Project Name: Thermal Power Station - FGD Addition 8Project Cost: 700 crores 8Project Description: Owner along with consultant have submitted a feasibility report for implementation of a sea-water based flue gas desulphurization system in the 2x600 MW units thermal power plant. Discussions regarding project schedule for FGDs is in process. Tenders for the same is expected soon. 8Project Event: RFQ of an EPC package for supply, installation, construction, and commissioning of the sea water based FGDs is expected by December 2018. 8Expenditure Approval: Q1:2019 8RFQ Date: Dec/2018 8Release Date: Dec/2018 8Start Date: 2020 8Completion Date: 2022 Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside) 8Project Name: Thermal Power Station - Installation of FGD 8Project Cost: 500 crores 8Project Description: Promoter is looking out for financial institutions for funding of WFGDs at its 1000 MW thermal power station. The project report has been prepared by Development Consultant Private Limited and submitted to the state government. The project is getting delayed at the state electricity regulatory authority as of now. Further bids are expected soon. 8Project Event: RFQ for design, supply, installation, erection, and commissioning of WFGDs is expected by December 2018, instead of Sept 2018. 8Expenditure Approval: Q3:2018 8RFQ Date: Dec/2018 8Release Date: Dec/2018 8Start Date: 2020 8Completion Date: 2022 Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside)Details
8SJVN has expressed grave concern over lack of payment for outstanding payments from UPCCL. 8The bill amount is mounting and is currently pegged at Rs 335 crore Click on Reports for more.Details
For reference purposes the website carries here the following tenders: 8Supply, Erection, Testing & Commissioning of 17 nos. 220 KV Isolators Details 8Supply, Erection, Testing & Commissioning of 33 nos. 245KV Current Transformers Details 8Tender for Purchase of Turbine Guide Bearing shell and Turbine Generator Shaft Coupling Bolts with accessories Details 8Tender for Laying of tower foundations ,Erection of towers and stringing & sagging of conductor with earth wire Details 8Tender for Routine preventive maintenance & occasional breakdown maintenance of Mechanical components Details 8Tender for Laying of tower foundations ,Erection of towers and stringing & sagging of conductor with earth wire for 66 KV line Details 8Tender for Supply of HT Ring main Unit Details 8Tender for Procurement of 11 kV & 6.6 kV Indoor Cast Resin Current & Voltage Transformers Details 8Tender for Construction of 05 Nos. of 132/33 KV Transformer Bays Details 8Tender for Construction of 03 Nos. of 132/33 KV Transformer Bays Details 8Tender for Construction of 132/33 KV Transformer Bays Details 8Tender for Routine maintenance of field units of C&I, IRP, control panels Details 8Tender for Shifting of 400KV, 63 MVAR line reactor Details 8Tender for the Work contract for Maintenance of HT/LT Lines Details 8Tender for Purchase of Governor Over-Speed device Details 8Tender for Services for Overhauling of Steam Turbine Generator Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Falling rupee puts 28,000 crore of solar projects at risk: report Details 8Coal India falls 4% as govt to sell stake in co via OFS Details 8Govt to sell 3% stake in CIL, floor price at Rs 266 a share Details 8Govt kickstarts process for further M&As in energy sector Details 8Ensure 24x7 power at global standards Details 8Indoor pollution in India contribute from 22 to 52% air pollution: UNEP Details 8ABB net up 30% in third quarter Details 8GE Power bags orders worth Rs 1,783 cr from NTPC. Details 8Coal block winners can sell excess output to Coal India at 15% discount Details 8Govt may step up disinvestment drive with power PSUs’ mergers Details 8Siemens eyes Asian markets to boost power generation business: Executive Details 8Amended solar policy to be out by November-end Details 8SunPower cuts view as panel price drop sparks order delays Details 8Subsidised solar pump scheme launched in Odisha Details You can also click on Newsclips for moreDetails
Project Name: Greenfield Thermal Power Project 8Project Cost: 1970 crores 8Project Description: Promoter is getting delayed in coming out of an EPC package bids for a 400 MW coal-based thermal power plant due to the pending approval for supply of imported Indonesian coal. EC has been granted. Further bids are expected soon. 8Project Event: RFQ for an EPC package is expected by December 2018, instead of Sept 2018. 8Expenditure Approval: Q4:2017 8RFQ Date: Dec/2018 8Release Date: Dec/2018 8Start Date: 2020 8Completion Date: 2024 Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside)Details
The owner has floated a bid for an EPC package in an 800 MW super-critical thermal expansion project. 8Major EPC companies have shown their interest in the pre-bid meeting. 8The project was on-hold for 3 years due to corporate insolvency and a bankruptcy case filed with the old EPC contractor. 8The new EPC contractor may choose to go with the existing sub-contractors as substantial engineering progress has been achieved. 8PMC contractor has been awarded the work for evaluation of bids. 8Further bids are expected soon. 8Project Cost: 7000 crores 8Project Event: RFQ for the price bid is expected by the end of November 2018. 8Expenditure Approval: 2014 8RFQ Date: 28/Nov/2018 8Release Date: 30/Nov/2018 8Start Date: Jul/2014 8Completion Date: 2021 Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside)Details
For reference purposes the website carries here the following tenders: 8Tender for the Procurement of bearings for Mill Gear Boxes of HP 803 Bowl Mills Details 8Tender for the Supply of Blanking Device for main Steam Strainers for Turbine Details 8Tender for Procurement of Air Port Ring Assembly for Coal Mill Details 8Tender for Supply of Iron & Steel Materials Details 8Tender for Supply of Air Preheater Seals Details 8Supplying, Providing, fabricating & erecting of MS Gratings Details 8Tender for the work of Installation of 245kV Hybrid Switchgear Details 8Tender for the Work of Dismantling of 160 MVA transformer Details 8Supply and Installation of Outdoor Type LT Panel Details 8Tender for the Work contract for Complete overhauling & Repairing of Hoists at CHP Details 8Supply of Aluminium LT Power cables Details 8Tender for Round the clock Routine, Preventive and Breakdown maintenance works of Bowl Mills (XRP-903) Details 8Tender for the work of Modification in programming, setting and tuning of existing Governor Details 8Annual contract for operation of pre treatment plant Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Electricity Supply Companies, KPTCL owe Rs 15K crore to power corporation Details 8Supreme Court throws lifeline for Tata, Adani, Essar power plants Details 8Rs 28,000cr solar projects face viability risk on falling Rupee: Crisil Details 8Tata Power to raise up to Rs 5,500 crore via NCDs Details 8Domestic coal supply significantly short of demand: Icra Details 8Actis could step up investments in India’s green energy space Details 8Coal union boosts giving to Democrats as hopes dim for industry revival Details 8NTPC, Railways ink Rs 10,000 crore deal to transport coal Details 8Discoms can seek tweak in PPAs for costlier coal: Supreme Court Details 8Why investors should pick NTPC over power grid Details 8Tata Power second-quarter profit soars 88.5 per cent Details 8China new solar power capacity down 20 per cent over Jan-Sept, says regulator Details 8Tata Capital plans infrastructure debt fund for green projects Details You can also click on Newsclips for moreDetails
BHEL's last quarter shows up a revenue hike by 1.7% YoY in the power segment while industry segment revenue shows up a healthy growth of 31.7% YoY. 8One of the major EPC company, BHEL, expects BTG ordering of 8-10 GW for tenders to be finalized in FY19. 8About 12,000 MW tenders are upcoming wherein BHEL will play a major role. 8Moreover, BHEL has entered into a technology agreement with Babcock for the SCR/SCNR technology equipment. 8The EPC company has received major orders from NTPC for the EPC packages and installation of FGD. 8Nevertheless, execution of orders won in Q2 2018 are expected to start by FY20. Click on Reports for more.Details
For reference purposes the website carries here the following tenders: 8Tender for the Work of replacement of old deteriorated earth wires of various old EHV lines Details 8Supply, Erection and Civil balance works including testing & commissioning of 132kV S/S Details 8Tender for Purchase of 02 No. Rivert Hart gate positioning measurement system Details 8Tender for the Supply of Round Corner Metallic Expansion Joint for Flue Gas Duct Details 8Supply of various types of Aluminium, LT Power cables Details 8Annual Electrical Maintenance Contract for CHP Details 8Supply Erection & Commissioning of Degassed cation Conductivity analyser Details 8Tender for Procurement of Thermo Gravimetric Analyser Details 8Tender for Maintenance Contract for Generator Circuit Breakers Details 8Supply, erection, testing & commissioning of 220V, 1000AH Lead Acid of Battery set Details 8Tender for Purchase of 18KW/24HP Submersible Dewatering Pump Motor Set Details 8Annual Maintenance of all 03 Nos. of 20 MW Hydro-Generating Units Details 8Supply, Erection and commissioning of 220V/900AH Tubular Type Lead Acid Station Battery set Details 8Supply and Erection of Auto Transformers Details 8Tender for the Long Term Maintenance Contract of Electrical and Control & Instrumentation System Details 8Tender for the Long Term Maintenance Contract for mechanical equipments Details 8Annual Maintenance Contract for Ash slurry disposal lines Details 8Annual Maintenance Contract for Electrical Maintenance jobs of Coal Handling Plant Details 8Tender for Procurement of different type of OFC cable Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8BHEL’s dim Q2 results hint at economic headwinds in India Details 8Smart electricity meters in rural India a win-win, says ADB Details 8SC allows Gujarat projects to renegotiate PPAs Details 8Share market update: Power shares trade in the green; Tata Power soars around 16% Details 8Rs 1.9 lakh crore benefit to power companies post Gujarat bailout Details 8Anti-nuclear plant outfit raises decibel against Chutka Details 8Uttarakhand to buy 500 electric buses as trial run achieves success Details 8Tamil Nadu's power demand crosses 14,500 Mw as AC use rises Details 8Barh super thermal power plant to be fully functional by April 2021 Details 8PNB’s non-core asset sale plan faces hurdles Details 8UT seeks details of spaces available for solar plants Details 8Clean energy: 15MW rooftop solar plants in west Delhi locality Details 8SECI postpones hybrid auction for fifth time; justifies low ceiling tariff Details 8Yet another green energy auction flops as investors stay away Details 8Temples to go green, recycle waste and tap solar power for needs Details 8Vattenfall looks to gas and biomass as end of coal power looms Details You can also click on Newsclips for moreDetails
Project Name: Greenfield Hydroelectric Project 8Project Cost: 1925.25 crores 8Project Description: Owner is undertaking additional S&I activities along with social impact assessment activities in a 270 MW greenfield hydel project on BOOT basis. Extension for the validity of TOR was granted. The EIA consultant is writing out the final EIA report. The public hearing is expected to conduct by the next 3 to 5 months. The project is getting delayed due to awaiting forest and wildlife clearance. Further bids are expected soon. 8Project Event: RFQ for the drilling and drifting works is expected by the Q2 2019. RFQ for the civil and H&M works is expected by the Q3 2019. 8Expenditure Approval: Q3:2019 8RFQ Date: Q2:2019 8Release Date: Q2:2019 8Start Date: 2020 8Completion Date: 2025 Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside)Details
Project Name: Thermal Power Station Maintenance Project 8Project Cost: 5 crores 8Project Description: Promoter has planned a 35-day scheduled annual overhaul in the 2000 MW Thermal Power Plant. The last annual overhaul in the unit-3 was successfully done as per schedule. The major scope of work includes inspection and round the clock maintenance of low-pressure turbine, high-pressure turbine and balance of plant area. A bid is expected soon. 8Project Event: RFQ for required maintenance activities is expected by mid-November 2018. Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside)Details
Project Name: Greenfield Super Thermal Power Project 8Project Cost: 13200 crores 8Project Description: Owner along with BTG and ESP contractor is carrying out the mechanical completion activities in the 1320 MW greenfield super-critical thermal power plant. The project is getting affected due to slow progress works of the civil contractor, Bridge & Roof Company Limited. Meanwhile, ISGEC Heavy Engineering Ltd has been selected as an EPC contractor for FGD. Further bids are expected soon. 8Project Event: RFQ for the piling and pedestal works for the FGD system is expected by November 2018. 8Expenditure Approval: Q1:2013 8RFQ Date: Nov/2018 8Release Date: Nov/2018 8Start Date: Q3:2013 8Completion Date: Q3:2019 Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside)Details
Project Name: Thermal Power Plant - FGD Addition 8Project Cost: 500 crores 8Project Description: A subsidiary power company is expected to extend the submission date for qualification documents for installation of a wet scrubber based (Limestone/Ammonia) FGD System in the 1320 MW Super Thermal Power complex in order to comply with the new environmental norms. Further bids are expected soon. 8Project Event: RFQ for re-opening for EPC package of FGD system is expected to start by November 2018. RFQ for the information of the shortlisted applicants is expected by the end of November 2018. RFQ for the request for proposal bid is expected by December 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Nov/2018 8Release Date: Nov/2018 8Start Date: Q2:2019 8Completion Date: Q4:2021 Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside, assembled in a manner never done before by anyone) Details
For reference purposes the website carries here the following tenders: 8Tender for Routine Maintenance of 4X60 MW Hydro-Turbine and auxiliaries Details 8Tender for the Construction of Coal Slurry Settling Pit Details 8Tender for Annual Overhauling of GT-1 during overhauling of Unit No.1 of TPS Details 8Tender for Construction work of 220 kV LILO line Details 8Tender for the work of Repair of Submerged Portion of Spillway Glacis and Stilling Basin at Dam of Power Station Details 8Tender for Construction of 18 nos of 220 & 132 kV End bays Details 8Tender for Procurement of Normal Disc, Antifog Disc, Normal Long Rod and Antifog Long Rod Insulators of various types Details 8Tender for Overhauling of boiler Non-pressure parts Details 8Annual Maintenance Contract for maintenance of coal mill auto reiection system Details 8Tender for Construction of add. T/F Plinth Details 8Tender for Life Extension Program of ESP Details 8Biennial Maintenance Contract for C&I equipments Details 8Supply and Laying of 600NB & 300NB MS Pipe Details 8Tender for the supply of 300A and 200A 415V Rewireable Porcelain Fuse units Details 8Tender for Balance Civil work of LWTP/AWRS Package Details 8Biennial Contract of Round the Clock Operation & Maintenance of S&T System at Expansion Power Plant Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Coal stock slips to an all-time low of 30 million tonnes as demand rises Details 8New round of coal auction with old and rejected mines, same problems Details 8Opinion- The many dangers from coal shortages Details 8Tata Steel may stick to its offer for Bhushan Power and Steel Details 8Low tariffs test plans on nuclear power Details 8ReNew Power & CII to work together to tackle air pollution in Delhi NCR Details 8Long way to go for India to fulfil renewable energy targets: Expert Details 8First Solar cuts 2018 earnings and sales outlook, shares slide Details 8EverSource to back renewable firm of former Ostro Energy executives Details 8BHEL approves Rs 1,628 crore share buyback; fixes price at Rs 86 a piece Details 8Odisha govt clears Hindalco's Rs 5,000 crore investment proposal Details 8Nine coal blocks identified for sale to priv companies, nine for state entities Details 8Stop foreign coal at ports: EPCA Details 8Delhi will use less coal power this winter Details You can also click on Newsclips for moreDetails
Project Name: Thermal Power Maintenance Project 8Project Cost: 4 crores 8Project Description: Promoter has planned a 35-day scheduled annual overhaul in the 1500 MW thermal power station. The major scope of work includes replacement of boiler pressure parts, inspection of the low-pressure turbine, replacement of air preheater regenerative baskets, among others. 8Project Event: RFQ for the required overhaul is expected by January 2019. Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside)Details
Project Name: Super-Critical Thermal Power Project - Installation of SNCR 8Project Cost: 700 crores 8Project Description: Owner's EoI for Selective Non-Catalytic Reduction System (SNCR) has been interrupted due objection by bidders to the Bid Evaluation Criteria (BEC) in the 1320 MW super-critical thermal power complex. Also, the award of tender for WFGDs is at the final stage. Further bids are expected soon. 8Project Event: RFQ for the design, engineering, supply, installation, and commissioning of the SNCR system is expected to be reopened by November 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Nov/2018 8Release Date: Nov/2018 8Start Date: Q3:2019 8Completion Date: Q3:2021 Click here for more details (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside)Details
Works for 48 MW greenfield hydropower project has been stalled. 8EPC contractors seem to have run into trouble over payment issues 8The delays are now expected to impact the completion schedule. Click on details for moreDetails
For reference purposes the website carries here the following tenders: 8Supply, Installation, Testing and Commissioning of Electrical Items for implementation of Disaster Management Plan Details 8Tender for Annual maintenance work of 400 KV Substation Details 8Tender for the Supply of Idlers Details 8Tender for Construction of 02 nos. 132KV Line Bays Details 8Design, Supply, Erection & commissioning of Chlorine di-oxide Plant Details 8Tender for Erection of 66KV equipment, structures, control wiring, yard Lighting etc Details 8Tender for the Supply of Clinker Grinder Roller with Shaft Details 8Tender for Erection work of 66 S/C line on ACSR Panther conductor Details 8Tender for the supply of GI Bare Wire Details 8Tender for Work of replacement of existing 160 kN glass insulator strings Details 8Procurement of Long Travel 630mm dia drive Wheel Bogie Assembly for Stacker Cum Re-claimer Details 8Tender for Shifting/ Height raising of 220 kV line Details 8Tender for Shifting/ Height raising of 66 kV line Details 8Tender for Shifting/ Height raising of 66 kV line Details 8Tender for Shifting/ Height raising of 132 kV line Details 8Tender for Shifting/ Height raising of 132 kV line Details 8Tender for Shifting/ Height raising of 66 kV line Details 8Annual repair & overhauling of 30 MW capacity machines Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Thermal power capacity addition to fall by 60% in 5 years: report Details 8BHEL Q2 net up 60 pc to Rs 185.17 cr Details 8Khurja plant to supply power at competitive rates, less pollutive: THDC Details 8Palaniswami writes to PM Modi over Kerala's proposal for new dam Details 8SAR Group re-enters in inverter, solar segment Details 8Ensure no interruption in power supply: Kumaraswamy to officials Details 8Electric vehicle charging stations may become mandatory in buildings Details 8Shutters down, polluter Badarpur power plant to return in green avatar Details 8Share market update: Power shares under pressure; BHEL down 3% Details 8Schneider Electric's Q3 revenue growth beats expectations Details 8CIL to get 8 new coal blocks with 1.3 billion tonne reserves Details 8ABB CEO says there is more work to improve Power Grids business Details 8Nepal’s dry session power import from India to go up Details 8No coal, Karnataka’s thermal power plants on verge of shutting down Details 8Pune: Solar power for all agriculture pumps by 2022, says state energy minister Details 8Tenders finalised for 3 Mw floating solar power project in Vizag Details You can also click on Newsclips for moreDetails
Project Name: Thermal Power Station: FGD Addition Project 8Project Cost: 400 crores 8Project Description: Owner along with consultant has submitted a draft DPR for implementation of FGD units at owner's headquarters for its 1000 MW Thermal Power Station. The technical parameters for development of FGD are under review. ESP is also to be upgraded as per revised environmental norms in the existing units. Further bids are expected soon. 8Project Event: RFQ for design, engineering, supply, installation, erection, and commissioning of FGD units are expected by December 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: Dec/2018 8Release Date: Dec/2018 8Start Date: 2021 8Completion Date: 2023 Click here for more details(This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside, assembled in a manner never done before by anyone)Details
Project Name: Greenfield Super Thermal Power Project 8Project Cost: 7000 crores 8Project Description: Promoter is evaluating the bidding process for the steam generator package in a 660 MW greenfield super-critical thermal power plant. NOC for consent to establish has been granted by SPCB on June 2018. NTPC has been selected as the project management consultant. The financial tie-up is still held-up with PFC. Further bids are expected soon. 8Project Event: RFQ for the price bid is expected by the end of October 2018. RFQ for the balance of plant package is expected by December 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Nov/2018 8Release Date: Nov/2018 8Start Date: Q2:2019 8Completion Date: Q3:2023 Click here for more details. (This link is going to carry you to our project monitoring software where more details are available. After you log in using your password, allow for some time for the page to load. Once inside the software, please go to our dashboard section, where we have mapped all power projects either planned or ongoing in the country. You will find a treasure house of information and key contacts inside, assembled in a manner never done before by anyone)Details
For reference purposes the website carries here the following tenders: 8Tender for Procurement of clamp & connectors for sub-stations Details 8Design, Engineering, Supply, Erection, Testing & Commissioning of 04 nos. 220kV GIS Feeder Bays Details 8Design, Engineering, Supply, Testing and Commissioning of 220kV D/C XLPE cable Details 8Supply of accessories required for HT Aerial Bunched Cable Details 8Tender for Retrofitting of Siemens make 0.4KV station service switchgear Details 8Supply, erection, testing and commissioning of 11KV XLPE power cable Details 8Design, Detailed Engineering, manufacture, supply of 400 kV UG cable and Accessories Details 8Design, Detailed Engineering, manufacture, supply of 400 kV UG cable and Accessories Details 8Design, Detailed Engineering, manufacture, supply of 400 kV UG cable Details 8Tender for Work of providing & fixing cooling system for 400kV Reactor Details 8Supply of M S Channel ISMC 75 X 40 in 1220 mm Length Details 8Supply of M S Channel ISMC 75 X 40 in 1900 mm Length Details 8Supply of M S Channel ISMC 100 X 50 in 2022 mm Length Details 8Supply of M S Channel ISMC 100 X 50 in 2112 mm Length Details 8Supply of M S Channel ISMC 100 X 50 in 3340 mm Length Details 8Tender for Re-conductoring of 132 KV S/C Transmission lines with HTLS Conductor Details 8Tender for Transportation of ROM Coal from Mine to Plant Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Bank of India puts NPAs worth Rs 10,700 crore on sale, five accounts on RBI lists put on block. Details 8Saudi's PIF to invest $45 bn in SoftBank fund for solar power projects. Details 8Diesel or solar: Could a push to power the Philippines turn greener?. Details 8Here's a lesser-known reason behind air pollution Details 8First decline in a decade in Asia Pacific's solar power demand this year Details 8Despite climate pledges, China struggles to break coal habit Details 8Uber aims to go all-electric in London in 2025 Details You can also click on Newsclips for moreDetails
Project Name: Thermal Power Station: AMC Project 8Project Cost: 3 crores 8Project Description: Owner is planning to come out with a bid for an annual maintenance contract of civil, electrical and C&I equipment of merry-go-round rail system and associated rolling stock in the existing 3000 MW facility of the thermal power station. The major scope of work includes round the clock maintenance of MGR system and its associated components. A further bid is expected soon. 8Project Event: RFQ for an annual maintenance contract for civil, electrical and C&I equipment of the MGR system is expected by the end of October 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: 30/Oct/2018 8Release Date: 31/Oct/2018 8Start Date: Q1:2019 8Completion Date: Q1:2020 Click here for more detailsDetails
Project Name: Thermal Power Station: Installation of FGD 8Project Cost: 500 crores 8Project Description: Promoter along with consultant is planning to come out with a bid for a wet limestone-based FGD system in the 2000 MW thermal power station. The feasibility report has been prepared and the same has been submitted to the government for approval. Meanwhile, the technical parameters of the FGD system are under evaluation. Further bids are expected soon. 8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet limestone-based FGD system is expected by December 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: Dec/2018 8Release Date: Dec/2018 8Start Date: 2020 8Completion Date: 2022 Click here for more detailsDetails
For reference purposes the website carries here the following tenders: 8Tender for Re-conductoring of 132 KV D/C Transmission lines with HTLS Conductor Details 8Tender for Repairing and internal cleaning including one coat of primer of cold end heating element baskets of Air Pre-heater Details 8Supply, Installation, testing and Commissioning of Penstock Discharge Measurement System Details 8Tender for Civil Works Packages for Hydroelectric Project Details 8Tender for Procurement of Steel chord conveyor Belt for Stacker Cum Reclaimer (SCR) systems Details 8Tender for Procurement of Conveyor Belt for CHP& ACHS conveyors Details 8Design, Manufacturing, Inspecting, Testing and Supply of 2 Nos. Unit Auxiliary Transformers Details 8Tender for the Work of strengthening of structural foundation of Apron Feeder Details 8Annual Contract for routine operation in shift and routine/capital/ breakdown maintenance work of 6.6 KV SWGR Details 8Tender for Re-conductoring of 132 KV S/C Transmission lines with HTLS Conductor Details 8Tender for Construction of 132 KV D/c transmission line with HTLS Conductor Details 8Tender for Construction of 132 KV D/C Transmission Line Details 8Tender for Re-conductoring of 132 Kv Trans. Line Details 8Tender for Procurement, Erection, Testing & Commissioning of 220 KV Current Transformer Details 8Tender for Supply of Non-Coking Coal Details 8Annual Contract for AHP Operation and Maintenance Details 8Tender for Re-conductoring of transmission lines with HTLS conductor on turn key basis Details 8Tender for Construction of 132 KV LILO line Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8CIL offers additional supplies to power sector Details 8NYSE-listed Azure Power raises $185 m Details 8Hydel sector needs full policy overhaul: Experts Details 8Tata Steel objects to JSW Steel’s ‘final’ bid for Bhushan Power Details 8Proposed Khurja coal power plant overpriced, threat to Delhi's air quality: IEEFA Details 8CIL offers 5 mn tonne coal to NTPC to reduce pithead stock Details 8ReNew Power to set up 3 MW floating solar project in Vizag Details 8Invest India wins top UN award for promoting renewable energy investment Details 8EU Commission clears 200 million euros in French renewable energy state aid Details 8BASF, Nornickel join forces in electric vehicle battery push Details 8Wind turbine maker Siemens Gamesa plans assembly plant in Taiwan Details You can also click on Newsclips for moreDetails
Here is one case where the owner wants to set up as many as three 800 MW supercritical power units 8But, due to environmental norms and MoEF orders, the expansion capacity was degraded from 3x800 MW to 3x660 MW units. 8Even so, amendments to the EC for 3x660 MW units is pending for 4 years. 8If they come through, then RFQs for main plant packages for the supercritical units are going to be coming ahead. Click on Reports for more.Details
Project Name: Thermal Power Station - FGD Addition 8Project Cost: 500 crores 8Project Description: The power generating company along with DPR consultant is carrying out the detailed project activities for installation of a wet flue gas desulphurization system at its 1000 MW unit thermal power complex. A pre-feasibility report has already been prepared. Further bids are expected soon. 8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by the end of October 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: 26/Oct/2018 8Release Date: 28/Oct/2018 8Start Date: Q3:2019 8Completion Date: Q1:2021 Click here for more detailsDetails
Domestic coal supply to the power plants has grown to double digits(11%) since July 2017. 8Since, July 2017 coal-based power generation has increased by 5% which is higher than conventional power generation growth of 4%. 8A generation capacity of 8710 MW has been commissioned in 2017-18 which shows uprising specific consumption of coal. 8Coal imports to increase by at least 15-20 MT in FY19. Click on Reports for more.Details
The specific challenge in transporting coal from mines to demand centers and lack of availability is working into the power sector in two insidious ways. 8In Maharashtra, for example, the state genco's 10GW owned coal generation capacity is operating just at 50-60% PLF. 8Low PLF is forcing the state discom to purchase power from the exchange. 8Power exchange prices have been doubled up in September due to lack of coal in merchant plants, forcing discoms to pay higher. 8This state of affairs has extended to other states as well. Click on Reports for more.Details
Project Name: Greenfield Hydroelectric Power Project 8Project Cost: 810 crores 8Project Description: The civil package contractor is undertaking the removal of slide deposit in the desilting tank area for owner's 84 MW greenfield hydroelectric power station. Moreover, open excavation of the diversion channel is in progress. The H&M package contractor has signed a contract agreement on September 2018. Mobilization of hydro-mechanical equipment is to start by the next month. Further bids are expected soon. 8Project Event: RFQ for the erection of hydro-mechanical equipment is expected by December 2018. 8Expenditure Approval: Oct/2017 8RFQ Date: Dec/2018 8Release Date: Dec/2018 8Start Date: Q2:2018 8Completion Date: Q4:2021 Click here for more detailsDetails
For reference purposes the website carries here the following tenders: 8Annual contract for repair / reconditioning of various components installed at Ash Handling Plant Details 8Annual contract for repair/ reconditioning of valves Details 8Tender for Supply of H.T. fasteners Details 8Supply, Installation Testing and Commissioning of 11 KV Medium Voltage Covered Conductor Details 8Tender for supply of 11 KV 36 KN Strain disc hardwares suitable Details 8Tender for Second circuit stringing of 220 kV line Details 8Tender for The work of replacement of damaged /broken disc Insulators Details 8Tender for Annual Rate Contract for work of attending emergency breakdown & shutdown work on 220/132 kV EHV lines Details 8Tender for Supply of 9000 nos. 8.00m PSC poles Details 8Tender for Replacement of conductor, H/W & Insulators of 66 kv line Details 8Tender for Procurement of Spares of various sizes Control valves Details 8Tender for Construction of Misc. Civil works at 220kv S/S Details 8Tender for Preventive maintenance works of Main boiler Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Coal shortage hits power sector again; how India can get its production right Details 8A sound policy regarding electric vehicles can be a game changer Details 8NTPC prepares war chest to bid for stressed assets; shortlists 8-9 projects Details 8Andhra Pradesh conserving power worth Rs 1,000 cr annually by energy efficiency Details 8ABB wins Rs 115-crore order to sell transformers to Indian Railways Details 8Can the CESC demerger unlock value for investors? Details 8Karna CM writes to Goyal on coal shortage in thermal plants Details 8EDF says protests could hit its coal power plants until 2019 Details 8New research punctures electric cars' greenhouse gas claims Details 8U.S. greenhouse emissions fell in 2017 as coal plants shut Details 8UK's Contour Global in talks to buy Iberdrola's solar power plant Details 8Siemens may have to share big Iraq power contract with GE Details 8How far away are we from commercial fusion energy? Details You can also click on Newsclips for moreDetails
Project Name: Thermal Power Station: FGD Addition 8Project Cost: 308 crores 8Project Description: The power generating company along with DPR consultant is carrying out the detailed project activities for installation of a wet flue gas desulphurization system at its 500 MW expansion unit thermal power complex. A pre-feasibility report has already been prepared. Further bids are expected soon. 8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by the end of October 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: 26/Oct/2018 8Release Date: 28/Oct/2018 8Start Date: Q3:2019 8Completion Date: Q1:2021 Click here for more detailsDetails
Project Name: Thermal Power Station: Chimney Package for FGD 8Project Cost: 110 crores 8Project Description: Promoter is planning to come out with a bid for chimney package for installation of FGD in the 3000 MW thermal power station. An IFB for limestone handling, crushing and gypsum storage package for the FGD system bids have been floated. Further bids are expected soon. 8Project Event: RFQ for the design and construction of RCC chimney package for implementation of an FGD is expected by November 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: Nov/2018 8Release Date: Nov/2018 8Start Date: Q3:2019 8Completion Date: 2021 Click here for more detailsDetails
For reference purposes the website carries here the following tenders: 8Design, Supply, Erection & Commissioning of Screw Air Compressor Details 8Supply, laying, testing and commissioning of 220KV cable system on turnkey basis Details 8Supply & erection work of DC new Tower Details 8Tender for the work of Erection of 66 KV D/C LILO line Details 8Tender for Procurement of LT AC 3-phase, 4-Wire CT operated Static, DLMS Compliant, Energy Meters Details 8Tender for work of replacement of existing old control and relay panel Details 8Tender for work of Stub-Strengthening of heavily-rusted Tower Details 8Tender for Supply of Boiler Tube Shield Details 8Tender for Procurement of knife edge Gate Valve Details 8Tender for supply of 11 KV 30 KN Strain disc hardwares Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Maharashtra cabinet nod for 1 lakh solar pumps at Rs 3,435 crore Details 8Bhushan Power lenders are said to back JSW’s $2.7 billion offer Details 8Magenta Power updates EV charging stations with new billing meters, to expand chargers to more highways Details 8Edelweiss-backed fund buys Essel Infra’s power assets for 6,000 cr Details 8SJVN pays total dividend of Rs 864.56 cr for 2017-18 Details 8India will add 8.5-GW renewable energy in FY19, says ICRA Details 8First stubble-to-coal plant misses deadline Details 8Coal scam: Court allows Naveen Jindal to travel abroad Details 8After four decades, Badarpur thermal plant shut for good Details 8Tangedco breathes easy as imported coal arrives at port Details 8Centre, states must cooperate in improving coal production, supply: Goyal Details You can also click on Newsclips for moreDetails
A hydro-based public sector power company is foraying into greenfield supercritical thermal power projects. 8All the statutory clearances have been applied for. 8Investment approval has also been granted. 8The project, however, has been stuck at the CCEA approval stage for now Click on details to know the fact behind.Details
Project Name: Thermal Power Station Maintenance Project Project Cost: 8 crores Project Description: Promoter has planned a 20- day scheduled annual overhaul in the 1500 MW thermal power station. The major scope of work includes boiler inspection, checking of boiler pressure parts and replacement of basket for the regenerative air preheater. A bid is expected soon. Project Event: RFQ for the required overhauling works is expected by the end of October 2018. Click here for more detailsDetails
Islanding schemes are implemented to isolate the healthy subsystems following a large-scale disturbance. 8The new system will help out under contingency conditions that will prevent from total block out by avoiding the effect of cascade tripping of all generating stations in the power system. 8Also, fast restoration of supply can be achieved. 8Various methodology for islanding scheme is proposed in the OPGC's 2x210 MW operational IB thermal power plant in Odisha and for 2x660 MW expansion project which is under construction. Click on the Reports to know more.Details
The major coal producers CIL and SCCL cumulative reported a less production of coal in Q3 2018. 8The supply chain issues due to inadequate rail-connectivity for coal evacuation and rake availability continues to be the major factor impacting the availability of coal. 8The scarcity of coal has compelled the merchant to raise the power tariffs. Click on Reports to find out more.Details
Coal imports grew by 14% during the past months at 95.2 MT. 8Australia, South Africa and Indonesia are the major countries supplying imported coal. 8Not only the IPPs, but captive units under steel and cement sectors use thermal coal as feedstock and coking coal as raw material are major drivers of demand for imported coal. 8Coal import trend is expected to rise as power, cement, and steel industry are expected to witness improvement in demand and capacity utilization. Click on Reports for more.Details
For reference purposes the website carries here the following tenders: 8Design, Engineering, Manufacturing, Supply, Installation and Commissioning of Grid Connected 70 MW Solar PV Project Details 8Annual Contract for the operation and maintenance work of 400 KV/220 KV/33 KV Switchyard Details 8Tender for Maintenance work of Heavy Mobile Equipment Details 8Design, Manufacturing and Supply of Power Transformers Details 8Procurement, Erection, Testing & Commissioning of 245 KV Capacitor Voltage Transformers Details 8Procurement, Erection, Testing & Commissioning of 400 KV Current Transformer Details 8Annual Contract for maintenance of wagon tipplers & Associated Equipments Details 8Annual Contract for maintenance of Conveyor System Details 8Tender for Procurement of Vertical Turbine CT Drain Pumps and Drain Sump Pump Details 8Tender for Chemical Treatment of Cooling Water Details 8Tender for the work of fabrication & Installation of Model Parts for 3D Comprehensive Model for Spillway and Power Intake Details 8Annual Rate Contract (ARC) for Supply of FR Grade Conveyor Belt Details 8Tender for Annual maintenance of Ash pond Details 8Tender for the Supply of Relay Details 8Tender for procurement of ACSR Raccoon Conductor Details 8Tender for the supply of square type coal nozzle tip including hard facing Details 8Tender for procurement of 11 KV 45 KN Polymer Composite (B&S) Disc Insulators Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Tapping sunshine: Tata Power aims to grow solar rooftop business four-times in four years Details 8Sajjan Jindal keen to buy out stressed hydroelectric plants Details 8Sterlite Power expects renewable energy to boost private participation as tussle over project allocations continues Details 8Saudi Arabia, BP eye major Indian solar play Details 8E-vehicle charging points in Bengaluru high-rises? Details 8Sterlite Power commissions 3,000 cr project in Jammu and Kashmir Details 8India to achieve 76% of renewable energy target by 2022: Wood Mackenzie Details 8MCL would achieve coal output target of 162.6 mt: Piyush Goyal Details 8India coal import forecast raised by 6MT in 2018 on local supply crunch Details 8Coal crisis intensifies with rising demand, poor evacuation at ports Details 8HSBC UK Pension Scheme to invest 250 mln pounds in wind and solar Details 8Spain's Iberdrola sells British power assets to Drax for 800 million euros Details 8States to get Rs 100 Cr award for being efficient under Saubhagaya scheme Details 8Power demand matches summer’s as temp rises in Mumbai Details 8CIL says supplies up 9%; Power Co's report low stock Details You can also click on Newsclips for moreDetails
Owner plans to set up a greenfield super-critical thermal power project. 8Currently, EPC bidding process is going on. 8The long-term coal linkage has been approved. 8Project is suffered due to delay in investment approval from the PIB. 8A pre-bid meeting was held. Major EPC players have participated in the process. 8Piling works are going on at the site location. 8Project Cost: 15010 crores 8Project Event: RFQ for the township package is expected by November 2018. RFQ for the design, engineering, procurement, construction and commissioning of merry-go-round rail track system is expected by November 2018. 8Expenditure Approval: Q4:2018 8RFQ Date: Nov/2018 8Release Date: Nov/2018 8Start Date: 2019 8Completion Date: 2024 Click here for more detailsDetails
For reference purposes the website carries here the following tenders: 8Supply, Installation, Testing and Commissioning of Energy Management System (EMS) Details 8Tender for Erection (Mechanical/Instrumentation) & Commissioning of ETP & STP Details 8Tender for Procurement of ST Cooling Tower Fill Pack and Drift Eliminator Details 8Annual rate contract of Dozer on hire for coal stockyard management Details 8Tender for Overhauling of ID fan & Coal Pipe Details 8Tender for Running and Breakdown Maintenance of ESP Details 8Tender for Requirement of Various types and sizes of Lugs & Cable Glands Details 8Tender for work of renovation of broken / rusted leg earthing to the towers of various Lines Details 8Tender for the Work of construction of 1X132kV End Bay Details 8Supply & Delivery of FRP Blades with Hub Assembly Details 8Supply, Installation and Commissioning of 60 kw roof top solar Plant Details 8Supply of Governor Main distribution Valve Details 8Tender for Overhauling of boiler pressure parts Details 8Supply and drawing of 33kV ACSR Conductor Details 8Tender for Supply of Earthing Coil set Details 8Supply of LT Guy Grip & Thimble Details 8Supply, Erection and Commissioning of 25 meter high mast Lighting System Details 8Supply of 245KV Potential Transformer Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Ex Ostro Energy CEO, COO to start renewable energy firm. Details 8Power plants wants PFC, REC to fund green compliance Details 8Delhi court grants bail to Naveen Jindal, others in coal scam case Details 8RP Sanjiv Goenka's CESC alters demerger plans as WBERC plays spoilsport Details 8JSW Energy puts solar power plans on backburner over policy uncertainties Details 8India needs to make a smooth and viable transition from coal, says IPCC report Details 8EESL inks MoU with DoP for distribution of energy-efficient appliances Details 8Govt to give priority to state power producers for coal supply; pvt plants in lurch Details 8Getting clearances major hindrance for hydro projects: Arunachal Pradesh CM Pema Khandu Details 8Jaiprakash, RKM, 5 others bag 1,900 MW power supply deals Details 8Musk rejoices as Tesla’s Model 3 passes 1,00,000 units produced mark Details 8Under pilot project, 1.2 Lakh houses in Tamil Nadu to get smart meters Details 8Gurugram asks EESL for 18,000 more street lights for dark stretches Details 8Maharashtra CM to inaugurate three schemes of state power utility Details 8TN plans to construct Anamalayar hydro dam under 60-yr old PAP Details 8Gujarat moves SC to ensure power plans not disrupted Details 8Adani Electricity offers subsidised tariff for Navratri, Durga Puja pandals Details You can also click on Newsclips for moreDetails
Project Name: Thermal Power Plant - Dismantling Project 8Project Cost: 210 crores 8Project Description: The Supreme Court of India mandated to shut down the owner's 850 MW operational thermal power plant with the commissioning of 400/220 kV sub-station. The sub-station will take the load off the TPS. The high-level committee of the owner is in discussion to dismantle the whole plant. Moreover, plans to implement a solar PV plant is still under a shadow. Further bids are expected soon. 8Project Event: RFQ for dismantling services of various equipment is expected by the Q1 2019. 8Expenditure Approval: Q4:2017 8RFQ Date: Q1:2019 8Release Date: Q1:2019 8Start Date: Q3:2019 8Completion Date: Q3:2020 Click here for more detailsDetails
Owner along with an EIA consultant was accorded the environmental clearance in a 105 MW greenfield hydroelectric power project. 8The project is getting delayed due to pending techno-economic clearance from the CEA. 8The forest clearance is also outstanding at the state forest department. 8The project has been renamed due to protests among the local. 8Pre-construction activities are yet to start. 8Further RFQs are expected soon. 8Project Cost: 1150 crores 8Project Event: RFQ for supply and erection of civil works and H&M works are expected by the Q1 2019. 8Expenditure Approval: Q1:2019 8RFQ Date: Q1:2019 8Release Date: Q1:2019 8Start Date: 2020 8Completion Date: 2025 Click here for more detailsDetails
Owner along with an EPC contractor is carrying out the mechanical completion activities in a 660 MW super-critical brownfield thermal power complex at the existing 1200 MW facility. 8Boiler light up is expected in November 2018. 8Tractebel Engineering Pvt Ltd has carried out the project engineering consultant works for implementation of an FGD. 8The pre-bid meeting for the FGD was held on September 2018. 8Major EPC contenders have been shortlisted in the technical bid. 8However, BHEL failed to qualify the techno-commercial part of the bid. 8A price bid is expected soon. 8Project Cost: 9450 crores 8Project Event: RFQ for the price bid of the shortlisted contenders is expected by November 2018. 8Expenditure Approval: 2014 8RFQ Date: Nov/2018 8Release Date: Nov/2018 8Start Date: 31/Dec/2014 8Completion Date: Dec/2018 Click here for more informationDetails
Project Name: Thermal Power Station - Installation of FGD 8Project Cost: 1050 crores 8Project Description: A JV company is evaluating pre-qualification bids of an EoI for installation of a wet limestone based flue gas desulphurization main package in a 1200 MW thermal power station. Also, the owner is on the lookout for financial institutions to fund the project. Further bids are expected soon. 8Project Event: RFQ for the civil works and design & construction of RCC chimney for implementation of wet limestone-based FGD is expected by November 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: Nov/2018 8Release Date: Nov/2018 8Start Date: Q2:2020 8Completion Date: Q3:2022 Click here for more informationDetails
There is always the other side to the picture on NTPC and PFC, very different from how we see them. 8There is a perception that NTPC has a history of brutal evictions for the construction of its power plants and coal mines. 8Virtually all of the company’s coal plants violate India’s air pollution standards and the ash residue from its power stations contaminates local water supplies, putting enormous health burdens on communities living nearby. 8Its safety record is also abominable as evidenced in 2017, when an explosion at one of NTPC’s plants killed 43 people and injured over 100 more. 8The other company is Power Finance Corporation. Under the control of the Ministry of Power, PFC sets up shell companies to finance, plan and facilitate so-called “Ultra Mega” coal power projects in India. These shell companies acquire the necessary land, obtain permits and financing for the projects that are then sold to other power companies in a bidding process. PFC was thus responsible for financing a large part of the Indian coal boom, which led to the tripling of India’s coal-fired capacity between 2007 and 2017. 8A 2017 report by India’s Comptroller and Auditor General (CAG) states that PFC’s lending to these coal projects was not properly vetted. 8As a consequence, PFC is now burdened with non-performing loans, which were sunk into stranded coal assets. PFC nonetheless currently still has 8,000 MW of new coal projects under development. Click on Reports for more
Details
The global average decarbonisation rate is less than half of what is needed. 8So where does this leave us? 8The gaps between current progress, the Paris Agreement’s national targets and the two degrees global goal indicate the potential for major disruptions Read more on the subject
Details
LNJ Power Ventures Limited 20 MW wind power project located in Jaisalmer, Rajasthan sems to have run into trouble 8And it is not just sub-par generation that is troubling the unit 8Know more on why the O&M subcontractor is facing an uphill task as well Find out moreDetails