8The package has moved into technical evaluation with only a pair of bidders in contention. 8Despite a relatively short alignment, design and execution stakes remain high. 8The outcome will depend on how risk is priced against limited competition.Details
8Design shift resets cost dynamics in 400 kV transmission package A late amendment recalibrates key engineering assumptions in a southern grid package. Tower loading margins are relaxed while select safety checks get tighter. 8Cost relief meets tighter reliability filters in 400 kV transmission package A late-stage amendment is recalibrating cost assumptions in a key southern grid project. Select design constraints have been eased, but reliability-linked clauses have been sharpened. The real test will emerge when aggressive pricing intersects with execution risk. 8Rs 150 crore threshold reshapes pre-bid strategy in 765 kV package A high-value entry gate is redefining how bidders approach a major transmission tender. The pre-bid tie-up model introduces new layers of exclusivity and risk-sharing. The real screening lies beneath the headline qualification. 8Third extension stretches bidding window in large thermal EPC civil package The deadline for a Stage-II main power block package has been pushed again without any change in scope or commercials. While the longer window may widen participation, contractor risk exposure remains unchanged. 8Retender resets ash handling EPC bid after multiple deadline extensions Repeated timeline pushes have led to a full reset of a thermal ash handling package. Notably, all technical and commercial conditions remain unchanged. The next round will show whether the earlier gap was in participation, pricing, or compliance.Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days. Get the daily updates for : 8LNG 8Crude 8Chemicals 8Fertilizers 8LPG 8Ammonia 8Coal & Coke 8All tankers 8Bulk and Dry cargo Click on Reports for more.Details
8WRPC issues DSM settlement statement for April 13–19, 2026 week to Western regional power utilities The Western Regional Power Committee (WRPC) issued the Deviation Settlement Mechanism (DSM) settlement statement for the week from April 13 to April 19, 2026, vide No. WRPC/Comml.-I/4/ABTDSM/2026/4.3 dated April 28, 2026. The document was circulated to key utilities including GUVNL, MSETCL, MSEDCL, MP Power Management Company, Chhattisgarh State Power, NTPC, PGCIL, and electricity departments of Goa, Daman, and Silvassa, in accordance with the Central Electricity Regulatory Commission's (CERC) DSM framework.
8NERPC releases May 2026 regional transmission account: Assam tops NER zone at Rs. 64.92 crore, Tripura billed Rs. 10.81 crore The North Eastern Regional Power Committee (NERPC) released the Regional Transmission Account for billing month May 2026 (dated April 29, 2026), detailing AC system usage charges, national component, bilateral and total transmission charges for NER zone states. Assam (GNA: 1,767 MW) topped the zone with total transmission charges of Rs. 64,92,16,000, followed by Tripura (GNA: 311 MW) at Rs. 10,80,71,790 and Meghalaya (GNA: 290 MW) at Rs. 12,08,57,907. Arunachal Pradesh's total stood at Rs. 7,98,86,142 with a GNA of 208 MW.
8NLDC releases revised SCED statement for September 2025: Kahalgaon STPP-II earns Rs. 6.94 crore, BRBCL refunded Rs. 1.33 crore The National Load Despatch Centre (NLDC) published Revision-1 of the National SCED Monthly Statement for September 2025 (dated April 24, 2026). Kahalgaon STPP-II (Eastern Region) recorded the highest net payable of Rs. 6,93,99,915, while Farakka STPP-I&II followed at Rs. 3,21,60,835 and Kahalgaon STPP-I at Rs. 2,52,04,484. BRBCL received a refund of Rs. 1,33,02,183 from the national SCED pool. The statement covers increments and decrements for each SCED generator by volume (MWHr) and variable cost charges.Details
8BSPHCL issues promotion orders for general cadre engineers under 2010 and 2012 BSEB resolutions Bihar State Power (Holding) Company Limited has issued a notification dated April 29, 2026, promoting General Cadre Engineers pursuant to erstwhile Bihar State Electricity Board (BSEB) Resolution No. 134 dated 20.08.2010, as read with Resolution No. 76 dated 07.05.2012. This promotion order, referenced under H-V/ACP-90104/2025, reflects the company's ongoing compliance with cadre management regulations under CIN: U40102BR2012SGC018495.Details
8PSPCL Amritsar promotes Rajinder Singh (Emp ID: 339001) from ALM to officiating LM under office order no. 45 dated April 29, 2026 Punjab State Power Corporation Limited's DS Circle City, Amritsar, has issued Office Order No. 45 dated April 29, 2026, promoting Rajinder Singh (Employee ID: 339001, DOB: March 21, 1983) from the post of ALM in Sub-Division (BC) Technical, Durgaiana Temple, Amritsar to Officiating Lineman (LM) at Sub-Division Technical, Durgaiana Temple, under DS Division, Hakima Gate, Amritsar. The promotion is against a vacant post, effective immediately.
8PSPCL Gurdaspur promotes 3 ALMs to officiating LM posts in DS sub-divisions under office order no. 45 dated April 29, 2026 Punjab State Power Corporation Limited's DS Circle, Gurdaspur, has issued Office Order No. 45 dated April 29, 2026, promoting three Assistant Linemen (ALMs) - Jatinderbir Singh (ID: 339273, DOB: Feb 2, 1991), Nirmal Jit Kumar (ID: 333483, DOB: Apr 12, 1978), and Anit Andoria - to the post of Officiating Lineman (LM) against vacant posts in various DS Sub-Divisions under Batala and Pathankot DS Divisions. All promotions are effective immediately.
8PSPCL Patiala HQ promotes Jasvir Kaur Randhawa (Emp ID: 265518) to officiating divisional superintendent under order no. 19 Punjab State Power Corporation Limited's HQ at Patiala has issued Office Order No. 19 dated April 29, 2026, promoting Jasvir Kaur Randhawa (Employee ID: 265518) from Circle Assistant in the DS Division to Officiating Divisional Superintendent against a vacant post. The promotion order, issued by the Office of Deputy Secretary/Engineer-1, PSPCL Patiala, takes immediate effect and is in line with PSPCL's ongoing cadre restructuring and promotional exercises.
TRAINING, COMPLIANCE & ADMINISTRATION
8PSPCL Bathinda Knowledge Centre deputes CHB workers for 5-day non-residential training programme from May 4–8, 2026 Punjab State Power Corporation Limited's Addl. SE Zonal Knowledge Centre, Bathinda (D-318 Thermal Colony, Mobile: 96461-22973) has issued Office Order No. 57 dated April 29, 2026, sanctioning deputation of CHB (Contract/Hired Basis) workers from different PSPCL offices to attend a 5-day Non-Residential Training Programme scheduled from May 4 to May 8, 2026. This training is part of PSPCL's ongoing skill development initiative for its contract workforce.Details
8Jaipur Vidyut Vitran Nigam hikes dearness relief for pensioners from 58% to 60% with effect from January 1, 2026 Jaipur Vidyut Vitran Nigam Limited (JVVNL), a Government of Rajasthan undertaking (CIN: U40109RJ2000SGC016486), issued an order dated April 29, 2026 revising the Dearness Relief (DR) for Nigam pensioners from 58% to 60% with effect from January 1, 2026. The order adopts the Finance Department (Rules Division), Government of Rajasthan's order No. F.12(8) FD/Rules/2017 dated April 23, 2026. Payments involving fractions of a rupee shall be rounded off to the next higher rupee.
8JVVNL revises dearness allowance for Nigam employees to 60% from 58% effective January 1, 2026 Jaipur Vidyut Vitran Nigam Limited (JVVNL) issued an order dated April 28, 2026 revising the Dearness Allowance (DA) for Nigam employees from 58% to 60% with effect from January 1, 2026, adopting Rajasthan Finance Department Order No. F.6(3)FD/Rules/2017 dated April 23, 2026. DA shall be calculated on basic pay as per the Pay Matrix and shall exclude Special Pay or Personal Pay. Payments with fractions of less than 50 paise shall be ignored, while those above 50 paise shall be rounded up.
8Ajmer Discom (AVVNL) authorises priority electricity connections for drinking water supply on undertaking basis till July 31, 2026 Ajmer Vidyut Vitaran Nigam Limited (AVVNL) issued an order dated April 29, 2026 (Comml. AJ-990) directing all concerned to release electricity connections for drinking water supply installations on priority, even on the basis of undertakings, up to July 31, 2026, in view of summer water requirements and a request from the PHED department. AEn (O&M) officers are authorized to accord financial and technical sanction up to 11 kV supply irrespective of estimate amount, per Comml. AJ-65. The order was signed by Additional Chief Engineer (HQ), AVVNL.
8Jodhpur Discom authorises priority release of electricity connections for drinking water supply on undertaking basis till July 31, 2026 Jodhpur Vidyut Vitran Nigam Limited (JdVVNL), vide its order from SE (RA&C) Jodhpur Discom, authorised release of electricity connections for drinking water supply installations on priority, even on the basis of undertaking submitted by applicants, up to July 31, 2026. This is to ensure water availability during the summer season and in consideration of PHED department's request. AEn (O&M) officers are already empowered to grant financial and technical sanction up to 11 kV supply irrespective of estimate amount.
8Rajasthan Discoms calculate FPPAs for May 2026 billing based on February 2026 fuel and power purchase data Jaipur, Ajmer, and Jodhpur Vidyut Vitaran Nigam Limited jointly prepared the Fuel and Power Purchase Adjustment Surcharge (FPPAS) calculation for billing month of May 2026, based on February 2026 actuals, in accordance with Ministry of Power Rule 14 of Electricity (Amendment) Rules, 2022 and Regulation 87 of RERC (Tariff) Regulations, 2025. The document, signed by Chief Engineer Rajeev Verma (AVVNL) on April 28, 2026 with RajKaj Ref No. 21862288, ensures timely recovery of fuel cost variations from distribution consumers.
OTHER STATE DISCOMS & PROCUREMENT
8PVVNL Meerut schedules 30-Apr-2026 mass power shutdown across 11 zones - over 50 feeders to go dark for up to 4 hours Pashchimanchal Vidyut Vitran Nigam Limited (PVVNL) has announced a sweeping planned shutdown across its Meerut jurisdiction on April 30, 2026, affecting more than 50 feeders spanning 11 zones including Bulandshahar, Ghaziabad, Meerut, Noida, Saharanpur, and Muzaffarnagar. Shutdowns range from 1 to 4 hours, with outages scheduled as early as 5:00 AM and as late as 6:30 PM, impacting thousands of urban, rural, and industrial consumers.
8Haryana's DNRE invites pre-bid comments for rate contracts on GCRT solar plants with and without battery banks The Department of New & Renewable Energy (DNRE), Haryana has called a Pre-Bid Meet for prospective bidders to give feedback on draft rate contracts for supply, installation, and commissioning of Grid Connected Rooftop (GCRT) Solar Power Plants - with and without battery banks - in government buildings, Gaushalas, social sector institutes, and un-electrified Dhanis. Bidders must submit comments by visiting the official HAREDA website at www.hareda.gov.in before the stipulated deadline.
8MEPDCL invites RFP for 50 master and 100 slave fault passage indicators for 11 kV & 33 kV networks in Meghalaya Meghalaya Power Distribution Corporation Limited (MePDCL), Office of the Chief Engineer (Distribution) Eastern Zone, Shillong-793001, issued a Request for Proposal (RFP) dated April 28, 2026 (No. MePDCL/CE(D)/EZ/T-48/Pt-III/2026-27), seeking procurement of 50 units of Master Fault Passage Indicators/Sensors (FSI/FPS) and 100 units of Slave Fault Passage Indicators/Sensors for 11 kV and 33 kV networks. Eligible OEMs/Firms may download specifications from www.meecl.nic.in and submit bids to the Chief Engineer (Distribution) Eastern Zone, MePDCL.
8HPPCL extends deadline for general manager (electrical) contract post applications to May 20, 2026 Himachal Pradesh Power Corporation Limited (HPPCL), a state government undertaking (CIN: U40101HP2006SGC030591), has extended the last date for receipt of applications for the post of General Manager (Electrical) on a contract basis from the original deadline of April 30, 2026 to May 20, 2026. Previously advertised on April 1, 2026, all other terms, conditions, and eligibility criteria remain unchanged. Candidates who already applied need not reapply.
8HVPNL nominates field staff for substation safety and equipment training at HPTI, Panchkula - May 7–8, 2026 Haryana Vidyut Prasaran Nigam Limited (HVPNL), vide Memo No. Ch-263/SEG-547/Vol-1 dated April 29, 2026, nominated multiple field cadre officials for a 2-day classroom training program at the HVPNL Power Training Institute (HPTI), Sector-26, Panchkula, scheduled for May 7–8, 2026. The program covers AIS substations, protection systems, SF6 Circuit Breakers, CT, PT, CVT, NCT, LA, isolators, VCBs, Capacitor Banks, and accident prevention, with nominees posted across 132 kV and 66 kV substations in Haryana.
8MSEB Holding Company invites applications for board-level director (fuel) at Maharashtra State Power Generation Company (MSPGCL) MSEB Holding Company Ltd. issued Advertisement No. 05/2026 dated April 29, 2026 for the position of Director (Fuel) at Maharashtra State Power Generation Company Limited (MSPGCL). The Board-level position requires a graduate engineer in Mechanical/Electrical/Instrumentation with a minimum of 20 years of experience in power generation, including a minimum of 5 years at Chief Engineer level or equivalent, with at least 1 year in a position just below Board level in a State Electricity Board or PSU. The role reports directly to the Chairman & Managing Director.
8MSEB Holding Company seeks board-level director (projects) for MSPGCL with minimum 20 years power sector experience MSEB Holding Company Ltd. released Advertisement No. 04/2026 dated April 29, 2026 for the position of Director (Projects) at Maharashtra State Power Generation Company Limited (MSPGCL). The Board-level role requires a graduate engineer in a relevant discipline with a minimum of 20 years of field experience, at least 5 years as Chief Engineer or equivalent, and 1 year in a position just below the Board level in a State Electricity Board or PSU. Candidates with an MBA are preferred. The Director (Projects) will report to the Chairman & Managing Director of MSPGCL.Details
8Shanti Act 2025 transforms India's nuclear sector: Private participation, pragmatic liability regime, and path to 100 GW by 2047 The SHANTI (Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India) Act, 2025 represents a landmark evolution of India's atomic energy legal framework - building on the Atomic Energy Act 1948, AE Act 1962, CLND Act 2010, and 2015 amendments. Presented at a workshop on April 28, 2026, the Act enables private sector and joint venture participation in nuclear power production, establishes a robust AERB regulatory regime, introduces a pragmatic liability regime, and aligns with international nuclear conventions. It will come into force on the date notified by the Central Government.
8GIC Re presents India Nuclear Insurance Pool (INIP) framework to enable 100 GW nuclear power roadmap under Shanti Act, 2025 GIC Re, India's national reinsurer, outlined the India Nuclear Insurance Pool (INIP) framework on April 17, 2026, as a key risk-management enabler for India's 100 GW nuclear power ambition under the SHANTI Act, 2025. The INIP operates on a pooling mechanism where multiple insurers share similar nuclear risks proportionate to their pool share, reducing reliance on traditional reinsurance that is often insufficiently available for nuclear liabilities. GIC Re's presentation covered pool structures, INIP modalities and policies, and future directions for scaling nuclear insurance capacity.
8Power Finance Corporation proposes innovative financing schemes for nuclear projects requiring Rs. 30+ crore per MW capital outlay Power Finance Corporation Limited (PFC), a Maharatna PSE, presented innovative financing schemes (dated April 17, 2026) for nuclear power projects, which typically require capital outlay exceeding Rs. 30 crore per MW - significantly higher than other energy alternatives. Key challenges highlighted include 7–10 year gestation periods, RBI's project finance norms requiring at least 51% repayment from project cash flows, stringent DCCO norms (3-year infra window), and limited tolerance for cost overruns (~10% cap). PFC emphasized the need for patient capital and specialized financial appraisal skills for this sector.
8CEA chief engineer reveals nuclear power tariff structure: 15.5% return on equity, Rs. 27.89 lakh/MW O&M for 700 MW PHWR under 2022–27 control period Goutam Ghosh, Chief Engineer at the Central Electricity Authority (CEA), presented the nuclear tariff determination governance framework and cost components, including a Return on Equity of 15.5% plus taxes, O&M costs of Rs. 27.89 lakh/MW for 700 MW PHWR (2022-23), and depreciation at 3% for existing plants. Under the SHANTI Act, tariff will be fixed by DAE, with disputes to be addressed by the Atomic Energy Redressal Council (comprising Chairperson AEC, Director BARC, Chairman AERB, and Chairman CEA), with further challenge provisions before APTEL.
8NTPC outlines Shanti Act's role in unlocking foreign nuclear technology for India's 100 GW by 2047 roadmap NTPC Limited's presentation (April 17, 2026) detailed how the SHANTI Act, 2025 enables technology access for India's 100 GW nuclear capacity target by 2047, comprising 46 GW PHWR, 39 GW PWR, 10 GW BSR/BSMR, and 5 GW FRB. NTPC's nuclear subsidiary ANUSHAKTI VIDHYUT NIGAM LIMITED (ASHVINI), with 89+ GW capacity base, is actively pursuing nuclear energy transition. Key aspects include support for indigenous PHWR technology scaling, decoupling of foreign PWR technology, and streamlining collaboration processes under the SHANTI framework. NTPC's Mahi Banswara Rajasthan Atomic Power Project (4×700 MW) commenced siting work in 2026.
8NPCIL's sub-committee shortlists 28 retiring thermal plant sites for nuclear power deployment under India's 100 GW nuclear roadmap A sub-committee constituted by NPCIL in January 2025, comprising officers from CEA, NPCIL, and AERB, has shortlisted 28 thermal power plant sites for potential repurposing for nuclear power deployment. Sites were initially screened based on unit age and retirement status - primarily units over 40 years old - and then evaluated against a 17-point checklist covering location, land and water availability, seismo-tectonic factors, and surrounding population. Repurposing leverages existing infrastructure, grid connectivity, and water access available at retiring coal plants, reducing greenfield nuclear project costs.
8Dr. A.K. Nayak argues India needs 400–500 GW captive nuclear power by 2070 beyond 100 GW target for Vikshit Bharat vision Dr. A.K. Nayak (FNAE, FMASc) argued at the SHANTI Act workshop that while India's 100 GW nuclear target (~800 TWh/year) is a promising start, India's Vikshit Bharat vision requires total energy of around 30,000 TWh/year or more. He highlighted that captive power plants grew from 40 GWe in 2012 to 80 GWe in 2020 (~2x in 8 years), with steel expected to grow 8x and cement 3x in 20 years, projecting captive power demand of 400–500 GW by 2070. Small & Micro Nuclear Reactors were presented as a key enabler for industrial decarbonization and energy security.
RENEWABLE ENERGY, EV & CLEAN TRANSITION POLICY
8Ministry of Heavy Industries chairs high-level meeting on financing e-buses and e-trucks to accelerate private sector EV adoption The Ministry of Heavy Industries (MHI), under Secretary Shri Kamran Rizvi, convened a high-level meeting on April 29, 2026, in New Delhi, to deliberate on financing mechanisms for electric buses (e-Buses) and electric trucks (e-Trucks) in the private sector. Key agenda items included current financing challenges, present adoption status, potential government interventions, and fiscal support required to catalyse EV fleet transition in the commercial transport segment.
8EPO-IEA April 2026 joint study flags battery circularity as a critical innovation frontier for future EV critical materials supply The European Patent Office (EPO) and the International Energy Agency (IEA) have jointly released a landmark April 2026 study titled 'Battery Circularity: Innovation Trends for a Future Source of Critical Materials', examining the rapidly evolving end-of-life battery recycling and reuse ecosystem. With EV battery volumes surging globally, the study warns of an imminent 'end-of-life wave' and calls for scaled innovation in circularity to reduce dependence on virgin critical minerals, presenting risk mitigation strategies across the geopolitical and environmental landscape.
8IISD: India's clean energy subsidies represent only 10% of total energy subsidies; fossil fuel support constrains renewable push A new analysis from the International Institute for Sustainable Development (IISD), published April 29, 2026, reveals that clean energy subsidies for renewable energy and electric vehicles (EVs) account for just 10% of India's total energy subsidy pool. While these allocations are gradually growing, they remain highly vulnerable to global oil price shocks, given India's structural fiscal dependence on oil and gas revenues - a structural imbalance that, the IISD warns, could undermine India's clean energy transition ambitions.
8TERI and Messe Frankfurt India release white paper on critical mineral security through circular economy at Wastetech India 6th edition A joint white paper titled 'Critical Mineral Security: The Circular Pathway' was released by The Energy and Resources Institute (TERI) and Messe Frankfurt India as part of WasteTech India's 6th Edition. The document, contributed to by TERI researchers including Director Souvik Bhattacharjya and Associate Fellow Mrunali Tembhurne, examines how circular economy strategies can secure India's critical mineral supply chains. Industry inputs were provided by Attero Recycling Pvt. Ltd., a leading e-waste recycler.
8TCE projects India's per capita electricity consumption to reach 6,400 kWh by 2050 and 10,000 kWh under net zero scenario R. Raghavan, Vice President and Head of Power Business at Tata Consulting Engineers (TCE), presented 'Supply Chain Localization & Implementation Approach' at the SHANTI Act 2025 workshop. Drawing on Goldman Sachs and NITI Aayog data, the presentation projects India's per capita electricity consumption at 6,400 kWh by 2050 (and 10,000 kWh under Net Zero Scenario), CO2 emissions dropping to ~0.3 kgCO2/kWh by 2050, and India aspiring to become a USD 30 trillion economy by 2047. TCE highlighted its longstanding association with India's nuclear programme as a key supply chain enabler.Details
8CEA grid report April 28, 2026: All-India monitored thermal capacity at 3.09 lakh MW, Northern nuclear generation 8.88% below target The Central Electricity Authority (CEA) All-India/Regionwise Power Generation Overview for April 28, 2026 (Sub-Report 1) shows Northern region total monitored capacity at 81,696.72 MW, with actual generation of 1,249.96 MU against a target of 1,184.47 MU - exceeding programme. However, Northern nuclear generation of 44.45 MU was 32.88% below the programme of 59.40 MU. The total Northern cumulative deviation from April 1 stands at -3,183.71 MU (-9.70%) due to shortfalls across thermal, nuclear, and hydro.
8CEA all-India capacity summary April 28, 2026: 2.69 lakh MW capacity online out of 3.10 lakh MW monitored; Western Region leads with 91,415 MW online The CEA All-India Summary Report (Sub-Report 3) for April 28, 2026 shows total monitored capacity of 3,09,716.29 MW across all regions, with 2,69,257.36 MW online after accounting for 40,458.92 MW under various outages. Planned maintenance accounts for 24,754.11 MW and forced outages for 6,699.30 MW. The Western Region leads with 91,415.38 MW online (out of 1,04,702.40 MW monitored), followed by Northern at 69,963.41 MW. The North Eastern region has the smallest online footprint at 4,299.04 MW out of 5,223.95 MW monitored.
8CEA sub-report 16 April 28, 2026: All-India coal capacity at 2.22 lakh MW online, 90.47% utilization; gas capacity only 49.07% available The CEA Capacity Utilization report (Sub-Report 16) for April 28, 2026 shows India's total monitored coal capacity at 2,21,940.01 MW with 2,03,187 MW online (8.45% under outage), achieving 90.47% of online capacity as gross generation. Lignite capacity stands at 6,620 MW with 80.62% online utilization. Gas/Liquid capacity of 20,122.42 MW is performing at only 49.07% availability, with 3,736.90 MW under planned maintenance and 5,454.30 MW under forced outage, revealing chronic underutilization of gas-based generation due to fuel cost and demand issues.
8CEA category-wise generation report April 28, 2026: Total coal generation 4,105.24 MU vs target 4,086.11 MU; natural gas exceeds target at 122.87 MU The CEA Category-Wise Fuel-Wise Generation Report (Sub-Report 17) for April 28, 2026 shows coal-based generation of 4,105.24 MU against a programme of 4,086.11 MU (slight outperformance), while lignite generation lagged at 99.97 MU versus target 111.32 MU. Natural gas generation of 122.87 MU surpassed the target of 88.86 MU. Total thermal generation (coal + lignite + gas + diesel) came in at 4,329.25 MU against a programme of 4,286.29 MU. Cumulative April 2026 coal generation stands at 108,387.91 MU versus target of 113,285.41 MU, trailing by nearly 4,900 MU.
8CEA sub-report 5 April 28, 2026: Southern Region's thermal availability at 88.79%, nuclear at 86.75%; Northern hydro online capacity at just 74.60% The CEA All-India Regionwise Power Generation Overview (Sub-Report 5) for April 28, 2026 reveals that the Western region leads in thermal availability with 90.95% (77,005 MW online of 84,671.01 MW stabilised). Southern region's nuclear availability stands at 86.75% (2,880 MW of 3,320 MW), while Northern nuclear availability is 90.09% (2,000 MW of 2,220 MW). The Northern region's hydro online capacity is only 74.60% (16,350.11 MW of 21,915.76 MW), while Western hydro shows 90.96% availability. The Eastern region data is not shown in the provided extract.
FUEL STOCK, HYDRO RESERVOIR & RENEWABLE TRACKING
8CEA coal stock report April 28, 2026: Panipat TPS at 168% of normative stock with 450,000 tonnes; Rajiv Gandhi TPS at 134% with 635,200 tonnes The Central Electricity Authority (CEA) Fuel Management Division Daily Coal Stock Report for April 28, 2026 reveals that Haryana's Panipat TPS (710 MW) holds 450,000 tonnes of coal - 168% of normative stock - at 73% Plant Load Factor, while the 1,200 MW Rajiv Gandhi TPS operates at 134% normative stock with 635,200 tonnes. The report covers all coal-linked, non-linked, and coal block category thermal power stations across state and central sectors, tracking daily consumption, receipts, and critical stock situations.
8CEA hydro reservoir report April 28, 2026: Bhakra Dam level at 485.6 m vs FRL 513.59 m with 1,728.8 MU energy potential; Pong Dam at 406.81 m The CEA Daily Hydro Reservoir Report (Sub-Report 6) for April 28, 2026 shows Bhakra (Himachal Pradesh) at 485.6 m (FRL: 513.59 m) with an effective capacity of 2,675.06 MCM at present level versus 6,516.07 MCM at FRL, and cumulative hydro generation since April 1 of 251.75 MU. Pong Dam (Himachal Pradesh) stands at 406.81 m against FRL of 426.72 m with a content of 2,592.95 MCM. Ranjit Sagar (Punjab) data is also included. The below-FRL levels signal constrained hydro potential as the pre-monsoon season progresses.
8CEA daily renewable generation report April 28, 2026: All-India wind, solar, biomass, and small hydro generation tracked across all states The Central Electricity Authority (CEA), Renewable Project Monitoring Division, released the Daily Renewable Generation Report for April 28, 2026, covering All-India state-wise and region-wise generation figures in Million Units (MU net) for wind, solar, biomass, bagasse, other small hydro, and cumulative generation during April 2026. States like Chandigarh and Delhi recorded zero generation from most renewable categories, while larger renewable-rich states contributed the bulk of cumulative renewable output for the month.
8CEA sub-report 4 April 28, 2026: Haryana generation exceeds target by 24% at 1,050.69 MU; Delhi trails 3.49% for April cumulative The CEA Region-wise/Utility-wise Summary Report (Sub-Report 4) for April 28, 2026 shows Haryana's cumulative April generation of 1,050.69 MU against a programme of 847.56 MU - an excess of 203.13 MU (+23.97%). Delhi's cumulative generation of 310.40 MU fell short of the 321.62 MU target by 11.22 MU (-3.49%). Himachal Pradesh's cumulative generation of 204.68 MU missed the 226.52 MU programme by 21.84 MU (-9.64%). The daily report shows Delhi at 28.64 MU (programme: 11.84 MU), reflecting I.P. CCPP and other units running above schedule.
PLANT MAINTENANCE & UNIT OUTAGES
8CEA maintenance report April 28, 2026: Ropar TPS unit 5 (210 MW) tripped for ID fans problem; Yamuna Nagar unit 2 on 300 MW boiler overhaul since Feb 2026 The CEA Daily Maintenance Report (Sub-Report 10) for April 28, 2026 records key outages for coal, lignite, and nuclear units. Punjab's Ropar TPS Unit 5 (210 MW) had a forced minor maintenance outage at 12:08 on April 28 for ID Fans Problem, with expected return at 20:00 same day. Haryana's Yamuna Nagar TPS Unit 2 (300 MW) remains under planned major maintenance (boiler overhaul/annual maintenance) since February 15, 2026. Punjab's Ropar TPS Unit 4 (210 MW) is on planned major overhaul since March 14, 2026.
8CEA maintenance report for 500 MW+ units April 28, 2026: Vedanta Ltd 600 MW unit on forced outage since April 14; Salaya TPP and Shree Singaji TPP hit turbine problems The CEA Daily Maintenance Report (Sub-Report 11) for units of 500 MW and above for April 28, 2026 records Vedanta Ltd. Chhattisgarh TPP Unit 1 (600 MW) on forced outage since April 14, 2026 for P.A. Fans Problem. Uttar Pradesh's Obra TPS Unit 14 had a Condensate Pump problem from April 27 and was synchronized by April 28 at 02:07. Gujarat's Salaya TPP Unit 1 encountered a Turbine Misc. Problem at 22:21 on April 28, and Madhya Pradesh's Shree Singaji TPP Unit 1 (600 MW) also had an outage.
8CEA sub-report 13: Indraprastha (I.P.) CCPP units 2,3,4,8 off grid since January 25, 2019; Rithala CCPP units idle since 2013 The CEA Sub-Report 13 on thermal/nuclear units out of grid for over one year (as on April 28, 2026) reveals that I.P. (Indraprastha) CCPP Units 2, 3, 4, and 8 (30 MW each) have been offline since January 25, 2019 - over 7 years - due to low system demand and reserve shutdown. Rithala CCPP Units 1, 2, and 3 have been out of grid since March and June 2013 - over 13 years - due to GT miscellaneous problems, no scheduling from beneficiaries, and grid disturbances. I.P. CCPP Unit 9 (30 MW) has been offline since November 2024 for turbine axial shift/thrust pad issues.
8CEA sub-report 14 April 28, 2026: Chhabbra-I phase-2 TPP unit 3 (250 MW) returns after 21-day annual maintenance; Obra TPS unit 14 (660 MW) back in 3 hours The CEA Sub-Report 14 on recommissioning of thermal/nuclear units (April 28, 2026) shows Chhabbra-I Phase-2 TPP Unit 3 (250 MW, Rajasthan) returning to grid at 04:56 after a major boiler overhaul/annual maintenance that began on April 7, 2026. Obra TPS Unit 14 (660 MW, UP) - with a condensate pump problem that started at 23:06 on April 27 - was synchronized by 02:07 on April 28. Ropar TPS Unit 5 (210 MW) and Suratgarh TPS Unit 5 (250 MW) both suffered and recovered from forced outages within the same day.
8CEA sub-report 8 April 28, 2026: NTPC's all-India generation 1,036 MU against target 1,058 MU; Eastern Region lags at -6.85% deviation The CEA Sub-Report 8 on NTPC station generation for April 28, 2026 shows all-India NTPC monitored capacity at 57,617.23 MW. The Eastern region (14,820 MW monitored) recorded the highest absolute deviation of -18.66 MU from the daily programme, while the Southern region outperformed by +13.34 MU (162.52 MU actual vs 149.18 MU programme). Cumulative April 1 to date deviation for NTPC is most severe in the Northern region at -581.87 MU (-10.19%). The North Eastern region (750 MW, Koldam) also lagged at -35.33 MU (-8.85%) cumulative.Details
8Grid-India's NLDC-REMC report for April 27, 2026 tracks VRE (wind + solar) contribution to all-India maximum demand Grid Controller of India Limited's (GRID-INDIA) NLDC-Renewable Energy Management Centre (REMC) has published its report for April 27, 2026, tracking the contribution of Variable Renewable Energy (VRE) - comprising wind and solar power - to India's all-India maximum demand met. The report provides critical operational visibility for grid balancing, published on April 28, 2026, as part of GRID-INDIA's daily monitoring of India's evolving renewable-heavy grid mix.
8Grid-India NLDC frequency profile for April 29, 2026: Grid stays within IEGC band for over 99% of day; no sub-49.7 Hz instance Grid Controller of India Limited's National Load Despatch Centre, New Delhi, has published the National Frequency Profile for April 29, 2026 (Wednesday), recording zero instances of frequency dipping below 49.7 Hz across the entire day. The frequency remained within the IEGC-prescribed 49.7–50.2 Hz band for more than 99% of the 1,440-minute day, with values oscillating in a narrow 49.80–50.35 Hz range - reflecting exemplary grid frequency discipline maintained across the unified national grid.
8Grid-India publishes all-India angular spread report for April 29, 2026; monitors phasor angles across 14 key grid substations Grid Controller of India Limited has published the All-India Angular Spread Report for April 29, 2026, tracking voltage phasor angles (in degrees) with respect to the Vindhyachal reference bus, across 14 key substations - Agra, Chandrapur, Gazuwaka, Hosur, Kalwa, Kolar, Korba, Kozikode, Moga, Talcher, Thrissur, Unnao, Bhuj, Pavagada, Bawana, and URI Tehri. Angular deviations of up to -70 to -80 degrees were recorded, providing crucial inter-regional synchronization insights.
8NLDC system reliability report April 29, 2026: ER-NR corridor violated for 4.75 hours (19.79%); WR-NR and NER corridors at zero violation Grid Controller of India Limited's National Load Despatch Centre has published the System Reliability Indices Report for April 29, 2026 (reporting date April 30, 2026), recording that the ER-NR transmission corridor experienced 19 blocks of ATC violations covering 4.75 hours (19.79% violation rate). All other monitored corridors - WR-NR, Import of NR, NEW-SR, and NER Import - reported zero ATC violations, indicating clean transmission performance across five of the six key inter-regional corridors.
8NLDC publishes SCUC generator schedule for April 30, 2026: Rihand, Singrauli, Vindhyachal lead with ECRs of 163.4–207.1 paise/kWh Grid Controller of India Limited's National Load Despatch Centre has published the Format-2 SCUC Generator Schedule for April 30, 2026 (issued D-1 on April 29, 2026 at 1500 hrs), listing committed generators with their scheduled MW and Economic Cost of Reserve (ECR) in paise/kWh. Top entries include Rihand Units 1, 2, 3 (scheduled at 352 MW, 375 MW, 333 MW, ECR: 163.4–165.4 paise/kWh), Singrauli TPS at 531 MW (ECR: 199.9 paise/kWh), and Vindhyachal STPS Stages 2–5 at ECRs of 205.2–207.1 paise/kWh.
8NLDC releases national SCED monthly statement revision 1 for October 2025: NPGC leads with Rs. 9.32 crore net payable, BRBCL receives Rs. 3.27 crore The National Load Despatch Centre (NLDC) published its Revision-1 National SCED Monthly Statement for October 2025 (dated April 24, 2026), covering 25+ generators across all regional power pools. NPGC (Eastern Region) topped net payables at Rs. 9,31,66,652, followed by Kahalgaon STPP-II at Rs. 5,84,79,855 and Farakka STPP-I&II at Rs. 4,80,04,940. BRBCL received the largest refund of Rs. 3,26,96,189 from SCED. The SCED mechanism incentivizes efficient scheduling by awarding incremental plants and refunding decremental plants from the national pool.
REGIONAL POWER SUPPLY & DEMAND (RLDCs)
8SRLDC power supply report April 29, 2026: Southern Region meets 57,584 MW evening peak demand and 54,257 MW off-peak with zero shortage Grid Controller of India Limited's Southern Regional Load Despatch Centre has released the Power Supply Position Report for April 29, 2026, confirming zero power shortage in the Southern Region. Evening peak demand (at 20:00 hours) was fully met at 57,584 MW at 50 Hz, while off-peak demand (at 03:00 hours) was fully served at 54,257 MW at 50 Hz, with total day energy (net MU) of 1,444.76 MU - reflecting a healthy power supply position across all Southern states.
8Grid-India Northern RLDC reports April 29, 2026 power supply: Evening peak demand met at 69,473 MW; day energy 1,552 MU, zero shortage Grid Controller of India's Northern Regional Load Despatch Centre has published the Daily Operation Report for the Northern Region for April 29, 2026, recording full demand satisfaction without any shortage. Evening peak demand (20:00 hours) was met at 69,473 MW at 49.996 Hz, while off-peak demand (03:00 hours) was served at 65,285 MW at 49.985 Hz. Total day net energy reached 1,552 MU with zero deficit - marking a robust power supply performance across all Northern Region states.
8Eastern Region RLDC reports full demand met on April 29, 2026: Evening peak 18,000 MW at 50 Hz, day energy 546.58 MU Grid Controller of India Limited's Eastern Regional Load Despatch Centre (ERLDC) has published the Daily Operation Report for April 29, 2026, confirming zero power shortage across the Eastern Region. The evening peak demand (20:00 hours) was fully met at 18,000 MW at 50 Hz, with off-peak demand (03:00 hours) at 26,192 MW at 49.98 Hz. Total day net energy of 546.58 MU was served without any deficit, underscoring robust power availability across Eastern Region states.
8Grid-India NER region daily operation report April 29, 2026: Evening peak demand 2,835 MW, off-peak 1,604 MW, zero shortage recorded Grid Controller of India's North Eastern Regional Load Despatch Centre has published its Daily Operation Report for April 29, 2026 (reporting date April 30, 2026), confirming zero power shortage in the NER. Evening peak demand (20:00 hours) was fully met at 2,835 MW at 50 Hz, while off-peak demand (03:00 hours) was served at 1,604 MW at 49.98 Hz. Total day energy of 50.74 MU was met without any deficit, reflecting stable power supply in the North-Eastern grid.
8SRLDC demand forecast for April 30, 2026: Southern Region peak projected at ~70,000 MW; April 28 forecast error at 1.23% MAPE Grid Controller of India's Southern Regional Load Despatch Centre has published the SR Demand Forecast for April 30, 2026, projecting Southern Region peak demand at approximately 70,000 MW during peak hours, with demand ranging from 35,000 to 70,000 MW across the 24-hour day. A retrospective review of the April 28, 2026 forecast shows the Day Ahead model achieved a Mean Absolute Percentage Error (MAPE) of 1.23%, demonstrating high forecasting accuracy for the Southern Region's load management.
TRANSMISSION & GENERATION OUTAGES
8Grid-India's Southern Regional Load Despatch Centre reports transmission forced outage on April 29, 2026 involving 400 kV transformer Grid Controller of India Limited's Southern Regional Load Despatch Centre (SRLDC), Bengaluru, has published its Transmission Forced Outage Report for April 29, 2026, recording a forced outage involving a 400 KV/230 KV transformer triggered by Buchholz trip, PRV-2 operation, and Transformer Differential protection relay. The report, filed on April 30, 2026, is part of GRID-INDIA's mandatory daily outage monitoring under the Grid Code for the Southern Region.
8SRLDC transmission outage report April 29, 2026: 400 kV Ramagundam–Telangana STPP-1 line under planned outage since March 24, 2023 Grid Controller of India Limited's Southern Regional Load Despatch Centre has published the Transmission Outage Report for April 29, 2026, listing planned outages including the 400 KV AC Line connecting Ramagundam to Telangana STPP-1 (owned by POWERGRID), which has been on outage since March 24, 2023 at 04:20 hours - with the line remaining in 'Idle Charge' status as it awaits readiness for idle charging at the Telangana end. The long-standing outage continues to be monitored.
8SRLDC generating unit outage report April 29, 2026: Lanco's LKPPL St2 units (233 MW and 133 MW) in Andhra Pradesh on reserve shut down Grid Controller of India Limited's Southern Regional Load Despatch Centre has published the Generating Unit Outage Report for April 29, 2026, listing planned outages in the Central Sector. LANCO's LKPPL ST2 plant in Andhra Pradesh had two units - Unit 1 (233 MW capacity) and Unit 2 (133 MW capacity) - placed under reserve shut down starting April 29, 2026 at 04:00 hours, with no expected revival date specified - indicating an extended reserve shutdown arrangement for these thermal generation units.
8Eastern Region NPMC logs zero central sector planned outages on April 29, 2026; OHPC's Burla hydro unit 4 (32 MW) on annual maintenance The Eastern Region's National Power Management Centre (NPMC) outage report for April 29, 2026 (reporting date April 30, 2026) records zero planned generation outages in the Central Sector. In the State Sector, Odisha Hydro Power Corporation (OHPC) reported Unit 4 (32 MW capacity) of Burla Hydro Station on planned annual maintenance outage. The report covers outages from 00:00 to 23:59 hours, reflecting the clean generation position in the Eastern Region on the day.Details
8IEX day-ahead market (DAM) snapshot April 29, 2026: Night hours hit Rs. 10,000/MWh cap while noon prices crash to Rs. 1,592/MWh The IEX Day-Ahead Market (DAM) snapshot for April 29, 2026 reveals extreme intra-day price volatility: purchase bids of up to 20,439.08 MWh and sell bids of 47,953.43 MWh (Hour 12) were recorded. Night-time hours (1–3 AM) cleared at MCP of Rs. 10,000/MWh, while peak solar hours (12 PM) saw MCP plunge to Rs. 1,591.59/MWh with cleared volume of 8,301.18 MWh. This captures a dramatic solar-driven price swing, with the MCV peaking at 8,428.09 MWh in Hour 13.
8IEX DAM weekly summary April 23–30, 2026: Total volume 854,143 MWh, max MCP Rs. 7,078/MWh on April 27, min MCP Rs. 5,587/MWh on April 30 The Indian Energy Exchange (IEX) Day-Ahead Market (DAM) weekly summary for April 23–30, 2026 shows total purchase bids of 4,635,214.76 MWh, sell bids of 2,989,389.49 MWh, and total cleared volume of 854,143.89 MWh (Final Scheduled). The maximum weighted MCP of Rs. 4,726.31/MWh was recorded on April 27, with the maximum peak MCP of Rs. 7,078.52/MWh on the same day. The minimum weighted MCP of Rs. 3,566.21/MWh occurred on April 26, while April 30 recorded the lowest MCP at Rs. 5,587.12/MWh.
REAL-TIME MARKET (RTM)
8IEX RTM market snapshot April 29, 2026: Hour 0 clears 4,766 MWh at Rs. 10,000/MWh, mid-day hours hit Rs. 1,900–2,200/MWh low The IEX Real-Time Market (RTM) snapshot for April 29, 2026 shows Hour 0 (midnight to 1 AM) clearing 4,766.41 MWh at MCP Rs. 10,000/MWh with a 20,359.45 MWh purchase bid. During Hour 7 (6–7 AM), MCP dropped sharply to Rs. 1,900.69/MWh (weighted: Rs. 1,888.91) as sell bids rose to 14,506.80 MWh. Mid-morning hours 8–10 saw MCPs of Rs. 2,241–2,262/MWh as solar supply increased. Total scheduled volumes ranged from 4,857–10,013 MWh across peak hours.
8IEX RTM weekly market summary April 23–30, 2026: Total volume 1.248 lakh MWh, max MCP Rs. 7,576.70/MWh on April 25 The IEX Real-Time Market (RTM) weekly market summary for April 23–30, 2026 shows total cleared MCV of approximately 1,24,798 MWh across 8 delivery dates, with total purchase bids of 4,519,187.63 MWh and sell bids of 2,306,775.38 MWh. The highest MCP of Rs. 7,576.70/MWh was recorded on April 25, while April 29 and 30 saw the lowest MCPs at Rs. 3,193.58 and Rs. 2,251.95/MWh respectively, reflecting growing solar supply in later days of the week. April 23 had the highest final scheduled volume of 152,108.97 MWh.
8IEX RTM market April 29, 2026: Hour 1 clears 1,800 MWh and hour 2 clears 1,300 MWh at Rs. 10,000/MWh; hours 3–24 see zero clearing The IEX Real-Time Market (RTM) Daily Volume Profile Report for April 29, 2026 shows clearing only in the first 2 hours: 1,800 MWh in Hour 1 (purchase bid: 1,690 MWh, sell bid: 450 MWh) and 1,300 MWh in Hour 2 (purchase bid: 540 MWh, sell bid: 325 MWh), both at Rs. 10,000/MWh. Hours 3 through 24 recorded zero clearing despite potentially available bids, indicating that buy-sell mismatches or scheduling constraints prevented RTM clearing for the rest of the day.
GREEN MARKETS (GDAM, GTAM, TAM)
8IEX green day-ahead market (GDAM) snapshot April 29, 2026: Total solar and hydro sell bids range 257–362 MWh per hour, MCP at Rs. 10,000/MWh night The IEX Green Day-Ahead Market (GDAM) market snapshot for April 29, 2026 shows hourly sell bid volumes ranging from 257.65 MWh (Hour 5) to 362 MWh (Hour 1), with a hydro component of approximately 8 MWh per hour. Night-time hours 1–5 cleared at Rs. 10,000/MWh MCP across all green energy segments (solar and hydro). The market saw no non-solar/non-hydro bids, reflecting a pure renewable profile on the GDAM platform.
8IEX GDAM weekly summary April 23–30, 2026: Total scheduled volume ~19,000 MWh, max MCP Rs. 6,890.41/MWh on April 25 The IEX Green Day-Ahead Market (GDAM) weekly market summary for April 23–30, 2026 reveals total purchase bids of approximately 2,077,712.99 MWh and scheduled volumes varying from around 5,512 MWh (April 25) to 9,086 MWh (April 23). The highest MCP was recorded on April 25 at Rs. 6,890.41/MWh, and the highest weighted MCP was on the same day at Rs. 4,011.30/MWh. April 23 had the highest final scheduled volume of approximately 19,925 MWh across all green categories.
8IEX green term-ahead market (GTAM) records 144 MWh daily trades at Rs. 6,800/MWh across 4 daily contracts on April 29, 2026 The Indian Energy Exchange (IEX) Green Term-Ahead Market (GTAM) Trade Details for April 29, 2026 show 4 daily contract trades (DY5-MON, DY5-THU, DY5-TUE, DY5-WED, DY6 series, and DY6-FRI, DY6-MON, DY6-SAT, DY6-SUN) each trading 144 MWh at a uniform price of Rs. 6,800/MWh, with 1 buy counter and 1 sell counter per contract. All trades were executed at Rs. 6,800/MWh - both lowest and highest price - confirming uniform price discovery across all GTAM daily contracts on this date.
8IEX term-ahead market (TAM) records 240 MWh trades at Rs. 7,500/MWh across multiple daily solar contracts on April 29, 2026 The IEX Term-Ahead Market (TAM) trade details for April 29, 2026 show multiple daily solar contract trades (DB1 series: FRI, MON, SAT, SUN, THU, TUE) each trading 240 MWh at a uniform price of Rs. 7,500/MWh, with 1 buy and 1 sell counter each. One other daily contract (D06-WED-WR) recorded zero total traded volume. The D06 series contract had a sell bid at Rs. 2,400 but resulted in zero clearance, while all DB1 contracts cleared uniformly at Rs. 7,500/MWh.
HIGH-PRICE & ANCILLARY MARKETS
8IEX HP-DAM market snapshot April 29, 2026: Hour 1–2 clear 54.90 MWh at Rs. 20,000/MWh cap, hours 3–24 record zero clearing The IEX High-Price Day-Ahead Market (HP-DAM) snapshot for April 29, 2026 shows clearing only in the first 2 hours of the day: 54.90 MWh was cleared in Hour 1 and Hour 2 at MCP of Rs. 20,000/MWh (the ceiling price), with purchase bids of 150 MWh and sell bids of 1,353.50 MWh. Hours 3 through 24 recorded zero purchase bids and zero cleared volume, with sell bids available in the range of 1,298.60–1,623.50 MWh per hour but no matching buyer demand.
8IEX HP-DAM weekly summary April 23–30, 2026: Total cleared volume only 2,386.15 MWh, April 23 tops with 1,476.55 MWh at MCP up to Rs. 20,000/MWh The IEX High-Price Day-Ahead Market (HP-DAM) weekly summary for April 23–30, 2026 shows a total cleared volume of just 2,386.15 MWh against total purchase bids of 41,854.92 MWh and sell bids of 309,596.78 MWh, indicating severely constrained demand at premium price levels. April 23 recorded the highest cleared volume of 1,476.55 MWh at a weighted MCP of Rs. 18,812.63/MWh. On April 25, 26, and 27, MCP touched Rs. 20,000/MWh with cleared volumes of just 7.64, 54.40, and 35.00 MWh respectively.
8IEX IDAS market April 29, 2026: 1,600 MWh cleared hourly in hours 1–4 at Rs. 10,000/MWh, hours 5–24 saw only sell-side bids The IEX Intra-Day Ancillary Services (IDAS) Market Daily Volume Profile Report for April 29, 2026 shows matching and clearing of 1,600 MWh (400 MW × 4 blocks) at Rs. 10,000/MWh in Hours 1, 2, and 3, and 400 MWh at Rs. 10,000/MWh in Hours 4–7. Hour 7 had 218 MWh in sell bids but a 400 MWh scheduled volume indicating a partially cleared session. Hours 8 onwards recorded only sell-side bids (211.75–276.75 MWh) with no purchase bids and no clearing.Details
8Bajel Projects bags ultra-mega 500 kV overhead transmission line EPC order from international MENA client Bajel Projects Limited (BSE: 544042, NSE: BAJEL) has disclosed to stock exchanges the receipt of an Ultra-Mega EPC order for a 500 kV Overhead Transmission Line from a Middle East and North Africa (MENA)-based international client. The disclosure, filed on April 29, 2026 under SEBI Listing Regulations 30, marks a significant international breakthrough for the infrastructure company in the high-voltage power transmission segment.
8Larsen & Toubro (BSE: 500510) executes SPA with Telangana Government's HML to divest entire 100% stake in L&T Metro Rail Hyderabad Larsen & Toubro Limited (L&T, BSE: 500510, NSE: LT) has announced a major divestiture - execution of a Share Purchase Agreement (SPA) with Hyderabad Metro Rail Limited (HML), a Government of Telangana Enterprise, for sale of its entire shareholding in L&T Metro Rail (Hyderabad) Limited. The transaction, disclosed on April 29, 2026 under SEBI Regulation 30, represents L&T's exit from the Hyderabad metro concession in a strategic portfolio realignment.
8BlackRock Inc. reports 2% decrease in aggregate holdings in PTC India Limited; discloses under SEBI takeover code regulation 29(2) BlackRock, Inc., operating on behalf of discretionary management clients from its 100 Bellevue Parkway, Wilmington, DE headquarters, has disclosed to BSE Limited that its aggregate shareholding in PTC India Limited has declined by 2% from its previous disclosure level. The April 29, 2026 filing under Regulation 29(2) of SEBI (Substantial Acquisition of Shares and Takeovers) Regulations, 2011 details the Annexure-2 format required by SEBI's takeover code.
8BIS conducts second inspection at UTL Solar's Bawal, Haryana facility following earlier Noida search; NSE: UTLSOLAR discloses under reg. 30 UTL Solar (Surana Solar Limited, NSE: UTLSOLAR, BSE: 544613) has disclosed that the Bureau of Indian Standards (BIS) visited its Bawal, Haryana manufacturing facility on April 28, 2026, as an extension of the earlier inspection conducted at the company's Noida facility (originally disclosed on April 3, 2026). The back-to-back BIS inspections signal heightened regulatory scrutiny over the company's solar product certification and standards compliance.
EARNINGS, BOARD MEETINGS & RESULTS
8Adani Power posts audited financial results for Q4 & FY2026 at board meeting held April 29, 2026 Adani Power Limited (BSE: 533096, NSE: ADANIPOWER) convened a Board of Directors meeting on April 29, 2026, starting at 12:30 PM and concluding at 3:20 PM, approving the Audited Standalone and Consolidated Financial Results for the quarter and full year ended March 31, 2026. The results, reviewed by the Audit Committee, were certified by statutory auditors M/s. SRBC & Co. LLP, and filed with BSE and NSE per SEBI Listing Regulations.
8Kalpataru Projects International (BSE: 522287) files large corporate initial disclosure for FY 2026-27 with SEBI Kalpataru Projects International Limited (KPIL), listed on BSE (Code: 522287) and NSE (KPIL), has filed its Initial Disclosure as a Large Corporate entity for FY 2026-27 under Chapter XII of SEBI Master Circular No. SEBI/HO/DDHS/DDHS-PoD/P/CIR/2025/0000000137 dated October 15, 2025. The disclosure, signed by Company Secretary Shweta Girotra, was submitted on April 29, 2026 for compliance with SEBI's framework governing fund raising via debt securities by large corporates.
CREDIT RATINGS & ANALYST CALLS
8CARE Ratings confirms CARE A-; stable on Wind Five Renergy's Rs. 168.37 crore bank facilities amid Adani Green co-obligor structure CARE Ratings has issued a final rating confirmation of 'CARE A-; Stable' on the long-term bank facilities worth Rs. 168.37 crore (reduced from Rs. 174.51 crore) of Wind Five Renergy Limited (WFRL), a subsidiary of Adani Green Energy Limited (AGEL). The rating draws strength from an inter-company agreement forming the 'Adani Wind Co-Obligor Group', enabling free fungibility of cash flows, as disclosed in the April 28, 2026 press release.
8ICRA revises credit ratings on Ola Electric subsidiaries OET and OCT; Ola Electric (NSE: OLAELEC) discloses under SEBI reg. 30 Ola Electric Mobility Limited (NSE: OLAELEC, BSE: 544225) has intimated stock exchanges that ICRA Limited revised and/or reaffirmed credit ratings on instruments of two material wholly-owned subsidiaries - Ola Electric Technologies Private Limited (OET) and Ola Cell Technologies Private Limited (OCT) - on April 28, 2026. The disclosure is made in compliance with Regulation 30 of SEBI Listing Regulations and adds fresh scrutiny to Ola Electric's debt profile.
8Coal India (COAL IN) Q4FY26 earnings beat; rating upgraded to 'accumulate', target price raised to Rs. 515 from Rs. 436 Coal India Limited (NSE: COAL) delivered a stronger-than-expected Q4FY26 performance, with EBITDA (ex-OBR) of INR 123 billion - up 8% YoY - beating analyst estimates on the back of cost efficiencies and a higher e-auction sales mix. Following the results, the rating was upgraded from 'HOLD' to 'ACCUMULATE' with a revised target price of Rs. 515 (against CMP Rs. 467), while FY27/28E EBITDA estimates were raised by ~2%, with the stock now valued at 5.5x FY28E.
8Coal India (Coal) maintains 'sell' rating; FY26 volumes fall to 745 mn tons (-2% YoY), realization drops to Rs. 1,598/ton A separate analyst note on Coal India Limited (NSE: COAL, CMP: Rs. 453) maintains a 'SELL' rating with a revised fair value of Rs. 370 (from Rs. 355 earlier), citing a weak Q4FY26 with volumes of 199 million tons (-1% YoY) and realization of Rs. 1,598/ton (-1% YoY). FY26 full-year volumes stood at 745 million tons (-2% YoY) with a 1% decline in average realization, and the company may absorb higher fuel costs due to the war scenario, capping near-term earnings growth.Details
8CERC issues order in Tata Power's petition 179/MP/2023 on Section 11(2) power supply compensation for March–June 2023 The Central Electricity Regulatory Commission (CERC) issued its order on April 29, 2026 in Petition No. 179/MP/2023 (on remand), filed by Tata Power Company Limited. The case involves determination of compensation for emergency power supply directed between March 15, 2023 and June 16, 2023 under Section 11(2) of the Electricity Act, 2003. Key respondents include Gujarat Urja Vikas Nigam Limited, Punjab State Power Corporation Limited, Maharashtra State Electricity Distribution Company Limited, and Ajmer Vidyut Vitaran Nigam Limited, in a 49-page order.
8CERC releases staff paper seeking public comments on introduction of capacity market for electricity in India The Central Electricity Regulatory Commission (CERC), New Delhi, issued a Public Notice dated April 29, 2026 (No. RA-14027(12)/1/2026-CERC) releasing a Staff Paper on 'Capacity Market for Electricity in India.' The paper explores how a capacity market — as opposed to India's current long-term PPA-based capacity contracting — could ensure adequate power system capacity by separately remunerating capacity holders. CERC references established capacity market models from the US, UK, and Europe, noting India's existing PPAs as inherent capacity contracts that guarantee full fixed cost recovery based on availability.
8MERC reserves orders in 5 high-stakes power disputes on April 28, 2026 — MSEDCL, Adani Power, and RattanIndia face verdicts The Maharashtra Electricity Regulatory Commission (MERC) reserved orders in 5 cases after an e-hearing on April 28, 2026, involving major utilities including MSEDCL, Adani Power Limited, RattanIndia Power Limited (RPL), and M/s Shriniwas Engineering Auto Components Pvt. Ltd. Parties in 4 of the 5 cases (Case Nos. 5, 8, 34, and 4 of 2026) have been given a 10-day window to file additional written submissions before final orders are passed.
8MERC gives 15-day deadline to resolve billing dispute between Pune consumer and MSEDCL in case no. 15 of 2026 In Case No. 15 of 2026, MERC ordered petitioner Mr. Sankalpa Shrihari Garud and MSEDCL to jointly examine and resolve outstanding computational issues — including adjustment of arrears up to March 2022 and interest calculation — within 15 days, with outcome submission due within a week thereafter. MSEDCL claimed full compliance with the earlier CGRF Pune Order dated May 20, 2024, while the petitioner alleged non-adjustment of arrears since the March 2022 disconnection date.
8MERC grants NHAI two weeks to file rejoinder in supervision charges dispute with MSETCL in case no. 22 of 2025 In Case No. 22 of 2025, MERC on April 28, 2026, granted a two-week extension to the National Highways Authority of India (NHAI) PIU Thane to file its rejoinder to MSETCL's reply. The petition seeks directions to levy supervision charges at 2.5% for shifting of transmission lines as per CEA guidelines dated March 10, 2023. MSETCL's counsel noted the petition effectively seeks amendment of applicable regulations on supervision charges, warranting a proper procedural process.
8MERC to issue notices to all parties in Adani Electricity Mumbai's case against MSLDC DSM supplementary bills In Case No. 16 of 2025, Adani Electricity Mumbai Limited-Distribution (AEML-D) is challenging supplementary bills issued by the Maharashtra State Load Despatch Centre (MSLDC) under MERC DSM Regulations, 2019. On April 28, 2026, MERC heard both parties and is set to issue notices to all concerned stakeholders, as the petitioner argued the DSM pool deficit supplementary billing requires a detailed regulatory dispensation. MSLDC stated it had formulated a Draft Procedure for raising DSM supplementary bills.
8Tata Power Renewable Energy seeks urgent hearing at MERC for SCOD extension in case no. 60 of 2026 Tata Power Renewable Energy Limited (TPREL) filed IA No. 52 of 2026 before MERC seeking urgent listing and hearing in Case No. 60 of 2026 (60/AD/2026), which is a petition for extension of Scheduled Commercial Operation Date (SCOD) and consequential reliefs. The respondent in this case is Tata Power Company Limited-Distribution (TPC-D). This was heard before MERC on April 28, 2026.
STATE COMMISSIONS (GERC, TNERC, PSERC, UPERC, BERC, KSERC)
8GERC hears Juniper Green Kite's plea for force majeure extension on 70 MW Gujarat wind project under February 2024 PPA M/s Juniper Green Kite Private Limited has filed Petition No. 2532 of 2025 before the Gujarat Electricity Regulatory Commission (GERC), seeking extension of the Scheduled Commercial Operation Date for its 70 MW wind power project in Gujarat under the Power Purchase Agreement dated February 8, 2024 with Gujarat Urja Vikas Nigam Limited (GUVNL). The petitioner cites Force Majeure events affecting project implementation. An interlocutory application (IA No. 76 of 2025) was also filed seeking interim relief against GUVNL.
8GERC reserves order in GUVNL's petition for 335 MW/670 MWh battery storage tariff adoption under Phase-VIII competitive bidding The Gujarat Electricity Regulatory Commission (GERC) reserved its order in Petition No. 2641 of 2026 filed by Gujarat Urja Vikas Nigam Limited (GUVNL) on April 28, 2026, seeking tariff adoption under a Competitive Bidding Process (RfS No. GUVNL/BESS/Phase VIII dated December 29, 2025) for 335 MW/670 MWh standalone Battery Energy Storage Systems (BESS) in Gujarat with Viability Gap Funding through PSDF. Respondents — M/s Advait Energy Transition Limited, M/s Equentia Natural Resources DMCC, and M/s Sub Drops Energia Pvt. Limited — were directed to file submissions within 7 days.
8TNERC lists 8 cases for April 30, 2026 hearing including TNPDCL order, TANTRANSCO tariff amendment, and APTEL remand The Tamil Nadu Electricity Regulatory Commission (TNERC) published Cause List No. 30/2026 for April 30, 2026 (forenoon), listing 8 cases. Key cases include M.P. No. 14 of 2026 and P.P.A.P. No. 6 of 2026 by Tamil Nadu Power Distribution Corporation Limited (TNPDCL) for orders, R.A. No. 2 of 2026 by TNPDCL/TNGECL on bagasse co-generation plant tariff (remanded by APTEL from Appeal No. 375 of 2017, order dated December 22, 2025), and M.P. No. 81 of 2025 by TANTRANSCO for amending Regulation 59 of TNERC Tariff Regulations, 2005.
8TNERC grants special relaxation of 5-month gestation period for medium-term open access to intra-state generators The Tamil Nadu Electricity Regulatory Commission (TNERC) in M.P. No. 13 of 2026 (order dated April 28, 2026), granted a special, non-precedential relaxation of the 5-month gestation period under Clause 14.2(e) of TNERC Regulations, 2014 for commencement of Medium-Term Open Access (MTOA) to intra-state generators. The petitioners — Chief Engineer (Grid Operation) TANTRANSCO and Chief Engineer (PPP) TNPDCL — obtained this order strictly for the specific power procurement arrangement (APP) in question. The State Load Despatch Centre (SLDC) is directed to follow grid security and Merit Order Dispatch principles.
8TNERC releases draft SLDC functions and accountability regulations 2026 for public comment by May 14, 2026 The Tamil Nadu Electricity Regulatory Commission (TNERC), Guindy, Chennai, published draft 'Tamil Nadu Electricity Regulatory Commission State Load Dispatch Centre (Functions and Accountability) Regulations, 2026' on April 29, 2026, inviting comments and suggestions from stakeholders on or before May 14, 2026. Framed under Sections 32(3), 33(1), 86(1)(h), (e), (i), (k), and 181 of the Electricity Act, 2003, the regulations define SLDC's functions, accountability framework, and reporting obligations, distinct from those of the State Transmission Utility.
8PSERC issues order in petition 29 of 2026 by M/s Chadha Sugar against Rs. 7.14 crore fixed charges demand by PSPCL The Punjab State Electricity Regulatory Commission (PSERC) issued its order dated April 29, 2026 in Petition No. 29 of 2026, filed by M/s Chadha Sugar and Industries Ltd., New Delhi, challenging PSPCL's demand of Rs. 7,13,99,835 (comprising Rs. 5.93 crore principal and Rs. 1.20 crore interest) on account of fixed charges for the period from April 2019 to June 2025. The petition seeks quashing of letters dated July 21, 2025 and subsequent notices issued by the Assistant Executive Engineer, DS Sub Division, PSPCL, Sh. Hargobindpur.
8PSERC admits PSPCL's petition for approving 4 MW intra-state solar power from Punjab Water Resources Department at Rs. 2.97/kWh for 25 years The Punjab State Electricity Regulatory Commission (PSERC) on April 29, 2026 admitted Petition No. 30 of 2026 filed by Punjab State Power Corporation Limited (PSPCL), seeking approval for procurement of 4 MW intra-state solar power from a project of the Water Resources Department, Punjab, at a tariff of Rs. 2.97 per kWh for a period of 25 years, under PSERC (Framework for Resource Adequacy) Regulations, 2024. PSPCL justified the procurement on grounds of necessity, reasonableness of tariff, and regulatory compliance.
8UPERC issues order in petition 2293 of 2025 by South East U.P. Power Transmission Co. on escalable transmission charge methodology The Uttar Pradesh Electricity Regulatory Commission (UPERC) issued its order in Petition No. 2293 of 2025 on April 29, 2026, filed by South East U.P. Power Transmission Company Limited (Plot No. 409, 4th Floor, Shalimar Titanium, Vibhuti Khand, Gomti Nagar, Lucknow). The petition under Sections 86(1)(c) and (f) of the Electricity Act, 2003 seeks directions on interpretation of escalable transmission charges under Schedules 5 and 7 of the Transmission Service Agreement dated January 20, 2012. Key respondents include U.P. Power Transmission Corporation Limited and multiple Vidyut Vitran Nigams.
8Bihar Electricity Regulatory Commission invites applications for part-time advisor (tariff & regulatory work) by May 21, 2026 The Bihar Electricity Regulatory Commission (BERC), Patna, issued Advertisement Notice No. 04 dated April 29, 2026 inviting applications for the part-time position of Advisor (Tariff and Regulatory Work) under BERC (Appointment of Consultants) Regulations, 2013. The last date for submission is May 21, 2026 by 5:30 PM. Detailed eligibility criteria and qualification requirements are available on BERC's official website (www.berc.co.in).
8KSEBL seeks 3-year extension of PPA with NTPC's Rajiv Gandhi combined cycle power project, Kayamkulam from March 2025 Kerala State Electricity Board Limited (KSEBL) filed a petition under Regulation 77 of KSERC Tariff Regulations, 2021 seeking approval for a 3-year extension of its Power Purchase Agreement with NTPC Limited's Rajiv Gandhi Combined Cycle Power Project (RGCCPP), Kayamkulam, from March 1, 2025. KSEBL is the designated distribution licensee in Kerala and an integrated state public sector power utility. Respondents are NTPC Limited (a Maharatna Central PSU) and the Government of Kerala's Additional Chief Secretary (Power).Details
For reference purposes the website carries here the following tenders: 8Tender for establishment of 765kV substation Details 8Tender for construction of platforms Details 8Tender for insulator replacement, dead end replacement and rectification of SD nature defects in 400kV line Details 8Tender for supply of industrial ethernet switches Details 8Tender for repair of road from CW pump house Details 8Tender for annual running contract for operation and maintenance of electrical distribution system Details 8Tender for supply of 10 MVA transformer Details 8Tender for supply of various types of idlers Details 8Tender for construction of 132 kV sub station Details 8Tender for erection 11 kV feeder Details 8Tender for monitoring of electrical erection activities Details 8Tender for supply installation and implementation of project information management system Details 8Tender for procurement of grinding rolls and bull ring segments for bowl mill XRP 883 Details 8Tender for monsoon preparedness in St 2 dyke Details 8Tender for monsoon preparedness in stage-I ash dyke Details 8Tender for hydrogen generation plant Details 8Tender for supply of manual pole pruner Details 8Tender for erection of esti for bifurcation 33 kV line feeder Details 8Tender for renovation of cotrol room, cable trench and yard at 33/11 kV S/s Details 8Tender for construction of control room, chain-link, mesh fencing, cable trench, earth pit networking Details 8Tender for procurement installation and commissioning of PSA N2 gas generator Details 8Tender for procurement of 125 ton capacity HIP LP-1, and LP-2 rotor stand along Details 8Tender for procurement of spares along with work for restoration of air drier system installed Details 8Tender for procurement of bearing housing along with white metal bearing Details 8Tender for work contract for repair of spares pump casing, impeller casing etc. of CW pump Details 8Tender for procurement of spares for condensate extraction pump installed Details 8Tender for repair of damages in link canal Details 8Tender for Re-carpeting of various Details 8Tender for supply of line materials under electric supply Details 8Tender for supply of line materials Details 8Tender for supply of line materials under electric supply Details 8Tender for procurement of electrical items Details 8Tender for job work of radiography of boiler tube weld joints Details 8Tender for supply of various consumable items Details 8Tender for work of overhauling, servicing, repairing of ID / FD / PA fan & it’s connecting system Details 8Tender for rate contract for (service/repairing/testing) of 12 kV SF6 CB/VCB installed Details 8Tender for capital repair of boiler feed pumps of TPP and CPP turbine. Details 8Tender for balance work of construction of toe drain with collection sump Details 8Tender for providing and fixing of roof cover for sedimentation tank of pump house Details 8Tender for work of laying 40 mm thick gravel above the ground in 400kV, 33kV switchyard Details 8Tender for restoration-protection work of dumping Details 8Tender for special repair of spillway piers with class R-4 cement based mortar Details 8Tender for Bi-annual rate contract for the work of transportation of any sub-station / line materials Details 8Tender for Bi-annual rate contract for 66kV undergound cable fault Details 8Tender for comprehensive annual maintenance contract of VRF AC system Details 8Tender for comprehensive annual maintenance of VRF-type HVAC air conditioner system installed Details 8Tender for procurement of 60W plus/minus 5W wellglass LED, 100W LED and 20W LED tube rod, complete fitting Details 8Tender for requirement of pressure transmitters and temperature transmitters installed Details 8Tender for work for complete cleaning of air ducting system and air balancing work of air conditioning system Details 8Tender for supply, ETC of battery banks and buyback of existing battery banks Details 8Tender for requirement of RTD and TC installed Details 8Tender for procurement of spares of elevators installed in boiler Details 8Tender for supply of CERM gear box for ESP Details 8Tender for construction of foundation for one additional caustic soda bulk storage tank Details 8Tender for annual contract for day to day R & M of civil works Details 8Tender for Bi-annual rate contract for supply of distilled water for hot line Details 8Tender for constructing 1175 m HT ABC Details 8Design, manufacturing, supply, installation, testing and commissioning of digital governor system with valve table assembly and auto synchronizer for the 1 X 16 MW PLBE power house Details 8Tender for providing, supplying and fixing in position rooftop rainwater harvesting module Details 8Tender for outsourcing work of erection, testing and commissioning of additional 3 no. 20 MVA power transformers Details 8Tender for PCC flooring with gravel spreading and drainage system Details 8Tender for procurement of spares for ID fans Details 8Tender for procurement of M.S. pipe of size 200 NB and 250 NB installed Details 8Tender for construction of around ERS yard at 220kV s/s Details 8Tender for construction of 132kV s/s Details 8Design, manufacturing, testing & delivery of 15 kV NCTs of assorted ratio Details 8Tender for providing and fixing of clamp and connector, isolator various spares Details 8Tender for work for replacement of perished/ rusted tower stubs of 132 kV line Details 8Tender for work of maintenance / servicing of 220/132/33 kV circuit breakers and other associated works Details 8Tender for strengthening of switchyard by providing spare clamp items at 132kV substations Details 8Tender for work of supply and erection of 132 kV CT/CVT junction box and surge counter at 132 kV substation Details 8Tender for work of supply and filling of SF6 gas at various substations Details 8Tender for preventive maintenance, overhauling /servicing and testing of circuit breakers at 132 kV substation Details 8Tender for up keeping of 132 kV substation Details 8Tender for safety purpose of C panel Details 8Tender for work for the installation of MCCBs and ACBs on 63 kVA, 100 kVA, 250 kVA, and 400 kVA transformers Details 8Tender for replacement and maintenance of DTR Details 8Tender for work for shifting of LT/HT line Details 8Tender for work of installation of 11/0.4 kV 990 KVA CSS Details 8Tender for annual maintenance of lines, DTRs, etc and redressal of consumer complaints along Details 8Tender for annual maintenance of lines, DTRs, etc Details 8Tender for annual maintenance of lines, DTRs, etc and redressal of consumer complaints along with other works Details 8Tender for annual maintenance of lines, DTRs, etc Details 8Tender for Bi annual rate of contract for work of fault finding of various 66kV class under ground XLPE/ aluminium corrugated 300/630 Sq mm faulty cable Details 8Tender for supply of 245kV potential transformer Details 8Tender for supply and application of mineral wool insulation on various pipes Details 8Tender for work of providing & construction of revetment wall for various tower Details 8Tender for work of provision of parallel SCADA FO (fiber optic) ring for redundancy at 400kV S/stn Details 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50 MVA, 132- 110/33 kV T/F Details 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 25 MVA, 132- 110/33 kV T/F Details 8Tender for work of overhauling, servicing & supply of spares of 400kV & 220kV various types of SF6 circuit breaker Details 8Tender for replacement of RCC structure by lattice type structure of various 400/220 kV equipments Details 8Tender for supply of 02 Nos. of 5kV insulation tester with accessories Details 8Tender for supply of MS hot dip galvanized grills for various Details 8Tender for work of purification/filtration of lubrication oil for T-G auxiliaries & hydraulic fluid Details 8Design, supply, fabrication, and erection work of 10,000 M3(cubic meter) capacity Details 8Tender for supply of current transformer(CT) for PA & ID motor during motor capacity Details 8Tender for work of repairing & rewinding of ESP rectifier transformers Details 8Tender for manufacture, supply, erection, testing & commissioning of refrigerated type hydrogen dryer system with associated auxiliaries Details 8Tender for supply of various fasteners for coal mill Details You can also click onTenders for more For reference purposes the website carries here the following newsclips: 8Karnataka High Court Grants Relief To Solar, Wind Players On Deviation Penalties Details 8Enviro Infra Acquires Wind Firm Suyog Urja for Rs 311 Crore, Boosts Renewables Details 8India accelerates green energy push, targets 500 GW capacity by 2030: Pralhad Joshi Details 8Nearly 1/3 of peak demand of 256 GW met via renewable energy: Pralhad Joshi Details 8India Signs Historic Coal Mine Agreements With Underground Gasification Provisions For First Time Details 8Ministry of Coal Approves 793 Crore Coal-to-Acetic Acid Project Under Rs 8,500 Crore Gasification Scheme in Gadchiroli Details 8Electrification can slash 1.2 billion tonne CO, cut energy 22%, save 7.9 lakh lives a year Details 8Green energy: FIIs bet big on three stocks; know details of each share Details 8Why India needs to develop concentrated solar thermal power plants Details 8Solar Cell Mandate Faces Readiness Test As Industry Flags Supply, Cost Risks Details 8Loom Solar’s Learn Solar Initiative Crosses 50,000 Participants Details 8India Becomes World’s Second-Largest Solar Market Details 8This solar stock just smashed estimates; Jefferies Sees 36% upside as order book hits 9.4GW Details 8INOX Solar Americas Acquires Boviet Solar's US Module Assets Details 8India emerges as world’s 2nd-largest solar market, green energy momentum accelerates: Experts Details 8Is India’s power system ready for the next phase of demand Details 8India hits milestone: Renewable energy ramps — 5 years ahead of 2030 Paris Agreement target Details 8India Mobilises All Power Sources As Electricity Demand Hits Record 256.1 GW Details 8India Records All-Time High Peak Power Demand of 256.1 GW, Meets Supply Without Shortage Details 8India meets record 256.1 GW peak power demand without shortage, sets new benchmark Details 8Coal India up 4%; surpasses Vedanta, HAL, Power Grid in market cap ranking Details 8Adani Group Targets 2,000 GW Energy Surge Amid Debt Concerns Details 8Is Coal India Stock Headed Towards Rs 600 Details 8REC Limited Signs Tripartite Agreement in Bihar for Smart Meter Verification Under RDSS to Boost Transparency Details 8Reconsider proposed joint venture in power sector in Ladakh: Religious bodies, stakeholders Details 8Lineman’s death during streetlight work in Tinsukia raises safety concerns in Assam power sector Details 8Best Battery Stocks in India 2026 Details 8India among world’s top countries in meeting climate targets: Piyush Goyal Details 8India meets nearly one-third of peak power demand through renewables: Minister Pralhad Joshi Details 8CBI Books Pvt Company, Directors In Rs 30 Crore Indian Bank Fraud Case Details You can also click on Newsclips for moreDetails
8A Rs 117.04 crore transmission package combining 220 kV cable systems and monopole works has attracted six bidders after an extended timeline. 8The scope goes beyond standard supply, embedding survey, XLPE execution and structural integration risks.Details
8Hydro EPC bid window shifts again as 120 MW package sees timeline reset and risk recalibration A 120 MW hydro electromechanical EPC package has seen its bid deadline pushed into May after multiple tender-stage adjustments. The cycle reflects deeper bidder caution following commercial tweaks and schedule drift.
8Smart metering DBFOOT push faces timeline drift as AMI tender struggles to hold bidder momentum A large-scale AMI rollout under the DBFOOT model is seeing repeated deadline extensions, signalling bidder unease beyond surface-level delays. The structure promises scale but raises execution and payment security questions. 8Thermal FGD package sees fresh timeline reset as EPC structure keeps bidder filters tight A semi-dry FGD EPC package at a large coal-based unit has been rescheduled again, extending bidder timelines without easing core qualification thresholds. The turnkey scope, liquidity exposure and collaborator-linked eligibility continue to shape participation strategy. 8Thermal WTP EPC package sees timeline extension as liability-heavy structure keeps bidders cautious A large water treatment EPC package linked to a 2×660 MW thermal project has received a bid deadline extension, but without any dilution in core commercial terms. The reverse auction mechanism, performance obligations and risk allocation remain intact. 8Transmission advisory bids see extension as renewable evacuation push sharpens consultant filters Independent engineer bids linked to renewable evacuation transmission packages have been extended, offering more time without easing qualification thresholds. The advisory scope remains technically demanding, limiting the serious contender pool. 8Hydel R&M package sees scope reset and timeline extension as risk allocation shifts beneath Rs 225 crore tender A Rs 225 crore hydel renovation package has been extended after a calibrated scope revision that subtly rebalances contractor risk. While core performance obligations remain intact, select site-linked exposures appear to have been eased. 8Massive bid security and 6 GW HVDC spine signal a new scale filter in renewable evacuation tenders A 6 GW HVDC-linked transmission package with a Rs 286 crore bid bond is setting a new benchmark for entry barriers in RE evacuation. Beyond the headline scale, the tender structure leans heavily on financial strength and execution depth. 8REZ transmission package tweaks specs as tighter transformer norms meet relaxed STATCOM efficiency filters A late-stage amendment in a renewable evacuation transmission tender recalibrates technical risk by tightening transformer specifications while easing STATCOM efficiency thresholds. The dual shift balances reliability focus with cost flexibility for bidders.Details
8NLDC records 2.5% day-ahead MAPE for 27 April 2026; real-time energy consumption error near zero at 0.1% Grid Controller of India's National Load Despatch Centre reported that on 27 April 2026, the day-ahead MAPE for demand met stood at 2.5% - marginally higher than the prior day - while the real-time error came in at 0.7%; most strikingly, real-time energy consumption forecasting achieved an extraordinarily low error of 0.1%, one of the best intraday accuracy figures in recent reporting, as required by IEGC 2023 Article 31.2(i), reflecting NLDC's strengthening real-time balancing capabilities. 8Eastern region day-ahead forecast error hits 4.49% MAPE on 27 April 2026; intraday real-time error improves to 1.86% - 1,725 MW under-forecast at midnight The Eastern Regional Forecasting Error report for 27 April 2026 shows a day-ahead MAPE of 4.49% and RMSE of 5.52% - indicating significant forecasting inaccuracy in the day-ahead timeframe; intraday forecasting achieved better accuracy at MAPE 1.86% and RMSE 3.32%; block-level data reveals that actual demand at midnight (00:00–00:15 hrs) was 31,105.5 MW versus a day-ahead forecast of just 28,434 MW - an under-forecast error of 1,725 MW. 8NLDC system reliability report 28 April 2026: all inter-regional corridors show zero ATC and N-1 violations; 765 kV voltage at Bhadla deviates 0.42% of day Grid Controller of India's National Load Despatch Centre's system reliability indices report for 28 April 2026 confirms that all five monitored inter-regional corridors - WR-NR, ER-NR, Import of NR, NEW-SR and NER Import - recorded zero ATC violations and zero N-1 criterion violations throughout the entire day; however, the voltage profile section reveals that at the 765 kV Bhadla substation (Rajasthan), voltage exceeded the upper IEGC limit for 0.42% of the day, while Bhadla-II exceeded it for 2.99%. 8NLDC SCUC generator schedule for 29 April 2026: Rihand 3 committed at 507 MW; Singrauli at 932 MW with ECR of 163.9–301 paise/kWh Grid Controller of India's National Load Despatch Centre published the SCUC (security constrained unit commitment) generator schedule table for 29 April 2026, published on D-1 basis on 28 April 2026 at 15:00 hrs; the schedule commits Rihand Stage 3 at 507.39 MW (ECR 163.9 paise/kWh), Singrauli TPS at 932.28 MW (ECR 199.9), Vindhyachal STPS stages 1–5 ranging from 128 to 311 MW (ECR 205–211 paise/kWh), and North Karanpura STPS at 639 MW (ECR 211.8), all marked SCUCYN = YES. 8SRLDC generation report 28 April 2026: Tamil Nadu demand at 20,293 MW; Vijayawada TPS peaks at 2,065 MW; Karnataka solar averages 1,360 MW The southern region's generation report for 28 April 2026 reveals Tamil Nadu as the highest-demand state at 20,293 MW, powered by Ramagundam NTPC (1,980 MW average), KUDGI (1,577 MW), and Kudankulam nuclear (33.57 MU); Andhra Pradesh's Vijayawada TPS peaked at 2,065 MW gross (45.86 MU net); Karnataka's Bellary TPS generated 35.97 MU and Karnataka solar averaged 1,360 MW - the highest renewable contribution among southern states on the day. 8CEA all-India capacity summary 26 April 2026: 3,09,716 MW total monitored; western region leads with 90,149 MW online; 13,299 MW under maintenance in north The Central Electricity Authority's Sub-Report 3 all-India capacity summary for 26 April 2026 shows total national monitored capacity at 3,09,716.29 MW; the western region had the highest monitored capacity at 1,04,702 MW with 90,149 MW online; the northern region had 81,696 MW monitored with 68,397 MW online - meaning 13,299 MW was under planned, forced or other maintenance; the southern region had 59,554 MW online of 70,967 MW monitored. 8CEA capacity utilisation report 26 April 2026: India's coal plants run at 91.46% of online capacity; gas units at 115% of online - total monitored 3,09,716 MW The Central Electricity Authority's Sub-Report 16 on capacity utilisation for 26 April 2026 reveals that coal plants generated 202,057 MW gross - 91.46% of the 201,038 MW online capacity; gas and liquid fuel plants, with only 9,348 MW online out of 20,122 MW monitored capacity, ran at 115.13% of their online capacity - an unusually high utilisation rate for gas, reflecting intensive deployment of every available gas MW; nuclear ran at 98.07% of online capacity. 8CEA NTPC performance report 26 April 2026: southern NTPC beats target by 11.67 MU; eastern NTPC falls short by 34.05 MU - wide regional variation The Central Electricity Authority's Sub-Report 8 on NTPC station performance for 26 April 2026 shows strong southern region NTPC output at 160.85 MU - 11.67 MU above the 149.18 MU programme (7.8% over); eastern region NTPC stations underperformed significantly, generating 268.11 MU against a 302.16 MU programme - a shortfall of 34.05 MU (-11.3%); NTPC's total national monitored capacity of approximately 56,867 MW makes its daily generation profile a pivotal factor in India's national energy balance. 8NLDC all-India angular spread report 28 April 2026: grid voltage angles at Agra, Chandrapur, Gazuwaka and 13 other key substations tracked w.r.t. Vindhyachal Grid Controller of India's National Load Despatch Centre published the all-India angular spread report for 28 April 2026, tracking bus voltage angle deviations at 16 key substations - including Agra, Alipurduar, Balipara, Bongaigaon, Chandrapur, Gazuwaka, Hosur, Kalwa, Korba, Moga, Unnao, Bhuj, Bawana and URI - all measured with reference to Vindhyachal; angular spread values ranged from around +10 degrees to -70 degrees during the 24-hour period, reflecting inter-regional power flows and grid stress during peak renewable generation. 8PSPCL sponsors 3 senior officers to 7th Annual India Power & Renewable Conference 2026 in Delhi at Rs. 1,19,475 fee Punjab State Power Corporation Limited's Principal/Training Wing, Patiala, in an office order dated 28 April 2026, has sanctioned the deputation of three officers - Engineer-in-Chief Inderjit Singh (NRSE & Thermal-D), Dy. Chief Engineer Mohit Gupta (SE/NRSE) and Addl. SE Sumit Sharma (Sr. XEN/Solar-2) - to attend a two-day residential training programme "7th Annual India Power & Renewable Conference 2026" at Hotel Hyatt Regency, New Delhi on 4-5 June 2026; the participation fee for the three delegates is Rs. 1,19,475, plus TA/DA. 8NLDC allocates Punjab round-the-clock import ATC of 10,700 MW for April 2027 with 5,203 MW T-GNA margin The National Load Despatch Centre, in Revision 0 issued on 28.03.2026, has approved Punjab's 24-hour total transfer capability of 11,200 MW for April 2027 with a reliability margin of 500 MW, leaving an available transfer capability of 10,700 MW; against an approved general network access of 5,497 MW, the temporary GNA margin works out to 5,203 MW, with N-1 contingencies of 400/220 kV ICTs at Rajpura, Dhanasu and Muktsar listed as limiting constraints. 8CEA station-wise generation report 26 April 2026: northern region's April-to-date actual at 27,138 MU vs 30,437 MU programme; Delhi's Pragati CCGT-III overperforms at 19.48 MU CEA's comprehensive station-wise, unit-wise Sub-Report 2 for 26 April 2026 tracks generation at individual power station and unit level across all five regional grids; in the northern region, accumulated actual generation from April 1 stood at 27,138.41 MU against a programme of 30,437.92 MU - a 10.8% shortfall; Delhi's Pragati CCGT-III (1,500 MW) generated 19.48 MU on the day - nearly triple its 7.17 MU programme; Haryana's Yamuna Nagar Unit 2 (300 MW) remained under planned annual boiler overhaul. 8Websol Energy posts audio recording of Q4 FY26 earnings call held on 28 April 2026 Kolkata-based Websol Energy System Limited (BSE: 517498, NSE: WEBELSOLAR; ISIN: INE855C01023) has informed exchanges on 28 April 2026 that the audio recording of its analysts/institutional investors meeting/earnings call held on 28 April 2026 to discuss the audited standalone & consolidated financial results for the quarter and financial year ended 31 March 2026 is now available on its website under Investors Relation > Financial Results > Earnings Call & Presentation. 8NLDC pegs S1-(S2&S3) transfer capability at 10,850 MW for April 2027; S3 import capped at 4,455 MW The National Load Despatch Centre, New Delhi, in Revision 0 issued 24/04/2026, has approved a total transfer capability of 11,300 MW between S1 (Andhra Pradesh, Telangana, Karnataka and Goa-SR) and S2&S3 (Tamil Nadu, Pondicherry and Kerala) for April 2027 with reliability margin of 450 MW (ATC 10,850 MW; net GNA 5,574 MW); S3 import capability is fixed at 4,575 MW TTC and 4,455 MW ATC, with limiting constraints including N-1 violations at 400/230 kV Salem, Pugalur, Kalivandapattu and NNTPP substations. 8IEX Green DAM weekly summary 22–29 April 2026: 22 April clears 2,846 MWh total at Rs. 6,693/MWh; 28 April at Rs. 10,000/MWh The IEX Green Day-Ahead Market weekly summary from 22 to 29 April 2026 shows significant price variation; on 22 April, 2,846.44 MWh was cleared at a weighted MCP of Rs. 6,693.52/MWh; by 28 April, the MCP reached Rs. 10,000/MWh - the exchange ceiling - reflecting extreme peak-summer demand pressure; solar-specific MCV peaked at 2,070.26 MWh on 22 April with a non-solar contribution of 7,571.97 MWh; the week demonstrates the growing role of India's green day-ahead market in channelling renewable energy while also showing its vulnerability to price-cap conditions during tight supply periods.Details
8Waa Solar Limited adopts new logo and rolls out two new investor email IDs effective 28 April 2026 Vadodara-based Waa Solar Limited (BSE: WAA, Scrip Code 541445; CIN: L40106GJ2009PLC076764) has informed BSE that it has designated investors@waasolar.in for investor grievances and replaced info@waasolar.org with info@waasolar.in for general communication; the company has also adopted a new corporate logo with immediate effect, while confirming no change in its business activities. 8BGR Energy Systems enters CIRP after NCLT Amaravati order; public announcement issued on 24 April 2026 Chennai-headquartered BGR Energy Systems Limited (NSE: BGRENERGY, BSE: 532930) has informed the exchanges that, pursuant to an order dated 17 April 2026 of the Hon'ble NCLT Amaravati Bench under Section 13 of the IBC, 2016, a public announcement under Section 15 of the IBC was made on 24 April 2026 in Business Standard (English), Prajasakti (Telugu) and Madras Mani (Tamil); the company is now undergoing the corporate insolvency resolution process. 8Refex Renewables elevates Rajeev Vaze to COO of CBG business; payroll shifts to wholly-owned subsidiary RSSL from 1 May 2026 Chennai-based Refex Renewables & Infrastructure Limited (BSE: 531260) has announced under SEBI Reg. 30 that Mr. Rajeev Vaze, currently Vice-President and Head – Supply Chain Management, will be re-designated Vice-President and Chief Operating Officer of the Compressed Bio-Gas (CBG) business with effect from 1 May 2026; his payroll moves to wholly-owned subsidiary Refex Sustainability Solutions Limited, the holding company for the CBG vertical. 8Bright Solar Limited reports fire at registered office on 27 April 2026; no casualties, operations temporarily suspended Ahmedabad-based Bright Solar Limited (NSE Symbol: BRIGHT; CIN: L51109GJ2010PLC060377), an EPC contractor and solar manufacturer, has informed NSE under SEBI Reg. 30 that a fire incident occurred on the morning of 27 April 2026 at its registered office building; the fire was controlled in time with no casualties or injuries to life, although operations at the said office have been temporarily suspended pending assessment of the cause.
POWER EXCHANGE & MARKET OPERATIONS
8Hindustan Power Exchange lists reverse auction No. HPX/28042026/00961 for Power Company of Karnataka - 200 MW round-the-clock block Hindustan Power Exchange Limited (formerly Pranurja Solutions Ltd; CIN: U74999MH2018PLC308448), via Circular HPX_RA_00932 dated 28 April 2026, has notified members of a single-side reverse auction by Power Company of Karnataka Ltd for the delivery period 02-31 May 2026; bid quantities are 200 MW for the 24-hour band, plus 100 MW each in the 05:00-09:00 and 18:00-22:00 windows, with auction submission on 29 April 2026 between 14:00-16:00 hrs. 8WRPC ABT-based DSM account shows Rs. 24.25 crore net receivable for western region in 6-12 April 2026 settlement Western Regional Power Committee (WRPC), Mumbai, has released the DSM settlement statement for the week 06.04.2026 to 12.04.2026 under CERC DSM Regulations, 2024; inter-regional charges totalled Rs. 162.27 crore payable and Rs. 186.53 crore receivable, leaving a net Rs. 24.25 crore receivable, with WR-SR alone accounting for Rs. 164.65 crore receivable while WR-ER (Rs. 74.47 crore) and WR-NR (Rs. 65.91 crore) were payable. 8WRPC western region reactive energy account posts Rs. 49.29 lakh net settlement for 13-19 April 2026 among 11 drawee states The Western Regional Power Committee has issued the western region reactive account (VARh) for the week 13.04.2026 to 19.04.2026 covering 11 drawee entities including Maharashtra (Rs. 28.59 lakh receivable from pool), Madhya Pradesh (Rs. 10.66 lakh receivable) and Gujarat (Rs. 5,805 payable to pool); generating stations contributed Rs. 1.21 crore receivable from pool, with Gadarwara alone receiving Rs. 43.94 lakh. 8WRPC TRAS account records Rs. 4.30 crore net payable by providers in shortfall condition for 13-19 April 2026 WRPC's TRAS-III settlement account for 13.04.2026 to 19.04.2026 shows total scheduled energy of 13,467.43 MWh under TRAS-Up against 32,796.77 MWh under shortfall TRAS-Down, with net charges of Rs. 4.30 crore payable by TRAS providers; Solapur faced the largest shortfall at Rs. 2.76 crore payable, while VSTPS I-V together received Rs. 4.13 crore as TRAS providers.Details
8BHEL signs technology transfer pact with NSTL-DRDO for LM2500 GT-IRSS on naval vessels Bharat Heavy Electricals Limited (Reference CC/MISC/2026-27/07 dated 28 April 2026) has informed BSE and NSE that it has signed a licensing agreement for transfer of technology (LAToT) with Naval Science & Technological Laboratory (NSTL), Vishakhapatnam, a constituent laboratory of DRDO, for fabrication, installation and commissioning of the LM2500 gas turbine-infrared suppression system (GT-IRSS) for naval vessels - a domestic Make-in-India Defence diversification initiative. 8G R Infraprojects receives completion certificate for 56.18 km Govindpur-Rajura NH-353B HAM project worth Rs. 907 crore G R Infraprojects Limited (BSE: 543317, NSE: GRINFRA) has informed exchanges on 28 April 2026 that the independent engineer has issued a completion certificate for the hybrid annuity mode (HAM) project of GR Govindpur Rajura Highway Private Limited - a wholly owned subsidiary - covering four-laning of the existing 2-lane stretch from Govindpur to Rajura (design length of 56.180 km on NH-353B in Maharashtra); the bid project cost was Rs. 907 crore (excluding GST) and the project is fit for commercial operation with effect from 25 March 2026. 8Ministry of Coal signs first-ever 4 CMDPAs with underground coal gasification provisions; Reliance and Axis Energy bag mines In a historic first under the 14th tranche of commercial coal mining auctions on 28 April 2026, the Ministry of Coal has executed coal mine/block production and development agreements (CMDPAs) for four mines with embedded underground coal gasification (UCG) provisions: Reliance Industries Limited has secured Recherla and Chintalpudi Sector A1, while Axis Energy Ventures India Private Limited has won Dip Extension of Belpahar and Tangardihi East - covering Andhra Pradesh and Odisha. 8PVVNL Meerut lists 29 April 2026 power cuts across 5 zones for maintenance and business plan 2025-26 works Paschimanchal Vidyut Vitran Nigam Limited (PVVNL), Meerut, has issued a detail of planned shutdown for 29 April 2026 covering Bulandshahar, Gajraula, Ghaziabad-1, Ghaziabad-2 and Ghaziabad-3 zones; outages last 1-4 hours starting from 6:30 hrs and affect 11 kV/33 kV feeders for transformer testing, panel & breaker work, conductor replacement and new 33 kV feeder installation under the business plan 2025-26. 8Kalpataru Projects International receives independent ESG rating of "53" (Adequate) from SEBI-registered rater Mumbai/Gandhinagar-headquartered Kalpataru Projects International Limited (BSE: 522287, NSE: KPIL; CIN: L40100GJ1981PLC004281) has informed exchanges via reference KPIL/26-27 dated 28 April 2026 that ESG Risk Assessments & Insights Limited, a SEBI-registered ESG rating provider, has independently assigned an environmental, social, and governance rating of "53" (Adequate) based on publicly available information; KPIL had not engaged the ESG provider for the rating.
INFRASTRUCTURE PIPELINE & POLICY
8India's National Infrastructure Pipeline swells 92% to ~Rs. 213 trillion across 14,563 projects by March 2026: CareEdge Report An April 2026 thematic note reports that India's National Infrastructure Pipeline (NIP), launched in 2019 for projects above Rs. 100 crore, now spans approximately 14,563 projects worth Rs. 213 trillion - a 92% rise from the original Rs. 111 trillion across ~6,800 projects; FY2026 added 1,563 projects (about half of FY2025) worth Rs. 28.4 trillion, with logistics taking 42% of the total, water management 18%, energy and power stable at ~18%, and the framework now spanning 33 sectors and 79 sub-sectors. 8Ember analysis: OECD fossil generation down 0.2% in 2025 - first non-COVID year without fossil rise this century An Ember analysis published 28 April 2026, authored by Wilmar Suárez and timed for the Transitioning Away from Fossil Fuels Conference at Santa Marta, Colombia, finds that fossil power generation across the 38 OECD member countries has reached a structural peak; global fossil generation fell 0.2% in 2025 - the first year since 2020 (and only the fifth this century) without a rise - as record solar growth met all new electricity demand, with declines extending into major non-OECD emerging economies.Details
8REC Limited board approves audited FY26 standalone & consolidated results with unmodified auditor opinion Maharatna CPSE REC Limited (BSE: 532955, NSE: RECLTD; CIN: L40101DL1969GOI005095), at its Gurugram corporate office, has informed BSE and NSE on 28 April 2026 that its board of directors, at the meeting held on the same date, considered and approved the audited standalone and consolidated financial results of the company for the quarter and financial year ended 31 March 2026; the joint statutory auditors have furnished an audit report with unmodified opinion on both standalone and consolidated results. 8Sunlite Recycling Industries' FY26 revenue jumps 97.9% to Rs. 2,765 million; ATC capacity doubled to 1,600 MTPA Kheda (Gujarat)-based Sunlite Recycling Industries Limited (NSE: SUNLITE; CIN: L27200GJ2022PLC134540) has filed an investor presentation for H2 & FY26 reporting standalone revenue of Rs. 2,764.7 million (+97.9% YoY), EBITDA of Rs. 596.9 million (+150.5%), PAT of Rs. 401.5 million (+181.3%) and EPS of Rs. 35.20 (+140.9%); the company doubled annealed tinned coated copper (ATC) capacity from 800 MTPA to 1,600 MTPA via Rs. 2.62 crore CAPEX, and recommended a final dividend of Rs. 1 per share. 8Larsen & Toubro pays Rs. 154.5 crore annual NCD interest on Rs. 2,000 crore issue (ISIN INE018A08BE9) on due date Larsen & Toubro Limited (BSE: 500510, NSE: LT; CIN: L99999MH1946PLC004768) has, in a 28 April 2026 certificate filed under Regulation 57 of the SEBI listing regulations, confirmed payment on due date of Rs. 154.5 crore in yearly interest on its non-convertible debentures of issue size Rs. 2,000 crore (ISIN INE018A08BE9), with record date 13 April 2026; no redemption was due, and the certificate was copied to IDBI Trusteeship Services, CRISIL Ratings and India Ratings. 8Fuji Electric hits record FY2025 net sales of ¥1,227.6 billion, operating profit crosses 11% margin a year ahead of plan Tokyo-listed Fuji Electric Co., Ltd. has reported all-time-high consolidated FY2025 results with net sales of ¥1,227.6 billion (+¥104.2 billion YoY), operating profit of ¥136.6 billion (+¥19.0 billion), ordinary profit of ¥139.3 billion and profit attributable to owners of parent of ¥98.0 billion; the operating profit ratio of 11.1% beat the medium-term target of >11% one year early, led by energy segment profit of ¥59.5 billion at a 15.1% margin.
BOARD MEETINGS & INVESTOR UPDATES
8Voltamp Transformers schedules 5 May 2026 board meeting to decide FY26 audited results and dividend Vadodara-headquartered Voltamp Transformers Limited (NSE: VOLTAMP, BSE: 532757) has, via reference VTL/BM/APRIL/2026 dated 28 April 2026, informed exchanges that its board will meet on Tuesday, 5 May 2026 under SEBI Reg. 29 to approve audited financial results for Q4 and FY ended 31 March 2026 and to consider dividend for FY 2025-26; the trading window has been closed since 1 April 2026 and reopens 48 hours after results. 8BHEL board to consider final dividend for FY 2025-26 in 4 May 2026 meeting Bharat Heavy Electricals Limited (CIN: L74899DL1964GOI004281) has informed BSE and NSE via letter No. AA/SCY/SEs dated 28.04.2026 that the previously notified board meeting on Monday, 4 May 2026 will additionally consider recommendation of final dividend, if any, for FY 2025-26; the disclosure was signed by Company Secretary Dr. Yogesh R Chhabra at BHEL House, Siri Fort, New Delhi. 8HBL Engineering (formerly HBL Power Systems) to hold board meeting on 23 May 2026 for Q4 & FY26 results and dividend Hyderabad-headquartered HBL Engineering Limited (BSE: 517271, NSE: HBLENGINE; CIN: L40109TG1986PLC006745), formerly HBL Power Systems Limited, has notified the exchanges that its board will convene on Saturday, 23 May 2026 to approve standalone and consolidated audited results for the quarter and year ended 31 March 2026 and to consider dividend for FY 2025-26; the trading window will reopen 48 hours after the meeting. 8Indian Energy Exchange lines up two investor meetings on 30 April 2026 with Motilal Oswal and Old Bridge Capital Indian Energy Exchange Limited (BSE: 540750, NSE: IEX; CIN: L74999DL2007PLC277039), based at Max Towers, Sector 16B, Noida, has informed exchanges on 28 April 2026 that on 30 April 2026 it will hold two analyst/institutional investor meetings - a one-on-one/virtual interaction with Motilal Oswal Financial Services and a one-on-one/Noida meeting with Old Bridge Capital Management; no unpublished price-sensitive information will be shared. 8Larsen & Toubro to hold Q4/FY26 earnings conference call on 5 May 2026 with analysts and institutional investors Larsen & Toubro Limited (BSE: 500510, NSE: LT; CIN: L99999MH1946PLC004768) has, under reference SEC/2026 dated 28 April 2026, intimated BSE and NSE under Reg. 46(2) of SEBI LODR Regulations of a virtual Q4/FY26 earnings conference call (Group Meet) scheduled on 5 May 2026; the disclosure was signed by company secretary & compliance officer Subramanian Narayan (ACS 16354). 8Genus Power Infrastructures to hold virtual group investor meeting on 4 May 2026 at 2:30 PM IST Jaipur/Noida-based Genus Power Infrastructures Limited (BSE: 530343, NSE: GENUSPOWER; CIN: L51909UP1992PLC051997), a Kailash Group Company, has informed BSE and NSE under Regulation 30(6) of the SEBI LODR Regulations on 28 April 2026 that company officials will meet investors and analysts virtually as a group meeting on 4 May 2026 from 14:30 IST onwards, with discussions confined to publicly available information. 8Jindal Steel to host Q4FY26 earnings conference call on 2 May 2026 at 1:00 PM IST with JM Financial Jindal Steel Limited (BSE: 532286, NSE: JINDALSTEL) has informed exchanges on 28 April 2026 that, in association with JM Financial Institutional Securities, it will hold a Q4FY26 earnings conference call on Saturday, 2 May 2026 at 13:00 IST (03:30 EDT, 08:30 UK, 15:30 HK/Singapore); company participants include CEO Gautam Malhotra, whole time director Damodar Mittal and CFO Sunil Agrawal.Details
8Fujiyama Power Systems stays out of SEBI "large corporate" net with Rs. 179.8 crore borrowings Fujiyama Power Systems Limited has informed BSE (Scrip Code 544613) and NSE (UTLSOLAR) that it does not fall under the large corporate category as on March 31, 2026, with outstanding borrowings of Rs. 179.8 crore and a CRISIL credit rating of "A"; the company is exempt from the mandatory debt-securities disclosure framework under SEBI Circular dated 26 November 2018 and 19 October 2023. 8Energy Development Company confirms non-applicability of SEBI large corporate rules for FY 2026-27 Kolkata-headquartered Energy Development Company Limited (CIN: L85110KA1995PLC017003) has filed a confirmation dated 28 April 2026 with both BSE and NSE stating it is not classified as a large corporate under SEBI Circulars 144/2018 and 172/2023 governing fund raising via debt securities; the disclosure was signed jointly by Company Secretary Sneha Naredi and CFO Prabir Goswami under reference EDCL/SE/Comp./2026-27/003. 8ICRA assigns AA+(Stable) long-term rating and reaffirms A1+ commercial paper of Adani Energy Solutions Ahmedabad-based Adani Energy Solutions Limited (BSE: 539254, NSE: ADANIENSOL) has informed exchanges on 28 April 2026 that ICRA Limited, on 27 April 2026, assigned a long-term fund-based proposed limits rating of [ICRA]AA+ (Stable) and reaffirmed [ICRA]A1+ on its commercial paper, under SEBI Reg. 30 of the listing regulations. 8ICRA downgrades Ola Electric Technologies to [ICRA]BBB (Negative)/[ICRA]A3+ on Rs. 1,887 crore facilities Bengaluru-headquartered Ola Electric Technologies Private Limited has been downgraded by ICRA on 28 April 2026 from [ICRA]BBB+ (Negative)/[ICRA]A2 to [ICRA]BBB (Negative)/[ICRA]A3+ on total rated facilities of Rs. 1,887 crore, including a Rs. 610 crore long-term term loan; Ola's effective e2W market share has dropped from 30% in FY2025 to low double-digits through FY2026, EBITDA loss stood at Rs. 1,594 crore in FY2025 (-34% margin) - comfort comes from the Rs. 5,500 crore IPO equity raise of August 2024. 8Nippon India Mutual Fund crosses 7% threshold in Orient Electric, acquires 12.85 lakh shares Nippon Life India Asset Management Limited (CIN: L65910MH1995PLC220793), through Nippon India Mutual Fund, has disclosed under Reg. 29(2) of SEBI SAST Regulations, 2011 that between 29 July 2024 and 24 April 2026 it acquired 12,85,576 shares (0.6025%) of Orient Electric Limited via open-market purchases; its post-acquisition holding stands at 1,51,05,650 shares or 7.0797% of the target company's equity share capital of Rs. 21.34 crore.
ELECTRICITY REGULATIONS & TARIFFS
8JSERC releases JBVNL true-up FY 2024-25, MYT FY 2026-27 to FY 2030-31 order; utility had sought 59% tariff hike The Jharkhand State Electricity Regulatory Commission (JSERC), in its order dated 25 March 2026 from Ranchi, has issued the true-up for FY 2024-25, annual performance review for FY 2025-26, approval of business plan and multi-year tariff (MYT) for the control period FY 2026-27 to FY 2030-31 and tariff determination for FY 2026-27 of Jharkhand Bijli Vitran Nigam Limited (JBVNL); JBVNL had sought a 59% tariff hike across all consumers to bridge the cumulative revenue gap. 8BERC admits SBPDCL & NBPDCL plea to switch Bihar's agricultural consumers from 4-season to monthly billing cycle The Bihar Electricity Regulatory Commission, in Case No. 15/2026 dated 28 April 2026, has admitted a joint petition filed by South Bihar Power Distribution Company Limited (SBPDCL) on behalf of itself and North Bihar Power Distribution Company Limited (NBPDCL) under Sections 86(1)(k) and 94(1)(f) of the Electricity Act, 2003 seeking to replace the existing four-harvesting-season billing for agricultural consumers with a standardised monthly billing system; the DISCOMs have been directed to publish the petition in two daily newspapers within one week. 8Bihar Electricity Regulatory Commission reserves order on 185 MW solar + 45.4 MW BESS hybrid project of BSPGCL at Kajra, Lakhisarai The Bihar Electricity Regulatory Commission, sitting at Vidyut Bhawan-II, Patna, in Case No. 05/2026 (DO_CN_05/2026 dated 28.04.2026) heard parties in BSPGCL's clarificatory petition under Regulation 41 of BERC intra-state open access regulations, 2018 seeking clarification on connectivity capacity for a 185 MW(AC) solar PV plus 45.4 MW/4-hour battery energy storage hybrid plant at Kajra, Lakhisarai; the bench of Chairman Amir Subhani and Member (Legal) P.S. Yadav reserved the order. 8PESB advertises Director (Projects) vacancy at Power Grid Corporation; pay scale Rs. 1,80,000-3,40,000 (IDA) The Public Enterprises Selection Board (Advt. No. 45/2026 dated 23.04.2026) has invited applications for the post of Director (Projects), Power Grid Corporation of India Limited - a Schedule-A Maharatna CPSE under the Ministry of Power; the vacancy date is 01.04.2026 and the scale is Rs. 1,80,000-3,40,000 (IDA), with PGCIL employing 9,723 regular staff (5,373 executives, 4,350 non-executives) as on 31.03.2026, with Government of India shareholding of 51.34%. 8PSPCL exempts government hospitals from smart prepaid meter rollout for sub-45 kVA connections Punjab State Power Corporation Limited (CIN: U40109PB2010SGC033813), via Memo SR-106 dated 28 April 2026, has communicated the MoP-PFC decision that only government hospitals will now be treated as critical emergency services and exempted from smart prepaid meter installation; the underlying instruction to install smart prepaid meters for all government connections up to a contract demand of 45 kVA from 01.03.2023 (CC No. 5/2023) continues to apply, with a 2% rebate on energy charges admissible under Regulation 39(2)(vii) of Supply Code-2024.Details
8Websol Energy FY26 revenue surges 82.4% to Rs. 1,049 crore; PAT almost doubles to Rs. 303 crore Kolkata-based Websol Energy System Limited (BSE: 517498, NSE: WEBELSOLAR) has filed an investor presentation showing Q4FY26 revenue of Rs. 401 crore (+132.1% YoY), EBITDA of Rs. 146 crore (+86.4%) and PAT of Rs. 125 crore (+157.9%); FY26 revenue rose to Rs. 1,049 crore (+82.4%), EBITDA to Rs. 429 crore (+69.6%) and PAT to Rs. 303 crore (+95.8%), with cell capacity doubled to 1.2 GW, net debt cut to Rs. (-)34 crore and CRISIL BBB+ Stable rating assigned. 8Waa Solar commissions 6,000 KW (AC) under PM Kusum-C, takes cumulative capacity to 42 MW across Gujarat Vadodara-based Waa Solar Limited (BSE: WAA, Code: 541445) has announced under SEBI Reg. 30 on 28 April 2026 that it has received two commissioning certificates from Paschim Gujarat Vij Company Limited (PGVCL) for the successful commissioning of grid-connected solar PV systems aggregating 6,000 KW (AC) under the PM KUSUM-C feeder level solarization scheme; with this milestone, the company's cumulative commissioned capacity under PM Kusum-C reaches 42 MW. 8Vikran Engineering buys 49% stake in NOPL Solar Projects for Rs. 4.9 crore, linked to 969 MW solar project under PM-KUSUM Thane-based Vikran Engineering Limited (BSE: 544496, NSE: VIKRAN) has informed exchanges on 28 April 2026 of the execution of a share purchase agreement to acquire a 49% equity stake in NOPL Solar Projects Private Limited for Rs. 4.9 crore; NOPL is linked to a 969 MW (AC) grid-connected solar project under Component C of the PM-KUSUM scheme in Maharashtra, marking VEL's strategic expansion in renewable energy beyond its core multi-sector EPC operations. 8TSECL plans 100-150 MW rooftop solarisation of up to 1.5 lakh homes under PM Surya Ghar in Tripura Tripura State Electricity Corporation Limited (TSECL), Agartala, has invited prospective bidders, EPC contractors and OEMs to a virtual market sounding on 5 May 2026 at 15:30 hrs IST for a planned 100-150 MW domestic rooftop solar implementation under PM Surya Ghar: Muft Bijli Yojana on the utility-led aggregation/CAPEX model; the project envisages 1.1 kWp grid-connected rooftop solar plants for 1-1.5 lakh residential consumers across nine electrical circles, with 10-year O&M and circle-level monitoring centres. 8CEA daily renewable generation report 27 April 2026: Rajasthan leads with 263.55 MU; Gujarat at 326.89 MU; all-India cumulative April wind+solar tops 7,343 MU in north The Central Electricity Authority's renewable project monitoring division's daily renewable generation report for 27 April 2026 shows Rajasthan generating 263.55 MU of renewable energy on the day (39.51 MU wind + 222.26 MU solar + 1.78 MU others) and a cumulative April 2026 total of 6,353.37 MU; Gujarat contributed 326.89 MU daily (159.57 MU wind + 167.32 MU solar), with cumulative April totalling 6,683.81 MU; the northern region's cumulative April renewable generation reached 7,343.04 MU. 8Adani Enterprises, Google, AdaniConneX and Nxtra break ground on gigawatt-scale AI hub at Visakhapatnam Adani Enterprises Limited (BSE: 512599, NSE: ADANIENT) has informed exchanges that on 28 April 2026 Google formally broke ground on its largest-ever India investment - a gigawatt-scale AI hub at Tarluvada, Andhra Pradesh - built in partnership with AdaniConneX and Nxtra by Airtel; the launch was attended by Union Minister Ashwini Vaishnaw, Andhra Pradesh CM N. Chandrababu Naidu, IT Minister Nara Lokesh, Google Cloud VP Bikash Koley and Adani Group directors Karan and Jeet Adani.
WIND & HYDRO ENERGY
8NCLT Ahmedabad approves Inox Green Energy demerger of power evacuation business into Inox Renewable Solutions w.e.f. 1 October 2024 Inox Green Energy Services Limited (BSE: 543667, NSE: INOXGREEN) has informed exchanges that on 27 April 2026 it received the certified copy of the NCLT Ahmedabad Division Bench order (CP(CAA)/56(AHM)2025) approving the scheme of arrangement under Sections 230-232 of the Companies Act, 2013 to demerge its power evacuation business into Inox Renewable Solutions Limited (formerly Resco Global Wind Services Pvt Ltd) with appointed date 1 October 2024. 8Infomerics reaffirms IVR BBB+/Negative on Sterling and Wilson Renewable Energy's Rs. 6,465.21 crore bank facilities Infomerics Valuation and Rating, in a press release dated 27 April 2026, has reaffirmed its long-term rating of IVR BBB+/Negative and short-term rating of IVR A2 on the enhanced bank facilities of Sterling and Wilson Renewable Energy Limited (SWREL), now sized at Rs. 6,465.21 crore (up from Rs. 5,903.99 crore); SWREL's FY25 consolidated revenue grew 108% to Rs. 6,301.86 crore, order book stood at Rs. 9,286.59 crore as on 30 September 2025, and key wins include a Rs. 1,313 crore EPC contract for a 240 MW solar PV project in South Africa. 8UERC rejects UJVN's petition for project-specific tariff on 4.5 MW Kaliganga-II SHP, locks in Rs. 6.33/kWh generic rate The Uttarakhand Electricity Regulatory Commission, in its order dated 28 April 2026 in Misc. Application No. 54 of 2024, dismissed UJVN Ltd's plea for a project-specific tariff for the 2x2.25 MW Kaliganga-II small hydro power station (revised cost Rs. 113.71 crore including IDC) on the ground that the petition was filed beyond the 18-month window stipulated under RE Regulations, 2018; UJVN will instead receive the generic tariff of Rs. 6.33/kWh fixed for SHPs up to 5 MW for the entire useful life of the project.Details
8CEA coal stock report 27 April 2026: Rajasthan's Chhabra-II TPP at 55% of normative stock; Haryana plants hold 148% - national coal adequacy varies sharply The Central Electricity Authority's fuel management division daily coal stock report as on 27 April 2026 reveals Rajasthan's Chhabra-II TPP (1,320 MW) with coal stocks at only 55% of normative requirements (244,300 tonnes actual versus 443,900 normative) and Suratgarh TPS (1,500 MW) at 58% of normative - both significantly below comfort levels; in contrast, Haryana's HPGCL fleet (2,510 MW) held 1,448,200 tonnes - 148% of normative stock. 8CEA category-wise generation 26 April 2026: coal at 4,079.67 MU; nuclear at 147.72 MU; hydro beats target by 75.77 MU; April cumulative coal 4,937 MU below plan CEA's Sub-Report 17 on category-wise, fuel-wise generation for 26 April 2026 shows coal generation at 4,079.67 MU - within 0.15% of the 4,086.11 MU programme; nuclear generation was below target at 147.72 MU (programme: 182.80 MU); hydro strongly overperformed at 424.48 MU against a 348.71 MU target; total national actual generation of 4,857.59 MU exceeded the 4,818.57 MU programme by 39 MU, but cumulative April 1 to 26 coal generation of 1,00,175.70 MU lagged the 1,05,113.19 MU programme by 4,937 MU. 8CEA sub-report 14 for 27 April 2026: national natural gas generation hits 107.79 MU - above 89.63 MU programme; gas plants perform better than usual CEA's Sub-Report 14 for 27 April 2026 documents daily gas-based power generation nationally; companion sub-report 17 data for the same period shows natural gas generation at 107.79 MU - 20.2% above the 89.63 MU programme - one of the rare instances where gas plants outperformed their schedule; this is likely due to increased scheduling of available gas capacity during April's peak demand conditions; total national thermal generation reached approximately 4,280.67 MU. 8Panipat TPS Unit 6 revived on 27 April 2026 after 7-day H.T./L.T. outage; 210 MW restored to northern region grid CEA's Sub-Report 10 for 27 April 2026 confirms that Haryana's Panipat TPS Unit 6 (210 MW), which had been on forced outage for HT/LT supply problems since 20 April 2026, was successfully restored on 27 April 2026 at 04:32 hrs - ending a seven-day outage; Yamuna Nagar TPS Unit 2 (300 MW) continues on planned annual boiler overhaul with no revival date confirmed; the return of Panipat Unit 6 adds 210 MW of thermal capacity to the northern region's generation portfolio at the peak of summer demand. 8Rajasthan's Suratgarh STPS Unit 8 (660 MW) trips on C&I fault on 27 April 2026; revived within 5 hours and 16 minutes CEA's Sub-Report 11 for 27 April 2026 documents a forced outage at Rajasthan's Suratgarh STPS Unit 8 (660 MW, RRVUNL), which tripped at 12:02 hrs due to control and instrumentation (C&I) problems and was revived by 17:18 hrs - a 5-hour 16-minute disruption during peak afternoon solar generation hours; Suratgarh STPS is one of Rajasthan's largest thermal stations, and its unit outages have direct implications for state reliability. 8NTPC Faridabad CCPP at near-zero output on 26 April 2026; Koldam hydro (800 MW) over-performs at 5.95 MU vs 4.43 MU programme CEA's Sub-Report 9 on NTPC station-level generation for 26 April 2026 shows Faridabad CCPP (431.59 MW, gas, Haryana) generating only 0.81 MU on the day - nearly zero capacity utilisation - reflecting the extreme under-deployment of gas-based NTPC capacity; in contrast, Koldam hydroelectric station (800 MW, Himachal Pradesh) outperformed at 5.95 MU against a 4.43 MU programme - a 34.3% beat. 8CEA all-India generation overview 26 April 2026: northern region nuclear deficit -33.46% April-to-date; thermal lags by -9.79% The Central Electricity Authority's Sub-Report 1 generation overview for 26 April 2026 shows northern region thermal generation of 984.52 MU against a programme of 958.91 MU on the day, but April-to-date thermal stood 9.79% below target (22,168 MU actual vs 24,573 MU programmed); nuclear generation was severely below target, with actual April-to-date output of 1,027.62 MU lagging 1,544.40 MU programme by -33.46% - indicating sustained reactor unavailability.
HYDRO GENERATION & RESERVOIRS
8CEA hydro reservoir report 26 April 2026: Bhakra at 485.87 m with 1,728.8 MU energy; Linganamakki holds 5,282 MU design potential at 539.05 m CEA's Sub-Report 6 on hydro reservoir levels for 26 April 2026 shows Bhakra reservoir (Himachal Pradesh) at 485.87 m (full reservoir level 513.59 m), with energy content of 1,728.8 MU against a full design energy of 5,282 MU - at only 32.7% of capacity, reflecting the pre-monsoon low-water period; Linganamakki (Karnataka) held 1,135.89 MU at 539.05 m, and SUPA reservoir (Karnataka) was at 532.49 m - these reservoir levels directly determine how much hydro generation India can safely dispatch during summer grid stress periods. 8SRLDC reservoir report 28 April 2026: Linganamakki at 1,135.89 MU, SUPA at 956 MU; three thermal units trip overnight The SRLDC reservoir and thermal outage report for 28 April 2026 shows Linganamakki reservoir holding 1,135.89 MU of energy at 539.05 m and SUPA at 956.37 MU (532.49 m level), while IDUKKI stands at 692.74 MU at level 710.79 m; on the thermal front, three units tripped during the night: Meenakshi Energy Stage 2 Unit 3 (350 MW, loss of flame), North Chennai TPS Stage-II Unit 4 (600 MW, boiler tube leakage), and Meenakshi Energy Stage 1 Unit 2 (150 MW, ESP issue) - withdrawing 1,100 MW from the southern generation pool within hours of each other.Details
8IEX day-ahead market 28 April 2026: purchase bids exceed 48,000 MW in early hours; MCP hits price cap of Rs. 10,000/MWh all day The Indian Energy Exchange's day-ahead market for 28 April 2026 registered massive purchase bids - exceeding 48,784 MW in the first time block - against sell bids of just 1,255 MW, resulting in a market clearing price of Rs. 10,000/MWh (the price cap) across all time blocks; cleared volumes ranged between approximately 980 MW and 1,250 MW per block in the early hours, far below purchase demand, as sell-side liquidity was severely constrained - signalling extremely tight power availability reflecting peak summer demand pressure. 8IEX RTM block-wise market snapshot 28 April 2026: Hour 1 Session 1 clears 7,186 MW; purchase bids exceed 18,000 MW at Rs. 10,000/MWh The IEX real-time market block-wise snapshot for 28 April 2026 reveals exceptionally large cleared volumes in the first sessions of the day: the first 15-minute block of Hour 1 cleared 7,186.27 MW out of a purchase bid of 18,341.60 MW and sell bid of 7,186.30 MW - all at Rs. 10,000/MWh; the second block cleared 7,468.98 MW; in later hours like Hour 2, cleared volumes exceeded 9,000 MW per session - among the largest block-level clearances recorded in the IEX RTM. 8IEX RTM hourly snapshot 28 April 2026: Hour 0 clears 7,790 MWh at Rs. 10,000; Hour 7 drops to Rs. 3,938/MWh as supply improves The IEX real-time market hourly snapshot for 28 April 2026 shows Hour 0 (midnight hour) clearing 7,790.56 MWh at Rs. 10,000/MWh with 17,733 MWh purchase bids; as the day progressed into daylight hours when solar generation improved supply availability, prices dropped: Hour 7 (06:00–07:00) cleared at a weighted MCP of Rs. 3,938.22/MWh - this intraday price volatility vividly illustrates solar energy's grid-balancing and price-suppression impact in India. 8IEX DAM weekly summary 22–28 April 2026: 28 April clears 110,187 MWh; weighted MCP drops from Rs. 7,078 to Rs. 4,726 by week's end The weekly IEX day-ahead market summary from 22 to 28 April 2026 reveals sharp swings in market conditions; on 27 April, the weighted MCP peaked at Rs. 4,726.31/MWh with 106,222 MWh cleared - one of the highest MCP weeks; by contrast, 26 April saw a weighted MCP of Rs. 3,566.21/MWh with 94,199 MWh cleared; on 28 April, approximately 110,187 MWh was traded, with price volatility underscoring the sensitivity of India's power exchange market to renewable generation patterns. 8IEX HPDAM weekly summary 22–29 April 2026: 23 April clears 1,476 MWh at weighted MCP Rs. 18,812/MWh; 28 April at Rs. 20,000/MWh The IEX high-price day-ahead market weekly summary from 22 to 29 April 2026 highlights that 23 April was the highest-volume day, with 1,476.55 MWh cleared at a weighted MCP of Rs. 18,812.63/MWh; on 24 April, 224.28 MWh cleared at Rs. 19,409/MWh; on 28 April, 65.83 MWh was cleared at Rs. 20,000/MWh - the full price ceiling; on 29 April, 214.10 MWh cleared at Rs. 20,000/MWh, suggesting another day of acute supply stress. 8IEX RTM weekly summary 22–28 April 2026: volume peaks at 153,831 MWh on 22 April; 28 April at 188,858 MWh with weighted MCP Rs. 4,885/MWh The IEX real-time market weekly summary from 22 to 28 April 2026 shows 22 April clearing 153,831 MWh at a weighted MCP of Rs. 5,970.63/MWh; volumes rose to 196,998 MWh on 27 April (weighted MCP Rs. 5,452/MWh) and further to 188,858 MWh on 28 April at a lower weighted MCP of Rs. 4,885.43/MWh - reflecting better solar-driven supply during daytime hours; across the entire week, RTM volumes on IEX totalled over one million MWh.
GREEN & ANCILLARY MARKETS
8IEX green DAM block-wise snapshot 28 April 2026: solar MCV ranges from 343–357 MW per block; MCP hits Rs. 10,000/MWh throughout The Indian Energy Exchange's green day-ahead market block-wise snapshot for 28 April 2026 shows solar market clearing volume (MCV) ranging between approximately 343 and 357 MW per 15-minute block during the early hours, against purchase bids of 12,000+ MW; despite solar offer quantities available, the MCP reached the price cap of Rs. 10,000/MWh in every block, driven by overwhelming excess demand - confirming that India's green day-ahead market on 28 April 2026 was in a severely supply-constrained state. 8IEX green term-ahead market 28 April 2026: DAC contracts clear at Rs. 9,993–9,995/MWh; total traded volume near 10 MWh per block at price cap Trade data from the Indian Energy Exchange's green term-ahead market for 28 April 2026 shows day-ahead contingency (DAC) contracts clearing at prices between Rs. 9,993.20 and Rs. 9,995.80/MWh - just below the Rs. 10,000 price ceiling - with 10.05–10.13 MWh per block across 5 buyer and 5 seller counterparties per trade; the DAC contracts for blocks 1 through 24 all recorded successful clearances, indicating active term-ahead green power trading at near-ceiling prices. 8ASDAM weekly summary 20–29 April 2026: zero volume cleared on all days; average MCP remains at 0.0000 Rs./MWh The weekly summary ancillary services day-ahead market snapshot covering 20 to 29 April 2026 confirms that zero MWh was cleared on every single day of the reporting period, with a total cleared volume of 0.0000 MWh and no market clearing price applicable; this sustained ASDAM dormancy across nine consecutive days reflects the current stage of India's ancillary services market development, where voluntary market-based ancillary procurement has yet to become a routine feature of daily grid balancing. 8IEX IDAS weekly summary 22–29 April 2026: only 29 April clears 1,600 MWh at Rs. 10,000/MWh; 28 April sees zero clearances The IEX IDAS weekly summary from 22 to 29 April 2026 shows that only 29 April successfully cleared 1,600 MWh of intra-day ancillary services at Rs. 10,000/MWh - the single active day in the entire week; on 28 April, purchase bids of 500 MWh and sell bids of 1,369 MWh were placed but zero MWh was cleared; this pattern reveals persistent matching failures in the IEX IDAS platform across the week, highlighting structural challenges in India's intra-day ancillary services market. 8IEX term-ahead market 28 April 2026: weekly western region contracts clear at Rs. 7,000–7,500/MWh; multiple day-block products traded Trade data from the Indian Energy Exchange's term-ahead market for 28 April 2026 shows multiple daily block contracts clearing for the western region; a Day 6 Wednesday WR contract cleared 5,280 MWh at Rs. 7,000/MWh (1 buyer, 2 sellers, 2 trades); multiple day-block 1 products (DB1-FRI-WR, DB1-MON-WR, DB1-SAT-WR, DB1-SUN-WR, DB1-TUE-WR, DB1-WED-WR) each cleared 432 MWh at Rs. 7,500/MWh, with 2 buyers, 2 sellers, and 2 trades each.Details
8India crosses historic 256.1 GW peak power demand on 25 April 2026 with zero shortage; FY 2025-26 adds record 65 GW capacity The Ministry of Power announced that India met an all-time-high peak electricity demand of 256.1 GW on 25 April 2026 at 15:38 hrs without any shortage, while continuing exports to neighbours; the figure surpasses the earlier peaks of 250 GW (30 May 2024) and 245.4 GW (9 January 2026) and is supported by a record FY 2025-26 capacity addition of around 65 GW; the source mix at peak comprised thermal 174,565 MW (66.9%), solar 56,204 MW (21.5%), hydro 11,422 MW, nuclear 6,293 MW, gas 5,205 MW and wind 4,897 MW, with grid frequency a clean 50.00 Hz and overall April 2026 consumption growing 8.9% YoY. 8NLDC daily PSP report 28 April 2026: all-India evening peak demand reaches 75,822 MW; zero shortage across all five regions Grid Controller of India's National Load Despatch Centre issued its daily PSP report for 28 April 2026 under IEGC Article 38(1), confirming an all-India evening peak demand of 75,822 MW with zero shortage across all five regional grids — northern, western, southern, eastern and north-eastern; the report, addressed to all five regional load despatch centres, serves as the national power balance reference for the day. 8Northern region meets 75,821 MW peak on 28 April 2026; UP leads at 27,984 MW; 1,649 MU day energy with minor 0.66 MU shortage in Haryana Grid Controller of India's Northern Regional Load Despatch Centre recorded a peak demand of 75,821 MW at 20:00 hrs on 28 April 2026, with a marginal day-energy shortage of 0.66 MU confined to Haryana; Uttar Pradesh dominated with 27,984 MW peak demand and 587.99 MU total requirement; Rajasthan generated 262.47 MU from its state fleet (173.15 MU thermal, 55.41 MU solar, 25.73 MU wind) and system frequency at evening peak was 50.105 Hz. 8Western region posts 74,047 MW evening peak and 1,766.7 MU day energy on 28 April 2026; zero power shortage throughout the day Grid Controller of India's Western Regional Load Despatch Centre confirmed zero power shortage in the Western Region on 28 April 2026, with an evening peak of 74,047 MW at 20:00 hrs and an off-peak demand of 69,698 MW at 03:00 hrs; day energy totalled 1,766.7 MU — the highest of any Indian regional grid on the day, with system frequency remaining healthy at 50.1 Hz during evening peak. 8Southern region meets 72,030 MW peak demand on 28 April 2026 with zero shortage; solar generates 161.25 MU and wind 74.46 MU Grid Controller of India's SRLDC confirmed zero power shortage in the southern region on 28 April 2026, with a regional peak demand of 72,030 MW at 15:44 hrs and day energy consumption of 1,483.89 MU; Tamil Nadu led with 21,211 MW peak, Karnataka at 18,207 MW and Andhra Pradesh at 14,076 MW; total solar generation reached 161.25 MU and wind 74.46 MU across all six southern states. 8Eastern region meets 29,441 MW evening peak on 28 April 2026; West Bengal leads at 10,495 MW; Odisha at 5,977 MW — zero shortage reported Grid Controller of India's Eastern Regional Load Despatch Centre confirmed zero power shortage in the eastern region on 28 April 2026, with an evening peak of 29,441 MW, off-peak of 26,201 MW and day energy of 654.2 MU; West Bengal led all states with a peak demand of 10,495 MW, followed by Bihar at 7,204 MW and Odisha at 5,977 MW; eastern region state generation totalled 377.78 MU. 8North-eastern region power supply report 28 April 2026: 2,921 MW evening peak met; Assam leads with 1,861 MW demand at zero shortage Grid Controller of India's North Eastern Regional Load Despatch Centre confirmed zero power shortage in the north-eastern region on 28 April 2026, with an evening peak demand of 2,921 MW at 20:00 hrs and off-peak of 1,557 MW at 03:00 hrs; day energy consumption totalled 50.76 MU with no deficit; Assam had the highest demand at 1,861 MW evening peak (32.82 MU day energy), followed by Meghalaya at 339 MW and Manipur at 171 MW. 8India sets all-time VRE peak of 90,189 MW on 27 April 2026; wind+solar penetration hits 37.29% of demand at 11:43 hrs The NLDC-REMC report for 27 April 2026 confirmed an extraordinary milestone: combined variable renewable energy (VRE) generation in India reached an all-time high of 90,189 MW on 27 April 2026 at 11:45 hrs, breaking the previous record of 82,537 MW set on 27 March 2026; Gujarat incurred 2,485 MW of solar curtailment (6.57 MU) and 947 MW of wind curtailment (1.37 MU) due to system requirements, while Rajasthan curtailed 315 MW of solar (0.71 MU) due to overloads on 400 kV lines at Bhadla.
TRANSMISSION OUTAGES & RELIABILITY
8SRLDC logs 11 forced transmission outages on 28 April 2026; 765 kV POWERGRID Kurnool–Maheshwaram line down for 5+ hours The Southern Regional Load Despatch Center documented 11 forced transmission outages on 28 April 2026; the most significant was the 765 kV Kurnool–Maheshwaram Line 2 (POWERGRID), which tripped on an R-Y fault at 18:03 hrs and was offline until 23:17 hrs — over five hours; additional outages included a 400 kV KPTCL Kaiga–Guttur line (direct trip, 11:02–11:42 hrs) and a 400 kV POWERGRID Tirunelveli–Kottayam line (B-N fault). 8SRLDC transmission report 28 April 2026: 42 forced outages, 35 planned and 5 voltage regulation outages across southern region The SRLDC transmission outage report for 28 April 2026 catalogues 42 forced outages, 35 planned outages and 5 voltage regulation outages; among the most severe forced interruptions, a 765 kV POWERGRID Kurnool–Cuddapah line tripped on over-voltage at 18:02 hrs, and a Madurai POWERGRID ICT transformer (400/230 kV) suffered heavy fire and Buchholz trip; the 765 kV Raichur–Sholapur-2 shutdown, ongoing since 24 April 2026, continues to reduce southern region import ATC by 150 MW and export by 750 MW. 8WRLDC reliability report 28 April 2026: Maharashtra violates ATC for 49% of day — 47 blocks; Goa breaches ATC in 21.9% of time Grid Controller of India's Western RLDC daily system reliability indices report for 28 April 2026 shows Maharashtra with the most severe grid code non-compliance: ATC was violated across 47 blocks — 49.0% of the 24-hour period — with the N-1 security criterion also violated in 15 blocks (3.8% of blocks); Goa recorded ATC violations in 21 blocks (21.9%), while Gujarat, Madhya Pradesh, Chhattisgarh and DNHDDPDCL registered zero violations for both ATC and N-1 criteria. 8SRLDC system reliability report 28 April 2026: S1 to S2+S3 corridor ATC violated for 20 blocks — 5 hours; N-1 violated for 1.5 hours The Southern Regional Load Despatch Centre's system reliability indices report for 28 April 2026 reveals that the intra-southern S1 to S2+S3 transmission corridor had its ATC violated in 20 blocks — equivalent to 5 hours and 20.83% of the day; the N-1 security criterion for the same corridor was violated in 6 blocks (1.5 hours, 6.25% of the day); these findings indicate meaningful transmission congestion within the southern region on 28 April 2026, likely exacerbated by the multiple forced outages on high-voltage transmission elements. 8Grid-India national transmission element outage report 28 April 2026: 765 kV, 400 kV and 220 kV line and transformer outages across all five regional grids in single database Grid Controller of India Limited's transmission element outage report for 28 April 2026, compiled by the system operation department, is the definitive national database of all transmission outages — integrating data from NRLDC, WRLDC, SRLDC, ERLDC and NERLDC into a single structured spreadsheet; on this particularly severe transmission outage day — with 42 forced outages in the southern region alone, including 765 kV POWERGRID lines tripping on phase faults, a major transformer fire at POWERGRID Madurai, and breaker maloperation events at KPTCL. 8NLDC all-India frequency profile 28 April 2026: average 50.016 Hz; grid in 49.9–50.05 Hz band for 75.13% of day Grid Controller of India's National Load Despatch Centre published the all-India frequency profile for 28 April 2026; the average frequency for the day was 50.016 Hz, with 75.13% of the time spent in the 50.0–50.1 Hz band; the system was within the IEGC band of 49.7–50.2 Hz for 99.65% of the day; maximum frequency reached 50.317 Hz and the minimum was recorded at 49.846 Hz — only 2.31% of the time was spent below 49.9 Hz. 8Southern grid frequency averaged 50.016 Hz on 28 April 2026; system outside IEGC band for 24.87% of day — nearly 6 hours Southern region frequency data for 28 April 2026 shows an average daily frequency of 50.016 Hz with a standard deviation of 0.051 Hz and a frequency deviation index of 0.026; the grid peaked at 50.317 Hz at 18:03 hrs and dipped to a minimum of 49.846 Hz at 10:37 hrs; critically, the system remained outside the IEGC prescribed band for 24.873% of the day — equivalent to nearly 5.97 hours — reflecting transient stress during peak renewable injection and multi-line outage periods.
ATC & TRANSFER CAPABILITY
8NLDC pegs WR-NR inter-regional ATC at 21,350 MW for April 2027; SR-WR capability set at 8,350 MW The National Load Despatch Centre, in its issue dated 28 April 2026 (Revision 0), has notified the total transfer capability and available transfer capability for inter-regional corridors for April 2027; key figures include WR-NR ATC of 21,350 MW (off-peak) and 18,050 MW (09:00-16:00), WR-SR ATC of 15,150 MW, ER-NR ATC of 6,300 MW and SR-WR ATC of 8,350 MW, with simultaneous import margins of up to 13,699 MW available for the southern region. 8NLDC approves West Bengal import ATC of 7,633 MW for April 2027; Sikkim capped at 104 MW The National Load Despatch Centre, in Revision 0 dated 24 April 2026, has approved the import total transfer capability for eastern region states for April 2027 at 7,633 MW for West Bengal (against demand of 9,676 MW and generation of 6,440 MW), 104 MW for Sikkim (peak and off-peak), with the West Bengal export ATC fixed at 3,500 MW; key limiting constraints include the tripping of 400 kV Jeerat-Subhasgram circuit. 8WRLDC sets western region April 2027 ATCs: Maharashtra 10,800 MW, Gujarat up to 14,140 MW, Madhya Pradesh 14,362 MW Western Regional Load Despatch Centre (WRLDC), Grid India, in Revision 0 issued on 24 April 2026, has notified the total transfer capability and available transfer capability for the western region for 1-30 April 2027; key control areas are Maharashtra at 10,800 MW ATC (TTC 11,400 MW), Gujarat at 14,140 MW (off-solar) / 12,220 MW (10:00-17:00 solar hours), Madhya Pradesh at 14,362 MW (TTC 14,766 MW), Chhattisgarh at 4,930 MW, and Goa at 705 MW. 8NLDC lists April 2027 ATC for northern states: UP 17,100 MW, Punjab 10,700 MW, Haryana 10,400 MW, Rajasthan margin through year The National Load Despatch Centre, in Revision 0, has issued import capability ATCs for April 2027 for the northern region states; Uttar Pradesh stands at 17,100 MW (TTC 17,700 MW, RM 600 MW) with 5,952 MW T-GNA margin, Punjab at 10,700 MW with 5,203 MW margin, Haryana at 10,400 MW with 4,982 MW margin; limiting constraints include N-1 contingencies of 400/220 kV ICTs at Sultanpur, Allahabad, Deepalpur, Hisar, Kabulpur and Panipat (BBMB). 8NLDC sets DNHDDPDCL total import capability at 1,375 MW for April 2027 (DNH 475 MW + DD 900 MW) The National Load Despatch Centre, in Revision 0 dated 28-03-2026, has issued the import total transfer capability for DNHDDPDCL for April 2027 at 1,375 MW total — comprising 475 MW for Dadra & Nagar Haveli (with 10 MW reliability margin) and 900 MW for Daman & Diu (with 20 MW reliability margin); approved GNA stands at 1,206 MW, leaving 139 MW of margin for T-GNA.Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days. Get the daily updates for : 8LNG 8Crude 8Chemicals 8Fertilizers 8LPG 8Ammonia 8Coal & Coke Click on Reports for more.Details
For reference purposes the website carries here the following tenders: 8Tender for construction of 230kV bays Details 8Tender for selection of network bandwidth service provider (NBSP) for provisioning of MPLS and internet connectivity Details 8Tender for supply of accessories 3 items for HT ABC 120sqmm and 150sqmm Details 8Tender for procurement of consumables and various other items Details 8Tender for procurement of rubber consumables Details 8Tender for supply O rings, gasket sets & hardware set of converter transformer Details 8Tender for procurement of chloride power systems Details 8Tender for work of overhauling, servicing & repairing of air preheater Details 8Tender for supply of MS hot dip galvanized grills Details 8Tender for renovation of substation switch yard Details 8Tender for extension of 3.3 kV overhead line erection from CL Jambad power substation Details 8Tender for erection of LT OH line and dismantling overhead lines Details 8Tender for shifting, installation, commissioning of pump set and installation of pump set Details 8Tender for rearrangement of LT overhead line Details 8Tender for providing power supply arrangement for newly constructed Details 8Tender for providing hume pipe culvert Details 8Tender for supply of ACSR panther conductor Details 8Tender for providing housekeeping services and maintenance of garden and sewer line Details 8Tender for construction of control room at 132 kV sub station Details 8Tender for construction of SPR room at 220 kV S/S Details 8Tender for manufacture, testing, supply and delivery of 610 nos. SCADA compatible 11kV VCB panels Details 8Tender for procurement of light diesel oil Details 8Tender for protection works for 132 kV exacuation line Details 8Tender for Re-grading of tile terracing of roof top Details 8Tender for civil works for front area concreting, storm water Details 8Tender for repair of spillway bucket 01 with HPC M65 grade Details 8Tender for construction of left bank spillway extension wall Details 8Tender for repair and maintenance of store room, door and windows, leakage Details 8Tender for river bank protection work Details 8Tender for painting and miscellaneous repair Details 8Tender for M and R work of type V and OBC residences Details 8Tender for procurement of 132kV &33kV BCU-based control & relay panels Details 8Tender for protecting existing towers Details 8Tender for reconductoring LT ABC transformer Details 8Tender for installation of additional 5 MVA transformer at 33 kV substation Details 8Tender for providing fencing and yard metalling Details 8Tender for supply of 245kV class centre break isolators with and without earth switch Details 8Tender for annual contract for the work of transportation of power transformer / ICT / reactor along Details 8Tender for construction of 03 Nos. of 33kV bays Details 8Tender for supply of complete service air compressor with motor Details 8Design, fabrication, supply, installation, testing and commissioning of total 63 KW grid connected solar PV power plant Details 8Design, fabrication, supply, installation, testing and commissioning of total 156 KW grid connected solar PV power plant Details 8Design, fabrication, supply, installation, testing and commissioning of total 25 KW grid connected solar PV power plant Details 8Tender for supply, retrofitting, testing and commissioning of distance protection relay Details 8Tender for construction of RCC pavement for approaches to loading area and weigh bridge Details 8Tender for N pit CPU regeneration area repair works Details 8Tender for procurement of bull rings segment for XRP-803 coal mills Details 8Tender for construction of RCC flood protection wall and allied civil works Details 8Tender for construction of 220kV ss Details 8Tender for repair and rehabilitation of 75 and 15 ton electric overhead travelling EOT crane installed Details 8Tender for repair of roof leakage of various 66 kV sub station Details 8Design, manufacture, testing, supply and delivery of 220kV Isolators and 220kV isolators with earth switch and spare 220kV solid core insulators Details 8Tender for construction of additional foundations for 1no. 66kV line bay for solar power and allied civil works Details 8Tender for repairing of defective/faulty 11 kV RMUs, including replacement of load break switch Details 8Tender for supply of complete tube bundle for 04 nos. external LP oil cooler and replacement work of tube bundles Details 8Tender for work contract for arresting of water leakage through MIV trunion bushes Details 8Tender for procurement of 01 No. complete rotor assembly of ring granulator Details 8Tender for purchase of ACSR bersimis conductor Details 8Tender for annual maintenance contract (non comprehensive) for metso DNA (valmet) DCS system Details 8Tender for supply of rubber expansion bellow of condenser make OEM Ms cori rubber Details 8Tender for replecment of rusted/dameged ST pole and providing pole Details 8Tender for replacement of old rusted pole providing new pole Details 8Tender for supply of decentralized material for shifting the electric lines Details 8Tender for operation work of 33/11 kV sub stations Details 8Tender for construction of composit rings main in 11/L.T.line Details 8Tender for maintenance of electric supply consumers complaints etc Details 8Tender for providing of De-centralized material Details 8Tender for supply of spares & complete pump assembly Details 8Tender for operation and maintenance of valves for water distribution Details 8Tender for miscellaneous civil works Details 8Tender for work of servicing and maintenance of high mast tower installed Details 8Tender for supply of plummer blocks installed Details 8Tender for supply of various carpentry work material for day to day maintenance work Details 8Tender for work of providing and fixing of non conductive turbo wind driven conical bird guards on tower of various Details 8Tender for conversion of existing 22 kV indoor SF6 switchgear pertaining to 50MVA, 220/22kV TF-3 & TF-5 LV bays Details 8Tender for work of AMC for overhauling /servicing /repairing of 33kV VCB's of with the supply of required spares Details 8Tender for work of AMC for overhauling /servicing /repairing of 33kV VCB's of with the supply of required spares at various Details 8Tender for work of AMC for overhauling /servicing /repairing of 33kV VCB's of with the supply of required Details 8Tender for work of electrification for class II Details 8Tender for providing additional 1X50 MVA,132/33kV T/F along Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8India Pioneers Underground Coal Gasification in Landmark Mine Agreements Details 8Govt signs first commercial coal mine deals under UCG framework Details 8Underground Coal Gasification Enters India’s Commercial Mining Framework Details 8Dividend alert: Big payouts from RIL, UltraTech, Coal India; full list here Details 8Metal sector stocks surge today, April 28: Coal India up 4.20%, MOIL rises 2.98%, SAIL surges 2.17% Details 8Cosmic PV Power Limited Perform Bhumi Poojan ceremony for 1.1 GW Solar Cell Manufacturing Unit at Narmada Puram, Madhya Pradesh Details 8Karnataka court pauses CERC grid penalties for renewables Details 8No More Heavy Fines Karnataka High Court Stays Stricter Penalties for Solar and Wind Firms Details 8Max Estates Accelerates Net-Zero Vision with Solar Power Adoption at Max Square, Sector 129 Noida Details 8Vikran Engineering Acquires 49% Stake in NOPL Solar Projects for Rs 4.9 Crore Details 8Solar Scale Shift Details 8Global Solar Encapsulant Market Consolidates As Top Three Players Dominate 2025 Shipments Details 8NSE welcomes CERC nod for market coupling in power sector Details 8Fossil fuel disruptions strengthen India’s case for boosting renewable energy investments Details 8India meets record 256.1 GW peak power demand without shortage, sets new benchmark Details 8India’s Power Transmission Sector Eyes FY27 Turnaround: SBICAPS Details 8India Industrial Output Slows to 4.1% in March Details 8Stocks to Watch: Adani Power, Vedanta and 10 Others Top Stocks Announce Q4 Results Today Details 8REC Reports Record Rs 16,282 Crore Profit in FY26; Declares Highest-Ever Dividend of Rs 18.55 Per Share Details 8Hindustan Power Secures Environmental Clearance for 1,600 MW Phase II Expansion of Anuppur Power Project Details 8Dip in manufacturing, power sector drags India's industrial output to five-month low amid West Asia crisis Details 8Orient Green Power and 6 other stocks hit 20% upper circuit today; Do you own any Details 8Is NTPC Starting New Nuclear Facilities in Bihar Company Clarifies Details 8March IIP growth slows to 5-month low of 4.1%; manufacturing, power drag Details 8Power Mech Projects Secures Rs 227.95 Crore Order for Vande Bharat Maintenance Depot Details 8Renewables Overtake Coal in Global Power Generation for First Time Details You can also click on Newsclips for moreDetails
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance. Click on Reports for moreDetails
8A 110 kV grid package has been awarded under a partial-turnkey structure, combining multiple substations and transmission stretches. 8While the contract value appears straightforward, the bundled scope introduces coordination and delivery challenges.Details
8IEEFA briefing: Japan's energy security response post-Middle East shock creating renewables blind spot, prioritising coal over clean energy The Institute for Energy Economics and Financial Analysis (IEEFA) April 2026 briefing by energy finance specialist Michiyo Miyamoto argues that Japan's response to the Middle East energy shock - prioritising LNG reduction through increased coal-fired generation and nuclear restarts - is creating a 'renewables blind spot.' The policy expands inflexible baseload at the expense of domestic renewable energy that could address import dependence without geopolitical exposure. 8IEEFA submits to Australian Energy Market Commission on gas networks in transition (GRC0082) directions paper The Institute for Energy Economics and Financial Analysis (IEEFA) has submitted a response dated 24 April 2026 to the Australian Energy Market Commission (AEMC) regarding the gas networks in transition (GRC0082) directions paper, commending the AEMC's review of gas network regulation and highlighting the certain decline in residential and small business demand facing gas networks across Australia. 8India Foundation issue brief 11/2026: 'From petro-state to electro-state - India's energy transition at a crossroads' by Parth Seth India Foundation has published issue brief 11, 2026, titled 'From petro-state to electro-state: India's energy transition at a crossroads' by research fellow Parth Seth, examining India's strategic shift from hydrocarbon import dependence toward renewable energy, covering themes of multilateralism, middle power dynamics, South Asia, MENA energy policy and great power competition in the context of India's emerging energy identity. 8UN ESCAP expert working group to hold 17th energy connectivity meeting in Bangkok on May 13-14, 2026 with hybrid participation The United Nations Economic and Social Commission for Asia and the Pacific (ESCAP) has scheduled its 17th expert working group meeting on energy connectivity in Bangkok, Thailand (hybrid format via MS Teams), on 13-14 May 2026, to advance cross-border electricity cooperation under the regional road map on power system connectivity adopted in 2021.Details
8AVVNL reports 11kV feeder interruption data for 15-21 April 2026: Udaipur tops with 8,111 outages The Ajmer Vidyut Vitran Nigam Ltd (AVVNL) 11kV feeder interruption and duration tracker for 15.04.2026-21.04.2026 across rural, mixed and AG zones records Udaipur circle with 771 feeders, 7,23,646 consumers and 8,111 interruptions averaging 10.52 outages per feeder, alongside Pratapgarh (475 feeders, 6,962 outages, 14.65 avg), Rajasamand (588 feeders, 7,096 outages, 12.07 avg), Chittorgarh (8,652 outages, 18.89 avg) and Salumbar (198 feeders, 3,423 outages, 17.29 avg) - most outages tagged as maintenance/feeder fault. 8AVVNL week-two 11kV feeder performance for 22-27 April 2026: Outages drop to 6,479 in Udaipur circle The Ajmer Vidyut Vitran Nigam Ltd (AVVNL) 11kV feeder interruption and duration report for 22.04.2026-27.04.2026 shows reduction in outages compared with the prior week, with Udaipur circle (771 feeders, 7,23,646 consumers) logging 6,479 interruptions averaging 8.40 per feeder, Chittorgarh (458 feeders, 3,84,325 consumers) recording 7,067 outages with 15.43 average, Pratapgarh dropping to 4,909 outages (10.33 avg), Rajasamand to 4,980 (8.47 avg) and Salumbar to 2,276 outages (11.49 avg) - predominantly attributed to maintenance/feeder fault. 8PVVNL Meerut plans shutdowns across Bulandshahar, Gajraula circuits on April 28, 2026 for 3-4 hours affecting 200+ consumers Paschimanchal Vidyut Vitaran Nigam Limited (PVVNL) Meerut has scheduled planned power shutdowns on 28 April 2026 for Bulandshahar EDC-2 industrial feeder (3 hours, 10:00-13:00) and Gajraula EDC-Amroha urban feeder (4 hours, 7:00-11:00), impacting over 200 consumers across multiple localities including Jokhabad, Begam Sarai, and Azad Road areas. 8RUVITSL releases merit order dispatch for 27 April-3 May 2026: SASAN cheapest at Rs. 1.55/kWh, DADRI LIQ costliest at Rs. 27.86/kWh Rajasthan Urja Vikas and IT Services Limited (RUVITSL) has issued the merit order dispatch (MOD) for 27-04-2026 to 03-05-2026 listing 43 generating stations ranked from highest to lowest variable cost, with DADRI LIQ at Rs. 27.86/kWh, AURIYA LIQ at Rs. 24.14/kWh and AURIYA CRF at Rs. 22.31/kWh at the top - and at the bottom NLC BARSINGHSAR at Rs. 3.08/kWh, SASAN at Rs. 1.55/kWh, RIHAND-2 STPS at Rs. 2.50/kWh, RIHAND-1 STPS at Rs. 2.57/kWh, KHURJA STPP at Rs. 4.42/kWh and KALISINDH TPP-1&2 at Rs. 4.61/kWh. 8MeECL issues bid-submission time extension notification no. 2026/01338/11 on 27 April 2026 Meghalaya Energy Corporation Limited (MeECL), through its chief accounts officer I/c (Sumitra Bataul/Dakhar), has issued notification no. MeECL/DF_MeECL/ACM/ACCOUNTS/2026/01338/11 dated 27 April 2026 extending the bid-submission deadline, with copies forwarded to the director (corporate affairs), company secretary, chief engineer (generation), chief engineer (transmission) MePTCL, chief engineer (distribution) eastern zone and chief engineer (commercial) MePDCL, Shillong - the document is verified through electronic verification code, requiring no physical signature.Details
8KSEB's PETARC schedules 5 training programs in May 2026 for newly promoted engineers in Idukki Kerala State Electricity Board Limited (KSEBL), through its Power Engineer's Training and Research Centre (PETARC) at Moolamattom, Idukki district (pin 685 589), has notified five training programs for May 2026 covering newly-promoted assistant executive engineers, senior superintendents and the 1st batch of 2026 recruit assistant engineers, with sessions running from 11.05.2026 to 31.05.2026 in a blended mode of 2 LMS days plus 4 classroom days, focused on the Electricity Act 2003, section 126 power-theft assessment, Right to Information Act 2005, and CEA safety & electric supply regulations. 8KSEBL calls nominations for 70-day ISTP mandatory training of direct-recruit assistant engineers joining May 2026 Kerala State Electricity Board Ltd (KSEBL, CIN U40100KL2011SGC021424), through its Power Engineer's Training and Research Centre (PETARC) at Moolamattom, Idukki - vide letter no. PET-110/training nomination/2025-26 - has invited controlling officers to nominate newly-recruited direct-recruit assistant engineers (electrical) joining KSEBL during 2025 and thereafter for the mandatory induction-cum-statutory training program (ISTP) commencing third week of May 2026, conforming to CEA (measures relating to safety and electric supply) regulations 2023 - with prescribed durations of 70 days for hydro generation (24 classroom + 12 field + 36 OJT), 17 for transmission, 17 for distribution; 103 engineers already trained and 62 currently in progress. 8PSPCL Bathinda ZKC sanctions 4-month induction training for newly recruited assistant linemen under CRA no. 312/2025 The office of additional SE zonal knowledge centre Bathinda, Punjab State Power Corporation Limited has issued office order no. 56 dated 27 April 2026, sanctioning 4 months induction training for newly recruited assistant linemen under CRA no. 312/2025, comprising 4 weeks in-house training at respective training centres/technical training institutes and 3 months on-the-job training in field offices. 8PSPCL issues PTW online training for Batala and Amritsar AEs: 66 kV operations training scheduled for April 28, 2026 Punjab State Power Corporation Limited (PSPCL, CIN: U40109PB2010SGC033813, email: pspclttcasr@gmail.com) has issued a training notice dated 24 April 2026, directing AE/Tech.-1 Randhir Kumar (Batala) and AE/ZKC Yogesh Bedi (Amritsar) to attend an online permit to work (PTW) implementation training session on 28 April 2026 at 10:00 am for 66 kV operations across the Batala and Amritsar areas. 8Tripura State Electricity Corporation Limited issues corrigendum on manager recruitment examination date notification Tripura State Electricity Corporation Limited (TSECL), a government of Tripura enterprise, has issued a corrigendum dated 24 April 2026, correcting the advertisement date from '07.11.2026' to '07.11.2025' in the notification for the written examination for recruitment to the post of manager (electrical/mechanical/civil), grade-A & B, advt. no. 04/2025.
EMPLOYEE ORDERS & HR MATTERS
8RVPN hikes dearness allowance from 58% to 60% for employees effective 1 January 2026 Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPN), Vidyut Bhawan, Janpath, Jyoti Nagar, Jaipur 302005 (CIN U40109RJ2000SGC016485), vide order no. RVPN/AAO/F&R/F.37(Pt.-II)/D.13 dated 21/04/2026 (F&R no. 1676) issued by CAO Pushpa Upadhyay, has adopted the Rajasthan finance department order no. F.6(3) FD (rules)/2017 dated 23.04.2026 to revise dearness allowance for Nigam employees from 58% to 60% with effect from 01.01.2026 - arrears for 01.01.2026 to 30.04.2026 to be credited to GPF-SAB account, with cash payment admissible from 01.05.2026 in the salary for May 2026. 8RVPN raises dearness relief from 58% to 60% for pensioners effective 1 January 2026 with April 2026 arrears Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPN, CIN U40109RJ2000SGC016485), Jaipur, vide order no. RVPN/AAO/F&R/DR/F.34(Pt.-II)/D.12 dated 24/04/2026 (F&R no. 1675) issued by CAO Pushpa Upadhyay, has adopted Rajasthan finance department order no. F.12(8) FD (rules)/2017 dated 23.04.2026 raising dearness relief for RVPN pensioners (including erstwhile RSEB pensioners) from 58% to 60% w.e.f. 01.01.2026 - with cash payment admissible from 01.01.2026 and arrears for 01.01.2026 to 31.03.2026 payable in one instalment along with April 2026 pension. 8RVPN adopts Rajasthan finance department clarification on ACP/MACP linkage to APAR reports Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPN, CIN U40109RJ2000SGC016485), Vidyut Bhawan, Janpath, Jyoti Nagar, Jaipur 302005, vide order no. RVPN/AAO/F&R/F.113/D.41 dated 24/04/2026 (F&R no. 1674) issued by chief accounts officer (IA & Estt.) Pushpa Upadhyay, has adopted the Rajasthan government finance (rules) department clarification F.15(88)Vitta/Niyam/2017 dated 25.03.2026 regarding linkage of annual career progression (ACP)/modified ACP (MACP) with annual performance appraisal reports (APARs) - clarifying that even after 9 years if the APAR is not available, remaining APARs of subsequent years may be considered for grant of MACP under rule 14 read with annexure-I sub-rule 2(b)(c) of the Rajasthan civil services (revised pay) rules 2017. 8PSPCL promotes Er. Harish Kumar Sharma (Emp. ID 104684) as engineer-in-chief/ARR&TR at pay scale Rs. 1,82,200-2,24,100 (L-23) Punjab State Power Corporation Limited has issued office order no. 87/BEG-I dated 27 April 2026, promoting Er. Harish Kumar Sharma (employee ID 104684), chief engineer/ARR&TR, to the position of engineer-in-chief/ARR&TR at the revised pay scale of Rs. 1,82,200-2,24,100 (level-23) with immediate effect, ahead of his retirement on 30 April 2026. 8PSPCL transfers and posts 3 chief engineers across Ludhiana, Patiala, and Jalandhar in public interest under office order no. 88/BEG-I Punjab State Power Corporation Limited has issued office order no. 88/BEG-I dated 27 April 2026, ordering the transfer and posting of Er. Jatinder Singh (Emp. ID 104802), chief engineer (electrical)/store & workshop, Patiala, to chief engineer/EA & enforcement, Ludhiana; Er. Sarabjit Singh (104994), CE/EA & enforcement, Patiala, to CE/DS north zone, Jalandhar; and a third engineer, all in public interest with immediate effect. 8UPRVUNL adopts revised UP state electricity service (acquisition) regulations 2026 effective 11 March 2026 U.P. Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), 12th floor, Shakti Bhawan Extn., 14-Ashok Marg, Lucknow-226001 (CIN U31901UP1985SGC007135), via letter no. 1/49378/2026 dated 24-04-2026 from the director (HR), has notified all unit heads, regional offices, civil/electrical/mechanical engineering, vigilance and safety wings about adoption of the state government's notification no. 191/Karmik-Anubhag-1-2026-13(5)/1998 dated 11.03.2026 prescribing the new 'UP state electricity service (acquisition) regulations 2026', superseding the 1956 framework, with attached annexure detailing the property declaration formats and procedural changes for promoted personnel. 8PSPCL issues mandatory digital life certificate circular for pensioners via Jeevan Pramaan app by May 25, 2026 Punjab State Power Corporation Limited's chief accounts officer/pension & funds (PSPCL, Patiala) has issued a mandatory circular (no. 45, 27 April 2026) directing all PSPCL pensioners to submit the digital life certificate through the Jeevan Pramaan app by 25 May 2026 for FY 2026-27, in continuation of earlier circulars (nos. 3411 dated 19 March 2026 and no. 22 dated 6 April 2026).Details
8200 MW solar project sees BoS tie-up strategy reshape early-stage competition
The latest 200 MW solar move shifts competitive positioning even before bids are formally submitted. The BoS tie-up model is redefining bidder eligibility and partnership structures at the pre-bid stage. 8Hybrid solar-BESS tender gets deadline extension in Himachal Pradesh The bid deadline for a solar-plus-storage package in Himachal Pradesh has been pushed back, offering developers additional preparation time. While timelines have shifted, the project’s technical scope and long-term performance obligations remain unchanged. 8Thermal retrofit package sees bid extension amid rising execution complexity The bid deadline for a thermal power plant ESP upgradation package has been extended again, indicating underlying execution challenges. While the move appears procedural, the brownfield retrofit scope introduces layered technical and outage management risks. 8Hydro procurement tender sees 44-day extension amid participation concerns The hydro procurement tender timeline has been extended by 44 days, pushing the closing date well beyond the original plan. The delay appears more structural than routine, hinting at possible friction in bid conditions or project structuring. 8Consultancy tenders in transmission and thermal segments see extended timelines Two consultancy tenders in the power sector have moved further into May after missing earlier bid deadlines. One relates to a transmission-linked independent engineer assignment, while the other reflects a more prolonged extension cycle. 8Ash dyke consultancy tender sees extended timeline with unchanged technical scope An ash dyke stability consultancy tender has seen its timeline stretch significantly beyond the original December deadline. Despite the procedural extensions, the technical scope remains tightly defined with no visible expansion. 81,000 MW RTC power tender sees deadline extension amid firm supply pressure The bid deadline for a 1,000 MW round-the-clock power tender has been extended, giving developers more time to navigate a demanding procurement structure. The format requires renewable-backed supply to mimic firm generation behaviour, raising the bar on reliability. 8Rs 1,499 crore smart metering tender sees limited-window extension under controlled bidding route The bid timeline for a Rs 1,499 crore smart prepaid metering package has been extended marginally, indicating a procedural adjustment rather than a structural shift. However, the limited-tender format points to tighter control over bidder participation and competition dynamics. 8Rs 516 crore hydro package sees repeated deadline extension amid rising execution risk The bid deadline for a Rs 516 crore hydro package has been extended again, continuing a pattern of timeline shifts. While the corrigendum keeps the process moving, the underlying challenges lie in complex dredging, dam access, and underwater inspection scope. 8Solar-plus-storage tender sees timeline stretch with tight Rs 1 crore entry filter The bid deadline for a solar-plus-storage package has been extended again, but the strict Rs 1 crore entry condition remains unchanged. While the move gives bidders more time, it does not ease the underlying commercial and execution pressures. 8400 kV substation spares tender sees timeline push amid tight vendor bandwidth The bid deadline for a 400 kV isolator spares package has been extended into May, reflecting continued timeline adjustments. While the scope remains narrowly defined, stringent fitment, warranty, and performance-security conditions persist.
8ICRA assigns [ICRA]AA+ (stable) to Adani Energy Solutions' Rs. 300 crore proposed bank facility; reaffirms [ICRA]A1+ on Rs. 1,000 crore CP ICRA has assigned [ICRA]AA+ (stable) to Adani Energy Solutions Limited's (AESL) newly proposed Rs. 300 crore fund-based bank facility (total now Rs. 1,300 crore), and reaffirmed [ICRA]A1+ on its existing Rs. 1,000 crore commercial paper programme, effective 27 April 2026. The ratings reflect AESL's satisfactory track record in power transmission with line availability above normative levels. 8ICRA assigns [ICRA]A (stable) to Delhi city electric bus operations' Rs. 567 crore bank facilities including Rs. 540.80 crore term loan ICRA has assigned [ICRA]A (stable) to Delhi City Electric Bus Operations Private Limited (DCEBOPL) for Rs. 540.80 crore term loans, Rs. 26 crore bank guarantee and Rs. 0.20 crore unallocated limits (total Rs. 567 crore), effective 27 April 2026. The rating reflects DCEBOPL's strong parentage with majority shareholding by GreenCell Mobility Private Limited (GCML, rated [ICRA]A+(Stable)). 8ICRA assigns [ICRA]A (stable) to PMI Electro Mobility Solutions' Rs. 800 crore bank facilities including Rs. 404 crore LC/BG ICRA has assigned [ICRA]A (stable) to PMI Electro Mobility Solutions Private Limited (PMI) for Rs. 120.50 crore cash credit/WCDL, Rs. 101.68 crore term loan and Rs. 173.82 crore proposed limits, and [ICRA]A2+ for Rs. 404 crore LC/BG non-fund based limits (total Rs. 800 crore), effective 27 April 2026, based on PMI's electric bus execution track record. 8Indian Energy Exchange (IEX) Q4 FY26: PAT misses estimates by 8% but volumes rise 21% YoY; HOLD rating at CMP Rs. 123, target Rs. 135 Indian Energy Exchange (IEX, NSE: IEX IN) Q4 FY26 results show PAT missed analyst estimates by 8% due to lower other income, despite robust volume growth of +21% YoY. An equity research update rates IEX as HOLD with CMP Rs. 123 and target price Rs. 135, citing FY27E sales of Rs. 6,990 mn and EBITDA of Rs. 5,976 mn. Market coupling and proposed ICX diversification remain key near-term risk factors. 8Transformers and Rectifiers (India) Limited secures export order worth USD 16,258,352 disclosed under regulation 30 of SEBI LODR Transformers and Rectifiers (India) Limited (BSE: 532928, NSE: TARIL) has disclosed the receipt of a significant export order valued at USD 16,258,352 under regulation 30 of SEBI (LODR) regulations 2015, via disclosure dated 27 April 2026 (Ref: TARIL/SECT/2026-27/NSE-BSE/COMPL/013) filed with both BSE and the National Stock Exchange of India.
SEBI DISCLOSURES & BOARD ACTIONS
8BHEL board appoints Ms. Nigar Fatima Husain (DIN: 11688785) as part-time official director with Ministry of Heavy Industries approval Bharat Heavy Electricals Limited (CIN: L74899DL1964GOI004281) has disclosed under regulation 30 of SEBI LODR 2015 that Ms. Nigar Fatima Husain, additional secretary & financial advisor to the Ministry of Heavy Industries, has been appointed as a part-time official (government nominee) director on the BHEL board. 8Jaiprakash Power Ventures (BSE: 532627) calls 156th board meeting for May 4, 2026 under regulation 29 of SEBI LODR Jaiprakash Power Ventures Limited (NSE: JPPOWER, BSE: 532627) has informed the stock exchanges (Ref: JPVL:SEC:2026, 27 April 2026) that its 156th board of directors meeting is scheduled for Monday, 4 May 2026, under regulation 29 of SEBI (LODR) regulations 2015, to consider matters to be subsequently disclosed to the exchanges. 8NTPC clarifies nuclear power expansion rumour pursuant to SEBI LODR 2015; exploring 2 nuclear units NTPC Limited (BSE: 532555, NSE: NTPC, ISIN: INE733E01010) has filed a clarification under SEBI (LODR) regulations 2015 in response to a news article headlined 'NTPC exploring 2 nuclear power units,' stating its position regarding the market rumour to provide factual clarity to investors, via letter dated 27 April 2026 (Ref: 01:SEC:LA:1). 8Bharat Coking Coal Limited changes senior management: Shri Parthaasis Ram transferred, Shri Anand Kumar takes over as HoD material management Bharat Coking Coal Limited (BSE scrip code: 544678, ISIN: INE05XR01022) has disclosed under regulation 30 of SEBI LODR 2015 (Ref: BCCL:CS:F-Post-Listing:127, 27 April 2026) that Shri Parthaasis Ram, GM/HoD (material management), has been transferred to another Coal India Limited subsidiary, with Shri Anand Kumar taking over the role. 8Websol Energy System (BSE: 517498, NSE: WEBELSOLAR) board approves audited financial results for Q4 and FY ended March 31, 2026 Websol Energy System Limited (BSE: 517498, NSE: WEBELSOLAR, ISIN: INE855C01023) has filed the outcome of its board meeting held on 27 April 2026 under regulation 30 of SEBI LODR 2015, confirming that the board approved audited standalone and consolidated financial results for the quarter and financial year ended 31 March 2026, with details filed with BSE's listing department and NSE's manager listing.Details
840th NCT drops Rs. 405 crore Bikaner-V 6 GW scheme, modifies Rs. 411.352 crore OPGW award to JTCL/Indigrid The minutes of the 40th meeting of the national committee on transmission (NCT), held on 15 April 2026 at New Delhi and circulated by CEA chief engineer & member secretary B.S. Bairwa on 27.04.2026, record that the Bikaner-V (6 GW) Rajasthan REZ phase-IV transmission scheme has been declared non-feasible - with the 6 GW renewable connectivity to be re-routed through Bikaner-I to IV pooling stations (commissioning Dec-2026 to Apr-2027) - and the OPGW scheme awarded to Jabalpur Transmission Company Ltd (JTCL/Indigrid) modified upward from Rs. 405.852 crores (6,676.1 km) to Rs. 411.352 crores (6,776.1 km) following CTUIL's revision of the 765 kV Jabalpur-Dharamjaygarh line length from 279.64 km to 379.64 km. 8237th OCCM approves May 2026 shutdown plan: Over 200 outage requests cleared for TSECL, NEEPCO, POWERGRID The 237th operational co-ordination committee meeting (OCCM) shutdown schedule for May 2026 lists more than 200 outage requests for pre-monsoon maintenance and system improvement on transmission elements owned by Tripura State Electricity Corporation Ltd (TSECL), North Eastern Electric Power Corporation (NEEPCO) and POWERGRID, including 132kV Agartala-Rokhia-1, 132kV Biswanath Chariali-Pavoi-1 and 132kV/33kV Ranganadi ICT-1 (RQ31627, RQ31807), all scheduled for 01-May-2026 from 09:00 to 16:00 hrs subject to availability conditions on parallel circuits. 8POWERGRID schedules 30 April 2026 board meeting on unsecured rupee term loan fund raising Power Grid Corporation of India Limited (NSE: POWERGRID, BSE scrip code 532898, ISIN INE752E01010), with corporate office at 'Saudamini', plot no. 2, sector-29, Gurugram-122001 (CIN L40101DL1989GOI038121), has informed both stock exchanges on 27 April 2026 through company secretary Satyaprakash Dash that its board of directors will meet on Thursday, 30 April 2026 to consider a fund-raising proposal through unsecured rupee term loan/line of credit (bank facility), in compliance with regulation 29(1)(d) of SEBI LODR regulations 2015. 8Southern RLDC planned transmission outage report April 27, 2026: POWERGRID 400KV Ramagundam lines under long-term outage since March 2023 Grid Controller of India's southern RLDC transmission outage report for 27 April 2026 reveals that 400KV POWERGRID lines RAMAGUNDAM-TELANGANA_STPP-1 and STPP-2 have been on planned outage since 24 March 2023 (04:20 and 04:21), awaiting idle charge after field testing completion (FTC). Additionally, APTRANSCO's 400KV GMR-VEMAGIRI line has been under maintenance from 11 January 2024 for aux load switching. 8NLDC SCUC schedule for April 28, 2026: Vindhyachal stage-4 leads 237.3 MW dispatch at ECR of 205.2 paise/kWh Grid Controller of India's NLDC has published the security constrained unit commitment (SCUC) schedule for 28 April 2026 (published 27 April at 1500 hrs), showing Vindhyachal STPS stage-4 leading with 237.3 MW dispatch at ECR of 205.2 paise/kWh. North Karanpura STPS is scheduled for 648.41 MW at 211.8 paise/kWh, Kahalgaon stage-2 for 672.58 MW at 274.3 paise/kWh, and Simhadri-NTPC stage-1 for 432.28 MW at 322.2 paise/kWh.Details
8CERC grants category-V inter-state trading licence to Energy Advisory Services Pvt Ltd via petition 32/TD/2026 The Central Electricity Regulatory Commission (CERC), New Delhi, by order dated 27.04.2026 in petition no. 32/TD/2026, has granted a category 'V' inter-state trading licence under sections 14 and 15(1) of the Electricity Act 2003 to Energy Advisory Services Private Limited (EASPL), based at WeWork Enam Sambhav, BKC Mumbai-400051, after the petitioner satisfied the Rs. 2 crore net worth, 1:1 current/liquidity ratio (per audited special balance sheet as on 30.11.2025) and full-time professional norms with Ms. Sadhu Madhuri (5+ years finance) and Mr. Sri Rama Chandra Murthy L. (18+ years power sector). 8CERC reserves order on Neufo Technologies Pvt Ltd's inter-state trading licence bid via petition 93/TD/2026 The Central Electricity Regulatory Commission (CERC), New Delhi, in petition no. 93/TD/2026 dated 27.04.2026, has reserved its order on Neufo Technologies Private Limited's (Pune-headquartered, Lodha Supremus, Sion Mumbai-400022) application under sections 14 and 15(1) of the Electricity Act 2003 for a category 'V' inter-state trading licence after the petitioner submitted via affidavit dated 13.04.2026 the audited special balance sheet, full-time professional documents and condonation request for delayed notice publication, in compliance with the record of proceedings dated 25.03.2026. 8WRPC issues DSM settlement statements for 06-12 April 2026 week under CERC regulations 2024 The Western Regional Power Committee (WRPC), Mumbai, vide letter no. WRPC/Comml.-I/4/ABTDSM/2026/4.2/11247-11376 dated 21.04.2026, has issued the deviation settlement mechanism (DSM) statements for the week 06.04.2026 to 12.04.2026 covering payable/receivable particulars in line with CERC DSM regulations 2024, CERC ancillary services regulation 2022 and the TRAS detailed procedure dated 18.04.2023, with 15-minute block-wise data implemented through schedule data received from WRLDC on 20.04.2026 and reference rates calculated as per the 94th CCM held on 14.08.2025. 8RERC notifies resource adequacy framework regulations 2026 via notification no. 162 in 24 April 2026 gazette The Rajasthan Electricity Regulatory Commission (RERC) notification no. RVVA/Sachiv/Vinniyam/162 dated 30 March 2026, published in the Rajasthan Gazette Vaisakha 04/April 24, 2026 (Saka 1948), introduces the 'Rajasthan Electricity Regulatory Commission (framework for resource adequacy) regulations 2026' - a 28-clause/8-chapter framework applicable to generating companies, distribution licensees, state load despatch centre and state transmission utility - mandating LT-DRAP demand-forecasting, capacity credit calculation, loss of load probability planning, EENS targets and long-term (>5 years) procurement governance, while repealing the RERC (power purchase & procurement process of distribution licensee) regulations 2004. 8Grid Controller of India NLDC publishes revision-1 of detailed procedure for tertiary reserve ancillary service (TRAS) under CERC regulations 2022 Grid Controller of India Limited (formerly POSOCO), NLDC, New Delhi, has published revision-1 (April 2026) of the detailed procedure for tertiary reserve ancillary service (TRAS), prepared in compliance with CERC (ancillary services) regulations 2022. The document sets out preamble, scope, definitions and operational procedures for TRAS implementation under the national grid's ancillary services framework.
HERC, TNERC & STATE COMMISSION ORDERS
8HERC grants HPPC source approval for 287.55 MW May & 337.68 MW June-Sep 2026 power from northern CGS pool The Haryana Electricity Regulatory Commission (HERC), Panchkula, by order dated 27.04.2026 in case no. HERC/petition no. 26 of 2026 (coram chairman Nand Lal Sharma, members Mukesh Garg and Shiv Kumar), has granted Haryana Power Purchase Centre (HPPC) source approval under section 86(1)(b) of the Electricity Act 2003 for 287.55 MW in May 2026 and 337.68 MW for June-September 2026 from the unallocated quota of central generating stations of northern region - citing projected deficits of 1,278 MW (May), 2,870 MW (June), 2,943 MW (July), 1,766 MW (August) and 635 MW (September) and FY 2026-27 peak demand expectation of 16,454 MW. 8TNERC lists 12 MW solar PM-KUSUM tender and Rs. 123 lakh/MW Greenko PSP tariff among 8 cases for 28 April hearing The Tamil Nadu Electricity Regulatory Commission (TNERC) cause list no. 29/2026 for forenoon hearing on 28.04.2026 (court hall, 11:00 AM, virtual & physical mode) features eight matters including TANTRANSCO/TNPDCL's M.P. no. 13 of 2026, TNPDCL's request to ratify deviation from clause 8.5 of TBSCB guidelines for procurement of 500 MW pumped storage capacity from a single bidder, P.P.A.P. no. 5 of 2026 to adopt tariff for 12 MW PM-KUSUM 'component A' solar plants, P.P.A.P. no. 6 of 2026 seeking section 63 approval of Rs. 123 lakhs/MW/annum annual fixed charge for 500 MW from M/s Greenko AP01 IREP Private Limited at 22.5% declared cycle loss, and Hindustan Unilever Limited's M.P. no. 46 of 2025 seeking refund of Rs. 19,54,290 from TNPDCL. 8HERC announces 14 May 2026 public hearing on UHBVNL & DHBVNL plea to defer FPPAS recovery at 47 paise/unit The Haryana Electricity Regulatory Commission (HERC), Bays no. 33-36, sector-4, Panchkula-134112, has issued a public notice for hearing on 14.05.2026 at 11:30 AM on petitions filed by Uttar Haryana Bijli Vitran Nigam Limited (UHBVNL) and Dakshin Haryana Bijli Vitran Nigam Limited (DHBVNL) - HERC/petition no. 7 of 2026 and HERC/petition no. 18 of 2026 - invoking removal of difficulty/relaxation under regulation 68 of MYT regulations 2024 to seek exemption from monthly fuel and power purchase adjustment surcharge (FPPAS) for FY 2025-26 and instead recover the same with carrying cost at a uniform rate of 47 paise per unit across all consumer categories, with stakeholder objections due by 01.05.2026. 8Tamil Nadu electricity ombudsman issues order no. 67 of 2025 from Chennai-600032 office on 27 April 2026 The Tamil Nadu electricity ombudsman, 4th floor, SIDCO corporate office building, Thiru-vi-ka industrial estate, Guindy, Chennai-600032 (phone +91-044-2953 5816, email elecobmn.tnerc@tn.gov.in), has issued order no. 67 of 2025 dated 27.04.2026 in a consumer petition involving a 110 KV substation connection in the Maraimalainagar area (pin 603 209/603 210) of Chengalpattu district, with the Tamil-language order copy circulated to the petitioner, TNPDCL superintending engineer (EDC Maraimalainagar), TANGEDCO chief engineer (distribution) Madurantakam, the chairman & managing director of TANGEDCO and the secretary, TNERC. 8JODHPUR DISCOM submits corrected SoP-1 Q3 quarterly report for FY 2025-26 to RERC on 16 April 2026 Jodhpur Vidyut Vitran Nigam Limited (Jodhpur DISCOM, CIN U40109RJ2000SGC016484), New Power House, Jodhpur-342003, vide letter no. JdVVNL/SE(RA&C)/JU/2025-26/D.16-19 dated 16 April 2026, the superintending engineer (RA&C) Ghanshyam Chouhan has submitted the corrected SoP-1 format of the Q3 quarterly report for FY 2025-26 to the secretary, Rajasthan Electricity Regulatory Commission (RERC), Vidyut Niyamak Bhawan, Sahkar Marg, Near Sigur Court Circle, Jaipur-302005, citing reference letter no. RVPN/CCM/Sec/JE(Tech-1)/D./Sf., dt 18.02.2025.
APTEL PROCEEDINGS
8APTEL resumes hearing in DVC vs West Bengal electricity cases (appeals 190 and 216 of 2019) on 27 April 2026 The Appellate Tribunal for Electricity (APTEL), in appeal nos. 190 and 216 of 2019, held proceedings on 27 April 2026 before officiating chairperson Ms. Seema Gupta and judicial member Mr. Virender Bhat. Damodar Valley Corporation (DVC Towers, VIP Road, Kolkata-700054) appears as appellant against the West Bengal Electricity Regulatory Commission and West Bengal State Electricity Distribution Company Limited. 8APTEL court-I list of finals as on April 27, 2026: Matters in chronological order for hearing per order dated July 15, 2022 in DFR-180/2021 The Appellate Tribunal for Electricity (APTEL) has published the list of finals for court-I as on 27 April 2026, listing electricity cases in chronological order (date of filing) for final hearing, per the direction of the hon'ble bench vide order dated 15 July 2022 in DFR-180/2021. Counsel are requested to confirm inclusion and remain prepared for hearing as cases come up in sequence. 8APTEL court-II list of finals April 27, 2026: Age-wise pending appeals including Gujarat Urja Vikas and Tata power cases The Appellate Tribunal for Electricity (APTEL) has released the court-II list of finals as on 27 April 2026, listing cases in chronological (age-wise) order with pleadings complete and ready for hearing, including landmark references from Gujarat Urja Vikas Nigam Ltd. (appeal 2/2015), Jaiprakash Power Ventures (appeal 232/2016), and Tata Power Company - transmission (appeal 280/2021). 8HPPCL land acquisition court lists 38 Renukaji dam project cases for 11 May 2026 hearing in Shimla The court of land acquisition collector, Himachal Pradesh Power Corporation Limited (HPPCL), Shimla-9, presided by Sh. Rayeesh Chandel, will hear 38 cases on 11.05.2026 at the BCS Shimla-9 venue, with the bulk of petitions filed against the Renukaji dam project & Ors and the principal secretary (power), government of Himachal Pradesh, including case nos. 1/2019, 5/2020, 30/2024, 88/2024, 9/2026 and 131/2025 covering admissions, replies, written statements, arguments, rejoinders and filing of legal representatives. 8APTEL court-I short matters list April 27, 2026: Indraprastha power vs DERC (case 27/2014), Sai service vs MERC among pending cases The Appellate Tribunal for Electricity (APTEL) court-I has published its short matters list as on 27 April 2026, featuring cases including Indraprastha Power Generation Co. Ltd. vs. Delhi Electricity Regulatory Commission & Ors. (cases 27, 28, 32/2014, filed December 2013), Sai Service Pvt. Ltd. vs. Maharashtra Electricity Regulatory Commission (case 194/2017), and other pending cases scheduled for hearing.Details
8Coal India reports all-India coal stock at 47,459.3 thousand tonnes across 146 linkage plants on 23 April 2026 The Coal India Limited (CIL) marketing & sales division coal stock position report as on 23-04-2026, prepared on the CEA reporting basis, shows total all-India coal stock of 47,459.3 thousand tonnes (indigenous 46,937.7 + imported 521.5) covering 21 days, with Haryana plants Indira Gandhi STPP holding 579.2 TT (34 days), Mahatma Gandhi TPS 499.7 TT (36 days) and Rajiv Gandhi TPS 643.3 TT (50 days), and Punjab plants GH TPS Lehra Mohabbat 393.4 TT (35 days), Goindwal Sahib TPP 205.0 TT and Rajpura TPP 425.7 TT - Bongaigaon TPP in Assam at 219.1 TT (30 days). 8CIL coal stock position on 25 April 2026 drops to 46,782.2 thousand tonnes amid 20-day cover trend The Coal India Limited (CIL) marketing & sales division coal stock position report as on 25-04-2026 records all-India total stock of 46,782.2 thousand tonnes (indigenous 46,250.5 + imported 531.8) at 20 days of cover - Haryana's Indira Gandhi STPP at 572.8 TT (33 days), Mahatma Gandhi TPS at 487.6 TT (33 days), Panipat TPS at 471.7 TT (66 days), Rajiv Gandhi TPS at 628.1 TT (48 days) and Yamuna Nagar TPS at 360.8 TT (61 days), with Bongaigaon TPP (Assam) carrying 219.8 TT (27 days). 8CEA daily coal stock report for 26 April 2026: 221,940 MW plants hold 54,750 thousand tonnes - 73% of normative The Central Electricity Authority (CEA) fuel management division daily coal stock report as on 26-04-2026 covers 221,940 MW of monitored capacity at 71% PLF with 24-day stock requirement - total all-India stock at 54,750.3 thousand tonnes (50,898.3 indigenous + 3,852.1 imported) standing at 73% of normative - with 20 plants flagged as critical, including HPGCL plants Panipat TPS (464.5 TT, 174% of normative), Rajiv Gandhi TPS (625.7 TT, 132%), Yamuna Nagar TPS (360.3 TT, 152%), and Rajasthan plants Chhabra-II TPP (239.4 TT, 54%, critical), Suratgarh TPS (333.9 TT, 59%, critical), Kalisindh TPS (283.9 TT, 68%) and Kota TPS (497.5 TT, 103%). 8CARE ratings reaffirms Coal India limited's CARE AAA stable rating on enhanced bank facilities of Rs. 8,605.38 crore CARE Ratings has reaffirmed Coal India Limited's (CIL) CARE AAA; stable rating on long-term bank facilities enhanced to Rs. 8,605.38 crore (from Rs. 8,492 crore), and reaffirmed CARE A1+ on short-term facilities of Rs. 5,625 crore (enhanced from Rs. 5,275 crore), citing CIL's majority GoI ownership and strategic national energy role as key rating strengths. 8CARE ratings flags Sunfuel Technologies LLP's Rs. 5.78 crore facility under 'issuer not cooperating' category CARE Ratings has maintained the CARE B-; stable rating of Sunfuel Technologies LLP (STL) on its Rs. 5.78 crore long-term bank facility under the 'issuer not cooperating' category, as STL failed to provide requisite information since 18 March 2025, and the rating is based on best available information only.Details
8CEA: All-India renewable generation hits 498.19 MU on 24 April 2026 with Rajasthan topping at 248.84 MU The Central Electricity Authority's (CEA) renewable project monitoring division daily renewable generation report for 24-April-2026 records 125.65 MU wind, 344.54 MU solar and 28 MU bio/bagasse/small-RES = 498.19 MU all-India total, with Rajasthan leading single-state output at 248.84 MU (16.54 wind + 229.73 solar + 2.57 others), Gujarat 271.98 MU (97.80 wind + 174.18 solar), northern region 286.55 MU, western region 369.56 MU and southern region 165.10 MU - cumulative April-2026 generation reaching 11,936.31 MU with Rajasthan at 5,627.37 MU and Gujarat at 5,799.11 MU. 8CEA daily RE generation report for 25 April 2026: All-India total drops to 461.53 MU; Rajasthan leads at 217.05 MU The Central Electricity Authority (CEA) renewable project monitoring division daily renewable generation report for 25-April-2026 logs 94.69 MU wind, 340.17 MU solar and 26.67 MU bio/bagasse/others - totaling 461.53 MU all-India - with Rajasthan generating 217.05 MU (9 wind + 206.66 solar + 1.39 others), Gujarat 274.97 MU (85.54 wind + 189.43 solar), Tamil Nadu 68.24 MU, Karnataka 72.14 MU and Maharashtra 44.99 MU - taking cumulative April-2026 generation to 12,397.84 MU with northern region at 6,760.21 MU and western region at 8,554.38 MU. 8CEA RE generation bounces to 496.61 MU on 26 April 2026; Gujarat wind hits 113.87 MU The Central Electricity Authority (CEA) renewable project monitoring division daily renewable generation report for 26-April-2026 records 128.26 MU wind, 341.23 MU solar, 27.12 MU others - totaling 496.61 MU all-India - with Gujarat wind generation jumping to 113.87 MU and total state output of 282.84 MU, Rajasthan 245.40 MU (19.11 wind + 224.85 solar), Maharashtra 48.91 MU, Karnataka 79.40 MU, Tamil Nadu 68.47 MU; cumulative April-2026 stood at 12,894.45 MU with northern region 7,043.11 MU, western region 8,931.69 MU and southern region 4,515.01 MU. 8RERC hikes 2025-26 RPO target to 33.01% with first amendment regulations effective 1 April 2026 The Rajasthan Electricity Regulatory Commission (RERC) notification no. RVVA/Sachiv/Vinniyam/163 dated 30 March 2026, published in Rajasthan Gazette Vaisakha 04/April 24, 2026 (Saka 1948), introduces the RERC (renewable purchase obligation) (first amendment) regulations 2026 effective 01.04.2026 - adding a new 'distributed renewable energy' definition for projects up to 10 MW (covering net-metering/gross-metering/virtual/group net-metering/behind-the-meter), revising RPO targets to 2.46% wind + 1.08% HPO + 26.37% other = 29.91% for FY 2024-25 and 3.36% wind + 1.48% HPO + 28.17% other = 33.01% for FY 2025-26. 8Green power commissioning: Subsidiary Gamma green power activates 1 no. of 3.3 MW wind turbine generator unit Greenpower (BSE: 533263, NSE: GREENPOWER) has informed stock exchanges under regulation 30 of SEBI LODR 2015 that its subsidiary, M/s Gamma Green Power Private Limited, has successfully commissioned 1 wind turbine generator (WTG) of 3.3 MW capacity, further to its intimation to exchanges dated 2 February 2026, regarding the wind energy project agreement. 8Premier energies unveils India's first all-black G12R DCR solar module at RenewX Chennai; files press release under SEBI regulation 30 Premier Energies Limited (BSE: 544238, NSE: PREMIERENE) has disclosed via a press release filed under regulation 30 of SEBI LODR 2015 (Ref: PEL 05/2026-27, 27 April 2026) that the company has launched India's first all-black G12R domestic content requirement (DCR) solar module at RenewX Chennai, marking a significant product innovation milestone in India's solar manufacturing sector.
HYDRO GENERATION & RESERVOIRS
8CEA hydro reservoir report for 25 April 2026: Bhakra at 485.95m; Pong at 406.90m; April 2026 cumulative hydro generation 210.2 MU The Central Electricity Authority (CEA) daily hydro reservoir report sub-report-6 for 25-Apr-2026 shows Bhakra (Himachal Pradesh) at 485.95m with energy content 637.79 MU and cumulative April 2026 hydro generation of 210.2 MU (up from 199.89 MU on 24 April). Pong reservoir is at 406.90m (FRL: 426.72m), Tehri at 2,479 ft / 109.18 MU (cumulative 133.51 MU), Sardar Sarovar at 426.44 ft / 942.76 MU (cumulative 199.90 MU), Koyna at 2,087.01 ft / 1,052.24 MU (cumulative 565.08 MU), and Idukki at 2,333.83 ft / 679.81 MU (cumulative 228.42 MU). 8Southern RLDC reservoir report: Idukki at 710.98m, Srisailam at 249.51m as on April 27, 2026; 14 major reservoirs monitored Grid Controller of India's southern RLDC reservoir report for 27 April 2026 shows 14 major reservoirs under monitoring: Idukki at 710.98m (energy content 702.7 MU), Srisailam at 249.51m (59.53 MU), Mettur at 750.53m (69.67 MU), and Linganamakki at 539.19m (1,150.54 MU), with inflows and last-year comparisons tracked for hydro generation planning. 8Eastern region generation outages April 27, 2026: OHPC units 4 & 5 at Burla HPS under annual maintenance The eastern region generation outages report for 27 April 2026 (dated 28 April) shows OHPC's Burla HPS/Hirakud: unit 4 (32 MW hydro) under annual maintenance since 21 April 2026 (expected return 10 May), and unit 5 (43.65 MW hydro) under annual maintenance since 19 January 2026 (expected return 30 April). The Balimela HPS is also listed under repair/maintenance.Details
8CEA daily generation overview for 25 April 2026: All-India output 5,140.01 MU beats programme by 6.93% The Central Electricity Authority (CEA) daily generation report sub-report-1 for 25-Apr-2026 shows all-India total generation of 5,140.01 MU against programme of 4,808.57 MU - total thermal at 4,520.35 MU, nuclear 169.38 MU, hydro 443.17 MU - with northern region total 1,316.64 MU vs programme 1,180.67 MU, western 1,868.71 MU vs 1,712.71 MU, southern 1,052.16 MU and eastern 836.31 MU; cumulative thermal generation reached 100,024.72 MU and all-India cumulative 113,258.55 MU. 8CEA fuel-wise generation for 25 April 2026: Coal output 4,259.55 MU; gas surges to 163.74 MU vs 89.03 MU target The Central Electricity Authority (CEA) daily generation report sub-report-17 for 25-Apr-2026 records coal 4,259.55 MU vs 4,076.71 MU programme, lignite 95.89 MU vs 111.32 MU, natural gas 163.74 MU vs 89.03 MU (+84%), diesel 1.17 MU, total thermal 4,520.35 MU vs 4,277.06 MU, nuclear 169.38 MU vs 182.80 MU, hydro 443.17 MU vs 348.71 MU, Bhutan imports 7.11 MU - all-India total 5,140.01 MU vs 4,808.57 MU programme; cumulative April-2026 thermal generation reached 100,024.72 MU and all-India 113,258.55 MU. 8CEA NTPC generation overview for 25 April 2026: 1,119.29 MU actual vs 1,053.27 MU programme with northern region at +15.8% The Central Electricity Authority (CEA) daily generation report sub-report-8 for 25-Apr-2026 records all-India NTPC monitored capacity 57,617.23 MW with 49,633.88 MW available - actual 1,119.29 MU vs programme 1,053.27 MU (+66.02 MU surplus) - northern region 243.57 MU vs 210.39 MU (+33.18 MU), western 418.30 MU vs 382.88 MU (+35.42 MU), southern 176.38 MU vs 149.18 MU, eastern 265.79 MU vs 296.56 MU (-30.77 MU shortfall) and north-eastern 15.25 MU; cumulative April actual 24,024.87 MU vs programme 25,588.57 MU (-6.11% shortfall). 8NRLDC March 2026 report: Northern region posts 1,271.9 MU peak energy met and 68,098 MW max demand on 6 March The Northern Regional Load Despatch Centre (NRLDC) operational monthly report for March 2026 records northern region peak energy met of 1,271.9 MU on 13-Mar-2026, maximum demand of 68,098 MW on 06-Mar-2026 at 09:00 hrs, zero shortage across all states, total monthly thermal generation of 21,768.3 MU, hydro 8,602.4 MU, solar 6,127.7 MU and wind 929.2 MU - with state-wise highs including Uttar Pradesh 18,841 MW max demand, Punjab 11,317 MW and Haryana 9,381 MW, and noting a 500 KV HVDC Balia-Bhiwadi bipole tripping incident on 28-Mar-2026 between 00:52 and 02:58 hrs lasting 02:06 hours, attributed by Power Grid to filter and AC supply faults. 8CEA all-India capacity availability for 25 April 2026: 264,437 MW online with 45,279 MW (14.62%) under outage The Central Electricity Authority (CEA) daily generation report sub-report-3 for 25-Apr-2026 records improvement in capacity availability - total monitored 309,716.29 MW with 6,989.30 MW planned maintenance + 28,716.11 MW forced + 9,573.82 MW others = 45,279.23 MW outage (14.62%) - northern 69,185.14 MW online (12,511.58 MW out), western 91,318.38 MW online (13,384.02 MW out, improvement of 3,125 MW over previous day), southern 58,742.27 MW, eastern 41,017.26 MW, and north-eastern 4,174.01 MW online - total online 264,437.06 MW.
PLANT MAINTENANCE & OUTAGES
8CEA daily maintenance report for 25 April 2026: 16,445 MW out as "others"; Jawaharpur unit-2 trips at 19:37 The Central Electricity Authority (CEA) daily maintenance report sub-report-10 for 25-04-2026 records 3,978.50 MW planned, 4,593.51 MW forced and 16,445 MW "others" as all-India total - with new entrants Jawaharpur STPP unit-2 (660 MW, turbine misc, 25/04/2026 19:37), Yadadri TPS unit-1 (800 MW, boiler aux misc, 20/04/2026), Yermarus TPP unit-2 (800 MW, super heater tube leakage), Maharashtra's Mauda TPS unit-3 returning 25/04/2026 04:58, and Tanda TPS units 1-2 (110 MW each since 30/06/2025) under fuel conservation/RSD. 8CEA long-outage report for 25 April 2026: 31,381.21 MW out for 15+ days including Tripura CCPP-2 (363.30 MW) The Central Electricity Authority (CEA) daily generation report sub-report-12 for 25-Apr-2026 totals 31,381.21 MW in long-duration outages - slightly higher than previous day - including Pragati CCPP series (104.60 MW units, grid disturbances/cooling water issues), Yamuna Nagar TPS unit-2 (300 MW), Rajiv Gandhi TPS unit-2 (600 MW), Mahatma Gandhi TPS unit-2 (660 MW), Faridabad CCPP units 1-3, GH TPS Lehra Mohabbat unit-2 (210 MW since 31/08/2025), Mejia TPS unit-2 (210 MW), IB Valley TPS unit-1 (210 MW since 06/03/2026) and Monarchak CCPP unit-2 (35.60 MW since 18/07/2025). 8CEA year-plus outage report stays at 6,113.91 MW as on 25 April 2026 with units idle since as far back as 1988 The Central Electricity Authority (CEA) daily generation report sub-report-13 for 25-Apr-2026 maintains the same 6,113.91 MW total of thermal/nuclear capacity out of grid for over one year - covering long-dormant units including I.P. CCPP units 2-9 (since 25/01/2019), Rithala CCPP, Pampore GPS liquid (since 01/02/2012), Giral TPS (since 2014/2016, likely scrapped), DAE Rajasthan, P. Nallur CCPP unit-1 (330.50 MW since 01/05/2022), Haldia GT (since 1988/2002), Kasba GT (since 26/06/2002), Titagarh TPS (since October 2016) and Lakwa GT-7 (20 MW since 08/04/2024). 8CEA: 9,529.69 MW recommissioned on 25 April 2026 featuring Barh STPS unit-3 & unit-4 (660 MW each) The Central Electricity Authority (CEA) daily generation report sub-report-14 for 25-Apr-2026 records 9,529.69 MW thermal/nuclear capacity recommissioned - including Barh STPS unit-3 (660 MW, water wall tube leakage, returned 25/04 15:30), Barh STPS unit-4 (660 MW, returned 25/04 18:52), Durgapur steel TPS unit-2 (500 MW, returned 25/04 23:25), Adani Raipur TPP unit-2 (685 MW, returned 25/04 11:00), Shree Singaji TPP unit-2 (600 MW, returned 25/04 22:02), Mauda TPS unit-3 (660 MW, returned 25/04 04:58), Bhusawal TPS unit-5 (500 MW, returned 14:45), and Wanakbori TPS units 1, 2, 5 (210 MW each). 8CEA 500+ MW maintenance report for 25 April 2026 adds Koradi unit-8 (660 MW) for super-heater tube leakage The Central Electricity Authority (CEA) daily maintenance report for 500 MW+ units on 25-04-2026 covers Jawaharpur STPP unit-2 (660 MW, turbine misc, 25/04 19:37), Marwa TPS unit-2 (500 MW, water wall tube leakage), Vedanta Chhattisgarh unit-1 (600 MW), Sasan UMTPP unit-2 (660 MW, boiler overhaul), Bhusawal TPS unit-5 (500 MW, returned 25/04 14:45), Koradi TPS unit-8 (660 MW, super heater tube leakage 25/04 05:59), Damodaram Sanjeevaiah units 1 & 3 (800 MW each), and Telangana's Yadadri TPS units 1 & 2 (800 MW each). 8CEA capacity utilization for 25 April 2026: 45,279 MW (14.62%) outage, net generation 241,501 MW The Central Electricity Authority (CEA) daily generation report sub-report-16 for 25-Apr-2026 shows all-India 309,716.29 MW monitored capacity with 45,279.23 MW (14.62%) under outage - improvement over previous day - coal at 22,657.01 MW out (10.21%, 202,203.83 MW gross, 92.33% of capacity online), gas/liquid at 9,650.10 MW out (47.96%), hydro at 10,612.12 MW out (20.54%, 35,765.92 MW gross), nuclear at 1,040 MW out (11.85%, 7,665.25 MW gross 87.65% of capacity online) - total max power generated 241,501.14 MW representing 91.33% of capacity online.
REGIONAL POWER SUPPLY REPORTS
8Northern region power supply April 27, 2026: 68,840 MW evening peak met with 155 MW shortage; day energy 1,633 MU Grid Controller of India's northern RLDC daily operation report for 27 April 2026 (dated 28 April) reveals an evening peak demand of 68,995 MW against 68,840 MW met, resulting in a 155 MW shortage at 50.065 Hz. Off-peak saw zero shortage (66,497 MW, 50.038 Hz). Total northern region day energy met was 1,633 MU with 0.47 MU shortage, tracked across Delhi, Haryana, Himachal Pradesh, Punjab, Rajasthan, UP, Uttarakhand and J&K. 8Southern region power supply: 59,206 MW evening peak demand met without shortage on 27 April 2026; day energy 1,475.62 MU Grid Controller of India's southern RLDC power supply position report for 27 April 2026 confirms zero shortage at the 59,206 MW evening peak (20:00) and 54,421 MW off-peak (03:00) with frequency at 50.08 Hz and 50.05 Hz respectively. Total day energy met was 1,475.62 MU. Andhra Pradesh alone met 106.27 MU net scheduled drawal with negligible UI of -0.06 MU. 8Western region power supply April 27, 2026: 71,075 MW evening peak met; day energy 1,700+ MU with zero shortage Grid Controller of India's western RLDC daily operation report for 27 April 2026 confirms zero power shortage at the evening peak of 71,075 MW (50.14 Hz) and 68,801 MW off-peak (50.04 Hz). Maharashtra, Gujarat, Madhya Pradesh, Chhattisgarh, Goa and other western region states contributed to the total western region day energy of over 1,700 MU with no shortfall reported. 8North eastern region power supply April 27, 2026: 2,638 MW evening peak met without shortage; day energy 48.28 MU Grid Controller of India's north eastern RLDC daily operation report for 27 April 2026 (reported 28 April) confirms zero power shortage with 2,638 MW met at the 20:00 evening peak and 1,402 MW at the 03:00 off-peak, with grid frequency at 50.06 Hz and 50.04 Hz respectively. Total north eastern region day energy met was 48.28 MU with zero shortage. 8Eastern region daily operation report April 27, 2026: 28,259 MW evening peak met with zero shortage; day energy 642.45 MU Grid Controller of India's eastern RLDC daily operation report for 27 April 2026 (reported 28 April) shows zero shortage at the 28,259 MW evening peak (20:00, freq: 50.06 Hz) and 24,697 MW off-peak (03:00, freq: 50.04 Hz). Total eastern region day energy met was 642.45 MU, with individual state-level thermal, hydro, renewable, and gas/diesel generation and drawal details tracked across all eastern states.
GRID FREQUENCY & SYSTEM RELIABILITY
8NLDC frequency profile April 27, 2026: Grid operates at 50.031 Hz average; within IEGC band 96.78% of time Grid Controller of India Limited's National Load Despatch Centre has published the frequency profile for 27 April 2026, showing an average grid frequency of 50.031 Hz and time within the IEGC target band (49.97-50.03 Hz) of 29.65%. The frequency stayed within the IEGC wider band (49.7-50.2 Hz) for 96.78% of the day, with 61.37% of time in the 50.0-50.1 Hz range. 8Grid Controller of India NLDC system reliability report April 27, 2026: Zero ATC violations across all 5 national grid corridors Grid Controller of India Limited's National Load Despatch Centre has published the system reliability indices report for 27 April 2026 (dated 28 April), confirming zero ATC (available transfer capability) violations and zero N-1 criteria violations across all five national corridors - WR-NR, ER-NR, import of NR, NEW-SR and NER import - for the entire day, along with the daily voltage profile report. 8Western RLDC system reliability April 27, 2026: Maharashtra ATC violated 42.7% of day in 41 blocks; Chhattisgarh 2.1% violation Grid Controller of India's western RLDC system reliability indices for 27 April 2026 show Maharashtra with the highest ATC violation: 41 blocks (10.2 hours, 42.7% of the day). Chhattisgarh had 2 blocks (0.5 hours, 2.1% violation). Gujarat, Madhya Pradesh, Goa and DNHDDPDCL recorded zero ATC violations, with western region grid reliability broadly maintained despite Maharashtra's transmission stress. 8Southern RLDC system reliability report April 27, 2026: S1->S2&S3 corridor ATC violated 28.12% of time (6:45 hours); zero N-1 violations Power System Operation Corporation's southern RLDC system reliability indices report for 27 April 2026 shows the S1->S2&S3 corridor with ATC (available transfer capability) violated in 27 blocks for 6 hours 45 minutes (28.12% of the day), while S1->S2&S3 N-1 criteria was violated in 17 blocks for 4:15 hours (17.71%). Import of S3 corridor recorded zero violations for both ATC and N-1 criteria. 8Southern RLDC generation report for April 27, 2026: Andhra Pradesh demand met at 10,512 MW with Jindal power contributing 422 MW Grid Controller of India's southern RLDC generation report for 27 April 2026 (reported 28 April) shows Andhra Pradesh's total demand met at 10,512 MW with net consumption of 273.66 MU. Jindal Power Limited (Simhapuri unit) contributed 422 MW (10.13 MU gross), while Greenko pumped hydro contributed 465 MW (11.16 MU), with Gautami CCPP and GMR Barge plants reporting zero generation.Details
8IEX day-ahead market hits Rs. 10,000/MWh price cap through most of 27 April 2026 with 7,792 MW MCV at 11AM The Indian Energy Exchange (IEX) day-ahead market 15-minute block snapshot for 27-04-2026 shows the market clearing price (MCP) hitting the Rs. 10,000/MWh price ceiling through morning, evening and night blocks, dropping to Rs. 2,242.73/MWh during the solar peak at 11:00-11:15 hrs (MCV 7,792.10 MW), with purchase bids ranging from 51,093.80 MW (00:00) to 16,387.50 MW (11:00) and sell bids climbing from 1,104.30 MW to 34,087.30 MW as solar generation flooded the market mid-day. 8IEX day-ahead market 27 April 2026 daily summary: 1,06,222 MWh cleared at average Rs. 7,078/MWh The Indian Energy Exchange (IEX) hourly day-ahead market summary for 27-04-2026 records total purchase bids of 7,61,649.16 MWh against sell bids of 2,99,730.38 MWh, with market clearing volume of 1,06,222.20 MWh and final scheduled volume identical, average MCP of Rs. 7,078.52/MWh and weighted MCP of Rs. 7,052.21/MWh - peak hourly MCV reached 9,401.02 MWh in hour 16 (15:00-16:00) while the lowest MCP of Rs. 2,074.73/MWh occurred in hour 13 (12:00-13:00). 8IEX DAM weekly round-up: 8.65 lakh MWh cleared between 21-28 April 2026 at average Rs. 6,663.79/MWh The Indian Energy Exchange (IEX) day-ahead market weekly snapshot from 21-04-2026 to 28-04-2026 shows total purchase bids of 50,69,001.42 MWh, sell bids of 29,14,623.89 MWh, MCV of 8,65,107.87 MWh and final scheduled volume of 8,63,583.85 MWh - with the highest single-day MCV of 1,15,320.44 MWh on 22-04-2026, lowest of 94,199.69 MWh on 26-04-2026, average MCP of Rs. 6,663.79/MWh and weighted MCP of Rs. 4,095.00/MWh, peaking at Rs. 7,078.52/MWh on 27-04-2026. 8IEX high price DAM activates briefly on 27 April 2026: 80 MW cleared at Rs. 20,000/MWh in single 21:30-22:00 window The Indian Energy Exchange (IEX) high price day-ahead market 15-minute snapshot for 27-04-2026 shows trading dormant through most of the day with sell bids hovering at 1,298.60-1,732.60 MW, suddenly activating at 21:30-21:45 with 60 MW cleared at the Rs. 20,000/MWh ceiling, peaking at 80 MW in 21:45-22:00, before falling silent again - daily totals: purchase bid 5,112.45 MWh, sell bid 38,608.60 MWh, MCV just 35 MWh at average MCP of Rs. 20,000/MWh. 8IEX HPDAM weekly snapshot logs 2,295 MWh cleared at average Rs. 19,663.96/MWh between 21-28 April 2026 The Indian Energy Exchange (IEX) high price day-ahead market weekly summary from 21-04-2026 to 28-04-2026 records aggregate purchase bids of 57,131.12 MWh and sell bids of 3,11,043.45 MWh, with total MCV of 2,295 MWh - peak day MCV being 1,476.55 MWh on 23-04-2026 at Rs. 18,812.63/MWh weighted MCP, and three back-to-back days (25, 26, 27 April) clearing at the Rs. 20,000/MWh ceiling, averaging Rs. 19,663.96/MWh weighted MCP across the eight-day window. 8PXIL high price DAM reports zero trading across all 96 blocks on 27 April 2026 The Power Exchange India Limited (PXIL) high price DAM 15-minute time-block snapshot for 27/04/2026 records zero purchase bids, zero sell bids, zero MCV, zero cleared volume, zero real-time curtailment loss, zero final scheduled volume and zero MCP across every fifteen-minute block from 00:00-00:15 through 23:45-24:00 - with daily totals, maxima, minima and averages all at 0.00 MWh.
GREEN DAY-AHEAD MARKET (GDAM)
8IEX green DAM 15-minute profile for 27 April 2026 caps at Rs. 10,000/MWh in off-peak, drops to Rs. 1,580 at 13:30 solar block The Indian Energy Exchange (IEX) green day-ahead market 15-minute time-block snapshot for 27-04-2026 shows non-solar GDAM MCP staying at the Rs. 10,000/MWh ceiling during early-morning and night hours, with the lowest cleared price of Rs. 1,580/MWh recorded in the 13:30-13:45 solar block, hydro MCV consistently around 6 MW for early hours dropping to 3 MW from 03:00, and total purchase bids ranging from 15,956.5 MWh down to 6,842.28 MWh during the solar export window. 8IEX GDAM 27 April 2026 hourly summary: Solar MCV peaks at 2,649 MWh in hour 14 with Rs. 1,585.15/MWh MCP The Indian Energy Exchange (IEX) green DAM hourly snapshot for 27-04-2026 logs the day's solar surge between hour 9 (08:00-09:00) and hour 17 (16:00-17:00), with peak solar MCV of 2,649.23 MWh in hour 14 at Rs. 1,585.15/MWh, hydro MCV around 21.5 MWh through these hours, total non-solar contributions of 218 MWh in hour 14, and weighted MCP collapsing from Rs. 10,000/MWh in non-solar hours to a low of Rs. 1,580.67/MWh during peak generation. 8IEX green DAM weekly snapshot records 22.64 lakh MWh MCV with average MCP Rs. 6,803.09/MWh in 21-28 April 2026 The Indian Energy Exchange (IEX) green DAM weekly summary from 21-04-2026 to 28-04-2026 totals purchase bids of 17,83,799.36 MWh against sell bids of 30,87,328.66 MWh, MCV of 22,64,332.65 MWh (solar 16,88,303 MWh; non-solar 5,54,367 MWh; hydro 2,192.98 MWh), with the highest single-day MCV of 3,32,247.79 MWh on 23-04-2026 at average MCP of Rs. 6,733.01/MWh - and average daily weighted MCP of Rs. 3,954.49/MWh across the eight-day window peaking at Rs. 7,094.26/MWh on 28-04-2026. 8PXIL green day-ahead market records zero trades for 10 consecutive days between 19-28 April 2026 The Power Exchange India Limited (PXIL) green DAM weekly snapshot covering 10 delivery dates from 19/04/2026 to 28/04/2026 reports zero purchase bids, zero sell bids, zero MCV, zero cleared volume (solar/non-solar/hydro/total), zero curtailment, zero scheduled volume and zero MCP every single day - with totals, maxima, minima and averages all at 0.00 in the summary table.
REAL-TIME MARKET (RTM)
8IEX real-time market 27 April 2026 snapshot shows MCP crashing to Rs. 41.45/MWh in 07:45-08:00 block, daily avg Rs. 5,452.47/MWh The Indian Energy Exchange (IEX) real time market 15-minute snapshot for 27-04-2026 reveals dramatic price swings with MCP plunging to Rs. 41.45/MWh in the 07:45-08:00 block (sell bid 17,929.10 MW vs purchase 7,529.80 MW), recovering to Rs. 10,000/MWh in night hours, peak MCV of 13,131.70 MW at 22:00-22:15, daily totals of 3,95,469.80 MWh purchase bids, 3,20,040.15 MWh sell bids, 1,96,998.34 MWh MCV and average MCP of Rs. 5,452.47/MWh across 96 sessions. 8IEX RTM 27 April 2026 hourly recap: MCP drops to Rs. 899.80/MWh in hour 7, daily avg Rs. 5,452.47/MWh The Indian Energy Exchange (IEX) real time market hourly snapshot for 27-04-2026 records the day's lowest MCP of Rs. 899.80/MWh in hour 7 (06:00-07:00) when sell bids of 14,099.28 MWh exceeded purchase bids of 6,946.20 MWh, while peak MCV of 12,262.70 MWh hit hour 22, with daily totals: purchase bid 3,95,469.85 MWh, sell bid 3,20,040.19 MWh, MCV 1,96,998.37 MWh, average MCP Rs. 5,452.47/MWh and weighted MCP Rs. 5,442.17/MWh. 8IEX RTM weekly summary: 11.49 lakh MWh cleared at avg Rs. 5,974.32/MWh between 21-28 April 2026 The Indian Energy Exchange (IEX) real time market weekly snapshot from 21-04-2026 to 28-04-2026 records total purchase bids of 50,37,393.37 MWh, sell bids of 21,68,530 MWh, MCV of 11,49,537.91 MWh and final scheduled volume of 11,43,173.42 MWh - with the highest day MCV being 1,96,998.34 MWh on 27-04-2026 and the lowest at 85,256.34 MWh on 28-04-2026, average daily MCP of Rs. 5,974.32/MWh peaking at Rs. 7,576.70/MWh on 25-04-2026. 8PXIL RTM weekly profile records 17,622 MWh total MCV at Rs. 10,000/MWh average across 21-28 April 2026 The Power Exchange India Limited (PXIL) real time market weekly volume profile from 21-04-2026 to 28-04-2026 reports total MCV of 17,622.50 MWh and matching scheduled volumes - with 21-04-2026 leading at 7,387.50 MWh, 22-04-2026 at 3,225 MWh, 27-04-2026 at 3,500 MWh - every clearance occurring at the Rs. 10,000/MWh weighted MCP ceiling and total purchase bids reaching 2,21,706.90 MWh against sell bids of 17,822.50 MWh. 8PXIL RTM 27 April 2026 hourly profile: 14,000 MWh cleared at Rs. 10,000/MWh in late evening hours 20-23 The Power Exchange India Limited (PXIL) real time market hourly volume profile for 27-04-2026 records 14,000 MWh total cleared volume across four evening hours - 1,600 MWh in hour 20 (19:00-20:00), 4,600 MWh in hour 21 (20:00-21:00), 5,400 MWh in hour 22 (21:00-22:00) and 2,400 MWh in hour 23 (22:00-23:00) - all clearing at the Rs. 10,000/MWh weighted MCP, with 1,070 MWh purchase bids in hour 1 going un-cleared.
TERM-AHEAD MARKET & ANCILLARY SERVICES
8IEX GTAM trade data for 27 April 2026: Daily and DAC contracts cleared at Rs. 9,000-Rs. 10,000/MWh price band The Indian Energy Exchange (IEX) green term-ahead market trade data for delivery date 27-04-2026 shows uniform contract pricing at Rs. 9,600/MWh across DAILY contracts (DY1 through DY4 series for Mon-Sun, NS and S types) with 55 MWh traded in 4 trades each, while day-ahead contingency (DAC) instruments cleared at Rs. 9,850-Rs. 10,000/MWh with the DAC-RTC-NS contract recording 288 MWh weighted average at Rs. 9,962.50/MWh in 4 trades - buy and sell bid volumes matching at 55 each for the daily contracts. 8IEX term-ahead market records DAILY & INTRADAY trades at Rs. 9,000-Rs. 10,000/MWh on 27 April 2026 The Indian Energy Exchange (IEX) term ahead market trade details for delivery date 27-04-2026 capture DAILY contracts (F10 through F12 hour-series, hours H01-H24) cleared at Rs. 9,000/MWh with 10-30 MWh per contract in 1 trade each, and intraday contracts (ITD-H10 through ITD-H24) cleared at Rs. 10,000/MWh with 100-200 MWh per contract in 1-3 trades - buy and sell bid counts mostly matched at 1-3, providing nearly 24-hour delivery coverage across the term-ahead segment. 8PXIL ASDAM records zero bids and zero MWh cleared volume across all 96 time blocks on 27 April 2026 The Power Exchange India Limited (PXIL) ancillary services day ahead market (ASDAM) snapshot for delivery date 27/04/2026 confirms that all 96 fifteen-minute time blocks from 00:00-00:15 to 23:45-24:00 registered zero TRAS bids, 0.0000 MWh cleared volume and 0.0000 Rs/MWh weighted average MCP, with the daily total summary also at zero - indicating no tertiary reserve ancillary services activity was transacted on the platform that day. 8PXIL IDAS weekly profile logs 7,256 MWh total bids across 8 days from 21-28 April 2026 without clearance The Power Exchange India Limited (PXIL) intra-day ancillary services weekly market volume profile from 21-04-2026 to 28-04-2026 shows aggregate purchase bids of 7,256.25 MWh and sell bids of 19,441.25 MWh - peak being 2,975 MWh purchase on 24-04-2026 and 3,939.75 MWh sell on 23-04-2026 - with no day in the eight-day window registering any MCV, scheduled volume, MCP or weighted MCP clearance. 8HPX issues circular for Damodar Valley Corporation single side reverse auction (thermal, auction no. HPX/27042026/00959) on 27 April 2026 Hindustan Power Exchange (HPX) has issued circular no. HPX_RA_00930 dated 27 April 2026, announcing an any-day(s) single side reverse auction (LDC RA segment) with auction no. HPX/27042026/00959 for buyer Damodar Valley Corporation, for thermal energy at regional delivery point, with auction initiation and publishing date of 27 April 2026 and ceiling price: NA. 8PXIL DSM report records zero buy, zero sell and zero price across all 96 time periods on 27 April 2026 The Power Exchange India Limited (PXIL) deviation settlement mechanism (DSM) report for delivery date 27-Apr-2026 - covering 96 fifteen-minute time periods from 00:00-00:15 to 23:45-24:00 - confirms zero cleared buy MW, zero cleared sell MW and zero Rs./MWh price across every block, with the report generated on 28-04-2026 spanning 3 pages.Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days. Get the daily updates for : 8LNG 8Crude 8Chemicals 8Fertilizers 8LPG 8Ammonia 8Coal & Coke Click on Reports for more.Details
For reference purposes the website carries here the following tenders: 8Tender for construction of retaining wall and RCC brick at west side of 220/132/33 kV G/S/S Details 8Tender for work involving the shifting of electric poles, lines, and transformers Details 8Tender for provide the new connections and other works Details 8Tender for construction of 01 No. roof truss based store shed at 132 kV GIS sub station Details 8Tender for construction and renovation of control room, cable trench and yard Details 8Tender for construction and renovation of control room, cable trench and yard at 33/11 kV S/s Details 8Tender for implementation of field quality plan through engagement of third party for construction of 765 kV DC line Details 8Tender for overhauling of one unit of boiler pressure parts and other associated parts Details 8Tender for CPU regeneration area repair works Details 8Tender for construction of 01 No. 33kV feeder bay Details 8Tender for extension of fire hydrant system at 132kV S/s Details 8Tender for construction of 02 Nos. 33kV feeder bay at 220kV S/s Details 8Tender for supply and fixing of NIFPS spares at 220 kV substation Details 8Tender for SITC of trash rack panels Details 8Tender for work of providing & fixing of 100W LED street light set Details 8Tender for work of overhauling, servicing, repair and maintenance of 145kV circuit breakers Details 8Tender for supply of various ratings of 24 kV CT Details 8Tender for supply of gas sample relay of converter transformer Details 8Tender for work for replacing the RCC pipes Details 8Tender for work contract of job work related to day to day routine activity work in shift at hydro power plant Details 8Tender for supply and application of corrosion protection lining of 02 mm thickness Details 8Tender for construction of hume pipe culvert Details 8Tender for supply, installation, testing and commissioning of LED street light Details 8Tender for providing power supply arrangement Details 8Tender for providing barbed wire fencing along Details 8Tender for day-to-day diversion, shifting and extension of HT overhead lines Details 8Tender for diversion and extension of 6.6 kV HT feeders Details 8Tender for supply of various DCS system spares Details 8Tender for drip irrigation system Details 8Tender for repair and maintenance work Details 8Tender for job contract for weighbridge Details 8Tender for AMC civil for CHP Details 8Tender for lawn maintenance at cable yard Details 8Tender for lawn maintenance at switchyard Details 8Tender for supply fabrication and installation of concertina coil fencing around Details 8Tender for supply, installation, testing and commissioning of decorative lighting systems Details 8Tender for construction of additional foundations for 1no. 66kV line bay Details 8Tender for attending routine complaints related to water supply system Details 8Tender for protection work Details 8Tender for fabrication, supply, installation, testing and commissioning of 45 MT new draft tube gate Details 8Tender for servicing of 10MT single girder E.O.T crane installed Details 8Tender for work of replacement of defective main ACB of LT panel room including work Details 8Tender for construction of 11 kV LT line Details 8Tender for replacement of bear ACSR conductor Details 8Tender for work of doing MRI of KCC, non KCC, solar consumers Details 8Tender for procurement of 33kV CBs (circuit breakers) Details 8Tender for work of replacement of 110kV gantry at 110kV substation Details 8Designing, supplying and installation of structural glazing Details 8Tender for supply of 12V 26AH batteries Details 8Tender for supply, installation, testing commissioning and comprehensive AMC of lifts Details 8Tender for supply of BIS certified energy efficiency level Details 8Tender for complete overhauling of electrical wire rope hoist along Details 8Tender for reconducting DTR with covered and ABC Details 8Design, manufacturing testing and supply of 11 kV extensible type SCADA compatible RMU of various Details 8Design, manufacturing, testing, supply and delivery of 541No. various type of relays Details 8Tender for repair and strengthening of stub and offshoots including welding of various towers Details 8Tender for stub strengthening muff repair and offshoot repair of various 132 and 220kV lines Details 8Tender for work of construction of 1 no. addl. 20 MVA 66/11 kV TF plinth along with allied civil works Details 8Tender for providing RCC chamber with protection wall Details 8Tender for fabrication dismantling erection strengthening modification of various chutes hoppers wagon tipplers belt conveyors crusher houses Details 8Tender for augmentation of 132kV S/Stn. Details 8Tender for supply energy efficient blade assembly Details 8Tender for installation of additional transformers Details 8Tender for additional 50MVA, 220/22kV power transformer along Details 8Tender for misc. civil work Details 8Tender for construction of RCC pavements at various Details 8Tender for supply of various type of thermocouples and RTDs Details 8Tender for supply of liquor ammonia for chemical lab Details 8Tender for supply, erection, testing and commissioning of 220 V DC, 510AH, KBH, Ni-Cd type battery set Details 8Tender for work of complete overhauling / breakdown maintenance of C.W pumps Details 8Tender for complete overhauling of 75/15 tones capacity Details 8Tender for annual rate contract for preventive maintenance, defect attending & emergency work related Details 8Tender for work of overhauling / servicing of gear box, & rail alignment of gantry crane Details 8Tender for repairing and replacement work of fire protection hydrant line & pumps overhauling etc Details 8Tender for supply of spares of penstock gate Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8Suzlon Energy share price live: Stock surges 5%. What technical indicators suggest Details 8Solar powers India as electricity demand hits record high of 256 GW Details 8Coal India Q4 Profit Rises 11% to Rs 10,839 Crore Details 8Coal India Profit Jumps 11% Amid Margin Pressure, Output Decline Details 8Dividend Bonanza: UltraTech, Coal India to Varun Beverages Details 8Import dependence bites: Coal volatility, shipping costs hit steel sector Details 8Coal India hosts workshop on electrification of mining fleet to drive sustainable operations Details 8Joint Solar expands high-efficiency module manufacturing Details 8Indian Green Energy Stocks Outshine Markets With Strong Gains On April 27, 2026 Details 8India's renewable energy deal value jumps five-fold to $2 billion in 2025 Details 8Loom Solar learn initiative engages 50000 participants Details 8U.S. government sets preliminary anti-dumping duties on solar imports from India, Indonesia, and Laos Details 8Vikran Engineering Buys 49% Stake in PM-KUSUM Solar Project for Rs 4.9 Crore Details 8India’s electricity story moves from 99.5% access to 366 GW peak demand Details 8Why Tata Power Share Price is Rising Details 8Torrent Power and 4 other power stocks that skyrockets by up to 42% this month; Do you hold any Details 8The Importance Of Asset Monitoring Solutions For Power Generation Plants Details 8NTPC Vindhyachal wins ‘Environment Excellence 2026’ award for sustainable power generation Details 8India's Energy Security Surge: A Strategic Investment Landscape Details 8India Heatwave Fuels AC & Power Stock Surge: Valuations & Risks Loom Details 8India’s Renewable Surge Cut Fossil Fuel Power Use in 2025 Details 8Blue Star, Voltas, NTPC Gain as Scorching Heatwave Fires Up Cooling, Power Demand Details 84 HVDC Stocks to Watch as India's Silent Power Transmission Megatrend Gains Momentum Details 8India's Nuclear Power Plan: How the Country Plans to Go from 8.8 GW to 100 GW by 2047 Details 8Small Hydro Power Development Schemes Strengthen Energy Security for Sustainable Development in India: A Report Details 8Chandrababu Naidu pushes for tech, low-cost power in Andhra Pradesh Details 8Rooppur loads fuel today, edges closer to nuclear power generation Details 8JD Cables Stock Surges 11% After Strong EPC Quarter and Record Revenue Details 8Govt Ramps Up Power Generation As Demand Surged Amid Heat Wave Details 8Why are power sector stocks rallying today, April 27 Explained Details You can also click on Newsclips for moreDetails
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days. Get the daily updates for : 8LNG 8Crude 8Chemicals 8Fertilizers 8LPG 8Ammonia 8Coal & Coke 8All tankers 8Bulk and Dry cargo Click on Reports for more.Details
8The Rs 139 crore rooftop solar package has seen 11 bidders clear the technical stage. 8The focus now shifts from qualification to aggressive tariff positioning. 8The bidder mix reflects intensifying competition in the resco space.Details
8A Rs 141.6 crore contract underscores the growing emphasis on strengthening substations. 8But the limited number of bidders suggests a concentrated supplier base. 8That dynamic may impact both pricing discipline and execution risk.Details
8After multiple deadline extensions, a key civil works package has finally reached financial bid opening. 8The long tender drift and selective technical progression hint at deeper procurement challenges. 8Pricing outcomes may reveal how bidders have factored execution risks unique to island conditions.Details
8Bihar State Power schedules induction training for 350 Technician Grade-II employees Bihar State Power (Holding) Company Limited issued orders scheduling induction training for 350 newly recruited Technician Grade-II employees across 7 batches from April 27, 2026 to May 15, 2026. The training is being organized at the Bihar Power Training Institute and covers operational and technical skills for new hires joining Bihar's power distribution and transmission network. 8PSPCL Technical Training Institute relieves 32 CHB workers after completing 5-day non-residential training programme from April 20–24, 2026 The Principal, Technical Training Institute, PSPCL Patiala issued Relieving Order No. 186 dated April 24, 2026, releasing 32 Contract Helper B workers back to their postings - from offices including East Tech Patiala, Rajpura, North Tech Patiala, Lehra, Moonak, and Nabha - following successful completion of the 5-day non-residential training at Shakti Vihar, Patiala. 8Tripura State Electricity Department releases eligible candidates list for Manager (Electrical) Grade-A written examination The electricity department of Tripura officially published the list of candidates eligible to appear for the written examination for the post of Manager (Electrical), Grade-A, with 35+ shortlisted applicants spanning districts including Agartala, Gomati, South Tripura, and Khowai - marking a key step in the state utility's recruitment drive for technical managerial positions. 8Select and wait list declared for Additional Executive Engineer (Civil) under Advertisement No. 16/2024; exam held July 23 and interview December 23, 2025 A power sector utility published the Select and Wait List for the post of Additional Executive Engineer (Civil) under Advertisement No. 16/2024 published March 4, 2025, following an Online Test conducted on July 23, 2025 and Personal Interviews held on December 23, 2025. The merit was drawn out of 100 marks - 80 from online test and 20 from interview - with minimum qualifying marks set at 30 for Open category and 20 for reserved categories. 8Select and wait list issued for Executive Engineer (Civil) under Advertisement No. 15/2024; online test on July 22, interview on December 23, 2025 A power utility's result notification for Executive Engineer (Civil) under Advertisement No. 15/2024 published March 4, 2025, released the Select and Wait List following an Online Test on July 22, 2025 and Personal Interviews on December 23, 2025. Merit was computed out of 100 marks, with minimum 30 marks for Open category and 20 marks for reserved categories; the list remains valid for 2 years from the date of declaration. 8PSPCL Zone-1 issues transfer order No. 68 on April 24, posting 9 junior staff across Punjab including Fazilka, Amritsar, Ludhiana, and Faridkot; 1 earlier order cancelled Punjab State Power Corporation Limited's Deputy Secretary/Zones-1, Patiala issued Office Order No. 68 dated April 24, 2026, ordering immediate transfers of 9 ALM/LM/RTM officials - including Gurpreet Singh from Nadampur to Sihar (Ahmedgarh), Mahinder Singh from Ladhuka/Fazilka to Hussanpura/Amritsar, and Amit Kumar from Sub-Urban Fazilka to Special Division Agar Nagar, Ludhiana - while simultaneously cancelling the earlier December 24 order posting JE Balwinder Singh to Dhariwal. 8Energy firm posts Delhi opening for Deputy Manager Regulatory Compliance with 5+ years power sector experience An energy sector company is hiring a Deputy Manager – Regulatory Compliance and Corporate Affairs, based in Delhi, reporting to the Head of Strategy and Regulatory. The role requires a BE/B.Tech in Electrical Engineering and a minimum of 5+ years of experience in regulatory compliance or corporate affairs in the power sector, involving management of regulatory filings and liaison with CERC, state regulators, and government ministries. 8Bihar State Power accepts resignation of EEE Sandeep (E13610) from Transmission Circle Patna Bihar State Power (Holding) Company Limited accepted the resignation of Sri Sandeep (Employee No. E13610), Executive Engineer (Electrical) posted at Transmission Circle, Patna (East), under Bihar State Power Transmission Company Limited. The resignation is effective from April 26, 2026, under Rule 73(1)(a)(iv) and 73(3)(a) of BSEB Service Regulation 1976, with Order No. 6/4 dated April 24, 2026 issued by the Department of General Administration.Details