8The detailed survey and investigations have been completed. 8Forest clearance stage -1 is in progress at the nodal office. 8Soil test was completed for both transmission line and substation, pooling station 8Meetings have been conducted with the private land owners for the project. 8RFQ for the 400 kV GiS S/S line is likely to be floated in October 2022. Click here for more detailsDetails
8The civil works package contractor has carried out the removal of slide deposits in the desalting tank area. 8The excavation of the diversion HRT tunnel and bifurcation of two HRT was completed. 8The erection and installation of TG units, and the first unit's oil lubrication system test were completed. 8 RFQ for the EPC package for the transmission line works is likely to be floated in October 2022. Click here for more detailsDetails
8The issue of the local protests at the site was being resolved by the Government. 8The project is being financed by the JICA group 8The forest clearance stage -1 and stage 2 have been accepted by the DFO. 8The hydrology report has been accepted by CWC and DPR is yet to be approved by the CEA. 8RFQ for the civil works package (lot-1) is likely to be floated in November 2022. Click here for more detailsDetails
8Pilling and foundation work at the BTG sites have been completed. 8Contractor selected for the civil and infrastructure works. 8Sub-contractor selected for NDCT works. 8The bidding is under progress for Wagon Tipler works. 8The RFQ AHP package is likely to be floated in Q4 2022. Click here for more detailsDetails
8Real-Time data availability from Jammu and Kashmir is very poor. There is zero visibility of data in J&K stations. 8With poor monitoring of data, it is very difficult to monitor the grid in an efficient manner 8Find out the progress to resolve the issue Click on Details for moreDetails
8Around 23 SDH equipment were installed under under its fibre optics communication system in various sub-stations in HP 8But only two RTU stations are presently communicating through these SDH equipment 8So the fingers are pointing only in one direction Click on Details for moreDetails
For reference purposes the website carries here the following reports: 8Waa Solar Ltd appoints a Company Secretary Click on Reports for more 8Powergrid gets LoA to establish ISTS Click on Reports for more 8Yamuna Kumar Chaubey appointed as CMD in a hydro generator Click on Reports for moreDetails
8New electricity rules has been implemented for monitoring of payments to supplier by DISCOMs 8Get the feature of new rules Click on Reports for moreDetails
8This generator got approval for closing the bus coupler installed between Unit 3 and Unit 4 to run the Expansion Project under common bus arrangement 8But it ended up violating the Grid Code 8Find out more Click on Reports for moreDetails
8Coal India has supplied 243.3 MTs coal to power sector during April-August’22, a growth of 18.6% compared to the same period last year 8Find out more Click on Reports for moreDetails
8The government has envisaged new railway line to provide coal evacuation capacity of about 125 MT by rail 8Find out more Click on Reports for moreDetails
8A thermal generator had sought direction to TANGEDCO to pay outstanding amounts 8But the regulator has refused to do so, find out why Click on Reports for moreDetails