All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Aug 2026
815. KPCL's Bellary Coal Tender Corrects a Grade-Mismatch Flaw But Halves the Supplier's Challenge Window KPCL's addendum aligns its Bellary coal price schedule with the same GCV 5050 Kcal/Kg (ARB) benchmark used at Yeramarus, closing a gap between declared grade and destination-tested acceptance. In the same breath, the referee-sample objection period shrinks from 14 days to seven, and post-award mine substitution is permitted only at a rate capped at the original quote — leaving suppliers with logistics flexibility but no corresponding price protection.
816. NTPC's Telangana Stage-II BOP Tender Adds a Full Flue-Gas Duct Scope Mid-Bid and Bills Consortiums an Extra 2% NTPC's international competitive package for Telangana Stage-II (3x800 MW) saw two deadline extensions totalling 40 days while Technical Amendment No. 02 converted "Nil" placeholders into a complete flue-gas ducting scope from the ID fan outlet to the chimney. Consortium bidders now face a dedicated 2% system-integration security on top of the standard 10% performance guarantee, aimed squarely at interface failure between the newly expanded balance-of-plant scope and the steam-generator package.
817. NTPC REL's 300 MW Nokhra Solar Tender Absorbs 60 Days and 12 Amendment Instruments Before Bid Close NTPC Renewable Energy's Nokhra solar EPC package saw its deadline move from 22 June to 21 August 2026 while accumulating seven corrigenda and five addenda — a volume of post-issue intervention suggesting the technical baseline was still being finalised well after the tender's original launch. A Rs 20 crore EMD locks in serious bidders even as completion schedule, LD structure and grid-interface boundaries remain undisclosed.
818. JPDCL's Udhampur-Chenani Tender Is Titled a "DPR" But Its BOQ Demands a Full 67 km Turnkey Line JPDCL's Rs 538.15 lakh notice calls for a "DPR for laying of 33 kV alternate line," yet the underlying BOQ requires 440 poles, 67 km of ACSR conductor and complete survey-to-energisation delivery — a title-versus-scope mismatch serious enough to distort how bidders price the job. An undisclosed formula lets JPDCL demand extra security from any bid 15% or more below its Rs 538.15 lakh estimate, with no stated ceiling.
819. OPTCL's Balasore-Chandipur Cable Tender Repeats the Same Portal-vs-Notice Date Conflict Seen Elsewhere OPTCL's Rs 147.97 crore underground 132kV package between Balasore and Chandipur shows a five-day gap between its notice's stated document-availability start and the portal's actual opening, while "single stage two part" and "Two Stages" again appear as conflicting descriptions of the same bidding structure. Route length, jointing design, outage coordination and completion period remain undefined at notice stage, just as in OPTCL's other underground-cable tenders.
820. OPTCL's Narendrapur-Chhatrapur Cable Tender Leaves Just One Hour Between Bid Closing and Opening This Rs 102.39 crore underground 132kV package carries the same notice-versus-portal date mismatch as OPTCL's other cable tenders, but adds a tighter operational squeeze: bid closing at 14:00 and techno-commercial opening at 15:00 on the same day, leaving virtually no buffer to resolve last-minute submission issues. Two live-substation bay extensions again sit inside the turnkey scope without a disclosed interface matrix.
821. OPTCL's 400 kV HTLS Reconductoring Tender Bundles Line Upgrade With Substation Bus Work Under One EPC OPTCL's Rs 301.22 crore Meramundali-Mendhasal package requires replacing twin AAAC Moose conductors with High Temperature Low Sag conductors while simultaneously upgrading equipment and bus systems at both substation ends — concentrating tower-adequacy, thermal-clearance and terminal-compatibility risk in a single contractor. The tender's document-download window closes just 15 minutes before bid submission, and the same one-stage/two-stage labelling conflict from OPTCL's other packages reappears.
822. NTPC's North Karanpura Ash-Water Tender Fixes a Pipeline's Minimum Length But Not Its Maximum NTPC's AWRS package for the 3x660 MW plant instructs bidders to price "3.5 km or actual, whichever is maximum" for the return-water pipeline — locking in a pricing floor while leaving the upper bound entirely open pending detailed engineering. A late-added requirement to bury 11 kV lines wherever they cross higher-voltage transmission corridors surfaced only after bidder questioning, adding an unpriced electrical-scope change deep into the bidding cycle.
823. NTPC Mining's Chatti Bariatu Coal-Handling Award Closes 16.6% Below Its Nearest Rival BTL EPC Limited won NTPC Mining's Rs 200.31 crore coal-handling contract at a price 16.6% below L2 and 26.1% below L3, after amendments doubled the magnetic-separator count, raised pipe-conveyor clearance from 3 to 5.5 metres, and shifted fire, dust-suppression and auxiliary water sourcing from existing infrastructure onto contractor-developed borewells. The wide L1-L2 gap raises the question of whether the winning bid fully priced in the expanded utility and interface risk transferred through those late technical changes.
For daily newsletters and other free services, fill in your details: