For reference purposes the website carries here the following tenders: 8Tender for Procurement of 5540 Kg Tinned copper fuse wire Details 8Tender for construction work of 132kV line Details 8Tender for Round the clock Routine and Preventive maintenance work of Oil/Coal Burner, Igniter guide pipes, Valves and Other associated equipment Details 8Tender for the work of Replacement of existing ACSR Panther conductor by equivalent CCC type HTLS Conductor Details 8Tender for the work of replacement of power T/F Details 8Tender for Procurement of Electro Pneumatic smart positioners Details 8Tender for Supply, erection, testing & commissioning for the work of construction of LILO on 400 KV line Details 8Tender for work of replacement of existing 400kV ACSR conductor Details 8Tender for AMC for attending oil leakage from various joints of EHV power T/F Details 8Supply, installation, testing and commissioning of comprehensive numerical Disturbance Recorder System Details 8Annual maintenance contract to carry out the routine repair & maintenance of Power house equipments Details 8Tender for construction of 132kV D/C LILO line Details 8Supply, erection, testing and commissioning of 500AH VRLA type substation battery sets Details 8Supply, erection, testing and commissioning of Tubular acid type substation battery sets Details 8Supply, installation and commissioning of equipments for online continuous effluent quality and stack emission monitoring system at TPS Details 8Tender for supply of hot water distribution pipes and accessories for cooling tower Details Click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Can India’s solar gift solve urgent problem for journos at UN? Details 8Sterlite Power inks pact to sell Arcoverde project Details 8Modi urges scientists to work in boosting solar energy, electric mobility Details 8New MERC rule may shock solar power consumers Details 8Redesigning power purchase: Peak-load pricing the way forward, India also needs to push renewables Details 8Google employees demand climate plan from the company Details 8Gujarat sets 30,000 MW renewable energy generation target by 2022 Details 8Renewable energy producers in Andhra Pradesh struggle to stay afloat Details 8ABB says electrification business will hit margin goal next year Details 8Southeast Asia’s energy demand set to grow twice the world average: IEA Details 8Power sector needs good dose of private investments: Amitabh Kant Details 8CG Power plans to raise Rs 800 cr via equity issue to tackle liquidity crisis Details 8Renewable energy: Solar makers to oppose MERC draft regulations Details 8Torrent Power Q2 profit rises 83% to Rs 755 crore Details 8Average spot power price drops 54% to two-year low at IEX Details 8Asian Development Bank to provide $451 mn loan for power supply Details You can also click on Newsclips for moreDetails
8Would govt again make the mistake of canceling coal auctions due to low premiums? Details 8Jindal Steel and Power: Coal cost to come down by Rs1300/t with option to sell 25% of production in open market Details 8Can India develop a competitive battery manufacturing ecosystem? Details 8What is the advantage of optimized use of battery energy storage system in the hybrid power system? Details 8Business opportunity in captive power plant Details 8PTC India: Power trading volumes declined by 1.5% yoy to 21,812 million units in Q2FY2020. Details 8Siemens Gamesa achieves record commercial activity in FY 2019 powered by energy transition Details 8Business opportunity: Coal mining projects Details 8Who power sector contracting is trouble: Contractor companies making good money Details Click on Reports for moreDetails
8India’s installed capacity in renewable energy could increase by just 40 to 104 GW by fiscal 2022 from 64.4 GW in fiscal 2019, because of enduring policy uncertainty and tariff glitches: Know more. Details 8JSW Energy: Company's Hydro plant recorded its best-ever PLF of 103% aided by better water availability. Details 8Fourth Partner Energy Private Limited: Robust growth in scale of operations during last two years Details 8Coal India: An underwhelming operating performance in October Details 8Macquarie Group has become a leading investor in renewable energy infrastructure across Asia: A report 8Vsv Renewables Private Limited: Exposed to project execution risks associated with the implementation of additional signed PPA.. Details 8No coal production at MCL’s Odisha mines: Imports to go up Details Click on Reports for moreDetails
Project Name: Simhadri Super Thermal Power Station - FGD Addition 8Project Cost: 500.00 crores 8Project Description:National Thermal Power Corporation Limited had selected GE Power India as the EPC contractor for the installation of an FGD system in the 2000 MW (4x500 MW) thermal power station located at Simhadri, in the Visakhapatnam district of Andhra Pradesh. L&T, ISGEC, Mitsubishi, Tata Power, Thermax, and SEPCO were among the major contenders. RFQs for geotechnical investigation and topographical survey works are likely to be floated in February 2020. RFQs for civil, architectural work and design, engineering, supply, installation, testing and commissioning of FGD is likely to be floated on Q2 2020. Click here for more detailsDetails
For reference purposes the website carries here the following tenders: 8Tender for the Break down maintenance works of dual belt gravimetric raw coal feeder Details 8Tender for supply of 200 NB MS pipes Details 8Tender for Procurement of Electro Pneumatic smart positioners Details 8Tender for procurement of spares of coupling Details 8Tender for Overhauling of main boiler (Non Pressure Parts) of TPS Details 8Tender for Supply of Sodium Chlorite Details 8Tender for Supply, Laying, Erection, Testing and Commissioning of 66kV XLPE Cable Details 8Tender for Work of erection of 66kV D/C line on D/C Panther tower Details 8Annual Maintenance contract & attending emergency/breakdown maintenance work of 132kV & 220kV EHV Substations Details 8Annual Contract for attending emergency fault & annual maintenance work at various EHV substations Details 8Tender for Annual Maintenance contract & attending emergency/breakdown maintenance work of 132 kV & 220 kV EHV Substations Details 8Tender for Work of Supply of Equipments/Material, Erection, Testing & Commissioning of 33 kV Bays Details 8Tender for Supply of HT XLPE & AB Cable Details 8Tender for the Procurement of various sizes of bearings for pulley of ECHS conveyors Details 8Tender for Procurement of 11kV UG XLPE Aluminium power cable Details 8Tender for AMC for C&I system Details Click on Tenders for more For reference purposes the website carries here the following Newsclips: 8For the first time, Assam capital gets electric buses Details 8Infosys inks deal with Siemens Gamesa Renewable Energy Details 8Climate threat: India may end up wasting its massive coal reserves Details 8Wind energy players’ woes pile up Details 8Jindal Steel & Power wins coal block in auction Details 8India taking continuous initiatives to develop clean energy: Harsh Vardhan Details 8MoUs worth Rs 27,812 cr have been signed in hydropower sector alone: Jai Ram Thakur, CM, HP Details 8Want to check possibility of tidal power plant in Goa: State power minister Details 8Renewable power firm Pattern Energy to be bought by CPPIB for $2.6 bln Details 8Power from non-coal sources on rise in India Details 8Tata Power creates new arm to set up 10,000 microgrids in India Details 8Anil Kakodkar wants govt to follow France, China on nuclear power addition Details 8Germany to hike electric car subsidies as VW launches car Details 8UPPCL will pay staff if money isn’t recovered from DHFL: UP Power Minister Details 8North Korean hackers targeted Tamil Nadu Nuclear plant, top nuclear scientists: South Korean intel group Details 8NTPC may have to shell out Rs 10k cr for NEEPCO, THDC buy Details 8Piaggio and SUN Mobility join hands for swappable batter technology Details 8Global energy efficiency growth at decadal low: IEA Details You can also click on Newsclips for moreDetails
8Power Grid Corporation of India Limited: Exposure to state distribution utilities which have relatively weak financial profile is a problem? Details 8India Grid Trust (IndiGrid): RBI’s nod to allow banks to lend to InvITs is a boost to IndiGrid as it will now have better access to debt markets both in terms of cost and tenures, leading to improved fund management. Details 8The grid will need to be modernized to achieve India's renewable energy target: An analysis Details 8What is the Impact of Flexible AC Transmission System Devices on thermal power system? Details 8Cummins India Ltd: Powergen business revenue declined by 4% YoY during Q2FY20 Details Click on Reports for moreDetails
Project Name: Greenfield Thermal Power Station 8Project Cost: Rs 31000 crore 8Project Description: Erection and commissioning of the first four units of SG 4x800 MW are in progress. Erection and commissioning of TG and natural draught cooling towers are also in progress. Currently, BHEL has floated tenders for erection, testing, commissioning and trial operation of the main boiler and its auxiliaries of unit 5 1x800 MW at Yadari TPS. Technical bids will be opened from 23rd November 2019. However, TG will be supplied by BHEL for its fifth unit. Civil and architectural works for the fifth unit of TG are in progress.RFQs for the design, engineering, erection, testing and commissioning of natural draught cooling tower for unit 5 is likely to be floated in February 2020. Further RFQs are expected soon. Click here for more detailsDetails
For reference purposes the website carries here the following tenders: 8Tender for AMC of fan, APH, Duct and ESP Details 8Tender for Procurement of Oil Filteration machines Details 8Tender for BMC of 220KV Switch yard Equipment and Power Transformer Details 8Tender for work of thermal Insulation & Cladding of Boiler Details 8Tender for work of Transportation with loading of coal from Mines to TPS Details 8Tender for Supply of spares of Journal LP inner outer casing Details 8Tender for Supply of HT and LT Power Cable Details 8Tender for Supply of LED lighting material Details 8Tender for Overhauling of 250 MVA generating transformer Details 8Tender for Supply of Spares of Journal bearing Details 8Design, Supply, Installation, Testing & Commissioning and 5 years comprehensive maintenance of distributed grid connected solar PV system Details 8Tender for supply of sulphuric acid for TPP Details 8Tender for Annual maintenance contract for work of supply,repairing & calibration of ABT metering Details 8Tender for Work of overhauling/servicing of 33KV Circuit Breakers at various EHV substations Details 8Tender for Flue Gas Desulphurization (FGD) System Package Details 8Tender for Procurement of 100 TPH close unloading telescopic spout assembly Details 8Tender for Procurement of Various sizes of Gate Valves for Ash Slurry Disposal System Details Click on Tenders for more For reference purposes the website carries here the following Newsclips: 8BHEL bags Rs 200cr order to upgrade Chilla hydro project Details 8India needs $30 bn yearly investment in renewables Details 8KEC International rises 4% on orders win worth Rs 1,806 crore Details 8Coal India likely to create new posts of executive director rank Details 8Inox Wind secures 38 MW order from ReNew Power Details 8ADB signs $60 million private sector deal to build hydropower plant in Nepal Details 8Delhi: 8th Indo-German Energy Forum takes place, 8 MoUs inked Details 8Australian Pacific Coal to appeal regulator's decision to refuse mine extension Details 8India's coal imports rise 9 pc to 127 MT in Apr-Sept Details 8Asia must quit 'coal addiction': UN chief Details 8Renew Power, Avaada, UPC, Tata unit bag solar projects Details 875% subsidy on farm solar pumps to phase out diesel Details 8How domestic banks are moving into rural solar power space Details 8MNRE planning review of 5,000 MW solar power scheme under JNNSM Details 8Power gencos' outstanding dues on discoms rise 37% to Rs 70,000 cr Details 8Chhattisgarh: New industrial policy to focus on bio-fuel, e-vehicles & farm Details 8JSW Energy aims to double capacity to 10 GW by 2024: CEO Details 8Anti-power theft campaign fetches Jaipur Discom Rs 91 crore Details 8Siemens signs agreements with NTPC, TERI for decarbonization Details You can also click on Newsclips for moreDetails
8What is the decisions taken by Power Committee on Disaster management plan for power sector? Details 8Global forecasts by IEA show the seaborne coal market will more than halve within two decades Details 8What is the scope of the off-grid refrigeration market? Details 8EOI sought for 5000 MW grid connected solat PV power Details 8Europe is the technology leader for offshore wind? Details 8Offshore wind is set to be a $1 trillion industry over the next two decades, but rapid growth hinges on government policies and industry strategies: An analysis Details 8What are the limitations of thermal energy storage in solar powerplants? Details Click on Reports for moreDetails
Greenfield Hydroelectric Power Project 8Project Cost: Rs 2223.59crores 8Project Description: The diversion of forest land was approved by the MoEF&CC. 80% of the acquisition of private land has been completed and remaining is under process. The first two-phases of the public hearing were completed and the third phase will be conducted soon. FC has been granted by MoEF&CC. The company along with AFC India Limited has completed the social impact assessment studies. Topographical surveys and geotechnical investigations were completed at the plant site. RFQs for the civil work package -1 is likely to be floated in February 2020. The project envisages construction of a 16 m high cofferdam, 716m FRL, a 453m length diversion tunnel, an 85m spillway, a 108.17m HRT-1, and 146.89m HRT-2.Details
For reference purposes the website carries here the following tenders: 8Tender for Annual routine maintenance of electrical installations Details 8Tender for procurement of coolers for fluid coupling Details 8Tender for Supply of Distribution Transformers Details 8Tender for procurement of screw compressor Details 8Tender for Work of replacement of 110 Volt DC battery bank with new battery bank Details 8Supply & ETC of In line magnetic separator and drive pulley Details 8Tender for procurement of P.G. clamp Details 8Tender for Supply of 35000 Nos. HT stay insulator Details 8Tender for supply and delivery of 132kv CT/PT operated, tri-vector energy meters Details 8Tender for Construction work of 132kv SCDC Line And End Bay Details 8Supply, installation, testing and commissioning of automatic weather station Details 8Tender for maintenance of 4x80 MW Hydro Generating Units and other equipments Details 8Tender for Biennial Maintenance Contract for 33/11KV Substation Details 8Design, Engineering, Manufacturing, Installation and Commissioning of 110 kV XLPE lead sheath cables Details 8Tender for supply, erection and commissioning of equipment for 33kV & 11kV outdoor feeder metering Details Click on tenders for more For reference purposes the website carries here the following Newsclips: 8India important trading partner of Riyadh: Saudi commerce minister Details 8Coal India spends a lot on salaries and wages; land acquisition is getting tougher, says director AK Jha Details 8ReNew Power becomes 11th firm globally to reach 5,000-Mw green capacity Details 8Amid US withdrawal from Paris climate deal, France calls ISA a political project Details 8Goldman-backed ReNew says Andhra Pradesh problems could hurt India's renewables target Details 8Coal supply hits power, but renewable generation falls in September Details 8Fifteenth Finance Commission raises concerns on debt levels of states Details 8Coal India's October production may fall 20% Details 8Court dismisses appeal against Australia's New Hope's Acland coal project Details 8S.Korea to close 6 older coal-fired power plants by 2021, from planned 2022 Details 8Cheaper solar power gains ground in southeast Asia Details 8India showing political will on renewable energy development: IRENA Details 8Two more nations ink ISA Framework Agreement; membership rises to 83 Details 8Large-scale adoption of electric mobility will spur renewable energy growth: Study Details 8UP government partially shuts three power plants post Diwali Details You can also click on Newsclips for moreDetails
Project Name:FGD Addition 8Project Cost: 320.00crores 8Project Description: Preparation of DPR for a partial excution of an FGD is under process and it is likely to be completed in November 2019. However, RfQs for the civil, architectural works are likely to be floated on March 2020 and RfQs for design, erection, supply, installation, testing, commissioning of FGD is likely to be floated on Q2 2020. The requirement of a Gas-Gas Heater might not be taken up due to the cost factor. Click here for more detailsDetails