All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Oct 2026
BHEL's Talabira water treatment EPC pushes a seven-month utility bridge onto the contractor
8The 30-month package for NLC India's 3x800 MW project bundles DM, condensate polishing, effluent and hydrogen systems under reverse auction with a Rs 50 lakh EMD.
8Conflicting spares-escalation clauses and milestone withholding of up to 3% make cashflow planning as critical as treatment technology.
BHEL doubles performance security in Mahi Banswara nuclear DG set tie-up
8BHEL's exclusive pre-bid partner search for 16 seismically qualified 4200 kW emergency DG sets raises performance security from 5% to 10% and adds a five-year latent-defect guarantee.
8Customer-linked bid validity, rewritten force majeure terms and asymmetric unit-pair pricing make this long-dated commitment harder to price.
MSEDCL's Rs 230 crore transformer tender makes performance guarantees bite from day one
8Version 2 of the 8,050-unit, 100 kVA procurement moves guarantee commencement from supply to issuance and requires electronic bank guarantees signed by two bank officials.
8Stores-level loss testing and complete-lot rejection risk mean execution discipline may count as much as price.
NTPC's NKSTPP coal haulage amendment lifts volume 20% within the same 12 months
8Amendment-1 replaces Amrapali with Chandragupta mine, shortens the haul band to 14–25 KM and raises quantity to 36 lakh MT without extending the contract period.
8A 60:40 award split, a 50% versus 60% local-content conflict and receipt-based reconciliation will decide whether bidders chase L1 or the matched share.
POWERGRID seeks exclusive EPC partner for 750 MWh Maheswaram BESS bid
8The pre-selected contractor for the 187.5 MW Telangana storage project must commit exclusively before POWERGRID's upstream tariff bid, and award depends on POWERGRID winning that bid.
8Broad qualification routes, a seven-day bid window and 15 years of maintenance create tension between a lean tariff and lifecycle risk.
KPCL's 1000 MW solar-plus-storage tender carries conflicting auction and security rules
8The indivisible build-own-operate package with 2000 MWh of storage demands a Rs 80 crore EMD and a Rs 400 crore PBG, with no VGF and developer-funded land and evacuation.
8Three different bid-validity periods and an unexplained year-11 jump in battery delivery need clarification before bids can be compared fairly.
PTCUL's 18-substation automation tender ties contractors to five years of integration support
8The Garhwal substation automation retrofit requires 366 BCUs, 99.98% availability over a 1,000-hour test and Windows compatibility support well beyond commissioning.
8An unexplained 18-BCU gap, conflicting guarantee triggers and contradictory JV wording leave key pricing assumptions unsettled.
JPDCL's Rs 159 crore Kathua Rural RDSS tender clouded by conflicting security terms
8The turnkey package for Billawar, Basohli and Ramkote covers over 930 km of AB cable, 882 transformers and more than 15,800 poles.
8Divergent additional-security formulas, a "sixty-five (60) days" payment clause and tiered rejection penalties could produce bids built on different exposures.
JPDCL's Rs 240 crore Kathua Urban loss-reduction tender drops functional guarantees
8The Heera Nagar and Kathua package spans HVDS, over 1,100 km of AB cable and 875 transformers, yet expressly excludes functional guarantee tests.
8Conflicting front-loading thresholds, additional-security bases and commissioning-linked payment relief will decide how comparably bidders price the work.
POWERGRID ties 765kV Kadapa-II–Thiruvalam contractor to its own tariff bid
8POWERGRID's TL02 package pre-selects a construction partner for a 33-month 765kV line before POWERGRID has won the transmission project itself.
8The critical question is how bidders will price an exclusive commitment when the construction award depends on a separate competition.
MPPGCL's Rs 293 crore Bargi uprating tender shifts generator power factor to 0.85
8MPPGCL's renovation of two 45 MW Bargi hydro units now carries a revised electrical design basis and a 15-day bid extension.
8An unreconciled efficiency guarantee, backed by steep per-point damages, raises a decisive question about the basis on which bidders will price.
NHPC's Rs 131 crore Dulhasti Stage-II package cuts defect-response window to seven days
8NHPC's Lot-3 contract places intake gates and pressure shaft liners under single-point responsibility, and the new gates must fit existing embedded parts.
8Layered securities and mismatched schedule clocks raise a crucial question about how much margin will remain once the reverse auction begins.
HPPCL seeks green hydrogen buyers for 1 MW Dabhota plant at Rs 1 EMD
8HPPCL's expression of interest opens a commercial outlet for hydrogen from its Nalagarh plant, with nominal security and a one-stage process.
8The more consequential question is what supply terms will turn early buyer interest into an enforceable offtake commitment.
WAPCOS caps Atal Park consultancy fee at 1% while stretching obligations to handover
8WAPCOS's Rs 3.31 lakh architectural assignment for CDA's Cuttack park spans surveys, approvals, construction support and as-built records.
8Conflicting security, payment and preference terms raise a crucial question about how far the modest fee can carry the risk being transferred.
UPRVUNL's 640 MW Rihand–Obra pumped storage tender moves to 27 October after ten extensions
8UPRVUNL's amended terms now require asset transfer after 40 years, dispatch without daily cycle limits and monthly performance tests.
8Behind the revised revenue protections lies a decisive question about how developers will price feasibility forfeiture against a fixed long-term tariff.
TNPGCL's three-unit NCTPS-I FGD tender schedules pre-bid meeting after opening
8Repeated corrigenda have pushed tender opening for TNPGCL's semi-dry FGD retrofit of three 210 MW units back by 204 days.
8Conflicting removal-efficiency guarantees and leftover wet-FGD clauses raise a critical question about whether offers can be compared on a single basis.
BHEL's revised MoU shifts indemnity onto its Mahi Banswara air-handling partner
8BHEL's exclusive pre-bid tie-up for the 4X700 MWe nuclear island package now carries softer award language and new termination remedies.
8The critical question is whether exclusive access justifies a contingent commitment backed by a Rs 3 crore EMD and an indemnity without a stated ceiling.
AEGCL admits joint ventures and AIS credentials into 400kV Umrangshu GIS tender
8AEGCL's addendum also cuts the extended GIS guarantee from 20% to 5% and moves online submission to 30 October.
8Unaligned SCC provisions and conflicting 24- and 36-month completion periods raise a crucial question about which terms bidders will actually price.
RVUN opens 12.5 lakh MT Suratgarh coal tender to group-backed suppliers
8After five deadline revisions, RVUN's Rs 1,125 crore procurement now accepts wholly owned group credentials and IPP supply experience.
8A Rs 1 per MT quality-payment cliff and only 70% initial payment raise a critical question about whether wider entry can sustain a competitive reverse auction.
MPPTCL's 23-transformer tender widens supply credit to 160 MVA units
8MPPTCL's 200 MVA, 220/132/33 kV procurement keeps its 5600 MVA capacity test while extending bid submission to 15 October.
8Conflicting security and commissioning terms, combined with allocation rules that favour incumbents, raise a crucial question about how new entrants will price.
RVPN's 220 kV NPH–VKIA cable tender slips 36 days amid escalation ambiguity
8Four corrigenda have pushed the Rs 128.54 crore Jaipur cable package to 4 November, but the 15-month execution clock is unchanged.
8A conflict between the SCC and Annexure-B leaves it unclear whether erection and civil escalation is payable at all.
GETCO fixes site levels and pile foundations in Dholera-II GIS tender
8The Rs 224.80 crore package has moved 54 days to 14 October, and clarifications confirm a levelled site needing only ±300 mm micro-grading.
8Claims for extra indoor GIB and GIS–LCC quantities remain barred, which pushes layout risk into reverse-bid pricing.
UJVN's Kulhal hydro revamp records three extensions without defining 'upgradation'
8The closing date for the Rs 110.57 crore turnkey package has moved 29 days across three time-extension entries.
8Capacity targets, efficiency guarantees and acceptance tests are still unquantified, making scope interpretation the core pricing risk.
BHEL ties Darlipali ash handling margins to a 4600 kW power guarantee
8In the 800 MW Stage-II package, every kW of auxiliary consumption above the guaranteed limit attracts US$5,245 in damages.
8Billing-allocation thresholds can also withhold supply payments, making cashflow as decisive as equipment price.
TNPDCL drops tapping from 5,000-unit, 100 KVA transformer tender
8The corrigenda remove tapping and delete the coil-length allowance, and the deadline moves 15 days to 22 October.
8Leftover tap references and conflicting no-load-current limits still need reconciling before units face strip-test scrutiny.
UJVN's Sirkari Bhyol Rupsiabagar E&M tender hits 23rd deadline revision
8The estimate for the 3x40 MW package has risen 53.3% to Rs 243.05 crore, and EMD has climbed 80.5% to Rs 5.7385 crore.
8A reversed seismic Zone VI amendment and a turbine-bearing redesign show the engineering baseline is still shifting 291 days past the original deadline.
GETCO widens LD base in Godadara GIS tender as deadline slips 36 days
8Amendment-I now charges delay damages on the whole contract price rather than only the delayed portion, with the 10% cap retained.
8Optional interest-bearing advances offer some relief, but GETCO rejected bidders' requests to relax escalation, LD and completion time.
DVC resets remote-substation SCADA clock to 12 months from LOA
8In the Rs 98.81 crore package, a corrigendum replaces an 18-month schedule and moves the start trigger from agreement to award.
8At least 30% of the price is locked into a seven-year AMC, so lifecycle costing now drives bid viability.
RVPN holds 2% quantity ceiling in Hathi Bhata GIS tender after five extensions
8Twelve firms attended the pre-bid meeting for the Rs 143.63 crore Ajmer package, but RVPN refused a request for 10% quantity headroom.
8Because of cable-loss capitalisation and a 15% service-price floor, the lowest quote may not be the lowest evaluated bid.
UJVN eases Kulhal entry thresholds while swapping in an oil-lubricated bearing
8Turnover requirements fall by about 15% and the current-ratio test drops from 1.5 to 1.0, after seven extensions totalling 91 days.
8The new bearing must meet thermal limits without forced water cooling, and any remedial work is at the contractor's own cost and time.
KPTCL keeps field-risk allocation unchanged in Byadagi substation tender
8All four pre-bid queries, on clearances, restringing, ROW and compensation, got the same reply: existing tender conditions prevail.
8In the Rs 131.92 crore package, the contractor must pay reimbursable compensation upfront, with no timeline for getting it back.
MCL's Garjanbahal surface-miner tender slips 44 days with escalation covering just 37%
8Price variation in the Rs 117.68 crore, five-year package adjusts only diesel, wage and other components, leaving 63% of the rate unindexed.
8The wording on work splitting, EMD and mediation is still contradictory and needs reconciling before award.
Keller and Bauer clear technical opening in NPCIL's GHAVP ground remediation tender
8Both bidders are admitted at the fee, pre-qualification and technical stage for remediation beneath several GHAVP-1-2 structures.
8With only two entries, a single rejection would leave NPCIL with one bidder at commercial comparison.
POWERGRID seeks exclusive partner for 765 kV Bulandshahr–Lucknow-II Part III line
8The TL10 contractor will back POWERGRID's tariff bid, but the 33-month execution award depends on POWERGRID winning the project.
8Bidders can qualify with 345 kV experience for this 765 kV package, which puts more weight on POWERGRID's separate capacity assessment.
POWERGRID ties Kukshi substation award to its own tariff bid win
8The SS 200T package combines a new 400/220/132/33 kV AIS substation with a 132 kV Pati extension, to be completed in 21 months.
8The selected bidder must commit exclusively before award, with no stated protection if POWERGRID loses the project.
POWERGRID gives TL08 bidders 10 days for exclusive 765 kV line tie-up
8The Part-I package requires 90 km of qualifying line experience and Rs 382.91 crore turnover, both from the bidding entity alone.
8Tractors are barred from tower erection, and composite mats and unlisted commissioning items stay within the contractor's scope.
POWERGRID's Babai TL02 package puts unlisted commissioning items on contractors
8Four 400 kV and 220 kV connections must be delivered in 27 months, and any commissioning item not expressly excluded falls within scope.
8Execution award again depends on POWERGRID winning the tariff bid, after an exclusive pre-award association.
GETCO's Rs 297.56 crore VCB panel tender splits guarantees at 66 months versus 18 months
8The same procurement gives 11kV panels a guarantee more than three times longer than 22kV panels, alongside cross-contract recovery rights across GUVNL.
8A doubled termination notice and arbitration through the High Court-administered centre ease some supplier exposure without removing uncompensated termination.
POWERGRID binds Kadapa-II 765kV bidders to an exclusive MOU before its own tariff bid
8The lowest evaluated bidder is only pre-selected, and the execution award depends on POWERGRID first winning the transmission project.
8Exclusivity, an outright tractor ban for tower erection and an NDA disclaiming information accuracy make the 33-month package costlier to commit to than its open label suggests.
APDCL's Rs 184 crore Guwahati cabling tender carries a 13-day submission-date conflict
8The BDS points to 15 October while the portal and notice fix 28 October, with competing closing times across the package.
8A 60% plant-price trigger for an extra 10% security, plus a JV rule requiring the lead partner to bring automation credentials, narrows the field further.
SECI's NDMC rooftop RfS doubles shortfall liability between its own RfS and PPA
8The RfS penalises generation shortfall at the full PPA tariff, while the draft PPA compensates at only 50% of it.
8Conflicting 10-year and 5-year module warranties, plus a site-visit clause that restricts due diligence to the successful bidder, leave the fixed tariff resting on unsettled terms.
NDMC solar bidders must commit Rs 49.68 lakh in service charges before final capacity is fixed
8SECI requires a full 3680 kW bid at one tariff, while building-by-building sizing is settled only after award.
8Inconsistent RFID placement rules and an undefined five-hour full-rated-output acceptance test add execution risk to a 25-year price.
OPTCL's Rs 1,677 crore Betakholi GIS package lifts receipt-stage supply payment from 70% to 80%
8The struck-out payment schedule moves ten percentage points of equipment value ahead of erection, improving contractor cashflow on the 765 kV build.
8That relief sits alongside 60-month defect liability, a 10-year SF6 leakage guarantee and a forest-clearance clause that points responsibility in two directions.
OPTCL coastal line tender's portal estimate sits 35.4% below its bidding document
8CPC-68 Lot-IV shows Rs 19.01 crore on the portal against Rs 29.41 crore in the IFB, and the two records also differ by a day on online closing.
8A cyclonic K4 factor limited to towers, an 80% receipt payment and a GCC 21 replacement that drops detailed delay machinery all need reconciling before bids.
NTPC triples its payment window on Dadri sodium bicarbonate while keeping offtake uncommitted
8The bid replaces GeM's 10-day payment term with 30 days and states that the 40,000 MT quantity is not a fixed monthly requirement.
8Suppliers must hold production and stock ready on five days' notice while NTPC can short-close unused quantity without liability.
SECI's CAU solar tranche schedules its pre-bid meeting at the exact minute of publication
8The 13-institution, six-state RESCO package records publication and pre-bid consultation at 3 pm on 7 October.
8Up to 40% ground-mounted capacity is now permitted, but conflicting site-visit rules leave bidders pricing 25-year tariffs before verifying roofs.
TNPDCL's DT metering workbook prices service charges over 93 months against a 102-month specification
8The nine-month gap cuts the service-charge multiplier by 8.8% across 4,72,500 transformer meters before any reverse-auction move.
8A Rs 30 crore minimum decrement, a stray "50 lakh meters" schedule reference and conflicting burnt-meter liability sharpen the clarification agenda.
NSPCL Bhilai pellet tender tells bidders to ignore its own GeM "No EMD" selection
8Variable EMD of up to Rs 1 crore applies by quoted daily quantity, while graded moisture deductions depart from the Ministry of Power model's rejection rule.
8A 2,200 MT quantity mismatch, contradictory variation clauses and exclusion of the top 15% of bids make allocation far more than an L1 contest.
POWERGRID gives Bikaner–Babai bidders two days to fix document access and one day to appeal
8The 765kV TL02 package closes bids on 16 October, leaving a compressed window between NDA-gated access and submission.
8An exclusive MOU before the tariff bid and an indefinite confidentiality duty mean firms must commit before any construction award is assured.
TNPDCL Chennai meter tender's phase subtotals overstate the scope by 4,94,414 meters
8Exhibit 1's printed category totals conflict with its own circle rows, although the 26,85,254-meter final quantity reconciles.
8An 18-month cross-provider integration deadline arrives before the 27-month installation milestone, and non-communicating meters cannot be invoiced at all.
UJVN Tiuni Plasu E&M tender moves 214 days through 20 deadline extensions
8The 2x36 MW package now allows two supporting manufacturers and deletes completed-work value gates, while adding a Rs 260 crore turnover test for that route.
8Air-gap, partial-discharge and vibration monitoring have been removed, and the authorisation and security chain still cites a superseded Form 14 deed.
NTPC pays CSIR-SERC fully in advance for Farakka ash-structure inspection without any guarantee
8The single-tender consultancy disapplies SD, PBG, LD and defect liability under an institutional MOU.
8Three extension notices give no replacement dates, and the preliminary report defers the real test programme and cost to a later proposal.
HPPTCL rejects transit-only insurance as autotransformer bids face a 47-day extension
8Four corrigenda push the World Bank-funded package to 12 October while pre-bid replies keep broad insurance with the manufacturer.
8The final 5% payment stays tied to commissioning performed by HPPTCL's own erection contractor, and the delivery schedule is deferred to award.
RVUN switches LSHS freight to actual railway charges after a 57-day extension
8Amendment No. 1 drops the lower-quantity freight basis, but material payment still follows the lower of invoice and RR quantity.
8Hidden BOQ quantities that diverge from the 37,600 MT schedule and a Rs 20 lakh gap in experience thresholds need resolving before 14 October.
For daily newsletters and other free services, fill in your details: