Project Name: Super-Critical Thermal Power Project
8Project Cost: 9000 crores
8Project Description: BHEL is the EPC contractor in a super-critical thermal power project.
8One of the units has been successfully synchronized.
8Erection works are under progress at the BOP area.
8An EPC contract for an FGD system is expected soon.
8What more NITs are expected in the project
8Check out the sub-contractors involved  
Click here for more details for project details and key contacts
Details
For reference purposes the website carries here the following tenders: 
8Supply & Erection of balance works, commissioning and testing of Ash Water Recirculation System Details
8Tender for High pressure water jet cleaning of heat transfer surface of first pass of boiler and clogged APH baskets Details
8Tender for Service contract for OH of APH Details
8Tender for Purchase of 03 Set Duplex Basket Filter System for Power Station Details
8Tender for Work contract for Re-insulation of stator bars Details
8Annual Routine maintenance of Electro- Mechanical & Hydro Mechanical Equipment’s Details
8Supply, erection, testing and commissioning of Energy efficient Vertical Single stage clear water pumps along with motor Details
8Tender for Procurement of Hydraulic Power Pack for Flap Gates in CHP Details
8Tender for Supply of Carbon Brush & Seal Ring Details
8Tender for Work of Supply, erection, testing & commissioning for the work of construction of LILO on 400 KV line Details
8Supply, Erection and commissioning of 01 No. DN 700mm online self cleaning strainer in ACW line Details
8Tender for supply of Sulphuric Acid Details
8Tender for Procurement of Tubes and bends for Hot Re- Heater Coils Details
8Annual Maintenance Contract for Operation and Maintenance of temporary chlorine dosing in C.W. Chlorination Plant Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Megha Engineering enters Limca records for fastest execution of power sub-station Details
8Encouraging neighbours to buy electricity from India: CERC eases power trading norms Details
8Govt notifies phased import duty hike on electric PV parts, lithium-ion cells Details
8NHPC aims to boost capacity to 10 GW by 2022: Chairman Balraj Joshi Details
8Kalpataru Power Transmission Ltd bags orders worth Rs 1,288 crore Details
8IFCI exits 2 power projects, realises Rs 1,174 cr Details
8Will the Centre’s package jumpstart stalled thermal power projects? Details
8Siemens arm picks up 46% stake in Poovani wind power project Details
8NTPC and Power Grid to form pan-India power distribution firm in an equal JV Details
8SHAKTI Scheme: Most power units barred from bidding for coal Details
8SECI to meet solar developers over 7.5-GW tender in Leh & Ladakh Details
8Clouds over solar power target of 100 Gw on inconsistent govt actions Details
8Gujarat likely to provide land for centre’s wind power projects Details
8NHPC eyes stressed 120 Megawatt Jal Power plant in Sikkim Details
8Tariff order may hit sale of stressed power assets Details
8Better-than-expected power tariff policy to give NTPC a boost Details
8KEC International bags Rs 1,323 crore orders for power transmission, railways Details
8L&T bags orders worth Rs 1,000 cr-Rs 2,500 cr from power T&D projects Details
You can also click on Newsclips for more
Details
What will be the levelized cost of electricity going to be in 2020, 2022, 2025 and 2030 from the following sources:
8Ground-Mounted Solar 
8Onshore Wind 
8Pithead Super Critical Coal 
8Non-Pithead Super Critical Coal 
8CPS System Tariff (R/kWh) 
8CTS System Tariff 
8HRES System Tariff 
-- CPS: 175 GW RE by 2022 and then capacity addition according to the NEP
-- CTS: More modest RE trajectory; greater coal additions in the 2020s
-- HRES: Maximize RE by 2030; no new coal beyond the current pipeline
Comment: None of these scenarios include an increase in gas-based generation. This is something gas suppliers will need to ponder upon
Click on Reports for more Details
The Union Government has approved measures to promote the Hydro Power Sector. In this, the large hydropower projects to be declared under the entity of non-solar Renewable Purchase Obligation. Moreover, the debt repayment period for the developers has been increased to 18 years and introducing escalating tariff of 2%. This has created opportunities for the hydropower developers to revive their stalled projects and signing of PPAs with Discoms. One such example for the project is as below:
Project Name:
Greenfield Hydroelectric Power Project
8Project Cost: 3000 crores
8Project Description: A greenfield hydropower project is at the Tendering stage.
8The project was stalled for 8 years, but, as of now, it is back on track.
8PPA with the state Discom is pending.
8All the statuary clearances have been accorded.
Find out the RFQs that are expected
Click here for more details for project details and key contacts
Details
8Project Name: Greenfield Hydroelectric Project
8Project Cost: 500 crores
8Project Description: NEEPCO has been handed over a greenfield hydel power project.
8Check out the latest stage in the project
8A PFR consultant for the site survey activities and grant of TOR is expected soon.
Click here for more details for project details and key contacts
Details
For reference purposes the website carries here the following tenders: 
8Tender for Balance Civil work of Dry Ash System Details
8Supply, Erection, Testing & Commissioning of 33kV Air Insulated Switchyard Details
8Tender for Work of Rectification With Replacement Of Worn Out Components Of Dribble Conveyor Details
8Supply & installation of Automatic Water Level Recorder Details
8Supply, Installation& Commissioning of Level Monitoring System for Automation of Turbine Pit Pumps Details
8Tender for ARC of HP-1003 type Bowl coal mills and Gravimetric R.C. Feeder Details
8Tender for Procurement of flexible insulated copper busbar Details
8Tender for Procurement of Spare Parts of Rotary Breaker for CHP Details
8Supply, Erection, Testing & Commissioning of 02 Nos. 66 kV bays along with equipments Details
8Tender for Annual Running Contract for Operation of Mechanical workshop Details
8Tender for Procurement of Polyelectrolyte required for various power project Details
8Tender for Procurement of Thyristors Details
8Tender for Procurement of Hydrochloric Acid, Caustic Soda Lye and Liquid Chlorine required for various power project Details
8Tender for Work contract for condenser tube replacement Details
8Tender for Procurement of Air washer Assembly, Wetting unit (Economizer hopper) with discharge Fitting for AHP Details
8Tender for Overhauling of Power Transformers Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Tata Power unlikely to agree on lower tariffs for Prayagraj Power Generation Details
8If a firm got a stressed power asset at discount, it must cut tariff: UPERC Details
8Govt cancels sixth, seventh rounds of coal mines auction Details
8Wind loses energy as policy paralysis blows through this renewable sector Details
8Modi slams Cong for 'crippling' power sector, lays foundation stone for 2 power plants in UP, Bihar Details
8Himachal CM hails PM Narendra Modi's boost to hydro-power sector Details
8Tamil Nadu govt gearing to release electric vehicle policy Details
8Power crisis can worsen if water is drawn from Linganamakki dam to Bengaluru: Expert Details
8Cash sops for states to secure land for green power projects Details
8Wind projects exit Gujarat as leasing land gets tougher Details
8RERC relief to renewable projects worth Rs 4000 cr Details
8Maha pushes for green energy on spinning mills’ surplus land Details
You can also click on Newsclips for more
Details
Project Name: Thermal Power Station - Installation of FGD
8Project Cost: 500 crores
8Project Description: GE Power has awarded chimney package for the FGD system in a thermal power project.
8Civil works are under progress
8Find out the RFQs expected
Click here for more details for project details and key contacts
Details
Project Name: Thermal Power Expansion Project
8Project Cost: 6000 crores
8Project Description: BHEL is the EPC contractor for an expansion thermal power project.
8BTG works have been done.
860% of works have been completed at the CHP.
8Get the names of contractors and sub-contractors involved
Find out the RFQs that are left
Click here for more details for project details and key contacts
Details
For reference purposes the website carries here the following tenders: 
8Annual Contract for the work of routine breakdown & capital maintenance work of LT switchgear Details
8Tender for Supply of Transformer Oil Details
8Tender for Laying of tower foundations ,Erection of towers and stringing & sagging of conductor with earth wire Details
8Tender for Up gradation of ABT Management System (including supply of ABT compliant energy meters) Details
8Tender for Supply of Conveyors Rollers Details
8Tender for Fabrication, Repairing work of Roller Coal Mills Details
8Supply of Vera Bar Used in Primary Air Flow Measurement in PA Duct To Coal Mill Details
8Annual contract of Routine, Breakdown and Capital Maintenance work of Roller Coal Mill Details
8Tender for Operation assistance fly ash conveying of ESP passes, APH and Duct Hoppers Details
8Supply of spares for air circuit breakers Details
8Annual running contract (ARC) of TG System/ Equipments Details
8ARC for Desiltation of feeder channels Details
8Tender for Establishment of 132/33kV substation along with transmission line Details
8Tender for Routine mechanical maintenance and lubrication of equipment’s Details
8Tender for R&M and Uprating of Auxiliaries ans related Boiler works Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Govt approves Rs 31,560-cr investments for power projects. Details
8Hartek Group looks for Rs 100 crore funding to fuel growth Details
8Azure Power Wins 300 MW in 1.2 GW ISTS SECI Solar Auction Details
8Cabinet clears nearly Rs 26,000-crore investment for 2 thermal, 1 hydro power projects Details
8Govt nod to Khurja power plant in UP big blow to public health and wealth: Greenpeace India Details
8Discoms cannot evade late payment surcharge Details
8ReNew Power raises $375 mn via green bonds Details
8PM to launch projects worth Rs 65K-cr in Kanpur today Details
8Cabinet approves coal supply to short-term PPAs; Renewable status to hydro plants, Rs 21,000 cr power plants in UP, Bihar Details
8Solar power generation 5.8 per cent costlier with GST: Report Details
8Cabinet approves renewable status for large hydro power projects Details
8Power Minister rules out mega consolidation of power sector PSUs Details
You can also click on Newsclips for more
Details
Project Name: Thermal Power Expansion Project
8Project Cost: 6000 crores
8Project Description: A brownfield thermal power project is running on schedule. Boiler erection works at the main plant are in progress. Also, civil works are under progress at the balance of the plant area.
8The work at the site is being carried out by
 Toshiba JSW Systems Private Limited
 Doosan Power System India Limited
 Bygging India Ltd
 Desein Indure Pvt Ltd
 ABB
 Flsmidth
 Power Mech Projects Ltd
 Chemin C&I Pvt Ltd
 GE Power India
 REC Transmission Projects Company Limited
8Expenditure Approval: Sep/2015
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: Q2:2016
8Completion Date: Q1:2020
Click here for more details for project details and key contacts
Details
8Project Name: Thermal Power Station - Installation of FGD
8Project Cost: 500 crores
8Project Description: Owner along with consultant is evaluating cost estimates for installation of an FGD system in a thermal power project.
8Find out the RFQs expected
8Expenditure Approval: Q3:2018
8RFQ Date: May/2019
8Release Date: May/2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details for project details and key contacts
Details
India's captive power base is large and rapidly expanding.
8The website has used trained mechanical engineers to put together what is India's most extensive captive power knowledge base.
The following details are covered:
8For new projects:
-- Planning to commissioning schedules (multiple tracking from pre-feasibility to commissioning)
-- Milestone events and dates (Capital approval, RFQ dates, release date, start and completion date)
-- Key project developments
-- Project requirements (timing and requirement parameters for key equipment and services)
-- Project contractors and sub-contractors and their requirements
-- Details of key decision makers
-- An easy to use the archiving system
-- Planned and unplanned maintenance
8The facility database covers installed and upcoming industrial facilities where the projects are located, and includes:
-- Primary & Secondary NIC codes
-- Utility matrix
-- Transportation matrix
-- Raw material matrix
-- Technology licensors
-- Design and actual capacity tables
-- Up to 10 key department head contacts
8There are dozens of other details in our database
Get in touch with our marketing department for more Details
The new destination in the energy sector seems to be the off-grid market. 
8There is strong interest in evolving the utility business model beyond electricity service provision for global investors and funding is getting easier. 
8Front end players are experimenting with ‘value-stacking’ add-on services like internet, water, productive appliances, financial products and services, and other retail goods. 
8The point to note is that millions of households that have never had a reliable grid connection are a ‘blank-slate’ opportunity to redefine the utility-customer relationship, and the utility business model altogether.
8A new breed of pure play PAYG players has begun eliciting investor response of late. Heavy duty strategic investors are stepping into this arena
8Is it time for large oil & gas companies wanting to de-risk their emission-heavy investments to begin looking at the newly emerging off-grid segment more carefully than they did before?
Click on Reports for detailed inputs. Details
For reference purposes the website carries here the following tenders: 
8Annual work contract for Routine, Breakdown & Capital Maintenance of Air Preheater Details
8Tender for Implementation of Energy Management System Along with Installation & Commissioning Details
8Tender for Supply of Coal Mill Grinding Elements Details
8Tender for Procurement of Light Weight quick erect Aluminium alloy modular boiler scaffolding system for TPS Details
8Tender for Balance Civil Work for CW Liner and CW Channel in Cooling Tower Area Details
8Tender for Procurement of SS Liner Plates of Turbines Details
8Tender for Design & Construction of single lane steel truss bridge for HEP Details
8Tender for Biennial Maintenance Contract for CHPH Details
8Tender for the work of Distribution of Power Supply from 33/0.44 KV Sub-Station Details
8Tender for Laying of 33kV XLPE UG cable Details
8Tender for Supply of Critical Spare Numerical Protection relays Details
8Supply of field breaker & field flashing contactor for DAVR of hydro generator Details
8Tender for the Work of attending to resolving the Fuse-Off-Call Complaints & LT/HT line Breakdowns Details
8Design, Manufacture ,Testing before dispatch & Delivery of 11KV Air Break switches Details
8Tender for Erection of 11KV Line/LT Line, Augmentation of existing HT/LT Lines & Cables Details
8Tender for Procurement of 6.6 KV HT Motor Details
You can also click on Tenders for more
 For reference purposes the website carries here the following Newsclips:
 
8Cabinet approves GoM's recommendations on stressed power plants Details
 
8Wind power installations will cross 8,000 MW next year: Tulsi Tanti Details
 
8SunSource Energy to Develop a 70MW Open Access Solar Project in Uttar Pradesh Details
 
8NHPC pays Rs526.53 crore interim dividend to government Details
 
8Jharkhand cabinet approves 2.77-acre land for Adani Power Details
 
8PM Modi to launch renewable energy projects worth Rs 9,300 crore in UP Details
 
8NEEPCO handed over 2 hydro power projects in Meghalaya Details
 
8Gujarat: Policy for small scale solar units announced Details
 
8Govt cancels coal auction meant for open market sale Details
 
8Rs 389 crore loans at centre of ED’s probe of Kochhars Details
 
8No takers for Gujarat's 1k-MW solar auction Details
 
8Kerala State Electricity Board seeks regulator’s nod to pay Rs 168 crore Details
 
You can also click on Newsclips for more
Details
For reference purposes the website carries here the following tenders: 
 
8Tender for Procurement of 11kV Grade Aluminum Armoured Power cable Details
 
8Supply, Erection, Commissioning & Testing of 33/11 KV sub-station Details
 
8Tender for Breakdown maintenance of cooling towers and its accessories Details
 
8Tender for Supply of Transformer Oil for Thermal Power station Details
 
8Tender for Work of appointing consultant for preparation of DPR for installation of cooling tower Details
 
8Supply, Erection, Commissioning and Testing of 145KV SF6 Gas Circuit Breaker Details
 
8Annual contract for Routine, Breakdown and Capital Maintenance work of Effluent Treatment Plant Details
 
8Tender for Supply of Power cables Details
 
8Supply, installation and commissioning of geo-technical instruments Details
 
8Annual Maintenance Contract for Conveyor Belt Maintenance job at CHP Details
 
8Annual Rate Contract for Coal Mill Overhauling of Pulveriser Details
 
8Annual Rate Contract for Maintenance of Ball tube Mills & Gravimetric feeder Details
 
8Design, Engineering, Supply, Erection & Commissioning of Complete Chlorine dioxide Details
 
8Tender for Balance work of 01 no. of 132kV end /line bay Details
 
8Tender for Works Contract for the work of Providing & Applying of High Voltage Insulation Resistance Coating Details
 
You can also click on Tenders for more
 
For reference purposes the website carries here the following Newsclips:
 
8Power projects in Uttar Pradesh, Bihar may get govt nod ahead of Elections 2019 Details
 
8Supreme Court to start hearing plea against RBI Feb 12 circular from today Details
 
8These states giving cheaper electricity to consumers despite missing UDAY targets Details
 
8GMR doesn't account for Chhattisgarh power plant's Rs 2,250 cr diminution, defends move Details
 
8Banks risk adding $25 billion in power sector NPAs on Supreme Court decision Details
 
8Two 660 MW units at Maharashtra's Koradi Thermal Power Station get cabinet nod Details
 
8TERI signs MoU with WAPCOS on power, water, and infra Details
 
8Discom dues to power generators grow 33% during April-January Details
 
8GE's CEO warns of negative industrial cash flow in 2019, shares drop Details
 
8Power demand in Telangana touches 10,505 MW Details
 
8Arbitration Charge: NTPC to explore ‘statutory remedies’ Details
 
8Average spot power price dips 4 per cent to Rs 3.08 per unit in Feb Details
 
8Chandigarh seeks report on steps taken to meet summer power supply demand Details
 
You can also click on Newsclips for more Details
8Project Name: Greenfield Pumped Storage Project
8Project Cost: 6000 crores
8Project Description: WAPCOS is carrying out site survey activities for a 1000 MW pumped-storage hydropower project. PFR has been approved by the Ministry of Water Resources. DPR works are expected to complete by mid-2020.
8Expenditure Approval: Q4:2018
8RFQ Date: May/2019
8Release Date: May/2019
8Start Date: 2021
8Completion Date: 2025
Click here for more details for project details and key contacts
Details
Project Name: Hydroelectric Power Plant: RM&LE Project
8Project Cost: 300 crores
8Project Description: A DPR report is getting prepared for a renovation, modernization, and up-gradation of a hydropower project. A German financial agency has been withdrawn for the funding. Owner is in now look-out for a new funding agency. An EPC turnkey contractor bid is also ahead.
8Expenditure Approval: Q2:2019
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details for project details and key contacts
Details
For reference purposes the website carries here the following tenders: 
8Tender for the works for the FGD system equipment and accessories Details
8Annual Rate Contract for Preventive/ Routine/ Breakdown maintenance of 220kV Switchyard Details
8Tender for Work of Erection & Dismantling of Cup-lock Scaffolding & Hydro-Jetting in First Pass of Boiler Details
8Design, Supply, Installation & commissioning of high Performance Energy chain system for coal mill crane Details
8Tender for Operation and Routine maintenance of Recovery water system (Mechanical & Electrical Portions) Details
8Tender for Supply of LT Mini Pillar boxes with tripping facility Details
8Tender for AMC for Mechanical maintenance work at various Power Houses Details
8Tender for Electrical & Instrumentation maintenance work at various Power Houses Details
8Tender for Running Maintenance of Ball Tube Mills, Gravimetric Feeders etc Details
8Tender for routine maintenance works, replacement of journal head liner assembly & Stop bolt and stop bolt bush in the Mill and Feeder components Details
8Tender for Procurement of Spares for safety valves of boiler drum, super heater and CRH Details
8Tender for Procurement of various mill spares of XRP-803 and HP-803 bowl mills Details
8Tender for Annual job Contract for Electrical Maintenance Details
8Design, manufacture, supply & delivery of 415V, 3 Phase with Neutral LT AC Reserve, Station & Unit Auxiliary Boards Details
8Tender for Supply of 11 KV Grade HT AB Cable Details
8Design, Engineering, Supply, Erection, Testing and Commissioning of Communicable Type Fault Passage Indicator Details
8Tender for Performing work of day to day / routine Electrical Maintenance of generating units and their auxiliaries Details
8Tender for Balance work of LILO on 220kV Line Details
8Design, supply, installation, commissioning and operation of the MBBR technology STP Details
8AMC of Preventive and Breakdown Maintenance of Compressors Details
8Design, Engineering, Manufacture, Supply, Installation, Erection, Testing and Commissioning of FGD Package Details
8Tender for Triennial contract of Boiler, Turbine & Auxiliaries and off site Equipments Details
8Supply, Installation, Testing and Commissioning of Solar System Details
8Tender for Electrical maintenance of 400kV/132kV Switchyard Transformers Details
8Tender for Procurement of Economizer Middle Bank Pairs Coil Assemble Details
8Tender for Procurement of Mill Spares Details
8Design, Supply, Erection & Commissioning of Chlorine dioxide Details
8Tender for Supply of Valves Details
8Annual contract for routine/breakdown & annual maintenance of Boiler, Turbine, Generator & auxiliaries Details
8Tender for Maintenance of Motors Details
8Design, Engineering, Manufacture, Supply, Installation, Erection, Testing and Commissioning of 400kV Bus Reactor Bay Details
8Tender for Supply & Installation of Flue Gas Desulphurisation (FGD) and Auxiliary System Details
8Tender for Procurement of various size of protection shields & cassette baffles for boiler Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Uttar Pradesh to get 40 paise/unit cheaper power from plant Details
8Coal India's supplies to power sector up by 7.1% in April-February Details
8Electricity supply by private producers suffers a jolt in Gujarat Details
8After a decade of slump, investment in coal power may rebound, courtesy MP Details
8Centre clears Rs 14,000 crore Adani SEZ project in Jharkhand Details
8Piyush Goyal dedicates to nation 1,000-MW thermal power project of NTPL Details
8Adani forays into solar panel retailing Details
8Coal plants now have sufficient fuel stocks to generate electricity: Piyush Goyal Details
8High costs of power purchase stifle Discoms across country Details
8India projected to be on track to achieve Paris climate agreement target: US expert Details
8Gujarat’s green energy policy will lead to land hoarding, fear small firms Details
8APERC move to reduce PPA duration worries green energy companies Details
8Central Bank puts Bhushan Power, Essar Steel accounts up for sale to recover bad loan dues Details
8Centre seeks report on electric vehicle charging stations in Chandigarh Details
8 NGT orders study for revamp of power plant in Chembur Details
8Rajasthan 750 Mw solar auction: Five firms to invest Rs 3,000 crore Details
8Nashik Thermal Power Station to begin water conservation programme Details
8Mahagenco to install two coal-fired power plants of 1,320 Mw capacity Details
8In a first, Delhi Cabinet approves rolling out 1,000 electric buses Details
You can also click on Newsclips for more
Details
For reference purposes the website carries here the following tenders: 
8Tender for Supply of Control & Relay Panels Details
8Tender for Procurement of Spares of Mill XRP-623 Details
8Tender for Procurement of 200NB MS ERW Pipes Details
8Supply, Erection, Testing & Commissioning of LT AC Unit Auxiliary Boards Details
8Tender for Procurement of Basket for PAPH Details
8Tender for Procurement of Mill Discharge Valve Assy Details
8Supply, Installation & commissioning of grid connected Rooftop Solar Photo voltaic system Details
8Tender for Supply of Breaker Timing and CB Analyser Details
8Tender for Procurement of 450 NB MS ERW pipe for replacement of ash slurry disposal pipeline Details
8Tender for supply of LT XLPE Cable Details
8Tender for Laying, Testing and Commissioning of 11kV XLPE Aluminium UG Cable Details
8Tender for Construction of 11kV UG Cable Details
8Tender for Work of revamping & repairing of worn out components of Mechanical Conveyor installed at Coal Handling Plant Details
8Supply for Up-gradation of GE make series 90-30 PLC of belt conveyor system of CHP Details
8Tender for Procurement of Forney Flame Scanners Details
8Tender for Starter Ash Dyke Package Details
You can also click on Tenders for more|
For reference purposes the website carries here the following Newsclips:
8Cabinet approves Rs 1236 crore investment for Arun-3 hydro project Details
8Maharashtra: Onus fully on Adani Power to use fly ash generated from Tiroda plant Details
8Private power firms seek urgent settlement of state-run discoms’ dues Details
8Power tariffs slashed in Chhattisgarh, domestic consumers to benefit Details
8States seek Centre’s funds to meet environmental norms for thermal power plants Details
8India's solar capacity addition down 15.5% at 8.2 GW in 2018 Details
8Private equity firm Ardian invests 300 mn euros in Swedish wind project Details
8EverSource, NIIF buy stake in Ayana Renewable for $330 million Details
8Chandigarh: CREST submits plans to achieve solar panel target Details
8ABB reports forecast-beating Q4 profit as robotics shines Details
8Months of coal stock deficit ends as power plants report healthy volumes Details
8Tamil Nadu asks Centre for more coal Details
You can also click on Newsclips for more
Details
 < 1 2

Showing 51–69 of 69 items