All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


May 2025

Explore the implications of a petition seeking to review a decision on direct power purchase agreements.
8Understand how this might set a precedent for future short-term energy procurement strategies in India.
Click on Details for more
Details
The tribunal's decision delineates the boundaries of what constitutes a Change in Law event under PPAs.
8Clarity on the timing and nature of regulatory changes is crucial for stakeholders navigating compensation claims.
Click on Details for more
Details
The tribunal confirmed that revisions in coal surface transportation charges do not qualify as Change in Law events.
8This decision clarifies and narrows the scope for compensation under existing power agreements.
Click on Details for more
Details
Rattan India's claims for compensation under new fly ash transportation regulations were deemed premature.
8The tribunal highlighted the necessity for incurred expenses as a condition for compensation, setting a precedent for future claims.
Click on Details for more
Details
The Central Transmission Utility's endorsement nudges the NERGS-I project towards a transmission license.
8Delve into the regulatory nuances and what this means for the region's energy infrastructure.
Click on Details for more
Details
8In the latest Indian power sector news, a fiercely competitive thermal power plant tender saw the top two bids separated by under Rs. 40 crore
8Meanwhile, PSU heavyweight BHEL submitted a bid nearly twice that of its competitors, sparking discussions on Indian power sector reforms, EPC contracts strategy, and cost considerations
8Our detailed analysis reveals the driving factors behind such divergent cost assumptions and what it signals for future thermal and renewable energy tenders in India
Click on Details for more Details
In a significant move, UPCL has petitioned for the cancellation of KEIPL's trading license due to chronic non-payment issues.
8This action highlights the enforcement challenges in India's power trading landscape and the regulatory body's pivotal role in maintaining market integrity.
Click on Details for more Details
In a landmark case, CERC must assess if Adani Power's supply route justifies exemption from state charges.
8The deliberations could influence regulatory policy on inter-state versus intra-state transmission
Click on Details for more
Details
The Central Electricity Regulatory Commission scrutinizes SECI's petition to adopt tariffs for a 100 MW wind project.
8This case highlights unique adjustments in project capacity to meet technical connectivity requirements, ensuring optimal utilization and regulatory compliance.
Click on Details for more
Details
With a focus on innovative carbon capture methods, the CMPDI-led hackathon seeks to transform India's carbon management landscape.
8Participants will have the chance to showcase their solutions, potentially influencing national policy and industry standards.
Click on Details for more Details
8Find a snapshot of thermal, hydro, pumped storage, solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
8Over 3 lakh units were cleared in HPDAM at zero price, pointing to likely grid stability instructions or undersubscribed hydro bids.
Click on Details for more Details
8India attempt to build green Ammonia capacity seems to be completely stuck
8A tender to purchase green Ammonia has been extended as many as 10 times as no bidder was ready to bid
8Knowing, that the effort is going no where, the government is now trying a salvage operation
8But will that work?
Click on Details for more Details
8Some evening RTM slots traded below Rs.3/unit while others crossed ?10/unit marking one of the sharpest intra-day spreads in recent weeks.
Click on Details for more Details
8Day-ahead prices remained elevated due to persistent northern grid demand, even though cleared volumes were slightly below mid-week average.
Click on Details for more Details
8Evening blocks continued to show price strength in the hourly DAM segment, with clearing rates surpassing ?6/unit across multiple bids
Click on Details for more Details
Learn about the multi-purpose projects under examination between India and Nepal, such as Pancheshwar MPP.
8This collaboration represents a significant step in regional energy cooperation and capacity enhancement.
Click on Details for more
Details
Recent Tribunal rulings highlight the impact of changing PPA "Effective Dates" from signing to approval, reducing project pressures.
8This shift is pivotal for developers navigating regulatory and commissioning timelines in India's solar sector.
Click on Details for more
Details
8The multiple bid extensions stretching over a year suggest either intense bidder lobbying or fundamental internal shifts in tender preparedness
8The absence of finalized bids despite multiple deadline cycles suggests hesitancy among EPC firms, either due to commercial terms or project risk
Click on Details for more Details
The SCED statement highlights how economic dispatch decisions are reshaping power economics in Northern India.
8Understand the dynamics of energy scheduling and its financial impact, set against the backdrop of recent regulatory changes.
Click on Details for more
Details
Explore the April 2025 insights into Plant Load Factor performance, with some plants exceeding expectations while others lag behind.
8Analyze the factors influencing these variations and their strategic importance.
Click on Details for more
Details
Learn about the multi-purpose projects under examination between India and Nepal, such as Pancheshwar MPP.
 
8This collaboration represents a significant step in regional energy cooperation and capacity enhancement.
Click on Details for more
Details
With three units commissioned and another on the way, the Parbati-II HEP exemplifies India's commitment to scaling up hydroelectric capacity.
8Delve into the project's impact on regional power supply.
Click on Details for more Details
Despite having vast hydroelectric potential, the Northeastern region utilizes only a fraction, highlighting a significant opportunity for growth.
8This untapped potential could drive regional development and energy security.
Click on Details for more
Details
Despite having vast hydroelectric potential, the Northeastern region utilizes only a fraction,highlighting a significant opportunity for growth.
8This untapped potential could drive regional development and energy security.
Click on Details for more
Details
8In a landmark decision, the Tribunal clarified that regulatory approval delays should not financially burden developers, setting a new standard in handling land acquisition and project execution timelines in India's renewable energy sector.
Click on Details for more
Details
 For reference purposes the website carries here the following tenders:
8Design, fabrication, supply, installation, testing, commissioning with RMS of 19 kW capacity of GCRT Details
 8Design, fabrication, supply, installation, testing, commissioning of 118 KW grid connected solar PV power plant Details
 8Design, fabrication, supply, installation, testing, commissioning of 118 KW distribution capacity grid connected solar PV power plant Details
 8Design, fabrication, supply, installation, testing, commissioning with RMS of total cumu. 12 kWp GCRT Details
 8Design, fabrication, supply, installation, testing, commissioning with RMS of 05HP.DC solar water pumping system Details
 8Design, fabrication, supply, installation, testing, commissioning with RMS of total 234 kWp GCRT Details
 8Tender for service wire maintenance work Details
 8Tender for annual complete operation work along with minor maintenance work Details
 8Tender for overhauling and repairing work of 33 KV circuit breaker situated at Various Details
 8Tender for dismantling, overhauling and installation of boiler circulation pump and its motor assembly Details
 8Tender for protection work at tower Details
 8Tender for construction of RCC platform inside the switchyard Details
 8Tender for construction of recharge well for rain water harvesting and allied supporting civil construction Details
 8Tender for repairing of cable trench and installation of BPI and connecting Details
 8Tender for construction of rain water harvesting system Details
 8Tender for augmentation of power transformer Details
 8Tender for procurement of 1. 11KV fixed contact for 11 KV AB switch Details
 8Tender for procurement of 66KV OIP bushing for power transformer complete Details
 8Tender for purchase of 400 KV current transformers Details
 8Tender for EPC project for design, engineering, supply, testing, installation , erection, commissioning & capacity up gradation of PA fan and ID fan motors Details
 8Tender for providing vibration dampers and arcing horns (also replacing the suspension hardware with the suitable suspension hardware which supports the provision of arcing horns) in 132kv line Details
 8Tender for procurement of fire fighting hose and couplings Details
 8Tender for procurement of 56" cushion rollers for conveyors Details
 8Tender for procurement of bearings for motor repair works Details
8Tender for balance civil works Details
 8Tender for providing / repairing / servicing of rolling shutters of various Details
 8Tender for providing and laying carpet and seal coat on existing Details
 8Tender for supply of 5 kVA single phase out door type completely self protected aluminium wound energy efficient level-1 distribution transformers Details
 8Tender for erection of 33 KV line (6.08 KM O/G and 0.52 KM U/G cable Details
 8Tender for construction of 33/11 KV GSS Details
 8Tender for installation of new street light with poles and repair and maintenance of street light Details
 8Tender for SITC of split type air conditioners Details
 8Tender for creation of 132kV line bays at 220kV to accommodate LILO of existing 132kV S/C line Details
 8Tender for development of distribution infrastructure for Package 21 Details
 8Tender for development of distribution infrastructure for Package 22 Details
 8Design, engineering & supply of puppet valve for LRSB of boiler Details
 8Tender for work of supply, installations & commissioning of various size headers, pipes, bends & connection flanges of cooling water system Details
 8Tender for supply & application of fire retardant cable insulating coating Details
 8Tender for work of ash handling plant related operation & maintenance (mechanical, electrical, and instrumentation) work during online, routine, preventive, breakdown Details
 8Tender for supply of bag filters Details
 8Tender for supply of cable and accessories Details
 8Tender for fabrication and supply of utility vertical water pump column pipe Details
 8Tender for hiring of services for design fabrication installation and commissioning of agitators Details
 8Tender for supply and installation of drainage pumps motor set along with pipe, valves, fitting etc Details
 8Tender for procurement of LT metal parts Details
 8
Tender for R/M of control room with leak proof treaetment andnew sewer system at 33/11 kv p/s/s Details
 
8Design, engineering, preparation of DPR and execution for rehabilitation of control room hall pre engineered steel structure at 132,33 KV GSS Details
 
8Tender for replacement of 11KV overhead HT lines with HT cables by rerouting of three incomer lines. Details
 
8Tender for work of plantation of 2000 plants Details
 
8Tender for work of CW pump, TWS and routine operation and maintenance of EOT cranes Details
 
8Tender for creation of 33KV SStn Details
 
8Tender for supply of impact pads for various conveyors installed Details
 
8Tender for supply of pressure calibrators Details
 
8Tender for providing RCC chamber with protection Details
 
8Tender for erection of 66kV S/C from 66kV S/S line Details
 
8Tender for roof treatment and allied masonary works Details
 
8Tender for supply, installation and commissioning of 145KV disconnector for bus section bay at 132kV main bus Details
 
8Tender for overhauling of HT motors Details
 
8Tender for installation and operation of submersible pump sets for dewatering of stilling basin Details
 
8Tender for work of providing new mild steel bar (MS bar) fencing for 250/400 KVA distribution transformers of 33/11 kV sub station Details
 
8Tender for work of supply of mobile trolley for 400 KVA transformer Details
 
8Tender for development of distribution infrastructure for Package 8 Details
 
8Tender for development of distribution infrastructure for Package 14 Details
 
8Tender for development of distribution infrastructure for Package 13 Details
 
8Tender for development of distribution infrastructure for Package 12 Details
 
8Tender for development of distribution infrastructure for Package 11 Details
 
8Tender for development of distribution infrastructure for Package 10 Details
 
8Tender for development of distribution infrastructure for Package 9 Details
 
8Tender for development of distribution infrastructure for Package 20 Details
 
8Tender for development of distribution infrastructure for Package 19 Details
 
8Tender for development of distribution infrastructure for Package 18 Details
 
8Tender for development of distribution infrastructure for Package 17 Details
 
8Tender for development of distribution infrastructure for Package 16 Details
 
8Tender for development of distribution infrastructure for Package 15 Details
 
8Tender for supply and application of paint on steel structures of CHP conveyors andequipment Details
 
8Tender for procurement of decanted water pump assy Details
 
8Tender for supply of critical valve cooling spares for pole I & II at 500KV HVDC S/stn Details
 
8Tender for supply of reputed make ISI marked and various type of fire extinguisher Details
 
8Tender for erection of 66kV equipment, structures, control wiring, yard lighting Details
 
8Tender for procurement of 50 MT GI stranded wire 6 SWG Details
 
8Tender for procurement of 55 MT GI stranded wire Details
 
8Tender for supply of B-check maintenance kit spares Details
 
8Tender for supply of ANTICO pump spares Details
 
8Tender for supply of fenner make V-belts Details
 
8Tender for procurement of SEMs from power grid Details
 
8Tender for strengthening of column below 5A conveyor belt in plow feeder Details
 
8Tender for construction of operator cabin JE room and store room for coal handling and turbine Details
 
8Tender for supply of lighting meterials Details
 
8Tender for supply of water and AIR hoses Details
 
8Tender for M and R works to surface structures Details
 
8Tender for repairs to existing pumpshed Details
 
8Tender for procurement of HDPE pipe 200mm for use Details
 
8Tender for providing of carrying IDLER for 1200 MM conveyor system Details
 
8Tender for construction of control room equipment foundation, switchyard Details
 
8Tender for protection grill fixing at ground floor windows Details
 
8Tender for renovation of dilapidated pipeline Details
 
8Tender for structural rectification at various Details
 
8Tender for (annual maintenance contract) of 125 kVA & 400 kVA DG sets installed Details
 
8Tender for supply of pump shaft assembly for CWP Details
 
8Tender for supply of impeller assembly for CWP Details
 
8Tender for work of complete overhauling of boilers with air pre heater, BTD, coal & oil burners of 210 MW boilers Details
 
8Tender for augmentation of substations by replacement of ICTs Details
 
8Tender for work of second circuit stringing along with end bays in r/o (i) 132 kV line Details
 
8Tender for work of supply, installation, testing, and commissioning of transformer auxiliary monitoring system Details
 
8Tender for augmentation of substation by providing of 1X100 MVA 220/33kV T/F alongwith HV&LV bays at 220kV SS Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:

 8
Coal India Subsidiaries BCCL & CMPDI IPO Filing Soon Details
 8Govt considering amendments to Atomic Energy Act nuclear liability law Details
 8Pumped storage: the missing link in global renewable energy transition Details
 8Digital Edge announces renewables deal for major data centre Details
 8WattPower Achieves 2X Growth in One Year Details
 8Green energy stock jumps 4% after receiving 285-MWp solar projects Details
 8Inox Green Share Price Jumps 5% After Major Solar Project Deal Details
 8Vikram Solar shines as India’s top PV brand 2025 Details
 8Adani, Tata, Vedanta make a power play for coal-fired projects after five-year lull Details
 8A Blueprint to Advance the U.S.-India Energy Security Partnership Details
 8The growing importance of carbon capture for India’s sustainable industrial future Details
 8BHEL Records Highest-Ever Annual Order Inflow In FY25 Details
 8
India's Inox Green wins 285 MWp solar O&M contracts Details
 
8India emerges as global leader in electric three-eheelers for second consecutive year Details
 
8Here's what drove Reliance Power shares up by 4% on Monday, May 19 Details
 
8Reliance Power to build Bhutan's largest solar project in ?2,000 cr JV Details
 
8ZF Wind Power Commissions India’s Largest Gearbox and Powertrain Test Facility Details
 
8India's coal import drops to 263.56 MT in 2024-25 Details
 
8KEC International bags new T&D orders worth Rs 1,133 cr Details
 
8Several global consulting firms evince interest to implement Vedanta's USD 20-bn expansion projects Details
 
8ReNew to invest $2.5b for hybrid RE projects in India Details
 
8Mumbai Firm Wins Transmission Orders Worth Rs 1133 Cr Details
 
You can also click on Newsclips for more Details
Discover the implications of NRPC's latest revision in reactive energy charges due to a technical error affecting regional generators.
8Understand how these adjustments impact your financial planning and what steps to take next.
Click on Details for more
Details
8With the technical bid now opened, the sheer volume of competition suggests financial bids may dip sharply below Rs. 3.04 ceiling—especially with multiple Meena family names in the race.
8The current bid round sees new entrants challenging established EPC norms.
8Is the decentralised solar market entering a fresh price-discovery phase?
Click on Details for more Details
8A highly specialized Rs. 100 plus crore package for ultra high voltage CTs has just two qualified bidders
8Our analysis explores what narrowed the playing field, and how it could shift L1 odds
8Both technically qualified bidders are industry leaders. But a deeper dive into their past 765kV CT projects shows key differences in performance, specs offered, and L1 strategy
Click on Details for more Details
8A fresh 4,000-unit transformer tender has shown a gap of over Rs. 800 crore between the lowest albeit lesser discussed L-1 winner and third-lowest bidder.
8This hints at deeper competitive shifts or divergent assumptions on cost inputs.
8With a two-year validity, this contract may lock in pricing strategies that extend beyond a single fiscal year. This poses both risks and opportunities in a volatile materials market.
Click on Details for more Details
The Supreme Court has upheld a Tribunal judgment favoring Tungabhadra Solar Parks, ensuring they receive the original tariff rate.
8This decision is crucial for developers, ensuring fair compensation despite procedural delays in project commissioning.
Click on Details for more Details
8A key aluminum-wound transformer tender has revealed an unexpectedly tight bid by the L1 player
8Digging deeper into the unit pricing and previous tenders reveals a new pricing benchmark that could ripple across the segment
Click on Details for more Details
8An FGD project tender sees its 18th deadline extension since late 2023 — raising serious questions around bidder response, internal approvals, and scope clarity.
Click on Details for more Details
8In what is now the eighth extension, the deadline has been pushed to 4th June 2025
8This is raising eyebrows for those watching the Rs 2000 crore package.
Click on Details for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
8The Shahpura Circle project under TN-DSM-32 now pushed to May 21, 2025 suggesting either high complexity or low bidder turnout despite massive EPC scope across solar, substations, and O&M
Click on Details for more Details
Independent Power Producers (IPPs) demonstrated near-full capacity utilization in April 2025, with a notable performance improvement over the previous year.
8This is a key indicator of the sector's potential to meet growing energy demands while enhancing operational effectiveness.
Click on Details for more
Details
Independent Power Producers (IPP) have driven significant growth in India's energy sector, with marked improvements in generation efficiency and capacity utilization reported for April 2025.
8This trend emphasizes the increasing importance and effectiveness of private sector participation in meeting national energy demands.
Click on Details for more
Details
8From network reliability to consumer connectivity, the selected bidder essentially becomes a shadow operator at feeder level
8The project mandates solar generation near 33/11kV substations with backend KPIs likely linked to uptime, load balancing, and consumer outages
8The model is running into bidder resistance, and the tender had to be extended multiple terms
Click on Details for more Details
The Bhutan Import Region has faced a substantial drop in energy performance, achieving only 22.50% of its April 2025 target.
8This stark contrast to other regions underscores potential challenges in energy imports that need immediate attention.
Click on Details for more
Details
April 2025 marked a milestone for nuclear energy in India, exceeding program goals by an impressive 111.43%.
8This surge indicates robust operational efficiency and strategic emphasis on nuclear as a key energy pillar, crucial for professionals in policy and infrastructure planning.
Click on Details for more
Details
8The tender for a long-term distribution network revamp under a hybrid annuity model has now been extended seven times, with the new deadline pushed to 21st May 2025.
8Is bidder readiness the issue or are commercial terms being debated?
8The project includes decade-long operations and maintenance responsibilities.
8Could this be the reason for cascading extensions?
8The inclusion of SPV-based implementation means bidders must float special purpose vehicles.
8This is a setup common in renewable, but trickier in multi-component distribution projects.
Click on Details for more Details
8A complex blend of feeder segregation, solar plant deployment, and LT network management under HAM seems to be testing contractor appetite
8The mix of capex-intensive solar and opex-heavy LT upkeep under one annuity model is raising tough internal questions
8Contractors used to physical infra now face digital performance guarantees, forcing a rethink on execution partnerships
8Decentralized solar plants now require custom feeder-level sizing based on load profiles not just generic 500 kW templates.
Click on Details for more Details
8Privately-run thermal plants operated at only 76% of target generation in April 2025. State and central plants fared better but still missed the mark, pulling down overall thermal performance.
Click on Details for more Details
8Green day-ahead supply saw under-subscription, as buyers avoided noon RE blocks amid over-forecasting risks and uncertainty in solar output.
Click on Details for more Details
8The real-time market on May 19 saw an unexpected volume jump, with key utilities covering demand gaps caused by fluctuating RE forecasts.
Click on Details for more Details
8Several state utilities actively revised their evening demand estimates and entered bids up to ?12/unit, showing low reserve margins.
Click on Details for more Details
8A recent tender has opened for over Rs 220 crore worth of 11kV VCB panels under a buyback scheme
8What’s notable is the scale and the timeline 10 months for execution, with variable pricing terms rarely seen in past cycles
8Beyond technical specs, vendors now face tightened pre-qualification criteria, including updated financial thresholds and renewed vendor registration mandates even for previously listed suppliers
8While the current tender is for supply only, the structure of the commercial terms especially in documentation compliance suggests that upcoming tenders may bundle in erection and commissioning as part of turnkey packages
Click on Details for more Details
‹ First  < 3 4 5 6 7 >  Last ›

Showing 201–250 of 542 items