8Tender for annual maintenance contract for the work of refilling & providing new spares for existing fire extinguishers available at various EHV sub-stations Details
 8Tender for work of replacement of existing 33kV circuit breaker at various EHV substations Details
 8Tender for various civil maintenance work at 132 kV Sub/stn Details
 8Tender for work of replacement of 132kV, 50/1A metering CT by 132kV, 100/1A metering CT Details
 8Tender for work of various miscellaneous work at 132 kV switchyard Details
 8Tender for day to day maintenance for civil assets sub-station Details
 8Tender for annual maintenance contract (AMC) for work of servicing / maintenance of battery sets and chargers, taking capacity tests of battery sets Details
 8Tender for AMC for work of repairing/overhauling with providing & fixing of spares for 33kV VCB at various EHV sub-stations Details
 8Tender for work of replacement of existing 132kV circuit breaker Details
 8Tender for annual rate contract for the work of atending emergency breakdown works planned maintenance works on various 220/132/100 kV EHV lines Details
 8Tender for shifting of RMU and UG infrastructure Details
 8Tender for Bi-annual ARC for erection of 66kV S/S equipment, structures, control wiring etc Details
 8Tender for Bi-annual rate contract for the work of shifting of various 66/132/220 kV class existing transmission lines Details
 8Tender for erection, testing and commissioning of 66kV TR bay (augmentation) & new 66kV feeder Details
 8Tender for work of shifting of old 66/11kV control room Details
 8Tender for ARC work of erection of 66kV equipment, structures, control wiring, yard lighting etc Details
 8Tender for supply of MS grill and fabrication & epoxy paint of stairs, railing, structure Details
 8Tender for supply of LTSH and economizer coils for boiler stage Details
 8Tender for work of dismantling replacement / repairing of PF pipe, orifice & PF bend of coal mills Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newclips:
 
8Coal India Expands Globally with Singapore Critical Minerals Office Details
 
8Railtel Corporation secures Rs 1,647.87 crore order from Western Coalfields Details
 
8Freyr Energy drops new smart inverters with 97.8% efficiency Details
 
8How India can develop polysilicon manufacturing, the first step in solar production Details
 
8Hindustan Power Secures Rs 1,135 Crore for 435 MWp Solar Project Details
 
8SJVN Green Energy Tenders 1 GW Solar EPC Package Details
 
8Domestic solar cell supply shortage short term, market set to realign soon: Experts Details
 
8AMPIN Energy Transition secures $195 million green financing from SMBC and Rabobank for 100 MW hybrid renewable energy project Details
 
85,000 fault repair workers to get up to Rs 30 lakh financial security Details
 
8Indian Power Sector - Electricity - Electrician Safety In India Details
 
8Over 5,400 Power Sector Legal Cases Stall India Energy Projects Details
 
8Beyond Baseload: Reforming Thermal PPAs for India's energy transition Details
 
8Uttarakhand Proposes Stricter Deviation Settlement for Renewables Details
 
8PFC, REC drop up to 3% as Morgan Stanley downgrades amid loan growth woes Details
 
8Building India’s Skilled Workforce for Clean Energy Targets Details
 
85 Under the Radar Electrical Capital Goods Stocks in India Details
 
8Transmission Constraints Emerge As Key Hurdle To India's Renewable Energy Expansion: ICRA Details
 
8Why India’s DISCOM reforms need data driven decisions, not just infrastructure Details
 
8NLC India Tenders for 1,500 Acres Land in Tamil Nadu Details
 
8Core industries growth slows to 5.4% in July as iron ore, power ease Details
 
8UERC Rejects Review of Solar and Battery Storage Trading Margins Details
 
8Suzlon, IEX, Inox Wind, ACME, NTPC, Power Grid, Tata Power shares: Top 3 power stock ideas Details
 
8India Considers Low-Cost Loans For Renewable Projects Hit By Power Curbs Details
 
8Rhetan TMT Starts Power Generation From 1 MW Solar Project, BIS Certification Opens Access To Government Orders Details
 
8India Power Grid Struggles As Renewables Outpace Infrastructure Details
 
8Solar Stocks vs Traditional Power Stocks Details
 
8Adani Power wins appeal in electricity tribunal, impacting compensation calculations Details
 
8Auto sector stocks today, August 20: Ola Electric gains 1.74%, Hyundai Motor India up 1.16%, Olectra Greentech rises 1.01% Details
 
8POWERGRID Appoints Amol Babulal Taori as CFO, Continues as Director (Finance) Details
 
8Morgan Stanley downgrades PFC and REC to Equal-weight, cuts targets on sharp loan growth slowdown Details
 
You can also click on Newsclips for more Details
8SGEL bundles land into its 1,000 MW two-state solar EPC and keeps price pressure alive through e-reverse auction The NIT fixes the commercial architecture — two envelopes, e-reverse auction, a capacity-linked EMD of Rs 10 lakh per MW — while the entire engineering risk matrix sits in documents still "To be Uploaded". Technical qualification is only the gateway: survivors must surrender price headroom electronically while carrying land, Punjab-Rajasthan execution and five-year O&M exposure. How much capacity to pursue becomes a liquidity decision before it becomes an engineering one.

8UPPTCL's Sector-155 GIS tender taxes bid aggression through a tiered security ladder instead of rejecting low prices Bids up to 10% below estimate attract 0.5% additional security for every 1% of discount, 1% per 1% beyond that, and UPPTCL-designated high-risk firms post 15% instead of 10%. A deemed-in-scope completeness clause and owner-supplied transformers the contractor must still erect and commission concentrate interface risk behind the Rs 112.05 crore headline. The deeper the discount, the more banking capacity a bidder must mobilise to defend it.

8JKPDC's Rs 9.57 lakh design consultancy carries a retention tail that can outlast its 90-day programme by years Ten per cent of every bill is withheld until construction-linked conditions or 12 months after final deliverables, while another 10% of the fee sits behind open-ended execution support with no ceiling on visits or revisions. Soil investigation and possible NIT/IIT proof checking come at the consultant's cost, and Clause 27 resolves drafting conflicts in the department's favour. The modest estimate understates how long the consultant's cash and liability stay locked in.

8KPTCL bundles five station works into one Rs 154.15 crore contract while its portal record describes a computer lab The signed schedule fixes a 17 September bid date and 180-day validity; the KPP metadata shows a 25 August receipt deadline, 90-day validity, a different procuring entity and "Setting up of Computer Lab" as scope. Bidders must plan BG validity, GIS-OEM consents and consortium approvals backwards from dates the public portal contradicts. The refundable 0.1%-per-day stage penalty — returned if the full package finishes within 24 months — is the one meaningful counterweight.

8RVUNL's 1,000 MWh battery tender turns residual cycles into a revenue variable priced at half tariff The BESPA runs a minimum 15 years with a possible five-year extension governed by remaining battery cycles — payable only at 50% of the discovered tariff, forcing degradation and augmentation strategy into the bid model. Turnover is expressly "Not Used"; a Rs 32 lakh/MWh net-worth test and AIF routes open the field to capital platforms, and technology can still change at financial closure. How "remaining cycles" will be measured is the clause the extension economics hang on.

8RREC fragments 146 MW into 1 MW plant-wise awards while leaving its daily-LD formula unstated Plant-wise L1 discovery under a 50 MW cap lets developers cherry-pick sites but can scatter wins into fragmented portfolios, each carrying 25-year RMS, metering and 11 kV evacuation duties. Clause D.8 pegs delay LD to the PBG "on per Day basis" without stating a divisor — no small gap against an Rs 8.75 crore maximum PBG. Post-award land disputes buy no additional time, making site control the real qualification test.

8RREC's Ajmer 158 MW round asks a fixed 25-year tariff to absorb a growing list of non-generation costs The SPG funds 11 kV evacuation, three ABT meters, RMS with 99% data availability, recurring communications and land — including replacement land without schedule relief if the original parcel lands in litigation. Qualification scales with cumulative quoted capacity, so a stretched portfolio bid can disqualify itself outright. The mandatory revolving LC is the bankability counterweight lenders will test first.

8JdVVNL's 0.4% estimate correction quietly moves every qualification gate on the Churu RDSS package A Rs 52.39 lakh revision lifts EMD, all three experience thresholds, MAAT and liquid-asset requirements simultaneously — a clerical-looking reset that borderline bidders must re-screen against. Untouched is the sharper conflict between a nine-month bidding schedule and Part 3's 12-month completion definition, with Part 3 declaring itself supreme. Estimate corrections here are qualification events, not BOQ housekeeping.

8NREDCAP's Tirupati WtE bid strips tariff out of competition and makes public cash the only price With power fixed at Rs 7.95 per unit subject to APERC approval, bidders compete solely on the Grant sought — payable at the lowest of the quote, 150% of equity or 30% of project cost. The authority guarantees 600 TPD with escalating default consequences, while escrow, a standby LC and a confirming party backstop payments. Unreconciled 90-versus-180-day validity and "25% (twenty per cent)" instalment wording are the loose bolts in an otherwise sophisticated frame.

8OPTCL's Pahala GIS package makes interface convergence the real contract as notice and portal disagree on bid structure One EPC counterparty must deliver a new 2x100 MVA GIS, roughly 9.94 km of 220 kV line and two bay extensions inside the live Balianta installation, so slippage at any interface propagates straight into energisation. The signed notice says single-stage two-part; the portal says "Two Stages" — not interchangeable concepts once submission sequencing matters. PBG, payment and LD architecture sit entirely beyond the notice, leaving the decisive risk allocation still unread.

8APEPDCL's hybrid pre-bid corrigendum widens access while the SCADA contract keeps integration risk on one agency The hybrid-mode meeting contradicts the portal's "Offline" label, opening remote engagement before OEM-EPC positions freeze. Behind it sits a Rs 143.32 crore package where 10 lakh tags, ADMS, cybersecurity, 220 V DC conversions and live-substation retrofits share a single payment-gated critical path. A Rs 1.74 crore gap between the portal estimate and the BOQ aggregate is a quiet prompt to reconcile the commercial baseline before pricing.

8RVPN grants 34 more days on its Rs 84.72 crore EHV package without loosening a single risk gate Two corrigenda move closing from 5 August to 8 September while brownfield dismantling, OPGW works, codified land-compensation duties under Rajasthan's 2024-25 notifications and lump-sum quantities executed without extra payment all stand untouched. Price adjustment on tower steel and conductor is real but asymmetric — delayed supplies are priced on the basis most beneficial to the client. The extensions buy preparation runway, not relief.

8BHEL's Talabira ash-handling tender reaches a 13th deadline revision with every entry barrier intact Submission has drifted 94 days from 23 May through near-weekly resets to 25 August, yet the 30 TPH pneumatic, 50 TPH bottom-ash and 60 TPH HCSD credentials, Rs 222 crore turnover test and consortium-liability rules remain exactly as issued. BHEL is protecting competition through time rather than dilution. The next date movement is itself the signal worth watching.

8UPPTCL inserts a mid-lifecycle payment haircut for above-benchmark rates into the Sirsira GIS tender Items priced more than 10% above the higher of SOR or estimate now earn Stage-1 supply payment at 70% of the benchmark, not the quote, with the differential parked behind broadened erection and housekeeping interlocks. The portal's 180-day work period still contradicts the document's 18 months, EMD-exemption entries conflict, and two different amendments both carry the "Corrigendum no. 4" label. Amendment control has become as decisive as pricing strategy.

8OPTCL screens for 765 kV manufacturing capacity first and lets the price war begin only inside a captive pool The Rs 552.07 crore, 21-unit ICT tender demands full-tender-quantity supply history, dynamic short-circuit proof and turnover equal to 100% of the estimate before reverse auction and a 70:30 or 50:30:20 split at L1 economics take over. IEEMA variation is capped at +20% but uncapped downward, shifting the commodity cycle's tail onto manufacturers. A prescribed Rs 5.52 crore EMD coexisting with an embedded nil-EMD declaration is the contradiction no bidder can leave unresolved.

8RVPN's Sawai Madhopur extensions add 34 days while qualification stays anchored to the original opening date Experience tests still reference the originally scheduled opening, so the extra time improves preparation without creating new eligibility. The 500 MVA transformer runs as a contract within the contract — dedicated security, 36-month defect liability and loss LDs of Rs 8-10 lakh per kW — while bids more than 15% below estimate trigger additional security worth half the unbalanced amount. Cheap and disciplined are not the same bid here.

8Two corrigenda keep UJVN's Rs 158.53 crore hydro E&M package in active recalibration The 3x40 MW Sirkari Bhyol electro-mechanical tender concentrates design-through-commissioning accountability in one EPC envelope, so any amendment touching interfaces can shift risk without moving the headline estimate. The lifecycle records two formal revisions whose clause-level content — not their count — will decide whether this is clarification or redistribution. Bid-opening price dispersion will show how the market read them.

8NREDCAP's Vijayawada WtE concession stacks four security layers around a lowest-Grant contest Bidders quoting minimum capital support face Rs 3.24 crore EMD, Rs 16.24 crore performance security, Rs 9.72 crore O&M security and a Rs 25 lakh/MW PPA guarantee — while the payable Grant stays capped by equity and project-cost tests even after winning. Escrow, a revolving LC and confirming-party support attack the municipal-payment problem directly. The RFP's 180 days against the portal's 90, plus contradictory EMD hard-copy rules, are responsiveness traps that precede the economics.

8Mejia solar award leaves L1 defending a 14.4% discount against a market clustered at tender value The Rs 56.92 crore winning bid sits 15.3% below an L2-L3 pair separated by just 0.6% and parked within about 1% of the Rs 66.50 crore benchmark — an asymmetric field, not an evenly fought one. The contract behind that price is fixed, with contractor-funded site intelligence, a 21 MU first-year generation guarantee and a punch-list ceiling halved to 1% mid-tender. The LoA's Rs 6.25 crore "basic" O&M value against a Rs 4.74 crore scheduled payable figure is a billing distinction worth policing from day one.

8Pudimadaka transformer award exposes a 52% price spread across four qualified manufacturers BHEL's Rs 324.94 crore L1 sits 8.7% under L2 before the curve breaks — L3 at 39.4% and L4 at 51.8% above — evidence that short-circuit-test timing, completion-linked cash and factory capacity were priced very differently across the field. NTPC held the 10% completion-linked supply payment and the twelve-month post-LOA test deadline against repeated bidder pressure, conceding mainly the tertiary vector-group alternative. Manufacturing capacity and balance sheet, not design alone, separated the bids.

8Turga PSP access package rejects four of seven bidders before price and awards A 57.1% technical rejection rate — clauses 4.2 and 6.2(IV) recurring across the failures — left three contractors to set the market, with Brahmaputra 6.2% under Dineshchandra and 21.4% under Patel. Bundling the project road with the Main Access Tunnel puts geological, blasting and rock-support risk into one 540-day package. A Rs 7.28 crore provisional sum, roughly 9.3% of L1, means the headline is not the final economics. Details
 For reference purposes the website carries here the following tenders:
 
8Tender for transformer augmentation work of 40 /50 MVA transformer at 220 kV GSS Details
 
8Tender for grouting of foundation and gravelling of capacitor bank bay at 220 kV GSS Details
 
8Tender for installation of 500 Sq. mm and 630 Sq. mm 132 kV XLPE underground copper cable work Details
 
8Tender for purchase of 33kV 1CX630 SQ.MM XLPE insulated armoured aluminium cable Details
 
8Tender for erection of 220/132 kV 160 MVA transformer and associated work Details
 
8Tender for procurement of 2400KW/11kV mill motor Details
 
8Tender for procurement of 2100KW/11kV CW motor Details
 
8Tender for supply, installation, testing and commissioning of the outdoor display unit Details
 
8Tender for supply and amp ETC of 10 number 30 M lighting mast Details
 
8Tender for construction of coal transportation Details
 
8Tender for R&M of barbed fencing work along railway line Details
 
8Tender for demolition of old and damaged civil structures at 400/220 kV substation Details
 
8Tender for CAMC of inverters at PV sites for 5 Years for 75 MW Details
 
8Tender for electrical renovation, rewiring, installation of electrical fittings, lawn lights and associated works Details
 
8Tender for construction and commissioning work for installation of 200 and 315 KVA addl DTR at various Details
 
8Tender for work of installation of addl DTR 05 No. 315 KVA and 03 No. 200 KVA and 11 kV line Details
 
8Tender for work of installation of addl 200 KVA DTR Details
 
8Tender for biennial contract for routine preventive scheduled breakdown maintenance of boiler pressure part Details
 
8Tender for biennial maintenance contract for availing expert services from UPS system Details
 
8Tender for annual maintenance of railway siding Details
 
8Tender for repair / renovation of power house, choked drainage system and other allied works Details
 
8Tender for protection work against sliding earth for upkeeping water conductor Details
 
8Tender for replacement of damaged window panes, painting, repair of drains, construction of septic tank and other civil works Details
 
8Tender for repairs to damaged civil structures Details
 
8Tender for repair and renovation of sumbal link Details
 
8Tender for refurbishing of existing palte earthing system with earth mat lower yard at 110kV substation Details
 
8Tender for capital work of 110kV substation Details
 
8Tender for procurement of 5622100 meters of 1.1kV PVC insulated Al Twin Core 2.5sq.mm PVC sheathed weather proof wire Details
 
8Tender for construction of 110kV substation Details
 
8Tender for providing double bus-bar arrangement with 01 no. of 66 kV bus coupler bay Details
 
8Tender for restoration of damagedrailing of various bridges/ superpassges between Details
 
8Tender for work of construction of civil works for extension of 66 kV double bus bar at 220 kV substation Details
 
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
 
8Tender for annual maintenance of 220 kV single circuit line Details
 
8Tender for SITC of HSD storage tank and associated fuel handling system at 66 kV substation Details
 
8Tender for carrying out geotechnical investigation for protection/ treatment of vulnerable stretches Details
 
8Tender for work of erection of 66kV equipment, structures, control wiring Details
 
8Tender for work of erection of 66kV equipment, structures, control wiring, yard lighting Details
 
8Tender for supply of dry calcium carbonate powder (CaCO3- lime powder) for CFBC boiler Details
 
8Tender for supply of various CS and SS 316L pipes and fittings Details
 
8Tender for supply of PVC cable 2x6 Sq.mm (armoured) Details
 
8Tender for work of providing and fixing of digital panel meters at 220 kV substation Details
 
8Tender for supply, installation and commissioning of 110V 50 Amp. battery charger at 66 kV substation Details
 
8Tender for work of providing, fixing, testing and commissioning of electric surveillance system and associated work Details
 
8Tender for strengthening of switchyard by procurement and installation of 33 kV CTs at 132 kV S/s Details
 
8Tender for supply of 33 kV indoor type circuit breaker at 132kV substation Details
 
8Tender for procurement of 245 kV isolator arm at 220 kV substation Details
 
8Tender for supply, installation and commissioning of 3-phase 440V AC supply distribution box in switchyard Details
 
8Tender for supply, erection, commissioning of 110 V/100 Amp DC automatic battery charger at 132 kV S/s Details
 
8Tender for turnkey extension of existing 245 kV GIS by addition of 245 kV GIS feeder bays Details
 
8Tender for construction of cement concrete pavement around the cooling tower Details
 
8Tender for supply of 110HP ATS (2+1MCC) control starter panel Details
 
8Design, engineering, supply, erection, testing, commissioning and comprehensive operation & maintenance for 5 (five) years for 65 KWp rooftop solar PV power project Details
 
8Tender for supply and repairing of various duct of ventilation system Details
 
8Tender for work of providing services for loading, unloading, shifting and stacking of materials Details
 
8Tender for requirement for hydraulic spares Details
 
8Tender for comprehensive O and M contract of complete AHP system Details
 
8Tender for work of complete repair, refurbishment and reclamation of old damaged feed end and discharge Details
 
8Tender for operation and maintenance of air conditioning system including Details
 
8Tender for procurement of 01 No., 2x600 HP twin power pack diesel hydraulic shunting locomotive Details
 
8Tender for supply of mandatory spare parts and consumable items for 02 nos of automatic bomb calorimeter Details
 
8Tender for requirement of spares of silica, sodium and chloride analysers Details
 
8Tender for annual maintenance contract (AMC) for the various emergency breakdown & planned outage work of 400 kV,220 kV,& 33 kV bays along Details
 
8Tender for work of replacement and retrofitting of existing numerical back up protection relay with line differential inbuilt distance protection relay Details
 
8Tender for providing and erection of 145 kV capacitive voltage transformer CVTs and associated work at 132/33 kV substation Details
 
8Tender for providing fixing and installation of electric fencing and strengthening of safety system of power cables Details
 
8Tender for construction of 12 Nos 33/11kV substations and associated 33kV lines Details
 
8Tender for supply of LT XLPE AB cable 3x120 plus1x95 plus 1x16Sq.mm 400Km Details
 
8Tender for supply of LT three phase channel cross arm Details
 
8Tender for erection of 110KV DC line on DC/MC tower Details
 
8Erection of 110KV DC line on DC/MC tower Details
 
8Tender for supply of back clamp 8 Mtr 10000Nos back clamp Details
 
8Tender for construction of 110/11 kV outdoor control room electrification, borewell, plumbing works Details
 
8Tender for laying of 33 kV, 1 x 1000 sq mm XLPE UG cable Details
 
8Tender for laying of 3x300 Sqmm XLPE UG cable Details
 
8Tender for biennial maintenance contract for dredging of intake channel, pump chamber, silt traps etc. Details
 
8Tender for repairing and painting of pipe, cable rack structure from power house to CW pump house Details
 
8Tender for supply of acid bulk tank for DM plant Details
 
8Tender for erection of 66 kV D/C line on D/C and M/C tower with ACSR panther conductor. Details
 
8Tender for erection of equipment and structure, control wiring, yard Details
 
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Panoli Details
 
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Panetha Details
 
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Bitada Details
 
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Chhidra Details
 
8Tender for work of replacement of existing old/static/obsolete-technology busbar protection schemes at various EHV substations Details
 
8Tender for annual maintenance contract for the work of repairing, overhauling, servicing, maintenance & alignment of 220/132/33kV isolators Details
 
8Tender for construction of compound wall at various at 110kV S/stn Details
 
8Tender for procurement of 750hm unbalanced HF cable for R&M works Details
 
8Tender for work of providing & fixing of non-conductive turbo wind driven conical bird guards on various EHV lines Details
 
8Tender for procurement of insulated modular scaffolding set Details
 
8Tender for Bi- annual rate contract for emergency power restoration work of 400/220/132/66kV lines Details
 
8Tender for work of replacement of rusted tower of 132kV D/C line Details
 
8Tender for Bi-annual rate contract for shifting/modification work of existing various 66/132/220 kV class transmission lines Details
 
8Tender for work of erection, commissioning, transportation, loading & unloading of 66kV equipments Details
 
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
 
8Tender for supply of measuring instrument & tools Details
 
8Tender for BRC order for work of operation & maintenance of vacuum based ash handling plant Details
 
8Tender for supply of limit switches & timers Details
 
8Tender for repair and modification of existing NDCT of 210MW Unit#3 through design, engineering, supply, erection, testing, commissioning and performance guarantee testing of the natural draught cooli Details
 
8Tender for work of erection of 66kV equipment, structures, control wiring, yard lighting Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India’s Steel Expansion Is Deepening Its Coking-Coal Exposure Details
 
8Reliance Industries rises on buzz of Rs 2.73 lakh crore coal gasification project Details
 
8Coal India Arm BCCL Stops Mining At New Akashkinaree Colliery In Dhanbad After DGMS Directive Details
 
8Prism Johnson spurts after securing additional coal linkages worth Rs 70.49 crore annually Details
 
8India’s Power Sector Explained: How the System Works and What’s Changing Details
 
8Beyond Baseload: Reforming Thermal PPAs for India's energy transition Details
 
8How liberalisation pushed power sector from persistent outages to surpluses Details
 
8India’s under-construction renewable pipeline surpasses 150 GW Details
 
8Transmission constraints threaten to curb India’s renewable energy expansion, says ICRA Details
 
84 Power Stocks with Strong Growth Plans in India (2026) Details
 
8Singareni Contributes to National Energy Security Through Coal as well as Renewable Power Details
 
8Amritsar residents embrace solar energy amid rising power costs Details
 
8India Energy Summit & Expo 2026 Concludes in Hyderabad, Highlights Telangana’s Roadmap for a Clean, Secure and Technology-Driven Energy Future Details
 
8Bajel Projects Wins Rs 600 Crore+ 765kV Transmission Order Details
 
8Chennai Data Center Deploys 974 kW BIPV Solar System Details
 
8Amol Taori Appointed as Director (Finance) of Power Grid Corporation Details
 
8Inox Clean Energy completes Vena Energy India buy Details
 
8India hosts 8th BRICS Youth Energy Summit, focuses on energy security, access and innovation Details
 
8Aurora Energy Research launches India’s first grid analytics service as renewable curtailment surges Details
 
85 Power Transmission Stocks with Strong Order Books and Project Pipelines as of June 2026 Details
 
8The sustainability dividend: How renewable energy is reshaping residential real estate Details
 
8Hyderabad C&I Firms Pivot to Solar to Slash Power Costs Details
 
8Freyr Energy Launches SiC Solar Inverters for Indian Rooftops Details
 
8GUVNL Launches 1 GW/4 GWh Battery Storage Tender Details
 
8Exicom Becomes the First Company in India to Manufacture Liquid-Cooled Power Modules for EV Chargers Details
 
8C&I Solar Adoption Surges Amid Rising Grid Tariffs Details
 
8Enviro Infra Engineers forms Wind Earth Pvt Ltd for renewable power Details
 
8Data centre power needs and nuclear push shape India’s energy sector: JM Financial lists big movers in August Details
 
8Siemens Energy, L&T to Hitachi: Jefferies’ 7 ‘Buy’-rated power and T&D picks with 18% to 33% upside Details
 
8Odisha Showcases Energy Transition Vision At India Energy Summit & Expo 2026 Details
 
You can also click on Newsclips for more Details
CORPORATE AND SYSTEM BRIEFS

8CG Power reports suspected cyber incident; core operations remain unaffected
8Adani Energy gets Rs 5,000 crore new bank-loan rating at AA+/Stable

REGULATORY PRONOUNCEMENT RECORDS

8PSERC pronounces Sunny Enclave connection order without publishing the operative result
8PSERC pronounces Preet City connection order without publishing the operative result
8PSERC pronounces two Vector Green GST change-in-law orders without outcomes
8PSERC pronounces seasonal grain-market connection order without the decision
8PSERC pronounces Mihit Solar GST-RCM order without stating the relief
8PSERC pronounces rooftop-solar portal amendment order without publishing the result Details
8Odisha panel backs a 100 MW chemicals complex with a 61.05 MW captive hybrid plan and an unfinished CETP dependency Details
8UERC keeps 4% solar and 5-paise BESS margins after rejecting UJVN's review
8CERC condones 758 of 790 delayed days on Fatehgarh-II transformer and allows Rs 88.57 crore capital cost
8CERC fixes Rs 35.42 crore first-year charges for 14 eastern-grid assets after tariff true-up
8Telangana discoms seek a judicially disputed flag before legacy claims trigger PRAAPTI sanctions
8POWERGRID seeks Rs 282.99 crore clearance to replace 12 reactors and transformers older than 35 years
8POWERGRID proposes bundling Gajuwaka HVDC Pole II with the Rs 853 crore Pole I refurbishment Details
8CEA records 14 of 22 hydro-renovation schemes complete as eight remain in the 2022-27 programme Details
8Om Infra's Rs 2,107 crore order book meets a Rs 640 crore arbitration pipeline still tied up in courts
8India Coke keeps BBB rating as a 0.42% margin and mine delay turn the outlook negative
8Rs 870 crore equity commitment stabilises Radiance's outlook as debt remains 13.5 times operating profit
8Premier Energies gains A+/Positive rating after Rs 3,011 crore of orders and rapid factory expansion
8Energy One lifts cash EBITDA 42% as customer attrition rises to 5.2%
8Vento's renewable pool wins an upgrade while 5 MW of merchant hydro retains tariff and hydrology exposure
8Astrum's solar project pays on time as output trails P90 and leverage stays above six times EBITDA
8DGMS halts New Akashkinaree blasting after subsidence until BCCL proves the mine area safe
8HEG clears the NCLT stage for a 1:1 demerger, but effectiveness still awaits filings and approvals
8Nava targets September for 100 MW solar as Maamba thermal completion moves to mid-2027 Details
8APCPDCL posts 10.16% T&D losses with 256,753 distribution transformers still unmetered
8Kerala regulator ratifies nine power-banking deals while 440 MU of return obligations remain open
8Madhya Pradesh opens three-month green banking but caps it at 30% and deducts 8% in kind
8Day-ahead power price falls 3% while five evening hours clear at the Rs 10/kWh cap Details
8Thailand's 66% gas dependence persists as rooftop-solar payback stretches to six or seven years Details
8MSPGCL's regulatory data-gap reply traces the 660 MW unit from a Rs 4,548 crore DPR to a revised project estimate above Rs 6,900 crore and raises post-commissioning capitalisation to Rs 1,173.62 crore.
8The beneficiary has been asked to choose between completing flue-gas desulphurisation and paying its operating cost, or stopping the system while still absorbing capital already spent. Details
8The Odisha discom recorded 2,302.24 MU of net input, 2,051.97 MU of sales and 250.27 MU of loss in the April-June quarter, equal to a 10.87% distribution loss.
8Its report can state the system-wide result but has far less measurement inside the network, with only 18% transformer metering and incomplete 11 kV coverage. Details
8Japan budgeted JPY 586 billion across four ammonia and hydrogen subsidy programmes in FY2025 while targeting 20% ammonia co-firing in coal plants by 2030.
8IEEFA finds that only one unit has demonstrated the target at scale, while system-wide deployment would require ammonia imports comparable with the entire global traded market of 2019. Details
8TGGENCO's 19 August reservoir sheet put equivalent energy at 1,028.9 MU, down from 1,984.2 MU on the same date in 2025, while live storage fell to 239.0 TMCft from 447.8 TMCft.
8The decline is concentrated in the Krishna basin and especially Nagarjuna Sagar, reducing the hydropower buffer even though the table by itself does not prove an immediate supply shortfall. Details
8Q1 FY27 total income rose 126% year on year to Rs 520.97 crore and infrastructure-development revenue increased 142% to Rs 504.75 crore.
8The scale-up protected project progress but not project economics, as labour, fuel, equipment and transmission-corridor costs reduced gross margin to about 20% from 28% in the preceding quarter. Details
8Purvah Green Power will buy six ReNew special-purpose companies with 1.4 GWp of operating assets at an enterprise value of Rs 4,859 crore and upfront cash of about Rs 1,582 crore.
8Long-term fixed-price contracts provide revenue from the outset, but the debt absorbed with the assets increases leverage before CESC's organic renewable projects add their own cash flow. Details
8CareEdge upgraded Rs 2,643.39 crore of long-term bank facilities to BB-/Stable after the discom resumed information sharing and showed better operating performance.
8The improved rating still rests on state support because delayed government receivables, no tariff increase and a subsidy-heavy consumer mix leave internal cash generation short of debt service. Details
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details
 1 2 3 >  Last ›

Showing 1–50 of 341 items