Oct 2022
Details
8Forest clearance stage 2 has been accorded by the DFO.
8Approval from Railway, Defence, PTCC, and Civil aviation has been granted.
8The soil test is completed and pilling and foundation works have been completed for the lattice tower.
8Land acquisition works completed for substation works and the contractor has been selected for the S/S works.
8RFQ for the P/S works is likely to be floated in December 2022.