All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Sep 2026

 For reference purposes the website carries here the following tenders:
 8Tender for supply of aluminum bronze and MS flats required Details
 8Tender for supply of gate valve PN64 for bypass lines Details
 8Tender for supply of hydraulic tools torque wrenches, hydraulic pump and bolt tensioner Details
 8Tender for supply of fasteners for the turbine assembly Details
 8Tender for procurement of PLC system spares for stacker and reclaimer Details
 8Tender for replacement of CLR polymer insulators Details
 8Tender for supply of GI nuts and bolts with washer Details
 8Tender for construction of impervious liner in ash dyke Details
 8Tender for construction of rainwater harvesting facility Details
 8Tender for biennial civil maintenance and misc works of plant Details
 8Tender for sheeting and miscellaneous civil work for existing shed Details
 8Tender for award of contract for system strengthening works for survey installation testing and commissioning of new 5MVA 33 /11kV substation Details
 8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details
 8Tender for complete engineering, design, supply, erection, commissioning and testing of Variable frequency drive VFD system Details
 8Tender for procurement of 220V DC RXM relay, opening and closing buffer and limit switch for MV switchgear Details
 8Tender for annual operation of 02 Nos tube well pumps and water supply including watch and ward of pumps Details
 8Tender for operation of control room of beehar barrage including watching and recording of water level Details
 8Tender for supplying and installation of 100 MT fully electronic modular welded design type pit less weighbridge Details
 8Tender for procurement of various spares for SWAS system Details
 8Tender for strengthening of the existing plate and pipe earthing Details
 8Design, manufacture, testing, supply installation and commissioning of 33/11 kV containerized substation comprising of 33 kV RMU, 11kV AIS including supply of cable termination kits Details
 8Tender for fabrication and supply of galvanised steel yard structures for substations Details
 8Tender for RMU associated UG cable Details
 8Tender for supply of MCCB for 160 Amp and 200Amp suitable for LTDB Details
 8Tender for construction of internal grid roads at 220 kV substations Details
 8Tender for contract for fishing of pond Details
 8Tender for procurement of 200KVA station transformer Details
 8Tender for work of replacement of deteriorated H-frame and mechanical strengthening and stub strengthening work of 66kV line Details
 8Tender for providing RCC pavement in HPS switchyard Details
 8Tender for supply of mill internal spares Details
 8Tender for supply, installation and commissioning of FRP street light poles Details
 8Tender for rate contract for retrofitting and strengthening of machine foundations Details
 8Tender for supply of heat shrinkable type straight joint kits suitable for 11kV, 3 x 300 sqmm cable Details
 8Tender for procurement of 1000 Nos tapping channel cross arm Details
 8Tender for supply of outer and inner sleeve for LT 4x240sq.mm cable. Details
 8Tender for supply of 11kV polymer composite PIN insulator Details
 8Tender for supply of 11 kV standalone complete set of structure materials Details
 8Tender for supply of 11kV polymer composite DISC insulator Details
 8Tender for earth work excavation, stub setting, concreting, supply, transport and erection of 110 kV DC line on DC tower Details
 8Tender for rectification replacement of defective tubes in LTSH coils economizer hanger Details
 8Tender for rectification replacement of defective rear arch goose neck bends tubes and water wall reducer tubes and allied works Details
 8Tender for providing transformer plinth, structural plinths, cable duct, fire protection wall & AH , VC , WC tower arrangements Details
 8Tender for manufacture and supply of 7/2.5 mm GI stranded wire Details
 8Tender for repairing of dam site internal road from dam control room along power channel Details
 8Tender for fabrication, supply and erection of 415V AC, 50KA, LT AC panel Details
 8Tender for work of replacement of existing 0.2 ACSR panther conductor along Details
 8Tender for work of providing & fixing of maintenance free earthing and renovation of existing earthing system Details
 8Tender for miscellaneous fabrication and steel work in various Details
 8Design, engineering, supply, erection, testing, commissioning of 20 KWp rooftop solar PV power project Details
 8Tender for supply of 110HP ATS (2+1 MCC) control starter panel Details
 8Tender for Bi-nnual rate contract for erection of 66kV transmission lines Details
 8Tender for conversion of exist. 66kV S/C H-frame line to S/C panther line Details
 8Design, supply, installation, retrofitting, testing and commissioning of 220kV bus bar panel/scheme, 220 kV bus coupler relay Details
 8Tender for supply of dry calcium carbonate powder Details
 8Tender for supply of contactors Details
 8Tender for miscellaneous civil works Details
 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metal-clad draw-out type VCB panels Details
 8Tender for procurement of different hardware for 132kV and 220kV transmission lines Details
 8Tender for work of capacity enhancement of 132kV bus from single moose to twin moose Details
 8Tender for providing and replacement of insulator string and other accessories at 132kV lines Details
 8Tender for annual routine maintenance preventive and breakdown of 220kV lines Details
 8Tender for annual maintenance contract preventive of 220kV and 132kV transmission lines Details
 8Tender for special repair and maintenance of project Details
 8Tender for procurement of complete pulley assembly Details
 8Tender for common procurement of HT fasteners nut, bolt and washers Details
 8Tender for biennial contract for repairing and maintenance of sanitary and plumbing works in and around plant Details
 8Tender for service contract for round the clock operation of BOBR rakes unloading and paddle feeder operation job Details
 8Tender for biennial mechanical maintenance contract of coal handling plant Details
 8Tender for procurement of 11 Nos. 420kV and 05 Nos. 245kV capacitive voltage transformer Details
 8Tender for OH of air/flue gas duct, expansion joint Details
 8Tender for repair and maintenance of the flume line along with other associated civil works Details
 8Tender for diversion of 11kV feeder Details
 8Tender for supply of rubber item & consumable items for ash handling plant Details
 8Tender for supply of various protective shields, guide pipes Details
 8Tender for work of cleaning of bus ducts/MCCs, actuator overhauling, and cable dressing works Details
 8Tender for various civil maintenance work of switchyard & other allied civil works Details
 8Tender for annual maintenance contract (AMC) for work of overhauling / servicing & alignment of various make 220kV, 132kV & 33kV isolators installed Details
 8Tender for augmentation of substation by providing of 1X25 MVA 132/33kV T/F along with HV&LV bays Details
 8Tender for work of augmentation of substation by addition of 25MVA, 132/33kV power transformer along Details
 8Tender for supply of various types of cable & dismantling, ETC work of 36 kV circuit breakers at various S/Stns Details
 8Tender for work of radiator cleaning of convertor transformer & smoothing reactor Details
 8Tender for biennial maintenance contract for the work of replacement of failed / sick substation equipments Details
 8Tender for work of replacement of old earthing pipeline and sanitary related maintenance works of Qtr and CR at 132kV S/Stn Details
 8Tender for work of servicing / overhauling of operating mechanism of 245kV kV& 400kV SF6 circuit breakers Details
 8Tender for supply of spares & complete mechanism overhauling of 132kV circuit breakers at 132kV S/s Details
 8Tender for work of providing & fixing of sheet moulding compound (SMC) chequered sheet cable trench covers for indoor application Details
 8Tender for work of health assessment of grounding system and soil resistivity measurement (earthing audit) of existing earth mat at various S/Stns Details
 8Tender for work of supply, erection, testing commissioning of an additional 1X 25MVA 132/33kV power transformer along Details
 8Tender for work of supply, erection testing and commissioning of additional 132/33 kV, 50 MVA power T/F along with HV, LV bay & 33kV bus extension Details
 8Tender for work of servicing, repairing & overhauling of ABB make 245kV & 145 kV circuit breakers Details
 8Tender for work of supply of 22/33 kV circuit breaker Details
 8Tender for augmentation of substation by providing additional 1X50 MVA 132/33 PTF along with HV& LV bays Details
 8Tender for augmentation of transformation capacity by additional transformer 132/33 kV, 1 X 50 MVA at 132kV S/stn Details
 8Tender for dismantling old RCC concrete structure & erection of EHV equipments on new lattice type GI structure at 220kV substation Details
 8Tender for supply, erection & commissioning of 10 MVA, 66/11 kV step down transformer at switchyard Details
 8Tender for supply, installation & commissioning of automated chlorine dioxide (ClO2) generation system Details
 8Tender for supply of various consumable items required for routine maintenance/AOH Details
 8Tender for providing waterproofing treatment on terrace Details
 8Tender for providing and fixing PVC water tank Details
 8Tender for dismantling of existing rail table assembly and erection, alignment, testing & commissioning of new rail table assembly of wagon tippler Details
 8Tender for erection and maintenance of HT/LT/TC work Details
 8Tender for providing & laying underground cabling & jointing work Details
 8Tender for conversion of existing 11kV bar conductor line Details
 8Tender for BRC for work of rewinding and overhauling of 11kV HT motors Details
 8Tender for supply of various insulation materials for boiler Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
India Has the Sun, But Where Is Its Concentrated Solar Industry Details
 
8Geothermal Energy: A New Chapter In India’s Clean Energy Journey Details
 
8Enviro Infra Ltd secures 190 INR-Crore wind power project order from Tata Power Details
 
8REIL Invites Bids For 15 MWp Rooftop Solar Projects Under RESCO Model Details
 
8Gains for power stocks depend on execution, valuations Details
 
8India’s power demand hits record August high as heat and weak monsoon stretch grid Details
 
8CRISIL: Power Sector Investments to Drive 100–200 bps Revenue Growth for Large EPC Companies to 9–10% Details
 
8India's Rs 9,150b power grid push could drive new aluminium demand Details
 
8Mahatransco IPO Takes Shape as Maharashtra Power Utility Eyes Rs.10,000-Crore Share Sale Details
 
8Nepal floods halt contentious hydropower exports to Bangladesh via India Details
 
8ISMA Conference 2026: Sugar industry eyes green hydrogen, SAF and CBG to power India’s energy security Details
 
8Solis Marks India Milestone with First EverCore 1.04 MWh Energy Storage Deployment in Chennai Details
 
8Geothermal Energy: India’s quiet bet on a new renewable asset class Details
 
8Windergy India 2026 to Spotlight India’s Wind Manufacturing and Export Potential Details
 
8Renewable Energy Funding and M&A Roundup: Key Global Trends Details
 
8Northern Coalfields improves operational performance with retreating rains Details
 
8ICRA: Cement Companies to Expand Green Power Capacity to 6 GW by FY2028 Details
 
8Coal India output jumps 40% as rains ease; power-sector supplies rise 27% Details
 
8CIL Accelerates Coal Output as Monsoon Eases, Power Sector Dispatch Jumps 24% Details
 
8India Power Demand Hits 260 GW, Strains Coal Supply Details
 
8India Launches Rs 2 Crore Solar Heat Scheme to Cut Industrial Fossil Fuel Use Details
 
8Cement majors line up Rs 13,000 crore green power push; capacity to rise 50% by FY28 Details
 
8Cummins India to showcase integrated power solutions at bauma CONEXPO India 2026 Details
 
8Power Finance Corporation appoints joint statutory auditors for FY 2026-27 Details
 
8SECI Aggregates MSME Power Demand to Cut Renewable Costs Details
 
8Power Mech Bags Rs 970 Crore O&M Order From Vedanta Power's Sakti Thermal Plant Details
 
8DEE Development Engineers reports a total order execution of Rs 87.37 crores for August 2026 Details
 
You can also click on Newsclips for more Details
NHPC's Rs 496.90 crore Dulhasti Stage-II E&M package gains a full crane chapter and loses half a point of turbine efficiency
8A post-publication corrigendum inserted four EOT crane installations with tandem rotor lifting and an obligation to raise capacity without extra cost, while the responsiveness threshold fell from 94.5% to 94%.
8Four closing-date extensions have stretched the bid window without touching the 38-month execution clock, leaving the question of whether relaxed efficiency can offset unpriced interface quantities.

NTPC Renewable's 600 MW Anantapur wind tender gives bidders a week more to price but no way to ask why
8Corrigendum No. 1 pushed submission to 22 September 2026 while leaving the 1 September query deadline untouched, so late-discovered ambiguity has nowhere formal to go.
8With Rs 50 crore bid security, ten-year comprehensive O&M and roads, pooling and evacuation all outside the WTG package, the unresolved issue is who carries commissioning delay at the boundary.

 

JdVVNL rewrites the BOQ a third time and swaps Bikaner territories between two RDSS packages
8Corrigendum 3 moved Dungargarh and Nokha into TNTW-796 while DD-I, DD-II and Khajuwala travelled the other way, settling the value at Rs 119.89 crore — a net movement of about 0.1%.
8That small headline change can conceal much larger line-item additions and deletions, which is precisely what bidders repeatedly queried before the revision.

 

AEGCL's Khumtai 400kV GIS tender carries a Rs 50 lakh EMD contradiction and a 12-month schedule gap
8The invitation and ITB 2.37.1 set two years for completion while SCC 8.2 requires 36 months, and the EMD reads Rs 5.5 crore in numerals against "Rupees Five Crore only" in words.
8Turnover and financial-resource thresholds carry the same numeral-versus-wording conflict, making eligibility itself uncertain before the 12 October closing.

 

GETCO's Viksit Gujarat @2047 adviser tender records two turnover thresholds twenty times apart
8The GeM page states Rs 48 crore while the RFP and buyer-added conditions demand Rs 1,000 crore, and submission and opening dates differ by a day between portal and document.
8With GST treatment also contradicted between two clauses, the tender risks producing technically incomparable bids priced on different assumptions.

 

GETCO's Rs 210.62 crore Bharuch cable package lets each approved OEM back only one bid
8Amendment-I restructured qualification into OEM, nominated-OEM and two-member JV routes, then barred any firm from appearing in different roles across competing bids.
8The contest may therefore be settled by early OEM alignment rather than by how many erection contractors can qualify.

 

KPTCL's Rs 131.92 crore Byadagi package reaches the market tagged as a computer lab
8The portal lists bid validity as 90 days against the signed document's 180, describes the scope as "Setting up of Computer Lab", and keeps the clarification window open 30 minutes after bids close.
8A Clause 3.2(e) heading referring to a 100 MVA transformer against a 160 MVA requirement compounds the risk of divergent qualification readings.

 

RRVUN cuts the coal experience bar by 6.25% and then quietly extends group credentials to technical qualification
8Amendment-I lowered the single-contract threshold from 1 million MT to 9,37,500 MT and admitted IPP supplies; Corrigendum-I then widened 100%-owned parent or subsidiary reliance from financial to both technical and financial PQR.
8JV and consortium participation stays barred, so the widening favours tightly held corporate groups rather than assembled bidding alliances.

 

WBSETCL's Sadarghat composite package republishes its evaluation clause with a broken cross-reference
8Amended ITB 28.2 now reads "DP = Differential price calculated according to0", severing the link to the calculation method in ITB 28.4, while the reverse-auction cross-reference disappears entirely.
8Reverse-auction clause 9 separately dispenses with additional security where L1 is "less than 20% of the estimated cost" — a literal reading that relaxes protection at the lowest prices.

 

NHPC raises generator efficiency loading 20.6% on the Rs 641.11 crore Uri-I Stage-II package
8The turbine equalisation rate moved from Rs 8.32 lakh to Rs 8.74 lakh per 0.1 percentage point, while the generator rate jumped from Rs 21.64 lakh to Rs 26.10 lakh.
8Cheaper machines with weaker guarantees can now lose their price advantage at evaluation, even before PLCC relocation and revised cooling-water scope are priced.

 

WBSETCL's 68 km Salboni 400 kV line tender resolves a 60 mm creepage conflict but keeps ROW with the contractor
8The pre-bid response directed bidders to the technical specification's 430 mm over the BOQ's 370 mm and issued a revised BOQ, while fixing conductor diameter at 28.62 mm and sag at 15.93 m.
8Tower-footing compensation, trees, crops and access remain contractor-priced with no escalation for court-driven delay, and the 24-month clock survives two extensions.

 

RRECL's 201 MW solar tender slips 63 days and then adds a letter of credit
8Four corrigenda moved submission from 14 July to 15 September 2026 while the nine-month commissioning obligation and 25-year term stayed fixed.
8The pre-bid addendum inserted a revolving monthly LC and replaced the client's first charge over liquidated assets with priority application of proceeds — a lender accommodation whose value depends on the still-ambiguous "Cover-1 & Cover-2" opening language.

 

HPSEBL extends its Rs 3.72 crore Kinnaur-Spiti PMC tender for the fifth time without explaining why
8Corrigenda I to V added 64 calendar days to both submission and technical opening while leaving scope, staffing, securities and the 246 man-month deployment untouched.
8The unresolved question is award mechanics: a 70:30 QCBS formula and an English e-reverse auction sit in the same document with no stated hierarchy.

 

GETCO shifts LD on the Rs 224.80 crore Dholera-II GIS package from the delayed portion to the whole contract
8SCC clause 41 now calculates 0.5% per week on the full contract price capped at 10%, recoverable across GUVNL group contracts, while requests to extend 30 months to 34 and to substitute PEB for RCC were refused.
8A local civil or commissioning slip can now generate package-wide exposure on a site carrying saline conditions, seismic zone 5 and cast-in-situ piling.

 

MePDCL splits Khasi Hills into six lots and hands four of them to one contractor
8The Rs 120.42 crore award concentrates Rs 82.12 crore, or 68.2% of L1 value, with a single firm across Lots 1, 3, 5 and 6.
8Lot 3 reached financial opening with one responsive bidder out of seven, leaving no L2 comparator to test whether that price was competitive at all.

 

NHPC rewrites force majeure and idling-cost recovery across both its hydro E&M packages
8The revised GCC Clause 37 adds terrorism, qualifying strikes and pandemic spread while removing the magnitude-7 earthquake threshold and express treatment of bandhs, lightning and unprecedented floods.
8Annex-A now caps compensable idling through a formula using 5% of composite contract price, with a 2% sub-cap on miscellaneous establishment expenditure and extended-warranty recovery at 2.25% per annum.

 

RVUN's Rs 1,125 crore coal tender is tagged emergency procurement without naming which rule applies
8The portal cites Rule 40(1), 43(6) or 43(7) but does not identify the provision invoked or the factual justification, and the original window ran just seven days from publication to submission.
8Coal grade, sampling agency, delivery duration, LD framework and PBG terms are absent from the published notice, leaving the commercial risk difficult to quantify before bidding.

 

WBSETCL's H1-elimination auction meets a 10% security stack that runs five years past commissioning
8The Sadarghat package removes the highest offer only where four valid price bids exist, so two or three qualified bidders all proceed to the auction intact.
8The winner must then carry separate 10% guarantees on GIS equipment for three years and transformers for five from the Taking-Over Certificate, with formal joint ventures barred.

Details
8India met the day’s solar-assisted peak, but the non-solar peak still showed a 4,965 MW shortage, exposing the different system challenge after sunlight fades. Details
8The NCLT rejected an insolvency petition against EKI Energy after finding a pre-existing carbon-credit pricing and payment dispute; the ruling does not decide the underlying commercial claim. Details
8The daily weighted price stayed far below Rs 10 even though 64 of 96 settlement blocks cleared at that level, revealing a sharp concentration of lower-priced volume in the remaining hours. Details
8NLC’s operating cash generation fell sharply while capital spending exceeded it and group borrowings rose above Rs 27,800 crore, sharpening the funding question behind its expansion programme. Details
8Solarworld wants to redirect Rs 420 crore of unused IPO proceeds from a 1.2 GW cell plan into a 2.4 GW joint-venture project already under construction. Details
8Southern grid operators report renewable curtailment of about 3,900 MW around a heavily loaded corridor whose second circuit is expected only around the end of 2026. Details
8GVK Power’s creditors have rejected two restructuring plans and moved toward asset-wise sales against admitted financial claims of about Rs 15,945 crore. Details
8Coal-gasification support can cover 20% of eligible machinery cost, but milestone security and steep delay reductions make execution timing decisive for applicants.
8Force-majeure periods are excluded from the delay clock. Details
8A tribunal bench has questioned whether force-majeure relief includes money and referred the issue for an authoritative ruling, leaving an Rs 82.58 crore transmission claim unresolved. Details
8NLC’s auditor has identified inadequate mining land as a material uncertainty over the Neyveli operation’s ability to continue, while management says contingency mining can sustain output at additional cost. Details
8Empower profit rises to Rs 18 crore as operating cash turns negative
8Empower seeks five-year auditor appointment after reporting lapses
8Empower’s standalone and group audits give conflicting accounts of edit logs
8XL Energy’s Rs 3.08 crore loss adds to unresolved debt accounting
8XL Energy’s share restructuring awaits exchange action as relisting appeal continues
8XL Energy records governance gaps beyond its transition window
8XL Energy seeks corrective director vote and approval for new manager
8NHPC names three joint auditors for FY27
8POWERGRID appoints four joint statutory auditors for FY27
8IRCON appoints Vinod Singhal & Co LLP for FY27 audit
8BHEL adds S Venkatram as auditor for Ranipet and southern power sector
8Alaknanda's full-year profit rose to Rs 285 crore, GVK report says
8Alaknanda's Rs 30 crore interest dispute with BHEL remains in appeal
8GVK's Rs 1,383 crore loss follows loss of control over its energy subsidiary
8Alaknanda issued Rs 2,031 crore of debentures before prepaying its term loan
8Gautami lenders received Rs 200 crore against Rs 2,760 crore of claims
8GVK reports water-tax relief for Alaknanda, with refund proceeds subject to pass-through
8Ratle's Rs 290 crore arbitration receivable remains tied to lender settlement
8GVK carries Rs 117 crore of SEZ land while title-document dispute remains unresolved
8GVK auditor flags financial-asset test; company disputes need for NBFC registration
8GVK discloses gaps in accounting audit trails
8GVK seeks three more years for unpaid whole-time director
8GVK proposes five-year renewal for T R Chadha as statutory auditor
8GVK Coal (Tokisud) Company Private Limited entered insolvency in May, annual report says
8Empower reports April change in managing director and finance chief
8Empower auditor lists Rs 6.04 crore in tax disputes despite nil income-tax contingency note
8Alaknanda report retains Rs 131 crore royalty dispute under pending review
8Alaknanda tariff disclosure shows competing appeals over capacity-cost recovery Details
8Solarworld carries Rs51.51 crore SJVN receivables as Rs219.34 crore claim awaits adjudication
8Solarworld's module business reports Rs15.21 crore segment loss in its first revenue year
8Znshine bank statements show creditor differences as Solarworld discloses audit-trail limits
8Coal-gasification support combines product caps with a ranked allocation contest
8Coal-gasification applicants face security and recovery conditions beyond selection Details
8Zelio seeks three separate Rs1,000 crore financial authorities
8Zelio puts Arya leadership and remuneration proposals before shareholders
8Zelio proposes five-year renewal of Jagsir Singh as secretarial auditor
8RMC wins Rs14.99 crore Maharashtra solar-pump allocation
8Siemens names Aditya Ramkrishna to lead Digital Industries from October1
8Amara Raja schedules Tata Mutual Fund management meeting for September11
8Taylormade proposes five-year renewal for CMD Dharmendra Gor
8Taylormade proposes Surana and Kothari for five-year secretarial-audit term
8Taylormade board recommends no FY2025–26 dividend
8Orient Electric schedules Axis Capital investor conference participation
8Kirloskar Electric relieves HR vice-president Sukanya Reddy after resignation
8KP Energy wins Emmvee captive-hybrid LOI for Karnataka
8CG Power secures conditional stay on disputed tax demand
8CAG appoints SCV & Co as Engineers India auditor for FY2026–27
8CESC incorporates two renewable-power companies with Rs1 lakh capital each
8NIRL receives 200 MW award under SJVN wind selection
8NLC sets September22 shareholder deadline ahead of final-dividend vote
8CAG appoints five firms to NTPC's FY2026–27 audit
8CAG names G S Mathur and S K Mehta as REC statutory auditors
8LIC crosses 5% REC holding after market purchase
8Suzlon wins Ayana wind EPC order in Madhya Pradesh
8Torrent commissions 322 MWp of Nashik agricultural-feeder solar
8GE Power India receives Odisha GST demand and considers appeal Details
8Solarworld seeks fivefold rise in borrowing authority to Rs5,000 crore
8Solarworld puts Rs65,000 cost-audit fee to shareholder ratification
8Solarworld seeks Mangal Chand Teltia reappointment at September AGM
8NLC signs NPCIL nuclear-development MoU and prepares PHWR feasibility
8NLC-Rajasthan venture develops 375 MW lignite project through feasibility packages
8NIRL-Assam venture identifies sites for 1 GW green-energy programme
8NIRL-Rajasthan venture receives land parcels for 2 GW programme
8NIRL and PTC sign agreement for 500 MW first-phase renewable venture
8NIRL-MAHAPREIT green-energy agreement awaits venture formation
8NLC signs Indian Oil MoU for Tamil Nadu renewable joint venture
8NLC and CSIR-CECRI agree critical-mineral extraction collaboration
8NLC signs TEXMiN memorandum for critical-mineral exploration research
8NLC and IREL agree cooperation on critical-mineral assets
8NLC and KABIL sign global critical-mineral project agreement
8NLC agrees proof-of-concept carbon-capture work with IIT Madras
8NIRL secures SECI solar-plus-storage award
8NIRL receives 600 MW Bundelkhand solar award
8NIRL records August SECI award for 200 MW wind
8NIRL wins 900 MW Gujarat solar award with GUVNL offtake Details
8NLC 03 - CTUIL revocation leaves NLC's 200 MW Gujarat solar project waiting for connectivity and land
8NLC 04 - Boiler technology tie-up becomes the immediate hurdle for NLC's 1,000 MW Neyveli expansion
8NLC 05 - Ghatampur's third unit enters service as another cost revision awaits government approval
8NLC 06 - NUPPL's BGR support exposure grows as risk-and-cost advances receive full provisions
8NLC 07 - Pachwara begins coal production, but Ghatampur still needs bridge supply through ramp-up
8NLC 08 - Talabira'sRs 27,213 crore power project shows a wide gap between financial and physical progress
8NLC 09 - NLC pays SECI under hybrid scheme while solar land and wind works lag
8NLC 10 - NIRL's 1,430 MW transfer is complete in accounts, with title and contract handovers still pending
8NLC 11 - Renewable spending surges while NLC's segment result falls 15%
8NLC 12 - NLC's 39% profit increase rests on a much smaller tax charge and regulatory movements
8NLC 13 - Talabira mining-charge dispute carriesRs 463.53 crore provision
8NLC 14 - NLC's inventory audit gap covers aRs 1,612 crore standalone stock balance
8NLC 15 - Bithnok and Barsingsar revival talks leave old capital and contractor claims unresolved
8NLC 16 - NLC recordsRs 379 crore mineral-land-tax recovery through lignite energy charges
8NLC 17 - NLC releasesRs 417.63 crore TPS-I interest liability while TANGEDCO appeal remains pending
8NLC 18 - TPS-II tariff remand yieldsRs 128.41 crore liability reversal and fresh interest accrual
8NLC 19 - Kerala linked-mine tax case addsRs 85.06 crore interest to NLC's income
8NLC 20 - Inclusion of Mine-II Expansion in pooled lignite pricing producesRs 166.98 crore interest income
8NLC 21 - NLC retainsRs 411.57 crore liability as discom tax-recovery disputes move to CERC
8NLC 22 - Barsingsar moves to lower petitioned fuel price and reversesRs 30.79 crore provision after credits
8NLC 23 - NLC carriesRs 500 crore of O&M and special-cost tariff assets awaiting recovery
8NLC 24 - NLC's ageing thermal fleet records weaker availability even after a unit modification
8NLC 25 - Surrendered power rises as NLC's exchange sales recover only a fraction of unused supply
8NLC 26 - NLC faces nearly 4,950 retirements over five years as recruitment and regularisation continue
8NLC 27 - NLC's board-composition gaps leaveRs 59.59 lakh of exchange fines unpaid
8NLC 28 - Three worker fatalities keep NLC's safety improvements under scrutiny
8NLC 29 - NLC's absolute emissions rise 5% while revenue-based intensity improves
8NLC 30 - Tamil Nadu storage project moves into EPC execution under a 12-year service agreement
8NLC 31 - NLC's Odisha renewable JV plan combines wind and pumped storage under a 1 GW programme
8NLC 32 - NLC's coal pipeline moves into MDO procurement, with mine clearances still decisive
8NLC 33 - NLC advances phosphate and critical-mineral blocks into exploration work
8NLC 34 - NLC's overburden-to-sand programme gains a 1 million-tonne plant and state disposal permission
8NLC 35 - NLC's decommissioned TPS-I sale deliversRs 89.34 crore annual profit as dismantling proceeds in stages
8NLC 36 - NTPL seeks dividend exemption after payout falls below the stated minimum
8NLC 37 - NLC and NALCO sign 1,080 MW captive-power venture agreement for smelter expansion
8NLC 38 - NCRTC captive-solar venture reaches land identification and balance-of-system tender
8NLC 39 - NLC's green-hydrogen pilot moves through EPC execution before production can be tested
8NLC 40 - NLC targets 2027 rare-earth pilot using lignite fly ash
8NLC 41 - Barsingsar solar starts billing atRs 2.45 while GST-change claim takes a separate route
8NLC 42 - Khavda and Pugal solar projects face different equipment milestones before commissioning
8NLC 43 - NLC's 450 MW NTPC hybrid award still awaits its long-term PPA
8NLC 44 - NIRL places 200 MW wind EPC order with Inox after SJVN award Details
8Singla Forging gets protection from coercive furnace-charge recovery
8Shri Krishna Forgings wins interim protection in furnace-charge case
8HPERC gives P&G two more weeks in renewable-obligation verification
8Pathania’s 250 kW solar PPA petition listed for consideration
8DVC seeks November thermal, hydro and non-solar supply through auctions
8PXIL circular limits liability to affected fees or Rs 10 lakh
8PSPCL seeks reconciliation of Rs 19.47 crore in connection collections
8PSPCL calls for August processing-fee reconciliation
8PSPCL schedules pay-arrears audit across three divisions
8PSPCL assigns faculty for smart-metering and loss-reduction training
8PSPCL nominates 65 staff for September SBS training
8Guna completes ten substations and approves 61 further network works
8Guna reports Rs 85.77 lakh in daytime smart-meter rebates
8September Lok Adalat offers conditional relief on electricity assessments
8PVVNL schedules September 9 shutdowns for network works
8The Lodhi expansion deferred with higher solar-capacity requirement
8ISIC expansion needs fuller solar and backup-power submissions
8Nagaland House redevelopment held for solar and backup details
8Maharashtra agenda lists transfer of 40 MW cogeneration clearance
8SECI reiterates mandatory site certificate for NIWE rooftop bid Details
8IMP Powers restarts transformer production as net working capital remains negative
8TGGENCO reservoir energy potential falls 58% as Nagarjunasagar drops 74%
8CEA reports all-India August coincident peak fully met while Uttarakhand missed 13.2% of its peak
8Solarworld builds a Rs 2,813 crore order book while adding module and storage manufacturing capacity
8East–West settlement accounts for 96% of Eastern Region deviation-settlement receivables
8POWERGRID’s Rs 8 crore Dynamic Line Rating pilot faces Rs 4.6 crore pre-GST relocation quote

STATE REGULATOR NEWS

8KSERC opens consultation on 2026 multi-year tariff regulations for 29–30 September

GRID AND MARKET DEVELOPMENTS

8POWERGRID expects August 2028 operation for Udumalpet–Madurai upgrade amid continuous single-contingency violations
8SRPC considers Yelahanka gas plant for voltage support around Bengaluru
8Southern states split over new reserve shut-down option for thermal units
8Adani transmission arm seeks early commercial operation to recover charges before prerequisite elements finish
8POWERGRID proposes joint refurbishment of both 500 MW Vizag HVDC poles
8NLCIL says Thermal Power Station II units may shut below 50% of maximum continuous rating Details
8Emergency reserve dispatch gives Eastern pool a Rs7.04crore net receivable
8Eastern SCUC pays out Rs73.30lakh despite more downward than upward scheduling
8SRAS incentives almost offset Eastern generators' energy refunds Details
8Three Pothencode insulator failures trigger a root-cause and condition review
8Pothencode protection scheme awaits end-to-end test evidence after entering service
8Southern underfrequency shedding plan rises to 15,875 MW with implementation still under discussion
8July frequency event prompts checks for premature underfrequency relay operation
8Southern grid review flags a possible 3,000 MW export-capability loss during high renewable output
8BHAVINI startup network arrangements return for clarification after temporary line charging
8Staggered irrigation supply cuts Andhra Pradesh evening peak by about 400 MW
8Talcher–Kolar spare-transformer list includes three units still requiring deployment or repair
8JSWEL compensator purchase moves toward order with delivery expected around year-end
8Tamil Nadu's 528 MVAr capacitor plan awaits revised-cost approval before retender
8Neyveli transformer works require a retender after bidder fails qualification
8Puducherry's 35 MW battery project awaits administrative approval before award
8Ariyalur–North Chennai line faces an all-insulator replacement proposal after decapping
8NHAI readiness pushes Janagaon–Julurupadu diversion from September to November
8Emergency restoration equipment remains below stated utility norms as orders run into 2027
8Tamil Nadu and Puducherry load despatch staffing stands well below stated norms
8Tamil Nadu's August deviations bring fresh follow-up after a 1,066-block overdrawal quarter
8Long-running reactor repairs remain tied to imported parts and approval decisions
8Ennore SEZ units carry August and October 2027 commissioning expectations
8Tamil Nadu plans an 800 MW Thoothukudi project using Uppur materials and Udangudi facilities
8Yermarus reactor proposal shifts toward tariff recovery after eight-year delay
8Edayarpalayam reactor package moves to retender after contract termination
8Automatic demand-management performance faces corrective review after months of inadequate response
8June black-start exercise count is zero as SRPC retains a December completion target
8Andhra Pradesh moves SAMAST toward internal funding while PSDF response remains pending
8Ramagundam stage-I AGC gap narrows to unit 1 after April implementation on units 2 and 3
8Tamil Nadu awards AGC tenders covering 1,800 MW at North Chennai-II and Mettur-II
8Sharavathi and Varahi AGC tests leave the commercial mechanism as the next decision
8PGCIL replacement proposal calls for studies on seven reactors and five transformers
8Kalpakka–Gazuwaka loading restrictions put clamps and jumpers under review
8Kasargode GIS commercial-operation timing remains linked to a right-of-way-delayed line
8Ennore expansion moves through approved bidding route without a recorded award Details
8MSETCL transmission availability certified at 90.20% for July
8Lakadia Vadodara July availability falls below its cumulative measure
8Mumbai Urga Marg July availability stands at 94.79%
8Raipur Pool Dhamtari records full July availability with cumulative figure still at 86.866%
8POWERGRID western AC availability certified at 99.71% for July
8Western DSM account shows Rs 343.09 crore payable to the eastern region
8Chhattisgarh and Maharashtra carry the largest state DSM payables in western account
8Maharashtra and Gadarwara lead reactive-account credits in the western region Details
8Ranganadi availability stands far below the hydro stations beside it in August account
8Subansiri account separates 81.16 million free units from saleable energy
8Kameng merchant allocation accounts for more than half its August schedule
8Agartala combined-cycle availability remains below 30% in August
8Assam gas station's load factor trails its availability in August
8Bongaigaon has high availability but 231,240 MWh of cumulative unrequisitioned entitlement
8Palatana August availability exceeds its cumulative level but remains below norm
8Assam imports bilaterally while recording net IEX sales in August account
8Meghalaya's temporary-access sales far exceed purchases in August schedule Details
8Southern region accounts for more than the net renewable scheduling shortfall
8Grid frequency stays outside the reported operating band for almost six hours
8Maheshwaram voltage exceeds 800 kV for more than a third of the day
8Bellary’s 700 MW unit trips while southern plants restore 3,080 MW
8All four Kadamparai units remain on forced outage in September operating record
8Tripura transfer corridor exceeds available capacity for 17.5 hours
8Bongaigaon and Balipara reactor replacements remain under shutdown
8Chuzachen’s 110 MW shuts on silt after earlier evacuation interruptions
8Eastern intraday demand forecast improves daily accuracy but misses evening ramp
8Nine gas plants show zero schedules in NLDC’s 9 September commitment table
8Kayamkulam’s reserve-shutdown units require 45 days’ fuel notice
8Selected southern transmission report records six restorations on 8 September
8Southern major reservoirs hold 35% less stored energy than a year earlier
8Koppal RenewOjas battery records 75 MW discharge peak in the evening
8Udangudi records 9.76 million units while still labelled infirm generation
8Kudankulam transformer awaits priority replacement of all three high-voltage bushings
8Northern reservoirs show a 21% reduction in reported stored energy
8Rajasthan corridor exceeds available transfer capability for 28.47% of the day
8Subansiri Lower supplies a quarter of northeastern regional-entity generation
8Lower Kopili records 1.31 million units under an infirm-generation label
8Tehri pumped storage records evening output but negative net daily energy
8Neemba Renew Surya Vihaan produces 70% less energy than scheduled
8Bihar account receives 63% of ERPC weekly reactive-energy receivables
8Weekly reactive balances conceal daily reversals at West Bengal and DVC
8Gas-fired generation falls 40% in a day as Ratnagiri output contracts
8Hydro trails annual programme by 10 billion units while total generation stays ahead
8Loktak stored energy falls 17% between consecutive CEA reservoir reports
8Parbati-II output nearly vanishes as two hydro stations lose 13.6 million units in a day
8Korba output rebounds 69% as more units return after a 2,100 MW trip
8Sasan remains 68% below daily generation programme as coal stocks reach 7% of norm
8Ghatampur generation falls 35% after another day of unit disruptions
8Two Teesta stations account for 95% of the Eastern hydro programme gap
8Rajasthan reactor 8 carries more programme than the nuclear station’s entire shortfall
8Raghunathpur unit 2 records a 91% generation-programme shortfall
8Vedanta’s Chhattisgarh unit trails generation programme by 92% despite ample coal stock
8All seven RRVUNL coal-stock entries are critical in CEA’s September 7 report
8Three critical Andhra plants hold twice as much coal at ports as at their stations
8Coal buffers diverge sharply between Adani’s Mundra units and Mundra UMPP
8Toranagallu reports zero closing coal stock despite receiving and burning fuel
8Butibori and Pathadi coal buffers shrink below a day on reported consumption measures
8JSWEUL falls 7.4% short of its weekly schedule
8Teesta's final-day shortfall reverses six days of positive deviation Details
8PXIL real-time buyers found no matching supply for three consecutive delivery days
8PXIL's day-ahead spot report records bids without matching sellers
8IEX real-time power returned to Rs 10 from 16:45 to midnight
8IEX high-price market cleared only 358 MWh, all at Rs 20 per unit
8IEX green day-ahead price rose 22% as cleared volume fell 23%
8IEX's green term-ahead trades show a wide price range across contract series
8Thirty-one contracts accounted for three-quarters of IEX's daily term-ahead trading Details
 For reference purposes the website carries here the following tenders:
 8Tender for procurement of spare parts of S/R and ERH vibro feeder installed Details
 8Tender for work contract for rebabbiting of white metal ID FD PA fan bearings Details
 8Tender for supply of 33 kV vacuum circuit breaker pole of various Details
 8Tender for supply, installation and commissioning of new M.S. pipeline Details
 8Tender for construction of watch towers Details
 8Tender for supply,erection, testing & commissioning of 220kV 1Cx1200 Sq.mm,2x(3+0) copper conductor Details
 8Tender for fencing work of ACC and rainwater harvesting pond Details
 8Tender for construction of biomass pellet storage facility Details
 8Tender for balance civil works of CHP package Details
 8Tender for biennial work for dredging of the barrage basin Details
 8Tender for supply and apply of marine grade paints with rust converter Details
 8Tender for supply, erection, testing and commissioning of 132kV 2x(3+0) 1Cx800sq.mm U/G cable Details
 8Tender for supply, laying, erection, testing and commissioning of 66kV, 1CX630 sqmm XLPE cable Details
 8Tender for augmentation of transformation capacity by providing additional 1x50MVA, 132/33kV PTR along with HV & LV bays Details
 8Tender for work of providing & fixing of silica gel breather & supply of blue silica gel for various EHV TF/ICT at various Details
 8Tender for augmentation of transformation capacity by providing additional 1x50MVA, 132/33kV PTR along Details
 8Tender for enhancement of transformation capacity of substation by providing 1x100MVA, 220/132kV ICT along Details
 8Tender for supply of various size of tool holders and its spares of various lathe machines Details
 8Tender for procurement of curved tooth connecting coupling Details
 8Tender for work of stub strengthening tower of 220kV line Details
 8Tender for cleaning of confined hot water duct in natural draft cooling tower Details
 8Design, engineering, supply, erection, testing, commissioning and comprehensive operation & maintenance for 5 (five) years for 65 KWp rooftop solar PV power project Details
 8Tender for supply of plumbing materials Details
 8Tender for rate contract for retrofitting and strengthening of machine foundations Details
 8Tender for maintenance and miscellaneous works Details
 8Tender for internal and external painting of wall and structural steel including water proofing treatment Details
 8Tender for work of welding of carbon steel, stainless steel and alloy steel pipeline and structural work Details
 8Tender for work of insulation and rolling shutters maintenance work Details
 8Tender for replacement/revamping of conventional FLP/old FLP LED light fittings Details
 8Tender for replacement of deteriorated tower and stub strengthening of D/C 220kV line Details
 8Tender for construction of 05 no. bunkers Details
 8Tender for sample collection at various for coal Details
 8Tender for running contract for carrying out the O and M works, improvement works and capital works, maintenance works and DCW works Details
 8Tender for annual maintenance of unit no.1 and 2 at power house Details
 8Tender for supply and application of coating material on different underwater parts Details
 8Tender for replacement of existing 11 kV ACSR conductor with 11 kV AAAC, AL-59, 99 sq.mm covered conductor Details
 8Tender for annual maintenance of 33/11kV line and all distribution transformer Details
 8Tender for replacement of existing ACSR Zebra conductor by HTLS conductor Details
 8Tender for construction of 4 (Four) Nos. of new tower and associated work Details
 8Tender for upgradation of existing 220/132/33kV GIS at 400kV level with transformation capacity Details
 8Tender for rerouting 11kV line using covered conductor Details
 8Tender for constructing 11kV line using covered conductor Details
 8Tender for Re-constructing using HT covered conductor Details
 8Tender for restoration of unit-I including SITC of couplings Details
 8Tender for ETC of boiler and PCP at 2X660 MW Details
 8Tender for supply of tie bar of rail track system Details
 8Tender for providing and laying G. I. pipe Details
 8Tender for providing and laying concrete & steel cover for unit 1 to 5 boiler side Details
 8Tender for R/M of control room with roof treatment at 220/132/33kV G.S.S Details
 8Tender for procurement of various type of control transformers Details
 8Tender for providing & fixing safety showers and sintex tank including other miscellaneous civil works Details
 8Tender for providing muffing on periphery of existing various steel structure of coal yard Details
 8Tender for rate contract for supply of travelling water screen (TWS) system Details
 8Tender for work of providing & fixing of LED lights in switchyard Details
 8Tender for supply of IBR-approved electrically operated butt-weld end gate valve assemblies, complete with actuators, bypass valve Details
 8Tender for supply of cooling water treatment chemicals compatible with on line monitoring and auto chemcal addition control system Details
 8Tender for supply and works for online ABT energy metering monitoring system Details
 8Tender for work of retrofitting of existing BPL make PLCC link of 132 kV line Details
 8Tender for annual maintenance contract (AMC) for the various emergency breakdown & planned outage work of 400 kV,220 kV,& 33 kV bays along Details
 8Tender for annual work contract for material handling and housekeeping in 02 Nos. store shed Details
 8Tender for procurement of GTC journal sleeves for coal mill XRP-903 Details
 8Tender for procurement of insulation protection aluminum sheet (Cladding Sheet) for routine maintenance and AOH of boiler Details
 8Tender for replacement of damaged/worn out various size fire hydrant and spray pipelines Details
 8Tender for procurement of spares for plant air compressor model Details
 8Tender for procurement of various erosion protection sleeves (shield) and other spares for boiler Details
 8Tender for raising of temporary path connecting ram setu at ash dyke Details
 8Tender for providing and laying factory made 80 mm thick cement concrete paver block Details
 8Tender for procurement of 3300KM of ACSR rabbit conductor Details
 8Design, manufacture, testing, supply and delivery of 15kV NCTs of various ratios Details
 8Tender for procurement of 2000 meters, 900NB MS pipe for new intake pipe line Details
 8Tender for procurement of grinding elements (grinding roll, bull ring segment, air port ring assembly ) of bowl mill Details
 8Tender for service contract for OH of boiler Pr. parts (unit #5) and replacement of platen superheater coil Details
 8Tender for repairing of PA fan silencer and canopy during overhauling Details
 8Tender for procurement of 80 MT liquid chlorine Details
 8Tender for laying of 3C 33kV 400 SQ MM XLPE UG cable Details
 8Tender for manufacture, testing, supply and delivery of 33 kV O/D live tank /dead tank oil immersed CT with CTR Details
 8Tender for operation and maintenance of 11 kV, LT lines Details
 8Tender for operation and maintenance of 11 kV, LT lines and sub-stations Details
 8Tender for supply of decentralize material Details
 8Tender for rate contract for internal inspection of T/F or ICT & for attending oil leakages by replacement of gasket & miscellaneous /auxiliary parts of various capacities ICT & power T/F at various Details
 8Tender for construction of peripheral RCC compound wall at 220 kV substation Details
 8Tender for procurement of PLCC cards of ETL/41/42 for establishing MMR PLCC LTS network. Details
 8Tender for supply of various types of cable & dismantling, ETC work of 245 & 145 kV circuit breakers at various S/Stns Details
 8Tender for chemical washing of disc/PLRI strings of various 400 kV Tr. lines Details
 8Tender for supply, civil, ETC works of 3 x 167MVA 400/220/33kV ICT along with HV/LV bays, 400/220kV bus extension Details
 8Tender for day to day maintenance for civil assets Details
 8Tender for day to day maintenance for civil assets in sub-station Details
 8Tender for second circuit stringing on 132kV line Details
 8Tender for various civil maintenance work for upkeepment of 132 kV S/Stn Details
 8Tender for upgradation of substation by replacement of old C&R panels, battery set battery charger Details
 8Tender for supply, civil, ETC works of 400kV 1x125MVAr 3ph bus reactor with NGR along Details
 8Tender for procurement of 75Ohm unbalanced I-lF cable Details
 8Tender for work of establishment of 132-110/33 kV s/s Details
 8Tender for work of enhancement of existing corridor of 220kV line Details
 8Tender for augmentation for enhancement of transformation capacity of ss by addition of ICT’s Details
 8Tender for work of supply and application of anti-corrosive paint/coating on external Surface of various steel structures, pipelines and auxiliaries Details
 8Tender for supply of air blower, pump and sludge panel & its accessories Details
 8Tender for work of safety related miscellaneous fabrication work at various Details
 8Tender for supply of various boiler tubes bends Details
 8Tender for supply and application of plastic refractory in various of boiler Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
NMDC to begin commercial coal production next quarter Details
 
8Mahanadi Coalfields sustains over 200 MT annual coal production and dispatch: Govt Details
 
8Coal Gasification Scheme Tests India’s Industrial Transition Details
 
8CMPDI in focus as coal gasification scheme draws 7 applications, with Adani and NTPC among applicants Details
 
8Reddy rules out coal shortage despite 58 power plants reporting critical stocks Details
 
8Indian sponge iron at two-year high, boosted by costly coal imports, domestic shortages Details
 
8From India to Germany: Populating the green energy workforce Details
 
8Can India’s solar farms become living laboratories for clean-tech innovation Details
 
870% of Karnataka's power demand met by renewables, says state energy minister Details
 
8India’s regulator proposes mandatory co-located storage for new solar, wind projects Details
 
8The Looming Energy and Water Burden of India’s Data Centres Details
 
8NLC India Subsidiary NIRL Gets LOA For 200 MW Wind Project From SJVN Details
 
8Tata Power Solar of crosses 500,000 rooftop solar installations Details
 
8Why GE Vernova T&D India Share Price is Rising Details
 
8Suzlon Secures 200 MW Wind Order From Ayana Renewable Power Details
 
8Saubhagya Scheme Legacy: Impact on Power Sector Financials Details
 
8Solar, battery storage and $1 billion: Inside Madhya Pradesh’s new ADB-backed energy push Details
 
8India Holds 123 Million Tonnes Coal; 23-Day Buffer at Plants Details
 
88 Cable & Wire Stocks With Order Books Up to Rs 26,665 Crore to Keep on Your Radar Details
 
8Torrent Green Energy Commissions 322 MWp Decentralized Solar Capacity Across 50 Sites In Nashik Details
 
8India’s Data Center Expansion Faces Water, Power, and Currency Headwinds Details
 
8Seven Applicants for Rs 37,500-Crore Coal Gasification Scheme Details
 
8From 3 lakh to 5 lakh: Tata Power Solaroof scales rooftop solar across residential, C&I segments Details
 
8India has 124 MT coal stocks, adequate for 51 days: Reddy Details
 
8Our EPC-Led Approach Enables Us To Deliver Future-Ready Infrastructure Solutions: JAKSON Infra Details
 
8NTPC Vindhyachal ED Kishore Kumar Hota honoured with ‘Leader of the Year’ award Details
 
8Odisha approves Rs 15,949 crore power grid investment for future demand Details
 
8Gaining Momentum: Developers’ perspective on the wind power sector Details
 
8India’s Energy Storage Requirement to Reach 411 GWh by FY32 Details
 
You can also click on Newsclips for more Details
RRVUN's Rs 1,125 crore Suratgarh coal tender sets a three-month delivery clock against a 365-day portal period
8The tender seeks 12.5 lakh MT of domestic coal at 3 lakh–4.5 lakh MT a month, yet Clause 2.28 fixes completion at three months while the portal records a 365-day work period.
8The unresolved question is how bidders price a schedule RRVUN can defer or cancel without admitting a claim, against coal that earns Rs 1 per MT once ash crosses 34% or GCV falls below 4,000 Kcal/kg.

 

APEPDCL grants 24 extra days on its Rs 143.32 crore SCADA package without touching a single execution obligation
8Three corrigenda moved submission from 1 September to 25 September 2026, but the 18-month implementation period, five-year FMS and 10% performance security stayed exactly where they were.
8What the extensions really concede is preparation time for a bidder pool that must satisfy two separate qualification streams and assemble OEM authorisations before it can quote.

 

RVPN's Rs 83.38 crore Shiv Enclave GIS package makes unlisted work the contractor's problem
8A 132/33 kV, 2x80 MVA GIS substation with a 4 km LILO cable arrangement carries a 545-day execution period and a 10% performance security, extended eight days by Corrigendum No. 01.
8The clause that matters is GCC 3.2, which absorbs reasonably inferable items into the contractor's scope without automatic additional payment.

 

NTPC puts 2,184 man-months of construction safety at Telangana Stage-II behind a 52-month firm-rate contract
8The consultant must field 47 personnel, run a 24/7 IP-camera control room and approve other agencies' JSA/HIRA documents across a 3 x 800 MW build.
8The commercial risk is not the Rs 5,000-per-day non-deployment penalty but firm rates through a unilateral 12-month extension, 5% retention and no interest on deferred payment.

 

TNPDCL asks for 5,000 distribution transformers while the protected BOQ shows a quantity of one
8The M-256 tender covers 5,000 units of 100 kVA, EEL-2 aluminium-wound transformers with a Rs 1,00,20,500 EMD, a ±25% quantity variation and a 60-month guarantee.
8The BOQ's "1.0 No." line and its residual civil-work text sit inside a spreadsheet bidders are forbidden to alter, converting a template artefact into a responsiveness risk.

 

JdVVNL's Rs 119.89 crore Bikaner package carries two completion periods inside the same document
8The NIT records eight months for supply, erection, testing and commissioning while Appendix 4 records nine, both against an unchanged nine-month total, with the portal and NIT also differing on the 22 September opening time.
8Performance security is quoted at both 180 days and 30 days beyond the defect-liability period, and guarantee charges turn on which one controls.

 

Bidder queries force JdVVNL to reopen the BOQ on its Rs 91.47 crore Bikaner DD package before bids close
8Corrigendum-3 supersedes the 14 August NIT, revising the BOQ, specifications, estimate and EMD to Rs 1.83 crore without publishing the superseded figures for comparison.
8The sharper problem is composition: JdVVNL's own estimate puts supply at 79.6% of value while ITB 37 treats supply above 70% of the quoted price as front-loaded and demands additional security.

 

Phalodi package climbs 0.7% across two corrigenda, with the entire increase landing in supply
8Between Corrigendum-I and Corrigendum-3, supply rose by Rs 38.89 lakh while erection fell by Rs 1.21 lakh, taking TNTW-792 to Rs 97,59,20,302.39 and EMD to Rs 1,95,18,407.
8No item-level change register accompanies the revision, and the portal and SBD still disagree on whether technical bids open at 11:00 am or 5:00 pm.

 

Jaisalmer's Rs 121.13 crore RDSS package stacks four separate security layers on one contractor
8Beyond the 10% performance security sit abnormal-bid security, supply-unbalancing security and a further 10% guarantee on major equipment running to 36 months after completion.
8With 77.4% of the estimate in supply and no pre-bid meeting scheduled, bidders must also decide whether the EMD instrument reads Rs 2,42,25,139 or Rs 2,42,25,140.

 

JVVNL withdraws the vendor-registration security waiver as it tenders 25,000 CSP transformers
8Appendix-A replaces EMD and SBG references with Bid Security and removes the relaxation that JVVNL registration alone previously conferred, on a Rs 16,025 lakh, 16 kVA programme.
8The allocation formula caps L1 at 20% and spreads half the quantity across other firms, making past repair performance an eligibility filter rather than a reference note.

 

Navkar Global Infra takes NTPC Mouda ash transport at 47.6% of base rates against 23 other accepted bidders
8The accepted percentage produces a Rs 142.80 crore contract value, a 52.4% discount to the Rs 300 crore estimate and far past NTPC's own 10% abnormally-low threshold.
8Section C nonetheless caps each shortlisted bidder at Rs 50 crore cumulative and guarantees no purchase order at all, separating the headline award from bankable work.

 

Churu package falls Rs 7.45 crore in Corrigendum-3 after rising in Corrigendum-1 TNTW-798 moved from Rs 132.60 crore to Rs 133.13 crore and then down to Rs 125.67 crore, with supply cut 6.5% against erection's 2.0%, and no clause-level reconciliation published.
8Bidders have ten calendar days from republication to reprice, while the portal and corrigendum differ by Rs 60 on an EMD that decides envelope-one compliance.

 

UJVN Limited raises its BESS tariff ceiling 3.8% but leaves 165 MWh outside VGF support
8The 90 MW/225 MWh Chilla project draws VGF on only 60 MWh, while the ceiling capacity charge moves to Rs 3,30,400/MW/month against the Rs 3,96,747 bidders sought.
8After 12 years the entire asset transfers to UJVN Limited without consideration, so residual value has to be recovered inside a capped tariff stream.

Details
 For reference purposes the website carries here the following tenders:
 
8Tender for erection of 66kV SS equipment, structures, control wiring Details
 
8Tender for erection of 66kV SS equipment, structures, control wiring, yard lighting Details
 
8Tender for provision of balance steel reinforcement for construction of 110/33kV indoor 110/33kV substation. Details
 
8Tender for conducting tube thickness survey in first and second pass Oxide scale Thickness Measurement in Super heater, Reheater Details
 
8Tender for procurement of 100KVA/11KV/433V energy efficient level-2 aluminum wound distribution transformers Details
 
8Tender for supply, installation, testing and commissioning of 11kV to 415V ,315KVA LT transformer Details
 
8Tender for supply of 400 kV and 220 kV CVTs for various substations Details
 
8Tender for earthing of switchyard gantries Details
 
8Tender for supply, installation, and commissioning of tower/floor-mount split air conditioners for the control room, battery room Details
 
8Design, engineering, manufacturing, testing, supply, stringing, installation, testing and commissioning etc. for construction of LILO of 220 kV line Details
 
8Tender for biennial electrical & mechanical maintenance for machine Details
 
8Tender for work of new 66kV switchyard with single zebra bus with section isolator along Details
 
8Tender for work contract for carry out cleaning of algae removal from the trash rack of CV, VT & MV pumps Details
 
8Tender for Re-conductoring HT line Details
 
8Tender for constructing new 11kV UG cable Details
 
8Tender for shifting of new sewage pipeline inside plant Details
 
8Tender for fixing of PVC chain link fencing Details
 
8Tender for grouting work at conveyor 2A side wall Details
 
8Tender for biennial maintenance contract for civil works Details
 
8Tender for operation and maintenance of garbage PIT Details
 
8Tender for CAMC for real-time environmental data transmission Details
 
8Tender for job contract for supply and laying of coir geotextile Details
 
8Tender for providing and fixing of precoated galvanized iron profile sheet roofing Details
 
8Tender for civil repair and maintenance works of CE (PRG) shed Details
 
8Tender for standardisation of transformers Details
 
8Tender for erection of tower material/ tower structure, beams, bus bars for various 220/132kV sub stations Details
 
8Tender for technological upkeep of silo and fly ash bagging machine Details
 
8Tender for restoration of damaged protection work Details
 
8Tender for providing and laying of external water supply pipeline Details
 
8Tender for repairing of floor tiles at hydro power Details
 
8Tender for construction of new protection wall for protection of tower Details
 
8Tender for repair and painting work of 220kV GIS substation Details
 
8Tender for puncture insulator detection (PID) of insulator string of various towers of 132kV line Details
 
8Tender for replacement of old 110 Volt 300AH battery bank and battery charger at 132kV S/s Details
 
8Tender for new turfing at newly constructed 132kV TBC bay and strengthening of pathway Details
 
8Tender for procurement and replacement of old 33kV circuit breakers Details
 
8Tender for shifting of 33 kV line Details
 
8Tender for supply, dismantling and erection of 33kV isolators Details
 
8Tender for supply of control panel spares of pump house Details
 
8Tender for miscellaneous civil works for water supply Details
 
8Tender for collection, transportation and treatment of industrial liquid effluent inclusive of disposal of sludge generated Details
 
8Tender for new 33 by 11 kV sub-stations augmentation or addition capacity including associated line Details
 
8Tender for new 33 by 11 kV sub-stations Details
 
8Tender for interlinking 11kV line Details
 
8Tender for stringing new HT feeder using ABC 150 sq.mm Details
 
8Tender for upper hydro electric project 1x24 MW powerhouse Details
 
8Tender for capacity enhancement of 110kV DC line Details
 
8Tender for upgradation of 33kV substation Details
 
8Tender for work contract for annual maintenance work of various types of cranes installed Details
 
8Tender for procurement of various HYDAC make filters installed Details
 
8Tender for procurement of 33kV polmer insulator strings Details
 
8Design, manufacture, testing, supply and delivery of 220kV PTs and 220kV CTs of various ratio Details
 
8Tender for shifting of 66kV line Details
 
8Design, manufacture, testing, supply and delivery of 66kV 2000A isolators with earth switch with solid core insulators Details
 
8Tender for supplying, laying and compaction of good earth at 66kV S/S Details
 
8Tender for construction of additional foundations for 1 no 66 kV line bay Details
 
8Tender for rate contract for removing, lifting, shifting, dismantling and overhauling of 6.6 kV HT motors Details
 
8Tender for ARC for erection of HT / LT / TC and maintenance work Details
 
8Tender for work of overhauling of air-preheater Details
 
8Tender for supply of various fasteners and consumables Details
 
8Tender for supply of filled hydrogen gas cylinder with own transportation for mechanical operation for all units Details
 
8Tender for repairing & maintenance work of ash pond Details
 
8Tender for procurement of seal kit sets for scoop actuator and air line Details
 
8Tender for procurement of HART calibrator required for calibration purpose Details
 
8Tender for procurement of different alloy CI pipe bends and fittings Details
 
8Tender for procurement of different sizes MS ERW pipe Details
 
8Tender for procurement of several LT 415V power cable Details
 
8Tender for procurement of different submersible pumps Details
 
8Tender for Bi-annual rate contract for U4 B and A equipment Details
 
8Tender for supply and delivery of non centralized local materials like 33kV line Details
 
8Tender for construction of electricity test lab Details
 
8Tender for construction of protection wall and other misc.civil works at 33/11 kV S/S Details
 
8Tender for construction of electricity test lab Details
 
8Tender for establishment of 220/33kV substation Details
 
8Tender for interconnection by link line between 220kV line Details
 
8Tender for work of procurement of HV critical spares (11/22/33kV CT’s, PT’s & LA’s) for various EHV substations Details
 
8Tender for replacement of 1x 25MVA 132/33kV TF by 1X50MVA 132/33kV transformer along Details
 
8Tender for ARC of work of erection, testing & commissioning of 66kV feeder bay, transformer bay Details
 
8Tender for work of cleaning of bus ducts/MCCs, actuator overhauling, and cable dressing works Details
 
8Tender for biennial rate contract for ash handling plant Details
 
8Tender for supply of riser duct liners of beater wheel mill Details
 
8Tender for supply of electrical actuator for ID Fan & PA Fan IGV for 200 MW Details
 
8Tender for supply, dismantling and commissioning of new acid tank (H2SO4 -Concentration 98%) with accessories Details
 
8Tender for supply of MS grill for walkways of boiler & coal mill Details
 
8Tender for work of removal of old damaged refractory, application of the new castable refractory/ fire brick lining in bottom ash hopper & fabrication work Details
 
8Tender for ARC for erection of HT / LT / TC and maintenance work Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
CIL's daily coal production rises 35% Details
 
8India tenders 700MW of solar capacity for C&I offtake Details
 
8Kajaria Ceramics Inks 20 MW Wind-Solar PPA with Sunsure Details
 
8Solis Commissions 1.04 MWh EverCore BESS in Chennai Details
 
8MENA Renewable Energy Capacity Surges to 16 GW in 2025 Details
 
8Solar Manufacturing In UP Gets A Fillip, Alpex Solar Set To Become Second Cell Maker From State Details
 
8India’s non-fossil fuel power capacity crosses 300 GW mark Details
 
8India’s Thermal Power Demand Rises Amid Renewable Shift Details
 
8Siemens Energy India: SF6-Free Circuit Breaker for Cleaner Grid Details
 
8Bhakra Nangal Dam Declared Safe as India Pushes for Atmanirbhar Power Sector Details
 
8Coal Loading to Power Sector Rises to 444 Rakes: Government Details
 
8India Ramps Up Rail Coal Deliveries as Power Plant Stockpiles Dwindle Details
 
8Coal ministry steps up supplies as rake loading rises 20% in four days Details
 
8Siemens Energy India Commissions Its First 145kV SF6-Free Circuit Breaker Details
 
8Urgently augment power generation’: Punjab engineers write to Bhagwant Mann Details
 
8Corrective supply steps on to tackle stock situation, says CoalMin Details
 
8NTPC Limited Strengthens Supplier Ecosystem with Velocious Details
 
8CIL Accelerates Coal Output as Monsoon Eases, Power Sector Dispatch Jumps 24% Details
 
8Coal India, SCCL Boost Power Sector Coal Supply as Daily Rake Loading Climbs to 444, Up 74 Rakes Details
 
8Coal Loading For Power Sector Maintains Steady Upward Momentum, Government Highlights Consistent Growth Trend Details
 
8GE Vernova T&D India Declared L1 Bidder for 6000 MW HVDC Project by Power Grid Details
 
8Adani Power Leads Thermal Sector in NSE Sustainability ESG Rating Details
 
8Coal loading to power sector shows consistent upward trend: Govt Details
 
8Adani Power: Investor Presentation Highlights Sep 2026 Growth Strategy Details
 
8ADB, Madhya Pradesh Partner To Unlock $1 Billion For Green Energy Details
 
8Coal Supply to Power Plants Improves as Rake Loading Rises Details
 
8Punjab Power Output Dips Despite 117% Coal Stock at PSPCL Plants, Centre Says Supply Isn’t the Issue Details
 
You can also click on Newsclips for more Details
NHPC rebuilds Rs 2,253.97 crore Link-3 package through eight extensions, raising turnover bar to Rs 813 crore while relaxing gate credential
8Corrigendum 8 lifted one-work civil experience to Rs 1,841 crore and cut the vertical-lift gate threshold from AxH 224 cubic metres to 100, while nine activity milestones collapsed into seven system-level checkpoints with TBM availability due in month three.
8The cut-off wall depth also moved from about 15 m to 20 m without extending the 36-month execution period.

 

UJVNL puts 3x40 MW Sirkari Bhyol Rupsiabagar electro-mechanical works out at Rs 158.53 crore on a one-page notice
8The turnkey EPC package covers design through commissioning, but the notice carries no equipment configuration, battery limits, completion period, LD regime or security structure, while two corrigenda sit on the portal without disclosed content.
8A 47-day window with only 27 days after the pre-bid meeting leaves bidders pricing "other associated different works" without a responsibility matrix.

 

NTPC Barauni ash package caps compressor power at 1,050 kW with Rs 1.81 lakh payable for every excess kilowatt
8The dry fly ash augmentation contract carries Rs 6.09 lakh daily delay LD, a 12% performance-LD ceiling and a seven-day continuous trial, while amendments deleted the original scheme and layout drawings and pushed construction power onto the bidder.
8Geotechnical data arrived only through Annexure P after bidders had already priced foundations.

 

MSEDCL asks for 3,599 SCADA-ready RMUs while its own documents disagree on whether the breaker is 200 A or 400 A
8Section III specifies a 400 A vacuum circuit breaker with 400-200/1 CTs; the embedded 11 kV specification repeatedly says 200 A, a divergence that reaches type-test validity, protection coordination and price comparability across a Rs 387.52 crore package.
8The bid notice and portal also differ by 30 minutes on both submission and opening.

 

WBSETCL Package C3 lets bidders choose between lead and corrugated aluminium sheath on the same 220 KV cable
8Rather than amending the conflicting specification, the utility resolved KEC International's pre-bid query by transferring sheath selection to bidders while fixing the metallic-sheath fault level at 40 KA for one second.
8A revised BOQ landed on 6 May against an 11 May deadline, with residual formula errors left correctable during price evaluation.

 

NRPC's Rs 25,000 audit tender cannot decide whether it is a single-packet or two-packet bid
8The GeM configuration prescribes two packets and marks arbitration "No", while ATC Clause 1.1.1 mandates a single-packet process and Clause 4.5.2 installs an arbitrator appointed by NRPC's own Member Secretary.
8Force majeure thresholds inside the same document sit at three months and two months.

 

SECI ties 700 MW of solar to SEZ/EOU status and tells developers that losing it is neither Change in Law nor Force Majeure
8Clause 20.11 makes de-bonding, cancellation or suspension the developer's sole risk across a 25-year PPA whose ALMM exemption depends on that very status, with the Odisha C&I off-taker unnamed.
8SECI can still annul the process after tariff discovery if no buyer emerges.

 

RVUN seeks 12.5 lakh MT of coal in seven days, bars JVs and demands a single 1-million-MT contract record
8The Rs 1,125 crore Suratgarh tender requires turnover equal to the full estimate, net worth above Rs 375 crore and rail-loading access, while prohibiting consortiums that would normally combine coal, rail and balance-sheet strength.
8The portal flags it as emergency procurement without naming the rule invoked.

 

DHBVN admits five bidders on Palwal RDSS package 58 days after the scheduled technical opening
8Agarwal Electrical, Agarwal Traders, Century Infrapower, Laser Power & Infra and RP Infrapower cleared the fee, prequalification and technical stage on 3 September against a 7 July opening date.
8The Rs 133.62 crore turnkey scope still depends on feeder-wise BOQs to be surveyed and approved after award.

 

UJVNL extends Kulhal RMU bidding five times, moving the deadline 68 days without touching the 52-month schedule
8The Rs 110.57 crore turnkey package makes the contractor reconstruct the engineering baseline of a 1975 plant through reverse engineering, 3D scanning, CFD, FEA and residual-life assessment at its own risk.
8Manufacturer-backed qualification attracts 15% performance security instead of 10%, plus another 5% against the authorised scope.

 

JUSNL cuts consultancy turnover threshold by 22.9% after tendering against the wrong estimate
8The corrigendum reduces minimum average annual turnover from Rs 17.32 crore to Rs 13.35 crore and relevant-business revenue from Rs 4.33 crore to Rs 3.34 crore, correcting a base that mixed an excluding-GST figure with an including-GST estimate.
8The liquid-resource requirement and the conflicting bid-start and opening timestamps remain untouched.

 

NTPC prepays CSIR-SERC in full for Farakka structural assessment with no bank guarantee, LD or defect liability
8The single-tender consultancy waives EMD, security deposit, PBG, qualifying requirements and evaluation while NTPC additionally funds travel, boarding, local transport and PPE for the visiting scientists.
8Three extension instruments in the archive state neither the original nor the revised dates.

 

NHPC trims derived-rate overhead from 20% to 18.63% on Rs 267.94 crore Salal bypass tunnel
8Corrigendum 1 rewrote the insurance clause so NHPC funds the works policy while the contractor handles claims, deductibles and reinstatement, with up to 5% withholdable from running-account bills for incomplete claim information.
8Disclosed geology includes solution cavities, squeezing ground, rock burst, hot water and ingress above 6,000 litres per minute.

 

GSECL asks one consultant to write the Dharoi PSP contracts and then police them for 68 months
8The Rs 2.10 crore EMD, 75-mark technical threshold, 200 MW hydro reference and JV prohibition narrow the field before methodology scoring begins, while a "Stop Gap" clause lets
GSECL exclude declared periods from the completion count.
8The tender never states the project's installed capacity.

 

RRVPN rejects every pre-bid attempt to widen the field on Rs 125.98 crore Sawai Madhopur substation
8Requests to count bay-extension work, cut the four-substation threshold to two and drop bidder-level transformer experience were all answered with instructions to follow the existing PQR.
8Bids more than 15% below estimate attract additional security equal to half the unbalanced amount.

 

Only BHEL and LC Infra clear technical opening on UJVNL's Rs 1,024.45 crore Lakhwar EPC
8Both bids were admitted on 5 September after a single seven-day extension, leaving no redundancy if detailed evaluation eliminates either offer.
8Turnover thresholds rise from Rs 308 crore to Rs 820 crore for manufacturer-backed bidders, who also face 15% performance security and a lock on the named turbine and generator OEM.

 

WAPCOS excludes arbitration from its own Rs 1.50 crore transformation mandate while listing the Arbitration Act as applicable law
8Claims must pass an internal EIC or GM (HR) decision, a Departmental Review Committee and mediation before reaching the Delhi courts, with early filing treated as material breach.
8A corrigendum chain moved the pre-bid meeting from "not held" to an online session, then pointed to both August and September.

 

MAHAGENCO's Koradi skirt-board tender carries two qualification frameworks and two different carbides
8Turnover is required at both 30% and 100% of estimated cost, while experience is tested through a seven-year 40/50/80 formula in one schedule and a three-year plus 25%-order test in another.
8The subject line and panel description say tungsten carbide; the service-item text says modular silicon carbide.

Details
 For reference purposes the website carries here the following tenders:
 
8Tender for interlinking 11 kV line Details
 
8Tender for interlinking of feeder Details
 
8Tender for upgradation of 66kV substation Details
 
8Tender for reconstruction of damaged internal using Details
 
8Tender for protection and reconstruction of existing drainage channel at 110kV substation Details
 
8Tender for installation of third 220/110 kV, 100 MVA, 3 phase transformer Details
 
8Tender for supply of RAPH spares for RAPH model no. 33.5 VAT 1530 at 2X660 MW Details
 
8Tender for requirement of ferrous / Non ferrous items Details
 
8Tender for requirement of control cables Details
 
8Tender for const. of control room at 33 kV sub-station Details
 
8Tender for construction of 0.5KM 220 LILO transmission line Details
 
8Tender for RLA test on different rating transformer Details
 
8Tender for contract for residual coal cleaning of wagons during rake unloading Details
 
8Tender for biennial maintenance works (masonry & carpentry) to RB’s Details
 
8Tender for maintenance of earth pits inside factory Details
 
8Tender for construction of soild waste management yard Details
 
8Tender for construction of inspection hut including chain link Details
 
8Tender for supply installation testing and commissioning of Nine Nos. SMAs and One No. seismometer to replace existing non functioning units Details
 
8Tender for handling, lifting, unloading of four numbers of steam generators and accessories Details
 
8Tender for procurement of 11kV fixed contact 200A Details
 
8Tender for turbine transportation of HP and IP rotor assembly Details
 
8Tender for upkeepment and monitoring of conveyors and related equipments attending breakdown, preventive mechanical maintenance works in conveyor Details
 
8Tender for upkeepment and attending breakdown and preventive mechanical maintenance of conveyors Details
 
8Tender for supply of M.S back clamp for 8m PSC pole Details
 
8Tender for service contract for thorough overhauling of wagon tippler Details
 
8Tender for procurement of carrying idler for CHP Details
 
8Tender for short shut down maintenance work of BHEL ESP Details
 
8Tender for restoration of damaged protection work Details
 
8Tender for protective coating of underwater parts of turbine Details
 
8Tender for annual maintenance work of 33/11 kV S/s Jalali Details
 
8Tender for annual maintenance work of 33/11 kV S/s Bagwalipokher Details
 
8Tender for annual maintenance work of 33/11 kV S/s Details
 
8Tender for replacement of rabbit/weasel conductor Details
 
8Tender for annual maintenance work of 33/11 kV S/s Details
 
8Tender for replacement of bare conductor by covered conductor ACS AL59 104.98 Sq.MM Details
 
8Tender for replacement of bare conductor by covered conductor Details
 
8Tender for replacement of bare conductor by covered conductor ACS AL59 104.98 Sq.MM Details
 
8Tender for replacement of bare conductor by covered conductor Details
 
8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 25 MVA, 132- 110/33 kV T/F Details
 
8Tender for supply & installation of MFM energy meters at various EHV sub-stations Details
 
8Tender for work of conversion of existing 110 kV SCSC line Details
 
8Tender for work of replacement of faulty MOG, air-cells of transformer’s & ICT’s at various 220/132/110kV S/Stns Details
 
8Tender for restoration and complete revamping of existing SAS at 220kV sub station Details
 
8Tender for work of arresting oil leakages from various joints & bolts of EHV Transformer, ICTs, CTs, PTs & other equipments Details
 
8Tender for work of strengthening of existing providing new tower along with suitable hardwares, accessories Details
 
8Tender for work of application of RTV coating on 33 kV tertiary bushing,33kV PT, 33kV LA & support insulators Details
 
8Tender for procurement of 420kV, 2x80MVAr switchable line reactor along Details
 
8Tender for work of shifting/raising of DC 220kV line Details
 
8Tender for work of shifting/raising of DC 132kV panther conductor Details
 
8Tender for ARC for erection of HT / LT / TC and maintenance Details
 
8Design, supply, installation and commissioning of high performance heavy duty energy chain system along Details
 
8Tender for supply of ceramic blanket [50 mm thk.] for 1X500 MW boiler Details
 
8Tender for supply of I to P converters Details
 
8Tender for erection of 66kV SS equipment, structures, control wiring, yard lighting Details
 
8Tender for erection of 66kV SS equipment, structures, control wiring Details
 
8Tender for supply of BEE 5 Star 30 watt LED tube light & 20W inverter Details
 
8Tender for supply, erection, testing & commissioning of LILO of both circuits of existing 220kV D/C line Details
 
8Tender for ARC for erection of HT / LT / TC and maintenance work Details
 
8Tender for supply, erection, testing and commissioning of 220V DC, 63 AH, KPH 63P, Ni-Cd type battery set Details
 
8Tender for maintenance of ash dyke Details
 
8Tender for providing RCC chamber with protection wall and cabin for installation of flow analyzer Details
 
8Tender for supply of carbon steel, mild steel, alloy steel pipes and its fittings Details
 
8Tender for work of O/H & servicing of ID fan/ FD fan / PA Fan & their connected system Details
 
8Tender for laying of new XLPE cable against Details
 
8Tender for work of preventive maintenance, shutdown & emergency maintenance of IAC/SAC compressor, air washery Fan/pump motor Details
 
8Tender for work of routine, preventive, overhauling and breakdown maintenance of Air conditioning systems Details
 
8Tender for supply of various ratings LT motor Details
 
8Tender for work of supply, installation, complete overhauling and testing of 60 tones DT gate crane Details
 
8Tender for supply of GI coated heavy duty MS grill Details
 
8Tender for ARC for supply erection and commissioning of of GI cable tray Details
 
8Tender for work of laying & removing of various power, control & instrument cables Details
 
8Tender for supply of CPVC pipes, fittings and valves Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
ECL Suffers Rs 1,257 Crore Loss Despite Record Coal Production of 52 MT Details
 
8Coal India Production, Dispatch Set To Accelerate As Monsoon Weakens Details
 
8Wind power generation in TN rises 3.3% as July, August output surges Details
 
8ICRA Reaffirms [ICRA]A1+ Rating For Solar Industries India’s INR 500 Crore Commercial Paper Programme Details
 
8Noida Expressway: Authority To Install 1,200 Solar-Powered Streetlights For Illumination Details
 
8India’s NMDC targets Q4 thermal coal production, up to 1 million tonnes in FY27 sales Details
 
8USD 3.5 tn vision: Gujarat bets big on AI, chips and green energy to power 2047 growth Details
 
8Centre Says Adequate Coal Supplied to Punjab Power Plants Details
 
8Punjab power generation drops by 1,500 MW amid severe coal shortage Details
 
8Rs 12-crore power boost for Chandigarh's northern sectors Details
 
8PL group spots next capex wave in power, data centres, and renewables Details
 
8Will industry participate in the government's call for participation in indigenous SMR development Details
 
8plants with critical coal levels rise to 58; experts say no crisis Details
 
8National coal shortage deepens power crisis in Punjab; 2 thermal plants operating with critically low stock Details
 
8Coal India’s Extra Coal Offer: Why Are Power Plants Running Low Details
 
8Sarda Energy Clarifies Volume Movement Following Supreme Court SKS Power Order Details
 
8NMDC to Start Commercial Coal Production Next Quarter Details
 
8Karnataka’s big power bet: 66 GW capacity by 2030, Rs 3 lakh crore investment Details
 
8India Thermal Power Plants Face Coal Shortage As Demand Peaks Details
 
8Centre ensures adequate coal supply to Punjab’s power plants from PSPCL mines Details
 
8BCCL – CCL come to Punjab power plants’ rescue, but coal lifting lags Details
 
8Power grid booster: CG Power unveils India’s largest single-location transformer manufacturing plant Details
 
8Coal India Boosts Production and Dispatch as Monsoon Rains Recede Details
 
You can also click on Newsclips for more Details
 For reference purposes the website carries here the following tenders:
 8Tender for providing and fixing of 220kV and 132kV isolator male and female arm assembly Details
 8Tender for replacement and installation of anti climbing devices across various towers Details
 8Tender for replacement of 2x315MVA, 400/220kV transformer Details
 8Tender for strengthening of earthing system Details
 8Tender for work and material for adding of 33kV bay Details
 8Tender for construction of 132kV bay Details
 8Tender for rate contract for refractory application inside boiler during Details
 8Tender for providing metering and testing services Details
 8Tender for supply, installation, testing and commissioning of 80 nos. of 12V 75 Ah batteries with buyback of old batteries Details
 8Tender for non destructive test on concrete with combined Details
 8Tender for supply of 24 fibre ADSS single mode OFC cable Details
 8Tender for balance civil works of bottom ash overflow tank, surge tank, bottom ash seal water tank Details
 8Tender for procurement and installation of one no additional 500KVA rating DG set Details
 8Tender for procurement of speed probes for main turbine Details
 8Tender for work contract for repairing of damaged concrete panels Details
 8Tender for miscellaneous civil works Details
 8Tender for balance erection and commissioning works of limestone handling system Details
 8Tender for procurement of various insulating materials for BHEL make 588 MVA, 21 kV turbo-generator Details
 8Tender for comprehensive annual work contract for related works Details
 8Tender for supply and erection of 33kV 10km O/H line Details
 8Tender for supply of 12.5 Lakh MT domestic coal Details
 8Tender for revival restoration work of 1st pass of boiler Details
 8Tender for supply of knife edge gate valve (pneumatically operated) and butter fly valves Details
 8Tender for supply of EPDM rubber bellows for 6.6kV SPBD and 15.75 kV IPBD busduct connecting to EHV transformers Details
 8Tender for drawing dedicated 11kV feeder using covered conductor Details
 8Tender for construction of 110kV substation Details
 8Tender for setting up of 700 MW ISTS-connected solar PV power projects Details
 8Tender for upgradation and modernization of critical infrastructure work Details
 8Tender for work of Bi-annual AMC for planned and breakdown/ emergency substation maintenance work along with spares Details
 8Tender for construction of new turfing in 132kV switchyard Details
 8Tender for construction of new road from gate of substation to switchyard gate Details
 8Tender for procurement and erection of copper wound oil cooled constant voltage transformers Details
 8Tender for work of protection wall at tower Details
 8Tender for annual routine maintenance preventive and breakdown of 132kV line Details
 8Tender for providing fixing commissioning and testing of 33kV 110V PT at 132kV substation Details
 8Tender for concertina coil fencing and cement concreting work at tower base Details
 8Tender for providing fixing and commissioning of 33kV isolator Details
 8Tender for construction of 33 kV line Details
 8Tender for replacement work existing weasel conductor with various Details
 8Tender for replacement work existing weasel conductor with various size of 3 Ph AB cable Details
 8Tender for construction of 33 kV line for rope-way from 33/11 kV substation Details
 8Tender for replacement work of existing weasel conductor with various size Details
 8Tender for procurement of spares of intake pump Details
 8Tender for Bi-annual rate contract for coal cleaning and housekeeping Details
 8Tender for comprehensive biennial maintenance contract for room, tower and duct-able air conditioner systems Details
 8Tender for supply, installation, testing, commissioning and comprehensive annual maintenance contract of SCADA system for a period of Five years at 10 MW solar PV power plant Details
 8Tender for operation maintenance for a period of 05 years of grid connected rooftop solar PV power plants of cumulative capacity 8.415 MWp Details
 8Tender for supply, installation, testing, commissioning and comprehensive annual maintenance contract of SCADA system for a period of Five years at 10 MW solar PV power plant Details
 8Tender for operation maintenance for a period of 05 years of grid connected rooftop solar PV power plants of cumulative capacity 8.415 MWp Details
 8Tender for manufacturers only for manufacture, testing, supply and delivery of 11kV and 33kV polymer post insulator Details
 8Tender for operation of 33/11kV substation maintenance of 33/11 kV substation Details
 8Tender for construction of single circuit transmission line Details
 8Tender for diversion/shifting of existing 220 kV D/C transmission line Details
 8Tender for rectification replacement of defective boiler tubes in 9th header economizer coils Details
 8Tender for rectification replacement of defective tubes in water wall area S panel Details
 8Design, manufacture, testing, inspection, packing and delivery of 2,10,000 Nos. 11kV composite polymer disc insulators Details
 8Tender for repair augmentation of existing 66kV line Details
 8Tender for work of repairing of damaged OPGW wire strand Details
 8Tender for work of various civil maintenance works of hot line maintenance unit Details
 8Tender for work of various miscellaneous work at 33 kV switchyard Details
 8Tender for work of upgradation & restoration of existing GE Make partial working SCADA system along Details
 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 25MVA, 132- 110/33 kV T/F along Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
UPERC Extends P2P Renewable Energy Trading Pilot to 2027 Details
 
8Stocks in news swiggy coal india anlon healthcare action Details
 
8Govt's Rs 37,500-crore coal gasification scheme fails to attract bids Details
 
8Waste-to-energy plants are highest-polluting industrial sector in India, new CFA report finds Details
 
8Eastern Coalfields Limited to close 11 active coal mines, cites financial loss Details
 
8India proposes mandatory battery storage for new solar, wind projects from July 2027 Details
 
8New geothermal data reveals India holds 10.6 gigawatts of subterranean thermal capacity Details
 
8Kerala Apartment Complex Installs 20 kW Rooftop Solar System Details
 
8GREW Solar bags Rs 430 Crore G12R module order Details
 
8PowerMin body for 10% energy storage for RE projects after July 2027 Details
 
8Why does India want new solar, wind projects to have batteries Details
 
8India Plans Mandatory Battery Storage at Solar and Wind Projects Details
 
8Coal Remains Key: Critical role in providing firm, continuous and flexible power Details
 
8Wind Revival: Building momentum towards 2030 Details
 
8Govt invites industry to lead Rs 60,000 crore PM-SETU initiative to revamp ITIs Details
 
8MP High Court: Landowner Consent Not Required for Power Lines Details
 
8Digital public infrastructure and the future of renewable energy: insights from India Energy Stack Details
 
8Power Stock Surpasses 15 GW Capacity Milestone, Renewable Energy Portfolio Crosses 60% Details
 
8SECI Invites Bids for 700 MW ISTS-Connected Solar Projects Details
 
8Govt urges industry to lead Rs 60K crore PM-SETU initiative to drive energy, industrial transformation Details
 
8CG Power Rolls Out First Transformer from India’s Largest Facility at Sehore (MP) Details
 
8India Mandates Battery Storage For New Renewable Projects From July 2027 Details
 
8Inside The Kirloskar Anglo Belgian Indigenous 6 MW Marine Diesel Engine Program That Could Power India’s Future Warships Details
 
8Jefferies picks 5 sectors for up to 49% gains in FY27: HDFC, Adani Energy, DLF lead stock bets Details
 
8How DRDO Plans To Build India’s Next-Generation Electronic Warfare Edge through SHIELD Program Details
 
You can also click on Newsclips for more Details
BSPGCL's 500 MWh Kajra storage tender makes charging energy the developer's problem behind a single discharge tariff
8The developer must buy its own charging power and absorb losses while quoting one Rs/kWh rate at 132 kV.
8That turns a battery EPC price into a 15-year commodity exposure on top of Rs 70 crore of layered security.
8The September 8 pre-bid will show whether contradictory extension clauses and an undefined handover standard force a rewrite.

 

UPPTCL taxes aggressive bidding on the Rs 102 crore Prayagraj GIS package with a sliding security ladder
8Every percentage point below benchmark adds performance security, rising to 1.00% per point beyond a 10% discount.
8Routine arbitration is deleted too, so undercutting costs cash and disputes run through internal committees.
8With no combined cap and no transformer delivery schedule, the question is how narrow the field gets by September 24.

 

TGTRANSCO's Sadashivpet–NIMZ line package carries a 22-RTU obligation the price schedule never mentions
8Clause 5.26.1 calls for 22 RTUs while the priced schedules cover just two SAS units for the NIMZ bays.
8A deemed-completeness clause and a one-way lump-sum correction rule push that gap onto the contractor.
8Whether a corrigendum lands before September 24 decides if it stays drafting noise or becomes scope.

 

MSEDCL's Rs 179 crore 22 kV cable tender pairs firm prices with a 100% extension option
8Prices for 7,34,000 metres stay firm with no commodity variation, yet MSEDCL can order the same quantity again on unchanged terms.
8Type-test validity is stated as both ten years and five, and IS 7098 appears in both its 1985 and 2011 editions.
8Even after the September 1 opening, the 50% cap on an out-of-state L1 means the lowest price will not settle the order book.

 

MSEDCL's Rs 98 crore 11 kV and 33 kV cable tender loosens drum lengths but keeps every commercial lever
8Clause 9.02 now allows 500 or 250 metre drums, but MSEDCL can still demand 250 metres wherever it chooses.
8The same type-test and IS 7098 conflicts recur, alongside a payment clock that starts only when a full monthly lot arrives.
8The open question is how many bidders sized their 20% minimum offer to real extrusion capacity.

 

GETCO rewrites the Tharad STATCOM engineering bargain across four extensions without touching the 24-month clock
8The Rs 244.54 crore package moved 80 days to September 17 while shifting to a 50°C rating and a 1.5% loss ceiling.
8In exchange, bidders take on oscillation proof, HVDC interaction studies and five years of post-guarantee interference liability.
8The reverse auction will show whether easier equipment thresholds get priced harder than open-ended network risk.

 

NHPC trims derived-rate margins and rewrites insurance on the Rs 268 crore Salal sediment bypass tunnel
8The contractor still funds reinstatement and faces 5% bill withholding if claim paperwork lags.
8Two extensions added 88 days to bidding but nothing to the 29-month execution period.

 

DVC holds the 12-month clock on Chandrapura's Rs 90 crore line diversion after four extensions and a late arrester spec
8Submission moved 42 days to September 14, with the lightning-arrester specification added only 11 days before that.
8Underground cable is half the estimate, yet the named cable contractor cannot be replaced after award.
8The issue is whether bidders load the uniform percentage or walk away from a schedule they called unworkable.

 

BHEL's Darlipali ash handling tender adds 50% more slurry pumps and a fixed hydraulic baseline while the 4,600 kW cap stays put
8Corrigendum 05 fixed wash-water and sludge duties and raised bottom-ash disposal pumps from six to nine.
8Four extensions took bids to September 10, but the 34-month schedule and US$5,245-per-kW damages never moved.
8The reverse auction will reveal whether cautious bidders lose to those assuming detailed engineering absorbs the gaps.

 

BHEL's Darlipali ash handling tender dates its experience cut-off nine months before its own NIT
8Annexure 1 reckons experience "as on 06/11/2025" against an NIT dated July 29, 2026.
8Milestone withholding, 5% delay LD and 12% performance LD stack on one counterparty with no interest on withheld sums.
8Whether the three qualification routes widen the field enough for a meaningful auction is the thing to watch.

 

NPCIL bolts a 15% import loading onto the Kudankulam 5 and 6 common services package after eight extensions
8Corrigendum-XII inserted high-seas-sale transfer, customs procedures and a 15% CIF loading 177 days after the original deadline.
8Corrigendum-XI separately enlarged chiller envelopes to 32 MT, reaching into foundations on a 1,278-day schedule.
8With BHEL, L&T, NCC and Tata Projects in the query record, the question is whether the loading reorders a small field rather than widening it.

 

BHEL's Korba West coal handling tender puts 75% of the price on land it does not expect until May 2027
8One lump sum splits 25:75 between internal and external CHP, with no compensation if the external land arrives late.
8Reverse auction was deleted a day after the NIT, but cross-default across every LOA leaves no contractual ring-fence.
8After five extensions to September 10, the open issue is how much contingency lands in Package B.

 

SECL's Gevra weighbridge consultancy asks five CPSUs to price 2,520 days against a portal that shows five years
8GeM displays five years, but the corrigenda fix 2,520 days of exposure backed by an 86-month ePBG.
8The PMC also runs a 20% imprest and pays contractors, with 45% of its Stage III fee tied to that role.
8With five invitees and no floor price, the question is whether the lowest percentage survives seven years.

 

NTPC's Rs 200 crore Kahalgaon pond ash contract offers five contractors a panel seat and none of them guaranteed work
8GeM says no bid splitting, but the ATC splits the contract five ways, caps each at Rs 40 crore and allows minus 100% quantity.
8Payment follows the lowest of three measurements before 5% reconciliation and 2% safety retention.
8The real test after the August 31 close is how many ranked bidders accept the discovered L1 across all six distance slabs.

Details
 For reference purposes the website carries here the following tenders:
 
8Tender for biennial maintenance of civil works Details
 
8Tender for providing pedestal for water tanks and replacement of CGI sheet roofing Details
 
8Tender for restoration of the retaining structures and supporting the areas affected by slips/landslides Details
 
8Tender for energy management system for stage 1 and stage 4 Details
 
8Tender for slope protection of high embankment of MGR railway track Details
 
8Tender for supply and installation of multi-tier racking systems along with material handling equipment Details
 
8Tender for supply installation commissioning of interlocking wall block machine Details
 
8Tender for repair maintenance of CISF barrack and sewage system Details
 
8Tender for contract for rain water harvesting work Details
 
8Tender for biennial rate contract for civil repair and maintenance and other miscellaneous works Details
 
8Tender for chain link fencing Details
 
8Tender for SR works augmentation of infrastructure Details
 
8Tender for BRC for various natures of RCC dismantling, demolishing, cutting and strengthening works Details
 
8Tender for supply of resin Details
 
8Tender for supply of 11 kV measuring potential transformers of accuracy class 0.2 Details
 
8Tender for supply of 11 kV current transformers (CTs) of accuracy class Details
 
8Tender for supply and spreading of bajri at various 33 kV sub- stations Details
 
8Tender for ARC of cleaning work of boiler and its auxiliaries Details
 
8Tender for procurement of spares for bulldozer-BD155 installed Details
 
8Tender for construction of RR masonry/ RCC revetment wall/ hume pipe culvert Details
 
8Tender for empanelment of contractors to award a contract for 11 kV under ground railway crossing Details
 
8Tender for manufacture and supply of LT cables Details
 
8Tender for rate contract for rewinding of different rating of 3-phase, 415 V, sq. cage LT induction motor Details
 
8Tender for procurement of stacker/reclaimer and wagon tippler installed Details
 
8Tender for deputation of service engineer for complete servicing of DAVR along with reviewing settings and PSS tunning Details
 
8Tender for supply, installation and commissioning of electronic water level indicator Details
 
8Tender for procurement of EIP make spares for ash level indicators in ESP, buffer and duct hoppers Details
 
8Tender for procurement of blowing tubes of semi retractable soot blowers installed Details
 
8Tender for procurement of HPBP steam pressure control valves ARS 100 and water spray temperature control valve Details
 
8Tender for procurement of complete runner shaft assembly for core Air fan labyrinth shaft seal Details
 
8Tender for procurement of spares for power reeling drum for travelling tripper installed Details
 
8Tender for availing OEM supervisory service for complete servicing, reinsulation and overhauling of BHEL make 11/6.6 kV HT switchgear panel modules Details
 
8Tender for procurement of 6.6kV 910 KW CW pump motor Details
 
8Tender for enhancement of transformation of capacity of substation by replacement of 2x100MVA, 220/132kV ICTs by 2X200MVA, 220/132kV ICTs Details
 
8Tender for work of enhancement of transformation capacity by replacement of existing 2X100MVA, 220/132kV ICT Details
 
8Tender for maintenance of the power house Details
 
8Tender for supply of finned economizer coil J bend material Details
 
8Tender for procurement of 1100V, 4x240 sqmm LT UG XLPE armoured aluminium power cable. Details
 
8Tender for supply of economizer coil U bends for unit V boiler Details
 
8Tender for supply of pressure parts tubes and bends for 210 MW capacity boiler Details
 
8Tender for supply of straight tubes and bends for pressure parts Details
 
8Tender for supply and erection of deteriorated and dislodged insulation and re insulation with new insulation materials Details
 
8Tender for supply of pressure parts tubes and bends for 210 MW capacity boiler Details
 
8Tender for supply of acute bend of size Details
 
8Tender for supply of economizer coil ‘U’ bends for unit Iv boiler Details
 
8Tender for complete overhaul of APH A and B sides and other related works Details
 
8Tender for entrusting works contract for carrying out all type of maintenance and breakdown activities by engaging additional gang at 400 kV substation Details
 
8Tender for supply of stay wire 7/12 SWG 15000 kg Details
 
8Tender for works contract for execution of extension, improvement, DCW and various works Details
 
8Tender for construction of boundary wall towards eastern side of 132/33 kV G/S/S Details
 
8Design manufacturing testing inspection installation commissioning demonstration and supply of energy meter Details
 
8Design, supply, including civil works related to site preparation for installation, testing, commissioning, operations and maintenance for charging stations Details
 
8Design, manufacture, supply, testing, laying, jointing, commissioning of 132 kV single core 400 mm2 XLPE (aluminium conductor) UG cable Details
 
8Tender for repair augmentation of existing 66kV line Details
 
8Tender for procurement of caustic lye commerical grade Details
 
8Tender for rate contract for work of rewinding and repairing of various rating of LT motor, submersible pump and various Details
 
8Tender for renovation the shed of fire station Details
 
8Tender for supply, erection, testing and commissioning of data acquisition, condition monitoring cum analytics system for transformers Details
 
8Tender for construction of diesel dispensing unit Details
 
8Design, supply, and installation of free water knock out system Details
 
8Tender for repairing work in power house Details
 
8Tender for replacement of MIV disc seals and all associated works for all three units Details
 
8Tender for conversion and renovation of 11 kV bare conductor to MVCC line Details
 
8Tender for rate contract for supply of different grades of shell lubricants Details
 
8Tender for work of chimney height raising for 220 KV and 110 kV lines Details
 
8Design, engineering, supply, erection, testing and commissioning and comprehensive O&M for 5 years for 1000 KWP DC capacity rooptop solar PV power system Details
 
8Tender for work of mechanical and stubstrengthening for 66kV line Details
 
8Tender for work of erection of 66kV Lilo to S/s line from 66KV S/C with ACSR panther conductor Details
 
8Tender for annual rate contract for new HT Conn., LT Conn. & TC erection & maintenance of line work Details
 
8Tender for work for replacement of suspension/ tension conventional insulator by SRI on 220kV class lines Details
 
8Tender for work of erection, testing and commissioning of new FOAC cable in existing 66kV UG line network Details
 
8Tender for work of erection- dismantling of 66kV/11KV equipment’s, structures, control wiring Details
 
8Tender for rate contract for loading, unloading, shifting and transportation of materials Details
 
8Tender for procurement and installation of 15 MT capacity single girder under slung EOT cranes Details
 
8Tender for interior repairing and maintenance of 18 nos. C/D-type Details
 
8Tender for consultancy firm for feasibility study for BESS and DPR for battery bank system Details
 
8Tender for work of coal mill performance test of unit Details
 
8Tender for procurement of water flow meters for raw water intake pump houses Details
 
8Tender for supply of LT feeder piller box Details
 
8Tender for manufacturing and providing of spares of barrage gates Details
 
8Tender for renovation up gradation and modernization of supervisory control and data acquisition and control room interior Details
 
8Tender for supply of 3kV outdoor pole mounted combined CT-PT unit with meter box Details
 
8Tender for fabrication work of weather protective shed/canopy on foundations of boiler side HT & LT motors Details
 
8Tender for supply of controller slewing, long travel & luff operation of stacker reclaimer Details
 
8Tender for supply of flap gate assembly with motorized linier actuator for coal handling plant Details
 
8Tender for supply of various size valves for boiler unit Details
 
8Tender for work of residual life assessment study of removed HP, IP & LP turbine rotors Details
 
8Tender for urgent construction of compound wall to replacement existing damaged chain link at 220kV S/stn Details
 
8Tender for Bi-AMC for internal inspection, attending oil leakages through HV & LV bushing Details
 
8Tender for work of annual maintenance contract for the work of repairs/servicing of various transformer’s and ICT’s cooling fans Details
 
8Tender for annual maintenance contract for the work of chemical treatment Details
 
8Tender for work of renovation and augmentation of existing earthing system Details
 
8Tender for work of retrofitting of existing air conditioning system Details
 
8Tender for enhancement of transformation capacity of substation by replacement of 3X105MVA, 440/220/33kV ICT-I by Details
 
8Tender for work of monkey patrolling of S/C & D/C towers Details
 
8Tender for work of supply, civil and ETC of replacement of 220kV & 132kV CTs and PTs without tan delta point and 33kV CTs at various EHV S/stn Details
 
8Tender for erection and maintenance work of HT/LT/TC line Details
 
You can also click on Newsclips for more
 
For reference purposes the website carries here the following newsclips:
 8
CEA Proposes Mandatory Energy Storage for Solar and Wind Projects Details
 
8India’s installed renewable energy capacity crosses 290 GW, experts urge focus on green skills Details
 
8Bondada Engineering Sets Up Subsidiary For 225 MW/450 MWh BESS Project In Andhra Pradesh Details
 
8As water stress deepens, India asks thermal power plants to account for every drop Details
 
8Jharkhand to repurpose closed coal mines; two units selected for pilot projects Details
 
8Mahanadi Coalfields Files DRHP for 66.18 Crore-Share OFS Details
 
8Surrounded by energy crises, Bihar eyes Rs 1.38 lakh crore solar investment Details
 
8India Needs 888 GWh of Energy Storage by 2035-36 to Support Renewable Energy Growth: IESA Chennai Connect 2026 Details
 
8Windergy India 2026 to Spotlight India’s Growing Wind Manufacturing and Export Ambitions Details
 
8Kalpa Power Appoints Jabraj Singh as Chief Operating Officer Details
 
8We’re Quite Excited About It”, Says Rajesh Ganesh, MD & CEO, Bajel Projects On India’s Transmission Buildout Details
 
8RECPDCL Awards 6 GW Solar Transmission Project in Rajasthan Details
 
8Solex Energy secures INR 74.77 crore solar module supply orders Details
 
8Inox Clean Energy to Acquire Vena Energy India Platform with 1 GW Operational Capacity and 5.4 GW Solar-Wind Pipeline Details
 
8India needs to support larger turbines”: Interview with IWTMA’s Aditya Pyasi Details
 
8Haryana Electricity Regulatory Commission reserves order on pvt power distribution licence for Gurugram Details
 
8NTPC Green Energy: Should You Buy, Hold, or Sell Right Now Details
 
8Adani Power: 3 key reasons why MOFSL is bullish on this Adani group stock Details
 
8Inox Wind Secures 100 MW Turnkey Order from Indian Oil Corporation Details
 
8Coal India Rushes Supplies to Power Plants as Stocks Dip Details
 
8Adani Power’s Expansion Tests India’s Next Energy Buildout Details
 
8Data centres to add just 0.13% to India GDP: Moody’s Details
 
8Clean Max Enviro Energy Solutions Shares Rise Following Rs 199 Crore Block Deal Details
 
8Madhya Pradesh: Sehore Transformers Set to Power Global Markets as New Scale Unit Begins Production Details
 
8Power Grid Wins Transmission Project for 7,500MW Gujarat Renewable Energy Integration Details
 
8Karnataka to scale up power generation for 2030 Details
 
You can also click on Newsclips for more Details
8A servo-motor repair at Kerala’s 340 MW Sabarigiri hydro station finished about 19 hours ahead of its approved outage and preserved an estimated 17.59 MU of generation worth Rs 8.79 crore, KSEB says.
8The intervention also addressed a valve defect that could have caused severe hydraulic damage and a prolonged unit outage. Details
8Serentica Renewables has 6.8 GW of contracted renewable capacity but still must deploy about Rs 22,700 crore as 3.6 GW remains under construction.
8Its storage headline is also much larger than its operating base: roughly 2 GW is planned or contracted, while only 50 MW was operational in the rating record. Details
8Uttar Pradesh Power Corporation says it has credited Rs 32.75 crore to 92,231 smart-meter consumers after irregular charges were identified.
8The regulator accepted the verified refund position but ordered a two-month replacement roadmap for 907 older prepaid meters that were excluded because those accounts had not been charged. Details
8SAEL Solar P6 has lost its bid for unrestricted energy banking and complete exemption from banking, transmission and wheeling charges for a captive solar project in Uttar Pradesh.
8The regulator held that project-specific relief would shift costs to other consumers and preserved only the 50% network-charge concession available under state policy. Details
8Karnataka’s electricity regulator has rejected a request to postpone industrial outage compensation for three years.
8Eligible high-tension factories must receive demand-charge relief when monthly interruptions breach the approved limit, with the cost assigned to the distribution company or recovered from the transmission utility according to who caused the outage. Details
8Indowind Energy is asking shareholders to approve a related-party purchase worth up to Rs 57.80 crore—143.31% of its FY2025-26 consolidated turnover.
8The proposed seller is promoter Bala Kutti, and the asset is a 20% stake in EPC contractor Everon Power, putting both valuation and conflict controls at the centre of the vote. Details
8A construction consortium has secured a Rs 392.31 crore arbitral award against NHPC for the 2,000 MW Subansiri Lower hydropower project, less than half its Rs 796.87 crore claim.
8NHPC says the award can enter project cost and be recovered through tariff, a position that still depends on regulatory treatment rather than the tribunal alone. Details
8Fujiyama Power Systems says a May fire affected assets carrying approximately Rs 143.6 crore and temporarily stopped operations at its 1.3 GW lead-acid battery plant in Bawal.
8Insurance and outsourced production may contain the disruption, but neither the final physical loss nor the insurance recovery has yet been established. Details
8Sagardighi’s new 660 MW unit reported unaudited pre-commissioning fuel cost of Rs 9.767 a unit while its infirm power was billed at Rs 1.78.
8The West Bengal regulator has allowed the resulting net cost to be capitalised, placing a Rs 186.01 crore short recovery inside the project-cost account rather than the electricity sale. Details
8A Rs 1,088.91 crore expansion of Data Center Holdings India’s Airoli park has been deferred after the company said it had not obtained fire approvals for two proposed buildings.
8The same proposal carries 209 MW of demand and 189 diesel generator sets, making the missing approvals material to a very large new electricity load. Details
8India’s monitored state-sector hydro stations generated 7,156.98 GWh in August 2026, 30.7% below the 10,322 GWh programme and 34.6% below August 2025.
8The shortfall is broad enough to matter for system balancing: the monitored fleet covers 27,524.94 MW, so this is not a single-station outage dressed up as a national trend. Details
8A new 6 GW export route from Rajasthan’s Barmer solar zone carries annual transmission charges of Rs 3,244.33 crore and a roughly 1,000-km high-voltage direct-current line across three states.
8The scale makes the award more than another evacuation project: it commits users to one of the country’s largest recurring transmission bills while concentrating delivery risk in a single interstate corridor. Details
8India’s monitored coal plants hold 49% of normative stock with 45 stations critical Details
8IEX day-ahead demand reaches 805,933 MWh as offered supply falls to 258,699 MWh
8IEX real-time price jumps 23% as scheduled volume falls 63% in one day
8India’s grid spends 9.67 hours outside its frequency band as low-frequency time dominates
8More than 60.6 GW of monitored generation is unavailable as forced outages lead
8Raigarh Pugalur’s missing reverse mode could remove about 3,000 MW of southern export capability
8A Pothencode insulator failure blacks out the 220 kV station and cuts about 300 MW
8All four Kadamparai pumped-storage units are out on stator and rotor earth faults
8Fifteen southern substations breach the transformer N minus one loading test
8Northern ancillary and SCUC settlements total Rs 111.90 crore for one week
8Bongaigaon’s August SCED adjustment returns Rs 3.74 crore to the regional pool
8North Eastern SCUC settlement reaches Rs 1.69 crore for the latest weekly account Details
8QPower defers Winwin-linked securities issue while funding mode and due diligence remain open
8Shera commits up to Rs 3.52 crore to captive solar vehicle and approves related-party PPA
8Kirloskar Electric directs entire Rs 40 crore preferential issue to working capital and debt
8Hitachi Energy India’s independently assigned ESG score rises eight points to 69
8Servotech seeks five-year MD term with pay capped at Rs 3 crore annually
8KPI Green’s finance chief leaves weeks after resigning, with no successor named
8KPI Green subsidiary changes auditor to BDO firm but reports no management concern
8PTC’s cross-border trade jumps 37% as Bhutan dry-season supply rises 77%
8GK Energy shareholders approve a higher borrowing limit without disclosing the new ceiling
8Mahanadi Coalfields files an offer for sale covering up to 661.8 million shares
8ReNew’s 100 MW Tamil Nadu solar project carries 128 debtor days and Rs 228 crore debt
8Hexa’s Solapur captive solar plant beats its P90 output case but leverage remains above 6.5 times Details
8Rajasthan opens four separate 500 MW October auctions with no ceiling price
8West Bengal seeks 200 MW of high-price evening power without a ceiling
8SECI awards 1,500 MW peak renewable supply after bids total 5,605 MW
8Indowind pushes Rs 21.5 crore solar deadline after domestic-module rule causes two-month delay
8Andhra Pradesh seeks four-hour batteries equal to half each participating renewable plant Details
8NIDP seeks short-term round-the-clock renewable power as its RPO remains in deficit
8Madhya Pradesh offers 30% theft-case reduction and waives all accrued interest
8Uttar Pradesh cuts Rosa Power’s five-year fixed-cost claim by Rs 50.89 crore
8West Bengal secures up to 351.155 MW from Bhutan with tariffs rising to Rs 7.67
8DVC secures up to 137.5 MW from Bhutan under the same escalating hydro tariff
8BRPL’s computed fuel surcharge reaches 57.13% while the July levy remains unstated
8Noida Power seeks approval for 300 MW round-the-clock renewable supply with storage
8Noida Power asks to procure 100 MW thermal supply under the SHAKTI framework
8B and G Renewable’s power agreement dispute moves toward arbitration review in Uttar Pradesh Details
 1 2 > 

Showing 1–50 of 89 items