All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Jul 2025

 For reference purposes the website carries here the following tenders:
8Tender for insertion of an additional glass disc in suspension insulators in 400/220 kV line Details
 8Tender for award of contract for system strengthening works for survey, installation, testing and commissioning of new 5 MVA 33/11 kV substation Details
 8Tender for protection works at tower Details
 8Tender for procurement of numerical and auxiliary relays as spare installed Details
 8Tender for procurement of spares of transport air compressor Details
 8Tender for supply, fabrication, erection of GI steel structures, earthing, materials, etc Details
 8Tender for civil work for the earthwork excavation, stub setting, concreting, earthing of towers Details
 8Tender for replacement of damaged woven wire fencing including miscellaneous steel structural works Details
 8Tender for replacement of broken slab of drain at 400 kV switchyard Details
 8Tender for replacement of damaged insulations Details
 8Tender for carbonated fly ash brick (C-brick) plant Details
 8Tender for supply, erection, testing & commissioning of 24-core armoured Details
 8Tender for procurement of 132kV dry type self supporting termination and straight through jointing kits for XLPE cable Details
 8Tender for work contract for BAH & seal through puncture repairing, refractory applying, boiler Details
 8Tender for work of overhauling, rewinding, repairing & testing of ESP transformers Details
 8Tender for supply of throden bearing for jackwell pump Details
 8Tender for developing of rain water harvesting system Details
 8Tender for bi annual rate of contract for restoration work of 66kV & 132kV transmission line Details
 8Tender for erection of 66 kV D/C line from 220 kV SS Details

8Tender for construction of balance civil works for new 66 kV sub station Details
 8Tender for appointment of representative agency for witnessing the third party sampling Details
 8Tender for capital work of 110kV substation Details
 8Tender for reconductoring 4.7km 110kV DC wolf conductor with AL59 and insertion of one tower Details
 8Tender for shifting HT/LT line Details
 8Tender for work of augmentation of substation by addition of 132/33kV 50MVA power transformer along Details
 8Tender for work of 66kV line from 66kV S/S Details
 8Tender for supply of sulphuric acid commercial grade for DM plant cooling tower. Details
 8Tender for AMC services for hydrogeological study of plant Details
 8Tender for supply of material, erection, of GI M type angles at the center of 112 nos M plus 6 towers Details
 8Tender for supply of HT cables Details
 8Tender for construction of 220kV sub-station Details
 8Tender for providing and fixing safety hand rail Details
 8Tender for repair and painting with other miscellaneous works Details
 8Tender for repairing of existing drain situated Details
 8Tender for engagement of consultant for preparation detailed project report for determining requirements Details
 8Tender for manufacture, testing, supply and delivery of 33 kV 3CX400 sq. mm and 33 kV 1CX1000 sq. mm XLPE armoured aluminium cable Details
 8Tender for repairing and maintenance of bituminous road Details
 8Tender for procurement of spares of VM-12 breaker for U-2 and 5 overhauling Details
 8Tender for service contract for high altitude 220/400 kV annual switch yard Details
 8Tender for service contract for refractory and insulation work Details
 8Tender for supply of materials for maintenance of water supply and sanitary system Details
 8Tender for supply of 4 inch seamless pipe line with its connected Details
 8Tender for supply of strain hardware fittings Details
 8Tender for supply of 33kV dual ratio combined CT PT units for feeder metering Details
 8Tender for work of replacement of damaged 33 kV cable Details
 8Tender for work for release of new service connection Details
 8Tender for supply of 350 NB seamless pipes Details
 8Tender for procurement of worm gear hub for XRP 763 bowl mills Details
 8Tender for procurement of HS straight joint kit for XLPE cable Details
 8Tender for procurement of 7/2.50mm AAAC WEASEL conductor Details
 8Tender for supply of vertically operated 11kV gang operated air breaker switch with composite polymer insulators Details
 8Tender for replacement of ACSR weasel conductor Details
 8Tender for replacement of ACSR weasel conductor by 11 kV AAAC AL-59, 99 sqmm. covered conductor Details
 8Tender for procurement of carbon brush grade LFC554 for slipring of generators Details
 8Tender for procurement of solar panels   Details
 8Tender for work of supply, installation & commissioning of DM water plant with RO at hot line Details
 8Tender for work of overhauling, servicing & repairs of 145kV circuit breaker at various EHV S/stns Details
 8Tender for attending emergency breakdown work & annual routine maintenance of 220/132/110kV various EHV lines Details
 8Tender for dismantling and erection of 66/11kV indoor equipments, earthing, control wiring Details
 8Tender for dismantling and erection of 66/11kV indoor equipments Details
 8Tender for supply of cast basalt bends for wet and dry fly ash de-ashing system Details
 8Tender for annual contract for repair work of raw water reservoir Details
 8Tender for annual contract routine, breakdown and annual maintenance of HT switchgear, HT motors Details
 8Tender for annual contract for routine /breakdown and annual maintenance of boiler pressure part, HP valves and its auxiliaries Details
 8Tender for contract for the work of complete operation, maintenance and housekeeping of automated PLC based coal handling plant Details
 8Tender for requirement of hydraulic pumps and spares for wagon tipplers Details
 8Tender for requirement of insulating mats for electrical panels Details
 8Tender for comprehensive annual maintenance contract for UPS of C&I system Details
 8Tender for procurement of cooling water treatment chemicals Details
 8Tender for engagement of one dozer machine Details
 8Tender for procurement of MS plate, sailhard PM plate and CS plate Details
 8Tender for construction of foundations, bus-strengthening, FP wall, oil sump, cable trench & misc. civil works Details
 8Tender for procurement of GTC sleeve for journal shaft assembly Details
 8Tender for annual civil repair and maintenance work in power house Details
 8Tender for proposal for annual work of water distribution gate valves for supply of drinking water Details
 8Tender for biennial rate contract for complete overhauling/ repairing /servicing of hydraulic cylinder assembly of coal mill installed Details
 8Tender for work contract for rectifying/resolving the technically complicated defects and attending the major breakdown of 2x10 Nm3/hr capacity hydrogen gas generation plant Details
 8Tender for procurement of various spares of air pre heater Details
 8Tender for setting up of cumulative capacity of 2214 KW grid connected rooftop solar PV power projects Details
 8Tender for setting up of cumulative capacity of 1400 KW grid connected rooftop solar PV power projects Details
 8Design, manufacturing, testing, commissioning and installation of CBMS Details
 8Tender for supply of gland packing material Details
 8Tender for supply and commissioning of thyrister package AC system Details
 8Tender for rewiring works and provide new earthing Details
 8Tender for work of repairing of SF6 to air bushing with all associated activities Details
 8Tender for supply of 400 kV CVT Details
 8Tender for works of testing & commissioning of various generator, transformer Details
 8Tender for procurement of various types of air conditioners Details
 8Tender for work of mechanical strengthening, stub strengthening Details
 8Tender for supply of copper flexible strip connectors links for LV duct of 75 MW generator Details
 8Tender for job work of fly ash filling in tanker from ESP hopper Details
 8Tender for supply of various size of MS ERW pipes, CI gate valves Details
 8Tender for erection of 66kV S/C line on D/C panther tower structure Details
 8Tender for operation and maintenance of electrical systems Details
 8Tender for supply of PH & analyzer and PH sensor cable Details
 8Tender for work of annual maintenance contract for maintaining of EHV sub station Details
 8Tender for work of second circuit stringing along with end bays Details
 8Tender for agumention of substation by providing additional T/Fs & replacement of T/Fs of EHV substation Details
 8Tender for AMC for various work related to all ICT's, reactors & transformers Details
 8Tender for work of enhancement of transformation capacity by addition of 1 x 25MVA 220/33kV power transformer Details
 8Tender for work of annual maintenance contract for attending emergency breakdown and also carrying out various Details
 8Tender for work of supply of IED panels & retrofiting of IEDs at various substations Details
 8Tender for work of servicing / overhauling of 145kV&245kV SF6 circuit breakers (CBs) with supply of mandatory & minimum optional spares at various substations Details
 8Tender for work of tower earthing of various of 220/132/110kV EHV line towers Details
 8Tender for work of upgradation of existing SCADA system Details
 8Tender for bi-annual maintenance contract (Bi-AMC) for work of refilling & providing new spares for existing fire extinguishers Details
 8Tender for work hotline (live line) crossing of 400 kV DC line Details
 8Tender for work of augmentation of substation by addition of 220/33KV 50MVA power transformer Details
 8Tender for work of augmentation of substation by addition of 132/33kV 25MVA power transformer Details
 8Tender for establishment of 220/132 kV S/S along with construction of 220 kV DC line Details

 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8TATA-group power company invests Rs 120 crore for 40% stake in 600 MW Khorlochhu hydro power project in Bhutan Details
 8J&K receives 144 MU of power from NLC India in FY 2024-25 Details
 8India’s thermal coal production to significantly outpace demand in 2025 Details
 8Bluebird Solar to boost solar panel production To 2.5 GW by october 2025, eyes major manufacturing expansion Details
 8The next frontier in India’s energy infrastructure: Why execution risk management is the missing piece Details
 8Revayu Energy: Innovating in the renewable energy space with tribrid projects Details
 8Panama schedules new solar auction for July 2026 Details
 8Waaree launches Prime+ platform to empower India’s solar integrators Details
 8India drafts cybersecurity rules for rooftop solar monitoring systems Details
 8India Gets Rs 48,120 Cr investment under solar PLI scheme Details
 8India’s power transmission capacity surged from 75,050 MW to 1,20,340 MW in 8 years: Minister Details
 8JSW Energy secures first long-term agreement for dispatchable renewable power with SECI Details

 
8Renewables help India save 4 lakh crore in fossil fuel & pollution costs in 2024 Details
 
86 Adani Group stocks in which FIIs reduced their stake by up to1,833 Cr in Q1 Details
 
8Dhanbad mine 'collapse': NDRF rescue ops yet to begin as exact location remains unidentified Details
 
8MNRE issues draft security guidelines for rooftop solar inverters and communication devices Details
 
8Torrent Power Chases $1 Billion Thermal Jackpot from L&T Details
 
8IEX Q1 Results | Net profit, revenue, margins rise; electricity volume grows 15% Details
 
8Wipro Wins Multi-Year Saudi electricity deal Details
 
8Why IEX Share Price is Falling Details
 
8Overcoming land constraints for India’s solar energy future Details
 
8Global coal demand to remain on a plateau in 2025 and 2026 Details
 
8Nuclear Power makes up 3% of India's electricity, says government Details
 
8NLC India expands thermal power to 1660 MW via NTPL & NUPPL Details
 
You can also click on Newsclips for more Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
High-value logistics contract awarded amid tight bidder spread
8A Rs. 170.8 crore award for a bulk ash evacuation deal saw the top 5 bids packed within a Rs. 10 crore band. The intense clustering reflects growing interest in long-haul ash logistics linked to road construction projects.
8For a 17 LCM ash transport contract from a major thermal plant, the L1-L2 bid gap is just Rs. 2 crore, suggesting aggressive price positioning. With over 15 technically qualified bidders, this tender may signal a shift in ash logistics competition dynamics.
820 total participants, only 16 passed technical scrutiny. Disqualified players included mid-tier names, while qualified bids came from both MSEs and high-turnover logistics firms, making this a diverse yet cut-throat bid environment.
8The gap between L1 and L5 bids was under Rs. 8 crore in a Rs. 210 crore spread. For bidders, margins are razor-thin; for procurers, competition is at its best. The awarded bidder stood out more on pricing than on scale. Details
RESCO mode returns to Ladakh solar space with storage-heavy scope
8This 7MW / 9MWh project marks a renewed push for RESCO-mode investments in remote geographies, with performance-based returns and storage integration emerging as key risk variables in Indian renewable energy ventures.
8The bid documents reveal more aggressive BESS lifecycle expectations up from prior 3,000-cycle standards. Bidders in Indian renewable energy tenders must now offer higher throughput batteries, likely raising EPC and O&M pricing benchmarks.
8The liquidated damages for underperformance are capped at 10 percent of the total project cost, placing sharper accountability on the developer under the RESCO structure an increasingly common feature in Indian renewable energy contracts.
8Such risk-aligned structures reflect how Indian renewable energy deployments in high-altitude, off-grid terrains are evolving to embed energy storage with stricter financial penalties and real-time delivery metrics.
8As Indian renewable energy policies deepen their focus on round-the-clock supply in strategic regions, RESCO projects like this offer critical case studies in balancing viability, availability, and regulatory compliance. Details
Open access ambitions on hold as Saptagir Camphor withdraws from regulatory battle
8Saptagir Camphor's decision to abandon its open access petition sheds light on the complexities and strategic considerations in India's evolving energy market.
Active Power's hydel project: No compensation for non-operational period, rules APERC
8Citing PPA terms, the regulator denies compensation claims for past inactivity, emphasizing contractual adherence in Active Power's tariff approval process.
Andhra Pradesh extends FPPCA feedback deadline, signaling open regulatory process
8The extension for stakeholder feedback on FPPCA petitions indicates APERC's commitment to an open and consultative regulatory process, which could set a precedent for future petitions.
Click on Details for more
Details
Regulatory commission grants extension for PPA submission in Tata Steel case
8The Jharkhand commission has allowed TSUISL additional time to file a draft PPA, highlighting procedural rigor in regulatory oversight.
8This move reflects ongoing compliance challenges in energy contracts.
SLDC's procedural delay hints at deeper operational issues
8The postponement requested by SLDC could be indicative of underlying challenges within Jharkhand's electricity dispatch system.
8Analysts should consider possible impacts on system operations.
JBVNL and JREDA face JSERC's intensified scrutiny in ongoing case
8With JREDA now a party to the JSERC proceedings, both agencies face heightened regulatory scrutiny.
8This development may lead to strategic adjustments in their operations and compliance strategies.
Tribunal examines electricity Act's applicability to SEZ developers in Tamil Nadu
8The tribunal's decision may redefine the scope of the Electricity Act concerning SEZ developers, with implications for licensing requirements and cross-subsidy obligations.
Competitive bidding dynamics: Jindal Power's PPA approved at Rs. 5.22/kWh
8The competitive bidding process sees Jindal Power securing a PPA at Rs. 5.22/kWh, emphasizing the evolving dynamics and pricing strategies in India's energy market.
Click on Details for more
Details
Jharkhand power project faces potential delays due to JBVNL report postponement
8The JBVNL's delay in submitting key reports may disrupt the project timeline, highlighting inefficiencies in regulatory processes.
JSERC demands transparency in JBVNL’s power distribution practices
8Highlighting significant power interruptions, JSERC requests a senior JBVNL official to explain operational challenges and regulatory compliance in the next hearing.
Legal tussle highlights Tata Steel's renewable energy strategies in Jharkhand
8Tata Steel's legal proceedings with JREDA signal strategic posturing in renewable energy compliance. Industry watchers should note how large corporations are navigating state-level regulatory landscapes.
Regulatory delay: Tata Steel's renewable energy compliance in question
8As JREDA seeks additional time in its case with Tata Steel, questions arise about the effectiveness and speed of regulatory compliance processes affecting corporate renewable strategies.
Tata Steel-JREDA case adjournment could signal broader regulatory tensions
8The adjournment in the Tata Steel and JREDA proceedings may reflect wider regulatory frictions as industries navigate compliance with evolving state energy policies.
Click on Details for more
Details
Regulatory scrutiny on ESL Steel and JREDA highlights compliance complexities
8As legal proceedings unfold, the case between ESL Steel and JREDA highlights the intricate compliance landscape in India's renewable energy sector.
8Stakeholders should watch closely for implications on policy and practice.
Regulatory compliance in spotlight as JBVNL seeks high court relief
8With JBVNL's compliance report filed, the focus shifts to its high court petition effort, a move that could redefine regulatory compliance expectations and legal strategies in Jharkhand's power distribution sector.
Jharkhand power dispute could reshape state’s electricity distribution landscape
8The regulatory case between IPL and JBVNL may signal changes in Jharkhand's power distribution strategies, impacting contracts and operational norms in the state.
Regulatory proceedings highlight affidavit compliance issues in Jharkhand power case
8A recent Jharkhand State Electricity Regulatory Commission hearing reveals ongoing compliance issues with affidavits filed by Inland Power Limited.
8The case underscores the importance of meticulous documentation in regulatory disputes.
Awaited decision in DVC case could realign power sector norms
8A forthcoming decision in the DVC vs. HT consumers case promises to realign sector norms, potentially affecting future regulatory decisions and market dynamics.
Click on Details for more
Details
Legal complexities unfold as Green Energy Association joins TSL-JREDA case
8The inclusion of the Green Energy Association in the TSL vs. JREDA proceedings adds a new layer of complexity to the case, with potential implications for stakeholder roles and regulatory policies in Jharkhand's energy sector.
Legal proceedings reveal competitive dynamics in Jharkhand's energy sector
8The ASPL case proceedings shed light on the competitive and regulatory challenges facing energy projects in Jharkhand.
8Legal strategies and timeline extensions could have broader implications for market dynamics.
Regulatory scrutiny intensifies: Jharkhand's renewable projects under the microscope
8The ongoing legal proceedings between ASPL and JREDA highlight increased regulatory oversight on renewable energy projects, affecting future stakeholder engagements and bids.
ESL Steel's latest legal move could shift renewable compliance norms
8By filing a rejoinder against JREDA, ESL Steel is potentially reshaping the standards for responding to renewable energy obligations.
8This case could influence future compliance norms in Jharkhand and beyond.
Regulatory commission's role in ESL-JREDA case under scrutiny
8The Jharkhand State Electricity Regulatory Commission's handling of the ESL-JREDA dispute will be closely watched, given its potential impact on regulatory precedents.
Click on Details for more
Details
Feasibility contract for green hydrogen jetty goes to RINA at Rs. 49.56 lakh
8RINA Consulting Private Limited emerged as L1 among six contenders, securing the feasibility consultancy for the green jetty plan in Pudimadaka. Their quote was nearly 33% below the next bidder, raising cost realism questions in the context of green hydrogen projects in India.
8The feasibility study is a critical enabler for the Pudimadaka hydrogen hub, aimed at streamlining exports of green ammonia a flagship example of emerging green hydrogen projects in India. The winning bidder must assess marine, environmental, and logistical complexities in detail.
8The competition featured Arup, Tractebel, SMEC, RINA, BMT, and Eka Infra blending global pedigree with local expertise. That mix reflects the strategic seriousness now driving pre-development phases of green hydrogen projects in India.
8Tractebel quoted Rs. 1.222 crore the highest among all bidders and landed at H3, suggesting that even top-tier players face pricing volatility in tenders linked to green hydrogen projects in India.
8As feasibility and export-linked infrastructure gain traction, tenders like this signal a maturing phase for green hydrogen projects in India, where cost, credibility, and execution readiness are under sharper scrutiny. Details
Grid-India faces software development hurdles for market coupling pilot
8The tight timeline for developing software for market coupling prompted an extension and formation of a committee to address the complexities and ensure smooth implementation.
CERC condones 71-month delay for PKTCL's key assets
8In a landmark decision, CERC has condoned extensive delays in PKTCL's transmission project, highlighting the regulatory body's flexibility in addressing infrastructural setbacks.
8Industry stakeholders must evaluate the implications for project timelines and cost recovery.
Adani's Rs.3645 crore asset valuation under regulatory review
8With Adani's transmission asset valuation at Rs.3645 crore, CERC's review could alter accepted capital cost frameworks, influencing investment strategies across the power sector.
New regulatory clause mandates 20% local content in renewable energy projects
8A new clause in the tender requires that 20% of all materials and components be sourced locally, potentially boosting domestic industries and altering supply chain strategies for EPC contractors.
CERC’s Category-V trading license proposal attracts industry attention
8The Commission’s proposal for Clean Renewable Energy Hybrid Fifteen to trade electricity inter-state has caught the eye of market watchers, with a decision looming in early August.
Click on Details for more
Details
VGF-backed 2000 MW storage bid opens doors to India's largest grid-scale battery push
8A landmark storage tender with PSDF support signals Gujarat's aggressive entry into utility-scale BESS. Developers will operate 4000 MWh across multiple sites, with 2-cycle daily dispatch and CEA-compliant integration protocols marking a major milestone in renewable projects in India.
8Unlike past tenders, the procurer commits to providing charging power based on round-trip efficiency, making the project bankable and removing grid uncertainty a game-changing move for developers engaged in renewable projects in India.
8The tender enforces year-wise minimum dispatchable energy from 97.5% in year 1 to 70% by year 12 requiring developers to provision augmentation or risk liquidated damages. Few renewable projects in India have built in such clarity and long-term performance enforcement.
8Despite technical flexibility, all 2000 MW BESS capacity is tied to the procurer under a firm on-demand usage structure. This positions the system primarily for grid support, not arbitrage or market-linked trading—signaling a maturity leap in grid-aligned renewable projects in India.
8With VGF backing and structured risk allocation, the tender could redefine bankability norms for storage-linked renewable projects in India, particularly where grid reliability and dispatch certainty are paramount. Details
Four oil majors in race for three-year fuel supply to state thermal stations
8A long-term rate contract for FO, LDO, and HSD has attracted all three public sector refiners alongside a private major. The supply spans multiple thermal plants owned by a Madhya Pradesh-based utility, with competitive implications for pricing and logistics over the next three years.
8The technical bid opening saw participation from leading PSU and private sector oil marketers for supplying FO, LDO, and HSD. This reflects strategic interest in high-volume, steady demand contracts from the state power sector.
8The equal footing of public and private bidders in this tender reflects the evolving dynamics of India’s fuel supply market, especially where institutional power sector clients are concerned. Details
Dry ash evacuation upgrade for thermal unit sees 8th deadline extension
8The tender for augmenting dry ash infrastructure at a coal-fired plant owned by a central utility has now been extended till 4 August. This marks the eighth deadline shift, indicating active bidder queries or scope recalibrations in the ash handling segment part of broader thermal power plant updates in India.
8With bid deadlines pushed from mid-June to early August, this tender reflects either keen bidder engagement or multiple clarifications. The ash handling segment, crucial to thermal power plant updates in India, is seeing renewed traction amid policy shifts on disposal norms.
8Even though BTG is excluded, the tender suggests mechanical–civil interface demands like hopper base rebuilding, reservoir lining, and structural steel extensions common features in ongoing thermal power plant updates in India.
8Such repeated extensions underscore the complexities bidders face in ash handling augmentation an emerging trend across several thermal power plant updates in India involving older coal units.
8Attention to plant geometry and access constraints will be crucial as vendors navigate interface-heavy retrofits, which are increasingly shaping thermal power plant updates in India. Details
Satellite monitoring pilot gains ground at NTPC coal mines
8A central generation utility is piloting satellite-based monitoring to assess mine slope stability across its coal operations. The initiative may pave the way for digital-first geotechnical surveillance, reducing ground crew dependency.
8The tender has been pushed thrice from early July to now 31 July implying internal realignment or engagement hurdles, especially since the project is on a single-source basis.
8While framed as a safety initiative, the outputs may also help NTPC comply with evolving mine surveillance norms. The overlap with DGMS and MoC expectations could enhance multi-agency utility. Details
Three-substation ICT package hints at deeper standardization shift
8KPTCL's latest turnkey tender spans three distinct substations two AIS and one GIS signaling a possible push toward harmonized specs across voltage levels. Each 500MVA ICT comes with embedded R&M, suggesting a lifecycle-oriented planning shift.
8The GIS scope at one of the locations includes new building construction, equipment footings, earthing, and pressurization distinct from earlier AIS-only models. The civil–electrical interface could drive bid premiums.
8The control and relay panels for GIS must operate on redundant DC supply with AC fallback and interlocked protections. The specification reinforces fail-safe design norms for new installations. Details
Single bay tender opens for BESS connectivity at major grid hub
8A new transmission tender focuses on just one 220kV line bay for BESS integration—a minimal yet high-impact move pointing to India’s shifting grid flexibility needs. The tender bypasses high-voltage works, unlike its June counterpart.
8Unlike earlier substation tenders serving bulk RE evacuation, this package supports battery-based flexibility. Such moves suggest evolving operational priorities for RE-balancing rather than just RE inflow.
8While June’s Bikaner package covered dual bays and 400kV busbar work, this July tender strips down to one 220kV bay—marking a clear shift in strategy, cost efficiency, and intent.
8This tender designates a 220kV-only connection point for a major asset, deliberately omitting 400kV handling—unlike the more complex design used just a month prior. Tailored engineering is at play here. Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Ash handling EPC tender floated for twin 800 MW units under central utility’s Stage-III expansion
8A critical ash handling package has been released for a 2x800 MW thermal expansion. The EPC scope includes bottom and fly ash systems, silo integration, and dry ash compliance, embedded within a station-wide control architecture.
8The bid window, originally set for June 27, has been extended five times, with the latest corrigendum pushing submission and opening to July 30. This reflects heightened bidder interest or document-level revisions.
8Five successive corrigenda within a month suggest high bidder engagement or scope clarifications underway—typical for large multi-system EPC projects nearing submission.
8With a dry ash dispatch clause hinted, the package may be positioned to support downstream applications—such as cement or brick manufacturing—reflecting policy-aligned ash utilization strategy. Details
Supercritical ash EPC tender sees fifth deadline shift
8The EPC package for ash handling at a 1x800 MW unit under a central utility has now been extended for the fifth time, with the latest bid deadline pushed to 29 July. The cascading extensions point to complex bid preparation and possibly intense pre-bid clarifications.
8The corrigendum introduces key corrections to NIT clauses, eligibility requirements, and document referencing—suggesting serious bidder-side confusion or initial drafting gaps. These mid-process amendments signal high stakes and tight margins for participants.
8The corrigendum silently shifts EMD validity from 90 to 180 days beyond bid validity—potentially reflecting extended evaluation timelines and raising carrying costs for participating bidders.
8The ITB clause for price bid submission is corrected, reiterating that the BOQ uses auto-calculated formulas—a hint that BHEL wants strict adherence to format with zero manual overwriting Details
 For reference purposes the website carries here the following tenders:
8Tender for electrification of additional un-electrified Details
 8Tender for electrification of additional un-electrified Details
 8Tender for electrification of additional un-electrified households Details
 8Tender for electrification of additional un-electrified households Details
 8Tender for supply of single phase digital transformer Details
 8Tender for supply of non-contact type AC voltage detectors Details
 8Tender for providing and fixing of fencing in various Details
 8Tender for work of annual rate contract for ash handling plant related Details
 8Tender for supply of different type of jointing Details
 8Tender for supply of different type of insulator Details
 8Tender for work of anticorrosive epoxy painting on various structure, pipelines, tanks etc. Details
 8Tender for procurement of complete assembly of oil free water cooled screw type air compressors Details
 8Tender for supply, erection, commissioning and testing of hydrogen gas leak detector system Details
8Tender for breakdown/preventive /RMC/AMC of all hydro mechanical equipments Details
 8Tender for laying of tower foundations, erection of towers, stringing and sagging of conductor for LILO of 220 kV DC line Details
 8Tender for upgradation of power supply module Details
 8Tender for keeping day to day record of water level Details
 8Design, supply, installation and commissioning of dynamic facade lighting Details
 8Tender for annual rate contract for rewinding major repair of HT motors and LT motors Details
 8Tender for service contract for repairing of submersible pumps Details
 8Tender for selection of roof top developer for setting up grid connected solar roof top plants Details
 8Tender for manufacture, testing, supply and delivery of 11 kV grade armoured XLPE cable Details
 8Tender for manufacture, testing, supply and delivery of 11 kV 3x95 Sqmm,11 kV 3x185 Sqmm, 11 kV 3x300 Sqmm and XLPE armoured aluminium cable Details
 8Tender for biennial rate contract for miscellaneous civil repair and maintenance works Details
 8Tender for procurement of structural steel items Details
 8Tender for balance work of CN type three storied Details
 8Tender for procurement, installation, upgradation and commissioning of oil burner accessories Details
 8Tender for supply of ISI marked LT AB cable Details
 8Tender for construction of shifting new 33/11 kV S/s Details
 8Tender for contract for efficiency testing pre and post overhaul Details
 8Tender for civil, architectural works in foundations, civil superstructure Details
 8Tender for supply of transformer lamination cut to length line Details
8Tender for dredging of sedimentation basin of ash dyke Details
 8Tender for biennial contract for manufacturing of fly ash bricks Details
 8Tender for maintenance and upkeeping of beautification works including Details
 8Tender for work contract for arresting leakages laying replacement of firefighting /service water MS /ERW lines Details
 8Tender for procurement of LT three phase channel cross arm Details
 8Tender for procurement of fan blade assembly Details
 8Tender for procurement of LT three phase angle cross arm Details
 8Tender for procurement of spool pipes for XRP 763 bowl mills Details
 8Tender for supply of 11 kV metal parts Details
 8Tender for procurement of 22kV polymer composite pin insulator Details
 8Tender for procurement of 22kV standalone structure materials Details
 8Tender for procurement of big U seal rings for 600MW turbine Details
 8Tender for procurement of 250NB lug type butterfly valve and 80NB ss316 gate valve Details
 8Tender for work of testing of EHV grade transformer oil samples Details
 8Tender for supply of various gates and dampers and its spares for boiler Details
 8Tender for work contract for attending running repairs, scheduled preventive break down maintenance with overhauling of locomotives Details
 8Tender for supply of common electrical items contactors, relays Details
 8Tender for supply of 40 HP and 10 HP non clog vertical type slurry/mud pump with electrical motor Details
 8Tender for supply of capacitance type point level switch and spares for air compressors Details
 8Tender for supply of spares for ESP Details
 8Tender for BRC for work of operation & maintenance of vacuum based ash handling plant Details
 
8Tender for const. of B.wall, earth filling and other misc. civil works at 33 kV S/S Details
 
8Tender for supply of 33 kV horn gap fuse sets with 2x24 kV post insulator Details
 
8Tender for up-gradation of HMI and EWS (composer) along with controllers and network switches Details
 
8Tender for overhaul and load testing of ID FD PA Fan hoists assembly Details
 
8Tender for routine maintenance and repairing work of rail track Details
 
8Tender for providing assistance in operation of locomotives for shunting and pushing of rolling stock Details
 
8Tender for hopper cleaning and breaking of oversize coal/ stone boulders over hopper mesh of wagon tippler Details
 
8Tender for procurement of spares of PLC installed Details
 
8Tender for work contract for annual routine maintenance of Boiler firing system, coal feed system Details
 
8Tender for work contract for replacement of existing old deteriorated ash slurry lines, fly ash conveying lines Details
 
8Tender for annual work contract for assistance in monitoring work and round the clock watch and ward Details
 
8Tender for procurement of refractory patching material for boiler Details
 
8Tender for civil works for installation of 250 LPH commercial RO with chillers and piping network Details
 
8Tender for procurement of paddle feeder Details
 
8Tender for laying of 33 kV, 3 x 400 sqmm XLPE UG cable 132/33 kV GSS Details
 
8Tender for augmentation of power transformer Details
 
8Tender for service contract for overhauling job of U 3 ESP 500MW Details
 
8Tender for service contract for complete overhauling of rotary air pre heaters Details
 
8Tender for supply, installation, testing & commissioning of conversion of S/C 66kV line Details
 
8Tender for construction of control room foundations, precast cable trench Details
 
8Tender for construction of control foundations, cable trench Details
 
8Tender for replacement of ACSR panther conductor by 33 kV ACS AL-59, 232.5 sqmm. covered conductor Details
 
8Tender for construction of 33 kV line Details
 
8Tender for work of maintenance contract for repair for servicing of air conditioners Details
 
8Tender for bi-annual maintenance & attending emergency breakdown work of 400kV quadruple & twin conductor Details
 
8Tender for agumention of substation by providing additional 1X50 MVA, 132/33 kV T/F at 132kV S/s Details
 
8Tender for work of provision of dedicated metering CT’s & CVT’s Details
 
8Tender for supply & installation of passive fire protection advance cable transit system at various 220/132kV EHV substations Details
 
8Tender for augmentation of substation by providing additional 1x50MVA, 132/33kV transformer Details
 
8Tender for providing & fixing by pass twin jumpering arrangement by boltless C-type wedge connectors to the jump at tension towers Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8The solar-plus-storage opportunity: How developers can lead India’s renewable transition Details
 8CEA Proposes 777 GW optimal power mix For 2029-30 With 62% non-fossil capacity – report Details
 8Waaree Energies launches Waaree Prime+ mobile app to empower solar integrators Details
 8Create more space for solar power Details
 8Only 3% of India’s wind and solar targets needed to power 2032 EV fleet: report Details
 8Solar myths and misconceptions put to sword Details
 8Goa's solar industry set for 325 crore turnover by 2027: SPAG Details
 8JSW Energy signs electricity supply pact with BESCOM for solar project with battery storage Details
 8Power stock jumps after signing power purchase agreement with BESCOM Details
 8CERC Directs phased implementation of market coupling in power exchanges starting january 2026 Details
 8
RITES and CMPDI join hands to tap mining and renewable energy opportunities Details
 
891% of new renewables in 2024 were cheaper than fossil fuel alternatives Details
 
8Inox Wind board clears Rs 1,249 cr rights issue at 27% discount Details
 
8Indosol Solar accelerates solar expansion, targets 10 GW by 2026 Details
 
8IEX Shares slide 15% after CERC clears way for market coupling Details
 
8India’s nuclear power capacity to touch 22,380 MW by 2031-32: Jitendra Singh Details
 
8Biggest problem with India's rooftop solar industry is lack of quality guarantee on end-to-end product by local installer Details
 
8Powering the Green Transition: Imperative of including TTPs in the Carbon Credit Trading Scheme Details
 
8Market Reforms: Round-up of key recent power regulations Details
 
8Comic Con India and IICT join hands to power India’s creative future Details
 
8India’s auto industry can cut emissions by 87% through green electricity, low-carbon steel: CEEW Details
 
8Arjun Mehta, Director – growth & programs, GH2 India Details
 
You can also click on Newsclips for more Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
Massive civil scope unveiled for 2x800 MW thermal expansion in eastern India
8The latest tender reveals an unusually wide scope under BOP works, spanning everything from CWPH and RWPH to solar rooftop foundations, FPS facilities, and deluge systems all in a non-BTG zone for a central PSU project, adding depth to current thermal power plant updates in India.
8In a rare instance, this BOP tender for a large 2x800 MW unit has seen its due date extended for the sixth time. The consistent extensions suggest intense bidder interest or possible scope clarification back-and-forths an emerging pattern in recent thermal power plant updates in India.
8Though BTG scope is excluded, several items like CW ducts, switchgear rooms, and reservoir outlet links imply tight mechanical/civil interface requirements for the winning bidder typical of complex thermal power plant updates in India.
8This civil-heavy scope signals how thermal power plant updates in India are now pushing higher expectations for coordination and execution even in traditionally segregated BOP packages.
8The detailed structuring of non-BTG responsibilities reflects how thermal power plant updates in India are evolving toward more integrated, interface-sensitive tendering practices. Details
Double transformer greenfield substation tender signals eastern Rajasthan grid upgrade
 
8A state transmission utility has invited bids for setting up a 2×500MVA, 400/220kV substation on a turnkey basis in eastern Rajasthan. The package includes 5 shunt reactors and full civil scope marking a major addition to the region’s backbone infrastructure and adding new depth to transformer supply contracts in India.
8Unlike earlier tenders with minimal compensation, this one calls for a total of 445MVAR through both bus-type and line-type shunt reactors. The shift signals a design focus on system stability and bulk corridor readiness, with implications for future transformer supply contracts in India.
8Compared to past projects like TN15 with only one transformer, the new bid mandates two 500MVA units. This signals either future-proofing for high load zones or redundancy against outages in RE-linked corridors a growing trend in large-scale transformer supply contracts in India.
8The new tender calls for 4×80MVAR line-type reactors a configuration absent in recent state utility bids. This could reflect tighter voltage management or a harmonics damping strategy on outbound feeders, setting fresh benchmarks for transformer supply contracts in India.
8As Rajasthan’s grid evolves into a high-capacity transmission node, such tenders are reshaping specifications and procurement trends, underscoring the critical role of transformer supply contracts in India in enabling next-gen infrastructure. Details
Tumkur solar transmission project benefits from phased central grants
8Phased central grants significantly defray costs in PGCIL's Tumkur project, illustrating a model for funding mega projects.
8Energy developers should explore similar phased funding strategies for financial efficiency.
Rs. 13,308 crore approved capital cost sets new benchmark for Southern Region
8The sanctioned capital cost of Rs. 13,308 crore for the Southern Region projects sets a significant financial benchmark, influencing tariff structures and investment strategies.
Legal appeal highlights payment delays in Uttarakhand's solar sector
8A legal appeal against UPCL for delayed solar energy payments reveals systemic issues in the state’s solar sector, impacting future investment and contractual trust.
UJVN Ltd. alleges regulatory oversight in delay due to design changes
8UJVN Ltd. argues that UERC disregarded approved design changes leading to project delays, raising questions about the Commission's methodology in distinguishing between controllable and uncontrollable delays.
Ombudsman case closed without ruling as residents find satisfaction in UPCL's billing practice
8The Electricity Ombudsman concluded the Rock Valley case without a merit decision after the association agreed with UPCL's revised billing.
8This signals the efficacy of responsive utility management.
Tribunal considers 'zero date' in tariff dispute: investment approval vs. contract award
8A key point of contention is the 'zero date' for SCOD, affecting delay calculations and financial implications, with potential industry-wide repercussions.
Click on Details for more
Details
Advanced EMS integration mandated in Bihar’s new solar–BESS tender
8For the 116MW solar + 241MWh BESS setup, the OE must oversee commissioning of EMS that integrates solar, BESS, and SCADA platforms underscoring rising complexity in hybrid control architectures and real-time dispatchability expectations in renewable projects in India.
8Unlike past RE tenders, this OE engagement covers solar pile foundations, BESS layout, SLDC interfacing, and as-built O&M infrastructure vetting suggesting stricter pre-commissioning gatekeeping in renewable projects in India for this state-owned hybrid rollout.
8BSPGCL's tender demands that OE validate the system’s ability to deliver real-time data to SLDC, a grid integration clause absent in comparable 2022 renewable projects in India tenders potentially signalling tighter scheduling and regulatory synchronization.
8As hybrid tenders evolve, renewable projects in India now increasingly feature EMS-led dispatch protocols, making OE oversight a critical checkpoint before system go-live.
8This trend highlights how renewable projects in India are transitioning from passive generation to active, dispatch-capable grid participants especially where BESS is co-located. Details
 For reference purposes the website carries here the following tenders:
8Tender for supply of 33 kV single circuit Details
 8Tender for bi annual contract for routine cum breakdown and annual shutdown maintenance work of turbine generator penstock system Details
 8Tender for bi annual contract for routine cum breakdown and annual shutdown maintenance work Details
 8Tender for bi annual contract for routine cum breakdown and annual shutdown mechanical maintenance work of 2x25 MW turbine generator Details
 8Tender for annual rate contract (arc) for supply of spares of air compressors for various Details
 8Tender for extension of new feeders Details
 8Tender for construction of new 11 kV feeders Details
 8Tender for laying of UG cable Details
 8Tender for work of protection audit of 132 kV transmission sub stations Details
 8Tender for construction of 33 kV bay at 132 kV S/S Details
 8Tender for civil works related to increasing capacity 2X40 to 3X40 MVA at 132 KV sub station Details
 8Tender for annual maintenance and repair work at 220 kV sub station Details
 8Tender for cleaning of tubes of turbine condenser of 250 MW unit-III and IV with hydro jet and water powered Details
 8Tender for procurement of unarmoured copper control cable of various sizes Details
 8Tender for supply of centrifugal single stage auxiliary cooling water pump motor set Details
8Tender for work of overhauling/cleaning of CV/ MV& VT pump misc. auxiliaries Details
 8Tender for setting up of cumulative capacity of 1555 KW grid connected rooftop solar PV power projects Details
 8Tender for setting up of cumulative capacity of 3276 KW grid connected rooftop solar PV power projects Details
 8Tender for setting up of cumulative capacity of 3055 KW grid connected rooftop solar PV power projects Details
 8Tender for work of application of nano technology-based acid and alkali resistant nano- modified anti-corrosive coating on rusted transmission line towers leges Details
 8Tender for work of overhauling/servicing of 145kV & 245kV circuit breakers Details
 8Tender for work of overhauling/servicing of 145kV circuit breakers Details
 8Tender for supply of various measuring instruments Details
 8Tender for work of operation & maintenance of mobile coal sampling equipment Details
 8Tender for work of fabrication/re pairing /erection of metallic expansion bellows at various Details
 8Tender for supply of various types & sizes of fasteners Details
 8Tender for supply, installation, testing & commissioning of 240 volt 500AH UPS battery set Details
 8Tender for supply, installation, testing & commissioning for the modernization of lift Details
 8Tender for supply and retrofitting work of 1MW solar central inverter of canal top solar plant Details
 8Tender for supply of spares for fly ash handling system Details

8Tender for supply, retrofitting, testing and commissioning of VCBs Details
 8Tender for supply, installation, testing and commissioning of hydraulic lab Details
 8Tender for supply & erection of 16 MVA,110 kV class power transformers. Details
 8Tender for replacement of 7 unit 11 kV indoor VCB panel Details
 8Tender for work of dismantling, shifting and erection of indoor equipments Details
 8Tender for supply of constant load hanger assembly for HP803 bowl mills Details
 8Tender for supply, erection, testing and commissioning of vacuum type manual gas chlorinators Details
 8Tender for supply of power switchgear spares Details
 8Tender for supply of spares for boiler feed pump Details

8Tender for painting and miscellaneous repair works Details
 8Tender for improvement works of secondary crusher house Details
 8Tender for supply of iron and steel materials, fabrication and erection of structures Details
 8Tender for attending routine and breakdown maintenance works in vacuum pumps and its accessories Details
 8Tender for supply, installation, testing, commissioning comprehensive annual maintenance contract of SCADA system Details
 8Tender for repairing of the damaged embankment portion at 10MW solar plant Details
 8Tender for replacement of existing ACSR zebra conductor by HTLS conductor Details
 8Tender for procurement of different types of LED luminaries Details
 8Tender for procurement of burner spares of unit 5 overhauling Details
 8Tender for supply and integration of RTU Details
 8Tender for RMC/AMC of fire fighting system of power house Details
 8Tender for painting of different equipment i.e. junction boxes, marshalling boxes Details
 8Tender for erection work of 66kV LILO line Details
 8Tender for supply of various size of ash pipes Details
 8Tender for work for attending puncture / leakages and replacement of various sizes service, fire / emulsifier water pipe line Details
 8Tender for overhauling of turbine Details
 8Tender for overhauling and rectifying the problem of turbine governing rack Details
 8Tender for painting for crusher house Details
 8Tender for work of erection of 66kV S/C line Details
 8Tender for outsouce activitiy of four number sub-station Details
 8Tender for extension of SHB in size 35.5ft x 28.5ft and capactior bank at 33 kV S/Stn Details
 8Tender for supply of 11 kV (5 KN ) and 33 kV (10 KN) polymer pin insulator Details
 8Tender for supply of 11 KV (45 KN) and 33 KV (45 KN) polymer disc insulator Details
 8Tender for supply of BIS certified energy efficiency level Details
 8Tender for supply of 33kV & 11kV vacuum circuit breaker Details
 8Tender for installation, testing and commissioning of 11 kV line, distribution transformer Details

 
8Tender for renewal and replacement of damaged paint electrical wiring joinery water supply sanitary and other allied civil works Details
 
8Tender for renovation and modernization of protection and measurement system of 3 no. stage-2 power houses Details
 
8Tender for procurement of 11 kV B and S type 70 kN and 90 kN disc insulators Details
 
8Tender for work of extension of switch house at 66 kV sub station Details
 
8Tender for work of extension of switch house Details
 
8Tender for procurement of coupling for fan and motor shaft of PA and FD fans Details
 
8Tender for procurement of optical bundle installed Details
 
8Tender for overhauling works of turbine & generator Details
 
8Tender for routine/breakdown/overhauling maintenance of auxiliary pumps, clarified pumps Details
 
8Tender for overhauling of pressure parts Details
 
8Tender for supply of sulphuric acid Details
 
8Tender for misc. different breakdown works Details
 
8Tender for supply, installation, testing & commissioning of multi-zone door frame metal detectors Details
 
8Tender for replacement of control & relay panel along with control cables & civil work Details
 
8Tender for supply, erection, civil, testing & commissioning work in r/o establishment of additional station transformer Details
 
8Tender for shifting of RMU and UG infrastructure for various Details
 
8Tender for supply of ESP collecting rapping gear box assembly for boiler Details
 
8Tender for supply of forged hammer ring for 500MW coal handling plant Details
 
8Tender for supply of equivalent spares of feeder breaker Details
 
8Tender for replacing the damaged polymeric asphalt membrane tar felt sheet and allied civil works Details
 
8Tender for supply of 1000 kgs TC fuse wire 16 SWG Details
 
8Tender for supply of 1000 kgs TC fuse wire 14 SWG Details
 
8Tender for supply and delivery of 8000 sets of composite hardware fittings for ACSR 30 or50 sq mm conductor Details
 
8Tender for work of replacement of H-frame by tower Details
 
8Tender for procurement of grinding roll & bull ring segment Details
 
8Tender for service contract for repairing of air flue duct Details
 
8Tender for service contract for in situ servicing of different valves PRDS SCAPH and APH wash system Details
 
8Tender for biennial contract for complete overhauling/repairing and rewinding of different LT motors Details
 
8Tender for procurement of MS ERW pipe Details
 
8Tender for work of replacement of existing old isolators of 220kV, 132kV and 33kV voltage level & strengthening/renovation of existing earthing system Details
 
8Tender for supply of coal slurry pumps and dewatering pumps Details
 
8Tender for supply of various accessories and spares for chiller AC plant Details
 
8Tender for supply of HT motors spares Details
 
8Tender for supply, erection & commissioning of complete hydrastep system Details
 
8Tender for work order for the ESP & boiler various auxiliary/equipment miscellaneous maintenance work Details
 
8Tender for supply of DC battery cell preventive maintenance work at 220 kV & 400 kV switchyard Details
 
8Tender for supply of 66kV isolators at switchyard Details
 
8Tender for procurement of spares for sprinkler system at ash dyke lagoon Details
 
8Tender for supply of discharge rods of various ratings Details
 
8Tender for work of P&F for protection of lines, using of pipe type, special earthling technique Details
 
8Tender for work 2nd circuit stringing of 132 kV line Details
 
8Tender for work of augmentation by replacement of existing 132/33kV 2x25 MVA TF by 132/33kV 2x50MVA power transformer Details
 
8Tender for replacement of CTs & jumps of 132kV bay having HTLS conductor for line various EHV substation Details
 
8Tender for work of chemical cleaning of dust/bird shit contaminated insulator string Details
 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8Tracking Growth: Demand trends and capacity expansion in the power sector Details
 8Jammu Kashmir: low river discharge hits power generation Details
 8Solar Lifeline: Lighting up homes in remote villages of Himachal Pradesh Details
 8Multibagger stock: Inox Wind wins first order from THIS energy company; shares below Rs 200 Details
 8Vena Energy signs India’s first load-following renewable power purchase agreement with SECI Details
 8First phase of green energy corridor project facing delays due to multiple reasons Naik Details
 8Just 3% of India’s 2032 wind and solar target can power its entire EV fleet: Ember Details
 8Green power, low-carbon steel key to 87% emission cut in auto industry Details

 8
India’s core industries output grows 1.7% in April Details
 
8Inox Wind secures 51 MW order from Thermax Group’s first energy Details
 
8Zelestra switches on 435 MW DC Gorbea solar plant in Rajasthan Details
 
8Reliance Industries to start solar cell production in India in Q3 Details
 
8Solar module prices on a clear downward trend Details
 
8Sharika enterprises To digitally upgrade BMM Ispat’s power infrastructure with SCADA automation Details
 
8Odisha’s homegrown young engineers power India’s first of its kind statewide Power Distribution Technology Centre Details
 
8Nash Energy and rincell corporation join hands to manufacture NMC cells in India Details
 
8AI gains bigger role in reliable and cost-effective power industry Details
 
8AIFI, BEE sign MoU to advance clean tech in forging industry Details
 
8The reform India’s power sector needed Details
 
You can also click on Newsclips for more Details
Award split validates cost-driven L1 selection in Make-in-India ecosystem
8The dual-package structure saw both awards go to MSMEs conforming to MII norms, reaffirming BHEL's GeM-based procurement filtering by cost and local content. Price spread between both packages suggests scope-size alignment with bidder strengths
8While one contract was awarded for an inland super thermal expansion (8T–10T EOTs), the other served an FGD retrofit in a southern utility (underslung and semi-gantry units). The shared tender ID camouflages these distinct application contexts
8The crane contract for a major central utility expansion was bagged by a Make-in-India-compliant MSME, with a quote near Rs. 2.15 crore. The L1 bidder’s price alignment indicates tight cost engineering despite heavy-duty specs and long baylengths. Details
8Find a snapshot of thermal, hydro, pumped storage, solar,
 wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
Swiss challenge opens IPP route for 1.5 MW hydro project in J&K
8A micro hydro scheme in Kashmir is being offered under Swiss Challenge mode, with a 40-year concession and RoFR to the originator. JAKEDA expects competitive upfront premiums as the sole bid variable, making financial structuring critical
8The bid deadline, originally set for July 10, has been extended twice—now closing July 31 for e-submission and August 1 for hard copies. This suggests muted initial participation, prompting JAKEDA to stretch timelines
8The project demands bidders to show civil infra experience pegged to per-MW capital costs, but Corrigendum-II softens thresholds from Rs. 1.5 crore to Rs. 0.9 crore/MW—opening the door for more mid-sized players Details
Third-party audit planned for Rs 9000+ crore northeast power scheme
8A high-value government-funded transmission and distribution scheme in Arunachal Pradesh and Sikkim is entering the audit phase, with a consultancy tender seeking detailed verification of over 290 infrastructure elements. The owner is a central transmission utility
8From EHV substations to rural 33 kV links, the audit scope spans all transmission and sub-transmission assets under a comprehensive T&D scheme. Both completed and pending works are within audit purview
8The third-party audit will track execution of over 3600 circuit kilometers and 1900 MVA of grid infrastructure, with site validation, GIS tagging, and milestone tracking built into consultant responsibilities
Details
Assam Faces 21 BU Power Deficit by FY36 as Existing Contracts Fall Short
8Despite planned additions, Assam could witness up to 58% unmet demand by 2035–36 prompting urgent coal tie-ups, storage deployment, and market procurement strategies.
APDCL's High-Growth Forecast Pushes Contracting Targets to 17.8 GW
8With demand CAGR at 11.2% and industrial expansion from TATA Semicon to Advantage Assam 2.0, APDCL needs to secure over 13 GW fresh capacity to maintain reliability.
RPO Compliance Slips Into Red: Assam to Miss FY36 Targets by 39%
8The state's renewable shortfall grows year-on-year despite ambitious solar and wind additions, underlining structural gaps in RE tie-ups and fungibility planning.
Click on Details for more
Details
Tamil Nadu, Puducherry Lead Pool Payables Amid Southern Grid VAR Imbalances
8Tamil Nadu and Puducherry alone account for over Rs 21.8 lakh in net reactive energy charges payable to the pool, reflecting persistent VAR drawal pattern against grid norms under IEGC 2023.
NTPC, Telangana, and Karnataka Emerge Top Beneficiaries in VAR Settlement
8NTPC’s thermal units and Telangana’s state utilities lead the receivable list, with Karnataka drawing over Rs 41.5 lakh pointing to sustained grid support by high-injection entities.
Solar Parks at Pavagada and NP Kunta Clock Cumulative Rs 2.3 Cr Payables
8Over 30 solar and wind developers including Tata, Avaada, and NTPC RE arms booked reactive energy dues, underlining growing grid management costs from hybrid renewables.
Click on Details for more
Details
Southern Grid Hits 52.8 GW Peak TN, TS, KA Drive Load Despite Solar and Gas Lulls
8Tamil Nadu (17 GW) and Telangana (12.8 GW) powered the Southern Region to a peak of 52.8 GW, but gas-based generation remained negligible, and solar availability dipped below 1.3 GW during peak hours forcing heavy thermal ramp-up and over 12 MU net UI drawals.
Northern Region Maintains Surplus Amid 74.5 GW Max Load UP Alone Draws Over 28 GW
8Despite a massive 74.5 GW maximum regional demand, the Northern grid stayed balanced on 22 July, thanks to stable thermal and solar inputs. Uttar Pradesh led with 28.3 GW peak, while Rajasthan and Punjab also clocked double-digit GWs but Himachal and Uttarakhand showed extreme ACE volatility.
North-East Grid Shows Minimal Shortage, But Assam and Meghalaya See Deviation Spikes
8The North-Eastern grid reported zero evening peak shortages, but Assam (-101 MW ACE at 10:30) and Meghalaya (-104 MW at 07:30) revealed critical demand-supply mismatches, especially in the morning ramp. Solar and small hydro support remains too shallow to stabilize intra-day spikes.
Click on Details for more
Details
NTPC Generation Trails by 14 BUs in FY26; Southern & Eastern Regions Lead Slippage
8NTPC stations cumulatively fell short by nearly 14 billion units (BU) in FY26 YTD generation, with Southern (-19.67%) and Eastern (-14.15%) regions contributing the steepest drops, pointing to demand mismatches and operational constraints.
Thermal Capacity Utilization Slips to 69%; 64 GW Offline as 22% Generation Lost
8On 21 July, 64.2 GW of generation capacity across thermal, nuclear, and hydro was unavailable translating to over 21% of monitored assets. Coal segment alone had 23.1 GW offline, with only 69.3% of total monitored capacity utilized for actual output.
Flurry of Recommissionings on 21 July: Over 20 Units Synced Back After RSD and Faults
8Units from Kawas, Faridabad, Suratgarh, Ropar, and Ratnagiri were among over 20 plants recommissioned on 21 July, many after conservation shutdowns or minor faults highlighting a day of major revival across India's base-load backbone.
Over 6.4 GW Knocked Offline on 21 July Alone Due to Boiler & Turbine Failures
8Fresh outages hit plants like Bellary, Anpara, Bhusawal, Neyveli, and Ratnagiri mostly due to P.A. fan issues, furnace fires, or condenser problems totaling a net capacity loss of 6,448 MW on a single day.
Genco Zombie List Grows: Over 100 Units Out for Over a Year, 38 GW Stuck in Grid Limbo
8Stations from Ratnagiri to Pampore and Rithala show long-term dormancy, primarily due to fuel shortages, uneconomic operation, and absence of PPAs. No clear recommissioning timeline, with some units inactive since 2012.
Hydro Holds Ground with 97% Utilization Amidst Thermal Volatility
8Hydro units delivered 39.99 GW against an available 40.4 GW representing a 97% utilization rate. This steadiness contrasts starkly with thermal generation, which hovers around 89% gross utilization.
Coal Plants Clock 3,762 MU on 21 July But Lag Monthly Targets by Over 10%
8While daily coal-based generation reached 3,762 MU, the current month’s coal target slippage widened. FY26 generation from coal stands at 456.5 BU against a target of 495.9 BU pointing to systemic delivery gaps.
Click on Details for more
Details
DAM Evening Spikes Persist as Peak Block MCPs Hit Rs 10/kWh
8Day-Ahead Market saw MCPs peak at Rs 10,000/MWh between 20:00–23:00 hours despite robust supply bids, indicating sustained demand-side stress and thin elasticity in peak-hour responses.
GDAM Solar Sell Depth Grows But Clearing Stalls Near Rs 4300/MWh
8Solar participation in Green DAM rose sharply, with MCV for solar nearing 1.5 GW in blocks, but clearing stagnated under Rs 4500/MWh spotlighting oversupply and buyer price ceiling limits.
HPDAM Logs Zero Clearances Despite 5.5 GW Supply Depth
8The High Price DAM market remained entirely illiquid throughout the day, with zero MCV or FSV recorded raising concerns on pricing structure and buyer-side visibility.
RTM Dips During Daylight, Surges to 10/kWh After Sunset
8Real-Time Market prices collapsed to below Rs 1200/MWh during solar flush but shot back to Rs 10,000/MWh in post-peak hours, exposing a yawning gap in flexible ramping resources.
Click on Details for more
Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
GIS and AIS integration raises complexity in new 160 MVA substation tender
8A new 2×80 MVA, 132/33 kV substation project in Bihar blends GIS bays at one end with AIS connections at the other. This hybrid design could escalate engineering interface risks, especially for contractors unfamiliar with GIS-AIS transition points.
8The 80 MVA transformers specified in this project must include nitrogen injection-based fire extinguishing systems. While this improves safety, it adds to the bidder's capex and maintenance training requirements, marking a shift from older tender norms.

Turnkey feeder separation project in Rajasthan sees single bidder despite multiple deadline extensions
8Despite multiple bid extensions, this turnkey RDSS project part of the wider push for transmission equipment tenders in India attracted only one technical bid for feeder segregation in Dholpur Circle. The low bidder turnout raises concerns over execution capacity bottlenecks or commercial risk perceptions among contractors.
8The project involves segregating mixed 11 kV feeders to isolate agricultural supply from other consumers, improving grid management under Jaipur discom's jurisdiction. The pattern mirrors trends seen across transmission equipment tenders in India, where large-scale turnkey projects often face limited bidder participation due to perceived execution risks.
8This development adds to a growing list of transmission equipment tenders in India encountering similar challenges, particularly under RDSS schemes targeting rural feeder separation. Sector experts suggest that the single-bid outcome may prompt a review of structuring strategies, echoing concerns from other recent transmission equipment tenders in India where project complexity has affected competition. Details
Bid deadline for Andaman rooftop solar EPC project now extended to 29th July
8Following multiple extensions, the latest submission deadline stands at 29th July 2025.
8This extension reflects bidder concerns over logistics, approvals, and bid preparation for a complex remote island execution package.
8Unlike many mainland solar EPC tenders, this package explicitly shifts the burden of net-metering approvals and DISCOM interface entirely to the contractor.
8The responsibility extends to procuring meters, taking approvals, and handling NOC clearances a critical risk factor in project timelines.

Rajasthan storage tender expands from 500 MW to 1000 MW with new site flexibility
8Unlike the earlier 500 MW storage round, which restricted location to specific plants, this new renewable energy tender in India allows developers to propose storage at any STU-connected site within Rajasthan. The shift opens up competitive location selection, with L1 bidders receiving the first right of choice—marking a significant change in how renewable energy tenders in India structure site flexibility.
8Developers are now required to guarantee battery system dispatchability from 98% in year one, tapering to 70% by year fifteen. This clause, not present in previous Rajasthan renewable energy tenders in India, shifts long-term operational risk to developers, making lifecycle cost modelling more complex and critical for bid strategy.
8Viability gap funding under the PSDF scheme is split into three stages: 20% at financial closure, 50% at COD, and 30% after the first year of operation. This staggered release pattern ties subsidy to project delivery milestones—an increasingly common feature in recent renewable energy tenders in India aimed at tightening compliance and ensuring project execution.
8Unlike merchant storage models seen globally, the entire 1000 MW / 2000 MWh capacity in this renewable energy tender in India is locked into offtake by state-designated buying entities. The tender prioritizes grid service and ancillary support, reinforcing Rajasthan’s strategy for renewable integration rather than open market play.

Details
Repeated deadline extensions signal bidder hesitation in 100 MW Gujarat wind EPC tender
8A state-backed green energy tender for wind capacity in Gujarat has seen 17 extensions, with the latest pushing the deadline to August for hard copy submissions. This pattern may reflect bidder concerns over risk allocation, land acquisition complexities, or O&M liabilities across the 10-year contract term.
8The 100 MW wind project scope requires not just EPC delivery but also land procurement, title transfer or lease, and right-of-way clearances for evacuation infrastructure up to the state transmission utility point. This all-inclusive structure may alter bidder participation strategy.
8The project is backed by a power purchase agreement signed with the state distribution utility under a wind capacity scheme. However, developers face a strict 480-day commissioning window from LOA, aligning the EPC and financial closure schedules closely with PPA milestones.

Gadarwara’s high-voltage interface package draws final bid extension
8A central utility’s 2x800 MW thermal expansion has pushed its 765 kV and 132 kV switchyard tender to a final submission date of 31st July. This follows multiple extensions since March, reflecting bidder preparation complexities and clarifications on scope.
8Unlike earlier NTPC switchyard packages, this tender mandates bidders to submit PSS/E and ETAP simulations for connectivity compliance under the latest CERC GNA norms. The change shifts more regulatory burden onto EPC contractors.
8A notable deletion in the technical amendment removes the requirement for spare cores in control cables, streamlining installation but potentially increasing project-specific customization risk during execution.
8Starting from an initial bid deadline of February, the tender has seen six extensions, with the latest moving closure to 31st July. The extensions reflect ongoing scope clarifications, particularly on simulations, fiber optic systems, and cable routing.

Details
Nuclear power enters Himachal's energy mix with 500MW proposal
8As part of its green energy goals, HPSEBL proposes replacing thermal power with nuclear, signaling a strategic pivot that could redefine the state's energy landscape and align with national sustainability targets.
DERC's handling of MYT regulations questioned in tribunal ruling
8The tribunal's scrutiny of DERC's application of Multi-Year Tariff regulations reveals lapses in regulatory compliance, affecting BSES's financial integrity.
Torrent Power's distribution license bid faces scrutiny from 39 objections ahead of July hearing
8With 39 formal objections filed, including from major unions and consumer groups, Torrent Power's bid for a Thane-Palghar distribution license faces significant public scrutiny.
Competitive pressures mount as Torrent Power eyes Pune
8Torrent Power's bid to enter Pune's electricity distribution market could intensify competition, particularly for MSEDCL.
8Industry experts are analyzing potential impacts on tariffs and supply reliability.
Nagpur power distribution: Torrent Power's strategic move under regulatory lens
8Torrent Power’s strategic maneuver into Nagpur’s power distribution is under regulatory scrutiny, a move that could alter competitive strategies.
8Insight into regulatory outcomes is vital for stakeholders.
Adani’s Navi Mumbai electricity bid: A test of regional influence
8The bid for a Navi Mumbai distribution license could redefine energy distribution, testing Adani's influence amidst substantial public and political input.
Click on Details for more
Details
 For reference purposes the website carries here the following tenders:
8Tender for renovation and modification work Details
 8Tender for preventive maintenance and emergency breakdown works in 384 KMS of EHT lines Details
 8Tender for preventive maintenance and emergency breakdown works in 278 KMS of EHT lines Details
 8Tender for replacement of plugged eroded economizer upper and lower banks in Unit V boiler Details
 8Tender for preventive maintenance and emergency breakdown works in 387 KMS of EHT lines Details
 8Tender for preventive maintenance and emergency breakdown works in 450 KMS of EHT lines Details
 8Tender for preventive maintenance and emergency breakdown works in 355 KMS of EHT lines Details
 8Tender for preventive maintenance and emergency breakdown works Details
 8Tender for procurement of XLPE insulated single core unarmoured 35 Sqmm cable Details
 8Tender for supply, installation testing and commissioning of CT PT and CVT Details
 8Tender for supply of HT and LT cables for raw water pump house Details
 8Tender for procurement of brake shoe, coolant, restore plus, contractor tip, air hose pipe, brake pipe Details
 8Tender for procurement of spares for SWAS analyzers Details
 8Tender for procurement of in line magnetic separator coil Details
 8Tender for work of maintenance & trouble-shooting of various lighting systems & routine, preventive, conditioning monitoring, shut down, breakdown maintenance & other misc. works Details
 8Tender for certain improvement and modification works Details
 8Tender for certain improvement works Details
 8Design & engineering for supply, erection, testing, commissioning for retrofitting of nodes Details
 8Tender for construction of pile foundation/open foundation in different existing 132 kV & 220kV transmission line Details
 8Tender for supply, civil, ETC works of augmentation of substations by providing additional 1x50MVA T/F along Details
 8Tender for supply, civil, ETC works of augmentation of substations Details
 8Tender for routine maintenance works related to masonry work Details
 8Tender for supply of 100 amp and 250 amp lighting distribution panel Details
 8Tender for supply of H.V. bushings of power transformers installed Details

8Tender for revetment for gantry tower D60 at proposed 110kV substation Details
 8Tender for supply of cast iron pipes Details
 8Tender for annual contract for repair of submersible motors installed Details
 8Tender for AMC services for carrying out environmental monitoring and testing in and around the plant. Details
 8Tender for work of extension of switch house Details
 8Tender for supply, installation and commissioning of portable/flexible surface mounted Details
 8Tender for supply, installation and commissioning of portable/flexible surface mounted road weigh bridge Details
 8Tender for engagement of engi. consult. firm for the complete engi.consult. services Details
 8Design, supply, erection and commissioning of VFDs in CEP motors Details
 8Tender for providing and fixing safety grill Details
 8Tender for RRT protection work Details
 8Tender for purchase of 1 No 132 kV and 2 Nos of 220 kV bushing for 220/132 kV 100 MVA transformer Details
 8Tender for supply of cables Details
 8Tender for procurement of spares for CRD of travelling trippers Details
 8Tender for work of extension of switch house Details
 8Tender for work of construction of flood protection wall rainwater harvesting system ramps and other allied works Details

8Design, fabrication, supply, installation, testing, commissioning of solar street light Details
 8Design, fabrication, supply, installation, testing, commissioning of total 126 KW grid connected solar PV power plant Details
 8Tender for work of complete overhauling of 20 cumecs capacity pump Details
 8Tender for EPC project for design, engineering, supply, testing, installation, erection, commissioning & capacity up gradation of PA fan and ID fan motors Details
 8Tender for supply of SCBA set Details
 8Tender for supply of various analytical instruments & its spares Details
 8Tender for collecting, loading, unloading and disposing of debris, fly ash/ reject coal from damper Details
 8Tender for work of fabrication of various ducts of 210 MW boiler Details
 8Tender for work of erection/ repairing of various ducts during Details
 8Tender for work of complete overhauling of 75/15 MT EOT cranes Details
 8Tender for construction of outdoor spread out type febricated switchyard Details
 8Tender for manufacture, testing, supply and delivery of 1.1kV, LT AB cable Details
 8Tender for supply, delivery, installation and commissioning of 145kV, 2500A, 31.5kA, SF6 circuit breaker Details
 8Tender for replacement of existing main switches and modification of existing wiring system Details
 8Tender for procurement of pipe and pipe fittings Details
 8Tender for supply of 11kV single pole standalone structure materials Details
 8Tender for supply of LT three phase channel cross arm Details

 8Tender for round the clock operation routine preventive and breakdown mechanical maintenance works of ash handling plant Details
 8Tender for supply of non ferric alum, hydrated lime Details
 8Design, supply, installation, testing, and commissioning of perimeter intrusion detection system Details
 8Tender for purchase of 11kV 100Amps DO fuse With polymeric insulator Details
 8Tender for laying 2.4 km 11kV HT UG cable Details
 8Tender for supplying of air break switch (AB switch) 11kV 400A, composite polymer Details
 8Design, detailed engineering, manufacturing, testing, quality control, transportation, supply at site, demonstration, complete sets of emergency restoration systems Details
 8Design, fabrication, supply, installation, testing, commissioning of total 200 KW grid connected solar PV power plant Details
 8Tender for supply of 11 kV station type surge arrester Details
 8Tender for augmentation work of 220/132kV, 100MVA transformer, dismantling of equipments Details
 8Tender for procurement of complete sets of RC shut off gates with power cylinder Details
 8Tender for procurement of seal kits of actuators Details
 8Tender for repair of air end assembly of screw air compressor Details
 8Tender for annual maintenance contract for carrying out work of dismantling, erection & other allied activities in planned outage & emergency/breakdown for power transformers Details
 8Tender for work of erection, testing and commissioning of 66kV LILO line Details
 8Tender for strengthening work of conveyor gentry, junction tower and crusher house Details
 8Tender for rate contract for work of O/H, lifting shifting of various sizes of LT motors Details
 8Tender for work of in-situ metallography of tubes / pipes, headers, blades etc Details
 8Tender for fabrication & erection of bunker partition plate, side wall, support & structure Details
 8Tender for supply of relay testing kit for testing of all types of relay Details
 8Tender for work of complete servicing / overhauling/fault attending / repairing / checking and supply of spare of various Details
 8Tender for repairing with retrofitting work of various Details
 8Tender for work of overhauling of 11kV HT motors Details
 8Tender for supply of coal discharge pipe Details
 8Tender for supply, commission & erection of 160 KVA DG set Details
 8Tender for supply of microprocessor base motor and feeder protection relay Details
 8Tender for work of O/H & servicing of boiler feed pump Details
 8Tender for supply of lime stone powder for CFBC boiler Details
 8Tender for dismantling and erection of 66/11kV indoor equipments, earthing, control wiring Details
 8Tender for supply, installation testing and commissioning of differential numeric relays at various substations Details
 8Tender for comprehensive scheme for strengthening of transmission and distribution system Details
 8Tender for annual rate contract for repair and maintenance of stage-II power house Details
 8Tender for service job for shortening of conveyor 9A and 9B by isolating bunker Details
 8Tender for works contract including materials for provision of additional earth pits Details
 8Design, supply, installation and commissioning of 10 nos 30 mtr high mast Details
 8Tender for procurement of spares of Ash water pumps Details
 8Tender for assistance in routine maintenance work at 220kV switchyard Details
 8Tender for supply, erection, testing & commissioning for 220kV D/C TSS line Details
 8Tender for construction of 132/33kV GSS Details
 8Tender for construction of 2/80 MVA 132/33kV GSS Details
 8Tender for construction of monopole for height raising of 132 kV D/C tower Details
 8Tender for work of supply, installation, testing and commissioning of 3.5 Core x 240 Sq.mm. LT armored cable Details
 8Tender for erection, testing and commissioning of dedicated 400kV metering current transformer and inductive voltage transformer and 220kV metering current transformer and inductive voltage transforme Details

 
You can also click on Tenders for more
 For reference purposes the website carries here the following newsclips:
8WattPower, first solar host solar connect in Hyderabad Details
 8India's Navitas Solar received USD-4.7m investment from Parishi Capital Details

8Juniper Green Energy commissions additional 43 MWp in Maharashtra Details
 8Wiring safety: The missing link in India’s infrastructure boom Details
 8RENK opens manufacturing facility in Tamil Nadu to boost industrial production Details
 8Massive push for domestic coal: imports dip sharply as India saves 60,681 Crore in FY25 Details
8Serentica Renewables Partners with SANY Renewable to Power 336 MW Wind Project in Karnataka Details
 8Goodbye to chargers – introducing the first electric car that charges itself while you drive, without cables or charging stations Details
 8India adds record 22 gigawatts of wind and solar in first half of 2025 Details
 8JK Srivastava Group, Hynfra join forces to build $4 billion green hydrogen and ammonia hub in Andhra Pradesh Details
 8BHEL Bags supplier excellence award from BSES for strengthening Delhi’s power backbone Details
 8AIFI, BEE forge strategic pact to drive energy efficiency in India's forging sector Details
 
8RenewSys to expand encapsulant manufacturing capacity to 30 GW Details
 
8Andhra Pradesh to develop India’s largest ecosystem for green hydrogen Details
 
8India adds 48 GW transmission for green power Details
 
8Powering India’s clean energy transition: AI, storage, and hybrid systems at the core Details
 
8L&T to set up India's largest green hydrogen plant at IOCL Panipat Details
 
8India awarded 2.2 GW of standalone battery storage projects in H1 2025: Rystad Energy Details
 
8India adds record 22GW renewables capacity Details
 
8Exemption from FGD norms eases financial pressure on coal-based power plants: CareEdge Details
 
You can also click on Newsclips for more Details
Adani, Tata Power, Power Grid and Resonia line up for high-stakes tariff bid
8With four pre-qualified players, including a major public sector giant and private heavyweights, the competition is expected to push transmission tariffs lower in the e-reverse auction stage.
 Unlike consortia bids, all four qualified entities are bidding solo, committing 100% equity into the 
SPV acquisition. This suggests confidence in project viability and financial returns under the TBCB model.
8Given the bidder profile, the tariff discovery for the 400/220 kV Velgaon substation could set a new benchmark for intra-state GIS projects in Maharashtra. Auction dynamics will determine the extent of cost competitiveness.
8With both a central transmission PSU and private sector giants in the fray, the bidding outcome may influence future dynamics of Maharashtra’s TBCB-driven transmission expansion Details
Twin 400 KV intra-state transmission projects attract fresh bidding cycle amid Karnataka grid upgrades
8Two high-capacity substation packages—one in southern Karnataka and another in the north—have been put up for tariff-based competitive bidding under REC coordination. Both projects are critical for meeting regional load growth and renewable evacuation targets, with bid deadlines now extended into August.
8Both the Hampapura and Mekhali tenders include built-in space and bay provisions for additional ICTs, line bays, and reactors. This pre-provisioning reduces future shutdown risks but also signals higher upfront capex for civil and structural works compared to older tenders.
8The Mekhali substation tender requires 63 MVAR switchable line reactors with NGR bypassing for the Dhoni-Mekhali section—reflecting a design focus on minimizing transient overvoltages during light load conditions. This specification aligns with advanced grid safety norms but requires specialized execution experience.
8Each substation comes with over a dozen bays across 400 kV and 220 kV levels, including sectionalizers, couplers, and bus reactors. For EPC players, this means complex GIS (Hampapura) and AIS (Mekhali) execution with tight timelines and interface risks. Details
8Find a snapshot of thermal, hydro, pumped storage, solar, 
wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
NTPC Trails Program by 1,382 MU as Regional Slippages Widen
8NTPC stations reported a cumulative generation shortfall of over 11.8% year-on-year, with the Southern and Eastern regions dragging down national performance despite Western zone outperformance on 19 July.
Over 44 GW of Thermal Capacity Under Outage, Nuclear Adds 2.1 GW More
8On 19 July, nearly 58.4 GW of thermal capacity was offline across coal, gas, and lignite segments. Nuclear added another 2.1 GW, pushing total grid-unavailable capacity to over 67 GW affecting over 22.4% of installed monitored base.
Fuel Shortage Continues to Haunt Gas Stations 50+ Units Idle Over a Year
8A staggering number of gas-based units, from Ratnagiri to Gautami and Jegurupadu, remain indefinitely out due to chronic fuel constraints revealing long-term structural challenges in gas procurement and scheduling across multiple states.
Faridabad to Darlipali: 28 Units Synced Back on 19 July After Varied Shutdowns
8A flurry of recommissioning activity saw 28 major units, including from Faridabad, Anpara, Sasan, Bhusawal, and Darlipali, come back online indicating a rapid normalization of assets after brief or seasonal halts.
5.7 GW Offline on Just One Day: 19 July Logs Heavy Daily Grid Losses
8CEA logs show 5715 MW of fresh grid loss on a single day due to boiler, condenser, fuel supply, and ash handling issues raising flags on O&M robustness even as monsoon demand remains moderated.
Hydro Output Climbs to 81.7% Utilization as Thermal Plants Lag Below 70%
8Hydro stations led by Himachal and Northeast units operated at nearly full load with 94.8% peak output vs monitored capacity, outperforming coal and gas counterparts that remained below 70%.
Lignite Capacity Runs at Just 43%, Gas at 35% Despite Installed Base
8Lignite and gas-based power generation remain grossly underutilized, with utilization at 43% and 35% respectively, reflecting continued issues in offtake agreements, fuel security, and cost viability.
Year-to-Date Generation Gap Widens to 62 BU Thermal Core Still Lags
8As of 19 July, India has generated nearly 63 BU less than planned, with thermal sources accounting for the bulk of the deficit. NTPC and nuclear offset some pressure, but hydro’s high seasonal load could narrow the gap if sustained.
Click on Details for more
Details
India Breaches 27% VRE Share in Afternoon Peak: Solar Punch Lifts Grid Dynamics
8On July 20, variable renewables clocked a peak share of 27.39% of national demand at 13:16 hours, with solar alone touching 20.55%. A midday solar surge pushed VRE output to 55.7 GW, exposing grid stress points and renewable variability risk.
Ancillary Services Swing to Historic Deficit as TRAS Down Surpasses 25 GWh
8On July 20, TRAS downward dispatch surged to -25,691 MWh, outstripping upward dispatch by nearly 5:1. This imbalance, coupled with a 4092 MW max downward requirement, signals over-commitment amid volatile renewable generation.
Grid Frequency Dips Below 49.6 Hz as Evening Demand Peaks New Stability Concerns Surface
8On July 21, frequency plummeted to 49.590 Hz at 19:46, coinciding with high load conditions and sagging reserves. The Frequency Deviation Index (FDI) stood at 27.4, with nearly 6.5 hours outside the IEGC band, highlighting load-generation imbalance.
Zero Corridor Violations for Fourth Straight Day But Local Voltage Breaches Continue
8Despite no interregional ATC or N-1 violations on July 21, high voltage excursions occurred at Ajmer, Chittorgarh, and Nizamabad, with over 1.7% time spent beyond 420 kV. Peripheral nodes still challenge real-time voltage compliance.
Angular Spread Flags Persistent Instability at Vindhyachal Node Wide Divergence with Eastern Sites
8Angular spread across 23 critical nodes showed outliers at Vindhyachal, pointing to persistent phase angle stress vs Balipara and Silchar. Reactive power dynamics and loop flows may be contributing to increasing localized grid strain.
Click on Details for more
Details
DAM Clears 197 MU, But Rs10/kWh MCPs Grip Evening Blocks
8Power prices in DAM plunged as low as Rs 2119/MWh during solar hours but peaked at Rs 10000/MWh post 19:00 hours for six consecutive blocks, highlighting a stretched evening ramp and demand peak pressure
GDAM Sees Solar Rejection Despite 5 GW+ Sell Offers
8Though solar bids surged in GDAM with over 1.7 GW offered in multiple blocks, solar FSV hovered below 1.1 GW as prices stayed capped at Rs 4300/MWh or lower, revealing latent oversupply and price mismatch
HPDAM Remains Illiquid Zero Clearing Despite 5.5 GW Sell Depth
8HPDAM saw consistent sell-side bidding at over 5 GW throughout the day, but no buyer-side response was recorded This signals either a regulatory or incentive design failure for high price demand aggregation
RTM Mirrors DAM: Rs 10/kWh Evening Prices Amid Morning Lull
8RTM cleared over 153 MU, with MCPs between Rs 2600–Rs 4000/MWh during solar hours But evening blocks again saw price cap saturation, replicating DAM’s stress pattern and hinting at structural ramping inadequacies
Click on Details for more
Details
Compliance Crunch: 18 Units Still Lag PSS Mandate in Southern Grid
8Despite regulatory compulsion under IEGC 2023, 18 generating units across the Southern Region have not submitted PSS tuning reports raising reliability red flags amid growing RE share.
OEM Gaps Undermine Field Validation; SRPC Pushes for Accountability
8Several generators flagged that OEMs are either skipping mandated tests or refusing to provide technical rationale prompting SRPC to demand documented justification and stricter testing protocols.
RE Grid Realities Amplify PSS Urgency: SRPC Warns of Inertia Collapse
8With synchronous machines declining and RE integration surging, SRPC warns that poorly tuned PSS units now pose critical risks to low-frequency damping and grid resilience.
Click on Details for more
Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal and Coke
8LPG
8Ammonia
8All tankers
8Bulk and Dry cargo
Click on Reports for more. Details
 < 1 2 3 4 5 >  Last ›

Showing 101–150 of 351 items