All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Jul 2026

8The Gujarat regulator has frozen FY2026 tariffs after independently reversing the licensee's projected revenue gap into a sizeable surplus. Details
8Adani Power said its expansion programme exceeds Rs 2 lakh crore and will require an interim debt-market contribution of about Rs 60,000 crore after projected fund flow from operations of more than Rs 1.4 lakh crore over the programme period. Management expects expansion capex of about Rs 25,000 crore in FY27, Rs 33,000 crore in FY28 and more than Rs 35,000 crore thereafter, while seeking to keep net debt-to-EBITDA between two and three times. Details
8The critical-minerals outlook says restrictions on battery materials, equipment and technology threaten grid storage, electric vehicles, data centres and defence supply chains together. Details
8The EAC has recommended environmental clearance for the Rs 14,952 crore Nivakane integrated pumped-storage project in Satara, subject to specific safeguards, even as newly proposed components sit about 0.15 km from the Sahyadri Tiger Reserve buffer. Details
8The EAC has sent the two basin studies back for new data and basin-specific analysis after finding that they did not properly assess carrying capacity in river systems exposed to landslides, flash floods and GLOFs. Details
8Adani Power is studying whether its Bina site can meet nuclear-project requirements and is evaluating domestic and overseas technologies, but it said no project has been planned and decisions depend on rules that the government has not yet issued. Management referred to a 10 GW nuclear ambition by 2035 and estimated at least five years for execution once conditions are clear. Details
8THDC proposes to use the Kalu River for initial filling and evaporation losses at its 1,200 MW Malshej Ghat PSP, but the EAC team found the inspected reach dry except for one 40-metre pool. Details
8The Ombudsman set aside the consumer forum order and directed recovery from the responsible UPCL staff after finding that IDF billing continued for 24 cycles when only the first two could lawfully be charged to the consumer. Details
8The EAC has recommended specific ToRs for THDC's Rs 8,470.89 crore Humbarli Birmani pumped-storage project after an eco-sensitive-zone NOC removed the obstacle that caused its April deferral. Details
8Adani Power raised its capacity ambition from 42 GW to 45 GW on the same timeline and gave a near-term commissioning sequence: the 1,320 MW Korba Phase II project is expected before December 2026, followed by the first 800 MW Mahan Phase II unit in Q1 FY28 and the second unit normally six months later, although the company is trying to advance it to Q2. Details
8Both principal exchange products reached the ceiling for hours, while daily averages of Rs 4.81 and Rs 4.35 per kWh concealed the late-evening scarcity. Details
8BGR Energy approved up to Rs 29 crore of unsecured loans from its managing director and up to Rs 150 crore of secured or unsecured promoter-group loans, with a conversion option subject to approvals. The company reported a standalone Q1 loss of Rs 226.07 crore on operating revenue of Rs 15.30 crore, while finance costs reached Rs 203.79 crore and auditors said unresolved NARCL assignment terms create material uncertainty over going concern. Details
8One day of inter-regional deviation produces a Rs 34.96 crore Western Region receipt and Rs 31.48 crore Southern Region charge
8Western Region's inter-regional deviation account swings to a Rs 71.80 crore net receipt in the week ended 19 July
8Eastern Region's weekly deviation pool retains Rs 51.17 crore after Rs 359.69 crore of payables
8Madhya Pradesh receives Rs 27.67 crore from Western Region's deviation pool while Chhattisgarh owes Rs 29.09 crore
8China's mineral export controls push European gallium and heavy-rare-earth prices to five times domestic levels Details
8BHEL says viral 1,200 kV transformer "breakthrough" is recycled news from 2011
8POWERGRID buys the Bhadla-Ramgarh SPV for Rs 12.86 crore to add bays at three substations
8KEC's transmission business reaches a Rs 23,000 crore backlog after Rs 17,700 crore of FY26 orders
8ERPC corrects NVVN-Bhutan's reactive-energy bills after an erroneous calculation
8Bihar and Jharkhand collect the largest shares of Eastern Region's Rs 36.51 lakh reactive-energy pool Details
8Western Region carries 21.19 GW of generation outages, but only 8.41 GW is forced Details
8Coal stocks remain at 60 percent of normative levels as 33 power plants enter the critical list
8IEA sees a 25% copper shortfall in 2035 as China's share of critical-mineral refining concentration rises again
8Vedanta Power's sales jump 38% as Meenakshi shifts toward domestic coal and Talwandi raises availability to 86% Details
8NTPC's 1,500 MW Amba project would use 112.56 ha of forest land despite selecting the least-forest layout
8Novarion's 1,200 MW Ranavadi project gets study terms before its 29.87 ha forest-diversion application is filed
8THDC's Humbarli Birmani design would discard 40.77 lakh cubic metres of muck in the Western Ghats
8Amba's environmental inspection finds nearby villages outside submergence-but leaves landslide and spring risks open
8Humbarli Birmani's capacity has risen 50% beyond its Maharashtra MoU while the amendment is still pending
8UJVNL's 81 MW Arakot Tiuni hydro scheme enters environmental study with a nine-kilometre headrace tunnel Details
8CERC proposes a Khavda licence amendment for Sarjan Realties' 1,100 MW connection at KPS3
8CERC fixes a declining Rs 84.27 crore-to-Rs 76.11 crore annual charge path for Northern system-strengthening assets
8CERC proposes a separate Dhule RTM licence for Adyant Enersol's 94 MW grid connection Details
8UPERC ties renewable-generator interest to each PPA's bill due date, exposing non-uniform payment-default terms
8CSERC sends biomass developers' five-year PPA extension back to CSPDCL after they offer unchanged energy charges
8UPERC asks why a Rs 4.95 per kWh ceiling and total-power APPC were used for waste-gas and slop renewable PPAs
8Uttar Pradesh's 5 percent biomass co-firing claim goes to CEA without a verified cost or plant-modification case
8Bihar regulator questions a Rs 3.46 per kWh renewable bid and an RPO deficit built on a two-year-old letter
8East Central Railway's additional 70 MW open-access request remains tied up in Bihar's NOC process
8CSERC moves the prosumer agreement into the domestic service application to remove a net-metering bottleneck
8A 1 MW solar plant seeks Rs 1.44 crore after module degradation, but repowering consent remains unresolved
8Punjab seeks to carry a provisional renewable-obligation surplus into FY2027 before final compliance is settled
8NTPC's Uttar Pradesh distribution-network transfer cannot proceed until a joint survey and revised estimate are filed
8UPERC approves KSK Mahanadi's change to JSW Mahanadi but bars any commercial effect on Uttar Pradesh buyers
8Three Uttarakhand consumer orders separate corrected billing, recoverable dues and a solar-property transfer gap Details
8Inox Wind wins Rs 1,600 crore NLC order as its turbine backlog reaches 4.7 GW
8Energy-cost anxiety jumps 13 points in India as global confidence in AI-ready grids falls to 35 percent
8Western Ghats site inspections become a standing environmental gate for pumped-storage proposals
8Government-change approvals push Orient Green's 25.4 MW solar and repowering programme to September
8NTPC Green adds the final 50 MW solar tranche to a 100 MW round-the-clock project in Rajasthan
8REC transfers Shongtong transmission SPV to Terralight Solar for Rs 20.41 crore
8India's interstate renewable fleet produces 436.59 MU in a day from 62.43 GW of listed capacity
8O2 Renewable's Glenmark solar project misses its P90 generation case as leverage remains above six times Details
8Orient Green's 1 GW target loses its 2028 deadline as management searches for capital and acquisitions
8Mumbai Metro One insolvency petition withdrawn after NARCL restructuring, but revival remains possible on default
8Schneider lifts its 2026 target after data-centre demand drives record first-half revenue and a 244% cash-flow jump
8Suzlon's record 506 MW delivery masks a 358-basis-point margin fall as its new platform absorbs upfront costs
8L&T's order book reaches Rs 7.79 trillion even as Middle East disruption cuts its first-quarter margin Details
8GE Vernova T&D's Rs 21,456 crore backlog and 27% margin trigger a rating upgrade and Rs 1,000 crore expansion plan
8More than one million Chinese EV exports remain unsold abroad as global auto-industry profits fall 65% Details
830 July 2026: UPERC continuation hearing in Petition 2349/2026 on late-payment surcharge and connected matters.
830 July 2026: UPERC hearing in Petition 2377/2026 after filing of a supplementary PPA to clarify the project district.
830 July 2026: UPERC hearing in Petition 2389/2026 after UPPCL was directed to file generating-unit configuration and commissioning dates supporting a 20.4 MW bagasse supply.
84 August 2026, 3:30 pm: CSERC hearing on Jindal Steel's distribution ARR, FY2027 retail tariff, FY2026 revised estimate and FY2025 true-up in Petition 18/2026.
84 August 2026, 3:30 pm: CSERC hearing on Jindal Steel's transmission ARR, FY2027 transmission tariff, FY2026 revised estimate and FY2025 true-up in Petition 17/2026.
813 August 2026: UPERC hearing in Petition 2340/2026 on degraded-module replacement and claimed generation-loss compensation for Dhruv Milkose's 1 MW solar plant.
819 August 2026, 11:30 am: PSERC hearing in Petition 58/2026 on carrying PSPCL's provisional FY2026 RPO surplus into FY2027.
820 August 2026: Last date for objections in CSERC's suo motu BSP township tariff proceeding, Petition 27/2026.
820 August 2026: UPERC hearing in Petition 2363/2026 on UPPCL's renewable-tariff amendment and the basis for a Rs 4.95 per kWh ceiling.
820 August 2026, 11:00 am: UPERC hearing in Petition 2402/2026 on provisional tariff for 21 MW supply from the Kuberpur waste-to-energy plant.
821 August 2026, 3:30 pm: CSERC hearing in the BSP township tariff proceeding after the licensee missed its filing deadline.
825 August 2026, 11:30 am: BERC admission hearing in Case 33/2026 on renewable tariff adoption after deficiencies in the Rs 3.46 per kWh bid and RPO need case.
81 September 2026, 11:30 am: BERC hearing in Case 21/2022 on the NOC for East Central Railway's additional 70 MW long-term open access.
83 September 2026: UPERC hearing in Petition 1181/2017 after reply and rejoinder deadlines in the Shaurya Power Tech recall matter.
88 September 2026: UPERC hearing in Petition 2246/2025 on Rosa Power's MYT and additional-capex case.
815 September 2026: UPERC hearing in Petition 2308/2025 after CEA vetting of LPGCL's 5 percent biomass-blending technical and cost case.
822 September 2026: UPERC hearing in Petition 2372/2026 after the joint survey and revised estimate for the NTPC distribution-network transfer. Details
 For reference purposes the website carries here the following tenders:
 
8Tender for work of EHV bays strengthening for capacity enhancement of 220kV line Details
 
8Tender for rate contract for the work route alignment, detailed survey, land scheduling and soil investigation work Details
 
8Tender for procurement of earthing leads and rods for 400 kV voltage level Details
 
8Tender for procurement of 30 Gbps upstream internet bandwidth Details
 
8Tender for C puncture insulator detection PID scanning of porcelain insulator for various Details
 
8Tender for B puncture insulator detection PID scanning of porcelain insulator for various Details
 
8Tender for puncture insulator detection PID scanning of porcelain insulator for various transmission lines Details
 
8Tender for construction of 60000 liters RCC OHT and bore well with 15HP submersible pump set Details
 
8Tender for construction of dropper line support, bus & kiosk platform Details
 
8Tender for supply, erection, testing, stamping and commissioning of un manned road weighbridge of 100 MT capacity Details
 
8Tender for material handling work Details
 
8Tender for supply of single phase duplex scanner Details
 
8Tender for rate contract for supply of 33 kV and 11 kV vacuum interrupter Details
 
8Tender for providing fixing and installation of yard fencing Details
 
8Tender for supply, erection and commissioning of bucket wheel body with shaft for stacker cum reclaimer installed Details
 
8Tender for procurement of power pack diesel engine locomotive available Details
 
8Tender for procurement of 225 KW, 3 phase, 6.6 kV, 978 RPM, coal mill motor Details
 
8Tender for procurement of thrust bearing of bearings for BFP model FK6D30 and booster pump model Details
 
8Tender for procurement of spares for hydraulic coupling Details
 
8Tender for procurement of DCSIM can transceiver for ESP PLC installed Details
 
8Tender for assistance in day to day work of various Details
 
8Tender for procurement of various rating of spare motors Details
 
8Tender for procurement of boiler tube bends for boiler of 1X500MW unit Details
 
8Tender for SITC of complete heating system Details
 
8Tender for procurement of HT power cables Details
 
8Tender for item rate for day to day civil maintenance work water supply system Details
 
8Tender for work of installation of cable tray with support hanger in main and branch cable trenches at 132/33 kV GSS Details
 
8Tender for painting of switchyard equipment, support structure etc. in switchyard at 132/33 kV GSS Details
 
8Tender for naming of 132 kV, 33kV feeders in their respective bays and structure and equipment Details
 
8Tender for urgent requirement of 132/33 kV 50 MVA and 20 MVA power transformer accessories at 132/33kV GSS Details
 
8Tender for overhauling, testing etc. of one no. 132/33 kV, 50 MVA IMP make power transformer Details
 
8Tender for complete overhauling work of 150 MVA, 220/132 kV auto transformer Details
 
8Tender for repairing of roof leakage, drain, APP work etc Details
 
8Tender for repair maintenance of collapsed and woven wire fencing Details
 
8Tender for Re construction of damage retaining wall and stone pitching of tower Details
 
8Tender for shifting of route 11kV link line Details
 
8Tender for supply erection commissioning and testing of electrical equipments Details
 
8Tender for annual maintenance contract for carrying out work of dismantling, erection & other allied activities in planned outage & emergency/breakdown for power transformers Details
 
8Tender for biennial maintenance contract for the work of restoration of collapsed towers in emergency/breakdown situation of EHV lines Details
 
8Tender for proposed 110kV substation Details
 
8Tender for erection, maintenance and dismantling work of overhead HT/LT line Details
 
8Tender for repair of non-star rated transformers of 11 / 0.433kV damaged aluminium wound distribution transformers Details
 
8Tender for erection of tower structures, beams and bus-bars for various 220kV/132kV substations Details
 
8Tender for construction of all technical civil works of 66 kV S/S Details
 
8Tender for engagement of agency for carrying out operation and maintenance of 33 kV overhead underground network Details
 
8Tender for supply of crusher hammer set Details
 
8Tender for construction of soild waste management yard Details
 
8Tender for work for raising the height of 132kV SC from 220kV sub/stn Details
 
8Tender for work of servicing & repairing of window AC, split AC and water coolers Details
 
8Tender for BRC for work of rewinding and overhauling of 11kV HT motors of MV/NVT pumps Details
 
8Tender for work of repair and dynamic balancing of shafts and impellers of 20 cumec pumps Details
 
8Tender for erection of HT/LT/TC maintenance and crossing Details
 
8Tender for protection and strengthening of tower no 179 of 132 kV line Details
 
8Tender for supply, fabrication, repair and replacement of 4 Nos. damaged trash rack panels Details
 
8Tender for protection work near surge shaft Details
 
8Tender for restoration of switchyard Details
 
8Tender for extension of existing control room with ACP puffed panel Details
 
8Tender for supply of wireless LCM kit for 220kV and 66kV class switchyard Details
 
8Tender for supply of network cables for network maintenance Details
 
8Design, supply, installation, retrofitting, testing and commissioning of 220kV bus bar panel/scheme, 220 kV bus coupler relay Details
 
8Tender for fabrication work of weather protective shed/canopy on foundations of boiler side HT & LT motors Details
 
8Tender for rerouting existing of 11kV OH line Details
 
8Tender for constructing 11kV feeder Details
 
8Tender for construction of TR No-3 bay foundations, cable trench and other misc. civil works Details
 
8Tender for construction of transformer and feeder bay foundations, oil sump with pipe line Details
 
8Tender for construction of 33/11 kV GSS along Details
 
8Tender for construction of 33/11 kV GSS alongwith associated 33 and 11 kV lines works Details
 
8Tender for construction of 33/11 kV GSS Details
 
8Tender for erection of 33kV line Details
 
8Tender for construction of 33 /11 kV sub station Details
 
8Tender for services for the replacement of the BFP cartridge assembly Details
 
8Tender for procurement of LSHS for various power plants Details
 
8Tender for stringing of of 2nd circuit of 220kV line Details
 
8Tender for construction of 3rd additional 160MVA TF plinth and allied civil works Details
 
8Tender for construction/shifting of HT/LT line and 11/0.4 kV S/s Details
 
8Tender for supply of spares for various cranes Details
 
8Tender for service contract for various C and I related overhauling jobs Details
 
8Tender for biennial rate contract for maintenance and operation of hoist and EOT cranes Details
 
8Tender for repairing and maintenance work of ash pond Details
 
8Tender for evacuation of new 11kV OG feeder Details
 
8Tender for laying of 32 mm dia. earth rod for earth grid extension, construction of auxiliary Details
 
8Tender for erection of 02 nos 220 kV bay cable laying earthing and commissioning including other allied work Details
 
8Tender for AMC for the work of repair/overhauling/servicing & alignment of various make 220kV, 132kV & 33kV isolators Details
 
8Tender for procurement of 400kV grading capacitors for 400kV CBs Details
 
8Tender for work of nano technology based acid and alkali resistant nano-modified anti corrosive coating on transmission tower Details
 
8Tender for work of nano-technology based acid and alkali resistant Nano modified anticorrosive coating on various rusted Details
 
8Tender for AMC for replacement of installed failed converter transformer Details
 
8Tender for supply of various ratings of 24kV CT Details
 
8Tender for procurement of supply / spares parts (AMC) for maintenance, servicing & repairing of 220 VDC & 48 VDC battery sets and battery chargers Details
 
8Tender for work of annual maintenance contract for work of overhauling / servicing & alignment of various make 220 kV, 132 kV & 33 kV isolator installed Details
 
8Tender for providing RCC chamber with protection wall and cabin for installation of flow analyzer Details
 
8Tender for works for removal of unwanted scrap/pipes/plates etc. Details
 
8Tender for supply of acid bulk tank for DM plant Details
 
8Tender for supply of long range 350W LED flood light fixtures for coal handling plant Details
 
8Tender for supply, installation, testing & commissioning of conversion of 66kV line Details
 
8Tender for supply, installation, commissioning and testing of vibration monitoring system for continuous vibration measurement Details
 
8Tender for work of replacement of various spares of drive system of wagon tippler Details
 
8Tender for work of removal, supply and application of spray thermal insulation on drive turbines Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8POWERCON Group names Suresh Darade to lead renewable energy skilling Details
 
8Why India can't use all the renewable power it generates Details
 
8Around 6900 GWh power restricted from evacuation in FY26: Naik Details
 
8Rooftop solar could be answer to Bangladesh's power crisis Details
 
8MHI holds pre-bid meeting for final 10 GWh ACC battery PLI allocation Details
 
8Why India’s EV and Green Energy Push is a Windfall for Copper Stocks Details
 
8ACME Solar raises Rs 3,404 crore for FDRE project Details
 
8FinMin: India Needs Reforms for Evolving Global Challenges Details
 
8Pace Digitek Arm Crosses 300 BESS Containers Milestone Representing 1.5 GWh Storage Capacity Details
 
8Coal India Approves Rights Issue Investment In CIL Rajasthan Akshay Urja To Strengthen Renewable Energy Expansion Details
 
8India’s carbon market targets too modest to drive significant industrial decarbonization, says new report Details
 
8Emerson Ovation Software Selected by Adani for India’s Largest Battery Energy Storage System Details
 
8Power systems are our biggest opportunity.” – Susheel Todi Details
 
8AI data centres to add 26.3 GW to India's power demand by FY32: Govt Details
 
8NTPC CMD Gurdeep Singh Gets Six-Month Extension Details
 
8Policy support for generating more solar power Details
 
8Indian corporates to clock 9 pc aggregate revenue in FY27: Fitch Details
 
8Lithium-ion Battery Recycling Plant Setup in India: Cost, Process Flow, Machinery, DPR & Financial Guide 2026 Details
 
8India’s electricity demand is surging: How AI data centers and dwindling coal are testing India’s power grid Details
 
8The Rs 9 lakh crore grid upgrade: 3 transformer stocks expanding capacity by up to 400% Details
 
8Green Energy Stock Jumps 3% After Bagging Rs 1,600 Crore Wind Energy Order From NLC India Details
 
8India's AI data centre boom could attract up to $435 billion by 2030: Report Details
 
8L&T arm bags NTPC order worth Rs 10,000–15,000 crore for 1,600 MW thermal power plant in Chhattisgarh Details
 
8BHEL wins its largest-ever gas turbine order from Nigeria's Dangote refinery amid global competition Details
 
8India’s carbon market targets too weak to drive industrial transformation: Report Details
 
8No address yet for Tata Power's Odisha nuclear plant as site awaits nod Details
 
8India's biggest power producer NTPC plans to invest $178bn through 2037 Details
 
84 Fast-Growing Power Stocks in India to Watch Details
 
8India added 6,057.02 MW of wind power in 2025-26, the highest annual rise in the sector Details
 
8Mfg, power sector see sharp jump in June IIP Details
 
You can also click on Newsclips for more Details
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details
8PSPCL's Rs 296.70 crore transformer award converts one reverse-auction price into a common rate for five different manufacturers The auction compressed the lowest quote from Rs 86,500 to Rs 84,770.01 per unit, then PSPCL applied that same rate to four other suppliers who had bid higher. The 35,000-unit order splits into four 8,000-unit packages and one 3,000-unit package, spreading manufacturing risk across five factories. All five bids clustered within 0.5% of each other, showing convergent rather than distressed pricing.

8KPTCL's Rs 143.65 crore Chadchan transmission tender draws zero bidder participation at its pre-tender meeting No agency attended, and no query arrived by post, email or portal before the clarification deadline closed. The package bundles a new 220/110 kV substation with 90.408 km of associated 220kV and 110kV lines and seven terminal bays. Advance payment has been deleted entirely, forcing contractors to self-finance mobilization against a Rs 35.91 crore liquidity requirement.

8JdVVNL's Rs 100 crore, 4-lakh-pole tender gets a six-day extension without touching any commercial term The 9-metre PCC pole procurement moved its technical opening from 29 July to 4 August 2026, with all pricing, security and qualification clauses left unchanged. Price variation stays locked to a 1 June 2026 base date even though bidding now closes in August. Suppliers who delivered under 50% of a prior JdVVNL order face exclusion or reduced allocation on this one.

8NHPC's Rs 5,416.94 crore Sawalkot Lot-1 tender rewrites its insurance and hydro-mechanical rules after 147 days of extensions The package cost rose 5.6% after a capacity correction, pushing turnover and bid-capacity thresholds higher in step. Hydro-mechanical subcontractor approval now happens 12 months before that work begins rather than at bid stage, widening the pool of eligible lead bidders. The contractor's overhead-and-profit allowance on variations was simultaneously cut from 20% to 18.63%.

8NPCIL's Rs 43.20 lakh Rajasthan guest house design contract keeps the consultant on the hook until construction finishes The four-month design sprint is followed by an open-ended site-support obligation, with the final 5% fee tied to building completion rather than drawing delivery. No price escalation applies despite the extended tail. NPCIL also retains unrestricted rights to reuse the guest house and hostel designs for future repetitions at no separate fee.

8POWERGRID's Lakadia-II 765kV pre-bid tie-up asks contractors to commit before the project itself is won The pre-selected L1 bidder signs an exclusive MOU and cannot support any competing transmission bidder for the same corridor, yet receives a contract only if POWERGRID wins its own tariff bid. The IFB states a 27 July closing date while the portal and qualification annexure both point to 5 August — an unresolved conflict bidders must navigate. Full route and quantity data sit behind an NDA-gated document request.

8MahaSTU's Jalna Independent Engineer tender shows a GeM field and a contract clause disagreeing on performance security The GeM summary marks ePBG as not required, but Clause 34.1 demands a 10% Contract Performance Guarantee valid 90 days beyond final acceptance. The consultant's mandate extends into assessing cost reasonableness, time extensions and change-in-law claims — functions closer to dispute arbitration than routine monitoring. A 70-point technical cutoff under QCBS scoring precedes any price comparison.

8POWERGRID's Nawada-Durgapur TL02 tender repeats the pre-bid tie-up model for a second 765kV corridor Bidders need Rs 312 crore turnover and Rs 52 crore liquidity just to qualify, with subsidiary or parent-company credentials expressly barred from counting. The 27-month completion clock starts regardless of the contractor's conditional status. Full technical specifications, route length and tower schedule remain restricted behind an NDA.

8RRECL's Rajasthan EV charging RfP bundles installation with long-term operation under the PM E-Drive scheme The tender shifts from equipment procurement to full lifecycle accountability, covering deployment, uptime and maintenance across Category A and B charging packages statewide. Revenue and utilisation risk depend on traffic and demand assumptions the document leaves to bidders to model. The structure is likely to favour integrated operators over pure hardware suppliers.

8KPTCL's Dyagerahalli substation tender surfaces under the wrong procuring entity on its own portal listing The listing names Karnataka State Electronics Development Corporation Limited and describes the scope as a "computer laboratory," despite the actual package being a 220/66/11 kV substation with 28.784 km of associated 66kV lines. The query deadline sits 30 minutes after the bid-submission deadline, reversing normal clarification sequencing. Contractors must independently verify alignment feasibility across developed urban corridors before pricing.

8NPCIL's Rs 12.49 lakh Agroha township consultancy ties 80% of its fee to regulator-controlled approval milestones Payment for environmental consents releases through stages like "information of approval or intent of approval" — a threshold the tender never precisely defines. The 270-day approval window can extend by 90 days only at NPCIL's discretion, not automatically. Dual NABET accreditation across two separate sectors is mandatory, narrowing the eligible consultant pool sharply below what the small contract value would suggest.

8RVUNL's Rs 358 crore LSHS fuel tender restricts bidding to refinery-owning petroleum manufacturers The qualification framework favours integrated producers over traders or intermediaries, prioritising supply-chain control over price competition. Bid security is fixed at Rs 7.16 crore, reinforcing the utility's preference for financially resilient, execution-proven suppliers. The structure signals a broader strategic-fuel procurement approach built around reliability rather than lowest cost.

8MSEDCL's Rs 972.17 crore Kalyan-Bhandup distribution tenders let the utility reject an entire transformer lot on one failed sample test The two turnkey packages combine survey, supply, construction, GIS mapping and asset-tagging under indivisible single-point contracts. MSEDCL can select any power transformer for destructive short-circuit testing at the contractor's expense. Quantity variation runs as wide as 50% per item, and a single Rs 300+ crore completed project is required just to qualify through the one-contract route.

8WBSETCL's 200 MVA transformer tender adopts Revision-8 of its technical specification, tightening protection and monitoring standards The update adds digital RTCC relay provisions, expanded conservator protection, revised bushing current-transformer arrangements and dual DC supply requirements. Commercial terms remain untouched — the entire revision is engineering-focused rather than a pricing or risk-allocation change. The tighter specification is likely to favour established manufacturers with strong design-validation and testing infrastructure over smaller, price-focused bidders.

8
RECPDCL's Parli 765kV TBCB bid slips 37 days past its original deadline while the 24-month construction clock stays fixed
 
Amendment-III moves online submission to 2 September — the third date reset since the RFP's original 7 July closing. The Rs 21.88 crore bid bond and Rs 54.70 crore performance guarantee stand unchanged, and the winning developer still faces scheduled COD 24 months from the effective date. All principal elements — three 1,500 MVA ICTs, the 765kV LILO into the Warora–Parli corridor and two 400kV links — must commission together before 100% of the quoted 35-year tariff becomes recoverable.

8RECPDCL's 7,500 MW Lakadia Phase-II tender reaches its tenth amendment without touching a single technical clause
Amendment-X extends the bid deadline by a week, moving every downstream milestone — technical opening, reverse auction, LOI, SPV transfer — in step. The HVDC-ready substation, synchronous condensers, 36-month COD and all qualification and security terms remain exactly as the original RFP set them.

8RECPDCL's 14 GW-linked Nasik package gets its eighth amendment one day before the bid deadline
The amendment adds seven days for submission, but LoI shifts eight days against seven for SPV transfer — leaving just 11 days to convert a Rs 36 crore bid bond into a Rs 90 crore performance guarantee. Qualification stays at Rs 1,800 crore experience and Rs 720 crore net worth, with the 36-month COD untouched.

8GUVNL splits November's 1,000 MW into two 15-day blocks a day after the RFP went live
The corrigendum keeps the month's quantum and 720 hours intact but raises requisitions from six to seven, letting different suppliers and tariffs clear each half. The bid deadline stays put with no extra preparation time, and the penalty regime — 20% of tariff on excess shortfall, double-tariff damages for diverted capacity — applies unchanged to both blocks.

8SECI's 5,290 kW rooftop RESCO tender locks in 25-year fixed tariffs before developers can fully survey the buildings
Ceiling tariffs run from Rs 4/kWh to Rs 6.40/kWh across eight projects in six states, yet detailed site due diligence is allowed only after LoA and final capacity is fixed at PPA signing. PPAs sit with eight separate institutions rather than SECI, and the 2,000 kW IIT Mandi package adds zero-export, behind-the-meter complexity.

Details
8Solar curtailment reached 2,417 GWh in April, 3,235 GWh in May and 2,481 GWh in June 2026. The three-month total turns a recurring operating intervention into a material integration problem for generators, networks and market design. Details
8CEA projects an all-India surplus for 2026-27 while the Southern and Eastern regions together carry 14,065 MW of forecast peak deficits. The risk is sharpened by the previous LGBR overshooting actual peak demand by 8.9 percent, making transfer capability and local constraints central to the new outlook. Details
8Sardar Sarovar's 400 kV network has operated above 420 kV for 15-20 percent of the recorded winter period, with a maximum of 427 kV. River Bed Power House machines are absorbing reactive power as synchronous condensers while unavailable reactors and delayed network works leave the generating station bridging the control gap. Details
8Maharashtra reported load shedding on 11 June days, including a 1,850 MW maximum on 27 June, while it also persistently over-drew during low frequency from 25-28 June. Low Koyna storage, roughly 2,000 MW of forced outages and unavailable real-time power turned a state supply squeeze into a regional security problem. Details
8The Northern Region's simultaneous import ATC falls from 27,950 MW to 18,850 MW during the 09:00-16:00 solar window in the July 2027 study. Low voltages and N-1 loading risks mean the region's transfer headroom contracts precisely when renewable output changes the direction and scale of flows. Details
8CEA's daily monitor shows 10,987.30 MW unavailable out of 20,122.42 MW of gas and liquid-fuel capacity, while maximum output reached only 37.66 percent of fleet size. The Western Region outage ledger adds the commercial layer: several gas units have remained stranded for years by missing PPAs, expensive fuel or related constraints. Details
8IEX's real-time market scheduled 198.10 GWh against 178.18 GWh in the day-ahead market on 28 July. Weighted real-time prices were lower by about Rs 1.03 per kWh even though at least one block in both products reached Rs 10 per kWh, exposing the difference between daily averages and scarcity intervals. Details
8The advanced-chemistry-cell programme has awarded 40 GWh of capacity, but domestic value addition remains below 60 percent. With only a 1.4 GWh plant commissioned and a separate 10 GWh grid-storage allocation under way, the policy test is shifting from awards to manufacturing depth and deployment. Details
8The national rooftop programme has recorded 75,25,418 applications and 39,72,447 installed systems covering 48,02,717 households. The gap is not a direct rejection rate, but it shows the scale of the conversion task as the government pushes discom processes, finance and subsidy delivery. Details
8Suzlon delivered a Q1 record 506 MW and reported an order book of about 6.1 GW, but 1,257 MW of erected turbines still awaited commissioning. The distinction between delivery, erection and grid commissioning now determines how quickly the operational pipeline can become recognised output and revenue. Details
8L&T's Energy Green order book reached Rs 146,700 crore, with 97 percent tied to international work, after offshore-wind orders lifted inflow. At the same time, solar supply-chain disruption following the West Asia conflict weighed on segment revenue, placing concentration and execution risk beside the backlog. Details
8The Vapi-II-Sayali double-circuit line was charged in August 2024 and dismantled the following month because of a helipad. Diversion approval in May 2026 produced no tangible progress in the OCC record, moving the case from engineering delay into performance accounting. Details
830 July: KSEB plans trial charging of the new 110 kV Periyattadukkam-Kuttikol double-circuit line and Kuttikol substation in Kasaragod. Source: KSEB public notice, OCR recovery, note 105.
831 July, 11:00 am: SECI second pre-bid meeting for the 500 MW x two-hour CfD peak-supply tender. Source: note 094.
811 August: Last date for objections to PSPCL's rooftop-solar Regulation 11.13 amendment petition. Source: note 149.
812 August, 11:30 am: PSERC hearing and public hearing on Petition 57/2026. Source: note 149.
821 August, 11:30 am: BERC next hearing in Case 11/2026, Sonika Sinha v SBPDCL officers. Source: note 239.
88 September, 11:30 am: BERC next hearing on BGCL's capital investment and capitalisation petition, Case 25/2026. Source: note 241.
86 October: BERC next hearing in APTEL-remanded Case 49/2025. Source: note 240. Details
8Five live KPS-3 bays trigger a fight over early commercial operation before the linked scheme is ready
8PTCC clearance ends, but transmission projects still face an unsettled replacement approval path
8Storage and series-compensation assets now enter the availability ledger element by element
8A court-driven line-safety fix may shift Rs 18 crore and outage risk to transmission beneficiaries
8WRPC widens AUFLS inspections because its own team cannot cover the region
8Four missed Gujarat and Goa reviews leave constraint-relief schedules without current scrutiny
8Utilities approach the IEGC self-audit deadline with submissions still missing
8Salegaon's August target still lacks a quantified gain in Goa transfer capability
8Jodhpur Discom lets BSNL batch Bharat Net connections with Rs 8,200 deposits
8Coal India and NTPC reset senior roles across marketing, human resources and the top office Details
8Deferred awards slow L&T's conventional-energy order inflow even as backlog exceeds Rs 2.21 lakh crore
8L&T folds power-development arm into the parent after Nabha exit and metro divestment deal
8Coal India beats its quarterly capex target as evacuation projects absorb Rs 949 crore
8Om Infra emerges L1 for Rs 568.98 crore Mahanadi barrage and irrigation package
8PFC Consulting creates Benchigere SPV to launch tariff-based bidding for Tumakuru's 400 kV system
8Suzlon appeals SEBI penalties as Rs 15.95 crore exposure shadows a strong operating quarter
8Suzlon says no known event explains material share-price movement on July 28
8Orient Electric lifts Q1 profit 79.7% as consumer-electrical revenue grows 22.7%
8Ratings Watch: Kalpataru Projects receives an unsolicited ESG score of 56, assessed as Adequate
8Alfa Transformers reshuffles audit roles as internal auditor moves into the statutory mandate
8Inox Wind wins Rs 1,600 crore NLC turnkey order for 200 MW
8O2's captive solar tariff stays fixed while Maharashtra banking rules remain stayed
8SEIL contracts 97 percent of capacity while Rs 8,000 crore remains outstanding Details
8Discoms get Rs 4,950 crore incentive architecture for the first 18 GW
8Centre acknowledges rooftop-export complaints but leaves settlement to state rules
8Centre rules out Odisha offshore wind action after weak resource economics
8MNRE has no wind-blade EPR plan beyond 2016 disposal guidelines
8Eastern UP green corridor completes 4,120 MVA of 10,440 MVA programme
8India's EV incentive stack has no national 2047 fleet target
8MNRE says oversized solar panels need not breach sanctioned AC load
8SECI calls second bidder meeting for 500 MW renewable CfD tender
8Model Solar Village declarations reach 455 districts without proving delivery
8Jharkhand converts only 3,106 of 10,186 rooftop-solar applications
8Maharashtra installs 5.52 lakh of 5.75 lakh sanctioned KUSUM pumps
8Renewable forecasts are being built on missing telemetry and a model change as Maharashtra starts daily penalties
8Wind edges solar as renewables generate 1,193 MU in a day, led by the Southern Region Details
8KSERC leaves KINESCO with Rs 124.67 crore FY25 surplus after limited review
8PSPCL asks PSERC to replace a second rooftop agreement with the portal contract
8Tamil Nadu Ombudsman restores a name-transfer application with a 15-day deadline
8BERC sends BGCL's capital plan to public scrutiny within one week
8BERC seeks High Court records before hearing an Ombudsman non-compliance claim
8BERC keeps APTEL-remanded BGCL case under data scrutiny until October Details
8Teesta III's entire 1.2 GW fleet remains offline nearly three years after the Lhonak disaster
8Bus fault knocks all 510 MW of Teesta V off the grid before a same-hour restoration Details
8Linked power-plant coal stocks fall by 260,800 tonnes in a day while cover holds at 15 days Details
8Two towers on a two-year-old 400 kV line collapsed, but the weather explanation remains under review
8Gujarat is switching and dispatching around an 800 MW corridor after permanent outlets slipped 15 months
8Western utilities must turn repeat line trips into a cause-and-correction ledger
8A 660 MW Khargone overhaul has no agreed window as supply delay collides with two states' peak seasons
8Four overlapping 765 kV outages require a separate WR–ER corridor coordination plan
8Tower restoration still needs inspector approval because OCC could not waive a statutory safety step
8Western Region has a generator outage plan but still lacks the matching transmission programme
8Large units are leaving service without the agreed outage code, weakening control-room coordination
8A 30-day evacuation-line shutdown has produced a regional template for sharing outage risk
8Emergency-restoration readiness remains incomplete more than a year after the regional direction
8Dehgam's ageing control room forces a protection migration with future tariff recovery at stake
8Forced outages dominate Eastern Region's 5.53 GW unavailable generation stack
8Bandel's 215 MW Unit 5 faces a six-week forced outage under critical technical constraints
8Boiler and valve failures remove four western units while ACBIL remains out for low coal stock
8Forced losses make up most of Southern Region's 13.14 GW outage stack Details
8Fifth wrong-line operation puts Western grid switching controls and outsourced crews under scrutiny
8Gujarat used 49 switching operations to contain 434 kV conditions while generator VAR visibility remained incomplete
8Western frequency quality worsened despite zero reported regional peak shortfall
8Chhattisgarh's largest June curtailment came after midnight as outages exhausted replacement supply
8Maharashtra is the only Western state without WRLDC's 220 kV network-model coverage
8Generators say governor mode is active, but WRLDC still sees inadequate primary response
8Plants are completing overhaul windows without the full five-year Grid Code test suite
8State generators still offer no AGC dates despite the above-200 MW mandate
8Grid-India's harmonics rule moves to stakeholder review, with comments due in ten days
8Western Region exported 10,333 MU but fell 732 MU short of its June schedule
8India meets a 242.31 GW daytime peak before a 235 MW evening shortfall emerges in the Northern Region
8Nearly 49.53 GW of generation remains unavailable as the grid enters the evening peak
8Forced outages make up 33.05 GW of CEA's 56.57 GW unavailable generation fleet
8Coal fleet carries the system with 32.42 GW unavailable and output at 76.6% of monitored capacity
8Monitored generation beats the daily programme by 222.87 MU as western and southern output runs ahead
8Grid operator schedules 43.51 GWh upward through SCUC while ancillary dispatch leans sharply downward
8Coal units carry the D-1 SCUC stack while high-cost gas stations remain uncommitted
8Grid frequency spends one-quarter of July 28 outside the 49.90-50.05 Hz band
8Inter-regional corridors avoid violations even as three 765 kV nodes run high for double-digit shares of the day
8Eastern Region clears a 30.21 GW peak without shortage as Bihar and West Bengal set the load shape
8Southern Region meets a 56.57 GW evening peak with no shortage as wind supplies 244 MU
8Telangana undershoots its daily energy forecast by 14.57 MU, accounting for the Southern Region gap
8Huliyurdurga 400 kV hub is energised with two 500 MVA transformers and four line connections charged
8Cable-termination failure cuts supply at RVPPL PSS-2 and removes 81 MW for more than two hours
8Tower collapses and highway works keep four major Southern Region corridors constrained
8Fault-level controls and unfinished protection work shape Western Region's long-running transmission outage book
8Southern Region's 21.3 GW import capability rests on three angular-stability corridors and Gazuwaka voltage
8Gujarat's July 2027 solar-hour import capability falls 526 MW below approved GNA
8Maharashtra enters July 2027 with only 336 MW of import headroom over effective GNA
8Goa's import headroom narrows to 32 MW as studied voltages approach 0.9 per unit
8Punjab gets 5.2 GW of short-term import margin despite multiple N-1 bottlenecks
8Tamil Nadu-Puducherry interface retains 5.28 GW of short-term margin despite local N-1 constraints
8Kerala carries 1.78 GW of July 2027 import margin with Kozhikode and Thrissur contingencies setting the ceiling
8DNHDDPDCL retains only 139 MW of short-term import margin under two local contingency limits
8Assam's evening import headroom shrinks to about 100 MW under Rangia voltage and Bongaigaon-Mirza limits
8India-Bangladesh export corridor leaves only 18 MW beyond approved access for July 2027
8Bhutan import headroom narrows to 145 MW as Birpara contingencies and low voltage set the limit
8A single 132 kV contingency caps the Uttar Pradesh-Nepal corridor at 50 MW Details
8Solar supplies most of the roughly 26 GWh scheduled through IEX green day-ahead market
8High-price day-ahead market draws 37.85 GWh of sell offers but no buyers
8PXIL real-time price reaches Rs 10 per kWh as thin-volume reports require reconciliation
8PXIL intraday auction attracts buy interest but no sellers, leaving the market uncleared
8Multiple PXIL short-term products remain inactive on July 28
8Green term-ahead blocks trade near the Rs 10 per kWh ceiling on IEX
8Eastern-region term-ahead power trades at Rs 6.40 per kWh in 1,200 MWh daily contracts
8RGPPL's three-week grid-support bill crosses Rs 174 crore across SCUC and TRAS
8RGPPL captures two-thirds of Western Region's Rs 91.88 crore weekly SCUC bill
8Western reserve settlement runs into tens of crores as service directions diverge
8North-Eastern DSM pool closes the week with a Rs 14.73 crore balance as inter-regional deviations dominate
8TRAS dominates North-Eastern reserve costs as SCUC refunds offset part of the weekly bill
8Sitac Kabini seeks Rs 22.27 lakh DSM refund after revised liability shifts to Manikaran
8Western reactive-power behaviour created weekly credits at VSTPS and Rewa
8Ranganadi, Palatana and HVDC BNC lead Northeast reactive-energy credits Details
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details
 For reference purposes the website carries here the following tenders:
 8
Tender for construction of cable trench covers slab for switchyard Details
 
8Tender for supply of 01 No hydraulic ACSR conductor Details
 
8Tender for procurement of pulse jetting solenoid valves, 3 way solenoid valves Details
 
8Tender for procurement of spares of electro pneumatic smart positioners for control valve Details
 
8Tender for supply and replacement of NDCT components for 1x 800 MW Details
 
8Tender for construction of control room foundations Details
 
8Tender for requirement of various size and types of conveyor belt rollers for coal handling plant Details
 
8Tender for supply of various spares for SWAS system of boiler Details
 
8Tender for fresh electrical modular wiring Details
 
8Tender for repair, maintenance, and upkeep of the 11kV overhead line Details
 
8Tender for complete repairing and full overhauling with spares of one 150 mtr head, 1000 GPM, 3 CHR, 200x150 MM multistage pump assembly Details
 
8Tender for erection of lighting line Details
 
8Tender for annual maintenance of the including civil repair works, water supply Details
 
8Tender for supply of 245kV class centre break isolators with and without earth switch Details
 
8Tender for operation and maintenance for electrical system Details
 
8Tender for procurement of 200MVA generator transformer Details
 
8Tender for estimate for the feeder 33kV feeder Details
 
8Tender for survey, installation, testing and commissioning of new 5 MVA 33/11kV substation Details
 
8Tender for procurement of advanced microprocessor based spare Details
 
8Tender for procurement of various MTM thermocouples installed Details
 
8Tender for procurement of spares of pneumatic cylinder installed in various Details
 
8Tender for procurement of consumables sealing sets for servicing of HP and LP bypass hydraulic actuators installed Details
 
8Tender for Re-tubing of tubular APH of boiler Details
 
8Tender for assistance for preparation and transferring chemical solution Details
 
8Tender for civil works at drill site Details
 
8Tender for relocation of existing 33kV switchyard Details
 
8Tender for civil works at drill site Details
 
8Tender for work of preventive maintenance of various 220 kV switchyard Details
 
8Tender for procurement of spares of dust extraction system Details
 
8Tender for construction of revetment towers constr of support trench Details
 
8Tender for Re-babbitting on 03 nos turbine guide bearing shells Details
 
8Tender for work of laying of tile and paver block Details
 
8Tender for supply of 3/.4kV, 1000 kVA, BIS mark EEL:2 (New), copper wound, distribution transformer Details
 
8Tender for work of replacement of deteriorated H-frame and mechanical strengthening and stub strengthening work of 66kV line Details
 
8Tender for Re-construction of other allied civil works to prevent the 33 kV S/Stn. Details
 
8Tender for overhauling of flue gas and air ducting and dampers Details
 
8Tender for erection for 66kV substation 66 kV substation S/C line Details
 
8Tender for erection for 66kV substation Details
 
8Tender for work of Dog to panther conversion of 66kV line Details
 
8Tender for repair of existing cable trench wall, old cover, making new cover etc. Details
 
8Tender for work of removal and transportation of coal mill reject and coal powder from coal Mill Details
 
8Tender for supply of gasket and work of dismantling, chemical cleaning & Re-gasketing of plate heat exchanger installed Details
 
8Tender for crate protection works d/s of headworks Details
 
8Tender for repairing of damaged spillway channel Details
 
8Tender for improvement/upgradation of canal head works Details
 
8Tender for repair/reconstruction of damaged RCC panels Details
 
8Tender for procurement of 100000 Nos PG clamps Details
 
8Tender for new construction of 33/11 kV sub station, 1x315 KVA capacity power transformer Details
 
8Tender for construction of 33/11 kV GSS Details
 
8Tender for transformer augmentation work of 31.5 MVA transformer and 132/33 kV bay Details
 
8Tender for construction of 132/33kV bay at 132 kV GSS Details
 
8Tender for construction of 1 Nos. 132 kV solar bay at 220 kV GSS Details
 
8Tender for construction of 1 Nos. 132 kV M/s green grid solar bay at 132 kV GSS Details
 
8Tender for construction of 1 Nos. 132/33 kV bay at 220 kV GSS Details
 
8Tender for requirement of spares of LP By pass HPSU, LP shut off and control valve Details
 
8Tender for supply of servo valves and its spares installed Details
 
8Tender for erection, dismantling transportation of poles, distribution transformers, HT/LT lines Details
 
8Tender for supply of HS type Str joint kit suitable for 33kV x630 sqmm Details
 
8Tender for work of preventive maintenance AMC of 132kV substation Details
 
8Tender for work of assistance in carrying out miscellaneous routine maintenance works of 220kV substation Details
 
8Tender for work of assistance in carrying out miscellaneous routine maintenance works of 132kV substation Details
 
8Tender for construction of miscellaneous civil works at 33/11 kV sub-station Details
 
8Tender for giving 800 KVA new connection to M/s sewerage treatment plant Details
 
8Tender for construction of other miscellaneous civil works Details
 
8Tender for procurement of different types of ropes and gaskets Details
 
8Tender for restoration and protection work of landslide Details
 
8Tender for construction of 33kV 2nd distribution bus and renovation of existing 33/11 kV substation Details
 
8Tender for procurement of 200 MVA, 220/132/33 kV, 3 phase auto transformers Details
 
8Tender for procurement of 400/220/33kV, 315 MVA auto transformers Details
 
8Tender for SITC of numerical line differential cum distance protection relay Details
 
8Tender for supply, installation, testing & commissioning of 250kVA diesel generator (DG) set Details
 
8Tender for resurfacing and maintenance of existing 500kV substation Details
 
8Tender for providing concreate flooring and allied repair work of 500kV store Details
 
8Tender for miscellaneous civil works for 500kV substations and switchyards Details
 
8Tender for providing & fixing of 20 + 5 spare cooling fan control cubicle with WTI & OTI with double power source Details
 
8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x50 MVA, 132- 110/33 kV T/F with allied civil works at 110 kV S/s Details
 
8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 25MVA, 132- 110/33 kV T/F Details
 
8Tender for work of supply installation and commissioning of wireless announciation and microcontroller Details
 
8Tender for supply of cooling fan motors of converter transformer installed Details
 
8Tender for supply of flap gate assembly with motorized linier actuator for coal handling plant Details
 
8Tender for supply of boiler tube and fittings Details
 
8Tender for supply of various fasteners and consumables Details
 
8Tender for supply of CPVC pipe & fittings Details
 
8Tender for work for replacement of various pulleys and its bearing at various Details
 
8Tender for work of erection of 66 kV S/C line Details
 
8Tender for work of residual life assessment study of removed HP, IP & LP turbine rotors Details
 
8Tender for supply of various types of bushings for 250 MVA, 420/15.75 kV, BHEL make generator transformers Details
 
8Tender for supply of various ratings LT motor Details
 
8Tender for supply of MS grill and fabrication & epoxy paint of stairs, railing , structure Details
 
8Tender for providing and laying concrete & steel cover for unit 1 to 5 boiler side Details
 
8Tender for work of Re-tubing of tube nests of LP heater Details
 
8Tender for work of repairing of various pulleys of conveyor belts Details
 
8Tender for supply of various size of gate valves, diaphragm valve Details
 
8Tender for supply of C&S ACB & panel spares Details
 
8Tender for services for lift operators Details
 
8Tender for work of rubber lining of various equipments, pipes and fittings Details
 
8Tender for biennial rate contract for works of online, preventive and breakdown maintenance of coal mills Details
 
8Tender for supply of gravimatric feeders Details
 
8Tender for supply of scraper bar for scraper chain conveyor system Details
 
8Tender for supply of electrical actuator for feed control valve Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Coal India’s Q1 Capex Rises 16% To Rs 3,399 Crore Exceeds Quarterly Target Details
 
8Chitranjan Kumar assumes charge as Director (Technical) at ECL Details
 
8Why Coal India Share Price is Falling Details
 
8Coal India announces cessation of Dr. Vinay Ranjan as Director Details
 
8India's Solar Generation Soars 57% in June, Outpaces Wind by a Wide Margin Details
 
8Why renewable energy will power India’s next generation of data centres Details
 
8Centre rules out offshore wind energy projects off Odisha coast Details
 
8NCLT Approves Inox Green and Authum Consortium Plan to Acquire WWIL Assets Details
 
8Suzlon Energy Q1 Net Profit Falls to Rs 305 Crore, Missing Estimates of Rs 400 Crore Details
 
8Rajasthan, California regulators sign MoI on grid modernisation and clean energy Details
 
8Brookfield Targets Southern India Projects To Avoid Grid Congestion Details
 
8AI data centres to add 26.3 GW to India's power demand by FY32: Govt Details
 
8India Curtailed 8,133 GWh of Solar Power Despite Record Summer Electricity Demand Details
 
8India's Industrial Output Accelerates To 7.3 Per Cent In June As Manufacturing, Capital Goods And Power Sectors Drive Broad-Based Growth Details
 
8Gujarat accounts for nearly one-third of India’s wind power output Details
 
8Koldam NTPC Hydro Project: Record Power Generation FY26 Details
 
8Coal India shares fall 3% after earnings miss but Jefferies finds valuations attractive Details
 
8Adani Power schedules in-person analyst meet in Mumbai on Aug 3 Details
 
8Industrial Production Jumps 7.3% in June, Driven by Manufacturing & Power Details
 
84.7 GW Order Book: Multibagger Suzlon Competitor Secures Rs 1,600 Crore Repeat Order from NLC India Details
 
8Tata Power expects to build its first nuclear plant as early as 2032 Details
 
8India’s Thermal Coal Imports Drop 27% in FY26 Details
 
8Solar power takes centre stage as 250 exhibitors meet in Nairobi Details
 
8Tripura: Rooftop solar capacity crosses 15 MW under PM Surya Ghar scheme Details
 
8Power Exchange Prices Near Zero: What It Means For Energy Stocks Details
 
8Gujarat CM commends power personnel for swift restoration of electricity supply after heavy rains: Jitu Vaghani Details
 
8Inox Wind secures a 200 MW turnkey order from NLC India Details
 
8NTPC extends tenure of Chairman & Managing Director Gurdeep Singh Details
 
8Jaiprakash Power Ventures announces cessation of Independent Director Smt. Vandana R. Singh Details
 
You can also click on Newsclips for more Details
 1 2 3 >  Last ›

Showing 1–50 of 557 items