All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Oct 2022

For reference purposes the website carries here the following tenders:
 
8Tender for work of centralized rate contract of hydrated lime Details
 
8Tender for works contract for laying of 11KV XLPE cable Details
 
8Tender for providing additional 12.5/16 MVA, 66/11 KV T/F at 66kV s/stn Details
 
8Tender for ARC for performing different types of day to day maintenance work turbine maintenance Details
 
8Tender for annual work contract for maintenance of ash handling plant Details
 
8Tender for work of construction of 33 /11 KV S/S Details
 
8Tender for operation and maintenance work of various sub stations Details
 
8Tender for BM-to carryout complete replacement of SCW rear wall panels and bend tubes Details
 
8Tender for biennial contract for running and maintenance of water supply pipeline Details
 
8Tender for the supply of 630KVA  oil filled transformer Details
 
8Design, engineering, construction, fabrication, supply, erection, trial run and commissioning of 2X6.3 MVA, 33/6.6-3.3 kV substation Details
 
8Tender for construction of transformer plinth and cable duct for enhancement of existing 110/33-22 kV SS power transformer Details
 
8Tender for work of running and maintenance of transit house Details
 
8Tender for re-opening, salvaging, rehabilitation, development and operation of discontinued underground mine Details
 
8Tender for deployment on rental basis of 7.5 KVA, DG set along-with telescopic lighting tower Details
 
8Tender for the procurement of 610 KW ,6.6 kV intake motor Details
 
8Tender for work of testing and analysis of coal samples at various loading points of NCL of coal Details
8Tender for supply, installation, testing and commissioning of new 11 KV lines, LT line on AB cable  Details
8Tender for work contract for annual preventive/breakdown maintenance of non pressure parts of boiler Details
8Tender for supply, installation, testing and commissioning of busbar protection scheme at various 220 kV s/s Details
8Tender for work of river bank protection/ erosion control measures on the left bank Details
8Tender for repair reconstruction of left bank project Details
8Tender for supply and installation of MCCB for auxiliary feeder of L.T. panel and control cable at 400KV sub-station Details
8Tender for procurement of lightning arrestor for substation Details
8Tender for procurement of 36 KV C Ts at various substations Details
8Tender for the supply of 420KV capacitive voltage trasnformer at 400KV sub-station Details
8Tender for work of shifting HT/LT poles Details
8Tender for the supply of journal shaft for HP 803 bowl mills Details
8Tender for the supply of 36 centre distance worm gear & gear worm shaft assembly for bowl mills Details
8Tender for supply of gear box output shaft (vertical shaft) with lock and key for HP 803 bowl mills Details
8Tender for the supply of bowl hub assembly for HP803 bowl mills Details
8Tender for supply, laying, erection, testing, commissioning of 110kV XLPE Al UG cable Details
8Tender for the supply of TC fuse wire 14 SWG Details
8Tender for the supply of 22 KV polymer composite pin insulator Details
8Tender for the supply of TC fuse wire 16 SWG Details
8Tender for work of RLA studies, feasibility studies for up rating of machines and preparation of DPR for RMU Works Details
8Tender for procurement of ceramic lined pipes Details
8Tender for work of various maintenance work in 132 kV switchyard at 132 kV Details
You can also click on Tenders for more
For reference purposes the website carries here the following newsclips:
8Jetty policy will convert Goa into coal hub, gambling den: Alemao Details
8ReNew pledges to be net-zero firm by 2040 Details
8Researchers invent anode material to aid ultra-fast charging, ensure long life of lithium batteries Details
8Wall clock, e-bike maker Oreva group at centre of Morbi bridge collapse Details
8Panasonic to Start Building Kansas Battery Plant Next Month Details
8Toyota Profit to Rise but Eyes Will Be on Its Shaky Supply Chain, EV Strategy Details
8Increased demand of electricity by 31% creates power crisis in Rajasthan Details
8Renault-backed Beyonca EV venture touts health monitoring, targets Audi in China Details
8Electric automobiles market set for big leap in Vizag metropolis Details
8Power cos near pasture lands found violating SC orders Details
8Bengal to launch more electric, CNG buses to reduce air pollution Details
8Survival of discoms is questionable now: PowerMin to state govts Details
8Isro successfully tests engine that will power LVM-3 to space with 36 OneWeb satellites Details
8PE funds in electrical automobiles could cross $1 billion in 2022 Details
8Octopus Energy to buy failed British energy supplier Bulb Details
8NTPC Q2 net profit dips over 7% to Rs 3,418 cr on back of higher expenses  Details
8ONGC plans 1 GW solar power plant in Rajasthan Details
8Big tech's dirty supply chains undercut climate promises from headquarters Details
8Adani group to invest $150 billion in pursuit of $1 trillion valuation Details
8Environmental concerns, renewable energy key components of Modi govt policies: Minister Puri Details
8India among leading nations: PM Modi on solar power, 1st solar village Details
8Coal scam kingpin Suryakant Tiwari surrenders in court Details
You can also click on Newsclips for more

 

Details

8Forest clearance stage 2 has been accorded by the DFO.

8Approval from Railway, Defence, PTCC, and Civil aviation has been granted.
8The soil test is completed and pilling and foundation works have been completed for the lattice tower.
8Land acquisition works completed for substation works and the contractor has been selected for the S/S works.
8RFQ for the P/S works is likely to be floated in December 2022.
Click here for more details

Details
8The state discoms had sought permission to exit from the PPAs from from Farakka I & II and Kahalgaon- I with effect from May, 2022
 
8So commission has refused the request of discoms
 
8Find out why?
 Click on Details for more
Details
8CEA has the mandate to provide the requisite staff to Regional Power Committees but the central agency has failed to do so
 
8Find out what is being done on this front now
 Click on Details for more
Details
8A standing committee is required for physical inspection in cases of tower collapse and equipment failure
 
8Find out how will this committee work?
 Click on Details for more
Details
8RE generation addition is growing at a fast pace which in turn is creating a number of operational and technical issues.
 
8So it is necessary to deliberate these issues at a common forum at the Regional Power Committee level so that they can be monitored an resolved
 Click on Details for more
Details
8The hydrology report for the same has been approved by the CWC.
8Forest clearance for the same is pending at the regional office.
8The geotechnical investigation and the topographical survey report have been approved by the GSI.
8The approach road construction was getting affected due to unfavorable weather conditions and critical geological terrain.
8RFQ for the  PMC package is likely to be floated in December 2022.
Click here for more details Details
8Civil work (lot-1) contractor has completed the mobilization of equipment at the site. Know who the contractor is
8Bid evaluations are in progress for the civil works package (lot-2). Get to know who the bidders are
8RFQ for the HM work is likely to be floated in January 2023 instead of Q4 2022
 Click here for more details Details
8Forest clearance stage 1 and 2 has been granted by MoEF.
8The Prime minister has laid the foundation stone for the project.
8Boring work for HRT is in the initial phase.
8Pre-bid meeting has been completed for the EM work
8RFQ for the EOT crane package is likely to be floated in Q1 2023
Click here for more details Details
For reference purposes the website carries here the following reports: 
 
8IREDA will have a new director (finance). Click on reports for more
 
8HEC is a leading player in coal handling work: Find out more on coal handing projects under execution by the company. Click on reports for more
 
8Indowind Energy appoints new company secretary Click on reports for more
 
8JSW Energy has appointed a director. Click on reports for more
 
8Yashita Pansari appointed as company secretary and compliance officer at a solar firm Click on reports for more
 
8Rajiv Mehrishi appointed as as an additional director in a power generator Click on reports for more
 
8High Energy Batteries (India) Ltd gets new company secretary Click on Reports for more
 
8REC Ltd gets a new director Click on reports for more
 
8Arun Kumar appointed as company secretary at India's leading power producer. Click on Reports for more
 
8There has been a change in CEA's ease of doing business nomenclature. Click on Reports for more
 
8Nigeria is currently collaborating with India on improving its solar energy capacity and infrastructure. Click on Reports for more
 
8The 27th Conference of Parties— COP27— is once again the subject of enormous expectations but the Indian play will be unique in this event. Click on Reports for more
Details
8State will have 500 MW power from Kudgi STPS from tomorrow
 
8Get the revised power allocation data for interstate generation stations of the Southern Region
 Click on Reports for more
Details
8A large number of coal mines either discontinued or abandoned before 2009
 
8There is a need to close these mines scientifically in such a manner that they provide benefit to the community, prevent illegal mining etc.
 
8The ministry has floated new guidelines to closed these mines.
 
8Get the new guidelines here.
 Click on Reports for more
Details
8An EPC firm has secured orders to build a 380kV transmission lines and a 230kV Gas Insulated Substation (GIS)
 
8Find out more
 Click on Reports for more
Details
8This tariff is adopted for the purchase of 102 MW power under FOO (Finance, Own and Operate) Guidelines
Click on Reports for more
Details
8A $100 trillion climate change transition is needed to stay within the 2.0 degrees global warming
 
8And this is a realistic target, and that amount of funding can indeed be raised
 
8What are the key takeaways?
 Click on Reports for more
Details
8An economic return alone might not be sufficient to induce green financing
8A more holistic rate of return will be appropriate.
8The Indian financing story may be the example that the world may be looking at
Click on Reports for more
Details
For reference purposes the website carries here the following tenders:
 
8Tender for supply, installation, testing, commissioning and maintenance of hydro meteorological instruments Details
 
8Tender for works contract for proposal of HVDS in 11 kV feeder Details
 
8Tender for the procurement of conveyor belt Details
 
8Tender for civil and architecture works of integrated boiler Details
 
8Tender for the requirement of electro hydraulic actuators of turbine Details
 
8Tender for appointment of an agency for providing integrated channel complaint handling system Details
 
8Tender for work of three year maintenance of green belt at internal dump yard Details
 
8Tender for supply of control cards and genius blocks required for 24/96 draglines Details
 
8Tender for misc. civil works related to mine safety preparation Details
 
8Tender for requirement of maintenance assistance for day-to-day repair and maintenance work Details
 
8Tender for procurement of hydraulic pump and hydraulic cylinder Details
 
8Tender for making portable rest shelter with structural steel Details
 
8Tender for the supply of spares for D-155 dozer Details
 
8Tender for the supply of spares for spare parts of REL-650 drill spares Details
 
8Tender for the supply of spares for EX-1200 hydraulic excavator Details
 
8Tender for providing LT service connections Details
 
8Tender for the supply of spares for motor grader Details
 
8Tender for procurement of telephone cables, paging cables and power cables Details
 
8Tender for procurement of steel material Details
 
8Tender for annual maintenance contract of turbine and auxiliary Details
 
8Tender for protection work on left bank of switchyard Details
 
8Tender for work of filling of pond ash in low-lying Details
 
8Tender for remaining civil works at 132 KV sub station Details
 
8Tender for maintenance works for O &M of various 400 KV sub-station Details
 
8Tender for the supply of copper control cable Details
 
8Tender for the supply of  triple screw motor pump set LP oil cooler Details
 
8Tender for the supply of different types of spares for 132 KV SF6 breakers Details
 
8Tender for purchase of various spares for the boiler Details
 
8Tender for purchase of spares of TAC (model no. ZA6H) Details
 
8Tender for installation of ACB and laying of LT AB cable Details
 
8Tender for work of assistance in operation of boiler and turbine DCS Details
 
8Tender for overhauling / renovation work (both mechanical and electrical) for EOT cranes Details
 
8Tender for the supply of constant load spring cages Details
 
8Tender for erection, testing and commissioning including handling of materials Details
 
8Tender for framework agreement for service contract for miscellaneous maintenance activities Details
 
8Tender for work of construction of 110kV GIS substation Details
 
8Tender for work of augmentation of 66KV substation Details
 
8Tender for procurement of spares for bowl mills Details
 
8Tender for work of assist in the work under thermal operation in the execution of operational jobs Details
 
8Tender for works contract for agriculture feeder segregation in 11 KV feeder Details
 
You can also click on Tenders for more
For reference purposes the website carries here the following newsclips:
810 things India can do to achieve net-zero emission goals, according to Mckinsey report Details
8Gogoro Electric Scooters: The Competition In The e-Scooter Market To Hot Up Even Further, Gogoro About To Enter Details
8Telangana power staffers threaten stir against Centre’s Electricity Bill Details
8G7 countries urge India to join Just Energy Transition Partnership Details
8India, Sweden collaborate for sustainable future via innovation projects Details
8Tata Power Q2 PAT climbs 85% YoY to Rs 935 cr Details
8Will ‘price cap’ for power work? Details
8Kishtwar to emerge as major hydropower centre in North India Details
8ArcelorMittal arm AMNS India to invest Rs 60,000 crore to expand Hazira plant: Chairman Aditya Mittal Details
8Tata Power net profit jumps 94% in Sept quarter on strong energy demand Details
8Almost 30% power consumers yet to apply for monthly electricity subsidy: Delhi Govt Details
8JSW Energy posted 37% rise in PAT to Rs 466 cr in July-Sept quarter  Details
8Slovenia reduces illumination of highways to save electricity  Details
8Eramet inspecting doubling of lithium capability in Argentina Details
8CG Power keen to supply systems for makers of Vande Bharat trainsets Details
You can also click on Newsclips for more
Details
For reference purposes the website carries here the following reports: 
 
8Megha Engineering gets LoA for a refinery project Click on Reports for more
 
8NTPC gets relief on account of ash transportation charges Click on Reports for more
 
8IndiGrid to appoint a Chief Executive Officer Click on Reports for more Details
8The Revenue has been increased on account of higher plant availability in Mundra, higher sales across distribution companies and capacity addition in renewables
 
8Find out more
 Click on Reports for more
Details
8Domestic coal production has crossed 380 MT during H1FY23 registering a growth of 21% y-o-y over the same period in FY22
 
8This growth was supported by various government initiatives to maintain the coal demand and supply in the country
 
8Find out more
 Click on Reports for more
Details
8This solar generator had sought an extension of SCOD of a 150 MW solar project by 3 months
 
8But only two month's extension has been granted
 
8Find out why?
 Click on Reports for more
Details
8Find out why the power allocation has been delayed
 
8And also know how many states are in line to availing of power from Unit 3&4 of KKNPP
 Click on Details for more
Details
8As 700 MW RE Hybrid project is delayed (which is Adani’s main source of meeting RPO), it  would impact its ability meet the cumulative RPO shortfall till 31 March 2023
8So alternate sources will be needed, find out what is being done on this fornt
Click on Reports for more
Details
8PMUs are required to be installed at the RE pooling stations to monitor and analyse the performance of RE sources
 
8In South Region (SR), 4274 MW of renewable energy do not have PMUs installed at the stations
 
8PMUs will help to get more visibility on the transient behavior of RE stations during grid incidents and their compliance to Grid Standards
Click on Details for more
Details
8This is the largest aluminum player in India
8This company plans an expansion of rolled product capacity from existing 50 KTPA to 180 KTPA
8And also an expansion of smelter capacity from existing 580 KTPA to 994 KTPA .
Click on Reports for more
Details
8The nuclear generator's present fuelling plan are such that they have to shut down the units for two months and run the units for 10 months.
8Every year their refuelling shut down/maintenance falls during the peak season hampering the LGB of all the states
8So one beneficiary has suggested a proposal to unit's availability at peak period
 Click on Details for more
Details
8Get the new maintenance schedule of this thermal power station
 Click on Details for more
Details
8UP has faced consistent difference of approx. 70MW in each time block in the drawl schedule
 
8Why is this happening?
 
8And what deal has been done?
 Click on Details for more
Details
8This will ensure capacity availability for all the states/ discoms when  crisis hits
8This scheme can be implemented in three phases
8NTPC will play an important role in this scheme
 Click on Details for more
Details
8NPCIL has an outage planned for mandatory replacement of enmasse reactor coolant channels & reactor feeders at a power  station
 
8So beneficiary DISCOMs need to arrange power from other resources for meeting their requirements
 
8Find out outage schedule here
 Click on Details for more
Details
8Civil and structural works are in progress for BTG.
8Pilling and foundation work for BOP have been completed.
8LOA for the Wagon Tripler package has been completed.
8Bid evaluations are in progress for the Stacker Reclaimer package
8RFQ for the DM plant package is likely to be floated in December 2022.
 Click here for more details Details
8DPR of the project has been approved by CEA.
8Construction of the approach road has been completed.
8Bidding is in progress for the PMC package.
8RFQ for the civil works package(lot-1) package is likely to be floated in Q1 2023.
Click here for more details Details
8Technical bids have been completed for the civil work and the price bid is yet to be started.
8Pre-bid meetings for HM work have been temporarily put on hold
8PMC tender has been floated for the feeder canal works.
8RFQ for the EM works package is likely to be floated in January 2023
Click here for more details Details
For reference purposes the website carries here the following tenders:
 
8Tender for extraction and transportation of ash from ash ponds and slag pitching over dykes Details
 
8Tender for construction of rusted damaged tower muffs of various 66kv lines Details
 
8Tender for supply, installation, testing and commissioning of lighting tower Details
 
8Tender for supply, installation, commissioning and testing of distribution transformer Details
 
8Tender for providing and laying of 250 mm dia. ductile iron pipeline Details
 
8Tender for transportation, installation, extension and tail end shifting of pony belt Details
 
8Tender for supply, delivery and installation of centrifuge separator oil filtration machine Details
 
8Tender for supply, delivery and installation of hydraulic mobile crane with mandatory spares Details
 
8Tender for procurement of grinding element for 8.5E9 coal mill Details
 
8Tender for supply of electrical accessories for renovation and modification of 33KV double circuit lines Details
 
8Tender for ARC for performing different mechanical maintenance jobs Details
 
8Tender for annual service contract for the job of operation of ammonia dosing system and chlorination plant Details
 
8Tender for installation of 04 numbers of level crossing at wagon trippler Details
 
8Tender for design, supply, installation and commissioning of 10 kW capacity on-grid SPV power plant Details
 
8Tender for design, supply, installation and commissioning of 100 kW capacity on-grid SPV power plant Details
 
8Tender for requirement of hardware fitting for grid construction works and transmission line Details
 
8Tender for supply of  grinding rolls, compatible bull ring segments an airport ring assembly for XRP 1043 bowl mill Details
 
8Tender for breakdown maintenance of milling system Details
 
8Tender for work of erection of towers and stringing of double phase conductor of 132 KV line Details
 
8Tender for construction of shed and plateform i/c oil tank at yard Details
 
8Tender for procurement of shrink discs suitable for hydraulic motors Details
 
8Tender for work contract for annual overhauling of secondary crusher Details
 
8Tender for AMC for civil day to day maintenance works Details
 
8Tender for the supply of limit switches and air filter regulators Details
 
8Tender for the supply of pressure switch, temperature switch and proximity switches Details
 
8Tender for the supply of hydrazine hydrate Details
 
8Tender for the supply of male & female sliders/tube spacers for boiler pressure Details
 
8Tender for the supply of blades of PA fans with blade screw Details
 
8Tender for contract for round the clock operation support services and miscellaneous jobs at PT plant, DM plant Details
 
8Tender for supply, erection, commissioning of modified air pre-heater Details
 
8Tender for the supply of zip type belts for stock make dual belt gravimetric feeder Details
 
8Tender for the supply and replacement of FRP cable tray Details
 
8Tender for major overhauling of generators along with air coolers Details
 
8Tender for carrying out excavation work of emergency reclaim hopper Details
 
8Tender for execution & construction of tower & equipment's foundations,cable trenche, pump house & water tank at 400KV yard of 400/220KV substation Details
 
8Tender for construction of 9th raising of lagoon-1 stage-II ash dyke Details
 
8Tender for work of 220kV & 110kV UG cable laying and allied works  Details
 
8Tender for providing GI sheet roofing for 110kV GIS Details
 
8Tender for AMC of fire extinguishers of upper kolab hydro electric project Details
 
8Tender for work of repair and rewinding of 400KVA copper wound transformer Details
8Tender for the supply of bends for coal mills  Details
8Tender for procurement of 3 phase 11 KV-433-250V 10 KVA transformer Details
8Tender for supply, transport and erection of GCO tower and stringing of panther conductor and earth wire of 110 KV DC line Details
8Tender for work of cleaning of HFO HSD guns, operation follow up of soot blowers retracting of blowers Details
8Tender for procurement of LT MS 4 way pillar boxes Details
8Tender for design, engineering, supply, construction, erection, testing, commissioning, and comprehensive O& M of 15 MW(AC) floating solar PV power plant Details
8Tender for work of various balance supply, erection, testing and commissioning works at 220 kV S/stn Details
You can also click on Tenders for more
For reference purposes the website carries here the following newsclips:
 
8EMotorad raises Rs 24 crore Details
 
8Charge Plus Zone to set-up charging stations for Mahindra electric SUVs: Check details Details
 
8LG Electronics Q3 profit down on weak demand Details
 
8Bharat Electronics signs pact with Meslova for developing products, services in artificial intelligence/machine learning Details
 
8Goa’s first solar ferry to be operational before Iffi Details
 
8Linde Expects to Benefit From U.S. Clean-Energy Transition Details
 
8TerraPower, PacifiCorp to Study 5 More Advanced Nuclear Reactors Details
 
8IHCL installs over 224 EV charging stations at its 92 properties Details
 
8Toyota considers sharp boost in output of first EV, but not before 2025, sources say Details
 
8Vacant posts in Punjab’s power sector lead to worries about supply, efficiency Details
 
8After little success in past, India revisits plan to repower its ageing wind turbines Details
 
8Govt may tap green bonds to fund battery? storage, NE hydel projects Details
 
8Adhocism in power sector continues Details
8EKI Energy Services, First Source Energy to form JV to set up climate edtech, finance marketplace Details
8Norway’s Statkraft submits debt resolution plan for Lanco unit & More Trending News Details
8Hindustan Motors, European partner complete due diligence for EV project Details
8India’s energy demand to be highest globally during 2021-2030: IEA Details
8Delhi airport deploys 57 EVs as part of Green Transportation Program Details
You can also click on Newsclips for more
Details
8Forest clearance stage 1 and 2 has been accorded by the DFO.
8Land acquisitions have been completed for S/S and Erection and installation works have been completed.
8Detailed engineering works are in progress for pooling station works.
8RFQ for the ACSR moose conductor package is likely to be floated in November 2022.
Click here for more details Details
For reference purposes the website carries here the following tenders:
8Tender for work of erosion control measures on the right bank of river subansiri by provision of RCC jack jetty Details
8Tender for design, supply & installation of mixed resin storage vessel at CPU regeneration plant Details
8Tender for major overhauling of 21 MW STG Details
8Tender for work of centering, alignment & balancing of all units (40x3 MW hydro generating unit) Details
8Tender for construction of drain along coal stock yard Details
8Tender for operation and maintenance of STP Details
8Tender for BMC for welding and repair works on HDPE, FRP and PPR pipelines of various Details
8Tender for supply of turbo generator vibration rectification and minor overhaul works Details
8Tender for biennial contract for civil maintenance works Details
8Tender for procurement of balance structural steel for dry ash system Details
8Tender for fabrication and fixing of 8.5 MTR long M.S. twins moulds,clamps, anchor box increase the capacity of poles Details
8Tender for supply, installation, commissioning and testing of solar LED street lights Details
8Tender for procurement of battery charger for 220V DC, 350A ,1395 Ah battery bank Details
8Tender for the supply of LT line spacers Details
8Tender for procurement of various erosion protection sleeves (shield) for various HP tubes of boiler Details
8Tender for procurement of spares of recirculation valves of BFP for AOH Details
8Tender for design and testing of 400kV multi-circuit towers Details
8Tender for attending the breakdown/preventive maintenance in ash slurry line Details
8Tender for attending day to day maintenance of the ash slurry lines Details
8Tender for rectification of sheared runner bolts by dismantling all turbine Details
8Tender for design, manufacture, testing, supply, installation and commissioning of 220 V DC, 400 AH capacity battery Details
8Tender for construction of 11KV capacitor bank foundations and allied civil works  Details
8Tender for supply of overhauling kit and spares for 220 KV breaker Details
8Tender for work of supply & apply elastomeric thermoplastic graft co-polymer anti-corrosive treatment in 220KV switch yard  Details
8Tender for supply, erection, testing and commissioning of compressed air system Details
8Tender for procurement of voltmeters, ammeters & accessories of generator auxiliaries control panels Details
8Tender for providing portable package assembly liquid chiller system on hire basis to control /reduce temperature of ACW system Details
8Tender for job work for repairing,vulcanizing, reinstalling, replacement of various damaged / torn out conveyor belt Details
8Tender for modification/height raising of 132 KV SC line Details
8Tender for annual contract for routine breakdown and capital maintenance work of air pre heater Details
8Tender for annual contract for the work of complete operation maintenence and housekeeping of coal handling plant Details
8Tender for annual work contract for routine and breakdown maintenance of turbine, heat exchangers,TDBFP turbine and their auxiliaries Details
8Tender for annual contract for routine breakdown and capital maintenance work of boiler pressure Details
8Tender for annual contract for routine and breakdown maintenance of firefighting system Details
8Tender for routine maintenance works of PT plant and DM plant Details
8Tender for deployment of one man lifter with capacity of 120 ft lift of boom lift basket  Details
8Tender for annual transport contract for work for transportation of power transformer Details
8Tender for erection of balance equipments near generator transformer area and providing earthing for equipments, structures and fencing of 220 KV switchyard Details
8Tender for procurement of bentonite powder Details
8Tender for bi-annual maintainance contract for ESP Details
8Tender for service contract for maintenance & O/H of fly ash handling system Details
8Tender for fabrication, erection, assembly of dry fly ash silo for ash handling system Details
8Tender for design, supply and installation of fire proof cable Details
8Tender for supply, transport & erection of towers/extension and stringing of panther conductor and earth wire for the erection of 110KV DC line on DC tower Details
8Tender for supply, transport and erection of MD/KSR towers with tower extension and stringing of zebra conductor  Details
8Tender for supply, transport and erection of tower and stringing of panther conductor and earth wire for the balance portion of 110 KV DC line Details
8Tender for earthwork excavation and erection of tower and stringing of panther conductor and earth wire for balance portion of erection of 110 KV SC line Details
8Tender for work of supply, civil & ETC for establishment of 132/33KV S/stn Details
You can also click on Tenders for more
For reference purposes the website carries here the following newsclips:
 
8India’s Cochin Airport Is the World’s First Solar Powered Airport Details
 
8DoT Has Addressed TRAI Fears Over Dilution Of Power: Vaishnaw Details
 
8Govt may tap green bonds to fund batterystorage, N-E hydel projects Details
 
8Report: Global crises can speed up move to clean energy Details
 
8Energy Crisis Sparked by Ukraine War to Speed up Green Transition -IEA Details
 
8India’s clean energy transition is rapidly underway, benefiting the entire world Details
 
8Jagan to launch third 800-MW unit at Krishnapatnam thermal power plant in Andhra Pradesh on October 27 Details
 
8EU to provide $504 mn in grants for Western Balkans to tackle energy crisis Details
 
8GM: All US facilities will be powered by renewables by 2025 Details
 
8India’s energy demand could rise over 3% annually until 2030: IEA Details
 
8U.S. Treasury Launches Industry Outreach on Clean Energy Tax Credits Details
 
8Volkswagen brand will be electric-only carmaker in Europe from 2033, says brand chief Details
 
8Toyota Slashes Leasing Fee for Troubled EV to Rekindle Orders Details
 
8More than meets the eye: Leading transformer maker Hammond Power is expanding fast Details
 
8How Technological Innovation To Leverage In Offshore Wind Energy Market? Details
 
8Bihar: 53 wagons of coal-laden goods train derail, rail traffic disrupted Details
 
8Tata Power Solar Systems launches off-grid solar solutions in Bengal, Bihar Details
 
8Power utilities in Andhra Pradesh to focus on improving generation capacity, supply at affordable price and reduction of T&D losses Details
 
8Here’s a step-by-step guide to apply for power subsidy in Delhi  Details
 
8EU, US set up task force to resolve feud over electric vehicle batteries Details
 
You can also click on Newsclips for more
Details
8Siemens is accused of not listening to state government suggestions on SCADA/EMS system implementation
 
8These are being taken by PowerGrid and POSOCO, so the multinational thinks suggestions from states are not needed to be adhered to
 Click on Details for more
Details
8Pilling and foundation work at the BTG area have been completed.
8Sub-contractor has been selected for the  AHP works.
8The coal linkage issue has been resolved by the CIL.
8Bid evaluations are in progress for the wagon tippler package
8RFQ for the PT plant package is likely to be floated in November 2022.
 Click here for more details Details
8The winter is coming and renewable power infusion will create its own peculiar set of problems.
 
8And how will that be dealt with?
 
8There is much hang wringing going on just now
 Click on Details for more
Details
8Delhi Transco Ltd has a peculiar problem which other transmission companies are not facing.
 
8And the complaint is that it is facing high quotes for its tenders
 
8So what really is the solution?
 Click on Details for more
Details
8Forest clearance stage 2 has been accorded by the DFO.
8Approval from PTCC, civil aviation, and defense have been granted.
8Private land acquisition is in progress for the T/L works and it is in the advanced stage of completion.
8Land acquisition was completed for substation works.
8RFQ for the P/S works is likely to be floated in December 2022.
Click here for more details Details
8Forest clearance 2 has been accorded by the DFO.
8Civil works contractor has been selected and mobilization of equipment has been completed by the contractor
8Boring works are in progress for HRT.
8RFQ for the HM works package is likely to be floated in January 2023 instead of Q4 2022.
Click here for more details Details
8Construction of the approach land to the dam site has been completed.
8PMC has been selected.
8Pre-bid meetings have been completed for the civil works package
8RFQ for the HM works package is likely to be floated in December 2022.
Click here for more details Details
8Rajasthan excess solar power is going to ferried to Andhra Pradesh
8And it will be 7000 Mw of power
Click on Details for more
Details
8New problems have arisen over the blending of imported coal with domestic coal
8A deadline is approaching and there is all round confusion
Click on Details for more
Details
8An interesting solution has been forwarded on how to cut delay is environmental clearance for transmission projects
8It can cut both cost and time overrun
Click on Details for more
Details
For reference purposes the website carries here the following reports: 
8Adani Green Energy Ltd appoints a director Click on Reports for more
8Government gets Rs 74 crore as dividend from a copper producer Click on Reports for more
8REC Ltd appoints a Chief Risk Officer (CRO) Click on Reports for more
8ReNew transmission acquires a transmission asset Click on Reports for more Details
8Smart metering in India has made a lot of progress
 
8But it faces some serious challenges too
 
8Billing efficiency may have gone up but collections have been going downhill
 Click on Reports for more
Details
8EIA/EMP report has been approved by MoEF.
8Hydrology report has been approved by CWC
8Consent of PPA as per CERC tariff has been obtained.
8Pre-bid meetings are yet to be conducted for the civil works package(lot-1)
8RFQ for the civil works package (lot-2) is likely to be floated in January 2023.
Click here for more details Details
8Forest clearance stages 1 and 2  have been accorded by the DFO.
8CEA has approved the DPR of the project
8Contractor have been selected for civil, HM and EM work.
8Site preparation has been completed for the P/S works.
8RFQ for the 400kV S/S works is likely to be floated in Q1 2023.
Click here for more details Details
 1 2 3 >  Last ›

Showing 1–50 of 264 items