All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Nov 2026

NTPC drops the final 80% cap in its Korba pond-ash haul but still withholds 20% of running bills
8Corrigendum C8 to the Rs 98.48 crore, one-year contract to move 8.4 lakh MT of ash 250–300 km keeps monthly payment at 80%, with a Rs 50 lakh EMD, 5% ePBG and closing moved to 9 November.
8No reconciliation deadline, conflicting diesel base dates, clashing arbitration terms and a minus 100% variation clause keep cash-flow and volume risk with transporters.

 

WCL awards Rs 416.62 crore Kolarpimpri OB-and-coal contract to Chennai Radha at 17.5% below estimate
8The 1,490-day contract against a Rs 504.80 crore base covers 2.92 crore CUM of OB and 81.2 lakh tonnes of coal, with seven of nine bids reaching the financial stage.
8Payment for only 70% of OB before seam exposure, a PBG that works out to Rs 5.10 crore or Rs 20.83 crore depending on the clause and an undisclosed low-bid benchmark keep liquidity risk with the contractor.

 

RECPDCL moves Bikaner V Part C deadline to 30 November while Part B terms stand unchanged
8Amendment V shifts submission by 14 days but LoI and SPV transfer by only 11, leaving Part B's Rs 66.40 crore bid bond, Rs 166 crore CPG and 36-month scope untouched.
8No stated reason, a submission-to-transfer window cut to 28 days from 31 and a three-day document-to-LoI gap keep execution-readiness risk with bidders.

 

RECPDCL's Bikaner V Part C extension leaves the Rs 165.50 crore guarantee and commissioning lock intact
8The amendment puts bids 42 days past the original 19 October deadline for the Bulandshahr–Lucknow-II 765 kV package, which carries a Rs 66.20 crore bid bond and 36-month simultaneous commissioning.
8No reason for the delay, a pending CEA critical-element list and payment tied to prerequisite elements keep revenue-timing and financing risk with bidders.

 

RECPDCL's Bikaner V Part C amendment comes with a Part D RFP attached
8Amendment V extends submission by 14 days to 30 November and names the Part C SPV, but the cover and notification of the accompanying RFP identify Part D.
8Unreconciled package identity, no revision of bid or bond validity and a document-to-LoI window cut to three days keep compliance and document-control risk with bidders.

 

POWERGRID ties YEIDA GIS package award to winning the tariff bid first
8The SS206T package for a 400/220 kV GIS at YEIDA, an Aligarh extension and a 220 kV cable link closes on 23 November with 16-month completion and a Rs 235.13 crore turnover bar.
8Exclusive pre-bid association, an extra 10% equipment guarantee, indefinite NDA confidentiality and no relief if POWERGRID loses keep conditional-award risk with contractors.

 

POWERGRID's Talaricheruvu BESS tender leaves AP-BESS-12 out of its completion clause
8Three packages totalling 250 MW/1,000 MWh close on 18 November with 15-month completion and 12-year maintenance, with award depending on POWERGRID winning APPCC's 1,250 MW/5,000 MWh selection.
8A duplicated AP-BESS-11 entry, no degradation or augmentation terms and no stated EMD or PBG keep lifecycle and conditional-award risk with contractors.

 

POWERGRID lets substation contractors qualify for Andhra Pradesh battery storage packages
8The Talaricheruvu IFB accepts two 33 kV breaker bays, 50 MW of solar or wind, or 10 MWh of BESS as entry routes, with start-ups and MSEs meeting 80% of the financial bars.
812-year maintenance without usable-energy or replacement rules and no MoU terms on price validity keep performance and pricing risk with contractors.

 

POWERGRID gives BESS contractors seven days to bid and commit to exclusive association
8Document access for the three Talaricheruvu packages closes two days before the 18 November deadline, with one-day appeals, private openings and cancellation without liability.
8An NDA that hands improvements to POWERGRID, no reimbursement if the upstream bid fails and an undefined exclusivity period keep bid-cost risk with contractors.

 

CCL's Magadh coal-evacuation tender says no ePBG but demands 5% performance security
8The Rs 96.29 crore, two-year GeM package for 35,000 TPD of loading and short-haul transport closed on 9 November with a Rs 50 lakh EMD, 3% retention and ±30% volume variation.
Conflicting bid-splitting rules, no JV route below Rs 100 crore and no idle-time claims for lack of coal or unloading space keep utilisation risk with transporters.

Details
8A committee has recommended three transmission packages despite an expert’s warnings about demand, low non-solar loading and daily switching.
8The minutes reveal competing assessments of whether the network will be adequately used. Details
8The research institute sought government grant support. The transmission committee recommended a regulated-tariff mechanism instead, while recording an expert’s objection that testing facilities should not be treated as transmission assets. Details
8Adani’s 6 GW link needs neighbouring network models that have largely not been shared.
8The committee permits generic studies for now, requires later refinement and rules out extra time or cost compensation for the present non-availability. Details
8The utility says the existing system has no margin, yet 90 MW of access has been granted with identified strengthening.
8The committee has now sent that strengthening plan for comprehensive review. Details
8Revised documents for 150 MW of solar and 75 MW/300 MWh of storage remain before the regulator.
8The obstacle is the treatment of electricity the projects draw from the grid during auxiliary consumption, maintenance and shutdowns. Details
8The utility sought a standalone approval.
8The regulator recorded incomplete compliance with an earlier directive and required the proposal to return through the 2027–28 tariff petition. Details
8Bhadla-IV renewable connection: Battery operation is part of the transmission plan
8Small transmission schemes: What do Rs. 211.49 crore of awards disclose
8Punjab firm renewable project: What changes after the 250 MW procurement approval
8Tamil Nadu power procurement: Tendering proceeds before the next round of comments
8Damodar Valley Corporation tariff exercise: Tender completion leaves the next execution step open
8Tata Steel renewable-agency cases: A missed reporting timetable reaches its last opportunity Details
8Southern power scheduling: More below-threshold events, but what does the account measure
8Southern generating stations: Why do four below-threshold entries move against the wider decline
8Southern despatch settlement: Rs. 12.36 crore receivable, but where is the payment trail
8Minimum-turndown support: Why September’s zero-payment letter is not the whole pool account
8Day-ahead electricity market: The Rs. 10,000 hour behind a Rs. 3,563 daily average
8Power-system frequency: A near-50 Hz average hides almost seven hours outside the reported band Details
8Power generation outage register: What does the 5,987.51 MW total leave unexplained
8Rajahmundry and Essar generation: Fuel and power contracts remain the recorded barriers
8Western Region transmission equipment: Why do decade-old outage entries persist
8Champa and Dharamjaygarh substations: Fault-level control remains a multi-year outage reason
8Nagothane transmission interface: A burnt reactor and a new connection need separate scrutiny
8Nasik and Giral generation units: Likely scrapping is still only an outage remark Details
8Kandalgaon transmission award: What exactly did the Rs. 326.19 crore annual bid price
8Kandalgaon transmission schedule: Can the connection plan bridge a 184-day gap
8Kandalgaon transmission tender: Bidders challenged the basis for pricing the route
8Kandalgaon substation land: Why does the estimate use a quarter of the stated market rate
8Kandalgaon transmission route: Survey entries and environmental queries tell different stories
8Kandalgaon pumped-storage connection: Why were plant locations unavailable to bidders Details
 For reference purposes the website carries here the following tenders:
 8Tender for supply and retrofitment of valve surge arresters Details
 8Tender for supply of CT analyzer kit for various Details
 8Tender for repainting and related miscellaneous civil works at 400/220 kV GIS substation Details
 8Tender for supply of 33 kV, 300 sq. mm, 1C XLPE power cable various Details
 8Tender for supply of automatic third harmonic resistive current measurement kit for gapless surge arrestor for various Details
 8Tender for procurement, installation, commissioning and maintenance (AMC) of LED based solar operated street light Details
 8Tender for misc. maintenance of evacuation of ash and transportation from Ash disposal lines Details
 8Tender for installation and commissioning of paddle feeder and tripper panel Details
 8Design, engineering, supply, installation, testing and commissioning of 180 kWp solar PV project Details
 8Tender for construction of 30KL overhead tank with pump room Details
 8Tender for coal handling plant Part-B Package-2 Details
 8Tender for COH OF IP, LP (including NFT and MPI), turbo generator and auxiliaries Details
 8Tender for crane operators and slingers for material handling works Details
 8Tender for Package A i.e. ETC of boiler and PCP PIPING and package Details
 8Tender for SCADA integration of newly commissioned 220kV line Details
 8Tender for laying of LHS and power cable for FDA system Details
 8Tender for supply of 2000AH battery bank with stand Details
 8Tender for supply of caustic soda pure Details
 8Tender for supply of ESP roof aluminum corrugated sheet Details
 8Design, engineering, supply, erection, testing, commissioning of 20 KWp rooftop solar PV power project Details
 8Tender for replacement of cement sheet with C.G.I sheet from structure Details
 8Tender for supply of turbidity analyser for PT plant installed Details
 8Tender for work of supply, installation, complete overhauling and testing of 60 tones DT gate crane Details
 8Tender for general civil works Details
 8Tender for drilling of new boreholes and making arrangements for rock mechanics investigations, including Details
 8Tender for major maintenance of generating Unit no power house Details
 8Tender for supply of new cartridge assembly without mechanical seal Details
 8Design, manufacture, testing, supply and delivery of earthing sticks sets complete with accessories suitable for use at 400 kV/220kV/132 kV sub-stations/transmission line Details
 8Tender for estimate for providing 30 No. DTR fencing Details
 8Tender for capacity enhancement by installation of 16MVA, 110/33kV transformer Details
 8Tender for purchase of thermal imaging camera for 220 kV substation Details
 8Tender for RMU CCC 1 No 3 load break switches RMU CTC 2 Nos 2 load break switches and one circuit breaker Details
 8Tender for empanelment of agencies for new 33/11 kV substation, additional augmentation of PTR at existing 33/11 kV S s, HT lines, LT lines Details
 8Tender for work contract for in- situ refurbishment work of bowl hub grooved portion of coal mills Details
 8Tender for procurement of spares of dust suppression actuator Details
 8Tender for work contract for complete refurbishment of damaged/worn out inlet support rollers of stock make (model- EG3651) gravimetric raw coal feeder installed Details
 8Tender for procurement of spares for 18 TR,24 TR and 11TR package AC installed Details
 8Tender for work contract for complete filter media replacement and minor repair work Details
 8Tender for hiring 01 No mobile crane of 150MT capacity for loading, unloading and placement of power transformers upto 31.5MVA for carrying out various Details
 8Tender for work for PCC and metal laying / spreading in 220kV transformer (ICT) bays Details
 8Tender for work for painting of switchyard equipment, metal fencing, gate, door etc. at 132/33kV GSS Details
 8Tender for work for providing tower protection of 220kV D/C transmission line Details
 8Tender for procurement of relays / electrical items and material at 132/33kV GSS Details
 8Tender for work for angle with stub welding in rusted tower legs, dismantling and re-construction of damage portion foundation plinth, construction of chemical earthing required Details
 8Tender for supply of materials under electric supply Details
 8Tender for epoxy painting of draft tube (DT) gates, TRT gates, TRT gantry and DT gantry, along Details
 8Tender for supply, installation, testing and commissioning of 02 No emergency flood pumps for collection gallery including all accessories Details
 8Tender for supply, installation and commissioning (SITC) of starter panels of spillway and under sluice with wiring MCBS along Details
 8Tender for supply, installation, testing and commissioning of overhead gantry crane Details
 8Tender for balance work, replacement of damaged GI roofing of power house Details
 8Tender for replacement of existing sindh gate Details
 8Tender for upgradation of fire fighting system which includes detection system and fire panels/ control panels Details
 8Tender for replacement of 16 Nos ESP field internals overhauling of the remaining 8 Nos ESP field internals and conducting gas distribution test Details
 8Tender for supply and erection of structural steel lift room including installation of new lift Details
 8Tender for turnkey execution of design, supply, installation, testing & commissioning of RTCC panels of transformers Details
 8Tender for supply, installation & commissioning of new motor operated roof extractor fan Details
 8Tender for supply of various lifting & shifting equipments Details
 8Tender for work of overhauling of air-preheater Details
 8Tender for work of radiography testing of various weld joints during Details
 8Tender for providing and fixing galvalume sheet over compound wall including rising of concertina fencing Details
 8Tender for providing and supplying of towers and monopole towers, stub setting, concreting, tower erection, stringing of ACSR panther conductor Details
 8Tender for construction of outdoor control room electrification, plumbing works Details
 8Tender for providing and supplying of towers and monopole towers, stub setting, concreting, tower erection, stringing of ACSR panther conductor for erection of 110kV DC line Details
 8Tender for supply of tower parts, bolts & nuts, ACSR panther conductor Details
 8Tender for supply of tower stub setting concreting tower erection stringing of ACSR panther conductor, 120KN & 90KN disc insulator Details
 8Tender for fabrication, manufacture, supply (except power transformer and breakers), erection, testing and commissioning of 33 kV /11 kV substation Details
 8Tender for providing RCC fencing and allied civil works for the establishment of 110/33 kV SS Details
 8Tender for providing 110/33/11 kV yard equipment, plinth, cable trench Details
 8Tender for supply of tower parts, bolts & nuts, line materials Details
 8Tender for construction of 33/11kV yard equipment Plinths, cable duct, filling Details
 8Tender for stub setting, foundation concreting, supply of tower, line materials, tower erection, stringing of ACSR panther conductor Details
 8Tender for earthwork excavation, stub setting, concreting, erection, and stringing of panther conductor and earth wire Details
 8Tender for providing new additional concrete supporting pedestals including stringer supports in conveyor Details
 8Tender for overhauling of dual line grease lubrication system centralized lubrication power pack Details
 8Tender for supply, erection, testing and commissioning of 110 kV DC line on DC towers Details
 8Tender for construction of RCC and revetment wall for protection line Details
 8Tender for construction of protection wall for tower Details
 8Tender for supply of 11kV polymer disc insulator B and S type Details
 8Tender for supply of 11kV polymer pin insulator with pin Details
 8Tender for annual rate contract for major chute maintenance work Details
 8Tender for purchase of 300 sq.mm 6.6 kV aluminium power cable Details
 8Tender for supply, delivery, installation and commissioning of 160 KVA silent DG set Details
 8Tender for civil works for reconstruction of collapsed/ tilted compound wall by RCC frame Details
 8Tender for work contract for lifting / shifting of MDBFP and CW pump HT motor Details
 8Tender for work of modification in suction screen/trash rack of MVP at PS-4 & 5 of SBC pumping Details
 8Tender for BRC for work of rewinding and overhauling of 11kV HT motors of MV/NVT pumps Details
 8Tender for work of attending coil (tube) punctured in HP heaters Details
 8Tender for fabrication work of weather protective shed/canopy on ESP rectifier transformer Details
 8Tender for work of erection & testing of pipe line Details
 8Tender for repairing & renovation of boiler lifts Details
 8Tender for AMC/ CAMC of solar energy power plant Details
 8Tender for work for replacement of M. S.ERW pipe and other miscellaneous job work Details
 8Tender for supply and erection of earthing pit Details
 8Tender for work of testing, examination and certification of various lifting tools Details
 8Tender for supply, erection & commissioning of H2 leak detection system and fire detectors at various Details
 8Tender for supply of various capacity IE 3 type energy efficient 3-phase 415V LT motors Details
 8Tender for supply of coal compartment assemblies for boiler Details
 8Tender for work of complete overhauling of MS & HRH strainers, HP & IP stop and control valves, TG bearings Details
 8Tender for replacement and providing roof sheets at various Details
 8Tender for repair and maintenance of misc. civil structure Details
 8Tender for supply of various types/size of welding electrodes to all power stations Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8India’s coal production likely to hit record 1,090 million tonnes in 2026: World Bank Details
 
8Reliance plans $4.6 billion coal gasification project in Andhra Pradesh Details
 
8Orient Green Power clocks Rs 106 Crore H1 FY27 Net Profit with an industry-leading 76% EBITDA margin Details
 
8Refex Industries' Ash And Coal Handling Order Book Rises To Rs 1,721 crore Details
 
8Oyster Renewable Commissions 39.3 MWp Solar Project Details
 
8India Identifies 5-8 GW Wind Capacity For Repowering, Eyes 50 percent Generation Boost Details
 
8India's Renewable Investment Hits $32 Bn As Small-Scale Solar Additions Reach 16.9 GW: BNEF Details
 
8Haryana Expands Solar Subsidy Limit to 30 kW for Shrimp Farmers Details
 
8Renewables save India Rs 9.4 lakh crore in coal, gas imports: IEA Details
 
8From AI to solar power: PM Modi outlines vision to transform Indian agriculture Details
 
8Oswal Pumps Reports Q2 Consolidated Net Profit of Rs 39.6 Crore vs Rs 97.5 Crore YoY Details
 
8India Solar Capacity Rises 21% YoY in 9M 2026 Details
 
8Bengaluru Tech Park Installs 200 kW Rooftop Solar System Details
 
8Green Stocks Update: Tata Power, Oswal Pumps and INA Solar Details
 
8India Renewable Investment Hits $32 Billion Details
 
8EPC Project Management Office Standards for Solar & Wind Details
 
85 Power Stocks to Watch After India's Rs 68,800 Crore Transmission Push Details
 
8Sambhv Steel Tubes Secures Andhra Paper Power Generation’s Approval for MS and ERW Pipe Supply Details
 
8CAG initiates first nationwide audit of 39 discoms, 5 power departments Details
 
8India’s Solar Capacity Crosses 174.5 GW As October Additions Reach 3.5 GW In 2026 Details
 
8Hitachi Energy India Reports Q2 EBITDA Growth Amid Margin Compression Details
 
8CEA And Danish Energy Agency Release Technology Catalogue To Advance India’s Energy Storage Sector Details
 
8CAG begins nationwide audit of discoms to help frame power sector policies Details
 
8Why grid-level storage is crucial for self-reliance in electricity Details
 
8Tata Power Misses H1 RE Targets, Aims 2.5 GW by FY27 Details
 
8Solar PV and Battery Storage Integration in India Details
 
8Rajasthan CM directs Energy Dept to operate in mission mode for power generation and supply Details
 
You can also click on Newsclips for more Details
PTCUL's Rs 55.30 crore HTLS reconductoring L1 sits against a Rs 102.16 crore award record
8JSK Industries beat Sterlite by 3.0% and APAR by 4.3% for five 132 kV line sections in Package-3, which carries a Rs 77.76 lakh EMD, 24-month completion, a 10% PG and a five-year warranty.
8An 84.7% gap between the price comparison and the award summary, sag wording still at 800 A against a 1,000 A requirement, no idling compensation and no guaranteed shutdowns keep execution and outage risk with the contractor.

 

PSPCL splits Rs 205.06 crore biomass pellet order for Lehra Mohabbat among 13 suppliers
8The reverse auction for 2.92 lakh MT a year at GHTP cut the opening best price by 0.9% to Rs 2.1896 per 1,000 kCal, with R.A.B. & Company taking 19.8% of the award value.
8An undisclosed allocation basis, a firm-price rule against variable-price wording, conflicting moisture-deduction methods and zero payment below 2,000 kCal keep quality and margin risk with suppliers.

 

BSPGCL cuts Kajra BESS commissioning to 12 months and opens bidding to foreign developers
8The amendments to the 125 MW/500 MWh BOOT tender halve financial closure to six months, cut the success charge to Rs 3 crore and allow bank guarantees for the Rs 25 crore PSD, against a Rs 13 crore EMD and Rs 32 crore PBG.
8A renewable-charging damages formula mixing kWh and Rs/MWh, a zero-shading rule, an 85% green-charging test and 30-day PSD top-ups keep charging-cost and compliance risk with developers.

 

RVUN extends Suratgarh supercritical O&M bids for the tenth time, to 1 December
8Corrigendum X pushes the Rs 180 crore, three-year contract 162 days past the original deadline, keeping the Rs 3.60 crore EMD, 1,108-person staffing and 5% performance guarantee unchanged.
8Guarantees of 85% availability and a 2,145.68 kcal/kWh heat rate against actuals of 80.52% and 2,464.92, a self-contradictory transition-KPI note, a sign error in the APC formula and 10% withheld monthly keep performance and liquidity risk with operators.

 

BHEL switches to a one-way indemnity in Mahi Banswara nuclear air-handling tie-up
8Revised MoU terms for the 4×700 MWe ASHVINI package replace mutual indemnity and change "to award" to "may issue" an order, alongside a Rs 3 crore EMD and a deadline pushed 47 days to 19 November.
8Unresolved seismic conflicts, bearing and belt choices left to detailed engineering, FOR-despatch versus site-delivery wording and payment tied to ASHVINI's receipt certificate keep pre-award and cash-flow risk with suppliers.

 

RECPDCL pushes Bikaner V Part A bids to 20 November without fixing its STATCOM rating
8Amendment VII names the SPV and moves all milestones 35 days past the original RFP dates for the 36-month package, which carries a Rs 73.72 crore bid bond and a Rs 184.30 crore CPG.
8No stated reason for the extension, a "2x+300" versus "2x±300 MVAr" mismatch, a document-to-LoI window cut to three days and payment tied to prerequisite elements keep interface and revenue-timing risk with bidders.

Details
8Round 3 sets application rules and a deadline of 11 January, but identifies no selected projects, locations or awardees. Details
8The letter of intent states annual transmission charges; the company separately reports Rs. 8,106.97 crore as the cumulative total for 11 projects. Details
8The award notice names two Kalyanpur units and a 35-month execution period, but does not allocate the disclosed value across equipment and work phases. Details
8The September-quarter filing reports Rs. 1,652.04 crore net profit after tax and Rs. 19,964.30 crore consolidated total income. Details
8Separate orders cover June and September bills, with the same additional percentages allowed for one month from each order date. Details
8The amendment sets a route to withdraw an entire connectivity quantum, bars partial withdrawal and gives the nodal agency 15 days to process a request. Details
8Power-plant coal imports fall 6.39% as blending volumes drop 35.23%
8Captive and commercial coal dispatch rises 36% in October as Lohari receives mine-opening permission
8Pumped-storage status report lists 347 GW potential but 7.43 GW operating
8Central Electricity Authority report puts operating large-hydro capacity at 44.89 GW
8Jammu and Kashmir profile lists 3.55 GW of hydro capacity under construction Details
8West Bengal challenges ancillary-charge calculations against plant-level figures
8West Bengal agenda records real-time-market resale concern, not a breach finding
8Pusauli schedule dispute pits Power Grid’s portal-reset claim against ERLDC’s entitlement explanation
8Eastern Region agenda records Stage I partial-outage claim after turbine stress
8Talcher Kaniha’s planned bus shutdown raises a declared-capability protection issue
8Kanti-II and Barh-II ramp reversals leave schedule and equipment concerns unresolved
8National Thermal Power Corporation links schedule-update failures to reported settlement losses
8Barh Stage II seeks minimum-load support after Rs. 7.5 lakh in deviation-settlement charges
8Barh Stage I seeks return to ancillary services after September exclusion
8Patratu Unit 1 challenges deviation-settlement reference rates after two outage cases Details
8Tata Power reports Singapore attachment notices over subsidiary shares, with no completed sale reported
8CARE places SJVN Thermal’s Rs. 8,520.92 crore facilities on positive watch pending merger approvals
8CARE withdraws four Athena Solar ratings after downgrade and reported debt top-up
8Orient Green Power’s release leaves two first-half net-profit references unreconciled
8ICRA upgrades Cleantech Green Energy’s Rs. 6.23 crore term-loan rating on parent support Details
8Haryana orders force distributors to disclose 11 kV furnace-surcharge records
8Tripura commission rejects Rs. 6.15 tariff review despite Rs. 467.60 lakh impact claim
8Tripura commission sends tariff dispute to consultation without calculating the contested rate
8Balsane transmission filing assigns 73:27 charge split without a licence grant Details
POWERGRID dates Mandola water-tank bids before the tender was issued
8The Rs 22 lakh (ex-GST) civil and pumping package runs on a single-stage, two-envelope process with no reverse auction, a Rs 0.44 lakh bid security, a 10% performance guarantee and eight-month completion.
8A 3 November deadline against a 4 November issue date, a pre-bid meeting after opening, conflicting Integrity Pact rules and unrelated watch-tower sheets hidden in the price workbook keep bid-validity and margin risk with contractors.

 

Gujarat's draft BESS policy makes storage mandatory for new renewables but shares merchant gains with DISCOMs
8The 30 October draft, valid to December 2031, mandates storage of 25% of AC capacity for solar and hybrid projects and 10% for wind, with minimum duration rising from two to four hours for projects commissioned after 30 June 2029.
8Lifetime capacity compliance, limits on discharging during solar hours, unpriced Grid Security Charges and an undefined 50:50 net-gain formula keep utilisation and revenue risk with developers.

 

RECPDCL drops solid-state AVR mandate but tightens STATCOM study rules in Bikaner-V Part A
8Amendment VI adds a solar-peak study case and moves CTU network files and OEM models to PSSE version 36 for the 36-month package, which carries a Rs 73.72 crore bid bond and a Rs 184.30 crore performance guarantee.
8An undefined "very high" voltage trigger, no assumptions for the solar-peak case, a retained typical-data fallback and no revised bid calendar keep modelling and OEM-interface risk with bidders.

 

RECPDCL's revised Bikaner V Part B SPA leaves bidders defending pre-closing claims without a cap
8The agreement names the SPV and transfers 50,000 shares at par, subject to a closing-date audit adjustment, alongside a Rs 166 crore performance guarantee and 36-month simultaneous commissioning of the Panipat and Mohali GIS substations.
8An indemnity that survives termination sits beside one-year warranties, and with a wrong Clause 6.3 cross-reference and no procedure for the price adjustment, it keeps legacy and closing-account risk with the buyer.

 

OPTCL ties Therubali–Gopalpur forest-clearance consultancy to final approval
8The Rs 1.63 crore reverse-auction contract closed on 28 October with a Rs 1.63 lakh EMD, an Odisha Stage-I and Stage-II experience bar, a 10% PBG and an 18-month guarantee running after Stage-II clearance.
8Undefined route and diversion area, no relief for delays caused by authorities, payment milestones split between price-schedule items 1.1 and 3.1, and lump-sum versus rate-contract wording keep approval and cash-flow risk with consultants.

 

RECPDCL pushes Bikaner V Part D bids to 17 November but trims the post-auction document window
8Amendment IV shifts every milestone by seven days, putting the reverse auction on 27 November, the LoI on 7 December and SPV transfer on 17 December.
8The package carries a Rs 61 crore bid bond and a Rs 152.50 crore guarantee for the Lucknow-II and Asana corridors.
8A six-day move for the hard-copy deadline, no stated reason for the extension, survey disclaimers and payment tied to a critical-element list CEA has yet to issue keep interface and carrying-cost risk with bidders.

 

PFCCL's Rs 639 crore guarantee anchors Madhya Pradesh thermal evacuation TBCB with no land-delay relief
8The 48-element, eight-substation BOOT scheme for 4,000 MW closes on 5 January 2027 with a Rs 93.85 crore bid bond and Rs 4,692.50 crore experience bar, and staggered CODs in January 2030 and January 2031.
8Conflicting financial-opening dates, contradictory bay O&M wording, a missing CEA critical-element list and a 1,400/1,440 A mismatch at Waraseoni keep revenue-timing and interface-cost risk with developers.

 

JKPTCL fixes 99% tariff split in Rajouri–Akhnoor package but keeps payment locked to full commissioning
8Amendment No. 03 names the SPV, lifts the two substations' combined share to 37% from 34% and cuts the Siot–Akhnoor-II line to 36%, against a Rs 4.03 crore bid bond, a Rs 10.07 crore CPG and 30-month completion.
8"Progressive" versus "simultaneous" commissioning, a bond amount that clashes with its own 2% formula, six Siot bays for two double-circuit lines and a malformed issue date keep financing-carry risk with bidders.

 

JKPTCL amendment pushes Wahipora–Baghthali tariff split to 101%
8Amendment No. 03 names the SPV, raises the Kishen Ganga–Wagoora LILO to 11% and trims the Jatwal–Baghthali line to 33% in a 24-month package with a Rs 3.56 crore bid bond and a Rs 8.90 crore CPG.
8No instruction to normalise the total, a bond that clashes with its own formula, GIS versus AIS wording at Baghthali and mismatched schedule start dates keep recovery and equipment-pricing risk with bidders.

 

PFCCL opens Babai 765 kV TBCB to AIFs but leaves the capital threshold blank
8Amendment No. 1 lets SEBI Category I and II infrastructure funds qualify on available capital for investment, certified within a month of the deadline and maintained until financial closure, with financial support required until COD. The project carries a Rs 24.64 crore bid bond and a Rs 61.60 crore CPG.
8Blank "Rs ____ crore" thresholds, a ">26%" illustration against an "at least 26%" definition, fund-tenure tests tied to actual COD and no revised calendar keep eligibility and financing risk with fund-backed bidders.

Details
8Applications close on January 11; incentive scoring weighs the amount sought, capacity, project cost, technology tie-up and applicant finances. Details
8The revised fuel cost includes royalty, cess and excise duty; any resulting under- or over-recovery is to be settled in six monthly instalments. Details
8The capex letter of credit sits within the term-loan limit; any transfer of the licence to a lender nominee still needs separate prior approval. Details
8The order ties the extension to a 500 MW/2,000 MWh battery project, floating-solar feasibility work and a signed memorandum within one month. Details
8The company also indicated Rs. 25,000–30,000 crore of capitalisation and reported 981 circuit kilometres of transmission lines commissioned in Q2. Details
8The alliance also says its island-state platform has a USD 500 million project pipeline, including a proposed 220 MW Mauritius project. Details
8ACME Dhaulpur solar project posts 30.3% trailing plant load factor
8Malwa Power biomass plant faces tariff dispute and operating pressure
8India’s pumped-storage pipeline nears 100 GW, with 7.17 GW operating
8India’s electrolyser awards total nearly 1.5 GW of annual capacity Details
8Fujiyama Power Systems Limited reports Ratlam expansion milestones and Q2 growth
8Bharat Heavy Electricals Limited reports dropped GST demand
8Adani Power Limited says ICRA upgraded long-term ratings to AA+
8Fourth Partner Solar Power rating rises as long-term contracts cover 97.6%
8Premier Energies reports IPO proceeds fully utilised
8Websol Energy System targets 750 MW TOPCon line by financial year-end Details
8Odisha Power Generation Corporation seeks bids for Stage III ash corridor surveys
8Andhra Pradesh Power Development Company invites coal reclaim bids
8Telangana transmission utility tenders 61 33 kV vacuum circuit breakers
8Telangana utility sets December deadline for 53 current transformers Details
8Central Electricity Regulatory Commission backs Beawar Rs. 387.37 crore security
8Kerala commission approves Rs. 4,799.39 lakh Thrissur capital plan
8Punjab utility sets over-80% loading trigger for two-group farm supply planning
8Tamil Nadu Ombudsman orders retrospective industrial tariff for crusher
8Tamil Nadu regulator condones 690-day delay in system operator filing
8National Load Despatch Centre records 197,627 MW peak demand met Details
8Committee recommends 2,800 MW coal linkage for Madhya Pradesh
8Rajasthan utility receives one-year tapering coal bridge linkage
8Kerala retains 500 MW coal linkage under older SHAKTI route
8Committee recommends 1,600 MW coal linkage transfer for Telangana Details
MSETCL bundles breakdown and planned upkeep of Nashik 220/132 kV lines on an as-required basis
8The Rs 100 lakh annual contract closes on 15 November with a Rs 1 lakh EMD, a two-bid SRM process and entry restricted to registered MSETCL contractors.
8Undefined line inventory, response times and standby pay, a 2025-26 reference against 2026 dates and an "if possible" opening keep readiness and margin risk with bidders.

 

OPGC seeks Patnagarh hostel design in three months but leaves the support tail unpriced
8The Rs 9.98 lakh limited tender closed on 9 November with no EMD or ePBG, but deducts 10% from running bills and ties 75% of fees to milestones up to institute vetting.
8An "Enterprise Architect" profile, an undefined POC, a stray NIOT reference, unscheduled construction visits and an LD clause without a time interval keep scope and payment risk with consultants.

 

PVUNL halves performance security on Patratu boiler PAUT but guarantees no minimum work
8The 5,000-joint package for Unit 3's 800 MW boiler, opening on 10 November, cuts security to 5% from the template's 10%, drops EMD and runs for three months at firm prices.
8Uncompensated idle time, dependence on BHEL repair cycles, a one-day clarification window against a three-day rule and conflicting power-supply clauses keep utilisation and cost risk with the agency.

 

AEGCL cuts GIS guarantee to 5% and opens price variation in Rs 455.90 crore Sarusajai conversion
8Three extensions add 38 days to the 24-month AIS-to-GIS package, which now offers a 10% mobilisation advance, 90% supply payment and IEEMA variation capped at 10%.
8Uncapped downward variation, no upward adjustment past the original completion date, unreconciled 20% SCC clauses and inconsistent transformer counts keep live-station and cost risk with contractors.

 

NVVN hands Andaman LNG project consultancy to NTPC through a single tender
8The 30-month GeM award for the 57.105 MW plant spans design, revised EC and CRZ, inspection, commissioning, CERC tariff and GSA support, with no EMD or ePBG.
8Best-endeavour liability on NTPC's civil designs, no regular site staffing, open-ended travel and repeat-work charges and disputes routed to NTPC's CMD keep execution and fuel risk with NVVN.

 

MSETCL voids live bids on any corrigendum in Lonikand 400 kV patrolling tender
8The Rs 8.42 lakh first-call contract closed on 9 November with a Rs 8,422 EMD, a JV ban, and technical and commercial openings set for 12 November "if possible".
8Undefined route length, patrol frequency and duration, unrestricted cancellation rights and mandatory re-bidding after any amendment keep pricing and participation risk with agencies.

 

MPPGCL eases low-bid security and adds wage pass-through in Rs 89.01 crore Birsinghpur CHP contract
8Three extensions moved bids to 5 November for the 730-day, 710-person O&M and unloading package, with abnormal-low-bid security now based on the shortfall below 80% of the estimate.
8An as-is handover, unloading volumes that can be cut by 100%, a binding 12-month extension at year-two rates and generation-loss recoveries keep volume and margin risk with contractors.

 

GUVNL ties Phase XII wind greenshoe to L1 and keeps CTU charge risk outside change-in-law
8The 250 MW RfS, with up to 250 MW more, closes on 30 November and requires Rs 13 lakh/MW EMD, Rs 32 lakh/MW PBG, Rs 1.27 crore/MW net worth, 25% minimum CUF and 24-month supply.
8An L1-plus-2% award band, Rs 1,000/day/MW financing extensions that don't move SCSD, and conflicting CSD, SCSD and SCOD milestones keep connectivity, cash and exit risk with developers.

Details
8Certificate issuance remains subject to verification of eligibility and supporting documents. Details
8The regulator has reserved orders in separate petitions from both BSES distributors. Details
8The approved price is Rs. 4.55 per unit plus a seven-paise trading margin. Details
8The revised design separates installed renewable and storage capacity from simultaneous power transfers. Details
8A proposed corridor would move about 20 GW through one double-circuit route. Details
8Mandsaur licence amendment covers 800 MW renewable connections
8Power Grid appoints Anupam Kumar as government nominee
8Telangana transmission utility invites hotline-equipment bids
8Telangana reservoir statement shows lower stored hydro energy Details
8Exchange snapshots show lower prices as sell bids rise
8Chhabra report records partial precipitator-condition compliance
8Parsa East and Kanta Basan washery reports coal quality
8Coal Ministry schedules second-round gasification application opening Details
8Delhi generators pursue late-payment surcharge dispute
8Tehkhand tax-compensation case moves to January hearing
8Bihar regulator declines urgent railway open-access hearing Details
8Andhra capital-region diversion awaits maintenance responsibility agreement
8Hyderabad substation automation work seeks December outages
8Kurnool–Nellore diversion seeks 40-day transmission shutdown
8Nagarjuna Sagar–Kadapa diversion seeks December circuit outage
8Power Grid proposes Rs. 263.96 crore equipment replacement Details
8Eastern grid minutes record September frequency low of 49.413 Hz
8Talcher bus shutdown awaits islanding and restoration studies
8Kolkata supply corridor returns to regional reliability review
8Damodar Valley links receive conditional regional backing
8Joda industrial feeder faces repeated manual disconnections
8Malda–Gajol reinforcement schedule extends beyond requested winter window
8Nabinagar unit overhaul moves to November 30
8Kanti uprating awaits approvals and trial certification Details
 For reference purposes the website carries here the following tenders:
 
8Tender for FDPS R and M Package Details
 
8Tender for civil fabrication works for structural strengthening to install additional EOT crane Details
 
8Tender for attending roof leakage special repair work Details
 
8Tender for supply of primary injection kit along with its accessories Details
 
8Tender for supply, installation, testing, commissioning of 75 nos. 12W LED solar based street lights along Details
 
8Tender for construction of yard structure and Equipment Foundation, earthmat, yard metalling, cable trench and laying for 33kV substation Details
 
8Tender for constructing of 1700M UG cable Details
 
8Tender for construction of power and control cable trench Details
 
8Tender for insertion of 1 number narrow based type tension tower Details
 
8Tender for replacement of existing sindh gate Details
 
8Tender for repair/stabilization of slopes from CR adit of HRT to bailey bridge Details
 
8Tender for work of replacing the damaged LT AB cable Details
 
8Tender for work of replacing the damaged LT AB cable to laying a new LT AB cable of 33/11 kV S/S Details
 
8Tender for procurement of grinding roll & bull ring segment Details
 
8Tender for procurement pressure transmitter for lubrication oil system Details
 
8Tender for replacement of sill beams of the log gates and main gates Details
 
8Tender for cleaning of deposited materials from the sump pit and open channel Details
 
8Tender for downhill river side protection work of underground desilting chamber Details
 
8Tender for work of dismantling of existing 132KV & 220KV various equipments deteriorated RCC structures and erection of GI structures at 220kV S/stn Details
 
8Tender for balance scope against the work of augmentation of substation by providing additional 50MVA 1X50MVA 132/33kV power transformer along Details
 
8Tender for work of supply, civil and ETC of replacement of 220kV & 132kV CTs and PTs without tan delta point and 33kV CTs at various EHV S/stn Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8
Coal gasification scheme: Second-round applications to open on November 10 Details
 
8Central PSUs pledge Rs 2 trn investment in UP's thermal, clean energy sectors Details
 
8Waaree Energies to invest 15,000 crore in green ammonia project in Andhra Details
 
8Uttar Pradesh, Maharashtra, Gujarat shine as residential rooftop solar nears 20 GW Details
 
8Grid storage, critical mineral push to boost India's energy self-reliance Details
 
8India Power Corporation Ltd Locks at Upper Circuit With 4.7% Gain Amid Rising Delivery Volumes Details
 
8Meet 3 specialist companies behind India’s Rs 20-lakh- crore nuclear power push Details
 
8India’s Wind Energy Sector Moves Towards First Recyclable Turbine Blades With Grasim-Suzlon Partnership Details
 
8GUVNL Invites Bids for Wind Power Projects Phase XII Details
 
8India’s Emissions Rise Shows Clean Energy Shift Is Still Too Slow Details
 
8Price of Carbon: How the steel sector can turn CBAM into a green hydrogen advantage Details
 
8Odisha Approves 750 MW Hybrid Renewable Power Procurement Details
 
8Evacuation Constraints: Timely transmission development key to efficient renewable integration Details
 
8Bridging the Skills Gap: Strengthening the workforce through training and industry participation Details
 
8Constellation Energy stock's post-earnings rally is an opportunity to sell Details
 
8Tamil Nadu floats tender to procure 3500 MW thermal power for summer 2027 demand Details
 
8Meet 3 specialist companies behind India’s Rs 20-lakh- crore nuclear power push Details
 
8India Emissions Break Rapid Growth as Clean Power Displaces Coal Details
 
8India’s Energy Storage Scheme Targets $10 Billion Investment Details
 
8Aligning Price Signals: Integrating regulated, competitive and market-based electricity at the despatch level Details
 
You can also click on Newsclips for more Details
8The November reports identify low plant-level cover without establishing an electricity shortage.
Click on Details for more.
Details
8Avaada Inclean upgraded after Bhachau transformer replacement
8ADM Solar targets April module and cell manufacturing expansion
8HBL Engineering industrial-battery sales rise despite wider revenue decline
8Power Grid raises half-year capex to Rs. 16,864 crore
8Coal report identifies 86 plants with critical fuel stocks
8India meets 195,673-megawatt demand peak in latest grid report Details
8Power Mech subsidiary signs Rabigh expansion erection contract
8RMC Switchgears receives Madhya Pradesh distribution-box award
8Fujiyama commissions two-gigawatt Ratlam power-electronics factory
8Schneider Electric Infrastructure orders rise as quarterly profit falls
8Kirloskar Electric returns to quarterly profit as orders grow
8Quality Power starts Sangli coil and Turkish conversion factories Details
 1 2 3 > 

Showing 1–50 of 109 items