8The TOR is under examination of MoEF. 8The MOU was signed with the state government for implementation of the project. 8The RFQ for the DPR consultant is likely to float in Q4 2022. Click here for more detailsDetails
8Application for PTCC, civil aviation, and defense have been submitted. 8Soil test was completed for the additional land. 8Forest clearance is in progress at the nodal office. 8RFQ for the EPC package for T/L works is likely to be floated in October 2022. Click here for more detailsDetails
8Geotechnical investigation and topographical survey have been completed. 8Collection of three-season monsoon data was completed and preparation of hydrology report is in progress 8Construction of the approach road works is in progress. Drilling and drifting works at the site are in progress. 8The RFQ for the SIA consultant is likely to float in September 2022. Click here for more detailsDetails
8The project was delayed for several years due to shortcomings in the DPR report. 8 TOR for the same was accepted by the MoEF 8The DPR consultants were selected. Find out who were the major contenders in the price bid. 8The RFQ for the EIA/EMP consultants is likely to be floated in October 2022. Click here for more detailsDetails
8The world is currently far from a net-zero emissions trajectory 8Getting to net zero will not be easy and will require some transformative changes Click on Details for moreDetails
8Telangana has punched holes in the recently announced power ministry policy on connectivity to central generating stations with interstate transmission systems Click on Details for moreDetails
8Nepal is a small country but the addition of more and more power generation into the system, the existing aging transmission arrangements are inadequate to evacuate power to load centers. 8So a raft of transmission projects are coming up Click on Details for moreDetails
8Wind power projections are subjected to vagaries of nature 8And this time around, the projection in this region was 22% off the mark Click on Details for moreDetails
For reference purposes the website carries here the following reports: 8DMR Hydroengineering & Infrastructures Ltd has appointed a director. Click on Reports for more 8An International Dam Safety Conference is coming up Click on Reports for more 8Websol Energy System Ltd gets an independent director Click on Reports for more 8Abir Infrastructure Private Limited: Find out why it is not cooperating. Click on Reports for moreDetails
8Power demand during July 2022 was up to 2069 MW less than June 2022 8Meanwhile, consumption was 28775 MU which is around 1762 MU less than the consumption during June 2022 8Find out more Click on Reports for moreDetails
8IREDA has signed an MOU with a renewable firm for RE projects to be implemented for state utilities, local bodies and the infrastructure of Renewable Energy Parks 8Find out more Click on Reports for moreDetails
8The company has secured a Mine Development & Operation (MDO) project from CCL 8This project will strengthen the already robust order book even further and enable the Company to diversify its order book 8Find out more Click on Reports for moreDetails
8Grid security is getting compromised as some stakeholders are shutting down Restricted Governor Mode Operations (RGMOs)| 8This has been termed as a dangerous trend given the huge installed capacity of renewable power Click on Reports for moreDetails
8Climate tech finance is a complex subject 8And in India is even more complicated, as approvals are not easy 8Find out what those who are involved or interested in such funding have to say Click on Reports for moreDetails
For reference purposes the website carries here the following tenders: 8Tender for annual maintenance contract of coal milling system Details 8Tender for routine maintenance, preventive maintenance and overhauling of LT motors Details 8Tender for overhauling of OLTC (on load tap changer) of power transformer Details 8Tender for annual maintenance contract of boiler Details 8Tender for annual maintenance contract of turbine & generator Details 8Tender for operation of condensate polishing unit Details 8Tender for work of tower footing resistance measurement Details 8Tender for the supply of PVC LT line spacers Details 8Tender for work of centering, alignment & balancing of all units a hydro generating station Details 8Tender for retrofitting of ACB in Place of DK21 contractor modules Details 8Tender for annual maintenance of power station Details 8Tender for balance civil works of Ash disposal pipe line Details 8Tender for annual breakdown /running maintenance of H.P./ L.P. valve of boiler and turbine Details 8Tender for round the clock routine maintenance of turbine & its auxiliaries Details 8Tender for round the clock operation and maintenance of complete coal handling plant Details 8Tender for replacement of collapsed/ damaged 05 Nos. 220 KV Details 8Tender for replacement of GIS software Details 8Tender for procurement of hydrogen gas Details 8Tender for procurement of double disc segregating valve for vacuum lines Details 8Tender for design, manufacture, supply, erection, testing and commissioning of control and relay panels Details 8Tender for procurement of various types T&P power house Details 8Tender for procurement of grinding roll and bull ring segment of XRP 1003 coal mill Details 8Tender for work of construction of 03 Nos RCC retaining walls Details 8Tender for work of circuit stringing of 132kV substation Details 8Tender for annual maintenance of switchyard Details 8Tender for AMC for repairing, servicing and testing of healthiness of nitrogen (N2) injection fire prevention Details 8Tender for work of revamping of 33/11KV electrical distribution system Details 8Tender for supply and supervision of erection, testing & commissioning of steam and water analysis system Details 8Tender for supply and supervision of erection, testing and commissioning of large diameter butterfly valves Details 8Tender for supply and supervision of erection, testing and commissioning of 11kv isolated phase bus duct (IPBD) Details 8Tender for work of inspection, servicing, overhauling & rectification of on load tap changer Details 8Tender for work of AMC for servicing /overhauling of various make 11KV circuit breaker Details 8Tender for work of providing & fixing Spike type bird Guards Details 8Tender for work of construction of 33KV AIS bay at 220KV substation Details 8Tender for AMC for carrying out breakdown maintenance and routine maintenance of 400 KV line Details 8Tender for supply and installation of power quality analyzer Details 8Tender for transportation of the ash from ash dyke/silos Details 8Tender for taking delivery of raw coal from mine Details 8Tender for turnkey construction of 132kV traction bay Details 8Tender for supply and replacement of parts of GT Details 8Tender for work of requirement of equipments, materials and various balance works for updation of 220 kV S/S Details 8Tender for augmentation of substation by addition /replacement of transformers Details 8Tender for work of providing/fixing special type maintenance free earthing with extra high current carrying capacity earth pits Details 8Tender for work contract for height raising work of 132 kV line Details 8Tender for the supply of G.I. wire Details Click on Tenders for more For reference purposes the website carries here the following newsclips: 8Coal-based power plants’ PLF to hit 5-year high this fiscal: Crisil. Details 8Tata Power : TP Renewable Microgrid and SIDBI collaborate to set up 1,000 green energy enterprises nationwide to support rural entrepreneurs Details 8Norway announces 49 pc stake in solar power plant in Rajasthan developed by Italian Enel Details 8Hyundai mulls speeding up construction of US EV plant amid new law Details 8India at 75: The growing EVolution in auto industry Details 8Electricity Bill 2022 is a remedy worse than the disease afflicting India’s power sector Details 8CM Yogi hold meeting to review state's energy requirements, demands new solar energy policy Details 830,000 incidents of power failure across Maharashtra in June Details 8Nepal exported electricity worth nearly Rs 2 billion to India in first month of FY 2022/23; plan to export an additional 111 MW Details 8ONGC readies to pump geothermal power at 14,000 feet in Ladakh Details 8Green energy plans have an import problem Details 8L&T to invest up to $2.5 billion in green energy Details 8Ravindra Kumar Tyagi joins POWERGRID as Director Operations Details 8New Study Alerts Investors in Solar/ Wind Energy As Climate Change Adversely Impacts The Future Trends Details 8Power utilities' debarment shows India needs to fast-forward electricity reforms Details 8Adani’s open offer for Ambuja Cements, ACC gets approval Details 8We have to make Indian infrastructure up to world standards: Gadkari Details 8Bharat signs key hydro-deal with Nepal replacing China Details 8The case for a comprehensive Indian climate bill Details 8Union Minister Jitendra Singh unveils India's first Hydrogen fuel cell bus Details 8Adani Power gains 4%, hits new high on DB Power deal; up 47% in one month Details 8Centre's plan on sale of RE power to states offers only a flickering hope Details Click on Newsclips for moreDetails
8The additional land requirement was approved by the MoEF 8Wildlife clearance has been granted by the warden. Forest clearance stage 1 and stage -2 have been granted by the DFO 8Price bid will be opened soon for civil works (lot-1 and lot-2). Find out who are the major contenders in the technical bids. 8The RFQ for the HM works packages is likely to be floated in Q4 2022 Click here for more detailsDetails
8The geotechnical investigation and topographical survey works have been completed and the reports are under examination by GSI 8 The preparation of the SIA report has just started. 8Consultant selected for PMC works, get the name here. 8The RFQ for the drilling and drifting work is likely to be floated in September 2022. Click here for more detailsDetails
8The project will be financed by JICA. 8The project was newly allocated to the owner due to shortcomings in earlier PFR and other reports. 8WAPCOS has been selected as a new PFR consultant. 8Re-assessment of Geotechnical investigation and topographical surveys are in progress. 8EOI for EIA/EMP consultant is likely to be in Q4 2022 Click here for more detailsDetails
8Drilling and drifting works have been completed. 8Preparation of DPR completed and the report is under examination by CEA. 8Land acquisition and the rehabilitation, and resettlement works have been completed. 8Forest clearance stage 1 was granted by the DFO and stage 2 is in progress at the regional office. 8 RFQ for the civil works package (lot-1&2) is likely to be floated in September 2022. Click here for more detailsDetails
8TOR has been granted by the MoEF&CC. 8Drilling, drifting works are in progress at the site 8The public hearing was completed. 8Geotechnical investigation and topographical survey report have been accepted by the GSI. 8RFQ for the PMC package is likely to be floated in October 2022 Click here for more detailsDetails
8Application for PTCC, civil aviation, and defense have been submitted. 8Soil test is in progress for both the pooling station and the transmission line. 8Meetings were conducted with the landowner for private land acquisitions. 8RFQ for the EPC package for T/L works is likely to be floated in October 2022. Click here for more detailsDetails
For reference purposes the website carries here the following reports: 8Get a fully updated list of manufacturers of solar equipment Click on Reports for more 8Torrent Power plan to appoint new director Click on Reports for more 8Nine more coking coal washeries coming up Click on Reports for more 8Palimarwar Solar Project Private Limited: Rating withdrawn Click on Reports for moreDetails
8The low carbon era is likely to be far more material intensive than the fossil fuel era 8India is incentivising domestic manufacture of RE equipment, but it is not likely that this effort will reduce the import of key minerals and technologies for the production of solar modules and batteries. 8Investment in relatively high-cost domestic manufacturing will effectively increase the cost of reducing carbon emissions and may misallocate scarce capital that may be better employed in adaptation measures for climate change 8Find out more Click on Reports for moreDetails
8Bids are invited for an expert consultant for providing Project Management Consultancy (PMC) services for implementation of 1200 MW Solar Park 8Find out more Click on Reports for moreDetails
Here is an update on capex plans for hydro power projects 8500 MW Hydro Electric Project 82100 MW Pumped Storage Project 8168 MW Hydro Electric Project Click on Reports for moreDetails
8ReNew's corporate tariffs are cheaper for customers than alternatives 8The company has total 1.3GW Corporate PPA portfolio of which 616 MW is commissioned as of 1QFY23 8Find out more Click on Reports for moreDetails
8The generator has signed a MoU with Investment Board Nepal for preparation of DPR and development of two hydropower projects in Nepal 8Find out more Click on Reports for moreDetails
8KTL is a 100% subsidiary of L&T Infrastructure Development Projects Limited. The project involved the construction of 400/765 kV D/C lines of 482-km length in Karnataka on BOOM basis, to evacuate power from the Kudgi thermal power plant of NTPC Ltd. 8KTL has signed a fixed price O&M contract for the next one year, which provides some comfort Click on Reports for moreDetails
8What is the projected price increase as a result of the imposition of duties on imported solar modules and cells? 8Here is a realistic estimate 8Also, how long will the uncertainty last? Click on Details for moreDetails
8A whole set of transmission outage programmes have been approved 8Business opportunities are likely in quite a few of them, requiring repairs Click on Reports for moreDetails
8Ministry has executed agreements with the successful bidders for 16 coal mines. 8These coal mines are expected to generate employment for 32000 persons directly & indirectly 8Find out more Click on Reports for moreDetails
8The renewable open access market faces all kinds of hiccups 8And unless these are removed, particularly at the state level, really high growth rates will evade this segment Click on Reports for moreDetails
8This public sector company has a Rs 10,000 crore capex for the next financial year 8What kind of the IRR is the company looking at for this kind of capex? 8Find out more Click on Details for moreDetails
For reference purposes the website carries here the following tenders: 8Tender for the supply of 11 kV/433 V, 500 kVA distribution transformers Details 8Tender for providing and fixing of steel lagging and steel Ribs at the initial reach in mat of power house Details 8Tender for laying of tower foundations, erection of towers, stringing and sagging of conductor Details 8Tender for work contract for bay extension, breaker erection in 110/22 KV substation Details 8Tender for RLA of Boilers during overhauling Details 8Tender for overhauling of HP, LP valves, NRVs, actuators and heat exchangers Details 8Tender for annual maintenance contract of turbine and auxiliary system Details 8Tender for annual maintenance contract for assistance in operation, running maintenance at CHP Details 8Tender for works of routine, preventive / breakdown maintenance of XRP 1003 bowl mill Details 8Tender for operation & maintenance of 33 KV, 11 KV & LT lines Details 8Tender for supply and delivery of copper wound CRGO core station service distribution transformer Details 8Tender for supply, installation and commissioning of fabric compensator Details 8Tender for installation of 11/0.4 KV 990 KVA CSS Details 8Tender for operation and maintenance of PDFAC system and wet sluice system Details 8Tender for work of repair and maintenance of false ceiling main power house Details 8Tender for construction work of LILO of 220 KV Details 8Tender for work of replacement of old equipment by new equipment at 400kV substation Details 8Tender for work of AMC for attending emergency breakdown, scheduled works and other urgent works on various EHV lines Details 8Tender for supply and installation of digital interactive display (LED) Details 8Tender for annual maintenance contract for supply of spares and repairing of ABT metering system Details Click on Tenders for more For reference purposes the website carries here the following newsclips: 8Capital and Investment mulls 30 MW solar power farm in TN Details 8India added 1.9GW of renewable energy open access capacity in FY 2022 despite regulatory bottlenecks Details 8Power cost variation of discoms to be passed on to consumers Details 8Ola Electric wants to disrupt India's car industry. Does it have what it takes Details 8Power Mech Projects Limited BagsFGD Projects of Rs. 6 163.20 Crores from Adani Group Details 8Mumbai-based e-tractor start-up AutoNxt Automation raises Rs 6.4 crore in seed round Details 8Vikram Solar Gets Sebi Nod To Mop-Up Funds Via IPO Details 8REC to showcase its new Alpha Pure-R solar at Renewable Energy India Details 8Sun Mobility partners EVeez for deploying 10,000 electric two-wheelers by 2023 Details 8MK Stalin ‘raises objections to Neet, NEP, Karnataka’s dam plan and power bill in meet with PM Modi’ Details 8Electric double-decker bus new attraction in Mumbai's BEST fleet Details 8More than 107 coal mines to be auctioned in near future: Pralhad Joshi Details 8Coal mining lease SC imposes Rs one lakh cost on Centre for its callous approach Details 8Renewable Energy India: REC showcases its new Alpha Pure-R solar panel Details 8Solutions to India’s jobs problem lie in creating better regulatory conditions for private sector while protecting rights of workers Details 8What is Electricity (Amendment) Bill 2022? Details 8The Drive to The Future with E-Mobility - Building India’s EV Char]ging Infrastructure through Clean Energy Details 8India targets 900 million tonne coal production in FY23: Minister Details 8Power Engineers' body opposes competition in sector Details 8PLI wind beneath renewables wings Details 8Goldman-Backed ReNew Secures $1 Billion Loan for India Project Details 8The woes of power: A moderate approach to the discom sector might be the answer Details Click on Newsclips for moreDetails
8The survey and investigation work for the T/L from the powerhouse to the common P/S has been completed 8 Mobilization has been completed. Excavation and boring works for HRT are in progress. 8The techno-economic clearance and forest clearance (Stage-I&II) have been accorded. 8The 400 kV GIS S/S works are likely to be floated in September 2022 instead of August 2022 due to delays in the P/S survey and investigation works. Click here for more detailsDetails
8The Water Resource Department and Energy Department have approved the project. 8DPR is in the advanced stage for completion. Pre-DPR chapters have been approved by the CEA. 8EIA/EMP and SIA studies are in progress and it is in the advanced stage of completion. 8The Civil works package(lot-1) is likely to be floated in the second half of Q4 2022 instead of Q3 2022. Click here for more detailsDetails
8Geotechnical investigation and topographical survey works were completed and the reports are under examination by GSI 8 FC stage -1 is pending at the nodal office. 8Drilling and drifting works at the site are in progress. 8RFQ for the SIA consultant is likely to be floated in October 2022. Click here for more detailsDetails
8The generator had planned shutdown of 500 MW unit at Rihand and 110 MW unit at Tanda TPS 8But OCC forum has Rejected the planned shutdown request by NTPC 8Find out why? Click on Details for moreDetails
8The state plans to generate 17,360 MW of solar energy with a few more projects in the pipeline for the next five years Click on Details for moreDetails
8India will need an investment of Rs 4 lakh crore for the implementation of 113 GW of renewable energy (RE) projects in the pipeline Click on Details for moreDetails
8Indian wire and cable market, which stood at USD 8.5-9 billion in FY21 is expected to grow by over 10% per annum in medium term. 8Get to know more about the company which is enjoying the tailwinds from this growth in this niche segment Click on Reports for moreDetails