All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.
Sep 2026
GSECL's Ukai ZLD Tender States Both 5% and 10% Performance Security in the Same Document
8GSECL's zero-liquid-discharge and water-reuse EPC package for Ukai TPS shows GeM's ePBG field at 5% for 47 months while the incorporated ATC separately demands a 10% security-cum-performance guarantee — a five-percentage-point gap that directly affects bank-limit planning from LOI onward.
8A 15-year capitalised power-consumption penalty stacked atop an incompletely described "zero liquid discharge" process (RO and UF are listed only as future improvements) leaves both the financial evaluation and the technical scope only partially defined.
GETCO's 1,507-Breaker Tender Extends 19 Days While the Portal Still Shows Old Dates
8GETCO's Rs 113.94 crore switchgear procurement — 95% concentrated in 66kV SF6 breakers — moved its technical opening from 9 to 28 September 2026 through Corrigendum 1, but the public portal continues displaying the original early-September schedule, creating a submission-control risk that bidders shouldn't dismiss as cosmetic.
8A five-times-manufacturing-capacity qualification test could effectively require certified annual output of 7,160 units from any bidder attempting the full 66kV lot alone.
BSPHCL's Bagasse Co-Gen Tender Cuts Its Term From 15 Years to 5 After Bidder Pushbac
8BSPHCL's 100 MW bagasse co-generation procurement slashed its contract tenure from 15 years to 5 and dropped the enforceable minimum PLF from 53% to 25% — corrections that acknowledge seasonal crushing realities — but then reversed a separate concession allowing multi-plant owners to submit project-wise bids, restoring the original single-application restriction without explanation.
BSPGCL's 150 MW Solar-Plus-Storage Tender Fixes a Doubled ESS Ratio That Nobody Caught
8BSPGCL's firm-and-dispatchable renewable procurement corrected its own PPA, which had originally required twice the battery capacity specified in the RfS — 1 MW/4 MWh instead of the intended 0.5 MW/2 MWh per MW of solar — while extending commissioning from 18 to 24 months and allowing the declared CUF to move downward for the first time, not just upward.
RVPN's Budhadeeth GSS Tender Discloses Coordinates But Withholds the Contour Sheet
8RVPN's Rs 50.55 crore turnkey substation package finally pinpointed its exact site location after bidder requests, but the promised contour and ground-level data needed to price foundations, drainage and earthwork remains deferred to "shortly" — leaving civil-cost estimation incomplete just weeks before an 18-month clock is set to start.
8A late-added, highly detailed capacitor-bank breaker specification arrived without any corresponding schedule relief.
UJVN's Chilla BESS Tender Raises Its Ceiling Tariff 3.8% But Won't Define When Batteries Get Dispatched
8UJVN's 90 MW/225 MWh storage project corrected its land location from the wrong district and lifted the capacity-charge ceiling to Rs 3,30,400/MW/month, yet still hasn't specified peak/off-peak windows, minimum dispatch notice, or whether scheduling will be day-ahead or real-time — leaving developers to size augmentation and degradation reserves against an undefined two-cycle-per-day operating profile on a site UJVN itself calls "tentative."
NTPC's Pudimadaka Green Hydrogen Water Plant Excludes O&M From Its Own Delay Penalty Cap
8NTPC's turnkey water-treatment package for NGEL's hydrogen hub quietly removed the five-year O&M contract value from the denominator used to calculate maximum delay-liquidated-damages exposure — reducing the theoretical LD ceiling — while separately introducing payment relief when NTPC's own delay blocks performance-guarantee testing for a full year.
Power Grid's 32-Item Tower Steel Award Shows a Tight L1-L2 Race and a Wide L3-L4 Split
8Power Grid's Rs 171.15 crore transmission-material award to Shilpa Steel separated from the second-place bidder by just 3.3%, but the gap widened to 19.2% by the fourth qualified bidder — a spread suggesting sharply different assumptions on steel, galvanising, prototype assembly and the 730-day execution commitment behind seemingly comparable headline totals.
NTPC's Rihand Transformer Tender Says "No Civil Work" While Its Own Spec Says Otherwise
8NTPC's replacement-transformer package for two 400 kV units flatly told a bidder "No Civil work is in scope of vendor," yet the underlying technical specification still assigns transformer and cooler-bank foundations to the supplier — a contradiction NTPC never formally repaired, leaving brownfield interface responsibility genuinely unclear before bid submission.
WBSETCL's Rs 339 Crore Transmission Award Shows an Unexplained Rs 4.60 Crore Price Drop
8WBSETCL's composite eight-project EPC award to Kalpataru Projects beat KEC by just 4.9% and Larsen & Toubro by 24.0%, but the winning bidder's evaluated price fell Rs 4.60 crore below its own comparative BOQ total for reasons the disclosed documents never reconcile — while a portal contract date two years after the actual letter of award adds a separate chronology puzzle.
WBSETCL's Transformer Auction Ends in a Rs 1 Lakh Photo-Finish, Then Adds 90 Days to Delivery
8WBSETCL's four-transformer procurement saw its reverse auction compress the top two bids to within Rs 1 lakh of each other on a Rs 33+ crore contract, yet the eventual purchase order quietly extended final delivery by 90 days beyond what the original tender demanded — a post-auction concession that shifts the traded value from pure price competition toward negotiated schedule relief.
NHPC's Haryana Rooftop Solar Tender Protects Good Bids From Bad Neighbors
8NHPC's 30.93 MWac government-rooftop RESCO tender inserted a new clause preventing a bidder's failure in one district or category from automatically disqualifying its otherwise-compliant bids elsewhere — a fix that kept nine of eleven original bidders in play for the eventual district-wise reverse auctions.
NTPC's Darlipali Ash Rate Contract Shows a Documented Award 54.5% Below Its Own Estimate
8NTPC's ash-to-road-construction logistics tender priced six equal Rs 22.75 crore contracts totaling Rs 136.50 crore against an original Rs 300 crore estimate — but with quantity deviation permitted down to zero and no guaranteed purchase orders, that headline gap may reflect discretionary allocation as much as aggressive pricing.
REC's YEIDA Transmission Tender Makes the Contractor Indemnify Risks It Never Created
8REC Power Development's Sector-28 YEIDA substation RFP requires the winning bidder to indemnify the seller against all past, present and future third-party claims tied to pre-closing project decisions — while the acquisition price for the project SPV remains blank until just 20 days before bid closure, and a stray reference sends the performance guarantee to CTUIL despite this being a purely intra-state UPPTCL project.
REC's Alkud-II Transmission RFP Finally Names Its Own Project Company
8A one-line amendment to REC's 765/400/220 kV Sangli transmission tender replaces every placeholder reference to "[Insert SPV name]" with "Alkud II Power Transmission Limited" — a housekeeping fix touching the RFP, TSA and SPA simultaneously, though the acquisition price, MERC-pending reverse-auction parameters and the project's all-or-nothing 24-month commissioning dependency remain unresolved.
Showing 1–20 of 20 items
For daily newsletters and other free services, fill in your details: