All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Aug 2026

8NPCIL's riser insulation package lists one set against four pipe sizes and 24 riser positions The bidder must fund detailed engineering, mock-ups, radiation qualification, five installation trials and site training before any payment falls due. ATC clause 13.0 ties 100% payment to final acceptance and completion of training, on a firm price held over 364 days. The GeM summary marks arbitration "No" while ATC clause 24.0 sets a three-arbitrator tribunal.

8NTPC Mining asks developers for indicative tariffs while holding the land lease rate back to the RFP The 50 MWp splits evenly across two mines, but one sits on an overburden dump and the other carries mandatory levelling plus a developer-scope 33 kV line on a shorter schedule. Penalties, payment security, deemed generation and curtailment treatment are all still open to market input. A later limited tender may be confined to those who respond now.

8WAPCOS's Rs 1 crore mandate says no pre-bid meeting will be held; GeM scheduled one with a Teams link The GeM field records 10:00 against a description reading 10:30-12:30, validity reads 90 days in one document and 120 in the other, and MSE relaxation is "No" in one and 50% in the other. Basic turnover eligibility starts at Rs 50 lakh while scored turnover starts at Rs 50 crore. Arbitration is expressly waived even though the 1996 Act appears in the same document's regulatory framework.

8AEGCL's Rs 6.72 lakh Narengi consultancy buys PLS CADD tower spotting and states no completion period Two lump-sum items cover bay feasibility and full route survey with profile drawings, with forest proposal and tree enumeration expressly carved out. Corridor width, accuracy tolerances, route alternatives and permitted iterations are undefined. The whole cycle from launch to close runs eight days.

8Tata Power's one-year final-checking agreement for a 765 kV line gives bidders 10 days and no quantities Tower counts, line length, inspection formats, acceptance authority, manpower and reporting protocol are all absent from the notice. So are EMD, PBG, payment cycle, LD and liability caps. For a year-long framework, minimum workload and call-off frequency are the terms that matter, and neither is stated.

8TGTRANSCO's Rs 60.71 crore package keeps negative escalation running after positive escalation stops Delay attributable to the contractor removes upward price protection while leaving downward adjustment enforceable, on top of milestone and post-completion penalties. Section 1.2 deems unlisted but necessary components into bidder supply, closing the variation route. A bid 20% below estimate draws additional security of 10% of the estimated cost by the document's own worked example.

8KPTCL's Rs 108.02 crore Ayyanahalli package deleted its 25% consortium floor after a pre-bid nobody attended The line qualification can now sit entirely with one partner, with a three-year electrical-works test replacing it for the other. The proceedings record nil bidder representatives; the queries that produced the change arrived by email. Underlying kilometre thresholds are unchanged.

8APGENCO reserves the right to amend its metering cubicle tender after its own submission window shuts Bids close at 14:00, technical opening is 15:00, and modifications are permitted up to 15:00. Validity reads 180 days in the NIT and 120 in the attached general conditions, while the covering enquiry gives a third set of times. Manufacturer-site QA inspection is marked "Not Required", moving conformity onto supplier certificates.

8NHPC's Sawalkot Lot-1 added Rs 287.91 crore, deleted a qualification route and moved its deadline eleven times The estimate reset from Rs 5,129.03 crore to Rs 5,416.94 crore carried turnover, working capital and bid capacity up with it, while the quantity-based dam alternative disappeared, leaving only an 80 m concrete dam. Project capacity was corrected from 1856 MW to 1800 MW without explanation. No reason is recorded against any of the 161 days of extensions.

8MPPGCL's 30 MWac solar tender moved its query-response date three times, ending seven days before bids close Responses now land after the deadline they were originally meant to precede, leaving one week to absorb them across engineering, vendor quotes, generation modelling and O&M pricing. Evaluation runs on Rs/kWh combining capex, discounted five-year O&M and accepted NEEGG. Omitted-but-necessary equipment is deemed included and prices stay firm.

8NHPC's Kamala amendment moved HM qualification into execution, then needed an errata to fix the clause it cited The same corrigendum cut muck disposal from four zones to two, removing both sites nearest the dam and leaving two shared 50/50 with the adjacent lot. Adverse climate moved from employer risk "Nil" to EOT, and earthquake gained express compensation. Grid power is tentative at two years out, with captive generation and compulsory later uptake both on the contractor.

8THDC's Kalai-II package moved 216 days and rewrote shotcrete from "no extra payment" to Rs 180 per kg Eight extensions ran alongside two substantive amendments and a notice refusing further queries — followed by another date revision. The 31.5-month clock now starts after a 30-day mobilisation period rather than on the seventh day from LOA. The road tunnel is carved out of the milestone-damage waiver every other milestone enjoys.

8AEGCL's Sonapur extension notice pushes bids to 2026 and schedules the opening for 2023 The same package records an NIT date in the pre-bid minutes that post-dates both the NIT and portal publication. A pre-bid meeting materialised where the portal fields read "NA", drawing nine firms. Prices stay fixed for 24 months and the request for conductor and cable escalation was refused.

8MPMKVVCL narrowed its type-test waiver to one rating and readmitted a disqualified bidder after opening The concession originally covered a new bidder lacking reports for any rating; it now covers only the 10 MVA unit. EMD is Rs 1 lakh against post-award security of 1% plus 9% on a 66-month instrument. A bidder rejected as a medium enterprise returned on the MSME notification preserving previous-category benefits for three years.

8NHPC's Salal award is 8.7% below estimate, or 1.5% above it, depending which estimate applies The benchmark rose 11.1% late in the cycle, taking experience, turnover, working capital and bid capacity up with it after an earlier corrigendum had widened technical eligibility. One of three bidders failed qualification, leaving a two-bid contest 3.4% apart. The NIT provides for reverse auction; the comparative statement shows only two values.

8WBSEDCL cut its retesting charge 90% and drew 188 bids in which L2 sits 44.0% above L1 EMD fell 30.0% and 16.7% across categories at pre-bid, while the charge per repeat inspection went from Rs 50,000 to Rs 5,000. Of 188 bids, 148 cleared technically, many only partially by capacity or transformer type. A bidder removed from the restricted-opening table after a corrigendum resurfaced in the price ranking at L22. Details
 For reference purposes the website carries here the following tenders:
 8Tender for work of annual/routine testing of various equipments installed at 400 kV GIS S/S Details
 8Tender for civil works for construction of 01 No. 63 MVA transformer plinth and related 132/33 kV bay Details
 8Tender for civil maintenance and upkeeping work at various volts transmission sub stations Details
 8Tender for diversion of submerged tower 400 kV line Details
 8Tender for supply of cross patrolling of transmission lines Details
 8Tender for supply of LT three phase channel cross arm and angle cross arm Details
 8Tender for procurement of transformer structure materials double pole Details
 8Tender for procurement LT GI pins Details
 8Tender for providing pile foundation for various tower Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for procurement of spares for SAM make sludge disposal pump model Details
 8Tender for construction work for new proposed 33/11 kV line Details
 8Tender for construction of new borewell at 132 kV GSS Details
 8Tender for construction of civil foundation and other misc civil works in yard for 20/25 MVA Tr At 132 kV GSS Details
 8Tender for construction of civil foundation and other misc civil works in yard Details
 8Tender for levelling and gravelling work of 132 kV switch yard at 132 kV GSS Details
 8Tender for procurement of 220V-600AH lead acid tubular type battery sets Details
 8Tender for procurement of non ferric alum Details
 8Tender for repairing/retrofitting/renovation of raw water pump house Details
 8Tender for supply of CPVC pipe & fittings Details
 8Tender for supply and application of epoxy glass flake coating with UV resistance PU top coat on various external surfaces Details
 8Tender for work of preventive maintenance of various 220 kV switchyard Details
 8Tender for supply of GI coated heavy duty MS grill Details
 8Tender for EPC package for ash handling system package Details
 8Tender for work of RCC revetment/protection wall work at various Details
 8Tender for procurement of furnace oil Details
 8Tender for construction of 132 kV sub-station Details
 8Tender for extension of control room construction of 02 No. 66kV bays Details
 8Tender for supply of wireless LCM kit for 220kV and 66kV class switchyard Details
 8Tender for supply of C&S electric make ACB & panel spares Details
 8Tender for procurement 22 kV, 200A AB switch Details
 8Tender for supply of LT three phase X arm channel Details
 8Tender for supply of T.C.fuse wire 12,14,16 SWG Details
 8Tender for supply of transformer structure materials Details
 8Tender for construction of new 11 kV, LT lines and 11/0.4 kV DTR Details
 8Tender for construction and shifting of existing 33kV/11kV/LT OH/UG lines Details
 8Tender for Re-construction of existing 33 kV UG line Details
 8Tender for construction of new 33 kV line from 33/11 kV DSS Details
 8Design, fabrication, supply, installation, testing, commissioning of on grid solar ground mounted project with net meter and remote monitoring system, capacity of 46 kW Details
 8Design, fabrication, supply, installation, testing, commissioning of on grid solar ground mounted project with net meter and remote monitoring system, capacity of 83 kW Details
 8Design, fabrication, supply, installation, testing, commissioning with RMS of total 156 kW grid connected solar PV power plant Details
 8Tender for supply and erection of 50TR capacity air cooled DX condensing unit for 400kV switchyard Details
 8Tender for supply, retrofit commissioning of 90 kW and above LT air contactor modules (DK21) with LT vacuum contactors Details
 8Tender for supply and replacement of LTG and HTG tubes Details
 8Tender for empanelment of contractors to award a rate contract award RCA for DTR renovation work of 63 KVA, 100 KVA, 200 KVA and 315 KVA substation Details
 8Tender for empanelment of contractors to award a rate contract award RCA for work for aug/conversion of LT line 3x95 Sqmm and 3 X 150sq.mm.XLPE cable Details
 8Tender for augmentation of 33 kV line on H-Beam using ACSR Dog conductor Details
 8Tender for empanelment of contractors to award a rate contract award RCA for work of aug conversion LT cable Details
 8Tender for work of aug of existing 11 kV line to ACSR Dog/Raccoon with 13Mtr H beam/PCC pole Details
 8Tender for procurement of lighting items for power houses Details
 8Tender for annual maintenance work of railway siding for power house Details
 8Tender for supply and running out of ballast for railway maintenance work Details
 8Tender for construction of new hydrogen shed for 1x210 MW unit Details
 8Tender for work contract of transportation of the ash from ash dyke II Details
 8Tender for construction of precast RCC cover and stone Details
 8Tender for procurement of spares of electromagnetic flow meter and SWAS spares installed Details
 8Tender for manufacture, testing, supply, delivery and operational training/ commissioning of three phase transformer turns ratio test sets Details
 8Tender for manufacturing, testing, supply and delivery of 50 Nos. 220V/100AH and 30 Nos.24V/100AH DC distribution boards and 80 Nos. 415V, 11 circuit, AC distribution boards Details
 8Tender for work related to construction and electrification of line and shifting of lines and poles Details
 8Tender for replacement of defective meters Details
 8Tender for maintenance and repair of 11 kV HT/LT line Details
 8Tender for replacement of defective meters Details
 8Tender for work of installation of one (01) No. 12.5 MVA power transformer Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures Details
 8Tender for erection, testing & commissioning work of 66kV equipments, structures, control wiring Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Karamsad Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Borsad Details
 8Tender for procurement of MS pipes 550 NB for replacement Details
 8Tender for thorough interior civil renovation and allied work Details
 8Tender for work of atactic polypropylene APP treatment to arrest leakages Details
 8Tender for supply loading at factory and transportation of LT distribution box Details
 8Tender for supply and delivery of different local materials Details
 8Tender for construction of 1 No 33 kV bay, 2 Nos. 11 kV feeder bay and providing transformer plinth Details
 8Tender for laying of 11kV 3x300sq.mm XLPE UG cable Details
 8Tender for laying of 11kV 3x300sq.mm XLPE UG cable for erection of new 11 kV feeder Details
 8Tender for supply of stay set complete Details
 8Tender for work of providing & fixing of 33kV numerical backup relay with non-directional three phase over current (3 O/C) & earth fault (E/F) protection Details
 8Tender for AMC for CTR make nitrogen injection fire protection system (NIFPS) for ICTs & transformer Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown works & planned maintenance works in various 220/132 kV EHV S/Stn Bhandara Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown works & planned maintenance works in various 220/132 kV EHV S/Stn Details
 8Tender for biennial maintenance contract of replacement of installed smoothing reactor by spare smoothing reactor Details
 8Tender for supply of pressure relay of converter transformer Details
 8Tender for annual maintenance contract (AMC) for the work of attending emergency breakdown work & planned maintenance works in various 220/132kV EHV S/S Details
 8Tender for refilling, servicing & maintenance, supply of spares for fire extinguishers at various substations Details
 8Tender for annual maintenance contract (AMC) for work of underground cables at various Details
 8Tender for attending emergency breakdown work & annual routine maintenance of 220/132/110kV various EHV lines Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Mehsana Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Patan Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Himatnagar Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Chhatral Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Dhansura Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Jamla Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Vijapur Details
 8Design, supply, installation, testing, commissioning with comprehensive maintenance contract of 5 years for solar rooftop projects at Agiyol Details
 8Tender for supply of pre engineering shed Details
 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metalClad draw-outtype VCB panels Details
 8Tender for supply, installation commissioning, & testing of soft starter with major/minor modification in existing panels for various motors Details
 8Tender for supply of assorted size of MS grill for repairing of platform of ash slurry line Details
 8Tender for supply of mill discharge first piece after MPO for coal mill Details
 8Tender for purchase of standard toolkit bag Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 
8Hinduja Renewables Bets On BESS, Pumped Storage To Make Renewables More Dispatchable Details
 
8Maharashtra Floats EOI for 170 MW Floating Solar & BESS Project Details
 
8NVVN Invites EOI for 263 MW Solar Open Access Power Details
 
8ACME Solar Refinances Rs 21.5 Billion Debt for 450 MW Portfolio Details
 
8MNRE Approves INR 258.83 Crore HRD Programme To Strengthen India’s Renewable Energy Workforce Details
 
8Rooftop solar installations soar in India Details
 
8CIL, ArcelorMittal sign MoU to explore syn-gas usage from a coal gasification plant at Paradip Details
 
8DNHDDPCL Invites Bids for 5 MW Rooftop Solar Program Details
 
8India’s small steelmakers could save money and cut emissions with switch to renewable power Details
 
8How India can get its BESS projects right Details
 
8India on e-wheels: There are hardly any electric cars on Srinagar’s roads; here is why Details
 
8H2 Innovation eyes collaboration with universities, government to develop green hydrogen in India Details
 
8Power Ministry Urges States: Accelerate Smart Meter Rollout Details
 
8Dr Jitendra shares in LS India’s Thorium driven indigenous Nuclear strategy Details
 
8Siemens Energy India to attend Motilal Oswal investor meet Details
 
8Gentari Explores Sale of India EV Charging Network With 3,000 Chargers Details
 
8Data Centre Power Boom: Why renewable developers are demanding a Rs 3,000 crore relief package Details
 
8Stocks to Watch: Solar Industries, LG, Tata Motors PV and 7 Other Stocks Announcing Q1 Results Today Details
 
8SJVN Commissions 75 MW Jamui Solar Power Project in Bihar, Expands Renewable Energy Portfolio Details
 
8India’s Solar Surge Highlights 50 GW Power Gap Challenge Details
 
8India's Planned Coal Mining Capacity Hits 638 MTPA Details
 
83 Best-Performing Mutual Funds With High Holdings in NTPC, Adani Power & Tata Power in 2026 Details
 
8Demand aggregation of renewable electricity can cut power costs for India’s secondary steel MSME clusters by 34 percent Details
 
8Bajel Projects Bags Rs 400 Crore Order From Power Grid for 765kV Transmission Line Details
 
8Power sector stocks today, August 12: TD Power Systems jumps 15.87%, Gujarat Industries up 7.40%, Diamond Power rises 4.36% Details
 
8India’s solar power cuts coal use in the day, but evening demand keeps fossil fuel running Details
 
8El Niño drives India's July power demand to a record high: Crisil report Details
 
8India nearly doubles proposed coal mine capacity as global pipeline expands: Report Details
 
8CEA Proposes New 2026 Grid Connectivity Technical Standards For Power Sector Entities Details
 
8How the Indian Railways moves closer to becoming net-zero carbon emitter by 2030 Details
 
You can also click on Newsclips for more Details
8PLI awards and private investment have expanded module capacity much faster than cells, wafers and raw materials. The result is a larger domestic manufacturing base with a narrowing-but still material-upstream dependence. Details
8IRENA expects the solar fleet to expand from 2,383 GW in 2025 to more than 5 TW by 2030 under its 1.5°C scenario. The same build-out could create more than 25 million tonnes of panel waste a year by 2050, while most markets still lack solar-specific end-of-life rules. Details
8Haldia Energy recovered its fixed charges in FY26, but cash conversion is being held back by delayed tariff true-ups and an appealed refund direction. The pressure is visible in debtors of Rs 2,939 crore and leverage close to the rating agency's stated guardrail. Details
8The approved procurement runs from October 2026 to March 2027 and varies by hour and month, rather than providing round-the-clock supply. Bidders cut some offers from Rs 12.99/kWh to Rs 9.98/kWh, but the final tariff still embeds a premium for firm peak-period availability. Details
8The 12 August exchange report shows a seven-fold gap between purchase and sell bids in the real-time market. Clearing at the ceiling does not mean every purchase bid was served; it shows scarce offered volume was absorbed at the maximum permitted price. Details
8The 8 August event involved fire, smoke and oil spillage at the 400/220 kV station, with both interconnecting transformers going out together. The operating record identifies protection and restoration questions, but the final forensic cause is still under investigation. Details
8NRLDC's resource-adequacy study finds that daily or aggregate surpluses can coexist with shortages after solar output fades. Punjab, Delhi, Uttarakhand and Himachal Pradesh also show uncovered periods, while Rajasthan and Haryana did not provide usable data for the study. Details
8The gap between allocation and output is concentrated in clearances, mining leases, land and development work. Even among 23 blocks described as operational, eight had not reached the source's separate producing category at 30 June. Details
8POWERGRID has charged four transformers and a Bikaner line loop-in, but the 682 km Bikaner-III-Neemrana-II corridor remains the schedule driver. The delay limits full Rajasthan renewable-zone evacuation without meaning that the entire scheme is unavailable. Details
8Government data show national scale in rooftop and solar-pump programmes alongside very uneven capacity and beneficiary outcomes. The same tables also mix broad renewable additions with scheme-specific delivery, so the numbers cannot be treated as one programme total. Details
8The regulator accepted post-facto approval because 90% central support and project deadlines were at stake, but warned the utility over procedural lapses. If delayed awards cause grant refusal or conversion to a loan, the resulting cost stays outside the consumer tariff. Details
8The expert committee recommended amended terms of reference for the Basania multipurpose project, not environmental clearance or construction approval. Its energy and irrigation case will now be tested against land, forest and social impacts at appraisal. Details
8Fifty-eight eligible units have requested about Rs 932 crore under a Rs 1,500 crore incentive scheme. The oversubscription signals capacity appetite, but the government will disburse only against eligible investment, commercial production and specified milestones. Details
8KABIL obtained permission for invasive exploration in April and selected a drilling contractor, but final local concurrence remains pending. Feasibility is now scheduled for March 2029, leaving production dependent on exploration results rather than the ownership of five blocks alone. Details
8CESC's Malegaon distribution franchise continues to depend on equity and inter-corporate funding while it invests in the local network. The exposure is measurable, but the rating report does not establish a completed turnaround or a regulator-backed recovery path. Details
8Government contests reports of a major coal-depot fire - but supplies no independent incident record
8Gita Renewable seeks a Rs 200 crore borrowing ceiling - after reporting no quarterly operating revenue
8Monthly averaging preserved frequency-response eligibility - despite zero response in two events
8CERA's open-access refund claim failed on limitation - not on the disputed formula
8Intraday buyers found no sellers on 12 August
8High-price sellers offered 41,078.4 MWh - no buyer entered
8A 101 MW solar developer withdrew its extension case - its Rs 10.10 crore guarantee remains exposed
8SJVN's 75 MW Jamui solar plant entered commercial operation, adding contracted Bihar supply at Rs 2.96/kWh
8JSW and Druk Green's agreement creates a joint-development vehicle for Bhutan's 920 MW Punatsangchhu-III hydro project
8EAC recommended study terms for Gandikota's proposed expansion from 1,000 MW to 1,800 MW, putting the larger design into environmental appraisal
8India completed 4,081 ckm by July, adding part of the 16,554 ckm transmission network planned for FY27
8UPERC opened tariff scrutiny for seven thermal stations totalling 4,190 MW Details
8Western-region outage reports listed 6,646 MW unavailable on 12 August, cutting supply available to western-region grid users
8Yadadri, Vallur and SEPC outages removed 1,825 MW from the southern stack, reducing supply available to Telangana and Tamil Nadu grid users
8Eastern-region outage report listed 4,895 MW unavailable on 12 August, with flood-damaged Teesta III alone withholding 1,200 MW from regional supply
8Southern-region report listed 2,040 MW unavailable on 12 August as valve, emissions-control, fire and fuel-handling failures removed ten units Details
8National grid frequency stayed outside its prescribed band for 6.93 hours on 12 August, extending the control-quality deviation recorded across July
8Northern import interfaces breached transfer limits for 12.75 hours in July, narrowing secure interregional transfer headroom
8Five substations spent 51–78 hours outside voltage bands in July, constraining secure operation at persistent problem points Details
8Fifteen collapsed towers kept the Gadag-Koppal double-circuit line constrained, limiting renewable evacuation until permanent restoration
8Telangana’s reservoir energy fell to 1,047.7 MU from 2,054.3 MU, reducing hydro headroom at the 13 August snapshot
8Assam and Tripura exceeded available transfer capability for 44.2% and 91.2% of 11 August, tightening secure import headroom for both state systems Details
8Maharashtra added 16,176 MW of renewable capacity in three years, enlarging the operating base for its FY30 demand-share target
8PM-KUSUM feeder solarisation is moving farm supply into daytime blocks and locking solar procurement into 25-year PPAs Details
8Lower battery prices expanded India’s first VGF-backed storage programme from 4 GWh to 13.8 GWh without increasing its Rs 3,760 crore budget
8India has awarded 756,100 tonnes a year of green-hydrogen production capacity and 3,000 MW a year of electrolyser manufacturing, establishing the mission’s planned pipeline Details
8Renewable generation missed its day-ahead schedule by 85.19 MU - even as output peaked at 88,958 MW
8Koppal-Gadag grid works missed December 2025 - although several lines and transformers are already charged Details
8Madhya Pradesh allocated 30 commercial coal blocks - only four were producing at 30 June
8Jammu and Kashmir has 3,551.5 MW of hydro under construction - more than the 3,360 MW already operating Details
8APTEL reopened tariff recovery for three Himachal hydro stations - the state can still convert the disputed loans into grants
8EAC recommended study terms for a 240 MW pumped-storage project - 30.241 hectares of forest and a conservation reserve remain in the appraisal
8UPERC escalated smart-meter overcharging after discoms failed to follow refund directions Details
8Purvah agreed to acquire 1,411 MWp of ReNew assets at Rs 4,859 crore enterprise value - closing will require Rs 1,582 crore in cash
8Kalpataru's Rs 66,607 crore order book supports growth - delayed awards and water payments slow conversion
8IRCON's quarterly income rose to Rs 2,042.7 crore - profit fell 44% despite a Rs 23,366 crore order book Details
8KSEB's Rs 65.87 lakh 110 kV upgrade deleted its 5 km experience threshold and took a bid 9.91% below estimate Terms and conditions XVIII required 110 kV work "for at least 5km length of line completed in last 7years"; corrigendum-3 removed the length and applied the change to all clauses stating experience. Three bidders were admitted — L1 Rs 59,34,453.02, L2 16.4% above, L3 26.5% above and rejected on rate. Special condition 18 sets defects liability at 60 months while clauses 1.9, 1.18 and the payment language repeat 36. 

8SECI's 45.6 MW Ramagiri wind package issued Corrigendum-1 nine minutes after queries closed and four hours before the pre-bid meeting Queries shut at 10:00 RTZ on 27 July, the corrigendum is timestamped 10:09, the pre-bid meeting sat at 14:30, and the amendment wording appears nowhere in the record. EMD is Rs 8.4368 crore for domestic and international bidders alike, against a Rs 25,000 processing fee. The tendering pattern reads "Single Stage Two Envelope followed by e-ReverseAuction" while the portal's evaluation-mechanism field reads "Not Applicable". PBG, bid validity, LD and maintenance duration sit outside the notice.

8RECPDCL's ERES-47 765 kV corridor turns a Rs 55.32 crore bid bond into a Rs 138.30 crore guarantee within ten days of LoI A 150% step-up lands on the winner the moment tariff competition ends. Qualification runs Rs 2,766 crore aggregate capex at Rs 553.20 crore per project and Rs 1,106.40 crore net worth. Clause 2.5.7 puts site, geology, transport and grid diligence on the bidder with no relief after deadline, while BSPTCL's Nawada–Guraru works and space at Jeerat stay outside TSP control. Assets, land, ROW and clearances transfer at zero cost 35 years after COD.

8RECPDCL's Solapur/Paranda GIS RFP moved its bid date 34 days and left the rest of Clause 2.7.2 behind Submission goes from 7 July to 10 August, stranding technical opening, qualification, initial offers, reverse auction, LoI and SPV transfer at their original July–August dates. CPG is Rs 30 crore, net worth Rs 250 crore, aggregate capex Rs 600 crore at Rs 120 crore per project. Three LILOs on HPC conductor and a Quad Moose link to Pune West carry a fallback obliging the TSP to buy adjacent land if utility space runs short. LD is 3.33% of monthly charges per day for 60 days then 5%, against a 24-month COD and 98% availability.

8OPTCL's Palaspanga–Barbil package states its estimate as Rs 3.15 crore in the narrative and Rs 315.27 crore in Table-A The smaller figure is exactly one-hundredth of the portal value and identical to the EMD. Table-A items 12–16 run a day behind the portal, while the IFB puts soft copies at 11 August, hard copies at 11 August 11:01 and EMD at 10 August 11:00. Lot-I and Lot-II are labelled separately but "shall be treated as a single contract" — two GIS upgrades plus 1.2 Rkm cable and 69.2 Rkm of 220 kV line. Both inside 24 months from LoA, with e-reverse auction reserved under ITB clause 29.

8NSPCL's Durgapur coal-mill R&M restored 24 mandatory pump assemblies eight days before closing, having cut them to three Amendment No. 2 made the reduction; Amendment No. 4, issued 10 August against an 18 August deadline, restored the original BOQ figure. Amendment No. 3 fixed instrumentation at one instrument for OLCS and two for CLCS and protection. Errata No. 01 corrected the tender ID to 2026_NSPCL_273894_1. The deadline moved 102 days across sixteen corrigenda while the technical baseline was still changing, with eight pulverisers to be replaced inside existing space without disturbing boiler performance.

8PSPCL's Ferozepur RDSS package went to the bidder that was 6.9% dearer before the auction and the only one that quoted in it The BOQ chart had SKS at Rs 84.95 crore against Nucon at Rs 90.84 crore; in the auction Nucon quoted Rs 84.87 crore and SKS was "Not Quoted". Final evaluation records Nucon Rs 83.80 crore at rank 1 and SKS Rs 84.95 crore at rank 2 — 1.4% apart, 31.0% and 32.8% above the Rs 63.97 crore published value. Corrigendum no. 3 reframes the tender from four packages to three and package 5 disappears unexplained. Financial opening was November 2024, final evaluation August 2026.

8RECPDCL's Barmer-II HVDC tender set a Rs 5,728 crore net-worth floor and five bidders cleared it Adani Energy Solutions, DRAIPL-CG Consortium, POWERGRID, Resonia and Terralight qualified; four are sole bidders, the fifth splits 26/74 between DRAIPL and Cube Grid Investments Pte. Ltd. The bid bond is Rs 286.40 crore and the CPG Rs 716 crore, due within ten days of LoI alongside full SPV acquisition. Scope covers two 6,000 MW ±800 kV LCC terminals, roughly 900 km of bipole and two synchronous condensers. Bipole-1 targets 48 months and Bipole-2 54, but the RFP requires simultaneous commissioning.

8BSUL's Rs 379.25 crore Jalaun evacuation package states EMD as Rs 3.80 crore in the NIT and Rs 38 lakh on the portal The tender ID shifts the same way, 913540_1 in the scanned NIT and Corrigendum-1 against 913570_1 across the CPPP record, clarification, Corrigendum-4 and opening report. Corrigendum-1 widened ITB 2.2.1 from "Sub-Station and/or Transmission line works" to "Sub-Station or any other electrical works" while holding the Rs 303.40/189.62/151.70 crore thresholds and the two 220 kV-plus bay test. SCC 3 keeps LD at 0.5% of total contract price per week where partial facilities cannot be beneficially used; SCC 3.1 and 4.0 read "Deleted" with substantive O&M text beneath, and the trial run reads "72 (Seventy-two) 24 (Twenty Four) hours continuously". Ten bidders were admitted on 10 August with the PGCIL Orai bay extension inside the contractor's scope.

8BHEL lets Talabira bidders borrow the ash-handling credentials they lack, then bills the prime bidder if a partner walks Vacuum conveying can substitute for pressure conveying where detailed engineering is vetted by an IIT or qualifying firm; missing water-impounded bottom-ash-hopper experience can be bridged by a design agency plus a performance-support undertaking; civil and structural gaps go to consortium partners. Clause 23.10 keeps the prime bidder accountable throughout. Clause 23.12 permits encashment of a departing partner's security, mandates replacement, and otherwise recovers the cost difference plus a 5% overhead factor. Clause 23.15 adds 1% consortium security, with reverse auction under clause 19.0 after technical qualification. Details
 For reference purposes the website carries here the following tenders:
 8Tender for work of supply, installation, testing and commissioning (SITC) of intelligent addressable hot redundancy based continuously available Details
 8Tender for supply of 36kV copper XLPE power cable Details
 8Tender for erection of new 132/33kV 40MVA T/F Details
 8Tender for construction of 2x40 MVA 132/33kV S/S Shahjahanpur Details
 8Tender for construction of 2x40 MVA 132/33kV S/S Details
 8Tender for construction of 2x63 MVA 132/33kV S/S Details
 8Tender for SITC of numerical line differential cum distance protection relay Details
 8Tender for work of PID testing of various tower various 132 kV, 220 kV & 400 kV lines Details
 8Tender for augmentation by replacement of existing 2x100MVA, 220/132kV ICTs by 2x200MVA, 220/132kV ICTs Details
 8Tender for AMC for repair/ service/ overhauling/problem attending of compressor of 245/145 kV circuit breaker at various Details
 8Tender for construction of LILO on 100kV line Details
 8Tender for repair maintenance of Two nos. 33kV, 10MVA transformer installed Details
 8Tender for providing fixing of negative sequence relay, over current earth fault relay Details
 8Tender for electrical works Details
 8Tender for supply and completion of HT straight through cable joints Details
 8Tender for re-organization and installation of 3.3kV overhead line and LT overhead line Details
 8Tender for replacement of 250KW, 6.6kV, HT motor of 20 no pump Details
 8Tender for dismantling, shifting of HT OH line Details
 8Tender for installation of Acs with accessories and installation of 30 nos. of streetlights Details
 8Tender for replacement of damaged GI sheets and various Details
 8Tender for making 02 Nos foundation and ramp for shifting of existing 100MT weigh bridges Details
 8Tender for replacement of old GI sheet on roof with profile sheet and misc. repair work Details
 8Tender for construction of control room foundations, cable trench Details
 8Tender for renovation of yard light works Details
 8Tender for repair of submersible pump for various 33kV S/S Details
 8Tender for renovation of control room and misc. civil works at 33kV S/S Details
 8Tender for renovation of sanitary, electric yard levelling gravelling work Details
 8Tender for suppy of P/F FRP fencing for RMU, transformer Details
 8Tender for construction of prestressed precast and brick masonry Details
 8Tender for work contract for work of lifting and disposal of used thermal insulation material Details
 8Tender for work contract for availing OEM supervisory services for complete overhauling along with commissioning of 6.6 kV, 360 KW glandless boiler Details
 8Tender for procurement of 250 NB and 300 NB sleeve type expansion joint for installation in pressure conveying line Details
 8Tender for construction of new 11 kV, LT lines and 11/0.4 kV DTR Details
 8Tender for miscellaneous civil work Details
 8Tender for replacement of flame proof (FLP) lighting distribution boards (LDBs) at various Details
 8Tender for construction of box culverts Details
 8Tender for rectification works for structural and civil defects in C-Row Details
 8Tender for job contract for removal of brick partition wall and extension of stage-1HT switchgear Details
 8Tender for civil works of construction of culvert and other necessary repair work Details
 8Tender for supply and retrofitting of 400 kV SF6 circuit breakers Details
 8Tender for work of erection, testing and commissioning of new FOAC cable in existing 66kV UG line network Details
 8Tender for work of erection-dismantling of 66kV/11kV equipment’s, structures, control wiring Details
 8Tender for work of complete servicing/ overhauling/ defect attending of various hoists and cranes Details
 8Tender for work of penthouse /APH centre section sealing for the unit Details
 8Tender for supply of liquor ammonia 25 % (AR grade) for boiler water treatment Details
 8Tender for EPC package for ash handling system Details
 8Tender for framework agreement for various industrial operations Details
 8Design, engineering, manufacture, supply, erection, testing & commissioning of 6.6 kV indoor metalclad draw-out type VCB panels Details
 8Tender for renovation of power house Details
 8Tender for shifting of electrical utilities in connection Details
 8Tender for interlinking of 11kV feeder Details
 8Tender for supply, erection & commissioning of 11 kV lines with MVCC conductor & dismantling of existing open conductor 11 kV lines Details
 8Tender for works contract for replacement of existing overhead bare conductor Details
 8Tender for works contract for replacement of existing overhead bare conductor ACSR 7 4.09 mm, AAAC 7 3.15 mm and AAAC 7 2.59 mm by XLPE coated covered conductor Details
 8Tender for turnkey construction of one no. of 33kV feeder bay and associated works at 220/132kV GSS Details
 8Tender for conversion of 11 kV feeder Details
 8Tender for refurbishment of coal burner nozzles and tips of 2x270 MW units Details
 8Design, manufacture, testing, supply and delivery of 162 nos. 66kV, 39 nos. 132kV and 63 nos. 220kV SF-6 circuit breakers Details
 8Tender for creation of new control room at 132kV S/stn Details
 8Tender for casting of machine pressed solid Details
 8Tender for work of annual rate contract for attending on site minor repairs / maintenance works / OLTC overhauling of EHV class power transformers / ICTs Details
 8Tender for laying of three single core 11kV XLPE 185 sq.mm. cable on elevated PSC structure Details
 8Tender for laying of three single core 11kV XLPE 185 sq.mm. cable Details
 8Tender for supply of BWSR spares Details
 8Tender for providing PVC coated chain link fencing Details
 8Tender for erection of 66 kV line Details
 8Tender for replacement of acid and alkali resistant tiles in DM plant Details
 8Tender for procurement of complete assembly of gear box model Details
 8Tender for procurement of M/s coupling and its spiders installed Details
 8Tender for rate contract for maintenance of AC machines Details
 8Tender for service contract for online leak sealing job as and when required Details
 8Tender for biennial contract of the job operation of gate valve for smoothly distributing Details
 8Tender for supply of vertically operated 11kV gang operated air breaker switch Details
 8Tender for works contract for carrying out HT LT DCW, improvement and capital extension works Details
 8Tender for works contract for stores handling works Details
 8Tender for procurement of MS bolt nut Details
 8Tender for provide services for installation of solar meter along Details
 8Tender for work of overhauling of 132KV/220 kV CB poles and mechanism of with required spares Details
 8Tender for work of two-year rate contract for the work of cold line washing of insulator strings of various Details
 8Tender for supply, installation & commissioning of neutral grounding reactor (NGR) for power transformer Details
 8Tender for work of providing & applying of high insulation resistance compound coating having Di-electric strength Details
 8Tender for annual maintenance contract for the work of attending emergency, break down and maintenance work of 220kV, 132kV lines Details
 8Tender for supply of equipments/ material, erection, testing and commissioning for the work augmentation by providing additional 1 x 50MVA, 132- 110/33 kV T/F along Details
 8Tender for supply of various CDS tubes and bend for drain & vent line Details
 8Tender for conductor replacement with hardware & SRI of 66kV tower line Details
 8Tender for loading & unloading of material and transformer Details
 8Tender for erection, maintenance and dismantling work of overhead HT/LT line Details
 8Tender for supply of spare for bosch make loudophone at switchyard Details
 8Tender for work of rubber lining of various equipments, pipes and fittings Details
 8Work of repairing of various pulleys of conveyor belts Details
 8Tender for biennial work contract for maintenance of ash handling plant Details
 8Tender for various maintenance works of wagon tippler Details
 8Tender for work of carry out corrosive test of various MS structure of coal handling plant Details
 8Tender for supply of control panel spares of pump house Details
 8Tender for work of misc pressure part related activity of boiler stage Details
 8Tender for work for dismantling, design & supply, installation and commissioning of GI duct and air filter assembly with supporting structure Details
 8Tender for rate contract for routine, preventive & breakdown maintenance of TPS lighting system, fans etc Details
 8Tender for work of replacement of various spares of drive system of wagon tippler Details
 8Tender for supply of various ratings LT motor Details
 8Tender for supply of various boiler tubes bends Details
 8Tender for carting of 11,500 Nos. of 8 meter PSC poles Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following newsclips:
 8How India seeks to translate its offshore wind potential into large-scale deployment Details
 8Coal India Weighs Buyout of Wealth Minerals' Chilean Lithium Unit Details
 8Five decades of research leads to solar PV’s emergence as the world’s dominant energy source Details
 8Look beyond solar, draw up roadmap for all renewable energy sectors: House panel to MNRE Details
 8Powering the Next Generation of Commercial Rooftops: Hoymiles MIT-5000-8T Takes Centre Stage in Hyderabad Solar Project Details
 8Beyond modules: Why cell manufacturing will shape India’s next solar growth story Details
 8ReNew Sells Solar Assets for Rs 4,859 Crore Details
 8Sodium-Ion Battery Prototypes Reach 200 Wh/kg Milestone Details
 8India Strengthens Energy Storage Framework With INR 5,400 Crore VGF And Transmission Incentives Details
 8India’s solar revolution lights the path to a Viksit Bharat Details
 8India's Delhi faces rising night-time power peaks: report Details
 8India awards 1 GW of round-the-clock renewables at competitive tariff Details
 8Electricity Demand Expected To Rise Up to 7.5% In FY27 Amid Higher Heat, Rainfall Deficit: Crisil Details
 8Huf India Commissions 1 MW Rooftop Solar Project in Pune Details
 8India’s Coal Imports For Power Blending Fall 71.5% In Two Years: Govt Details
 8India Accelerates Power Distribution Digitalization With Smart Meters And Grid Modernization Details
 8Global Renewable Energy Capacity Hits 5.2 TW Milestone Details
 8Lloyds Metals Secures 66 MW Renewable Power via Gentari Deal Details
 8UP to resume smart meter rollout after consumer awareness drive: State Power Minister Details
 8Cummins India Q1 FY27: Revenue rises 18%, data centers drive power gen growth Details
 8Shadows Over Green Energy Details
 8Porter Marks 10,000th Electric Truck Deployment in Delhi Details
 8Why India Had To Open Its Nuclear Power Sector Details
 8NLC India Renewables Bags SECI Letter of Award for 200 MW Wind Power Project in Karnataka Details
 8India's Draft National Electricity Policy 2026: Key proposals explained Details
 8HCC secures contract of around Rs 524 crore from State-run NHPC in Jammu and Kashmir Details
 8Jakson Infra Wins Rs 128 Crore Power Project in Karnataka Details
 8Hindustan Construction Company Wins Rs 524.17 Crore NHPC Order for Salal Hydro Project in J&K Details

 
You can also click on Newsclips for more Details
8SCADA, IT/OT and smart-distribution work now reaches 28 states and 45 utilities, alongside 19.79 crore sanctioned consumer meters.
Only Rs 23.36 crore of a Rs 100.9 crore training allocation had been used by July, leaving operational capability as the counterweight.
Details
8BRPL, BYPL and TPDDL may recover total FPPAS of 17.94%, 17.43% and 18.50% respectively for June 2026.
The order is a one-month regulatory relaxation; it does not remove the normal ceiling or convert unallowed claims into approved revenue.
Details
8The 1,980 MW station’s tariff case remains open while NTPC supplies package-level escalation and audited cost reconciliation.
Beneficiaries can face fixed-charge consequences only after the regulator decides which expenditure is prudent and attributable.
Details
8The government plans 139 first-mile projects by FY30 and eight railway schemes, within a logistics plan covering 33 critical rail projects.
Domestic production and dispatch both fell provisionally in FY26, so planned handling capacity has not yet become higher delivered volume.
Details
8The dedicated plant’s annual supply to Bangladesh increased from 155.55 MU in FY23 to 9,131 MU in FY26.
India also exported to Nepal, Bhutan and Myanmar, but APJL’s exclusive contract is distinct from domestic central-station allocation.
Details
8The state has Rs 10,391 crore of loss-reduction work and Rs 4,112.43 crore of smart metering sanctioned under RDSS.
Consumer-meter installation is substantial, while transformer meters, disaster-resilient works and grant release remain incomplete.
Details
8The government counts 22.6 million tonnes a year as operating or under implementation and expects a new Rs 37,500 crore scheme to support about 75 million tonnes more.
Eight projects have been approved under the earlier Rs 8,500 crore scheme, but only Rs 235.52 crore had been disbursed and commissioning remains the decisive test.
Details
8Imports for blending at domestic coal-based plants fell from 23.9 million tonnes in FY24 to 6.8 million tonnes in FY26.
Coal India also held 122.46 million tonnes in March, yet imported-coal plants and technically necessary blending remain outside a simple substitution claim.
Details
8National supply met the May 2026 peak in full, while the official FY27 forecast rises to 289 GW.
Thermal generation still supplied 68.3% to 72.7% from April to June, and the remaining gaps were attributed mainly to state-network constraints.
Details
8The regulator approved a Rs 479.24 crore revenue gap but allowed only Rs 117.77 crore against the FY27 tariff after calculating that full recovery would require a 42.82% average increase.
It paired partial recovery with smart-meter consent, billing-resolution and grievance directions, protecting consumers now while retaining future financial obligations.
Details
8Projects across conventional hydro and pumped storage remain untaken up even after appraisal, with some concurrences or environmental approvals already expired.
The clearance-pending category alone includes 14,649 MW in the CEA table, showing how a project pipeline can remain large without becoming executable capacity.
Details
8One case covers 1,200 MW of firm dispatchable renewable supply; the other covers 600 MW of inter-state wind projects selected through separate bidding.
For the firm and dispatchable procurement, HPSEB has sought state approval for the contracted power but had not executed its power-sale agreement at the hearing.
Details
8The state distributor’s petition says the project must be commissioned within 18 months of the storage-purchase agreement and that land and connectivity will be provided.
Public comments are due before the September hearing, so the discovered tariff and contractual allocation still require regulatory adoption.
Details
8The Centre says Odisha’s utilities are ineligible because RDSS financial assistance is limited to state-owned distributors and power departments.
It also says no formal Rs 10,000 crore special power-package proposal was submitted after Cyclone Yaas, separating the state’s actual RDSS request from the larger claimed package.
Details
8The Centre says funding is linked to physical and financial progress and vendor checks are built into standard bidding documents.
The monitoring chain reaches from state committees to PFC, REC and the Union power secretary, yet billing redress and meter mode remain with utilities and state regulators.
Details
8Uttar Pradesh moves its draft Grid Code hearing by one day - objections still close on the earlier timetable
8Gas stations flag a low-frequency threshold mismatch - compensation remains under regulatory review
8Secure meter-data software slows regional accounting - manual handling is still filling the processing gap
8Genus meter decryption produces conversion defects - corrected files are still awaited
8DSM defaults trigger letter-of-credit scrutiny - security compliance has not cured the pool’s unpaid balance
8Unreturned reconciliation statements are being deemed accepted - administrative closure does not create fresh cash
8NP Kunta’s STATCOM needs an SMPS upgrade - reliability work requires a planned equipment shutdown
8Hyderabad substation’s automation migration needs 400 kV outages - modernisation temporarily narrows network availability
8Talcher - Kolar HVDC Pole 1 seeks an eight-hour shutdown - refurbishment inspection still awaits outage clearance
8India’s demand forecast error moved across 7 - 9 August - three daily readings do not establish model performance
8Intraday auction reports expose bids, clearing and schedules block by block - the latest sheet is a market snapshot
8WCL still carries compassionate-appointment applications from earlier years - the source confirms backlog, not a clean total
8Odisha’s closed coal mines face an unfinished reclamation question - completion evidence is not established
8Fatehgarh - Bhadla lenders may take security over the transmission asset - a licence transfer still needs prior approval
8Tadas Wind challenges where DSM charges are computed - the interconnection point could change the bill
8SGPL presses a Haryana energy-charge claim - the hearing record does not award the money
8Osmanabad Solar seeks Rs 3.42 crore in DSM dues - the hearing was deferred before the merits were reached
8TPTCL’s withheld-dues dispute returns to jurisdiction - the Commission wants arguments before deciding the claim
8Teesta Low Dam IV’s tariff case reaches the order stage - additional capital claims remain under scrutiny
8MEL’s transmission-licence process draws a compliance warning - proposed approval is not yet unconditional
8Solarcraft seeks more time after bay-sharing delays - missing guidelines do not automatically extend connectivity
8Kreate’s banking claim against SPTPL meets a denial of monetary liability - updated claims still need adjudication
8UGVCL’s accident register records fatal network incidents - responsibility remains case-specific
8UGVCL tracks complaints received, resolved and pending - the extracted register does not yield a reliable aggregate
8UGVCL records transformer failures and restoration complaints - a verified failure-rate figure is missing
8UGVCL’s reliability register contains outage indices - the source slice cannot support a performance ranking
8Faulty-meter replacement remains in UGVCL’s operating records - the backlog needs a clean count
8UGVCL reports no standards-of-performance compensation in the selected table - nil claims require an audit trail
8UGVCL records unauthorised-use and theft enforcement - mixed source rows prevent a verified total
8Reserve-shutdown fuel-oil compensation needs a calculation rule - eligibility alone does not fix the quantity
8Faulty special-energy meters remain unreplaced after earlier meetings - delay keeps commercial disputes alive
8Radhanesda’s meter failure produced a Rs 17.83 lakh DSM revision claim - the account still needs correction
8RDSS funds workforce training for digital distribution - utilisation must match the technology rollout
8Grid-security readings were mostly compliant at Agra but weaker at Ajmer - one report cannot grade the corridor
8Western-region outages and line states changed on 10 August - the operating list is not an adequacy forecast
8The Centre retains 15% of central-station power as unallocated - states compete within the remaining allocation rules
8Chhattisgarh’s mining funds must favour high-priority services - allocation rules do not prove local delivery
8NLC’s TPS-I Expansion true-up accepts an 8.5% auxiliary-consumption norm - the wider tariff still rests on reconciled costs
8Vindhyachal Stage I seeks tariff and life-extension capital - the rules may prevent double recovery
8NLC TPS-II’s additional-capital claim contains a cash-basis mismatch - reconciliation must precede the order Details
8NTPC wants station-transformer loads explicitly counted at Vindhyachal and Korba - only export apportionment would change under its proposal
8Legacy and current power-pool deficits are still holding back disbursement - collections received do not eliminate the unpaid tail
8Municipal bonds raise Rs 6,540.44 crore across 23 cities - green issuance does not prove project delivery
8NTPC Lara has settled rehabilitation claims for most affected families - jobs remain conditional on vacancies and suitability
8Ashoknagar’s petroleum lease has been extended twice - commercial oil and gas production still has not begun
8Electrical installations may use five-year inspection or self-certification cycles - digital reporting must keep the option auditable
8Public EV-charging use rises 39% in FY26 - four states dominate the national total
8Telangana’s station-wise generation moved through July - the monthly sheet reveals unit performance but not the cause of every change Details
8Andaman solar and storage operators seek must-run compensation - deemed generation still needs a contractual basis
8ReNew seeks protection against a bank-guarantee call - the dispute has not erased the underlying obligation
8Sarda seeks tax and open-access reimbursement for 100 MW - contract allocation will decide who pays
8NTPC Renewable and SECI dispute a scheduled-completion extension - delay relief depends on the cause and notice record
8APPCPL’s banking claim meets SPTPL’s insolvency moratorium - recovery rights now collide with bankruptcy protection
8SEIL challenges coal-freight deductions - the dispute turns on whether transport was recoverable or already priced in
8Tamil Nadu’s Ombudsman protects the existing tariff for qualifying small extensions - separate construction can still trigger Tariff VI Details
8Assam is included in plans for 200 MWh of battery storage - but no state capacity has yet been allocated
8Nathpa Jhakri seeks recovery for hydrology shortfall - the case turns on evidence that water, not operation, caused the loss
8Kynshi and other hydro DPRs return for revision - redesign may improve viability but delays appraisal Details
8India Energy Stack pilots begin in five utility markets - the national power-data architecture is still unproved
8RDSS pushes distribution utilities deeper into digital operations - installation counts still do not prove better service
8Private discoms report longer supply and lower losses than state utilities - but averages conceal company gaps Details
8Amara Raja’s new-energy sales grow by more than 50% - but exports and factory execution pull in opposite directions
8Jagdambey Hydro retains fixed-tariff visibility - weak generation and one buyer still constrain the credit
8PFC and REC loans survive TANGEDCO’s restructuring - Rs 12,822 crore of annual interest shows the continuing burden Details
 1 2 3 >  Last ›

Showing 1–50 of 207 items