Sep 2025
Repeated deferrals reflect systemic pattern across Northeast utilities
8Similar extension cycles have been seen at APDCL and MNRE funded projects The issue is not isolated to MeECL It signals a structural bottleneck in regional GIS procurement.
Downstream RDSS timelines face pressure — MSEDCL
8Delays in cable procurement ripple into distribution projects. DT connections and feeder segregation schedules may slip. This puts RDSS milestone compliance at risk.
Twelve extensions highlight weak bidder appetite — NTPC Andaman Nicobar gas project
8The bid cycle has stretched nearly nine months through 12 rounds. Such persistent extensions reflect a thin contractor pool willing to risk mobilisation. It signals systemic hesitation about project viability.
Trend of micro - extensions continues — NHPC Dulhasti
8Like past hydro packages NHPC is using incremental date relief rather than wholesale rescheduling. This approach aims to keep project sequencing intact. However it risks repeated drip - feed delays if bidder appetite does not improve.