All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Aug 2026

8UJVN's Lakhwar Hydro-Mechanical Design Tender Sets 20 BOQ Lines Against a 23-Item Scope UJVN's Rs 2.70 crore consultancy for pre-EPC design of Lakhwar's gates, penstocks and SCADA carries a price schedule that omits standalone billing for tender preparation and revised cost estimation — outputs Appendix III explicitly treats as separately payable. The same document simultaneously requires 120-day and six-month bid validity, and bars price adjustment in one clause while permitting it in another.

8TGGENCO's Naini-Yadadri Coal Logistics Tender Can't Decide If It's Moving 3 or 6 Million Tonnes TGGENCO's Rs 21 crore-EMD road-rail coal transport package states "3.0 million tonnes per annum for two years" in one clause and "approximately 3.0 million tonnes across two years" in another — a contradiction that could double or halve the real contracted volume. An exclusive-siding requirement demanding prior government-utility operating history, combined with a consortium ban, narrows the field to firms already embedded in the Khurda Road Division's coal network.

8ECL's RailTel Connectivity Award Closes 6.3% Above Its Own Displayed L1 Offer ECL's single-source, five-year Rs 145.47 crore managed-connectivity contract with RailTel shows a displayed offer of Rs 136.86 crore against an executed contract value Rs 8.61 crore higher — with no reconciliation supplied and no competing bid to benchmark against. GeM marks both EMD and ePBG as "No" even as the underlying conditions of contract require 5% performance security and 3% running-bill retention.

8UJVN's Second Lakhwar Design Tender Repeats the Same Radial-Gate Threshold Contradiction This companion filing on UJVN's hydro-mechanical design consultancy shows qualification clause 1.4.1(B)(iii) stating a 40% experience threshold while assigning it a rupee figure equal to 80% of the estimate — a discrepancy that could exclude or admit very different bidder pools depending on which figure controls. The tender also retains JV application forms despite explicitly barring joint-venture participation.

8NTPC REL's Nokhra Solar Tender Posts a Corrigendum 37 Minutes After Its Own Deadline NTPC Renewable Energy's 300 MW solar EPC package shows its first corrigendum timestamped at 15:37 on 22 June — just after the original 15:00 submission deadline on the same day — before seven total corrigenda and five addenda stretched the closing date by 60 days. A Rs 20 crore EMD locks in serious bidders even as land, evacuation and performance-guarantee terms remain undisclosed in the notice.

8NTPC's Farakka Pipeline-Bridge Assessment Is a Competitive Tender Wrapped Around a Named Consultant NTPC's structural-diagnostics assignment for ash-slurry pipeline bridges repeatedly identifies CSIR-SERC as the executing agency throughout its scope and payment clauses, despite running as a domestic competitive bid — and pays the entire preliminary-inspection fee in advance with no bank guarantee, no LD and no defect liability.

8WBSETCL's 22-Unit Transformer Tender Rebalances Delivery Without Extending Its Deadline WBSETCL's addendum cut the first delivery tranche from five transformers to three while pushing it 30 days later, keeping the 510-day completion date fixed — meaning later batches now carry a steeper production ramp. A pre-declared 14:8 split lets a second supplier win a share of the order, but only by matching the L1 price exactly.

8NHPC's Sawalkot Dam Tender Raises Its Estimate 5.6% and Moves Its Deadline 171 Days NHPC's Rs 5,416.94 crore Lot-1 package for the Sawalkot hydroelectric project quietly changed the plant's stated capacity from 1856 MW to 1800 MW mid-procurement while increasing turnover, working-capital and bid-capacity thresholds in step with the higher estimate. Thirty-four of 121 technical drawings were revised after original issue, and two separate documents both bear the label "Corrigendum No. 3."

8AEGCL's Umrangshu Financing EOI Attaches the Wrong Project's Supporting Documents AEGCL's EOI seeking a Rs 554 crore term loan for its 400/132 kV Umrangshu substation includes a prudential-norm attachment that actually belongs to an unrelated APDCL transformer-augmentation scheme, while the tender reference number itself alternates between "Tech-26" and "Tech-28" across different pages of the same notice.

8TNPGCL's North Chennai FGD Tender Keeps Extending a Procurement Its Own Notes Say Should Be Scrapped TNPGCL's seawater-FGD EPC package for two 600 MW units has moved its bid opening from April to August 2026 — a 143-day drift — even though an internal administrative note explicitly states that floated tenders "shall be revisited and fresh tenders shall be floated" after committee approval. The unchanged 24-month execution clock and deleted-escalation clause mean bidders keep refreshing offers for a process that may not survive in its current form.

8HPPTCL's World Bank Transformer Tender Ships With a Hidden Pricing Sheet From an Older Contract HPPTCL's ten-transformer procurement for Paonta Sahib, Kala Amb and Kunihar contains concealed spreadsheet tabs carrying historical rates and the name of a different contractor from an earlier turnkey package — a document-integrity failure sitting alongside an unresolved conflict over whether the current contractor's scope includes erection and commissioning or only supervision.

8BHEL's Darlipali Ash Handling Tender Locks Payment to Where Bidders Put Their Money BHEL's ash-handling EPC package for NTPC Darlipali penalizes bidders who price installation below 10% or civil work outside a 30-50% band by withholding that portion, non-interest-bearing, until physical milestones catch up — while a completeness clause makes any unlisted-but-necessary item the contractor's cost regardless of BOQ coverage.

8BHEL's Companion Darlipali Ash Tender Extends Three Times While Its Risk Stack Compounds A second BHEL filing for the same Darlipali ash-handling package shows three deadline extensions totaling 21 days against an unchanged 34-month delivery clock, with functional LD reaching 12% of contract price stacked atop a separate 5% delay-LD ceiling and layered security deposits — a cumulative exposure that may exceed what any single clause suggests.

8RECPDCL's Apta 765 kV Substation Tender Narrows to Two Bidders After a Documentation Rejection RECPDCL's Maharashtra transmission tender for the 765/400/220 kV Apta substation excluded Shivalaya Construction for failing to submit requested documents within the evaluation window — leaving only Adani Energy Solutions and Resonia to compete in a process that has already drifted 191 days past its original qualification-announcement date.

8SECI's One-Year Battery Storage Tender Threatens to Zero Out a Month's Entire Payment SECI's short-term 50 MW/100 MWh storage procurement requires an already-commissioned asset and imposes a sliding penalty scale where round-trip efficiency below 70% in any month eliminates that month's capacity payment entirely — on top of standard availability damages — while missing the 1 November 2026 start date triggers full PBG encashment and termination.

8SECI's NIWE Rooftop Tender Buries Its Core Technical Spec in a Separately Attached Annexure SECI's 100 kW hybrid rooftop replacement at NIWE's Chennai campus — requiring dismantling the existing plant and achieving seamless grid-to-island transition — defers the actual storage sizing, control architecture and performance-test methodology to an Annexure-B that isn't included in the main RfP, making bid comparability impossible without that missing document.

8POWERGRID's 765 kV Reactor Award Lands 11.3% Below Estimate With Freight Costs Still Unset POWERGRID's Rs 166.74 crore award to CG Power for 15 single-phase 765 kV reactors came in well under the Rs 187.90 crore indicative benchmark, but freight and insurance charges remain unpriced pending destination confirmation — meaning the apparent discount doesn't yet reflect the full delivered cost.

8POWERGRID's Bushing Tender Extended Ten Times Yet Still Contains Conflicting Delivery Dates POWERGRID's Rs 18.144 crore award to Hitachi Energy for 48 EHV bushings moved its closing date across ten separate extensions spanning 71 days while simultaneously cutting turnover and liquidity qualification thresholds by 25% each — yet the final award record still shows an 18-month consignee-table deadline alongside a corrigendum-amended 24-month schedule that were never formally reconciled. Details
8OPTCL's Pandiabil-Gopalpur 400 kV Line Tender Can't Agree on Its Own Bidding Structure OPTCL's Rs 745.49 crore, 157.363 km Quad Moose transmission line repeats the familiar "single stage two part" versus "Two Stages" conflict seen across its other tenders, alongside a header dated three months after the notice itself was signed. Route access, ROW responsibility, completion period and LD terms are all absent from the notice, leaving the headline estimate largely uninformative about actual execution risk.

8HPPCL's Green Hydrogen Offtake Notice Blurs Market Sounding With Formal Procurement HPPCL's EoI for offtake from its 1 MW Dabhota plant sets a token Rs 1 EMD and marks "Is Tender: No," yet schedules a formal cost-opening event just one hour after submission closes — leaving unclear whether this is genuine demand discovery or a binding commercial process. No hydrogen volume, purity, pressure or delivery-point boundary is specified, making any submitted price impossible to compare across respondents.

8OPTCL's Palaspanga-Barbil-Unchabali Tender Shows a Hundredfold Estimate Error OPTCL's turnkey substation-and-line package lists its own cost as both Rs 3.15 crore and Rs 315.27 crore in different parts of the same document — a discrepancy that maps suspiciously close to the actual EMD figure. Two technically distinct lots are bundled into one indivisible contract, concentrating GIS, cable and 400 kV overhead-line risk in a single balance sheet despite three competing bid-deadline versions in the record.

8TNGECL's Velimalai Pumped Storage Tender Freezes Bidder-Declared Efficiency for 40 Years TNGECL's 1,000 MW/6,000 MWh PSP concession prices declared cycle efficiency directly into the bid formula, then locks that same figure into monthly revenue reconciliation for the entire concession term — creating a direct tension between winning the auction and defending a bankable long-term operating assumption. Five deadline extensions accompanied progressive release of geophysical and layout data, even as the RFP continues to disclaim reliability of TNGECL's own site information.

8NPCIL's 220 MWe BSR Engineering Tender Bans Subcontracting Its Own Core Deliverable NPCIL's Rs 128.22 crore plant-engineering contract requires an integrated CADMATIC 3D model spanning 10,000 support qualifications and 8,500 piping isometrics, but forbids delegating that modelling work to any subcontractor — concentrating single-point failure risk in whichever firm wins. A late corrigendum superseded all prior buyer-added conditions wholesale rather than amending individual clauses, adding interpretive uncertainty just before technical evaluation.

8NTPC's Telangana Ash Handling Tender Cuts Disposal Redundancy From Five Streams to Four NTPC's ash handling package for three 800 MW units reduced bottom-ash slurry disposal from five pipelines to four while simultaneously tightening aeration, weighbridge coverage and conveyor-belt specifications elsewhere — a design trade that leaves only two working streams designated to serve three generating units. A disputed 8mm bottom-ash sizing requirement was relaxed to 25mm at intermediate silos, but the downstream secondary-crushing obligation bidders called commercially unproven remains unresolved.

8DVC's Durgapur Switchyard R&M Tender Carries a 92-Month Security Obligation for an 18-Month Job DVC's Rs 133.63 crore brownfield GIS conversion at old DTPS calculates performance-security validity out to 92 months — nearly five times the contractual completion period — while simultaneously barring the contractor from claiming delay-related escalation or overstay costs even where DVC itself causes the delay. Five deadline extensions accompanied unresolved BOQ numbering errors that survived bidder challenge.

8UJVN's Tankul SHP Tender Moves Its Deadline Three Times Without Explaining Why UJVN's Rs 87.90 crore small-hydro package combining river diversion, tunnelling, powerhouse construction and hydro-mechanical works pushed its submission date from 10 July to 18 July, then 20 July, before the tender portal independently displayed 4 August — a cumulative 25-day drift with no stated technical justification recorded in the extension notices.

8NTPC's Pudimadaka WTP-Substation Tender Corrects a 10x Access-Road Error NTPC's lump-sum turnkey package bundling a water treatment plant, firefighting system and 132/33 kV GIS substation fixed an access road mistakenly specified as 45 metres wide instead of 4.5 metres, while separately expanding the electrical battery limit from 300 to 800 metres — a net scope shift that removes one civil-cost distortion while adding cable and routing exposure elsewhere. A strict 90% RO-recovery guarantee and 110% design-margin requirement now bind process performance directly to the lump-sum price.

8BHEL's Darlipali-Telangana ACC Tender Monetises Auxiliary Power Consumption in Bid Evaluation BHEL's combined air-cooled condenser package for four 800 MW units evaluates Darlipali and Telangana separately but loads bid prices for guaranteed power consumption and civil RCC quantities before ranking — meaning the cheapest ACC on paper may not win once turbine-cycle efficiency losses are capitalised. Complete technical specifications are withheld until bidders sign a confidentiality agreement, delaying full technical assessment until deep into the bidding window.

8NPCIL's Gorakhpur Ground Remediation Tender Pays for Grout Once, Not Twice NPCIL's Rs 576.86 crore TAM-grouting package beneath GHAVP's cooling towers and turbine island measures treatment points only once, leaving pipe damage, blocked packers and rejected grout batches as entirely non-payable contractor risk. Four deadline extensions totaling 36 days preceded a specialist proof-consultancy requirement naming a specific external firm alongside mandatory AERB-facing review visits.

8NTPC's Ramagundam LP Rotor Tender Closes With Exactly One Bid After Five Months NTPC's turbine spare procurement for a GE-retrofitted 210 MW unit drew zero bids at one stage before GE Power India Limited alone submitted an offer at Rs 94.25 crore — well over five months after the original March deadline — while NTPC quietly reinstated a 5% performance guarantee that the original tender had explicitly waived. Three conflicting delivery dates (12 months, 365 days, and a fixed calendar date) remain unreconciled in the award record.

8UPPTCL's Sirsira GIS Completion Tender Caps Payment for Rates 10% Above Its Own Benchmark UPPTCL's Rs 80.47 crore brownfield substation-completion package now withholds 30% of invoiced value whenever a bidder's quoted rate exceeds UPPTCL's benchmark by more than 10% — deferring the excess until erection milestones are met. Three deadline extensions totaling 41 days accompanied a rewritten joint-venture qualification clause and a BOQ correction changing GIS erection units from individual counts to complete functional sets.

8DHBVN's Faridabad SCADA Tender Awards at a 0.1% Margin Between L1 and L2 DHBVN's Rs 95.69 crore RDSS automation award for SCADA, DMS and OMS infrastructure saw the winning and second-place bids separated by barely 0.1%, while the third bidder priced roughly 6% higher — a spread suggesting sharply different assessments of GIS-integration and cybersecurity risk. The performance-security clause itself contains an unresolved conflict between 30-day and 90-day post-defect-liability validity periods. Details
8A Dun & Bradstreet India review of more than 100 waste-to-energy mandates argues that municipal solid-waste power projects cannot be financed on electricity revenue alone. The plant provides a waste-treatment service whose value is not fully reflected in a commodity power tariff, so successful contracts combine long-term power or gas offtake with tipping fees, minimum tonnage guarantees, land support or viability-gap funding. Details
8Engineers India secured Rs 7,978 crore of business in FY2025-26, lifting its order book to a record Rs 15,109 crore from Rs 11,717 crore. Consultancy contributed Rs 6,009 crore of the inflow and turnkey assignments Rs 1,968 crore. Details
8Power Mech Projects ended FY2025-26 with a Rs 30,383 crore order backlog after Rs 7,210 crore of order inflow. Mining development and operation contracts and renewables supplied nearly three-quarters of the backlog even though they were a small share of new orders, because the underlying contracts run much longer than conventional EPC packages. Details
8RMC Switchgears closed FY2025-26 with more than Rs 800 crore of confirmed orders and over Rs 1,500 crore of active tenders, against consolidated revenue from operations of Rs 401.59 crore. The company says its historical tender conversion is about 30% to 35%, so the tender pool is an opportunity measure rather than contracted revenue. Details
8The Central Electricity Regulatory Commission has told Power Grid Corporation of India to correct mismatched and unrelated spreadsheets in two petitions seeking the true-up of 2019-24 transmission tariffs and determination of 2024-29 tariffs for assets associated with the Mundra Ultra Mega Power Project. Details
8India’s grid dispatched 67,227 MWh of downward ancillary reserves on 26 August, more than double the 33,261 MWh used a day earlier. Upward reserve dispatch moved the other way, falling from 23,308 MWh to 17,058 MWh. The system therefore spent much of the day reducing scheduled generation, but still recorded a 1,565 MW shortage at 19:23 during non-solar hours. Details
8Jindal Steel Limited Transmission asked the Chhattisgarh State Electricity Regulatory Commission to recognise a Rs 165.22 lakh revenue gap after carrying costs. The commission instead found a Rs 155.95 lakh surplus. The difference between the two positions is Rs 321.17 lakh and directly changes the amount that the transmission licensee may recover in FY 2026-27. Details
8Juniper Green Energy’s August 2026 initial public offering brought in Rs 1,800 crore of primary capital after the renewable developer ended June with total debt of Rs 13,182 crore. The company reported net debt of Rs 11,217 crore and net worth of Rs 3,463 crore at 30 June, putting net debt at 3.24 times net worth. It says post-issue net worth has risen to about Rs 5,200 crore. Details
Tariff decisions, filing defects, compliance deadlines and regulatory consequences

8CERC makes Bhachau transformer tariff depend on a documented cost overrun
8CERC asks Powergrid to account for delay in Gwalior reactor conversion
8Government-controlled board vacancies cost eight state companies Rs 1.78 crore across both exchanges

Projects and Tenders

Awards, signed contracts, live procurements and the execution obligations attached to them

8Adani’s Rs 4,700 crore corridor must arrive alongside the 4,500 MW storage it serves
8GK Energy’s Rs 454.50 crore rooftop award puts 100,000 homes on 60-day work orders
8ACME wins 300 MW of peak supply but the project still awaits its power contract
8ACME fixes continuous railway power at Rs 4.35 for twenty five years
8Suzlon’s new 250 MW order takes Torrent partnership above 1.3 GW
8L&T wins three Middle East batteries totalling 6 GWh without naming value
8DMR’s Laos hydropower win extends overseas work but adds only USD 200,000 over twelve months
8Meghalaya seeks 180 fault-sensor sets while warranty and response clauses remain unresolved
8REC opens Pirpainti’s 2,400 MW evacuation bid before disclosing network value or award date
8REC creates Alkud vehicle before Maharashtra selects its transmission provider

Companies and Financial Results

Operating results, balance-sheet exposure, legal developments and decisions that change company scope

8KPI energises 630 MW in three months after taking seventeen years for 533 MW
8Juniper’s quarterly profit grows 54 per cent behind a 72 per cent generation rise
8RMC’s revenue rises 26 per cent while profit falls 27 per cent
8Power Mech grows profit 18 per cent while returns on capital decline
8Refex’s bio-gas revenue reaches Rs 5.04 crore as losses widen
8GR Infra disputes a Rs 321.60 crore GST notice before liability is established
8Tata Power loses Singapore award challenge and prepares an appeal
8Modern Transformers’ improving FY 2025 numbers remain behind an unmonitored rating
8Siemens Energy separates a profitable unit to prioritise generation and grids
8Quality Power packs six fund meetings into one day but rules out new price-sensitive disclosure

Grid and Market Developments

Daily and monthly evidence on adequacy, balancing, renewable output, fuel and market operation

8Rs 876.97 crore of upward scheduling leaves the national ancillary pool Rs 50.52 crore short
8July’s ancillary market procures no upward energy but 751 MU downward
8Security-constrained scheduling creates Rs 40.68 crore of the western grid’s Rs 41.97 crore charge
8Wind and solar meet one third of demand before the evening shift
8Four large state plants hold less than one sixth of normative coal

LATEST CERC TARIFF AND REGULATORY NEWS

Seven further tariff instruments put capital cost, delay evidence and liquidated damages under examination

8Contractor penalties could reduce Powergrid’s claimed tariff for two Raipur reactors
8Powergrid must correct interest across four assets before CERC settles its communication tariff
8A Rs 3,000 mismatch prevents Powergrid’s northern transformer tariff record from closing
8Contractor penalties could reduce Powergrid’s Koteshwar and Roorkee bay tariffs
8Powergrid cannot charge Bhatapara transformer costs already recovered from contractors
8Powergrid’s tariff now turns on whether Tripura’s downstream network was ready
8CERC ties Bikaner-II tariff to proof of who caused each commissioning delay

STATE REGULATOR NEWS

The Chhattisgarh order creates a time-limited transmission discount and a hard commissioning cliff for solar projects.

8Chhattisgarh’s 33% solar transmission charge ends for projects commissioned after 2026

COMPANY, FINANCING AND GOVERNANCE NEWS

New filings expose control changes, related-party capacity, credit withdrawals and board-composition costs.

8KPI Green seeks to lift a Rs 1,000 crore related-party ceiling for Sun Drops
8Promoter buys 10.83 lakh Onix Solar shares to push its voting stake above 53%
8REC’s board-composition gap costs Rs 21.55 lakh at each exchange
8BF Utilities pays Rs 3.66 lakh after failing to appoint an independent woman director
8Juniper’s 150 MW Solapur project loses a public rating after lender consent
8Refex’s biogas expansion rests on shareholder support after losses deepen
8Urja Global’s standalone growth is offset by a weaker consolidated result
8Power Mech’s 10 lakh employee options would dilute holders after profit rises 18% Details
Exchange and system files show scarcity prices outside solar hours, zero-clearing products and a sharp day-ahead price retreat

8Day-ahead power prices retreat after 24 August’s Rs 7,299 ceiling
8Real-time power reaches the Rs 10,000 cap despite 172.92 GWh clearing
8High-price day-ahead volume slips to 209 MWh while price stays near Rs 19,000
8PXIL’s deviation-settlement market records bids but no trade

INTERNATIONAL AND TECHNOLOGY NEWS

A carbon-market review shows falling reported coal emissions can coexist with rising on-site pollution.

8Australian coal mines approach the entire methane-credit supply without cutting gross emissions

NORTHERN REGION MONTHLY GRID NEWS

The July report adds four independent system findings beyond the daily operational files.

8Northern grid adds 2,790 MVA as 394 MW of renewables raises evacuation pressure
8Rajasthan curtailed 40.66 million units of renewable power in twelve active July days
8Punjab exceeded transfer limits for 37.25 hours while Haryana breached both ATC and TTC
8Northern demand reached 92.7 GW without peak shortage, but daily energy still fell short

STATE HYDRO AND RESERVOIR NEWS

8Telangana’s reservoir energy falls 46% as Nagarjunasagar storage contracts

TENDERS, RATINGS AND UTILITY OPERATIONS

8NEEPCO gives 98 solar streetlights 120 days and a five-year security tail
8OPG Energy’s rating exit follows negative operating margin and an expired gas contract
8PSPCL sets a 5.6 efficiency floor for new five-star split air conditioners through 2028
8PVVNL plans two-to-four-hour outages to underground lines and rebuild distribution assets

SHAREHOLDER AND AUDIT NEWS

8EKI director vote passes after 60% of participating public holders oppose it
8CG Power proposes a Rs 1.58 crore auditor after SRBC resigns
8REC shareholders approve private-placement authority while the PFC merger remains in view

CURRENT GRID AND SYSTEM DATA

Compatible daily series reveal where demand, shortage, outages, forecast accuracy and scheduling actually moved.

8Northeast evening shortage rises to 50 MW and remains entirely in Manipur
8Eastern day-ahead forecast error improves despite a blank published summary
8Eastern forced outages fall 330 MW while Teesta and delayed returns keep risk visible
8Zero corridor breaches hide worsening voltage stress at Nizamabad
8Northern evening demand rises as shortage falls by nearly one third
8Grid scheduling adds low-cost coal while leaving seven expensive gas units unused
8Southern region serves more energy with zero peak shortage
8Southern load-forecast error rises to 1.61% but stays below 2%
8Southern forced outages fall 800 MW after one unit returns

CURRENT EXCHANGE AND TRADE DATA

Current market series show price caps persisting, demand going unmatched and one-day trades failing to become continuous liquidity.

8A Rs 10,000 price survives even as real-time volume halves
8Intraday buy interest more than doubles but no seller clears
8Ancillary spot market records ten straight days without an upward trade
8One Rs 10,000 real-time trade disappears on the next two days
8Green term-ahead prices stay at Rs 10,000 across both reported days
8Western term-ahead discounts vanish as every listed contract reaches Rs 10,000
8Green day-ahead volume rises 4.7% while buyers pay 5.9% more Details
8CTUIL's Ratle-Kiru Independent Engineer Tender Turns One Consultant Into a Future Claims Referee CTUIL's QCBS-based appointment for the 400 kV Kishtwar-Samba-Jalandhar evacuation scheme goes well beyond routine site inspection — the same Independent Engineer will later assess time-extension claims, change-in-law events and cost reasonableness for the transmission service provider. A seven-month consultancy term sits uneasily against the scheme's 24-month COD, raising the question of whether surveillance coverage will actually last through commissioning.

8WAPCOS's Balangir Design Tender Locks In a Binding 25% Option Clause With No Corresponding Bidder Consent WAPCOS's architectural-design consultancy for a Rs 62.09 crore Odisha complex carries an estimated fee of just Rs 49.67 lakh, yet the buyer can expand quantity or duration by up to 25% post-award without the consultant's agreement. A 45-day payment cycle and no ePBG requirement further tilt working-capital exposure toward the design firm.

8TGGENCO's Grinding-Roll Rate Contract Shows a Rs 1 Portal Estimate Against a Rs 1.15 Crore EMD TGGENCO's two-year rate contract for bowl-mill grinding rolls and bull ring segments treats failure of either wear component as failure of the entire matched set — an aggressive reliability transfer layered onto a tender whose own portal-listed estimated value is commercially incompatible with its EMD and turnover thresholds. No minimum purchase quantity is guaranteed despite the extensive security stack required to participate.

8RRECL's Seven-City EV Charging Tender Extends 20 Days While Its Own Cover Count Stays Unreconciled RRECL's Rs 99.77 crore PM E-DRIVE rollout across Jaipur, Udaipur, Kota, Ajmer, Alwar and Jodhpur pushed its bid deadline by three weeks, but the RFP still describes the financial bid as "Cover 3" even though the portal configuration uses only two covers. An H1 revenue-share award model means the winning bidder profits from promising the most to RRECL — not from building the cheapest network.

8NHPC's Kamala Dam Tender Defers Hydro-Mechanical Vendor Vetting to After Award NHPC's Rs 5,541 crore Lot-1 package for the 216-metre Kamala dam pushed its bid deadline by 64 days across five extensions while quietly moving specialist gate-manufacturer qualification from bid stage to six months before execution — a deliberate loosening of entry barriers that keeps the underlying technical benchmark untouched. Disposal zones were also cut from four to two, both now shared with the adjoining Lot-2 contractor.

8NHPC's Uri-I Stage-II E&M Package Raises Idling Compensation Just as It Extends Bidding by 47 Days NHPC's Rs 641.11 crore underground turbine-generator package for the 240 MW Uri-I Stage-II project increased its idling-cost recovery ceiling from 4% to 5% of contract value and introduced partial operational acceptance, but continued to reject contractor requests to cap liquidated damages or shorten latent-defect exposure. Performance-equalisation rates for turbine and generator efficiency were also raised, sharpening the evaluated-price penalty for weaker guarantees.

8DVC's Chandrapura Cable Diversion Tender Splits Into Two Contracts But Keeps One Bidder Fully Liable DVC's Rs 90.20 crore 220 kV line-diversion package for the 2×800 MW CTPS expansion now awards supply and erection as two separate contracts to the same lowest bidder, doubling the performance-security instruments without diluting single-point technical accountability. An asymmetric qualification route still lets an overhead-line contractor bring in a cable specialist, but not the reverse.

8UJVN's Chilla BESS Tender Raises Its Tariff Ceiling by 3.8% After Bidder Pushback UJVN's 90 MW/225 MWh storage project near Chilla HEP corrected its capacity-charge ceiling to Rs 3,30,400/MW/month and admitted Insurance Surety Bonds as an EMD alternative, but kept the free-transfer BOOT structure, limited VGF coverage of just 60 MWh, and rejected a cure period for delayed financial closure. Two mandatory daily charge-discharge cycles over 12 years put degradation and augmentation costs squarely on the developer.

8BHEL's Talabira Ash Handling Tender Hits Its 14th Deadline Extension BHEL's EPC package for ash and mill-reject handling at the 3x800 MW NLC Talabira project has now moved 101 days past its original May deadline through 14 separate corrigenda, while every technical, financial and liability threshold remains untouched. The pattern suggests BHEL is using time — not qualification relief — to manage a persistently thin or slow-forming bidder field.

8NTPC's Ramagundam Transformer Swap Halves Site Time While Waiving a Costly Short-Circuit Retest NTPC's replacement of two 250 MVA autotransformers with 500 MVA units kept its 30-month deadline fixed but reallocated it — cutting erection and commissioning from six months to three while extending factory time to 27 months. Manufacturers with an already-tested similar 500 MVA design can skip a fresh dynamic short-circuit test, quietly narrowing the practical vendor pool to firms with that specific reference design.

8MPPGCL's Birsinghpur Solar Tender Adds a ±10% Land-Driven Price Corridor MPPGCL's 30 MWac solar EPC-plus-O&M package now lets contracted capacity, price, O&M charges and schedule all move by up to 10% if the final usable land differs from the tentative parcel — while separately deleting an extra 3% security once imposed on every non-lead consortium partner. Interim O&M payment before final acceptance testing rose from zero to 75% of applicable charges, easing cashflow for a plant already delivering power to the grid.

8TANTRANSCO's Samugarengapuram GIS Tender Refuses a Schedule Extension Despite a 32-Month Transformer Lead Time TANTRANSCO corrected a mislabelled BOQ item showing an autotransformer where a 420 kV, 3150A SF6 breaker was intended, but held firm on its 24-month completion period even after a bidder cited roughly 32-month manufacturing lead times for the required transformers. A parallel conflict over whether TANTRANSCO or the contractor supplies the autotransformers remains unresolved between the invitation document and Appendix 4.

8GSECL's Ukai Protection Retrofit Tender Adds Full Cabling Scope After Original Issue GSECL's busbar and transformer protection modernisation at Ukai now includes newly specified copper cabling for 12 existing bays plus a mandatory new GPS clock synchronising every legacy 220 kV relay — obligations absent from the original specification. A "most stringent clause governs" rule resolves internal contradictions in the buyer's favour, including an unexplained shift from a four-zone to a two-zone busbar protection scheme.

8JVVNL's 25,000-Unit Transformer Tender Ties Future Allocation to Past Repair Performance JVVNL's Rs 160.25 crore distribution-transformer procurement withdraws the old vendor-registration security exemption and introduces a distributed award formula capping L1 at just 20% of quantity — while suppliers whose historical guarantee-period repair rate falls below 75% can find their price bid rejected outright regardless of current compliance. Zero positive tolerance on losses and CTL-gated payment convert factory testing into a continuous field-performance obligation.

8SJVN's Panipat BESS Tender Shrinks Its Commissioning Window While Demanding 100% Grid-Forming Compliance SJVN's 265 MW/530 MWh battery storage tender for UHBVNL cut SCOD from 18 months to 15 and tightened availability from a 95% annual average to a stricter 95% monthly floor — even as a new CEA advisory now mandates full grid-forming inverter capability across the entire capacity. The fixed 13-acre site allocation arrives with no geotechnical, drainage or contamination data, leaving developers to self-investigate a plot bidders argue may be undersized.

8NHPC's Dulhasti Stage-II E&M Tender Inserts an Entire Crane Specification Mid-Bid NHPC's Rs 496.90 crore Lot-2a package for the 260 MW Dulhasti Stage-II project added a complete new chapter covering powerhouse and cavern cranes after the original tender issue, while separately lowering the minimum guaranteed turbine efficiency threshold from 94.5% to 94% to keep more bidders responsive. A revised 22-item interface matrix now ties this lot's cabling and protection scope directly to a second, separately contracted package.

8MCL's Lingaraj Surface-Mining Tender Lets Machines Be Reassigned Across Mines Without Compensation MCL's Rs 90.91 crore, 1.99 crore cubic-metre surface-mining contract at Lingaraj OCP permits company-wide relocation of contracted equipment "without additional claims," turning what looks like a site-specific award into a mobile fleet commitment. A ten-day mobilisation clock and a contract-precedence conflict — between the GeM-generated contract and a separately issued LOA — add further uncertainty before bidding even closes.

8RVUNL's Bodana Pooling Station Tender Repeatedly Dilutes Its Own JV Threshold RVUNL's Rs 497.34 crore twin pooling-station package for the Bodana solar park cut the lead joint-venture partner's required financial contribution from 50% to just 25% across two separate corrigenda, and now accepts a secured order still under execution as qualifying experience — a marked widening of entry after five deadline extensions totaling 60 days. A single 20-month completion obligation still binds both stations together despite unresolved conflicts between the tender's 180-day and 240-day bid-validity clauses. Details
8The Power Ministry has directed that the software and hardware used to monitor and operate electricity grids, formally called supervisory control and data acquisition systems, should not be imported beyond 2030. Details
8Karnataka's electricity regulator has set purchase tariffs for new distributed solar projects commissioned, or applied for, from 25 August 2026 through 30 June 2029. Details
8Southern Power Distribution Company of Andhra Pradesh reported combined losses from electricity lost in the network and bills not collected of 24.66% in the year ended March 2026, up from 7.99% a year earlier. Details
8Gorbea Solar's 300 MW project in Rajasthan could not send about 38% of its potential output to the grid during the first ten months of the year ended March 2026 because it was operating through temporary access while the permanent transmission system was delayed. Details
8Northern India could supply only 79,148 MW against an evening requirement of 81,141 MW on 25 August, leaving a 1,993 MW gap at 8 p.m. by our arithmetic. The region also recorded 7.82 million units of unmet energy over the day. Details
REGULATORY ORDERS & PROCEEDINGS

8Meghalaya regulator hears revised grid fees for outside power purchases on 27 August
8Galwalia Ispat's grid-charge dispute awaits Uttarakhand order after 25 August hearing
8Bhilangana Hydro gets final two-week evidence window before Uttarakhand payment ruling
8CERC may deny Bawana Mandola costs unless Power Grid files missing evidence
8Power Grid has until 10 September to substantiate Ludhiana transformer charges at CERC
8Bhuj's ninth transformer needs corrected cost evidence before CERC sets charges
8CERC requires linked loan and damage records before deciding Northern fibre charges
8Southern grid control charges face CERC decision after 10 September evidence deadline
8Power Grid must prove Dehgam equipment costs before CERC sets charges
8Power Grid faces 10 September deadline for Western communication evidence at CERC
8Power Grid must prove New Navsari equipment entered service before CERC decides costs
8CERC gives Power Grid until 10 September to reconcile Bhutan power network assets and loans
8Power Grid must document financing and delays for fibre linking Western generators before CERC rules
8CERC reviews Northern grid upgrade loans and damage records before setting charges
8Power Grid must file Western grid upgrade loan records before CERC sets charges
8CERC asks whether Power Grid must treat Kishenpur Moga transformer failures as maintenance costs
8Power Grid must complete three Northern fibre cost records for CERC by 10 September
8CERC keeps Ayana invoice protection until final hearing on 22 September
8TP Saurya retains protection from Rs 14.17 crore damages while CERC prepares delayed-project ruling
8Electricity trader Refex keeps its CERC licence until it proves all liabilities are paid
8Railway buyers get final reply chance before CERC hears 5%-to-12% solar tax claim
8Delhi court order preserves ReNew grid access until CERC's 6 October hearing Details
8Renewable Energy Ministry blocks 66 solar vendors from new customers until backlogs improve
8Madhya Pradesh regulator requires 3% stored renewable power from April 2027 with 85% sourcing test
8Renewable Energy Ministry requires India-based wind data systems before random inspections Details
8India's July coal output rises 7.6% while four-month production remains 3.1% lower Details
8Western grid participants record Rs 14.92 crore net receivable after large offsets Details
8Adani leads Rs 4,700 crore Satara grid bid without receiving formal award
8India adds 3.14 GW renewable capacity in July with no thermal project commissioned
8Adani's 7,000 MW Khavda corridor slips one year as land access blocks construction
8Power Grid's four Khavda corridor transformers run six months late and disrupt planning
8Power Grid pushes Boisar's fifth transformer five months late, delaying added capacity Details
8Solar developer ACME secures 130 MW railway deal at Rs 4.35 per unit for 2029 supply
8Suzlon secures 250 MW Torrent order and lifts joint portfolio above 1.3 GW
8Kribhco Green loses ethanol buyers after two-year delay while parent considers debt repayment
8Eight Amplus solar companies refinance 65.6 MW pool but remain exposed to shared defaults
8Viviana has cash but leaves bondholder unpaid after bank verification blocks Rs 9,173 transfer
8Dhariwal profit rises 14.5% as debt and finance costs climb faster Details
8Chhattisgarh regulator cuts Jindal's annual distribution cost claim by Rs 113.37 crore
8Chhattisgarh regulator ends Jindal network discount for solar projects commissioned after 2026
8Chhattisgarh regulator defers Jindal's Rs 90.57 crore distribution claim to later cost review
8Uttar Pradesh regulator approves 300 MW solar deal but bars tariff delay claims
8Gujarat regulator requires written requests before lawyers can add unlisted cases to hearings
8Gujarat regulator keeps Tata Motors' Rs 5.59 crore wind surcharge dispute open for final replies
8CERC preserves ReNew's grid access pending compensation ruling after 13-day delay
8Electricity trader PTC India faces CERC enforcement review over disputed Rs 64 crore payment
8State-owned renewable developer NTPC Renewable must show why CERC can hear its tax claim
8Power Exchange India seeks CERC approval to credit surplus electricity as competing platform asks to join
8MB Power's ash claim advances at CERC despite unresolved delay objection before 22 October
8CERC weighs four Reliance grid connection costs after Power Grid prices only two
8Power Grid's Neemuch compensation claim turns on whether the tender fixed the project site
8CERC asks solar developer ACME whether its Rs 42.97 crore claim deducts rerouting savings
8Adani's 600 MW tax and equipment claim enters CERC review without approved payment
8Uttar Pradesh regulator upholds Barabanki Satrikh route and leaves landowners to claim compensation
8Jaypee seeks 77% larger single power connection with distributor response due before 6 October
8Uttar Pradesh defers 600 MW wind purchase pending CERC tariff and corrected capacity data
8Uttar Pradesh regulator closes 7 MW sugarcane waste power case so buyer can correct contract
8Tripura law mandates lift registration and rescue devices with Rs 50,000 penalty for breaches Details
 For reference purposes the website carries here the following tenders:
 
8Tender for civil work for construction of 01 No. 33 kV bay at 220 kV S/S Details
 
8Tender for work of underground section of 132 kV SC line Details
 
8Tender for construction of 132 kV double circuit line with panther equivalent HTLS conductor on DC tower Details
 
8Tender for connecting and extending the pipeline Details
 
8Tender for works contract for heightening the pillar boxes Details
 
8Tender for empanelment of agencies for new 33/11kV substation, additional /augmentation of PTR at existing 33/11 kV S/s, HT lines, LT lines Details
 
8Tender for providing and laying of water proofing treatment over roof Details
 
8Tender for procurement of filter elements for TG and LP bypass governing rack installed Details
 
8Tender for procurement of smart positioners along with their installation and commissioning for pneumatic power cylinder Details
 
8Tender for exterior and interior emulsion painting etc. Details
 
8Tender for works contract for heightening the pillar boxes Details
 
8Tender for procurement of 270 kgs each of TC fuse wire of 12 SWG,14 SWG,16 SWG Details
 
8Tender for supply of TC fuse wire 12 SWG 200kgs TC fuse wire 14 SWG 400 kgs Details
 
8Tender for supply of SEC wire 18 SWG Details
 
8Tender for supply of SEC wire 21 SWG Details
 
8Tender for balance civil works for 400 by 220 kV substation Details
 
8Tender for supply of 66kV and 33kV potential transformers (PTs) for various substations Details
 
8Tender for supply of 1000KVA 6600/433V, 3 Ph dry type LT transformer for auxiliary supply system Details
 
8Tender for replacement of roofing sheet and false ceiling Details
 
8Tender for supply and distribution of ration kit Details
 
8Design, development, testing and supply of 11 kV outdoor metering cubicle with resin cast current transformers and potential transformers Details
 
8Tender for supply of compressed gas refill in JPL cylinders for plant operational requirement Details
 
8Tender for installation barbed wire fencing Details
 
8Tender for laying of pipeline with thermal lagging and electrical heat tracing Details
 
8Tender for supply of fire system pumps Details
 
8Tender for additional new 1 x 220/22kV 50MVA TF along with 220kV hybrid switchgear Details
 
8Tender for work of installation of addl. DTR of 315 KVA at various Details
 
8Tender for work of installation of addl. DTR 13x200 KVA,1x 315, 8x100 KVA substation Details
 
8Tender for work of 33 kV interconnection work of feeder from 33/11 kV substation Details
 
8Tender for procurement of spares of domestic water pumps Details
 
8Tender for procurement of front end grabber machine used Details
 
8Tender for ARC/AMC for operation & maintenance of HT/LT switchgear, transformers Details
 
8Tender for overhauling of 59 fields of ESP during overhauling Details
 
8Tender for special estimate for creation of 02 No. 132kV line bays Details
 
8Tender for outsourcing work of ETC of 1 no additional 12.5 MVA power T/F Details
 
8Tender for replacement of 1x 25MVA 132/33kV TF by 1X50MVA 132/33kV transformer along Details
 
8Tender for procurement of spares of scanner air fan for unit no. 1 and 2 and complete runner shaft assembly Details
 
8Tender for procurement of HRC fuses and lugs for various power houses Details
 
8Tender for work contract for providing man days for assistance in day to day mechanical and electrical maintenance and store related work Details
 
8Tender for annual maintenance for power house Details
 
8Tender for procurement of spares of MIL make various control valves Details
 
8Tender for availing supervisory services of service engineer for servicing of vacuum pump Details
 
8Tender for supply of AC digital tong tester Details
 
8Tender for supply and ETC of construction of LILO of 132 kV SC line Details
 
8Tender for annual contract for RBC maint work of 4x750 KVA DG set of Unit-1to4, elect system Details
 
8Tender for procurement of various type of control transformers Details
 
8Design, supply, installation, retrofitting, testing and commissioning of 220kV bus bar panel Details
 
8Tender for supply of various protective shields, guide pipes Details
 
8Tender for supply and retrofitting of LT incomer/tie breakers and modules Details
 
8Tender for rate contract for removing, lifting, shifting, dismantling and overhauling of 6.6 kV HT motors Details
 
8Tender for supply of high pressure valves (IBR approved) for boiler unit Details
 
8Tender for annual rate contract for electrical maintenance job Details
 
8Tender for repairing and painting of TP-35 and TP-38 and the interconnecting conveyor gallery Details
 
8Tender for procurement of different spares of bowl mill XRP 1003 Details
 
8Tender for installation of 200 mm dia bullah piles (600 meter new and 106 meter repairing) with drum sheet walling Details
 
8Tender for procurement of 100 MT caustic soda lye Details
 
8Tender for service contract for monitoring and emergency repairing of track hopper gratings Details
 
8Tender for biennial maintenance contract for pest control and rodent control activities Details
 
8Tender for laying of 3C 33 kV 400 SQ MM XLPE UG cable Details
 
8Tender for supply and delivery of LED light fittings and fixtures Details
 
8Tender for earth work excavation, stub setting, concreting, supply, transport and erection of 110 kV DC line Details
 
8Tender for supply of 11 kV AB switch with clamps & HG fuse set with clamps for 11kV single pole structure Details
 
8Tender for procurement of 11kV AB switch with PT insulator Details
 
8Tender for procurement of stay set complete Details
 
8Tender for supply, & fabrication of RS joist, MS channels, MS plate, supply of MS flat, MS rod Details
 
8Tender for procurement of 33kV 1 x 630sq mm UG XLPE aluminium power cable. Details
 
8Tender for supply of cold fill pump Details
 
8Tender for supply &. retrofitting of numerical distance relay Details
 
8Tender for work of annual maintenance contract (AMC) for troubleshooting, repairing, and maintenance for 145kV & 245kV ABB make circuit breaker along Details
 
8Tender for work of chemical cleaning of insulators Details
 
8Tender for work of supply, erection testing and commissioning of additional 132/33 kV, 50 MVA power T/F Details
 
8Tender for work of supply, erection, testing, commissioning of an additional 1X50MVA 220/33kV power transformer along with HV,LV bay Details
 
8Tender for work of supply, erection, testing and commissioning of an additional 1X 25MVA 132/33kV power transformer along Details
 
8Tender for second circuit stringing on 132kV lines Details
 
8Tender for additional of 1 X 100MVA, 220/22-22KV kV T/F along with EHV GIS bay Details
 
8Tender for providing additional 50 MVA 220/22 kV TF along with EHV GIS bays Details
 
8Tender for day to day maintenance for civil assets in sub-station Details
 
8Tender for procurement of C37 card required for communication of line differential relay Details
 
8Tender for procurement of various communication cards of FOTE panels Details
 
8Tender for renovation of earthing work of ICT&TF at 220 kV substation Details
 
8Tender for annual maintenance contract (AMC) for work of repair of ABT PC system, installation of ABT meter Details
 
8Tender for ARC work of erection of 66kV equipment, structures, control wiring, yard lighting etc. Details
 
8Tender for annual rate contract for providing and fixing of 11 kV heat shrinkable outdoor, indoor & straight through joint type cable Details
 
8Tender for supply of shaft for bearing housing assembly for beater wheel coal pulverised mill Details
 
8Tender for miscellaneous civil works Details
 
8Tender for construction of store shed platform with ramp Details
 
8Tender for BRC for work of rewinding and overhauling of 11kV HT motors of MV/NVT pumps Details
 
8Tender for work of design, supply, erection, testing and commissioning of new generator relay panels Details
 
8Tender for annual rate contract for onsite maintenance of 11/0.250 kV, 1- phase & 11/0.433 kV 3-phase distribution transformers Details
 
8Tender for supply of hydraulic accumulator, bladder, nitrogen charging kit & fittings for coal mill Details
 
8Tender for supply of consumable material Details
 
8Tender for dismantling, supply, installation, testing & commissioning of passenger cum goods lift in boiler Details
 
8Tender for supply of BWSR spares for 2 x 250 MW Details
 
8Tender for work of residual life assessment study of removed HP, IP & LP turbine rotors Details
 
8Tender for providing muffing on periphery of existing various steel structure of coal yard Details
 
8Tender for providing & fixing safety showers and sintex tank including other miscellaneous civil works Details
 
8Tender for providing and laying concrete & steel cover for unit 1 to 5 boiler side Details
 
8Tender for supply of C&S electric make ACB & panel spares Details
 
8Tender for supply of cooling water treatment chemicals compatible with on line monitoring and auto chemcal addition control system Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8Flash Report on Central Sector Infrastructure Projects worth Rs150 crore and above Details
 8India tracks infra projects worth Rs 37.11 lakh crore as of July; 36 added in month Details
 8Eastern Coalfields Inducts 127 Employees Under Employment and Rehabilitation Schemes Details
 8UPERC Puts UPPCL’s 600 MW Wind Power Procurement Under Scrutiny Details
 8Gujarat Leads India in Renewable Energy, Cuts 49.79 Million Tonnes of Carbon Emissions Details
 8Minister Nara Lokesh launches Suzlon’s INR 10,500 crore wind energy projects in Anantapur Details
 8Hitachi Energy vs Siemens Energy: Which Stock Is Better Positioned for Rs 1.6 Lakh Crore HVDC Opportunity Details
 8Renewables news: Otovo, Green Panel Solar Energy, Edisun Power, Flender Details
 8India’s solar PV manufacturing capacity hits 100 GW, but upstream import dependence remains high: NITI Aayog Details
 8Otovo Acquires Green Panel Solar for $11 Million Expansion Details
 8Rooftop Solar, KUSUM Drive 40% of Solar Additions In FY27: Bernstein Details
 8CERC Grid Relief and MNRE ALMM Expansion: Industry Update Details
 8POWERGRID Tenders 530 MWh BESS Project in Haryana Details
 8Adani Green Energy Success Story: The World’s Largest Renewable Energy Portfolio Details
 8Repowering Tamil Nadu’s wind power sector Details
 8Rigid thermal power contracts putting India’s energy transition at risk, finds CSE study Details
 8Power sector at tipping point as SC takes up DERC plea today Details
 8India’s Renewable Energy Generation Rises 17.27% In July 2026, Crosses 38,497 MU Details
 8Renewables Reach 63% of Türkiye’s Power Capacity Details
 8Advancing Gender-Responsive Just Transitions in India’s Coal Belt Details
 8Kshema Power Secures EPC Order For 315-MW Wind Power Evacuation In Karnataka Details
 8The future is in electrification, electricity will take over oil’s growth role, says IEA Details
 8L&T Wins Major 6 GWh Battery Energy Storage Project in Middle East Details
 8India to stop SCADA imports beyond 2030; local content still below 20% Details
 8India’s Power Grid Faces Squeeze From AI Boom and AC Demand Details
 8A flickering trade Details
 8CSE Report Flags Rigid Power Contracts as Risk to Energy Transition Details
 8REC Limited Honoured with Two Silver Awards at ASSOCHAM Corporate Bond Market Summit Details

 
You can also click on Newsclips for more Details
8The Southern Region carried a 13% jump in July peak demand with a sharply smaller hydro cushion. Its operating committee also records the grid outside the permitted frequency band for more than a quarter of the month. Details
8The annual energy account reports distribution losses of 7.9%. Weak collections lift the combined technical and commercial loss to 24.7%, while more than 1.2 million consumers and every listed distribution transformer remain unmetered. Details
8Uttarakhand’s regulator has approved a replacement power line to Kedarnath only after the utility awarded the work. The new line follows the loss of underground cables from a government-funded project that had operated for about seven months. Details
8India’s central regulator has fixed generic tariffs for small hydro and biomass projects for the current control year. Developers won the tariff order but lost their attempt to reset capital costs, maintenance allowances and financing assumptions. Details
8The power ministry wants the control-room systems that run the grid to stop being imported after this decade. The committee designing that transition says current local content is still below 20%, with hardware carrying three-quarters of system cost. Details
8Monday turned the price warning from the previous edition into a physical shortage. India’s reported peak shortfall rose to 1,513 MW from 200 MW on Sunday, while the next day’s exchange auction eased only to Rs 6.82 a unit. Details
REGULATORY ORDERS AND PROCEEDINGS

8CERC keeps Adhunik’s disputed invoices under interim protection while the case is adjourned
8CERC asks for more evidence on Athena Jaipur Solar’s reactive-power change claim
8DB Power settles an Rs 11.22 crore payment case through six instalments
8Mundra power disputes remain paused while APTEL reviews related issues
8JSW’s request to excuse delay at a 540 MW wind project remains undecided
8POWERGRID seeks 748 extra days and Rs 438.82 crore for the Sikar system
8Kreate Energy’s licence-revocation case waits for an appellate ruling
8SECI opens a GST compensation case for a 300 MW solar project
8Khandukhal Rampura transmission relief remains pending after another adjournment
8Adani Green’s claim for transmission charges and lost generation stays at pleading stage
8Khaba Renewable’s 90-day connectivity extension request is reserved for order
8Jharkhand’s renewable-payment case gets more time for clarification
8Datta Power wins an urgent hearing before its grid access expires
8POWERGRID seeks 673 extra days and Rs 151.07 crore for Aligarh Sikar works
8NLC’s 200 MW Bhuj solar case keeps its interim protection
8Tata Power Delhi starts a damages case over delayed SECI solar supply
8Buxar seeks Rs 82.04 crore for 401.87 million units of pre-commercial power
8Gujarat asks a captive-power surcharge dispute to complete its written record
8Gujarat allows inspection of Kundan Solar after module replacement raises capacity questions
8Hindalco’s renewable-obligation case remains open for updated compliance data
8Paryapt Solar’s safeguard-duty claim moves to account reconciliation
8UPERC gives Ayesha Steel one last chance to support its load-reduction request
8Punjab publishes an RPO-surplus order without the decision in the supplied copy

COMPANIES AND FINANCE

8Yuva Bio Energy’s 12-tonne CBG plant starts with stretched liquidity
8Inox Renewable allots 4.90 crore shares under its approved demerger

GRID AND MARKET PULSE

8Generation outages remain above 48,000 MW with state units carrying the larger share
8Eastern imports into the North exceed their operating limit for five blocks
8Western 765 kV voltages stay high at Banaskantha for almost three hours Details
8Thirty-eight coal plants hold critical stocks as the national pile reaches half its norm Details
8Kerala proposes a full tariff framework for batteries and pumped storage
8Gujarat gives a 20 MW hybrid project thirty days to finish connection formalities
8Andhra consumers face a 40 paise fuel-cost adjustment in September bills Details
8POWERGRID wins a 7,500 MW Gujarat evacuation system at Rs 822.91 crore yearly
8L&T wins a 6 GWh Middle East battery order worth Rs 5,000–10,000 crore
8Insolation wins nine Maharashtra solar projects requiring about Rs 425 crore
8Khavda transmission line reaches AAA while refinancing introduces a five-year put risk Details
8RECPDCL's Nasik-Pimpalgaon Transmission Tender Draws a Five-Way Field With Zero Consortium Bids REC's TBCB process for the 765/400/220 kV Nasik substation and its two evacuation corridors qualified five bidders — Adani Energy Solutions, Ceigall India, Dilip Buildcon, Power Grid and Resonia — all bidding solo with 100% equity, bypassing the consortium route entirely. A single 36-month COD ties all six project elements together for tariff recovery, meaning a delay in any one bay or reactor can block revenue across the whole package.

8RECPDCL's Lakadia REZ Mega-Tender Rejects Dilip Buildcon While Six Others Clear a Rs 4,506 Crore Bar RECPDCL's Gujarat renewable-evacuation package — featuring a 7,500 MW pooling station, synchronous condensers and space reserved for a future 6,000 MW HVDC terminal — qualified six of seven bidders, with Dilip Buildcon rejected as non-responsive without a disclosed reason. The qualified-bidder notice arrived 42 days late against the original schedule, and only four of the six will advance to the reverse auction.

8PFC's Rundh Gidawara 765 kV Tender Ties 100% Tariff Recovery to Simultaneous Commissioning of Every Element PFC Consulting's Alwar substation RFP demands a 30-month build-own-operate-transfer delivery where the developer can't monetise any single completed asset until the whole interdependent system — GIS station, 765 kV line, LILO and 400 kV connection — goes live together. The acquisition price for the SPV won't even be disclosed until 20 days before bid closure, leaving bidders to finalize financing on short notice.

8PFC's Bhojrajka Substation Tender Launches With Its Own SPV Still Unnamed PFC Consulting's Rajasthan RFP for the 400/220 kV Bhojrajka station bundles a new double-circuit line, two voltage-level LILO programmes and works inside an existing 765 kV station — all under one 30-month deadline — while the project-specific SPV remains listed as "under incorporation" in the very clauses that require its acquisition. A 15-minute discrepancy between the Hindi invitation and the English RFP over technical-bid opening time (15:45 vs 15:30) adds a small but avoidable procedural risk.

8POWERGRID's 765 kV Transformer Award Lands 15% Below Its Own Reverse-Auction Estimate BHEL won POWERGRID's Rs 514.56 crore Lot-7 bulk transformer package at a price Rs 90.59 crore below the Rs 605.15 crore indicative benchmark, with the tender notably replacing cash EMD with a bid-securing declaration backed by a one-year ineligibility threat. Twenty-three single-phase 500 MVA units must ship in phased batches, with cross-defaulted supply and services contracts ensuring that any site-side slippage carries consequences across the whole award.

8NTPC's Great Nicobar Substation EPC Slips 80 Days While a Daily Rs 37 Lakh Penalty Clock Stays Fixed NTPC's twin 132/33 kV substation package for Gandhinagar and Campbell Bay saw its bid deadline pushed three times — ultimately by 80 calendar days — without any corresponding extension to the underlying 24-month completion period. Materials must reach two remote island locations reachable mainly by ship and helicopter, while the daily delay-damage rate of Rs 37.03 lakh starts ticking from day one of any slippage.

8TNPGCL's North Chennai FGD Retrofit Tender Pushes Its Opening Date Back 164 Days Across Eight Corrigenda TNPGCL's flue-gas desulphurisation package for three 210 MW units at North Chennai has seen its tender-opening date slide from 7 April to 18 September 2026 through eight separate corrigenda, alongside five postponements of the pre-bid meeting. The 24-month execution clock remains untouched despite the extended runway, and price escalation has been deleted entirely from the contract.

8Raipur's Korba West Consultancy Tender Reveals a Coal Handling Plant Built Ahead of Its Environmental Clearance E.D. (Project), Raipur has floated a consultancy assignment to amend the environmental clearance for HTPS Korba West after land was already acquired for the coal handling plant — meaning physical site development appears to have outpaced the regulatory approval it depends on. The notice discloses no land quantum, deliverables, timeline or liability terms, leaving the assignment's real scope entirely undefined.

8RVUNL's Suratgarh O&M Tender Can't Decide If It's a Three-Year or Five-Year Contract RVUNL's Rs 180 crore comprehensive O&M package for the 2x660 MW Suratgarh plant states a three-year term in its NIT and portal listing, while six separate annexures independently declare a five-year duration — a contradiction that survives five deadline extensions spanning 115 days. Performance penalties for DSM charges, demurrage and environmental notices sit entirely outside the tender's headline 10% liquidated-damages cap.

8TGGENCO's Srisailam Generator Replacement Ties 45% of Payment to a 72-Hour Test Run TGGENCO's brownfield replacement of a 150/175 MW generator-motor at SLBHES requires the new machine to fit precisely around a retained MELCO-era turbine, brackets and excitation system, with commissioning-linked payment retention rising from 40% to 45% if delivery slips. The bid security's own claim period contradicts itself — one clause says three months, another says six.

8WBSETCL's Salboni HTLS Line Tender Rewrites Its Price-Comparison Formula Mid-Bid WBSETCL's 68 km, 400 kV HTLS transmission package extended its bid deadline by 14 days while simultaneously replacing its bid-comparison clause with a new formula that converts technical deficiencies directly into rupee penalties on the evaluated price. A conflicting insulator creepage-distance requirement (370mm vs 430mm) was resolved in favour of the stricter technical specification through a revised BOQ.

8NTPC's Ramagundam Transformer Replacement Halves Its Site-Execution Window to Add Factory Time NTPC's replacement of two 250 MVA auto-transformers with 500 MVA units at Ramagundam kept the overall 30-month deadline fixed but reallocated it — supply time grew from 24 to 27 months while erection and commissioning shrank from six months to just three. A parallel concession lets bidders skip a costly dynamic short-circuit test if they can prove design similarity to a previously validated 500 MVA unit.

8BSPGCL's Kajra BESS Tender Hands Over Land But Leaves Battery Chemistry and Degradation Undefined Bihar State Power Generation's 500 MWh, four-hour standalone battery storage tender under a build-own-operate-transfer model provides the Kajra site but discloses no chemistry, augmentation obligation, availability standard or tariff-payment mechanism in the notice itself. A Rs 13 crore EMD plus a Rs 15 lakh non-refundable processing fee creates a steep entry cost before any of that technical risk is even resolved.

8NRPC's Rs 25,000 Audit Tender Can't Agree With Itself on Bidding Structure or Arbitration Northern Regional Power Committee's tiny financial-audit engagement for FY 2025-26 shows GeM's portal declaring a "Two Packet Bid" while the tender's own ATC clause insists on a single-packet process — and GeM separately marks arbitration as "No" even as the underlying contract conditions prescribe a full NRPC-appointed arbitration mechanism. Despite the negligible Rs 25,000 estimate, a bid-security declaration carries a two-year non-responsiveness penalty for withdrawal or default.

8AEGCL's Sarusajai GIS Conversion Tender Locks Prices Firm for 730 Days With No Escalation Relief AEGCL's Rs 455.90 crore turnkey conversion of a live 220/132/33 kV AIS substation to GIS technology declares prices "firm" and explicitly excludes price adjustment "on any account," despite a two-year execution period exposed to steel, copper and GIS-component volatility. A five-year extended guarantee on the GIS equipment itself is backed by security equal to 20% of that equipment's cost — layered on top of the standard 10% performance guarantee.

8NSPCL's Tax-Law Migration Tender Reappears With Wider Scope and the Same Unresolved Contradictions NSPCL's republished consultancy tender for migrating to the Income-tax Act, 2025 now requires validating the correctness of historical tax positions — not just forward-looking compliance — while GeM's portal says no EMD and no arbitration are required even as the underlying GCC clauses impose a 5% performance guarantee and a full arbitration mechanism. Two separate clauses set the Class-I local-content threshold at both 50% and 60%, leaving basic eligibility unsettled.

8Raipur's Korba West Environmental Consultancy Notice Repeats Itself Without Adding a Single New Detail A near-identical restatement of E.D. (Project), Raipur's HTPS Korba West environmental-clearance consultancy still fails to disclose the additional land area, the coal handling plant's revised footprint, or any deliverable, timeline or liability term — confirming that the underlying regulatory-sequencing question remains as open as the assignment's scope itself. Details
 For reference purposes the website carries here the following tenders:
 
8Tender for construction of 2x401x63MVA MVA 132kV S/S Meerut Details
 
8Tender for construction of 2x40 MVA 132kV S/S Budaun Details
 
8Tender for construction of 132kV SC line Details
 
8Tender for construction of LILO of 220kV DC line Details
 
8Design, engineering, manufacture, factory testing, supply, transportation, supervision of installation and commissioning of 33kV and 11kV RMUs for 33kV substation Details
 
8Tender for construction of new concrete retaining wall adjacent to the existing concrete retaining wall at switchyard Details
 
8Tender for standardization of transformer station Details
 
8Tender for rerouting of HT line Details
 
8Tender for stringing high tension 33kV covered conductor, shifting and modification of the existing 11 kV, and low tension (LT) electrical distribution network Details
 
8Tender for river training works at headworks for protection of water conductor Details
 
8Tender for selection of agency for providing facility management services for operation, maintenance, monitoring and management of SCADA infrastructure Details
 
8Tender for repairing of Two Nos. 50 MVA three phase 132/33 kV power transformer Details
 
8Tender for AMC for regular maintenance work, outage work and attending emergency breakdown work of 220 kV & 400 kV transmission lines Details
 
8Tender for construction of 33kV S/S Details
 
8Tender for construction of civil foundation for transformer bay, CTR, cooling bank and gravelling work Details
 
8Tender for transformer augmentation work of 132 kV transformer and 132/33 kV bay at 132 kV GSS Details
 
8Tender for construction of civil foundation for transformer bay, CTR, cooling bank for 160 MVA transfer Details
 
8Tender for augmentation of 160 MVA transformer at 220 kV GSS Details
 
8Tender for augmentation of 31.5 MVA transformer and associated civil work at 132 kV GSS Details
 
8Tender for transformer augmentation work of 132 kV transformer and 132/33 kV bay Details
 
8Tender for construction of 2 No. 132 kV bay at 132 kV GSS Details
 
8Tender for contract for the work of complete operation, maintenance and housekeeping of coal handling plant Details
 
8Tender for procurement of automatic measurement kit Details
 
8Tender for supply, design, erection, retrofitting and commissioning of 400 kV circuit breakers in switchyard Details
 
8Tender for annual maintenance contract (including preventive maintenance) of underground / overhead OFC links Details
 
8Tender for supply, erection and commissioning of special protection scheme for 400/220kV 315 MVA ICT-1 and 400/220kV, 315MVA ICT-2 at 400kV S/Stn Details
 
8Tender for supply and supervision of ETC of 72.5kV circuit breakers Details
 
8Tender for supply, I and C of oil filtration machine along with spare Details
 
8Tender for procurement of outlet turret complete with wearing plate, turret cone and top cover of 8.5 E9 coal mills Details
 
8Tender for procurement of electrical actuators and spare parts Details
 
8Tender for work contract for disposal of spent mineral wool through common hazardous waste-treatment, storage disposal facility Details
 
8Tender for work contract for overhauling of battery banks Details
 
8Tender for miscellaneous repair and civil maintenance work including sanitary works, water supply maintenance works Details
 
8Tender for roof treatment of different type Details
 
8Tender for biennial contract for civil maintenance works Details
 
8Tender for hiring of coil tubing and pumping services Details
 
8Tender for procurement of LT three phase channel cross arm Details
 
8Tender for procurement of LT three phase angle X arm Details
 
8Tender for procurement of LT GI pin Details
 
8Tender for procurement of 33kV 1 x 630sq mm UG XLPE aluminium power cable. Details
 
8Tender for procurement of cast basalt lined MS pipes Details
 
8Tender for procurement of 22 kV structure material for 9 Mtr PSC pole Details
 
8Tender for enhancement of existing 110/33kV power transformer capacity Details
 
8Tender for procurement of seal kit for the brake jack assembly of generators Details
 
8Tender for supply, installation & commissioning of new saftey guard for various auxiliaries Details
 
8Tender for erection of 66kV SS equipment, structures, control wiring, yard lighting Details
 
8Tender for work of misc pressure part related activity of boiler Details
 
8Tender for supply of various boiler tubes bends Details
 
8Tender for work of preventive maintenance, shutdown & emergency maintenance of IAC/SAC compressor, air washery fan/pump motor Details
 
8Tender for erection work of 66kV line Details
 
8Tender for supply, installation & commissioning of 5-star energy efficient inverter based split Details
 
8Tender for creation of 1 no. 33kV line bay to accommodate 33kV S/Stn Details
 
8Tender for ARC of coal mill and gravimetric feeders etc. Details
 
8Tender for ARC for cleaning, removal of garbage and ash from boiler and its auxiliaries Details
 
8Tender for providing additional 01 no. 100 MVA 220/132kV T/F Details
 
8Tender for procurement of special purpose welding electrodes Details
 
8Tender for survey, design, fabrication, supply, laying of foundation, erection and commissioning of 66 kV monopole line Details
 
8Tender for erection, testing & commissioning work of 66kV equipments Details
 
8Tender for removal/transportation of silt, mud and water algae from cooling tower, CW system and various Details
 
8Tender for repair and HP-HVOF coating of 01 No runner of 77 MW francis hydro-turbine Details
 
8Tender for procurement of different dia pipe and pipe fittings Details
 
8Tender for biennial maintenance contract for pest control and rodent control activities Details
 
8Tender for procurement of spares for complete coal nozzle assembly Details
 
8Tender for procurement of different types of spares of vibrating feeder and flats for APH and auxiliaries Details
 
8Tender for procurement of dry ashing spares for overhauling Details
 
8Tender for service contract for round the clock operation of in-plant rail movement control cabin Details
 
8Tender for procurement of 33/33 kV, UE, 3C x 185sqmm, XLPE cable Details
 
8Tender for Bi-annual rate contract for jointing and repairing of conveyor belt and drum rubber lagging Details
 
8Tender for procurement of throat plate assembly for coal mill Details
 
8Tender for procurement of BA crusher and jet pulsion pump Details
 
8Tender for stability testing of concrete and steel structures within the plant Details
 
8Tender for erection and commissioning of cast basalt MS pipe line Details
 
8Tender for supply, fabrication & erection of steel structure, erection of equipment?s, erection of earth mat, earth raisers, laying of control cable Details
 
8Tender for attending the breakdown maintenance works in ash slurry lines Details
 
8Tender for supply of various type of tarpaulin, transparent plastic sheet & miscellaneous materials for various Details
 
8Tender for erection and maintenance of HT/LT/TC work Details
 
8Design, engineering, supply, erection, testing, commissioning and comprehensive operation & maintenance for 5 (five) years for 1140 KWp rooftop solar PV power project Details
 
8Tender for erection and maintenance of HT/LT/TC work Details
 
8Tender for installation of double circuit AB cable Details
 
8Tender for replacement of existing of 11kV ACSR rabbit conductor with 11kV AAAC covered conductor Details
 
8Tender for replacement of existing of 11kV ACSR rabbit conductor Details
 
8Tender for replacement of existing of 33kV DOG conductor Details
 
8Tender for works related to leakage in forebay No. 01 and epoxy grouting in draft tube Details
 
8Tender for providing & fixing of chain link cage around distribution transformer Details
 
8Tender for various civil maintenance work for upkeepment of 132kV and 220kV S/Stn Details
 
8Tender for various civil maintenance work for upkeepment of RTC, 400 kV and 132kV S/Stn Details
 
8Tender for various civil maintenance work for upkeepment of 132 kV, 220 kV S/stn Details
 
8Tender for turnkey based contract for conversion of existing of 11kV HT line Details
 
8Design, engineering, supply, erection, testing, commissioning and comprehensive operation & maintenance for 5 (five) years for 1000 KWp rooftop solar PV power project Details
 
8Tender for turnkey based contract for conversion of existing of 11kV HT line Details
 
8Tender for turnkey based contract for conversion of existing of 11kV HT line network Details
 
8Tender for turnkey based contract for conversion of existing of 11kV HT line Details
 
8Tender for ARC work of erection of 66kV equipment, structures, control wiring, yard lighting etc. Details
 
8Tender for construction of double circuit cable trench Details
 
8Tender for work of providing services for loading, unloading, shifting and stacking of materials Details
 
8Tender for biennial work contract for maintenance of ash handling plant Details
 
8Tender for work of replacement / fitting of M.S. / GI grills, hand railing and misc. fabrication and other safety related works Details
 
8Tender for work of routine and preventive / breakdown maintenance activities & miscellaneous works Details
 
8Tender for supply of high pressure valves (IBR approved) for boiler Details
 
8Tender for supply of relay testing kit for different type testing generator relay panel, distance protection testing, 6.6kV/415V relay testing Details
 
8Tender for supply of various types of clamp for 220 kV switchyard Details
 
8Tender for purchase, erection, including foundation of conductor/cable measuring machine Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Flender opens new wind generator plant in Chennai Details
 
8Suzlon to launch Rs 10K crore wind power projects Details
 
8India’s Solar Generation Jumps 49% in July; Wind Output Rises 5% Details
 
8KELTRON Invites Bids For Solar Power And Street Light Projects Across North And East India Details
 
8India needs a grid revolution Details
 
8How ReNew Cuts Carbon Emissions & Grows Clean Power in India Details
 
83 Strong Undervalued Power Stocks in India to Watch in August 2026 Details
 
8India’s Power Capacity Push Strengthens Data Centre And Technology Investment Case: Piyush Goyal Details
 
8India Adds Record 3 GW Open-Access Solar in Q2 2026 Details
 
8Vikas Poddar Appointed Chief Financial Officer at Torrent Power Details
 
8Emerson software supports India’s largest battery energy storage system Details
 
8Talabira II & III coal mine records highest-ever production of 19.14 MT in FY 2025-26 Details
 
8Rongjie Energy Signs MOU with JSW Energy for 5 GWh Energy Storage Systems Details
 
8India’s Electrical and Electronics Sector Steps Up R&D Investment Details
 
8SECI Discovers Rs 5.99/kWh Tariff for 4-Hour Peak Power Details
 
8Could India Become a Perennial Market for Nepali Electricity Details
 
8Lineage Power Secures 100 MWh BESS Order from Kalpa Power Details
 
8Jefferies’ power play: 8 stocks with up to 43% upside; JSW Energy, Adani Energy top picks Details
 
8India Crosses 300 GW Clean Energy Capacity Milestone Details
 
8India AI Data Centres to Drive 191 TWh Power Demand, Creating Huge Renewable Energy Opportunity Details
 
8Tata Power Renewables Commissions 190.5 MW Solar FDRE Project in Rajasthan Details
 
8NLC India’s Talabira II & III Mine Achieves Record 19.14 MT Coal Production in FY 2025-26 Details
 
8NHPC Advances 2,000 MW Subansiri Lower Project as Rotor Assembly Begins for 250 MW Unit 7 Details
 
8Gujarat Industries Power Co. reports Rs 402.41 Crore profit, recommends Rs 4.10 dividend Details
 
8Rajasthan targets 125 GW renewable capacity by 2030, steps up push for fresh investment Details
 
8Bharat Heavy Electricals announces senior management change as Rs 50 crore contract gains attention Details
 
8India Proposes New Power Export Charge for Bangladesh Details
 
You can also click on Newsclips for more Details
81. UJVN's Rs 1,024 Crore Lakhwar Hydro EPC Tender Gives Bidders Just 32 Days for a 300 MW Package UJVN's electro-mechanical EPC notice for the 3x100 MW Lakhwar project sets a bid window running from 24 July to 25 August 2026 — unusually tight for a package of this scale and technical breadth. The notice doesn't specify EMD, PBG, reverse auction or qualification thresholds, leaving bidders to price against an incomplete risk picture. A tender-list webpage compounds the confusion by showing the pre-bid date as the closing date.

82. UJVN's Lakhwar Hydro Tender Extends by a Week as a 15% Security Premium Locks In for Manufacturer-Backed Bidders Corrigendum No. 1 pushes UJVN's Rs 1,024.45 crore Lakhwar EPC deadline from 25 August to 1 September 2026, giving bidders more time to assemble OEM authorisations and financial evidence. Beneath the schedule relief sits a steeper security structure: performance security rises from 10% to 15% where qualification relies on manufacturer credentials, on top of a Rs 20.50 crore EMD and a 270-day bid-validity clock.

83. UJVN's Tiuni Plasu Hydro Tender Rewrites Its Own Rules Across Six Addenda and 181 Days UJVN's Rs 259.60 crore EPC package for the 2x36 MW Tiuni Plasu HEP has seen its bid deadline move from 12 March to 9 September 2026 while addenda deleted contract-value experience thresholds, doubled the permitted OEM count from one to two, and quietly removed dedicated vibration and partial-discharge monitoring even as guaranteed output rose. The qualification bar simultaneously shifted from project pedigree to a steep Rs 260 crore turnover test for manufacturer-backed bidders.

84. UPPCL's Undefined GeM Bid Demands Rs 148 Crore Turnover for 13 Mystery Units UPPCL's GeM tender for the 132 kV Martinpurwa substation names a Rs 148.20 crore turnover threshold and a 180-day bid-validity lock, but never discloses what the 13 procured units actually are — no ratings, technical scope, EMD, PBG or delivery terms appear anywhere in the record. Bidders are being asked to commit capital and pricing certainty against a near-total information vacuum.

85. RVPN's Ajmer GIS Tender Turns a 15%-Below-Estimate Bid Into an Automatic Security Penalty This companion filing on RVPN's Hathi Bhata substation tender details how ITB Clause 32.1 charges additional security equal to 50% of the shortfall the moment a bid drops more than 15% below the Rs 143.63 crore estimate — while a parallel 15% floor on erection and civil pricing blocks the opposite strategy of front-loading supply value. Railway-block charges beyond two hours also shift onto the contractor, adding a live-line execution risk to an already interface-heavy GIS-and-cable package.

86. RVPN's Jaipur GIS Tender Shows a Rs 50 Lakh Gap Between Its Own Estimate and the Portal Figure RVPN's Shiv Enclave substation package lists Rs 83.38 crore in the bid document against Rs 83.88 crore on the state procurement portal — a discrepancy that needs resolving before price evaluation can proceed cleanly. Layered on top is a 15% anti-skew pricing floor, loss-capitalised cable and transformer evaluation, and a threshold-triggered additional security mechanism nearly identical to RVPN's sister tenders.

87. OPTCL's Kalahandi Transmission Tender Can't Decide If Completion Takes 18 or 24 Months OPTCL's Rs 104.02 crore Padepadar-Mukhiguda package states "18 months" numerically in one clause while spelling out "twenty four" months in words in the very same provision, with a separate clause independently confirming 24 months. The document also mislabels the interconnected substation's voltage class and leaves PBG, LD and bid-validity terms undisclosed — turning basic schedule interpretation into a pre-bid clarification priority.

88. JdVVNL's Jaisalmer RDSS Tender Makes GIS Data Entry Part of Physical Completion TNTW-795's Rs 120.42 crore turnkey package requires contractors to geotag every new or upgraded asset on JdVVNL's platform "without additional payment" as a condition of payment release, on top of layered security for abnormally low or supply-heavy bids. A portal-versus-SBD mismatch over bid-opening time — 11 am against 5 pm — adds a procedural wrinkle bidders can't safely ignore.

89. JdVVNL's Churu RDSS Tender Shrinks Its Effective Bidding Window by Quietly Moving the Publication Date TNTW-798's Rs 133.13 crore package states an RFB release of 14 August 2026, but the procurement portal shows publication only on 20 August — cutting roughly six days from the nominal bidding period. Three different technical-opening times appear across the tender set (11 am, 3 pm, 5 pm), while individual BOQ quantities can swing by plus or minus 50% after award.

810. MSEDCL's Rs 387 Crore SCADA-Ready Switchgear Tender Can't Agree on Its Own Breaker Rating MSEDCL's 3,599-unit ring-main-unit procurement describes a "400 ampere" vacuum circuit breaker in its headline section while the detailed specifications repeatedly call for 200 Amps — a conflict that directly affects fault-duty design, CT coordination and price. Type-test validity windows (5 years vs 10 years) and turnover thresholds (30% vs 60%) diverge just as sharply between the two document layers.

811. JdVVNL's Bikaner RDSS Tender May Have Double-Counted Feeders From a Neighbouring Package TNTW-796's Rs 120.01 crore package lists feeder-bifurcation entries under SDGH and Nokha even though those locations are separately assigned to sister tender TNTW-797 — a package-boundary ambiguity that could distort quantity pricing and survey planning. A descending-value, multi-package bid-capacity mechanism across eight concurrent RDSS tenders also means winning one package can block a bidder's access to financial opening on others.

812. OPTCL's Puri Underground Cable Tender Can't Settle Whether It's a One-Stage or Two-Stage Bid OPTCL's Rs 121.99 crore Samagara-Samuka 132kV cable-and-bay package calls itself a "single stage two part system" in the IFB while the procurement portal labels it "Two Stages" — a live classification conflict alongside a document-availability window that moved five days without any identified corrigendum. Route length, jointing method, protection integration and completion period are all left undefined at notice stage.

813. RPCL's Rs 188.80 Crore Yeramarus Coal Tender Swaps a Declared Grade for a Destination-Tested GCV Benchmark An addendum replaces "G8 grade" with "GCV 5050 Kcal/Kg (ARB)" across RPCL's domestic coal-supply pricing schedule — making unloading-end calorific measurement, not mine-side grade declaration, the operative commercial benchmark. The mechanism ignores any GCV surplus above 5050 while penalising shortfall, and a Rs 377.60 crore turnover threshold keeps the bidder pool narrow.

814. NTPC's Mouda Ash-Evacuation Tender Lets the Utility Cut Contracted Volume to Zero NTPC's Rs 83.17 crore pond-ash tender for Nagpur permits total contract variation from minus 100% to plus 20%, meaning a contractor can mobilize a full fleet within 15 days and still see the entire order disappear without compensation. A mandatory 50:50 split between two vendors and a 10%-below-estimate security trigger complete a tightly engineered risk-transfer package.

815. KPCL's Bellary Coal Tender Corrects a Grade-Mismatch Flaw But Halves the Supplier's Challenge Window KPCL's addendum aligns its Bellary coal price schedule with the same GCV 5050 Kcal/Kg (ARB) benchmark used at Yeramarus, closing a gap between declared grade and destination-tested acceptance. In the same breath, the referee-sample objection period shrinks from 14 days to seven, and post-award mine substitution is permitted only at a rate capped at the original quote — leaving suppliers with logistics flexibility but no corresponding price protection.

816. NTPC's Telangana Stage-II BOP Tender Adds a Full Flue-Gas Duct Scope Mid-Bid and Bills Consortiums an Extra 2% NTPC's international competitive package for Telangana Stage-II (3x800 MW) saw two deadline extensions totalling 40 days while Technical Amendment No. 02 converted "Nil" placeholders into a complete flue-gas ducting scope from the ID fan outlet to the chimney. Consortium bidders now face a dedicated 2% system-integration security on top of the standard 10% performance guarantee, aimed squarely at interface failure between the newly expanded balance-of-plant scope and the steam-generator package.

817. NTPC REL's 300 MW Nokhra Solar Tender Absorbs 60 Days and 12 Amendment Instruments Before Bid Close NTPC Renewable Energy's Nokhra solar EPC package saw its deadline move from 22 June to 21 August 2026 while accumulating seven corrigenda and five addenda — a volume of post-issue intervention suggesting the technical baseline was still being finalised well after the tender's original launch. A Rs 20 crore EMD locks in serious bidders even as completion schedule, LD structure and grid-interface boundaries remain undisclosed.

818. JPDCL's Udhampur-Chenani Tender Is Titled a "DPR" But Its BOQ Demands a Full 67 km Turnkey Line JPDCL's Rs 538.15 lakh notice calls for a "DPR for laying of 33 kV alternate line," yet the underlying BOQ requires 440 poles, 67 km of ACSR conductor and complete survey-to-energisation delivery — a title-versus-scope mismatch serious enough to distort how bidders price the job. An undisclosed formula lets JPDCL demand extra security from any bid 15% or more below its Rs 538.15 lakh estimate, with no stated ceiling.

819. OPTCL's Balasore-Chandipur Cable Tender Repeats the Same Portal-vs-Notice Date Conflict Seen Elsewhere OPTCL's Rs 147.97 crore underground 132kV package between Balasore and Chandipur shows a five-day gap between its notice's stated document-availability start and the portal's actual opening, while "single stage two part" and "Two Stages" again appear as conflicting descriptions of the same bidding structure. Route length, jointing design, outage coordination and completion period remain undefined at notice stage, just as in OPTCL's other underground-cable tenders.

820. OPTCL's Narendrapur-Chhatrapur Cable Tender Leaves Just One Hour Between Bid Closing and Opening This Rs 102.39 crore underground 132kV package carries the same notice-versus-portal date mismatch as OPTCL's other cable tenders, but adds a tighter operational squeeze: bid closing at 14:00 and techno-commercial opening at 15:00 on the same day, leaving virtually no buffer to resolve last-minute submission issues. Two live-substation bay extensions again sit inside the turnkey scope without a disclosed interface matrix.

821. OPTCL's 400 kV HTLS Reconductoring Tender Bundles Line Upgrade With Substation Bus Work Under One EPC OPTCL's Rs 301.22 crore Meramundali-Mendhasal package requires replacing twin AAAC Moose conductors with High Temperature Low Sag conductors while simultaneously upgrading equipment and bus systems at both substation ends — concentrating tower-adequacy, thermal-clearance and terminal-compatibility risk in a single contractor. The tender's document-download window closes just 15 minutes before bid submission, and the same one-stage/two-stage labelling conflict from OPTCL's other packages reappears.

822. NTPC's North Karanpura Ash-Water Tender Fixes a Pipeline's Minimum Length But Not Its Maximum NTPC's AWRS package for the 3x660 MW plant instructs bidders to price "3.5 km or actual, whichever is maximum" for the return-water pipeline — locking in a pricing floor while leaving the upper bound entirely open pending detailed engineering. A late-added requirement to bury 11 kV lines wherever they cross higher-voltage transmission corridors surfaced only after bidder questioning, adding an unpriced electrical-scope change deep into the bidding cycle.

823. NTPC Mining's Chatti Bariatu Coal-Handling Award Closes 16.6% Below Its Nearest Rival BTL EPC Limited won NTPC Mining's Rs 200.31 crore coal-handling contract at a price 16.6% below L2 and 26.1% below L3, after amendments doubled the magnetic-separator count, raised pipe-conveyor clearance from 3 to 5.5 metres, and shifted fire, dust-suppression and auxiliary water sourcing from existing infrastructure onto contractor-developed borewells. The wide L1-L2 gap raises the question of whether the winning bid fully priced in the expanded utility and interface risk transferred through those late technical changes.

Details
 For reference purposes the website carries here the following tenders:
 8Tender for service contract for framework agreement for assistance in miscellaneous work Details
 8Tender for erection testing commissioning trial operation and handing over of electrostatic precipitator of unit 7 at 1x800 MW Details
 8Tender for major overhaul of turbine and generator Details
 8Tender for supply of 25000 sets of 30KN strain disc hardware (metal parts for rabbit and weasel conductor) Details
 8Tender for supply of 500 sets of 22kV AB switch with PT insulator Details
 8Tender for procurement of various electrical materials for electrical maintenance work Details
 8Tender for replacement of 33 kV GIS C.T. at 132 kV S/S Details
 8Tender for civil works for construction of 01 No. 132 kV line Details
 8Tender for civil works related to increasing capacity 2x160 1x100 MVA to 3x160 MVA at 220 kV sub station Details
 8Tender for civil works related to increasing capacity 2x40 1x63 MVA to 3x63 MVA 1 No 132 KV bus couplar bay Details
 8Tender for construction of 132kV main bus bar extension throught XLPE cable, 132kV switchyard Details
 8Tender for upgradation of the existing SAS based 132kV GIS substation to 220kV GIS substation Details
 8Tender for construction of 220 kV DC with Zebra equivalent HTLS conductor line Details
 8Tender for construction of UG 132 kV TSS line Details
 8Tender for construction of 132 kV DC line Details
 8Tender for connecting and extending the pipeline Details
 8Tender for procurement of caustic soda lye Details
 8Tender for complete residual life assessment of boiler Details
 8Tender for site enabling works package Details
 8Tender for supply, installation and commissioning of FOTE system Details
 8Tender for assistance in the execution of various works Details
 8Tender for repair and maintenance of damaged portion of bypass Details
 8Tender for annual maintenance contract (AMC) of external firewall installed Details
 8Tender for procurement of tools and plants for transmission line Details
 8Tender for diversion of 400kV D/C TL line Details
 8Tender for construction of coal lab Details
 8Tender for repair of 40/50 MVA 132/33kV power transformer Details
 8Tender for procurement of 400kV CVT Details
 8Design, supply, erection and commissioning of mono rail for lifting arrangement of drainage and dewatering system Details
 8Tender for annual maintenance of generating units of 31.4 MW turbines and generators assemblies Details
 8Tender for annual civil maintenance and repair works of barrage Details
 8Tender for purchase of 45ton gantry crane with lifting beam Details
 8Tender for supply, erection and commissioning of battery bank and battery charger at substations Details
 8Tender for repair of damage drains to safeguard machinery including damaged brest walls Details
 8Tender for erection/ construction of tin shed for the DG set and storage of spare transformers lying Details
 8Tender for construction of new 110kV bay for the erection of 25MVAr capacitor bank at 110kV substation Details
 8Tender for laying of HT UG cable Details
 8Tender for empanelment of agencies for new 33/11 kV substation, additional /augmentation of PTR at existing 33/11 kV S/s, HT lines, LT lines Details
 8Tender for procurement of lubricating oil pump installed in 8.5 E9 ABL make coal mills Details
 8Tender for procurement of electrical actuators and spare parts Details
 8Tender for procurement of collecting electrode of ESP Details
 8Tender for excavation, loading and transportation of pond ash Details
 8Tender for complete rewiring of A, B and C type Details
 8Tender for restructuring of old 400kV system of PH 3, up gradation existing SCADA system of 400 kV system Details
 8Tender for procurement of bibby resilience coupling and spare grid spring for PA, SA fan and coal mill gear box Details
 8Tender for proposal for procurement of complete HP valves and various recommended spares of valves installed Details
 8Tender for procurement of lubricating oil pump installed in 8.5 E9 ABL make coal mills Details
 8Tender for work of soil investigation at ash pipeline Details
 8Tender for supply and on-site fabrication and installation of 03 sets of upper turbine cover relieving pipe along Details
 8Tender for routine repair maintenance and occasional breakdown maintenance of hydro mechanical and electrical equipments Details
 8Tender for procurement of bladders with seal kits for various accumulators installed Details
 8Tender for procurement of spare BTS 2000 relay used in bus transfer scheme of 11kV unit switch gear installed Details
 8Tender for procurement of triple screw pump assembly for coal mill lube oil system Details
 8Tender for in-situ drilling, tapping and plugging work on embedded draft tube for assembly of upper and lower loose flanges on draft tube of 250 MW francis turbine Details
 8Tender for procurement of different type of MCBs & MCCBs Details
 8Tender for operation & comprehensive maintenance of existing SBR based 0.4 MLD sewage treatment plant Details
 8Tender for procurement of capacitive voltage transformers (CVT) and potential transformer Details
 8Tender for procurement of lighting arrestor (LA) or surge arrestor (high class) for different Voltage level Details
 8Tender for procurement of 33 kV circuit breaker (CB) for different Details
 8Tender for construction of 33 kV s/s Details
 8Tender for new 33 by 11 kV sub-stations augmentation or addition capacity including associated line Details
 8Tender for supply of insulation resistance tester Details
 8Tender for earthing of power transformer at 33 kV S/S Details
 8Tender for construction of tubewell for power earthing and water supply arrangement Details
 8Tender for renovation of electric fitting and yard lights at various Details
 8Tender for construction of 33kV S/S Details
 8Tender for hiring, erection and dismantling of M.S. cup lock type scaffolding Details
 8Tender for requirement of sodium hexa meta phosphate Details
 8Tender for supply of spares for pumps at AHP Details
 8Tender for supply of LT shackle and metal parts Details
 8Tender for supply of LT single phase channel cross arm, LT three phase channel cross Details
 8Tender for supply of 11 kV single pole standalone structure material complete set Details
 8Tender for supply of LT MS 4 way pillar boxes Details
 8Tender for giving of LT/HT SC line Details
 8Tender for restoration of 132 kV GIS sub station and its associated transmission line Details
 8Tender for work of nano technology based acid and alkali resistant nano-modified anti corrosive coating on transmission tower Details
 8Tender for work of chemical washing of Disc/PLRI strings of various 400 kV Tr. lines Details
 8Tender for work of supply and installation of advance multi cable transit system Details
 8Tender for creation of 400/220 kV switchyard Details
 8Tender for establishment of 220/22 kV substation Details
 8Tender for work of removal, supply and application of spray thermal insulation on drive turbines Details
 8Tender for biennial rate contract for repairing, replacement, and maintenance of damaged, torn, and burnt NN fire resistant conveyor belts Details
 8Tender for ARC work of erection of 66kV equipment, structures, control wiring, yard lighting etc. Details
 8Tender for erection of equipment and structure, control wiring, yard Details
 8Design, supply, erection, testing & commissioning of conversion work of existing 132kV S/C line Details
 8Tender for stub strengthening of 220kV D/C line Details
 8Tender for supply of MS grill for walkways of boiler & coal mill Details
 8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes Details
 8Tender for supply of various ratings LT motor Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8India needs rapid battery storage expansion as renewable capacity rises Details
 
8India hits $0.068/kWh tariff in 4-hour peak renewable power tender Details
 
8Telangana accounts for 70 pc of major coal mine mishaps in India Details
 
8Prakash Industries secures environmental clearance for Bhaskarpara Coal Mine expansion Details
 
8India’s coal fleet must learn to flex or its solar boom will keep hitting a wall Details
 
8Govt weighs supply-profile tweaks to rescue stalled RE bids Details
 
8Chhattisgarh to emerge as leading State in Solar Energy: Chief Minister Sai Details
 
8India's Solar Cell Imports Hit $3 Billion, Sparking Industry Woes Details
 
8Acme Solar, PTC Industries in Focus After MarketSmith Report Details
 
8SaurEnergy Explains- What It Actually Takes to Power a Gigawatt Data Centre Details
 
8Floating solar: Can it be India’s next renewable energy success story Details
 
8Chhattisgarh CM Vishnu Deo Sai discusses solar boost at Samvad 2026 Details
 
8Nuclear energy could power India’s future Details
 
8Power sector at tipping point as SC takes up DERC plea today Details
 
8Rising FDRE, RTC volumes to drive electricity futures market growth Details
 
8Tariff, technology & FDI: India Inc flags key concerns in draft nuclear rules Details
 
8World Wisdom Forum : J&K’s youth power key to India’s development story: LG Details
 
8Tata Steel Ludhiana Secures India’s First BIS Certification For Octagonal Billets Details
 
8BERC panel proposes Tk 6.48 solar power tariff for MPPs Details
 
8The physical and financial losses in Nigeria’s power sector Details
 
8Mukul Agarwal and Madhusudan Kela back these 2 recently listed power microcaps Details
 
8Power Sector: Jefferies Bullish on Private Players, Picks Adani Energy and JSW Energy as Top Bets Details
 
8Insolation Green Energy Pvt Ltd receives 9 contracts of solar power projects from MSEDCL Details
 
8Govt weighs supply-profile tweaks to rescue stalled RE bids Details
 
8India Targets 'Electro State' Shift With 300 GW Milestone Details
 
8The Real Crisis Is Not Electricity, But Energy Details
 
8Hyundai Motor India Share: Nomura Maintains Buy, Sees 25% Upside on New Launch Pipeline Details
 
8Defence Minister Rajnath Singh sets sights on global shipbuilding: Can India become the next maritime power Details
 
You can also click on Newsclips for more Details
8The ERPC order records Bihar's firm entitlement in Farakka I&II at 0.000%, relinquished, and hands Punjab a 20.585% firm share it never previously held. The transfer runs 39 days, from midnight on 23 August, and moves central power from a state that stopped wanting it to the state with the window's worst evening shortfalls. Details
8The August investor presentation aggregates what no state discom tender shows alone: of 20,920 MW of thermal PPAs awarded under recent SHAKTI-linked state rounds, 13,945 MW went to Adani Power - including every megawatt awarded by Bihar, UP, Maharashtra and Assam. The same deck records FY26 EBITDA and profit lower than a year earlier, and a 42,050 MW target that rests on capacity not yet built. Details
8ICRA reaffirmed both Axis Wind Farms SPVs on the strength of their ultimate parent, not their counterparty. The rationales document a payment regime in which the better the wind year, the more free power Andhra Pradesh's discom receives - a dispute now before the AP High Court. Details
8The Q1 FY27 numbers show a company growing at 125% with its best-ever margin; the transcript shows a lead-acid battery plant at Bawal written down by Rs 143.6 crore after a fire, and a restart that waits on the insurer. The stop-gap, disclosed only in the call: rent someone else's operating battery plant, with a deal expected in about a month. Details
8The covering letter announces a routine subsidiary acquisition; Annexure A discloses that promoter Dr Faruk G. Patel personally holds 8.95% of the target being bought with the group's paper. The target, incorporated in November 2021, took its revenue from Rs 30.62 crore to Rs 213.98 crore in two years. Details
8NLDC's Sunday bulletin reports a 200 MW evening shortfall, confined to the Northern Region - the mildest reading of the three-day window. Every forward-looking instrument for Monday says the opposite: buy bids at twice the sell volume, a clearing price up 28% in a day, term-ahead trades at the Rs 10 cap, and the costliest fleet on the system scheduled hours in advance. Details
8The notified Sixth Amendment reduces what renewable open-access consumers pay for parking surplus power with the grid, from the Rs 1.50 a unit charged since February 2024. The two decisions that will be felt longest sit below the headline rate: a proviso that zeroes the charge for any discom that fails to file sworn data, and a Statement of Reasons that forecloses every refund claim for the past two and a half years. Details
8Seventeen GSECL solar projects built under Gujarat's 2019 land-subsidy scheme are feeding the grid with no tariff determined and no payment received, and the state generator now wants 95% of its claim provisionally. The Commission's answer was to put GUVNL, the buyer, on the stand: claimed tariffs exceed the Rs 1.50 a unit both parties once confirmed, capital costs run past the Rs 4 crore per MW the scheme assumed, and no independent prudence check was ever done. Details
UP's regulator clears a Rs 4,239.50 crore wires slate and repairs its 4,000 MW hydro tender

8UPERC approves 24 transmission schemes worth Rs 4,239.50 crore - and trims the YEIDA substation by the Rs 22 crore it was double-counted
8UPERC rewrites three clauses of UPPCL's 4,000 MW hydro tender - bidders lose the right to guess their own transmission cost
8Dhariwal's Rs 38.93 crore substitute-coal claim against Noida Power is admitted - Rs 11.38 crore of it still unpaid
8PVVNL asks UPERC to keep India's interstate blockchain power-trading pilot alive - hearing 27 August

Bihar's regulator writes two consumer checks into the smart prepaid rollout

8Chargeable service-cable replacement now needs a JE's signature - BERC closes the SOP it ordered in December
8Prepaid arrears in Bihar will be recovered over 12 to 24 months by slab, effective immediately

Two benches tip their hands while the cases stay open

8KSERC records that INKEL's stuck wind "merits priority" - and sends KSEB's chief engineers to the next hearing
8Tarini's 16-year-old small-hydro tariff case now runs on a Supreme Court clock - with an expert-appointment fight inside it

A connectivity swap approved, a supply code redrafted

8WBERC lets the Sprng group swap the grid connection behind CESC's 100 MW hybrid PPA - tariff and CUF untouched
8Karnataka proposes one supply code to replace six - with a doubled EV-charging mandate and outage counts printed on bills Details
A doubled top line meets its depreciation bill

8Insolation's revenue doubles to Rs 745 crore; profit falls 12% as the expansion's interest and depreciation land

Governance signals from the annexures

8One in four institutional votes opposed Harsh Goenka's commission at KEC's AGM - the resolution still passed with 90.43%
8IREDA removes its entire Projects-wing senior management layer in one board stroke - no successors named
8Refex Renewables' promoter block consolidates into one entity at 74.87% - a whisker under the ceiling

Distress, data centres and an IPO reprice the mid-market

8India Power Corporation's creditors meet today to re-publish the invitation for resolution bids
8A hyperscale Hyderabad data centre orders Rs 52.86 crore of cables from Diamond Power - its data-centre book passes Rs 575 crore
8Lumino Industries opens a Rs 700 crore IPO this week on a Rs 3,149.88 crore order book
8Vedanta Aluminium hands S&S Power's subsidiary its largest-ever order - "more than Rs 50 crore" is all the filing says Details
 1 2 3 >  Last ›

Showing 1–50 of 367 items