8KSEB's Rs 65.87 lakh 110 kV upgrade deleted its 5 km experience threshold and took a bid 9.91% below estimate Terms and conditions XVIII required 110 kV work "for at least 5km length of line completed in last 7years"; corrigendum-3 removed the length and applied the change to all clauses stating experience. Three bidders were admitted — L1 Rs 59,34,453.02, L2 16.4% above, L3 26.5% above and rejected on rate. Special condition 18 sets defects liability at 60 months while clauses 1.9, 1.18 and the payment language repeat 36.
8SECI's 45.6 MW Ramagiri wind package issued Corrigendum-1 nine minutes after queries closed and four hours before the pre-bid meeting Queries shut at 10:00 RTZ on 27 July, the corrigendum is timestamped 10:09, the pre-bid meeting sat at 14:30, and the amendment wording appears nowhere in the record. EMD is Rs 8.4368 crore for domestic and international bidders alike, against a Rs 25,000 processing fee. The tendering pattern reads "Single Stage Two Envelope followed by e-ReverseAuction" while the portal's evaluation-mechanism field reads "Not Applicable". PBG, bid validity, LD and maintenance duration sit outside the notice.
8RECPDCL's ERES-47 765 kV corridor turns a Rs 55.32 crore bid bond into a Rs 138.30 crore guarantee within ten days of LoI A 150% step-up lands on the winner the moment tariff competition ends. Qualification runs Rs 2,766 crore aggregate capex at Rs 553.20 crore per project and Rs 1,106.40 crore net worth. Clause 2.5.7 puts site, geology, transport and grid diligence on the bidder with no relief after deadline, while BSPTCL's Nawada–Guraru works and space at Jeerat stay outside TSP control. Assets, land, ROW and clearances transfer at zero cost 35 years after COD.
8RECPDCL's Solapur/Paranda GIS RFP moved its bid date 34 days and left the rest of Clause 2.7.2 behind Submission goes from 7 July to 10 August, stranding technical opening, qualification, initial offers, reverse auction, LoI and SPV transfer at their original July–August dates. CPG is Rs 30 crore, net worth Rs 250 crore, aggregate capex Rs 600 crore at Rs 120 crore per project. Three LILOs on HPC conductor and a Quad Moose link to Pune West carry a fallback obliging the TSP to buy adjacent land if utility space runs short. LD is 3.33% of monthly charges per day for 60 days then 5%, against a 24-month COD and 98% availability.
8OPTCL's Palaspanga–Barbil package states its estimate as Rs 3.15 crore in the narrative and Rs 315.27 crore in Table-A The smaller figure is exactly one-hundredth of the portal value and identical to the EMD. Table-A items 12–16 run a day behind the portal, while the IFB puts soft copies at 11 August, hard copies at 11 August 11:01 and EMD at 10 August 11:00. Lot-I and Lot-II are labelled separately but "shall be treated as a single contract" — two GIS upgrades plus 1.2 Rkm cable and 69.2 Rkm of 220 kV line. Both inside 24 months from LoA, with e-reverse auction reserved under ITB clause 29.
8NSPCL's Durgapur coal-mill R&M restored 24 mandatory pump assemblies eight days before closing, having cut them to three Amendment No. 2 made the reduction; Amendment No. 4, issued 10 August against an 18 August deadline, restored the original BOQ figure. Amendment No. 3 fixed instrumentation at one instrument for OLCS and two for CLCS and protection. Errata No. 01 corrected the tender ID to 2026_NSPCL_273894_1. The deadline moved 102 days across sixteen corrigenda while the technical baseline was still changing, with eight pulverisers to be replaced inside existing space without disturbing boiler performance.
8PSPCL's Ferozepur RDSS package went to the bidder that was 6.9% dearer before the auction and the only one that quoted in it The BOQ chart had SKS at Rs 84.95 crore against Nucon at Rs 90.84 crore; in the auction Nucon quoted Rs 84.87 crore and SKS was "Not Quoted". Final evaluation records Nucon Rs 83.80 crore at rank 1 and SKS Rs 84.95 crore at rank 2 — 1.4% apart, 31.0% and 32.8% above the Rs 63.97 crore published value. Corrigendum no. 3 reframes the tender from four packages to three and package 5 disappears unexplained. Financial opening was November 2024, final evaluation August 2026.
8RECPDCL's Barmer-II HVDC tender set a Rs 5,728 crore net-worth floor and five bidders cleared it Adani Energy Solutions, DRAIPL-CG Consortium, POWERGRID, Resonia and Terralight qualified; four are sole bidders, the fifth splits 26/74 between DRAIPL and Cube Grid Investments Pte. Ltd. The bid bond is Rs 286.40 crore and the CPG Rs 716 crore, due within ten days of LoI alongside full SPV acquisition. Scope covers two 6,000 MW ±800 kV LCC terminals, roughly 900 km of bipole and two synchronous condensers. Bipole-1 targets 48 months and Bipole-2 54, but the RFP requires simultaneous commissioning.
8BSUL's Rs 379.25 crore Jalaun evacuation package states EMD as Rs 3.80 crore in the NIT and Rs 38 lakh on the portal The tender ID shifts the same way, 913540_1 in the scanned NIT and Corrigendum-1 against 913570_1 across the CPPP record, clarification, Corrigendum-4 and opening report. Corrigendum-1 widened ITB 2.2.1 from "Sub-Station and/or Transmission line works" to "Sub-Station or any other electrical works" while holding the Rs 303.40/189.62/151.70 crore thresholds and the two 220 kV-plus bay test. SCC 3 keeps LD at 0.5% of total contract price per week where partial facilities cannot be beneficially used; SCC 3.1 and 4.0 read "Deleted" with substantive O&M text beneath, and the trial run reads "72 (Seventy-two) 24 (Twenty Four) hours continuously". Ten bidders were admitted on 10 August with the PGCIL Orai bay extension inside the contractor's scope.
8BHEL lets Talabira bidders borrow the ash-handling credentials they lack, then bills the prime bidder if a partner walks Vacuum conveying can substitute for pressure conveying where detailed engineering is vetted by an IIT or qualifying firm; missing water-impounded bottom-ash-hopper experience can be bridged by a design agency plus a performance-support undertaking; civil and structural gaps go to consortium partners. Clause 23.10 keeps the prime bidder accountable throughout. Clause 23.12 permits encashment of a departing partner's security, mandates replacement, and otherwise recovers the cost difference plus a 5% overhead factor. Clause 23.15 adds 1% consortium security, with reverse auction under clause 19.0 after technical qualification.Details
For reference purposes the website carries here the following tenders: 8Tender for work of supply, installation, testing and commissioning (SITC) of intelligent addressable hot redundancy based continuously available Details 8Tender for supply of 36kV copper XLPE power cable Details 8Tender for erection of new 132/33kV 40MVA T/F Details 8Tender for construction of 2x40 MVA 132/33kV S/S Shahjahanpur Details 8Tender for construction of 2x40 MVA 132/33kV S/S Details 8Tender for construction of 2x63 MVA 132/33kV S/S Details 8Tender for SITC of numerical line differential cum distance protection relay Details 8Tender for work of PID testing of various tower various 132 kV, 220 kV & 400 kV lines Details 8Tender for augmentation by replacement of existing 2x100MVA, 220/132kV ICTs by 2x200MVA, 220/132kV ICTs Details 8Tender for AMC for repair/ service/ overhauling/problem attending of compressor of 245/145 kV circuit breaker at various Details 8Tender for construction of LILO on 100kV line Details 8Tender for repair maintenance of Two nos. 33kV, 10MVA transformer installed Details 8Tender for providing fixing of negative sequence relay, over current earth fault relay Details 8Tender for electrical works Details 8Tender for supply and completion of HT straight through cable joints Details 8Tender for re-organization and installation of 3.3kV overhead line and LT overhead line Details 8Tender for replacement of 250KW, 6.6kV, HT motor of 20 no pump Details 8Tender for dismantling, shifting of HT OH line Details 8Tender for installation of Acs with accessories and installation of 30 nos. of streetlights Details 8Tender for replacement of damaged GI sheets and various Details 8Tender for making 02 Nos foundation and ramp for shifting of existing 100MT weigh bridges Details 8Tender for replacement of old GI sheet on roof with profile sheet and misc. repair work Details 8Tender for construction of control room foundations, cable trench Details 8Tender for renovation of yard light works Details 8Tender for repair of submersible pump for various 33kV S/S Details 8Tender for renovation of control room and misc. civil works at 33kV S/S Details 8Tender for renovation of sanitary, electric yard levelling gravelling work Details 8Tender for suppy of P/F FRP fencing for RMU, transformer Details 8Tender for construction of prestressed precast and brick masonry Details 8Tender for work contract for work of lifting and disposal of used thermal insulation material Details 8Tender for work contract for availing OEM supervisory services for complete overhauling along with commissioning of 6.6 kV, 360 KW glandless boiler Details 8Tender for procurement of 250 NB and 300 NB sleeve type expansion joint for installation in pressure conveying line Details 8Tender for construction of new 11 kV, LT lines and 11/0.4 kV DTR Details 8Tender for miscellaneous civil work Details 8Tender for replacement of flame proof (FLP) lighting distribution boards (LDBs) at various Details 8Tender for construction of box culverts Details 8Tender for rectification works for structural and civil defects in C-Row Details 8Tender for job contract for removal of brick partition wall and extension of stage-1HT switchgear Details 8Tender for civil works of construction of culvert and other necessary repair work Details 8Tender for supply and retrofitting of 400 kV SF6 circuit breakers Details 8Tender for work of erection, testing and commissioning of new FOAC cable in existing 66kV UG line network Details 8Tender for work of erection-dismantling of 66kV/11kV equipment’s, structures, control wiring Details 8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes Details 8Tender for work of penthouse /APH centre section sealing for the unit Details 8Tender for supply of liquor ammonia 25 % (AR grade) for boiler water treatment Details 8Tender for EPC package for ash handling system Details 8Tender for framework agreement for various industrial operations Details 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metalclad draw-out type VCB panels Details 8Tender for renovation of power house Details 8Tender for shifting of electrical utilities in connection Details 8Tender for interlinking of 11kV feeder Details 8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing open conductor 11 kV lines Details 8Tender for works contract for replacement of existing overhead bare conductor Details 8Tender for works contract for replacement of existing overhead bare conductor ACSR 7 4.09 mm, AAAC 7 3.15 mm and AAAC 7 2.59 mm by XLPE coated covered conductor Details 8Tender for turnkey construction of one no. of 33kV feeder bay and associated works at 220/132kV GSS Details 8Tender for conversion of 11 kV feeder Details 8Tender for refurbishment of coal burner nozzles and tips of 2x270 MW units Details 8Design, manufacture, testing, supply and delivery of 162 nos. 66kV, 39 nos. 132kV and 63 nos. 220kV SF-6 circuit breakers Details 8Tender for creation of new control room at 132kV S/stn Details 8Tender for casting of machine pressed solid Details 8Tender for work of annual rate contract for attending on site minor repairs / maintenance works / OLTC overhauling of EHV class power transformers / ICTs Details 8Tender for laying of three single core 11kV XLPE 185 sq.mm. cable on elevated PSC structure Details 8Tender for laying of three single core 11kV XLPE 185 sq.mm. cable Details 8Tender for supply of BWSR spares Details 8Tender for providing PVC coated chain link fencing Details 8Tender for erection of 66 kV line Details 8Tender for replacement of acid and alkali resistant tiles in DM plant Details 8Tender for procurement of complete assembly of gear box model Details 8Tender for procurement of M/s coupling and its spiders installed Details 8Tender for rate contract for maintenance of AC machines Details 8Tender for service contract for online leak sealing job as and when required Details 8Tender for biennial contract of the job operation of gate valve for smoothly distributing Details 8Tender for supply of vertically operated 11kV gang operated air breaker switch Details 8Tender for works contract for carrying out HT LT DCW, improvement and capital extension works Details 8Tender for works contract for stores handling works Details 8Tender for procurement of MS bolt nut Details 8Tender for provide services for installation of solar meter along Details 8Tender for work of overhauling of 132KV/220 kV CB poles and mechanism of with required spares Details 8Tender for work of two-year rate contract for the work of cold line washing of insulator strings of various Details 8Tender for supply, installation & commissioning of neutral grounding reactor (NGR) for power transformer Details 8Tender for work of providing & applying of high insulation resistance compound coating having Di-electric strength Details 8Tender for annual maintenance contract for the work of attending emergency, break down and maintenance work of 220kV, 132kV lines Details 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50MVA, 132- 110/33 kV T/F along Details 8Tender for supply of various CDS tubes and bend for drain & vent line Details 8Tender for conductor replacement with hardware & SRI of 66kV tower line Details 8Tender for loading & unloading of material and transformer Details 8Tender for erection, maintenance and dismantling work of overhead HT/LT line Details 8Tender for supply of spare for bosch make loudophone at switchyard Details 8Tender for work of rubber lining of various equipments, pipes and fittings Details 8Work of repairing of various pulleys of conveyor belts Details 8Tender for biennial work contract for maintenance of ash handling plant Details 8Tender for various maintenance works of wagon tippler Details 8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details 8Tender for supply of control panel spares of pump house Details 8Tender for work of misc pressure part related activity of boiler stage Details 8Tender for work for dismantling, design & supply, installation and commissioning of GI duct and air filter assembly with supporting structure Details 8Tender for rate contract for routine, preventive & breakdown maintenance of TPS lighting system, fans etc Details 8Tender for work of replacement of various spares of drive system of wagon tippler Details 8Tender for supply of various ratings LT motor Details 8Tender for supply of various boiler tubes bends Details 8Tender for carting of 11,500 Nos. of 8 meter PSC poles Details You can also click on Tenders for more For reference purposes the website carries here the following newsclips: 8How India seeks to translate its offshore wind potential into large-scale deployment Details 8Coal India Weighs Buyout of Wealth Minerals' Chilean Lithium Unit Details 8Five decades of research leads to solar PV’s emergence as the world’s dominant energy source Details 8Look beyond solar, draw up roadmap for all renewable energy sectors: House panel to MNRE Details 8Powering the Next Generation of Commercial Rooftops: Hoymiles MIT-5000-8T Takes Centre Stage in Hyderabad Solar Project Details 8Beyond modules: Why cell manufacturing will shape India’s next solar growth story Details 8ReNew Sells Solar Assets for Rs 4,859 Crore Details 8Sodium-Ion Battery Prototypes Reach 200 Wh/kg Milestone Details 8India Strengthens Energy Storage Framework With INR 5,400 Crore VGF And Transmission Incentives Details 8India’s solar revolution lights the path to a Viksit Bharat Details 8India's Delhi faces rising night-time power peaks: report Details 8India awards 1 GW of round-the-clock renewables at competitive tariff Details 8Electricity Demand Expected To Rise Up to 7.5% In FY27 Amid Higher Heat, Rainfall Deficit: Crisil Details 8Huf India Commissions 1 MW Rooftop Solar Project in Pune Details 8India’s Coal Imports For Power Blending Fall 71.5% In Two Years: Govt Details 8India Accelerates Power Distribution Digitalization With Smart Meters And Grid Modernization Details 8Global Renewable Energy Capacity Hits 5.2 TW Milestone Details 8Lloyds Metals Secures 66 MW Renewable Power via Gentari Deal Details 8UP to resume smart meter rollout after consumer awareness drive: State Power Minister Details 8Cummins India Q1 FY27: Revenue rises 18%, data centers drive power gen growth Details 8Shadows Over Green Energy Details 8Porter Marks 10,000th Electric Truck Deployment in Delhi Details 8Why India Had To Open Its Nuclear Power Sector Details 8NLC India Renewables Bags SECI Letter of Award for 200 MW Wind Power Project in Karnataka Details 8India's Draft National Electricity Policy 2026: Key proposals explained Details 8HCC secures contract of around Rs 524 crore from State-run NHPC in Jammu and Kashmir Details 8Jakson Infra Wins Rs 128 Crore Power Project in Karnataka Details 8Hindustan Construction Company Wins Rs 524.17 Crore NHPC Order for Salal Hydro Project in J&K Details You can also click on Newsclips for moreDetails
8SCADA, IT/OT and smart-distribution work now reaches 28 states and 45 utilities, alongside 19.79 crore sanctioned consumer meters. Only Rs 23.36 crore of a Rs 100.9 crore training allocation had been used by July, leaving operational capability as the counterweight.Details
8BRPL, BYPL and TPDDL may recover total FPPAS of 17.94%, 17.43% and 18.50% respectively for June 2026. The order is a one-month regulatory relaxation; it does not remove the normal ceiling or convert unallowed claims into approved revenue.Details
8The 1,980 MW station’s tariff case remains open while NTPC supplies package-level escalation and audited cost reconciliation. Beneficiaries can face fixed-charge consequences only after the regulator decides which expenditure is prudent and attributable.Details
8The government plans 139 first-mile projects by FY30 and eight railway schemes, within a logistics plan covering 33 critical rail projects. Domestic production and dispatch both fell provisionally in FY26, so planned handling capacity has not yet become higher delivered volume.Details
8The dedicated plant’s annual supply to Bangladesh increased from 155.55 MU in FY23 to 9,131 MU in FY26. India also exported to Nepal, Bhutan and Myanmar, but APJL’s exclusive contract is distinct from domestic central-station allocation.Details
8The state has Rs 10,391 crore of loss-reduction work and Rs 4,112.43 crore of smart metering sanctioned under RDSS. Consumer-meter installation is substantial, while transformer meters, disaster-resilient works and grant release remain incomplete.Details
8The government counts 22.6 million tonnes a year as operating or under implementation and expects a new Rs 37,500 crore scheme to support about 75 million tonnes more. Eight projects have been approved under the earlier Rs 8,500 crore scheme, but only Rs 235.52 crore had been disbursed and commissioning remains the decisive test.Details
8Imports for blending at domestic coal-based plants fell from 23.9 million tonnes in FY24 to 6.8 million tonnes in FY26. Coal India also held 122.46 million tonnes in March, yet imported-coal plants and technically necessary blending remain outside a simple substitution claim.Details
8National supply met the May 2026 peak in full, while the official FY27 forecast rises to 289 GW. Thermal generation still supplied 68.3% to 72.7% from April to June, and the remaining gaps were attributed mainly to state-network constraints.Details
8The regulator approved a Rs 479.24 crore revenue gap but allowed only Rs 117.77 crore against the FY27 tariff after calculating that full recovery would require a 42.82% average increase. It paired partial recovery with smart-meter consent, billing-resolution and grievance directions, protecting consumers now while retaining future financial obligations.Details
8Projects across conventional hydro and pumped storage remain untaken up even after appraisal, with some concurrences or environmental approvals already expired. The clearance-pending category alone includes 14,649 MW in the CEA table, showing how a project pipeline can remain large without becoming executable capacity.Details
8One case covers 1,200 MW of firm dispatchable renewable supply; the other covers 600 MW of inter-state wind projects selected through separate bidding. For the firm and dispatchable procurement, HPSEB has sought state approval for the contracted power but had not executed its power-sale agreement at the hearing.Details
8The state distributor’s petition says the project must be commissioned within 18 months of the storage-purchase agreement and that land and connectivity will be provided. Public comments are due before the September hearing, so the discovered tariff and contractual allocation still require regulatory adoption.Details
8The Centre says Odisha’s utilities are ineligible because RDSS financial assistance is limited to state-owned distributors and power departments. It also says no formal Rs 10,000 crore special power-package proposal was submitted after Cyclone Yaas, separating the state’s actual RDSS request from the larger claimed package.Details
8The Centre says funding is linked to physical and financial progress and vendor checks are built into standard bidding documents. The monitoring chain reaches from state committees to PFC, REC and the Union power secretary, yet billing redress and meter mode remain with utilities and state regulators.Details
8Uttar Pradesh moves its draft Grid Code hearing by one day - objections still close on the earlier timetable 8Gas stations flag a low-frequency threshold mismatch - compensation remains under regulatory review 8Secure meter-data software slows regional accounting - manual handling is still filling the processing gap 8Genus meter decryption produces conversion defects - corrected files are still awaited 8DSM defaults trigger letter-of-credit scrutiny - security compliance has not cured the pool’s unpaid balance 8Unreturned reconciliation statements are being deemed accepted - administrative closure does not create fresh cash 8NP Kunta’s STATCOM needs an SMPS upgrade - reliability work requires a planned equipment shutdown 8Hyderabad substation’s automation migration needs 400 kV outages - modernisation temporarily narrows network availability 8Talcher - Kolar HVDC Pole 1 seeks an eight-hour shutdown - refurbishment inspection still awaits outage clearance 8India’s demand forecast error moved across 7 - 9 August - three daily readings do not establish model performance 8Intraday auction reports expose bids, clearing and schedules block by block - the latest sheet is a market snapshot 8WCL still carries compassionate-appointment applications from earlier years - the source confirms backlog, not a clean total 8Odisha’s closed coal mines face an unfinished reclamation question - completion evidence is not established 8Fatehgarh - Bhadla lenders may take security over the transmission asset - a licence transfer still needs prior approval 8Tadas Wind challenges where DSM charges are computed - the interconnection point could change the bill 8SGPL presses a Haryana energy-charge claim - the hearing record does not award the money 8Osmanabad Solar seeks Rs 3.42 crore in DSM dues - the hearing was deferred before the merits were reached 8TPTCL’s withheld-dues dispute returns to jurisdiction - the Commission wants arguments before deciding the claim 8Teesta Low Dam IV’s tariff case reaches the order stage - additional capital claims remain under scrutiny 8MEL’s transmission-licence process draws a compliance warning - proposed approval is not yet unconditional 8Solarcraft seeks more time after bay-sharing delays - missing guidelines do not automatically extend connectivity 8Kreate’s banking claim against SPTPL meets a denial of monetary liability - updated claims still need adjudication 8UGVCL’s accident register records fatal network incidents - responsibility remains case-specific 8UGVCL tracks complaints received, resolved and pending - the extracted register does not yield a reliable aggregate 8UGVCL records transformer failures and restoration complaints - a verified failure-rate figure is missing 8UGVCL’s reliability register contains outage indices - the source slice cannot support a performance ranking 8Faulty-meter replacement remains in UGVCL’s operating records - the backlog needs a clean count 8UGVCL reports no standards-of-performance compensation in the selected table - nil claims require an audit trail 8UGVCL records unauthorised-use and theft enforcement - mixed source rows prevent a verified total 8Reserve-shutdown fuel-oil compensation needs a calculation rule - eligibility alone does not fix the quantity 8Faulty special-energy meters remain unreplaced after earlier meetings - delay keeps commercial disputes alive 8Radhanesda’s meter failure produced a Rs 17.83 lakh DSM revision claim - the account still needs correction 8RDSS funds workforce training for digital distribution - utilisation must match the technology rollout 8Grid-security readings were mostly compliant at Agra but weaker at Ajmer - one report cannot grade the corridor 8Western-region outages and line states changed on 10 August - the operating list is not an adequacy forecast 8The Centre retains 15% of central-station power as unallocated - states compete within the remaining allocation rules 8Chhattisgarh’s mining funds must favour high-priority services - allocation rules do not prove local delivery 8NLC’s TPS-I Expansion true-up accepts an 8.5% auxiliary-consumption norm - the wider tariff still rests on reconciled costs 8Vindhyachal Stage I seeks tariff and life-extension capital - the rules may prevent double recovery 8NLC TPS-II’s additional-capital claim contains a cash-basis mismatch - reconciliation must precede the orderDetails
8NTPC wants station-transformer loads explicitly counted at Vindhyachal and Korba - only export apportionment would change under its proposal 8Legacy and current power-pool deficits are still holding back disbursement - collections received do not eliminate the unpaid tail 8Municipal bonds raise Rs 6,540.44 crore across 23 cities - green issuance does not prove project delivery 8NTPC Lara has settled rehabilitation claims for most affected families - jobs remain conditional on vacancies and suitability 8Ashoknagar’s petroleum lease has been extended twice - commercial oil and gas production still has not begun 8Electrical installations may use five-year inspection or self-certification cycles - digital reporting must keep the option auditable 8Public EV-charging use rises 39% in FY26 - four states dominate the national total 8Telangana’s station-wise generation moved through July - the monthly sheet reveals unit performance but not the cause of every changeDetails
8Andaman solar and storage operators seek must-run compensation - deemed generation still needs a contractual basis 8ReNew seeks protection against a bank-guarantee call - the dispute has not erased the underlying obligation 8Sarda seeks tax and open-access reimbursement for 100 MW - contract allocation will decide who pays 8NTPC Renewable and SECI dispute a scheduled-completion extension - delay relief depends on the cause and notice record 8APPCPL’s banking claim meets SPTPL’s insolvency moratorium - recovery rights now collide with bankruptcy protection 8SEIL challenges coal-freight deductions - the dispute turns on whether transport was recoverable or already priced in 8Tamil Nadu’s Ombudsman protects the existing tariff for qualifying small extensions - separate construction can still trigger Tariff VIDetails
8Assam is included in plans for 200 MWh of battery storage - but no state capacity has yet been allocated 8Nathpa Jhakri seeks recovery for hydrology shortfall - the case turns on evidence that water, not operation, caused the loss 8Kynshi and other hydro DPRs return for revision - redesign may improve viability but delays appraisalDetails
8India Energy Stack pilots begin in five utility markets - the national power-data architecture is still unproved 8RDSS pushes distribution utilities deeper into digital operations - installation counts still do not prove better service 8Private discoms report longer supply and lower losses than state utilities - but averages conceal company gapsDetails
8Amara Raja’s new-energy sales grow by more than 50% - but exports and factory execution pull in opposite directions 8Jagdambey Hydro retains fixed-tariff visibility - weak generation and one buyer still constrain the credit 8PFC and REC loans survive TANGEDCO’s restructuring - Rs 12,822 crore of annual interest shows the continuing burdenDetails
8JP Nigrie seeks scheduling recognition after a coal-supply change - fuel availability must still support the declared output 8New Colliery Control rules replace the 2004 framework’s Rule 9 - compliance changes now depend on the substituted text 8India has auctioned 124 commercial coal blocks and attracted 44 first-time bidders - allocation totals still outrun producing mines 8FY26 coal output and dispatch fall - logistics additions have not prevented a weaker annual resultDetails
8Gujarat says schedule-allocation errors distorted weekly DSM accounts - corrected data could redistribute charges between entities 8Avaada’s PPA-and-merchant portfolio needs one DSM contract rate - the wrong method can shift deviation charges between sales routes 8Fuel-quality variation is being tested against partial-outage DSM treatment - one cause should not be labelled as another 8Western-region DSM defaults are delaying pool payments - unpaid participants shift the cash burden to compliant members 8Maharashtra’s legacy DSM deficit remains unpaid - old shortfalls are still reducing current disbursement capacity 8Rajasthan revises merit order after a central-station tariff change - cheaper dispatch depends on using the new cost ranking 8RGPPL’s Rs 18.64 crore legacy DSM amount is still awaiting settlement - recognition has not produced payment 8Renewable DSM calculations remain subject to interim High Court orders - final settlement still depends on the litigation 8June’s national SCED pool has paid generators under the monthly statement - heat-rate degradation compensation remains separateDetails
8Northern planners propose 23 optical terminals and an STM-64 data corridor - but allocation still starts a 12-month delivery clock 8Powergrid cuts planned VoIP control centres from 82 to 73 - while Ladakh and Chandigarh remain outside the approved scope 8Fibrehome support expires in October as replacement lags - RRVPNL wants Powergrid to take over delivery 8Repeated switching is stressing Maheshwaram’s 765 kV GIS - a flashover shows the wear is no longer theoretical 8Outage approvals delay tests on 53 ageing transmission lines - raising the failure risk they are meant to expose 8Grid-India escalates the Jeypore - Gazuwaka outage - east - south transfers remain dependent on alternative paths without a restoration date 8Kudankulam’s protection scheme delivered less load relief than intended - Nandikotkur stayed connected through a second line 8Kaiga’s Guttur circuits have been out since May - operators warn the remaining evacuation path could overload 8Odisha’s section of the Jagdishpur-Haldia gas pipeline is complete - Cuttack connectivity now depends on use, not construction 8Avaada’s connectivity-relaxation case is reserved for order - the requested network exception is not yet granted 8Gorbea Solar seeks compensation for delayed grid access - but generation loss remains a claim, not an awarded amount 8VEH Saur wants 33 MW more generation within existing connectivity - CERC first wants evidence that the projects are ready 8Kanjhawala’s 11 kV bus outage contributed to a one-hour consumer interruption - restoration is still an operating issueDetails
8Solar contributed 44.6 GW and wind 6.1 GW to the year’s non-fossil additions, taking non-fossil sources above 54% of installed capacity. The simultaneous build-outs leave transmission, storage, coal utilisation and peak adequacy to determine whether the two fleets complement each other or impose parallel system costs.Details
8The regulator approved a Rs479.24 crore revenue gap but allowed only Rs117.77 crore against the FY27 tariff after calculating that full recovery would require a 42.82% average increase. It paired partial recovery with smart-meter consent, billing-resolution and grievance directions, protecting consumers now while retaining future financial obligations.Details
8Projects across conventional hydro and pumped storage remain untaken up even after appraisal, with some concurrences or environmental approvals already expired. The clearance-pending category alone includes 14,649 MW in the CEA table, showing how a project pipeline can remain large without becoming executable capacity.Details
8One case covers 1,200 MW of firm dispatchable renewable supply; the other covers 600 MW of inter-state wind projects selected through separate bidding. For the firm and dispatchable procurement, HPSEB has sought state approval for the contracted power but had not executed its power-sale agreement at the hearing.Details
8The state distributor’s petition says the project must be commissioned within 18 months of the storage-purchase agreement and that land and connectivity will be provided. Public comments are due before the September hearing, so the discovered tariff and contractual allocation still require regulatory adoption.Details
8The Centre says Odisha’s utilities are ineligible because RDSS financial assistance is limited to state-owned distributors and power departments. It also says no formal Rs10,000 crore special power-package proposal was submitted after Cyclone Yaas, separating the state’s actual RDSS request from the larger claimed package.Details
8State-level AT&C losses fell from 41.72% in FY21 to 22.76% in FY25, and the reported cost-revenue gap moved to a small surplus. Borrowings still stood at Rs49,239 crore, while large portions of sanctioned RDSS network and smart-meter work remained to be installed or completed.Details
8Utilities in Delhi, Gujarat, Andhra Pradesh, Uttar Pradesh and Mumbai have been selected for proof-of-concept implementation. The proposed stack is meant to connect power-sector systems through secure common protocols, with interoperability, governance and consumer protection still to be demonstrated in practice.Details
8The Draft National Electricity Policy, 2026 calls for fixed charges to recover fixed costs and for monthly automatic fuel-and-power purchase adjustments. It also seeks cost-reflective tariffs without new regulatory assets, placing distribution-company finances and household affordability in the same unresolved policy choice.Details
8The Centre says funding is linked to physical and financial progress and vendor checks are built into standard bidding documents. The monitoring chain reaches from state committees to PFC, REC and the Union power secretary, yet billing redress and meter mode remain with utilities and state regulators.Details
8The exemption covers TBEA Energy India, Nanjing Electric India, New Northeast Electric India and Taikai Electric India from 24 June 2026. Government says wider competition can ease supply constraints and stabilise prices, while the conditional waiver keeps the domestic-manufacturing trade-off visible.Details
8The sanctioned total covers consumers, feeders and distribution transformers; all schemes together account for 7.24 crore installed smart meters. Government cites check meters, independent testing and third-party laboratory verification, but billing complaints remain the responsibility of state utilities and regulators.Details
8The five-year proposal is intended to advance carbon-capture, utilisation and storage across power, steel, cement, refineries and chemicals. The Ministry of Power says the programme is still being established, leaving cluster selection, audit standards and implementation rules to follow after approval.Details
8The solar developer and contractor’s order book was 3.83 times FY26 operating income, giving it substantial revenue visibility after an 81% rise in annual income. CareEdge nevertheless identifies project concentration, higher gearing, heavy use of supplier finance and timely equity for co-developed projects as the counterweights to that growth.Details
8The Divitipally project is designed for grid-scale and commercial-and-industrial storage, with operations scheduled to begin in the third quarter of FY27. The company has already commissioned a customer-qualification plant, but the larger manufacturing plan still depends on phased cell and storage-factory start-ups over FY27 and beyond.Details
8Thermal coal-stock reports cover 6 - 9 August - four daily observations cannot establish a durable inventory trend 8India’s generation reports compare 7 and 8 August - the two-date fuel mix is an operating snapshot, not a transition trend 8Uttar Pradesh moves its draft Grid Code hearing by one day - objections still close on the earlier timetable 8Gas stations flag a low-frequency threshold mismatch - compensation remains under regulatory review 8Secure meter-data software slows regional accounting - manual handling is still filling the processing gap 8Genus meter decryption produces conversion defects - corrected files are still awaited 8DSM defaults trigger letter-of-credit scrutiny - security compliance has not cured the pool’s unpaid balance 8Unreturned reconciliation statements are being deemed accepted - administrative closure does not create fresh cash 8NP Kunta’s STATCOM needs an SMPS upgrade - reliability work requires a planned equipment shutdown 8Hyderabad substation’s automation migration needs 400 kV outages - modernisation temporarily narrows network availability 8Talcher - Kolar HVDC Pole 1 seeks an eight-hour shutdown - refurbishment inspection still awaits outage clearance 8India’s demand forecast error moved across 7 - 9 August - three daily readings do not establish model performance 8High-price day-ahead sellers offered 37,838.4 MWh - no purchase or cleared volume followed 8Intraday auction reports expose bids, clearing and schedules block by block - the latest sheet is a market snapshot 8WCL still carries compassionate-appointment applications from earlier years - the source confirms backlog, not a clean total 8Odisha’s closed coal mines face an unfinished reclamation question - completion evidence is not established 8Fatehgarh - Bhadla lenders may take security over the transmission asset - a licence transfer still needs prior approval 8Tadas Wind challenges where DSM charges are computed - the interconnection point could change the bill 8SGPL presses a Haryana energy-charge claim - the hearing record does not award the money 8Osmanabad Solar seeks Rs3.42 crore in DSM dues - the hearing was deferred before the merits were reached 8TPTCL’s withheld-dues dispute returns to jurisdiction - the Commission wants arguments before deciding the claim 8Teesta Low Dam IV’s tariff case reaches the order stage - additional capital claims remain under scrutiny 8MEL’s transmission-licence process draws a compliance warning - proposed approval is not yet unconditional 8Solarcraft seeks more time after bay-sharing delays - missing guidelines do not automatically extend connectivity 8Kreate’s banking claim against SPTPL meets a denial of monetary liability - updated claims still need adjudication 8UGVCL’s accident register records fatal network incidents - responsibility remains case-specific 8UGVCL tracks complaints received, resolved and pending - the extracted register does not yield a reliable aggregate 8UGVCL records transformer failures and restoration complaints - a verified failure-rate figure is missing 8UGVCL’s reliability register contains outage indices - the source slice cannot support a performance ranking 8Faulty-meter replacement remains in UGVCL’s operating records - the backlog needs a clean count 8UGVCL reports no standards-of-performance compensation in the selected table - nil claims require an audit trail 8UGVCL records unauthorised-use and theft enforcement - mixed source rows prevent a verified total 8Telangana’s reservoir sheet compares storage on 11 August - a single date cannot establish seasonal security 8Odisha’s hydro report links reservoir levels to available units - sparking and open gates constrain the snapshot 8Reserve-shutdown fuel-oil compensation needs a calculation rule - eligibility alone does not fix the quantity 8Faulty special-energy meters remain unreplaced after earlier meetings - delay keeps commercial disputes alive 8Radhanesda’s meter failure produced a Rs17.83 lakh DSM revision claim - the account still needs correction 8RDSS funds workforce training for digital distribution - utilisation must match the technology rollout 8SCUC reports show upward and downward schedules from 7 - 10 August - the short series is operational, not predictive 8Real-time market data run through 10 August - block prices and volumes need a longer benchmark 8Grid-security readings were mostly compliant at Agra but weaker at Ajmer - one report cannot grade the corridor 8Western-region outages and line states changed on 10 August - the operating list is not an adequacy forecast 8The Centre retains 15% of central-station power as unallocated - states compete within the remaining allocation rules 8Chhattisgarh’s mining funds must favour high-priority services - allocation rules do not prove local delivery 8NLC’s TPS-I Expansion true-up accepts an 8.5% auxiliary-consumption norm - the wider tariff still rests on reconciled costs 8Vindhyachal Stage I seeks tariff and life-extension capital - the rules may prevent double recovery 8NLC TPS-II’s additional-capital claim contains a cash-basis mismatch - reconciliation must precede the orderDetails
8Delhi lets three discoms recover June fuel and power costs above the 10% billing ceiling - but only for one month and below their full claims 8NTPC wants station-transformer loads explicitly counted at Vindhyachal and Korba - only export apportionment would change under its proposal 8Legacy and current power-pool deficits are still holding back disbursement - collections received do not eliminate the unpaid tail 8Municipal bonds have raised Rs6,540.44 crore across 23 urban bodies - green issuance is growing but incentives do not prove project delivery 8NTPC Lara has settled rehabilitation claims for most affected families - jobs remain conditional on vacancies and suitability 8Ashoknagar’s petroleum lease has been extended twice - commercial oil and gas production still has not begun 8India met a 270.8 GW peak in May against a 289 GW FY27 forecast - national adequacy still leaves local network constraints 8Electrical installations may use inspection or self-certification cycles of up to five years - digital reporting must make the option auditable 8Public EV-charging electricity use rose from 107.41 MU to 149.58 MU between April 2025 and March 2026 - four states dominate the annual total 8Telangana’s station-wise generation moved through July - the monthly sheet reveals unit performance but not the cause of every changeDetails
8Andaman solar and storage operators seek must-run compensation - deemed generation still needs a contractual basis 8ReNew seeks protection against a bank-guarantee call - the dispute has not erased the underlying obligation 8Barh Stage I capital costs require another reconciliation - escalation cannot enter tariff without an accepted basis 8Sarda seeks tax and open-access reimbursement for 100 MW - contract allocation will decide who pays 8Sikkim Urja, PTC and NDMC trade reciprocal dues - set-off cannot replace proof of each underlying bill 8NTPC Renewable and SECI dispute a scheduled-completion extension - delay relief depends on the cause and notice record 8APPCPL’s banking claim meets SPTPL’s insolvency moratorium - recovery rights now collide with bankruptcy protection 8SEIL disputes coal-transport deductions under its power-supply arrangement - the case must decide whether freight was recoverable or already embedded in another charge 8Tamil Nadu’s Ombudsman protects the existing tariff for qualifying small extensions - separate construction can still trigger Tariff VI 8Adani’s Jharkhand plant supplies Bangladesh exclusively - cross-border trade adds power without entering India’s domestic allocationDetails
8Assam is included in plans for 200 MWh of battery storage - but no state capacity has yet been allocated 8Nathpa Jhakri seeks recovery for hydrology shortfall - the case turns on evidence that water, not operation, caused the loss 8Kynshi and other hydro DPRs go back for revision - redesign delays appraisal but may be necessary for a viable project 8Draft power policy backs storage and flexible grids - integration measures remain plans until capacity and networks are commissionedDetails
8PSPCL proposes an online settlement for 37.2 lakh consumers owing about Rs6,201 crore - agricultural accounts are excluded and PSERC approval is pending 8RDSS pushes distribution utilities deeper into digital operations - installation counts still do not prove better service 8Private discoms average 23.87 hours of daily supply and 10.05% AT&C losses versus state utilities’ 23.22 hours and 15.40% - group averages still hide company-level variation 8Andhra Pradesh advances RDSS cabling and smart meters - large awards still leave an installation gap 8RDSS adds SCADA, IT/OT integration and smart-distribution-city projects - cybersecurity becomes part of reliabilityDetails
8Amara Raja’s new-energy sales grow by more than 50% - but exports and factory execution pull in opposite directions 8Jagdambey Hydro retains fixed-tariff visibility - weak generation and one buyer still constrain the credit 8PFC and REC loans survive TANGEDCO’s restructuring - Rs12,822 crore of annual interest shows the continuing burden 8Quality Power’s income rises 32% and its order book reaches Rs19,455 million - reported profit still carries a hyperinflation adjustmentDetails
8JP Nigrie seeks scheduling recognition after a coal-supply change - fuel availability must still support the declared output 8New Colliery Control rules replace the 2004 framework’s Rule 9 - compliance changes now depend on the substituted text 8Power-sector coal imports fall 71.5% to 6.8 million tonnes in two years - the source does not isolate how much domestic coal replaced them 8India has auctioned 124 commercial coal blocks and attracted 44 first-time bidders - allocation totals still outrun producing mines 8Coal-gasification incentives support a 100 million-tonne ambition - projects still need buyers, feedstock and working economics 8FY26 coal output and dispatch fall - logistics additions have not prevented a weaker annual result 8Coal India plans 139 first-mile projects with 1,319 million-tonne capacity by FY30 - eight rail schemes still have to turn that capacity into dispatchDetails
8Gujarat says schedule-allocation errors distorted weekly DSM accounts - corrected data could redistribute charges between entities 8Avaada’s PPA-and-merchant portfolio needs one DSM contract rate - the wrong method can shift deviation charges between sales routes 8Fuel-quality variation is being tested against partial-outage DSM treatment - one cause should not be labelled as another 8Western-region DSM defaults are delaying pool payments - unpaid participants shift the cash burden to compliant members 8Maharashtra’s legacy DSM deficit remains unpaid - old shortfalls are still reducing current disbursement capacity 8Rajasthan revises merit order after a central-station tariff change - cheaper dispatch depends on using the new cost ranking 8RGPPL’s Rs18.64 crore legacy DSM amount is still awaiting settlement - recognition has not produced payment 8Renewable DSM calculations remain subject to interim High Court orders - final settlement still depends on the litigation 8June’s national SCED pool has paid generators under the monthly statement - heat-rate degradation compensation remains separateDetails
8Northern planners propose 23 optical terminals and an STM-64 data corridor - but allocation still starts a 12-month delivery clock 8Powergrid cuts planned VoIP control centres from 82 to 73 - while Ladakh and Chandigarh remain outside the approved scope 8Fibrehome support expires in October as replacement lags - RRVPNL wants Powergrid to take over delivery 8Repeated switching is stressing Maheshwaram’s 765 kV GIS - a flashover shows the wear is no longer theoretical 8Testing on 53 ageing transmission lines is being slowed by outage approvals - the delay raises the failure risk the tests are meant to reduce 8Grid-India escalates the Jeypore - Gazuwaka outage - east - south transfers remain dependent on alternative paths without a restoration date 8Kudankulam’s protection scheme delivered less load relief than intended - Nandikotkur stayed connected through a second line 8Kaiga’s Guttur circuits have been out since May - operators warn the remaining evacuation path could overload 8Odisha’s section of the Jagdishpur-Haldia gas pipeline is complete - Cuttack connectivity now depends on use, not construction 8Avaada’s connectivity-relaxation case is reserved for order - the requested network exception is not yet granted 8Gorbea Solar seeks compensation for delayed grid access - but generation loss remains a claim, not an awarded amount 8VEH Saur wants 33 MW more generation within existing connectivity - CERC first wants evidence that the projects are ready 8Kanjhawala’s 11 kV bus outage contributed to a one-hour consumer interruption - restoration is still an operating issue 8India plans to raise inter-regional transfer capacity from 120 GW to 168 GW by 2032 - renewable growth still needs the lines to arriveDetails