All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Jun 2026

COAL PRODUCTION & STOCK

8CEA reports power plants holding 47.7 million tonnes of coal on 8 June 2026, with 27 stations critical
The Central Electricity Authority's Fuel Management Division reported all-India coal stock at thermal power plants of 47,723.2 thousand tonnes (44,805.1 domestic plus 2,918.0 imported) as on 8 June 2026 — about 63% of the normative requirement and roughly 24 days of cover across 190 stations totalling 2,23,498 MW. Of these, 27 plants were flagged as critical or super-critical, while the monitored fleet ran at an average 72% plant load factor.

8Coal India says linked power plants stocked 41.3 million tonnes of coal as on 7 June 2026
Coal India Limited's Marketing & Sales Division reported, per CEA data, that power plants with coal linkage to CIL and SCCL held 41,346.4 thousand tonnes of coal as on 7 June 2026 — 40,669.3 thousand tonnes of indigenous coal plus 677.2 thousand tonnes imported. Eighteen of the linked plants were in the critical or super-critical category. The report tracks station-wise stock against an at-55%-PLF normative requirement, Coal India said.

8NRPC's 243rd OCC finds zero critical-stock units in the Northern Region in early May 2026
A key finding of the Northern Regional Power Committee's 243rd OCC meeting was that the coal-stock position of all Northern Region generating stations showed zero units in the critical-stock category during the first ten days of May 2026, signalling improved fuel security ahead of peak summer. The meeting also discussed PTCUL's request to divert a 500 MVA, 400/220 kV ICT from cold-spare reserve to the 400 kV Rishikesh substation for Kumbh Mela 2027.

GENERATION & PLF

8CEA: India generates 4,726.88 MU on 8 June 2026, running 1.86% below the FY27 programme
The Central Electricity Authority's daily generation overview recorded all-India power generation of 4,726.88 MU on 8 June 2026 against a programme of 4,732.89 MU, from a monitored capacity of 3,11,573.79 MW. Thermal contributed 4,112.62 MU, hydro 413.54 MU, nuclear 183.49 MU and Bhutan imports 17.23 MU. Cumulative generation since 1 April 2026 stands at 3,17,410.80 MU, some 6,003.40 MU (1.86%) short of programme, CEA said.

8CEA: NTPC stations generate 1,040.27 MU on 8 June 2026, 3.14% below the FY27 programme year-to-date
The Central Electricity Authority's NTPC overview shows the utility's stations producing 1,040.27 MU on 8 June 2026 — marginally above the day's 1,038.29 MU programme — from a monitored capacity of 60,007.23 MW (available 52,849.58 MW). The Western Region led with 358.59 MU. Cumulative NTPC generation since 1 April stands at 70,367.09 MU, 2,283.26 MU (3.14%) below programme, CEA said.

8CEA: coal powers 3,945 MU of India's 4,727 MU generation on 8 June 2026
The Central Electricity Authority's fuel-wise report for 8 June 2026 shows coal stations generating 3,945.17 MU of the day's 4,726.88 MU all-India total, ahead of hydro (413.54 MU), nuclear (183.49 MU), lignite (84.97 MU) and natural gas (81.35 MU). Coal's monitored capacity stood at 2,23,497.51 MW, and year-to-date coal generation has reached 2,66,385.84 MU since 1 April 2026, CEA said.

8RUVITSL merit-order list for 8-14 June 2026 ranks Sasan cheapest at Rs. 1.54/kWh, Dadri Liquid dearest at Rs. 27.81
Rajasthan Urja Vikas and IT Services Limited's merit-order dispatch schedule for 8-14 June 2026 ranks 43 generating stations by tariff inclusive of transmission losses. Sasan UMPP is cheapest at Rs. 1.54/kWh, followed by NLC Barsinghsar at Rs. 3.17/kWh, while gas and liquid-fuel stations occupy the costly end — Dadri Liquid at Rs. 27.81/kWh and Auriya Liquid at Rs. 24.04/kWh. The order is dated 8 June 2026.

8RVUNL's 1,200 MW Kalisindh plant reports May 2026 water use at 2.99 m3/MWh, below the 3.5 norm
Rajasthan Rajya Vidyut Utpadan Nigam Limited submitted May 2026 environmental data for its 2x600 MW Kalisindh Thermal Power Project, Jhalawar, to the Central Electricity Authority. The plant generated 615.26 GWh during the month and recorded specific water consumption of 2.99 m3/MWh against the prescribed 3.5 m3/MWh norm, operating on zero liquid discharge. Stack, ambient-air and effluent parameters across its four monitoring locations were within prescribed limits.

GAS & LNG

8Ember says gas's share in the global power mix fell for a fifth straight year in 2025
An Ember analysis published on 9 June 2026 found the share of gas in the global power mix declined for the fifth consecutive year in 2025, even as absolute gas-fired generation edged up slightly. Strong growth in clean power, led by solar and wind, met about 68% of global electricity-demand growth over 2021-2025, curbing the need for additional gas. The report examines the trend across the G7, China, India and Brazil.

HYDRO & RESERVOIR

8CEA basin data shows only 33% of India's 1,33,410 MW hydro potential tapped; Brahmaputra holds 65,400 MW
As on 31 May 2026, just 44,539.07 MW — about 33.39% — of India's 1,33,410 MW exploitable large-hydro potential above 25 MW is in operation, the Central Electricity Authority's basin-wise status shows. The Brahmaputra basin holds the largest untapped resource at 65,400 MW assessed but only 9.06% operational, while 13,373.5 MW is under construction and 19,974 MW concurred but not yet taken up. The inventory includes the 11,200 MW Upper Siang project.

8Odisha's reservoir hydro stations generate 625 MW on 9 June 2026, led by Upper Indravati's 260 MW
The reservoir generation report for 9 June 2026 shows Odisha's hydro powerhouses averaging a combined 625.38 MW, equivalent to about 15.01 million units. Upper Indravati (Mukhiguda) led with 259.96 MW and a 554.5 MW peak, followed by Balimela at 225.625 MW, while reservoir levels held near full — Balimela at 1,469.2 ft against an FRL of 1,516 ft. The Machkund station, under APGENCO control, recorded zero generation with machines available.

8CEA reservoir report puts Bhakra at 480.97 m and Tehri at 741.41 m as on 8 June 2026
The Central Electricity Authority's daily hydro-reservoir report for 8 June 2026 tracks levels and energy content across roughly 30 major reservoirs, with Bhakra at 480.97 m against a full reservoir level of 513.59 m, and Tehri at 741.41 m versus an FRL of 829.79 m. Sardar Sarovar held 127.86 m and Koyna 622.34 m. The report logs present-versus-full energy potential and cumulative hydro energy generated since 1 April, CEA said.

8SRLDC reservoir report shows Idukki at 706.72 m on 9 June 2026, below last year's 726.14 m
The SRLDC reservoir report for 9 June 2026 shows all 14 major Southern Region reservoirs below last year's levels, with Idukki at 706.72 m (stored energy 481.64 MU) versus 726.14 m a year ago, and Kakki at 942.17 m versus 976.31 m. Supa led current inflow at 1.11 MCM with stored energy of 674.85 MU, while Mettur stood at 749.75 m with no inflow against 784.16 m a year earlier, SRLDC said.
Details
PEAK DEMAND & POWER SUPPLY POSITION

8India meets a 2,59,448 MW peak on 9 June 2026 with zero shortage across all five regions
Grid Controller of India's NLDC daily report shows all-India peak demand met at 2,59,448 MW at 15:14 hrs on 9 June 2026, with zero shortage in every region and total energy met at 5,698 MU. The Northern Region led at 86,927 MW, followed by the Western Region at 78,611 MW and Southern Region at 59,781 MW. Coal supplied 65% of gross generation (3,975 MU), while total generation outage stood at 33,466 MW nationally.

8Northern Region clears 79,048 MW at the evening peak on 9 June 2026, with Uttar Pradesh taking 29,313 MW
The NRLDC daily report shows the Northern Region meeting 79,048 MW at the 20:00 hrs evening peak on 9 June 2026, with total energy of 1,904 MU and a residual shortage of just 0.41 MU in Uttarakhand. Uttar Pradesh dominated at 29,313 MW with 660.03 MU consumed, followed by Punjab at 15,187 MW and Rajasthan at 14,668 MW. The region's all-day maximum reached 86,927 MW at 14:58 hrs, per SCADA data.

8Western Region sets a 78,948 MW peak on 9 June 2026, with Maharashtra and Gujarat in the lead
The WRLDC daily report shows the Western Region reaching a maximum of 78,948 MW at 15:00 hrs on 9 June 2026, with zero shortage and total energy of 1,737.2 MU. Maharashtra peaked at 30,017 MW and consumed 659.3 MU, while Gujarat reached 27,427 MW (560.7 MU); Madhya Pradesh peaked at 13,137 MW. Regional own generation contributed 1,031.4 MU, including 197.7 MU of wind and 131.4 MU of solar, WRLDC said.

8Southern Region meets a 59,775 MW peak on 9 June 2026 with 1,274.29 MU delivered and zero shortage
The SRLDC power-supply report shows the Southern Region reaching an all-day maximum of 59,775 MW at 15:04 hrs on 9 June 2026, with zero shortage and total energy of 1,274.29 MU. Tamil Nadu led at 20,095 MW (429.34 MU), followed by Andhra Pradesh at 13,535 MW and Karnataka at 12,396 MW, while Telangana met 11,330 MW. Telangana posted the only positive energy deviation, at +4.84 MU against the LGBR forecast.

8Eastern Region hits a 33,709 MW peak at 23:18 hrs on 9 June 2026, led by West Bengal
The ERLDC power-supply report shows the Eastern Region reaching an all-day peak of 33,709 MW at 23:18 hrs on 9 June 2026, with a regional energy total of 712.86 MU and zero shortage. West Bengal led at 13,047 MW (261.44 MU), followed by Bihar at 8,309 MW and Odisha at 7,297 MW. DVC was a net exporter within the region at minus 38.87 MU. Regional thermal generation totalled 331.4 MU, ERLDC said.

8North Eastern Region delivers 69.77 MU on 9 June 2026 with a 3,499 MW evening peak, led by Assam
The NERLDC power-supply report shows the North Eastern Region meeting 3,499 MW at the 20:00 hrs evening peak on 9 June 2026, with zero shortage and total energy of 69.77 MU. Assam dominated at 2,247 MW (45.73 MU), with the region's maximum reaching 3,558 MW at 19:29 hrs. Hydro supplied 7.66 MU and gas 5.52 MU; Tripura showed the largest positive LGBR deviation at +1.32 MU, NERLDC said.

8NRPC's 243rd OCC projects a 98,600 MW June peak for the Northern Region against 1,03,200 MW available
The Northern Regional Power Committee's 243rd OCC meeting on 15 May 2026 projected the region's June 2026 peak requirement at 98,600 MW against available capacity of 1,03,200 MW — a slim 4,600 MW surplus — with energy availability of 55,150 MU against a 54,823 MU requirement. It flagged grid risk from the 800 kV Champa-Kurukshetra HVDC link, which lost 6,600 MW and 5,800 MW of import ATC in trips on 30 April and 2 May. Haryana faces a 2,868 MW peak deficit.

8Uttarakhand meets 56.75 MU against 57.20 MU demand on 8 June 2026, drawing 1.07 MU from exchanges
Uttarakhand's power-position statement for 8 June 2026 shows total availability of 56.75 MU against actual demand of 57.20 MU, leaving a small shortfall. State generation contributed 14.38 MU and the central share 21.03 MU (35.41 MU from firm sources), while net IEX/PXIL exchange drawal added 1.07 MU and other sources 21.34 MU. The state utility's report also tabulated area-wise rostering for the day.

FREQUENCY & DEVIATION INDICES (FDI/VDI)

8Grid frequency runs at 50.017 Hz on 9 June 2026 with 26.3% of the day outside the IEGC band
The NLDC frequency profile for 9 June 2026 shows an average all-India frequency of 50.017 Hz, a Frequency Deviation Index of 26.3 and a standard deviation of 0.0614. The grid stayed within the 49.90-50.05 Hz band for 73.73% of the day but was outside the IEGC band for 6 hours 18 minutes (26.27%). The instantaneous maximum was 50.298 Hz at 19:03 hrs and the minimum 49.846 Hz at 14:25 hrs, NLDC said.

8SRLDC VDI flags Asupaka above 420 kV for 7.78 hours on 9 June 2026
The SRLDC Voltage Deviation Index report for 9 June 2026 identifies several 400 kV substations breaching the 420 kV upper limit, led by Asupaka at 7.78 hours (VDI 0.32), Dichipally at 7.22 hours and Annaikavadu at 4.47 hours. Peak voltages reached 426.86 kV at Annaikavadu and 425.08 kV at Dichipally. No monitored node fell below the 380 kV lower limit, indicating robust voltage support across the Southern Region, SRLDC said.

8ERLDC VDI shows all Eastern Region 765 kV and 400 kV substations within band on 8 June 2026
The Eastern Regional Load Despatch Centre's Voltage Deviation Index report for 8 June 2026 recorded perfect compliance, with all monitored 765 kV substations — including Ranchi New (average 779.73 kV), Angul, Gaya and Darlipali — logging zero hours outside the IEGC band. At 400 kV, Jamshedpur (409.01 kV), Maithon (406.72 kV) and Barh (405.60 kV) also held 100% within band. The report covered more than 30 nodes, ERLDC said.

8NERLDC reports zero voltage deviations at 16 substations but 27.42% of 8 June 2026 outside the frequency band
The NERLDC daily indices for 8 June 2026 show all 16 monitored 400 kV substations across the North Eastern Region — including Azara, Balipara, Bongaigaon, Palatana and New Kohima — holding 100% within the 380-420 kV band, with averages from 404 to 412 kV. However, the Frequency Deviation Index report recorded the grid outside the IEGC band for 27.42% of the day (6.58 hours), with frequency ranging from 49.67 Hz to 50.18 Hz.

SYSTEM RELIABILITY & SECURITY

8NLDC reliability indices for 9 June 2026 show only one ATC violation block on the NR import corridor
Grid Controller of India's NLDC System Reliability Indices report for 9 June 2026 showed a near-perfect picture: of five inter-regional corridors monitored, only the Import of Northern Region corridor recorded a single block of ATC violation (0.25 hours, 1.04% of the day), and no corridor breached the N-1 criterion. Among voltage nodes, Moga spent 1.11% of the day below 728 kV and Khetri 0.35%, with most substations fully within band.

LOAD FORECAST

8SRLDC forecasts Southern Region demand of 40,000-63,000 MW for 9-15 June 2026, with 1.95% prior-day error
The SRLDC weekly demand forecast for 9-15 June 2026 projects Southern Region demand ranging from about 40,000 MW in off-peak hours to a peak near 63,000 MW during afternoon periods. Validation against actuals for 7 June 2026 showed a Mean Absolute Percentage Error of 1.95%, indicating high accuracy. SRLDC prepares these forecasts under IEGC 2023 obligations for advance scheduling and congestion management across the six-state region.

8ERLDC forecast error for 8 June 2026: day-ahead MAPE 4.48%, intra-day just 1.51%
ERLDC's Eastern Region forecasting-error report for 8 June 2026 recorded a day-ahead MAPE of 4.48% (RMSE 5.45%) and an intra-day MAPE of just 1.51%, showing real-time corrections close most of the gap. The largest day-ahead error came in the 09:00-09:15 block, an over-forecast of 2,701 MW against actual demand of 25,755 MW. The model shows a systematic over-forecast bias during afternoon solar-ramp periods, ERLDC said.

TRANSMISSION CAPACITY (TTC/ATC)

8NERLDC flags 53 blocks of TTC violation on the Tripura corridor on 8 June 2026
The NERLDC System Reliability Report for 8 June 2026 found the NER-Tripura corridor breaching its Total Transfer Capability in 53 blocks, totalling 13.35 hours — or 55.6% of the day — while the NER-Assam corridor saw 17 blocks (4.4 hours, 18.2%). All other intra-regional corridors recorded zero violations. Utilities in importing control areas were instructed to restrict drawal to keep within limits, NERLDC said, with TTC computed on the N-1 criterion.

8CEA adds 18,515 MVA of transformation capacity in FY 2026-27, beating its 12,564 MVA target
Substations completed in FY 2026-27 up to 31 May 2026 added 18,515 MVA of transformation capacity (220 kV and above), the Central Electricity Authority reported, comfortably exceeding the cumulative target of 12,564 MVA. The 765 kV class dominated with 10,500 MVA, including POWERGRID ICTs at Fatehgarh-III, Khavda and Bikaner-III and Resonia's 3,000 MVA Beawar substation. Much of the new capacity supports renewable evacuation from the Rajasthan and Gujarat zones.

8CEA reports 7,190 MVA of new substation capacity commissioned in May 2026
India commissioned 7,190 MVA of substation transformation capacity (220 kV and above) in May 2026, the Central Electricity Authority reported, against a 6,689 MVA monthly target. The central sector added 2,000 MVA — POWERGRID's 500 MVA ICT at Satna and a 1,500 MVA 765/400 kV ICT at Fatehgarh-III — while the state sector contributed 5,190 MVA across about 20 augmentations. The single largest state addition was MSETCL's 500 MVA Jejuri substation.

8India's total transformation capacity hits 14,69,041 MVA in May 2026, CEA says
The Central Electricity Authority's May 2026 growth summary puts India's cumulative transformation capacity (220 kV and above) at 14,69,041 MVA, after adding 7,190 MVA in the month and 18,515 MVA in FY 2026-27. By voltage, the 400 kV class accounts for 5,36,148 MVA and 765 kV for 3,80,200 MVA. Sector-wise, the state sector leads with 7,79,733 MVA against the central sector's 5,92,791 MVA, with ISTS capacity at 6,40,105 MVA.

LINE & GENERATION OUTAGES

8NLDC's May 2026 grid-events report logs the 800 kV Champa-Kurukshetra HVDC blocking at about 3,000 MW
The National Load Despatch Centre's May 2026 grid-events report documents disturbances across all five regional grids, with the Northern Region accounting for the bulk. On 2 May 2026 the 800 kV Champa-Kurukshetra HVDC link, then carrying about 3,000 MW, saw Poles 1 and 3 block at 16:31 hrs on CLD protection after a telecom failure, followed by Pole-2 at 16:51 hrs, against an antecedent regional load near 65,085 MW. Events are classified as grid incidents and grid disturbances.

8CEA reports 43,184 MW under maintenance on 8 June 2026, leaving 2,68,390 MW online
The Central Electricity Authority's capacity-availability summary for 8 June 2026 shows 43,184.22 MW of monitored capacity under maintenance — 5,457.65 MW planned, 27,454.67 MW forced and 10,271.90 MW for other reasons — out of 3,11,573.79 MW monitored. That left 2,68,389.56 MW online nationally. The Northern Region carried the heaviest forced outage at 9,394.06 MW, CEA said.

8CEA flags 29,678 MW of thermal and nuclear capacity out of grid for over 15 days as on 8 June 2026
The Central Electricity Authority's report on units out of the grid for more than 15 days lists thermal and nuclear capacity totalling 29,678.36 MW as on 8 June 2026, spanning dozens of units with their maintenance start and expected return dates. The tally reflects prolonged outages across India's conventional fleet during FY 2026-27, with each entry noting the reason or present status of the stalled unit, CEA said.

8CEA logs 7,785 MW of thermal and nuclear units recommissioned by 8 June 2026, including Kalisindh's 600 MW
The Central Electricity Authority's recommissioning report shows units totalling 7,785.18 MW synchronised back to the grid as on 8 June 2026, among them Kalisindh TPS Unit-1 (600 MW), Ukai TPS Unit-6 (500 MW), Rihand STPS Unit-4 (500 MW) and Chandrapur STPS Unit-8 (500 MW). Each return is tagged with its outage reason, from low-temperature superheater tube leakage to control-and-instrumentation faults, CEA said.

8CEA reports 5,053 MW of thermal capacity tripped out of grid on 8 June 2026
The Central Electricity Authority's report on units that went out of the grid on 8 June 2026 logs 5,053.10 MW of thermal capacity, led by Tamnar TPP Unit-2 (600 MW), Bandakhar TPP Unit-1 (300 MW), Suratgarh TPS Unit-6 (250 MW) and Ropar TPS Unit-5 (210 MW). Outage causes ranged from turbine and milling-system problems to furnace flame failure, with each unit's time off-bar and expected return recorded, CEA said.

8SRLDC logs a Kalpakka bus-bar trip taking out five APTRANSCO elements at once on 9 June 2026
The SRLDC generation report for 9 June 2026 records a cluster of simultaneous forced outages at Kalpakka at 19:26 hrs, triggered by bus-bar protection, taking out five APTRANSCO elements together, including the 400 kV Gazuwaka-Kalpakka-1 and -2 lines and Kalpakka-ICT-3. Two POWERGRID 400 kV Gazuwaka-Simhadri lines tripped on an R-Y fault minutes later. Among units, North Chennai TPS Stage-III (800 MW) and SEIL P2 Unit-2 (660 MW) also went off, SRLDC said.

8ERLDC reports 3,828.65 MW of Eastern Region generation on outage on 9 June 2026
The ERLDC generation outage report for 9 June 2026 shows a total of 3,828.65 MW out — 2,445 MW central (all forced) and 1,383.65 MW state. Fresh forced outages included NTPC KHSTPP Unit-2 (210 MW, rotor earth fault) and Maithon Power Unit-2 (525 MW, boiler tube leakage). Teesta Stage III (six units of 200 MW) and Stage I (three of 170 MW) remain off since the October 2023 cloudburst, with revival timing still uncertain, ERLDC said.

8WRLDC reports 2,863 MW of Western Region central capacity on forced outage on 9 June 2026
WRLDC's generating-unit outage report for 9 June 2026 records 2,863 MW of central-sector forced outages and 1,370 MW planned. Key forced outages include JPL Stage-II Unit-3 (600 MW, Jindal Power), Sasan UMPP Unit-1 (660 MW, boiler tube leakage) and VEDANTA Unit-1 (600 MW). RGPPL Units 1A and 1B (320 MW each) remain off since 2014 on gas shortage, while NTPC KSTPS Unit-5 (500 MW) is under annual overhaul until 19 June, WRLDC said.

8PVVNL schedules planned shutdowns across about 85 Meerut-zone feeders for 10 June 2026
Paschimanchal Vidyut Vitran Nigam Limited, Meerut, published a planned-shutdown schedule dated 9 June 2026 listing roughly 85 feeders across its Meerut-zone circles and divisions for outages, mostly on 10 June 2026. The maintenance windows, several running about four hours, cover urban and rural feeders for erection and augmentation works such as new transformers and ABC cabling, with affected areas and timings detailed feeder by feeder.

TRANSMISSION LINE ENERGIZATION

8CEA lays 2,022 ckm of new transmission lines in FY 2026-27, anchored by the 765 kV Kurnool-Maheshwaram link
Transmission lines completed in FY 2026-27 up to 31 May 2026 totalled 2,022 circuit-km (220 kV and above), the Central Electricity Authority reported, against a full-year target of 16,554 ckm. The 400 kV class led with 1,171 ckm, followed by 508 ckm at 765 kV — chiefly POWERGRID's 508 ckm Kurnool-III to Maheshwaram line for the Andhra Pradesh Kurnool zone. Key state additions included MSETCL's 456 ckm Babhleshwar-Kudus line.

8CEA logs 1,121 ckm of transmission lines commissioned in May 2026
India added 1,121 circuit-km of transmission lines (220 kV and above) in May 2026, the Central Electricity Authority reported, split between 650 ckm in the central sector and 471 ckm in the state sector. The headline central projects were POWERGRID's 765 kV Kurnool-III to Maheshwaram line and Circuit-1 of the 400 kV Navsari-Kala line, while UPPTCL's 400 kV Farrukhabad-Badaun double-circuit line led state additions, CEA said.

8India's transmission network crosses 5,08,535 ckm in May 2026, with 1,20,340 MW of inter-regional capacity
The Central Electricity Authority's May 2026 growth summary pegs India's total transmission-line length (220 kV and above) at 5,08,535 circuit-km, after adding 1,121 ckm in the month and 2,022 ckm in FY 2026-27. Inter-regional transfer capacity now stands at 1,20,340 MW. By sector, the state sector accounts for 2,71,723 ckm, the central sector 1,91,207 ckm and the private sector 45,605 ckm of the network.

REGIONAL ENERGY ACCOUNT (REA/REMC)

8WRPC SCED nets a Rs. 5.33 crore outflow from the Western Region pool in May 2026
The Western Regional Power Committee's Security Constrained Economic Dispatch statement for May 2026 shows a net payable charge of Rs. 5.33 crore from the Western Region pool. Across 16 SCED generators, incremental generation stood at 78,996 MWh against decremental obligations of 88,656 MWh, yielding gross charges of Rs. 25.05 crore and refunds of Rs. 30.38 crore. NTPC Solapur was the largest net beneficiary at Rs. 12.89 crore, WRPC said.

8KAWAS and GANDHAR gas plants earn Rs. 11.49 crore as WRPC's TRAS week shows a small surplus
The WRPC tertiary reserve ancillary services settlement for 25-31 May 2026 shows a net SRAS surplus of Rs. 27.21 lakh, with KAWAS-ComGas and GANDHAR-ComGas the biggest earners at net receivables of Rs. 5.76 crore and Rs. 5.73 crore on their TRAS-Up schedules. NTPC Gadarwara-I faces the steepest net payable at Rs. 1.37 crore. Total UP regulation was 14,549.64 MWh and DOWN regulation 23,679.77 MWh over the week, WRPC said.

8WRPC reactive-energy account for 25-31 May 2026 shows Gujarat and Maharashtra as the largest net receivers
The Western Regional Power Committee's reactive-energy account for 25-31 May 2026 records a sub-total drawee payable of Rs. 92.98 lakh and receivable of Rs. 1.86 crore, with Gujarat (Rs. 23.72 lakh net) and Maharashtra (Rs. 28.68 lakh net) the largest beneficiaries. Among stations, NTPC Gadarwara led receivables at Rs. 39.08 lakh, followed by KSTPS I, II and III at Rs. 30.59 lakh. Charges follow IEGC-2023 Regulation 39, WRPC said.

8WRPC DSM statement for 25-31 May 2026 shows generators payable Rs. 10.65 crore as wind and solar swing positive
The Western Regional Power Committee's Deviation Settlement statement for the week to 31 May 2026 shows ISGS and conventional generators with a net payable of Rs. 4.61 crore (payable Rs. 10.65 crore, receivable Rs. 6.04 crore), while wind and solar generators flipped to a net receivable of Rs. 4.10 crore on over-performance. Inter-regional WR-NR transactions netted a Rs. 12.54 crore payable from WR, prepared under CERC DSM Regulations 2024, WRPC said.

8ERPC's commercial pool posts a Rs. 3,967.92 lakh surplus for 25-31 May 2026, with BSPHCL topping payables
The Eastern Regional Power Committee's consolidated DSM, SRAS, TRAS and SCUC account for 25-31 May 2026 shows a pool surplus of Rs. 3,967.92 lakh, with total payable to pool of Rs. 36,139.25 lakh and receivable of Rs. 32,171.33 lakh. BSPHCL carried the largest net payable at Rs. 1,011.96 lakh, followed by DVC at Rs. 182.99 lakh, while WBSETCL took the largest credit of Rs. 840.67 lakh. The East-South corridor accounted for Rs. 28,050.15 lakh payable.

8ERPC reactive-energy charges for 25-31 May 2026 total Rs. 66.45 lakh at 6 paise/KVArH, WBSETCL pays most
The Eastern Regional Power Committee's reactive-energy charge statement for 25-31 May 2026 records total charges payable to pool of Rs. 66.45 lakh and receivable of Rs. 24.21 lakh, at a rate of 6 paise/KVArH effective 2 October 2025 under IEGC-2023. WBSETCL alone accounted for Rs. 65.45 lakh of payables, reflecting sustained lagging reactive drawal across its 400 kV boundary. JIPL led receivables at Rs. 4.59 lakh, ERPC said.

8APJL's Godda station exports 800.28 MU to Bangladesh in May 2026
Adani Power (Jharkhand) Limited's Godda generating station exported 800.28 million units of electricity to Bangladesh during May 2026, according to a statement issued by the Eastern Regional Power Committee. The figure, recorded as 800.281235 MU, represents the sole cross-border transaction at the Bangladesh connection point for the period. The statement, numbered ERPC/COMM/REA-GODDA/2026-27/491 dated 9 June 2026, was issued pursuant to a special-meeting decision of May 2023.
Details
DAY-AHEAD MARKET (DAM/GDAM/HPDAM)

8IEX day-ahead market clears 1,39,929 MWh for 9 June 2026 at a weighted Rs. 3,935.72/MWh
The Indian Energy Exchange's day-ahead market cleared 1,39,929.06 MWh for delivery on 9 June 2026, drawing purchase bids of 3,33,613.95 MWh against sell bids of 4,51,410.85 MWh. The day's weighted average market clearing price settled at Rs. 3,935.72/MWh, with snapshots pointing to a peak MCP of Rs. 5,232.11/MWh. Across the 3-10 June window, IEX DAM cleared a cumulative 10,62,695 MWh, the exchange reported.

8IEX green day-ahead market trades 32,703 MWh of renewable power for 9 June 2026 at Rs. 3,567/MWh
The Indian Energy Exchange's green day-ahead market cleared 32,702.69 MWh for delivery on 9 June 2026 against purchase bids of 1,12,646.31 MWh and sell bids of 3,82,858.36 MWh. Solar contracts made up the bulk of cleared volume at 20,874.73 MWh, with the day's weighted average price at Rs. 3,567.46/MWh and a peak MCP of Rs. 5,712.46/MWh. The 15-minute, hourly and daily snapshots all confirmed steady green-power liquidity, IEX said.

8IEX high-price day-ahead market draws a blank on 9 June 2026 despite 74,196 MWh of sell bids
The Indian Energy Exchange's high-price day-ahead market recorded zero cleared volume for delivery on 9 June 2026, even as sellers offered 74,196.25 MWh into the segment. Over the 3-10 June window the HP-DAM cleared just 4,659.19 MWh in total, with the clearing price touching its Rs. 20,000/MWh ceiling on days trade occurred. Buyers stayed largely absent, leaving the high-price window dormant for the delivery date, IEX data showed.

8HPX green day-ahead market records zero trade right through 1-10 June 2026
The Hindustan Power Exchange's green day-ahead market reported nil purchase bids, nil cleared volume and a zero market clearing price for delivery on 9 June 2026, a pattern repeated on every day from 1 to 10 June 2026. The 15-minute, hourly and daily snapshots all showed no solar, non-solar or hydro green volume changing hands. The segment stayed inactive across the entire reporting window, HPX data showed.

8HPX high-price day-ahead market logs no cleared volume on 9 June 2026
The Hindustan Power Exchange's high-price day-ahead market saw zero cleared volume and no market clearing price for delivery on 9 June 2026. The only bid activity in the 1-10 June window was a lone 2,000 MWh purchase bid on 4 June, none of which cleared. The HP-DAM remained effectively dormant across all time blocks for the delivery date, according to HPX data covering the full window.

REAL-TIME MARKET (RTM)

8IEX real-time market clears 1,61,053 MWh on 9 June 2026 at Rs. 3,822.78/MWh
The Indian Energy Exchange's real-time market handled 1,61,052.91 MWh of cleared volume for 9 June 2026, with a final scheduled volume of 1,61,044.02 MWh, against purchase bids of 2,29,588.08 MWh and sell bids of 3,57,166.98 MWh. The market clearing price averaged Rs. 3,822.78/MWh. The RTM cleared a cumulative 12,85,186 MWh over the 3-10 June period, peaking at 1,99,178 MWh on 5 June, IEX reported.

8HPX real-time market clears 1,015 MWh on 9 June 2026 at the Rs. 10,000/MWh cap
The Hindustan Power Exchange's real-time market cleared 1,015.42 MWh of final scheduled volume for delivery on 9 June 2026, against purchase bids of 2,000 MWh and sell bids of 1,200 MWh, at a market clearing price of Rs. 10,000/MWh. It was the busiest RTM day in the 1-10 June window, which saw cumulative cleared volume of 1,095.42 MWh. Trade was concentrated in a handful of fifteen-minute blocks, HPX said.

8PXIL real-time market clears 100 MWh on 9 June 2026 at Rs. 10,000/MWh
Power Exchange India Limited's real-time market cleared 100 MWh for delivery on 9 June 2026 — drawn from purchase bids of 705 MWh and sell bids of 100 MWh — at a market clearing and weighted price of Rs. 10,000/MWh. Over the 3-10 June window the segment's biggest day was 3 June, when 937.5 MWh cleared, also at Rs. 10,000/MWh. The volume-profile report showed clearing confined to a few early-morning blocks.

TERM-AHEAD & GREEN TERM-AHEAD (TAM/GTAM)

8IEX green term-ahead market trades about 1,912 MWh across 64 green contracts on 9 June 2026
Trading on the Indian Energy Exchange's green term-ahead market totalled roughly 1,911.97 MWh on 9 June 2026, executed through about 135 trades across 64 green daily-auction contracts. Clearing prices ranged from Rs. 1,863/MWh up to the Rs. 10,000/MWh ceiling, with most blocks settling near Rs. 10,000/MWh. The contracts spanned solar and non-solar green instruments delivered across the day's time slots, IEX data showed.

8IEX term-ahead market trades about 15,663 MWh in roughly 1,074 deals on 9 June 2026
The Indian Energy Exchange's conventional term-ahead market saw about 15,663 MWh change hands on 9 June 2026 through roughly 1,074 trades across some 345 contracts. Daily auction contracts dominated at around 13,288 MWh while intraday contracts added about 2,375 MWh, with prices ranging from Rs. 1,153/MWh up to the Rs. 10,000/MWh cap. Volumes covered northern, western, southern and eastern delivery points, IEX reported.

ANCILLARY & INTRADAY (ASDAM/IDAS/SCUC)

8NLDC SCUC table for 10 June 2026 commits 41 generators; Darlipali cheapest at 115.9 paise/kWh
The National Load Despatch Centre's Security Constrained Unit Commitment schedule for 10 June 2026, issued on D-1 basis, commits 41 generators, with Darlipali the cheapest dispatchable unit at 115.9 paise/kWh and 467.16 MW for blocks 44-54. NTPC coal plants dominate mid-merit dispatch, while four gas plants — RGPPL-RLNG at 1,601 paise/kWh, Gandhar-ComGas at 1,941, Dadri CRF at 1,957 and Kawas-ComGas at 1,966 — are committed at zero MW, priced out of merit order.

8HPX ancillary services day-ahead market sees nil clearing for 9 June 2026
The Hindustan Power Exchange's ancillary services day-ahead market registered zero cleared volume and no market clearing price across all 96 fifteen-minute blocks for delivery on 9 June 2026. The hourly and daily resolutions likewise showed nil up-regulation bids and nil cleared volume. The ancillary segment recorded no activity through the entire 1-10 June period covered in the report, HPX data showed.

8PXIL intra-day market attracts 1,100 MWh of bids but clears nothing on 9 June 2026
Power Exchange India Limited's Intra-Day Auction Session drew 1,100 MWh of purchase bids and 339.5 MWh of sell bids for delivery on 9 June 2026, yet recorded no market clearing volume or price. The volume-profile report showed bid interest on every day from 3 to 10 June without any matched trade. Purchase bids held steady at 1,100 MWh per day through most of the window, PXIL data showed.

DEVIATION SETTLEMENT (DSM)

8PXIL deviation settlement report shows zero cleared volume for 9 June 2026
Power Exchange India Limited's Deviation Settlement Mechanism report recorded nil cleared buy and sell volumes and a zero price across every fifteen-minute block for delivery on 9 June 2026. The three-page report logged no DSM activity through the day, pointing to a quiet deviation-settlement session on the exchange. The data covered all 96 time blocks of the delivery day, PXIL said, with neither buyers nor sellers transacting.
Details
MINISTRY OF POWER

8Ministry of Coal notifies the Coal Exchange Rules, 2026 to launch India's first online coal-trading platform
The Ministry of Coal notified the Coal Exchange Rules, 2026 through Gazette notification G.S.R. 442(E) dated 4 June 2026, using powers under Section 18B of the MMDR Act, 1957. The rules establish a regulated online coal exchange — with the Coal Controller Organisation as the Authority — for competitive price discovery on delivery-based coal and lignite contracts. They prohibit cartelisation, circular trading and insider trading, and mandate a settlement guarantee fund, automated audit trails and coal-sampling-based quality verification.

CEA & GRID STANDARDS

8CEA's 41st NCT meeting clears RE-evacuation schemes, revises the Kandla 3 GW plan up to Rs. 8,238 crore
The Central Electricity Authority's National Committee on Transmission, at its 41st meeting on 18 May 2026, reviewed inter-State schemes to evacuate renewable power and revised the Kandla Phase-I 3 GW scheme cost up to Rs. 8,238 crore — a Rs. 732 crore rise over the earlier Rs. 7,506 crore estimate. It took up the 7.5 GW Lakadia and Bikaner-V 6 GW schemes, noted a projected RE surplus of 48-95 GW by 2030, and reviewed the Rs. 8,386 crore Vizag scheme assigned to RECPDCL.

8CEA extends the deadline to 21 June 2026 for comments on Amendment-II to its transmission planning manual
The Central Electricity Authority extended to 21 June 2026 the last date for stakeholders to submit suggestions on draft Amendment-II to the CEA Manual on Transmission Planning Criteria, 2023. The original 8 June 2026 deadline, set in a 19 May 2026 notice, was pushed back after several utilities sought more time. The proposed amendment updates planning factors, building on Amendment-I, which earlier added a new Chapter-7 to the manual.

TENDERS & PROCUREMENT (GEM/NIT)

8MePTCL calls a 9 June 2026 pre-bid meeting for GIS to upgrade Mawlai substation from 3x20 to 3x50 MVA
Meghalaya Power Transmission Corporation Limited notified a pre-bid meeting on 9 June 2026 for the supply of 132 kV and 33 kV indoor GIS and related services to augment the 132/33 kV Mawlai substation from 3x20 MVA to 3x50 MVA, with re-engineering of the 132 kV busbar. The work falls under the NESIDS OTRI Scheme in Meghalaya. Bidders were invited to join online via Google Meet, hosted at the MeECL conference hall in Shillong.
Details
SOLAR POWER

8CEA reports India's renewables generated 1,180.82 MU on 8 June 2026, led by 637 MU of solar
The Central Electricity Authority's Renewable Project Monitoring Division reported all-India renewable generation of 1,180.82 MU (net) on 8 June 2026, comprising 637.39 MU of solar, 515.07 MU of wind and 28.36 MU from other sources. ISGS renewable plants of 60,459.08 MW contributed 477.88 MU, with the 2,300 MW NP Kunta and 2,181 MW Pavagada solar parks generating 13.08 MU and 12.11 MU respectively. Cumulative renewable generation for June 2026 reached 8,344.72 MU.

WIND & HYBRID POWER

8Meta and CleanMax tie up for about 900 MW of renewables, adding 837 MW of new solar and wind in India
Clean Max Enviro Energy Solutions Limited announced on 10 June 2026 a roughly 900 MW renewable-energy partnership with Meta Platforms in India. The companies will support development of 837 MW of new solar and wind capacity across Rajasthan and Karnataka, taking the combined partnership beyond 900 MW once earlier projects are counted. CleanMax, listed under NSE symbol CLEANMAX, said the projects back Meta's drive to add new renewable generation to the grid.

STORAGE & GREEN HYDROGEN

8CEA pegs India's pumped-storage potential at 2,90,436 MW across 264 projects, only 7,426 MW operational
India's total pumped-storage potential stands at 2,90,435.60 MW across 264 projects, but just 10 projects totalling 7,425.60 MW are in operation, the Central Electricity Authority reported. Another 11 projects (15,870 MW) are under construction and 5 (6,580 MW) hold CEA concurrence, leaving 83 projects worth 1,16,840 MW yet to be built. Operating schemes include Greenko's 1,680 MW Pinnapuram plant alongside the 1,200 MW Sardar Sarovar and 1,000 MW Tehri pumped-storage stations.

POLICY & INCENTIVES

8MNRE rules out a blanket extension of ALMM List-II beyond 1 June 2026, offers case-by-case relief
In an Office Memorandum dated 25 May 2026, the Ministry of New & Renewable Energy ruled out a blanket extension of the ALMM List-II deadline, requiring net-metering and open-access renewable projects commissioned on or after 1 June 2026 to source solar cells from List-II and modules from List-I. Developers who have taken effective steps may seek case-by-case extensions, filing claims on the NISE portal by 30 June 2026; PM Surya Ghar consumers can opt out until 31 March 2027.

8SET 2026 ranks 21 Indian states as renewable capacity hits 274 GW and demand climbs to 1,707 billion units
The Indian States' Electricity Transition (SET) 2026 fact sheet evaluates the preparedness of 21 Indian states for the clean-electricity transition, noting India's electricity demand rose 34% between FY2021 and FY2026 to 1,707 billion units. India's renewable capacity reached 274 GW including large hydro, with over 150 GW of solar as of March 2026, taking non-fossil sources to 50% of installed capacity. Progress is uneven, with Karnataka and Himachal Pradesh among the strongest performers.
Details
PPA SIGNING & APPROVAL

8HPERC takes up the supplementary PPA for the 1.50 MW Bagipul hydro project, decided 9 June 2026
The Himachal Pradesh Electricity Regulatory Commission, in Petition No. 74 of 2026 decided on 9 June 2026, heard the joint petition of HP State Electricity Board Limited and M/s Shree Khand Mahadev Hydro Energy Private Limited for approval of a supplementary power purchase agreement for the 1.50 MW Bagipul Hydro Electric Project. The petition was filed under Section 86(1)(b) of the Electricity Act, 2003. It was instituted on 12 May 2026 and heard on 15 May 2026.

CAPACITY COMMISSIONING & COD

8CEA logs Subansiri Lower's fourth 250 MW unit and Tidong-I's first 50 MW unit online in May 2026
The Central Electricity Authority reported that the fourth 250 MW unit of the Subansiri Lower hydro project and the first 50 MW unit of Tidong-I were both commissioned in May 2026. As on 31 May 2026, India had 212 hydro stations above 25 MW totalling 44,539.07 MW in operation, against an identified potential of 539 projects and 1,33,410 MW. Another 29 projects (13,373.5 MW) are under construction, CEA said.

EQUITY & STAKE ACQUISITION

8Quality Power signs term sheet to acquire 100% of Winwin Speciality Insulators
Quality Power Electrical Equipment Limited told the exchanges on 9 June 2026 that it has executed a term sheet for the proposed acquisition of a 100% stake in Winwin Speciality Insulators Limited. The disclosure, under Regulation 30 of the SEBI LODR, said detailed terms will follow once definitive agreements are signed, subject to due diligence. Quality Power trades under NSE symbol QPOWER and BSE code 544367, and has logged the price-sensitive information in its Structured Digital Database.

8Adani Energy Solutions to buy 100% of IntelliSmart for Rs. 3,050 crore, building a 4.7-crore smart-meter platform
Adani Energy Solutions Limited signed a securities purchase and subscription agreement on 9 June 2026 to acquire 100% of Intellismart Infrastructure Private Limited from NIIF and Energy Efficiency Services Limited for a total consideration of Rs. 3,050 crore. IntelliSmart, among India's top three smart-metering players with over 2.2 crore meters across five states, will lift the group's portfolio past 4.7 crore meters. The deal makes AESL India's largest smart-metering platform, the company said.
Details
RETAIL TARIFF REVISION

8HESCOM to levy 35 paise/unit FPPCA in June 2026 after a Rs. 53.25 crore power-purchase cost spike
Hubli Electricity Supply Company Limited will collect a Fuel and Power Purchase Cost Adjustment charge of 35 paise per unit from all consumer categories between 1 and 30 June 2026. The levy follows a Rs. 53.25 crore increase (including the Z-factor) in HESCOM's April 2026 power-purchase cost over the amount approved in its 2025 tariff order, computed under the KERC FPPCA First Amendment Regulations, 2023. The order was issued on 30 May 2026.

COMMISSION ORDERS (CERC/SERC)

8CSERC dismisses CSPDCL's contempt plea against BALCO over cross-subsidy surcharge, citing a pending review
The Chhattisgarh State Electricity Regulatory Commission, in an order dated 8 June 2026 in Petition No. 14 of 2022, dismissed CSPDCL's plea seeking action under Sections 142 and 146 of the Electricity Act against Bharat Aluminium Company over a 27 July 2016 cross-subsidy-surcharge order for 2014-15 open-access power. The Commission held that with the dispute pending in Review Petition No. 04 of 2026, it would be inappropriate to act under Section 142, granting CSPDCL liberty to refile later.

8MERC orders MSEDCL to put Lumex Industries' 999 kW rooftop solar on net metering from April 2025
The Maharashtra Electricity Regulatory Commission, in Case No. 245 of 2025 dated 9 June 2026, directed MSEDCL to treat M/s. Lumex Industries Limited's 999 kW rooftop solar system under net metering from April 2025, when the firm first availed open access. MSEDCL had been crediting solar generation at gross-metering rates of Rs. 2.90 and Rs. 2.82 per unit. MERC ordered both parties to reconcile the differential credit within 30 days, with interest at the Bank Rate.

TRANSMISSION LICENSING & ORDERS

8CERC moves to grant Mumbai's PRMK Energy a Category-V inter-State trading licence, invites objections by 17 June 2026
The Central Electricity Regulatory Commission proposed, by order dated 3 June 2026 in Petition No. 214/TD/2026, to grant Mumbai-based PRMK Energy a Category-V licence for inter-State electricity trading across India. Issuing notice under Section 15(5)(a) of the Electricity Act, 2003, the Commission invited suggestions or objections from any person by 17 June 2026. The application and annexures may be inspected at the Commission's office or accessed on the applicant's website.

OMBUDSMAN & CONSUMER GRIEVANCE

8TNERC orders TNPDCL to fill vacancies in 12 consumer grievance forums by 15 June 2026
The Tamil Nadu Electricity Regulatory Commission directed TNPDCL, in a letter dated 8 June 2026, to immediately fill member vacancies in 12 Consumer Grievance Redressal Forums — including Chennai (North), Chennai (West), Salem, Tirupur, Vellore and Thiruvallur — operating below their full complement under Regulation 3(4) of the 2004 CGRF Regulations. Warning of possible action under Section 142 of the Electricity Act, the Commission sought a consolidated compliance report by 15 June 2026.

8HPERC extends its electricity ombudsman application deadline to 19 June 2026
The Himachal Pradesh Electricity Regulatory Commission, in a public notice dated 9 June 2026, extended the last date for applications for appointment of the Electricity Ombudsman to 19 June 2026, from the earlier 6 June 2026. The original notice had been advertised on 14 May 2026 in The Times of India (Chandigarh) and Amar Ujala. All other terms and conditions remain unchanged, the Commission said.
Details
ANNUAL RESULTS

8RMC Switchgears posts FY26 revenue of Rs. 401.6 crore, nearly 10 times its FY22 level
RMC Switchgears Limited reported full-year FY26 revenue of Rs. 401.6 crore in its Q4 and FY26 investor presentation, up from Rs. 41.6 crore in FY22, with EBITDA rising to Rs. 47.1 crore from Rs. 5.6 crore and PAT to Rs. 22.5 crore from Rs. 0.58 crore. The company attributed the surge to a shift toward higher-margin products such as its PulseBox smart-metering enclosures. The presentation was filed with BSE and NSE on 8 June 2026.

DIVIDEND & BOARD DECISIONS

8Torrent Power fixes 19 June 2026 as record date for its Rs. 5 final dividend
Torrent Power Limited told the exchanges it has set Friday, 19 June 2026 as the record date for a final dividend of Rs. 5 per equity share for the financial year ended 31 March 2026. The intimation was made under Regulation 42 of the SEBI LODR Regulations. The dividend remains subject to approval by shareholders at the company's forthcoming AGM. Torrent Power trades under BSE code 532779 and NSE symbol TORNTPOWER.

FUND RAISING & CAPITAL

8Ministry of Coal launches NLC India OFS to sell a 2% stake, or 2.77 crore shares, from 9 June 2026
The Ministry of Coal, acting for the President of India as promoter, opened an Offer for Sale of NLC India Limited shares (face value Rs. 10 each) from 9 June 2026. The base offer covers 2.00% of paid-up equity, or 2,77,32,732 shares, for non-retail investors on 9 June and retail investors on 10 June, with an oversubscription option to sell another 1.00%, or 1,38,66,366 shares. The sale runs through the stock-exchange OFS mechanism.

CREDIT RATING & ANALYST REPORT

8Moody's affirms 'Ba1/Stable' on JSW Hydro Energy's USD bonds, JSW Energy tells exchanges
JSW Energy Limited informed BSE and NSE on 9 June 2026 that Moody's Ratings, in a release dated 8 June 2026, affirmed a 'Ba1/Stable' rating on the Senior Secured Notes (USD bonds) of JSW Hydro Energy Limited, a step-down subsidiary. The intimation was filed under Regulation 30 of the SEBI LODR. JSW Energy, part of the O.P. Jindal Group, trades under BSE code 533148 and NSE symbol JSWENERGY.

8Choice Equity initiates 'Buy' on Yash Highvoltage with a Rs. 1,200 target, 71% above the Rs. 703 price
Choice Equity Broking initiated coverage on Yash Highvoltage Limited on 8 June 2026 with a 'Buy' rating and a target price of Rs. 1,200 against a market price of Rs. 703. The brokerage projects revenue, EBITDA and PAT CAGR of 47%, 53% and 48% respectively over FY26-29E, driven by backward integration and an improving product mix. It notes Yash is among fewer than 12 independent transformer-bushing makers globally, with NTPC and PGCIL approvals and 57.94% promoter holding.
Details
 For reference purposes the website carries here the following tenders:
 
8Tender for drawing new 11kV UG feeder Details
  8Tender for supply of various guide rollers and stands Details
  8Tender for providing & fixing concertina wire fencing with relevant misc. work Details
  8Tender for construction of 33/11 kV GSS Details
  8Tender for major maintenance like whitewash, roof treatment etc Details
  8Tender for supply of ESP spares Details
  8Tender for procurement of conveyor belt for mill rejects system Details
  8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details
  8Tender for biennial rate contract for works of online, preventive and breakdown maintenance of coal mills Details
  8Tender for fabrication dismantling erection strengthening modification of various chutes hoppers wagon tipplers belt conveyors crusher houses Details
  8Tender for erection, testing, commissioning, trial operation and handing over of boiler and auxiliaries Details
  8Tender for misc. civil work Details
  8Tender for work of erection and strengthening of H-frame lines for DOG to HTLS conductor conversion work Details
  8Tender for work of in situ repairing/overhauling of high energy drain valves and other low/medium/high pressure and temperature steam/water valves Details
  8Tender for supply of various sizes of M S ERW pipes/bends Details
  8Tender for supplying and laying of gravel with rain water harvesting system Details
  8Tender for maintenance of illumination system of ARS, technical cell stores and cable galleries Details
  8Tender for biennial mechanical maintenance contract for boiler, turbine and their auxiliaries Details
  8Tender for strengthening and protection of towers Details
  8Tender for repair, maintenance, renovation and development work Details
  8Tender for construction of main plant Details
  8Tender for supply, fabrication and erection of ducting and louvers/mist extractor of ventilation system Details
  8Tender for repair and HP-HVOF coating work of 01 no. top cover and 01 no. lower ring of 115 MW hydro generating Details
  8Tender for procurement of ESP spares for unit 4 ESP overhauling Details
  8Tender for construction of 11 kV dedicated feeder to provide power supply Details
  8Tender for work of overhauling & re-commissioning of R.O. feed pumps Details
  8Tender for repairing of various cards of DCS system installed Details
  8Tender for package A procurement of 22 nos air conditioning unit Details
  8Tender for balance works of 33kV lines Details
  8Tender for BMC for mill reject loading and conveying works Details
  8Tender for complete reconditioning overhauling revival of damaged 250 KVA 415V 3phase DG set Details
  8Tender for SITC of high mast yard lighting including laying of foundation for 132 by 33 kV outdoor switchyard Details
  8Tender for Re tubing of damaged coolers Details
  8Tender for SITC of 11kV VCB panel board 12kV 1250A 25KA with over current fault earth fault relays Details
  8Tender for construction of desilting basin Details
  8Tender for construction of control room RCC cable trench, drain, fencing Details
  8Tender for supply of armoured control cable multistrand of different size Details
  8Tender for carrying routine patrolling preventive breakdown maintenance of 132kV D/C transmission line Details
  8Tender for supply and installation of air condition Details
  8Tender for operation and minor maintenance of various EHV substations Details
  8Tender for providing round the clock assistance in day to day working of generation control Details
  8Tender for manufacture and supply of manganese steel toothed/plain ring hammers for coal handling plants Details
  8Tender for manufacture and supply of high pressure cold drawn seamless steel tubes for use in high pressure boilers Details
  8Tender for procurement of FR and NFR grade conveyor belt for various Details
  8Tender for procurement of ERW steel tubes for air preheaters of 210 MW capacity boilers Details
  8Tender for procurement of bag filters Details
  8Tender for annual work contract for hiring of 04 nos. water mist fog machines for silos Details
  8Tender for up-gradation of main turbine Details
  8Tender for distribution transformer station standardisation work Details
  8Tender for transformer fencing at various Details
  8Tender for development of distribution infrastructure Details
  8Tender for foundation construction, erection and stringing of DC NB 60 tower Details
  8Tender for external painting and essential repair works Details
  8Tender for construction of 66kV sub station Details
  8Tender for installation and shifting of pump sets and other repair and maintenance civil work Details
  8Tender for renovation of room for setting up of laboratory for testing of biomass pellets Details
  8Tender for supply of seals of various gates of 500MW boiler Details
  8Tender for work for emergency replacement, lifting & shifting, O/H and dismantling of 6.6 kV HT motors Details
  8Tender for miscellaneous civil works Details
  8Tender for supply, erection, testing & commissioning of wire rope hoist Details
  8Tender for work of thermal spray insulation of HP, IP turbine casing and governing valves of 4x210 KWU designs TG units Details
  8Tender for work of construction of new sub division Details
  8Tender for overhauling of boiler auxiliaries Details
  8Tender for work of 66kV line Details
  8Tender for beautification, rectification, safety compliance and system strengthening of low-lying LT and associated 11 kV distribution network Details
  8Tender for supply installation and commissioning of 27 No. 1.5 ton non inverter type split air conditioners Details
  8Tender for release of service connections of new HT/LT line & LT sub stations Details
  8Tender for temporary work of erection and dismantling 11 kV, LT line, street light connection Details
  8Tender for work of supply and installation of MCCBs in 25 KVA, 63 KVA and 100 KVA distribution transformers Details
  8Tender for work of replacement of existing ACSR weasel conductor Details
  8Tender for miscellaneous support service job Details
  8Tender for service contract for stage-III (1x660 MW) electrical maintenance Details
  8Tender for load testing and certification of 04 Nos. EOT cranes Details
  8Tender for repair & complete overhauling work of 298.6 MVA converter transformer & 360 mH 500 kV smoothing reactor Details
  8Tender for annual maintenance contract for attending emergency breakdown, planned maintenance activities of 220kV & 100kV lines Details
  8Tender for providing & fixing of portable & programmable battery charger suitable for 48V, 110V & 220V-50Amp with DC voltage monitoring and backup power system along Details
  8Tender for work of providing and fixing of 33 kV current transformers Details
  8Tender for work of replacement of faulty MOG, air-cells of transformer’s & ICT’s at various 220/132/110kV S/Stns Details
  8Tender for AMC for the work of repair/overhauling/servicing & alignment of various make 220kV, 132KV & 33kV isolators installed Details
  8Tender for work of overhauling, servicing, repair, and maintenance of 220kV & 132kV CBs at various EHV substations Details
  8Tender for work of shifting work of 220 kV S/C line Details
  8Tender for erection of 66 kV equipment, structures, control wiring, yard lighting & control-room electrification etc. Details
  8Tender for purchase of DP set for 10,16,25 KVA transformer Details
  8Tender for erection of structures, equipments, earthing, control wiring, yard lighting Details
  8Tender for route survey report for under ground cable line Details
  8Tender for Bi-annual rate contract for erection of 66 kV line feeder bay / transformer bay for various Details
  8Tender for Bi-annual rate contract for the work of an original survey with line Details
  8Tender for various C&I related job works Details
  8Tender for work of erection of structures, equipments, earthing, control wiring, yard lighting Details
  8Tender for erection work of 66kV S/C line on D/C towers Details
  8Tender for erection work of 66kV S/C line Details
  8Tender for work of repairing of various pulleys of conveyor belts Details
  8Tender for supply of various sizes of metallic expansion bellow of flue gas duct of boiler Details
  8Tender for work of repairing of various pulleys of conveyor belts in coal handling plant Details
  8Tender for supply of electrical actuator for feed control valve Details
  8Tender for providing JCB and hitachi machine and other civil works Details
  8Tender for providing & spreading metal at switchyard and misc. civil works Details
  8Tender for replacement of damaged water supply and drainage line Details
  8Tender for providing acid resistant brick lining Details
  8Tender for repair, maintenance, and installation of plant/ systems/equipments Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Govt publishes rules for setting up coal exchanges to boost transparency Details
 
8Coal Ministry notifies Coal Exchange Rules, paves way for market-based coal trading Details
 
8SAIL, NMDC Explore Russian Coal Mines Amid Raw Material Push Details
 
8Coal exchanges get green light; market-driven price discovery to follow Details
 
8Mandatory domestic solar cell rule set to reshape industry, drive consolidation: Report Details
 
8India's hidden battery fleet can become key to managing power demand Details
 
8GREW Solar seeks ALMM nod for 3.5 GW cell capacity Details
 
8Solar Module Manufacturers Flag Concerns Over Domestic Cell Availability Details
 
8Solar And Storage Must Go Together", Says Hanish Gupta, Founder & MD Sunkind India Ltd Details
 
8From ESG to EBITDA: Indian Cement Makers Turn to Solar and Green Power to Protect Margins Details
 
8Grid bottlenecks threaten renewable energy push, warn industry leaders Details
 
8ACME Solar Raises Rs 2800 Crore Through QIP, Attracts Strong Global And Domestic Investor Interest Details
 
8Rajnath Singh approves 250 MW solar plant on defence land in UP's Sitapur Details
 
8EPIL Invites EPC Partners for 250 MW Solar Project in Rajasthan Details
 
8CMR Green Technologies IPO Listing Date: 5 key things retail investors should know before it hits BSE, NSE Details
 
8A small bird has taken over a plot of land, forcing the suspension of a 10-million-panel solar project Details
 
8How PM Surya Ghar Is Bringing India’s Energy Security Push Into People’s Homes Details
 
8Rajnath Singh Approves First Large-Scale Solar Power Project on Defence Land in Uttar Pradesh Details
 
8Amul’s Rs 700 Crore West Bengal Plant: A Dairy Sector Update Details
 
8Tamil Nadu moves to standardise renewable energy sector, simplify approvals Details
 
8PESB names PLSS Chaitanya Prakash for NLC India Ltd's Director (Power) post Details
 
8BP Restructures Leadership for Upstream and Downstream Units Details
 
8Solar power growth outpaced gas by 17 times in 2025: Ember Details
 
8NTPC bets on internal talent, elevates 34 executives to senior leadership Details
 
8Adani Energy Solutions Signs Binding Agreement To Acquire IntelliSmart Details
 
8Bosch Introduces Third-Generation SiC Chips for Electric Vehicle Applications in India Details
 
8PESB Recommends PLSS Chaitanya Prakash as Director (Power) of NLC India Limited Details
 
8Solar surge pushes gas power to the margins globally: Report Details
 
You can also click on Newsclips for more Details
8New Delhi's bold bet on a digital coal marketplace promises transparent pricing and energy security - but industry veterans warn the devil is in the details. Details
8CERC's draft regulation to hand price-discovery powers to Grid India has split India's electricity sector right down the middle - with power exchanges fighting back in the Supreme Court, DISCOMs cheering from the sidelines, and everyone else somewhere in between. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8LPG
8Ammonia
8Coal & Coke
Click on Reports for more. Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
8200 MVA transformer-bay package sharpens focus on turnkey execution capability and bidder risk allocation
A transmission package centred on a 200 MVA transformer deployment carries implications that extend well beyond equipment supply. The tender structure concentrates responsibility across engineering, civil works and commissioning while intensifying commercial pressure through competitive price discovery.

8Mandsaur solar bid framework redraws qualification norms for a 900 MW opportunity with a Rs 3 crore bid security
A seemingly straightforward solar EPC exercise carries a qualification structure that could reshape bidder behaviour before commercial competition even begins. The tender embeds a series of filters that reward scale, financial strength and execution experience while limiting alternative routes to participation.

8Uri-I Stage-II package worth Rs 641 crore sharpens focus on execution strength and compliance discipline
A high-value hydroelectric package is doing more than seeking an execution partner. The procurement framework reveals a deliberate effort to balance competition, qualification standards and regulatory compliance within a single bidding structure.

8ESP upgrade package tightens bidder flexibility as emissions-control retrofit requirements grow more demanding
A major emissions-control retrofit package is centred on rebuilding a legacy electrostatic precipitator system, but the more significant story lies in the evolving procurement framework. The tender narrows technical flexibility for bidders while expanding engineering, integration and execution responsibilities.

8Transformer repair programme worth Rs 275 crore tightens capability filters across a statewide rate contract
A large-scale asset restoration programme is entering the market with a contract structure that offers unusual pricing flexibility compared with conventional repair tenders. The qualification framework places greater emphasis on infrastructure-backed execution capability, potentially raising the bar for participation.

8GIS alliance framework signals a deeper shift in risk allocation ahead of a major nuclear-linked transmission package
The tender is less about procuring GIS equipment and more about securing a long-term technology partner before the main transmission project reaches award stage. A combination of localisation requirements, customer-approval mechanisms and extended post-supply obligations redistributes execution risk across the supply chain.

8GIS qualification framework shifts as Rs 50 crore benchmark and package-wide evaluation redefine bidder strategy
A series of late-stage amendments has reshaped how suppliers qualify and compete for a critical GIS package linked to a major nuclear power expansion programme. The most significant development is not the extension of timelines but the redesign of qualification thresholds and package-level evaluation criteria.

8Rs 774 crore transformer procurement drive highlights the growing importance of scale, capacity and execution readiness
A large multi-package transformer procurement programme has emerged as utilities intensify efforts around network strengthening, standardisation and supply reliability. While the contract value attracts attention, the deeper competitive challenge may revolve around manufacturing capability, delivery commitments and compliance preparedness. Details
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details
8A transmission package covering upgrades at four substations across two districts has been awarded at almost Rs 144 crore, incorporating SCADA integration, fibre connectivity and GIS-based asset mapping.
8Unlike several recent grid projects that saw limited participation, this package attracted a broader mix of interested players and delivered a comparatively disciplined pricing outcome. Details
PEAK DEMAND & POWER SUPPLY POSITION

8All-India peak demand of 2,70,820 MW fully met in May 2026 with zero shortage, though Kerala faced 4.8% gap: CEA
According to CEA's provisional Peak Power Supply Position report, India's all-India peak demand of 2,70,820 MW in May 2026 was met in full, registering 0.0% peak shortage. State-level stress was concentrated in the south and islands: over April-May 2026, Kerala's peak demand of 6,488 MW saw 311 MW, or 4.8%, unmet, and the Andaman & Nicobar system left 6 MW unmet, while Telangana, Karnataka and Puducherry reported minor shortfalls. Uttar Pradesh topped the demand chart at 31,824 MW, fully met.

8India met 99.9% of power demand in May 2026 with 1,64,438 MU supplied against 1,64,565 MU requirement: CEA
CEA's provisional Energy Power Supply Position report shows all-India energy requirement of 1,64,565 MU in May 2026, against which 1,64,438 MU was supplied, leaving an energy shortfall of just 127 MU, or 0.1%. The Northern Region recorded the largest deficit at 92 MU, with Haryana at 40 MU and Punjab at 28 MU the biggest contributors, while Rajasthan, Gujarat and Madhya Pradesh reported zero shortfall. For cumulative April-May 2026, the country needed 3,17,521 MU and was supplied 3,17,180 MU, a 0.1% gap.

8Northern Region meets its 8 June 2026 peak with a small 314 MW shortfall: NRLDC
The Northern Regional Load Despatch Centre's daily report for 8 June 2026 showed the region largely meeting demand but recording a peak shortfall of 314 MW during the day's maximum-demand hour. The deficit, concentrated in a handful of states during the evening peak, was partly met through inter-regional support over the national grid. The NRLDC report tracks served demand against schedule across the northern states, with the 314 MW shortfall representing a fraction of a percent of the region's overall peak requirement.

8Western Region meets its evening peak in full on 8 June 2026, Maharashtra at zero shortage: WRLDC
The Western Regional Load Despatch Centre's daily operation report for 8 June 2026 recorded the region meeting its evening peak demand in full, with Maharashtra — the largest load centre in the region — registering zero unmet demand. The report covers served demand, frequency and reliability across Gujarat, Maharashtra, Madhya Pradesh, Chhattisgarh, Goa and the union territories. The fully-met outcome aligns with the all-India picture of negligible peak shortage during the early-June period across the synchronised national grid.

8Eastern Region peaks at 30,372 MW on 8 June 2026 with zero shortage: ERLDC
The Eastern Regional Load Despatch Centre's daily report for 8 June 2026 recorded a regional peak demand of 30,372 MW met with zero shortage. Spanning Bihar, Jharkhand, Odisha, West Bengal, Sikkim and the DVC system, the region drew on its thermal-heavy generation base supplemented by inter-regional exchanges. The zero-shortage outcome continued the trend of fully-met demand across India's regions during the early-June window, even as individual generating units such as NTPC's Darlipali remained under forced outage.

8North Eastern Region peaks at 3,796 MW on 8 June 2026, Tripura among leading loads: NERLDC
The North Eastern Regional Load Despatch Centre's daily report for 8 June 2026 recorded a regional peak demand of 3,796 MW, with Tripura among the leading load centres in the region. Covering the seven north-eastern states, the report tracks served demand alongside transmission constraints on the NER-Tripura and NER-Assam corridors, both of which saw Total Transfer Capability breaches in the period. Despite the corridor congestion, the region met its peak demand without a recorded shortage on the day.

8Southern Region peaks at 54,946 MW on 8 June 2026, Tamil Nadu topping demand: SRLDC
The Southern Regional Load Despatch Centre's daily report for 8 June 2026 recorded a regional peak demand of 54,946 MW, with Tamil Nadu the largest contributor among the southern states. The report tracks served demand, generation mix and reservoir status across Andhra Pradesh, Karnataka, Kerala, Tamil Nadu, Telangana and the union territories. Southern peak demand was met without a significant recorded shortfall, even as Kerala continued to register a small unmet-demand gap in the monthly CEA assessment.

8Southern grid handles 1,261.4 MU of energy at its daily peak on 8 June 2026: SRLDC
The Southern Regional Load Despatch Centre's daily system-operation report for 8 June 2026 recorded the region handling 1,261.4 MU of energy through its synchronised network during the day. The figure captures total energy scheduled and dispatched across the Southern Region's generation and inter-regional exchanges, against a peak demand that touched 54,946 MW. The daily energy-handled metric tracks the operational throughput of the region's load-despatch function across thermal, hydro, nuclear and renewable sources.

FREQUENCY & DEVIATION INDICES (FDI/VDI)

8India's grid stays stable on 8 June 2026 with 50.01 Hz average frequency but spends 6.58 hours outside IEGC band
Grid Controller of India's NLDC frequency profile for 8 June 2026 recorded an average system frequency of 50.01 Hz with a standard deviation of 0.062 and a Frequency Deviation Index of 0.039. Instantaneous frequency peaked at 50.183 Hz at 08:00 and dipped to 49.672 Hz at 12:40, while the grid spent 27.42% of the day — about 6.58 hours — outside the prescribed IEGC band of 49.9–50.05 Hz. Only 40% of daily time fell within the tighter 49.97–50.03 Hz band, underscoring notable intra-day frequency volatility.

8Southern grid logs a Voltage Deviation Index of 0.43 at Annaikavadu on 8 June 2026: SRLDC
The Southern Regional Load Despatch Centre's deviation-indices report for 8 June 2026 recorded a Voltage Deviation Index of 0.43 at the Annaikavadu node, a measure of how far bus voltage strayed from its nominal value over the day. The VDI complements the region's frequency-deviation tracking in gauging power-quality and reactive-management performance. The reading at Annaikavadu, one of the monitored Southern Region nodes, fed into SRLDC's assessment of voltage stability across the southern grid during the pre-monsoon demand period.

SYSTEM RELIABILITY & SECURITY

8WRLDC flags DNHDDPDCL ATC violations in 28 blocks on 8 June 2026, the Western Region's highest breach
The WRLDC's Daily System Reliability Indices report for 8 June 2026 highlighted that DNHDDPDCL violated Available Transfer Capability limits in 28 blocks — 7.0% of the day — for a total of 29.2 hours, the highest breach in the Western Region. Maharashtra breached ATC in 6 blocks, or 1.5% of the day. For the N-1 security criterion, DNHDDPDCL again led with 14 blocks of violation, while Gujarat, Madhya Pradesh, Chhattisgarh and Goa recorded zero violations on both metrics.

8Grid-India tracks angular separation across 22 monitored buses on 8 June 2026
Grid Controller of India's system-reliability monitoring for 8 June 2026 reported the angular separation of voltage phasors across 22 monitored buses spanning the national grid, a key indicator of transmission stress and the risk of loss of synchronism. The angular-spread data, drawn from wide-area phasor measurement units, complements the day's frequency and Available Transfer Capability indices in assessing system security. The 22-bus spread remained within operationally acceptable bounds, indicating no imminent stability threat across the synchronised grid.

8NERLDC reports 16 North Eastern substations holding voltage within band on 8 June 2026
The North Eastern Regional Load Despatch Centre's reliability report for 8 June 2026 recorded 16 substations across the region maintaining bus voltages within the prescribed operating band, supporting frequency and voltage stability in a region prone to transmission-corridor congestion. The voltage-profile data accompanies the NER-Tripura and NER-Assam Total Transfer Capability assessments for the same period. Holding voltages within band across the monitored substations reduced the risk of equipment stress and reactive-power imbalance in the north-eastern network.

LOAD FORECAST

8SRLDC week-ahead demand forecast for 8–14 June 2026 spans a 45,000–65,000 MW band
SRLDC released its week-ahead demand forecast for the Southern Region covering 8–14 June 2026, projecting demand across a wide band of roughly 45,000–65,000 MW based on historical load patterns. The daily forecast for 8 June 2026 shows the region expected to touch around 60,000 MW during peak afternoon and evening hours. The previous day's forecast accuracy was validated at a MAPE of 1.97%, indicating strong predictive performance by SRLDC's LGBR-based model, guiding scheduling and ancillary-services procurement decisions.

8ERLDC's demand forecast for the Eastern Region logs a 4.24% MAPE on 8 June 2026
The Eastern Regional Load Despatch Centre's load-forecasting report for 8 June 2026 recorded a Mean Absolute Percentage Error of 4.24% against actual demand, a wider miss than the Southern Region's 1.97% on the same metric. The forecast guides the Eastern Region's day-ahead scheduling and reserve planning across Bihar, Jharkhand, Odisha, West Bengal, Sikkim and the DVC area. The higher error reflects the comparatively greater volatility in the region's demand profile during the pre-monsoon period.

TRANSMISSION CAPACITY (TTC/ATC)

8NERLDC reports NER–Tripura TTC violated in 43 blocks and NER–Assam in 16 blocks on 7 June 2026
The North Eastern Regional Load Despatch Centre's System Reliability Report for 7 June 2026 revealed significant Total Transfer Capability violations on two critical inter-state corridors. The NER–Tripura corridor saw TTC breached in 43 blocks — 10.78% of the day, or 44.9 hours — the largest in the region, while the NER–Assam corridor recorded violations in 16 blocks, or 3.9%. Utilities in both import and export control areas were directed to restrict drawal or injection to keep TTC within limits, with all intimations confirmed to the relevant SLDCs.

LINE & GENERATION OUTAGES

8Eastern Region outage report shows NTPC Darlipali 800 MW unit still offline, 2,510 MW in forced central outage on 8 June 2026
The ERLDC generation outage report for 8 June 2026 showed NTPC's Darlipali Unit 2 — 800 MW, Odisha, coal — still offline after a boiler-tube-leakage forced outage on 6 June, with revival expected on 9 June. Teesta HPS units 1, 2 and 3 (170 MW each) of NHPC in Sikkim have been in forced outage since October 2023, as have all six Teesta Stage III units (200 MW each) hit by the 2023 glacier cloudburst. Total Central Sector forced outage capacity stood at 2,510 MW.

8Southern Region runs 11 forced transmission outages and 1,748 MW of generation outages on 8 June 2026: SRLDC
The Southern Regional Load Despatch Centre's outage report for 8 June 2026 recorded 11 forced transmission-line outages alongside 1,748 MW of generating-unit outages across the region. On the generation side, the report noted Vijayawada Thermal contributing 1,824 MW and Greenko's pumped-storage facility supplying 511 MW to the southern grid during the day. No Total Transfer Capability or Available Transfer Capability violations were recorded in the region, indicating the outages were absorbed without breaching inter-state transfer limits.

OCC MEETINGS & OUTAGE PLANNING

8SRLDC planned transmission shutdown report for 8 June 2026 lists Southern network elements under extended outage
SRLDC's planned transmission shutdown report for 8 June 2026 documents a series of scheduled outages on Southern Region transmission elements, several running since 2023–2025. Notable long-duration cases include the two 400 kV Ramagundam–Telangana STPP lines of POWERGRID under outage since March 2023 pending hot test and full commissioning, APTRANSCO's 400 kV GMR–Vemagiri and GVK–Vemagiri lines offline since 2024, and KPTCL's dual 220 kV Narendra–Mahalingapura lines down since August 2025 for LILO works and commissioning of a new 220 kV Bannur substation.

REGIONAL ENERGY ACCOUNT (REA/REMC)

8ERPC revises MTPS-II and Odisha transmission deviation accounts after GNA correction to 390 MW; Odisha billed Rs. 4.28 lakh
The Eastern Regional Power Committee on 8 June 2026 issued revised Regional Transmission Deviation Accounts for Maithon Power's MTPS-II covering October 2023 to March 2026 and a revised account for Odisha for September 2024, citing an inadvertent error in GNA figures. For MTPS-II the injection GNA was corrected to 390 MW from 354.9 MW, producing overdrawal charges of Rs. 2,70,116 for December 2025 and smaller sums in other months. For Odisha, an excess drawal of 3,300.890 MW in September 2024 generated transmission deviation charges of Rs. 4,27,762.
Details
COAL PRODUCTION & STOCK

8CEA pegs all-India coal stock at 47.89 million tonnes — just 63% of norm — across 223,498 MW of thermal plants on 7 June 2026
CEA's Daily Coal Stock Report as on 7 June 2026 shows India's 190 monitored thermal plants, totalling 223,498 MW, holding 47,891.6 thousand tonnes of coal — only 63% of the 75,555.7-thousand-tonne normative requirement. Against a daily requirement of 3,107.8 thousand tonnes, plants received 2,615.1 thousand tonnes and consumed 2,586.5 thousand tonnes that day. As many as 27 plants were flagged with critical stock, while NTPC and its joint ventures, at 63,210 MW, held 76% of their normative stock.

GENERATION & PLF

8India generates 4,678.61 MU on 6 June 2026, 1.85% below the 4,746.46 MU programme: CEA
CEA's All-India and Region-wise Power Generation Overview for 6 June 2026 records actual generation of 4,678.61 MU against a day programme of 4,746.46 MU, a 1.85% shortfall, from a monitored capacity of 311,573.79 MW. Thermal stations contributed 4,067.00 MU, hydro 415.33 MU and nuclear 185.80 MU, with a further 10.48 MU imported from Bhutan. The Western region overshot its programme at 1,686.17 MU against 1,615.44 MU, while the Northern region fell 6.72% short at 1,199.94 MU.

8NTPC stations generate 1,033.61 MU on 6 June 2026, running 3.15% behind FY27 target: CEA
CEA's NTPC generation reports for 6 June 2026 show NTPC's monitored capacity of 60,007.23 MW — of which 52,493.88 MW was available — generating 1,033.61 MU against a 1,047.58 MU day programme. From 1 April, NTPC stations produced 68,343.11 MU versus a programmed 70,564.48 MU, trailing the target by 2,221.37 MU, or 3.15%. The companion station-wise report broke output down by individual thermal and hydro units, including an 800 MU-potential hydro block.

8Coal-fired stations supply 3,894.49 MU of India's 4,678.61 MU generation on 6 June 2026: CEA
CEA's fuel-wise generation breakdown for 6 June 2026 shows coal-fired thermal stations supplying 3,894.49 MU out of India's total 4,678.61 MU of generation, underscoring coal's dominant share of the daily energy mix. The balance came from gas, hydro at 415.33 MU, nuclear at 185.80 MU and renewables, with a small import of 10.48 MU from Bhutan. The fuel-wise split highlights the continued reliance on coal for baseload supply even as renewable capacity expands across the national grid.

HYDRO & RESERVOIR

8CEA tracks 25 major reservoirs on 6 June 2026; Bhakra at 481.29 m against 513.59 m full level
CEA's Daily Hydro Reservoir Report for 6 June 2026 monitored 25 major reservoirs nationwide ahead of the monsoon. Bhakra in Himachal Pradesh stood at 481.29 m against its full reservoir level of 513.59 m, carrying an energy potential of 5,282 MU at full level, while Gujarat's Sardar Sarovar was at 127.93 m versus a 138.68 m full level. Other large reservoirs tracked included Telangana's Nagarjuna Sagar and Odisha's Balimela, data that feeds into national hydro scheduling decisions.

8CEA has concurred 105 hydro schemes totalling 70,930 MW since 2002-03, led by recent PSP mega-projects
CEA's listing of hydro-electric schemes concurred or appraised since 2002-03, updated as on 31 May 2026, now runs to 105 schemes with a combined installed capacity of 70,930 MW. The most recent additions in 2025-26 are dominated by large private pumped-storage projects, including Torrent Power's 3,000 MW Saidongar Karjat PSP concurred 9 January 2026, Adani's 1,500 MW Tarali PSP and JSW Energy's 1,500 MW Pane PSP, alongside NHPC's 1,720 MW Kamala HEP. The list spans landmark projects from the 2,000 MW Subansiri Lower to the 800 MW Kol Dam.

8CEA says 26,554 MW across 31 hydro schemes concurred but still awaiting construction over clearances
CEA's Annex-II, as on 31 May 2026, lists 31 hydro-electric schemes totalling 26,554 MW that have been concurred or appraised but are yet to be taken up for construction. The largest block — 20,420 MW — is stalled over environment and forest clearance issues, with a further 1,213 MW held up for other reasons, 4,675 MW where the validity of concurrence has expired, and 246 MW where MoUs were cancelled. Marquee stuck projects include NHPC's 800 MW Tawang Stage-II and the 520 MW Teesta Stage-IV in Sikkim.

8CEA examining three hydro schemes worth 3,805 MW, including NHPC's 1,605 MW Subansiri Upper and Avaada's 1,560 MW PSP
CEA's Annex-III shows three hydro-electric schemes totalling 3,805 MW currently under examination as on 31 May 2026. These comprise NHPC Limited's 1,605 MW Subansiri Upper project in Arunachal Pradesh, Avaada Closed Water Loop Battery Pvt. Ltd's 1,560 MW Chichlik off-stream pumped-storage project in Uttar Pradesh, and NHDC Ltd's 640 MW Indirasagar Omkareshwar scheme in Madhya Pradesh. The mix highlights the growing role of private off-stream PSPs alongside conventional central-sector hydro capacity.

8Southern hydro reservoirs tracked on 8 June 2026; Supa holds 673.65 MU of energy potential: SRLDC
The Southern Regional Load Despatch Centre's reservoir monitoring for 8 June 2026 tracked major southern hydro storages including Supa, which held an energy potential of 673.65 MU, alongside the Srisailam reservoir on the Krishna. The reservoir data feeds into the region's hydro-scheduling decisions ahead of the south-west monsoon, when inflows typically rebuild storage. Southern hydro availability supplements the region's thermal-heavy generation base and supports peaking and balancing as renewable penetration rises across Andhra Pradesh, Karnataka and Telangana.
Details
MNRE & BEE

8MNRE constitutes Expert Committee to adjudicate ALMM List-II exemption requests for solar projects missing 31 May deadline
The Ministry of New & Renewable Energy issued Office Memorandum No. 283/63/2025 on 8 June 2026, constituting a four-member Expert Committee of officials from SECI, IREDA and NISE to examine project-wise applications for commissioning extensions beyond 31 May 2026 and exemptions from ALMM List-II for solar PV cells. All claims from RE developers must be submitted by 30 June 2026 through the NISE portal; cases involving solar components of 10 MW AC or below are delegated to the senior-most Secretary in the respective state's Power Department.

TENDERS & PROCUREMENT (GeM/NIT)

8MAHAPREIT floats 100 MW behind-the-meter rooftop solar tender for Maharashtra MSMEs with 25-year fixed tariff
Mahatma Phule Renewable Energy & Infrastructure Technology Limited has issued RFP No. MAHAPREIT/RESCO/BTM/01/2026-27 dated 8 June 2026, seeking developers to install 100 MW of rooftop solar across Maharashtra under the RESCO model at zero upfront cost to MSME consumers. The tender is split into four 25 MW sub-categories — solar-only and solar-plus-BESS for the 20–100 kW and 101–250 kW ranges — each with a fixed 25-year PPA. Bidders must deposit an EMD of Rs. 2.25 lakh per MW and submit bids by 23 June 2026.

8JBVNL issues EOI No. 62 seeking 100 MW of wind power for RPO compliance
Jharkhand Bijli Vitran Nigam Limited issued Expression of Interest No. 62/PR/JBVNL/2025-26 seeking qualified agencies to supply 100 MW of wind power to the distribution licensee under a short-term or long-term arrangement, to meet the Wind Renewable Purchase Obligation trajectory mandated by the Jharkhand State Electricity Regulatory Commission. Eligible agencies may offer power from one or more commissioned wind projects with COD on or after the specified date, must hold a valid trading licence if applying as a trader, and must submit company details as per Annexure I.
Details
DAY-AHEAD MARKET (DAM/GDAM/HPDAM)

8IEX Day-Ahead Market clears 120,869.64 MWh for 8 June 2026 at a weighted Rs. 3,673.60/MWh
On the Indian Energy Exchange's Day-Ahead Market, 120,869.64 MWh cleared for delivery on 8 June 2026 at a volume-weighted average price of Rs. 3,673.60/MWh, with purchase bids of 358,597.79 MWh outweighed by sell bids of 405,765.86 MWh. Across the 96 fifteen-minute blocks, the market clearing price swung from about Rs. 1,048/MWh in solar-rich midday hours to the Rs. 10,000/MWh ceiling at night peak. Over 2-9 June, daily cleared volumes averaged 136,102.51 MWh and the daily MCP topped out at Rs. 5,870.35/MWh on 5 June.

8IEX Green Day-Ahead Market clears 241,299.63 MWh in early June, solar supplying 156,543.56 MWh
The Indian Energy Exchange's Green Day-Ahead Market cleared a cumulative 241,299.63 MWh over the early-June window ending with delivery on 8 June 2026, of which solar accounted for 156,543.56 MWh, non-solar 65,836.34 MWh and hydro 18,919.96 MWh — all fully scheduled. The average market clearing price was Rs. 6,072.85/MWh, ranging from Rs. 5,599.74/MWh to a peak of Rs. 6,453.40/MWh, with daily cleared volume averaging about 30,162 MWh. The 15-minute and hourly snapshots confirmed the 8 June delivery-date profile.

8IEX High-Price Day-Ahead Market clears just 4,366.19 MWh on 8 June 2026 despite 579,642 MWh of sell bids
On the Indian Energy Exchange's High-Price Day-Ahead Market, only 4,366.19 MWh cleared for 8 June 2026 even though sell bids totalled 579,642.29 MWh against just 18,253.28 MWh of purchase bids. The average clearing price was about Rs. 3,328.12/MWh, peaking near Rs. 4,166.67/MWh — well within the segment's elevated ceiling — reflecting thin buy-side demand in the high-price window. The 15-minute snapshot showed standing sell offers of around 2,502 MW with little to no clearance through the early blocks.

8HPX Green Day-Ahead Market sees nil clearance for 8 June 2026 across all blocks
The Hindustan Power Exchange's Green Day-Ahead Market recorded no cleared volume for delivery on 8 June 2026, with purchase bids, sell bids, market clearing volume and final scheduled volume all at zero across every fifteen-minute block and in the daily summary. The flat result, reflected consistently through the snapshots from 31 May onward, underscores the limited liquidity in HPX's green day-ahead segment during the period. The nil outcome contrasts with active clearing on rival exchanges for the same delivery date.

8HPX High-Price Day-Ahead Market also records nil clearance for 8 June 2026
The Hindustan Power Exchange's High-Price Day-Ahead Market registered no cleared volume for delivery on 8 June 2026, with market clearing volume and final scheduled volume both at zero across the day's fifteen-minute blocks. The flat outcome mirrors the nil result in HPX's Green Day-Ahead Market for the same date, underscoring the exchange's thin liquidity in its premium and green day-ahead segments. Trading activity for the delivery date was concentrated instead in HPX's Real-Time Market, which cleared 1,095.42 MWh at the Rs. 10,000/MWh ceiling.

REAL-TIME MARKET (RTM)

8IEX Real-Time Market clears 160,478.61 MWh for 8 June 2026 at Rs. 3,802.94/MWh
The Indian Energy Exchange's Real-Time Market cleared 160,478.61 MWh for delivery on 8 June 2026 at a market clearing price of Rs. 3,802.94/MWh, from purchase bids of 258,472.78 MWh and sell bids of 353,216.53 MWh. Across the 2-9 June period, RTM cleared a total of 1,258,713.05 MWh, averaging 157,339.13 MWh a day at an average MCP of Rs. 3,768.73/MWh; daily prices ranged from Rs. 2,972.99/MWh on 7 June to a high of Rs. 5,738.77/MWh on 3 June.

8HPX Real-Time Market clears 1,095.42 MWh for 8 June 2026 at the Rs. 10,000/MWh ceiling
The Hindustan Power Exchange's Real-Time Market cleared 1,095.42 MWh for delivery on 8 June 2026 from a market clearing volume of 1,280.00 MWh, against 9,137.50 MWh of purchase bids and 1,417.50 MWh of sell bids. Clearing prices sat at the Rs. 10,000/MWh ceiling, with block-level cleared volumes reaching as high as 800 MW, while real-time curtailment was recorded as nil. The thin volumes underscore HPX's limited real-time liquidity relative to the dominant IEX platform on the same delivery date.

8PXIL Real-Time Market clears 411 MWh for 8 June 2026 at Rs. 10,000/MWh
Power Exchange India Ltd's Real-Time Market Volume Profile Report records 411.00 MWh cleared and fully scheduled for delivery on 8 June 2026 at a price of Rs. 10,000/MWh, drawn from 505.00 MWh of purchase bids and 411.00 MWh of sell bids. Over 2-9 June, PXIL's RTM clearances were sporadic, ranging from nil on 7 June to 1,150.00 MWh on 2 June, consistently priced at the Rs. 10,000/MWh ceiling. The pattern highlights persistently thin participation in PXIL's real-time segment.

TERM-AHEAD & GREEN TERM-AHEAD (TAM/GTAM)

8IEX Green Term-Ahead Market trades 1,905.35 MWh in 162 deals on 8 June 2026
On the Indian Energy Exchange's Green Term-Ahead Market, 1,905.35 MWh changed hands across 86 daily non-solar contracts and 162 trades for delivery on 8 June 2026. Block-level prices ran from about Rs. 1,520/MWh up to the Rs. 10,000/MWh ceiling, with the individual fifteen-minute green blocks each clearing small volumes of roughly 19 to 29 MWh. The thin per-block volumes reflect the still-nascent liquidity in exchange-traded green term-ahead contracts on the IEX platform.

8IEX Term-Ahead Market trades 14,179.78 MWh across 969 deals on 8 June 2026
The Indian Energy Exchange's Term-Ahead Market saw 14,179.78 MWh traded in 969 deals across 297 contracts for 8 June 2026, spanning daily and intra-day instruments split by region. Prices ranged widely from about Rs. 101/MWh to the Rs. 10,000/MWh ceiling, with sizeable round-the-clock blocks such as a 900 MWh western-region contract clearing at Rs. 5,232/MWh and a 192 MWh eastern-region block at Rs. 6,000/MWh. The activity underlines the term-ahead market's role in bridging spot and bilateral procurement.

ANCILLARY & INTRADAY (ASDAM/IDAS/SCUC)

8PXIL Intra-Day Auction draws 1,100 MWh of bids but clears nothing for 8 June 2026
Power Exchange India Ltd's Intra-Day Auction Session shows 1,100.00 MWh of purchase bids and 867.25 MWh of sell bids for delivery on 8 June 2026, but no market clearing volume or scheduled volume — a nil clearance. Across the 2-9 June series, daily sell bids ranged from 339.50 MWh to 3,455.00 MWh, yet the auction registered no cleared trades throughout the window. The repeated nil outcomes point to a persistent mismatch between buy and sell price expectations in the segment.

8NLDC SCUC schedule for 9 June 2026 covers 44 generators; Darlipali leads at 115.9 paise/kWh, gas above 1,600
Grid-India's NLDC released its Security Constrained Unit Commitment schedule for 9 June 2026, published on a D-1 basis at 15:00 hrs on 8 June, covering 44 generators across thermal, gas and renewable categories. Among coal stations, NTPC's Darlipali in Odisha was the cheapest committed unit at an Economic Cost Rate of 115.9 paise/kWh, while Sipat STPS Stage 1 was scheduled at 131.6 paise/kWh for 910.15 MW. Gas units RGPPL-RLNG and Dadri_CRF cleared at 1,601 and 1,957 paise/kWh respectively, each with zero MW dispatch.

DEVIATION SETTLEMENT (DSM)

8PXIL Deviation Settlement Mechanism reports nil cleared volume for 8 June 2026
Power Exchange India Ltd's Deviation Settlement Mechanism Report for 8 June 2026 shows zero cleared buy and sell volumes and a zero price across all 96 fifteen-minute time blocks of the day. The blank settlement, generated on 9 June 2026, indicates that no DSM-based transactions were matched on PXIL for that delivery date. The nil result is consistent with the segment's intermittent activity, where matched deviation trades remain rare on the PXIL platform.
Details
SOLAR POWER

8UPERC clears India's first 5 MW concentrated solar power pilot in Unnao at fixed Rs. 4.73/kWh for 25 years
The Uttar Pradesh Electricity Regulatory Commission, in Petition No. 2335 of 2026 disposed on 8 June 2026, approved Cosmicwave Technology & Research Pvt. Ltd. to sign a PPA with UPPCL for a 5 MW Concentrated Solar Power project in Unnao at a fixed, non-escalating tariff of Rs. 4.73/kWh over 25 years. Built on an estimated Rs. 25 crore cost, the molten-salt thermal-storage plant will supply up to 40 MWh daily during eight evening peak hours. UPERC held the rate economical despite exceeding UPPCL's solar APPC of Rs. 3.62/kWh.

8India's renewable plants generate 1,063.12 MU on 7 June 2026, solar supplying 604.37 MU: CEA
CEA's Daily Renewable Generation Report for 7 June 2026 records 1,063.12 MU of renewable output, comprising 604.37 MU from solar, 432.92 MU from wind and 25.83 MU from other sources, lifting June 2026's cumulative RE generation to 7,163.89 MU. Inter-State Generating Stations contributed 410.02 MU of renewable energy that day, while NTPC's NP Kunta and Pavagada solar parks generated 12.75 MU and 10.44 MU respectively. The report underscores solar's dominant share of daytime renewable supply across the national grid.

WIND & HYBRID POWER

8WBERC clears CESC's 300 MW wind-solar hybrid PPA with Purvah Green Power at Rs. 3.75/kWh
The West Bengal Electricity Regulatory Commission, on 8 June 2026 in Case No. PPA-153/26-27, approved the PPA dated 16 April 2026 between Purvah Green Power Private Limited and CESC Limited for 300 MW of wind-solar hybrid power at Rs. 3.75/kWh for 25 years. The single largest award under CESC's 600 MW competitive tender carries a 2:1 wind-to-solar ratio, a 50% annual CUF and supply from 16 December 2027. WBERC found the rate reasonable against CESC's FY 2024-25 average power purchase cost of Rs. 5.17/kWh.

8CESC's 100 MW Adyant Power hybrid PPA gets WBERC nod at Rs. 3.75/kWh, sourced from Madhya Pradesh
In Case No. PPA-154/26-27 dated 8 June 2026, the West Bengal Electricity Regulatory Commission approved the 16 April 2026 PPA between Adyant Power Private Limited and CESC Limited for 100 MW of grid-connected wind-solar hybrid power at Rs. 3.75/kWh. Adyant Power is an SPV floated by Hexa Climate Solutions under the 21 August 2023 MoP competitive bidding guidelines, with both wind and solar delivered at the 220 kV Mandsaur ISTS substation in Madhya Pradesh. The 25-year project carries a 2:1 wind-solar ratio and a 50% annual CUF.

8Diyos Five Renewables wins WBERC approval for 100 MW CESC hybrid PPA at lowest tariff of Rs. 3.74/kWh
The West Bengal Electricity Regulatory Commission, on 8 June 2026 in Case No. PPA-155/26-27, cleared the 16 April 2026 PPA between Diyos Five Renewables Private Limited and CESC Limited for 100 MW of wind-solar hybrid power at Rs. 3.74/kWh — the most competitive rate discovered in CESC's 600 MW tender. Diyos Five, the SPV formed by Vismaya Renewables India Project, will deliver solar at the 220 kV Fatehgarh-IV station in Rajasthan and wind at the 220 kV Bijapur station in Karnataka. The 25-year hybrid carries a 2:1 wind-solar ratio.

8WBERC approves Sprng Green Energy 5's 100 MW hybrid PPA with CESC at Rs. 3.75/kWh
In Case No. PPA-156/26-27 dated 8 June 2026, the West Bengal Electricity Regulatory Commission approved the 16 April 2026 PPA between Sprng Green Energy 5 Private Limited and CESC Limited for 100 MW of grid-connected wind-solar hybrid power at Rs. 3.75/kWh. The SPV of Sprng Energy will supply over 25 years at a 2:1 wind-solar ratio and 50% annual CUF, delivering solar at the 400 kV Fatehgarh-III substation in Rajasthan and wind at the 220 kV Rajgarh substation in Madhya Pradesh from 16 December 2027.

ROOFTOP & DISTRIBUTED SOLAR (PM SURYA GHAR / KUSUM)

8UPERC adopts tariff and approves 21 PM-KUSUM C-2 solar PPAs totalling 49.6 MW at Rs. 2.20–2.99/unit
In Petition No. 2351 of 2026 dated 8 June 2026, the Uttar Pradesh Electricity Regulatory Commission approved 21 PPAs aggregating 49.6 MW between solar developers and UPPCL under Feeder Level Solarization of the PM-KUSUM Component C-2 scheme petitioned by UPNEDA and UPPCL. Discovered through competitive bidding for a cumulative 2,553.5 MW across 1,002 substations, the adopted tariffs ranged from Rs. 2.20 to Rs. 2.99 per unit, with developers including Excel Infrapower and Volttic Solar LLP. Cumulative approvals reached 363 PPAs for 1,114.9 MW.

8UPERC approves another 21 PM-KUSUM C-2 solar PPAs for 60.9 MW, lifting cumulative total to 1,164.5 MW
The Uttar Pradesh Electricity Regulatory Commission, in Petition No. 2352 of 2026 disposed on 8 June 2026, adopted the bid-discovered tariff and approved 21 PPAs totalling 60.9 MW between developers and UPPCL under the PM-KUSUM Component C-2 feeder-level solarization scheme filed by UPNEDA and UPPCL. The capacities, concentrated largely in Amroha and priced mostly at Rs. 2.99/unit within the Rs. 2.20–2.99 band, include Dhariwal Solar Energy's 8.3 MW and Gomti Solar Power's 6.73 MW. The order pushed cumulative approvals to 384 PPAs for 1,164.5 MW out of 2,553.5 MW tendered.

8CEEW pegs Rs. 5,000–14,400 crore annual O&M market in India's 10 GW residential rooftop solar segment
A June 2026 report by the Council on Energy, Environment and Water finds India's residential rooftop solar capacity has crossed 10 GW as of April 2026, with over 60% added since PM Surya Ghar: Muft Bijli Yojana launched in 2024 and adoption by more than 3 million households. The report warns the operations and maintenance ecosystem remains underdeveloped, estimating a total addressable market of Rs. 5,000–14,400 crore annually for bundled O&M services, and calls for a centralised national data platform with real-time monitoring and standardised protocols.

POLICY & INCENTIVES

8MNRE exempts 'Give It Up' PMSG:MBY rooftop-solar net-metering consumers from ALMM List-II until 31 March 2027
In an Office Memorandum dated 8 June 2026, the Ministry of New & Renewable Energy clarified that residential rooftop-solar consumers availing net metering under the 'Give It Up' option of the PM Surya Ghar: Muft Bijli Yojana are exempt from ALMM List-II for solar PV cells until the scheme ends on 31 March 2027. The exemption applies only to applications made through the PMSG National Portal, and such projects need not apply separately on the DCR Portal of the National Institute of Solar Energy.
Details
COMMISSION ORDERS (CERC/SERC)

8CERC disposes Welspun Narmada's 250 MW Bidar hybrid plea after developer withdraws connectivity post 77-day-late closure
By order dated 3 June 2026 in Petition No. 815/MP/2025, CERC disposed of Welspun Narmada Pvt. Ltd's plea on financial closure for its 250 MW wind-solar hybrid project at Bidar, Karnataka. The Commission held the issue no longer survives, as the company achieved closure on 13 November 2025 — 77 days late — and on 19 January 2026 sought withdrawal of connectivity. CTUIL was directed to process the withdrawal and inform the amount payable against bank guarantees of up to Rs. 5 crore within 10 days.

8GERC reserves order in GIPCL-GUVNL safeguard-duty change-in-law dispute under 2019 PPA
In a daily order dated 1 June 2026 in Petition No. 2003 of 2021, the Gujarat Electricity Regulatory Commission reserved its decision between Gujarat Industries Power Company Limited and Gujarat Urja Vikas Nigam Limited. GIPCL had sought compensation for a Change in Law event — the imposition of Safeguard Duty affecting project cost — under Article 9 of the PPA dated 26 August 2019. Both parties confirmed completing their submissions and sought no further hearing, leading the three-member bench chaired by Pankaj Joshi to reserve the matter.

OMBUDSMAN & CONSUMER GRIEVANCE

8TN Electricity Ombudsman dismisses Appeal No. 79 of 2025 against TNPDCL over voltage-fluctuation compensation
By order dated 8 June 2026, the Tamil Nadu Electricity Ombudsman dismissed Appeal Petition No. 79 of 2025 filed by a consumer of Ariyalur district against TNPDCL's Perambalur Electricity Distribution Circle. The appellant had sought compensation for voltage fluctuation and help registering a free agriculture bore service, escalating the matter after the Perambalur CGRF's order of 25 October 2025. The Ombudsman found the grievances already redressed, with no established loss; the appeal was disposed of with no costs.

REGULATORY PETITION & REVIEW

8CERC seeks fresh data from NTPC on emission-control and switchyard spend for 1,000 MW Vindhyachal Stage-III 2024-29 tariff
In Petition No. 1017/GT/2025 dated 8 June 2026, CERC directed NTPC Limited to file additional information on affidavit by 15 June 2026 for the 2024-29 tariff of the 1,000 MW Vindhyachal STPS Stage-III. The Commission questioned why NTPC did not file a separate supplementary-tariff application for the Emission Control System under the 2024 Tariff Regulations, and sought justification for added capital expenditure including 400 kV switchyard control, protection and SCADA replacement. Respondents must reply by 19 June 2026 and NTPC may file its rejoinder by 23 June 2026.

8CERC asks NHPC to reconcile Rs. 23.13 lakh HVAC add-cap claim in Chamera-II truing-up and 2024-29 tariff case
Through Petition No. 116/GT/2026 dated 8 June 2026, CERC asked NHPC's Chamera-II Power Station to submit additional information by 15 June 2026 covering both the 2019-24 truing-up and the 2024-29 tariff determination. The Commission flagged the Rs. 23.13 lakh additional capital expenditure claimed in 2022-23 for replacement of HVAC pipelines, ducts, AHUs and pumps, sought the decapitalisation value in Form 9B(i), and asked why NHPC claimed more than was allowed in the 6 January 2024 order in Petition No. 291/GT/2020.

8CERC directs NHPC to justify arbitration and add-cap claims for 132 MW Teesta Low Dam-III tariff
In Petition No. 140/GT/2026 dated 8 June 2026, CERC sought additional information from NHPC for the 132 MW Teesta Low Dam-III Power Station, spanning the 2019-24 truing-up and 2024-29 tariff periods, due by 15 June 2026. The Commission asked NHPC to cite a single regulation for each additional-capital-expenditure item, justify amounts exceeding those allowed under Order 320/GT/2018, and submit detailed computation — including principal and interest — for sums claimed under arbitration awards. Auditor-certified Forms 9C and 16 with a valid UDIN were also demanded.

8CERC flags Rs. 8,487.62 lakh liability mismatch and capital-spares claims in NTPC Vindhyachal Stage-III truing-up
Petition No. 982/GT/2025 dated 8 June 2026 sees CERC direct NTPC to furnish additional information by 15 June 2026 for the 2019-24 truing-up of the 1,000 MW Vindhyachal STPS Stage-III. The Commission noted that un-discharged liabilities of Rs. 8,487.62 lakh as on 31 March 2019 do not match the Rs. 8,488.33 lakh shown in Form-S, and demanded justification for high-value capital spares such as an LP rotor fully bladed at Rs. 2,314.27 lakh and a WDG-3A diesel locomotive at Rs. 2,152.50 lakh. Replies are due by 19 June 2026.

8GERC gives Shree Ganesh Enterprise two weeks to justify delay on 4.00 MW Bharuch solar project
By daily order dated 1 June 2026 in Petition No. 2479 of 2025, GERC directed Shree Ganesh Enterprise to file an affidavit within two weeks justifying its request for one more year to commission a 4.00 MW AC solar project at Dungri village, Bharuch district. GETCO and DGVCL noted that 23 months had passed since connectivity was granted and that the Solar Tariff Order of 31 August 2024 stays valid only to 31 March 2027. The petitioner said it had paid supervision charges to DGVCL on 2 April 2026.

8GERC allows Indian Wind Energy Association to amend parties in plea against GETCO's consumer-detail demand
In Petition No. 2652 of 2026, decided by daily order dated 1 June 2026, GERC permitted the Indian Wind Energy Association two weeks to amend its memo of parties to join distribution licensees in its challenge to GETCO. The association argues GETCO's insistence on furnishing consumer details at the connectivity-application stage is contrary to the Procedure for Grant of Connectivity dated 4 August 2025 and the Gujarat Renewable Energy Policy, 2025. GETCO must reply within two weeks of the amended memo, with the rejoinder due three weeks thereafter.

8GERC adjourns Sapana Sakar Buildcon's 101 MW solar plea, disposes urgent-listing application
By daily order dated 1 June 2026, GERC adjourned Petition No. 2654 of 2026 filed by Sapana Sakar Buildcon Private Limited seeking an extension of time to commission the evacuation line and connectivity for its 101 MW solar project, granting GETCO four weeks to file its reply. The petitioner had also moved IA No. 16 of 2026 for an ad-interim stay on encashment of its bank guarantee and IA No. 17 of 2026 for urgent listing; the Commission disposed of IA No. 17 as satisfied.

8UPERC grants B&G Renewable and UPRVUNL two weeks more on COD-extension plea, next hearing 2 July 2026
The Uttar Pradesh Electricity Regulatory Commission, in Petition No. 2214 of 2025 heard on 2 June 2026, allowed B&G Renewable Energy Private Limited — with Nirgajini Hydel Project and Salawa Hydel Project — and UPRVUNL two weeks each to file remaining submissions in the dispute seeking extension of the Commercial Operation Date under the PPA with UPPCL. Filed under Sections 86(1)(b) and (f) of the Electricity Act, 2003, the matter saw the Irrigation Department reply on 24 March 2026; UPERC listed the next hearing for 2 July 2026.

8UPERC adjourns B&G Renewable's change-in-law tariff-escalation claim against UPPCL to 2 July 2026
In Petition No. 2217 of 2025, heard on 2 June 2026, the Uttar Pradesh Electricity Regulatory Commission gave B&G Renewable Energy Private Limited and UPRVUNL two weeks to file fresh submissions seeking additional tariff for Change in Law events and quantification of escalation from increased capital cost. Filed jointly with Nirgajini Hydel Project and Salawa Hydel Project under Sections 86(1)(b) and (f) of the Electricity Act, 2003, the case saw the Irrigation Department reply on 24 March 2026. UPERC fixed 2 July 2026 for the next hearing.
Details
WORK ORDERS & SUPPLY CONTRACTS

8Waaree Renewable signs LoA for 300 MW/450 MWp ground-mount solar EPC contract from subsidiary Sunsational Power
Waaree Renewable Technologies Limited disclosed on 8 June 2026 under SEBI Regulation 30 that it has received and signed a Letter of Award from its wholly-owned subsidiary Sunsational Power to execute a 300 MW/450 MWp ground-mount solar project on an Engineering, Procurement and Construction basis, together with two years of operation and maintenance services. The intimation of the LoA signing was received at 10:47 a.m. IST on 8 June 2026, with details filed as Annexure A to the BSE and NSE.

CAPACITY COMMISSIONING & COD

8Samvardhana Motherson commissions first 15 MWp captive solar plant in Mahoba, UP, to generate 23.4 GWh a year
Samvardhana Motherson International Limited announced on 8 June 2026 the commissioning of its first ground-mounted captive solar project, a 15 MWp facility in Mahoba, Uttar Pradesh, through subsidiary Onega Solar Private Limited under Motherson New Energy Limited. Developed in partnership with ib vogt for land, approvals and EPC execution, the plant is expected to generate about 23.4 GWh of renewable electricity annually and cut roughly 17,000 MT of CO2 emissions a year. The power will supply multiple Motherson manufacturing plants across Uttar Pradesh.

8JSW Energy commissions Halol wind-blade plant with 450-blade annual capacity equivalent to 600 MW
JSW Energy Limited announced on 8 June 2026 the commissioning of its wind-blade manufacturing plant at Halol, Gujarat, with annual capacity of up to 450 blades — equivalent to supporting 600 MW of wind projects — producing 82-metre blades compatible with 4 MW turbines. The plant supports JSW Energy's vertical integration across 3.9 GW installed wind capacity, 6.5 GW of locked-in hybrid wind and 2.4 GW of plain-vanilla locked-in wind. A second plant at Chitradurga, Karnataka, is nearing commissioning, with total locked-in capacity of 32.1 GW.

EQUITY & STAKE ACQUISITION

8Adani Enterprises acquires 100% of Portus Ventures, folding it in as a wholly-owned subsidiary
Adani Enterprises Limited disclosed on 8 June 2026 under SEBI Regulation 30 that it had completed the acquisition of a 100% equity stake in Portus Ventures Private Limited, making it a wholly-owned subsidiary. The target operates primarily in the real-estate and hospitality space rather than core power generation, giving the transaction only tangential relevance to the electricity sector. The intimation was filed with the BSE and NSE, with the company classifying the deal as part of its diversification across infrastructure and allied businesses in the ordinary course.
Details
ANNUAL RESULTS

8DMR Engineering posts Rs. 1,056.06 lakh total income in FY26 as PAT slides to Rs. 95.63 lakh
DMR Engineering Limited reported total income of Rs. 1,056.06 lakh for FY26, down from Rs. 1,079.81 lakh a year earlier, as revenue from operations slipped to Rs. 1,025.80 lakh. PAT fell sharply to Rs. 95.63 lakh from Rs. 170.59 lakh, with the net profit ratio dropping to 9.32% from 16.30%, hit by reduced revenue from discontinued business debtors and higher finance costs of Rs. 37.61 lakh against Rs. 5.29 lakh. The firm's 17th AGM is set for 30 June 2026 via video conferencing.

CREDIT RATING & ANALYST REPORT

8Yash Highvoltage gets BUY initiation with Rs. 1,200 target, 71% upside seen on India's Rs. 9 trillion T&D buildout
Yash Highvoltage Limited, a Vadodara-based transformer-bushing maker trading at Rs. 703 on 8 June 2026, received a BUY initiation with a Rs. 1,200 target, implying a 71% price return. The thesis rests on India's National Electricity Plan-II target of adding 1,274 GVA of transformation capacity and 191,474 circuit km of lines by FY32, backed by over Rs. 9 trillion in T&D investment. Yash Highvoltage is also investing Rs. 1,530 million in a greenfield RIP-bushing plant, lifting annual capacity to 15,000 units.

8CareEdge reaffirms CARE A1+ on O2 Power's Rs. 3,375 crore short-term bank facilities
CareEdge Ratings on 8 June 2026 reaffirmed CARE A1+ on Rs. 3,375 crore short-term bank facilities and Rs. 300 crore commercial paper of O2 Power Private Limited, the EPC arm of JSW Energy Limited, while reaffirming CARE A+; Stable on reduced long-term facilities of Rs. 25 crore. The ratings draw on O2 Power's 843 MW order book as of May 2026, guarantees from JSW Neo, and JSW Energy's roughly 11 GW under-construction renewable pipeline. O2 Power's FY26 revenue fell to Rs. 1,431 crore from Rs. 1,909 crore.

8CareEdge reaffirms CARE A on Vena Energy Fatanpur's Rs. 458.64 crore facilities as 108 MW wind PLF rises to 18.4%
CareEdge Ratings reaffirmed CARE A; Stable on the reduced long-term bank facilities of Rs. 458.64 crore, down from Rs. 494.78 crore, of Vena Energy Fatanpur Power Private Limited on 8 June 2026, citing its 108 MW Madhya Pradesh wind project achieving a PLF of 18.4% in FY26 against 17.8% in FY25. Timely receipt of all 40 EMIs from off-taker MPPMCL under the Late Payment Surcharge scheme cut outstanding receivables to Rs. 6.56 crore by March 2026 from Rs. 86.14 crore in March 2023.
Details
8A long-duration overburden removal and coal extraction contract has been awarded for Rs 380.64 crore after attracting bids from 14 contractors, with several contenders eliminated during technical evaluation.
8The winning price came in significantly below the owner's estimate, highlighting aggressive competition in the mining services market. Details
8A transmission package awarded for Rs 170.87 crore combines a coastal grid-strengthening upgrade with a new substation development in an urban growth corridor.
8Despite attracting only one bid, the project delivered a pricing outcome that remained remarkably close to the owner's estimate, contrasting with trends seen in comparable packages. Details
8A transmission strengthening package valued at Rs 158.57 crore focuses on enhancing power-transfer capability through reconductoring of existing high-voltage corridors rather than building new infrastructure.
8The project carries significant execution dependencies, including critical shutdown requirements that lie outside the contractor's direct control. Details
8The largest substation package in a recent urban transmission procurement cycle has been awarded for Rs 238.64 crore, centred on gas-insulated switchgear technology and a demanding execution schedule.
8The combination of specialised technical requirements and stringent qualification expectations resulted in a single-bid outcome. Details
8A high-specification transmission package involving a grid substation and underground cable infrastructure has been awarded at a value of Rs 94.30 crore following a single-bid outcome.
8During the pre-bid stage, a request to ease a qualification requirement was declined, leaving the competitive landscape unchanged. Details
8A major transmission package combining a high-voltage digital switching station and associated transmission infrastructure has been awarded after a series of pre-bid technical revisions.
8While several protection and control requirements were relaxed during the tender stage, a key qualification criterion remained unchanged. Details
 For reference purposes the website carries here the following tenders:
 8Tender for civil works Details
 8Tender for increasing capacity of 33/11 kV sub-stations Details
 8Tender for construction of new 33/11 kV (2x5 MVA) sub-station Details
 8Tender for supply of 33kV control panel for single transformers Details
 8Tender for supply of 11/.4 kV 100 KVA distribution transformers Details
 8Tender for supply of 11/0.25 kV single phase, 10 KVA distribution transformers Details
 8Tender for work of line construction for completion energization of works Details
 8Tender for testing of different voltage level of circuit breakers installed Details
 8Tender for civil works related Details
 8Tender for construction work of rain water harvesting and sewar line Details
 8Tender for work of re-routing of damaged pipelines Details
 8Tender for annual civil M and R work Details
 8Tender for construction of 33 kV substation Details
 8Tender for ARC for Mtc. of hot water distribution system Details
 8Tender for up-gradation main turbine Details
 8Tender for annual work contract for hiring of 04 nos. water mist fog machines for silos Details
 8Tender for supply and fixing of new air cell of the main conservator oil tank, bucholz relay, MOG and breather of generator transformer Details
 8Tender for procurement of 300 NB specially designed and modified expansion joint and rubber gasket for wet ash disposal line Details
 8Tender for work contract for complete operation and cleaning work of sewage treatment plants Details
 8Tender for insurance of stock material Details
 8Tender for carting of 4000 Nos. of 10 Mt X 270 KG PSC poles Details
 8Tender for supply of chemicals for cooling water treatment Details
 8Tender for general civil work like rolling shutter overhauling, UPVC line, servicing of aluminium door, false celling Details
 8Tender for work of erection and commissioning of vortex finder in boiler Details
 8Tender for work of condenser tubes cleaning by high pressure water jetting with rotary nozzle method & bullet shot method Details
 8Tender for construction and renovation of control room, cable trench, chain-link, mesh fencing and misc. civil work Details
 8Tender for manufacture and supply of P A elbow assy guide pipe regulating rod Details
 8Tender for thermovision scanning of CLR polymer insulators Details
 8Tender for supplying and laying of gravel with rain water harvesting system Details
 8Tender for rehabilitation of C wing executive Details
 8Design, engineering, manufacturing, supply, erection, testing & commissioning of 125 MVAR STATCOM Details
 8Design, fabrication, supply, installation, testing and commissioning of total 17 KW grid connected solar PV power plant Details
 8Design, fabrication, supply, installation, testing and commissioning of total 47 KW grid connected solar PV power plant Details
 8Design, fabrication, supply, installation, testing and commissioning of total 156 KW grid connected solar PV power plant Details
 8Tender for Re-babbitting of turbine guide bearing Details
 8Tender for construction of new borewell and pump house Details
 8Tender for estimate for stringing of 11kV MVCC on the newly constructed 11kV line Details
 8Tender for construction of 11kV spur line with MVCC installation of 11/.4 kV 500 KVA pad mounted substation Details
 8Tender for supply installation and commissioning of 27 No. 1.5 ton non inverter type split air conditioners Details
 8Tender for renovation and improvement work Details
 8Tender for annual work contract for picking of stones / shales and other foreign material from coal Details
 8Tender for work contract for dismantling from old exchange room and shifting to new exchange Details
 8Tender for procurement of fasteners and studs for auxiliaries Details
 8Tender for AMC of 22kV HT line Details
 8Tender for work of bottom ash hopper restrengthening and repairing in boilers Details
 8Tender for supply, erection, testing and commissioning of 220 V DC, 63 AH, KPH 63P, Ni-Cd type battery set Details
 8Tender for construction of transformer plinth Details
 8Tender for supply of various type liftting tools tackles for boiler Details
 8Tender for interlinking HT line using covered conductor Details
 8Tender for constructing additional feeder using HT ABC Details
 8Tender for construction using ABC 120sq Details
 8Tender for constructing HT ABC line Details
 8Tender for installing new 200MVA, 220/110kV 3 ph Trfr station in existing spare bay available Details
 8Tender for new 11 kV line from 110 kV substation Details
 8Tender for construction using ABC 120sqmm Details
 8Tender for replacing of wire ropes and overhauling of hoist mechanisms Details
 8Tender for capital work of line maintenance Details
 8Tender for deployment of workers for various jobs Details
 8Tender for construction of RCC drains and misc. works along the coal evacuation Details
 8Tender for maintenance of 400 kV D/C line Details
 8Tender for construction of switch house Details
 8Tender for const. of new 33 kV s/stn Details
 8Tender for construction of new SHB and allied civil work at 33 kV sub stn Jyotisar. Details
 8Tender for construction of new SHB and allied civil work at 33 kV sub stn Details
 8Tender for const. of new 33 kV s/stn and various civil works Details
 8Tender for procurement of 11 kV VCB panels of assorted types Details
 8Tender for repair of 132kV substation Details
 8Tender for repair of damaged UC fencing and raising height Details
 8Tender for construction of PCC flooring with gravel spreading and drainage system in the switch yard Details
 8Tender for erection of 11kV line Details
 8Tender for procurement of duplex filter for main turbine Details
 8Tender for purchase of 420 kV solid core post insulator for isolator Details
 8Tender for supply of 35 Hp submersible pump set with control panel for mass dewatering of main sump tank Details
 8Tender for procurement of spares for NASH make vacuum pump Details
 8Tender for supply of spares for the capital overhauling work of 195 MW generator Details
 8Tender for rate contract for repairing of damaged defective distribution transformers Details
 8Tender for procurement of 132kV, 1250A isolator Details
 8Tender for procurement of 132kV isolator Details
 8Tender for engagement of 05 nos. non-listed MOS covered workers Details
 8Tender for stone removal coal cleaning and breaking from gratings Details
 8Tender for procurement of different MS pipes Details
 8Tender for refractory work by gunning machine inside bottom ash hopper during Details
 8Tender for comprehensive cleaning along road flanks Details
 8Tender for work for increasing capacity and installation of new DTR under 33/11 kV S/s Details
 8Tender for construction of retaining wall and other misc. civil worksat 33/11 kV S/S Details
 8Tender for work of supply, erection, testing commissioning of an additional 1X 50MVA 220/33kV power transformer along Details
 8Tender for work of supply, erection, testing commissioning of an additional 1X 25MVA 132/33kV power transformer along Details
 8Tender for supply of fire system pumps Details
 8Tender for Bi-annual rate contract for shifting/modification work of existing various 66/132/220 kV class transmission lines Details
 8Tender for supply of electrical hand gloves for max working voltage Details
 8Tender for supply and application of fire retardant cable insulating coating Details
 8Tender for construction of control room foundation, cable trench Details
 8Tender for Bi-annual rate contract for providing pile foundation to towers Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8Too Much Sun, Too Little Land: India’s Solar Dilemma Details
 8India's Solar Industry Faces Transformation with Domestic Mandate Details
 8Inox Clean’s 6 GW move reshapes renewable ambitions Details
 8MNRE forms panel to review ALMM-II exemption requests for solar projects Details
 8REC Ltd – Financing Infrastructure, Empowering India Details
 8Waaree Renewable bags LoA for 300 MW ground-mounted solar EPC order Details
 8GPS Renewables raises Rs 635 Crore in Series C round Details
 8GE Vernova Bags Advanced Turbine Production Project in India Details
 8FICCI Seeks Private Access to 700MW Nuclear Tech for Capacity Boost Details
 8JSW Energy Commissions Wind Blade Manufacturing Plant In Gujarat Details
 8GACL and CleanMax Partner on 160 MW Hybrid Renewable Energy Project Details
 8Driving India’s Energy Transition: NLC India’s Vision for Sustainable Growth and Energy Security Details
 8Odisha Governor inaugurates NBCC solar plant Details
 8A foundation built for scale: Dismantling carbon dependency in India’s power sector Details
 8West Asia conflict drives Indian power plants to spot gas market, it sees 336% surge in purchases Details
 8Household Construction, Corporate Credit, Power, And Steel — The Investment Cycle India's Narrative Missed Details
 8India's Coal Sector: A Decade of Transformation Under Modi's Leadership Details
 8Why storage is the missing layer in India’s clean energy story Details
 8Rise of AI: Unlocking new capabilities in grid management and asset performance Details
 8Centre has coal reserves for 80 days of power generation: Kishan Reddy Details
 8Why Hitachi Energy India Share Price is Falling Details
 8Why energy transmission is the next frontier for India Details
 8India’s Leading Power Generation Company Commissions Wind Blade Manufacturing Plant In Gujarat Details
 8Transformer Stocks: How Did Hitachi Energy and 4 Other Stocks Perform in FY26 Details
 8Why Adani is onboarding L&T for nuclear power projects Details

 
You can also click on Newsclips for more Details
8Regulatory filings show three CSPGCL power stations recorded a combined negative Fuel Cost Adjustment of Rs.16.13 crore in March 2026 - money that technically belongs to electricity consumers. Details
8Regulatory data shows Delhi's GTPS pays Rs.74.58/SCM for gas with nearly the same calorific value as fuel costing just Rs.33.61/SCM at Pragati PS-III - raising serious procurement efficiency questions. Details
8Government documents reveal Delhi's three major power stations paid over Rs.354 crore for gas in May alone, as landed costs surged up to 63% since February 2026. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Fertilizers
8LPG
8Ammonia
8Coal & Coke
8All tankers
8Bulk and Dry cargo

Click on Reports for more. Details
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
8Protection-system procurement advances through a restricted bidding route at a key transmission substation
A seemingly routine protection-panel procurement carries procedural signals that extend beyond equipment supply. The structure reveals how urgency, qualification control and domestic sourcing priorities are being balanced within transmission procurement.

8Rs 259.60 crore hydro package raises a deeper competition test for EPC bidders
The package has moved through a long extension cycle and several technical revisions. The headline value is only the visible layer of a tender that reshapes how EPC bidders can use manufacturer strength. The real story lies in how competition has been widened without removing performance exposure.

8Rs 2 crore bid security raises the entry cost for an 11 MW solar project
The EMD is material for an 11 MW AC project and creates a meaningful entry threshold for participants. By requiring substantial upfront commitment, the tender structure helps filter speculative bidding while testing bidder confidence in project execution. The provision offers insight into how procurement authorities are balancing competition with seriousness of participation.

8Rs 107 crore transmission package puts industrial power-readiness plans under a tighter filter
The latest grid infrastructure package looks like a routine turnkey tender, but the control points run deeper. Qualification requirements, monopole sourcing conditions and price-bid discipline are being used to narrow execution risk. The stronger signal may lie in how the procurement has been restructured in its latest call, offering clues about evolving utility priorities in transmission project delivery.

8A reliability-focused O&M package worth Rs 255 crore puts two critical plant systems under one contractor basket
The package pulls two critical plant systems into a single O&M framework. The value is significant, but the sharper issue is how reliability risk is being transferred through the contract structure. The final bid response will reveal whether contractors prioritize pricing discipline or pursue scale through long-duration operational responsibility.

8A technically demanding replacement package backed by a Rs 2.21 crore bid security creates a precision test for bidders
The package is built around a technically unforgiving replacement requirement. The scope extends beyond equipment supply into dismantling, fitment and commissioning responsibilities within an operating pumped-storage environment. The decisive issue is how bidders price execution uncertainty while managing performance risk inside an existing generating unit.

8A conductor procurement tender puts supplier discipline under sharper scrutiny as value crosses Rs 100 crore
The latest conductor procurement looks routine only at the surface. The deeper structure blends raw-material price protection with stricter vendor-performance consequences. The result could reshape how suppliers approach future distribution utility procurements and influence bidding strategies across large-volume conductor tenders.

8Hydrogen compatibility changes the EPC risk equation as a power project moves toward execution
The tender places future-fuel readiness inside the main equipment obligation rather than treating it as a later retrofit. That changes how bidders must think about engine selection, emissions compliance and lifecycle reliability. The commercial effect is likely to become visible only when serious OEM-backed bids are tested in a competitive environment.

8A 4,800 MWh peak-power auction raises the stakes for storage-backed renewable developers
The latest peak-power procurement is less about renewable generation and more about who can guarantee delivery when the grid needs it most. Hidden inside the qualification and connectivity framework are signals that could reshape bidder strategy long before tariffs are discovered. The real competitive battle may emerge far away from solar parks and much closer to transmission rights and storage economics.

8A new ownership vehicle enters the frame as a PSP-linked transmission bid moves toward tariff discovery
A one-line amendment has quietly altered the legal architecture behind an upcoming pumped-storage-linked transmission corridor. The change arrives at the precise point where bidders move from qualification to tariff discovery. What appears administrative on paper could reshape how investors assess ownership structures, liabilities and execution exposure.

8Transmission bid takes a quiet corporate turn as the project SPV formally enters the frame

A seemingly routine amendment has altered one of the most important legal foundations of the transmission project. The change arrives as a new renewable evacuation corridor moves toward implementation with significant long-term infrastructure implications. What looks administrative on paper may matter far more during acquisition, financing and project transfer stages.

8Bid takes a decisive corporate step as a key project vehicle formally emerges
A seemingly administrative amendment quietly alters the legal architecture of a high-profile transmission project. Behind the paperwork sits a grid investment designed around one of India's fastest-growing power demand segments. The implications extend well beyond a simple name change, particularly for project acquisition, financing and execution pathways.

8A transformer procurement programme worth Rs 445.25 crore sharpens efficiency priorities across the distribution network
A major transformer procurement programme is revealing how utilities are redefining equipment quality standards. Technical efficiency requirements appear to be shaping competition as much as commercial pricing. The broader implications extend beyond manufacturing and into long-term network performance.

8Large domestic coal procurement reveals deeper fuel-security priorities as a Rs 2 crore entry barrier shapes competition
The procurement is revealing more than just fuel demand. Supply-chain visibility and logistics accountability appear to be playing a bigger role than conventional commodity pricing. The deeper implications emerge when the sourcing controls are examined alongside the delivery framework, highlighting how fuel-security objectives are influencing bidder participation.

8A major coal procurement highlights supply-assurance priorities as a Rs 2 crore entry threshold shapes bidder participation
The procurement is revealing how fuel security is influencing tender design. Source visibility and delivery accountability appear to carry unusual weight within the bidding framework. The significance becomes clearer when the logistics obligations are examined alongside the commercial structure, offering insight into evolving approaches to fuel procurement risk management.

Details
COAL PRODUCTION & OFFTAKE

827 power plants hit critical coal stock as crisis deepens into peak summer
India's critical power-plant count rose from 25 to 27 within 24 hours, signalling a rapidly worsening coal supply position, per the CEA daily coal stock report for 5 June 2026. Total coal stock slipped to 47,920 thousand tonnes, barely 63% of normative levels. Telangana's plants hovered dangerously below 25% stock while Andhra Pradesh's generators continued battling shortfalls, pressuring Coal India subsidiaries MCL and SCCL to ramp up supplies.

8Coal still king but stumbling as year-to-date generation falls 5,633 MU behind target
Coal continues to shoulder over 83% of India's thermal power burden, generating 3,915 MU on 4 June 2026, slightly above its daily target, per the CEA fuel-wise generation report. But cumulative generation from 1 April stood at 2,98,808 MU against a programme of 3,04,442 MU — a shortfall of 5,633 MU. Hydro underperformance was the biggest drag at 1,551 MU behind schedule, while nuclear quietly overperformed.

8BCCL activates interim diesel price relief for HEMM and coal transport contractors
Bharat Coking Coal Limited disclosed that its Committee of Functional Directors, in meetings on 3 and 4 June 2026, approved adoption of Coal India Limited's interim relief to ease financial stress on contractors from abnormal bulk diesel price increases. Diesel price variation payable to eligible heavy earth-moving machinery and coal transportation contractors will be calculated with reference to prevailing bulk diesel rates, with the financial impact dependent on actual eligible claims.

E-AUCTION & PRICING

8Coal India puts record 35 MT of high-GCV coal under linkage auction on 12 June
Coal India Limited announced on 5 June 2026 that it is placing an all-time high of 35 million tonnes of high-GCV coal under a linkage auction on 12 June 2026, targeting the sponge iron sector to cut import dependence. CIL also offered 13.75 MT to the steel coking sub-sector under the ongoing Tranche-X linkage auctions begun 3 June, and permitted coking units to sell coal middlings in the open market.
Details
PEAK DEMAND & GRID FREQUENCY

8All-India peak demand hits 225,129 MW on 7 June with zero shortage, NLDC reports
GRID-INDIA's NLDC logged an all-India evening peak of 225,129 MW at 20:00 hrs on 7 June 2026, met with nil shortage across all five regions — Northern 76,223 MW, Western 68,121 MW, Southern 49,042 MW, Eastern 28,155 MW and North-Eastern 3,588 MW. Maximum demand during the day touched 236,686 MW at 22:51 hrs on SCADA, while energy met was 5,316 MU against a shortage of just 0.03 MU. Solar supplied 604 MU, wind 434 MU and hydro 417 MU.

8Northern Region peaks at 76,223 MW on 7 June as Uttar Pradesh tops states at 30,179 MW
NRLDC's daily operation report for 7 June 2026 shows the Northern Region meeting an evening peak of 76,223 MW at 20:00 hrs and an off-peak of 70,168 MW, with day energy of 1,712 MU and a shortage of only 0.03 MU. Uttar Pradesh led demand with a 30,179 MW evening peak, ahead of Rajasthan (12,763 MW), Punjab (10,883 MW) and Haryana (9,691 MW). Regional generation totalled 851.83 MU, of which thermal supplied 604.36 MU.

8Western Region meets 68,121 MW evening peak on 7 June with no shortage, WRLDC reports
WRLDC's daily operation report for 7 June 2026 records a Western Region evening-peak demand of 68,121 MW at 20:00 hrs at a frequency of 50.14 Hz and an off-peak of 66,735 MW, both met with zero shortage. Day energy met totalled 1,668.7 MU with nil energy shortage across the region, underlining comfortable supply conditions in the country's largest industrial power region through the day.

8Southern Region demand tops 49,042 MW on 7 June as Tamil Nadu leads at 16,554 MW
SRLDC's power supply position report for 7 June 2026 shows the Southern Region meeting a 49,042 MW evening peak at 20:00 hrs and a 48,822 MW off-peak, both with zero shortage, and day energy of 1,205.27 MU. Tamil Nadu posted the highest state evening peak at 16,554 MW, followed by Andhra Pradesh (10,332 MW), Karnataka (8,964 MW) and Telangana (8,690 MW). Andhra Pradesh recorded the day's maximum state demand of 13,604 MW at 14:56 hrs.

8Eastern Region demand reaches 28,155 MW on 7 June as Bihar tops states at 8,198 MW
ERLDC's daily operation report for 7 June 2026 shows the Eastern Region meeting a 28,155 MW evening peak at 20:00 hrs and a 27,896 MW off-peak, both with zero shortage and day energy of 661.05 MU. Bihar led state demand at an 8,198 MW evening peak, ahead of DVC (2,977 MW) and Jharkhand (2,387 MW). West Bengal generated the most within the region at 141.66 MU, with regional generation totalling 359.8 MU.

8North-Eastern Region peaks at 3,588 MW on 7 June as Assam leads at 2,315 MW
NERLDC's daily operation report for 7 June 2026 shows the North-Eastern Region meeting a 3,588 MW evening peak at 20:00 hrs and a 2,829 MW off-peak, both with zero shortage and day energy of 69.45 MU. Assam dominated demand with a 2,315 MW evening peak, far ahead of Manipur (203 MW) and Arunachal Pradesh (181 MW). Regional generation, almost entirely hydro and gas-based, totalled 12.79 MU against a scheduled drawal of 61.99 MU.

8All-India grid averages 49.998 Hz on 7 June but stays outside IEGC band for six hours
GRID-INDIA's NLDC frequency profile for 7 June 2026 records an average grid frequency of 49.998 Hz with a standard deviation of 0.0724 Hz and a frequency deviation index of 25.0. Instantaneous frequency swung between a high of 50.273 Hz at 08:57:40 and a low of 49.695 Hz at 07:48:00, with 169 excursions above 50.03 Hz and 156 below 49.97 Hz. The grid spent about six hours outside the 49.9 to 50.05 Hz IEGC band, based on 10-second samples from Agra.

8North-Eastern grid spends 21% of 6 June outside the IEGC band, NERLDC index shows
NERLDC's daily frequency profile for 6 June 2026 shows the region's frequency outside the IEGC band for 21.47% of the time, equal to about 5.15 hours, with frequency above 50.05 Hz for 18.82% of the day and below 49.9 Hz for 2.65%. Frequency swung between a maximum of 50.12 Hz and a minimum of 49.89 Hz, averaging 50.01 Hz over the day across the North-Eastern Regional Grid.

8Solar meets 26% of peak as VRE contribution touches 84,771 MW on 4 June: NLDC REMC
The NLDC Renewable Energy Management Centre report for 4 June 2026 shows variable renewable energy of 84,771 MW, about 34.23%, at an all-India maximum demand of 247,658 MW at 14:33 hrs, with solar at 64,859 MW (26.19%) and wind at 19,912 MW (8.04%). Peak solar generation reached 76,414 MW at 11:49 hrs and combined renewable generation a high of 93,638 MW at 11:53 hrs. Maximum VRE penetration relative to demand touched 39.58% during the day.

8Krishnapattanam leads Southern generation at 1,543 MW on 7 June, SRLDC station report shows
SRLDC's station-wise generation report for 7 June 2026 details output across Southern utilities, with the Krishnapattanam plant generating 37.03 MU (1,543 MW gross) and the Jindal Simhapuri unit 8.79 MU (366 MW). Greenko's pumped-storage units delivered about 12.63 MU (526 MW) during the day. Andhra Pradesh's control area met a demand of 10,332 MW against consumption of 265.86 MU.

8Real-time power crashes to Rs. 114.73 per MWh on 5 June as solar surplus floods the grid
The IEX Real-Time Market hourly snapshot for 5 to 7 June 2026 recorded the week's lowest figure, a market clearing price of just Rs. 114.73 per MWh at Hour 7 on 5 June, as solar flooded the grid faster than demand could absorb it. Sell bids of 22,610 MWh overwhelmed buyers at 7,740 MWh, creating near-total market saturation. The data is the clearest evidence yet of solar reshaping power-market price formation in India.

8Day-ahead prices swing from Rs. 499 at noon to Rs. 10,000 per MWh at midnight on 7 June
The IEX Day-Ahead Market hourly snapshot for 5 to 7 June 2026 captured a sharp solar-driven price chasm. On 7 June, the market clearing price crashed to Rs. 499 per MWh between noon and 1 PM as solar flooded the grid, while the same market demanded Rs. 10,000 per MWh after sunset. Sell bids exceeded 45,000 MWh at peak solar hours, nearly thirty times the night-time supply, reshaping assumptions about power procurement.

8Himachal hydro clears at Rs. 20,000 per MWh on HPDAM, double the day-ahead ceiling
The Himachal Pradesh Day-Ahead Market 15-minute data for 5 to 7 June 2026 shows hydro power clearing at a consistent Rs. 20,000 per MWh, double the regular day-ahead ceiling and forty times the midday solar-suppressed rate of around Rs. 500. Clearing volumes above 500 MW in the early hours signal strong demand for dispatchable, round-the-clock hydro power, highlighting the premium that firm renewable power commands in an increasingly solar-heavy grid.

8ERLDC holds day-ahead forecast error to 5.02% and intraday to 1.39% for 6 June
ERLDC's forecasting-error report for 6 June 2026 records a day-ahead demand MAPE of 5.02% with an RMSE of 5.86%, and a much tighter intraday MAPE of 1.39% with an RMSE of 1.67%. Block-wise data show actual demand tracking around 30,000 to 33,000 MW through the early-morning hours, with forecast deviations of a few hundred megawatts per 15-minute block across the Eastern Region.

8Odisha's seven hydro stations generate 698 MW on 5 June as Mukhiguda carries the load
OHPC's daily reservoir generation report for 5 June 2026 shows Odisha's seven hydropower stations collectively producing 698 MW, with UIHEP Mukhiguda contributing the highest at 266.5 MW across its available units. Balimela's output was hampered, with units 5 and 6 under renovation and modernisation and unit 4 shut on a guide-bearing oil leakage, while Burla's unit 5 was on annual maintenance. The report highlights the operational stress on Odisha's ageing hydro fleet amid rising water demand.

8GRID-INDIA keeps day-ahead demand forecast error at 2.8% for 5 June, NLDC bulletin shows
Per Article 31.2(i) of the Indian Electricity Grid Code 2023, GRID-INDIA's NLDC reported a day-ahead demand-met forecasting error of 2.8% and a real-time error of 1.5% for 5 June 2026. Energy-consumption forecast errors were tighter, at 2.0% day-ahead and 0.4% in real time. All figures are computed at the NLDC level for the all-India system, underscoring the accuracy of national load forecasting that underpins scheduling and reserve planning.

OCC MEETINGS & OUTAGE PLANNING

8Delhi Transco convenes second OCC meeting of FY 2026-27 with over 12 power agencies
Delhi Transco Limited convened its second Operation Coordination Committee meeting for FY 2026-27, bringing together more than 12 agencies including TPDDL, BRPL, BYPL, NDMC, IPGCL, DMRC and BBMB. The 21 May meeting at the 220 kV Park Street substation focused on planned June shutdowns and transformer upgrade decisions vital for Delhi's grid reliability heading into the peak summer demand season.

8Delhi OCC clears June shutdowns and 66 kV transformer upgrade at Shalimar Bagh substation
The minutes of Delhi Transco's second OCC meeting confirm approval for planned grid shutdowns in June 2026 and a key upgrade at the 220 kV Shalimar Bagh substation, replacing 33 kV power transformers with 66 kV units for N-1 compliance. The BHEL-supplied transformers are expected to strengthen Delhi's backbone grid and reduce outage risk during peak demand periods across north and west Delhi.

8WRLDC logs 8,072 MW of generation on planned outage and 4,799 MW forced on 7 June
WRLDC's generation outage report for 7 June 2026 shows 8,072.1 MW of capacity under planned outage — 4,395.6 MW central sector and 3,676.5 MW state sector — alongside 4,799 MW of forced outages, comprising 1,903 MW central and 2,896 MW state. A further 5,162.1 MW was under reserve shutdown, while hydro stations accounted for 440 MW of planned and 148 MW of forced outages across the Western Region.

8NTPC's 800 MW Darlipali unit trips as Eastern Region carries 3,820 MW of forced outages
The Eastern Region generation outage report for 7 June 2026 records 3,820 MW of forced outages — 2,510 MW central and 1,310 MW state sector — led by NTPC's 800 MW Darlipali unit-2, tripped on a boiler-tube leak on 6 June. NHPC's three 170 MW Teesta HPS units and a 200 MW Teesta Stage-III unit remain out since the October 2023 Lhonak Lake cloudburst, while planned state-sector outages total 163.65 MW.

8SRLDC reports 1,748 MW of central units on planned outage, including NPCIL's Kaiga-1
SRLDC's generating unit outage report for 7 June 2026 totals 1,748 MW of central-sector capacity under planned outage, including NPCIL's Kaiga Stage-1 unit-1 (220 MW), the Madras Atomic Power Station unit-1 (220 MW) and four Lanco LKPPL units stranded under NCLT since 2016. State-sector outages add Karnataka's Sharavathi unit-5 (103.5 MW) and three 150 MW Srisailam units under annual overhaul by TGGENCO.

8SRLDC logs 14 reservoirs and knocks off Rayalaseema's 600 MW unit on 7 June
SRLDC's reservoir report for 7 June 2026 lists levels at 14 southern reservoirs, including Idukki at 706.34 with storage energy of 464.71, Mettur at 749.82 and Srisailam at 249.54, with Linganamakki holding the highest energy at 549.52. The report flags thermal-unit outages including Rayalaseema TPP unit-6 (600 MW), Jindal unit-6 (300 MW), Vijayawada TPS units 2 and 6 (210 MW each) and OPG PGPL unit-4 (180 MW).

8WRLDC flags Western lines, including a Wardha-Warora 400 kV link out since 2018
WRLDC's line outage report for 7 June 2026 details transmission elements across the Western Region under planned, forced, emergency and voltage-regulation outage, spanning 220 kV, 400 kV and 765 kV levels. Among long-pending planned outages is the 400 kV Wardha-Warora-PG-2 line owned by POWERGRID, out of service since 4 May 2018 in connection with LILO work at the Warora pooling station.

8Three 400 kV lines trip in the South on 7 June; Suryapet-KV Kota out on phase fault
SRLDC's transmission forced outage report for 7 June 2026 records three 400 kV line outages. The Alamathy-NCTPS Stage-II-1 line of TANTRANSCO was restored at 10:38 after a fault about 1 km from the Almathy end, the NCTPS Stage-II-Vallur-1 line tripped briefly between 12:28 and 14:13, and the Suryapet-KV Kota-1 line of APTRANSCO tripped on an RYB-phase fault at 00:25 on 8 June.

8POWERGRID lines dominate NRLDC's 5-7 June planned shutdown of 120-plus elements
NRLDC's planned shutdown report for 5 to 7 June 2026 lists well over 120 transmission elements — bays, bus reactors and lines at 220 kV, 400 kV and 765 kV — taken out for maintenance, the bulk POWERGRID-owned. Scheduled outages include the 765 kV Khetri-Narela circuits 1 and 2, a 330 MVAR bus reactor at 765 kV Narela, and a 253 MVA generator transformer at the Bawana CCGTB station.

8PVVNL Meerut schedules four-hour June 6 shutdown at Swarnajayanti substation
Paschimanchal Vidyut Vitran Nigam Limited, Meerut, published a planned shutdown schedule dated 5 June 2026 for maintenance on 6 June across the Bulandshahar, Ghaziabad and Gajraula circles. A four-hour shutdown at the Swarnajayanti substation in Ghaziabad ran from 11:00 to 15:00 hrs for new transformer, ABC tiles and LT line work, with a one to three hour outage at Siddharth Vihar from 9:00 to 13:30 hrs.

8PVVNL schedules four-hour June 7 shutdown across Bulandshahar's UPSIDCE industrial zone
PVVNL Meerut's planned shutdown bulletin dated 6 June 2026 details industrial-zone outages on 7 June in the Bulandshahar and Hapur circles. At Sikandrabad, multiple Jokhabad feeders and the Basant Vihar feeder were shut from 10:00 to 13:00 hrs for line work, while in Hapur, industrial feeders serving Sukh Steel, UPSIDCE Phase 2, Paramount, KJS Concrete and Coca Cola were shut from 6:00 to 10:00 hrs for 33 kV CT and busbar installation.

8Over 24,000 MW sits under maintenance on a single day, CEA report shows
On 4 June 2026, forced and planned maintenance across India's coal, lignite and nuclear fleet took out over 24,000 MW of capacity, according to the CEA daily maintenance report. Water-wall tube leakages, superheater failures and boiler problems dominated the outage list from Korba to Yadadri. The Southern Region alone recorded 6,162 MW under minor forced maintenance, raising questions about the health of India's ageing thermal generation assets.

8India's biggest units falter as 11,585 MW of 500 MW-plus capacity goes offline
The CEA's maintenance report for units rated 500 MW and above shows that on 4 June 2026 a combined 11,585 MW of large-capacity units was under forced minor maintenance, with an additional 1,960 MW in planned shutdown and 2,000 MW in major forced outage. Yermarus TPP lost both its 800 MW units simultaneously, while Ghatampur and Korba-West added to the strain on India's largest thermal units.

REGIONAL ENERGY ACCOUNT

8India loses 3.53% of transmitted power in the week of 8-14 June, NLDC data shows
GRID-INDIA's NLDC reported a 3.53% all-India transmission loss for the week of 8 to 14 June 2026. Of 18,493 MU injected into the inter-state grid, over 625 MU was lost in transit. The CERC 2020 regulations mandate weekly calculation of these losses using real-time special energy meter data, keeping the spotlight on grid modernisation and accurate energy accounting across the national network.

8ER-NR interface faces Rs. 297.98 crore deviation charge in week of 18-24 May: NRPC
The Northern Regional Power Committee's deviation settlement account for Week 8 of FY 2026-27 (18 to 24 May 2026) places ER-NR at the top of the payable column at Rs. 29,797.71 lakh, followed by Uttar Pradesh at Rs. 3,112.05 lakh and Jammu & Kashmir at Rs. 2,114.86 lakh. On the receivable side, WR-NR leads at Rs. 38,143.38 lakh. The payment due date is 14 June 2026, with a late-payment surcharge of 0.04% per day.

8Uttar Pradesh tops Northern Region reactive energy receivables at Rs. 33.39 lakh
The Northern Regional Power Committee's reactive energy charges statement for 18 to 24 May 2026, calculated under the CERC Grid Code 2023, makes Uttar Pradesh the largest net beneficiary at Rs. 33.39 lakh receivable, with Haryana at Rs. 25.78 lakh and Rajasthan at Rs. 15.04 lakh. Among payables, Himachal Pradesh leads at Rs. 6.81 lakh and Delhi at Rs. 6.46 lakh. Payments are due into the NR pool account by 14 June 2026.

8NRPC issues Rs. 655 crore ancillary services bill for 18-24 May, payment due 11 June
The CEA's Northern Regional Power Committee released its Week 8 of FY 2026-27 ancillary services account and regional SCUC account covering 18 to 24 May 2026, totalling Rs. 65,507 lakh, with a payment due date of on or before 11 June 2026. The account is settled under the Ancillary Services Regulations 2022 and the CERC Grid Code 2023, including TRRAS-emergency charges for thermal IPPs and regional units of 250 MW and above.

8WRPC's April 13-19 DSM account shows Rs. 175 crore WR-NR payable
The CEA's Western Regional Power Committee issued its deviation settlement account for 13 to 19 April 2026. Among inter-regional transactions, the WR-NR exchange generated the largest payable at Rs. 1,75,48,85,385, while WR-SR yielded a receivable of Rs. 2,40,87,22,952, leaving a net inter-regional receivable of Rs. 43,97,99,288. MSEB recorded the highest beneficiary payable at Rs. 11,94,40,206 and GEB the highest receivable at Rs. 9,00,97,728.

8WRPC's April 20-26 DSM account sees WR-NR payable surge to Rs. 260 crore
The CEA's Western Regional Power Committee published its deviation settlement account for 20 to 26 April 2026, showing sharply elevated inter-regional flows. The WR-NR payable alone reached Rs. 2,59,88,01,339, up from Rs. 175 crore the prior week, driven by greater deviation by Northern beneficiaries. The WR-ER payable was Rs. 45,34,52,195, while WR-SR remained a large receivable at about Rs. 2,33,81,66,576. The period covered Karnataka High Court order implications under the amended DSM Regulations 2024.

8WR-NR interface owes Rs. 142.91 crore net DSM charge in week ending 5 April
The Western Regional Power Committee's deviation settlement account for 30 March to 5 April 2026 (fourth revision) shows the WR-NR interface as the largest net payer at Rs. 142.91 crore, followed by WR-ER at Rs. 26.44 crore. The WR-SR interface was the biggest net receivable entity at Rs. 207.97 crore. Among generators, TPCL Mundra (Rs. 71.61 lakh net payable) and BALCO (Rs. 65.59 lakh net payable) were notable, under DSM Regulation 2024.

8WR-ER DSM payable surges to Rs. 74.48 crore in week of 6-12 April
The Western Regional Power Committee's ABT-based deviation charge account for 6 to 12 April 2026 records WR-ER as the dominant payer at a net Rs. 74.48 crore, up sharply from the previous week. WR-NR follows at Rs. 65.96 crore net payable, while the WR-SR corridor remains the principal net receivable entity at Rs. 164.65 crore. AMNSIL carries a net payable of Rs. 1.97 crore for the beneficiary segment, under DSM Regulation 2024 effective 16 September 2024.

8PGCIL's Western Region transmission system clocks 99.77% availability in April 2026
The Western Regional Power Committee certified that PGCIL's AC transmission system in the Western Region achieved 99.77% availability in April 2026, excluding inter-regional AC and HVDC systems. The WR-NR inter-regional AC corridor recorded 99.85% availability, while the WR-ER inter-regional AC link delivered a perfect 100% for the month. The certificate was issued under the CERC Tariff Regulations 2024 and signed by Superintending Engineer P.D. Lone.

8Dozens of 400 kV Western Region reactors held out all of April for voltage regulation
PGCIL's Western Region element-wise tripping report for April 2026 shows a large number of 400 kV bus reactors and shunt line reactors at substations including Pune GIS, Parli and Aurangabad kept out of service for the entire 720-hour month under WRLDC instructions for voltage regulation. Several voltage-regulation devices at Pune-PG recorded outage durations of 719 hours and 59 minutes, indicating planned voltage management rather than forced tripping events.

8GRID-INDIA commits 66,521 MWh of up-reserves for 7 June ancillary services
GRID-INDIA's daily report on ancillary services and security-constrained unit commitment for 7 June 2026 shows SCUC-Up scheduled energy of 66,521 MWh and SCUC-Down of 30,361 MWh at the inter-state level. The report profiles spinning up and down reserves against requirement across the 24-hour day, with the inter-state reserve requirement taken as half of the total system reserve requirement for the all-India grid.

8India misses daily generation target by 75 MU on 4 June as hydro and nuclear lag
India generated 4,690 MU against a target of 4,765 MU on 4 June 2026, falling short by 75 MU in a single day, per the CEA all-India generation overview. The Northern Region recorded a 6.66% shortfall, with hydro generation underperforming by nearly 14% and Northern nuclear output 21.83% below target. While thermal broadly held its ground, cumulative year-to-date generation remained 5,633 MU below programme.

829,028 MW stuck out of grid for over 15 days, CEA report reveals
A total of 29,028 MW of thermal and nuclear capacity had been idle for more than 15 days as of 4 June 2026, according to the CEA daily report. From gas plants starved of fuel to coal units battling chronic boiler failures, units including Ramagundem STPS, Yadadri TPS and Raichur TPS have been offline for months, while multiple combined-cycle units remain in reserve shutdown due to costly fuel, exposing a systemic infrastructure strain.

8India recommissions 6,138 MW of capacity in a day even as outages outpace recovery
On 4 June 2026, India recommissioned 6,138 MW of power capacity into the national grid, according to the CEA daily report. Units from Yamuna Nagar, Kota, Ghatampur, Kawas CCPP and North Chennai TPS Stage 3 were restored after stints ranging from tube leakages to generator protection faults. However, the pace of units going out continued to outstrip recommissioning, keeping pressure on grid operators and state utilities.

810,338 MW tripped out of India's grid in a single day on 4 June
On 4 June 2026, a total of 10,338 MW of generation capacity exited India's national grid through a combination of forced outages, maintenance shutdowns and fuel conservation, the CEA reported. Yermarus TPP's twin 800 MW units went down simultaneously, North Chennai TPS Stage 3 tripped on furnace failure, and Korba-West lost 500 MW to a tube leakage, underscoring the fragility of India's power supply chain on a single day.

8Only 77.22% of India's monitored power capacity worked on 4 June, CEA data shows
India's monitored power generation capacity stood at 3,10,774 MW, but on 4 June 2026 only 77.22% was delivering electricity, the CEA capacity utilisation report shows. Coal plants performed best at 82.55% of monitored capacity, but gas and liquid-fuel plants managed a dismal 48.04% and hydro lagged at 68.92% on seasonal factors. Nearly 44,938 MW sat under various categories of outage, exposing a chronic efficiency gap.

8Over 5,724 MW has been out of India's grid for more than a year, CEA flags
Over 5,724 MW of India's installed capacity had been out of the grid for more than a year as of 4 June 2026, the CEA reported, with some units dormant for over a decade. Stations from Gautami CCPP and Kondapalli CCPP to Tuticorin TPS lie abandoned due to fuel shortages, missing power purchase agreements, or pending scrapping — dead capacity representing billions in stranded investment and gaps in long-term fuel security planning.

8India's power exchange clears over 11 lakh MWh in a week as average prices soften
The weekly Day-Ahead Market summary for 1 to 8 June 2026 shows total market clearing volume of about 11.13 lakh MWh across eight days, with 28.68 lakh MWh in purchase bids and 36.46 lakh MWh in sell bids. The average market clearing price slid from Rs. 5,619 on 4 June to Rs. 4,593 by 7 June, signalling a consistent easing of power prices, likely driven by rising solar surplus on the IEX platform.

8Real-time market clears 12.9 lakh MWh in a week as prices fall 48% mid-week
The weekly Real-Time Market summary for 1 to 8 June 2026 records total market clearing volume of about 12.94 lakh MWh, with the average price falling from Rs. 5,739 per MWh on 3 June to Rs. 2,973 by 7 June, a drop of nearly 48% in four days. Sell bids routinely exceeded purchase bids from 5 June onward, marking a decisive shift from a supply-constrained to a supply-surplus market on the IEX RTM.

8SRLDC tracks schedule-versus-drawal for six southern states as Tamil Nadu nears 10,000 MW
SRLDC's schedule-versus-drawal report for 7 June 2026 tracks the 24-hour scheduled and actual drawal of the six southern states — Andhra Pradesh, Karnataka, Kerala, Puducherry, Tamil Nadu and Telangana. The profiles show Tamil Nadu drawing close to 10,000 MW at its peak, Andhra Pradesh and Telangana hovering in the 4,000 to 6,000 MW range, and Puducherry the smallest at roughly 350 to 550 MW through the day.

8Maharashtra and DNHDDPDCL briefly breach ATC on 7 June, WRLDC indices show
WRLDC's daily system reliability indices report for 7 June 2026 shows Available Transfer Capability violated for Maharashtra in 3 blocks (0.8% of the day, 3.1 hours) and for DNHDDPDCL in 4 blocks (1.0%, 4.2 hours), while Gujarat, Madhya Pradesh, Chhattisgarh and Goa logged none. No state recorded any N-1 criterion violation, with TTC-crossing flows on intra-regional corridors used as the proxy, based on WRLDC SCADA data.

8Tripura breaches transfer capability for 45.6 hours on 6 June, NERLDC flags Assam strain
NERLDC's system reliability report for 6 June 2026 records Total Transfer Capability violations on two corridors: NER-Tripura in 44 blocks (10.93% of the time, 45.6 hours) and NER-Assam in 23 blocks (5.8%, 24.2 hours), with utilities intimated for corrective action. The Arunachal Pradesh, Manipur, Meghalaya, Mizoram and Nagaland corridors recorded no violations through the day across the North-Eastern Regional Grid.

8NLDC schedules Sipat at Rs. 1.32 per kWh atop 8 June merit-order stack as SCUC locks 24-hour despatch
GRID-INDIA's NLDC security-constrained unit commitment for 8 June 2026, published a day earlier at 15:00 hrs, ranks central thermal stations by energy charge rate. Sipat STPS Stage-1 was scheduled at 863.97 MW at Rs. 1.32 per kWh and Stage-2 at 313.55 MW, with Korba STPS Stages 1 and 2 together at 689.97 MW. Costlier blocks such as Barh-1 at 1,011.73 MW and the Vindhyachal and Kahalgaon units were also committed, all flagged SCUC-YES for despatch.

8India's intraday ancillary market logs over 10,000 MWh of bids but zero cleared volume in a week
The IEX Intraday Ancillary Services weekly summary for 1 to 8 June 2026 reveals a striking matching failure: combined purchase bids of over 8,600 MWh and sell bids of over 14,800 MWh across the week, yet zero cleared volume, zero scheduled energy and no market clearing price. Sell bids clustered during solar-peak hours while purchase bids appeared only at night, leaving willing participants unable to transact even as India's intraday flexibility needs grow with rising solar.
Details
CEA & GRID STANDARDS

8WRPC publishes April 2026 monthly progress report on Western Region capacity and grid operations
The CEA's Western Regional Power Committee released its monthly progress report for April 2026, covering the Western Region's installed capacity as on 30 April 2026, capacity additions during the month, and peak demand during solar and non-solar hours. The report also details energy requirement versus actual in MU, April 2026 versus April 2025 comparisons, schedule versus actual drawal, load shedding, generation by central, state and IPP stations, hydel reservoir storage, and grid frequency and voltage profiles at selected 400 kV and 765 kV substations.

8Eastern Region's 159th protection coordination committee meeting notice issued
The CEA's Eastern Regional Power Committee issued a notice for its 159th Protection Coordination Committee meeting, covering Bihar State Power Transmission Limited, Damodar Valley Corporation, Jharkhand Urja Sancharan Nigam, WBSETCL, OPTCL, NTPC's eastern stations including Farakka, Kahalgaon, Talcher, Barh and Darlipalli, POWERGRID ER-I and ER-II, NHPC and ERLDC. The committee oversees relay coordination and protection settings across the Eastern Regional Grid.

TENDERS & PROCUREMENT (GeM/NIT)

8IREDA schedules 8 June virtual pre-bid conference for empanelment of lenders' legal counsel
Indian Renewable Energy Development Agency Limited issued an advisory that the pre-bid conference for its RFP for empanelment of lenders' legal counsel (reference GeM/2026/B/7621560) will be held virtually on 8 June 2026 from 2:30 PM to 5:30 PM on Microsoft Teams. The meeting is open to all eligible law firms regardless of whether they filed pre-bid queries, with a maximum of two persons per bidder firm, and queries addressed in alphabetical order of firm names.
Details
SOLAR POWER

8KERC drafts distributed solar framework extending generation beyond rooftops
The Karnataka Electricity Regulatory Commission notified draft regulations for grid-interactive distributed solar PV plants, expanding installations beyond rooftops to building facades, elevated ground structures and walls. The framework, under Notification KERC/F-34 dated 2 June 2026, introduces virtual net metering and group net metering, allowing consumers to share solar generation credits. The move fundamentally redefines how Karnataka accounts for and incentivises decentralised solar power generation.

WIND & HYBRID POWER

8MNRE updates ALMM-WTC list for wind turbine blades and gearboxes as on 2 June
The Ministry of New and Renewable Energy released an updated Approved List of Models and Manufacturers for Wind Turbine Components as on 2 June 2026, covering blades and gearboxes. Pioneer Wincon Energy Systems lists the HT24 (24 m, 750 kW) and PW28 (27.75 m, 750 kW) blades certified to IEC 61400-22. ZF Wind Power Coimbatore holds IECRE certification valid to 6 May 2027 for the EF0953A gearbox rated 3,560 kW for the S144-3.0/3.15 MW turbine.

8Researchers design ESP8266 IoT system to detect wind turbine faults in under two seconds
A paper in the International Research Journal of Modernization in Engineering Technology and Science (Vol. 8, Issue 5, May 2026) from Amrutvahini College of Engineering, Sangamner, presents an IoT-based wind turbine monitoring and protection system using the ESP8266 NodeMCU. It tracks six parameters across five sensors and triggers relay disconnection within two seconds, with alerts on an LCD and ThingSpeak. With India targeting 500 GW renewable capacity by 2030 and about 44 GW of wind installed by 2024, the authors stress real-time fault detection.

POLICY & INCENTIVES

8India reaches 53.21% non-fossil electricity capacity by March 2026, five years ahead of target
India showcased its Carbon Credit Trading Scheme at the WTO Trade and Environment Week 2026 in Geneva on 5 June 2026. As of March 2026, non-fossil installed capacity reached 53.21%, surpassing the 50% NDC target set for 2030 by nearly five years. Emissions intensity of GDP also fell 37.38% between 2005 and 2022, beating the 33 to 35% NDC goal. The National Green Hydrogen Mission standards and the Indian Carbon Market framework were also presented.

8IEEFA flags Bangladesh's BDT 556.6 billion power subsidy gap as case for clean energy shift
An IEEFA report published 5 June 2026 by analyst Shafiqul Alam argues Bangladesh's energy transition must be seen beyond climate mitigation. The fossil-dominated power sector consumed about 7% of the national budget through a revenue shortfall of BDT 556.6 billion (USD 4.53 billion) in FY2024-25. After a 17% retail tariff hike, industries up to 5 MW load face tariffs rising to BDT 11.56 to 16.06 per kWh, making solar compelling; per-capita emissions stand at 1.48 tCO2eq versus a global 6.48.

8India's green day-ahead market trades over 21 lakh MWh in a week as solar glut pressures prices
The weekly Green Day-Ahead Market summary for 1 to 8 June 2026 recorded cleared volumes exceeding 21 lakh MWh, with solar accounting for the lion's share. Average market clearing price slipped from Rs. 6,454 per MWh on 4 June to Rs. 5,600 by 7 June, a clear downtrend. With sell bids consistently outpacing purchase bids, abundant clean energy supply is beginning to erode the premium that renewable generators have long relied upon.

8Green term-ahead market executes block trades at the Rs. 10,000 per MWh price cap
Green Term-Ahead Market trade data for 5 to 7 June 2026 shows day-ahead contingency contracts executed across multiple block slots at the maximum permissible price of Rs. 10,000 per MWh. Volumes per trade ranged from 5 to 85 MWh, but a rising number of trades reflects growing commercial interest in forward green power products. As India pushes renewable procurement reform, GTAM is emerging as a structured alternative to bilateral green power contracts.

8PXIL's green day-ahead platform records zero cleared volume across all sessions
While IEX's Green Day-Ahead Market remained active, PXIL's equivalent GDAM platform recorded zero cleared volume across its 15-minute, hourly and weekly formats from 5 to 8 June 2026. Purchase and sell bids, market clearing volume, curtailment and scheduled volumes all read nil. The contrast between the two licensed exchanges raises questions about market concentration and whether India's green energy market is effectively a single-exchange affair.
Details
WORK ORDERS & SUPPLY CONTRACTS

8BHEL bags over Rs. 21,000 crore EPC order for 3x800 MW Meja Stage-II project
Bharat Heavy Electricals Limited received a notification of award on 4 June 2026 from Meja Urja Nigam Private Ltd, a joint venture of NTPC Ltd and UPRVUNL, for the EPC package of the 3x800 MW Meja Supercritical Thermal Power Project Stage-II at Prayagraj, Uttar Pradesh. The contract, valued at over Rs. 21,000 crore excluding GST, covers design, supply, construction, erection and commissioning, with a completion target of 70 months. BHEL filed the disclosure on 5 June 2026.

8HCC bags Rs. 127 crore Bhutan hydro contract for Wangchhu diversion works
Hindustan Construction Company Ltd secured a contract worth about Rs. 127 crore from Wangchhu Hydroelectric Power Limited, Bhutan, for construction of diversion tunnels, hydromechanical gates and cofferdams at the Wangchhu Hydroelectric Project, to be completed within nine months. The award reinforces HCC's three-decade Bhutan presence, where it has executed Tala (1,020 MW), Punatsangchhu-1 (1,200 MW) and Nikachhu (118 MW), and has built 26% of India's installed hydropower capacity.

8HPX floats reverse auction for Chhattisgarh DISCOM's 100 MW hydro and non-solar blocks
Hindustan Power Exchange Limited issued Circular HPX_RA_00979 dated 5 June 2026 for a long-duration contract reverse auction for Chhattisgarh State Power Distribution Company Limited, seeking 100 MW each of hydro and non-solar energy across three delivery windows from 16 June to 31 August 2026 at a ceiling of Rs. 10,000 per MWh. Seller interest opens 7 June and closes 9 June, with the e-reverse auction on 9 June from 14:00 to 16:00 hrs.

8HPX runs back-to-back reverse auctions for BALCO's 100 MW thermal and non-solar blocks
HPX launched four long-duration contract reverse auctions on 5 June 2026 (Circulars HPX_RA_00980 to 00983) for Bharat Aluminium Company Ltd, covering 100 MW blocks of thermal and non-solar energy with no ceiling price for July to September 2026 delivery. Seller interest opens 8 June and closes 10 June, with reverse auction windows on 10 June from 14:00 to 16:00 hrs and allocation on 11-12 June. Parallel auctions were initiated on IEX and PXIL.

8HPX lists five reverse auctions for Rajasthan Urja Vikas and Chhattisgarh DISCOM
HPX issued five auction circulars on 6 June 2026 (HPX_RA_00984 to 00988) for two buyers: Rajasthan Urja Vikas and IT Services Limited, with four thermal auctions and no ceiling price, and Chhattisgarh State Power Distribution Company Limited, with one thermal auction at a Rs. 10,000 per MWh ceiling. Rajasthan's auctions run seller interest from 6 to 8 June with bidding on 8 June from 12:00 to 14:00 hrs. Parallel auctions run simultaneously on IEX and PXIL.

EQUITY & STAKE ACQUISITION

8Government offloads 6.01% NHPC stake in Rs. 4,362 crore OFS; promoter holding falls to 61.39%
The President of India, through the Ministry of Power, sold 60,38,47,814 equity shares of NHPC Limited — 6.01% of paid-up capital — via an offer for sale on 2 and 3 June 2026, for gross consideration of about Rs. 4,362.38 crore. The government's promoter holding fell from 67.40% to 61.39%, while total equity capital stayed at 10,04,50,34,805 shares. Up to 90,40,530 shares were offered to eligible employees, each capped at Rs. 2,00,000.

8Abhishek Kamdar acquires 17.13% stake in Onix Solar Energy via rights issue
Abhishek Ashvinbhai Kamdar of Surat, with his HUF, acquired 63,16,486 equity shares of Onix Solar Energy Limited through a rights issue allotment on 3 June 2026, equal to 17.13% of the expanded capital. His combined holding reached 17.18% of the total paid-up capital of 3,68,67,926 shares. The company's equity capital rose from Rs. 25.07 crore to Rs. 36.87 crore after the issue, crossing the SEBI Takeover threshold requiring disclosure.

8GMR Estate Management plans off-market buy of up to 7.46 crore GMR Power shares
GMR Estate Management Private Limited, a wholly owned subsidiary of GMR Enterprises Private Limited, filed an advance intimation under SEBI Takeover Regulation 10(5) disclosing its intent to acquire up to 7,46,00,000 equity shares of GMR Power and Urban Infra Limited from promoter GMR Enterprises through off-market transactions any time after four working days from 4 June 2026. The proposed acquisition is within the target company's promoter group.

8Catalyst Trusteeship releases pledge on 12 crore GMR Power shares worth 15.36% of capital
Catalyst Trusteeship Limited filed a disclosure under SEBI Takeover Regulations confirming the release of a pledge over 12,00,00,000 equity shares of GMR Power and Urban Infra Limited, equal to 15.36% of paid-up capital and 14.74% on a diluted basis. The shares had been pledged by GMR Estate Management as debenture trustee for debentures of GMR Sports Venture Private Limited. The release was reported on 4 June 2026 on BSE and NSE.

8Gujarat opens renewable grid access at 200-plus substations under GETCO May 2026 list
Gujarat Energy Transmission Corporation released its updated substation list for renewable energy integration effective May 2026, letting developers connect 30 to 70 MW at 66 kV level per substation, subject to a detailed system study and bay availability. The move accelerates Gujarat's clean energy push across more than 200 substations, though GETCO cautions that listed capacities are indicative and not guaranteed at the interconnection stage.
Details
COMMISSION ORDERS (CERC/SERC)

8JERC approves Rs. 22.99 crore revenue surplus for DNHDDPCL in FY 2024-25 true-up
The Joint Electricity Regulatory Commission issued its true-up order (Petition 176 of 2026, dated 4 June 2026) for DNH and DD Power Corporation Limited covering FY 2024-25, determining a net revenue surplus of Rs. 22.99 crore against the petitioner's claimed gap of Rs. 16.08 crore. Including holding costs through FY 2026-27, the surplus to be returned through a tariff rebate rises to Rs. 27.51 crore. The order, effective 1 July 2026, also incorporates an APTEL-directed carrying cost of Rs. 20.66 crore.

8APERC rules pre-2023 rooftop solar projects of 500-1000 kWp to continue under earlier net metering
The Andhra Pradesh Electricity Regulatory Commission, in a clarification dated 4 June 2026, ruled on APEPDCL's query that solar rooftop PV systems of 500 kWp to 1000 kWp commissioned before APERC Regulation 4 of 2023 will continue to be billed under earlier net or gross metering terms until their agreements expire. The Commission held that Clause 22 provides transitional protection, and that the 500 kWp ceiling under Clause 5.6 applies only prospectively.

8HPERC takes up Shiva Power's plea for Rs. 4.67 per kWh tariff on 3 MW Kapru Baner project
HPERC admitted Petition 212 of 2026 on 5 June 2026, filed by Shiva Power, seeking the applicable tariff of Rs. 4.67 per kWh for the 3.0 MW Kapru Baner Hydro Electric Project in Kangra after excluding an Industrial Development Scheme subsidy of Rs. 2.69 crore. The petition, with a fee of Rs. 1,05,000 deposited, arises from the Commission's earlier order dated 17 May 2022. HPSEBL has three weeks to reply, and the case is listed for 23 July 2026.

OMBUDSMAN & CONSUMER GRIEVANCE

8Tamil Nadu electricity ombudsman issues Order 77 in a consumer's favour
The Tamil Nadu electricity ombudsman has issued Order No. 77, adjudicating a consumer grievance against the state power utility from its SIDCO Corporate Office in Chennai. The body continues to assert its role as an independent redressal authority, reinforcing TNERC's push to institutionalise consumer rights in electricity distribution. The underlying case was filed on 5 June 2025, with the ombudsman's order issued in 2026.

REGULATORY PETITION & REVIEW

8APTEL batch-hears five appeals as Diwakar Renewable-MSEDCL RPO dispute takes centre stage
The Appellate Tribunal for Electricity, in Court-1 before Officiating Chairperson Seema Gupta and Judicial Member Virender Bhat, heard a batch of five linked appeals (Nos. 220, 103, 106, 125 and 110 of 2026) on 5 June 2026. The primary dispute involves Diwakar Renewable & Infra Pvt. Ltd., OPG Power Generation Pvt. Ltd. and MSEDCL before MERC, with respondents including Bhilwara Energy Ltd. and Patanjali Ayurved Ltd.

8CERC's 11 June cause list features MCD's MSW tariff and NDMC's 120 MW FDRE procurement
The Central Electricity Regulatory Commission listed four petitions for a hybrid hearing on 11 June 2026. Petition 23/2026 (MCD) seeks tariff adoption for power from a municipal solid waste plant at Ghazipur to Delhi DISCOMs, while Petition 62/2025 (NDMC) concerns procurement of 120 MW of firm and dispatchable renewable energy through NHPC as intermediary procurer under a 25 July 2025 agreement. Two waste-to-energy petitions, including Tehkhand's 18 MW plant, are also listed.

8HPERC admits KKK Hydro Power's plea to regularise PPA at Rs. 2.95 per kWh for 4.90 MW Baragran project
HPERC admitted Petition 210 of 2026 on 5 June 2026, filed by KKK Hydro Power Limited, seeking retrospective approval of its PPA dated 11 March 2008 and supplementary PPA dated 10 September 2010 with HPSEBL for the 4.90 MW Baragran Small Hydro Power Project, along with tariff determination at Rs. 2.95 per kWh. Respondents were granted three weeks to reply, and the matter is next listed for 23 July 2026.

8HPERC admits petition to approve PPA for 1.50 MW Baada Deo small hydro project
HPERC admitted Petition 209 of 2026 on 5 June 2026, filed jointly by HPSEBL and Baada Deo Small Hydel Projects Private Limited under Section 86(1)(b) of the Electricity Act, 2003, seeking approval of the power purchase agreement for the Baada Deo Hydro Electric Project of 1.50 MW installed capacity. After hearing the authorised representatives of both joint petitioners, the Commission reserved its order on the matter.

8UPERC reschedules 9 June hearing on UPSLDC's PSDF funding for 132 kV SCADA RTUs
The Uttar Pradesh Electricity Regulatory Commission, via a notice dated 5 June 2026, preponed to 9 June 2026 the hearing of Petition 2334 of 2025 filed by UPSLDC Limited. The petition seeks approval to disburse Power System Development Fund monies for procuring Remote Terminal Units for data transmission at 132 kV SAS and non-SAS substations of UPPTCL, to improve SCADA control, load management and protection. It was originally listed for 7 July 2026.

8PSPCL raises pole hire rates 5% to Rs. 295 per pole for cable and broadband operators
Punjab State Power Corporation Limited's Chief Engineer (Commercial), Patiala, issued Commercial Circular 25/2026 dated 5 June 2026 revising pole hire rates for cable TV and broadband operators effective 1 April 2026. Under a 5% annual escalation, the rate for up to 50,000 poles rises from Rs. 280 to Rs. 295 per pole per annum, from Rs. 255 to Rs. 270 for 50,001 to 1,00,000 poles, and from Rs. 245 to Rs. 255 for above one lakh poles.
Details
DIVIDEND & BOARD DECISIONS

8ACME Solar raises Rs. 2,800 crore in maiden QIP since its 2024 listing
ACME Solar Holdings Limited has completed a Rs. 2,800 crore qualified institutional placement, its first equity raise since the 2024 listing, drawing SBI Mutual Fund, Nippon MF, HDFC MF, ICICI Prudential, Kotak MF, BlackRock, Amundi, Goldman Sachs and the Abu Dhabi Investment Authority. Proceeds will reduce leverage and strengthen the balance sheet. The QIP was managed by ICICI Securities and IIFL Capital Services, with the company's contracted renewable capacity standing at 8,070 MW.

8BGR Energy Systems seeks shareholder nod to raise authorised share capital
BGR Energy Systems Limited has issued a postal ballot notice dated 25 May 2026 seeking approval through remote e-voting from 6 June to 5 July 2026 to increase its authorised share capital and amend the capital clause of its Memorandum of Association. If passed by the requisite majority, the resolution will be deemed approved on 5 July 2026, with results declared by 7 July 2026. The cut-off date for eligible shareholders was 29 May 2026.

8DEE Development Engineers' order book climbs to Rs. 2,434 crore, led by power at Rs. 1,251 crore
DEE Development Engineers Limited reported a closing order book of Rs. 2,433.90 crore as on 31 May 2026, up from Rs. 1,909.82 crore on 1 May, after inflows of Rs. 631.91 crore and execution of Rs. 107.83 crore during the month. The power sector contributed the largest share at Rs. 1,251.42 crore, ahead of oil and gas at Rs. 881.18 crore. PSERC fixed the Malwa Power division tariff at Rs. 5.437 per kWh for FY2026-27.

EARNINGS CALL & ANALYST MEET

8K.P. Energy lines up 12 June investor slot at Choice Institutional Equities INSIGHTX forum
K.P. Energy Limited has notified exchanges that its management will participate in a group meeting at the Choice Institutional Equities INSIGHTX Virtual Forum 2026 on 12 June 2026 between 4:00 PM and 5:00 PM IST. The interaction is held under SEBI Regulation 30 and Part A of Schedule III of the LODR Regulations, 2015. The company confirmed that no unpublished price sensitive information will be disclosed during the session.

8RMC Switchgears schedules analyst day for FY2026 results on 11 June
RMC Switchgears Limited will host an analyst day on 11 June 2026 from 4:00 PM to 5:00 PM IST to discuss its audited standalone and consolidated results for the quarter and full year ended 31 March 2026. The virtual event, hosted by Dickenson World, will feature management commentary on FY2026 performance and a Q&A session. Investors may register through the link circulated with the BSE and NSE intimation dated 5 June 2026.

8Sarda Energy schedules two June investor meets across InsightX and Systematix forums
Sarda Energy & Minerals Ltd has disclosed two investor engagements under SEBI Regulation 30(6): a virtual group meeting at the InsightX 2026 Choice Institutional Equities forum on 10 June 2026, and a physical group meeting at the Systematix Promoters and Founders Forum 2026 on 16 June 2026. The company confirmed that only publicly available information will be shared and no unpublished price sensitive information will be disclosed at either event.

8Adani Enterprises to host analyst interaction at Navi Mumbai International Airport site on 10 June
Adani Enterprises Limited has informed exchanges that its management will host an in-person interaction with investors and analysts at the Navi Mumbai International Airport on 10 June 2026. The physical meeting, filed under SEBI Regulation 30, gives market participants direct access to the group's strategic infrastructure asset. The presentation for the meeting has been made available on the company's website for shareholders and analysts.

8Solarium Green Energy posts FY2026 earnings call transcript covering H2 results
Solarium Green Energy Limited filed with BSE on 6 June 2026 the transcript of its H2 and FY2026 earnings call held on 2 June 2026, under SEBI LODR Regulations 30 and 46(2). Hosted by TIL Advisors, the call featured Chairman and Managing Director Ankit Garg, Whole-Time Director Pankaj Gothi, CFO Rohit Jindal and Company Secretary Pankti Thakkar discussing audited financial results for the half year and full year ended 31 March 2026.

8Advait Energy Transitions posts Q4 FY26 transcript, cites energy transition golden era
Advait Energy Transitions Limited filed the transcript of its Q4 FY26 earnings call, held 1 June 2026, with BSE on 6 June 2026 under SEBI LODR Regulation 30. Moderated by EY and hosted by Founder and Managing Director Shalin Sheth with CFO Narayan Singh, the call reviewed audited standalone and consolidated results for the quarter and year ended 31 March 2026. Sheth described the energy transition sector as being in a golden era driven by India's energy independence goals.

8Sarda Energy corrects FY2026 domestic coal sales figure to 158,000 MT
Sarda Energy & Minerals Ltd filed a correction on 5 June 2026 rectifying its 23 May 2026 investor presentation, clarifying that FY2026 domestic coal sales were 158 thousand MT, not 150 thousand MT, against 354 thousand MT in FY2025 — a year-on-year decline of 55.3% rather than the 57.0% earlier reported. The company confirmed there were no other changes to the presentation slide concerned.

CREDIT RATING & ANALYST REPORT

8Fitch affirms JSW Hydro Energy's senior secured USD bonds at BB+/Stable
JSW Energy Limited has informed exchanges that Fitch Ratings, on 5 June 2026, affirmed the rating of step-down subsidiary JSW Hydro Energy Limited's senior secured notes (USD bonds) at BB+/Stable. The rating action was filed under SEBI LODR Regulation 30, with the Fitch press release available on its website. The USD bonds are a significant component of the JSW group's international debt profile.

8CARE reaffirms CARE A-/Stable on Madhav Renewables' Rs. 7 crore bank facilities
CARE Ratings reaffirmed CARE A-/Stable on 5 June 2026 for Rs. 7.00 crore of long-term bank facilities of Madhav Renewables Private Limited, reduced from Rs. 11.70 crore earlier. The rating reflects a 25-year fixed-tariff PPA with Uttarakhand Power Corporation Limited and an interest coverage ratio of 9.30x in FY2026, up from 5.95x. The company prepaid Rs. 4.85 crore of term loan in FY2026, extending the tail period to about 14 years; capacity utilisation was 15.86%.
Details
8The headline number is easy to spot, but the real story sits inside the engineering mix.
8A transmission line, multiple transformers, a large STATCOM and renewable evacuation infrastructure have been bundled into a single competitive package with unusual risk allocation. Details
8Five qualified contenders entered the arena, but the final tariff tells a deeper story about where renewable transmission competition is heading.
8Behind the winning number sits a transmission package carrying unusually large future-capacity ambitions and execution dependencies.
8The outcome could influence how developers approach the next wave of renewable energy zone-linked transmission bids. Details
 For reference purposes the website carries here the following tenders:
 
8Tender for supply of 4800 MWh (1200 MW x 4 Hrs.) from ISTS connected RE projects Details
  
8Tender for annual maintenance contract (AMC) for condition monitoring of equipment Details
  
8Tender for assistance in the works Details
  
8Tender for providing and installation of LT panels Details
  
8Tender for supply, fabrication, field welding, erection of pipelines, structures and miscellaneous works Details
  
8Tender for disposal of solid waste Details
  
8Tender for drilling of 04 No. bore wells and installation of casing pipe Details
  
8Tender for repairing, machining of 02 sets (48 Nos) guide vanes Details
  
8Tender for construction of a new retaining wall Details
  
8Tender for supply of diesel engine spares for phase-II powerhouse Details
  
8Tender for supply of personal protective equipment (PPE), electrical and mechanical safety items Details
  
8Tender for procurement of 01 no. 33 kV protection panel for transformer Details
  
8Tender for supply and AMC of tower footing impedance kit Details
  
8Tender for comprehensive AMC of air conditioners installed Details
  
8Tender for protection works Details
  
8Tender for construction of pipe culvert along Details
  
8Tender for provision for replacement of worn-out floor tiles/allied works Details
  
8Tender for comprehensive upkeeping and maintenance of power house Details
  
8Tender for reconditioning of existing epoxy flooring Details
  
8Tender for provision for tapping of water Details
  
8Tender for facelifting and surface finishing of columns and other allied areas of the transformer Details
  
8Tender for protection of 33 kV line Details
  
8Tender for excavation & refilling of earth and laying of various size and capacity HT/LT power/control cables Details
  
8Tender for supply of water purifier & cooler for various Details
  
8Tender for ARC for Mtc. of ash duke Details
  
8Tender for supply of spares of BFP pump Details
  
8Tender for construction of new storage shed Details
  
8Tender for replacement work of butterfly valve of 1800 mm Details
  
8Tender for misc mechanical works Details
  
8Tender for construction of retaining wall in connection with upgradation of 66kV sc to 110kV DC line Details
  
8Tender for reconductoring 11kV OH line by HT covered conductor Details
  
8Tender for erection 33 of kV line bifurcation of 33 kV feeder Details
  
8Tender for various civil construction works pertaining to feeder bays, augmentation of X-mer, addl. X-mer etc. and civil R and M works at various Details
  
8Tender for operation and minor maintenance of various EHV substation Details
  
8Tender for various civil construction works pertaining to feeder bays, augmentation of X-mer, addl. X-mer etc. Details
  
8Tender for civil works for construction of 220kV voltage X-mer, 132kV voltage Details
  
8Tender for work contract for reconditioning of bevel gear pair installed Details
  
8Tender for triennium work contract for online inspection of condenser negative pressure parts of units Details
  
8Tender for procurement of complete dome valve assembly and blow valves Details
  
8Tender for routine, breakdown, preventive maintenance and overhauling jobs mechanical works of turbine, generator and their auxiliaries, HPBP, LPBP, regenerative system, condenser, piping valves etc. Details
  
8Tender for providing and fixing of fencing to transformers Details
  
8Tender for construction of 33 kV substation Details
  
8Tender for testing of metering equipments HTTVMs / ABT meters/ CTs, PTs/CVTs and CT-PT sets Details
  
8Tender for supply of LT XLPE insulated aerial bunched cables Details
  
8Tender for supply of ACSR rabbit conductor Details
  
8Tender for annual maintenance contract for electrical maintenance works Details
  
8Tender for overhauling of different LT motors during Details
  
8Tender for service order for overhauling of CW pumps Details
  
8Tender for bi annual maintenance contract for mechanical maintenance of MS-1 to MS-5 for un-interrupted dry ash disposal from main silo Details
  
8Tender for biennial maintenance contract for overall illumination maintenance jobs Details
  
8Tender for Bi-annual rate contract for 02 years for different electrical and cable related job Details
  
8Tender for annual rate contract for switchyard of old units Details
  
8Tender for conversion of HTOH to UG cable Details
  
8Tender for strengthening of rusted towers of 220kV lines Details
  
8Tender for protection work Details
  
8Tender for annual maintenance work of 33kV & 11kV line distribution transformer Details
  
8Tender for work of Re-tubing of tube nests of LP heater Details
  
8Tender for work of overhauling / servicing of gear box, & rail alignment of gantry crane Details
  
8Tender for retrofitting of 415 V TVDC bus incoming feeder modules Details
  
8Tender for procurement of 33kV circuit breaker Details
  
8Tender for work of providing and fixing of microprocessor based MFM meters along Details
  
8Tender for AMC for the drying out of converter transformer Details
  
8Tender for dismantling of removed converter transformer Details
  
8Tender for construction of retention (protection) wall for the protection of tower Details
  
8Tender for replacement of existing battery sets & battery chargers Details
  
8Tender for establishment of 220/132/33kV substation Details
  
8Tender for establishment of 132/33kV substation along Details
  
8Tender for work of various civil annual maintenance works at various substations Details
  
8Tender for various civil annual maintenance works of all substation Details
  
8Tender for renovation of damaged staircase including S.S railing Details
  
8Tender for providing and fixing PUF panel operator cabin Details
  
8Tender for providing & fixing safety showers and sintex tank including other miscellaneous civil works Details
  
8Tender for providing muffing on periphery of existing various steel structure of coal yard Details
  
8Tender for work of supply & application of flexane brushable coating on rubber expansion bellows of various transformers Details
  
8Tender for misc. civil works Details
  
8Tender for work of preventive and breakdown maintenance of induced draft cooling towers Details
  
8Tender for work of refurbishment of various spares of CW pump Details
  
8Tender for erection, testing & commissioning work of structure, earthing, switchyard yard Details
  
8Tender for ARC for erection of HT / LT / TC and maintenance work Details
  
8Tender for annual rate contract for construction of power cable trench required Details
  
8Tender for construction of control room foundations, cable trench Details
  
8Tender for Bi annual rate contract for work for erection of 66kV equipment, structures Details
  
8Tender for work of application of thermal Insulation & aluminum cladding of various ducts, piping, valve Details
 You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8Private investment jumps to Rs 56 lakh crore in FY26, signalling capex momentum: SBI Research Details
 
8RVUNL To Bring 1,000 MWh Battery Storage Capacity Online By September Details
 
8Tata Steel plans post-2030 iron ore strategy to retain captive mining advantage Details
 
8VOC Port accelerates green transition with green hydrogen, wind power and green methanol bunkering initiatives Details
 
8Price targets out! Why Axis Direct is bullish on NTPC, NLC India and JSW Energy Details
 
8Invisible Backbone of Atmanirbhar Bharat: Why Transmission Is The Next Frontier Details
 
8Indian and Sri Lankan firms secure landmark wind power transmission contract Details
 
8Gujarat govt expands skill training for youth, introduces 'new-age' courses Details
 
8Solar panel prices increase by thousands of rupees Details
 
8Why energy transmission is the next frontier for India Details
 
8TNEB tenders worth Rs 5K crore under review': Electricity Minister Nirmal Kumar Details
 
8US sees nuclear renaissance with new micro-reactor, eyes global markets, including India Details
 
8T.N. government’s decision to shelve smart meters project a grave mistake: BJP Details
 
8BHEL secures Rs 21,000 crore Meja Stage-II EPC contract Details
 
8India’s Infrastructure & Economic Transformation: 26 Milestones That Changed the Nation in Modi’s 12-Years Details
 
8Gujarat adds 11 new skill courses to prepare youth for AI and electric vehicle sectors Details
 
8300 engineers get promotion in landmark move by TNPDCL Details
 
8Odisha Governor inaugurates 485 kWp rooftop solar power plant at Lok Bhavan Details
 
8Select Indian Agencies And Firms Get Access To Anthropic’s Mythos AI Under Project Glasswing: Report Details
 
8States lean on exchanges as power demand scales record highs Details
 
8Adani Power, Adani Green, Adani Energy: Buy, says Jefferies as it shares target prices Details
 
8Kirloskar Oil Engines: Valuation Premium Faces Execution Test Details
 
8SAIL in Danger of Losing Maharatna Status; BHEL Shows Sharp Turnaround Details
 
8DEE Development Engineers order book rises to Rs 2,434 crore after strong May order inflow Details
 
You can also click on Newsclips for more Details
 For reference purposes the website carries here the following tenders:
 
8Tender for work of complete internal electrification or repairing of existing wiring along with supply and installation of lighting material Details
  
8Tender for procurement of spares parts of travelling tipper Details
  
8Tender for supply of low RPM thyristor cooling fans Details
  
8Tender for dog to panther conversion of 66kV line Details
  
8Tender for supply of various spares for SWAS system of boiler Details
  
8Tender for procurement of diaphragm valves Details
  
8Tender for purchase of various L&T make contactors/relays Details
  
8Tender for erection of Esti for bifurcation 33 kV line feeder Details
  
8Tender for supply of 11 kV and 33 kV polymer insulators Details
  
8Tender for supply of 11kV 3 core 300 Sqmm and 33 kV 3 core 300 Sqmm HT XLPE cable Details
  
8Tender for supply of ISI marked LT AB cable Details
  
8Tender for supply of 33 kV strain hardware Details
  
8Tender for supply of 11 kV strain hardware Details
  
8Tender for development of renewable energy projects support Details
  
8Tender for upgradation of performance analysis diagnostics and optimization (PADO) system Details
  
8Tender for biennial work contract for complete overhauling/ refurbishment of hydraulic pump/motors installed Details
  
8Tender for procurement of spares of SAM Make LP water model Details
  
8Tender for work contract of dismantling, dragging, shifting of the transformer Details
  
8Tender for work of hammering and poking of coal bunker in all three shift Details
  
8Tender for procurement of spares of pneumatic power cylinder of secondary air damper Details
  
8Tender for providing and laying of water proofing treatment work over roof Details
  
8Tender for procurement of one number multi-purpose fire tender with chassis from fabricator for firefighting services Details
  
8Tender for award of contract for onsite primary frequency response PFR testing of 2X270 MW generating units Details
  
8Design, engineering, supply, erection, testing, commissioning of 220/66kV GIS substation Details
  
8Tender for annual running and breakdown maintenance of outdoor process water, firefighting and drinking water pipelines Details
  
8Tender for insulation work in boiler turbine Details
  
8Tender for replacement of 08 Nos. of SWBP/SWLP pump packages Details
  
8Tender for construction of new retaining wall Details
  
8Tender for restoration of retaining wall along Details
  
8Tender for river protection work Details
  
8Tender for construction of 33kV switching substation Details
  
8Design, supply, installation, retrofitting, testing and commissioning of 220kV bus bar protection scheme Details
  
8Tender for de-stringing of existing panther conductor and restringing and supply of ACSR panther conductor Details
  
8Design, supply erection commissioning and testing of water distribution system for natural draught cooling towers Details
  
8Tender for providing masonry, plaster, flooring, painting and other misc. civil works Details
  
8Tender for biennial job contract for rubber lining Details
  
8Tender for construction of precast concrete solid Details
  
8Tender for construction of drain along coal pile Details
  
8Tender for replacement of roofing sheet of construction sheds Details
  
8Tender for biennial contract for maintenance of ash dyke Details
  
8Tender for construction of maintenance of crusher house Details
  
8Tender for repair maintenance and replacement of damaged false ceiling Details
  
8Tender for roof repair works Details
  
8Tender for procurement of gun metal valves for different plants Details
  
8Tender for work for repairing and re-strengthening of mid span joints and other associated works in circuit 01 of 400kV DC twin moose transmission line Details
  
8Tender for supply of MCCB for 160 Amp and 200Amp suitable for LTDB Details
  
8Tender for erection, dismantling and maintenance of HT/LT line and transformer Details
  
8Tender for providing and fixing of fencing to transformers Details
  
8Tender for erection of 0.68 Kms S/C 33 kV line Details
  
8Tender for modification work for height raising of 132kV DC line Details
  
8Tender for consultancy services regarding various problems in electrical system Details
  
8Tender for supply and works contract for conversion of existing overhead HT and LT lines Details
  
8Tender for construction of RCC 220kV s/s Details
  
8Tender for work of augmentation of substation by addition of 25MVA, 132/33kV power transformer along Details
  
8Tender for work of supply, installation, testing and commissioning of 3-phase DSP (digital earth surge protection) system Details
  
8Tender for procurement of 06 numbers of grinding ring and 216 number of balls Details
  
8Tender for procurement of mill overhauling spares Details
  
8Tender for procurement of different types of ropes and gaskets for maintenance of various auxiliaries Details
  
8Tender for procurement of different types of steel materials Details
  
8Tender for procurement of different types of HT bolts, nuts washers Details
  
8Tender for procurement of different types of ropes and gaskets Details
  
8Tender for procurement of grinding roll & bull ring segment of XRP 1003 coal mill Details
  
8Tender for procurement of fibre blanket & LRB mattress Details
  
8Tender for procurement of different HP valves Details
  
8Tender for procurement of different boiler tubes Details
  
8Tender for procurement of 02 no. of vertical movement hot air isolation gate for coal mill Details
  
8Tender for Bi-annual rate contract for providing errand and other miscellaneous services Details
  
8Tender for procurement of alumino ferric grade IV Details
  
8Tender for work of 11kV cable laying work including supply of jointing kit Details
  
8Tender for construction of project including ancillary structures Details
  
8Tender for construction, of a (new) Godown, along-with the upgradation, of the (existing) Details
  
8Tender for supply, erection and commissioning of new street light poles with cable laying Details
  
8Tender for erection, maintenance and dismantling work of overhead HT/LT line Details
  
8Tender for strengthening of various towers fall Details
  
8Tender for reconductoring with LT ABC Details
  
8Tender for erection of new RMU after laying 500 m UG cable Details
  
8Tender for shifting of 33 kV line Details
  
8Tender for construction of PCC flooring Details
  
8Tender for work of extension of switch house Details
  
8Tender for construction of PCC flooring with gravel spreading and drainage system Details
  
8Tender for construction of PCC flooring with gravel spreading and drainage system in the switch yard Details
  
8Tender for manufacture, testing, supply and delivery of battery chargers of various ratings Details
  
8Tender for maintenance of lines and attending the consumers complaint of 33/11 kV sub station Balbhadrapur Details
  
8Tender for maintenance of lines and attending the consumers complaint of 33/11 kV sub station Siggadi Details
  
8Tender for maintenance of lines and attending the consumers complaint of 33/11 kV sub station Jashodharpur Details
  
8Tender for maintenance of lines and attending the consumers complaint of 33/11 kV sub station Details
  
8Tender for annual maintenance of lines, DTRs, etc., and redressal of consumer complaints along Details
  
8Tender for annual maintenance of lines, DTRs, etc., Details
  
8Tender for replacement of ACSR conductor by 11 kV AAAC AL-59, 99 sqmm. Details
  
8Tender for replacement of ACSR conductor by 11 kV AAAC AL-59, 99 sqmm. covered conductor Details
  
8Tender for work of installation of aerial bunched (AB) cable Details
  
8Tender for work of providing and erecting additional poles Details
  
8Tender for work of installation of distribution transformers and construction of associated HT/LT lines Details
  
8Tender for supply, installation, testing and commissioning of 5 nos of 22kV bays at 400kV S/Stn Details
  
8Tender for work of providing & fixing of silica gel breather & supply of blue silica gel for various EHV TF/ICT Details
  
8Tender for work of the restringing of loose span of 220kV line Details
  
8Tender for work for construction of 2 no. new 33kV AIS feeder bay Details
  
8Tender for work of annual maintenance contract (AMC) for attending 400 kV & 220 kV lines Details
  
8Tender for supply of various ratings of 24 kV CT Details
  
8Tender for supply of 300 NB M.S.ERW pipes Details
  
8Tender for work of constructions of new maintenance free earth pit Details
  
8Tender for work of removal & laying of 6.6/11kV (E), 1C X 1000Sq.mm, aluminum cables along Details
  
8Tender for various maintenance works of wagon tippler 1 to 3 in coal handling plant Details
  
8Tender for work of replacement of deteriorated H-frame and mechanical strengthening work of 66kV lines Details
  
8Tender for work of shifting of 66kV line Details
 You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8CIL Boosts Coal Supply to Non-Regulated Sector, Record Auctions Details
 
8GE Vernova Introduces 3.8 Mw Workhorse Turbine In India Details
 
8India crosses 150 GW solar mark, eyes global no.2 spot: Rubix Data Sciences Details
 
8CareEdge: India Solar Module Capacity To Reach 250 GW Details
 
8CEEW Reports Highlight Rooftop Solar Growth and Job Creation Potential in India Details
 
8iNVERGY opens BESS Giga factory in Uttar Pradesh Details
 
8Solar Storage Push Gains Momentum as Centre Urged to Extend Battery Subsidy for Rooftop Systems Details
 
8Inox Clean Energy to acquire Vena Energy India’s 5.4 GW renewable energy and 2.5 GWh BESS platform Details
 
8Suzlon 2.0: Why the renewable energy giant's strategic shift matters Details
 
8Beyond capacity: Building the systems that will power India’s clean energy future Details
 
8Manju Gupta: Executive Director, Power Grid Corporation of India Limited Details
 
8India crosses 150 GW solar mark, eyes global no.2 spot: Rubix Data Sciences Details
 
8Coal India offers more coal, greater operational flexibility to non-regulated sector consumers Details
 
8Saatvik Green Energy Limited Honored with ‘Brand of the Year’ Award at India Power & Renewable Leadership Awards 2026 Details
 
8Strategic Framework: CEA releases the National Adequacy Plan up to 2035-36 Details
 
8CIL offers record 35 MT coal linkage auction to sponge iron sector Details
 
8Coal India unveils measures to boost coal supply Details
 
8World Environment Day: Is 24x7 solar power possible in India Details
 
8Coal India offers record coal volumes to non-regulated sectors, eases linkage norms Details
 
8How India’s smart meter rollout is accelerating the need for scalable IoT connectivity Details
 
8Sharika Enterprises Secures Uttarakhand Grid Modernisation Order in SCADA-ADMS Push. Details
 
8Former grid operations expert Sudhansu Sekhar Barpanda appointed OERC Member Details
 
8Er Punnerdeep Singh Brar assumes charge as PSPCL Director/Generation Details
 
8CIL ramps up coal availability for non-power sector, relaxes linkage rules Details
 
8NTPC and UPRVUNL Sign SJVA-III to Boost Meja Stage-II Capacity to 2,400 MW Details
 
8Rs 240,000 Crore Order Book: PSU Stock Jumps After Securing Rs 21,000 Crore Power Project Contract Details
 
8NTPC invites EOI for flexible thermal power solutions to support renewable energy integration Details
 
You can also click on Newsclips for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8LPG
8Ammonia
8Coal & Coke
Click on Reports for more. Details
 1 2 3 > 

Showing 1–50 of 116 items