All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Jul 2026

It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8LPG
8Ammonia

8All tankers
8Bulk and Dry cargo

Click on Reports for more. Details
8IEX's day-ahead hit the ceiling at both peaks and the floor at noon on 23 July
8IEX green power cleared above grey on 23 July - a Rs 428 premium that flips the usual discount
8IEX's real-time market carried the whole country's spot power on 23 July - 190,887 MWh
8Contingency and intraday contracts pinned at the Rs 10,000 ceiling, bar the Western Region
8Green term-ahead was the only live green venue: DAC contracts cleared in the Rs 9,600–9,920 band all day
8PXIL's short-term segments sat dormant: its real-time and deviation markets both cleared nil on 23 July
8HPX real-time market drew bids but cleared nothing - a bids-only presence all week
8High-price day-ahead stayed dormant on both venues on 23 July
8The second exchange's green day-ahead stayed shut for a tenth straight day
8Exchange ancillary market cleared nil for a tenth day; reserves procured through regulated SCUC instead
8Intraday segment took buy bids but formed no price - 550 MWh of demand met no sellers
8WBSEDCL goes to reverse auction for 600 MW of September night-block power across three exchanges
8PXIL takes its trading portal down for two and a half hours in the early hours of 24 July Details
8India met a 231 GW peak on 23 July without dropping a megawatt anywhere
8The grid ran too high for seven hours of 23 July - too much power, not too little
8Operators switched off about 95,000 MWh of generation on 23 July - the grid had too much
8The West and East carried the country on 23 July while the North leaned on 418 MU of imports
8Surplus solar and light load pushed the Southern grid over-voltage for most of 23 July
8The North-East to Tripura corridor sat over its transfer limit for 56% of 22 July
8India leaned on Bhutan and Nepal for a net 24.8 MU import on 23 July
8Uttar Pradesh ran unscheduled load-shedding on 23 July though the region logged zero shortage
8Grid-India switched on a new 765 kV line into over-voltage Rajasthan on 23 July
8Karnataka and Tamil Nadu hit repeated ICT-overload emergencies on 23 July; Telangana ran high on voltage
8Monsoon floods knocked out much of Gujarat's EHV grid on 23 July, yet the West still met 60 GW
8A zero-shortage grid split the exchange price on 23 July
8The transmission committee cleared about Rs 15,000 crore of lines
8The Western grid's protection layer frayed across 54 spring disturbances Details
8Monsoon floods force mass EHV line openings across Gujarat's Western grid on 23 July
8About 50.6 GW sat out of grid on 22 July - forced outages more than double planned maintenance
8The West kept nearly 20 GW of generation switched off on 23 July and never missed it
8The South kept 11 GW out on 23 July, led by a badly degraded Neyveli fleet
8NTPC's Barh-2 and DVC's RTPS-2 lead 3,888 MW held out of the Eastern grid
8A cluster of UP and Punjab units tripped overnight on 22 July, Jawaharpur's twin 660 MW loss still out
8Two 400 kV double-circuits stay collapsed in Karnataka 60–70 days on
8NHPC's Teesta-III - all 1,200 MW - has now been forced out 21 months
8Some 33,884 MW has sat out of grid beyond a fortnight, much of it gas idled on costly fuel
8A further 6,105 MW has been stranded beyond a year
8Monsoon tube leaks run through NTPC's coal fleet - KSTPS-4 out fresh, Sasan-4 back on the same fault Details
8Coal-critical count eases to 27 plants on 22 July, but Damodaram Sanjeevaiah and Sasan still sit at 3%
8India's gas-fired fleet prints zero generation on 22 July as costly RLNG stays out of merit
8Coal India has tied up 617.7 million tonnes of long-term coal supply for power plants
8Coal-mining committee weighs 12 cases on 4-5 August - NCL's Jayant seeks a 30-to-38-MTPA jump
8Three more coal-mine cases reach the appraisal committee on 27 July Details
8Telangana's Krishna storage has crashed to 128 MU from 1,742 MU a year ago
8Four of Odisha's seven OHPC power houses generated nothing on 23 July as forced outages spread
8India's big reservoirs stay well short of full mid-monsoon, Bhakra 29 metres below its brim
8Sikkim's 1,200 MW Teesta-III stays dark into a 22nd month, keeping Eastern hydro minimal
8All 25 workers trapped at NHPC's Teesta-VI tunnel confirmed dead
8India plans 100 GW of pumped storage by 2035-36, with about 5 GW now seeking clearance Details
8Power-sector cases pile up - 1,193 pending at CERC, 2,911 at APTEL as on 30 June
8NGEL's Section 142 action against SECI reserved for order after both sides close arguments
8Jhajjar's claim that mandated biomass co-firing is a Change-in-Law cost is reserved for order
8GUVNL v Tata Power admitted - a 39-day 2024 force-majeure claim that could claw back capacity charges
8SJVN Green's GST change-in-law claim on its 1,000 MW Bikaner solar project admitted
8NRSS XXXVI keeps its shield: CERC continues interim protection against UPPCL's Rs 8.33 crore LD
8POWERGRID admitted to fold 28 transmission SPVs into two survivors under Section 17
8GUVNL v Adani adjourned sine die as fresh 1 June 2026 SPPAs await separate approval
8Bihar discoms' pilot-power compensation claims against PTC India adjourned Details
8GERC ties Essar's diverted-power claim to a set-off, replies due before the 701 MU crux
8GERC races a five-week clock to recompute Essar's delayed-payment charges on compound interest
8GERC adjourns Tarini's 16-year-old small-hydro tariff again as a fresh Supreme Court CUF order stays unuploaded
8UERC clears UPCL's Rs 8.16 crore Khatima 33 kV works but rebukes it for bidding before approval
8MERC throws out a Rs 5.82 crore tower-compensation claim as premature
8Uttarakhand Ombudsman bars UPCL from cutting a paying consumer's line at a third party's behest
8PSERC admits PSPCL's rooftop-solar rule change, sets a 12 August public hearing on Regulation 11.13
8KSERC lists a 6 August hearing on KSEB's per-kVA/kW charges, opening a consumer-facing tariff fight
8UPERC puts a full state grid code out for comment, hearing set for 1 September
8AVVNL stops buying 5 kVA single-phase transformers, upsizing to 10 kVA to pre-empt load growth
8MePDCL orders every stand-alone prepaid meter swapped for ADB-funded smart meters
8Power Ministry declines a uniform transmission RoW compensation policy, keeps no data on affected farmers
8Government lets four China-linked equipment makers back into power bids for two years
8Power Ministry reaffirms rural-electrification programmes closed in 2022 at 18,374 villages
8Power Ministry maps a Rs 24,819 crore Khavda–Nagpur HVDC for Gadchiroli-Chimur Details
8Wind-led renewables feed the grid 980 MU on 23 July; seven ISGS stations sit dark
8NTPC Green declares its first 64.76 MW at the 225 MW Khavda solar block commercial from 24 July
8SECI's rooftop Tranche-IX clears at Rs 2.94/kWh as Renergo sweeps nine of 14 RESCO projects
8MNRE sets the Bharat RE Summit for 2–5 November
8Grid-India confirmed as registry and meta-registry for India's carbon market under CCTS
8Haryana drafts a compressed-biogas policy targeting 43,000 TPD by 2047 on a Rs 2 crore/TPD subsidy
8EAC-PM's "Duck and Camel" paper puts the summer evening ramp near 74 GW and daily solar spill at ~24 GWh
8India's thermal build pipeline swells past ~13 GW at appraisal even as this year's additions stall
8Renewable installed capacity has overtaken coal: 236.5 GW against 224.2 GW
8India's storage pipeline hardens: a 100 GW pumped-hydro roadmap Details
8PFC clears the way to borrow up to Rs 9 lakh crore for the power build-out
8POWERGRID lifts its FY27 bond ceiling by Rs 5,000 crore to Rs 35,000 crore
8POWERGRID names R.M. Bansal and Chandra Wadhwa its joint cost auditors for FY27
8JSW Energy's Rs 4,000 crore QIP sits almost wholly unspent a quarter after the raise
8IREDA floats an RFP to raise a USD 100 million unsecured green ECB term loan
8IEX Q1 profit rises to Rs 135 crore as its gas-exchange arm IGX files to list
8ICICI Direct cuts TARIL to Reduce even as its order book hits a record Rs 6,630 crore
8NTPC is running behind its own plan this year, and the North is the drag
8Orient Electric rotates out S.R. Batliboi for Price Waterhouse as statutory auditor
8Patel Engineering books Rs 1.25 crore ex-gratia as all 25 Teesta-VI tunnel workers confirmed dead
8Ind-Ra upgrades JSW Energy Utkal's unsupported rating to AA-, affirms AA(CE)
8ICRA strips APRAAVA of its AAA, cutting it to AA+ after the Jhajjar thermal sale
8CARE keeps Lanco Vidarbha at 'D' with Rs 9,614 crore of bank facilities in default Details
8WRPC's weekly deviation account settles net Rs 11.53 crore in the Western pool's favour
8The Western grid saw 339 emergency ancillary dispatches in a week, nearly all backing plant down
8WRPC's 16th ISTS meeting adjudicates 13 disputed May trippings
8WRPC's ISTS slippage register runs across 8 developers - Khavda ICTs slip again, Sterlite's Goa line stuck since 2023
8IndiGrid's JTCL seeks Change-in-Law and Rs 18 crore for de-inducting a 765 kV line
8WRPC's protection committee tables 54 spring disturbances before its 29 July sitting
8The protection committee's oldest action items keep rolling - NTPC Lara's oscillation study open since the 163rd meeting
8CEA's transmission committee clears about Rs 15,000 crore of inter-state lines
8CEA issues Corrigendum-I to the 42nd NCT minutes, clarifying the Sasaram substation scope
8POWERGRID's Director (Projects) post stays vacant a fourth month as the CMD's charge is extended again
8President appoints an MNRE Joint Secretary to IREDA's board
8Coal India moves an HR manager from Eastern to Western Coalfields
8Government tells Parliament an integrated Ministry of Energy is "beyond the purview"
8PSPCL publishes tentative Chief Engineer seniority lists for Civil and Electrical cadres
8PSPCL calls disciplinary-case reports on about 142 engineers for a promotion-vetting drive
8PSPCL reaffirms that AEE promotees who have not cleared the DAE get no promotional increment
8PSPCL dismisses an East Zone clerk absent from duty since January 2020
8PSPCL posts a JE from leave to its NRSE & Thermal Design wing against a vacant post
8PSPCL deletes 8 of 10 clerk-trainees from an induction batch
8PSPCL deletes two entries from a 2025 regulation circular on a Board decision Details
8The answer to the evening-ramp problem is finally taking shape as a pipeline. The Central Electricity Authority's roadmap targets 100 GW of pumped storage by 2035-36, two viability-gap battery schemes together back 43.8 GWh with Rs 168 crore already disbursed, and the environment committee takes up about 5 GW of new pumped-hydro projects next week - Adani, ReNew, Jindal and Torrent among the developers. Details
8The Western region's protection papers, now backed by their full March-to-May annexure, catalogue 54 detailed grid disturbances and 48 inter-state line trips flagged for breaching reporting and protection standards - with disturbance recorders un-synchronised or never shared. The biggest were a 1,704 MW loss at JSW Mahanadi and 1,153 MW at Adani's Raipur; the most telling are the small ones, where a thrown wire or a stolen conductor blacks out a whole wind farm. Details
8Two 1,320 MW coal plants tell opposite credit stories on the same day. ICRA cut Aprava Energy - the former CLP India - from AAA to AA+ after it agreed to sell its Jhajjar thermal station, while CARE flagged Lanco Vidarbha Thermal's entire Rs 9,614 crore of bank facilities in default and marked the borrower non-cooperating. Ownership and cash flow, not the asset, decide which way a thermal plant's paper goes. Details
8The Indian Energy Exchange reported a June-quarter consolidated net profit of about Rs 135 crore, up 12%, on record traded volume of 37.5 billion units, and moved to spin its gas arm into the market: subsidiary Indian Gas Exchange has filed to list, and a SEBI order requires IEX to cut its stake from 47.3% to 25%. A new Indian Coal Exchange rounds out a push to trade every fuel, not just power. Details
8The disaster at NHPC's under-construction Teesta-VI hydro project in Sikkim is now final: all 25 workers trapped when the Samardung head-race tunnel gave way have been confirmed dead, the contractor Patel Engineering told the exchanges, and the company has announced ex-gratia of Rs 5 lakh to each family, about Rs 1.25 crore in all. It is the deadliest single incident on an Indian power project in years. Details
8The National Committee on Transmission cleared a slate of inter-state schemes worth roughly Rs 15,000 crore at its 42nd meeting - a Rs 4,378 crore Northern-grid STATCOM package, a Rs 3,673 crore Kadapa system and more - even as the Northern region set a 94 GW peak and reported transformers overloading at Bhiwani, Moga and Jhatikara. The build is chasing a grid that is already running hot. Details
8Grid-India's June operational report records installed renewable capacity at about 236.5 GW against coal's 224.2 GW - the crossover the sector has been approaching for two years is now on the books. Counting large hydro and nuclear, non-fossil sources make up 54.2% of a 548.86 GW national fleet, though coal still did roughly seven in ten units of actual generation. Details
8Expert appraisal committees are lining up more than 13 GW of fresh coal and lignite capacity - Vedanta's 5,600 MW, Jindal's 2,400 MW, a DVC–Coal India 1,600 MW joint venture and more - for environmental clearance over the next fortnight, on top of Torrent's Rs 22,915 crore ultra-supercritical proposal cleared for terms of reference this month. It is the forward book behind the country's stalled coal additions: the plants being started now for the demand of the 2030s. Details
8The Prime Minister's Economic Advisory Council has put hard figures behind the price split that has run all month: as rooftop and utility solar flood the middle of the day, the grid's evening pick-up - the "duck" turning into a steeper "camel" curve - now needs about 74 GW of ramp in a few hours, double what it was, while about 24 GWh of solar is curtailed daily for want of anywhere to put it. The paper's fix is storage and a market that pays for flexibility, not more megawatts. Details
8The IEX day-ahead market cleared about 150,767 MWh on 23 July at an average Rs 5,375 a MWh, but the average again hides a violently two-shape day: the price held at or near the Rs 10,000 ceiling through the overnight and evening windows and fell towards the floor in the solar-flooded early afternoon. The grid behind it was comfortable to surplus - a 231,045 MW peak met with essentially nil shortage - and the other two exchanges cleared nothing, leaving IEX to carry the entire national market. Details
8Heavy rain across South Gujarat, Kutch and Dadra & Nagar Haveli forced a run of extra-high-voltage lines out of service on 23 July, collapsed a 220 kV tower on the Pirana–Barjedi circuit and tripped both 765 kV buses at Vadodara on breaker-failure protection. The Western grid still met a 60,061 MW peak with no shortage and exported about 303 MU north and east - the weather hit the wires, not the supply. Details
 For reference purposes the website carries here the following tenders:
 8Tender for supply & installation of power supply unit for battery charger Details
 8Tender for procurement of 5000sets 11kV 30KN strain disc hardware fittings for rabbit and weasel conductors Details
 8Tender for construction of balance compound wall at 230 kV feeder Details
 8Tender for work contract for laying of 33kV, 1x630 sq.mm XLPE UG cable Details
 8Tender for providing additional cable duct for erection of 230 kV bus bar protection panel Details
 8Tender for construction of fallen compound wall including fixing of MS "Y" angle with barbed wire Details
 8Tender for erection, testing, commissioning, trial operation & handing over of boiler and its auxiliaries Details
 8Tender for construction of protection wall at tower Details
 8Tender for supply of various sizes of hexagonal nuts and bolts, step bolts, spring washers Details
 8Tender for supply cum installation of new kiosk-based control and relay panel Details
 8Tender for supply of 36 kV PT accuracy 0.2S accuracy classes at various substations Details
 8Tender for regular operation and maintenance of electrical system Details
 8Tender for development, design and setup of 10 MLD water treatment plant Details
 8Tender for construction of monsoon flood damaged compound wall with retaining wall, yard metal, yard Details
 8Design, fabrication, supply, installation, testing commissioning of solar water heater at various Details
 8Design, fabrication, supply, installation, testing commissioning of 30 nos solar based LED street light systems Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 20 kW with net meter Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 25 kW with net meter Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 20 kW with net meter Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 20 kW Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 30 kW Details
 8Design, fabrication, supply, installation, testing commissioning of on-grid solar rooftop project of 30 kW with net meter Details
 8Tender for supply, installation, testing & commissioning of conversion of 66 kV Kheralu-Khanpur line Details
 8Tender for supply, installation, testing & commissioning of conversion of 66 kV line Details
 8Tender for work for hiring of BD155 or its equivalent capacity bull dozers for coal dozing/feeding & other works Details
 8Tender for supply of various sizes diaphragm valves Details
 8Tender for work contract for duct revival between ECO to air pre heater A and B flue gas duct Details
 8Tender for fabrication of general items seal oil tank bottom plate dome wall etc Details
 8Tender for renovation of room for setting up of laboratory for testing of biomass pellets Details
 8Tender for refurbishment / reconditioning works of ID Fan impellers Details
 8Tender for procurement of power quality meters Details
 8Tender for procurement of 1200 mm and 1500 mm wide conveyor belt. Details
 8Tender for repair and maintenance of damaged doors/windows of aluminium and allied works including Details
 8Tender for providing and fixing new fencing to separate the switchyard Details
 8Tender for transmission line Package- TL01 for design, engineering and construction of dedicated 400kV D/C transmission line with twin moose ACSR conductor Details
 8Tender for supply of 33kV 1250A outdoor vacuum circuit breaker Details
 8Tender for work for repairing of raincuts for bund protection Details
 8Tender for const. of 33 kV S/S Details
 8Tender for implementation of feeder data monitoring system Details
 8Tender for construction of store shed at 33 kV S/S Details
 8Tender for maintenance works of EHV equipment at various 400kV substation Details
 8Tender for requirement of spares of CW and ACW pumps installed Details
 8Tender for construction of control room, chain link mesh fencing, yard leveling and metaling, drilling tubewell and other civil work for new 33/11 kV S/s Details
 8Tender for construction of control room, chain link mesh fencing, yard leveling and metaling, drilling tubewell and other civil work Details
 8Tender for construction of control room, chain link mesh fencing, yard leveling and metaling, drilling tubewell and other civil work for new 33/11 kV S/s Details
 8Tender for construction of control room, chain link mesh fencing, yard leveling and metaling, drilling Details
 8Tender for appointment of an agency for development and operation of transformers, cables and conductors testing lab Details
 8Tender for procurement of filter elements of FRF regenerative system Details
 8Tender for annual work contract of loading of condition ash from the delivery points of ash silos Details
 8Tender for work contract for routine/preventive/breakdown maintenance of control and instrumentation equipment and its associated system Details
 8Tender for wheel wise load measurement Up gradation of existing 2 Nos. rail electronic in motion weigh bridge Details
 8Tender for work contract for routine maintenance of ESP Details
 8Tender for construction of 33/11 kV PSS Kandra Details
 8Tender for construction of 33/11 kV PSS Details
 8Tender for removal of the existing 200 MVA single phase transformer bank from 220kV substation Details
 8Tender for standardization of transformer station Details
 8Tender for shifting of electrical utilities Details
 8Design, manufacture, testing, supply and delivery of ACSR moose Details
 8Tender for work for dismantling of removal of old damaged corrugated sheet and fixing of corrugated 0.5 mm (roofing / cladding) Details
 8Tender for supply of various insulation materials for boiler Details
 8Tender for supply of various consumables, measuring instruments, Tools tackles, CPVC and fasteners items Details
 8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details
 8Tender for various maintenance works of wagon tippler Details
 8Tender for procurement of misc. electrical items Details
 8Tender for rate contract for one year for transportation carriage of materials Details
 8Tender for assistance in lifting/shifting and replacement of different HL/LT motors, replacement of bearing/coupling etc Details
 8Tender for biennial contract for various civil jobs Details
 8Tender for load testing and certification of 04 Nos. EOT cranes Details
 8Tender for manufacture, supply and ex-works delivery of 8m and 9m long PCC poles Details
 8Tender for procurement of 12 kV VCB switchgear panel set Details
 8Tender for construction of 11kV line Details
 8Tender for replacement/extra Ckt. of old/decrepit AB cable Details
 8Tender for supply of materials 11 kV line Details
 8Tender for construction of 11kV line Details
 8Tender for maintenance/ operation of 33/11 kV sub-stations, associated HT/LT lines Details
 8Tender for maintenance/ operation of 33/11 kV sub-stations Details
 8Tender for construction of other misc. civil works Details
 8Tender for maintenance/ operation of 33/11 kV sub-stations, associated HT/LT lines Details
 8Tender for supply of T&P equipment for mainteance of 33kV substations Details
 8Tender for work of annual maintenance contract for work of repair, servicing, overhauling and maintenance of window/split air conditioner Details
 8Tender for supply of spares and complete mechanism overhauling of 220kV & 132kV circuit breakers at various Details
 8Tender for construction of retention (protection) wall for the protection of tower Details
 8Tender for annual maintenance contract for overhauling/ servicing/ repairing of 33kV VCBs of various make at various EHV substation Details
 8Tender for work of servicing / overhauling of 145kV SF6 circuit breakers at various substations Details
 8Tender for rate contract for attending emergency breakdown and planned outage works on various 400 kV lines Details
 8Tender for Bi-annual maintenance & attending emergency breakdown work of 400kV transmission lines Details
 8Tender for work of overhauling of diverter switch and drive mechanism box of the OLTC of the transformers Details
 8Tender for work of strengthening of earth mat by providing and installation of enhanced chemical compound (EHCC) earthing electrodes Details
 8Tender for rate contract of excavation and laying of new power / control / telephone cables, replacement of faulty/damaged cables Details
 8Tender for providing and laying G. I. pipe Details
 8Tender for supply of fire water pump-3 with motor Details
 8Tender for supply, erection and commissioning of new street light poles with cable laying Details
 8Tender for work of dismantling replacement / repairing of PF pipe, orifice & PF bend of coal mills Details
 8Tender for repair, maintenance, and installation of plant/ systems/equipments Details
 8Design, supply erection commissioning and testing of water distribution system for natural draught cooling towers installed Details
 8Tender for supply of knife gate valve for ash handling plant Details
 8Tender for supply of LED flood light Details
 8Tender for supply, erection, testing, and commissioning of conversion of 66 kV line Details
 8Tender for supply, erection, testing, and commissioning of 132kV & 66kV equipments and materials Details
 8Tender for refurbishment / retrofitting of unit control desk (UCD) confirming Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8India on track to meet 2030 renewable energy target: Union MoS for New and Renewable Energy Details
 
8At Times Now event, Joshi spotlights wind solar energy advantages Details
 
8Suzlon Energy shares trade lower despite order win from Waaree Group Details
 
8Orient Cement Approves Q1 FY27 Results and Invests in Wind Power Firm Details
 
8Suzlon bags 201.6 MW wind energy order from Waaree Group for Andhra Pradesh project Details
 
8Experts Concerned, 81% Of SO? Emissions Around Delhi-NCR Come From Exempted Coal Plants Details
 
8Solar Urgency: India has made a smooth transition to green energy Details
 
8Power sector faces new challenges amid rising demand, says Manipur CM Details
 
8Indian Energy Exchange Reports 11.7% Growth in Q1 FY27 Consolidated Profit as Electricity Volumes Rise Details
 
8Adani Power's nuclear expansion depends on private-sector policy clarity Details
 
8India's Nuclear Mission Gains Major Momentum Details
 
8Global power demand to rise in 2026 and 2027, renewables outpace coal in power generation: IEA report Details
 
8Why Adani Green stocks are falling despite strong Q1 results Reasons Explained Details
 
8India targets 100 GW nuclear power capacity by 2047 Details
 
8Coal Stocks Fall To 13 Days As Power Demand Climbs Details
 
8India advances small reactor plans, targets five nuclear units by 2033 Details
 
8APGENCO felicitates Team India spinner Sree Charani Details
 
8India’s Data Centre Industry Set for Rapid Growth, Land and Power Remain Biggest Challenges: JM Financial Details
 
8REC stock reflects earnings recovery as borrowing costs reshape the outlook Details
 
8India Reaches 297 GW Clean Power; Eyes 500 GW Target by 2030 Details
 
8Coal Supplies 70% of India's Power As Demand Peaks at 270 GW Details
 
8IEA Forecasts 7% Electricity Demand Surge for India by 2026 Details
 
8Bondada Engineering gets CEA approval for energization for NLC India Renewable’s solar power project Details
 
8RattanPower Board To Review March Results On July 24 Details
 
8India Adds Record 6,057 MW Wind Power in FY26, Total Capacity Crosses 57,443 MW Details
 
8Adani Power Eyes 10 GW Nuclear Goal by 2035 Details
 
You can also click on Newsclips for more Details
8The IEX day-ahead market averaged Rs 5,249.71 a MWh on 22 July but sat pinned at the Rs 10,000 ceiling through the overnight and evening blocks and fell to Rs 1,379.70 in the solar-flooded early afternoon. None of it was scarcity - the grid met a 233,019 MW peak with essentially nil shortage; the crunch is the shape of the day, not a shortage of power. Details
8The Northern load-despatch pool's security-constrained unit-commitment account for 6–12 July shows Rs 46.28 crore paid to keep coal and gas units committed and run up, led by Rs 18.62 crore to NTPC's Dadri gas station. It is the same bill the Western and Eastern pools ran the same week - the cost of holding thermal ready while midday solar forces it down has now gone nationwide. Details
8Both 660 MW units of UP's Jawaharpur thermal station tripped together at 22:20 on 22 July when the 765 kV line to Greater Noida went out on generator-transformer protection, and neither was revived by cutoff. It lands as the Western committee's protection papers catalogue more than forty grid disturbances from the spring - including a 1,704 MW loss at JSW's Mahanadi plant when a lightning strike collapsed a transmission tower. Details
8National coal stock at power plants held about 40.4 million tonnes, roughly 13 days' cover, on 21 July - but 29 individual plants were running critical, two more than a week earlier. Andhra's Damodaram Sanjeevaiah was at 3% of its normative stock, about a day's cover, and Reliance's Sasan ultra-mega was at the same 3%. Details
8Adani Power reported a consolidated first-quarter net profit of Rs 4,866.60 crore, up 47%, on income of Rs 19,322 crore and a plant load factor lifted to 77.9%. The board cleared a Rs 15,000 crore equity raise and doubled the borrowing ceiling to Rs 1 lakh crore, as the group folded in three plants from the Jaiprakash Associates bankruptcy and signed a 1,600 MW supply deal with Maharashtra. Details
8JSW Energy's first-quarter net profit fell to Rs 533 crore from Rs 836 crore even though EBITDA edged up and capacity crossed 14,535 MW on a record organic addition. The drop is the cost of that growth - depreciation and finance charges on new plant, weak hydrology and a force-majeure at its Mahanadi coal station - as it also swallows GE Power India's boiler business and signs up another 300 MW of thermal. Details
8Aditya Birla Renewables has agreed to buy 100% of Solenergi Power - the holding company for Shell's Sprng Energy platform - for an enterprise value of about Rs 17,200 crore, taking on roughly 5 GW of solar and wind. The deal lifts the Aditya Birla green portfolio from 4.4 GW to 9.3 GW and marks a major oil-major's exit from the Indian renewable market. Details
8Adani Green Energy reported a June-quarter operating capacity of 20,142 MW, up 27% on the year, with energy sales up 30% and EBITDA at a record Rs 4,122 crore on a 94% margin. Its battery build at Khavda nearly doubled in the quarter to 3,551 MWh. Details
8The Appellate Tribunal for Electricity has stayed a Maharashtra commission order that apportioned regional-pool and legacy deviation charges to thermal generators injecting into the grid, allowing interim relief to Adani Power's Dahanu station and JSW Energy. JSW alone had paid about Rs 3.8 crore under protest; the tribunal's order freezes the demands while the appeals are heard. Details
8In SECI's 125 MW / 500 MWh standalone battery tender for Odisha, backed by viability-gap funding, Coal India won two of the three clusters - 80 MW in all - at monthly capacity charges of about Rs 3.04–3.05 lakh a MW. A coal miner taking grid-scale storage is the sharp edge of how the majors are hedging the energy transition. Details
8IEX day-ahead averaged Rs 5,250 on 22 July but held the Rs 10,000 ceiling overnight and at dusk
8The green day-ahead cleared at Rs 6,685 - a premium of more than two times the conventional price
8HPX drew no buyers for a fourth day and PXIL cleared nothing for an eighth, so IEX carried the market
8Rajasthan's merit order runs from Rs 1.55 at Sasan to Rs 28.11 for liquid-fuel peaking
8Andhra's discom levies a Rs 0.40 a unit fuel surcharge for May in the August bills Details
8India met a 233,019 MW maximum demand on 22 July at 11:19 - a solar-hour peak - with shortage near nil
8The grid ran high a sixth of 22 July and the operators backed generation down by nearly 56,000 MWh
8The North-East to Tripura corridor sat over its transfer limit for 63% of 21 July
8India imported 52 MU from Bhutan and wheeled 56 MU to Bangladesh on 22 July
8The West met a 63,684 MW evening peak with zero shortage as wind supplied 169 MU
8The South met a 55,049 MW peak shortage-free while carrying 10.7 GW of generation on outage Details
8About 52 GW of capacity sat under maintenance on 21 July, 30 GW of it forced out
8A 765 kV trip took both Jawaharpur units - 1,320 MW - off the bars late on 22 July
8The South spent 22 July switching around a twin-circuit line snap and a Mysore bus-bar cascade
8Western forced losses took out Adani Raipur, Sasan and Shree Singaji - three units near 660 MW each
8NTPC carried about 5.6 GW of its own fleet out on boiler and condenser leaks
8About 32 GW has been out beyond a fortnight, including two 800 MW Yadadri units and Kudankulam-1 Details
8Twenty-nine thermal plants ran coal-critical on 21 July; Damodaram Sanjeevaiah down to a day
8The coal ministry counts 42 mines scientifically closed and sets a Rs 40,000 crore closure corpus
8Bharat Coking Coal swings to a Rs 68 crore loss as production falls 27%
8A Northern Coalfields e-auction carries a disputed Rs 300 a tonne Singrauli rehabilitation charge Details
8Telangana's Krishna reservoirs hold about 93% less energy than a year ago deep into the monsoon
8The East runs almost no hydro - Teesta-III still out, Odisha's reservoirs bare and a pumped-storage unit drawing power
8Big reservoirs are still filling - Bhakra sits 30 metres below its full level Details
8The appellate tribunal stays Maharashtra's legacy-deviation charge on thermal generators
8Himachal's regulator clears nine rooftop and ground-mounted solar tariffs at Rs 3.47 a unit
8Himachal grants interim connectivity to a 4.8 MW small-hydro project through a spare 33 kV bay Details
8Uttarakhand fixes UPCL's recoverable from a 214 MW gas station at Rs 19.83 crore and rejects the review
8UP defers a giant captive solar project's plea for full transmission and banking exemption
8Maharashtra allows interest on delayed late-payment surcharge to an 11 MW bagasse cogenerator
8Haryana clears a flexible-load scheme and a graded surcharge, and quashes a township reference-meter demand
8Haryana defers plant-wise deviation settlement for the Panipat thermal station by a year
8Chhattisgarh puts ArcelorMittal's beneficiation plant back in the steel tariff category after a suo-motu reclassification
8Kerala's board asks its regulator to approve per-kW distribution cost data averaging Rs 1,563 a kW
8Tamil Nadu's ombudsman orders a Rs 2,982 refund and Punjab adopts a supply-code amendment
8UP tightens SCADA compliance on its utilities and extends a transmission line's deadline to December Details
8Coal India wins 80 MW of SECI's 125 MW Odisha battery tender
8The solar-cell approved list adds nearly 1,700 MW of domestic capacity in its eighth revision
8Adani Green's operating fleet crosses 20,000 MW on record quarterly EBITDA
8India's installed wind capacity reaches 57,443 MW, fourth largest in the world
8Suzlon lands a 202 MW wind order as Waaree Renewable buys into transmission
8Borosil Renewables' quarterly EBITDA doubles as it plans a 60% capacity expansion
8National statistics put India's assessed renewable potential at 4.7 million MW Details
8Adani Power's Q1 profit jumps 47% to Rs 4,867 crore with a Rs 15,000 crore raise
8JSW Energy's Q1 profit falls a third to Rs 533 crore
8Aditya Birla Renewables buys the Sprng platform from Shell for Rs 17,200 crore
8Bajel Projects wins a 500 kV Egyptian transmission order worth more than Rs 400 crore
8The Inox wind group lines up a Rs 600 crore raise, a Rs 3,500 crore captive order and an O&M demerger
8Orient Green's Q1 profit slips to Rs 24 crore as it winds up its European arm; Tata Power weighs a bond issue
8Ratings Watch - ICRA puts three Aditya Birla Renewables units on watch, upgrades Sunsure, and CARE withdraws Soleos Details
8The North's pool paid Rs 46 crore last week to keep thermal on bars
8The Western protection committee logs 40-plus spring disturbances, one a 1,704 MW loss at JSW Mahanadi
8The South's committee weighs an Adani 765 kV substation, a Rs 1.36 lakh crore HVDC plan and a Vallur battery award
8The East's disaster-management meeting orders an emergency restoration set and studies a Nepal-hydro black start
8Punjab's power strike stretches to four days as unions add pensioners and PSPCL orders no-work-no-pay
8Himachal advertises a regulatory Member (Law) vacancy as public-body staffing turns over Details
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details
 For reference purposes the website carries here the following tenders:
  
8Tender for Bi- annual rate contract for emergency power restoration work of 400/220/132/66kV lines Details
  
8Tender for Bi-ARC for original survey and check survey for various 400kV/220kV/132kV/66kV overhead line Details
  
8Tender for dismantling of existing fencing and installation of new main gate along Details
  
8Tender for supply, installation & commissioning of CSD Details
  
8Tender for drone based patrolling of transmission lines Details
  
8Tender for protection wall at tower Details
  
8Tender for supply of LED flood lights and street lights for replacement of faulty lights Details
  
8Tender for supply of 36 kV CT accuracy 0.2S accuracy classes along with terminal connectors and junction boxes Details
  
8Tender for inspection of TG bearings, in situ machining of LP rotor journal Details
  
8Tender for capability (performance) test of NDCT Details
  
8Tender for work for protection of water conductor Details
  
8Tender for replacement of conventional electrical switches Details
  
8Tender for EPC Package for internal coal handling plant Details
  
8Tender for annual maintenance of horticulture works Details
  
8Tender for standardization of transformer station Details
  
8Tender for repair of damaged UC fencing and allied civil works Details
  
8Tender for procurement of sulphuric acid commercial grade Details
  
8Tender for construction of 1 no. addl. 20 MVA 66/11 kV TF plinth along with allied civil works Details
  
8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects Details
  
8Design, supply, erection, testing and commissioning of new generator relay panels Details
  
8Tender for providing chain-link fencing Details
  
8Tender for supply of various type sleeves & fins for boiler Details
  
8Tender for supply & erection of MS grills at various Details
  
8Tender for day to day civil maintenance work Details
  
8Tender for repair and maintenance of external pipelines Details
  
8Tender for repair, renovation, and miscellaneous civil maintenance works Details
  
8Tender for procurement of spares for turbine supervisory system Details
  
8Tender for maintenance of station battery sets of power plant Details
  
8Tender for annual / running and breakdown maintenance of pipe lines Details
  
8Tender for annual repair and maintenance contract for electrical systems Details
  
8Tender for providing and fixing PUF panel operator cabin Details
  
8Tender for supply of electrical actuator Details
  
8Tender for supply of various types of pressure and temperature switches Details
  
8Tender for development of 2 Nos of bore wells for water supply Details
  
8Tender for annual maintenance of 04 (four) nos. of generating units Details
  
8Tender for repair of 02 KSB-manufactured 90 kW submersible pumps Details
  
8Tender for supply of material Details
  
8Tender for maintenance/operation of 33/11 kV sub-stations, associated HT/LT lines Details
  
8Tender for shifting and heightening of 11kV and LT lines including 11/0.4 kV DTRs Details
  
8Tender for biennial work contract for maintenance of ash handling plant Details
  
8Tender for renewal work with widening of existing Details
  
8Tender for work of attending hot-spots and oil DGA issues by modification of LV bushing internal connection Details
  
8Tender for empanelment of agencies for restoration of distribution infrastructure Details
  
8Tender for empanelment of contractors to award a contract for survey, installation, testing and commissioning of 33kV line Details
  
8Tender for work contract of day to day routine maintenance of 220kV and 400 kV switchyard, all HT and LT transformers, overhead line faults Details
  
8Tender for procurement of spares for caustic acid alum and polyelectrolyte dosind pumps installed Details
  
8Tender for const. of 33 kV S/S Details
  
8Tender for construction of power transformer and VCB foundation Details
  
8Tender for construction of store shed at 33 kV S/S Details
  
8Tender for construction of control room, water supply arrangement and yard levelling and gravelling work at 33 kV S/S Details
  
8Tender for roof leakage treatment, renovation Details
  
8Tender for purchase of 245kV 1250A motorized isolator Details
  
8Tender for purchase of 220V DC and 110V DC control and distribution board Details
  
8Tender for providing auxiliary earth mat at motorised isolator and earth switch mechanism point along Details
  
8Tender for construction of chemical earthing for towers along Details
  
8Tender for painting of HT and MS exposed steel structural tower member of 220 kV /132 kV LILO transmission line tower Details
  
8Tender for supply installation, connection and commissioning of 15 nos. bore type earth pit for improvement of earthing system of 50 MVA power with the work of pipe line Details
  
8Tender for complete overhauling of 132/33 kV 50MVA power transformer Details
  
8Tender for replacement of damaged cable hanger with providing perforated cable tray with cable tray support/fixture in 132 main and 132 kV side cable trenches Details
  
8Tender for repair and maintenance of grid control room at 400/220kV GSS Details
  
8Tender for work of aluminium and zinc chromat/phosphate based painting of rusted tower structure Details
  
8Tender for selection of cloud service provider for providing cloud infrastructure Details
  
8Tender for service contract for round the clock operation of 01 no. in motion weigh bridge Details
  
8Tender for Bi-annual maintenance contract of various equipments like dozers, DG sets, fire pump Details
  
8Tender for manufacture, testing, supply and delivery of 11 kV 200 A TPGO isolator with polymer post insulator. Details
  
8Tender for procurement of current transformers (400kV and 220kV C.T) Details
  
8Tender for supply of LT three phase channel cross arm Details
  
8Tender for supply of fixed contact for 11 kV AB switch Details
  
8Tender for supply of stay set complete Details
  
8Tender for supply of various sizes of MS bollt and nuts Details
  
8Tender for supply of HT /TI fitting and LT /TI fitting Details
  
8Tender for running works contract for effecting various works Details
  
8Tender for supply of HS type straight joint kit suitable for 33kV 1X630 sqmm XLPE UG cable Details
  
8Tender for supply of 11kV vertical type group operated AB switch with composite polymer insulators Details
  
8Tender for diversion of 220 kV transmission line Details
  
8Tender for maintenance/operation of 33/11 kV sub-stations Details
  
8Tender for maintenance/operation of 33/11 kV sub-stations, associated HT/LT lines Details
  
8Tender for supply and installation of pipe earthing Details
  
8Tender for supply and installation of pipe earthing in different capacity of DTRs Details
  
8Tender for electrical work for construction of 2X5 MVA 33/11 kV substation Details
  
8Tender for construction of 16.0 KM 33 kV line Details
  
8Tender for complete overhauling/maintenance work of 33 kV VCB’s panels Details
  
8Tender for complete overhauling/maintenance work of 33 kV VCB’s panels breakers complete unit) of different make installed Details
  
8Tender for complete overhauling/maintenance work of 33 kV VCB’s panels breakers Details
  
8Tender for regarding work shifting/displacement of 33 kV, 11 kV, LT lines Details
  
8Tender for work of providing and fixing of non-conductive turbo wind driven conical bird guards at various suspension tower Details
  
8Tender for AMC of optical fiber network and LAN for ERP and internet connectivity Details
  
8Tender for Bi-annual maintenance of NIFP system Details
  
8Tender for work of complete overhauling of 400kV breakers pole Details
  
8Tender for work of replacement of existing hanging/suspension type wave trap by new pedestal type wave trap along Details
  
8Tender for replacement work of 220kV GIS bays at 220 kV GIS substation Details
  
8Tender for work of servicing & overhauling along with providing & fixing of required spares of 245kV circuit breakers at various Details
  
8Tender for Bi-annual maintenance contract for work of repairs, servicing & alignment for 220kV, 132kV, 33kV isolators along Details
  
8Tender for work of providing and fixing of 33 kV current transformers at various sub-stations Details
  
8Tender for purchase of single phase SMC meter box Details
  
8Tender for purchase of LT shackle insulator Details
  
8Tender for supply and application of metal protective compound for various structure, pipes and duct Details
  
8Tender for supply of pre engineering shed for central store Details
  
8Tender for supply of ACB & panel spares Details
  
8Tender for supply of neutral grounding resistor Details
  
8Tender for supply and installation of an energy efficient lubricated rotary screw air compressor Details
  
8Tender for erection of new HT, LT line and transformer centers, replacement work, underground cabling work Details
  
8Tender for erection of 66kV Lilo line Details
  
8Tender for work of erection dismantling of 66kV/11KV equipment’s, structures, control wiring Details
  
8Tender for supply of fire system pumps Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Jindal Steel Deploys Indigenous Coal Gasification in Global First for Steelmaking Details
 
8Coal Ministry unveils roadmap for sustainable mine closure Details
 
8India's renewable energy potential more than doubled in FY25: Mospi Details
 
8Coal ministry releases AAROH mine-closure report, signs EUR 10-million mine closure cooperation pact with GIZ Details
 
8India's steel ambitions face a coal reality check Details
 
8India's solar power boom faces regional imbalance, manufacturing glut Details
 
8The next farm revolution will hinge on energy economics, not just better seeds Details
 
8India’s Green Hydrogen Mission Gains Momentum Despite Capacity And Infrastructure Challenges Details
 
8India's Renewable Energy Capacity Nearly Quadruples To 288.58 GW Since 2014 Details
 
8Gautam Solar Earns EcoVadis Silver Medal, Ranks Among Top 15% Globally for Sustainability Details
 
8Power distribution, petroleum import going private Details
 
8Solar Cell Import Relief Stirs Concerns for Domestic Makers Details
 
8First Solar margin expansion draws analyst optimism despite solar sector downturn Details
 
8Delhi Launches Smart Substation, Rooftop Solar Drive To Strengthen Power Infra Details
 
8JSW Energy Q1 FY27 results: Net profit declines 36% to Rs 532 crore Details
 
8India's solar capacity to exceed coal by 200 GW by 2036: Pralhad Joshi Details
 
8How China and India are supercharging the battery storage market Details
 
8India’s geothermal energy dreams gather steam Details
 
8India’s Wind Power Capacity Rises to 57,443 MW, Ranks Fourth Globally Details
 
8Nuclear power capacity to reach 22 GW by FY32, says Jitendra Singh Details
 
8India's Solar Capacity Touches 162.15 GW As Renewable Push Gains Momentum Details
 
8MNRE adds Avaada, expands Fujiyama capacity under ALMM List-II Details
 
8Bajel Projects Concludes 500kV Transmission Line Agreement In Egypt Details
 
8Energy minister seeks proposals to privatise power distribution Details
 
8Adani Power Q1 PAT jumps 47% as higher power sales, tariff realisation boost earnings Details
 
8NLC India Raises INR 150 Crore Through Commercial Paper Issuance Details
 
8Adani Power shares down 2%: Q1 net profit rises 47%, power generation capacity hits 18,330 MW Details
 
8Telangana Withstands 7,000 MW ‘El Niño’ Power Shock, No Power Cuts Across State: Deputy CM Bhatti Vikramarka Details
 
You can also click on Newsclips for more Details
81) IntelliSmart takes Indore smart metering at 21.7% below MPPKVVCL's estimate Ten bidders entered, three fell at the technical gate and six were eliminated on price, leaving a single survivor. The 6.9% gap to Apraava suggests competitive pressure rather than distress bidding. What remains untested is whether a Rs 417.15 crore price absorbs a 3,650-day service obligation comfortably. Under DBFOOT, the winner carries financing, deployment and lifecycle risk long after the award headline fades.

82) NTPC Green's Khavda BESS tender kept moving after its own deadline had passed Six corrigenda and one addendum landed inside a single bidding cycle, with the last posted a day after the original closing date. That sequence tells bidders the package was still being calibrated while they were expected to fix prices. The notice never states MW rating, discharge duration, chemistry or augmentation responsibility. A reverse auction on 3,300 MWh of undefined configuration is where the real risk sits.

83) MPPGCL formalises a site visit so bidders cannot later claim they did not know The corrigendum changes no scope, no price basis and no qualification bar — it simply schedules an inspection. Its commercial value lies in what it removes: the post-award claim that site conditions were unforeseeable. For a turnkey EPC carrying five years of O&M, land and interface assumptions made blind become expensive. The promoter has quietly shifted diligence responsibility back onto the bidder.

84) UJVNL puts the entire Sirkari Bhyol electro-mechanical chain under one turnkey price Rs 158.53 crore covers design through commissioning for a 3x40 MW hydro package with no interface escape route. The structure rewards firms with manufacturing depth rather than assembly capability. Coordination risk, not equipment cost, is likely to decide who prices this realistically. The pre-bid stage will show whether the market treats the estimate as workable.

85) POWERGRID removes the performance guarantee but moves payment behind a Collector's order Deleting the CPG frees working capital for the Morbi valuation package — an unusual relaxation for a consultancy assignment. What replaces it is milestone payment tied to acceptance by authorities the contractor cannot control. The award cap has also loosened from one package to two, reshaping who can win what. Easier entry, harder cash conversion.

86) Two extensions on Tankul suggest the market needed more time than UJVNL assumed The bidding window has stretched by 25 days without any visible change to scope, capacity or the Rs 87.90 crore estimate. The package runs from river diversion through tunnel, surge shaft and powerhouse into hydro-mechanical works. Geological risk allocation across those fronts is not resolved in the public notice. Repeated extensions usually mean bidders are still pricing what they cannot see.

87) NTPC's Barauni ash package rules out reverse auction and self-performed design cannot be bought in A three-week extension eases bid preparation but changes nothing about a 630-day delivery obligation. Qualification demands an executed pneumatic system with in-house design — closing the route of borrowed engineering credentials. Rs 1 crore bid security and Rs 6.09 lakh daily delay damages narrow the field further. NTPC appears to want fewer bidders who can actually finish.

88) BHEL caps some liability at Lakhanpur while leaving the worst exposure at 100% Corrigendum VIII gives bidders numbers to model: 5% for delay, 5% for performance shortfall, 30% for make-good. Termination and risk-and-cost completion still reach the full contract price. Requests to soften the one-year force majeure and three-year hold thresholds were refused outright. Five deadline extensions later, the risk envelope is clearer but no lighter.

89) MSEDCL reaches Version 5 on a Rs 109.58 crore transformer buy before opening a single bid Successive revisions and an incorporated pre-bid reply document suggest the utility preferred argument before award rather than after. Firm pricing survives every revision, leaving cost risk with manufacturers. The extended window improves bid quality but delays a purchase of one of the network's most routinely consumed assets. Document stability, not competition, appears to be the priority here.

810) BHEL wants its Anantapur BOS partner locked in before the project even exists This is a pre-bid tie-up, not an award — capability is being secured ahead of the downstream contest. A Rs 3 crore EMD against an uncertain project outcome is a serious commitment to demand upfront. It filters out speculative participation while pushing bid-stage risk onto prospective partners. For 1,200 MW, BHEL is buying execution certainty before it needs it.

811) Ennore's FGD tender has spent 162 days in procurement without changing a single risk clause Five extensions and a cancelled-then-restored pre-bid meeting have stretched the calendar without relaxing EMD, LD, warranty or completion terms. Contractors gained preparation time; the 30 and 32-month clocks did not move. The 4%-1% security split makes the technology provider a secured party rather than an adviser. Market formation, not administration, appears to be what took so long.

812) POWERGRID makes survey counts indicative and tells Anand bidders not to expect more money Corrigendum C5 deletes the performance guarantee, then transfers parcel-density risk in the same breath. Bidders must quote a fixed total before receiving the Land Plan Schedule, survey details and KML files. Payment splits 80:20, with the tail dependent on committee acceptance and a Collector's order. Lower entry cost, higher pricing blindness.

813) Mahagenco asks one contractor to find the land, build the plant, evacuate the power and run it for a decade This is a development platform transfer disguised as a 300 MWac EPC procurement. The 25 MWac floor widens entry, but a 15 MWac reference plant and per-MW financial ratios quietly narrow it again. Consortium partners can share technical credentials; the lead member carries the full financial test alone. A reverse auction then compresses prices built on land and evacuation uncertainty.

814) Kulhal's pre-bid meeting was rescheduled to a date after its own bid deadline The original calendar collapsed once clarification moved past the closing date, forcing a third extension. The 29-day shift restores roughly the same clarification-to-submission interval the tender first intended. What bidders learned during that window matters more than the extension itself. Rs 110.57 crore of brownfield hydro renovation cannot be priced from drawings alone.

815) CTUIL reorders its contract hierarchy one day before bids close The corrigendum makes the uploaded RfP supreme over conflicting GeM terms and the service-level agreement, without extending the deadline. Bidders must reconcile a 286-page document against a portal summary in a single day. The consultancy itself carries authority over delay claims, force majeure, cost reasonableness and asset valuation. Personnel controls make the CVs submitted a binding commercial promise, not a bid-stage flourish.

816) A one-minute discrepancy sits inside NTPC REL's 600 MW Dhule bid schedule The schedule table says one cut-off; the portal banner says another sixty seconds later. Electronic systems reject late bids automatically, which makes ambiguity a procedural risk unrelated to price or capability. Corrigendum-1 arrived seven days before submission alongside a second addendum. Rs 20 crore in bid security filters the field before a reverse auction compresses whatever margin survives.

817) BHEL bundles two Korba West packages that share nothing except a single price Package-A and Package-B carry different boundaries and 42 and 58-month schedules, yet must be quoted as one lump sum. The price will be split 25:75 by prescription, not by the bidder's own cost structure. BHEL can then redistribute orders at will, with cross-default linking every instrument it issues. Administrative separation without contractual separation is the whole design.

818) POWERGRID tightens the one-package rule for Kheda while consolidating its own conditions The revised ATC pulls qualification, evaluation, payment and scope into a single controlling document. Restricting each agency to one award prioritises parallel execution across districts over economies of scale. A package-opening sequence is being used to manage bidder capacity before firms exhaust their entitlement. Fifteen days per assignment leaves no room for slow mobilisation.

819) Corrigendum C7 shows POWERGRID still adjusting its Gujarat valuation terms before award The amendment modifies the bidding process after original publication and must be read alongside the base documents. GeM provisions and POWERGRID's own conditions now operate together rather than in sequence. Land valuation has moved from incidental consultancy to a scheduling input for transmission construction. The final conditions matter more than the original release. Details
81. PSTCL floats 90-day civil works tender for 160 MVA transformer at 220 kV Bathinda substation
PSTCL has published a notice inviting tender for civil works connected with a 160 MVA transformer at its 220 kV GNDTP Bathinda substation, with a compressed 90-day completion window and quoted rates valid for 120 days. Tender documents will be issued only to firms the corporation considers adequately experienced, though no qualification formula is disclosed. A striking drafting anomaly sits inside the notice: the document-issue deadline falls after the bid-submission deadline. Unless corrected, the timetable is internally unworkable and could undermine competitive participation.

 

82. UJVNL packages river diversion, tunnelling and powerhouse into single Rs 87.90 crore Tankul hydro contract
UJVN Limited has invited online bids for constructing the 12 MW Tankul small hydro project in Pithoragarh, combining trench weir, intake, river diversion, desilting tank, tunnel, surge shaft, powerhouse and hydro-mechanical works in one mandate. The submission deadline has moved by 25 days through two extensions alongside two corrigenda, signalling the package required correction before closure. Bidders must price geological uncertainty, river behaviour and remote Himalayan logistics into a compact contract value. The project's execution complexity far exceeds its modest installed capacity.

 

83. BSPGCL couples 150 MW solar with 75 MW/300 MWh battery in tariff-based bid with capacity-linked EMD
Bihar State Power Generation Company has issued an NIT to develop 150 MW of solar PV integrated with a four-hour battery system through tariff-based competitive bidding followed by e-reverse auction. The EMD scales at Rs 14.24 lakh per MW quoted, discouraging speculative capacity offers, while the original bid-security instrument must physically reach BSPGCL despite an otherwise digital process. Battery degradation, augmentation and charging rules — central to project economics — are left to the detailed documents. The outcome could set an early state benchmark for solar-plus-storage pricing.

 

84. HPSEBL seeks Rs 3.72 crore project management consultant under QCBS — then adds a reverse auction
HPSEBL has floated an RFP for a project management agency to support its reforms-linked distribution scheme, deploying 246 expert man-months across engineering review, field monitoring and funding-claim support, with the deadline extended by ten days. Selection follows a 70:30 quality-cost formula, yet the notice simultaneously announces an e-reverse auction — an unresolved structural clash. A Rs 70 crore annual turnover threshold towers over the modest assignment value, favouring large national consultancies. HPSEBL also retains the right to double expert deployment in every category, shifting staffing risk onto the consultant.

 

85. OCPL hands one consultant the entire blueprint for its 5 MTPA Manoharpur coal washery
Odisha Coal and Power Limited is appointing a single adviser to prepare the DPR, washability study, CAPEX-OPEX-IRR modelling and the complete EPC tender architecture for a proposed 5 MTPA coal washery, with the deadline extended by 18 days after the original schedule lapsed. The washability study must run through one of six named institutions, tying a core milestone to external laboratories. Joint ventures are barred, concentrating all credentials in one entity, while least cost selection meets a strict abnormally-low-bid clause that can exclude aggressive quoters from retenders. The 120-day programme leaves little slack for approval cycles.

 

86. GSECL's Rs 4.73 crore covered-conductor retrofit at Ukai TPS carries a 36-month owner-controlled execution horizon
GSECL has floated an open three-stage e-tender to replace 16 km of exposed 11 kV conductors at Ukai Thermal Power Station with medium-voltage covered conductors, including eight double-pole air-break switch structures and dismantling of old lines, as an indivisible supply-plus-works package. Supply must finish in six months, but the work order stays valid for 36 months — extendable by six more at unchanged prices. Thirty per cent of supply value remains locked until successful charging, tying contractor cashflow to shutdown availability. With no guaranteed work-release schedule, bidders are pricing a long-duration call-off obligation, not a fixed-schedule job.

 

87. MSEDCL extends commencement window but holds commercial line on Rs 130.38 crore STAR-II transformer buy
MSEDCL has issued Amendment No. 1 with pre-bid clarifications on its tender for 200 kVA STAR-II CRGO distribution transformers, extending the commencement period from two to three months while keeping the nine-month delivery schedule intact. Manufacturer requests for revised estimated cost, IEEMA price variation, relaxed experience thresholds and softer security terms were all rejected, while BEE certification was confirmed as not required for 22 kV units. The amendment signals selective operational flexibility without commercial concession. Certification-heavy entry barriers remain firmly in place for smaller suppliers.

 

88. POWERGRID engages exclusive land valuer for 219 km transmission corridor in Morbi under package-wise GeM bid
POWERGRID has invited a two-packet GeM bid to appoint a land valuer for transmission-line corridors in Morbi district under Package-7, covering roughly 219 km, with the consultant certifying survey-number-wise market rates for compensation and acquisition. The valuer must work exclusively for POWERGRID and is barred from representing any other project stakeholder — a stronger conflict-management measure than routine consultancy tenders carry. The district-wise package model spreads work across Gujarat while limiting how many packages one bidder can secure. The tender treats land valuation as project-critical infrastructure work rather than conventional advisory service.

 

89. NREDCAP offers 22-year DBFOT concession for Rs 324.70 crore Vijayawada waste-to-energy plant
NREDCAP, acting for Vijayawada Municipal Corporation and participating urban bodies, has issued an RFP for a private concessionaire to design, build, finance, operate and transfer a 15 MW municipal-waste-based power plant under a 22-year concession including two years of construction. The Rs 3.24 crore EMD and qualification framework point toward experienced infrastructure developers rather than general EPC contractors. Financing strategy and long-term operating assumptions will matter more than EPC pricing in determining competitiveness. The structure reflects a policy preference for private lifecycle ownership of complex municipal processing assets.

 

810. NTPC Ramagundam to double transformer capacity with 500 MVA units under integrated 30-month contract
NTPC has invited domestic bids to replace two 250 MVA auto transformers at Ramagundam with 500 MVA interconnecting units, bundling design, manufacture, transport, oil treatment, erection and commissioning into one accountability chain over 30 months. An unusual clause forces installation pricing into a 10–15% band of supply value, blocking payment-structure engineering. Loss penalties reach Rs 10 lakh per kW for no-load deviation — with no reward for overperformance — while the variable-price contract offers only narrow escalation relief. A Rs 1 crore bid security applies with no MSE exemption.

 

811. BHEL's 400 kV GIS package for Yamuna Nagar loads firm pricing, reverse auction and long-tail liabilities onto suppliers
BHEL is procuring a complete 400 kV gas-insulated switchgear installation for HPGCL's 800 MW ultra-supercritical expansion at Yamuna Nagar, with the deadline extended twice after a technical corrigendum rewrote testing, transport, packing and scope-boundary provisions. Prices stay firm across a 12-month supply cycle, while the 18-month warranty starts only after project trial operation — a milestone outside the supplier's control. Entire specification clauses were deleted without replacement, creating interpretation gaps, and packing must survive 24 months of outdoor monsoon exposure. Impact recorders must trace every shock from factory to site, with a reverse auction awaiting qualified vendors.

 

812. NTPC Talcher Kaniha's Rs 84.81 crore ash-backfilling contract pays only the lower of two measurements
NTPC has floated a GeM bid restricted to its enlisted ash-transport vendors for excavating, hauling and compacting ash from Talcher Kaniha into quarries and mine voids 50–100 km away, under a 12-month contract splittable 50:50 between two bidders. Payment follows the lower of dispatch-end or filling-site measurement, and every truck movement needs weighbridge, GPS, FASTag, toll and geotagged photo evidence uploaded daily — incomplete records mean withheld payment. A quantity mismatch between the scope figure and doubled BOQ entries demands careful reconciliation. Regulatory penalties on NTPC flow back entirely to the contractor, converting a transport job into a full land-reclamation obligation.

 

813. AEGCL's fixed-price 220 kV line for TATA semiconductor plant transfers all design-modification costs to the contractor
Assam Electricity Grid Corporation has published a turnkey tender for a 220 kV Sonapur-TSAT double-circuit line providing redundant power to the TATA semiconductor facility, spanning overhead line, underground cable, optical fibre and commissioning under single-point responsibility within 24 months. There is no advance payment and no escalation: AEGCL supplies the base design, but site-driven modifications — special towers, pile foundations, raised chimneys — must be executed at zero additional cost. The warranty runs five years from supply or four-and-a-half from commissioning, whichever is later, with liquidated damages at 1% per week up to 10%. Payments can take 60 days, subject to fund availability.

 

814. Powergrid caps land valuers at one package each across ten-district Gujarat valuation drive
Powergrid has issued a GeM bid for an IBBI-recognised land valuer covering 246 tower locations across 91.74 km spanning three transmission SPVs in Vadodara district, one of ten sequentially opened packages, with every assignment due within 15 days of intimation. A "one agency, one package" rule prevents any single firm from dominating, while packages with three or fewer bidders jump the price-opening queue. No escalation applies, quantities can swing 25% either way, and the bid summary denies arbitration even as attached conditions prescribe a full arbitration regime. Consistency across multiple independent valuers remains the unaddressed governance risk.

 

815. JREDA opens Jharkhand's 16-site hydro pipeline to solar, wind and thermal players through eligibility rewrite
JREDA has issued an EOI to identify developers for small hydro projects across 16 Jharkhand sites under the BOOT model, beginning with surveys and DPRs before full development, financing and long-term operation. Corrigendum-I broke the hydro-only entry barrier: any 5 MW DISCOM PPA — solar, wind or thermal — now qualifies, provided the bidder operates a plant in the supplying state, with the deadline extended by 14 days. A Rs 50 crore turnover floor screens for balance-sheet depth over technical pedigree. Concession terms, tariffs and free-power obligations are deferred entirely to the RfP stage, making second-stage evaluation the critical safeguard.

 

816. UJVNL's Sirkari Bhyol hydro tender swells 53% to Rs 243 crore through twenty corrigenda
UJVN Limited's EPC tender for the electromechanical works of the 3x40 MW Sirkari Bhyol Rupsiabagar project has been transformed through twenty corrigenda and seven addenda: the estimated value jumped 53% to Rs 243.05 crore, the EMD rose to Rs 4.87 crore, and every qualification threshold was rewritten upward. Technical access simultaneously widened through a fifteen-year experience window, more approved component makes and flexible efficiency testing, even as financial entry tightened. Himalayan logistics, construction power and site utilities stay contractor-facing despite repeated bidder requests for relief. Bidders must hold prices for 270 days on a package still being stabilised months after publication.

Details
8Daily Excel covering new tenders and all published updates including corrigendum, amendment, addendum, clarification and status revisions, along with technical and financial bid opening, evaluation completion and final award actions including AOC and LOA issuance.
Click on Reports for more Details
8IEX day-ahead averaged Rs 6,617 on 21 July but held the Rs 10,000 ceiling in 54% of blocks
8Real-time power took the day's biggest volume - 192.70 MU - at a weekly-low Rs 4,143
8The green day-ahead cleared Rs 6,755 and term strips settled flat at Rs 6,350 - no green discount
8PXIL cleared nothing and HPX drew no buyers, so IEX carried the entire cleared market on 21 July
8DVC-style peak buying returns as GUVNL and UPPCL float HPX reverse auctions for evening blocks
8Rajasthan's merit order runs from Rs 0.99 at NLC Barsinghsar to Rs 27.87 for liquid-fuel peaking Details
8India met a 235,132 MW evening peak and a 237,218 MW day-max on 21 July with zero shortage
8The grid ran high a quarter of 21 July and the operators backed generation down by 51,305 MWh
8The North-East to Tripura corridor sat over its transfer limit for 51.9% of 21 July
8Gujarat alone curtailed 922 MW of solar and 353 MW of wind for grid security on 21 July
8The Northern grid switched out about 25 of its 765 kV bus reactors at dawn to hold voltage up
8India imported 51 MU from Bhutan and 22 MU from Nepal while wheeling power to Bangladesh Details
 1 2 3 >  Last ›

Showing 1–50 of 459 items