All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Sep 2026
Addendum-VI reverses Zone VI error and switches Sirkari Bhyol turbine bearings to oil lubrication
8UJVNL has restored the project's IIT Roorkee-derived Zone V seismic basis after an intervening addendum wrongly cited Zone VI, and in the same document replaced water-lubricated guide bearings with babbitted oil-lubricated units with water cooling.
8The bearing change reaches cooling circuits, oil handling, monitoring and maintenance philosophy, so the harder question is how much lifetime auxiliary-system cost bidders must now carry into a 48-month fixed package.
NTPC issues second corrigendum on Simhadri 0.5 MMT coal without resolving 25% versus 10% quantity conflict
8Corrigendum C4 of 11 September supersedes C1 and the original buyer-added terms for the Rs 2 crore EMD Simhadri lot, retaining the right to move ordered quantity by up to 25% at award and again during the contract.
8Technical Specification Clause 3 still carries a plus or minus 10% station band, and with the GeM summary recording no ePBG against ITB Clause 22.0's mandatory 5% PBG, bidders must price a maximum volume and security exposure the documents do not settle.
UPPTCL deletes 'provided by UPPTCL' from transformer rows, forcing Noida GIS bidders to price erection
8Corrigendum-1 has replaced the BOQ for the Rs 112.05 crore Sector-155 substation, removing the entry that let bidders leave installation of the 160 MVA and 63 MVA owner-supplied transformers unpriced, and redefining 33 kV termination kits by interface rather than indoor or outdoor location.
8Submission moved a week to 17 September, but the real exposure is that the contractor now prices commissioning around equipment whose manufacture and delivery stay with UPPTCL, with no project-specific relief formula for late handover.
UPRVUNL converts 640 MW Rihand-Obra pumped storage from BOO to zero-consideration handover after 40 years
8The corrigendum replaces extendable BOO ownership with compulsory transfer to UPRVUNL 40 years from SCOD, in good running condition, free of liens and without transfer price or compensation, while the PBG moves to 5% of the Rs 3,953 crore estimate at Rs 197.65 crore and stays live until 12 months after actual commissioning.
8With nine extensions pushing bids to 12 October and forfeiture possible where the developer's own DPR finds the project infeasible, the test is how banks price terminal transfer beside pre-construction feasibility risk.
OPTCL opens Rs 301 crore HTLS reconductoring with two different estimates in its own records
8The Meramundali–Mendhasal package requires dismantling twin AAAC Moose and stringing twin HTLS on the live 400 kV double-circuit line, plus equipment and bus upgrades at both grid-substation ends, with bids closing 9 October.
8The signed notice states Rs 301,22,38,089 while the portal header reads Rs 3,01,26,70,182, and with outage allocation, tower adequacy and scrap responsibility all unspecified, bidders face a package whose basic commercial reference point is unreconciled.
POWERGRID ties 765kV GIS package SS 185T to a TBCB outcome bidders cannot influence
8The Orai, Patran and Agra extension package requires an exclusive MOU with the lowest evaluated qualified bidder, who receives a contract only if POWERGRID wins the upstream tariff-based bid, while exclusivity bars that bidder and connected entities from supporting rival TSPs.
8Four qualification routes admit manufacturers, collaborator and parent-backed Indian plants and EPC bidders, but with a further 10% ex-works guarantee on Routes 2 and 3 and no quantified compensation if POWERGRID loses, broad access on paper may still leave OEM gatekeeping intact.
NTPC builds six-contractor panel for Rs 300 crore Barh pond ash haulage with no purchase-order guarantee
8The 2026-27 rate contract splits work among up to six AST-01 vendors matching a single L1 price, one part reserved for an SC/ST MSE bidder, with roughly Rs 20 crore placed sequentially and Rs 50 crore as the cumulative ceiling per contractor.
8Payment follows compacted ash certified by the receiving road authority rather than trips or weighbridge tonnage, and with variation from minus 100% to plus 20%, panel entry buys eligibility rather than revenue.
GPCL risk-management RFP carries three submission deadlines and a hard copy that overrides the portal
8The ERM consultancy for GPCL's renewable, BESS, green hydrogen, mining and transmission portfolio records online closing at 18:00 on 21 September on the portal, 3 October in Chapter 1 and physical receipt on 6 October, with clause 5.3.2 giving the posted copy precedence.
8The QCBS 70:30 structure is designed to protect technical quality, but a compliant bidder could still be rejected for following one official instruction over another unless GPCL clarifies which date and channel govern.
MPPTCL bars partial bids on Rs 316 crore Sabalgarh package spanning substation, 34 km line and LILO
8TR-28/2026 bundles a new 400 kV substation, a Quad Moose double-circuit link to Morena Pooling and about 21 km of 220 kV LILO into one indivisible turnkey award, with 30-month and 24-month completion tracks and no rainy-season relief, while three 500 MVA and two 200 MVA transformers and two 125 MVAR reactors stay outside contractor supply.
8Price variation reaches only selected equipment and civil work, so reverse-auction pressure will meet a large block of fixed-price and deemed-inclusion exposure.
NTPC Lara mine-filling tender contradicts itself on diesel escalation and soil-cover thickness
8The Rs 255.06 crore package moving 20 lakh MT of ash into the Bishrampur and Dugga pits says no extra payment for fuel-rate changes at condition 2(h), then indexes 25% of contract price to diesel at Clause 14, while Scope Clause 1 fixes a 500 mm soil cap against Payment Clause 9(i)'s 300-500 mm band.
8With quantity variable from minus 100% to plus 20% across a six-way split and no order-of-precedence statement, both conflicts sit directly on the lump-sum price.
APCPL admits Talabira coal in one clause and excludes OCPL in another for 5 LMT Jhajjar buy
8The invitation for bids for the Rs 5 crore EMD package bars coal from CIL, SCCL, OCPL and NTPC group mines, while Technical Specification Clause 2 expressly permits OCPL and Talabira sources including the NLCIL captive mine.
8A second gap sits between Annexure-B1's 4,300 Kcal/kg ceiling and Clause 11's payment cap at 4,000 Kcal/kg, leaving a bidder unable to know whether its declared source qualifies or its better coal can be monetised.
MSEDCL grants nine days on Rs 97.87 crore cable tender but holds firm price against five bidders
8Shriram Cables, Torrent Electricals, Dynamic, KEI and Tirupati each sought price variation on the 33 kV and 11 kV 300 sq.mm HT XLPE package, and MSEDCL answered every request with "as per tender documents," also refusing KEI's three-month first-lot request and Tirupati's insurance surety bond proposal.
8Bidding moved from 1 September to 10 September, leaving a nine-month firm-price delivery, a 20% two-month mobilisation obligation and 1% weekly LD untouched.
OPTCL forces single award across Palaspanga and Barbil while its notice repeats the EMD as the estimate
8The Rs 315.27 crore package makes Lot-I and Lot-II one indivisible contract covering GIS at both stations, 1.2 Rkm of underground cable and roughly 69.2 Rkm of 220 kV overhead line including Twin Moose on 400 kV towers, all in 24 months.
8The opening notice states the estimate as Rs 3.15 crore, exactly the EMD figure, and Table-A carries 10 August against the portal's 11 August, leaving bidders to rely on portal precedence for basic commercial approvals.
HPPCL seeks green hydrogen offtakers for 1 MW Dabhota plant without naming volume, purity or delivery point
8The EOI sets a Rs 1 EMD, zero form fee and Rs 2,360 processing charge, with closing on 13 August and cost opening one hour later, but does not state saleable output, pressure, metering ownership, custody transfer or contract tenure.
8Classified simultaneously as procurement of services and miscellaneous works with a scheduled cost opening, the notification leaves respondents unsure whether they are quoting a purchase price, a service charge or a bundled logistics proposition.
NTPC leaves three quantity formulations live across its 2.5 MMT five-station coal package
8The Telangana lot under CS-0011-011(10)-9 now carries a plus or minus 20% variation in the revised detailed document, plus or minus 10% in the separate technical specification and a 25% GeM option clause at both order placement and during contract.
8Sequential station opening means a bidder's later price bids stay unopened once it reaches its declared Annexure-TC-10 limit, making award appetite a live competitive variable before any price is compared.
NTPC cuts Tanda coal ceiling to 3,700 Kcal/kg while lifting initial payment to 80%
8Revised Annexure-B1 pulls the GCV envelope down from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal caps of 12% and 14%, and the GCV challenge window contracts from ten working days to seven calendar days with a ±71.7 Kcal/kg admissibility threshold.
8The move from 50% to 80% initial payment is the clearest contractor gain in the package, but it arrives alongside ±20% quantity variation, station diversion rights and a source pool narrowed by the tighter specification.
Nabinagar sits last in NTPC's price-opening order, exposing it to a thinner field
8Corrigendum-1 leaves the 16 September dates unchanged for the 0.5 MMT lot and fixes the opening sequence as Telangana, Simhadri, Mouda, Tanda and Nabinagar, with bid security shown at Rs 10 crore for five stations against a visible overwritten Rs 8 crore in ITB Clause 7.1.
8Because bidders reaching their declared award ceiling drop out before later envelopes are opened, the last station in the queue may face the weakest price competition regardless of its own economics.
NHPC inserts a missing crane chapter and cuts turbine efficiency threshold to 94% at Dulhasti Stage-II
8Corrigendum No. 1 added the absent Chapter 18 covering two 190/30-tonne powerhouse cranes and three others, Corrigendum No. 5 rewrote the cooling-water and HVAC chapters and lowered the non-responsiveness threshold from 94.5% to 94%, and price-adjustment indices moved from 2011-12 to 2022-23.
8Four extensions have taken submission from 24 July to 28 September on the Rs 496.90 crore package, yet unit commissioning stays fixed at months 43 and 44 from the civil zero date.
UJVNL lets two OEMs cover turbine and generator at Tiuni Plasu after 18 extensions
8Addendum-II moved qualification from turbine and generator to turbine "and/or" generator and deleted the contract-value experience thresholds, and Addendum-VI then allowed as many as two manufacturers, with force-majeure substitution limited to BHEL, Voith Hydro, Andritz Hydro and General Electric.
8Addendum-III deleted air-gap, partial-discharge and vibration monitoring and cut excitation redundancy from n+n to n+1, so the widened front door arrives with a thinner reliability margin and a Rs 260 crore turnover test for manufacturer-backed bidders.
JERC bars consultants holding two of three earlier awards from Chandigarh STU-SLDC tariff work
8The Rs 18 lakh QCBS assignment covering business plans, MYT petitions, mid-term review and true-ups to FY 2029-30 excludes firms already awarded two of three specified JERC bids, while demanding ten years of experience, 20 assignments worth Rs 1 crore and two staff stationed at the Commission.
8Corrigendum C3 warns that a participation fee can render the bid null and void, even though the underlying RFP still requires a Rs 10,000 processing fee and advance hard copies.
SECI moves Ramagiri wind auction to cost per certified MU and drops turbine floor to 2.7 MW
8Amendment-01 rewrites ITB Clause 32.4.1 so bids rank on EBV divided by NIWE-certified ten-year P90 generation, with the denominator locked before the reverse auction and only price free to move, while the power-curve pass mark falls from 98% to 95% and the 96-hour test threshold from 98% to 96%.
8Repeated STPT failure no longer triggers WTG rejection and refund with 13% interest but a generation-linked LD at Rs 4.5 per kWh, leaving yield certification quality as commercially decisive as the EPC quote.
NPCL wants 300 MW RTC with 90% availability in six peak hours it picks day-ahead
8The 25-year BOO procurement requires a declared annual CUF of at least 75% held within plus or minus 10%, 50% of contracted capacity in every off-peak 15-minute block and 90% across six peak hours selected by NPCL on a day-ahead basis, with shortfall damages at 1.5 times tariff.
8Configuration and delivery points may change until financial closure but bring no SCSD relief, so the 24-month schedule and daily PBG encashment will likely surface as a firmness premium in the discovered tariff.
NTPC narrows Mouda coal window to 3,700 Kcal/kg as second corrigendum lands five days before bids close
8Corrigendum C4 of 11 September supersedes C1 for the 5 lakh MT package, while the revised document cuts maximum GCV from 4,300 Kcal/kg, ash from 50% to 45% and moisture to seasonal 12% and 14% caps, and moves payment from 50:40:10 to 80:10:10 with sampling charges down to Rs 2.97 per MT.
8GeM records no ePBG and no arbitration against Clause 22.0's 5% security and a Delhi-seated GCC arbitration, leaving document precedence to carry more commercial weight than the headline tonnage.
Odisha Coal and Power Limited caps Tangardihi North's exploration phase at Rs 25 crore and ranks bidders on 397 million tonnes
8A Phase I quotation above the ceiling is reduced to Rs 25 crore rather than improving the evaluated position, while the Base Mining Charge is multiplied across a comparison quantity that detailed drilling has yet to confirm.
8Around 14,000 metres of exploration sits inside the same contract whose 25-year operating commitment depends on what that drilling finds.
WAPCOS gives three masked bidders ten days to respond to a five-year strategy mandate classified as an emergency
8The Rs 1.50 crore QCBS assignment weights technique at 80%, with 60 of 100 technical marks resting on named expert CVs and a presentation.
8Arbitration and consensual ADR are excluded entirely, leaving employer-controlled internal review, mediation and Delhi civil courts as the dispute route.
Gujarat Energy Transmission Corporation Limited's Navsari cable tender lists 193,186 metres of 66 kV cable against a 24,218-metre route survey
8The Rs 98.48 crore item-rate package also carries six foundation categories each showing eight tower foundations while the total tower-erection quantity is also eight, leaving the BOQ open to interpretation before pricing.
8Amendment no. 1 moves delay damages from the delayed portion to 0.5% of the entire contract price per week, capped at 10%, or roughly Rs 9.85 crore plus GST.
Maharashtra State Electricity Transmission Company Limited puts a Rs 73.19 lakh breaker overhaul across 12 substations without a breaker count
8The notice covers spares supply and complete mechanism overhauling of CGL-make 132 kV breakers at sites spanning both 132 kV and 220 kV yards.
8Mechanism types, spare schedules, outage duration, testing protocol, warranty and completion period are not specified in the document, leaving the estimate impossible to test against actual scope.
NTPC Renewable's 600 MW Anantapur wind tender gives bidders a week more to price but no way to ask why
8Corrigendum No. 1 pushed submission to 22 September 2026 while leaving the 1 September query deadline untouched, so late-discovered ambiguity has nowhere formal to go.
8With Rs 50 crore bid security, ten-year comprehensive O&M and roads, pooling and evacuation all outside the WTG package, the unresolved issue is who carries commissioning delay at the boundary.
JdVVNL rewrites the BOQ a third time and swaps Bikaner territories between two RDSS packages
8Corrigendum 3 moved Dungargarh and Nokha into TNTW-796 while DD-I, DD-II and Khajuwala travelled the other way, settling the value at Rs 119.89 crore — a net movement of about 0.1%.
8That small headline change can conceal much larger line-item additions and deletions, which is precisely what bidders repeatedly queried before the revision.
AEGCL's Khumtai 400kV GIS tender carries a Rs 50 lakh EMD contradiction and a 12-month schedule gap
8The invitation and ITB 2.37.1 set two years for completion while SCC 8.2 requires 36 months, and the EMD reads Rs 5.5 crore in numerals against "Rupees Five Crore only" in words.
8Turnover and financial-resource thresholds carry the same numeral-versus-wording conflict, making eligibility itself uncertain before the 12 October closing.
GETCO's Viksit Gujarat @2047 adviser tender records two turnover thresholds twenty times apart
8The GeM page states Rs 48 crore while the RFP and buyer-added conditions demand Rs 1,000 crore, and submission and opening dates differ by a day between portal and document.
8With GST treatment also contradicted between two clauses, the tender risks producing technically incomparable bids priced on different assumptions.
GETCO's Rs 210.62 crore Bharuch cable package lets each approved OEM back only one bid
8Amendment-I restructured qualification into OEM, nominated-OEM and two-member JV routes, then barred any firm from appearing in different roles across competing bids.
8The contest may therefore be settled by early OEM alignment rather than by how many erection contractors can qualify.
KPTCL's Rs 131.92 crore Byadagi package reaches the market tagged as a computer lab
8The portal lists bid validity as 90 days against the signed document's 180, describes the scope as "Setting up of Computer Lab", and keeps the clarification window open 30 minutes after bids close.
8A Clause 3.2(e) heading referring to a 100 MVA transformer against a 160 MVA requirement compounds the risk of divergent qualification readings.
RRVUN cuts the coal experience bar by 6.25% and then quietly extends group credentials to technical qualification
8Amendment-I lowered the single-contract threshold from 1 million MT to 9,37,500 MT and admitted IPP supplies; Corrigendum-I then widened 100%-owned parent or subsidiary reliance from financial to both technical and financial PQR.
8JV and consortium participation stays barred, so the widening favours tightly held corporate groups rather than assembled bidding alliances.
WBSETCL's Sadarghat composite package republishes its evaluation clause with a broken cross-reference
8Amended ITB 28.2 now reads "DP = Differential price calculated according to0", severing the link to the calculation method in ITB 28.4, while the reverse-auction cross-reference disappears entirely.
8Reverse-auction clause 9 separately dispenses with additional security where L1 is "less than 20% of the estimated cost" — a literal reading that relaxes protection at the lowest prices.
NHPC raises generator efficiency loading 20.6% on the Rs 641.11 crore Uri-I Stage-II package
8The turbine equalisation rate moved from Rs 8.32 lakh to Rs 8.74 lakh per 0.1 percentage point, while the generator rate jumped from Rs 21.64 lakh to Rs 26.10 lakh.
8Cheaper machines with weaker guarantees can now lose their price advantage at evaluation, even before PLCC relocation and revised cooling-water scope are priced.
WBSETCL's 68 km Salboni 400 kV line tender resolves a 60 mm creepage conflict but keeps ROW with the contractor
8The pre-bid response directed bidders to the technical specification's 430 mm over the BOQ's 370 mm and issued a revised BOQ, while fixing conductor diameter at 28.62 mm and sag at 15.93 m.
8Tower-footing compensation, trees, crops and access remain contractor-priced with no escalation for court-driven delay, and the 24-month clock survives two extensions.
RRECL's 201 MW solar tender slips 63 days and then adds a letter of credit
8Four corrigenda moved submission from 14 July to 15 September 2026 while the nine-month commissioning obligation and 25-year term stayed fixed.
8The pre-bid addendum inserted a revolving monthly LC and replaced the client's first charge over liquidated assets with priority application of proceeds — a lender accommodation whose value depends on the still-ambiguous "Cover-1 & Cover-2" opening language.
HPSEBL extends its Rs 3.72 crore Kinnaur-Spiti PMC tender for the fifth time without explaining why
8Corrigenda I to V added 64 calendar days to both submission and technical opening while leaving scope, staffing, securities and the 246 man-month deployment untouched.
8The unresolved question is award mechanics: a 70:30 QCBS formula and an English e-reverse auction sit in the same document with no stated hierarchy.
GETCO shifts LD on the Rs 224.80 crore Dholera-II GIS package from the delayed portion to the whole contract
8SCC clause 41 now calculates 0.5% per week on the full contract price capped at 10%, recoverable across GUVNL group contracts, while requests to extend 30 months to 34 and to substitute PEB for RCC were refused.
8A local civil or commissioning slip can now generate package-wide exposure on a site carrying saline conditions, seismic zone 5 and cast-in-situ piling.
MePDCL splits Khasi Hills into six lots and hands four of them to one contractor
8The Rs 120.42 crore award concentrates Rs 82.12 crore, or 68.2% of L1 value, with a single firm across Lots 1, 3, 5 and 6.
8Lot 3 reached financial opening with one responsive bidder out of seven, leaving no L2 comparator to test whether that price was competitive at all.
NHPC rewrites force majeure and idling-cost recovery across both its hydro E&M packages
8The revised GCC Clause 37 adds terrorism, qualifying strikes and pandemic spread while removing the magnitude-7 earthquake threshold and express treatment of bandhs, lightning and unprecedented floods.
8Annex-A now caps compensable idling through a formula using 5% of composite contract price, with a 2% sub-cap on miscellaneous establishment expenditure and extended-warranty recovery at 2.25% per annum.
RVUN's Rs 1,125 crore coal tender is tagged emergency procurement without naming which rule applies
8The portal cites Rule 40(1), 43(6) or 43(7) but does not identify the provision invoked or the factual justification, and the original window ran just seven days from publication to submission.
8Coal grade, sampling agency, delivery duration, LD framework and PBG terms are absent from the published notice, leaving the commercial risk difficult to quantify before bidding.
WBSETCL's H1-elimination auction meets a 10% security stack that runs five years past commissioning
8The Sadarghat package removes the highest offer only where four valid price bids exist, so two or three qualified bidders all proceed to the auction intact.
8The winner must then carry separate 10% guarantees on GIS equipment for three years and transformers for five from the Taking-Over Certificate, with formal joint ventures barred.
APEPDCL grants 24 extra days on its Rs 143.32 crore SCADA package without touching a single execution obligation
8Three corrigenda moved submission from 1 September to 25 September 2026, but the 18-month implementation period, five-year FMS and 10% performance security stayed exactly where they were.
8What the extensions really concede is preparation time for a bidder pool that must satisfy two separate qualification streams and assemble OEM authorisations before it can quote.
RVPN's Rs 83.38 crore Shiv Enclave GIS package makes unlisted work the contractor's problem
8A 132/33 kV, 2x80 MVA GIS substation with a 4 km LILO cable arrangement carries a 545-day execution period and a 10% performance security, extended eight days by Corrigendum No. 01.
8The clause that matters is GCC 3.2, which absorbs reasonably inferable items into the contractor's scope without automatic additional payment.
NTPC puts 2,184 man-months of construction safety at Telangana Stage-II behind a 52-month firm-rate contract
8The consultant must field 47 personnel, run a 24/7 IP-camera control room and approve other agencies' JSA/HIRA documents across a 3 x 800 MW build.
8The commercial risk is not the Rs 5,000-per-day non-deployment penalty but firm rates through a unilateral 12-month extension, 5% retention and no interest on deferred payment.
TNPDCL asks for 5,000 distribution transformers while the protected BOQ shows a quantity of one
8The M-256 tender covers 5,000 units of 100 kVA, EEL-2 aluminium-wound transformers with a Rs 1,00,20,500 EMD, a ±25% quantity variation and a 60-month guarantee.
8The BOQ's "1.0 No." line and its residual civil-work text sit inside a spreadsheet bidders are forbidden to alter, converting a template artefact into a responsiveness risk.
JdVVNL's Rs 119.89 crore Bikaner package carries two completion periods inside the same document
8The NIT records eight months for supply, erection, testing and commissioning while Appendix 4 records nine, both against an unchanged nine-month total, with the portal and NIT also differing on the 22 September opening time.
8Performance security is quoted at both 180 days and 30 days beyond the defect-liability period, and guarantee charges turn on which one controls.
Bidder queries force JdVVNL to reopen the BOQ on its Rs 91.47 crore Bikaner DD package before bids close
8Corrigendum-3 supersedes the 14 August NIT, revising the BOQ, specifications, estimate and EMD to Rs 1.83 crore without publishing the superseded figures for comparison.
8The sharper problem is composition: JdVVNL's own estimate puts supply at 79.6% of value while ITB 37 treats supply above 70% of the quoted price as front-loaded and demands additional security.
Phalodi package climbs 0.7% across two corrigenda, with the entire increase landing in supply
8Between Corrigendum-I and Corrigendum-3, supply rose by Rs 38.89 lakh while erection fell by Rs 1.21 lakh, taking TNTW-792 to Rs 97,59,20,302.39 and EMD to Rs 1,95,18,407.
8No item-level change register accompanies the revision, and the portal and SBD still disagree on whether technical bids open at 11:00 am or 5:00 pm.
Jaisalmer's Rs 121.13 crore RDSS package stacks four separate security layers on one contractor
8Beyond the 10% performance security sit abnormal-bid security, supply-unbalancing security and a further 10% guarantee on major equipment running to 36 months after completion.
8With 77.4% of the estimate in supply and no pre-bid meeting scheduled, bidders must also decide whether the EMD instrument reads Rs 2,42,25,139 or Rs 2,42,25,140.
JVVNL withdraws the vendor-registration security waiver as it tenders 25,000 CSP transformers
8Appendix-A replaces EMD and SBG references with Bid Security and removes the relaxation that JVVNL registration alone previously conferred, on a Rs 16,025 lakh, 16 kVA programme.
8The allocation formula caps L1 at 20% and spreads half the quantity across other firms, making past repair performance an eligibility filter rather than a reference note.
Navkar Global Infra takes NTPC Mouda ash transport at 47.6% of base rates against 23 other accepted bidders
8The accepted percentage produces a Rs 142.80 crore contract value, a 52.4% discount to the Rs 300 crore estimate and far past NTPC's own 10% abnormally-low threshold.
8Section C nonetheless caps each shortlisted bidder at Rs 50 crore cumulative and guarantees no purchase order at all, separating the headline award from bankable work.
Churu package falls Rs 7.45 crore in Corrigendum-3 after rising in Corrigendum-1 TNTW-798 moved from Rs 132.60 crore to Rs 133.13 crore and then down to Rs 125.67 crore, with supply cut 6.5% against erection's 2.0%, and no clause-level reconciliation published.
8Bidders have ten calendar days from republication to reprice, while the portal and corrigendum differ by Rs 60 on an EMD that decides envelope-one compliance.
UJVN Limited raises its BESS tariff ceiling 3.8% but leaves 165 MWh outside VGF support
8The 90 MW/225 MWh Chilla project draws VGF on only 60 MWh, while the ceiling capacity charge moves to Rs 3,30,400/MW/month against the Rs 3,96,747 bidders sought.
8After 12 years the entire asset transfers to UJVN Limited without consideration, so residual value has to be recovered inside a capped tariff stream.
For daily newsletters and other free services, fill in your details: