Aug 2022

8The TOR for the same project was granted.
8The owner has selected Mantect as an EIA consultant.
8The application for forest clearance was pending at the nodal office.
8The baseline report was accepted by the CWC and the hydrology report is in progress.
8The RFQ for the SIA consultants is likely to be floated in October 2022.
Click here for more details Details
For reference purposes the website carries here the following tenders:
8Tender for replacement of existing obsolete programmable logic controller [PLC] based control system Details
8Tender for annual rate contract for complete overhauling/repairing and rewinding of different LT motors Details
8Tender for work of upgradation of 66kV substation Details
8Tender for work of laying 4500mtr XLPE UG cable Details
8Tender for EPC of green hydrogen pilot project, operation and maintenance of green hydrogen Details
8Tender for work of biennial maintenance contract of make UPS system Details
8Tender for augmentation of 132 KV substation Details
8Tender for AMC for the work of overhauling /servicing of 245kV circuit breakers at various substation Details
8Tender for work of replacement of existing old 220KV 1250A 0.5MH Wave trap by 220KV,2000A, 0.5MH, Wave trap Details
8Tender work of installation of earthing & renovation of earth mat Details
8Tender for AMC for the work of overhauling /servicing of 145kV circuit breakers at various substation Details
8Tender for dismantling, fabrication, erection of ETP clarifier Details
8Tender for maintenance of bottom ash hopper and DP extension /diversion of ash slurry disposal pipelines Details
8Tender for routine, preventive, breakdown & shutdown maintenance work of motorized & pneumatic operated valves & gear box Details
8Tender for design, engineering, manufacturing, supply, erection, testing, commissioning & Civil works on turnkey basis for construction of 66/22 kV sub-stations Details 
8Tender for ARC for electrical maintenance Details
8Tender for replacement of old ACSR conductor & ACSR rabbit conductor and laying of LT AB cable Details
8Tender for construction and increasing capacity of 11/0.4 KVA transformers Details
8Tender for works contract to carry out the erection of poles, distribution transformers Details
8Tender for maintenance and periodical maintenance work in the cooling water pumps Details
8Tender for procurement of grinding roll lock nut for BHEL make coal mill Details
8Tender for procurement of GI rigid conduits for station lighting Details
8Tender for procurement of personal protective equipments Details
8Tender for procurement of 9kV and 18kV, 5KA lightning arrestors polymeric type Details
8Tender for procurement of spares of coal burners Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8Policy support, competitiveness to fuel growth of renewable energy in Emerging Asia: Moody"s Details
8KP Energy to develop wind energy projects worth Rs 222 crore for Aditya Birla Group Details
8India Submits Updated NDC To UNFCCC, Says It's A Step Towards Net-Zero By 2070 Details
8Groundbreaking advances emerging vehicle battery production Details
8Bengal coal scam: Calcutta HC allows Maneka Gambhir to appear at ED's Kolkata office Details
8Serbian gov't publishes energy saving measures Details
8First Solar Pledges Big U.S. Factory Expansion Thanks to Climate LawDetails
8Ather Energy plans to open 150 Experience Centres across India by Mar '23 Details
8Adani Electricity investing Rs 500 cr for smart meter installations in Mumbai Details
8NHPC to sell hydro power to PTC India from upcoming Nepal projects Details
8Promoters to infuse Rs 800 cr into Inox Wind by subscribing debt Details
8Coal companies to bring more than 2,400 ha area under green cover this year Details
8Green energy will be growth driver, hydrocarbon capex to be decent: L&T Energy Head Details
8Indian wind energy issues need more attention Details
8Here's how EVs will play a big part in India's mission to go carbon neutral by 2070 Details
8Energy-Independent India —Why It Is Time To Take Electric Vehicle Technology More Seriously Details
8Coal India Says Price Hike Not Imminent Despite Higher Costs Details
8Wind energy has huge potential in India, to cost less by 2026: GWEC Details
8Incentivisation of green technologies in India Details
8How Nuclear Energy Can Aid India's Net-Zero Journey Details
8Why is there opposition to the proposed Electricity Amendment Bill? Details
8Azure Power announces the resignation of Harsh Shah as CEO Details
You can also click on Newclips for more
Details
8The DPR has been approved by the Godavari River Management Board.
8The construction works are getting delayed due to harsh weather and inaccessible terrain.
8Mobilization of construction equipment has been completed.
8The pre-bid has been conducted for the civil works package(lot-2) and technical biddings are in progress.
8The HM works are likely to be floated in Q4 2022.
Click here for more details Details
For reference purposes the website carries here the following reports:
8AFC allowed for transmission asset under “System Strengthening Scheme XVII” in Western Region. Click on Reports for more
8KP Energy Ltd to appoint new director. Click on Reports for more
8Find out the Transmission Charges for DICs for the billing month of September, 2022. Click on Reports for more Details
8Haryana Electricity Regulatory Commission (Fee) Regulations, 2005 has been amended
Click on Reports for more
Details
8Haryana will offtake 50% of the capacity declared by NVVN
8Find out why?
Click on Reports for more
Details
8PGCIL gets approval to raise funds up to Rs 6,000 crore from domestic market
Click on Reports for more
Details
8A solar generator had sought initiation of action against HVPNL
8But generator has been disappointed due to no stake in the solar project
Click on Reports for more
Details
8Jharkhand plans to procure 700 MW Solar power through SECI to fulfil its RPO
8The state regulator didn't adopt the tariff
8Find out why?
Click on Reports for more Details
8NTPC gets approval to raise funds up to Rs 12,000 crore
8Also gets approval to appoint director
Click on Reports for more
Details
Find out an update on capex plans for captive power plants: Following capacities are coming up
84.5 MW Captive Power Plant
83 MW Captive Power Plant
815 MW captive power plant
85.3 MW Cogen Power Plant
84.8 MW Power generation
85 MW Cogen Power Plant
84 MW Cogen Power Plant
Click on Reports for more
Details
8Greaves continued to emphasise on its new revenue streams, led by its EV business, which is well poised to be a significant beneficiary of EV adoption in India
8The company is lately focusing on developing EV retail brand, Auto EV Mart arm, which is focusing on retailing multiple brands in e-2Ws
Click on Reports for more
Details
8Power evacuation from 1000 MW solar park.
8 Forest clearance stage -1 is pending at the DFO.
8Detailed surveys and investigations have been completed.
8Land acquisitions are in progress for the sub-station and pooling station
8RFQ for the 400kv GIS S/S works is likely to float in Q4 2022.
Click here for more details Details
For reference purposes the website carries here the following tenders:
8Tender for supply and application of silicone coating on insulators details
8Tender for procurement of different luminaries with fixtures and accessories for various 
power houses details

8Tender for annual contract for operation and routine electrical maintenance works details
8Tender for work of common meter reading instrument  details
8Tender for capital overhaul of turbine and generator set  details
8Tender for design, supply, erection and commissioning of automatic rotary scoop type coal sampler  details
8Tender for works contract in respect of rural/ feeder segregation with bay extension in 22 KV feeders  details
8Tender for procurement of microprocessor based controller for gravimetric coal feeders   details
8Tender for procurement of chlorination system spares details
8Tender for providing assistance in routine day-to-day maintenance work of coal mill & coal feeders details
8Tender for purchase of spares parts of seal water pump  details
8Tender for maintenance of railway track and other related capital works  details
8Tender for annual operation works of 132KV substation  details
8Tender for loading, unloading & stacking of any material  details
8Tender for design, manufacture, testing, supply & delivery of isolators  details
8Tender for permanent restoration of damaged panels  details
8Tender for emergency unforeseen works of HEP old ganderbal caused due to natural calamities details
8Tender for providing 11KV HT line with AAAC 7/4.26mm2 condt. and AB cable details
8Tender for the supply of numerical protection relays  details
8Tender for work of inspection, servicing, overhauling & rectification of on load tap changer (OLTC) details
8Tender for supply, erection, testing and commissioning of additional 1 x 25MVA, 132/33 kV T/F along with bay equipments  details
8Tender for supply & installation of lighting arrestor  details
8Tender for work of circuit stringing of 132kV line substation  details
8Tender for work of PID testing of insulator strings on 400KV lines  details
8Tender for work of counter poise type tower earthing for 220KV & 110KV lines  details
8Tender for work of stub-strengthening of 220KV 110KV & 110KV line  details
8Tender for work of repair & maintenance of loading, unloading & stacking platform details
8Tender for work of AMC for servicing / overhauling of 11KV circuit breakers details
8Tender for survey work of estimate of 100KV, 220KV. 400KV EHV/HTLS lines details

You can also click on tenders for more
For reference purposes the website carries here the following Newsclips:
8Bhopal: Power department plans unmanned operation of 400 KV sub station Details
8Bengaluru To Have Electric Vehicle Charging Stations At Every 500 Metres By FY24 Details
8EV startup Faraday Future refutes claims made by top shareholder Details
8Ather Energy opens third expertise centre in Chennai Details
8Dutch wind farm overcomes opposition by selling shares to residents Details
8CIL hasn't raised prices in 4 yrs, planning to list BCCL, CMPDI: Chairman Details
8BPCL targets net zero, 10 GW of renewable energy by 2040 Details
8Cochin International Airport: India's champion in sustainable energy Details
8Giga power electronics unit to complete the circle of RIL’s green industry Details
8CAG faults Puducherry Electricity Department Details
8Interest In Nuclear Power On Rise As Cost Of Importing Energy Increases Details
8Power sector subsidy mostly myth Details
8EESL installs 10 lakh smart prepaid meters in Bihar Details
8Reliance Industries aims for 20 GW solar generation capacity by 2025 Details
8Centre directs Telangana Discoms to clear Rs 6.7K crore dues to AP Genco Details
8Manoj Sharma PFC’s new director (comm) Details
8Growth of Indian OEMs and challenges faced by them Details
8India’s Millions Consume More Than The Country Can Sustain Details
8Telangana ranked fourth in India in solar energy sector Details
8Coal India Rating: buy; Strong demand to boost earnings Details
8Power Grid delays tender that pushes outdated tech in smart meters Details
You can also click on Newsclips for more

Details
8Decommissioning works at the site have been completed.
8Pilling and foundation work at the BTG area have been completed.
8Sub-contractor has been selected for the conveyor system
8The RFQ for the Wagon Tripler package is likely to be floated in October 2022.
Click here for more details Details
8The detailed survey and investigation were completed.
8Approval from the civil and defense aviation department has been granted.
8Contractor selected for S/S works. Civil works are in progress.
8RFQ for the 765kV P/S works is likely to be floated in October 2022.
Click here for more details Details
8The project got delayed due to the villager's protest and inaccessible terrain in the project area
8The consultant has completed the detailed survey and investigation including a geotechnical investigation.
8The hydrology report for the same has been completed and it was accorded by the CWC.
8The RFQ for the PMC package is likely to be floated in Q4 2022.
Click here for more details Details
8FC stage-2 has been granted by the DFO
8Mobilization of equipment has been completed by the contractor.
8Construction of the approach road has been completed.
8The excavation works are in the active phase of construction.
8The RFQ for the HM works package is likely to be floated in Q4 2022.
Click here for more details Details
For reference purposes the website carries here the following reports:
8Power finance corporation gets director (commercial). Click on Reports for more
8Vijay Transformers: Non-Cooperating with rating agency. Click on Reports for more
8India Grid Trust appoints new CEO. Click on Reports for more
8lndosolar Ltd director appointed. Click on Reports for more
8ABB India to appoints a director. Click on Reports for more
8Hind Aluminium Industries Ltd gets director. Click on Reports for more Details
8Rajasthan needs to improve the voltage profile by providing required reactive power compensation
Click on Reports for more
Details
8NTPC’s board has approved an investment for 1320 MW Thermal Power Project
8The decision has been triggered by power cuts in a few states and strong upsurge in power demand
Click on Reports for more
Details
8Government has decided to reduce allocated power of Punjab
8Find out how deep a cut was imposed
Click on Reports for more
Details
8A biomass generator had sought directions to MSEDCL for Late Payment Surcharge (LPS) on energy bills
8Late Payment Surcharge should be paid as per provision of EPA (within 60 days from receipt of bill)
8Find out more
Click on Reports for more
Details
8A methodology has been decided for determination of additional surcharge payable by open access customers
8Find out more
Click on Reports for more
Details
8The weighted average tariff shall act as ceiling tariff for procurement of short-term power
8Find out more
Click on Reports for more
Details
8Bids are invited for EPC package with 220 kV S/S for grid-connected Solar PV projects
8Find out more
Click on Reports for more
Details
8The regulator has refused the request of solar generator due to project commissioned prior to LTA operationalization date
8Find out more
Click on Reports for more
Details
For reference purposes the website carries here the following Newsclips:
8Tender for ARC of routine/preventive/breakdown maintenance of entire equipment of BOP section viz cooling towers, CW pumps Details
8Tender for procurement of special purpose dissimilar alloys electrodes and hard facing electrode Details
8Tender for procurement of Pipes of different sizes for balance erection works Details
8Tender for strengthening/ replacement of structures at various Details
8Tender for the supply of single phase energy meter Details
8Tender for the supply of oxygen analyzer Details
8Tender for design, engineering, procurement, construction, integration of interfaces, testing & commissioning of transmission line Details
8Tender for AMC of electrical maintenance of ESP, FOPH & chimney Details
8Tender for supply, installation, commissioning & transportation of Heat shrink straight through jointing kit and Outdoor& indoor termination kit Details
8Tender for work of replacement of 400kV & 220kV suspension type wave trap by pedestal type wave trap along with accessories at 400kV substation Details
8Tender for supply of various forged hammer rings Details
8Tender for services for rail mode logistics and unloading of coal Details
8Tender for ARC for miscellaneous work of Ash slurry pipe lines & dry Ash conveying pipe lines Details
8Tender for supply, installation, testing & commissioning of one new screw chiller unit (with dual compressor) Details
8Tender for supply & fabrication of different types dowel pin & other items for generator Details
8Tender for work of rate contract for erection work of HT,LT lines and distribution transformer Details
8Tender for routine, breakdown and overhauling maintenance of CW Pump Details
8Tender for routine maintenance of main boiler Details
8Tender for design, engineering, manufacturing, testing, supply and delivery of 400KV circuit breakers Details
8Tender for development of distribution infrastructure for loss reduction Details
8Tender for manufacture, testing, supply & delivery of 66KV potential transformer Details
8Tender for repair/restoration of damaged protection walls and toe wall at tower 103 of 400 KV D/C transmission line Details
8Tender for repair/restoration of damaged foundation of leg A of tower Details
8Tender for work of supply of 220V 500AH, 48V 1000AH & 110V 200AH lead acid stationer battery Details
8Tender for work of supply and installation of bird diverters Details
You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips:
8ABB India expands and upgrades its smart power factory in Bengaluru  Details
8Why India is pushing ahead with nuclear power plans  Details 

8Imported coal lying idle in ports as gencos demur Details
8Concerted efforts needed from all sectors, states to achieve 500 GW renewable energy capacity: Union minister Details
8Plenty of roadblocks for automakers seeking EV success Details
8Mumbai's double-decker buses all set for comeback in electric avatar Details
8Power Grid pitches for obsolete tech in smart electricity meters, can hamper 5G dream Details
8Punjab Approves Rs 25,237-Cr Action Plan To Improve Quality, Reliability Of Power Supply To Consumers Details
8Share in hydropower projects: Uttarakhand to fight decisive battle against UP in Supreme Court Details
8Electricity Demand Up Due To Intense Heat: Uttar Pradesh Minister Details
8Chandigarh Tops All The Union Territories In Solar Power Installation  Details
8Tata Power-DDL ties up with BlocKnots for conducting Capacity Building Programs for discoms Details
8Punjab taps agricultural residues to speed up lean energy transition Details
8Himachal govt counters AAP: Offers free electricityDetails
8HPL Electric and Power bags Empanelment Certificate from Power Ministry Details
8Need to diversify agriculture towards power, energy sectors: Gadkari Details
8Centre is keen on privatising the entire power sector, alleges AIPEF chairman Details
You can also click on Newsclips for more
Details
8Forest clearance stage 1 has been granted by the DFO but stage -2 is in progress at the nodal office.
8The public hearings have been completed for both phases.
8The PMC has been selected.
8The RFQ for the EPC package is likely to be floated in Q4 2022.
Click here for more details Details
8The hot water duct columns construction has been completed for NDCT.
8 The project got delayed due to the slow progress in design, drawing by the contractors
8Land  Sub-contractor selected for chlorine dosing system.
8The RFQ for the hydro cyclone separator system package is likely to be floated in October 2022.
Click here for more details Details
8EIA and EMP studies are yet to be approved by MoEF.
8PPA has been signed with the Government.
8Government has completed the construction of approach land to the dam site.
8The PMC was selected for the project.
8The RFQs for the civil works package are likely to be floated in Q4 2022.
Click here for more details Details
8Government has floated Draft Central Electricity Authority (Flexible operation of thermal power plants) Regulations, 2022
8All thermal power plants should check their feasibility of operation at 55% and 40% status including ramping capability in consultation with OEM as per new Regulations
8But it becomes difficult to maintain the load capacity for some generator
Click on Details for more
Details
8The detailed survey and investigation were completed for lattice tower erection.
8Private land acquisitions have been completed for the T/L works.
8 Forest clearance stages 1 and 2 have been granted by the DFO.
8RFQs for the ACSR Deer conductor package are likely to be floated in September 2022.
Click here for more details Details
For reference purposes the website carries here the following reports:
8Find out the tariff for Tripura Gas Based Power Plant for 2022-24 tariff period Click on Reports for more
8Smart Power factory to transition with Industry 5.0 standards Click on Reports for more
8G R lnfraprojects Ltd gets Independent Director Click on Reports for more
8Simhapuri Energy Limited: Non-Cooperating with rating agency Click on Reports for more
8Get the review on tariff of Bairasiul Hydroelectric Power Station Click on Reports for more
8DISCOM gets 500 MW power at Rs 5.98/unit Click on Reports for more
8Hindalco Industries V/s MSEDCL: MSEDCL gets relief Click on Reports for more Details
8The voltage of both the Koderma units were injecting MVAR when voltage was above the acceptable limits on 16th August, 2022
8Find out the issue faced by Koderma generator
Click on Details for more
Details
8The issue of 400 KV Tala-Binaguri circuit-1 was resolved on 24th July 2022 and the line was charged on the same day
8But the frequent tripping of circuit-1 is being observed again
Click on Details for more
Details
8The power plant experienced a total blackout due to loss of evacuation path
8The availability of this plant is equally important from the Pan-India resource adequacy point of view
8Find out the progress to resolved the issue
Click on Details for more
Details
8Powergrid has agreed to provide the meters to NTPC Talcher
8Business opportunity ahead
Click on Details for more
Details
8The Odisha Generation Phase II Transmission Ltd had sought monetary compensation on account of occurrence of force majeure and change in law events
8Find out more
Click on Reports for more
Details
8The Generator shall supply despatchable RE Power complemented with power from any other source, in Round-The-Clock manner, keeping at least 90% availability annually
8Get the new guideline for procurement of Round-The Clock Power from Grid Connected Renewable Energy Power Projects
Click on Reports for more
Details
8The regulator cannot determine the distribution tariff for area outside the licence area
8Find out more
Click on Reports for more
Details
8Find out why Eastern Region (ER) need more support from thermal generator
Click on Details for more
Details
For reference purposes the website carries here the following Tenders:
 
8Tender for design, testing, manufacture, supply & stringing of high temperature low sag conductor (HTLS) Details
 
8Tender for procurement of spares of DCS installed for TCS(Turbine Control System) & TPS (turbine protection System) Details
 
8Tender for the work of repair, overhauling & servicing, maintenance, alignment of 220/ 132/ 33KV isolator Details
 
8Tender for strengthening of existing ACSR 7/2.59 mm conductor by ACSR 7/4.09 mm conductor Details
 
8Tender for supply of cable Al. 3x300Sq.mm 11KV XLPE Details
 
8Tender for supply of cable Al. 3x185Sq.mm 11KV XLPE Details
 
8Tender for supply of cable Al. 1x630Sq.mm 11KV XLPE Details
 
8Tender for biennial contract for assistance in ASH handling Details
 
8Tender for biennial job contract for maintenance of equipment’s located in Ash water pump Details
 
8Tender for two years running contract for operation of mechanical workshop& ITs petty maintenance Details
 
8Tender for supply of SS braided hose pipe Details
 
8Tender for annual maintenance & repair of power channel of hydro electric project Details
 
8Tender for procurement of various rubber items Details
 
8Tender for annual maintenance and operation work of 33/11 KV substation Details
 
8Tender for supply of Raw Material Details
 
8Tender for work of replacement of faulty diffrential line protection RED670 relays at 132KV substation Details
 
8Tender for work of chemical cleaning (cold line cleaning/washing) of equipments and insulators Details
 
8Tender for work of replacement of earth wire at 220/100KV substation Details
 
8Tender for replacement of GIS software Details
 
You can also click on Tenders  for more
For reference purposes the website carries here the following Newsclips: 
8Cygni Energy Raises USD 12.5 MN to Power Growth and Expansion Details 
8Reduce production of sugar and diversify agriculture towards energy and power sectors: Union Minister Nitin Gadkari Details 
8NMC begins process to set up electric vehicle charging stations across city Details 
8RIL, Adani, govt PSUs in faceoff over distressed thermal power project Details 
8Nabinagar, Kanti power projects merge with NTPC Details 
8By 2030, 50% of power capacity will be from non-fossil sources, India tells UN Details 
8In a first, govt mulls buying three goods trains to boost trade in Punjab Details 
8Mukesh Ambani seen to repeat Jio feat with potential disruptive green energy announcements at Reliance AGM Details 
8Hitachi Energy looks at acquisitions in India Details 
8Electricity (Amendment) Bill, 2022 not to benefit consumers: AIPEF Details 
8Meeting and exceeding India’s energy needs Details 
8ArcelorMittal Nippon Steel India To Acquire Essar Group’s Port, Power, Infrastructure, Logistics Assets For Rs 19,000 crores Details 
8Indian Economy to Grow at 7.4% in Financial Year 2022 And Next, Says FM; Issues Warning For THIS Sector Details 
8Adani Power vs Tata Power: Which should you pick for long-term investment? Details 
8Coal continues to be a concern for the country: Power ministe Details
You can also click on Newsclips for more
Details
 For reference purposes the website carries here the following tenders:
 
8Tender for work of overhauling of 245KV circuit breakers Details
 
8Tender for work of attending emergency breakdown & annual maintenance works for at 400kV substation Details
 
8Tender for work of providing retaining structure to tower of 132 kV line Details
 
8Tender for work of overhauling of 145KV circuit breakers Details
 
8Tender for replacement of existing 0.4 ACSR conductor by suitable HTLS conductor Details
 
8Supply, installation, testing and commissioning of DG sets Details
 
8Tender for R&M work of 02 nos. 220/132/33KV GSS Details
 
8Tender for procurement of air circuit breaker Details
 
8Tender for procurement of spare parts of Air Pre-heater Details
 
8Tender for the supply of economiser coil tubes & bends Details
 
8Tender for supply, installation, testing and commissioning of 220V DC Battery Details
 
8Tender for dismantling, fabrication, erection of ETP Clarifier Details
 
8Tender for annual contract for routine, breakdown & capital maintenance works of protection system Details
 
8Tender for supply of lead acid battery Details
 
8Tender for work of providing & application of metachem elastomeric thermoplastic graft Co-Polymer anti-corrosive treatment Details
 
8Tender for maintenance contract of electrical system comprising of HT & LT switch Gear, HT& LT motors, HT& LT cables Details
 
8Tender for assistance in carrying out miscellaneous routine works for preventive maintenance works of different 132KV Transmission lines Details
 
8Tender for erection of HT LT Lines and distribution transformer Details
 
8Tender for transportation of RoM coal Details
 
8Tender for implementation of substation monitoring system for 33/22/11 kV substations Details
 
8Tender for work of construction of 04 nos.132KV DCSS transmission line Details
 
8Tender for R&M work of 04 nos. 132/33KV GSS Details
 
8Tender for procurement of material required for laying work of 33KV underground cable Details
 
8Tender for work of providing & fixing of high voltage insulation electromat at various substation Details
 Click on Tenders for more
 For reference purposes the website carries here the following newsclips:
 
8GAIL targets net-zero emissions by 2040: Chairman Manoj Jain Details
 
8What Will Green Power Market Look Like In The Future? Details
 
8Gensol Engineering Bags Orders Worth Rs 153 Crore To Build 58.8 MW Solar Projects Details
 
8Uttar Pradesh CM Yogi Adityanath flags off 42 electric buses; to be deployed in Lucknow and Kanpur Details
 
8Chhattisgarh govt to set up 1,320 MW thermal power plant in Korba district Details
 
8Column: Australian and Indonesian thermal coal tread contrasting price paths: Russell Details
 
8Whitehaven books record profit, expects coal prices to stay elevated Details
 
8Australia Needs Massive Renewable Energy Expansion to Hit Net Zero by 2050 -Study Details
 
8Rooftop Solar Installations Fall 25 % to 389 MW in Apr-Jun: Report Details
 
8Rajasthan attracts investment commitments worth nearly Rs 70,000 crore Details
 
8Battery Maker Cygni Energy raises $12 mn from Meridian, others Details
 
8Power Grid acquires Neemuch Transmission Ltd Details
 
8Hero Electric, Jio-bp to boost 2-wheeler EV adoption, battery swapping infra Details
 
8Power gencos seek to join debate in SC over freebies Details
 
8How academia can facilitate the clean energy transition Details
 
8STIMA Partners With India’s One Electric For Kenyan Electric Motorcycle Market Details
 
8KKR looks to invest $400 m in Hero Future Energies Details
 
8Private Port Operators and Shipping industry experts believes that the proposed Indian Ports Bill, 2022, if enacted likely to take away powers of states Details
 
8How academia can facilitate the clean energy transition Details
 
8JAC demands withdrawal of Electricity (Amendment) Bill, 2022 Details
 
8IEEFA recommendations for India power sector reforms Details
 Click on Newsclips for more
Details
8The forest clearance is pending at DFO.
8Several meetings have been conducted with the landowner for transmission line works.
8Detailed survey and investigation have been completed.
8RFQ for the 765 kV S/S works is likely to be floated in September 2022.
Click here for more detail Details
8PG tests have been completed for all units of BTG. Mechanical completion is underway.
8The erection of all BOP works is in the advanced stage for completion.
8The civil and architectural works were completed for the absorber system.
8The RFQ for the limestone and gypsum handling system package is likely to be floated in October 2022.
Click here for more details Details
8The E&M contractor has carried out the balanced design and engineering works of the E&M equipment.
8 Erection and installation of the Main Inlet Valve and Butterfly valve have been completed
8Distilling chamber areas 1,2,3 is in progress slowly due to the Inadequate deployment of resources by the contractor.
8The project is getting affected due to the slow progress of civil works and the cash flow crisis faced by the contractor.
8Land acquisition works completed for power evacuation system.
8The RFQ for the EPC package for the power evacuation system is likely to be floated in Q4 2022.
Click here for more details Details
8EIA and EMP studies have been completed.
8Hydrology report is under examination by the CWC.
8The pre-DPR chapter has been approved by the CEA.
8The construction of the approach land to the dam site has been completed.
8The RFQs for the civil works package are likely to be floated in Q4 2022.
Click here for more details Details
8TP Kirnali Limited had sought relief on account of certain Force Majeure conditions.
 
8Find out more