All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Nov 2026
KPTCL awards Hanur 220 kV substation package at Rs 209.08 crore on a single bid, 24.3% above estimate
8The 24-month package for 2×150 MVA transformation, a 13.458 km 220 kV DC line and 58.733 km of 66 kV links went to M T Kumar after Amendment-I let bidders qualify through a tower-design consultant.
8An unclear GST basis for the award, conflicting time-extension clauses, ceiling-based tower payments and contractor-funded ROW compensation keep pricing and cash-flow risk with the contractor.
GUVNL's 1,500 MW RTC auction fills the requirement in only two of eight months
8The tender for 1,500 MW of RTC and 1,500 MW of non-solar power from 16 November 2026 to 30 June 2027 drew RTC tariffs of Rs 8.90–10.00/kWh, with volumes ranging from 75 MW in November to 1,500 MW in February and March.
8Anonymous "XX" entries, unreconciled overnight delivery windows, no recorded acceptance or PPA quantities and an unclear LC mechanism keep supply-adequacy risk with GUVNL.
GUVNL's non-solar power auction draws just 50 MW at Rs 29–35/kWh against a 1,500 MW requirement
8November and January drew no non-solar bids, and the other six periods recorded 50 MW each at up to 293.3% above the lowest RTC tariff, while RTC drew sources from Ambitious, Jindal, Tata, NVVN and PTC.
8Single-offer periods that need GERC consent, unidentified suppliers behind every non-solar price and no explanation of the weak response keep procurement risk with GUVNL.
PSPCL awards Kapurthala RDSS package to SKS Infra at Rs 88.94 crore after the auction flips the ranking
8SKS moved from L2 to L1 by undercutting ABI's Rs 89.24 crore opening bid by a single 0.1% decrement, leaving the award 28.8% above the Rs 69.06 crore estimate for HT/LT loss-reduction works in three divisions.
8An unexplained Rs 20.88 lakh post-auction cut, 3% versus 10% performance-security clauses, no steel-structure escalation and GIS-linked final payments keep working-capital risk with the contractor.
PSPCL awards Nawanshahar RDSS package to ABI Energy at Rs 101.38 crore with no fresh auction bids
8Package 14's three ranked offers clustered 29.2–32.8% above the Rs 78.74 crore estimate, and the 730-day award came in Rs 34.46 lakh below ABI's evaluated L1 for reasons the record does not give.
8Conflicting 3% and 10% security terms, a "sixty-five (60) days" payment clause, lot-rejection penalties and a 473-day gap between the NoA and the portal contract date keep cash-flow and compliance risk with the contractor.
Kashmirilal overtakes ABI by Rs 9.46 lakh to win PSPCL's Rs 94.47 crore Mahilpur package
8The reverse auction cut Kashmirilal's own bid by 4.4% but improved on the best opening offer by only 0.1%, leaving the Package 12 award 27.1% above the Rs 74.33 crore estimate.
8Quality penalties of up to 5% of contract price, 10-year latent-defect liability, conflicting 3% and 10% security clauses and GIS-linked final payments keep execution and liquidity risk with the contractor.
RECPDCL pushes YEIDA 400/220 kV GIS deadline to 25 November but keeps the 18-month schedule
8Amendment III adds eight days to the previous deadline for the UPPTCL project, 23 days later than the original, moving the reverse auction to 8 December and SPV transfer to 28 December with the Rs 5.28 crore bid bond and Rs 13.20 crore CPG unchanged.
8No stated reason, a 12-day LoI-to-transfer window against clause 2.15.3's ten days and payment tied to simultaneous commissioning keep revenue-timing and execution risk with bidders.
PSPCL awards Jalandhar-2 RDSS package to ABI Energy at 28% above estimate
8The Rs 87.10 crore award against a Rs 68.04 crore estimate is Rs 19 lakh below ABI's evaluated bid, with Mangal and Vindhya 7.4% and 8.3% higher.
8An unexplained price cut, conflicting award dates and steel left out of price adjustment keep margin and timeline risk with the contractor.
DVC clears GE Vernova, Siemens and Techno Electric for Rs 133.63 crore Durgapur switchyard rebuild after eight extensions
8The DTPS GIS bids closed 75 days late, after escalation caps were removed for power transformers and R. S. Infraprojects was rejected over its surety bond.
8A 92-month security period, no payment for extra cable trays and gaps between drawings and the BOQ keep engineering risk with contractors.
CSPDCL gives contractors a six-month exit in its Rs 1,193 crore fault-restoration tender
8The corrigendum raises the vehicle odometer limit from 30,000 km to 1 lakh km, and a separate amendment moves submission to 25 November.
8A wrong incentive example, conflicting penalty start dates and uncapped CSERC compensation keep performance and payroll risk with contractors.
CCL's Rs 467.16 crore Amrapali–Shivpur coal evacuation tender says no ePBG but demands 5% performance security
8The three-year GeM package for 32,000 TPD of loading, haulage and wagon loading carries a Rs 50 lakh EMD and 3% retention.
8Payment on railway weighment, ±30% volume swings and a draft work order that bars escalation keep utilisation and cash-flow risk with transporters.
NTPC's Rs 200 crore Kudgi ash-haul panel guarantees no work orders
8Up to five AST-01 contractors must match the L1 rate to haul ash up to 300 km, with each capped at Rs 40 crore of work.
8A minus 100% variation clause, measurement-linked payment and extra security for deep discounts keep volume and liquidity risk with transporters.
JPDCL draws 14 bidders for Rs 159.46 crore Kathua Rural RDSS package after cutting performance security to 6%
8Bids for the Billawar, Basohli and Ramkote package opened on 14 November after an eight-day extension, with security now accepted as BG or surety bond.
8Price-variation bills tied to available funds and dismantling with no extra payment keep cash-flow and pricing risk with contractors.
JPDCL's Kathua Urban RDSS opening lists a bid stamped after the deadline
8Ten bidders were admitted for the Rs 239.60 crore package, but Vijai Electricals' entry is timed at 16:41, after the 14:00 closing.
8Price-variation billing tied to available funds and a vendor list disclosed only after award keep execution and recovery risk with contractors.
GUVNL's short-term power auction draws only 50 MW at Rs 29/kWh for non-solar hours
8Offers met the full 1,500 MW RTC requirement only in February and March, with lowest quotes of Rs 8.90–9.66/kWh.
8Unnamed "XX" sources behind 900 MW and PPAs not yet signed keep supply-firmness risk with GUVNL.
For daily newsletters and other free services, fill in your details: