8Arunachal's Pathar Camp award carries two prices for the same bid, 19.0% apart Financial-opening proceedings record Techno Power at Rs 98.75 crore and Shyam Steel at Rs 119.57 crore; the BOQ comparative chart records Rs 82.98 crore and Rs 100.48 crore — the same 19.0% gap for both bidders. The award settles on the lower BOQ figure. Three of five bidders never reached price opening, falling on unsigned pages, missing OEM authorisations and EHV-licence gaps, leaving a 21.1% spread between the only two survivors. The portal and committee proceedings also cite two different NIT numbers for one tender ID.
8AVVNL's 110 MW rooftop tender now allocates a multi-lot winner's cheapest circle first, not its biggest Corrigendum No. 2 replaces descending lot quantity with ascending quoted price per unit as the allocation sequence — so a bidder that is L1 across several circles can have its highest-priced win displaced once the 20,000-consumer cap is reached. Turnover is tested at 30% of the total value quoted, making a five-lot bid a balance-sheet decision. Nineteen of the 25 technically admitted bids arrived only after the original deadline.
8Ukwa mine tender sets quantity variation at ±20% in one document and 25% in another The technical specification says "+/- 20%"; the GeM option clause permits 25% at issue and a further 25% post-award — a five-point gap across a four-year contract committing nine LHDs, 36 face drills and nine shotcrete machines. The GeM summary also reads "Arbitration Clause: No" while clause 48 sets out a sole-arbitrator regime with Nagpur jurisdiction. Corrigendum C5 declares itself to supersede all prior buyer-added terms.
8PVVNL's conductor tender qualified one bidder "as trial" while simultaneously coding it rejected The evaluation record shows "Rejected-Technical" alongside the remark "Techno Commercially qualified as trial" for the same participant — a status distinct from the seven bidders marked qualified as regular. What trial standing entitles that bidder to, whether its price bid opens, and how trial converts to regular are nowhere defined. Seven of nine reached the 6 August price opening on regular terms.
8JdVVNL's 110 MW rooftop tender makes MNRE guidelines override its own specification Clarification No. 1 states that where the tender's material specification conflicts with MNRE requirements, MNRE prevails — a compliance baseline that can move during a ten-year O&M term. The same package flips lot allocation from quantity-first to lowest-unit-price-first, swaps meter standard IS 14697 for IS 13779, and holds half the 10% performance security to year five and the balance to year ten.
8JVVNL's 18-lot rooftop tender lets a bidder's own price ladder decide which circles it loses Corrigendum No. 1 allocates successful lots in ascending order of quoted unit price, with a lottery in the Chief Engineer's chamber where price and lot quantity tie. Turnover is now tested against the lots actually quoted rather than the full Rs 627.50 crore estimate. The e-procurement record and the specification also carried different original technical-opening times — 3:00 pm against 5:00 pm — before the seven-day extension overrode both.
8NTPC's Rs 200 crore Kaniha ash contract ended with five identical contracts at 10.58% of base value All five awardees hold contracts of Rs 21.156 crore — a 0.0% spread across L1, L2 and L3 — because ranked bidders were invited to match the L1 price. The panel includes L1 through L4 and, unexplained, L9; L5 to L8 do not appear. Clause C's formula for calculating each bidder's cumulative cap against a five-member panel doesn't reconcile with the identical full-value contracts actually issued. Corrigendum C2 fixed a penalty clause that cross-referenced a nonexistent "Clause 16."
8UPNEDA's 40,000-light tender can extinguish a quarterly AMC payment if district verification doesn't happen in time The amended Clause 8.18 requires live RMS data to be verified by the district project officer each quarter and uploaded to RESIMS; failure causes that quarter's payment to lapse with no later claim — against a 15% retention released at 3% a year over five years. Corrigendum-1 separately disabled equalisation charging, which the original spec had mandated every 30±2 days on an LFP battery. Sixteen of 22 bidders cleared technical evaluation.
8BHEL's Bandhabal ASU tender doubled the power baseline used to load bids, from 400 kW to 800 kW The same amendment nets turbine-generated electricity against consumption before applying NPV loading over a 25-year life — so integration, not gross demand, decides evaluated L1. Qualification was cut in the opposite direction: the reference threshold fell from 1,000 TPD oxygen to 500 TPD, the window widened from 10 to 15 years, and required operating history halved to one year. Five closing-date extensions. A bidder's warning that simultaneous LOX and LIN vaporisation would breach the 10 TPH steam cap drew a request for figures, not a ruling.
8NHPC raised the generator performance coefficients on its Rs 641.11 crore Uri-I tender by 20.6% Both the bid-equalisation rate and the shortfall deduction moved from Rs 21.642 lakh to Rs 26.099 lakh and Rs 86.565 lakh to Rs 104.396 lakh — turbine figures rose 5.0%. Corrigendum No. 4 also replaced the cooling-water and HVAC chapters outright, rebased escalation indices from 2011-12 to 2022-23, added partial acceptance, and introduced a contractor-change route that pays nothing for rejected proposals. Deadlines have moved 32 days.
8JVVNL's 25,000-transformer tender withdrew the bid-security relaxation its own registered vendors previously enjoyed Appendix-A removes the Nigam-registration concession and resets performance security at 5%, with additional security where a bid falls more than 15% under estimate. L1 gets only 20% of the volume under the allocation ladder; 50% can go to firms outside the top four. Prior execution acts as a gate — a supplier under 50% delivered on an earlier order may find its bid unopened. Schedule-X prints a June 1 submission deadline for a tender published in August and closing 1 September.
8GETCO's Rs 94.87 crore HTLS tender pays more to bidders who refuse its advance Amended Clause 86.0 splits payment by financing choice: 90% progressive supply payment without the advance, less with it, and 80% versus 70% on erection RA bills — the advance carrying SBI MCLR interest against a 110% BG. Conductor losses are capitalised at Rs 1,60,000 per kW before reverse bidding starts, so the lowest percentage isn't automatically L1. RoW compensation moved to GETCO; RoW fieldwork stayed with the contractor. Security validity is written as "25 Months (60 Months + 01 Month)."
8CSPDCL's Atal Nagar batch bars Class III contractors from its Rs 1.37 lakh package while admitting them to the Rs 1.76 lakh one Only the 33KV isolator replacement at Mungi substation carries the tighter classification — the gate is voltage and operational risk, not value. All five packages share one deadline, one completion figure recorded simply as "30" with no unit stated, and a stated opening time identical to the closing time.
8TANTRANSCO's Rs 271.79 crore GEC-II substation limits escalation to transformers and reactors, and only on 90% of their cost Everything else — civil works, erection, freight, insurance, switchgear installation — stays firm across 24 months that expressly include rainy seasons, with the transformer adjustment itself capped at ±30%. Delay damages start softer than usual at 0.10% weekly, but can be calculated on the entire contract price where partial works can't be beneficially used. Unresolved level-3 ESHS non-conformity cuts interim certificates 33.3%, then 66.6%, then 100%. Guarantee obligations appear as 36 months in the payment documents, 60 months in the technical requirements and five years for ICTs in the Particular Conditions.
8APEPDCL called a hybrid pre-bid meeting for its Rs 143.32 crore SCADA tender one day before queries close Corrigendum-1 fixes the meeting for 18 August; the RFP keeps 19 August at 17:00 as the query cut-off, leaving roughly a working day to convert answers into formal clarifications on OEM responsibilities, field interfaces and FMS economics. The portal describes the meeting as offline while the corrigendum provides hybrid attendance. The BOQ separately requires five-year FMS charges to be at least 20% of SCADA project cost, with the annual figure identical across all five years.
8UPPTCL's conductor tender demands 10% performance security in the SBD and 5% on GeM — and says the SBD wins ITB 41.2 requires a CPBG of 10% of contract price including GST; the GeM page shows a 5% ePBG for 30 months, while BDS ITB 30 expressly gives the SBD precedence over GeM. The turnover threshold diverges the same way: Rs 224.82 crore in the BDS against Rs 56.20 crore on the portal. Positive IEEMA variation stops once supply runs past schedule even with an extension granted; negative variation continues.
8TPCODL halved its own GCC delay penalty on a Rs 44 crore substation conversion, then extended the liability tail to a decade Tender clause 7.1.7 sets LD at 0.5% weekly on unfinished work capped at 5%; the GCC position is 1% weekly on executed value capped at 10%. In exchange, the CPBG stays alive across a 78-month architecture and a five-year latent-defect warranty starts only after the 60-month guarantee ends. Clause 2.2 states there is no guarantee on quantity of job, with release orders issued only after substation-wise joint survey. Turnover requirement: Rs 100 crore against a Rs 44 crore estimate.
8OPTCL's Rs 102.39 crore Narendrapur cable tender can't agree with itself on how many stages it has The IFB describes a "single stage two part system"; the portal field reads "Stage: Two Stages" — a distinction that changes submission and evaluation mechanics for a bidder committing Rs 1.02 crore of EMD. The document-availability window also differs: the IFB closes it 6 July, the portal 8 July at 12:00, with tender closing at 14:00 the same day. The package bundles 132 kV underground cable with bay extensions at two live substations.
8JVVNL's 37-substation RDSS tender states nine months for completion in one part and 12 in another Part 1 gives one month for survey plus eight for execution; SCC GCC 8.1 and 8.2 give three months for commencement inside a 12-month total — and the contract hierarchy puts Part 3 above Part 1. The second 30% supply payment is conditioned on commissioning "a minimum one cluster," defined by electrification of rural households, inside a package that procures 33/11 kV substations. The technical specification also refers to supervision at substations "in state of Uttar Pradesh."
8RVPN's Dholpur line tender lists a bid amount of Rs 1.00 against a Rs 94.48 crore turnover requirement The portal field is economically meaningless beside a Rs 31.49 crore liquidity threshold and a 50 km single-order 400 kV execution test. Subsidiary, associate and subcontractor credentials don't count, and JV bidding is marked not applicable. OPGW installation runs predominantly live-line, with tower structural analysis and any resulting strengthening at no additional cost to the employer, plus a 99.9% availability target requiring a seven-person certified gang, a jeep and a Tata 407.
8NTPC REL extended its 540 MW Anantapur wind tender a day after the original deadline had passed Corrigendum-2 carries a 5 August timestamp; the original bid receipt closed 4 August, and the applicable deadline now reads 17 August. A WTG manufacturer may use only one qualifying route and, under the association route, back only one bidder — multiple participation can void all affected bids. Land acquisition, ROW, the external EHV line to the ISTS substation and ten years of comprehensive O&M all sit inside contractor scope. A 540 MW quote requires Rs 714.04 crore of average annual turnover.
8MPPMCL's 625 MW storage tender now closes six days after the opening date printed in its own schedule The portal header applies 10 August for bid receipt while the NIT table still shows the tender opening event on 4 August and document procurement closing 30 July — an 11-day extension layered over legacy dates never rewritten. Corrigendum-1 and Addendum #2 have both issued. Bid security runs Rs 2.20 lakh/MW across a BOO structure with VGF support and a reverse auction at the end.
8SJVN's 265 MW Haryana storage tender shows an addendum issued and no corrigenda at the same time Addendum #1 is flagged on the tender page while the portal separately records "No Corrigenda Issued," and the clauses it supplements aren't identified anywhere at NIT level. EMD scales with capacity at Rs 2.40 lakh per MWh rather than sitting as a fixed sum, and the Rs 15 lakh processing fee plus GST applies to each project. Degradation, augmentation, availability guarantees and PBG terms all sit outside the published notice.Details
8India has certified 78 green-steel units and advanced production-linked incentives for specialty steel, creating formal routes for cleaner and higher-value output. The policy architecture is moving, but the disclosed record still does not quantify how much certified low-emission steel has actually been produced or sold.Details
8BCCL started commercial operation of the 2.0 MTPA Bhojudih washery and monetised the 2.0 MTPA Dugda washery through a long-term operating agreement. Those projects could lift domestic washed-coking-coal supply, but profit after tax fell from Rs. 1,240.19 crore to Rs. 128.28 crore as production, offtake and costs moved against the company.Details
8Coal India spent Rs. 19,607 crore and commissioned the 100 MW Patan solar project while expanding into critical minerals and a proposed 1,600 MW thermal venture. The diversification advanced, but coal production slipped to 768.19 million tonnes and missed the company’s 937 million-tonne target by 168.81 million tonnes.Details
8PFC ended 2025–26 with Rs. 5.80 lakh crore of loan assets, Rs. 20,051 crore of standalone profit and a net NPA ratio of 0.15%. Asset quality strengthened, but sanctions fell to Rs. 2.86 lakh crore from Rs. 3.61 lakh crore, making the pace and quality of new commitments the next growth test.Details
8Inox Wind reported an order book of about 4.4 GW in July, including a 500 MW firm group order and a 200 MW NLC award. The pipeline is large, but first-quarter profit fell 34% and management’s equipment-sales pivot has yet to show the promised improvement in later quarters.Details
8Premier Energies raised quarterly profit by 53% and opened 5.6 GW of module capacity, expanding the manufacturing base behind its order pipeline. The new factory changes the company’s scale immediately, but earnings quality depends on utilisation, cell supply, pricing and sustained conversion of capacity into sales.Details
8Hitachi Energy India reported sharp growth in orders and revenue while retaining Rs. 1,841.66 crore of QIP proceeds as unutilised at quarter end. The balance sheet can fund expansion, but the investment case now depends on converting record demand and idle capital into delivered capacity, cash and margins.Details
8Amazon Data Services’ proposed Mumbai campus would require 473 MW of power and a large diesel-backup fleet across a multi-building development. The scale makes it a major new load, but the committee recommendation is not final clearance, grid sanction or proof of a contracted cleaner supply.Details
8CESC Green Power’s 3 GW solar-cell proposal has environmental clearance for its first phase at Jewar, not for the entire factory. The approval moves a major manufacturing investment forward, but Phase II, construction permissions and operating execution still sit outside the cleared gate.Details
8A Vemagiri bus fault removed about 1,150 MW of Andhra Pradesh demand for 14 minutes while overloaded transformers at another station also tripped. Supply returned quickly, but the scale of the loss shows how a local fault and stressed parallel equipment can combine into a statewide reliability event.Details
8Gujarat’s renewable network recorded repeated single-path events, including losses of about 800 MW and 540 MW, across the month’s grid-event register. Individual protection operations may have worked, but the recurrence shows that several generation pockets still depended on evacuation arrangements that did not survive one credible failure.Details
8During an approved shutdown of the BTPS–Rangia-I line, all six affected load centres were being supplied through the Sonabil–Depota and Sonabil–Ghoramari paths. Both lines tripped at 15:04, cutting about 130 MW until the network was restored, and turning a planned outage into a direct redundancy failure.Details
8A measuring-card failure blocked two poles carrying about 2,680 MW and triggered Punjab’s feeder defence scheme, while the state’s recorded demand changed by about 252 MW. Protection limited the disturbance, but the gap between transfer loss and demand response shows why the event cannot be described as 2,680 MW of consumer load shedding.Details
8Thirty plants were at critical stock even though total coal holdings reached 37 million tonnes, because the monitored fleet held only 60% of its normative requirement. The national pile therefore concealed plant-level exposure where location and delivery, not aggregate tonnes, determined security.Details
8CEA counted 55,674 MW unavailable across planned, forced and other outage categories while monitored stations still produced 98.2% of programme. The near-target output shows that the remaining fleet carried the day, but the outage burden narrowed the buffer against another large failure.Details
8India’s grid frequency left the prescribed band for 21.1% of the day even as the daily average stayed near 50 Hz 8Eastern grid operators cut day-ahead demand error from 7.53% to 1.04% intraday - but only after the operating day began 8Every interstate schedule will carry a 3.62% transmission-loss adjustment this week - but the national factor says nothing about any single project’s efficiency 8Odisha’s hydro stations reported 18.6646 MU, but duplicated rows prevent the table from proving a larger fleet total 8PXIL’s real-time market touched the Rs. 10,000/MWh ceiling - then recorded no trades across the next five reports 8Grid-India’s next security-constrained schedule starts with low-cost generators - but the dispatch plan becomes real only if those units run in the assigned blocks 8Late SCED payments in the eastern region will now attract daily interest - turning settlement delay into a rising cost for every entity shown as payable 8Two states capped reverse-auction bids at Rs. 10,000/MWh - while Rajasthan’s notices left bidders without a ceiling 8POWERGRID’s proposed Mandsaur licence change has entered formal hearing - but the company cannot use the revised terms unless CERC approves them 8Hexa Climate has finished arguing for connectivity relief over land documents - but the project remains exposed until CERC delivers its reserved order 8Gadag Power’s 190 MW solar project has reached the order stage - but its deadline extension and transmission-charge waiver remain undecided 8ReNew’s 73 MW Solapur project keeps interim protection - while final connectivity relief waits 8A new party and affidavit have widened the Tumkur-II transmission case - but they deliver neither the licence nor the tariff the project ultimately needs 8Lakadia-B seeks to push its transmission deadline to November - but force majeure still needs regulatory acceptance 8Solar developers say inverters should qualify for GST-change compensation - but CERC has not decided whether the equipment fits the claimed tax category 8NTPC REL commissioned six more inverters and moved the project forward - but tariff, tax and deadline claims still determine what the delay will cost 8India has opened accreditation for carbon-market verifiers - but no agency can validate credits until BEE completes the approval process 8PSPCL has taken smart-meter reconnection out of local hands - but its order gives no timeline or count for consumers waiting to be restored 8Punjab’s discom wants another settlement window for defaulting consumers - but the regulator is asking why the existing recovery mechanism was not used first 8Haryana ordered utilities to answer renewable-supply claims on a deadline - but kept deviation-settlement relief outside the interim order 8KEC’s CRISIL ESG score rose by five points - but the filing shows no change yet in borrowing cost, orders or operating performance 8Refex’s promoters plan to move 30.94% of the company within their own group - changing the holding structure without bringing in an outside buyer 8Sarda Metals gained Four Star Export House status - but investors still lack any disclosed export, revenue or incentive benefit 8Nuvoco and Nu Vista lost their current appraisal path because mandatory mapping files were missing - forcing both limestone proposals back before any merits decision 8Svaryu Energy asked to surrender its Category V interstate trading licence 8NLC asked CERC to determine the 2024–29 input price for Barsingsar lignite 8AK Renewables wants financial-close and commissioning deadlines aligned with delayed connectivityDetails
8Coal-gasification bidders won flexibility on products and technology - but every project must clear the approval gate before an award can be issued 8Amanthin’s Mumbai data-centre expansion seeks 200 MVA and 123 large generators - but its Rs. 6,670 crore plan remains a conditional recommendation 8Mevasa’s bauxite proposal gained an EAC recommendation - but road strength, dump stability and wildlife safeguards remain conditions on the mine 8Jhamarkotra’s phosphate expansion could not clear appraisal - because two foundational land and survey records remain unresolved 8Star Cement can study a 12 MTPA limestone mine - but the ToR does not permit mining 8Hindalco and Ambuja lead a 13-project industrial agenda worth watching - but every proposal still awaits the committee’s merits decision 8SECI is searching for dependable CO? supplies for green urea and methanol - but the exercise offers no tender, buyer or financial commitment 8TERI says solar heat can produce steam for about Rs. 1.20 a kilogram and pay back quickly - but industry still lacks the mission needed to overcome upfront risk 8Anant Raj’s Sonipat IT park would require 26 MW and 36 MVA of diesel backup - but its proposed solar capacity equals only 3% of sanctioned load 8Radiance’s Gurugram cyber park cut its planned load to 8.947 MW - but still pairs the project with large diesel backup and only 269 kWp of solarDetails
8Vikram Solar shipped more modules and lifted revenue 38% - but EBITDA nearly halved as margin fell to 8% 8Northern Coalfields selected only 545 people for 906 apprentice places - leaving 361 training positions unfilled 8Quality Power’s Rs. 19,455 million order book backs strong Q1 profit - but two capacity projects are still in installation and trial stages 8Reliance’s two Jamnagar battery units represent Rs. 3,162 crore of investment - but no ACC incentive had been claimed 8India counted 52,718 EV charging stations - but the government cannot say how many are fast chargers 8GK Energy crossed Rs. 15,325 million of annual turnover - but its Rs. 541 crore order book still has to convert into commissioned systems 8Batteries generated almost two-thirds of HBL Engineering’s quarterly segment revenue - concentrating growth in one business while electronics supplied the balance 8Bajel won a 765 kV interstate line worth at least Rs. 400 crore - but disclosed only a band and a 33-month delivery clock 8Refex can halve a solar loan exposure under a proposed settlement - but payment and legal withdrawals are still conditions 8L&T won ONGC work on subsea pipelines and four offshore platforms - but the Rs. 5,000–10,000 crore value band hides the exact contract economics 8GR Infraprojects led a Rs. 91.60 crore Varanasi logistics-park bid - but a 45-year concession starts with contract and finance risk 8Bajel plans to nearly double tower capacity even as quarterly revenue fell - betting Rs. 170 crore that margins can recover 8Inox Green’s profit rose 86% and a 4.5 GW wind-service acquisition cleared the tribunal - but the portfolio is not fully owned or consolidated yet 8Ola Electric cut operating losses but reversed a Rs. 57 crore provision without ministry approval - keeping the audit qualification alive 8Panasonic restarted dispatches after its Pithampur fire - but the damage is still unpriced and a battery-waste obligation remains unprovided 8NLC’s group generation rose 25% - but profit before tax increased only 9.76% 8IMP Powers multiplied quarterly revenue but still lost money - while auditors say old receivables and assets may be overstated 8Urja Global’s auditors flagged Rs. 34 crore of unreversed tax credits - alongside Rs. 42 crore of ageing receivables 8Anboto Solar says its supply deadline slipped because the ISTS substation was not ready - but status quo protects the project only until CERC decides the delay claim 8Power Mech proposed up to one million employee options at 10%–25% of market price - but shareholders and regulators still have to approve the plan 8Urja Global’s board opened a route to raise up to $500 million - but shareholders have not approved it and no instrument or price has been fixedDetails
8Load despatch centres seek 85% provisional fee billing - but CERC has not authorised the cash flow 8BALCO faces a Rs. 48 crore damages claim from TANGEDCO - but liability is frozen behind a pending review 8Korba Power seeks Rs. 36.88 crore for ash transport and surcharge - but none of it has been awarded 8GETCO listed 800 possible renewable connections - but warned that planned substations may never arrive 8Government support erased Andaman’s approved revenue gaps on paper - after the regulator found Rs. 1,613 crore across two years 8Haryana discoms want to postpone monthly fuel adjustments and recover them with interest - but the regulator demanded the full backlog first 8Two renewable projects want their connectivity clocks moved because the Koppal-II network may not be ready until 2027 - but neither extension has been granted 8Two discoms say Kreate Energy failed to return banked power and want its trading licence revoked - but an appellate status-quo order has frozen the regulatory hearing 8PSPCL approved a 15% wage rise across PESCO worker categories - but the new rate raises the utility’s outsourced labour bill before efficiency gains are known 8PSPCL can now cancel energy bills and optionally reverse late-payment interest - but larger corrections require progressively higher approval 8Goa–Tamnar wants its transmission deadline extended and force-majeure costs compensated - but the regulator has not accepted either claim 8Osmanabad Solar wants four months of 2022 power bills paid - but CERC has not ruled on who must correct the scheduling record 8IL&FS Tamil Nadu says Section 11 benchmark energy charges remain unpaid - but CERC has only opened the merits hearing 8KSK and southern discoms remain locked over 2013 capacity and transmission charges - but the 13-year-old disputes still have no merits ruling 8NHPC wants consumers to fund a 1997 pay-anomaly correction ordered in 2024 - but CERC has not admitted the cost to tariff 8DNH and Daman & Diu seek legacy gas, capacity and imbalance charges for 2006–12 - but the reopened dispute has no liability finding 8SEIL seeks fixed charges for 150 MW it says was available - but Andhra counterparties have not been ordered to pay 8SEIL wants June–July 2022 invoice deductions repaid with surcharge - but CERC has not decided that Telangana’s withholding was wrongful 8Adani Solar says long-term transmission charges are not its liability - but CERC has not allocated the costDetails
8IEX day-ahead power fell 45% in six days - but partial August 10 data cannot be used to extend the decline 8Suratgarh’s first two units breached both particulate and sulphur limits - turning monthly averages into a compliance warning 8India’s coal benchmark jumped 6.2% in June - with non-coking prices rising faster than coking coal 8A WRPC correction cut Pachora QCA’s DSM payable by 82% - while Bhuj accounts still showed liabilities above Rs. 3 crore 8Western interregional DSM revisions leave Rs. 20.19 crore payable - after a Rs. 75.65 crore southern receivable offsets larger eastern and northern duesDetails
8India’s five regions met their reported peaks without a shortage - but the eastern grid still ended the day 0.08 MU short 8The northeast’s Assam corridor breached its transfer limit for 6.8 hours - while the region’s other monitored corridors stayed within theirs 8Wind and solar delivered 82,670 MW during daylight - a major operating contribution that the available reports cannot show was sustained beyond one day 8Four 400 kV line trips hit the Gazuwaka area across two days - but the records do not show a matching consumer-supply loss 8Major generating units will remain under overhaul into September - narrowing the available fleet even though the separate outage registers cannot be added into one simultaneous total 8Two more Champa–Kurukshetra HVDC poles blocked after reactive-power control malfunctioned - but Haryana recorded no corresponding demand loss 8Telangana’s stored hydro energy was almost half last year’s level - tightening the buffer without proving an immediate shortage 8CERC reset tariffs for two Delhi transmission corridors - giving the assets regulated revenue but limiting recovery to approved capital and annual charges 8Bihar’s proposed grid code brings storage, reserves and cyber rules into one framework - but every obligation remains open to consultation 8POWERGRID kept transmission availability at 99.80% across a vast network - but investment delivery remains the test behind its quarterly scale 8A current-transformer failure at Fatehgarh-III blacked out nine renewable substations and cut 584 MW - after a bus coupler failed to isolate the fault 8A fault on one Chandigarh supply circuit pulled down the second and cut about 195 MW - exposing the risk behind two lines that did not behave independently 8One transmission fault removed 680 MW of Himalayan hydro generation and 131 MW of load - because cascading protection isolated three plants 8Jammu and Kashmir lost about 326 MW when an overload defence scheme opened its only 220 kV supply to Barn - protection worked, but the substation still blacked out 8Roorkee’s line fault produced a reported 183 MW load loss and a second unexplained 240 MW demand dip - after remote fault clearing arrived 360 milliseconds late 8A broken insulator at Jawaharpur triggered sensitive protection and removed about 972 MW - turning one 765 kV line fault into a two-unit station outage 8A stuck breaker pole at Salal cut roughly 720 MW of hydro generation and 278 MW of load - after backup logic tripped both buses instead of one 8Greenko lost about 1,200 MW when five pumped-storage units tripped at 49.5 Hz - while a breaker flashover simultaneously faulted the station busDetails
For reference purposes the website carries here the following tenders: 8Tender for development of ETP, PTP and CTBD Details 8Tender for work of supply, erection, testing & commissioning of 2X33 kV bus sectionalizer bay along with conversion of 33 kV single to twin bus Details 8Tender for work of providing & fixing of sheet moulding compound trench cover chequered plate Details 8Tender for rate contract for retrofitting and strengthening of machine foundations in the power plant Details 8Tender for supply of welding electrodes & MIG wire Details 8Tender for supply of universal high speed data acquisition system with voltage, current, thermocouple, strain gauge Details 8Tender for job contract for electrical maintenance works Details 8Tender for civil works for rail track extension Details 8Tender for civil renovation works to be carried Details 8Tender for material handling and management including receipt, unloading, verifying, shifting, stacking, preservation, handling and handing over of components of boiler for coal gasification unit Details 8Tender for levelling and grading of main plant area including BTG, transformer yard Details 8Tender for construction of new 33kV,1.4kM double circuit line Details 8Tender for ARC for arboriculture, plantation for development and maintenance of lawns including Details 8Tender for construction work for protection of tower footing Details 8Tender for work of revamping of earthing system and supply and installation of anti-climbing device in towers Details 8Tender for supply and erection of anti climbing device in different tower Details 8Tender for construction work for protection of tower footing Details 8Design, manufacture, supply, erection, testing & commissioning including five years comprehensive operation and maintenance of total 07 meter height 160 WP capacity solar high mast Details 8Design, fabrication, supply, installation, testing, commissioning with RMS of 46 KWp grid connected solar PV power plant Details 8Tender for complete restoration work of CHEP-I and accessories Details 8Tender for repair / renovation of power house, choked drainage system and other allied works Details 8Tender for replacement of damaged window panes, painting, repair of drains, construction of septic tank and other civil works Details 8Tender for construction of a new 33 kV line Details 8Tender for new 33 kV line from 132 EHV substation Details 8Tender for supply of fully automatic three phase calibration test bench Details 8Tender for supply of 11 kV polymer pin insulators Details 8Tender for empanelment of contractors to award a contract for 11 kV under ground railway crossing Details 8Tender for construction of 02Nos.4 bay shed Details 8Tender for repairing of cable trench, construction of CB steps and waterproofing work Details 8Tender for various civil maintenance work at 220kV sub station Details 8Tender for various civil work soil filing Details 8Tender for construction of patrolling path inside the periphery Details 8Tender for work proposal for structure strengthening work, fabrication, erection, refurbishment, modification, repair, overhauling of ring granuator Details 8Tender for annual pollution control works patrolling and watch and ward of 111 hectare ash bund Details 8Tender for procurement of optical bundle installed in flame scanner system Details 8Tender for procurement of special purpose hard facing welding electrode boiler of 1X500 MW unit Details 8Tender for comprehensive annual maintenance contract (CAMC) for servicing of 2X160 kVA UPS system installed Details 8Tender for supply of level transmitters for various Details 8Tender for work contract for annual routine maintenance work of turbine house auxiliaries, air compressor room auxiliaries etc Details 8Tender for procurement of L and T make electrical spare parts for paddle feeder Details 8Tender for construction of 33 /11 kV substations Details 8Tender for construction work for new proposed 33/11kV line Details 8Tender for construction work for uprating of 1.8 KM line Details 8Tender for construction of 220kV GSS associated transmission lines along Details 8Tender for construction of 45 km 220 kV D/C line Details 8Tender for construction of various transmission elements various 220kV & 132kV transmission lines Details 8Tender for construction of 220/132 kV GSS Details 8Tender for construction of 220/132kV, 160 MVA transformer Details 8Tender for annual contract for sanitary, sewerage and water supply works Details 8Tender for supply of spares of sky climber (Model-ALPHA 800 HD 230 VC/3PH) of boiler Details 8Tender for supply of SF6 gas for 220kV/ 132kV /66kV SF6 breakers of various Details 8Tender for rate contract for outsourcing of electrical wiring work related to grid construction activities Details 8Tender for work of MRI and bill distribution of KCC, PTW and solar Details 8Tender for work of MRI and bill distribution of KCC, PTW and solar consumers Details 8Tender for construction of new double circuit 11 kV line Details 8Tender for procurement of spares of coal mill rejection (MRS) system Details 8Tender for biennial maintenance contract of fire hydrant system emulsifier system including 250 KVA DG set Details 8Tender for procurement of metal parts for rabbit/weasel and raccoon/Dog conductor Details 8Tender for supply of fixed contact for 11kV AB switch Details 8Tender for laying of underground cable network Details 8Tender for work of annual maintenance contract (AMC) for troubleshooting, repairing, and maintenance for 145kV & 245kV ABB make circuit breaker along Details 8Tender for annual maintenance contract (AMC) for overhauling, repairing & servicing of 33 kV & 11kV circuit breakers Details 8Tender for supply & installation of MFM energy meters at various EHV sub-stations Details 8Tender for work of supply, installation, testing & commissioning (SITC) of dedicated infrastructure required Details 8Tender for providing & fixing of 20 + 5 spare cooling fan control cubicle with WTI & OTI with double power source arrangement Details 8Tender for work of replacement of existing 132kV circuit breaker at various EHV substations Details 8Tender for work of replacement of existing 33kV circuit breaker at various EHV substations Details 8Tender for annual maintenance contract for the work of refilling & providing new spares for existing fire extinguishers available at various Details 8Tender for rate contract for attending emergency breakdown and planned outage works on various 400 kV lines Details 8Tender for work of carrying out the earthling audit (health assessment) of existing mat and earthling electrode (earth pit) at substation Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8Auroville’s Hybrid Energy Experiment: Can Its Decentralised Renewable Model Work for the Rest of India Details 8Hitachi Energy India stock jumps 8% after strong Q1, top midcap gainer; brokerages eye power infra opportunity Details 8Acme Solar plans to spend up to Rs 20k crore on capex: CEO Details 8India needs 5,400 tonnes of uranium annually to secure nuclear energy in future Details 8Coal was meant to disappear. China, India keep it burning: 2 Asian giants consume nearly 70% of global coal Details 8Policy reforms speed up coal block operationalisation: Coal Secretary Details 8Inox Wind Reworks Its Biz Model: Can Equipment Supply Thrust Drive New Growth Details 8How Engineers Are Reinventing the Wind Turbine Details 8India bars employment of personnel from land border countries in renewable energy projects within 1km of border Details 8India’s renewable energy sector gains momentum with Rs 5.25/unit RTC tariff discovery Details 8Rooftop solar tops 1,000MW, cuts Bangladesh’s daytime power demand by 6% Details 8Oswal Pumps reveals Q1 FY27 investor presentation Details 8Bharat’s Rooftop Solar Revolution Hits 50 Lakh Homes. Here’s What’s Driving the Surge Details 8India Achieves Landmark 300 GW Non-Fossil Fuel Power Capacity Details 8Haryana Power employees announce three-day strike from today after talks fail Details 8The Guardian view on India’s green growth gamble: it will need more than private finance Details 8Indian Power Plants See Coal Stocks Declining 20% By September Details 8Hitachi Energy India Shares Rise 8% After Q1 Profit Doubles Details 8India's EV sector to create 30-40 million jobs by 2030 Details 8Lunch hour demonstration by engineers across India on August 11- AIPEF Details You can also click on Newsclips for moreDetails
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance. Click on Reports for moreDetails
For reference purposes the website carries here the following tenders: 8Tender for supply of 36 kV bus isolator and 36 kV line isolator at various substation Details 8Tender for engineering, supply, erection and commissioning of 01 No. 132kV GIS feeder bay at existing 220kV GIS substation Details 8Tender for construction work of 01No. 220 kV GIS bay Details 8Tender for installation of 20.00 meter high mast light Details 8Tender for routine and preventive breakdown maintenance of all mech. parts of mono-rail electric hoist Details 8Tender for work of plugging of platen superheater tubes Details 8Tender for supply and erection of electrical smart power fence (ESPF) along Details 8Tender for manufactured fly ash brick Details 8Tender for supply, installation, commissioning and CAMC for real time data transmission Details 8Tender for rate contract for the procurement of sodium chlorite Details 8Tender for complete fabrication of boiler drum including suspension assembly Details 8Tender for construction of allied civil works at 33 kV sub station Details 8Tender for Re-construction of other allied civil works to prevent the 33 kV S/Stn Mehmra Details 8Tender for Re-construction of other allied civil works to prevent the 33 kV S/Stn Details 8Tender for supply, installation testing and commissioning for bifurcation of overloaded 11 kV feeder Details 8Tender for procurement of ISI marked 11 kV XLPE UG cable 300sqmm Details 8Tender for setting up of grid connected 88 MW ground mounted solar PV project Details 8Tender for setting up of grid connected 922.635 kW rooftop solar PV power project Details 8Tender for annual overhauling works (lower mechanical portion only) of motorized and pneumatic operated valves and gear boxes Details 8Tender for procurement of self-propelled fully mobile tyre mounted hydraulic mobile crane Details 8Tender for repair of aeration tank and digester tank Details 8Tender for supply, removal and installation of thermal insulations on pipes, equipments Details 8Design, detailed engineering, manufacture, supply, erection, testing and commissioning of 230/110kV AIS SS Details 8Design, detailed engineering, manufacture, supply of 400/230-110kV AIS substation Details 8Tender for entrusting works contract for carrying out all type of maintenance and breakdown activities by engaging additional gang at 400 kV GIS substation Details 8Tender for replacement of bare conductor by AB cable in 11 kV feeder Details 8Tender for replacement of bare conductor by AB cable Details 8Tender for work of carrying out the earthling audit (health assessment) of existing mat and earthling electrode (earth pit) at substation Details 8Tender for work of overhauling, oil leakage attending and testing of 100MVA, 11/230 kV generating transformer Details 8Tender for work of residual life assessment study of removed HP, IP & LP turbine rotors Details 8Tender for providing and laying G. I. pipe Details 8Tender for construction of winch foundation near bottom ash scraper Details 8Tender for providing and laying concrete & steel cover for unit 1 to 5 boiler side Details 8Tender for supply of various consumables, measuring instruments, Tools tackles, CPVC and fasteners items Details 8Tender for constructing 1175 m HT ABC Details 8Tender for conversion of the existing 33 kV overhead power line Details 8Tender for drawing dedicated 11kV feeder using covered conductor Details 8Tender for reconductoring of feeder using covered conductor Details 8Tender for AMC for specialized civil maintenance work Details 8Tender for supply of numerical relay communicable type and numerical differential relay Details 8Tender for erection new 33/11 kV S/s Details 8Tender for supply of three phase fully automatic meter testing bench Details 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects on control room at various 220kV / 66kV sub-stations Details 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects on control room at various 132kV / 66kV sub-stations Details 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details 8Tender for procurement of spares of control valve of condensate line Details 8Tender for procurement of AR/GR/exceller grade ammonia solution Details 8Tender for procurement of HACH make fine chemicals for analyser such as silica, sodium and chloride etc. Details 8Tender for work contract for repair and maintenance of disturbed dry stone pitching Details 8Tender for procurement of spares of SADC pneumatic actuators Details 8Tender for procurement of various keys and support plate of BHEL make turbine machine Details 8Tender for procurement of high pressure boiler tube bends installed at boiler Details 8Tender for purchase of 16 KVA, 3 phase aluminium wound energy efficient level-1 (star-1) completely self protected (CSP) distribution transformers Details 8Tender for new 10KM 11kV line Details 8Tender for shifting/height raising work of 220 kV S/C line Details 8Tender for civil works for augmentation of 31.5 MVA transformer at 132 kV GSS Details 8Tender for civil works for augmenation of 132/33 kV, 20/25 MVA transformer Details 8Tender for requirement of spares for hydraulic system boiler and turbine Details 8Tender for supply of 245kV current transformer Details 8Tender for supply of chains and sprocket for rotary breakers and travelling trippers Details 8Tender for work of 66kV SC on DC line from 66kV SStn Details 8Tender for annual contract providing, fixing and repairing of chain link fencing work Details 8Tender for supply of staircase step grills for crusher house Details 8Tender for construction of HT/LT line and erection of distribution transformer Details 8Tender for supply of and fixing of T and P Details 8Tender for supply of decentralized material Details 8Tender for maintenance, overhauling of different capacity of 11/0.4 kV DTRs in EDSD Jaspur-II Details 8Tender for maintenance, overhauling of different capacity of 11/0.4 kV DTRs Details 8Tender for supply of boiler tube and fittings for boiler Details 8Tender for supply of wall soot blower and oil gun spares for boiler Details 8Tender for supply, erection and commissioning of various accessories of conveyor belt Details 8Tender for shifting of 11 kV HT and LT OH line for construction of 2nd rail line Details 8Tender for electrical works for augmentation of capacity of PTR Details 8Tender for shifting of 11 kV HT and LT OH line for construction of 2nd rail line Details 8Tender for painting of different switchyard equipments alongwith equipment structures Details 8Tender for procurement of 400 sets of 11kV standalone complete set Details 8Tender for supply of V cross arm 4.5 feet Details 8Tender for supply of 7/2.50mm AAA weasel conductor Details 8Tender for supply of various spare/liners of beater wheel mill Details 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50 MVA, 132- 110/33 kV T/F Details 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50 MVA, 132- 110/33 kV T/F with allied civil works Details 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 25MVA, 132- 110/33 kV T/F Details 8Tender for work of overhauling / servicing of 245kV SIEMENS make circuit breakers Details 8Tender for work of overhauling / servicing of 145kV SIEMENS make circuit breakers Details 8Tender for work of annual maintenance contract (AMC) for servicing / maintenance of 1.5T & 2.0T split air conditioners available Details 8Tender for work of supply erection testing commissioning of 2x33kV bays at 220kV substation Details 8Tender for work of replacement of old and repaired 33kV current transformer for feeder Details 8Tender for work of application of RTV coating on 33 kV tertiary bushing,33kV PT, 33KV LA & support insulators Details 8Tender for day to day maintenance for civil assets in sub-station Details 8Tender for work of painting of 200MVA 220/132kV ICT's Details 8Tender for SITC (supply, installation, testing & commissioning) of cassette type inverter technology of split room air conditioning Details 8Tender for various civil maintenance work at control room & switchyard Details 8Tender for various civil maintenance works such as metal spreading, providing metal edging Details 8Tender for work of overhauling, servicing & repairs of 245kV/145kV Areva make circuit breaker at various EHV S/stns Details 8Tender for work of overhauling of ESP pass Details 8Tender for supply of different types & ratings of LT energy efficient induction motors Details 8Tender for supply of various types of bushings for 250 MVA, 420/15.75 kV, BHEL make generator transformers Details 8Tender for supply of MS grill and fabrication & Eepoxy paint of stairs, railing, structure Details 8Tender for ARC for supply erection and commissioning of of GI cable tray Details 8Tender for erection of equipment and structure, control wiring, yard lighting, control room wiring Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8Odisha, MP sign MoU to accelerate renewable energy push Details 8Jindal India Renewable Energy Signs 160 MW Wind Turbine Supply Agreement with SANY Wind Energy India for SECI RTC Project Details 8No solar, wind, renewable energy project within 1 km of international border, says Home Ministry Details 8Juniper Green Energy bags 230 MW project from SECI Details 8World’s first 16MW floating wind platform begins operation, changing offshore energy forever Details 8MNRE weighs support scheme for polysilicon to back 10 GW capacity in solar manufacturing Details 8RTC Renewable Tariff Falls To Rs 5.25, Boosting Clean Energy Push Details 8NLC India Q1 profit falls 48% to Rs 436 crore as deferred tax base effect weighs Details 8JSW Energy completes acquisition of 100% stake in Maruti Clean Coal & Power Details 8Coal Ministry Pushes Private Investment Through Mining Reforms Details 8Coal India Named Preferred Bidder for Gadadharpur Block Details 8Commercial Rooftop Solar: India’s New Clean Energy Driver Details 8Premier Energies Q1 FY 2027 slides: strong growth, expansion plans Details 8SECI Invites Bids For PMU Installation At 100 MW Solar With 40 MW/120 MWh BESS Project In Chhattisgarh Details 8India Plans PLI Scheme For Polysilicon Manufacturing To Reduce China Dependence Details 8Navgrun Announces 1.2 GW TOPCon Solar Wafer and Cell Facility Details 8NTPC Invites Bids For O&M And Security Services At 15 MW Solar Plant In Madhya Pradesh Details 8GERC Approves Rs 4.87/kWh Tariff for 250 MW FDRE Project Details 8Heelstone Acquires 188 MW Cypress Pointe Solar Project Details 8India Plans Incentives For Polysilicon Production Details 8One in Three Indian Power Firms Use AI; Adoption Seen Reaching 65% by 2030: Report Details 8India & Sri Lanka Discuss Bilateral Cooperation In Cross-Border Electricity Trade Details 8Coal supply for power sector comfortable in July: Govt Details 8AI Set to Become a Core Operating Capability in India’s Power Generation Sector; Adoption Seen Rising 65% by 2030: ENCIS Survey Details 8India sees 68 major renewable sector grid disturbances, generation losses of up to 7 GW Details 8Bihar lays the groundwork for its energy transition Details 8Rajiv Kumar Porwal: Director (System Operation), Grid-India Details 8Schneider Electric and BSES Rajdhani (BRPL) Partner to Deploy India’s First Sustainable Pure Air RMU Pilot Project Details 8Bihar Leads India in Smart Meter Rollout, Accounts for 70% of Prepaid Installations: Energy Secretary Details 8Refex Renewables Subsidiary Secures 80 MW Wind Power Project from SECI Details You can also click on Newsclips for moreDetails
8RVUN's Rs 127 crore Bodana solar-park tender says JV experience counts and, on a separate page, that JVs aren't allowed Amendment-2 flipped "Experience of JV/sub-let will not be considered" to "Experience of JV will be considered," but Clause 3.1(xi) barring joint-venture participation was never deleted — and a bidder asking about it was pointed back to the amendment. The same amendment cut water-treatment capacity from 150 to 15 lakh litres a day; Amendment-4 then cut the BOQ evaluation quantity for that item from 15,000 KL to 1,500 KL. Three extensions, 41 days. Prices are firm — Clause 75 bars escalation over 18 months.
8KSEB's 885 km ABC cable tender reaches financial opening with the bid mechanism disclosed and almost nothing else The record establishes a reverse-bidding "Tender cum Auction" for 11kV ABC of 120 sqmm and a 10 August opening, but delivery schedule, lot structure, consignee locations, inspection method, EMD, PBG, LD ceiling, warranty and whether the quantity can be split among suppliers are all absent from the published summary. Technical evaluation closed 6 August; no bidder names, count or rejection reasons appear.
8KSEB's transformer tender carries two different project values, and its qualification thresholds are pegged to whichever one applies The NIT and portal state Rs 72.163 crore; the pre-qualification committee minutes of 3 August state Rs 61.70 crore — a 14.5% gap with no corrigendum explaining it. Because minimum turnover is 75% of PAC, the entry barrier moves by roughly Rs 7.85 crore a year depending on which figure governs. Three of the five pre-qualified firms got in on undertakings to produce compliant type-test reports later; Kerala Electrical & Allied Engineering was disqualified on past KSEB performance.
8Arunachal's Rs 98.87 crore Pathar Camp substation lost three of five bidders on paperwork before price opening ABN Tower fell on unsigned bid pages, missing manufacturer authorisations, unsigned GTPs and an EHV-licence gap; two others failed on lead-partner experience, liquidity and licensing. The two survivors then quoted 21.1% apart. L1's evaluated Rs 98.75 crore sits 0.1% under the estimate, but its BOQ base is Rs 82.98 crore — and the 19.0% bridge between the two isn't broken out anywhere in the financial-opening record.
8MPPKVVCL cut 2.43 lakh meters from its Ujjain AMI tender and cut the value by a larger percentage than the quantity Volume fell 17.4% while the NIT amount fell 18.2%, from Rs 1,116.90 crore to Rs 913.62 crore, with no explanation of the composition behind the revised estimate — so bidders can't treat it as a pro-rata reset. Amendment-3 then confirmed the AMISP bears SMS charges at up to five messages per consumer per day across 11.58 lakh consumers, plus SIM, MPLS, bandwidth and static-IP costs, for ten years at a firm service charge. Four timetable resets, 29 days.
8BHEL's ACC tender forces bidders to allocate at least 10% of value to erection and commissioning, or it will rewrite the split itself Clause 3.3 blocks the standard tactic of loading value into supply to accelerate cash release — relevant because 20% of both supply and E&C value stays tied to air-tightness testing, trial run and PG acceptance. Evaluation also monetises each bidder's declared guaranteed power consumption and its own M30 RCC and reinforcement quantities. Rule 144(xi) land-border restrictions are expressly disapplied for this package.
8UJVNL's Chilla BESS tender funds 60 MWh of a 225 MWh project and asks bidders to pre-price the discount if more support arrives VGF covers 60 MWh at Rs 18 lakh/MWh — Rs 10.80 crore against a Rs 352.30 crore project — leaving 165 MWh to stand unsubsidised under a Rs 3,18,401/MW/month tariff ceiling. Clause 3.24 separately requires a sealed envelope stating the capacity-charge reduction offered for every additional 10 MWh that later becomes VGF-eligible. Land details are tentative and can be swapped without an extra claim.
8NTPC Mining's Banardih substation tender lets a bidder borrow its parent's balance sheet but not its parent's project record Clause 2.1.1 permits holding-company support to meet the Rs 36.90 crore turnover test, while the technical QR notes exclude experience belonging to a group, holding or subsidiary company — and separately exclude reference work the bidder executed through a JV or consortium. Completion period, PBG quantum, LD structure and payment milestones are not stated at NIT level.
8DVC's Rs 90.50 crore limestone tender can order the full 277,857 MT or none of it The GeM option clause allows ±25%, but Volume IV states "+25% to -100%" and says DVC "does not guarantee any off-take" — while each call-off must still be met within 15 days across a 365-day contract. Quality deductions run at 20% or 50% of basic price plus freight depending on how far CaO falls below 47%. Price comparison happens first; only the prospective L1 then faces techno-commercial scrutiny.
8NPCIL's Rs 128.22 crore engineering tender bars the winner from subcontracting the one activity the whole package is built around Cadmatic 3D modelling cannot be subcontracted, and bidders must already hold five qualifying 3D-platform licences and five piping-stress licences with live AMC, plus 200 engineering staff — 150 of them graduates — each with a year's tenure. Corrigendum C3 moved the pre-bid meeting to 7 August without moving the 10 August deadline, leaving three days between clarification and submission.
8NTPC REL reopened document access for its 600 MW Dhule tender 12 days before bids close and 34 days after the original cut-off Corrigendum 4 pushed the download window from 3 July to 6 August without touching the 18 August deadline, which itself had already moved twice from 22 July. Corrigendum 1 briefly recorded submission at 14:00 before later documents reverted to 15:00. Bid security stays flat at Rs 20 crore whether a bidder quotes 300 MW or 600 MW — and the scope clause cites document NRE-CS-5816 while the tender is numbered NRE-CS-5820.
8NREDCAP's Vijayawada WtE tender fixes the tariff and makes the subsidy ask the only thing bidders compete on Clause 21.2 evaluates financial proposals solely on quoted capital grant support, while the model PPA hard-codes Rs 7.50/unit subject to APERC approval. The authority guarantees 1,000 TPD of acceptable waste with damages at 30% of average per-ton gross revenue for shortfalls. Three separate securities stack up — Rs 16.24 crore, Rs 9.72 crore renewable annually, and Rs 25 lakh/MW — while Clause 3.3 describes construction running "from the COD" and Clause 18.5(e) writes 110% as "in excess of 10%."
8NTPC's Telangana ash-handling tender reversed its own crushing requirement from 8 mm to 25 mm after bidders questioned it Errata-01 corrected the intermediate-silo bottom ash size threefold; separate amendments moved the compressor fleet from 9 working plus 6 standby to 10 plus 5 without adding machines, cut bottom ash slurry from five streams to four, and raised conveyor rated capacity from 70 to 72 TPH with a new sub-120°C inlet criterion. Delay LD is Rs 30.73 lakh per day per facility. The deadline has moved 69 days across three extensions.
8RVPN's Dholpur EPC tie-up gives bidders a document-request deadline that falls on the same day bids are due Clause 5.0 says requests must come "up to 01 (One) day prior to bid submission deadline" and then names 3:00 PM on 17/08/2026 — the submission deadline itself — leaving potentially no gap between receiving the NDA-gated technical package and lodging a physical hard-copy bid. The pre-selected contractor must sign an exclusivity MOU and stay out of the same TBCB project before RVPN even submits its tariff bid. JV participation is marked "NOT APPLICABLE" and subsidiary or group credentials don't count.
8NPCIL's Rs 576.86 crore Gorakhpur tender narrows "similar work" to TAM and permeation grouting alone That single definition sets qualifying-work hurdles of roughly Rs 230.74 crore each for three works, Rs 288.43 crore each for two, or Rs 461.49 crore for one. Blocked or damaged TAM pipes must be reinstalled at contractor cost with no separate measurement, and grout is paid only against automated batching-plant records of accepted consumption. Two corrigenda moved the deadline 23 days and the pre-bid meeting 20 — without publishing a revised query cut-off.
8NTPC's North Karanpura AWRS tender issued three extension notices that don't say what the new dates are All three uploaded files are byte-identical and contain only the heading announcing an extension. Meanwhile Amendment 01 advanced the starter-dyke layout from Rev 4 to Rev 5 and added drawings, without narrating what changed — the geometry that drives pipeline routing and civil quantities. Two seepage pump houses are a minimum, not a number: more are required if actual dyke contours create additional accumulation points. Delay LD runs Rs 2,51,954 a day, with functional-guarantee LD capped separately at 12%.
8THDCIL's Sonbhadra DPR tender says on GeM that no performance security is needed and in its own conditions that 5% is ITC Clause 12.1 requires 5% of contract price including GST within 28 days of award; the GeM ePBG field reads "Required: No" — and GeM's disclaimer says conflicting buyer-added terms can be invalid. The same split runs through dispute resolution: GeM records arbitration and mediation as "No" while GCC Clause 8 sets out both, seated in Delhi. All ten named experts must be in place at bid stage, with no substitution through award.
8NREDCAP's Tirupati WtE tender is labelled an EPC price bid on the portal and is actually a grant-based concession The portal reads "Price Bid EPC" with 90-day validity; RFP Clause 2.6 requires 180 days and Clauses 21 and 28 make capital grant support the sole ranking variable. The PPA defines tariff as the figure "quoted by the bidder" while Article 2.2 fixes Rs 7.95/unit. DCA Clause 22.3(c) writes each of four grant instalments as 25% numerically and "twenty per cent" in words, and refers to a third project milestone that Schedule 5 doesn't contain.
8BHEL cancelled the reverse auction on its Korba West coal-handling tender the day after publishing it Corrigendum 1 changed clause 11.0 from "Applicable" to "Not Applicable," making the first sealed price final for a package running 42 months on one side and 58 on the other. The same corrigendum fixed a civil-PQR presentation where stray connectors made two RCC-volume thresholds read as cumulative rather than alternative. Bidders quote one lump sum, split 25:75 for ordering — after which BHEL may regroup the orders, and a breach on one can be treated as breach of the others.Details
8ICRA reaffirmed the Delhi distributor at AA+/Stable after distribution losses improved to 5.42%. The rating still depends on converting approved regulatory assets into cash and resolving a licence that expires in 2029.Details
8Ballia alone has Rs 202.62 crore of loss-reduction work and Rs 176.56 crore of smart-metering work, alongside 517 households still awaiting connection. The programme succeeds only when sanctioned spending becomes energised assets, accurate bills and fewer consumer complaints.Details
8CEA separately recorded 58,359.8 MW unavailable across 312,333.8 MW of monitored conventional capacity on 5 August. That broader total uses a different fleet definition, but it shows why return dates and repeated unplanned losses matter more than installed capacity alone.Details
8Both 660 MW units lost evacuation for seven hours and 26 minutes after a current transformer failed and protection opened healthy connections. JIPL has changed the hard-wired logic, but a tested selectivity check is still needed to show that the failure will remain contained next time.Details
8Rooftop installations stood at 446 MW against a 750 MW policy target while peak demand reached 8.7 GW by June. Panels can cut daytime purchases, but storage and flexible demand are needed after sunset.Details
8Four operating hydro, wind and solar assets failed value-in-use tests in FY2026. Naitwar Mori carries the largest rupee charge, while the portfolio percentages show sharply different degrees of damage.Details
8Implementation agreements for Luhri-I, Sunni Dam and Dhaulasidh remain unsigned while construction exposure has risen sharply. Interim court protection prevents coercive action for now, but it does not settle ownership or future commercial terms.Details
8The projected FY2027 distribution shortfall is Rs 1,972.93 crore larger than a year earlier. Kerala’s regulator must separate efficient costs from avoidable expenditure before deciding how quickly consumers should bear the increase.Details
8The June incident removed 1,237 MW for more than six hours after turbine-vibration and breaker protections operated. Investigators found earthing and relay inconsistencies that must be resolved without weakening genuine machine protection.Details
8NERLDC found Assam above its secure import limit for nearly five hours while the other Northeast import corridors remained within bounds. Prolonged violations reduce operating margin and may require more local injection, lower imports or changed dispatch.Details
8Uttar Pradesh’s expert panel has recommended first-phase environmental clearance for the Rs 2,693.68 crore plant. Its industrial promise now depends on whether large treatment and recycling systems can manage the proposed chemical and water load.Details
8India has completed only 38% of its two-year rooftop-solar installation goal 8Raigarh awaits BHEL as selected western coal units leave 40% operation unproved 8Orissa Steel’s 1,119 MW coal-power expansion reaches the study stage, not approval 8India's annual power exports pull in different directions 8SJVN misses a land milestone and leaves 50 MW without an EPC award 8KSEBL's Cherthala substation takeover remains tied up in land terms 8Telangana reservoirs reverse from scarcity to a strong hydro cushion 8Imported gas makes two Delhi power stations nearly twice as costly 8Samalkot equipment sale faces lender approval amid Rs 1,842 crore demandDetails
8India has 24.65 GW of pumped storage in the pipeline—but only 15.87 GW is being built 8Refex locks in an 80 MW wind tariff before land, finance and evacuation are secured 8CESC wins 175 MW at Rs 3.85, but construction risk now replaces auction risk 8ReNew’s solar rating improves even as output remains about 9% below design 8Amazon-linked wind project misses buyer and lender deadlines as land work lags 8JSW’s solar-wind-battery project is nearly a year late despite partial completion 8Avaada’s upgrade narrows the risk, but generation remains just below its benchmark 8India funds 13.8 GWh of batteries without setting an electrification target 8SECI seeks real-time visibility as Rajnandgaon’s solar-storage plant complicates grid control 8Jamui misses another solar deadline without an official completion notice 8Nawa solar slips nine months beyond SJVN's original promise 8Sonitpur misses successive targets without an official completion notice 8Delhi's tiny battery base confronts an 8,748 MW night peak 8Delhi's low distribution losses mask weak green-market participation 8SJVN’s construction pipeline nearly matches its operating fleetDetails
8Bhubaneswari mine stays 3.5 million tonnes below design despite a stronger quarterly run-rate 8India’s 62-day coal cushion may still fail at individual power plants 8Faster coal auctions have yet to produce faster mines 8Ageing coal plants enter a repair queue without public funding 8India’s large-hydro output fell 10.75% through July, tightening the value of dependable supply 8Two weeks of coal cover hides plant-level shortages 8India beat its daily power programme, but coal still supplied 77.5% of generation 8CEA’s 5.9 GW outage subset cannot show whether India’s wider shutdown burden has eased 8NTPC’s daily shortfall shows scale cannot erase station constraints 8Nuclear led conventional availability on 5 August, but one day cannot establish a fleet advantage 8Gujarat weighs turning ageing KLTPS units into grid stabilisers instead of retiring them 8Maharashtra, Gujarat and NTPC utilities tell WRPC that BHEL delays are holding up overhauls 8Western generators still lack uniform frequency controls as grid-response obligations tighten 8Missing generator models weaken studies before the next grid disturbance 8Weak reactive-power absorption is worsening high-voltage stress in western India 8Upper Sengulam hydro slips amid litigation and blasting opposition 8Luhri Stage I recovery still points to a 2030 finish 8Dhaulasidh nears civil completion while its state agreement remains unsigned 8Sunni Dam advances under an agreement the state has not signed 8Arun-3 transmission progress cannot erase a 2028 finish 8Buxar Unit 2 misses its July commissioning marker 8Buxar books Rs 521 crore of sales before tariff orders arriveDetails
8Biharsharif substation failure followed maintenance warnings that remained unresolved 8Santaldih’s first bus-splitting attempt ended in a total station failure 8Rain entered Dikchu’s gas monitor and twice cut off the same hydropower station 8One tower collapse kept Rongnichu hydropower off the grid for 18 days 8Faulty control logic caused two large load losses across Godda and Pakur 8Darbhanga’s transformer trips exposed an autoreclosing scheme set for the wrong fault 8Buxar’s backup relay tripped before the line protection it was meant to supportDetails
8One balanced power day does not prove India’s grid readiness 8India’s average frequency hides nearly a quarter of the day outside band 8Upward reserve dispatch jumped as India’s grid needed more generation than schedules supplied 8Secure national corridors do not prevent local voltage trouble 8Northeast frequency leaves the operating band for one-fifth of the day 8Telemetry gaps are leaving western grid operators partly blind 8Delayed black-start drills leave recovery plans unproved 8Bhopal’s islanding plan clears approval but still needs working controls 8Indore’s 600 MW islanding design returns for another study 8Northern generators seek overlapping autumn outages across more than 2 GWDetails
8Nearly two-thirds of sanctioned rural power connections remain unfinished 8India Energy Stack pilots begin without common standards 8Thousands of overloaded transformers put Haryana’s grid works under pressure 8Bihar’s Rs 11,707 crore grid support still leaves execution with its discoms 8Six PSPCL offices hold 55% of its unresolved audit backlog 8Solar takes 92.8% of MNRE’s budget while annual underspending persists 8Bioenergy receives 0.83% of MNRE’s budget despite a wider waste-to-energy promise 8Offshore wind ambition still lacks the spending record needed to prove momentum 8Small hydro remains trapped between old liabilities and a weak new-project pipeline 8Green Energy Corridor spending lags while renewable evacuation needs accelerate 8Green hydrogen funding is moving slower than the industrial demand it must create 8Renewable research gets only 0.6% of MNRE’s budget 8Parliament presses MNRE to coordinate a renewable transition fragmented across states 8National grid spending comes without transformer-failure or accident dataDetails
8POWERGRID buys the Krishnagiri corridor vehicle before the hard construction begins 8Rajasthan’s new renewable corridor is commissioned after the development risk has passed 8POWERGRID’s Rs 856.94 crore southern line upgrade must lift capacity without a new corridorDetails
8Three revised deviation accounts move lakhs without changing market rules 8A revised reserve-services account reopens payments after schedule corrections 8Avaada’s 350 MW grid bay enters licensing without an approval 8Tata Motors keeps 33 kV supply but must pay for upgrades 8Gujarat’s Rs 4.87 firm-renewable tariff puts dispatchability on trial 8INKEL says Kerala’s voltage rule is stranding renewable capacity 8Garda’s shared grid plan waits for a commissioning ruling 8MERC makes MSEDCL pay for the time value of delay 8Gujarat’s 360 MWh storage dispute leaves damages and deadline unresolved 8Bihar’s bagasse ruling will decide a 20-year revenue stream 8PSPCL’s unmapped tax balances make accurate municipal settlement impossible 8KSEBL’s power-purchase bill is rising faster than its sales cushion 8KSEBL’s carrying cost is turning old gaps into a new tariff problem 8Bihar discoms miss five reform proposals in the new Supply Code 8MSEDCL resolves Rs 18.44 lakh consumer delays only after escalation 8Kerala’s evening power auction tests the price of cover 8PXIL’s new trading engine launches into a market with no bids 8IEX core markets clear heavily while premium power finds no buyerDetails
8Premier Energies’ profit surge raises the stakes on simultaneous expansion 8G R Infra’s group growth masks a weaker standalone quarter 8Bajel’s order boom still depends on debt and margins 8Premier’s Rs 5,000 crore funding plan turns growth into a deployment test 8Ola’s dealer pivot moves service risk to third parties 8Coal India’s iron-ore bid opens a long road to diversification 8HCC’s flat profit cannot hide collapsing margins and audit doubts 8HCC’s rights-issue delay tests its promise to investors 8Reliance Power’s profit recovery cannot outrun defaults and forensic review 8Torrent’s renewable push runs into weak earnings and transmission delays 8Viviana’s 246% revenue surge leaves a Rs 1,313 crore order book to prove 8GEE enters NPCIL’s supplier list without winning any business 8JSW Mahanadi’s rating holds while its 2028 contract gap approaches 8Aditya Birla renewable debt shrinks while leverage stays high 8Failed technology keeps Rajasthan Sun Technique in default 8Dhursar avoids fresh impairment while audit qualifications remain 8Reliance Power faces three investigations with outcomes unresolved 8Reliance Power puts four project groups into discontinued operationsDetails
8DVC’s pollution controls cannot clear its stalled ash bottleneck 8Vrajesh’s 56 MW captive-power plan is deferred over unresolved site evidence 8Shree Radhe’s 25 MW captive plant wins a conditional clearance recommendation 8Shakambhari’s 484 MW captive plant advances with river and land questions attached 8Maa Kali’s 90 MW power plan moves forward beside homes and forest 8SRS Steel’s 35 MW captive plant clears the panel with strict pollution controls 8Siddhiriddhi’s 40 MW plant advances despite a heavy coal and ore logistics burden 8Jagdamba withdraws its 50 MW power proposal after errors in the filing 8Rajshri’s 37 MW captive project is deferred over its reliance on an estate clearance 8Nav Durga’s 51 MW expansion is returned over coal and groundwater demandsDetails
8Talcher Stage III slips as land, roads and materials block construction 8Kosi-Seemanchal grid reinforcements stretch into the 2030s 8Khavda collapse leaves state frequency accountability unresolved 8KSEBL's Rs 5,131 crore generation plan is cut to Rs 1,490 crore 8India's thermal pipeline includes 4,845 MW of stressed projects 8Premier opens a 5.6 GW module plant as execution shifts to ramp-up 8Namrup and Kudgi storage pilots wait for funding decisions 8Rajasthan's grid-support plan shrinks to two STATCOMs under review 8Thirteen state cyber proposals remain trapped at different approval stages 8Three Northeast grid-visibility projects remain trapped at different approval stages 8Punjab and Rajasthan islanding plans remain unfinished 8Bhivpuri's 2029 target still depends on forest and road clearances 8India's wave-energy ambition still has zero installed capacity 8SJVN’s 500 MW Khavda solar build enters its final-month delivery test 8Two contractors face a November test on SJVN's 200 MW project 8SJVN's 200 MW Phase XVII solar project slips to December 8Bagodra solar deadline moves fifteen months after earlier delay costs 8GUVNL Phase XIII slips fifteen months after liquidated damages 8SJVN's 260 MW Phase XIV solar project slips to June 2027 8Premier's 7 GW cell plant approaches trials after civil completion 8Premier’s 10 GVA transformer expansion enters its final-month delivery test 8Delhi's own generation share falls from 20% to 13% 8Delhi sanctions 3,521 smart meters but installs none 8Delhi tariff transparency stops at FY2023 8Mankulam's 40 MW hydro project stalls on an unaffordable bid 8KSEBL cancels one solar project while others miss expectations 8SJVN provides Rs 18 crore after Luhri-II's original design fails 8DVC biomass use stays tiny as Chandrapura rejects the fuel 8Vishnugad Pipalkoti tunnel progress reaches 85% 8Tapovan Vishnugad records a tunnel breakthrough with work unfinished 8Ramp limits expose a scheduling penalty trap for Maharashtra generators 8Supply disruption forces western generators to rewrite outage plans 8Western generators changed outage dates without required approvals 8Railway work exposes missing rules for generator evacuation outages 8Generators risk incentives because frequency-response data remain incomplete 8Forced outages leave western schedules above declared capability 8July partial outages remain poorly explained across western stations 8Chhattisgarh plants withhold 158 MW of downward flexibility 8Missing transformer settings weaken voltage and restoration planning 8Late event data undermines western frequency-response grading 8Haryana prepares for a three-day power-sector strike 8Etawah's clean reliability claim collides with Rs 887 crore of grid work 8Robertsganj remains on rostered power despite a Rs 411 crore push 8Tribal electrification totals leave 11,838 households on off-grid solar 8Centre leaves tribal supply-hour accountability with the states 8Bihar adds interstate capacity while local delivery waits 8India's transmission plan faces a land-compensation execution test 8Metro power questions receive national answers but no city results 8Uttar Pradesh awards 28 green-corridor projects with delivery still ahead 8Renusagar's 60 MW banking extension reaches UPERC 8Grasim banking pact reaches UPERC without disclosed capacity 8SJVN governance gaps reach the board and two key committees 8NTPC opens 135 engineering posts without evidence of a wider shortage 8Viviana's transformer plans lack cost and commissioning dates 8Viviana exits two subsidiaries without disclosing transaction value 8Reliance Power forfeits Rs 303 crore after warrants lapse 8LN Steel power plan is deferred after opposition and land gapsDetails
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance. Click on Reports for moreDetails
For reference purposes the website carries here the following tenders: 8Tender for EPC Package of power project Details 8Tender for biennial job contract for painting works Details 8Tender for Package cooling tower Details 8Tender for air condition system Details 8Tender for architectural works for renovation and modernisation at 6X60 MW Details 8Tender for supply of various patch cords and opticalconnectors/ attenuators Details 8Tender for procurement of mechanical seal of ECW pump Details 8Tender for procurement of insulation material for unit-1 boiler Details 8Tender for supply of ISI marked AAA rabbit conductor Details 8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details 8Tender for procurement of opacity/dust analyzer for measurement of dust concentration Details 8Tender for procurement of spares for IL makes pneumatic actuators and power cylinders Details 8Tender for procurement of 415V LT air circuit breakers of different capacity installed Details 8Tender for procurement of coupling for fan and motor shaft of PA and FD fan installed Details 8Tender for work of refurbishment reblading of ID fan impeller and fitting Details 8Tender for work contract for hotline tightness and PID testing work of 400kV and 220kV switchyard Details 8Tender for work contract for bushing gasket replacement of 220 kV station transformer Details 8Tender for procurement of spares of pneumatic actuator Details 8Tender for procurement of spares for transport air compressor ZA-6 for ash handling system Details 8Tender for supply of motors Details 8Tender for construction of switch house Details 8Tender for supply of MS plates and angle structures Details 8Tender for construction of anti-flood wall and water collection tanks to tackle water logging at 33 kV s/stn. Details 8Tender for assistance in shift operation of boilers, including their auxiliaries Details 8Tender for medium repair of RCF, replacement of PA fan impeller assembly Details 8Tender for establishment of centralized transmission asset management service Details 8Tender for civil works for installation of 6 KLD grey water treatment plant Details 8Tender for work of attending daily, routine defects, preventive, breakdown, shutdown and emergency maintenance of various auxiliaries Details 8Tender for procurement of beater plate for coal mill Details 8Tender for AMC for the work of maintenance, repairing & servicing of battery set, battery charger & reconditioning of battery cells at various substations Details 8Tender for rate contract for work of rewinding and repairing of various rating of LT motor, submersible pump and various Details 8Tender for supply of various MS / CS pipe, bends Details 8Tender for procurement of composite long rod polymer insulators Details 8Tender for supply of lighting arrester for 220kV & 400kV switchyard Details 8Tender for drawing 11kV covered conductor Details 8Tender for DP erection and HT cabling 33kV substation Details 8Tender for purchase of digital level meter Details 8Tender for attending leakages/seepages in various underground structures Details 8Tender for providing muffing on periphery of existing various steel structure of coal yard Details 8Tender for providing and fixing PUF panel operator cabin Details 8Tender for work of erection dismantling of 132kV/66kV/11KV equipment’s Details 8Tender for utilization of 6.50 lakh metric tonne dry fly ash Details 8Tender for operation and maintenance of 114 Nos power quality meter Details 8Tender for renewal of sophos firewall subscription Details 8Tender for demolishing of cement concrete rock fragments Details 8Tender for renovation and reconfiguration of through interior fit out works Details 8Tender for maintenance and repair work of power channel Details 8Tender for supply, erection & commissioning of 110 volt 500Ah lead acid tubular LM type battery set and automatic 110V/100 Amp. battery charger Details 8Tender for implementation of islanding scheme Details 8Tender for owners engineer and project management consultant (OE and PMC) for 22.5 MW hydro power project Details 8Tender for supply of 11 kV moving contact 400 Amps Details 8Tender for supply of ISI marked 33 kV aluminium conductor Details 8Tender for execution of deposit works, including the supply, erection, installation, testing, and commissioning of materials/equipment Details 8Tender for purchase of 25 kVA, 3 phase aluminium wound energy efficient level-1 (star-1) completely self protected (CSP) distribution transformers Details 8Tender for supply of ACSR rabbit conductor Details 8Tender for construction of 2x33 kV bay for water resource Details 8Tender for requirement of ASCO make spares Details 8Tender for supply of 0.30 LMT limestone Details 8Tender for auction for lifting and disposal of wet ash Details 8Tender for procurement of ABT and bidirectional features digital summation unit Details 8Tender for supply of TC fuse wire 18 SWG Details 8Tender for supply of TC fuse wire 16 SWG Details 8Tender for supply of TC fuse wire 14 SWG Details 8Tender for supply of TC fuse wire 12 SWG Details 8Tender for supply of bolts and nuts of size 88 x 16 mm Details 8Tender for supply of bolts and nuts of size 63x16mm Details 8Tender for construction of 110/33/11 kV outdoor control room Details 8Tender for erection of 110 kV DC line on DC tower with panther conductor Details 8Tender for construction of 110/33/11kV yard equipment plinths, cable trench Details 8Tender for procurement of grinding elements of 8.5E (9) coal mill Details 8Tender for evacuation of pond ash including Details 8Tender for supply and retrofitting of chinese brand chiller compressor unit of capacity Details 8Tender for laying of 11 kV 3C 300 Sq mm XLPE UG cable Details 8Tender for construction of 132 kV M/C transmission line Details 8Tender for repair with complete rewinding including dismantling, loading, unloading, to and for transportation, inspection, testing, and other allied works Details 8Tender for repairing dismantling and fixing cage of chain link cage around distribution transformer Details 8Tender for erection work of 66kV S/C line on D/C towers Details 8Tender for erection work of 66kV S/C line Details 8Tender for work of overhauling of diverter switch and drive mechanism box of the OLTC of the transformers Details 8Tender for work of feeder re-orientation at 110kV substation Details 8Tender for work of DGA testing of T/F oil and other tests of oil for ICT's & transformers Details 8Tender for supply of various types of cable & dismantling, ETC work of 245 & 145 kV circuit breakers Details 8Tender for supply of various types of cable & dismantling, ETC work of 36 kV circuit breakers at various S/Stns Details 8Tender for replacement of existing tower at 220kV 60 Deg new towers Details 8Tender for AMC for work of repairing & overhauling of OLTC of ICT/ transformer Details 8Tender for enhancement of transformation capacity of substation by providing 1x50MVA, 132/33kV PTR along with HV & LV bays and allied civil works Details 8Tender for enhancement of transformation capacity of substation by providing 1x50MVA, 132/33kV PTR along Details 8Tender for annual maintenance contract for repairs, overhauling of 33 kV CGL make VCB installed at various Details 8Tender for work of chemical washing of insulator strings manually by using high voltage insulator Details 8Tender for work of maintenance contract for attending emergency breakdown & allied maintenance of any EHV line Details 8Tender for AMC for work of repairing/overhauling with providing & fixing of spares for 33kV VCB at various EHV sub-stations Details 8Tender for work of auxiliary power supply for 400/220kV substation Details 8Tender for turnkey based contract for 11 kV AL-59 ACS medium voltage covered conductor (MVCC) with its accessories Details 8Tender for supply of wireless LCM kit for 220kV and 66kV class switchyard Details 8Tender for replacement of side & roof sheet of boilers, conveyor galleries Details 8Tender for rate contract for complete rewinding of LT(415V/230V) AC motors Details 8Tender for supply of switchgear spares Details 8Tender for job work for radiography of boiler tube weld joints Details 8Tender for work of attending the boiler tube leakages & various pressure part related misc. works Details 8Tender for works for turnkey based contract for 11 kV AL-59 ACS medium voltage covered conductor Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8Serentica Renewables commissions first phase of 1 GWh battery energy storage system in Bikaner Details 8Next phase of Green Energy Corridor to cover 10,000 ckm: Pralhad Joshi Details 8NHPC should accord top priority to 20,000 MW pumped storage pipeline: Parliamentary panel Details 8Views of Manohar Lal: “India’s power sector has made significant progress Details 8AI To Be Part Of India’s Power Generation, Adoption To Rise To 65% By 2030: ENCIS Study Details 8Coal supply for power sector adequate, July despatch up 18%: Coal Ministry Details 8Rajiv Kumar Porwal: Director (System Operation), Grid-India Details 8Coal Supply for Power Sector Comfortable in July: Govt Details 8India's Coal Stocks Enough for 62 Days as Supply Strengthens Details 8Breaking Data Silos: MoP’s draft framework standardises information sharing across the electricity value chain Details 8Loops Within Loops: India’s meshed power grid Details 8Picking up Pace: Leveraging the balancing, storage and ramping benefits of hydropower Details 8Maharashtra sugar mills earn over Rs 8,250 crore from ethanol and power generation Details 8Why privatising electricity distribution could be a mistake Details 8Why Power Grid Corporation of India Share Price Is Falling Details 8India’s EV industry to create 30-40 million jobs by 2030 Details 8India Inc Bets Big on Tech: Data Centres and AI Drive 56% of Massive Rs 26.75 Lakh Crore Capex Surge Details 8India’s EV sector could generate up to 40 million jobs by 2030 Details 8Sonbhadra: Uttar Pradesh’s Energy Capital Transforming in 2026 Details 8IIFL prefers CG Power, ABB India, Siemens and L&T to Cummins India Details 8CPDL Enhances Power Reliability in Sector-31C with 1000 kVA Transformer Augmentation Details 8Torrent Power: Why Is It Betting on Gas Plants When Everyone Else Is Chasing Renewables Details 8India’s Coal Stocks Reach 148 MT, 62-Day Power Buffer Secured Details 8Reliance Power Stock Update: Shares Jump 3% on Strong Q1 Results Details 8India Crosses 300 GW Renewable Capacity, Targeting 500 GW by 2030 Details 8Microsoft launches Hyderabad cloud region to power India's AI economy, strengthen enterprise adoption Details 8POWERGRID Approves Rs 856.94 Crore Transmission Upgrade Project in Tamil Nadu Details 8NTPC-SAIL JV Selects U-Solar Clean Energy for Rs 127.47 Crore 20 MW Floating Solar Project in Bhilai Details 8India's coal supply adequate, production rises by 7.51% in July Details 8First Coal Consignment from SCCL’s Odisha Mine Reaches Telangana, Marks Historic Milestone Details You can also click on Newsclips for moreDetails